Takengon
Takengon
7.78
5.59
Rencana Realisasi
40.00%
35.00%
0.00%
Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17
RENCANA REALISASI
progres Rencana VS Realisasi
Bulan September 2017 periode september
- Rencana : 12.64 % 18.00
12.00
Komulatif s/d Agustus 2017 11.36
10.00
- Rencana : 69.19 %
8.00
- Realisasi : 55.57 %
6.00
- Deviasi : -13.62 %
4.00
2.00
0.00
Rencana Realisasi
Series1
Bulan Nilai
Uang Muka ke-2 30,584,125,600.00
MC-01 -
MC-02 1,163,053,760.00
MC-03 860,372,178.41
MC-04 1,609,945,723.21
MC-05 7,620,253,925.68
MC-06 1,928,083,868.51
MC-07 7,790,950,967.60
MC-08 4,147,560,567.35
MC-09 11,122,895,518.91
MC-10 8,450,255,312.37
MC-11 14,965,524,750.39
Total Penyerapan 90,243,022,172.43
Anggaran Tahun 2017 156,540,000,000.00
Sisa Anggaran 66,296,977,827.57
V DITCH ACBC BASE A
L
L
L
R
R
R
11+300 11+300 11+300
11+400 11+400 11+400
11+500 11+500 11+500
Preventif
Terpasang
11+600 11+600 11+600
11+700 11+700 11+700
11+800 11+800 11+800
11+900 11+900 11+900
253.26
12+100 12+100 12+100
12+200 12+200 12+200
12+300 12+300 12+300
12+400 12+400 12+400
12+500 12+500 12+500
12+600 12+600 12+600
12+700 12+700 12+700
12+800 12+800 12+800
12+900 12+900 12+900
13+000 13+000 13+000
13+100 13+100 13+100
Segmen 2
L
L
L
L
L
R
R
R
R
R
49+685 49+685 49+685 49+685 49+685
49+935 49+935 49+935 49+935 49+935
50+185 50+185 50+185 50+185 50+185
Preventif
Terpasang
50+435 50+435 50+435 50+435 50+435
50+685 50+685 50+685 50+685 50+685
50+935 50+935 50+935 50+935 50+935
51+185 51+185 51+185 51+185 51+185
3,588 m3
54+685 54+685 54+685 54+685 54+685
54+935 54+935 54+935 54+935 54+935
55+185 55+185 55+185 55+185 55+185
55+435 55+435 55+435 55+435 55+435
55+685 55+685 55+685 55+685 55+685
55+935 55+935 55+935 55+935 55+935
56+185 56+185 56+185 56+185 56+185
56+435 56+435 56+435 56+435 56+435
56+685 56+685 56+685 56+685 56+685
56+935 56+935 56+935 56+935 56+935
57+185 57+185 57+185 57+185 57+185
57+435 57+435 57+435 57+435 57+435
Segmen 5
5085 m1
I Di vi si 1. Um um
II Di vi si 2. Drai nase
2.3.(10) Saluran Berbentuk U Tipe DS 2 1,750.00 2,649,036,250 0.92
2.3.(12) Beton K250 (Fc’ 20) Untuk Struktur Drainase Beton Minor 648.00 1,033,187,037 0.36
2.3.(13) Baja Tulangan Untuk Struktur Drainase Beton Minor 68,791.50 1,346,819,937 0.47
SUB TOTAL PEKERJAAN II .......
V Di vi si 5. Perkerasan Berbuti r
5.1.(1) Lapis Pondasi Agregat Kelas A. 2,213.44 1,423,686,796 0.49
5.1.(2) Lapis Pondasi Agregat Kelas B. 1,604.60 923,112,781 0.32
SUB TOTAL PEKERJAAN V .......
VI Di vi si 6. Perkerasan Aspal
6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair 669.23 9,205,122 0.00
6.1 (2)(a) Lapis Perekat - Aspal Cair 109.10 1,478,081 0.00
6.3(5a) Laston Lapis Aus (AC-WC) 544.64 738,719,730 0.26
6.3(6a) Laston Lapis Antara (AC-BC). 3,740.09 4,815,640,692 1.67
6.3(6c) Laston Lapis Antara Perata (AC-BC(L) 141.77 182,243,042 0.06
6.3.(8) Bahan Anti Pengelupasan 706.98 50,549,043 0.02
SUB TOTAL PEKERJAAN VI .......
VII Di vi si 7. Struktur
7.1 (5) a Beton Mutu Sedang Fc’30 Mpa Lantai Jembatan/Pile Slab 125.43 382,446,571 0.13
7.1 (7) a Beton Mutu Sedang Fc’20 Mpa 150.37 283,900,733 0.10
7.1 (7) a Beton Mutu Sedang Fc’20 Mpa - - -
7.1 (10) Beton Mutu Rendah Fc’10 Mpa 21.40 25,143,792 0.01
7.3 (1) Baja Tulangan U 24 Polos 22,741.67 466,445,357 0.16
7.3 (2) Baja Tulangan U 32 Polos - -
7.3 (3) Baja Tulangan U 32 Ulir 40,412.71 912,862,464 0.32
7.6 (8) c Penyediaan Tiang Pancang Baja Diameter 150 Mm Dengan Te bal 5 Mm 1,342.67 454,255,458 0.16
7.6 (8) d Penyediaan Tiang Pancang Baja Diameter 300 Mm Dengan Te bal 12 Mm 1,190.00 2,255,444,771 0.78
7.6 (14) b Pemancangan Tiang Pancang Baja Diameter 150 Mm 1,342.67 52,565,279 0.02
7.6 (14) C Pemancangan Tiang Pancang Baja Diameter 300 Mm 1,190.00 88,396,175 0.03
7.9.(1) Pasangan Batu 146.35 104,089,270 0.04
SUB TOTAL PEKERJAAN VII .......
Lapis
Lapis Pondasi
Beton fc' 20 Beton fc' 10 ACBC Prime Coat Pondasi Total Satuan
Kelas A
Kelas B
Volume Rencana 1,824.5 21.4 5,344.7 2,508.9 3,431.4 2,371.0
Batu pecah #1" 1,003.5 12.4 1,015.9 m3
Batu pecah #3/4" 817.4 817.4 m3
Batu pecah #3/8" 691.7 691.7 m3
Abu Batu 1,257.6 1,257.6 m3
Pasir 821.0 9.0 356.3 1,186.3 m3
Semen 656,837.8 5,992.7 53,446.9 716,277.4 kg
Aspal 293,957.8 1,379.9 295,337.7 kg
Kerosin 1,129.0 1,129.0 kg
Antistriping 881.9 881.9 kg
Base A 3,774.5 3,774.5 m3
Base B 2,845.2 2,845.2 m3