ORIGINAL
Year
Month Jan'13 Feb'13 Mar'13
Project Month Progress 1 2 3
Plan Monthly (Orig) 2.00% 4.00% 5.00%
Plan Cumulative (orig) 2.00% 6.00% 11.00%
Actual Monthly (orig) 1.00% 3.50% 4.80%
Actual Cumulative (Orig) 1.00% 4.50% 9.30%
Plan Monthly (EOT)
Plan Cumulative(EOT)
Actual Monthly (EOT)
Actual Cumulative (EOT)
ORIGINAL
Year
Month Jan'13 Feb'13 Mar'13
Project Month Progress 1 2 3
Plan Monthly (Orig) 2.00% 4.00% 5.00%
Plan Cumulative (orig) 2.00% 6.00% 11.00%
Actual Monthly (orig) 1.00% 3.50% 4.80%
Actual Cumulative (orig) 1.00% 4.50% 9.30%
120.00%
100.00%
80.00%
60.00%
40.00%
20.00%
0.00%
1 2 3 4 5
60.00%
40.00%
20.00%
0.00%
1 2 3 4 5
ORIGINAL
Year
Month Jan'13 Feb'13 Mar'13
Project Month Progress 1 2 3
Plan Monthly (EOT) 1.00% 3.50% 4.80%
Plan Cumulative(EOT) 1.00% 4.50% 9.30%
Actual Monthly (EOT) 1.00% 3.50% 4.80%
Actual Cumulative (EOT) 1.00% 4.50% 9.30%
120.00%
100.00%
80.00%
60.00%
40.00%
20.00%
0.00%
1 2 3 4 5 6
3. Kurva S delay 94,6%
ORIGINAL
Year
Month Jan'13 Feb'13 Mar'13
Project Month Progress 1 2 3
Plan Monthly (EOT) 1.00% 3.50% 4.80%
Plan Cumulative(EOT) 1.00% 4.50% 9.30%
Actual Monthly (EOT) 1.00% 3.50% 4.80%
Actual Cumulative (EOT) 1.00% 4.50% 9.30%
Kurva
120.00%
100.00%
80.00%
Kurva
120.00%
100.00%
80.00%
40.00%
20.00%
0.00%
1 2 3 4 5 6 7 8 9
Bulan
ORIGINAL
Year
Month Jan'13 Feb'13 Mar'13
Project Month Progress 1 2 3
Plan Monthly (EOT) 1.00% 3.50% 4.80%
Plan Cumulative(EOT) 1.00% 4.50% 9.30%
Actual Monthly (EOT) 1.00% 3.50% 4.80%
Actual Cumulative (EOT) 1.00% 4.50% 9.30%
100.00%
90.00%
80.00%
70.00%
60.00%
Persentase 50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
1 2 3 4 5 6
10.00%
0.00%
1 2 3 4 5 6
LATIHAN MEMBUAT KURVA "S " DENGAN MS
2 3 4 5 6 7 8 9 10 11 12
2 3 4 5 6 7 8 9 10 11 12
2 3 4 5 6 7 8 9 10 11 12 13 14 15
Kurva S Delay
120.00%
100.00%
80.00%
Plan Kumulatif 12 bulan
Kurva S Delay
120.00%
100.00%
80.00%
Plan Kumulatif 12 bulan
60.00% Aktual Kumulatif 15 Bulan
Plan Akumulatif 15 bulan
40.00%
20.00%
0.00%
1 2 3 4 5 6 7 8 9 101112
Bulan
Kurva S
100.00%
90.00%
80.00%
70.00%
60.00%
Aktual Kumulatif 18 Bulan
e 50.00% Plan Kumulatif 15 bulan
Plan Kumuatif 12 bulan
40.00%
30.00%
20.00%
10.00%
0.00%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Bulan
10.00%
0.00%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Bulan
" DENGAN MS EXCEL
Des'13
12
3.00%
100.00%
EOT 3 BULAN DELAY 3 BULAN
2014
Des'13 Jan'14 Feb'14 Mar'14
12 13 14 15
4.50% 3.90% 2.70% 1.50%
91.90% 95.80% 98.50% 100.00%
5.20% 4.00% 3.00% 2.50%
85.10% 89.10% 92.10% 94.60%