Anda di halaman 1dari 2

RENCANA ANGGARAN BIAYA

PEKERJAAN JALAN & SALURAN KECAMATAN CIRACAS

HARGA SATUAN
No. JENIS PEKERJAAN VOLUME
(Rp)

1. Jalan SMA 58
a. Bobokan manual (Badan Jalan) 83.65 m3 350,000.00
b. Bobokan manual (Untuk Galian U-Ditch) 9.44 m3 350,000.00
.c. Urug Base Cause 45.63 m3 330,040.00
d. Pemasangan U-Ditch 60x60 143.50 m' 970,000.00
e. Pemasangan Tutup U-Ditch 60x60 143.50 m' 511,000.00
f. Beton Jepit 10/30 287.00 m' 45,000.00
g. Beton Fast Track K.350 85.54 m3 1,960,000.00
h. Beton B0 21.38 m3 800,000.00
TOTAL (1)

2. Jalan SMP 147


a. Bobokan manual (Untuk Galian U-Ditch) 40.92 m3 350,000.00
b. Bobokan manual (Badan Jalan) 54.38 m3 350,000.00
.c. Pemasangan U-Ditch 60x60 327.20 m' 970,000.00
d. Pemasangan Tutup U-Ditch 60x60 327.20 m' 511,000.00
e. Box Culvert 80x80 15.90 m' 2,400,000.00
f. Beton Jepit 10/30 331.00 m' 45,000.00
g. Beton Fast Track K.350 174.50 m3 1,960,000.00
h. Beton B0 43.62 m3 800,000.00
TOTAL (2)
GRAND TOTAL (1+2)
AN CIRACAS

JUMLAH HARGA
(Rp)

29,277,500.00
3,304,000.00
15,059,725.20
139,195,000.00
73,328,500.00
12,915,000.00
167,658,400.00
17,104,000.00
457,842,125.20

14,322,000.00
19,033,000.00
317,384,000.00
167,199,200.00
38,160,000.00
14,895,000.00
342,020,000.00
34,896,000.00
947,909,200.00
1,405,751,325.20