HARGA SATUAN
No. JENIS PEKERJAAN VOLUME
(Rp)
1. Jalan SMA 58
a. Bobokan manual (Badan Jalan) 83.65 m3 350,000.00
b. Bobokan manual (Untuk Galian U-Ditch) 9.44 m3 350,000.00
.c. Urug Base Cause 45.63 m3 330,040.00
d. Pemasangan U-Ditch 60x60 143.50 m' 970,000.00
e. Pemasangan Tutup U-Ditch 60x60 143.50 m' 511,000.00
f. Beton Jepit 10/30 287.00 m' 45,000.00
g. Beton Fast Track K.350 85.54 m3 1,960,000.00
h. Beton B0 21.38 m3 800,000.00
TOTAL (1)
JUMLAH HARGA
(Rp)
29,277,500.00
3,304,000.00
15,059,725.20
139,195,000.00
73,328,500.00
12,915,000.00
167,658,400.00
17,104,000.00
457,842,125.20
14,322,000.00
19,033,000.00
317,384,000.00
167,199,200.00
38,160,000.00
14,895,000.00
342,020,000.00
34,896,000.00
947,909,200.00
1,405,751,325.20