Anda di halaman 1dari 135

DUTAINTERIORMEDAN/AHSP/PERSIAPAN/HOSTEL/JALANPEMBANGUNAN/2019

A. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN


HARGA SATUAN
NO. URAIAN SATUAN KOEFISIEN
(Rp)
1. 1 M' Pagar Sementara Dari Kayu Tinggi 2 m
a. BAHAN
1 Dolken Kayu Ø 8-10 / 400 cm Btg 1.2500 14,569.00
2 Semen Portland Kg 2.5000 1,221.23
3 Pasir beton M3 0.0050 130,000.00
4 Koral Beton 2/3 M3 0.0090 242,959.50
5 Kayu balok terentang M3 0.0720 2,262,480.00
6 Paku Biasa 2" - 5" Kg 0.0600 20,053.80
7 Residu Kg 0.4000 6,941.70
JUMLAH BAHAN
b. UPAH
1 Pekerja Oh 0.4000 81,000.00
2 Tukang Kayu Oh 0.2000 108,000.00
3 Kepala Tukang Oh 0.0200 117,000.00
4 Mandor Oh 0.0200 90,000.00
JUMLAH UPAH
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

2. 1 M' Pagar Sementara Seng Gelombang Tinggi 2 m


a. BAHAN
1 Dolken Kayu Ø 8-10 / 400 cm Btg 1.2500 14,569.00
2 Semen Portland Kg 2.5000 1,221.23
3 Seng Gelombang BJLS-20 Lbr 1.2000 22,853.33
4 Pasir beton M3 0.0050 130,000.00
5 Koral Beton 2/3 M3 0.0090 242,959.50
6 Kayu balok terentang M3 0.0720 2,262,480.00
7 Paku Biasa 2" - 5" Kg 0.0600 20,053.80
8 Meni Besi Kg 0.4500 26,052.80
JUMLAH BAHAN
b. UPAH
1 Pekerja Oh 0.4000 81,000.00
2 Tukang Kayu Oh 0.2000 108,000.00
3 Kepala Tukang Oh 0.0200 117,000.00
4 Mandor Oh 0.0200 90,000.00
JUMLAH UPAH
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

3. 1 M' Pagar Sementara Kawat Duri Tinggi 1,80 m


a. BAHAN
1 Dolken Kayu Ø 8-10 / 400 cm Btg 1.0000 14,569.00
2 Semen Portland Kg 2.0000 1,221.23
3 Kawat Duri Kg 2.5000 54,419.50
4 Pasir beton M3 0.0050 130,000.00
5 Koral Beton 2/3 M3 0.0090 242,959.50
6 Paku Biasa 2" - 5" Kg 0.0600 20,053.80
JUMLAH BAHAN
b. UPAH
1 Pekerja Oh 0.3000 81,000.00
2 Tukang Kayu Oh 0.2000 108,000.00
3 Kepala Tukang Oh 0.0200 117,000.00
4 Mandor Oh 0.0200 90,000.00
JUMLAH UPAH
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

Halaman 1 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PERSIAPAN/HOSTEL/JALANPEMBANGUNAN/2019

A. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN


HARGA SATUAN
NO. URAIAN SATUAN KOEFISIEN
(Rp)

4. 1 M' Pengukuran Dan Pasang Bouwplank


a. BAHAN
1 Kayu kaso 5/7 M3 0.0060 2,876,777.60
2 Paku Biasa 2" - 5" Kg 0.0200 20,053.80
JUMLAH BAHAN
b. UPAH
1 Pekerja Oh 0.1000 81,000.00
2 Tukang Kayu Oh 0.1000 108,000.00
3 Kepala Tukang Oh 0.0100 117,000.00
4 Mandor Oh 0.0050 90,000.00
JUMLAH UPAH
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

5. 1 M² Pembuatan Kantor Sementara dgn Lantai Diplester


a. BAHAN
1 Dolken Kayu Ø 8-10 / 400 cm Btg 1.2500 14,569.00
2 Kayu Balok terentang M3 0.1800 2,262,480.00
3 Paku Biasa Kg 0.8500 20,053.80
4 Besi Strip Kg 1.1000 22,967.60
5 Semen Portland Kg 35.0000 1,221.23
6 Pasir Pasang M3 0.1500 110,000.00
7 Pasir beton M3 0.1000 130,000.00
8 Koral Beton2/3 M3 0.1500 242,959.50
9 Bata Merah Bh 30.0000 599.90
10 Seng Plat m' 0.2500 13,553.46
11 Kaca Polos 3mm M2 0.0800 74,901.80
12 Triplek 120 x 240 x 0,4 cm Lbr 0.0600 53,562.50
JUMLAH BAHAN
b. UPAH
1 Pekerja Oh 2.0000 81,000.00
2 Tukang Kayu Oh 2.0000 108,000.00
3 Tukang Batu Oh 1.0000 108,000.00
4 Kepala Tukang Oh 0.3000 117,000.00
5 Mandor Oh 0.0500 90,000.00
JUMLAH UPAH
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

6. 1 M² Pembuatan Gudang Semen dan Alat-alat


a. BAHAN
1 Dolken Kayu Ø 8-10 / 400 cm Btg 1.7000 14,569.00
2 Kayu balok terentang M3 0.2100 2,262,480.00
3 Paku Biasa Kg 0.3000 20,053.80
4 Semen Portland Kg 10.5000 1,221.23
5 Pasir Beton M3 0.0300 130,000.00
6 Koral Beton 2/3 M3 0.0500 242,959.50
7 Seng Gelombang BJLS 30 Lbr 1.5000 22,853.33
JUMLAH BAHAN
b. UPAH
1 Pekerja Oh 1.0000 81,000.00
2 Tukang Kayu Oh 2.0000 108,000.00
3 Kepala Tukang Oh 0.2000 117,000.00
4 Mandor Oh 0.0500 90,000.00
JUMLAH UPAH

Halaman 2 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PERSIAPAN/HOSTEL/JALANPEMBANGUNAN/2019

A. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN


HARGA SATUAN
NO. URAIAN SATUAN KOEFISIEN
(Rp)
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

7. 1 M² Pembuatan Bedeng Buruh


a. BAHAN
1 Dolken Kayu Ø 8-10 / 400 cm Btg 1.2500 14,569.00
2 Kayu balok terentang M3 0.1860 2,262,480.00
3 Paku Biasa Kg 0.3000 20,053.80
4 Semen Portland Kg 18.0000 1,221.23
5 Pasir Beton M3 0.0300 130,000.00
6 Koral Beton 2/3 M3 0.0500 242,959.50
7 Seng Gelombang BJLS 30 Lbr 1.5000 22,853.33
JUMLAH BAHAN
b. UPAH
1 Pekerja Oh 1.0000 81,000.00
2 Tukang Kayu Oh 2.0000 108,000.00
3 Kepala Tukang Oh 0.2000 117,000.00
4 Mandor Oh 0.0500 90,000.00
JUMLAH UPAH
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

8. 1 M² Membersihkan Lapangan dan Perataan


a. UPAH
1 Pekerja Oh 0.1000 81,000.00
2 Mandor Oh 0.0500 90,000.00
JUMLAH UPAH
b. JUMLAH UPAH
c. DIBULATKAN

9. 1 M² Pembuatan Jalan Sementara


a. BAHAN
1 Batu Belah 15/20 M3 0.1500 188,540.00
2 Batu Pecah 5/7 M3 0.0900 188,111.50
3 Pasir Pasang M3 0.0100 110,000.00
JUMLAH BAHAN
b. UPAH
1 Pekerja Oh 1.0000 81,000.00
2 Mandor Oh 0.0500 90,000.00
JUMLAH UPAH
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

10. 1 M3 Bongkaran Beton Bertulang


a. UPAH
1 Pekerja Oh 6.6670 81,000.00
2 Mandor Oh 0.3330 90,000.00
JUMLAH UPAH
b. JUMLAH UPAH
c. DIBULATKAN

11. 1 M3 Bongkaran Dinding Tembok Bata Merah


a. UPAH
1 Pekerja Oh 6.6670 81,000.00
2 Mandor Oh 0.0330 90,000.00
JUMLAH UPAH

Halaman 3 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PERSIAPAN/HOSTEL/JALANPEMBANGUNAN/2019

A. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN


HARGA SATUAN
NO. URAIAN SATUAN KOEFISIEN
(Rp)
b. JUMLAH UPAH
c. DIBULATKAN

12. 1 M¹ Pagar beton Pracetak ( 5 x 50 x 213 ) cm


a. BAHAN
1 Panel Beton Pracetak Lbr 0.9860 #REF!
2 Kolom Beton Pracetak Btg 0.5250 #REF!
3 Pasir Beton M3 0.0740 130,000.00
4 Koral 2/3 M3 0.1460 242,959.50
5 Semen abu - abu Kg 45.0000 1,221.23
JUMLAH BAHAN
b. UPAH
1 Pekerja Oh 0.3750 81,000.00
2 Tukang Batu Oh 0.1250 108,000.00
3 Kepala Tukang Oh 0.0120 117,000.00
4 Mandor Oh 0.0190 90,000.00
JUMLAH UPAH
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

13. 1 M¹ Pagar kawat ayam tiang besi L50.50.5, tinggi 1 m'


a. BAHAN
1 Kawat ram ayam Lbr 0.4340 #REF!
2 Besi siku L 50.50.5 Kg 6.7860 #REF!
3 Besi pelat (1,2 x 3) mm Kg 0.0424 #REF!
4 Baut bh 4.0000 514.20
5 Semen Portland Kg 2.5000 1,221.23
6 Pasir beton M3 0.0050 130,000.00
7 Koral Beton 2/3 M3 0.0090 242,959.50
JUMLAH BAHAN
b. UPAH
1 Pekerja Oh 0.3750 81,000.00
2 Tukang Batu Oh 0.1250 108,000.00
3 Kepala Tukang Oh 0.0120 117,000.00
4 Mandor Oh 0.0190 90,000.00
JUMLAH UPAH
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

14. 1 M2 Pagar BRC lengkap dengan tiang


a. BAHAN
1 BRC lengkap dengan tiang Lbr 0.4340 146,804.10
2 Semen Portland Kg 2.0000 1,221.23
3 Kawat Duri Kg 2.5000 54,419.50
4 Pasir beton M3 0.0050 130,000.00
5 Koral Beton 2/3 M3 0.0090 242,959.50
JUMLAH BAHAN
b. UPAH
1 Pekerja Oh 0.3750 81,000.00
2 Tukang Batu Oh 0.1250 108,000.00
3 Kepala Tukang Oh 0.0120 117,000.00
4 Mandor Oh 0.0190 90,000.00
JUMLAH UPAH
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

Halaman 4 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PERSIAPAN/HOSTEL/JALANPEMBANGUNAN/2019

A. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN


HARGA SATUAN
NO. URAIAN SATUAN KOEFISIEN
(Rp)
15. 1 M2 Steiger Werk / perancah dari Bambu
a. BAHAN
1 Bambu Ø 6 - 10 (600) cm btng 1.0000 12,855.00
2 Tali ijuk kg 0.2500 20,053.80
3 Pekerja org 0.2500 81,000.00
JUMLAH BAHAN
b. UPAH
1 Tukang kayu org 0.0170 108,000.00
2 Kepala tukang org 0.0020 117,000.00
3 Mandor org 0.0130 90,000.00
JUMLAH UPAH
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

16. 1 Set Memasang dan Membongkar Steiger Scafolding


a. BAHAN
1 Scafolding Set 1.0000 1,714.00
JUMLAH BAHAN
b. UPAH
1 Pekerja org 0.5000 81,000.00
2 Mandor org 0.0250 90,000.00
JUMLAH UPAH
c. JUMLAH UPAH + BAHAN
d. DIBULATKAN

Halaman 5 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PERSIAPAN/HOSTEL/JALANPEMBANGUNAN/2019

A. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN


HARGA SATUAN
NO. URAIAN SATUAN KOEFISIEN
(Rp)

Halaman 6 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PERSIAPAN/HOSTEL/JALANPEMBANGUNAN/2019

P.P
HARGA
(Rp)

Rp 18,211.25
Rp 3,053.06
Rp 650.00
Rp 2,186.64
Rp 162,898.56
Rp 1,203.23
Rp 2,776.68
Rp 190,979.42

Rp 32,400.00
Rp 21,600.00
Rp 2,340.00
Rp 1,800.00
Rp 58,140.00
Rp 249,119.42
Rp 249,119.00

Rp 18,211.25
Rp 3,053.06
Rp 27,424.00
Rp 650.00
Rp 2,186.64
Rp 162,898.56
Rp 1,203.23
Rp 11,723.76
Rp 227,350.50

Rp 32,400.00
Rp 21,600.00
Rp 2,340.00
Rp 1,800.00
Rp 58,140.00
Rp 285,490.50
Rp 285,490.00

Rp 14,569.00
Rp 2,442.45
Rp 136,048.75
Rp 650.00
Rp 2,186.64
Rp 1,203.23
Rp 157,100.06

Rp 24,300.00
Rp 21,600.00
Rp 2,340.00
Rp 1,800.00
Rp 50,040.00
Rp 207,140.06
Rp 207,140.00

Halaman 7 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PERSIAPAN/HOSTEL/JALANPEMBANGUNAN/2019

P.P
HARGA
(Rp)

Rp 17,260.67
Rp 401.08
Rp 17,661.74

Rp 8,100.00
Rp 10,800.00
Rp 1,170.00
Rp 450.00
Rp 20,520.00
Rp 38,181.74
Rp 38,182.00

Rp 18,211.25
Rp 407,246.40
Rp 17,045.73
Rp 25,264.36
Rp 42,742.88
Rp 16,500.00
Rp 13,000.00
Rp 36,443.93
Rp 17,997.00
Rp 3,388.36
Rp 5,992.14
Rp 3,213.75
Rp 607,045.80

Rp 162,000.00
Rp 216,000.00
Rp 108,000.00
Rp 35,100.00
Rp 4,500.00
Rp 525,600.00
Rp 869,845.80
Rp 869,846.00

Rp 24,767.30
Rp 475,120.80
Rp 6,016.14
Rp 12,822.86
Rp 3,900.00
Rp 12,147.98
Rp 34,280.00
Rp 569,055.08

Rp 81,000.00
Rp 216,000.00
Rp 23,400.00
Rp 4,500.00
Rp 324,900.00

Halaman 8 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PERSIAPAN/HOSTEL/JALANPEMBANGUNAN/2019

P.P
HARGA
(Rp)
Rp 731,505.08
Rp 731,505.00

Rp 18,211.25
Rp 420,821.28
Rp 6,016.14
Rp 21,982.05
Rp 3,900.00
Rp 12,147.98
Rp 34,280.00
Rp 517,358.70

Rp 81,000.00
Rp 216,000.00
Rp 23,400.00
Rp 4,500.00
Rp 324,900.00
Rp 679,808.70
Rp 679,809.00

Rp 8,100.00
Rp 4,500.00
Rp 12,600.00
Rp 6,300.00
Rp 6,300.00

Rp 28,281.00
Rp 16,930.04
Rp 1,100.00
Rp 46,311.04

Rp 81,000.00
Rp 4,500.00
Rp 85,500.00
Rp 89,061.04
Rp 89,061.00

Rp 540,027.00
Rp 29,970.00
Rp 569,997.00
Rp 569,997.00
Rp 569,997.00

Rp 540,027.00
Rp 2,970.00
Rp 542,997.00

Halaman 9 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PERSIAPAN/HOSTEL/JALANPEMBANGUNAN/2019

P.P
HARGA
(Rp)
Rp 841,495.50
Rp 841,496.00

#REF!
#REF!
Rp 9,620.00
Rp 35,472.09
Rp 54,955.13
#REF!

Rp 30,375.00
Rp 13,500.00
Rp 1,404.00
Rp 1,710.00
Rp 46,989.00
#REF!
#REF!

#REF!
#REF!
#REF!
Rp 2,056.80
Rp 3,053.06
Rp 650.00
Rp 2,186.64
#REF!

Rp 30,375.00
Rp 13,500.00
Rp 1,404.00
Rp 1,710.00
Rp 46,989.00
#REF!
#REF!

Rp 63,712.98
Rp 2,442.45
Rp 136,048.75
Rp 650.00
Rp 2,186.64
Rp 205,040.81

Rp 30,375.00
Rp 13,500.00
Rp 1,404.00
Rp 1,710.00
Rp 46,989.00
Rp 228,535.31
Rp 228,535.00

Halaman 10 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PERSIAPAN/HOSTEL/JALANPEMBANGUNAN/2019

P.P
HARGA
(Rp)

Rp 12,855.00
Rp 5,013.45
Rp 20,250.00
Rp 38,118.45

Rp 1,836.00
Rp 234.00
Rp 1,170.00
Rp 3,240.00
Rp 39,738.45
Rp 39,738.00

Rp 1,714.00
Rp 1,714.00

Rp 40,500.00
Rp 2,250.00
Rp 42,750.00
Rp 23,089.00
Rp 23,089.00

Halaman 11 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PERSIAPAN/HOSTEL/JALANPEMBANGUNAN/2019

P.P
HARGA
(Rp)

Halaman 12 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/TANAH/HOSTEL/JALANPEMBANGUNAN/2019

B. ANALISA HARGA SATUAN PEKERJAAN TANAH P.T.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1. 1 M³ Galian Tanah Biasa sedalam 1 m
a. UPAH
1 Pekerja Oh 0.4000 81,000.00 Rp 32,400.00
2 Mandor Oh 0.0400 90,000.00 Rp 3,600.00
JUMLAH UPAH Rp 36,000.00
b. JUMLAH UPAH + BAHAN Rp 36,000.00
c. DIBULATKAN Rp 36,000.00

2. 1 M³ Galian Tanah Biasa Sedalam 2 m


a. UPAH
1 Pekerja Oh 0.5260 81,000.00 Rp 42,606.00
2 Mandor Oh 0.0520 90,000.00 Rp 4,680.00
JUMLAH UPAH Rp 47,286.00
b. JUMLAH UPAH + BAHAN Rp 47,286.00
c. DIBULATKAN Rp 47,286.00

3. 1 M³ Galian Tanah Biasa Sedalam 3 m


a. UPAH
1 Pekerja Oh 0.7350 81,000.00 Rp 59,535.00
2 Mandor Oh 0.0730 90,000.00 Rp 6,570.00
JUMLAH UPAH Rp 66,105.00
b. JUMLAH UPAH Rp 66,105.00
c. DIBULATKAN Rp 66,105.00

4. 1 M³ Galian Tanah Keras Sedalam 1 m


a. UPAH
1 Pekerja Oh 0.6250 81,000.00 Rp 50,625.00
2 Mandor Oh 0.0620 90,000.00 Rp 5,580.00
JUMLAH UPAH Rp 56,205.00
b. JUMLAH UPAH + BAHAN Rp 56,205.00
c. DIBULATKAN Rp 56,205.00

5. 1 M³ Galian Tanah Lumpur Sedalam 1 m


a. UPAH
1 Pekerja Oh 0.8230 81,000.00 Rp 66,663.00
2 Mandor Oh 0.0830 90,000.00 Rp 7,470.00
JUMLAH UPAH Rp 74,133.00
b. JUMLAH UPAH + BAHAN Rp 74,133.00
c. DIBULATKAN Rp 74,133.00

6. 1 M² Pekerjaan Stripping Setinggi 10 cm


a. UPAH
1 Pekerja Oh 0.0500 81,000.00 Rp 4,050.00
2 Mandor Oh 0.0050 90,000.00 Rp 450.00
JUMLAH UPAH Rp 4,500.00
b. JUMLAH UPAH + BAHAN Rp 4,500.00
c. DIBULATKAN Rp 4,500.00

7. 1 M³ Pembuangan Tanah sejauh 150 m


a. UPAH
1 Pekerja Oh 0.5160 81,000.00 Rp 41,796.00
2 Mandor Oh 0.0500 90,000.00 Rp 4,500.00
JUMLAH UPAH Rp 46,296.00
b. JUMLAH UPAH + BAHAN Rp 46,296.00

Halaman 13 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/TANAH/HOSTEL/JALANPEMBANGUNAN/2019

B. ANALISA HARGA SATUAN PEKERJAAN TANAH P.T.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
c. DIBULATKAN Rp 46,296.00

8. 1 M³ Urugan Kembali
a. UPAH
1 Pekerja Oh 0.1920 81,000.00 Rp 15,552.00
2 Mandor Oh 0.0190 90,000.00 Rp 1,710.00
JUMLAH UPAH Rp 17,262.00
b. JUMLAH UPAH + BAHAN Rp 17,262.00
c. DIBULATKAN Rp 17,262.00

9. 1 M³ Pemadatan Tanah
a. UPAH
1 Pekerja Oh 0.5000 81,000.00 Rp 40,500.00
2 Mandor Oh 0.0500 90,000.00 Rp 4,500.00
JUMLAH UPAH Rp 45,000.00
b. JUMLAH UPAH + BAHAN Rp 45,000.00
c. DIBULATKAN Rp 45,000.00

10. 1 M³ Urugaan Pasir


a. BAHAN
1 Pasir Urug M3 1.2000 60,332.80 Rp 72,399.36
JUMLAH BAHAN Rp 72,399.36
b. UPAH
1 Pekerja Oh 0.3000 81,000.00 Rp 24,300.00
2 Mandor Oh 0.0100 90,000.00 Rp 900.00
JUMLAH UPAH Rp 25,200.00
b. JUMLAH UPAH + BAHAN Rp 84,999.36
c. DIBULATKAN Rp 84,999.00

11. 1 M² Pemasangan Lapisan Ijuk Tebal 10 cm


a. BAHAN
1 Ijuk m2 1.2000 18,854.00 Rp 22,624.80
JUMLAH BAHAN Rp 22,624.80
b. UPAH
1 Pekerja Oh 0.1500 81,000.00 Rp 12,150.00
2 Mandor Oh 0.0150 90,000.00 Rp 1,350.00
JUMLAH UPAH Rp 13,500.00
b. JUMLAH UPAH + BAHAN Rp 36,124.80
c. DIBULATKAN Rp 36,125.00

12. 1 M³ Urugan Sirtu


a. BAHAN
1 Sirtu M3 1.2000 174,399.50 Rp 209,279.40
JUMLAH BAHAN Rp 209,279.40
b. UPAH
1 Pekerja Oh 0.2500 81,000.00 Rp 20,250.00
2 Mandor Oh 0.0250 90,000.00 Rp 2,250.00
JUMLAH UPAH Rp 22,500.00
b. JUMLAH UPAH + BAHAN Rp 231,779.40
c. DIBULATKAN Rp 231,779.00

13. 1 M³ Urugan Tanah Pilihan


a. BAHAN
1 Tanah urug pilihan M3 1.2000 77,130.00 Rp 92,556.00

Halaman 14 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/TANAH/HOSTEL/JALANPEMBANGUNAN/2019

B. ANALISA HARGA SATUAN PEKERJAAN TANAH P.T.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
JUMLAH BAHAN Rp 92,556.00
b. UPAH
1 Pekerja Oh 0.2500 81,000.00 Rp 20,250.00
2 Mandor Oh 0.0250 90,000.00 Rp 2,250.00
JUMLAH UPAH Rp 22,500.00
b. JUMLAH UPAH + BAHAN Rp 115,056.00
c. DIBULATKAN Rp 115,056.00

14. 1 M² Pembuatan jalan sementara, tebal 25 cm


a. BAHAN
1 Batu belah M3 0.2750 188,540.00 Rp 51,848.50
2 Kerikil M3 0.0300 197,110.00 Rp 5,913.30
JUMLAH BAHAN Rp 57,761.80
b. UPAH
1 Pasir Urug M3 0.0500 60,332.80 Rp 3,016.64
2 Pekerja Oh 1.0000 81,000.00 Rp 81,000.00
3 Mandor Oh 0.1000 90,000.00 Rp 9,000.00
JUMLAH UPAH Rp 93,016.64
b. JUMLAH UPAH + BAHAN Rp 150,778.44
c. DIBULATKAN Rp 150,778.00

Halaman 15 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/TANAH/HOSTEL/JALANPEMBANGUNAN/2019

B. ANALISA HARGA SATUAN PEKERJAAN TANAH P.T.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)

Halaman 16 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PONDASI/HOSTEL/JALANPEMBANGUNAN/2019

C. ANALISA HARGA SATUAN PEKERJAAN PONDASI P.PD


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1. 1 M³ Pasanag Pondasi batu Kali adk 1pc : 3 ps
a. BAHAN
1 Batu Belah M3 1.1000 188,540.00 Rp 207,394.00
2 Semen Portland Kg 202.0000 1,221.23 Rp 246,687.45
3 Pasir Pasang M3 0.4850 110,000.00 Rp 53,350.00
JUMLAH BAHAN Rp 507,431.45
b. UPAH
1 Pekerja Oh 1.5000 72,000.00 Rp 108,000.00
2 Tukang Batu Oh 0.6000 108,000.00 Rp 64,800.00
3 Kepala Tukang Oh 0.0600 117,000.00 Rp 7,020.00
4 Mandor Oh 0.0750 90,000.00 Rp 6,750.00
JUMLAH UPAH Rp 186,570.00
b. JUMLAH UPAH + BAHAN Rp 694,001.45
c. DIBULATKAN Rp 694,001.00

2. 1 M³ Pasang Pondasi Batu kali adk 1pc : 4ps


a. BAHAN
1 Batu Belah M3 1.1000 188,540.00 Rp 207,394.00
2 Semen Portland Kg 163.0000 1,221.23 Rp 199,059.68
3 Pasir Pasang M3 0.5200 110,000.00 Rp 57,200.00
JUMLAH BAHAN Rp 463,653.68
b. UPAH
1 Pekerja Oh 1.5000 72,000.00 Rp 108,000.00
2 Tukang Batu Oh 0.6000 108,000.00 Rp 64,800.00
3 Kepala Tukang Oh 0.0600 117,000.00 Rp 7,020.00
4 Mandor Oh 0.0750 90,000.00 Rp 6,750.00
JUMLAH UPAH Rp 186,570.00
JUMLAH UPAH + BAHAN Rp 650,223.68
DIBULATKAN Rp 650,224.00

3. 1 M³ Pasang Pondasi Batu kali adk 1pc : 5ps


a. BAHAN
1 Batu Belah M3 1.1000 188,540.00 Rp 207,394.00
2 Semen Portland Kg 136.0000 1,221.23 Rp 166,086.60
3 Pasir Pasang M3 0.5440 110,000.00 Rp 59,840.00
JUMLAH BAHAN Rp 433,320.60
b. UPAH
1 Pekerja Oh 1.5000 72,000.00 Rp 108,000.00
2 Tukang Batu Oh 0.6000 108,000.00 Rp 64,800.00
3 Kepala Tukang Oh 0.0600 117,000.00 Rp 7,020.00
4 Mandor Oh 0.0750 90,000.00 Rp 6,750.00
JUMLAH UPAH Rp 186,570.00
JUMLAH UPAH + BAHAN Rp 619,890.60
DIBULATKAN Rp 619,891.00

4. 1 M³ Pasang Pondasi Batu Kosong (aanstamping)


a. BAHAN
1 Batu Belah M3 1.2000 188,540.00 Rp 226,248.00
2 Pasir Urug M3 0.3000 60,332.80 Rp 18,099.84
JUMLAH BAHAN Rp 244,347.84
b. UPAH
1 Pekerja Oh 0.7800 72,000.00 Rp 56,160.00
2 Tukang Batu Oh 0.3900 108,000.00 Rp 42,120.00
3 Kepala Tukang Oh 0.0390 117,000.00 Rp 4,563.00
4 Mandor Oh 0.0390 90,000.00 Rp 3,510.00
JUMLAH UPAH Rp 106,353.00

Halaman 17 dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PONDASI/HOSTEL/JALANPEMBANGUNAN/2019

C. ANALISA HARGA SATUAN PEKERJAAN PONDASI P.PD


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
JUMLAH UPAH + BAHAN Rp 350,700.84
DIBULATKAN Rp 350,701.00

Halaman 18 dari 135 Lembar


DUTAINTERIOR MEDAN/AHSP/BETON/HOSTEL/JALANPEMBANGUNAN/2019

D. ANALISA HARGA SATUAN PEKERJAAN BETON P.B.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1 1 M³ Membuat Beton Cor ; Spesi 1Pc:3Psr:5Krkl
a. BAHAN
1 Semen Portland Kg 247.0000 1,221.23 Rp 301,642.58
2 Pasir Beton M³ 0.8690 130,000.00 Rp 112,970.00
3 Batu Kerikil M³ 0.9990 242,959.50 Rp 242,716.54
4 Air Ltr 215.0000 45.11 Rp 9,697.63
JUMLAH BAHAN Rp 667,026.75
b. UPAH
1 Pekerja Oh 1.6500 81,000.00 Rp 133,650.00
2 Tukang Batu Oh 0.2500 108,000.00 Rp 27,000.00
3 Kepala Tukang Oh 0.0250 117,000.00 Rp 2,925.00
4 Mandor Oh 0.0800 90,000.00 Rp 7,200.00
JUMLAH UPAH Rp 170,775.00
JUMLAH Rp 837,801.75
DIBULATKAN Rp 837,802.00

2 1 M³ Membuat Beton Cor Mutu K-125 (fc'=9.8 Mpa), Slump (12+2),w/c=0,78


a. BAHAN
1 Semen Portland Kg 276.0000 1,221.23 Rp 337,058.10
2 Pasir Beton M³ 0.8280 130,000.00 Rp 107,640.00
3 Batu Kerikil M³ 1.0120 242,959.50 Rp 245,875.01
4 Air Ltr 215.0000 45.11 Rp 9,697.63
JUMLAH BAHAN Rp 700,270.75
b. UPAH
1 Pekerja Oh 1.6500 81,000.00 Rp 133,650.00
2 Tukang Batu Oh 0.2500 108,000.00 Rp 27,000.00
3 Kepala Tukang Oh 0.0250 117,000.00 Rp 2,925.00
4 Mandor Oh 0.0800 90,000.00 Rp 7,200.00
JUMLAH UPAH Rp 170,775.00
JUMLAH Rp 871,045.75
DIBULATKAN Rp 871,046.00

3 1 M³ Membuat Beton Cor Mutu K-150 (fc'=12.2 Mpa), Slump (12+2),w/c=0,72


a. BAHAN
1 Semen Portland Kg 299.0000 1,221.23 Rp 365,146.28
2 Pasir Beton M³ 0.7990 130,000.00 Rp 103,870.00
3 Batu Kerikil M³ 1.0170 242,959.50 Rp 247,089.81
4 Air Ltr 215.0000 45.11 Rp 9,697.63
JUMLAH BAHAN Rp 725,803.72
b. UPAH
1 Pekerja Oh 1.6500 81,000.00 Rp 133,650.00
2 Tukang Batu Oh 0.2500 108,000.00 Rp 27,000.00
3 Kepala Tukang Oh 0.0250 117,000.00 Rp 2,925.00
4 Mandor Oh 0.0800 90,000.00 Rp 7,200.00
JUMLAH UPAH Rp 170,775.00
JUMLAH Rp 896,578.72
DIBULATKAN Rp 896,579.00

4 1 M³ Membuat Beton Cor Mutu K-175 (fc'=14.5 Mpa), Slump (12+2),w/c=0,66


a. BAHAN
1 Semen Portland Kg 326.0000 1,221.23 Rp 398,119.35
2 Pasir Beton M³ 0.7600 130,000.00 Rp 98,800.00
3 Batu Kerikil M³ 1.0290 242,959.50 Rp 250,005.33
4 Air Ltr 215.0000 45.11 Rp 9,697.63
JUMLAH BAHAN Rp 756,622.31
b. UPAH

Halaman 19 dari 135 Lembar


DUTAINTERIOR MEDAN/AHSP/BETON/HOSTEL/JALANPEMBANGUNAN/2019

D. ANALISA HARGA SATUAN PEKERJAAN BETON P.B.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1 Pekerja Oh 1.6500 81,000.00 Rp 133,650.00
2 Tukang Batu Oh 0.2500 108,000.00 Rp 27,000.00
3 Kepala Tukang Oh 0.0250 117,000.00 Rp 2,925.00
4 Mandor Oh 0.0800 90,000.00 Rp 7,200.00
JUMLAH UPAH Rp 170,775.00
JUMLAH Rp 927,397.31
DIBULATKAN Rp 927,397.00

5 1 M³ Membuat Beton Cor Mutu K-200 (fc'=16.9 Mpa), Slump (12+2),w/c=0,61


a. BAHAN
1 Semen Portland Kg 352.0000 1,221.23 Rp 429,871.20
2 Pasir Beton M3 0.7310 130,000.00 Rp 95,030.00
3 Koral Beton 2/3 M3 1.0310 242,959.50 Rp 250,491.24
4 Air Ltr 215.0000 45.11 Rp 9,697.63
JUMLAH BAHAN Rp 785,090.08
b. UPAH
1 Pekerja Oh 1.6500 81,000.00 Rp 133,650.00
2 Tukang Batu Oh 0.2500 108,000.00 Rp 27,000.00
3 Kepala Tukang Oh 0.0250 117,000.00 Rp 2,925.00
4 Mandor Oh 0.0800 90,000.00 Rp 7,200.00
JUMLAH UPAH Rp 170,775.00
JUMLAH Rp 955,865.08
DIBULATKAN Rp 955,865.00

6 1 M³ Membuat Beton Cor Mutu K-225 (fc'=19.3 Mpa), Slump (12+2),w/c=0,58


a. BAHAN
1 Semen Portland Kg 371.0000 1,221.23 Rp 453,074.48
2 Pasir Beton m3 0.6980 130,000.00 Rp 90,740.00
3 Koral Beton 2/3 M3 1.0470 242,959.50 Rp 254,378.60
4 Air ltr 215.0000 45.11 Rp 9,697.63
JUMLAH BAHAN Rp 807,890.70
b. UPAH
1 Pekerja Oh 1.6500 81,000.00 Rp 133,650.00
2 Tukang Batu Oh 0.2500 108,000.00 Rp 27,000.00
3 Kepala Tukang Oh 0.0250 117,000.00 Rp 2,925.00
4 Mandor Oh 0.0800 90,000.00 Rp 7,200.00
JUMLAH UPAH Rp 170,775.00
JUMLAH Rp 978,665.70
DIBULATKAN Rp 978,666.00

7 1 M³ Membuat Beton Cor Mutu K-250 (fc'=21.7 Mpa), Slump (12+2),w/c=0,56


a. BAHAN
1 Semen Portland Kg 384.0000 1,221.23 Rp 468,950.40
2 Pasir Beton M3 0.6920 130,000.00 Rp 89,960.00
3 Koral Beton 2/3 M3 1.0390 242,959.50 Rp 252,434.92
4 Air ltr 215.0000 45.11 Rp 9,697.63
JUMLAH BAHAN Rp 821,042.95
b. UPAH
1 Pekerja Oh 1.6500 81,000.00 Rp 133,650.00
2 Tukang Batu Oh 0.2750 108,000.00 Rp 29,700.00
3 Kepala Tukang Oh 0.0280 117,000.00 Rp 3,276.00
4 Mandor Oh 0.0830 90,000.00 Rp 7,470.00
JUMLAH UPAH Rp 174,096.00
JUMLAH Rp 995,138.95
DIBULATKAN Rp 995,139.00

Halaman 20 dari 135 Lembar


DUTAINTERIOR MEDAN/AHSP/BETON/HOSTEL/JALANPEMBANGUNAN/2019

D. ANALISA HARGA SATUAN PEKERJAAN BETON P.B.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
8 1 M³ Membuat Beton Cor Mutu K-275 (fc'=26.4 Mpa), Slump (12+2),w/c=0,53
a. BAHAN
1 Semen Portland Kg 406.0000 1,221.23 Rp 495,817.35
2 Pasir Beton M3 0.6840 130,000.00 Rp 88,920.00
3 Koral Beton 2/3 M3 1.0260 242,959.50 Rp 249,276.45
4 Air ltr 215.0000 45.11 Rp 9,697.63
JUMLAH BAHAN Rp 843,711.43
b. UPAH
1 Pekerja Oh 1.6500 81,000.00 Rp 133,650.00
2 Tukang Batu Oh 0.2500 108,000.00 Rp 27,000.00
3 Kepala Tukang Oh 0.0250 117,000.00 Rp 2,925.00
4 Mandor Oh 0.0800 90,000.00 Rp 7,200.00
JUMLAH UPAH Rp 170,775.00
JUMLAH Rp 1,014,486.43
DIBULATKAN Rp 1,014,486.00

9 1 M³ Membuat Beton Cor Mutu K-300 (fc'=26.4 Mpa), Slump (12+2),w/c=0,52


a. BAHAN
1 Semen Portland Kg 413.0000 1,221.23 Rp 504,365.93
2 Pasir Beton M3 0.6810 130,000.00 Rp 88,530.00
3 Koral Beton 2/3 M3 1.0210 242,959.50 Rp 248,061.65
4 Air ltr 215.0000 45.11 Rp 9,697.63
JUMLAH BAHAN Rp 850,655.21
b. UPAH
1 Pekerja Oh 1.6500 81,000.00 Rp 133,650.00
2 Tukang Batu Oh 0.2750 108,000.00 Rp 29,700.00
3 Kepala Tukang Oh 0.0280 117,000.00 Rp 3,276.00
4 Mandor Oh 0.0830 90,000.00 Rp 7,470.00
JUMLAH UPAH Rp 174,096.00
JUMLAH Rp 1,024,751.21
DIBULATKAN Rp 1,024,751.00

10 1 M³ Membuat Tiang Pancang Beton Prestressed


a. BAHAN
1 Semen Portland Kg 440.0000 1,221.23 Rp 537,339.00
2 Pasir Beton M3 0.5000 130,000.00 Rp 65,000.00
3 Batu Kerikil M3 0.8000 242,959.50 Rp 194,367.60
4 Rapidrant Gln 2.4600 13,454.90 Rp 33,099.05
JUMLAH BAHAN Rp 829,805.65
b. UPAH
1 Pekerja Oh 1.6500 81,000.00 Rp 133,650.00
2 Tukang Batu Oh 0.2500 108,000.00 Rp 27,000.00
3 Kepala Tukang Oh 0.0250 117,000.00 Rp 2,925.00
4 Mandor Oh 0.0800 90,000.00 Rp 7,200.00
JUMLAH UPAH Rp 170,775.00
JUMLAH Rp 1,000,580.65
DIBULATKAN Rp 1,000,581.00

11 1 Kg Pembesian Dengan Besi Polos/ulir


a. BAHAN
1 Besi Beton ( Polos / Ulir ) Kg 1.0500 8,548.58 Rp 8,976.00
2 Kawat Beton Kg 0.0250 23,738.90 Rp 593.47
JUMLAH BAHAN Rp 9,569.48
b. UPAH
1 Pekerja Oh 0.0095 81,000.00 Rp 769.50
2 Tukang Besi Oh 0.0095 108,000.00 Rp 1,026.00

Halaman 21 dari 135 Lembar


DUTAINTERIOR MEDAN/AHSP/BETON/HOSTEL/JALANPEMBANGUNAN/2019

D. ANALISA HARGA SATUAN PEKERJAAN BETON P.B.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
3 Kepala Tukang Oh 0.0008 117,000.00 Rp 93.60
4 Mandor Oh 0.0004 90,000.00 Rp 36.00
JUMLAH UPAH Rp 1,925.10
JUMLAH Rp 11,494.58
DIBULATKAN Rp 11,495.00

12 1 Kg Memasang Jaring Kawat Baja


a. BAHAN
1 Jaring Kawat Baja M-6 Kg 1.0100 7,628.26 Rp 7,704.54
2 Kawat Beton Kg 0.0500 23,738.90 Rp 1,186.95
JUMLAH BAHAN Rp 8,891.48
b. UPAH
1 Pekerja Oh 0.0250 81,000.00 Rp 2,025.00
2 Tukang Besi Oh 0.0250 108,000.00 Rp 2,700.00
3 Kepala Tukang Oh 0.0020 117,000.00 Rp 234.00
4 Mandor Oh 0.0010 90,000.00 Rp 90.00
JUMLAH UPAH Rp 5,049.00
JUMLAH Rp 13,940.48
DIBULATKAN Rp 13,940.00

13 1 M² Pasang Bekesting Untuk Pondasi


a. BAHAN
1 Kayu papan terentang M3 0.0400 2,442,450.00 Rp 97,698.00
2 Paku Biasa 2" - 5" Kg 0.3000 20,053.80 Rp 6,016.14
3 Minyak Bekisting Ltr 0.1000 26,138.50 Rp 2,613.85
JUMLAH BAHAN Rp 106,327.99
Jumlah Bahan Mall Untuk 3 x pakai Ls 0.3333 106,327.99 Rp 35,442.66
b. UPAH
1 Pekerja Oh 0.0520 81,000.00 Rp 4,212.00
2 Tukang Kayu Oh 0.2600 108,000.00 Rp 28,080.00
3 Kepala Tukang Oh 0.0260 117,000.00 Rp 3,042.00
4 Mandor Oh 0.0050 90,000.00 Rp 450.00
JUMLAH UPAH Rp 35,784.00
JUMLAH Rp 71,226.66
DIBULATKAN Rp 71,227.00

14 1 M² Pasang Bekisting Untuk Sloof


a. BAHAN
1 Kayu papan terentang M3 0.0450 2,442,450.00 Rp 109,910.25
2 Paku Biasa 2" - 5" Kg 0.3000 20,053.80 Rp 6,016.14
3 Minyak Bekisting Ltr 0.1000 26,138.50 Rp 2,613.85
JUMLAH BAHAN Rp 118,540.24
Jumlah Bahan Mall Untuk 3 x pakai Ls 0.3333 118,540.24 Rp 39,513.41
b. UPAH
1 Pekerja Oh 0.0520 81,000.00 Rp 4,212.00
2 Tukang Kayu Oh 0.2600 108,000.00 Rp 28,080.00
3 Kepala Tukang Oh 0.0260 117,000.00 Rp 3,042.00
4 Mandor Oh 0.0050 90,000.00 Rp 450.00
JUMLAH UPAH Rp 35,784.00
JUMLAH Rp 75,297.41
DIBULATKAN Rp 75,297.00

15 1 M² Pasang Bekesting Untuk Kolom


a. BAHAN
1 Kayu balok terentang M3 0.0400 2,262,480.00 Rp 90,499.20
2 Paku Biasa 2" - 5" Kg 0.4000 20,053.80 Rp 8,021.52

Halaman 22 dari 135 Lembar


DUTAINTERIOR MEDAN/AHSP/BETON/HOSTEL/JALANPEMBANGUNAN/2019

D. ANALISA HARGA SATUAN PEKERJAAN BETON P.B.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
3 Minyak Bekisting Ltr 0.2000 26,138.50 Rp 5,227.70
4 Kayu balok terentang M3 0.0150 2,262,480.00 Rp 33,937.20
5 Multiplek Tbl.9mm Lbr 0.3500 89,556.50 Rp 31,344.78
6 Dolken Ø-8-10/4m Btg 2.0000 12,855.00 Rp 25,710.00
JUMLAH BAHAN Rp 194,740.40
Jumlah Bahan Mall Untuk 2,5 x pakai Ls 0.4000 194,740.40 Rp 77,896.16
b. UPAH
1 Pekerja Oh 0.6600 81,000.00 Rp 53,460.00
2 Tukang Kayu Oh 0.3300 108,000.00 Rp 35,640.00
3 Kepala Tukang Oh 0.0330 117,000.00 Rp 3,861.00
4 Mandor Oh 0.0330 90,000.00 Rp 2,970.00
JUMLAH UPAH Rp 95,931.00
JUMLAH Rp 173,827.16
DIBULATKAN Rp 173,827.00

16 1 M² Pasang Bekesting Untuk Balok


a. BAHAN
1 Kayu balok terentang M3 0.0400 2,262,480.00 Rp 90,499.20
2 Paku Biasa 2" - 5" Kg 0.4000 20,053.80 Rp 8,021.52
3 Minyak Bekisting Ltr 0.2000 26,138.50 Rp 5,227.70
4 Kayu balok terentang M3 0.0180 2,262,480.00 Rp 40,724.64
5 Multiplek Tbl.9mm Lbr 0.3500 89,556.50 Rp 31,344.78
6 Dolken Ø-8-10/4m Btg 2.0000 12,855.00 Rp 25,710.00
JUMLAH BAHAN Rp 201,527.84
Jumlah Bahan Mall Untuk 2 x pakai Ls 0.4000 201,527.84 Rp 80,611.13
b. UPAH
1 Pekerja Oh 0.6600 81,000.00 Rp 53,460.00
2 Tukang Kayu Oh 0.3300 108,000.00 Rp 35,640.00
3 Kepala Tukang Oh 0.0330 117,000.00 Rp 3,861.00
4 Mandor Oh 0.0330 90,000.00 Rp 2,970.00
JUMLAH UPAH Rp 95,931.00
JUMLAH Rp 176,542.13
DIBULATKAN Rp 176,542.00

17 1 M² Pasang Bekesting Untuk Lantai


a. BAHAN
1 Kayu balok terentang M3 0.0400 2,262,480.00 Rp 90,499.20
2 Paku Biasa 2" - 5" Kg 0.4000 20,053.80 Rp 8,021.52
3 Minyak Bekisting Ltr 0.2000 26,138.50 Rp 5,227.70
4 Kayu balok terentang M3 0.0150 2,262,480.00 Rp 33,937.20
5 Multiplek Tbl.9mm Lbr 0.3500 89,556.50 Rp 31,344.78
6 Dolken Ø-8-10/4m Btg 6.0000 12,855.00 Rp 77,130.00
JUMLAH BAHAN Rp 246,160.40
Jumlah Bahan Mall Untuk 2.5 x pakai Ls 0.4000 246,160.40 Rp 98,464.16
b. UPAH
1 Pekerja Oh 0.6600 81,000.00 Rp 53,460.00
2 Tukang Kayu Oh 0.3300 108,000.00 Rp 35,640.00
3 Kepala Tukang Oh 0.0330 117,000.00 Rp 3,861.00
4 Mandor Oh 0.0330 90,000.00 Rp 2,970.00
JUMLAH UPAH Rp 95,931.00
JUMLAH Rp 194,395.16
DIBULATKAN Rp 194,395.00

18 1 M² Pasang Bekesting Untuk Dinding


a. BAHAN
1 Kayu balok terentang M3 0.0300 2,262,480.00 Rp 67,874.40

Halaman 23 dari 135 Lembar


DUTAINTERIOR MEDAN/AHSP/BETON/HOSTEL/JALANPEMBANGUNAN/2019

D. ANALISA HARGA SATUAN PEKERJAAN BETON P.B.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
2 Paku Biasa 2" - 5" Kg 0.4000 20,053.80 Rp 8,021.52
3 Minyak Bekisting Ltr 0.2000 26,138.50 Rp 5,227.70
4 Kayu balok terentang M3 0.0200 2,262,480.00 Rp 45,249.60
5 Multiplek Tbl.9mm Lbr 0.3500 89,556.50 Rp 31,344.78
6 Dolken Ø-8-10/4m Btg 3.0000 12,855.00 Rp 38,565.00
7 Formit/ Penjaga Jarak Bekisting Btg 4.0000 12,855.00 Rp 51,420.00
JUMLAH BAHAN Rp 247,703.00
Jumlah Bahan Mall Untuk 2 x pakai Ls 0.4000 247,703.00 Rp 99,081.20
b. UPAH
1 Pekerja Oh 0.6600 81,000.00 Rp 53,460.00
2 Tukang Kayu Oh 0.3300 108,000.00 Rp 35,640.00
3 Kepala Tukang Oh 0.0330 117,000.00 Rp 3,861.00
4 Mandor Oh 0.0330 90,000.00 Rp 2,970.00
JUMLAH UPAH Rp 95,931.00
JUMLAH Rp 195,012.20
DIBULATKAN Rp 195,012.00

19 1 M² Pasang Bekesting Untuk Tangga


a. BAHAN
1 Kayu balok terentang M3 0.0300 2,262,480.00 Rp 67,874.40
2 Paku Biasa 2" - 5" Kg 0.4000 20,053.80 Rp 8,021.52
3 Minyak Bekisting Ltr 0.1000 26,138.50 Rp 2,613.85
4 Kayu balok terentang M3 0.0150 2,262,480.00 Rp 33,937.20
5 Multiplek Tbl.9mm Lbr 0.3500 89,556.50 Rp 31,344.78
6 Dolken Ø-8-10/4m Btg 2.0000 12,855.00 Rp 25,710.00
JUMLAH BAHAN Rp 169,501.75
Jumlah Bahan Mall Untuk 2 x pakai Ls 0.4000 169,501.75 Rp 67,800.70
b. UPAH
1 Pekerja Oh 0.6600 81,000.00 Rp 53,460.00
2 Tukang Kayu Oh 0.3300 108,000.00 Rp 35,640.00
3 Kepala Tukang Oh 0.0330 117,000.00 Rp 3,861.00
4 Mandor Oh 0.0330 90,000.00 Rp 2,970.00
JUMLAH UPAH Rp 95,931.00
JUMLAH Rp 163,731.70
DIBULATKAN Rp 163,732.00

Halaman 24 dari 135 Lembar


E. ANALISA HARGA SATUAN PEKERJAAN DINDING P.D.
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1 1 M² Pasang Bata Merah Tebal 1 Bata, 1pc : 3ps
a. BAHAN
- Bata Merah Bh 140.0000 599.90 Rp 83,986.00
- Semen Portland Kg 32.9500 1,221.23 Rp 40,239.36
- Pasir Pasang M3 0.0910 110,000.00 Rp 10,010.00
JUMLAH BAHAN Rp 134,235.36
b. UPAH
- Pekerja Oh 0.6500 72,000.00 Rp 46,800.00
- Tukang Batu Oh 0.2000 108,000.00 Rp 21,600.00
- Kepala Tukang Oh 0.0200 117,000.00 Rp 2,340.00
- Mandor Oh 0.0300 90,000.00 Rp 2,700.00
JUMLAH UPAH Rp 73,440.00
c. JUMLAH BAHAN + UPAH Rp 207,675.36
d. DIBULATKAN Rp 207,675.00

2 1 M² Pasang Bata Merah Tebal 1 Bata, 1pc : 4ps


a. BAHAN
- Bata Merah Bh 140.0000 599.90 Rp 83,986.00
- Semen Portland Kg 26.5500 1,221.23 Rp 32,423.52
- Pasir Pasang M3 0.0930 110,000.00 Rp 10,230.00
JUMLAH BAHAN Rp 126,639.52
b. UPAH
- Pekerja Oh 0.6500 72,000.00 Rp 46,800.00
- Tukang Batu Oh 0.2000 108,000.00 Rp 21,600.00
- Kepala Tukang Oh 0.0200 117,000.00 Rp 2,340.00
- Mandor Oh 0.0300 90,000.00 Rp 2,700.00
JUMLAH UPAH Rp 73,440.00
c. JUMLAH BAHAN + UPAH Rp 200,079.52
d. DIBULATKAN Rp 200,080.00

3 1 M² Pasang Bata Expose Brick; Tebal 1/2 Bata, Spesi 1pc : 2ps
a. BAHAN
- Bata Merah Bh 70.0000 1,714.00 Rp 119,980.00
- Semen Portland Kg 18.2000 1,221.23 Rp 22,226.30
- Pasir Pasang M3 0.1020 110,000.00 Rp 11,220.00
JUMLAH BAHAN Rp 153,426.30
b. UPAH
- Pekerja Oh 0.5850 72,000.00 Rp 42,120.00
- Tukang Batu Oh 0.1800 108,000.00 Rp 19,440.00
- Kepala Tukang Oh 0.0180 117,000.00 Rp 2,106.00
- Mandor Oh 0.0270 90,000.00 Rp 2,430.00
JUMLAH UPAH Rp 66,096.00
c. JUMLAH BAHAN + UPAH Rp 219,522.30
d. DIBULATKAN Rp 219,522.00

4 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 3ps


a. BAHAN
- Bata Merah Bh 70.0000 1,714.00 Rp 119,980.00
- Semen Portland Kg 14.3700 1,221.23 Rp 17,549.00
- Pasir Pasang M3 0.0400 110,000.00 Rp 4,400.00
JUMLAH BAHAN Rp 141,929.00
b. UPAH
- Pekerja Oh 0.3200 72,000.00 Rp 23,040.00
- Tukang Batu Oh 0.1000 108,000.00 Rp 10,800.00
- Kepala Tukang Oh 0.0100 117,000.00 Rp 1,170.00
- Mandor Oh 0.0150 90,000.00 Rp 1,350.00
JUMLAH UPAH Rp 36,360.00
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
c. JUMLAH BAHAN + UPAH Rp 178,289.00
d. DIBULATKAN Rp 178,289.00

5 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 4ps


a. BAHAN
- Bata Merah Bh 70.0000 1,714.00 Rp 119,980.00
- Semen Portland Kg 11.5000 1,221.23 Rp 14,044.09
- Pasir Pasang M3 0.0430 110,000.00 Rp 4,730.00
JUMLAH BAHAN Rp 138,754.09
b. UPAH
- Pekerja Oh 0.3200 72,000.00 Rp 23,040.00
- Tukang Batu Oh 0.1000 108,000.00 Rp 10,800.00
- Kepala Tukang Oh 0.0100 117,000.00 Rp 1,170.00
- Mandor Oh 0.0150 90,000.00 Rp 1,350.00
JUMLAH UPAH Rp 36,360.00
c. JUMLAH BAHAN + UPAH Rp 175,114.09
d. DIBULATKAN Rp 175,114.00
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
6 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 5ps
a. BAHAN
- Bata Merah Bh 70.0000 1,714.00 Rp 119,980.00
- Semen Portland Kg 9.6800 1,221.23 Rp 11,821.46
- Pasir Pasang M3 0.0450 110,000.00 Rp 4,950.00
JUMLAH BAHAN Rp 136,751.46
b. UPAH
- Pekerja Oh 0.3200 72,000.00 Rp 23,040.00
- Tukang Batu Oh 0.1000 108,000.00 Rp 10,800.00
- Kepala Tukang Oh 0.0100 117,000.00 Rp 1,170.00
- Mandor Oh 0.0150 90,000.00 Rp 1,350.00
JUMLAH UPAH Rp 36,360.00
c. JUMLAH BAHAN + UPAH Rp 173,111.46
d. DIBULATKAN Rp 173,111.00

7 1 M2 Pasang Dinding Roster Beton 20 x 20 adk 1pc : 3ps


a. BAHAN
- Roster / Terawang Bh 30.0000 12,683.60 Rp 380,508.00
- Semen Portland Kg 14.0000 1,221.23 Rp 17,097.15
- Pasir Pasang M3 0.0320 110,000.00 Rp 3,520.00
JUMLAH BAHAN Rp 401,125.15
b. UPAH
- Pekerja Oh 0.3000 72,000.00 Rp 21,600.00
- Tukang Batu Oh 0.1000 108,000.00 Rp 10,800.00
- Kepala Tukang Oh 0.0100 117,000.00 Rp 1,170.00
- Mandor Oh 0.0150 90,000.00 Rp 1,350.00
JUMLAH UPAH Rp 34,920.00
c. JUMLAH BAHAN + UPAH Rp 4,870.00
d. DIBULATKAN Rp 4,870.00

8 1 M2 Pasang Dinding Roster Beton 20 x 20 adk 1pc : 4ps


a. BAHAN
- Roster / Terawang Bh 30.0000 12,683.60 Rp 380,508.00
- Semen Portland Kg 11.0000 1,221.23 Rp 13,433.48
- Pasir Pasang M3 0.0350 110,000.00 Rp 3,850.00
JUMLAH BAHAN Rp 397,791.48
b. UPAH
- Pekerja Oh 0.3000 72,000.00 Rp 21,600.00
- Tukang Batu Oh 0.1000 108,000.00 Rp 10,800.00
- Kepala Tukang Oh 0.0100 117,000.00 Rp 1,170.00
- Mandor Oh 0.0150 90,000.00 Rp 1,350.00
JUMLAH UPAH Rp 34,920.00
c. JUMLAH BAHAN + UPAH Rp 5,200.00
d. DIBULATKAN Rp 5,200.00

9 1 M2 Pasang Dinding Roster/terawng (12 x 11 x 24) cm


a. BAHAN
- Roster / Terawang Bh 30.0000 12,683.60 Rp 380,508.00
- Semen Portland Kg 12.8000 1,221.23 Rp 15,631.68
- Pasir Pasang M3 0.0350 110,000.00 Rp 3,850.00
JUMLAH BAHAN Rp 399,989.68
b. UPAH
- Pekerja Oh 0.3000 72,000.00 Rp 21,600.00
- Tukang Batu Oh 0.1000 108,000.00 Rp 10,800.00
- Kepala Tukang Oh 0.0100 117,000.00 Rp 1,170.00
- Mandor Oh 0.0150 90,000.00 Rp 1,350.00
JUMLAH UPAH Rp 34,920.00
c. JUMLAH BAHAN + UPAH Rp 5,200.00
d. DIBULATKAN Rp 5,200.00
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
10 1 M2 Pasang Dinding Batako Besar Pres uk. 8x20x30 adk. 1pc:4ps
a. BAHAN
- Batako bh 13.0000 2,056.80 Rp 26,738.40
- PC kg 12.0000 1,221.23 Rp 14,654.70
- Pasir Pasang M3 0.0380 110,000.00 Rp 4,180.00
JUMLAH BAHAN Rp 45,573.10
b. UPAH
- Pekerja Oh 0.3000 72,000.00 Rp 21,600.00
- Tukang Batu Oh 0.1000 108,000.00 Rp 10,800.00
- Kepala Tukang Oh 0.0100 117,000.00 Rp 1,170.00
- Mandor Oh 0.0150 90,000.00 Rp 1,350.00
JUMLAH UPAH Rp 34,920.00
c. JUMLAH BAHAN + UPAH Rp 5,530.00
d. DIBULATKAN Rp 5,530.00
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
F. ANALISA HARGA SATUAN PEKERJAAN PLESTERAN P.PL.
HARGA SATUAN HARGA
No. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1. 1 M² Plesteran adk. 1pc : 2ps Tebal 15 mm
a. BAHAN
- Semen Portland Kg 10.2240 1,221.23 12,485.80
- Pasir Pasang M3 0.0170 110,000.00 1,870.00
JUMLAH BAHAN Rp 14,355.80
b. UPAH
- Pekerja Oh 0.2000 72,000.00 14,400.00
- Tukang Batu Oh 0.1500 108,000.00 16,200.00
- Kepala Tukang Oh 0.0150 117,000.00 1,755.00
- Mandor Oh 0.0100 90,000.00 900.00
JUMLAH UPAH Rp 33,255.00
JUMLAH Rp 47,610.80
DIBULATKAN Rp 47,611.00

2. 1 M² Plesteran adk. 1pc : 3ps Tebal 15 mm


a. BAHAN
- Semen Portland Kg 7.7760 1,221.23 9,496.25
- Pasir Pasang M3 0.0190 110,000.00 2,090.00
JUMLAH BAHAN Rp 11,586.25
b. UPAH
- Pekerja Oh 0.2000 72,000.00 14,400.00
- Tukang Batu Oh 0.1500 108,000.00 16,200.00
- Kepala Tukang Oh 0.0150 117,000.00 1,755.00
- Mandor Oh 0.0100 90,000.00 900.00
JUMLAH UPAH Rp 33,255.00
JUMLAH Rp 44,841.25
DIBULATKAN Rp 44,841.00

3 1 M² Plesteran adk. 1pc : 4ps Tebal 15 mm


a. BAHAN
- Semen Portland Kg 6.2400 1,221.23 7,620.44
- Pasir Pasang M3 0.0200 110,000.00 2,200.00
JUMLAH BAHAN Rp 9,820.44
b. UPAH
- Pekerja Oh 0.2000 72,000.00 14,400.00
- Tukang Batu Oh 0.1500 108,000.00 16,200.00
- Kepala Tukang Oh 0.0150 117,000.00 1,755.00
- Mandor Oh 0.0100 90,000.00 900.00
JUMLAH UPAH Rp 33,255.00
JUMLAH Rp 43,075.44
DIBULATKAN Rp 43,075.00

4 1 M² Plesteran Beton adk. 1pc : 2ps Tebal 15 mm


a. BAHAN
- Semen Portland Kg 9.3000 1,221.23 11,357.39
- Pasir Pasang M3 0.0180 110,000.00 1,980.00
JUMLAH BAHAN Rp 13,337.39
b. UPAH
- Pekerja Oh 0.2600 72,000.00 18,720.00
- Tukang Batu Oh 0.2000 108,000.00 21,600.00
- Kepala Tukang Oh 0.0200 117,000.00 2,340.00
- Mandor Oh 0.0130 90,000.00 1,170.00
JUMLAH UPAH Rp 43,830.00
JUMLAH Rp 57,167.39
DIBULATKAN Rp 57,167.00
HARGA SATUAN HARGA
No. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
5 1 M² Plesteran Beton adk. 1pc : 3ps Tebal 15 mm
a. BAHAN
- Semen Portland Kg 7.0700 1,221.23 8,634.06
- Pasir Pasang M3 0.0210 110,000.00 2,310.00
JUMLAH BAHAN Rp 10,944.06
b. UPAH
- Pekerja Oh 0.2600 72,000.00 18,720.00
- Tukang Batu Oh 0.2000 108,000.00 21,600.00
- Kepala Tukang Oh 0.0200 117,000.00 2,340.00
- Mandor Oh 0.0130 90,000.00 1,170.00
JUMLAH UPAH Rp 43,830.00
JUMLAH Rp 54,774.06
DIBULATKAN Rp 54,774.00

6 1 M² Plesteran Skoning adk. 1pc : 2ps, tebal 10mm


a. BAHAN
- Semen Portland Kg 0.5000 1,221.23 610.61
- Pasir Pasang M3 0.0130 110,000.00 1,430.00
JUMLAH BAHAN Rp 2,040.61
b. UPAH
- Pekerja Oh 0.0800 72,000.00 5,760.00
- Tukang Batu Oh 0.4000 108,000.00 43,200.00
- Kepala Tukang Oh 0.0400 117,000.00 4,680.00
- Mandor Oh 0.0040 90,000.00 360.00
JUMLAH UPAH Rp 54,000.00
JUMLAH Rp 56,040.61
DIBULATKAN Rp 56,041.00

7 1 M² Acian Plesteran
a. BAHAN
- Semen Portland Kg 2.0000 1,221.23 2,442.45
JUMLAH BAHAN Rp 2,442.45
b. UPAH
- Pekerja Oh 0.0953 72,000.00 6,864.00
- Tukang batu Oh 0.0713 108,000.00 7,704.00
- Kepala Tukang Oh 0.0070 117,000.00 819.00
- Mandor Oh 0.0070 90,000.00 630.00
JUMLAH UPAH Rp 16,017.00
JUMLAH Rp 18,459.45
DIBULATKAN Rp 18,459.00

8 1 M² Plesteran Siar adk. 1pc : 2ps batu belah


a. BAHAN
- Semen Portland Kg 6.3400 1,221.23 7,742.57
- Pasir Pasang M3 0.0120 110,000.00 1,320.00
JUMLAH BAHAN Rp 9,062.57
b. UPAH
- Pekerja Oh 0.3000 72,000.00 21,600.00
- Tukang Batu Oh 0.1500 108,000.00 16,200.00
- Kepala Tukang Oh 0.0150 117,000.00 1,755.00
- Mandor Oh 0.0150 90,000.00 1,350.00
JUMLAH UPAH Rp 40,905.00
JUMLAH Rp 49,967.57
DIBULATKAN Rp 49,968.00

9 1 M² Plesteran Siar adk. 1pc : 2ps dinding bata merah


a. BAHAN
- Semen Portland Kg 4.3200 1,221.23 5,275.69
HARGA SATUAN HARGA
No. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
- Pasir Pasang M3 0.0160 110,000.00 1,760.00
JUMLAH BAHAN Rp 7,035.69
b. UPAH
- Pekerja Oh 0.1500 72,000.00 10,800.00
- Tukang Batu Oh 0.0700 108,000.00 7,560.00
- Kepala Tukang Oh 0.0070 117,000.00 819.00
- Mandor Oh 0.0080 90,000.00 720.00
JUMLAH UPAH Rp 19,899.00
JUMLAH Rp 26,934.69
DIBULATKAN Rp 26,935.00

10 1 M' Pengecapan Bidang Plesteran Lebar 15-30 cm


a. BAHAN
- Semen Portland Kg 1.4400 1,221.23 1,758.56
JUMLAH BAHAN Rp 1,758.56
b. UPAH
- Pekerja Oh 0.1875 72,000.00 13,500.00
- Tukang Batu Oh 0.0875 108,000.00 9,450.00
- Kepala Tukang Oh 0.0088 117,000.00 1,023.75
- Mandor Oh 0.0100 90,000.00 900.00
JUMLAH UPAH Rp 24,873.75
c. ALAT BANTU
- 15% * (Jumlah Bahan + Upah ) Ls 0.1500 26,632.31 3,994.85
JUMLAH ALAT BANTU Rp 3,994.85
JUMLAH UPAH Rp 30,627.16
DIBULATKAN Rp 30,627.00

11 1 M' Pengecapan Bidang Plesteran Lebar 1-15 cm


a. BAHAN
- Semen Portland Kg 1.4400 1,221.23 1,758.56
JUMLAH BAHAN Rp 1,758.56
b. UPAH
- Pekerja Oh 0.2625 72,000.00 18,900.00
- Tukang Batu Oh 0.1225 108,000.00 13,230.00
- Kepala Tukang Oh 0.0123 117,000.00 1,433.25
- Mandor Oh 0.0140 90,000.00 1,260.00
JUMLAH UPAH Rp 34,823.25
c. ALAT BANTU
- 15% * (Jumlah Bahan + Upah ) Ls 0.1500 36,581.81 5,487.27
JUMLAH ALAT BANTU Rp 5,487.27
JUMLAH UPAH Rp 42,069.09
DIBULATKAN Rp 42,069.00
HARGA SATUAN HARGA
No. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
DUTAINTERIORMEDAN/AHSP/PENUTUPATAP/HOSTEL/JALAN PEMBANGUNAN/2019

G. ANALISA HARGA SATUAN PEKERJAAN PENUTUP ATAP P.P.A.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1 1 M² Pasang Rangka Atap Baja Ringan
a. BAHAN
1 Main Trust C-75 M' 2.5000 12,255.10 30,637.75
2 Roof Bottom (Reng R33-45 M' 3.5000 7,698.72 26,945.51
3 Self Drilling Screw dia 6x20 mm (trust screw) Bh 15.0000 141.41 2,121.08
4 Self Drilling Screw dia 4x16 mm (roof bottom ) Bh 25.0000 235.68 5,891.88
5 Dinabolt M-10 Bh 1.0000 2,571.00 2,571.00
JUMLAH BAHAN Rp 68,167.21
b. UPAH
1 Pekerja Oh 0.1760 81,000.00 14,256.00
2 Tukang kayu Oh 0.1176 108,000.00 12,700.80
3 Kepala tukang Oh 0.0100 117,000.00 1,170.00
4 Mandor Oh 0.0010 90,000.00 90.00
JUMLAH UPAH Rp 28,216.80
c. JUMLAH UPAH + BAHAN Rp 96,384.01
d. DIBULATKAN Rp 96,384.00

2 1 M² Pasang Atap Genteng Metal


a. BAHAN
1 Genteng metal m2 1.0500 44,092.65 46,297.28
2 Self Drilling Screw dia 4x16 mm (roof bottom ) Bh 10.0000 235.68 2,356.75
JUMLAH BAHAN Rp 48,654.03
b. UPAH
1 Pekerja Oh 0.1408 81,000.00 11,404.80
2 Tukang kayu Oh 0.0941 108,000.00 10,160.64
3 Kepala tukang Oh 0.0080 117,000.00 936.00
4 Mandor Oh 0.0008 90,000.00 72.00
JUMLAH UPAH Rp 22,573.44
c. JUMLAH UPAH + BAHAN Rp 71,227.47
d. DIBULATKAN Rp 71,227.00

3 1 M¹ Pasang Nok Genteng Metal


a. BAHAN
1 Nok stel gelombang Lbr 2.1000 69,331.30 145,595.73
2 Paku sekrup 3,5" Bh 6.0000 685.60 4,113.60
JUMLAH BAHAN Rp 149,709.33
b. UPAH
1 Pekerja Oh 0.0840 81,000.00 6,804.00
2 Tukang kayu Oh 0.1250 108,000.00 13,500.00
3 Kepala tukang Oh 0.0130 117,000.00 1,521.00
4 Mandor Oh 0.0040 90,000.00 360.00
JUMLAH UPAH Rp 22,185.00
c. JUMLAH UPAH + BAHAN Rp 171,894.33
d. DIBULATKAN Rp 171,894.00

4 1 M2 Pasang Alluminium Foil / Sisalation


a. BAHAN
1 Sisalation / alluminium foil M2 1.0500 12,855.00 13,497.75
JUMLAH BAHAN Rp 13,497.75
b. UPAH
1 Pekerja Oh 0.1500 81,000.00 12,150.00
2 Tukang kayu Oh 0.0500 108,000.00 5,400.00
3 Kepala tukang Oh 0.0050 117,000.00 585.00
4 Mandor Oh 0.0080 90,000.00 720.00
JUMLAH UPAH Rp 18,855.00

Halaman 34 Dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PENUTUPATAP/HOSTEL/JALAN PEMBANGUNAN/2019

G. ANALISA HARGA SATUAN PEKERJAAN PENUTUP ATAP P.P.A.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
c. JUMLAH UPAH + BAHAN Rp 32,352.75
d. DIBULATKAN Rp 32,353.00

5 1 M' Pasang Lisplank GRC ukuran 30 cm


a. BAHAN
1 GRC M' 0.3300 17,259.03 5,695.48
2 Paku GRC kg 0.0500 29,995.00 1,499.75
JUMLAH BAHAN Rp 7,195.23
b. UPAH
1 Pekerja Oh 0.1000 81,000.00 8,100.00
2 Tukang kayu Oh 0.2000 108,000.00 21,600.00
3 Kepala tukang Oh 0.0200 117,000.00 2,340.00
4 Mandor Oh 0.0050 90,000.00 450.00
JUMLAH UPAH Rp 32,490.00
c. JUMLAH UPAH + BAHAN Rp 39,685.23
d. DIBULATKAN Rp 39,685.00

6 1 M' Pasang Lisplank Cutting GRC


a. BAHAN
1 GRC M' 0.3300 72.85 24.04
2 Paku GRC kg 0.0500 195,310.30 9,765.52
JUMLAH BAHAN Rp 9,789.55
b. UPAH
1 Pekerja Oh 0.1000 81,000.00 8,100.00
2 Tukang kayu Oh 0.2000 108,000.00 21,600.00
3 Kepala tukang Oh 0.0200 117,000.00 2,340.00
4 Mandor Oh 0.0050 90,000.00 450.00
JUMLAH UPAH Rp 32,490.00
c. JUMLAH UPAH + BAHAN Rp 42,279.55
d. DIBULATKAN Rp 42,280.00

7 1 M' Seng BJLS


a. BAHAN
1 Seng Plat M' 1.0500 17,826.46 18,717.78
2 Self Drilling Screw dia 4x16 mm (roof bottom ) Kg 0.0150 235.68 3.54
3 Papan M³ 0.0190 1,775,446.90 33,733.49
JUMLAH BAHAN Rp 52,454.81
b. UPAH
1 Pekerja Oh 0.2000 81,000.00 16,200.00
2 Tukang kayu Oh 0.4000 108,000.00 43,200.00
3 Kepala tukang Oh 0.0250 117,000.00 2,925.00
4 Mandor Oh 0.0100 90,000.00 900.00
JUMLAH UPAH Rp 63,225.00
c. JUMLAH UPAH + BAHAN Rp 115,679.81
d. DIBULATKAN Rp 115,680.00

Halaman 35 Dari 135 Lembar


DUTAINTERIORMEDAN/AHSP/PENUTUPATAP/HOSTEL/JALAN PEMBANGUNAN/2019

G. ANALISA HARGA SATUAN PEKERJAAN PENUTUP ATAP P.P.A.


HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)

Halaman 36 Dari 135 Lembar


H. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANGIT-LANGIT & PA P.P.LL.
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1 1 M² Pekerjaan Rangka Gypsum Board
a. BAHAN
- Furing Btg 0.4150 29,995.00 12,447.93
- Furing Btg 0.1500 22,282.00 3,342.30
- Paku gypsum kg 0.0550 72,845.00 4,006.48
- Dina bolt Bh 2.0000 2,571.00 5,142.00
JUMLAH BAHAN Rp 24,938.70
b. UPAH
- Pekerja Oh 0.1400 81,000.00 11,340.00
- Tukang kayu Oh 0.1400 108,000.00 15,120.00
- Kepala tukang Oh 0.0013 117,000.00 146.25
- Mandor Oh 0.0013 90,000.00 112.50
JUMLAH UPAH Rp 26,718.75
c. JUMLAH UPAH + BAHAN Rp 51,657.45
d. DIBULATKAN Rp 51,657.00

2 1 M² Langit-langit Gypsum Board , tebal 9 mm


a. BAHAN
- Gypsum board ( 120 x 240 x 9 ) mm Lbr 1.1000 20,829.86 22,912.85
- Paku gypsum kg 0.0500 72,845.00 3,642.25
JUMLAH BAHAN Rp 26,555.10
b. UPAH
- Pekerja Oh 0.0650 81,000.00 5,265.00
- Tukang kayu Oh 0.0650 108,000.00 7,020.00
- Kepala tukang Oh 0.0350 117,000.00 4,095.00
- Mandor Oh 0.0067 90,000.00 603.00
JUMLAH UPAH Rp 16,983.00
c. JUMLAH UPAH + BAHAN + ALAT BANTU Rp 43,538.10
d. DIBULATKAN Rp 43,538.00

3 1 M¹ List Langit-langit Gypsum 10 cm


a. BAHAN
- List gypsum M¹ 1.0500 9,855.50 10,348.28
- Tepung gypsum Kg 0.1500 3,213.75 482.06
JUMLAH BAHAN Rp 10,830.34
b. UPAH
- Pekerja Oh 0.0500 81,000.00 4,050.00
- Tukang kayu Oh 0.0500 108,000.00 5,400.00
- Kepala tukang Oh 0.0050 117,000.00 585.00
- Mandor Oh 0.0030 90,000.00 270.00
JUMLAH UPAH Rp 10,305.00
d. JUMLAH UPAH + BAHAN Rp 21,135.34
e. DIBULATKAN Rp 21,135.00

4 1 M¹ List Langit-langit Kayu 1/4 cm


a. BAHAN
- List Kayu profil M¹ 1.0500 1,500.00 1,575.00
- Paku Kg 0.0100 20,396.60 203.97
JUMLAH BAHAN Rp 1,778.97
b. UPAH
- Pekerja Oh 0.0434 81,000.00 3,515.40
- Tukang kayu Oh 0.0500 108,000.00 5,400.00
- Kepala tukang Oh 0.0050 117,000.00 585.00
- Mandor Oh 0.0030 90,000.00 270.00
JUMLAH UPAH Rp 9,770.40
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
d. JUMLAH UPAH + BAHAN Rp 11,549.37
e. DIBULATKAN Rp 11,549.00
I. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DIND P.P.L.D
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
A. PEKERJAAN PENUTUP LANTAI
1 1 M² Lantai Keramik Roxy Black 20x20 cm Kw1
a. BAHAN
- Roxy Black 20x20 cm Kw1 M² 1.0500 48,000.00 50,400.00
- Semen portland Kg 9.8000 1,221.23 11,968.01
- Pasir pasang M³ 0.0450 110,000.00 4,950.00
- Semen warna Kg 1.5000 13,454.90 20,182.35
JUMLAH BAHAN Rp 87,500.36
b. UPAH
- Pekerja Oh 0.2400 81,000.00 19,440.00
- Tukang batu Oh 0.1200 108,000.00 12,960.00
- Kepala tukang Oh 0.0120 117,000.00 1,404.00
- Mandor Oh 0.0125 90,000.00 1,125.00
JUMLAH UPAH Rp 34,929.00
c. JUMLAH UPAH + BAHAN Rp 122,429.36
d. DIBULATKAN Rp 122,429.00

2 1 M² Lantai Keramik Galaxy Black 20x20 cm Kw1


a. BAHAN
- Galaxy Black 20x20 cm Kw1 M² 1.0500 54,000.00 56,700.00
- Semen portland Kg 9.8000 1,221.23 11,968.01
- Pasir pasang M³ 0.0450 110,000.00 4,950.00
- Semen warna Kg 1.5000 13,454.90 20,182.35
JUMLAH BAHAN Rp 93,800.36
b. UPAH
- Pekerja Oh 0.2400 81,000.00 19,440.00
- Tukang batu Oh 0.1200 108,000.00 12,960.00
- Kepala tukang Oh 0.0120 117,000.00 1,404.00
- Mandor Oh 0.0125 90,000.00 1,125.00
JUMLAH UPAH Rp 34,929.00
c. JUMLAH UPAH + BAHAN Rp 128,729.36
d. DIBULATKAN Rp 128,729.00

3 1 M² Lantai Granit Ex China; Uk. 60x60 cm


a. BAHAN
- Celonia Grey 20x40 M² 1.0500 78,000.00 81,900.00
- Semen portland Kg 9.8000 1,221.23 11,968.01
- Pasir pasang M³ 0.0450 110,000.00 4,950.00
- Semen warna Kg 1.5000 13,454.90 20,182.35
JUMLAH BAHAN Rp 119,000.36
b. UPAH
- Pekerja Oh 0.2400 81,000.00 19,440.00
- Tukang batu Oh 0.1200 108,000.00 12,960.00
- Kepala tukang Oh 0.0120 117,000.00 1,404.00
- Mandor Oh 0.0125 90,000.00 1,125.00
JUMLAH UPAH Rp 34,929.00
c. JUMLAH UPAH + BAHAN Rp 153,929.36
d. DIBULATKAN Rp 153,929.00

4 1 M² Dinding Keramik; Uk. 20x40


a. BAHAN
- Kobin Papandayan 20x40 M² 1.0500 74,400.00 78,120.00
- Semen portland Kg 9.8000 1,221.23 11,968.01
- Pasir pasang M³ 0.0450 110,000.00 4,950.00
- Semen warna Kg 1.5000 13,454.90 20,182.35
JUMLAH BAHAN Rp 115,220.36
b. UPAH
- Pekerja Oh 0.2400 81,000.00 19,440.00
I. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DIND P.P.L.D
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
- Tukang batu Oh 0.1200 108,000.00 12,960.00
- Kepala tukang Oh 0.0120 117,000.00 1,404.00
- Mandor Oh 0.0125 90,000.00 1,125.00
JUMLAH UPAH Rp 34,929.00
c. JUMLAH UPAH + BAHAN Rp 150,149.36
d. DIBULATKAN Rp 150,149.00

5 1 M² Pekerjaan Lantai Granit Ex. China; Uk. 60x60 cm


a. BAHAN
- Lantai Granit Ex. China; Uk. 60x60 cm M² 1.1000 116,666.67 128,333.33
- Semen portland Kg 9.8000 1,221.23 11,968.01
- Pasir pasang M3 0.0450 110,000.00 4,950.00
- Semen warna Kg 0.6500 13,454.90 8,745.69
JUMLAH BAHAN Rp 153,997.02
b. UPAH
- Pekerja Oh 0.7000 81,000.00 56,700.00
- Tukang batu Oh 0.3500 108,000.00 37,800.00
- Kepala tukang Oh 0.0350 117,000.00 4,095.00
- Mandor Oh 0.0350 90,000.00 3,150.00
JUMLAH UPAH Rp 101,745.00
c. JUMLAH UPAH + BAHAN Rp 255,742.02
d. DIBULATKAN Rp 255,742.00

6 1 M² Paving block natural 8 cm


a. BAHAN
- Paving block natural M² 1.050 76,452.97 80,275.62
- Pasir pasang Kg 0.100 110,000.00 11,000.00
JUMLAH BAHAN Rp 91,275.62
b. UPAH
- Pekerja Oh 0.2500 81,000.00 20,250.00
- Tukang batu Oh 0.5000 108,000.00 54,000.00
- Kepala tukang Oh 0.0250 117,000.00 2,925.00
- Mandor Oh 0.00250 90,000.00 225.00
JUMLAH UPAH Rp 77,400.00
c. JUMLAH UPAH + BAHAN Rp 168,675.62
d. DIBULATKAN Rp 168,676.00

7 1 M² Paving block natural 6 cm


a. BAHAN
- Paving block natural M² 1.100 71,645.20 78,809.72
- Pasir pasang Kg 0.100 110,000.00 11,000.00
JUMLAH BAHAN Rp 89,809.72
b. UPAH
- Pekerja Oh 0.2500 81,000.00 20,250.00
- Tukang batu Oh 0.5000 108,000.00 54,000.00
- Kepala tukang Oh 0.0250 117,000.00 2,925.00
- Mandor Oh 0.00250 90,000.00 225.00
JUMLAH UPAH Rp 77,400.00
c. JUMLAH UPAH + BAHAN Rp 167,209.72
d. DIBULATKAN Rp 167,210.00

8 1 M² Grass Block Lubang 5, Tebal 8 cm


a. BAHAN
- Grass block Bh 7.150 14,140.50 101,104.58
- Pasir pasang Kg 0.100 110,000.00 11,000.00
JUMLAH BAHAN Rp 112,104.58
b. UPAH
- Pekerja Oh 0.1500 81,000.00 12,150.00
I. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DIND P.P.L.D
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
- Tukang batu Oh 0.3000 108,000.00 32,400.00
- Kepala tukang Oh 0.0150 117,000.00 1,755.00
- Mandor Oh 0.00150 90,000.00 135.00
JUMLAH UPAH Rp 46,440.00
c. JUMLAH UPAH + BAHAN Rp 158,544.58
d. DIBULATKAN Rp 158,545.00

9 1 M² Grass Block Lubang 8, Tebal 6 cm


a. BAHAN
- Grass block Bh 8.250 23,567.50 194,431.88
- Pasir pasang Kg 0.100 14,140.50 1,414.05
JUMLAH BAHAN Rp 195,845.93
b. UPAH
- Pekerja Oh 0.1500 81,000.00 12,150.00
- Tukang batu Oh 0.3000 108,000.00 32,400.00
- Kepala tukang Oh 0.0150 117,000.00 1,755.00
- Mandor Oh 0.00150 90,000.00 135.00
JUMLAH UPAH Rp 46,440.00
c. JUMLAH UPAH + BAHAN Rp 242,285.93
d. DIBULATKAN Rp 242,286.00

10 1 M² Grass Block Lubang 8, Tebal 8 cm


a. BAHAN
- Grass block Bh 8.250 32,994.50 272,204.63
- Pasir pasang Kg 0.100 110,000.00 11,000.00
JUMLAH BAHAN Rp 283,204.63
b. UPAH
- Pekerja Oh 0.1500 81,000.00 12,150.00
- Tukang batu Oh 0.3000 108,000.00 32,400.00
- Kepala tukang Oh 0.0150 117,000.00 1,755.00
- Mandor Oh 0.00150 90,000.00 135.00
JUMLAH UPAH Rp 46,440.00
c. JUMLAH UPAH + BAHAN Rp 329,644.63
d. DIBULATKAN Rp 329,645.00

11 1 M² Dinding Batu Alam Palimanan Rata Alam


a. BAHAN
- Batu Alam Palimanan M² 1.0500 174,000.00 182,700.00
- Semen portland Kg 12.2500 1,221.23 14,960.01
- Pasir pasang M³ 0.0563 110,000.00 6,187.50
JUMLAH BAHAN Rp 203,847.51
b. UPAH
- Pekerja Oh 0.4800 81,000.00 38,880.00
- Tukang batu Oh 0.2400 108,000.00 25,920.00
- Kepala tukang Oh 0.0240 117,000.00 2,808.00
- Mandor Oh 0.0250 90,000.00 2,250.00
JUMLAH UPAH Rp 69,858.00
c. JUMLAH UPAH + BAHAN Rp 273,705.51
d. DIBULATKAN Rp 273,706.00
I. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DIND P.P.L.D
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
J. ANALISA HARGA SATUAN PEKERJAAN KAYU P.K.
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1 1 M3 Kusen Pintu & jendela kayu Kamper Samarinda
a. BAHAN
- Kayu Balok Kamper Samarinda m3 1.2000 7,399,080.90 8,878,897.08
JUMLAH BAHAN Rp 8,878,897.08
b. UPAH
- Pekerja Oh 4.0000 81,000.00 324,000.00
- Tukang Kayu Oh 12.0000 108,000.00 1,296,000.00
- Kepala Tukang Oh 1.5000 117,000.00 175,500.00
- Mandor Oh 0.3000 90,000.00 27,000.00
JUMLAH UPAH Rp 1,822,500.00
c. JUMLAH UPAH + BAHAN Rp 10,701,397.08
d. DIBULATKAN Rp 10,701,397.00

2 1 M3 Kusen Pintu & jendela kayu Kamper Medan/Kruing


a. BAHAN
- Kayu Balok Kamper Medan M3 1.2000 4,878,558.20 5,854,269.84
JUMLAH BAHAN Rp 5,854,269.84
b. UPAH
- Pekerja Oh 4.0000 81,000.00 324,000.00
- Tukang Kayu Oh 12.0000 108,000.00 1,296,000.00
- Kepala Tukang Oh 1.5000 117,000.00 175,500.00
- Mandor Oh 0.3000 90,000.00 27,000.00
JUMLAH UPAH Rp 1,822,500.00
c. JUMLAH UPAH + BAHAN Rp 7,676,769.84
d. DIBULATKAN Rp 7,676,770.00

3 1 M3 Kusen Pintu & jendela kayu Borneo Super


a. BAHAN
- Kayu Borneo Balok Super M3 1.2000 4,524,960.00 5,429,952.00
JUMLAH BAHAN Rp 5,429,952.00
b. UPAH
- Pekerja Oh 6.0000 81,000.00 486,000.00
- Tukang Kayu Oh 18.0000 108,000.00 1,944,000.00
- Kepala Tukang Oh 1.5000 117,000.00 175,500.00
- Mandor Oh 0.3000 90,000.00 27,000.00
JUMLAH UPAH Rp 2,632,500.00
c. JUMLAH UPAH + BAHAN Rp 8,062,452.00
d. DIBULATKAN Rp 8,062,452.00

4 1 M2 Pintu Panel Kayu Kamper Samarinda


a. BAHAN
- Kayu Papan Kamper Samarinda M3 0.0400 7,399,080.90 295,963.24
- Paku Biasa 2" - 5" Kg 0.0500 20,053.80 1,002.69
JUMLAH BAHAN Rp 296,965.93
b. UPAH
- Pekerja Oh 1.0000 81,000.00 81,000.00
- Tukang Kayu Oh 2.5000 108,000.00 270,000.00
- Kepala Tukang Oh 0.2500 117,000.00 29,250.00
- Mandor Oh 0.0500 90,000.00 4,500.00
JUMLAH UPAH Rp 384,750.00
c. JUMLAH UPAH + BAHAN Rp 681,715.93
d. DIBULATKAN Rp 681,716.00

5 1 M2 Pintu Panel Kayu Kamper Medan/Kruing


a. BAHAN
- Kayu Papan Kamper Medan M3 0.0400 4,878,558.20 195,142.33
- Paku Biasa 2" - 5" Kg 0.0500 20,053.80 1,002.69
JUMLAH BAHAN Rp 196,145.02
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
b. UPAH
- Pekerja Oh 1.0000 81,000.00 81,000.00
- Tukang Kayu Oh 2.5000 108,000.00 270,000.00
- Kepala Tukang Oh 0.2500 117,000.00 29,250.00
- Mandor Oh 0.0500 90,000.00 4,500.00
JUMLAH UPAH Rp 384,750.00
c. JUMLAH UPAH + BAHAN Rp 385,752.69
d. DIBULATKAN Rp 385,753.00

6 1 M2 Pintu & Jendela Kaca Kayu Kamper Medan


a. BAHAN
- Kayu Papan Kamper Medan M3 0.0350 4,878,558.20 170,749.54
JUMLAH BAHAN Rp 170,749.54
b. UPAH
- Pekerja Oh 0.8000 81,000.00 64,800.00
- Tukang Kayu Oh 2.0000 108,000.00 216,000.00
- Kepala Tukang Oh 0.2000 117,000.00 23,400.00
- Mandor Oh 0.0400 90,000.00 3,600.00
JUMLAH UPAH Rp 307,800.00
c. JUMLAH UPAH + BAHAN Rp 478,549.54
d. DIBULATKAN Rp 478,550.00

7 1 M2 Pintu & Jendela Jalusi Kayu Kamper Medan


a. BAHAN
- Kayu Papan Kamper Medan M3 0.0640 4,878,558.20 312,227.72
JUMLAH BAHAN Rp 312,227.72
b. UPAH
- Pekerja Oh 1.0000 81,000.00 81,000.00
- Tukang Kayu Oh 3.0000 108,000.00 324,000.00
- Kepala Tukang Oh 0.3000 117,000.00 35,100.00
- Mandor Oh 0.5000 90,000.00 45,000.00
JUMLAH UPAH Rp 485,100.00
c. JUMLAH UPAH + BAHAN Rp 797,327.72
d. DIBULATKAN Rp 797,328.00

8 1 M' Lisplang uk (3x20)cm, Kayu Kamper Medan


a. BAHAN
- Kayu Papan Kamper Medan M3 0.0072 4,990,653.80 35,932.71
- Paku Biasa 2" - 5" Kg 0.0500 20,053.80 1,002.69
JUMLAH BAHAN Rp 36,935.40
b. UPAH
- Pekerja Oh 0.1000 81,000.00 8,100.00
- Tukang Kayu Oh 0.2000 108,000.00 21,600.00
- Kepala Tukang Oh 0.0200 117,000.00 2,340.00
- Mandor Oh 0.0050 90,000.00 450.00
JUMLAH UPAH Rp 32,490.00
c. JUMLAH UPAH + BAHAN Rp 33,492.69
d. DIBULATKAN Rp 33,493.00

9 1 M¹ List Kayu Profil 5 cm


a. BAHAN
- Kayu Profil 10 cm M' 1.0500 7,370.20 7,738.71
JUMLAH BAHAN Rp 7,738.71
b. UPAH
- Pekerja Oh 0.0210 81,000.00 1,701.00
- Tukang Kayu Oh 0.0210 108,000.00 2,268.00
- Kepala Tukang Oh 0.0020 117,000.00 234.00
- Mandor Oh 0.0010 90,000.00 90.00
JUMLAH UPAH Rp 4,293.00
c. JUMLAH UPAH + BAHAN Rp 12,031.71
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
d. DIBULATKAN Rp 12,032.00
K. ANALISA HARGA SATUAN PEKERJAAN KUNCI & KACA P.K.K.
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
1. 1 Bh Pasang Kunci Tanam Classic Klas 1
a. BAHAN
- Dekkson LHR 8536 CF (Full Set) Bh 1.0000 787,154.50 787,154.50
JUMLAH BAHAN Rp 787,154.50
b. UPAH
- Tukang kayu Oh 0.5000 108,000.00 54,000.00
- Kepala tukang Oh 0.0500 117,000.00 5,850.00
JUMLAH UPAH Rp 59,850.00
JUMLAH BAHAN + UPAH Rp 847,004.50
DIBULATKAN Rp 847,005.00

2. 1 Bh Pasang Kunci Tanam Classic Klas 2


a. BAHAN
- Dekkson LS T6300 ET SSS (Full Set) Bh 1.0000 193,253.50 193,253.50
JUMLAH BAHAN Rp 193,253.50
b. UPAH
- Tukang kayu Oh 0.5000 108,000.00 54,000.00
- Kepala tukang Oh 0.0500 117,000.00 5,850.00
JUMLAH UPAH Rp 59,850.00
JUMLAH BAHAN + UPAH Rp 253,103.50
DIBULATKAN Rp 253,104.00

3. 1 Bh Lever Handle Dekkson L.H.R 10693 CF


a. BAHAN
- Dekkson L.H.R 10693 CF Bh 1.0000 282,810.00 282,810.00
JUMLAH BAHAN Rp 282,810.00
b. UPAH
- Tukang kayu Oh 0.3000 108,000.00 32,400.00
- Kepala tukang Oh 0.0100 117,000.00 1,170.00
JUMLAH UPAH Rp 33,570.00
JUMLAH BAHAN + UPAH Rp 316,380.00
DIBULATKAN Rp 316,380.00

4. 1 Bh Lever Handle Dekkson LHTR 0017


a. BAHAN
- Dekkson LHTR 0017 Bh 1.0000 155,545.50 155,545.50
JUMLAH BAHAN Rp 155,545.50
b. UPAH
- Tukang kayu Oh 0.3000 108,000.00 32,400.00
- Kepala tukang Oh 0.0100 117,000.00 1,170.00
JUMLAH UPAH Rp 33,570.00
JUMLAH BAHAN + UPAH Rp 189,115.50
DIBULATKAN Rp 189,116.00

5. 1 Buah Pasang Kunci Tanam Kamar Mandi


a. BAHAN
- Dekkson KCBL 8587 ET SSS Kunci Pintu Bh 1.0000 107,467.80 107,467.80
JUMLAH BAHAN Rp 107,467.80
b. UPAH
- Tukang kayu Oh 0.5000 108,000.00 54,000.00
- Kepala tukang Oh 0.0500 117,000.00 5,850.00
JUMLAH UPAH Rp 59,850.00
JUMLAH BAHAN + UPAH Rp 167,317.80
DIBULATKAN Rp 167,318.00

6. 1 Buah Pasang Engsel 5"


a. BAHAN
- Engsel pintu Bh 1.0000 43,364.20 43,364.20
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
JUMLAH BAHAN Rp 43,364.20
b. UPAH
- Tukang kayu Oh 0.1250 108,000.00 13,500.00
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
- Kepala tukang Oh 0.0125 117,000.00 1,462.50
JUMLAH UPAH Rp 14,962.50
JUMLAH BAHAN + UPAH Rp 58,326.70
DIBULATKAN Rp 58,327.00

7. 1 Buah Pasang Engsel 4"


a. BAHAN
- Engsel pintu Bh 1.0000 25,924.25 25,924.25
JUMLAH BAHAN Rp 25,924.25
b. UPAH
- Tukang kayu Oh 0.1250 108,000.00 13,500.00
- Kepala tukang Oh 0.0125 117,000.00 1,462.50
JUMLAH UPAH Rp 14,962.50
JUMLAH BAHAN + UPAH Rp 40,886.75
DIBULATKAN Rp 40,887.00

8. 1 Buah Pasang Engsel 3"


a. BAHAN
- Engsel jendela Bh 1.0000 25,924.25 25,924.25
JUMLAH BAHAN Rp 25,924.25
b. UPAH
- Tukang kayu Oh 0.1250 108,000.00 13,500.00
- Kepala tukang Oh 0.0125 117,000.00 1,462.50
JUMLAH UPAH Rp 14,962.50
JUMLAH BAHAN + UPAH Rp 40,886.75
DIBULATKAN Rp 40,887.00

9. 1 Buah Pasang Engsel Tanam 8"


a. BAHAN
- Engsel jendela Bh 1.0000 244,245.00 244,245.00
JUMLAH BAHAN Rp 244,245.00
b. UPAH
- Tukang kayu Oh 0.2000 108,000.00 21,600.00
- Kepala tukang Oh 0.0200 117,000.00 2,340.00
JUMLAH UPAH Rp 23,940.00
JUMLAH BAHAN + UPAH Rp 268,185.00
DIBULATKAN Rp 268,185.00

10. 1 Buah Pasang Engsel Tanam 12"


a. BAHAN
- Engsel jendela Bh 1.0000 320,518.00 320,518.00
JUMLAH BAHAN Rp 320,518.00
b. UPAH
- Tukang kayu Oh 0.2000 108,000.00 21,600.00
- Kepala tukang Oh 0.0200 117,000.00 2,340.00
JUMLAH UPAH Rp 23,940.00
JUMLAH BAHAN + UPAH Rp 344,458.00
DIBULATKAN Rp 344,458.00

11. 1 Buah Pasang Kait Angin 8"


a. BAHAN
- WS 001 8" SSS Bh 1.0000 53,733.90 53,733.90
JUMLAH BAHAN Rp 53,733.90
b. UPAH
- Tukang kayu Oh 0.1500 108,000.00 16,200.00
- Kepala tukang Oh 0.0150 117,000.00 1,755.00
JUMLAH UPAH Rp 17,955.00
JUMLAH BAHAN + UPAH Rp 71,688.90
DIBULATKAN Rp 71,689.00
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
12. 1 Buah Pasang Kait Angin 10"
a. BAHAN
- WS 001 8" SSS Bh 1.0000 58,447.40 58,447.40
JUMLAH BAHAN Rp 58,447.40
b. UPAH
- Tukang kayu Oh 0.1500 108,000.00 16,200.00
- Kepala tukang Oh 0.0150 117,000.00 1,755.00
JUMLAH UPAH Rp 17,955.00
JUMLAH BAHAN + UPAH Rp 76,402.40
DIBULATKAN Rp 76,402.00

13. 1 Buah Pasang Engsel Saloon 9"


a. BAHAN
- Salon ES SL 9" CP Bh 1.0000 21,210.75 21,210.75
JUMLAH BAHAN Rp 21,210.75
b. UPAH
- Tukang kayu Oh 0.1500 108,000.00 16,200.00
- Kepala tukang Oh 0.0150 117,000.00 1,755.00
JUMLAH UPAH Rp 17,955.00
JUMLAH BAHAN + UPAH Rp 39,165.75
DIBULATKAN Rp 39,166.00

14. 1 Buah Pasang Engsel Saloon 5"


a. BAHAN
- Salon ES SL 5" CP Bh 1.0000 16,497.25 16,497.25
JUMLAH BAHAN Rp 16,497.25
b. UPAH
- Tukang kayu Oh 0.1500 108,000.00 16,200.00
- Kepala tukang Oh 0.0150 117,000.00 1,755.00
JUMLAH UPAH Rp 17,955.00
JUMLAH BAHAN + UPAH Rp 34,452.25
DIBULATKAN Rp 34,452.00

15. 1 Buah Pasang Door Closer (Hold Open)


a. BAHAN
- DekssonType DCL 105 DCL Bh 1.0000 617,468.50 617,468.50
JUMLAH BAHAN Rp 617,468.50
b. UPAH
- Tukang kayu Oh 0.6000 108,000.00 64,800.00
- Kepala tukang Oh 0.0600 117,000.00 7,020.00
- Mandor Oh 0.0030 90,000.00 270.00
JUMLAH UPAH Rp 71,820.00
JUMLAH BAHAN + UPAH Rp 689,423.50
DIBULATKAN Rp 689,424.00

16. 1 Buah Pasang Door Closer (Non Hold Open)


a. BAHAN
- Dekkson DCL 300 NHO Non Hold Open Bh 1.0000 226,248.00 226,248.00
JUMLAH BAHAN Rp 226,248.00
b. UPAH
- Tukang kayu Oh 0.5000 108,000.00 54,000.00
- Kepala tukang Oh 0.0500 117,000.00 5,850.00
- Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 60,075.00
JUMLAH BAHAN + UPAH Rp 286,323.00
DIBULATKAN Rp 286,323.00

17. 1 Buah Pasang Pegangan Pintu / Door Stopper


a. BAHAN
- Dekson DS 009 SS Bh 1.0000 56,562.00 56,562.00
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
JUMLAH BAHAN Rp 56,562.00
b. UPAH
- Tukang kayu Oh 0.6000 108,000.00 64,800.00
- Kepala tukang Oh 0.0600 117,000.00 7,020.00
JUMLAH UPAH Rp 71,820.00
JUMLAH BAHAN + UPAH Rp 128,382.00
DIBULATKAN Rp 128,382.00

18. 1 Bh Pasang Engsel Tanam (8" + 12" & SUS 304)


a. BAHAN
- Dekkson FB 040 SSS (8" + 12" & SUS 304) Bh 1.0000 244,245.00 244,245.00
JUMLAH BAHAN Rp 244,245.00
b. UPAH
- Tukang kayu Oh 0.5000 108,000.00 54,000.00
- Kepala tukang Oh 0.0500 117,000.00 5,850.00
JUMLAH UPAH Rp 59,850.00
JUMLAH BAHAN + UPAH Rp 304,095.00
DIBULATKAN Rp 304,095.00

19. 1 Bh Pasang Engsel Tanam (12" + 24" & SUS 304)


a. BAHAN
- Dekkson FB 050 SSS (12" + 4" & SUS 304) Bh 1.0000 320,518.00 320,518.00
JUMLAH BAHAN Rp 320,518.00
b. UPAH
- Tukang kayu Oh 0.5250 108,000.00 56,700.00
- Kepala tukang Oh 0.0525 117,000.00 6,142.50
JUMLAH UPAH Rp 62,842.50
JUMLAH BAHAN + UPAH Rp 383,360.50
DIBULATKAN Rp 383,361.00

20. 1 Bh Pasang Rambuncis


a. BAHAN
- Dekkson CWH 103 Z SN Bh 1.0000 44,306.90 44,306.90
JUMLAH BAHAN Rp 44,306.90
b. UPAH
- Tukang kayu Oh 0.1000 108,000.00 10,800.00
- Kepala tukang Oh 0.0100 117,000.00 1,170.00
JUMLAH UPAH Rp 11,970.00
JUMLAH BAHAN + UPAH Rp 56,276.90
DIBULATKAN Rp 56,277.00

21. 1 Bh Pasang Engsel Saloon/Jungkit 5"


a. BAHAN
- Dekkson Salon ES SL 5" CP Bh 1.0000 16,497.25 16,497.25
JUMLAH BAHAN Rp 16,497.25
b. UPAH
- Tukang kayu Oh 0.1000 108,000.00 10,800.00
- Kepala tukang Oh 0.0100 117,000.00 1,170.00
JUMLAH UPAH Rp 11,970.00
JUMLAH BAHAN + UPAH Rp 28,467.25
DIBULATKAN Rp 28,467.00

22. 1 Bh Pasang Engsel Saloon/Jungkit 9"


a. BAHAN
- Dekkson Salon ES SL 9" CP Bh 1.0000 21,210.75 21,210.75
JUMLAH BAHAN Rp 21,210.75
b. UPAH
- Tukang kayu Oh 0.1000 108,000.00 10,800.00
- Kepala tukang Oh 0.0100 117,000.00 1,170.00
JUMLAH UPAH Rp 11,970.00
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
JUMLAH BAHAN + UPAH Rp 33,180.75
DIBULATKAN Rp 33,181.00

24. 1 M² Pasang Kaca , tebal 3 mm


a. BAHAN
- Kaca M2 1.1000 74,901.80 82,391.98
JUMLAH BAHAN Rp 82,391.98
b. UPAH
- Pekerja Oh 0.0150 81,000.00 1,215.00
- Tukang kayu Oh 0.1500 108,000.00 16,200.00
- Kepala tukang Oh 0.0150 117,000.00 1,755.00
- Mandor Oh 0.0008 90,000.00 67.50
JUMLAH UPAH Rp 19,237.50
JUMLAH BAHAN + UPAH Rp 101,629.48
DIBULATKAN Rp 101,629.00

25. 1 M² Pasang Kaca , tebal 5 mm


a. BAHAN
- Kaca M2 1.1000 95,127.00 104,639.70
JUMLAH BAHAN Rp 104,639.70
b. UPAH
- Pekerja Oh 0.0150 81,000.00 1,215.00
- Tukang kayu Oh 0.1500 108,000.00 16,200.00
- Kepala tukang Oh 0.0150 117,000.00 1,755.00
- Mandor Oh 0.0008 90,000.00 72.00
JUMLAH UPAH Rp 19,242.00
JUMLAH Rp 123,881.70
DIBULATKAN Rp 123,882.00

27 1 Bh Pasang Pull Handle


a. BAHAN
- Pull Handle M2 1.1000 227,190.70 249,909.77
JUMLAH BAHAN Rp 249,909.77
b. UPAH
- Pekerja Oh 0.1500 81,000.00 12,150.00
- Tukang kayu Oh 0.4500 108,000.00 48,600.00
- Kepala tukang Oh 0.0150 117,000.00 1,755.00
- Mandor Oh 0.0008 90,000.00 72.00
JUMLAH UPAH Rp 62,577.00
JUMLAH Rp 312,486.77
DIBULATKAN Rp 312,487.00
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
L. ANALISA HARGA SATUAN PEKERJAAN PEKERJAAN SANITASI P.S.
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
1 1 Buah Closet jongkok Toto
a. BAHAN
- Toto CE-7 bh 1.0000 329,088.00 329,088.00
- P.C (50 gk) Kg 6.0000 1,221.23 7,327.35
- Pasir pasang m3 0.0100 110,000.00 1,100.00
JUMLAH BAHAN Rp 337,515.35
b. UPAH
- Pekerja org 0.5000 81,000.00 40,500.00
- Tukang batu org 0.7500 108,000.00 81,000.00
- Kepala Tukang org 0.7500 117,000.00 87,750.00
- Mandor org 0.0800 90,000.00 7,200.00
JUMLAH UPAH Rp 216,450.00
c. JUMLAH UPAH + BAHAN Rp 553,965.35
d. DIBULATKAN Rp 553,965.00

2 1 Buah Closet jongkok Toto Flush


a. BAHAN
- CE9/TV150NWV12J bh 1.0000 3,359,440.00 3,359,440.00
- P.C (50 gk) Kg 6.0000 1,221.23 7,327.35
- Pasir pasang m3 0.0100 110,000.00 1,100.00
JUMLAH BAHAN Rp 3,367,867.35
b. UPAH
- Pekerja org 1.0000 81,000.00 81,000.00
- Tukang batu org 1.5000 108,000.00 162,000.00
- Kepala Tukang org 1.5000 117,000.00 175,500.00
- Mandor org 0.1600 90,000.00 14,400.00
JUMLAH UPAH Rp 432,900.00
c. JUMLAH UPAH + BAHAN Rp 3,800,767.35
d. DIBULATKAN Rp 3,800,767.00

3 1 Buah Closet Duduk Toto


a. BAHAN
- Toto CW421J/SW420JP bh 1.0000 1,345,490.00 1,345,490.00
- P.C (50 gk) Kg 6.0000 1,221.23 7,327.35
- Pasir pasang m3 0.0100 110,000.00 1,100.00
JUMLAH BAHAN Rp 1,353,917.35
b. UPAH
- Pekerja org 1.0000 81,000.00 81,000.00
- Tukang batu org 1.5000 108,000.00 162,000.00
- Kepala Tukang org 1.5000 117,000.00 175,500.00
- Mandor org 0.1600 90,000.00 14,400.00
JUMLAH UPAH Rp 432,900.00
c. JUMLAH UPAH + BAHAN Rp 1,786,817.35
d. DIBULATKAN Rp 1,786,817.00

4 1 Buah Urinoir
a. BAHAN
- Toto U57 bh 1.0000 2,511,010.00 2,511,010.00
- P.C (50 gk) Kg 6.0000 1,221.23 7,327.35
- Pasir pasang m3 0.0100 110,000.00 1,100.00
JUMLAH BAHAN Rp 2,519,437.35
b. UPAH
- Pekerja org 1.0000 81,000.00 81,000.00
- Tukang batu org 1.0000 108,000.00 108,000.00
- Kepala Tukang org 0.1000 117,000.00 11,700.00
- Mandor org 0.0010 90,000.00 90.00
JUMLAH UPAH Rp 200,790.00
c. PERLENGKAPAN
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
Perlengkapan 10 % harga urinoir lot 0.1000 2,511,010.00 251,101.00
JUMLAH PERLENGKAPAN Rp 251,101.00
d. JUMLAH UPAH + BAHAN+ PERLENGKAPAN Rp 2,971,328.35
e. DIBULATKAN Rp 2,971,328.00

5 1 Buah Wastafel
a. BAHAN
Toto LW811CJ unit 1.0000 1,414,050.00 1,414,050.00
P.C (50 gk) Kg 6.0000 1,221.23 7,327.35
Pasir pasang m3 0.0100 110,000.00 1,100.00
JUMLAH BAHAN Rp 1,422,477.35
b. UPAH
Pekerja org 1.2000 81,000.00 97,200.00
Tukang batu org 1.4500 108,000.00 156,600.00
Kepala Tukang org 0.1500 117,000.00 17,550.00
Mandor org 0.1000 90,000.00 9,000.00
JUMLAH UPAH Rp 280,350.00
c. PERLENGKAPAN
Perlengkapan 12 % harga wastafel lot 0.1200 1,422,477.35 170,697.28
JUMLAH PERLENGKAPAN Rp 170,697.28
d. JUMLAH UPAH + BAHAN+ PERLENGKAPAN Rp 1,873,524.63
e. DIBULATKAN Rp 1,873,525.00

6 1 Buah bak Mandi Fibreglass Volume 0,30 m3


a. BAHAN
Bak fibreglass 0.60m x 0.60m bh 1.0000 557,050.00 557,050.00
JUMLAH BAHAN Rp 557,050.00
b. UPAH
Pekerja org 1.8000 81,000.00 145,800.00
Tukang batu org 2.7000 108,000.00 291,600.00
Kepala Tukang org 0.5400 117,000.00 63,180.00
Mandor org 0.1100 90,000.00 9,900.00
JUMLAH UPAH Rp 510,480.00
c. PERLENGKAPAN
Perlengkapan 18 % harga bak lot 0.1800 557,050.00 100,269.00
JUMLAH PERLENGKAPAN Rp 100,269.00
d. JUMLAH UPAH + BAHAN+ PERLENGKAPAN Rp 1,167,799.00
e. DIBULATKAN Rp 1,167,799.00

7 1 M' Saluran Air Limbah Buis beton d = 30 cm - 60 cm


a. BAHAN
Buis beton Ø 30 cm bh 1.1000 52,876.90 58,164.59
Bata merah bh 25.0000 599.90 14,997.50
P.C (50 gk) Kg 10.3000 1,221.23 12,578.62
Pasir pasang m3 0.0610 110,000.00 6,710.00
Pasir urug m3 0.0690 60,332.80 4,162.96
JUMLAH BAHAN Rp 96,613.67
b. UPAH
Pekerja org 0.3800 81,000.00 30,780.00
Tukang batu org 0.1900 108,000.00 20,520.00
Kepala Tukang org 0.0190 117,000.00 2,223.00
Mandor org 0.0190 90,000.00 1,710.00
JUMLAH PERLENGKAPAN Rp 55,233.00
c. JUMLAH UPAH + BAHAN+ PERLENGKAPAN Rp 151,846.67
d. DIBULATKAN Rp 151,847.00

8 1 M' Saluran Air Limbah Gravelbeton d = 20 cm - 40 cm


a. BAHAN
Gravel beton Ø 30 cm bh 1.1000 32,566.00 35,822.60
Bata merah bh 25.0000 599.90 14,997.50
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
P.C (50 gk) Kg 10.3000 1,221.23 12,578.62
Pasir pasang m3 0.0610 110,000.00 6,710.00
Pasir urug m3 0.0690 60,332.80 4,162.96
JUMLAH BAHAN Rp 74,271.68
b. UPAH
Pekerja org 0.3800 81,000.00 30,780.00
Tukang batu org 0.1900 108,000.00 20,520.00
Kepala Tukang org 0.0190 117,000.00 2,223.00
Mandor org 0.0190 90,000.00 1,710.00
JUMLAH PERLENGKAPAN Rp 55,233.00
c. JUMLAH UPAH + BAHAN+ PERLENGKAPAN Rp 129,504.68
d. DIBULATKAN Rp 129,505.00

9 1 Buah Bak Kontrol Pas Bata Merah Uk (60 x 60) cm


a. BAHAN
Bata merah bh 186.0000 599.90 111,581.40
P.C (50 gk) Kg 114.0000 1,221.23 139,219.65
Pasir pasang m3 0.1840 110,000.00 20,240.00
Batu pecah 2/3 m3 0.0330 242,959.50 8,017.66
Besi beton m3 4.8500 8,548.58 41,460.59
Pasir beton m3 0.1200 130,000.00 15,600.00
JUMLAH BAHAN Rp 336,119.30
b. UPAH
Pekerja org 2.1600 81,000.00 174,960.00
Tukang batu org 0.7200 108,000.00 77,760.00
Kepala Tukang org 0.0720 117,000.00 8,424.00
Mandor org 0.1080 90,000.00 9,720.00
Tukang gali org 0.1000 81,000.00 8,100.00
JUMLAH UPAH Rp 278,964.00
c. JUMLAH UPAH + BAHAN Rp 615,083.30
d. DIBULATKAN Rp 615,083.00

10 1 Buah Bak Kontrol Pas Bata Merah Uk (30 x 30) cm


a. BAHAN
Bata merah bh 53.0000 599.90 31,794.70
P.C (50 gk) Kg 44.0000 1,221.23 53,733.90
Pasir pasang m3 0.0700 110,000.00 7,700.00
Batu pecah 2/3 m3 0.0700 242,959.50 17,007.17
Besi beton m3 1.6000 8,548.58 13,677.72
Pasir beton m3 0.0600 130,000.00 7,800.00
JUMLAH BAHAN Rp 131,713.49
b. UPAH
Pekerja org 3.2000 81,000.00 259,200.00
Tukang batu org 1.0150 108,000.00 109,620.00
Kepala Tukang org 0.0015 117,000.00 175.50
Mandor org 0.0160 90,000.00 1,440.00
JUMLAH UPAH Rp 370,435.50
c. JUMLAH UPAH + BAHAN Rp 502,148.99
d. DIBULATKAN Rp 502,149.00

11 1 M' Pipa PVC Ø 1/2" (AW)


a. BAHAN
Pipa pvc Ø 1/2" m' 1.1000 8,591.00 9,450.10
JUMLAH BAHAN Rp 9,450.10
b. UPAH
Pekerja org 0.0250 81,000.00 2,025.00
Tukang batu org 0.0500 108,000.00 5,400.00
Kepala Tukang org 0.0050 117,000.00 585.00
Mandor org 0.0015 90,000.00 135.00
JUMLAH UPAH Rp 8,145.00
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
c. PERLENGKAPAN
Perlengkapan 35 % harga pipa lot 0.2500 9,450.10 2,362.53
JUMLAH PERLENGKAPAN Rp 2,362.53
d. JUMLAH UPAH + BAHAN + BAHAN Rp 19,957.63
e. DIBULATKAN Rp 19,958.00

12 1 M' Pipa PVC Ø 1" (AW)


a. BAHAN
Pipa pvc Ø 1" m' 1.1000 13,541.00 14,895.10
Pekerja org 0.0360 81,000.00 2,916.00
JUMLAH BAHAN Rp 17,811.10
b. UPAH
Tukang batu org 0.0600 108,000.00 6,480.00
Kepala Tukang org 0.0060 117,000.00 702.00
Mandor org 0.0018 90,000.00 162.00
JUMLAH UPAH Rp 7,344.00
c. PERLENGKAPAN
Perlengkapan 35 % harga pipa lot 0.2500 14,895.10 3,723.78
JUMLAH PERLENGKAPAN Rp 3,723.78
d. JUMLAH UPAH + BAHAN + BAHAN Rp 28,878.88
e. DIBULATKAN Rp 28,879.00

13 1 M' Pipa PVC Ø 11/2" (AW)


a. BAHAN
Pipa pvc Ø 11/2" m' 1.1000 22,689.00 24,957.90
JUMLAH BAHAN Rp 24,957.90
b. UPAH
Pekerja org 0.0360 81,000.00 2,916.00
Tukang batu org 0.0600 108,000.00 6,480.00
Kepala Tukang org 0.0060 117,000.00 702.00
Mandor org 0.0018 90,000.00 162.00
JUMLAH UPAH Rp 10,260.00
c. PERLENGKAPAN
Perlengkapan 35 % harga pipa lot 0.2500 24,957.90 6,239.48
JUMLAH PERLENGKAPAN Rp 6,239.48
d. JUMLAH UPAH + BAHAN + PERLENGKAPAN Rp 41,457.38
e. DIBULATKAN Rp 41,457.00

14 1 M' Pipa PVC Ø 2" (AW)


a. BAHAN
Pipa pvc Ø 2" m' 1.1000 23,717.00 26,088.70
JUMLAH BAHAN Rp 26,088.70
b. UPAH
Pekerja org 0.0360 81,000.00 2,916.00
Tukang batu org 0.0600 108,000.00 6,480.00
Kepala Tukang org 0.0060 117,000.00 702.00
Mandor org 0.0018 90,000.00 162.00
JUMLAH UPAH Rp 10,260.00
c. PERLENGKAPAN
Perlengkapan 35 % harga pipa lot 0.2500 24,957.90 6,239.48
JUMLAH PERLENGKAPAN Rp 6,239.48
d. JUMLAH UPAH + BAHAN + PERLENGKAPAN Rp 42,588.18
e. DIBULATKAN Rp 42,588.00

15 1 M' Pipa PVC Ø 3" (AW)


a. BAHAN
Pipa pvc Ø 4" m' 1.1000 43,943.00 48,337.30
JUMLAH BAHAN Rp 48,337.30
b. UPAH
Pekerja org 0.0810 81,000.00 6,561.00
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
Tukang batu org 0.1350 108,000.00 14,580.00
Kepala Tukang org 0.0135 117,000.00 1,579.50
Mandor org 0.0041 90,000.00 369.00
JUMLAH UPAH Rp 23,089.50
c. PERLENGKAPAN
Perlengkapan 35 % harga pipa lot 0.2500 48,337.30 12,084.33
JUMLAH PERLENGKAPAN Rp 12,084.33
d. JUMLAH UPAH + BAHAN + PERLENGKAPAN Rp 83,511.13
e. DIBULATKAN Rp 83,511.00

16 1 M' Pipa PVC Ø 3/4" (AW)


a. BAHAN
- Pipa pvc Ø 3/4" m' 1.1000 11,184.00 12,302.40
JUMLAH BAHAN Rp 12,302.40
b. UPAH
- Pekerja org 0.0810 81,000.00 6,561.00
- Tukang batu org 0.1350 108,000.00 14,580.00
- Kepala Tukang org 0.0135 117,000.00 1,579.50
- Mandor org 0.0041 90,000.00 369.00
JUMLAH UPAH Rp 23,089.50
c. PERLENGKAPAN
- Perlengkapan 35 % harga pipa lot 0.2500 12,302.40 3,075.60
JUMLAH PERLENGKAPAN Rp 3,075.60
d. JUMLAH UPAH + BAHAN + PERLENGKAPAN Rp 38,467.50
e. DIBULATKAN Rp 38,468.00

17 1 Buah Bak Cuci piring Stainless steel


a. BAHAN
- Bak cuci stainless steel + aks. bh 1.0000 167,115.00 167,115.00
JUMLAH BAHAN Rp 167,115.00
b. UPAH
- Pekerja org 0.0300 81,000.00 2,430.00
- Tukang batu org 0.3000 108,000.00 32,400.00
- Kepala Tukang org 0.0300 117,000.00 3,510.00
- Mandor org 0.0015 90,000.00 135.00
JUMLAH UPAH Rp 38,475.00
c. JUMLAH UPAH + BAHAN Rp 205,590.00
d. DIBULATKAN Rp 205,590.00

18 1 Buah Kran Ø 1/2" - 3/4"


a. BAHAN
Kran Onda bh 1.0000 64,917.75 64,917.75
Seal tape bh 0.0250 3,599.40 89.99
JUMLAH BAHAN Rp 65,007.74
b. UPAH
Pekerja org 0.0750 81,000.00 6,075.00
Tukang batu org 0.0750 108,000.00 8,100.00
Kepala Tukang org 0.0075 117,000.00 877.50
Mandor org 0.0050 90,000.00 450.00
JUMLAH UPAH Rp 15,502.50
c. JUMLAH UPAH + BAHAN Rp 80,510.24
d. DIBULATKAN Rp 80,510.00

19 1 Buah Kran Flexibel


a. BAHAN
Kran Flexible bh 1.0000 82,229.15 82,229.15
Seal tape bh 0.0250 3,599.40 89.99
JUMLAH BAHAN Rp 82,319.14
b. UPAH
Pekerja org 0.0750 81,000.00 6,075.00
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
Tukang batu org 0.0750 108,000.00 8,100.00
Kepala Tukang org 0.0075 117,000.00 877.50
Mandor org 0.0050 90,000.00 450.00
JUMLAH UPAH Rp 15,502.50
c. JUMLAH UPAH + BAHAN Rp 97,821.64
d. DIBULATKAN Rp 97,822.00

20 1 Buah Floor Drain


a. BAHAN
- Floor drain bh 1.0000 82,957.60 82,957.60
JUMLAH BAHAN Rp 82,957.60
b. UPAH
- Pekerja org 0.0100 81,000.00 810.00
- Tukang batu org 0.1000 108,000.00 10,800.00
- Kepala Tukang org 0.0100 117,000.00 1,170.00
- Mandor org 0.0050 90,000.00 450.00
JUMLAH UPAH Rp 13,230.00
c. JUMLAH UPAH + BAHAN Rp 96,187.60
d. DIBULATKAN Rp 96,188.00

21 1 Bh Spray Closet
a. BAHAN
- Toto Spray THX20SMCRB Bh 1.0000 89,556.50 89,556.50
JUMLAH BAHAN Rp 89,556.50
b. UPAH
- Tukang batu org 0.6500 108,000.00 70,200.00
- Kepala Tukang org 0.0175 117,000.00 2,047.50
- Mandor org 0.0018 90,000.00 157.50
JUMLAH UPAH Rp 72,405.00
c. JUMLAH UPAH + BAHAN Rp 161,961.50
d. DIBULATKAN Rp 161,962.00

22 1 Bh Shower Spray
a. BAHAN
- Toto Shower Mandi TX402SP Bh 1.0000 127,264.50 127,264.50
JUMLAH BAHAN Rp 127,264.50
b. UPAH
- Tukang batu org 0.7500 108,000.00 81,000.00
- Kepala Tukang org 0.0175 117,000.00 2,047.50
- Mandor org 0.0018 90,000.00 157.50
JUMLAH UPAH Rp 83,205.00
c. JUMLAH UPAH + BAHAN Rp 210,469.50
d. DIBULATKAN Rp 210,470.00

23 1 M' Pasang Talang Plastik PVC U 15 cm (AW)


a. BAHAN
- Talang plastik UPVC m' 1.0500 20,557.29 21,585.15
- Perlengkapan 35 % harga talang lot 0.3500 21,585.15 7,554.80
JUMLAH BAHAN Rp 29,139.96
b. UPAH
- Pekerja org 0.1500 81,000.00 12,150.00
- Tukang batu org 0.4000 108,000.00 43,200.00
- Kepala Tukang org 0.0250 117,000.00 2,925.00
- Mandor org 0.0013 90,000.00 112.50
JUMLAH UPAH Rp 58,387.50
c. JUMLAH UPAH + BAHAN Rp 87,527.46
d. DIBULATKAN Rp 87,527.00

24 1 M' Saluran Air Limbah Buis Beton Ø 60 cm


a. BAHAN
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
- Buis beton Ø 60 cm bh 1.1000 112,181.30 123,399.43
- Bata merah bh 25.0000 599.90 14,997.50
- P.C (50 gk) zak 0.2060 1,221.23 251.57
- Pasir pasang m3 0.0610 110,000.00 6,710.00
- Pasir urug m3 0.0690 60,332.80 4,162.96
JUMLAH BAHAN Rp 149,521.47
b. UPAH
- Pekerja org 0.3800 81,000.00 30,780.00
- Tukang batu org 0.1900 108,000.00 20,520.00
- Kepala Tukang org 0.0190 117,000.00 2,223.00
- Mandor org 0.0190 90,000.00 1,710.00
JUMLAH UPAH Rp 55,233.00
c. JUMLAH UPAH + BAHAN Rp 204,754.47
d. DIBULATKAN Rp 204,754.00

25 1 M' Pasang Talang Seng Datar


a. BAHAN
Seng pelat 3" x 6" lbr 0.5000 17,826.46 8,913.23
Paku kg 0.0150 20,053.80 300.81
Kayu kelas II m3 0.0096 4,795,600.60 46,037.77
Meni besi kg 0.2500 76,273.00 19,068.25
JUMLAH BAHAN Rp 74,320.05
b. UPAH
Pekerja org 0.1500 81,000.00 12,150.00
Tukang batu org 0.4000 108,000.00 43,200.00
Kepala Tukang org 0.0250 117,000.00 2,925.00
Mandor org 0.0013 90,000.00 112.50
JUMLAH UPAH Rp 58,387.50
c. JUMLAH UPAH + BAHAN Rp 132,707.55
d. DIBULATKAN Rp 132,708.00

26 1 Buah Tangki Air fibreglass Volume 1 m3


a. BAHAN
- Bak fibreglass kapasitas 1 m3 bh 1.0000 1,128,154.80 1,128,154.80
JUMLAH BAHAN Rp 1,128,154.80
b. UPAH
- Pekerja org 3.3000 81,000.00 267,300.00
- Tukang batu org 1.1000 108,000.00 118,800.00
- Kepala Tukang org 0.0010 117,000.00 117.00
- Mandor org 0.1600 90,000.00 14,400.00
JUMLAH BAHAN Rp 400,617.00
b. PERLENGKAPAN
- Perlengkapan 6 % harga bak lot 0.0600 1,528,771.80 91,726.31
JUMLAH PERLENGKAPAN Rp 91,726.31
d. JUMLAH UPAH + BAHAN + PERLENGKAPAN Rp 1,620,498.11
e. DIBULATKAN Rp 1,620,498.00

27 1 Unit Septictank 1,00x2,00x2,00 m + Rembesan


a. UPAH DAN BAHAN
- Galian tanah m3 4.0000 47,286.00 189,144.00
- Pasir urug m3 0.1902 60,332.80 11,476.64
- lantai kerja m3 2.0000 837,801.75 1,675,603.49
- Pas bata adk 1pc : 3ps m2 13.3333 207,675.36 2,769,004.85
- Pelat beton K-225 m3 0.2667 978,666.00 260,977.60
- Plesteran adk 1pc : 3ps m2 13.3333 43,830.00 584,400.00
- Pipa PVC 4" jenis AW m' 4.8000 55,019.40 264,093.12
- Pipa GIP 1 1/2" m' 1.1000 40,064.75 44,071.23
- Galian tanah untuk rembesan m3 3.0000 36,000.00 108,000.00
- Pas ijuk kg 4.8000 20,053.80 96,258.24
- Urugan kerikil 3/5 m3 0.9333 221,363.10 206,605.56
HARGA SATUAN HARGA
NO. URAIAN SATUAN VOLUME
(Rp) (Rp)
- Pipa PVC 4" berlubang jenis AW m' 8.0000 31,451.90 251,615.20
- Urugan dan perataan tanah m3 1.0000 62,262.00 62,262.00
b. JUMLAH UPAH + BAHAN + PERLENGKAPAN Rp 6,523,511.93
c. DIBULATKAN Rp 6,523,512.00

28 1 Unit Septictank 2,00x3,00x2,00 m + Rembesan


- Galian tanah M³ 12.0000 47,286.00 567,432.00
- Pasir urug M³ 0.5707 60,332.80 34,429.92
- lantai kerja M³ 6.0000 837,801.75 5,026,810.48
- Pas bata adk 1pc : 3ps M² 40.0000 207,675.36 8,307,014.55
- Pelat beton K-225 M³ 0.8000 978,666.00 782,932.80
- Plesteran adk 1pc : 3ps M² 40.0000 43,830.00 1,753,200.00
- Pipa PVC 4" jenis AW M' 14.4000 55,019.40 792,279.36
- Pipa GIP 1 1/2" M' 1.1000 40,064.75 44,071.23
- Galian tanah untuk rembesan M³ 9.0000 36,000.00 324,000.00
- Pas ijuk kg 14.4000 20,053.80 288,774.72
- Urugan kerikil 3/5 M³ 2.8000 221,363.10 619,816.68
- Pipa PVC 4" berlubang jenis AW M' 24.0000 31,451.90 754,845.60
- Urugan dan perataan tanah M³ 3.0000 62,262.00 186,786.00
b. JUMLAH UPAH + BAHAN + PERLENGKAPAN Rp 19,482,393.34
c. DIBULATKAN Rp 19,482,393.00

29 1 Unit Groundtank 1,50x2,00x2,00 m + Rembesan


- Galian tanah M³ 6.0000 47,286.00 283,716.00
- Pasir urug M³ 0.2853 60,332.80 17,214.96
- lantai kerja M³ 3.0000 837,801.75 2,513,405.24
- Pas bata adk 1pc : 3ps M² 20.0000 207,675.36 4,153,507.28
- Pelat beton K-225 M³ 0.4000 978,666.00 391,466.40
- Plesteran adk 1pc : 3ps M² 20.0000 43,830.00 876,600.00
- Galian tanah untuk rembesan M³ 4.5000 36,000.00 162,000.00
- Pas ijuk kg 7.2000 20,053.80 144,387.36
- Urugan kerikil 3/5 M³ 1.4000 221,363.10 309,908.34
- Pipa PVC 4" berlubang jenis AW M' 12.0000 31,451.90 377,422.80
- Urugan dan perataan tanah M³ 1.5000 62,262.00 93,393.00
b. JUMLAH UPAH + BAHAN + PERLENGKAPAN Rp 9,323,021.38
c. DIBULATKAN Rp 9,323,021.00
M. ANALISA HARGA SATUAN PEKERJAAN CAT P.C.
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1 1 M² Mengikis / Mengerok Permukaan Cat Tembok Lama
a. BAHAN
- Soda api Kg 0.0500 30,509.20 1,525.46
JUMLAH BAHAN Rp 1,525.46
b. UPAH
- Pekerja Oh 0.1500 81,000.00 12,150.00
- Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 12,375.00
c. JUMLAH UPAH + BAHAN Rp 13,900.46
d. DIBULATKAN Rp 13,900.00

2 1 M² Mendempul Dan Menggosok Kayu


a. BAHAN
- Dempul Kg 0.1500 30,680.60 4,602.09
- Minyak cat Kg 0.0350 32,908.80 1,151.81
- Batu apung Kg 0.0250 25,367.20 634.18
JUMLAH BAHAN Rp 6,388.08
b. UPAH
- Pekerja Oh 0.0750 81,000.00 6,075.00
- Tukang cat Oh 0.0750 108,000.00 8,100.00
- Kepala tukang Oh 0.0075 117,000.00 877.50
- Mandor Oh 0.0038 90,000.00 337.50
JUMLAH UPAH Rp 15,390.00
c. JUMLAH UPAH + BAHAN Rp 21,778.08
d. DIBULATKAN Rp 21,778.00

3 1 M² Pengecatan Bidang Kayu Lama Setara Sieve


a. BAHAN
- Plamir Kg 0.1500 20,568.00 3,085.20
- Cat dasar Kg 0.1700 19,282.50 3,278.03
- Cat penutup setara sieve 2x Kg 0.1700 47,992.00 8,158.64
JUMLAH BAHAN Rp 14,521.87
b. UPAH
- Pekerja Oh 0.0700 81,000.00 5,670.00
- Tukang cat Oh 0.0750 108,000.00 8,100.00
- Kepala tukang Oh 0.0075 117,000.00 877.50
- Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 14,872.50
c. JUMLAH UPAH + BAHAN Rp 29,394.37
d. DIBULATKAN Rp 29,394.00

4 1 M² Pengecatan Bidang Kayu Baru Setara Sieve


a. BAHAN
- Cat meni Kg 0.2000 26,052.80 5,210.56
- Plamir Kg 0.1500 20,568.00 3,085.20
- Cat dasar Kg 0.1700 19,282.50 3,278.03
- Cat penutup 3x setara sieve Kg 0.3500 47,992.00 16,797.20
JUMLAH BAHAN Rp 28,370.99
b. UPAH
- Pekerja Oh 0.0700 81,000.00 5,670.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
- Tukang cat Oh 0.1050 108,000.00 11,340.00
- Kepala tukang Oh 0.0040 117,000.00 468.00
- Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 17,703.00
c. JUMLAH UPAH + BAHAN Rp 46,073.99
d. DIBULATKAN Rp 46,074.00

5 1 M² Pelaburan Bidang Kayu dengan Politur


a. BAHAN
- Politur Ltr 0.1500 41,136.00 6,170.40
- Politur jadi Ltr 0.3720 96,583.90 35,929.21
JUMLAH BAHAN Rp 42,099.61
b. UPAH
- Tukang cat Oh 0.0600 108,000.00 6,480.00
- Kepala tukang Oh 0.0160 117,000.00 1,872.00
- Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 8,577.00
c. JUMLAH UPAH + BAHAN Rp 50,676.61
d. DIBULATKAN Rp 50,677.00

6 1 M² Pelaburan Bidang Kayu dengan Cat Residu dan Ter


a. BAHAN
- Residu atau ter Ltr 0.3500 6,941.70 2,429.60
JUMLAH BAHAN Rp 2,429.60
b. UPAH
- Pekerja Oh 0.1000 81,000.00 8,100.00
- Mandor Oh 0.0060 90,000.00 540.00
JUMLAH UPAH Rp 8,640.00
c. JUMLAH UPAH + BAHAN Rp 11,069.60
d. DIBULATKAN Rp 11,070.00

7 1 M² Pengecatan Bidang Kayu Daun Pintu dengan Cat Milamic


a. BAHAN
1 Wood Filler Kg 0.1500 41,993.00 6,298.95
2 Woodstain Ltr 0.2500 55,705.00 13,926.25
3 Sending Sealer Ltr 0.3500 64,275.00 22,496.25
4 Melamic Top Coat Ltr 0.2500 69,417.00 17,354.25
5 Thinner Ltr 0.5000 20,482.30 10,241.15
6 Amplas Lbr 0.5000 5,142.00 2,571.00
7 Alat Bantu Ls 0.1000 72,887.85 7,288.79
JUMLAH BAHAN Rp 80,176.64
b. UPAH
1 Pekerja Oh 0.5000 81,000.00 40,500.00
2 Tukang Cat Oh 0.5000 108,000.00 54,000.00
3 Kepala Tukang Oh 0.0500 117,000.00 5,850.00
4 Mandor Oh 0.0050 90,000.00 450.00
JUMLAH UPAH Rp 100,800.00
c. JUMLAH UPAH + BAHAN Rp 180,976.64
d. DIBULATKAN Rp 180,977.00

8 1 M' Pengecatan Bidang Kayu Kusen dengan Cat Milamic


a. BAHAN
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1 Wood Filler Kg 0.0750 41,993.00 3,149.48
2 Woodstain Ltr 0.1250 55,705.00 6,963.13
3 Sending Sealer Ltr 0.1750 64,275.00 11,248.13
4 Melamic Top Coat Ltr 0.1250 69,417.00 8,677.13
5 Thinner Ltr 0.2500 20,482.30 5,120.58
6 Amplas Lbr 0.2500 5,142.00 1,285.50
7 Alat Bantu Ls 0.0500 72,887.85 3,644.39
JUMLAH BAHAN Rp 40,088.32
b. UPAH
1 Pekerja Oh 0.2500 81,000.00 20,250.00
2 Tukang Cat Oh 0.2500 108,000.00 27,000.00
3 Kepala Tukang Oh 0.0250 117,000.00 2,925.00
4 Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 47,250.00
c. JUMLAH UPAH + BAHAN Rp 88,913.32
d. DIBULATKAN Rp 88,913.00

9 1 M² Pengecatan Tembok Baru Eksterior Setara ICI


a. BAHAN
- Cat dasar Dulux Kg 0.1200 41,136.00 4,936.32
- Cat Dulux penutup 2x setara ICI Kg 0.2600 80,772.25 21,000.79
JUMLAH BAHAN Rp 25,937.11
b. UPAH
- Pekerja Oh 0.0200 81,000.00 1,620.00
- Tukang cat Oh 0.0630 108,000.00 6,804.00
- Kepala tukang Oh 0.0063 117,000.00 737.10
- Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 9,386.10
c. JUMLAH UPAH + BAHAN Rp 35,323.21
d. DIBULATKAN Rp 35,323.00

10 1 M² Pengecatan Tembok Baru Eksterior Setara Catylac


a. BAHAN
- Cat dasar Catylac Kg 0.1200 19,282.50 2,313.90
- Cat Catylac penutup 2 x Kg 0.2600 33,423.00 8,689.98
JUMLAH BAHAN Rp 11,003.88
b. UPAH
- Pekerja Oh 0.0280 81,000.00 2,268.00
- Tukang cat Oh 0.0420 108,000.00 4,536.00
- Kepala tukang Oh 0.0042 117,000.00 491.40
- Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 7,520.40
c. JUMLAH UPAH + BAHAN Rp 18,524.28
d. DIBULATKAN Rp 18,524.00

11 1 M² Pengecatan Tembok Baru Interior Setara ICI


a. BAHAN
- Cat dasar Dulux Interior Alkali Sealer Kg 0.1200 37,665.15 4,519.82
- Cat Dulux penutup 2x Interior Putih Glow Kg 0.2600 24,853.00 6,461.78
JUMLAH BAHAN Rp 10,981.60
b. UPAH
- Pekerja Oh 0.0200 81,000.00 1,620.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
- Tukang cat Oh 0.0630 108,000.00 6,804.00
- Kepala tukang Oh 0.0063 117,000.00 737.10
- Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 9,386.10
c. JUMLAH UPAH + BAHAN Rp 20,367.70
d. DIBULATKAN Rp 20,368.00

12 1 M² Pengecatan Tembok Baru Interior Setara Catylac


a. BAHAN
- Cat dasar Catylac Kg 0.2400 19,282.50 4,627.80
- Cat Catylac penutup 2 x Kg 0.1800 21,425.00 3,856.50
JUMLAH BAHAN Rp 8,484.30
b. UPAH
- Pekerja Oh 0.0280 81,000.00 2,268.00
- Tukang cat Oh 0.0420 108,000.00 4,536.00
- Kepala tukang Oh 0.0042 117,000.00 491.40
- Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 7,520.40
c. JUMLAH UPAH + BAHAN Rp 16,004.70
d. DIBULATKAN Rp 16,005.00

13 1 M² Pengecatan Plafond ( 3x ) Setara Ecohome


a. BAHAN
- Cat Plafond Kg 0.3600 10,712.50 3,856.50
- Rol cat Bh 0.0100 25,710.00 257.10
JUMLAH BAHAN Rp 4,113.60
b. UPAH
- Pekerja Oh 0.0700 81,000.00 5,670.00
- Tukang cat Oh 0.1050 108,000.00 11,340.00
- Kepala tukang Oh 0.0040 117,000.00 468.00
- Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 17,703.00
c. JUMLAH UPAH + BAHAN Rp 21,816.60
d. DIBULATKAN Rp 21,817.00

14 1 M² Pengecatan Plafond ( 2x ) Setara Ecohome


a. BAHAN
- Cat tembok setara Vinilex Kg 0.2400 18,339.80 4,401.55
- Rol cat Bh 0.1000 25,710.00 2,571.00
JUMLAH BAHAN Rp 6,972.55
b. UPAH
- Pekerja Oh 0.0600 81,000.00 4,860.00
- Tukang cat Oh 0.0900 108,000.00 9,720.00
- Kepala tukang Oh 0.0030 117,000.00 351.00
- Mandor Oh 0.0020 90,000.00 180.00
JUMLAH UPAH Rp 15,111.00
c. JUMLAH UPAH + BAHAN Rp 22,083.55
d. DIBULATKAN Rp 22,084.00

15 1 M² Pengecatan Permukaan Baja dengan Meni Besi


a. BAHAN
- Meni besi Kg 0.1000 36,465.35 3,646.54
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
- Kuas 3" Bh 0.0100 22,282.00 222.82
JUMLAH BAHAN Rp 3,869.36
b. UPAH
- Pekerja Oh 0.0700 81,000.00 5,670.00
- Tukang cat Oh 0.1050 108,000.00 11,340.00
- Kepala tukang Oh 0.0040 117,000.00 468.00
- Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 17,703.00
c. JUMLAH UPAH + BAHAN Rp 21,572.36
d. DIBULATKAN Rp 21,572.00

16 1 M² Pengecatan Permukaan Conwood Dengan Propan Fiberkote


a. BAHAN
- Cat Propan Fiberkote Kg 0.3600 76,273.00 27,458.28
- Kuas 3" Bh 0.0100 22,282.00 222.82
JUMLAH BAHAN Rp 27,681.10
b. UPAH
- Pekerja Oh 0.1750 81,000.00 14,175.00
- Tukang cat Oh 0.1750 108,000.00 18,900.00
- Kepala tukang Oh 0.0175 117,000.00 2,047.50
- Mandor Oh 0.0018 90,000.00 157.50
JUMLAH UPAH Rp 35,280.00
c. JUMLAH UPAH + BAHAN Rp 62,961.10
d. DIBULATKAN Rp 62,961.00

19 1 M² Pengecatan Lapis Duco (2xlapis sampai rata)


a. BAHAN
- Cat Dduco Kg 0.5000 65,046.30 32,523.15
- Clear Kg 0.2000 94,270.00 18,854.00
- Thinner A Ltr 0.8370 20,482.30 17,143.69
JUMLAH BAHAN Rp 68,520.84
b. UPAH
- Pekerja Oh 0.0750 81,000.00 6,075.00
- Tukang cat Oh 0.9000 108,000.00 97,200.00
- Kepala tukang Oh 0.0900 117,000.00 10,530.00
- Mandor Oh 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 114,030.00
c. JUMLAH UPAH + BAHAN Rp 182,550.84
d. DIBULATKAN Rp 182,551.00
N. ANALISA HARGA SATUAN PEKERJAAN LISTRIK P.L.
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1 Titik Lampu Dalam/ttk Bawah Plafond (Kabel NYM 2x1,5mm)
a. BAHAN
- Pipa Listrik Btg 1.0000 13,283.50 13,283.50
- Kabel NYM 2x1,5mm Roll 0.1000 257,100.00 25,710.00
- Klem Pipa Bh 5.0000 428.50 2,142.50
- Klem Kabel Dus 0.1000 29,995.00 2,999.50
- T-Dus Btg 1.0000 4,285.00 4,285.00
- Fitting Bh 1.0000 29,566.50 29,566.50
- Saklar Bh 1.0000 23,567.50 23,567.50
JUMLAH BAHAN Rp 101,554.50
b. UPAH
- Pekerja Oh 0.3000 81,000.00 24,300.00
- Tukang Listrik Oh 0.1500 108,000.00 16,200.00
Mandor Oh 0.0750 90,000.00 6,750.00
JUMLAH UPAH Rp 47,250.00
c. ALAT
- Pahat Bh 0.0500 47,135.00 2,356.75
- Alat Bantu Lain (5% x Jumlah Harga) Ls 1.0000 7,440.23 7,440.23
JUMLAH ALAT Rp 9,796.98
d. JUMLAH UPAH + BAHAN+ALAT Rp 158,601.48
e. DIBULATKAN Rp 158,601.00

2 Titik Lampu Dalam/ttk Bawah Dak (Kabel NYM 2x1,5mm)


a. BAHAN
- Pipa Listrik Btg 1.0000 13,283.50 13,283.50
- Kabel NYM 2x1,5mm Roll 0.1000 257,100.00 25,710.00
- Klem Pipa Bh 5.0000 428.50 2,142.50
- Klem Kabel Dus 0.1000 29,995.00 2,999.50
- T-Dus Btg 1.0000 4,285.00 4,285.00
- Pipa Flexible Btg 1.0000 4,285.00 4,285.00
- Fitting Bh 1.0000 29,566.50 29,566.50
- Saklar Bh 1.0000 23,567.50 23,567.50
JUMLAH BAHAN Rp 105,839.50
b. UPAH
- Pekerja Oh 0.4000 81,000.00 32,400.00
- Tukang Listrik Oh 0.2000 108,000.00 21,600.00
Mandor Oh 0.1000 90,000.00 9,000.00
JUMLAH UPAH Rp 63,000.00
c. ALAT
- Pahat Bh 0.0500 47,135.00 2,356.75
- Alat Bantu Lain (5% x Jumlah Harga) Ls 1.0000 8,441.98 8,441.98
JUMLAH ALAT Rp 10,798.73
d. JUMLAH UPAH + BAHAN+ALAT Rp 179,638.23
e. DIBULATKAN Rp 179,638.00

3 Titik Stop Kontak Biasa /ttk (Kabel NYM 3x1,5mm)


a. BAHAN
- Pipa Listrik Btg 1.0000 13,283.50 13,283.50
- Kabel NYM 3x1,5mm Roll 0.1000 323,946.00 32,394.60
- Klem Pipa Bh 0.1000 428.50 42.85
- Klem Kabel Dus 0.0500 29,995.00 1,499.75
- T-Dus Btg 1.0000 4,285.00 4,285.00
- Stop Kontak Bh 1.0000 23,567.50 23,567.50
JUMLAH BAHAN Rp 75,073.20
b. UPAH
- Pekerja Oh 0.3000 81,000.00 24,300.00
- Tukang Listrik Oh 0.1500 108,000.00 16,200.00
Mandor Oh 0.0750 90,000.00 6,750.00
JUMLAH UPAH Rp 47,250.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
c. ALAT
- Pahat Bh 0.0500 47,135.00 2,356.75
- Alat Bantu Lain (5% x Jumlah Harga) Ls 1.0000 6,116.16 6,116.16
JUMLAH ALAT Rp 8,472.91
d. JUMLAH UPAH + BAHAN+ALAT Rp 130,796.11
e. DIBULATKAN Rp 130,796.00

4 Titik Stop Kontak Khusus /ttk (Kabel NYM 3x2,5mm)


a. BAHAN
- Pipa Listrik Btg 1.0000 13,283.50 13,283.50
- Kabel NYM 2x1,5mm Roll 0.1000 1,006,118.00 100,611.80
- Klem Pipa Bh 0.1000 428.50 42.85
- Klem Kabel Dus 0.0500 29,995.00 1,499.75
- T-Dus Btg 1.0000 4,285.00 4,285.00
- Stop Kontak Bh 1.0000 23,567.50 23,567.50
JUMLAH BAHAN Rp 143,290.40
b. UPAH
- Pekerja Oh 0.4000 81,000.00 32,400.00
- Tukang Listrik Oh 0.2000 108,000.00 21,600.00
Mandor Oh 0.1000 90,000.00 9,000.00
. Rp 63,000.00
c. ALAT
- Pahat Bh 0.0500 47,135.00 2,356.75
- Alat Bantu Lain (5% x Jumlah Harga) Ls 1.0000 10,314.52 10,314.52
JUMLAH ALAT Rp 12,671.27
d. JUMLAH UPAH + BAHAN+ALAT Rp 218,961.67
e. DIBULATKAN Rp 218,962.00

5 Pekerjaan Arde/Pentanahan/ttk
a. BAHAN
- Kawat BC dia 6mm M' 4.0000 9,855.50 39,422.00
- Pipa GIP dia 1/2" Btg 0.5000 93,498.70 46,749.35
JUMLAH BAHAN Rp 86,171.35
b. UPAH
- Pekerja Oh 0.7500 81,000.00 60,750.00
- Tukang Listrik Oh 0.7500 108,000.00 81,000.00
Mandor Oh 0.3750 90,000.00 33,750.00
. Rp 175,500.00
c. ALAT
- Pahat Bh 0.1000 47,135.00 4,713.50
- Alat Bantu Lain (10% x Jumlah Harga) Ls 1.0000 13,083.57 13,083.57
JUMLAH ALAT Rp 17,797.07
d. JUMLAH UPAH + BAHAN+ALAT Rp 279,468.42
e. DIBULATKAN Rp 279,468.00

6 Pekerjaan Box Sikring/bh 2 Group


a. BAHAN
- Box Sikring Bh 1.0000 21,425.00 21,425.00
- MCB Bh 1.0000 47,220.70 47,220.70
- Pipa Listrik Btg 1.0000 13,283.50 13,283.50
- Klem Pipa Bh 6.0000 428.50 2,571.00
- T-Dus Bh 2.0000 4,285.00 8,570.00
JUMLAH BAHAN Rp 93,070.20
b. UPAH
- Pekerja Oh 1.0000 81,000.00 81,000.00
- Tukang Listrik Oh 0.5000 108,000.00 54,000.00
Mandor Oh 0.1667 90,000.00 15,003.00
. Rp 150,003.00
c. ALAT
- Pahat Bh 0.0500 13,083.57 654.18
- Alat Bantu Lain (5% x Jumlah Harga) Ls 1.0000 12,153.66 12,153.66
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
JUMLAH ALAT Rp 12,807.84
d. JUMLAH UPAH + BAHAN+ALAT Rp 255,881.04
e. DIBULATKAN Rp 255,881.00

7 Pekerjaan Box Sikring/bh 4 Group


a. BAHAN
- Box Sikring Bh 1.0000 29,995.00 29,995.00
- MCB Bh 1.0000 47,220.70 47,220.70
- Pipa Listrik Btg 1.0000 13,283.50 13,283.50
- Klem Pipa Bh 6.0000 428.50 2,571.00
- T-Dus Bh 2.0000 4,285.00 8,570.00
JUMLAH BAHAN Rp 101,640.20
b. UPAH
- Pekerja Oh 1.0000 81,000.00 81,000.00
- Tukang Listrik Oh 0.5000 108,000.00 54,000.00
Mandor Oh 0.1667 90,000.00 15,003.00
. Rp 150,003.00
c. ALAT
- Pahat Bh 0.0500 12,153.66 607.68
- Alat Bantu Lain (5% x Jumlah Harga) Ls 1.0000 12,582.16 12,582.16
JUMLAH ALAT Rp 13,189.84
d. JUMLAH UPAH + BAHAN+ALAT Rp 264,833.04
e. DIBULATKAN Rp 264,833.00

8 Pekerjaan Box Sikring/bh 6 Group


a. BAHAN
- Box Sikring Bh 1.0000 47,135.00 47,135.00
- MCB Bh 1.0000 47,220.70 47,220.70
- Pipa Listrik Btg 1.0000 13,283.50 13,283.50
- Klem Pipa Bh 6.0000 428.50 2,571.00
- T-Dus Bh 2.0000 4,285.00 8,570.00
JUMLAH BAHAN Rp 118,780.20
b. UPAH
- Pekerja Oh 1.0000 81,000.00 81,000.00
- Tukang Listrik Oh 0.5000 108,000.00 54,000.00
Mandor Oh 0.1667 90,000.00 15,003.00
. Rp 150,003.00
c. ALAT
- Pahat Bh 0.0500 12,582.16 629.11
- Alat Bantu Lain (5% x Jumlah Harga) Ls 1.0000 13,439.16 13,439.16
JUMLAH ALAT Rp 14,068.27
d. JUMLAH UPAH + BAHAN+ALAT Rp 282,851.47
e. DIBULATKAN Rp 282,851.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
O. PEKERJAAN PENANAMAN POHON P.P.P.
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1 1 Lubang Penanaman Pohon Pelindung
a. BAHAN
- Pupuk kandang krg 0.0800 21,425.00 1,714.00
- Furadan kg 0.0010 20,568.00 20.57
- Pohon pelindung btng 1.0000 21,425.00 21,425.00
JUMLAH BAHAN Rp 23,159.57
b. UPAH
- Pekerja org 0.0800 81,000.00 6,480.00
- Mandor org 0.0080 90,000.00 720.00
JUMLAH UPAH Rp 7,200.00
c. JUMLAH UPAH + BAHAN Rp 30,359.57
d. DIBULATKAN Rp 30,360.00

2 1 Lubang (70x70x70) cm, tanam bambu krisik/jepang


a. BAHAN
- Pupuk kandang krg 0.0800 21,425.00 1,714.00
- Furadan kg 0.0010 20,568.00 20.57
- Bambu krisik/jepang btng 1.0000 42,850.00 42,850.00
JUMLAH BAHAN Rp 44,584.57
b. UPAH
- Pekerja org 0.0250 81,000.00 2,025.00
- Mandor org 0.0025 90,000.00 225.00
JUMLAH UPAH Rp 2,250.00
c. JUMLAH UPAH + BAHAN Rp 46,834.57
d. DIBULATKAN Rp 46,835.00

3 1 Lubang (40x40x40) cm, tanam pohon perdu (polibag)


a. BAHAN
- Pupuk kandang krg 0.0400 21,425.00 857.00
- Furadan kg 0.0010 20,568.00 20.57
- Pohon perdu btng 1.0000 8,570.00 8,570.00
JUMLAH BAHAN Rp 9,447.57
b. UPAH
- Pekerja org 0.0200 81,000.00 1,620.00
- Mandor org 0.0020 90,000.00 180.00
JUMLAH UPAH Rp 1,800.00
c. JUMLAH UPAH + BAHAN Rp 11,247.57
d. DIBULATKAN Rp 11,248.00

4 1 M² Tanam rumput gajah (silang papan catur)


a. BAHAN
Pupuk kandang krg 0.0400 21,425.00 857.00
Rumput gajah mini m2 0.5000 12,855.00 6,427.50
JUMLAH BAHAN Rp 7,284.50
b. UPAH
- Pekerja org 0.0400 81,000.00 3,240.00
- Mandor org 0.0040 90,000.00 360.00
JUMLAH UPAH Rp 3,600.00
c. JUMLAH UPAH + BAHAN Rp 10,884.50
d. DIBULATKAN Rp 10,885.00
DAFTAR HARGA SATUAN UPAH
Periode : Tahun Anggaran 2019
Klasifikasi : Menengah
Proyek : Pembangunan Kost-Kostan (Hostel)
Lokasi : Jln. Pembangunan
Wilayah : Deli Serdang

NO URAIAN SATUAN UPAH (Rp.)

1 Mandor Org/hr Rp 90,000.00


2 Kepala Tukang Batu Org/hr Rp 117,000.00
3 Kepala Tukang Kayu Org/hr Rp 117,000.00
4 Kepala Tukang Besi Org/hr Rp 117,000.00
5 Kepala Tukang Cat Org/hr Rp 117,000.00
6 Kepala Tukang Listrik Org/hr Rp 117,000.00
7 Kepala Tukang Org/hr Rp 117,000.00
8 Tukang Batu Org/hr Rp 108,000.00
9 Tukang Kayu Org/hr Rp 108,000.00
10 Tukang Besi/Baja Org/hr Rp 108,000.00
11 Tukang Cat Org/hr Rp 108,000.00
12 Tukang Listrik Org/hr Rp 108,000.00
13 Tukang Pipa Org/hr Rp 108,000.00
14 Tukang Plitur Org/hr Rp 108,000.00
15 Tukang Taman Org/hr Rp 108,000.00
16 Tukang Org/hr Rp 108,000.00
17 Pembantu Tukang Org/hr Rp 81,000.00
18 Pekerja Biasa Org/hr Rp 72,000.00
19 Penjaga Malam Org/hr Rp 81,000.00
20 Sopir Org/hr Rp 108,000.00
21 Operator Org/hr Rp 135,000.00
22 Mekanik Org/hr Rp 135,000.00
23 Pembantu Sopir Org/hr Rp 90,000.00
24 Pembantu Operator Org/hr Rp 81,000.00
25 Pembantu Mekanik Org/hr Rp 81,000.00

harga sudah termasuk PPN dan keuntungan


KETERANGAN
PERINCIAN BIAYA SMK3 KONSTRUKSI
UNTUK PEKERJA : PEMBANGUNAN KANTOR KEPALA DESA KAMPUNG BARU KECAMATAN BILAH BARAT

HRG.SATUAN BIAYA
NO URAIAN PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 3 4 5 6
BIAYA SMK3 KONSTRUKSI :
1. Penyiapan RK3K terdiri atas :
a. Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja dan Set 5.00 280,650.00 Rp 1,403,250.00
b. Pembuatan Kartu Identitas Pekerja (KIP); Lbr - 1,500.00
Biaya Penyiapan RK3K Rp 1,403,250.00
2. Sosialisasi dan Promosi K3 terdiri atas :
a. Induksi K3 (Safety Induction); khusus untuk pekerja baru Org - 7,016.25
b. Pengarahan K3 (safety briefing) : Pertemuan Keselamatan
Org - 1,403,250.00
(Safety Talk dan/atau Tool Box Meeting);
c. Pelatihan K3; -
c.1. Bekerja di ketinggian Org - 7,016.25
c.2. Peralatan Konstruksi & Penggunaan bahan Kimia (MSDS) Org - 7,016.25
c.3. Analysis Keselamatan Pekerjaan Org - 7,016.25
c.4. Perilaku Berbasis Keselamatan (Budaya K3) Org - 7,016.25
c.5. P3K Org - 1,637,125.00
d. Simulasi K3; Org - 7,016.25
e. Spanduk (banner); Lb 5.00 140,325.00 Rp 701,625.00
f. Poster; Lb - 46,775.00
g. Papan Informasi K3. Bh - 187,100.00
Biaya Sosialisasi dan Promosi K3 Rp 701,625.00
3. Alat Pelindung Kerja terdiri atas:
a. Jaring Pengaman (Safety Net); Ls - 4,677,500.00 Rp -
b. Tali Keselamatan (Life Line); Ls - 935,500.00 Rp -
c. kebutuhancPenahan Jatuh (Safety Deck); Ls - 4,677,500.00 Rp -
d. Pagar Pengaman (Guard Railling); Ls - 14,032,500.00 Rp -
e. Pembatas Area (Restricted Area). Ls - 2,806,500.00 Rp -
Biaya Alat Pelindung Kerja Rp -
4. Alat Pelindung Diri terdiri atas:
a. Topi Pelindung (Safety Helmet); Bh 50.00 70,162.50 Rp 3,508,125.00
b. Pelindung Mata (Goggles, Spectacles); Psg 50.00 23,387.50 Rp 1,169,375.00
c. Tameng Muka (Face Shield); Bh 50.00 70,162.50 Rp 3,508,125.00
d. Masker Selam (Breathing Apparatus); Bh - 93,550.00 Rp -
e. Pelindung Telinga (Ear Plug, Ear Muff); Psg - 46,775.00 Rp -
f. Pelindung Pernafasan Dan Mulut (Masker); Bh 50.00 4,677.50 Rp 233,875.00
g. Sarung Tangan (Safety Gloves); Psg 50.00 4,677.50 Rp 233,875.00
h. Sepatu Keselamatan (Safety Shoes) untuk staf; Psg - 252,585.00 Rp -
i. Sepatu Keselamatan (Rubber Safety Shoes_and toe cap) Psg 50.00 135,647.50 Rp 6,782,375.00
j. Penunjang Seluruh Tubuh (Full Body Harness); Bh - 701,625.00 Rp -
k. Jaket Pelampung (Life Vest); Bh - 93,550.00 Rp -
l. Rompi Keselamatan (Safety Vest); Bh 50.00 23,387.50 Rp 1,169,375.00
m. Celemek (Apron/Coveralls); Bh - 37,420.00 Rp -
n. Pelindung Jatuh (Fall Arrester); Bh - 93,550.00 Rp -
Biaya Alat Pelindung Diri Rp 16,605,125.00
5. Asuransi Dan Perijinan terdiri atas :
a. BPJS Ketenagakerjaan Dan Kesehatan Kerja; Ls 1.00 17,901,728.00 Rp 17,901,728.00
b. Surat Ijin Kelaikan Alat; Alat/Kend - 7,951,750.00 Rp -
c. Surat Ijin Operator; Lb/Alat - 6,080,750.00 Rp -
d. Surat Ijin Pengesahan Panitia Pembina
Ls - 467,750.00 Rp -
Keselamatan Kesehatan Kerja (P2K3);
Biaya Asuransi Dan Perijinan Rp 17,901,728.00
6. Personil K3 terdiri atas :
a. Ahli K3 OB - 6,548,500.00 Rp -
b. Petugas K3 Ls 1.00 18,710,000.00 Rp 18,710,000.00
c. Petugas Tanggap Darurat OB - 2,806,500.00 Rp -
d. Petugas P3K OB - 2,806,500.00 Rp -
e. Petugas Pengatur Lalu Lintas (Flagman ); OB - 2,806,500.00 Rp -
f. Petugas Medis. OB - 2,806,500.00 Rp -
Biaya Personil K3 Rp 18,710,000.00
7. Fasilitas sarana kesehatan;
a. Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka) Ls 5.00 247,907.50 Rp 1,239,537.50
b. Ruang P3K (T. Tidur Pasien,Stetoskop, Timbangan Badan) Ls - 4,677,500.00 Rp -
c. Peralatan Pengasapan (Fogging) ; Bh - 1,403,250.00 Rp -
d. Obat Pengasapan. Ls - 14,032.50 Rp -
Biaya Fasilitas sarana kesehatan Rp 1,239,537.50
8. Rambu- Rambu terdiri atas :
a. Rambu Petunjuk; Bh - 70,162.50 Rp -
b. Rambu Larangan; Bh - 70,162.50 Rp -
c. Rambu Peringatan; Bh - 70,162.50 Rp -
d. Rambu Kewajiban; Bh - 70,162.50 Rp -
e. Rambu Informasi; Bh - 70,162.50 Rp -
f. Rambu Pekerjaan Sementara; Bh - 70,162.50 Rp -
g. Tongkat Pengatur Lalu Lintas (Warning Lights Stick) ; Bh - 46,775.00 Rp -
h. Kerucut Lalu Lintas (Traffic Cone) ; Bh - 93,550.00 Rp -
i. Lampu Putar (Rotary Lamp ); Bh - 93,550.00 Rp -
j. Lampu Selang Lalu Lintas. Ls - 935,500.00 Rp -
Biaya Rambu- Rambu Rp -
9. Lain- Lain Terkait Pengendalian Risiko K3
a. Alat Pemadam Api Ringan (APAR); Bh - 514,525.00 Rp -
b. Sirine; Bh - 93,550.00 Rp -
c. Bendera K3; Bh 5.00 46,775.00 Rp 233,875.00
d. Jalur Evakuasi (Escape Route ); Ls - 46,775.00 Rp -
e. Lampu Darurat (Emergency Lamp ); Bh - 65,485.00 Rp -
f. Program Inspeksi Dan Audit Internal; Ls - 1,871,000.00 Rp -
g. Pelaporan dan Penyelidikan Insiden. Ls 12.00 187,100.00 Rp 2,245,200.00
Biaya Pengendalian Risiko K3 Rp 2,479,075.00

TOTAL BIAYA SMK3 KONSTRUKSI Rp 59,040,340.50

Medan; 3 September 2019

Dibuat Oleh
DAFTAR HARGA SATUAN BAHAN BANGUNAN
Periode : Tahun Anggaran 2019
Klasifikasi : Menengah
Proyek : Pembangunan Kost-Kostan (Hostel)
Lokasi : Jln. Pembangunan
Wilayah : Deli Serdang

NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)

A. AGREGAT KASAR,BAHAN PEREKAT & BAHAN JADINYA


1. Tanah - Urug Pilihan M³ 77,130.00
- liat M³ 26,824.10
2. Pasir - Urug M³ 60,332.80
- Pasang Kali M³ 110,000.00
- Beton M³ 130,000.00
- Pasir Beton (BJ = 1400 Kg/M3) M³ 85.70
3. Abu Batu M³ 221,963.00
4. Sirtu M³ 174,399.50
5. Batu - Gosok ( Apung ) M³ 25,367.20
- Pecah Mesin 1/2 M³ 292,494.10
- Pecah Mesin 2/3 M³ 242,959.50
- Splitz (BJ = 1800 Kg/M3) Kg 134.98
- Pecah Mesin 3/5 M³ 221,363.10
- Pecah Mesin 5/7 M³ 188,111.50
- Belah Pondasi M³ 188,540.00
- Bronjol ( Untuk Bronjong ) M³ 154,945.60
- Koral Beton Kali M³ 197,110.00
- Tempel Hitam M³ 82,786.20
- Pinggir Beton 10 x 20 x 35 Bh 12,083.70
- Kerikil M³ 149,975.00
6. Batako Kecil Kecil; Uk. 8x10x20 cm Bh 1,714.00
Besar; Uk. 8 x 20 x 30 Bh 2,056.80
7. Con Blok Uk. 8 x 20 x 40 Bh 4,627.80
8. Bata Merah Bakar kelas I Bh 599.90
Bakar kelas II Bh 561.34
Oven(Klingker);Uk.4,5x9,5x18 cm Bh 1,714.00
9. Roster Beton Uk. 20 x 20 Bh 12,683.60
Uk. 30 x 30 Bh 13,283.50
10. Grass Blok Lubang 5, Tebal 8 cm Bh 14,140.50
Lubang 8, Tebal 6 cm Bh 23,567.50
Lubang 8, Tebal 8 cm Bh 32,994.50
11. Paving Blok Natural 8 cm Natural Tebal. 8 cm M² 76,452.97
Warna Tebal. 8 cm M² 102,377.22
Natural Tebal 6 cm M² 71,645.20
Warna Tebal 6 cm M² 81,072.20
12. Semen Portland Cement 1 Sak = 40 kg Sak 48,849.00
Portland Cement 1Kg Kg 1,221.23
Putih Sak 79,443.90
Warna Kg 13,454.90
16. Air Ltr 45.11

B. LABURAN,PENGISI DAN ALATNYA


1 Plamir Nippon Paint Matex (Wall Putty) Kg 17,140.00
Bioduco Wood Putty Mini Can WHITE Ltr 20,568.00
2 Cat Tembok Dulux eksterior; weathershield putih Briliant Ltr 80,772.25
Dulux; Interior Putih Glow Ltr 24,853.00
Catylac eksterior Kg 33,423.00
Catylac interior Kg 21,425.00
Cat Tembok Vinilex Kembang Kg 18,339.80
3 Cat Dasar Dulux; Exterior Wheatershield Kg 41,136.00
Dulux; Interior Alkali Sealer Kg 37,665.15
Catylac Sealer Kg 19,282.50
Ecohome Kg 10,712.50
4 Cat Zinc Chromate Nippon Kg 36,465.35
5 Water Profing Emulsion Kg 59,990.00
Membrance Kg 53,562.50
6 Rool Cat Tembok Bh 25,710.00

Page 79 BHN
NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)

7 Kape Tembok Bh 7,284.50


Kayu Bh 8,570.00
8 Soligneum 1 Blek Kg 21,425.00
9 Plincote M³ 24,853.00
10 Penawetan Kayu M³ 327,888.20
11 Pegopenan Kayu Bh 317,090.00
12 Kwas 4" Bh 22,282.00
13 Oker Bks 18,854.00
14 Oyan Bks 4,456.40
15 Oten ( Pewarna Plitur ) Ltr 4,713.50
16 Spirtus Kg 12,855.00
17 Bahan Pelitur Kripik ( Sirlak India ) Kg 94,270.00
18 Dempul Lilin Kg 29,309.40
Plitur Kg 32,308.90
Halus / Imfra ( Wood Filler ) Kg 32,308.90
Jadi Kg 30,680.60
Plastik Kg 33,594.40
Duco Kg 30,680.60
19 Politur Biasa Kg 41,136.00
Jadi Kg 96,583.90
20 Terpentin Kg 16,711.50
21 Tiner Tipe A Kg 20,482.30
Tipe B Kg 18,339.80
22 Kumpon Kg 26,395.60
23 Melamik Kg 44,992.50
24 Ampelas Lbr 5,142.00
25 Dempul Kayu Cap Kucing Kg 20,910.80
26 Meni Kayu / Besi Kg 26,052.80
27 Zinkcromat Kg 35,051.30
28 Cat Kayu Avian High Gloss Enamel (Kayu & Besi) Kg 47,992.00
29 Cat Besi Kg 37,708.00
30 Cat Besi Duco Danaglos / ICI Kg 65,389.10
31 Cat Bron kg 58,018.90
32 Karet lis bh 2,828.10
33 Minyak cat Kg 32,908.80
34 Glass beet Kg 42,935.70
35 Residu Ltr 6,941.70
36 Woodfiller Ltr 41,993.00
37 Woodstain Ltr 55,705.00
38 Sending Sealer Ltr 64,275.00
39 Melamic Top Coat Ltr 69,417.00
40 Propan - Fiberkote Ltr 76,273.00
41 Cat Duco - Nippe 2000 Ltr 65,046.30
42 Clear - Danagloss Ltr 94,270.00

C. BAHAN KAYU BERIKUT BAHAN JADINYA


1 Bambu Ukuran Dia.5 s/ 7 cm Btg 10,284.00
Ukuran Dia.7 s/ 10 cm Btg 12,855.00
2 Kayu Balok Terentang Kamper Singkil/Kapur ( kls II ) M³ 6,079,943.65
Balok Borneo Super M³ 4,524,960.00
Balok Kamper Medan (Kruing ) M³ 4,878,558.20
Balok Kamper Banjar M³ 5,453,605.20
Balok Kamper Samarinda M³ 7,399,080.90
Balok Rasamala M³ 2,277,906.00
Jati Jatim Tua dia. 40 cm M³ 17,801,604.00
Jati Jateng Tua dia. 40 cm M³ 19,015,458.80
Jati Jabar Tua dia. 40 cm M³ 11,676,967.80
Jati Jabar Tua dia. 40 cm kebawah M³ 10,914,837.70
Kelas I (Segeng,Mahoni,Laban ) M³ 1,773,818.60
Balok Albasia M³ 1,603,018.50
Papan Albasia M³ 1,775,446.90
Papan Borneo Super M³ 4,795,600.60
Papan Kamper Medan (Kruing ) M³ 4,990,653.80
Papan Kamper Banjar M³ 5,695,022.10
Papan Kamper Samarinda M³ 7,476,725.10
3 Dolken Diameter 5 s/d 7 Btg 12,855.00

Page 80 BHN
NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)

Diameter 7 s/d 10CM Btg 14,569.00


4 List Profil Kayu Lebar 1 cm M' 3,813.65
Lebar 2 cm M' 4,285.00
Lebar 4 cm M' 6,127.55
Lebar 5 cm M' 7,370.20
Lebar 10 cm M' 12,597.90
5 Pegangan Tangga Profil Jati M' 137,205.70
Profil Kamper M' 104,982.50
6 Kayu Kaso 4/6 M³ 2,375,604.00
7 Kayu Kaso 5/7 Kamper Medan M³ 2,876,777.60
8 Kayu Reng 2/3 Borneo Super M' 3,856.50
2/3 Kamper Banjar M' 4,542.10
3/4 Kamper Medan M³ 5,142.00
9 Kayu Papan Terentang M³ 2,442,450.00
10 Kayu Balok Terentang M³ 2,262,480.00
11 Batang Kelapa Btg 222,391.50
12 Tali Ijuk Kg 20,053.80
13 lapisan Ijuk tebal 10 cm M² 18,854.00
14 Venetion Blind M² 460,466.10
15 Vertikal Blind M² 300,978.40
16 Teakwood - 3 mm (Lapis Jati) M² 83,771.75
- 4 mm (Lapis Jati) M² 93,627.25
17 Formika - 0,6 mm; Uk.120 x 240 cm M² 136,691.50
- 0,6 mm; Uk.90 x 180 cm M² 80,129.50

D. BAHAN PENUTUP RANGKA PLAFOND


1 Plafond Enternit 4 mm M² 14,911.80
hardpleks 5 mm 120 x 240 Lbr 53,476.80
Asbes Semen 5 mm M² 19,282.50
Asbes Semen 3,5 mm M² 16,711.50
2 Gypsum; Ukuran 1,20 x 2,40 meter; Tbl.9mm Jayaboard M² 20,829.86
Elephant M² 18,151.74
Knauf M² 17,556.60
Star M² 17,556.60
Aplus M² 17,259.03
3 GRC; Ukuran 1,20 x 2,40 meter GRC / Versaboard Tbl. 4 mm M² 17,259.03
GRC / Versaboard Tbl. 6 mm M² 27,423.96
GRC / Versaboard Tbl. 9 mm M² 46,180.51
4 Cotton Plester 1 Roll=50 meter Roll 9,427.00
5 Cornice Coumpound A Plus Kg 3,213.75
6 List gypsum M' 9,855.50
7 Screw Gypsum Bh 72.85
Topping 8x2 cm Bh 94.27
Topping 8x3 cm Bh 119.98
Topping 8x4 cm Bh 134.55
Topping 8x5 cm Bh 171.40
Dinabolt Bh 2,571.00
Paku Tembak; P=25mm Bh 257.10
8 Rangka Plafond Main Tee; Panjang = 3,60 meter M' 5,951.39
Croos Tee; Panjang =1,20 meter M' 5,356.25
Wall Angel; Panjang = 3 meter M' 3,999.33
Wall Angel; 19x19mm; PN 212 EX Btg 11,998.00
Top Cross; Panjang = 3,60 m M' 9,980.00
Top Cross; Tbl.22mm Btg 35,928.01
Hollow Galvalum 2x400cm Btg 22,282.00
Hollow Galvalum 4x400cm Btg 29,995.00
Hollow Galvanis 32x320cm Btg 13,283.50
Hollow Galvanis 4x400 cm Btg 47,135.00
9 Sealent Lem Kaca Natural M² 26,995.50

E. BAHAN KAYU LAPIS


1 Triplek Biasa - 3 mm 120 x 240 cm Lbr 44,992.50
- 4 mm 120 x 240 cm Lbr 53,562.50
- 6 mm 120 x 240 cm Lbr 65,560.50
- 9 mm 120 x 240 cm Lbr 89,556.50
- 12 mm 120 x 240 cm Lbr 130,692.50

Page 81 BHN
NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)

- 15 mm 120 x 240 cm Lbr 158,116.50


- 18 mm 120 x 240 cm Lbr 182,112.50
2 Triplek Film/ Tego 1 Muka - 9 mm 120 x 240 cm Lbr 170,628.70
- 12 mm 120 x 240 cm Lbr 197,967.00
- 15 mm 120 x 240 cm Lbr 230,961.50
- 18 mm 120 x 240 cm Lbr 278,096.50
3 Triplek Melamin - 3 mm 120 x 240 Lbr 94,270.00
- 4 mm 120 x 240 Lbr 111,410.00
- 6 mm 120 x 240 Lbr 128,550.00
- 9 mm 120 x 240 Lbr 145,690.00

F. BAHAN LANTAI DAN PELAPIS DINDING


1 Asia Tile;Keramik Lantai Kamar Mandi Roxy Black 20x20 cm Kw1 M² 48,000.00
Galaxy Black 20x20 cm Kw1 M² 54,000.00
2 Asia Tile;Keramik Dinding Kamar Mandi Celonia Grey 20x40 M² 78,000.00
Kobin Papandayan 20x40 M² 74,400.00
3 Ganit Ex China - Vienna; Uk. 60x60 cm; Polish M² 100,000.00
- Vienna; Uk. 60x60 cm; Unpolish M² 116,666.67
4 Batu Alam Palimanan Rata Mesin M² 174,000.00
Rata Alam M² 114,000.00

G. BAHAN SALURAN AIR KOTOR / BERSIH


1 Grafel U 20 cm' M' 29,138.00
2 Grafel U 30 cm' M' 32,566.00
3 Grafel U 40 cm' M' 47,135.00
4 Buis Beton 20 cm ( 1 M' ) M' 42,164.40
5 Buis Beton 30 cm ( 1 M' ) M' 52,876.90
6 Buis Beton 40 cm ( 1 M' ) M' 69,331.30
7 Buis Beton 50 cm ( 1 M' ) Stk 80,815.10
8 Buis Beton 60 cm ( 1 M' ) Stk 112,181.30
9 Buis Beton 100 cm ( 0.50 M' ) Stk 256,928.60
10 Buis Beton 80 cm ( 0.50 M' ) Stk 255,814.50
11 BuisTanah 10 cm ( 0.50 M' ) Stk 8,227.20
12 BuisTanah 15 cm ( 0.50 M' ) Stk 10,883.90
13 BuisTanah 20 cm ( 0.50 M' ) Stk 14,397.60
14 BuisTanah 25 cm ( 0.50 M' ) Stk 19,539.60
15 Ijuk Kg 14,911.80

H. BAHAN LOGAM DAN BAHAN JADINYA


1 Besi Beton U-24 Rata-rata Kg 8,548.58
2 Besi Beton U-39 / U-32 Rata-rata Kg 12,327.95
3 Pagar BRC lengkap tiang ( Tanpa Pondasi ) M² 146,804.10
4 Bondek M² 158,545.00
5 Kawat Beton Kg 23,738.90
6 Kawat Duri Kg 54,419.50
7 Kawat Pengikat M' 857.00
8 Kawat Las Listrik M² 20,225.20
9 Wiremesh M8 Uk.2,1 x 5,4 Mtr Lbr 471,350.00
Wiremesh M8 Berat Per Lembar 61,79 Kg Kg 7,628.26
10 Wiremesh M6 Uk.2,1 x 5,4 Mtr Lbr 269,955.00
Wiremesh M6 Berat Per Lembar 34,76 Kg Kg 7,766.25
11 Plat Srip Ø 2 x 30 mm ( 6 m1 ) Btg 28,281.00
12 Plat Srip Ø 3 x 30 mm ( 6 m1 ) Btg 28,366.70
13 Plat Strip Btg 15,597.40
14 Besi Strip Kg 22,967.60
15 Handle Alumunium ( Tarikan Pintu Alumunium ) Bh 295,836.40
16 Kait Angin Alumunium Psng 89,556.50
17 Karet Asisoris Kusen / Pintu Alumunium M' 6,427.50
18 Jalusi Alluminium M' 29,995.00
19 Sunscreen Almunium M² 325,831.40
20 Seng Plat BJLS - 30 60 cm ( 100 m1 ) Roll 1,355,345.50
- 30 90 cm ( 100 m1 ) Roll 1,782,645.70
21 Besi Hollow (20 x 40 x 2) mm (600cm) Btg 16,368.70
(40 x 40 x 2,3) mm (600cm) Btg 19,588.16

I. BAHAN KACA

Page 82 BHN
NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)

1 Kaca Polos 2 mm ( ASAHI ) M² 59,133.00


2 Kaca Polos 3 mm ( ASAHI ) M² 74,901.80
3 Kaca Polos 5 mm ( ASAHI ) M² 95,127.00
4 Kaca Polos 8 mm ( ASAHI ) M² 156,916.70
5 Kaca Rayband 5 mm ( ASAHI ) M² 127,435.90
6 Kaca Rayband 8 mm ( ASAHI ) M² 277,153.80
7 Kaca Rayband 12 mm ( ASAHI ) M² 537,339.00
8 Kaca cermin - 5 mm M² 128,978.50
- 6 mm M² 159,744.80
- 8 mm M² 200,795.10
9 Glass Block - DN 20 x 20 ( Kedawung ) Bh 18,854.00
DN 20 x 20 Ex LN Bh 107,724.90
10 Sealant Kg 181,512.60

J. BAHAN PAKU DAN MUR BAUT


1 Paku 1/2" s/d 2" Kg 20,396.60
Bh 203.97
2 Paku 2" s/d 5" Kg 20,053.80
3 Paku 8 cm s/d 15 cm Kg 17,140.00
4 Paku Beton 2 cm s/d 5 cm Bh 1,371.20
5 Paku Kait Lengkap Bh 771.30
6 Paku Cacing Kg 48,934.70
7 Besi Beugel Kuda - Kuda Kg 18,596.90
8 Duk Angker Bh 6,427.50
9 Angker Mur Baut dia. 19 / Panjang 60 cm Bh 61,532.60
10 Mur Baut HTB dia. 19 s/d 16 ( 5 cm ) Bh 13,626.30
11 Mur Baut Biasa dia. 19 s/d 16 ( 5 cm ) Bh 7,970.10
12 Piser dia.12 s/d 20 cm Bh 4,542.10
13 Paku skrup 3" Bh 685.60
14 Ramset / Dinabolt Bh 6,170.40
15 Baut Besar Bh 514.20
16 Baut Kecil Bh 257.10
17 Paku GRC Kg 29,995.00
18 Paku gypsum Kg 14,997.50
19 Sekrup fixer Btg 214.25
20 Kawat Nyamuk Btg 23,996.00
21 Self Drilling Screw dia 6x20 mm (trust screw) Bh 141.41
22 Self Drilling Screw dia 4x16 mm (roof bottom ) Bh 235.68

K. BAHAN PERPIPAAN
1 Besi Pipa Hitam 1" t = 2 mm Btg 147,661.10
2 Besi Pipa Hitam 2" t = 2 mm Btg 195,310.30
3 Besi Pipa Hitam 3" t = 2mm Btg 313,490.60
4 Besi Pipa Hitam 4" t = 2 mm Btg 491,146.70
5 Besi Pipa Hitam 6" t = 2 mm Btg 661,946.80
6 Pipa GIP Medium A 1/2" ( 6 m1 ) Btg 93,498.70
7 Pipa GIP Medium A 3/4" ( 6 m1 ) Btg 136,605.80
8 Pipa GIP Medium A 1" ( 6 m1 ) Btg 155,545.50
9 Pipa GIP Medium A 1 1/4" ( 6 m1 ) Btg 222,220.10
10 Pipa GIP Medium A 1 1/2" ( 6 m1 ) Btg 240,388.50
11 Pipa GIP Medium A 1 3/4" ( 6 m1 ) Btg 279,724.80
12 Pipa GIP Medium A 2" ( 6 m1 ) Btg 400,561.80
13 Pipa GIP Medium A 2 1/2" ( 6 m1 ) Btg 575,989.70
14 Pipa GIP Medium A 3" ( 6 m1 ) Btg 728,364.30
15 Pipa GIP Medium A 4" ( 6 m1 ) Btg 788,697.10
16 Macam2 Sambungan GIP 1/2" Bh 5,399.10
17 Macam2 Sambungan GIP 3/4" Bh 7,370.20
18 Macam2 Sambungan GIP 1" Bh 14,311.90
19 Macam2 Sambungan GIP 1 1/4" Bh 16,968.60
20 Macam2 Sambungan GIP 1 1/2" Bh 17,739.90
21 Macam2 Sambungan GIP 1 3/4" Bh 19,453.90
22 Macam2 Sambungan GIP 2" Bh 43,878.40
23 Macam2 Sambungan GIP 2 1/2" Bh 51,762.80
24 Macam2 Sambungan GIP 3" Bh 65,046.30
25 Macam2 Sambungan GIP 4" Bh 101,640.20
26 Pipa PVC RUCIKA type AW 1/2" Btg 34,365.70

Page 83 BHN
NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)

27 Pipa PVC RUCIKA type AW 3/4" Btg 44,735.40


28 Pipa PVC RUCIKA type AW 1" Btg 54,162.40
29 Pipa PVC RUCIKA type AW 1 1/4" Btg 68,474.30
30 Pipa PVC RUCIKA type AW 1 1/2" Btg 90,756.30
31 Pipa PVC RUCIKA type AW 2" Btg 94,869.90
32 Pipa PVC RUCIKA type AW 2 1/2" Btg 143,204.70
33 Pipa PVC RUCIKA type AW 3" Btg 175,770.70
34 Pipa PVC RUCIKA type AW 4" Btg 298,150.30
35 Pipa PVC RUCIKA type AW 6" Btg 548,480.00
36 Pipa PVC RUCIKA type AW 8" Btg 701,283.10
37 Pipa PVC MASPION ABU ( AW ) 1/2" Btg 19,282.50
38 Pipa PVC MASPION ABU ( AW ) 3/4" Btg 23,824.60
39 Pipa PVC MASPION ABU ( AW ) 1" Btg 34,708.50
40 Pipa PVC MASPION ABU ( AW ) 1 1/4" Btg 50,134.50
41 Pipa PVC MASPION ABU ( AW ) 1 1/2" Btg 51,591.40
42 Pipa PVC MASPION ABU ( AW ) 2" Btg 64,960.60
43 Pipa PVC MASPION ABU ( AW ) 2 1/2" Btg 108,239.10
44 Pipa PVC MASPION ABU ( AW ) 3" Btg 124,864.90
45 Pipa PVC MASPION ABU ( AW ) 4" Btg 220,077.60
46 Macam2 Sambungan Paralon 1/2" Bh 3,770.80
47 Macam2 Sambungan Paralon 3/4" Bh 4,027.90
48 Macam2 Sambungan Paralon 1" Bh 4,199.30
49 Macam2 Sambungan Paralon 1 1/4" Bh 6,170.40
50 Macam2 Sambungan Paralon 1 1/2" Bh 8,141.50
51 Macam2 Sambungan Paralon 1 3/4" Bh 11,569.50
52 Macam2 Sambungan Paralon 2" Bh 13,540.60
53 Macam2 Sambungan Paralon 2 1/2" Bh 22,624.80
54 Macam2 Sambungan Paralon 3" Bh 25,452.90
55 Macam2 Sambungan Paralon 4" Bh 29,138.00
56 Sambungan Pipa PVC Jenis AW 4" TY Bh 77,044.30
57 Lem Paralon Tube 8,655.70
58 Solatip Ledeng Roll 3,599.40
59 Pipa PVC 4" Berlobang Jenis AW M' 31,451.90

L. BAHAN SANITAIR
1 Stop Kran 3/4" KIT Bh 89,042.30
2 Stop Kran 1" KIT Bh 106,439.40
3 Stop Kran 1 1/2" KIT Bh 178,256.00
4 Stop Kran 2" KIT Bh 229,590.30
5 Stop Kran 2 1/2" KIT Bh 611,212.40
6 Stop Kran 3" KIT Bh 711,567.10
7 Check Valve 1/2" Bh 74,044.80
8 Double Neple 1/2" Bh 27,766.80
9 Water Mur 1/2" Bh 34,451.40
10 Perlengkapan TOTO Closet Duduk TOTO CW 420 J Unit 1,345,490.00
Closet Duduk CW637J/SW637JP Unit 2,571,000.00
CE-7 (Closet Jongkok) Unit 329,088.00
CE-6 (Closet Jongkok) Unit 538,196.00
CE9/TV150NWV12J (Closet Jongkok Flush) Unit 3,359,440.00
Wastafel LW811CJ Unit 1,414,050.00
Wastafel LW574J Unit 1,371,200.00
Urinoir U57 Unit 2,511,010.00
Partisi Urinoir A100 Unit 1,396,910.00
Kran Air Tembok TX108LDN Unit 925,560.00
Kran Air Tembok TX115LP Unit 874,140.00
Kran Flexible TX609 K Unit 468,779.00
Kran Flexible T320AR13V7N Unit 425,072.00
Kran Air Tembok TX109LD Unit 655,605.00
Kran Air Tembok TX109LRR Unit 712,167.00
Shower Spray THX20SMCRB Unit 278,096.50
Shower Mandi TX402SP Unit 500,573.70
Paper Holder TX703AQV1 Unit 593,044.00
Tempat Sabun S186 Unit 283,667.00
Tempat Sabun S6NV1 Unit 124,265.00
Gantungan TX724AC Unit 1,276,930.00
TOTO TX1DBV1 Floor Drain Unit 259,773.84

Page 84 BHN
NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)

11 Kitchen Zink Stainless - 1 Lubang Bh 167,115.00


12 Bak Air / Bak Mandi Fiber Oval Uk 55x55x60 Cm (120 Liter ) Unit 557,050.00
13 Kran Flexible - Flexible Unit 82,229.15
- Besi Unit 64,917.75
14 Spray Closet - Onda Unit 89,556.50
15 Shower Spray - Onda Unit 127,264.50
16 Flour Drain - Onda Unit 82,957.60
17 Talang UPVC Unit 82,229.15

M. BAHAN PENUTUP ATAP


1 Atap Seng Gelombang 270 cm x 105 cm x 4mm Lbr 62,818.10
240 cm x 105 cm x 4mm Lbr 56,476.30
210 cm x 105 cm x 4mm Lbr 50,134.50
150 cm x 105 cm x 4mm Lbr 36,251.10
150 cm x 102 cm x 5mm Lbr 67,274.50
180 cm x 102 cm x 5mm Lbr 83,300.40
300 cm x 105 cm x 4 mm Lbr 68,560.00
2 Atap Bitumen - Underlayer Geotextile M² 61,704.00
Per Lbr (33x100 cm); L=0,144M²; 1M²=7 Lbr - Type CT-3 Shingle;UK.0,33*1 Mtr M² 18,180.64
Per Lbr (33x100 cm); L=0,144M²; 1M²=7 Lbr - Sirap Iko Ex.Canada;UK.0,33*1 Mtr M² 24,914.21
- Baut JF 4x10mm M² 49.02
- Lem Bitumen; UK.5cm x 10 Meter M' 975.69
- Sisalation / alluminium foil M' 12,855.00
Per Lbr (34x100 cm); L=0,145M²; 1M²=7 Lbr - Shingle Bitumen Bardoline Pack 530,088.78
- Shingle Bitumen Bardoline Pcs 25,242.32
- Underlayer - Ondubar Roll 1,168,690.90
3 Atap Genteng Plentong - Pres Bakar KW I Bh 1,628.30
- Pres Molen Oven KW I Bh 2,313.90
- Pres Molen Oven Jatiwangi Bh 1,971.10
4 Genteng - Metal ( Rainbow Roof ) M² 174,056.70
- Metal Hana M² 148,003.90
- Spandek 0,35 mm M² 44,092.65
5 Nok Atas Metal - Rainbow Roof Lbr 118,694.50
- Hana Lbr 69,331.30
- Pingir Metal ( Rainbow Roof ) Lbr 90,242.10
- Pingir Metal Hana Lbr 86,385.60
6 Wall Flasing - Flasing ( Rainbow Roof ) Lbr 71,902.30
- Hana Lbr 76,015.90
7 Bubungan - Genteng Plentong Bh 5,142.00
- Genteng pres Bulat Ex Jatiwangi Bh 6,427.50
8 Nok - Stel Gelombang Bh 6,427.50
- Stel Gelombang Lbr 32,651.70
- Atap Seng Lbr 32,137.50
9 Trusses - Taso-75 t=0.8 Rangka Utama M' 12,255.10
- Taso-100 t=0.5 Rangka Utama M' 42,421.50
10 - Reng; R33-45 M' 7,698.72
11 Seng BJLS - 0,2mmx1,8m x 80 cm M' 22,853.33
- 0,3mmx1,8m x 80 cm M' 32,375.56

N. BAHAN MEKANIKAL
1 Jockey Pump kap. 80 gln/menit 100 m1 ( 18.6 kW ) Unit 61,186,714.80
2 Electrical Pump kap. 750 gln/menit 120 m1 ( 90 kW ) Unit 185,419,577.30
3 Diesel Pump kap. 750 gln/menit 120 M' (105 kW) Unit 507,041,564.70
4 Presure Tank kap. 500 liter lengkap Unit 31,706,686.10
5 Hydran Box dlm Gedung ( Lengkap ) Unit 5,874,220.80
6 Fire House 1.5 x 30 m + nose Unit 4,170,247.70
7 Exhaust Fan Panasonic Tipe Wall Seri FV-10EGSI Unit 358,140.30
Tipe Wall Seri FV-25RUN5 Unit 305,949.00
Tipe Ceiling Seri FV-25TGU5 Unit 232,431.26
8 AC Split 3 PK Setara Panasonic CS-PU24UKP 2 1/2 PK Split Standar Inverter R32 Unit 11,788,035.00
9 AC Split 2 PK Setara Panasonic CS-PN18TKP Split Wall Mounted Std. R32 Unit 5,656,200.00
10 AC Split 1 PK Setara Panasonic CS-PN9TKJ Split Wall Mounted Std. R32 Unit 3,582,260.00
11 Mesin AC Split DAIKIN ( Indoor / Outdoor Unit ) 1 BTU 3,599,400.00
12 Tangki Air Profil Tank Kapasitas 550 Ltr Set 1,928,250.00
Kapasitas 1100 Ltr Set 2,828,100.00
Kapasitas 1500 Ltr Set 3,128,050.00

Page 85 BHN
NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)

Kapasitas 2000 Ltr Set 4,242,150.00


13 Pompa Air Grundfos Pompa Jet Pump JD Basic 5 Unit 4,656,938.00
CMV3-9-Pompa Dorong Unit 6,716,309.00

O. BAHAN ELEKTRIKAL
1 Kabel NYM 1 x 1.5 Supreme ( 1 rol = 50 m' ) Roll 88,013.90
2 Kabel NYM 1 x 2.5 Supreme ( 1 rol = 50 m' ) Roll 130,006.90
3 Kabel NYM 2 x 1.5 Supreme ( 1 rol = 50 m' ) Roll 257,100.00
4 Kabel NYM 2 x 2.5 Supreme ( 1 rol = 50 m' ) Roll 748,161.00
5 Kabel NYM 3 x 1.5 Supreme ( 1 rol = 50 m' ) Roll 323,946.00
6 Kabel NYM 3 x 2.5 Supreme ( 1 rol = 50 m' ) Roll 1,006,118.00
7 Kabel NYM 4 x 2.5 Supreme ( 1 rol = 50 m' ) Roll 1,325,779.00
8 MCB 1 PAS Bh 47,220.70
9 MCB 3 PAS Bh 90,842.00
10 Saklar Schneider - 1 Gang Bh 23,567.50
- 2 Gang Bh 32,137.50
- 3 Gang Bh 38,136.50
11 Stop Kontak Schneider Bh 44,135.50
12 Lampu Phillips - Essensial 9 Watt Bh 23,567.50
- Essensial 18 Watt Bh 30,423.50
- Essensial 23 Watt Bh 39,850.50
13 Down Light + SL 25 W Bh 263,013.30
14 Lampu SL Philip 25 W Bh 263,013.30
15 Lampu Sirkel TL 20 W Lengkap Bh 58,190.30
16 Lampu Mercuri 80 W Bh 126,321.80
17 Lampu Taman + Tiang + Lampu 1 Buah Bh 263,613.20
18 Lampu Baret 30 cm + Neon Bh 189,996.90
19 Lampu Neon Arcrilik 2 x 40 W Lengkap Bh 632,466.00
20 Jarum Penangkal Petir 16 Bh 86,985.50
21 Kawat BC ( Tembaga ) M' 9,855.50
22 Pentanahan Penangkal Petir Ttk 363,110.90
23 Pentanahan Panel Ttk 253,757.70
24 Pipa Listrik Btg 13,283.50
25 Pipa Flexible M' 4,285.00
26 Klem Pipa Btg 428.50
27 Klem Kabel Dus 29,995.00
28 Fitting Down Light Btg 29,566.50
29 T-Dus Bh 4,285.00
30 Box Sikring - 2 Group Bh 21,425.00
31 - 4 Group Bh 29,995.00
- 6 Group Bh 47,135.00

P. BAHAN ALAT PENGANTUNG DAN KUNCI


1 Dekkon LHR 8536 CF Mortise Set 787,154.50
2 Dekkon LHR 81033 MAB Mortise Set 556,193.00
3 Dekkson LHTR 0820 + Body Mortise IL DL 8485  Cylinder TC DL 60 MM SN Set 362,939.50
4 Dekkson KCBL 8587 ET SSS Kunci Pintu Bulat Putar Dekson KCBL8587 Set 107,467.80
5 Dekkson Lever Handle Clasic L.H.R 10693 CF Set 282,810.00
LHTR 0017 Set 155,545.50
Dekkson LS T6300 ET SSS (Full Set) Set 193,253.50
6 Grendel Tanam / Flush Bolt Dekkson FB 040 SSS (8" + 12" & SUS 304) Set 244,245.00
FB 050 SSS (12" + 24" & SUS 304) Set 320,518.00
7 Dekkson; Door Holder DCL 300 NHO Non Hold Open Set 226,248.00
DCL 105 DCL Set 617,468.50
8 Dekkson Engsel Ecoline 5x3x3MM 4BB SSS Bh 43,364.20
Ecoline 4x3x2MM 2BB SSS Bh 25,924.25
Ecoline 3x3x2MM 2BB SSS Bh 25,924.25
Salon ES SL 9" CP Bh 21,210.75
Salon ES SL 5" CP Bh 16,497.25
9 Dekkson Kait Angin WS 001 10" SSS Bh 58,447.40
WS 001 8" SSS Bh 53,733.90
10 Dekkson Penahan Magnet DS 009 SS Bh 56,562.00
11 Dekkson Kunci Slot Grendel Jendela CWH 103Z  Bh 44,778.25
12 Dekkson Kait Hak Angin SQ001 001 8" SSS Bh 53,733.90
WS 001 10" SSS Bh 58,447.40
13 Dekkson Rambuncis CWH 103 Z SN Bh 44,306.90

Page 86 BHN
NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)

14 Dekkson Set Pintu Sliding Sliding Rail Type D6 SR 8901 300 cm Bh 848,430.00
Sliding Rail Type D4 SR 8901 200 cm Bh 315,804.50
15 Dekkson Slide &Fold Aksesoris 1.WH 9105-L Galv/Roda Atas Pinggir Set 344,886.80
2.WH 9106-RD 4 Galv/Roda Atas Tgh Set 212,107.50
3.HN 8306 Galv (Engel Tengah) Set 108,410.50
4.WH 8205 (Roda Bawah Tengah) Set 107,467.80
5.WH 8206 (Roda Bawah Pinggir) Set 80,129.50
6.4x3x2MM 2BB SSS (Engl. Kupu) Set 70,702.50
7.FBP 8" SS (Grendel Tanam Plat) Set 139,990.95
8.BB 9204 (Grendel Bawah Biasa) Set 87,199.75
9.TR 9129 (Rel Atas); L= 2,9 M' Set 315,804.50
10.TR 9244 (Rel Bawah); L= 3 Mtr Set 230,961.50
11.BR 9100 GALV (Breket Samping) Set 69,486.42
12.PH D855 SSS (Pull Handle) Set 227,190.70
13.MTS DL 8585 SSS (Mortise) Set 164,972.50
14.CYL DC DL 60 MM SN Set 80,129.50
15.ESCN 855 SSS (Dop Handle) Set 32,994.50
16.WH 8144-RD4 (Roda Atas Tngh) Set 259,242.50
17.BF 3/8X2,5" (Braket &Fischer) Set 16,968.60
16 Dekkson Pull Handle PH D268 Bh 2,073,940.00
PH D351 Bh 518,485.00
17 Dekkson Knob Kunci Silinder CYL DL DL 60MM 10 MK SN Set 116,894.80
CYL DL DL 60MM 8 MK SN Set 80,129.50
18 Dekkson Grendel Pintu; DB D02 3" SS Bh 53,733.90
Jendela; SK. 028 SQ SN Bh 70,231.15
19 Kunci Lemari Espagnolete Huben HL 690 Bh 122,551.00

Q. BAHAN PENGISAP AIR SUMUR DALAM


1 Pompa Kodok Unit 147,918.20
2 Pompa Dragon Tegal Unit 208,936.60
3 Pompa Dragon Asli Unit 615,754.50
4 Mesin Pompa Air 100 W - Sanyo Unit 942,871.40
5 Mesin Pompa Air 150 W - Sanyo Unit 1,620,329.90
6 Pompa Zet Pump 250 W - Sanyo Unit 4,252,005.50
7 Pompa Zet Pump 450 W - Sanyo Unit 6,751,446.00
8 Pompa Submersible kap. 150 liter / menit 3 KW Unit 23,268,578.40
9 Gear Pump Kap. 60 liter / menit Unit 13,457,213.90
10 Deep Well dengan kelengkapannya kap. 150 liter / menit Unit 147,448,992.50
11 Hand Oil Pump Unit 4,452,372.10

R. BAHAN PENAMPUNG AIR


1 Tangki Air Fiber Glass 0.5 m3 ( Excel ) Bh 1,004,832.50
2 Tangki Air Fiber Glass 1 m3 ( Excel ) Bh 1,128,154.80
3 Tangki Air Fiber Glass 2 m3 ( Excel ) Bh 1,674,749.40
4 Bak KM Fiber 60 x 60 Bh 218,792.10
5 Bak Taraso WC 40 x 40 Bh 101,554.50
6 Bak KM Taraso 60 x 60 Bh 138,062.70

S. ALAT TUKANG
1 Palu 0.5 kg Bh 33,680.10
2 Cangkul Bh 38,136.50
3 Singkup Bh 35,479.80
4 Sekrop Bh 42,935.70
5 Pengki Bh 19,111.10
6 Linggis Bh 35,736.90
7 Rool Meter 30 meter ( Bahan Plastik ) Bh 86,557.00
8 Rool Meter 5 meter ( Bahan Besi ) Bh 32,394.60
9 Selang Plastik untuk Water Pas dia. 0.5 cm M' 1,371.20
10 Water Pas Alumunium 60 cm Bh 75,587.40
11 Sewa Scafolding Bh 1,714.00
12 Pahat Bh 47,135.00

T. BAHAN BAKAR DAN PELUMAS


1 Minyak Tanah Ltr 15,426.00
2 Kayu Bakar dari Kayu Karet M³ 129,492.70
3 Bahan Bakar Residu Ltr 24,368.80

Page 87 BHN
NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)

4 Minyak Solar Ltr 6,127.55


5 Bensin Premium Ltr 6,684.60
6 Plus Oil Ltr 2,828.10
7 Oil Mesran 40 SAE Ltr 47,135.00
8 Elpiji / botol @15 Kg Kg 89,642.20
9 Asitilin / Botol 15,10 Kg Kg 76,187.30
10 Angin ( O2 ) / botol Btl 56,904.80
11 Karbit Kg 16,625.80
12 Minyak Bekisting Ltr 26,138.50
13 Rapidrant Glng 13,454.90
14 Soda Api Kg 30,509.20
15 Sabun Bh 2,056.80
16 Arang Kayu Kg 9,512.70
17 Kawat Las Bh 1,199.80
18 Resin Ltr 47,135.00
19 Mata Grenda Batu Bosch 4" Bh 16,283.00
Biasa 4" Bh 5,142.00

U. BIDANG PERTAMANAN
1 Aglonema Btg 42,850.00
2 Bambu krisik/jepang Btg 42,850.00
3 Furadan Kg 20,568.00
4 Kompos/pupuk kandang Krng 21,425.00
5 Matoa (2 m) Btg 34,280.00
6 Palm (botol, ekor tupai, putri, dll) tinggi 2 m Btg 85,700.00
7 Philo Btg 64,275.00
8 Pohon pelindung (angsana, mahoni, kamboja dll) tinggi 2m Btg 21,425.00
9 Pohon perdu (kaca piring, puring, mawar, melati, dll) Btg 8,570.00
10 Rumput gajah mini M² 12,855.00
11 Plastik Mulsa; Lebar 1,20 M' M² 2,142.50

harga sudah termasuk PPN dan keuntungan

Page 88 BHN
DAFTAR ANALISA HARGA SATUAN PEKERJAAN AHSP
Periode : Tahun Anggaran 2019
Klasifikasi : Menengah
Proyek : Pembangunan Kost-Kostan (Hostel)
Lokasi : Jln. Pembangunan
Wilayah : Deli Serdang

HARGA
NO URAIAN PEKERJAAN
(Rp)
A. PEKERJAAN PERSIAPAN
1 1 M' Pagar Sementara Dari Kayu Tinggi 2 m 249,119.00
2 1 M' Pagar Sementara Seng Gelombang Tinggi 2 m 285,490.00
3 1 M' Pagar Sementara Kawat Duri Tinggi 1,80 m 207,140.00
4 1 M' Pengukuran Dan Pasang Bouwplank 38,181.74
5 1 M² Pembuatan Kantor Sementara dgn Lantai Diplester 869,846.00
6 1 M² Pembuatan Gudang Semen dan Alat-alat 731,505.08
7 1 M² Pembuatan Bedeng Buruh 679,809.00
8 1 M² Membersihkan Lapangan dan Perataan 6,300.00
9 1 M² Pembuatan Jalan Sementara 89,061.00
10 1 M3 Bongkaran Beton Bertulang 569,997.00
11 1 M3 Bongkaran Dinding Tembok Bata Merah 841,496.00

B. PEKERJAAN TANAH
1 1 M³ Galian Tanah Biasa sedalam 1 m 36,000.00
2 1 M³ Galian Tanah Biasa Sedalam 2 m 47,286.00
3 1 M³ Galian Tanah Biasa Sedalam 3 m 66,105.00
4 1 M³ Galian Tanah Keras Sedalam 1 m 56,205.00
5 1 M³ Galian Tanah Lumpur Sedalam 1 m 74,133.00
6 1 M² Pekerjaan Stripping Setinggi 10 cm 4,500.00
7 1 M³ Pembuangan Tanah sejauh 150 m 46,296.00
8 1 M³ Urugan Kembali 17,262.00
9 1 M³ Pemadatan Tanah 45,000.00
10 1 M³ Urugaan Pasir 84,999.00
11 1 M² Pemasangan Lapisan Ijuk Tebal 10 cm 36,125.00
12 1 M³ Urugan Sirtu 231,779.00
13 1 M³ Urugan Tanah Pilihan 115,056.00
14 1 M² Pembuatan jalan sementara, tebal 25 cm 150,778.44

C. PEKERJAAN PONDASI
1 1 M³ Pasanag Pondasi batu Kali adk 1pc : 3 ps 694,001.00
2 1 M³ Pasang Pondasi Batu kali adk 1pc : 4ps 650,224.00
3 1 M³ Pasang Pondasi Batu kali adk 1pc : 5ps 619,891.00
4 1 M³ Pasang Pondasi Batu Kosong (aanstamping) 350,701.00

D. PEKERJAAN BETON
1 1 M³ Membuat Beton Cor ; Spesi 1Pc:3Psr:5Krkl 837,802.00
2 1 M³ Membuat Beton Cor Mutu K-125 (fc'=9.8 Mpa), Slump (12+2),w/c=0,78 871,046.00
3 1 M³ Membuat Beton Cor Mutu K-150 (fc'=12.2 Mpa), Slump (12+2),w/c=0,72 896,579.00
4 1 M³ Membuat Beton Cor Mutu K-175 (fc'=14.5 Mpa), Slump (12+2),w/c=0,66 927,397.00
5 1 M³ Membuat Beton Cor Mutu K-200 (fc'=16.9 Mpa), Slump (12+2),w/c=0,61 955,865.00
6 1 M³ Membuat Beton Cor Mutu K-225 (fc'=19.3 Mpa), Slump (12+2),w/c=0,58 978,666.00
7 1 M³ Membuat Beton Cor Mutu K-250 (fc'=21.7 Mpa), Slump (12+2),w/c=0,56 995,139.00
8 1 M³ Membuat Beton Cor Mutu K-275 (fc'=26.4 Mpa), Slump (12+2),w/c=0,53 1,014,486.00
9 1 M³ Membuat Beton Cor Mutu K-300 (fc'=26.4 Mpa), Slump (12+2),w/c=0,52 1,024,751.00
10 1 M³ Membuat Tiang Pancang Beton Prestressed 1,000,581.00
11 1 Kg Pembesian Dengan Besi Polos/ulir 11,495.00
12 1 Kg Memasang Jaring Kawat Baja 13,940.00
13 1 M² Pasang Bekesting Untuk Pondasi 71,227.00
14 1 M² Pasang Bekisting Untuk Sloof 75,297.00
15 1 M² Pasang Bekesting Untuk Kolom 173,827.00
16 1 M² Pasang Bekesting Untuk Balok 176,542.00
17 1 M² Pasang Bekesting Untuk Lantai 194,395.00
18 1 M² Pasang Bekesting Untuk Dinding 195,012.00

Page 89 HARSAT
HARGA
NO URAIAN PEKERJAAN
(Rp)
19 1 M² Pasang Bekesting Untuk Tangga 163,732.00

E. PEKERJAAN PASANGAN DINDING


1 1 M² Pasang Bata Merah Tebal 1 Bata, 1pc : 3ps 207,675.00
2 1 M² Pasang Bata Merah Tebal 1 Bata, 1pc : 4ps 200,080.00
3 1 M² Pasang Bata Expose Brick; Tebal 1/2 Bata, Spesi 1pc : 2ps 219,522.00
4 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 3ps 178,289.00
5 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 4ps 175,114.00
6 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 5ps 173,111.00
7 1 M2 Pasang Dinding Roster Beton 20 x 20 adk 1pc : 3ps 4,870.00
8 1 M2 Pasang Dinding Roster Beton 20 x 20 adk 1pc : 4ps 5,200.00
9 1 M2 Pasang Dinding Roster/terawng (12 x 11 x 24) cm 5,200.00
10 1 M2 Pasang Dinding Batako Besar Pres uk. 8x20x30 adk. 1pc:4ps 5,530.00

F. PEKERJAAN PLESTERAN DAN SIARAN


1. 1 M² Plesteran adk. 1pc : 2ps Tebal 15 mm 47,611.00
2. 1 M² Plesteran adk. 1pc : 3ps Tebal 15 mm 44,841.00
3 1 M² Plesteran adk. 1pc : 4ps Tebal 15 mm 43,075.00
4 1 M² Plesteran Beton adk. 1pc : 2ps Tebal 15 mm 57,167.00
5 1 M² Plesteran Beton adk. 1pc : 3ps Tebal 15 mm 54,774.00
6 1 M² Plesteran Skoning adk. 1pc : 2ps, tebal 10mm 56,041.00
7 1 M² Acian Plesteran 18,459.00
8 1 M² Plesteran Siar adk. 1pc : 2ps batu belah 49,968.00
9 1 M² Plesteran Siar adk. 1pc : 2ps dinding bata merah 26,935.00
10 1 M' Pengecapan Bidang Plesteran Lebar 15-30 cm 30,627.00
11 1 M' Pengecapan Bidang Plesteran Lebar 1-15 cm 42,069.00

G. PEKERJAAN ATAP
1 1 M² Pasang Rangka Atap Baja Ringan 96,384.01
2 1 M² Pasang Atap Genteng Metal 71,227.00
3 1 M¹ Pasang Nok Genteng Metal 171,894.00
4 1 M¹ Pasang Nok Genteng Metal 171,894.00
5 1 M' Pasang Lisplank GRC ukuran 30 cm 39,685.00
6 1 M' Pasang Lisplank Cutting GRC 42,280.00
7 1 M' Seng BJLS 115,680.00

H. PEKERJAAN LANGIT-LANGIT
1 1 M² Pekerjaan Rangka Gypsum Board 51,657.00
2 1 M² Langit-langit Gypsum Board , tebal 9 mm 43,538.00
3 1 M¹ List Langit-langit Gypsum 10 cm 21,135.00
4 1 M¹ List Langit-langit Kayu 1/4 cm 11,549.00

I. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DINDING


1 1 M² Lantai Keramik Roxy Black 20x20 cm Kw1 122,429.00
2 1 M² Lantai Keramik Galaxy Black 20x20 cm Kw1 128,729.00
3 1 M² Lantai Granit Ex China; Uk. 60x60 cm 153,929.00
4 1 M² Dinding Keramik; Uk. 20x40 150,149.00
5 1 M² Pekerjaan Lantai Granit Ex. China; Uk. 60x60 cm 255,742.00
6 1 M² Paving block natural 8 cm 168,676.00
7 1 M² Paving block natural 6 cm 167,210.00
8 1 M² Grass Block Lubang 5, Tebal 8 cm 158,545.00
9 1 M² Grass Block Lubang 8, Tebal 6 cm 242,286.00
10 1 M² Grass Block Lubang 8, Tebal 8 cm 329,645.00
11 1 M² Dinding Batu Alam Palimanan Rata Alam 273,706.00

J. ANALISA HARGA SATUAN PEKERJAAN KAYU


1 1 M3 Kusen Pintu & jendela kayu Kamper Samarinda 10,701,397.00
2 1 M3 Kusen Pintu & jendela kayu Kamper Medan/Kruing 7,676,770.00
3 1 M3 Kusen Pintu & jendela kayu Borneo Super 8,062,452.00
4 1 M2 Pintu Panel Kayu Kamper Samarinda 681,716.00
5 1 M2 Pintu Panel Kayu Kamper Medan/Kruing 385,753.00
6 1 M2 Pintu & Jendela Kaca Kayu Kamper Medan 478,550.00

Page 90 HARSAT
HARGA
NO URAIAN PEKERJAAN
(Rp)
7 1 M2 Pintu & Jendela Jalusi Kayu Kamper Medan 797,327.72
8 1 M' Lisplang uk (3x20)cm, Kayu Kamper Medan 33,493.00
9 1 M¹ List Kayu Profil 5 cm 12,031.71

K. ANALISA HARGA SATUAN PEKERJAAN KUNCI & KACA


1. 1 Bh Pasang Kunci Tanam Classic Klas 1 847,005.00
2. 1 Bh Pasang Kunci Tanam Classic Klas 2 253,104.00
3. 1 Bh Lever Handle Dekkson L.H.R 10693 CF 316,380.00
4. 1 Bh Lever Handle Dekkson LHTR 0017 189,116.00
5. 1 Buah Pasang Kunci Tanam Kamar Mandi 167,318.00
6. 1 Buah Pasang Engsel 5" 58,327.00
7. 1 Buah Pasang Engsel 4" 40,887.00
8. 1 Buah Pasang Engsel 3" 40,887.00
9. 1 Buah Pasang Engsel Tanam 8" 268,185.00
10. 1 Buah Pasang Engsel Tanam 12" 344,458.00
11. 1 Buah Pasang Kait Angin 8" 71,689.00
12. 1 Buah Pasang Kait Angin 10" 76,402.00
13. 1 Buah Pasang Engsel Saloon 9" 39,166.00
14. 1 Buah Pasang Engsel Saloon 5" 34,452.00
15. 1 Buah Pasang Door Closer (Hold Open) 689,424.00
16. 1 Buah Pasang Door Closer (Non Hold Open) 286,323.00
17. 1 Buah Pasang Pegangan Pintu / Door Stopper 128,382.00
18. 1 Bh Pasang Engsel Tanam (8" + 12" & SUS 304) 304,095.00
19. 1 Bh Pasang Engsel Tanam (12" + 24" & SUS 304) 383,361.00
20. 1 Bh Pasang Rambuncis 56,277.00
21. 1 Bh Pasang Engsel Saloon/Jungkit 5" 28,467.00
22. 1 Bh Pasang Engsel Saloon/Jungkit 9" 33,181.00
24. 1 M² Pasang Kaca , tebal 3 mm 101,629.00
25. 1 M² Pasang Kaca , tebal 5 mm 123,882.00
27 1 Bh Pasang Pull Handle 312,487.00

L. ANALISA HARGA SATUAN PEKERJAAN PEKERJAAN SANITASI


1 1 Buah Closet jongkok Toto 553,965.00
2 1 Buah Closet jongkok Toto Flush 3,800,767.00
3 1 Buah Closet Duduk Toto 1,786,817.00
4 1 Buah Urinoir 2,971,328.00
5 1 Buah Wastafel 1,873,525.00
6 1 Buah bak Mandi Fibreglass Volume 0,30 m3 1,167,799.00
7 1 M' Saluran Air Limbah Buis beton d = 30 cm - 60 cm 151,847.00
8 1 M' Saluran Air Limbah Gravelbeton d = 20 cm - 40 cm 129,505.00
9 1 Buah Bak Kontrol Pas Bata Merah Uk (60 x 60) cm 615,083.00
10 1 Buah Bak Kontrol Pas Bata Merah Uk (30 x 30) cm 502,149.00
11 1 M' Pipa PVC Ø 1/2" (AW) 19,958.00
12 1 M' Pipa PVC Ø 1" (AW) 28,879.00
13 1 M' Pipa PVC Ø 11/2" (AW) 41,457.00
14 1 M' Pipa PVC Ø 2" (AW) 42,588.00
15 1 M' Pipa PVC Ø 3" (AW) 83,511.00
16 1 M' Pipa PVC Ø 3/4" (AW) 38,468.00
17 1 Buah Bak Cuci piring Stainless steel 205,590.00
18 1 Buah Kran Ø 1/2" - 3/4" 80,510.00
19 1 Buah Kran Flexibel 97,822.00
20 1 Buah Floor Drain 96,188.00
21 1 Bh Spray Closet 161,962.00
22 1 Bh Shower Spray 210,470.00
24 1 M' Saluran Air Limbah Buis Beton Ø 60 cm 204,754.00
25 1 M' Pasang Talang Seng Datar 132,708.00
26 1 Buah Tangki Air fibreglass Volume 1 m3 1,620,498.00
27 1 Unit Septictank 1,00x2,00x2,00 m + Rembesan 6,523,512.00
28 1 Unit Septictank 2,00x3,00x2,00 m + Rembesan 19,482,393.00
29 1 Unit Groundtank 1,50x2,00x2,00 m + Rembesan 9,323,021.00

M. PEKERJAAN PENGECATAN

Page 91 HARSAT
HARGA
NO URAIAN PEKERJAAN
(Rp)
1 1 M² Mengikis / Mengerok Permukaan Cat Tembok Lama 13,900.00
2 1 M² Mendempul Dan Menggosok Kayu 21,778.00
3 1 M² Pengecatan Bidang Kayu Lama Setara Sieve 29,394.00
4 1 M² Pengecatan Bidang Kayu Baru Setara Sieve 46,074.00
5 1 M² Pelaburan Bidang Kayu dengan Politur 50,677.00
6 1 M² Pelaburan Bidang Kayu dengan Cat Residu dan Ter 11,070.00
7 1 M² Pengecatan Bidang Kayu Daun Pintu dengan Cat Milamic 180,977.00
8 1 M' Pengecatan Bidang Kayu Kusen dengan Cat Milamic 88,913.00
9 1 M² Pengecatan Tembok Baru Eksterior Setara ICI 35,323.00
10 1 M² Pengecatan Tembok Baru Eksterior Setara Catylac 18,524.00
11 1 M² Pengecatan Tembok Baru Interior Setara ICI 20,368.00
12 1 M² Pengecatan Tembok Baru Interior Setara Catylac 16,005.00
13 1 M² Pengecatan Plafond ( 3x ) Setara Ecohome 21,817.00
14 1 M² Pengecatan Plafond ( 2x ) Setara Ecohome 22,084.00
15 1 M² Pengecatan Permukaan Baja dengan Meni Besi 21,572.00
16 1 M² Pengecatan Permukaan Conwood Dengan Propan Fiberkote 62,961.00
19 1 M² Pengecatan Lapis Duco (2xlapis sampai rata) 182,551.00

N. ANALISA HARGA SATUAN PEKERJAAN LISTRIK


1 Titik Lampu Dalam/ttk Bawah Plafond (Kabel NYM 2x1,5mm) 158,601.00
2 Titik Lampu Dalam/ttk Bawah Dak (Kabel NYM 2x1,5mm) 179,638.00
3 Titik Stop Kontak Biasa /ttk (Kabel NYM 3x1,5mm) 130,796.00
4 Titik Stop Kontak Khusus /ttk (Kabel NYM 3x2,5mm) 218,962.00
5 Pekerjaan Arde/Pentanahan/ttk 279,468.00
6 Pekerjaan Box Sikring/bh 2 Group 255,881.00
7 Pekerjaan Box Sikring/bh 4 Group 264,833.00
8 Pekerjaan Box Sikring/bh 6 Group 282,851.00

O. PEKERJAAN PERTAMANAN
1 1 Lubang Penanaman Pohon Pelindung 30,359.57
2 1 Lubang (70x70x70) cm, tanam bambu krisik/jepang 46,834.57
3 1 Lubang (40x40x40) cm, tanam pohon perdu (polibag) 11,247.57
4 1 M² Tanam rumput gajah (silang papan catur) 10,884.50

Page 92 HARSAT
REKAPITULASI PEKERJAAN
Perihal : Tahun Anggaran 2019
Periode : Menengah
Klasifikasi : Pembangunan Kost-Kostan (Hostel)
Proyek : Jln. Pembangunan
Lokasi : Deli Serdang

JUMLAH HARGA
NO. URAIAN PEKERJAAN
(Rupiah)
(1) (2) (5)
A. PEKERJAAN PERSIAPAN Rp 3,554,996.63
B. PEKERJAAN DARI ELEVASI -1.60 M' s/d + 4,00 m' (AREA RUANG BASEMENT)
I PEKERJAAN TANAH Rp 7,014,547.69
II. PEKERJAAN PONDASI Rp 11,703,444.58
III. PEKE PEKERAAN PONDASI DANGKAL Rp 136,768,824.60
IV. PEKERJAAN DINDING Rp 39,307,839.58
V. PEKERJAAN PLESTERAN & ACIAN Rp 28,749,979.41
VI. PEKERJAAN KUSEN, DAUN PINTU JENDELA KAYU Rp 18,324,549.24
VII. PEKERJAAN PENGGANTUNG DAN KACA Rp 5,706,021.15
VIII. PEKERJAAN PELAPIS LANTAI DAN DINDING Rp 27,752,935.53
IX. PEKERJAAN PLAFOND Rp 7,546,107.65
X. PEKERJAAN INSTALASI LISTRIK Rp 4,917,637.00
XI. PEKERJAAN SANITARY Rp 16,642,675.74
XII. PEKERJAAN BESI Rp 3,690,000.00
XIII. PEKERJAAN PENGECATAN Rp 16,365,892.66
C. PEKERJAAN DR. ELEVASI 4,00 S/D 5,15 MTR
I. PEKERJAAN BETON Rp 42,171,649.14
II. PEKERJAAN DINDING Rp 44,563,010.72
III. PEKERJAAN PLESTERAN & ACIAN Rp 30,662,825.29
IV. PEKERJAAN KUSEN, DAUN PINTU JENDELA KAYU Rp 18,886,845.49
V. PEKERJAAN PENGGANTUNG DAN KACA Rp 5,706,021.15
VI. PEKERJAAN PELAPIS LANTAI DAN DINDING Rp 22,536,099.17
VII. PEKERJAAN PLAFOND Rp 7,364,285.20
VIII. PEKERJAAN INSTALASI LISTRIK Rp 4,917,637.00
IX. PEKERJAAN SANITARY Rp 9,110,655.74
X. PEKERJAAN BESI Rp 4,890,000.00
XI. PEKERJAAN PENGECATAN Rp 16,080,917.61
XII. PEKERJAAN PENUTUP ATAP Rp 18,771,926.88
JUMLAH HARGA SELURUH PEKERJAAN (I) +(II) ………......…. (1) Rp 553,707,324.86
PPN (10%) ……………….…... (2) Rp -
JUMLAH HARGA PEKERJA + PAJAK ….……. (3) Rp 553,707,324.86
HARGA PEKERJAAN DIBULATKAN ………. (4) Rp 553,700,000.00

Terbilang : LIMA RATUS LIMA PULUH TIGA JUTA TUJUH RATUS RIBU RUPIAH

Medan; 5 Juni 2020

Dibuat Oleh
Konsultan Perencana
DUTA INTERIOR MEDAN

( EDWART NAPITUPULU )
JUMLAH HARGA
NO. URAIAN PEKERJAAN
(Rupiah)
(1) (2) (5)
RENCANA ANGGARAN BIAYA RAB
Perihal : Tahun Anggaran 2019
Periode : Menengah
Klasifikasi : Pembangunan Kost-Kostan (Hostel)
Proyek : Jln. Pembangunan
Lokasi : Deli Serdang

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)
A. PEKERJAAN PERSIAPAN
### #REF! 0.00 M² 6,300.00 Rp -
1) Sewa Scafolding Selama 2 Bulan 1,250.00 Set 1,500.00 Rp 1,875,000.00
2) Pekerjaan Pengukuran & Bowplank 44.00 M' 38,181.74 Rp 1,679,996.63
JUMLAH PEKERJAAN PERSIAPAN .............................. (I) Rp 3,554,996.63
B. PEKERJAAN DARI ELEVASI -1.60 M' s/d + 4,00 m' (AREA RUANG BASEMENT)
I PEKERJAAN TANAH
1) Pekerjaan Galian Tanah Pondasi Menerus Di Bawah Sloof Uk.15x20 cm 9.79 M³ 36,000.00 Rp 352,404.00
2) Pekerjaan Galian Tanah Pondasi Menerus Di Bawah Sloof Uk.15x50 cm 13.60 M³ 36,000.00 Rp 489,528.00
3) Galian Tanah Pondasi Telapak
3.1. Pondasi Telapak; Uk.55x100 cm; (P-1) 7.80 M³ 47,286.00 Rp 368,830.80
3.2. Pondasi Telapak; Uk.70x100 cm; (P-2) 0.91 M³ 47,286.00 Rp 43,030.26
4) Galian Tanah Sloof
4.1. Sloof Uk.15x20 cm 0.75 M³ 36,000.00 Rp 27,108.00
4.2. Sloof Uk.15x50 cm 2.74 M³ 36,000.00 Rp 98,517.60
5) Pekerjaan Urugan Tanah Kembali
5.1. Pekerjaan Urugan Tanah Pondasi Telapak 1.35 M³ 17,262.00 Rp 23,320.96
6) Pekerjaan Timbunan; Tebal=40 cm
6.1.a. Peninggian Lantai; Tanah Didatangkan; Tbl.10 cm 18.18 M³ 115,056.00 Rp 2,091,372.91
6.1.b. Peninggian Lantai; Timbunan Sirtu ; Tebal 10 cm 9.76 M³ 231,779.00 Rp 2,263,090.16
7) Pekerjaan Pemadatan
7.1. Pemadatan Tanah Timbun 18.18 M³ 45,000.00 Rp 817,965.00
7.2. Pemadatan Sirtu 9.76 M³ 45,000.00 Rp 439,380.00
JUMLAH PEKERJAAN TANAH .............................. (II) Rp 7,014,547.69
II. PEKERJAAN PONDASI
II.A. PEKERAAN PONDASI DANGKAL
1) Pekerjaan Pondasi Menerus
1.1. Pekerjaan Lantai Kerja Pondasi
a. Pekerjaan Pasir Urug; Tbl. 5 cm 0.75 M³ 84,999.00 Rp 64,004.25
b. Pekerjaan Pasangan Batu Kosong; Tbl. 5 cm 0.75 M³ 350,701.00 Rp 264,077.85
1.2. Pekerjaan Pondasi Menerus 6.93 M³ 650,224.00 Rp 4,508,571.94
II.B. PEKERAAN PONDASI DALAM
1 Pekerjaan Pondasi Plat Setempat
1.1. Pondasi Plat Setempat Uk.0,55 x1,10 M'; (P-1)
1.1.a. Pekerjaan Lantai Kerja
1.1.a.1. Pekerjaan Urugan Pasir 0.40 M³ 84,999.00 Rp 33,659.60
1.1.a.2. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 0.40 M³ 837,802.00 Rp 331,769.59
1.1.b. Pekerjaan Mall/ Bekisting 10.80 M² 71,227.00 Rp 769,251.60
1.1.c. Pekerjaan Pembesian; D10 - 150 mm 276.31 Kg 11,495.00 Rp 3,176,159.33
1.1.d. Pengecoran K-250 (fc'=21.7 Mpa), Slump (12+2) 1.80 M³ 995,139.00 Rp 1,791,250.20
1.2. Pondasi Plat Setempat Uk.70x110 cm'; (P-5')
1.2.a. Pekerjaan Lantai Kerja
1.2.a.1. Pekerjaan Urugan Pasir 0.04 M³ 84,999.00 Rp 3,272.46
1.2.a.2. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 0.04 M³ 837,802.00 Rp 32,255.38
1.2.b. Pekerjaan Mall/ Bekisting 1.08 M² 71,227.00 Rp 76,925.16
1.2.c. Pekerjaan Pembesian D13 - 150 mm 36.74 Kg 11,495.00 Rp 422,370.11
1.2.d. Pengecoran K-250 (fc'=21.7 Mpa), Slump (12+2) 0.23 M³ 995,139.00 Rp 229,877.11
JUMLAH PEKERJAAN PONDASI .............................. (II) Rp 11,703,444.58
III. PEKERJAAN BETON
1. Pek. Beton K-250; (fc'=21.7 Mpa), Slump (12+2),w/c=0,56
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)
1.1. Stump Beton Uk. 15x60 cm (K-1); s/d Elv.Lantai (±0,00)
1.1.a. Pekerjaan Mall/ Bekisting (K-1) 21.60 M² 173,827.00 Rp 3,754,663.20
1.1.b. Pekerjaan Pembesian (K-1)
- Berat Stek Besi 8 D13 mm 165.03 Kg 11,495.00 Rp 1,897,072.54
- Berat Beugel Besi Ø8-150 mm 70.31 Kg 11,495.00 Rp 808,220.26
1.1.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 3.46 M³ 1,024,751.00 Rp 3,541,539.46
1.2. Pekerjaan Stump Beton Uk. 30x60 cm (K-2)
1.2.a. Pekerjaan Mall/ Bekisting 2.16 M² 173,827.00 Rp 375,466.32
1.2.b. Pekerjaan Pembesian K-2
- Berat Stek Besi 16 D16 mm 24.07 Kg 11,495.00 Rp 276,656.41
- Berat Beugel Besi Ø10-100 mm 7.16 Kg 11,495.00 Rp 82,318.73
1.2.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 0.30 M³ 1,024,751.00 Rp 304,351.05
2. Pekerjaan Beton K-250; (fc'=21.7 Mpa), Slump (12+2),w/c=0,56
2.2. Pekerjaan Kolom Struktur Uk. 15x60cm (K-2)
2.2.a. Pekerjaan Mall/ Bekisting 63.00 M² 173,827.00 Rp 10,951,101.00
2.2.b. Pek. Pembesian Kolom Uk.15x60 cm
- Berat Stek Besi 8 D13 mm 450.09 Kg 11,495.00 Rp 5,173,834.21
- Berat Beugel Besi Ø10-200 mm 143.82 Kg 11,495.00 Rp 1,653,177.79
2.2.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 3.78 M³ 995,139.00 Rp 3,761,625.42
2.3. Pekerjaan Kolom Struktur Uk. 30x60cm (K-3)
2.3.a. Pekerjaan Mall/ Bekisting 6.30 M² 173,827.00 Rp 1,095,110.10
2.3.b. Pek. Pembesian Kolom Uk.30x60 cm (K-2)
- Berat Stek Besi 18 D13 mm 75.39 Kg 11,495.00 Rp 866,617.23
- Berat Beugel Besi Ø8-150 mm 17.45 Kg 11,495.00 Rp 200,558.36
2.3.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) (K-4) 0.63 M³ 995,139.00 Rp 626,937.57
2.4. Pekerjaan Sloof Uk.15x20 cm
2.4.a. Pekerjaan Mall/ Bekisting 10.04 M² 75,297.00 Rp 755,981.88
2.4.b. Pekerjaan Pembesian
- Berat Stek Besi 8 D10 mm 61.90 Kg 11,495.00 Rp 711,501.42
- Berat Beugel Besi Ø8-100 mm 29.89 Kg 11,495.00 Rp 343,561.64
2.4.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 0.75 M³ 995,139.00 Rp 749,339.67
2.5. Pekerjaan Sloof Uk.15x50 cm
2.5.a. Pekerjaan Mall/ Bekisting 45.61 M² 75,297.00 Rp 3,434,296.17
2.5.b. Pekerjaan Pembesian
- Berat Stek Besi 8 D10 mm 380.16 Kg 11,495.00 Rp 4,369,973.67
- Berat Beugel Besi Ø8-200 mm 85.86 Kg 11,495.00 Rp 986,906.32
2.5.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 2.74 M³ 995,139.00 Rp 2,723,297.39
2.6. Pekerjaan Plat Lantai Dasar; Tbl.10 cm
2.6.a. Pekerjaan Pembesian; Wiremesh M-6 653.86 Kg 13,940.00 Rp 9,114,842.33
2.6.b. Pek. Pengelasan (Joint Wire Mesh ke Stek Besi Sloof) 255.50 Cm' 2,500.00 Rp 638,750.00
2.6.c. Pekerjaan Pengecoran; Spesi 1:3:5 12.00 M³ 837,802.00 Rp 10,053,624.00
2.7. Pekerjaan Tangga
2.7.a. Pekerjaan Mall/Bekisting 8.56 M² 163,732.00 Rp 1,400,743.63
2.7.b. Pekerjaan Pembesian 219.28 Kg 13,940.00 Rp 3,056,717.48
2.7.c. Pekerjaan Pengecoran K-250 (fc'=21.7 Mpa), Slump (12+2) 0.43 M³ 995,139.00 Rp 428,825.30
2.8. Pekerjaan Ring Balok Uk.15x20 cm
2.8.a. Pekerjaan Mall/ Bekisting 10.04 M² 176,542.00 Rp 1,772,481.68
2.8.b. Pekerjaan Pembesian
- Berat Stek Besi 4 D13 mm 61.90 Kg 11,495.00 Rp 711,501.42
- Berat Beugel Besi Ø8-100 mm 32.44 Kg 11,495.00 Rp 372,928.79
2.8.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 0.75 M³ 995,139.00 Rp 749,339.67
2.9. Pekerjaan Ring Balok Uk.15x50 cm
2.9.a. Pekerjaan Mall/ Bekisting 45.61 M² 176,542.00 Rp 8,052,080.62
2.9.b. Pekerjaan Pembesian
- Berat Stek Besi 10 D13 mm 475.20 Kg 11,495.00 Rp 5,462,467.09
- Berat Beugel Besi Ø8-100 mm 162.50 Kg 11,495.00 Rp 1,867,886.81
2.9.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 4.10 M³ 995,139.00 Rp 4,084,946.08
2.10. Pekerjaan Ring Balok Tangga; Uk.15x40 cm
2.10.a. Pekerjaan Mall/ Bekisting 3.90 M² 176,542.00 Rp 689,219.97
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)
2.10.b. Pekerjaan Pembesian
- Berat Stek Besi 6 D13 mm 30.51 Kg 11,495.00 Rp 350,670.99
- Berat Beugel Besi Ø8-200 mm 13.53 Kg 11,495.00 Rp 155,521.17
2.10.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 0.44 M³ 995,139.00 Rp 437,065.05
2.11. Pekerjaan Plat Lantai 2; Tbl.10 cm
2.11.a. Pekerjaan Mall 88.98 M² 194,395.00 Rp 17,297,267.10
2.11.b. Pek. Pembesian ø9 mm 769.76 Kg 11,495.00 Rp 8,848,433.24
2.11.c. Pekerjaan Pengecoran K-250 (fc'=21.7 Mpa), Slump (12+2) 10.68 M³ 995,139.00 Rp 10,625,696.19
2.12. Pekerjaan Plat Meja Dapur
2.12.a. Pekerjaan Mall/ Bekisting 0.54 M² 194,395.00 Rp 104,973.30
2.12.b. Pekerjaan Pembesian Meja Dapur 11.47 Kg 11,495.00 Rp 131,812.02
2.12.c. Pekerjaan Pengecoran K-175 0.05 M³ 927,397.00 Rp 50,079.44
2.13. Pekerjaan Kolom Fantasi
2.13.a. Pekerjaan Mall/ Bekisting 2.15 M² 194,395.00 Rp 418,338.04
2.13.b. Pekerjaan Pembesian 23.82 Kg 11,495.00 Rp 273,851.51
2.13.c. Pekerjaan Pengecoran K-175 0.17 M³ 1,014,486.00 Rp 174,653.91
JUMLAH PEKERJAAN BETON .............................. (III) Rp 136,768,824.60
IV. PEKERJAAN DINDING
1) Pek.Pasangan Batu; Tebal 1/2 Bata; Spesi 1Pc : 4Psr 224.47 M² 175,114.00 Rp 39,307,839.58
JUMLAH PEKERJAAN DINDING .............................. (IV) Rp 39,307,839.58
V. PEKERJAAN PLESTERAN & ACIAN
1. Pekerjaan Plesteran Spesi 1Pc:3Psr 448.94 M² 44,841.00 Rp 20,130,918.54
2. Pekerjaan Acian
2.1. Pekerjaan Acian Dinding Plesteran 448.94 M² 18,459.00 Rp 8,286,983.46
2.2. Acian Pada Kolom Fantasi 4.70 M² 18,459.00 Rp 86,757.30
2.3. Acian Plat Kanopy 13.29 M² 18,459.00 Rp 245,320.11
JUMLAH PEKERJAAN PLESTERAN ACIAN .................... (V) Rp 28,749,979.41
VI. PEKERJAAN KUSEN, DAUN PINTU JENDELA KAYU
1) Pekerjaan Kusen
1.1. Pekerjaan Kusen Pintu 0.46 M³ 7,676,770.00 Rp 3,549,929.46
1.2. Pekerjaan Kusen Jendela 0.09 M³ 7,676,770.00 Rp 653,762.33
2) Pekerjaan Daun Pintu
2.1. Daun Pintu (P-1); Uk.90x2,10 M' 9.45 M² 681,716.00 Rp 6,442,216.20
2.2. Daun Pintu Kamar Mandi (folding door) 5.00 Set 1,050,000.00 Rp 5,250,000.00
3) Pekerjaan Daun Jendela
3.1. Daun Jendela(V-1); Uk.40x60 cm (Kombinasi Kaca) 1.20 M² 478,550.00 Rp 574,260.00
3.2. Daun Jendela(J-1); Uk.40x60 cm (Kombinasi Kaca) 3.88 M² 478,550.00 Rp 1,854,381.25
UMLAH PEK. KUSEN, DAUN PINTU JENDELA .............. (VI) Rp 18,324,549.24
VII. PEKERJAAN PENGGANTUNG DAN KACA
1) Handle Pintu Dekkson Type 0820 (Full Set) 5.00 Set 253,104.00 Rp 1,265,520.00
2) Pekerjaan Door Stopper Dekkson Type MDS 889 SN 5.00 Set 128,382.00 Rp 641,910.00
3) Pekerjaan Engsel Pintu Dan Jendela
3.1. Pekerjaan Engsel Pintu Dekkson Ecoline 4x3x2MM 2BB SSS 10.00 Bh 40,887.00 Rp 408,870.00
3.2. Pek. Engsel Jendela Dekkson Ecoline 3x3x2MM 2BB SSS 20.00 Bh 40,887.00 Rp 817,740.00
4) Pekerjaan Rambuncis Dekkson Type CWH 103Z  10.00 Bh 56,277.00 Rp 562,770.00
5) Pekerjaan Kait Angin Dekkson Type WS 001 10" SSS 10.00 Bh 71,689.00 Rp 716,890.00
6) Pekerjaan Engsel Jungkit Dekkson Type ES SL 5" CP 20.00 Bh 33,181.00 Rp 663,620.00
7) Pekerjaan Kaca
7.1. Kaca Ventilasi 1.20 M² 123,882.00 Rp 148,658.40
7.2. Kaca Jendela 3.88 M² 123,882.00 Rp 480,042.75
JUMLAH PEK. PENGGANTUNG & KACA.................... (VII) Rp 5,706,021.15
VIII. PEKERJAAN PELAPIS LANTAI DAN DINDING
1) Pek. Lantai Keramik; Asia Tile (setaranya) Uk. 20x20 ; unpolish
1.a. Area Kamar Mandi 8.80 M² 122,429.00 Rp 1,077,375.20
1.b. Area Dapur 0.48 M² 122,429.00 Rp 58,765.92
2) Pek. Lantai Keramik; Granit Ex. China; Uk. 60x60 43.80 M² 153,929.00 Rp 6,742,090.20
3) Pekerjaan Lantai Teras; Granit Ex. China; Uk. 60x60
3.1. Area Teras dan Dapur 35.47 M² 153,929.00 Rp 5,459,861.63
3.2. Area Tangga 11.09 M² 153,929.00 Rp 1,707,072.61
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)
4) Pek. Dinding Keramik; Asia Tile (setaranya) Uk. 20x40
4.1. Area Kamar MAndi 46.05 M² 150,149.00 Rp 6,914,361.45
4.2. Area Dapur 3.84 M² 150,149.00 Rp 576,572.16
5) Pek. Pelapis Kolom; Batu Alam Palimanan 19.06 M² 273,706.00 Rp 5,216,836.36
AH PEK. PELAPIS LANTAI & DINDING ................... (VIII) Rp 27,752,935.53
IX. PEKERJAAN PLAFOND
1) Pekerjaan Rangka Plafond Gypsum (Sisi Dalam) 43.80 M² 51,657.00 Rp 2,262,576.60
2) Pekerjaan Plafond Gypsum (Sisi Dalam) 43.80 M² 43,538.00 Rp 1,906,964.40
3) Pekerjaan Rangka Plafond Gypsum (Sisi Luar) 35.47 M² 51,657.00 Rp 1,832,273.79
4) Pekerjaan Plafond Gypsum (Area Selasar) 35.47 M² 43,538.00 Rp 1,544,292.86
JUMLAH PEKERJAAN PLAFOND .................. (IX) Rp 7,546,107.65
X. PEKERJAAN INSTALASI LISTRIK
1) Pek. Titik Lampu Dalam/ttk Bawah Plafond (Kabel NYM 2x1,5mm) 12.00 Titik 158,601.00 Rp 1,903,212.00
2) Pek. Titik Stop Kontak Biasa /ttk (Kabel NYM 3x1,5mm) 6.00 Titik 179,638.00 Rp 1,077,828.00
3) Pek. Titik Stop Kontak Khusus /ttk (Kabel NYM 3x2,5mm) 5.00 Titik 218,962.00 Rp 1,094,810.00
4) Pekerjaan Aarde/Pentanahan 2.00 Titik 279,468.00 Rp 558,936.00
5) Pekerjaan Box Sikring 6 Group 1.00 Bh 282,851.00 Rp 282,851.00
MLAH PEKERJAAN INSTALASI LISTRIK ....................... (X) Rp 4,917,637.00
XI. PEKERJAAN SANITARY
1) Pekerjaan Kloset Duduk Tidy (Setaranya) 5.00 Set 1,786,817.00 Rp 8,934,085.00
2) Pekerjaan Floor Drain 5.00 Bh 96,188.00 Rp 480,940.00
3) Pekerjaan Kran Air Onda
3.a. Kran Tembok Onda 5.00 Bh 80,510.00 Rp 402,550.00
3.b. Kran Flexibel Onda 1.00 Bh 97,822.00 Rp 97,822.00
4) Pekerjaan Zink Sink 1 Lubang 1.00 Set 205,590.00 Rp 205,590.00
5) Pekerjaan Shower
5.1. Spray Closet Onda 5.00 Bh 161,962.00 Rp 809,810.00
5.2. Shower Spray Onda 5.00 BH 210,470.00 Rp 1,052,350.00
6) Pekerjaan Pipa Air
6.a. Pekerjaan Pipa Air Bersih (1/2") 28.44 M' 19,958.00 Rp 567,605.52
6.b. Pekerjaan Air Buangan (2") 31.56 M' 42,588.00 Rp 1,344,077.28
6.c. Pekerjaan Air Kotor (3") 32.90 M' 83,511.00 Rp 2,747,845.94
JUMLAH PEKERJAAN SANITARY ......................... (XI) Rp 16,642,675.74
XII. PEKERJAAN BESI
1) Pekerjaan Railing Besi Tangga 7.38 M² 500,000.00 Rp 3,690,000.00
JUMLAH PEKERJAAN BESI ......................... (XII) Rp 3,690,000.00
XIII. PEKERJAAN PENGECATAN
1) Pengecatan Dengan Cat Air
1.1. Pekerjaan Pengecatan Dulux Wheatershield (Ekterior) 159.61 M² 35,323.00 Rp 5,637,904.03
1.2. Pekerjaan Pengecatan Catylac (Interior) 316.70 M² 16,005.00 Rp 5,068,783.50
2) Pekerjaan Mendempul Dan Menggosok Kayu
2.1. Bidang Kayu Kusen 14.25 M² 21,778.00 Rp 310,336.50
2.2. Bidang Kayu Daun Pintu dan Jendela 21.40 M² 21,778.00 Rp 466,049.20
3) Pengecatan Dengan Cat Kayu/Besi
3.1. Pekerjaan Pengecatan Kusen
3.1.a. Pekerjaan Pengecatan Kusen Pintu
3.1.a.1. Kusen Pintu Gendong 12.45 M² 50,677.00 Rp 630,928.65
3.1.b. Pekerjaan Pengecatan Kusen Jendela
3.1.b.1. Kusen Ventilasi (V= 0,40*0,60 M') 1.80 M² 50,677.00 Rp 91,218.60
3.2. Pekerjaan Pengecatan Daun
3.2.a. Pekerjaan Pengecatan Daun Pintu 17.60 M² 50,677.00 Rp 891,915.20
3.2.b. Pekerjaan Pengecatan Daun Jendela 2.80 M² 50,677.00 Rp 141,895.60
3.2.c. Pekerjaan Pengecatan Daun Jendela Kamar Mandi 1.00 M² 50,677.00 Rp 50,677.00
4) Pekerjaan Pengecatan Plafond 79.27 M² 22,084.00 Rp 1,750,598.68
5) Pengecatan Besi
5.a. Pekerjaan Pengecatan Railing Besi 5.82 M² 21,572.00 Rp 125,549.04
6) Pekerjaan Coating / Vernish Batu Alam 19.06 M² 62,961.00 Rp 1,200,036.66
JUMLAH PEKERJAAN PENGECATAN ......................... (XIII) Rp 16,365,892.66

JUMLAH HARGA PEKERJAAN 1.50 S/D ELEVASI 4.00 METER Rp 328,045,451.47


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)
JUMLAH HARGA PEKERJAAN 1.50 S/D ELEVASI 4.00 METER Rp 328,045,451.47

C. PEKERJAAN DR. ELEVASI 4,00 S/D 5,15 MTR


I. PEKERJAAN BETON
1 Pek. Beton; Spesi 1:2:3
1.a. Pekerjaan Kolom Struktur
1.a.1. Pekerjaan Kolom Struktur Uk. 15x15 cm
- Pekerjaan Mall/ Bekisting 89.10 M² 57,942.33 Rp 5,162,661.90
- Pek. Pembesian Kolom Uk.15x15 cm
Berat Stek Besi 4 D10 mm 325.51 Kg 11,495.00 Rp 3,741,760.44
Berat Beugel Besi Ø8-200 mm 117.18 Kg 11,495.00 Rp 1,347,033.76
- Pekerjaan Beton ; Spesi 1:2:3 3.34 M³ 927,397.00 Rp 3,098,665.23
1.a.2. Pekerjaan Kolom Struktur Uk. 15x60 cm
- Pekerjaan Mall/ Bekisting 20.25 M² 173,827.00 Rp 3,519,996.75
- Pek. Pembesian Kolom Uk.15x60 cm
Berat Stek Besi 8 D13 mm 37.88 Kg 11,495.00 Rp 435,404.85
Berat Beugel Besi Ø10-150 mm 66.58 Kg 11,495.00 Rp 765,360.09
Pekerjaan Beton ; Spesi 1:2:3 0.81 M³ 927,397.00 Rp 751,191.57
1.b. Pekerjaan Ring Balok
1.b.1. Pekerjaan Ring Balok Uk.15x20 cm
- Pekerjaan Mall/ Bekisting 33.64 M² 176,542.00 Rp 5,938,872.88
- Pekerjaan Pembesian
- Berat Stek Besi 4 D13 mm 207.39 Kg 11,495.00 Rp 2,383,954.95
- Berat Beugel Besi Ø8-200 mm 108.10 Kg 11,495.00 Rp 1,242,604.63
- Pekerjaan Beton; Spesi 1:2:3 2.52 M³ 927,397.00 Rp 2,339,822.63
Pekerjaan1.b.2.
Ring Balok Uk.15x40 cm
- Pekerjaan Mall/ Bekisting 6.08 M² 176,542.00 Rp 1,073,375.36
- Pekerjaan Pembesian
Berat Stek Besi 6 D13 mm 47.51 Kg 11,495.00 Rp 546,126.94
Berat Beugel Besi Ø8-200 mm 6.92 Kg 11,495.00 Rp 79,597.45
- Pekerjaan Beton; Spesi 1:2:3 0.46 M³ 927,397.00 Rp 422,893.03
1.c.Pekerjaan Plat Lantai
1.c.1. Pekerjaan Plat Lantai Dudukan Tangki Air; Tbl.10 cm
- Pekerjaan Mall 4.28 M² 194,395.00 Rp 831,038.63
- Pek. Pembesian ø9 mm 46.29 Kg 11,495.00 Rp 532,116.60
- Pekerjaan Pengecoran Spesi 1:2:3 0.51 M³ 927,397.00 Rp 475,754.66
1.c.2. Pekerjaan Kanopy dan Janggutan
- Pekerjaan Mall 19.98 M² 194,395.00 Rp 3,884,012.10
- Pek. Pembesian ø9 mm 161.39 Kg 11,495.00 Rp 1,855,232.86
- Pekerjaan Pengecoran Spesi 1:2:3 1.60 M³ 927,397.00 Rp 1,482,351.36
1.c.3. Pekerjaan Plat Meja Dapur
- Pekerjaan Mall/ Bekisting 0.54 M² 194,395.00 Rp 104,973.30
- Pekerjaan Pembesian Meja Dapur 9.29 Kg 11,495.00 Rp 106,767.73
- Pekerjaan Pengecoran K-175 0.05 M³ 927,397.00 Rp 50,079.44
JUMLAH PEKERJAAN BETON .............................. (I) Rp 42,171,649.14
II. PEKERJAAN DINDING
1) Pek.Pasangan Batu; Tebal 1/2 Bata; Spesi 1Pc : 4Psr 254.48 M² 175,114.00 Rp 44,563,010.72
JUMLAH PEKERJAAN DINDING .............................. (II) Rp 44,563,010.72
III. PEKERJAAN PLESTERAN & ACIAN
1. Pekerjaan Plesteran Spesi 1Pc:4Psr
1.a. Pekerjaan Plesteran Pas. Bata 483.51 M² 43,075.00 Rp 20,827,279.40
2. Pekerjaan Acian
2.1. Pekerjaan Acian Dinding Plesteran 483.51 M² 18,459.00 Rp 8,925,148.01
2.2. Acian Plat Lantai, Kanopy, dan Janggutan 9.22 M² 18,459.00 Rp 170,191.98
2.3. Acian Plat Kanopy 26.07 M² 18,459.00 Rp 481,226.13
2.2. Acian Plat Lantai Janggutan 14.03 M² 18,459.00 Rp 258,979.77
UMLAH PEKERJAAN PLESTERAN ACIAN .................... (III) Rp 30,662,825.29
IV. PEKERJAAN KUSEN, DAUN PINTU JENDELA KAYU
1) Pekerjaan Kusen
1.1. Pekerjaan Kusen Pintu 0.46 M³ 7,676,770.00 Rp 3,549,929.46
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)
1.2. Pekerjaan Kusen Jendela 0.09 M³ 7,676,770.00 Rp 653,762.33
2) Pekerjaan Daun Pintu
2.1. Daun Pintu (P-1); Uk.90x2,10 M' 9.45 M² 681,716.00 Rp 6,442,216.20
2.2. Daun Pintu Kamar Mandi (folding door) 5.00 M² 1,050,000.00 Rp 5,250,000.00
3) Pekerjaan Daun Jendela
3.1. Daun Jendela(V-1); Uk.40x60 cm (Kombinasi Kaca) 1.20 M² 478,550.00 Rp 574,260.00
3.2. Daun Jendela(J-1); Uk.40x60 cm (Kombinasi Kaca) 3.88 M² 478,550.00 Rp 1,854,381.25
3.3. Pekerjaan Jalusi; Uk. 50x235 cm 1.18 M² 478,550.00 Rp 562,296.25
MLAH PEK. KUSEN, DAUN PINTU JENDELA .............. (VII) Rp 18,886,845.49
V. PEKERJAAN PENGGANTUNG DAN KACA
1) Handle Pintu Dekkson Type 0820 (Full Set) 5.00 Set 253,104.00 Rp 1,265,520.00
2) Pekerjaan Door Stopper Dekkson Type MDS 889 SN 5.00 Set 128,382.00 Rp 641,910.00
3) Pekerjaan Engsel Pintu Dan Jendela
3.1. Pekerjaan Engsel Pintu Dekkson Ecoline 4x3x2MM 2BB SSS 10.00 Bh 40,887.00 Rp 408,870.00
3.2. Pek. Engsel Jendela Dekkson Ecoline 3x3x2MM 2BB SSS 20.00 Bh 40,887.00 Rp 817,740.00
4) Pekerjaan Rambuncis Dekkson Type CWH 103Z  10.00 Bh 56,277.00 Rp 562,770.00
5) Pekerjaan Kait Angin Dekkson Type WS 001 10" SSS 10.00 Bh 71,689.00 Rp 716,890.00
6) Pekerjaan Engsel Jungkit Dekkson Type ES SL 5" CP 20.00 Bh 33,181.00 Rp 663,620.00
7) Pekerjaan Kaca
Kaca
7.1. Ventilasi 1.20 M² 123,882.00 Rp 148,658.40
7.2.
Kaca Jendela 3.88 M² 123,882.00 Rp 480,042.75
JUMLAH PEK. PENGGANTUNG & KACA.................... (V) Rp 5,706,021.15
VI. PEKERJAAN PELAPIS LANTAI DAN DINDING
1) Pek. Lantai Keramik; Asia Tile (setaranya) Uk. 20x20 ; unpolish
1.a. Area Kamar Mandi 8.80 M² 122,429.00 Rp 1,077,375.20
1.b. Area Dapur 0.48 M² 122,429.00 Rp 58,765.92
2) Pek. Lantai Keramik; Granit Ex. China; Uk. 60x60 43.80 M² 153,929.00 Rp 6,742,090.20
3) Pekerjaan Lantai Teras; Granit Ex. China; Uk. 60x60
3.1. Area Teras dan Dapur 35.47 M² 153,929.00 Rp 5,459,861.63
3.2. Area Tangga 11.09 M² 153,929.00 Rp 1,707,072.61
4) Pek. Dinding Keramik; Asia Tile (setaranya) Uk. 20x40
4.1. Area Kamar MAndi 46.05 M² 150,149.00 Rp 6,914,361.45
4.2. Area Dapur 3.84 M² 150,149.00 Rp 576,572.16
5) Pek. Pelapis Kolom; Batu Alam Palimanan 11.72 M² 273,706.00
MLAH PEK. PELAPIS LANTAI & DINDING ................... (IX) Rp 22,536,099.17
VII. PEKERJAAN PLAFOND
1) Pekerjaan Rangka Plafond Gypsum (Sisi Dalam) 43.80 M² 51,657.00 Rp 2,262,576.60
2) Pekerjaan Plafond Gypsum (Sisi Dalam) 43.80 M² 43,538.00 Rp 1,906,964.40
3) Pekerjaan Rangka Plafond Gypsum (Sisi Luar) 33.56 M² 51,657.00 Rp 1,733,608.92
4) Pekerjaan Plafond Gypsum (Area Selasar) 33.56 M² 43,538.00 Rp 1,461,135.28
JUMLAH PEKERJAAN PLAFOND .................. (X) Rp 7,364,285.20
VIII. PEKERJAAN INSTALASI LISTRIK
1) Pek. Titik Lampu Dalam/ttk Bawah Plafond (Kabel NYM 2x1,5mm) 12.00 Titik 158,601.00 Rp 1,903,212.00
2) Pek. Titik Stop Kontak Biasa /ttk (Kabel NYM 3x1,5mm) 6.00 Titik 179,638.00 Rp 1,077,828.00
3) Pek. Titik Stop Kontak Khusus /ttk (Kabel NYM 3x2,5mm) 5.00 Titik 218,962.00 Rp 1,094,810.00
4) Pekerjaan Aarde/Pentanahan 2.00 Titik 279,468.00 Rp 558,936.00
5) Pekerjaan Box Sikring 6 Group 1.00 Titik 282,851.00 Rp 282,851.00
LAH PEKERJAAN INSTALASI LISTRIK ....................... (XI) Rp 4,917,637.00
IX. PEKERJAAN SANITARY
1) Pekerjaan Kloset Duduk Tidy (Setaranya) 5.00 Set 1,786,817.00 Rp 1,786,817.00
2) Pekerjaan Floor Drain 5.00 Bh 96,188.00 Rp 96,188.00
3) Pekerjaan Kran Air Onda
3.a. Kran Tembok Onda 5.00 Bh 80,510.00 Rp 402,550.00
3.b. Kran Flexibel Onda 1.00 Bh 97,822.00 Rp 97,822.00
4) Pekerjaan Zink Sink 1 Lubang 1.00 Bh 205,590.00 Rp 205,590.00
5) Pekerjaan Shower
5.1. Spray Closet Onda 5.00 Bh 161,962.00 Rp 809,810.00
5.2. Shower Spray Onda 5.00 Bh 210,470.00 Rp 1,052,350.00
6) Pekerjaan Pipa Air
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)
6.a. Pekerjaan Pipa Air Bersih (1/2") 28.44 M' 19,958.00 Rp 567,605.52
6.b. Pekerjaan Air Buangan (2") 31.56 M' 42,588.00 Rp 1,344,077.28
6.c. Pekerjaan Air Kotor (3") 32.90 M' 83,511.00 Rp 2,747,845.94
JUMLAH PEKERJAAN SANITARY ......................... (XII) Rp 9,110,655.74
X. PEKERJAAN BESI
1) Pekerjaan Pagar Pembatas 11.60 M² 400,000.00 Rp 4,640,000.00
2) Pekerjaan Besi Siku (Dudukan Tangki Air) 1.00 Ls 250,000.00 Rp 250,000.00
JUMLAH PEKERJAAN BESI ......................... (XIII) Rp 4,890,000.00
XI. PEKERJAAN PENGECATAN
1) Pengecatan Dengan Cat Air
1.1. Pekerjaan Pengecatan Dulux Wheatershield (Ekterior) 159.61 M² 35,323.00 Rp 5,637,904.03
1.2. Pekerjaan Pengecatan Catylac (Interior) 316.70 M² 16,005.00 Rp 5,068,783.50
2) Pekerjaan Mendempul Dan Menggosok Kayu
2.1. Bidang Kayu Kusen 14.25 M² 21,778.00 Rp 310,336.50
2.2. Bidang Kayu Daun Pintu dan Jendela 21.40 M² 21,778.00 Rp 466,049.20
3) Pengecatan Dengan Cat Kayu/Besi
3.1. Pekerjaan Pengecatan Kusen
3.1.a. Pekerjaan Pengecatan Kusen Pintu 12.45 M² 50,677.00 Rp 630,928.65
3.1.b. Pekerjaan Pengecatan Kusen Jendela
- Kusen Ventilasi (V= 0,40*0,60 M') 1.80 M² 50,677.00 Rp 91,218.60
- Pekerjaan Jalusi Uk.20x235 cm 2.17 M² 50,677.00 Rp 109,969.09
3.2. Pekerjaan Pengecatan Daun
3.2.a. Pekerjaan Pengecatan Daun Pintu 17.60 M² 50,677.00 Rp 891,915.20
3.2.b. Pekerjaan Pengecatan Daun Jendela 2.80 M² 50,677.00 Rp 141,895.60
3.2.c. Pekerjaan Pengecatan Daun Jendela Kamar Mandi 1.00 M² 50,677.00 Rp 50,677.00
4) Pekerjaan Pengecatan Plafond 77.36 M² 22,084.00 Rp 1,708,418.24
5) Pengecatan Besi
5.a. Pekerjaan Pengecatan Railing Besi 10.12 M² 21,572.00 Rp 218,308.64
5.a. Pekerjaan Pengecatan Besi Siku 0.77 M² 21,572.00 Rp 16,610.44
6) Pekerjaan Coating / Vernish Batu Alam 11.72 M² 62,961.00 Rp 737,902.92
JUMLAH PEKERJAAN PENGECATAN ......................... (XIV) Rp 16,080,917.61
XII. PEKERJAAN PENUTUP ATAP
1) Pekerjaan Rangka Atap 104.11 M² 96,384.01 10,034,539.11
2) Pekerjaan Atap Spandek 104.11 M² 71,227.00 7,415,442.97
3) Pekerjaan Jurai Atap; Seng BJLS 7.78 M' 115,680.00 899,990.40
4) Pekerjaan Kalsiplank 9.98 M' 42,280.00 421,954.40
JUMLAH PEKERJAAN PENGECATAN ......................... (XIV) Rp 18,771,926.88

JUMLAH HARGA PEKERJAAN 4,00 S/D ELEVASI 9.20 METER Rp 225,661,873.39

10 TOTAL JUMLAH PEKERJAAN PEKERJAAN DARI ELV. - 1.60 S/D 4.00 MTR Rp 328,045,451.47
2) TOTAL JUMLAH PEKERJAAN PEKERJAAN DARI ELV. 4.00 S/D 9.20 MTR Rp 225,661,873.39
3) JUM;AH TOTAL BIAYA PEKERJAAN Rp 553,707,324.86
4) DIBULATKAN Rp 553,700,000.00
5) LUASAN LANTAI M² 190.874
6) HARGA PER METER Rp 2,900,866.54

Terbilang = LIMA RATUS LIMA PULUH TIGA JUTA TUJUH RATUS RIBU RUPIAH
Medan; 5 Juni 2020

Dibuat Oleh
Konsultan Perencana
DUTA INTERIOR MEDAN

( EDWART NAPITUPULU )
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)
FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

VOLUME PEKERJAAN
ELEVASI - 20.00 s/d 3.70 METER
Perihal : Rekapitulasi Harga Satuan Pekerjaan
Periode : Tahun Anggaran 2019
Klasifikasi : Menengah
Proyek : Renovasi
Lokasi : Medan
Wilayah : Deli Serdang

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
C. PEKERJAAN DR. ELEVASI 4,00 S/D 5,15 MTR
I. PEKERJAAN BETON
1 Pek. Beton; Spesi 1:2:3
1.a. Pekerjaan Kolom Struktur
1.a.1. Pekerjaan Kolom Struktur Uk. 15x15 cm
- Pekerjaan Mall/ Bekisting 89.10
Dik : 1. Jumlah = 33.00 Set
2. Panjang = 0.15 M'
3. Lebar = 0.15 M'
4. Tinggi = 4.50 M'
Luasan 1 Bh Mall = (2*(0,15+0,15))*4 M'
= 2.70 M²
Luasan 20 Bh Mall = 20 x 1,62 M²
= 89.10 M²
- Pek. Pembesian Kolom Uk.15x15 cm
Dik : a. Koefisien Besi = 0.006165
b. Jumlah Kolom = 33.00 M'
c. Panjang = 0.15 M'
d. Lebar = 0.15 M'
e. Pjg Besi (Stek+Angker) = 4.00 M'
f. Stek Besi Diameter = 10.00 MM
g. Jumlah Stek Besi = 4.00 Bh
h. Total Pjng Stek Besi = 528.00 M'
i. Beugel Besi Diameter = 8.00 MM
j. Jarak Beugel Besi = 0.20 MM
k. Pjg 1 Bh Beugel Besi = 0.45 M'
l. Jumlah Beugel Besi = 660.00 Bh
m. Tot.Pjng Beugel Besi = 297.00 M'
Berat Stek Besi 4 D10 mm = 0,006165*16mm*16mm*286,56 M' 325.51
= 325.51 Kg
Berat Beugel Besi Ø8-200 mm = 0,006165*8mm*8mm*250,74 M' 117.18
= 117.18 Kg
- Pekerjaan Beton ; Spesi 1:2:3 3.34
Dik : a. Jumlah = 33.00 M'
b. Panjang = 0.15 M'
c. Lebar = 0.15 M'
d. Tinggi = 4.50 M'
Vol. Cor Stump Beton 30x40 cm = 18 Set*(0,20*0,40*1,35) M'
= 3.34 M³
BESI BETON
RASIO BESI : BESI = 442.70 : 3.34
= 132.49 Kg/M³

1.a.2. Pekerjaan Kolom Struktur Uk. 15x60 cm


- Pekerjaan Mall/ Bekisting 20.25
Dik : 1. Jumlah = 3.00 Set
2. Panjang = 0.15 M'

Page 103 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
3. Lebar = 0.60 M'
4. Tinggi = 3.00 M'
Luasan 1 Bh Mall = (3*(0,15+0,6))*4 M'
= 6.75 M²
Luasan 3 Bh Mall = 3x 1,62 M²
= 20.25 M²
- Pek. Pembesian Kolom Uk.15x60 cm
Dik : a. Koefisien Besi = 0.006165
b. Jumlah Kolom = 3.00 M'
c. Panjang = 0.15 M'
d. Lebar = 0.60 M'
e. Pjg Besi (Stek+Angker) = 4.00 M'
f. Stek Besi Diameter = 8.00 MM
g. Jumlah Stek Besi = 8.00 Bh
h. Total Pjng Stek Besi = 96.00 M'
i. Beugel Besi Diameter = 10.00 MM
j. Jarak Beugel Besi = 0.15 MM
k. Pjg 1 Bh Beugel Besi = 1.35 M'
l. Jumlah Beugel Besi = 80.00 Bh
m. Tot.Pjng Beugel Besi = 108.00 M'
Berat Stek Besi 8 D13 mm = 0,006165*16mm*16mm*286,56 M' 37.88
= 37.88 Kg
Berat Beugel Besi Ø10-150 mm = 0,006165*8mm*8mm*250,74 M' 66.58
= 66.58 Kg
- Pekerjaan Beton ; Spesi 1:2:3 0.81
Dik : a. Jumlah = 3.00 M'
b. Panjang = 0.15 M'
c. Lebar = 0.60 M'
d. Tinggi = 3.00 M'
Vol. Cor Stump Beton 15x60 cm = 3 Set*(0,20*0,40*1,35) M'
= 0.81 M³
BESI BETON
RASIO BESI : BESI = 104.46 : 0.81
= 128.96 Kg/M³

1.b. Pekerjaan Ring Balok


1.b.1. Pekerjaan Ring Balok Uk.15x20 cm
- Pekerjaan Mall/ Bekisting 33.64
Dik : a. Panjang = 84.10 M'
b. Tinggi (2 Sisi) = 0.40 M'
Luasan Mall Sloof Uk.15x20 cm = 33.64 M²
- Pekerjaan Pembesian
Dik : a. Koefisien Besi = 0.006165
b. Panjang Balok = 84.10 M'
c. Tebal = 0.15 M'
d. Lebar = 0.20 M'
e. Stek Besi Diameter = 10.00 MM
f. Jumlah Stek Besi = 4.00 Bh
g. Total Pjng Stek Besi = 336.40 M'
h. Beugel Besi Diameter = 8.00 MM
i. Jarak Beugel Besi = 0.20 MM
j. Pjg 1 Bh Beugel Besi = 0.65 M'
k. Jumlah Beugel Besi = 421.50 Bh
l. Tot.Pjng Beugel Besi = 273.98 M'
Berat Stek Besi 4 D13 mm = 0,006165*13mm*13mm*685,20 M' 207.39
= 207.39 Kg
Berat Beugel Besi Ø8-200 mm = 0,006165*10mm*10mm*662,58 M' 108.10
= 108.10 Kg

Page 104 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
- Pekerjaan Beton; Spesi 1:2:3 2.52
Dik : a. Panjang = 84.10 M'
b. Tebal = 0.15 M'
c. Lebar = 0.20 M'
Vol. Pengecoran Balok 15x20 cm = 71,25 x 0,35 x 0,25 M'
= 2.52 M³
BESI BETON
RASIO SLOOF 25X35 CM = 315.49 : 2.52
= 125.05 Kg/M³

1.b.2. Pekerjaan Ring Balok Uk.15x40 cm


- Pekerjaan Mall/ Bekisting 6.08
Dik : a. Panjang = 7.60 M'
b. Tebal = 0.40
c. Lebar = 0.15
d. Tinggi (2 Sisi) = 0.80 M'
Luasan Mall Sloof Uk.15x40 cm = 6.08 M²
- Pekerjaan Pembesian
Dik : a. Koefisien Besi = 0.006165
b. Panjang Balok = 7.60 M'
c. Tebal = 0.40 M'
d. Lebar = 0.15 M'
e. Stek Besi Diameter = 13.00 MM
f. Jumlah Stek Besi = 6.00 Bh
g. Total Pjng Stek Besi = 45.60 M'
h. Beugel Besi Diameter = 8.00 MM
i. Jarak Beugel Besi = 0.20 MM
j. Pjg 1 Bh Beugel Besi = 0.45 M'
k. Jumlah Beugel Besi = 39.00 Bh
l. Tot.Pjng Beugel Besi = 17.55 M'
Berat Stek Besi 6 D13 mm = 0,006165*13mm*13mm*685,20 M' 47.51
= 47.51 Kg
Berat Beugel Besi Ø8-200 mm = 0,006165*10mm*10mm*662,58 M' 6.92
= 6.92 Kg
- Pekerjaan Beton; Spesi 1:2:3 0.46
Dik : a. Panjang = 7.60 M'
b. Tebal = 0.40 M'
c. Lebar = 0.15 M'
Vol. Pengecoran Balok 15x20 cm = 71,25 x 0,35 x 0,25 M'
= 0.46 M³
BESI BETON
RASIO SLOOF 25X35 CM = 54.43 : 0.46
= 119.37 Kg/M³

1.c.Pekerjaan Plat Lantai


1.c.1. Pekerjaan Plat Lantai Dudukan Tangki Air; Tbl.10 cm
- Pekerjaan Mall 4.28
Luasan Plat Lantai = 4.28
- Panjang = 2.85
- Lebar = 1.50

- Pek. Pembesian ø9 mm 46.29


Dik : a. Panjang Besi 92.70
2.85 - Pjng Besi = 285 cm = 2.85 M'
Jumlah Besi = 285 cm = 11.00 Bh
= 31.35 M'
2 Set Pjg Besi 285 cm = 62.70
- Pjng Besi = 150 cm = 1.50 M'

Page 105 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
Jumlah Besi =150 cm = 20.00 Bh
= 30.00 M'
b. Koef. Besi = 0.006165
c. Besi = 9.00 mm
d. Berat Besi = 46.29 Kg

- Pekerjaan Pengecoran Spesi 1:2:3 0.51


Dik : a. Luasan = 4.28 M'
b. Tebal = 0.12 M'
Vol. coran Plat Lantai Tbl. 10 cm = 418,76 * 0,20 M'
= 0.51 M³

RASIO BESI : BETON = 46.29 : 0.51


= 90.24

1.c.2. Pekerjaan Kanopy dan Janggutan


- Pekerjaan Mall 19.98
Luasan Plat Lantai = 19.98
- Panjang = 32.32
- Lebar = 1.00

- Pek. Pembesian ø9 mm 161.39


Dik : a. Panjang Besi 323.20
32.32 - Pjng Besi = 100 cm = 32.32 M'
Jumlah Besi =100 cm = 5.00 Bh
= 161.60 M'
1 Set Pjg Besi 323,2 cm = 161.60
- Pjng Besi = 323.2 cm = 1.00 M'
Jumlah Besi =323.2 cm = 161.60 Bh
= 161.60 M'
1 Set Pjg Besi 150 cm = 161.60
b. Koef. Besi = 0.006165
c. Besi = 9.00 mm
d. Berat Besi = 161.39 Kg

- Pekerjaan Pengecoran Spesi 1:2:3 1.60


Dik : a. Luasan = 19.98 M'
b. Tebal = 0.08 M'
Vol. coran Plat Lantai Tbl. 10 cm = 418,76 * 0,20 M'
= 1.60 M³

RASIO BESI : BETON = 161.39 : 1.60


= 100.97

1.c.3. Pekerjaan Plat Meja Dapur


- Pekerjaan Mall/ Bekisting 0.54
Dik : 1. Panjang = 0.90 M'
2. Lebar = 0.60 M'
Luasan Meja Dapur = 0,9 x 0,60 M'
= 0.54 M²
- Pekerjaan Pembesian Meja Dapur 9.29
Dik : a. Panjang Besi 6.20
- Pjng Besi = 80 cm = 0.80 M'
Jumlah Besi = 80 cm = 4.00 Bh
= 3.20 M'
- Pjng Besi = 60 cm = 0.60 M'
Jumlah Besi = 60cm = 5.00 Bh
= 3.00 M'

Page 106 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
b. Koef. Besi = 0.006165
c. Besi = 9.00 mm
d. Berat Besi = 3.10 Kg
3 Lapisan Pembesian Tikar = 9.29 Kg

- Pekerjaan Pengecoran K-175 0.05


Dik : a. Luas Area = 0.54 M²
b. Tebal = 0.10 M'
Vol. Pengecoran = 1,42 M² * 0,10 M'
= 0.05 M³
RASIO BESI : BESI BESI BETON
= 9.29 : 0.05
= 172.00 Kg/Cm³

II. PEKERJAAN DINDING


1) Pek.Pasangan Batu; Tebal 1/2 Bata; Spesi 1Pc : 4Psr 254.48
Dik: 1 Luasan Pas.Bata =
Arah X = 10.99+5.24+1.22+(1*16.06)+(3*2.62)
= 12.23+(2*6.3)+6.76+8.89+(2*14.09)+
= (2*3.89)+(2*(3.65+1.38))+2.42
= 130.29 M²
Arah Y = (3*13.9)+(4.63)+1.87+(3*4.13)+
= ((3*(3.65+1.3))+7.53+4.8+2.82+
= 13.69+2.82+11.17+5.92
= 124.19 M²
Luasan Pas.Dinding Bata Arah Y = 254.48 M²

III. PEKERJAAN PLESTERAN & ACIAN


1. Pekerjaan Plesteran Spesi 1Pc:4Psr
1.a. Pekerjaan Plesteran Pas. Bata 483.51
2. Pekerjaan Acian
2.1. Pekerjaan Acian Dinding Plesteran 483.51
2.2. Acian Plat Lantai, Kanopy, dan Janggutan 9.22
2.3. Acian Plat Kanopy 26.07
2.2. Acian Plat Lantai Janggutan 14.03

IV. PEKERJAAN KUSEN, DAUN PINTU JENDELA KAYU


Dik : 0.25 = 0.00635 M'
0.50 = 0.01270 M'
1.00 = 0.02540 M'
2.00 = 0.05080 M'
4.00 = 0.10160 M'
6.00 = 0.15240 M'
8.00 = 0.20320 M'
Vol. Kusen Per 1 mtr = 1.00000 M'
= (2 ichi x 6 inchi)x 100 cm
= (0,0508 M x 0,1524 M )x 1 M
= 0.00774192 M³
FAK. BUANG POTONG = 0.1000
FAK. BUANG POTONG = 0.0008
TOT. KUBIKASI KUSEN = 0.0085 m³ per meter

Vol. Kusen Per 1 mtr = 1.00000 M'


= (1 ichi x 4 inchi)x 100 cm
= (0,0254 M x 0,1016 M )x 1 M
= 0.00258064 M³
FAK. BUANG POTONG = 0.1000

Page 107 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
FAK. BUANG POTONG = 0.0003
TOT. KUBIKASI KUSEN = 0.0028 m³ per meter

1) Pekerjaan Kusen
1.1. Pekerjaan Kusen Pintu
- Kusen Pintu Gendong 0.46
Dik : 1 Jumlah Kusen = 5.00 Set
2 Panjang Kusen = 10.86 M'
3 Tot. Panjang Kusen = 54.30 M'
1.2. Pekerjaan Kusen Jendela
- Kusen Ventilasi (V= 0,40*0,60 M') 0.09
Dik : 1 Jumlah Kusen = 5.00 Set
2 Panjang Kusen = 2.00 M'
3 Tot. Panjang Kusen = 10.00 M'

2) Pekerjaan Daun Pintu


2.1. Daun Pintu (P-1); Uk.90x2,10 M' 9.45
Dik : 1 Jumlah Daun Pintu = 5.00 Set
2 Pjng Daun Pintu = 2.10 M'
3 Lebar Daun Pintu = 0.90 M'
4 Luasan Pintu = 9.45 M²
2.2. Daun Pintu Kamar Mandi (folding door) 5.00

3) Pekerjaan Daun Jendela


3.1. Daun Jendela(V-1); Uk.40x60 cm (Kombinasi Kaca) 1.20
Dik : 1 Jumlah Daun Pintu = 5.00 Set
2 Pjng Daun Pintu = 0.60 M'
3 Lebar Daun Pintu = 0.40 M'
4 Luasan Jendela = 1.20 M²
3.2. Daun Jendela(J-1); Uk.40x60 cm (Kombinasi Kaca) 3.88
Dik : 1 Jumlah Daun Pintu = 5.00 Set
2 Pjng Daun Pintu = 1.55 M'
3 Lebar Daun Pintu = 0.50 M'
4 Luasan Jendela = 3.88 M²

3.3. Pekerjaan Jalusi; Uk. 50x235 cm 1.18

V. PEKERJAAN PENGGANTUNG DAN KACA


1) Handle Pintu Dekkson Type 0820 (Full Set) 5.00
2) Pekerjaan Door Stopper Dekkson Type MDS 889 SN 5.00
3) Pekerjaan Engsel Pintu Dan Jendela
3.1. Pekerjaan Engsel Pintu Dekkson Ecoline 4x3x2MM 2BB SSS 10.00
3.2. Pek. Engsel Jendela Dekkson Ecoline 3x3x2MM 2BB SSS 20.00
4) Pekerjaan Rambuncis Dekkson Type CWH 103Z  10.00
5) Pekerjaan Kait Angin Dekkson Type WS 001 10" SSS 10.00
6) Pekerjaan Engsel Jungkit Dekkson Type ES SL 5" CP 20.00
7) Pekerjaan Kaca
7.1. Kaca Ventilasi 1.20
7.2. Kaca Jendela 3.88

VI. PEKERJAAN PELAPIS LANTAI DAN DINDING


1) Pek. Lantai Keramik; Asia Tile (setaranya) Uk. 20x20 ; unpolish
1.a. Area Kamar Mandi 8.80
- Jumlah Kamar Mandi = 5.000
- Luas Km.Mandi Kanan = 1.760
Tot.Luasan Km.Mandi = 8.800 M²

Page 108 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
1.b. Area Dapur 0.48
- Panjang = 0.800 M'
- Lebar = 0.600 M'
2) Pek. Lantai Keramik; Granit Ex. China; Uk. 60x60 43.80
Dik : 1 Luasan Lantai 1 Kamar = 8.76 M²
2 Jumlah Kamar Kamar = 5.00 Set
3 Tot. Luasan Lt. Kamar = 43.80 M²
3) Pekerjaan Lantai Teras; Granit Ex. China; Uk. 60x60
3.1. Area Teras dan Dapur 35.47
3.2. Area Tangga 11.09
4) Pek. Dinding Keramik; Asia Tile (setaranya) Uk. 20x40
4.1. Area Kamar MAndi 46.05
4.2. Area Dapur 3.84
5) Pek. Pelapis Kolom; Batu Alam Palimanan 11.72

VII. PEKERJAAN PLAFOND


1) Pekerjaan Rangka Plafond Gypsum (Sisi Dalam) 43.80
1.a. Pekerjaan Rangka Plafond
Dik 1 Luasan Plafond = 411.68
1.b. Pekerjaan Plafond Gypsum Jayaboard Tbl.9mm
2) Pekerjaan Plafond Gypsum (Sisi Dalam) 43.80
1.a. Pekerjaan Rangka Plafond
Dik 1 Luasan Plafond = 411.68
1.b. Pekerjaan Plafond Gypsum Jayaboard Tbl.9mm
3) Pekerjaan Rangka Plafond Gypsum (Sisi Luar) 33.56
4) Pekerjaan Plafond Gypsum (Area Selasar) 33.56
1.a. Pekerjaan Rangka Plafond
Dik 1 Luasan Plafond = 78.46

VIII. PEKERJAAN INSTALASI LISTRIK


1) Pek. Titik Lampu Dalam/ttk Bawah Plafond (Kabel NYM 2x1,5mm) 12.00
2) Pek. Titik Stop Kontak Biasa /ttk (Kabel NYM 3x1,5mm) 6.00
3) Pek. Titik Stop Kontak Khusus /ttk (Kabel NYM 3x2,5mm) 5.00
4) Pekerjaan Aarde/Pentanahan 2.00
5) Pekerjaan Box Sikring 6 Group 1.00

IX. PEKERJAAN SANITARY


1) Pekerjaan Roof Tank + Instalasi + Jet Pump 1.00
1) Pekerjaan Kloset Duduk Tidy (Setaranya) 5.00
2) Pekerjaan Floor Drain 5.00
3) Pekerjaan Kran Air Onda
3.a. Kran Tembok Onda 5.00
3.b. Kran Flexibel Onda 1.00
4) Pekerjaan Zink Sink 1 Lubang 1.00
5) Pekerjaan Shower
5.1. Spray Closet Onda 5.00
5.2. Shower Spray Onda 5.00
6) Pekerjaan Pipa Air
6.a. Pekerjaan Pipa Air Bersih (1/2") 28.44
6.b. Pekerjaan Air Buangan (2") 31.56
6.c. Pekerjaan Air Kotor (3") 32.90

X. PEKERJAAN BESI
1) Pekerjaan Pagar Pembatas 11.60
Dik. - Panjang = 11.60
- Lebar = 1.00

Page 109 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
2) Pekerjaan Besi Siku (Dudukan Tangki Air) 1.00

XI. PEKERJAAN PENGECATAN


1) Pengecatan Dengan Cat Air
1.1. Pekerjaan Pengecatan Dulux Wheatershield (Ekterior) 159.61
1.2. Pekerjaan Pengecatan Catylac (Interior) 316.70
- DInding Kamar Sisi Dalam = 193.20 M²
- Km. Mandi = 36.10 M²
- DInding Kamar Sisi Luar = 22.25 M²
- Area Dapur = 54.24 M²
- Tangga = 10.91 M²
2) Pekerjaan Mendempul Dan Menggosok Kayu
2.1. Bidang Kayu Kusen 14.25
- Kusen Pintu Gendong = 2.49 M²
- Kusen Ventilasi = 0.36 M²
Luasan/ Unit Kamar = 2.85 M²
5 Luasan/ Unit Kamar = 14.25 M²
2.2. Bidang Kayu Daun Pintu dan Jendela 21.40
- Daun Pintu = 3.52 M²
- Daun Jendela = 0.56 M²
- Ventilasi = 0.20 M²
Luasan/ Unit Kamar = 4.28 M²
5 Luasan/ Unit Kamar = 21.40 M²

3) Pengecatan Dengan Cat Kayu/Besi


3.1. Pekerjaan Pengecatan Kusen
3.1.a. Pekerjaan Pengecatan Kusen Pintu
3.1.a.1. Kusen Pintu Gendong 12.45
Dik : 1 Panjang Kusen = 2.49 M'
2 Jumlah = 5.00 M'
3 Luasan Pengecatan = 12.45 M²
3.1.b. Pekerjaan Pengecatan Kusen Jendela
- Kusen Ventilasi (V= 0,40*0,60 M') 1.80
Dik : 1 Panjang Kusen = 0.36 M'
2 Jumlah = 5.00 M'
3 Luasan Pengecatan = 1.80 M²
- Pekerjaan Jalusi Uk.20x235 cm 2.17
3.2. Pekerjaan Pengecatan Daun
3.2.a. Pekerjaan Pengecatan Daun Pintu 17.60
3.2.b. Pekerjaan Pengecatan Daun Jendela 2.80
3.2.c. Pekerjaan Pengecatan Daun Jendela Kamar Mandi 1.00

4) Pekerjaan Pengecatan Plafond 77.36


5) Pengecatan Besi
5.a. Pekerjaan Pengecatan Railing Besi 10.12
Dik: - Handle Railing = 5.82
Panjang ; 428 Cm = 0.68
Panjang ; 14 Cm = 0.10
Panjang ; 312 Cm = 0.55
Panjang ; 10 Cm = 0.50
Panjang ; 125 CM = 1.20
Panjang ; 116 CM = 0.50
Panjang ;35 CM = 0.15
Panjang ;54 CM = 0.20
Panjang ;44 CM = 0.40
- Tiang Railing = 1.54
5.a. Pekerjaan Pengecatan Besi Siku 0.77

Page 110 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
XII. PEKERJAAN PENUTUP ATAP
1) Pekerjaan Rangka Atap 104.11
2) Pekerjaan Atap Spandek 104.11
3) Pekerjaan Jurai Atap; Seng BJLS 7.78
4) Pekerjaan Kalsiplank 9.98

Page 111 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

VOLUME PEKERJAAN
ELEVASI - 20.00 s/d 3.70 METER
Perihal : Rekapitulasi Harga Satuan Pekerjaan
Periode : Tahun Anggaran 2019
Klasifikasi : Menengah
Proyek : Renovasi
Lokasi : Medan
Wilayah : Deli Serdang

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
I. PEKERJAAN PERSIAPAN
1) Sewa Scafolding Selama 2 Bulan 2,500.00
Dik : 1. Pjg Bangunan = 12.00 M'
2. Lbr Bangunan = 10.00 M'
3. Lebar Scafolding = 1.20 M'
4. Tinggi Scafolding = 1.70 M'
5. Tinggi Bangunan = 4.00 M'
6. Durasi Scafolding = 2.00 Bulan
= 60.00 Hari
Arah X
Jwb : = ((2x (Panjang + Lebar))) x Tinggi Bangunan
/Luasan Scafolding x Durasi Scafolding
= ((2*(21,65 + 24,45))) x 8 M' / (1,20x1,70 M')
= 41.67 Set/ Hari
= 2,500.00 Set/ 60 Hari

2) Pekerjaan Pengukuran & Bowplank 44.00


Dik : 1. Panjang = 10 M'
2. Lebar = 12 M'
Jwb : = 2x(Panjang + Lebar)
= 2*(21,65 + 24,45)
= 44.00 M'
II. PEKERJAAN TANAH
1) Pekerjaan Galian Tanah Pondasi Menerus Di Bawah Sloof Uk.15x20 cm 9.79
Dik : 1. Panjang = 25.10 M'
2. Lebar = 0.60 M'
3. Kedalaman = 0.65 M'
- Urugan Pasir = 0.05 M'
- Batu Kosong = 0.10 M'
- Batu Kali = 0.50 M'
Vol. = Panjang x Lebar x Kedalaman
= 107,58 x(0,60x0,65x0,55) M
= 9.79 M³
2) Pekerjaan Galian Tanah Pondasi Menerus Di Bawah Sloof Uk.15x50 cm 13.60
Dik : 1. Panjang = 41.84 M'
2. Lebar = 0.50 M'
3. Kedalaman = 0.65 M'
- Urugan Pasir = 0.05 M'
- Batu Kosong = 0.10 M'
- Batu Kali = 0.50 M'
Vol. = Panjang x Lebar x Kedalaman
= 107,58 x(0,60x0,65x0,55) M
= 13.60 M³
3) Galian Tanah Pondasi Telapak
3.1. Pondasi Telapak; Uk.55x100 cm; (P-1) 7.80
Dik : 1. Jumlah P.T. Uk.55 x 100cm = 12.00 Set
2. Panjang = 0.50 M'

Page 112 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
3. Lebar = 1.00 M'
4. Kedalaman = 1.30 M'
Vol. = Jumlah P.T.*Panjang x Lebar x Kedalaman
= 16 Set x (1,20x1,40x1,00) M
= 7.80 M³
3.2. Pondasi Telapak; Uk.70x100 cm; (P-2) 0.91
Dik : 1. Jumlah P.T. Uk. 70 x 100cm = 1.00 Set
2. Panjang = 0.70 M'
3. Lebar = 1.00 M'
4. Kedalaman = 1.30 M'
Vol. = Jumlah P.T.*Panjang x Lebar x Kedalaman
= 2 Set x (0,80x1,20x1,00) M
= 0.91 M³

4) Galian Tanah Sloof


4.1. Sloof Uk.15x20 cm 0.75
Dik : 1. Lebar = 0.15 M'
2. Tebal = 0.20 M'
3. Panjang = 25.10 M'
Vol. = Lebar x Tebal x Panjang
= 0,20 x 0,25 x 107,58 M'
= 0.75 M³
4.2. Sloof Uk.15x50 cm 2.74
Dik : 1. Lebar = 0.15 M'
2. Tebal = 0.40 M'
3. Panjang = 45.61 M'

Vol. = Lebar x Tebal x Panjang


= 0,35 x0,45 x 85,65 M'
= 2.74 M³

5) Pekerjaan Urugan Tanah Kembali


5.1. Pekerjaan Urugan Tanah Pondasi Telapak 1.35
Dik : 1 Vol. Galian P.T.-1 = 7.80 M³
2 Vol. Galian P.T.-2 = 0.91 M³
3 Volume Lt. Kerja = 0.87 M³
4 Vol. Foot Plate = 1.80 M³
5 Vol. Stump Beton = 3.78 M³
Sisa Urugan Tanah = 1.35 M³
6) Pekerjaan Timbunan; Tebal=40 cm
6.1.a. Peninggian Lantai; Tanah Didatangkan; Tbl.10 cm 18.18
Dik : 1. Sisa Urugan Tanah = 1.35 M³
2. Tinggi TimbunTanah = 0.20 M'
Tebal Sloof = 0.50 M'
Tebal Plat Lantai = 0.15 M'
Tebal Sirtu = 0.10 M'
Tebal Tanah = 0.20 M'
3. Luas Area Bangunan = 97.64 M²
Area Serbaguna = 118.91 M²
Area Admin + Kantor = 118.91 M²
Area Km.Mandi (Kiri) = 6.89 M²
Area Gudang = 3.21 M²
Area Selasar +Lobby = 116.84 M²
Janitor = 2.64 M²
Rg.Ganti = 3.21 M²
Km.Mandi = 3.21 M²
Rg.Konsistori = 44.96 M²
Selasar Luar = 81.96 M²

Page 113 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
Volume Timbunan Tanah = (Tbl Tanah x Luas Area Bangunan)
- Sisa Urugan Tanah
= (0,10x500,72) - (46,29)
= 18.18 M³
6.1.b. Peninggian Lantai; Timbunan Sirtu ; Tebal 10 cm 9.76
Dik : 1. Tinggi Timbun Sirtu = 0.10 M'
2. Luas Area Bangunan = 97.64 M²
Volume Timbunan Sirtu = 9.76 M³

7) Pekerjaan Pemadatan
7.1. Pemadatan Tanah Timbun 18.18
7.2. Pemadatan Sirtu 9.76

II. PEKERJAAN PONDASI


II.A. PEKERAAN PONDASI DANGKAL
1) Pekerjaan Pondasi Menerus
1.1. Pekerjaan Lantai Kerja Pondasi
a. Pekerjaan Pasir Urug; Tbl. 5 cm 0.75
Dik : a. Lebar = 0.60 M'
b. Panjang = 25.10 M'
c. Tebal = 0.05 M'
Volume Pek.Batu Kali (Retaining) = 0.75 M³
b. Pekerjaan Pasangan Batu Kosong; Tbl. 5 cm 0.75
Dik : a. Lebar = 0.60 M'
b. Panjang = 25.10 M'
c. Tebal = 0.05 M'
Volume Pek.Batu Kosong = 0.75 M³

1.2. Pekerjaan Pondasi Menerus 6.93


Dik : a. Lebar Pnmpng Atas = 0.25 M'
b. Lebar Pnmpng Bwh = 0.60 M'
c. Lebar Penampang = 0.43 M'
d. Tinggi = 0.65 M'
e. Panjang = 25.10 M'
Volume Pondasi Pek.Batu Kali = 6.93 M³

II.B. PEKERAAN PONDASI DALAM


1 Pekerjaan Pondasi Plat Setempat
1.1. Pondasi Plat Setempat Uk.0,55 x1,10 M'; (P-1)
1.1.a. Pekerjaan Lantai Kerja
1.1.a.1. Pekerjaan Urugan Pasir 0.40
Dik : - Jumlah = 12.00 Set
- Panjang = 0.60
- Lebar = 1.10
- Tebal = 0.05
- Volume = 0.40
1.1.a.2. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 0.40
Dik : - Jumlah = 12.00 Set
- Panjang = 0.60
- Lebar = 1.10
- Tebal = 0.05
- Volume = 0.40
1.1.b. Pekerjaan Mall/ Bekisting 10.80
Dik : 1. Jumlah = 12.00 Set
2. Panjang = 0.50 M'
3. Lebar = 1.00 M'
4. Tebal Foot Plate = 0.30 M'
Luasan 1 Bh Mall Foot Plate = 0,3*(1,0+1,0+1,2+1,2)

Page 114 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
= 0.90 M²
Luasan 18 Bh Mall Foot Plate = 18 x 1,80 M²
= 10.80 M²
1.1.c. Pekerjaan Pembesian; D10 - 150 mm 276.31
Dik : 1 Koefisien Besi = 0.006165
2 Jumlah = 12.00 M'
3 Panjang = 0.50 M'
4 Lebar = 1.00 M'
5 Tebal Foot Plate = 0.30 M'
6 Stek Besi Diameter = 13.00 MM
7 Jarak Stek Besi = 0.200 M'
8 Jumlah Stek Besi (X) = 3.50 Bh
9 Jumlah Stek Besi (Y) = 6.00 Bh
10 Jumlah Stek Besi (Z) = 1.00 Bh
11 Pjng Stek Besi (X) = 1.40 M'
12 Pjng Stek Besi (Y) = 2.40 M'
13 Pjng Stek Besi (Z) = 2.80 M'
14 Tot. Pjng Stek Besi (X) = 4.90 M'
15 Tot. Pjng Stek Besi (Y) = 14.40 M'
16 Tot. Pjng Stek Besi (Z) = 2.80 M'
17 Tot.Pjg Besi (X)+(Y) = 22.10 M'
18 Tot.Pjg Besi (X)+(Y) = 265.20 M'
Berat Stek Besi 8D16 - 100 mm = 0,006165*16mm*16mm*1072 M'
= 276.31 Kg
1.1.d. Pengecoran K-250 (fc'=21.7 Mpa), Slump (12+2) 1.80
Dik : a. Jumlah = 12.00 Set
b. Tebal = 0.50 M'
c. Lebar = 1.00 M'
d. Tebal Foot Plate = 0.30 M'
Vol. Pengecoran Foot Plate = 16 Set*(1,0*1,2*0,3) M'
= 1.80 M³
BESI BETON
RASIO Foot Plate = 276.31 : 1.80
= 153.50 Kg/M³

1.2. Pondasi Plat Setempat Uk.70x110 cm'; (P-5')


1.2.a. Pekerjaan Lantai Kerja
1.2.a.1. Pekerjaan Urugan Pasir 0.04
Dik : - Jumlah = 1.00 Set
- Panjang = 0.70 M'
- Lebar = 1.10 M'
- Tebal = 0.05 M'
- Volume = 0.04 M³
1.2.a.2. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 0.04
Dik : - Jumlah = 1.00 Set
- Panjang = 0.70 M'
- Lebar = 1.10 M'
- Tebal = 0.05 M'
- Volume = 0.04 M³
1.2.b. Pekerjaan Mall/ Bekisting 1.08
Dik : - Jumlah = 1.00 Set
- Panjang = 0.70 M'
- Lebar = 1.10 M'
- Tebal Foot Plate = 0.30 M'
Luasan 1 Bh Mall Foot Plate = 0,3*(1,5+1,5+1,5+1,5)
= 1.08 M²
Luasan 18 Bh Mall Foot Plate = 18 x 1,80 M²
= 1.08 M²

Page 115 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
1.2.c. Pekerjaan Pembesian D13 - 150 mm 36.74
Dik : 1 Koefisien Besi = 0.006165
2 Jumlah = 1.00 M'
3 Panjang = 0.70 M'
4 Lebar = 1.10 M'
5 Tebal Foot Plate = 0.30 M'
6 Stek Besi Diameter = 13.00 MM
7 Jarak Stek Besi = 0.150 M'
8 Jumlah Stek Besi (X) = 5.67 Bh
9 Jumlah Stek Besi (Y) = 8.33 Bh
10 Jumlah Stek Besi (Z) = 1.00 Bh
11 Pjng Stek Besi (X) = 1.80 M'
12 Pjng Stek Besi (Y) = 2.60 M'
13 Pjng Stek Besi (Z) = 3.40 M'
14 Tot. Pjng Stek Besi (X) = 10.20 M'
15 Tot. Pjng Stek Besi (Y) = 21.67 M'
16 Tot. Pjng Stek Besi (Z) = 3.40 M'
17 Tot.Pjg Besi (X)+(Y)+(Z) = 35.27 M'
18 Tot.Pjg Besi (X)+(Y)+(Z) = 35.27 M'
Berat Stek Besi D13 - 150 mm = 0,006165*16mm*16mm*81,20 M'
= 36.74 Kg
1.2.d. Pengecoran K-250 (fc'=21.7 Mpa), Slump (12+2) 0.23
Dik : a. Panjang = 1.00 M'
b. Tebal = 0.70 M'
c. Lebar = 1.10 M'
d. Tebal Foot Plate = 0.30 M'
Vol. Pengecoran Foot Plate = 2 Set*(1,0*1,4*0,3) M'
= 0.23 M³
BESI BETON
RASIO Foot Plate = 36.74 : 0.23
= 159.06 Kg/M³

III. PEKERJAAN BETON


1. Pek. Beton K-250; (fc'=21.7 Mpa), Slump (12+2),w/c=0,56
1.1. Stump Beton Uk. 15x60 cm (K-1); s/d Elv.Lantai (±0,00)
1.1.a. Pekerjaan Mall/ Bekisting (K-1) 21.60
Dik : 1. Jumlah = 12.00 Set
2. Panjang = 0.15 M'
3. Lebar = 0.60 M'
4. Tinggi = 1.20 M'
Luasan 1 Bh Stump Beton = (2*(0,6+0,6))*1,70 M'
= 1.80 M²
Luasan 12 Bh Stump Beton = 20 x 1,62 M²
= 21.60 M²
1.1.b. Pekerjaan Pembesian (K-1)
Dik : a. Koefisien Besi = 0.006165
b. Jumlah Stump Beton = 12.00 M'
c. Panjang = 0.15 M'
d. Lebar = 0.60 M'
e. Pjg Besi (Stek+Angker) = 1.65 M'
Angker Besi = 0.45 M'
Stek Besi s/d Sloof = 0.60 M'
Sloof = 0.60 M'
f. Stek Besi Diameter = 13.00 MM
g. Jumlah Stek Besi = 8.00 Bh
h. Total Pjng Stek Besi = 158.40 M'
i. Beugel Besi Diameter = 8.00 MM

Page 116 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
j. Jarak Beugel Besi = 0.15 MM
k. Pjg 1 Bh Beugel Besi = 1.35 M'
l. Jumlah Beugel Besi = 132.00 Bh
m. Tot.Pjng Beugel Besi = 178.20 M'
Berat Stek Besi 8 D13 mm = 0,006165*16mm*16mm*936 M' 165.03
= 165.03 Kg
Berat Beugel Besi Ø8-150 mm = 0,006165*10mm*10mm*702 M' 70.31
= 70.31 Kg
1.1.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 3.46
Dik : a. Jumlah = 12.00 M'
b. Panjang = 0.15 M'
c. Lebar = 0.60 M'
d. Tinggi = 3.20 M'
Vol. Cor Stump Beton 15x60 cm = 18 Set*(0,20*0,40*1,35) M'
= 3.46 M³
BESI BETON
RASIO BESI : BESI = 235.35 : 3.46
= 68.10 Kg/Cm³

1.2. Pekerjaan Stump Beton Uk. 30x60 cm (K-2)


1.2.a. Pekerjaan Mall/ Bekisting 2.16
Dik : 1. Jumlah = 1.00 Set
2. Panjang = 0.30 M'
3. Lebar = 0.60 M'
4. Tinggi = 1.20 M'
Luasan 1 Bh Stump Beton = (2*(0,3+0,6))*4 M'
= 2.16 M²
1.2.b. Pekerjaan Pembesian K-2
Dik : a. Koefisien Besi = 0.006165
b. Jumlah Stump Beton = 1.00 M'
c. Panjang = 0.30 M'
d. Lebar = 0.60 M'
e. Pjg Besi (Stek+Angker) = 1.65 M'
f. Stek Besi Diameter = 13.00 MM
g. Jumlah Stek Besi = 14.00 Bh
h. Total Pjng Stek Besi = 23.10 M'
i. Beugel Besi Diameter = 8.00 MM
j. Jarak Beugel Besi = 0.15 MM
k. Pjg 1 Bh Beugel Besi = 1.65 M'
l. Jumlah Beugel Besi = 11.00 Bh
m. Tot.Pjng Beugel Besi = 18.15 M'
Berat Stek Besi 16 D16 mm = 0,006165*16mm*16mm*936 M' 24.07
= 24.07 Kg
Berat Beugel Besi Ø10-100 mm = 0,006165*10mm*10mm*702 M' 7.16
= 7.16 Kg
1.2.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 0.30
Dik : a. Jumlah = 1.00 M'
b. Panjang = 0.30 M'
c. Lebar = 0.60 M'
d. Tinggi = 1.65 M'
Vol. Cor Stump Beton 20x40 cm = 18 Set*(0,20*0,40*1,35) M'
= 0.30 M³
BESI BETON
RASIO BESI : BESI = 31.23 : 0.30
= 105.15 Kg/Cm³

2. Pekerjaan Beton K-250; (fc'=21.7 Mpa), Slump (12+2),w/c=0,56


2.1. Pekerjaan Kolom Struktur Uk. 15x15 cm (K-1)

Page 117 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
2.1.a. Pekerjaan Mall/ Bekisting 50.40
Dik : 1. Jumlah = 21.00 Set
2. Panjang = 0.15 M'
3. Lebar = 0.15 M'
4. Tinggi = 4.00 M'
Luasan 1 Bh Mall = (2*(0,15+0,15))*4 M'
= 2.40 M²
Luasan 20 Bh Mall = 20 x 1,62 M²
= 50.40 M²
2.1.b. Pek. Pembesian Kolom Uk.15x15 cm
Dik : a. Koefisien Besi = 0.006165
b. Jumlah Kolom = 21.00 M'
c. Panjang = 0.15 M'
d. Lebar = 0.15 M'
e. Pjg Besi (Stek+Angker) = 4.00 M'
f. Stek Besi Diameter = 10.00 MM
g. Jumlah Stek Besi = 4.00 Bh
h. Total Pjng Stek Besi = 336.00 M'
i. Beugel Besi Diameter = 8.00 MM
j. Jarak Beugel Besi = 0.20 MM
k. Pjg 1 Bh Beugel Besi = 0.45 M'
l. Jumlah Beugel Besi = 420.00 Bh
m. Tot.Pjng Beugel Besi = 189.00 M'
Berat Stek Besi 4 D10 mm = 0,006165*16mm*16mm*286,56 M' 207.14
= 207.14 Kg
Berat Beugel Besi Ø10-200 mm = 0,006165*8mm*8mm*250,74 M' 74.57
= 74.57 Kg
2.1.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 1.89
Dik : a. Jumlah = 21.00 M'
b. Panjang = 0.15 M'
c. Lebar = 0.15 M'
d. Tinggi = 4.00 M'
Vol. Cor Stump Beton 30x40 cm = 18 Set*(0,20*0,40*1,35) M'
= 1.89 M³
BESI BETON
RASIO BESI : BESI = 281.72 : 1.89
= 149.06 Kg/M³

2.2. Pekerjaan Kolom Struktur Uk. 15x60cm (K-2)


2.2.a. Pekerjaan Mall/ Bekisting 63.00
Dik : 1. Jumlah = 12.00 Set
2. Panjang = 0.15 M'
3. Lebar = 0.60 M'
4. Tinggi = 3.50 M'
Luasan 1 Bh Mall = (2*(0,15+0,50))*3.50M'
= 5.25 M²
Luasan 12 Bh Mall = 12 x 1,62 M²
= 63.00 M²
2.2.b. Pek. Pembesian Kolom Uk.15x60 cm
Dik : a. Koefisien Besi = 0.006165
b. Jumlah Stump Beton = 12.00 M'
c. Panjang = 0.15 M'
d. Lebar = 0.60 M'
e. Pjg Besi (Stek+Angker) = 4.50 M'
f. Stek Besi Diameter = 13.00 MM
g. Jumlah Stek Besi = 8.00 Bh
h. Total Pjng Stek Besi = 432.00 M'
i. Beugel Besi Diameter = 8.00 MM

Page 118 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
j. Jarak Beugel Besi = 0.20 MM
k. Pjg 1 Bh Beugel Besi = 1.35 M'
l. Jumlah Beugel Besi = 270.00 Bh
m. Tot.Pjng Beugel Besi = 364.50 M'
Berat Stek Besi 8 D13 mm = 0,006165*16mm*16mm*286,56 M' 450.09
= 450.09 Kg
Berat Beugel Besi Ø10-200 mm = 0,006165*8mm*8mm*250,74 M' 143.82
= 143.82 Kg
2.2.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 3.78
Dik : a. Jumlah = 12.00 M'
b. Panjang = 0.15 M'
c. Lebar = 0.60 M'
d. Tinggi = 3.50 M'
Vol. Cor Stump Beton 30x40 cm = 18 Set*(0,20*0,40*1,35) M'
= 3.78 M³
BESI BETON
RASIO BESI : BESI = 593.91 : 3.78
= 157.12 Kg/M³

2.3. Pekerjaan Kolom Struktur Uk. 30x60cm (K-3)


2.3.a. Pekerjaan Mall/ Bekisting 6.30
Dik : 1. Jumlah = 1.00 Set
2. Panjang = 0.30 M'
3. Lebar = 0.60 M'
4. Tinggi = 3.50 M'
Luasan 1 Bh Stump Beton = (2*(0,2+0,4))*1,35 M'
= 6.30 M²
Luasan 20 Bh Stump Beton = 20 x 1,62 M²
= 6.30 M²
2.3.b. Pek. Pembesian Kolom Uk.30x60 cm (K-2)
Dik : a. Koefisien Besi = 0.006165
b. Jumlah Stump Beton = 1.00 M'
c. Panjang = 0.30 M'
d. Lebar = 0.60 M'
e. Tinggi = 3.50 M'
Joint Stek Besi = 0.52 M'
f. Stek Besi Diameter = 13.00 MM
g. Jumlah Stek Besi = 18.00 Bh
h. Total Pjng Stek Besi = 72.36 M'
i. Beugel Besi Diameter = 8.00 MM
j. Jarak Beugel Besi = 0.15 MM
k. Pjg 1 Bh Beugel Besi = 1.65 M'
l. Jumlah Beugel Besi = 26.80 Bh
m. Tot.Pjng Beugel Besi = 44.22 M'
Berat Stek Besi 18 D13 mm = 0,006165*13mm*13mm*72,36 M' 75.39
= 75.39 Kg
Berat Beugel Besi Ø8-150 mm = 0,006165*8mm*8mm*250,74 M' 17.45
= 17.45 Kg
2.3.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) (K-4) 0.63
Dik : a. Jumlah = 1.00 M'
b. Panjang = 0.30 M'
c. Lebar = 0.60 M'
d. Tinggi = 3.50 M'
Vol. Cor Stump Beton 30x60 cm = 1 Set*(0,30*0,60*1,35) M'
= 0.63 M³
BESI BETON
RASIO BESI : BESI = 92.84 : 0.63
= 147.36 Kg/M³

Page 119 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)

2.4. Pekerjaan Sloof Uk.15x20 cm


2.4.a. Pekerjaan Mall/ Bekisting 10.04
Dik : a. Panjang = 25.10 M'
b. Tinggi (2 Sisi) = 0.40 M'
Luasan Mall Sloof Uk.25x35 cm = 10.04 M²
2.4.b. Pekerjaan Pembesian
Dik : a. Koefisien Besi = 0.006165
b. Panjang Balok = 25.10 M'
c. Tebal = 0.20 M'
d. Lebar = 0.15 M'
e. Stek Besi Diameter = 10.00 MM
f. Jumlah Stek Besi = 4.00 Bh
g. Total Pjng Stek Besi = 100.40 M'
h. Beugel Besi Diameter = 8.00 MM
i. Jarak Beugel Besi = 0.15 MM
j. Pjg 1 Bh Beugel Besi = 0.45 M'
k. Jumlah Beugel Besi = 168.33 Bh
l. Tot.Pjng Beugel Besi = 75.75 M'
Berat Stek Besi 8 D10 mm = 0,006165*13mm*13mm*685,20 M' 61.90
= 61.90 Kg
Berat Beugel Besi Ø8-100 mm = 0,006165*10mm*10mm*662,58 M' 29.89
= 29.89 Kg
2.4.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 0.75
Dik : a. Panjang = 25.10 M'
b. Tebal = 0.20 M'
c. Lebar = 0.15 M'
Vol. Pengecoran Balok 15x20 cm = 71,25 x 0,35 x 0,25 M'
= 0.75 M³
BESI BETON
RASIO SLOOF 25X35 CM = 91.78 : 0.75
= 121.89 Kg/M³

2.5. Pekerjaan Sloof Uk.15x50 cm


2.5.a. Pekerjaan Mall/ Bekisting 45.61
Dik : a. Panjang = 45.61 M'
b. Tinggi (2 Sisi) = 1.00 M'
Luasan Mall Sloof Uk.15x50 cm = 45.61 M²
2.5.b. Pekerjaan Pembesian
Dik : a. Koefisien Besi = 0.006165
b. Panjang Sloof = 45.61 M'
c. Tebal = 0.40 M'
d. Lebar = 0.15 M'
e. Stek Besi Diameter = 13.00 MM
f. Jumlah Stek Besi = 8.00 Bh
g. Total Pjng Stek Besi = 364.88 M'
k. Beugel Besi Diameter = 8.00 MM
l. Jarak Beugel Besi = 0.20 MM
m. Pjg 1 Bh Beugel Besi = 0.95 M'
n. Jumlah Beugel Besi = 229.05 Bh
o. Tot.Pjng Beugel Besi = 217.60 M'
Berat Stek Besi 8 D10 mm = 0,006165*16mm*16mm*65,60M' 380.16
= 380.16 Kg
Berat Beugel Besi Ø8-200 mm = 0,006165*10 mm*10 mm*95,45 M' 85.86
= 85.86 Kg
2.5.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 2.74
Dik : a. Panjang = 45.61 M'
b. Tebal = 0.40 M'

Page 120 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
c. Lebar = 0.15 M'
Vol. Pengecoran Balok 20x20 cm = 71,25 x 0,35 x 0,25 M'
= 2.74 M³
BESI BETON
RASIO SLOOF 25X35 CM = 466.02 : 2.74
= 170.29 Kg/M³

2.6. Pekerjaan Plat Lantai Dasar; Tbl.10 cm


2.6.a. Pekerjaan Pembesian; Wiremesh M-6 653.86
Dik : a. Luasan Lantai = 120.00 M²
b. Wire Mesh 1 Lapis = 120.00 M²
Wiremesh Arah (Atas) = 120.00 M²
Cat: Wire mesh Uk.2,1 x 5,4 M' = 61.79 Kg/Lbr
11.34 = 61.79 Kg/Lbr
Luasan Wire Mesh 759,58 M² = (120/2,1x5,4) * 61,79
= 653.86 Kg/ 120 M²
2.6.b. Pek. Pengelasan (Joint Wire Mesh ke Stek Besi Sloof) 255.50
Dik : a. Jumlah Joint Las = 25550.00 Cm'

Arah X = 26.90 M'


= 135.50 M'
Konversi ke Centimeter = 13550.00 Cm'
Arah Y = 23.80 M'
= 120.00 M'
Konversi ke Centimeter = 12000.00 Cm'
b. Jarak Pengelasan = 0.20 M'
c. Panjang Pengelasan = 0.01 Cm
d. Tot.Pjg Pengelasan = 255.50 Cm'
2.6.c. Pekerjaan Pengecoran; Spesi 1:3:5 12.00
Dik : a. Luasan = 120.00 M'
b. Tebal = 0.10 M'
Vol. coran Plat Lantai Tbl. 10 cm = 418,76 * 0,20 M'
= 12.00 M³

2.7. Pekerjaan Tangga


2.7.a. Pekerjaan Mall/Bekisting 8.56
- Plat Tangga
Dik : 1 Luasan 1 Plat Tangga = 0.23 M²
2 Jumlah Tangga (Set) = 15.00 Set
3 Luasan Tangga = 3.40 M²
- Plat Bordes + Mezzanine
Dik : 1 Luasan = 5.15 M²
2 Jumlah = 1.00 Set
3 Luasan Tangga = 5.15 M²
Total Luasan Mall = 8.56
2.7.b. Pekerjaan Pembesian
- Plat Tangga
Dik : 1. Koefisien Besi = 0.006165
2. Lebar Tangga = 0.27 M'
3. Panjang Tangga = 0.84 M'
4. Besi Plat = 10.00 mm
5. Jumlah Plat Tangga = 19.00 mm
Total Pjng Besi Ø13mm = 9.36 M'
Jarak Besi Arah X = 5.40 M'
Jarak Besi Arah Y = 3.96 M'
6. Total Pjng Besi Ø13 mm = 177.84 M'
- Berat Besi Ø13mm = 0,006165*13*13*80,66 M 219.28
= 109.64 Kg

Page 121 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
1 Set Tangga = 219.28 Kg
2.7.c. Pekerjaan Pengecoran K-250 (fc'=21.7 Mpa), Slump (12+2) 0.43
Dik : a. Jumlah Tangga (Set) = 19.00 Set
b. Luasan 1 Tangga = 0.23 M'
c. Tebal = 0.10 M'
Vol. Pengecoran Plat Tangga = 19 * (0.23*0,10)
= 0.43 M³
Rasio Besi : Beton = 219.28 : 0.43
= 508.86

- Plat Mezzanine
Dik : 1. Koefisien Besi = 0.006165
2. Lebar Tangga = 0.89 M'
3. Panjang Tangga = 5.79 M'
4. Besi Plat = 13.00 mm
5. Jumlah Plat Tangga = 1.00 mm
Total Pjng Besi Ø13mm = 51.53 M'
Jarak Besi Arah X = 25.77 M'
Jarak Besi Arah Y = 25.77 M'
6. Total Pjng Besi Ø13 mm = 51.53 M'
- Berat Besi Ø13mm = 0,006165*13*13*80,66 M 107.38
= 53.69 Kg
1 Set Tangga = 107.38 Kg
2.7.c. Pekerjaan Pengecoran K-250 (fc'=21.7 Mpa), Slump (12+2) 0.43
Dik : a. Jumlah Tangga (Set) = 19.00 Set
b. Luasan 1 Tangga = 0.23 M'
c. Tebal = 0.10 M'
Vol. Pengecoran Plat Tangga = 19 * (0.23*0,10)
= 0.43 M³
Rasio Besi : Beton = 107.38 : 0.43
= 249.18

2.8. Pekerjaan Ring Balok Uk.15x20 cm


2.8.a. Pekerjaan Mall/ Bekisting 10.04
Dik : a. Panjang = 25.10 M'
b. Tinggi (2 Sisi) = 0.40 M'
Luasan Mall Sloof Uk.15x20 cm = 10.04 M²
2.8.b. Pekerjaan Pembesian
Dik : a. Koefisien Besi = 0.006165
b. Panjang Balok = 25.10 M'
c. Tebal = 0.15 M'
d. Lebar = 0.20 M'
e. Stek Besi Diameter = 10.00 MM
f. Jumlah Stek Besi = 4.00 Bh
g. Total Pjng Stek Besi = 100.40 M'
h. Beugel Besi Diameter = 8.00 MM
i. Jarak Beugel Besi = 0.20 MM
j. Pjg 1 Bh Beugel Besi = 0.65 M'
k. Jumlah Beugel Besi = 126.50 Bh
l. Tot.Pjng Beugel Besi = 82.23 M'
Berat Stek Besi 4 D13 mm = 0,006165*13mm*13mm*685,20 M' 61.90
= 61.90 Kg
Berat Beugel Besi Ø8-100 mm = 0,006165*10mm*10mm*662,58 M' 32.44
= 32.44 Kg
2.8.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 0.75
Dik : a. Panjang = 25.10 M'
b. Tebal = 0.15 M'
c. Lebar = 0.20 M'

Page 122 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
Vol. Pengecoran Balok 15x20 cm = 71,25 x 0,35 x 0,25 M'
= 0.75 M³
BESI BETON
RASIO SLOOF 25X35 CM = 94.34 : 0.75
= 125.28 Kg/M³

2.9. Pekerjaan Ring Balok Uk.15x50 cm


2.9.a. Pekerjaan Mall/ Bekisting 45.61
Dik : a. Panjang = 45.61 M'
b. Tinggi = 0.50 M'
c. Tinggi (2 Sisi) = 1.00 M'
Luasan Mall Sloof Uk.15x50 cm = 45.61 M²
2.9.b. Pekerjaan Pembesian
Dik : a. Koefisien Besi = 0.006165
b. Panjang Ring Balok = 45.61 M'
c. Tebal = 0.60 M'
d. Lebar = 0.15 M'
e. Stek Besi Diameter = 13.00 MM
f. Jumlah Stek Besi = 10.00 Bh
g. Total Pjng Stek Besi = 456.10 M'
k. Beugel Besi Diameter = 8.00 MM
l. Jarak Beugel Besi = 0.15 MM
m. Pjg 1 Bh Beugel Besi = 1.35 M'
n. Jumlah Beugel Besi = 305.07 Bh
o. Tot.Pjng Beugel Besi = 411.84 M'
Berat Stek Besi 10 D13 mm = 0,006165*16mm*16mm*65,60M' 475.20
= 475.20 Kg
Berat Beugel Besi Ø8-100 mm = 0,006165*10 mm*10 mm*95,45 M' 162.50
= 162.50 Kg
2.9.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 4.10
Dik : a. Panjang = 45.61 M'
b. Tebal = 0.60 M'
c. Lebar = 0.15 M'
Vol. Pengecoran Balok 15x60 cm = 45.61 x 0,15 x 0,60 M'
= 4.10 M³
BESI BETON
RASIO SLOOF 15X60 CM = 637.70 : 4.10
= 155.35 Kg/M³

2.10. Pekerjaan Ring Balok Tangga; Uk.15x40 cm


2.10.a. Pekerjaan Mall/ Bekisting 3.90
Dik : a. Panjang = 4.88 M'
b. Tinggi (2 Sisi) = 0.80 M'
Luasan Mall Balok Uk.15x40 cm = 3.90 M²
2.10.b. Pekerjaan Pembesian
Dik : a. Koefisien Besi = 0.006165
b. Panjang Ring Balok = 4.88 M'
c. Tebal = 0.60 M'
d. Lebar = 0.15 M'
e. Stek Besi Diameter = 13.00 MM
f. Jumlah Stek Besi = 6.00 Bh
g. Total Pjng Stek Besi = 29.28 M'
k. Beugel Besi Diameter = 8.00 MM
l. Jarak Beugel Besi = 0.20 MM
m. Pjg 1 Bh Beugel Besi = 1.35 M'
n. Jumlah Beugel Besi = 25.40 Bh
o. Tot.Pjng Beugel Besi = 34.29 M'
Berat Stek Besi 6 D13 mm = 0,006165*13mm*13mm*65,60M' 30.51

Page 123 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
= 30.51 Kg
Berat Beugel Besi Ø8-200 mm = 0,006165*8 mm*8 mm*95,45 M' 13.53
= 13.53 Kg
2.10.c. Pekerjaan Beton K-250 (fc'=21.7 Mpa), Slump (12+2) 0.44
Dik : a. Panjang = 4.88 M'
b. Tebal = 0.60 M'
c. Lebar = 0.15 M'
Vol. Pengecoran Balok 15x60 cm = 71,25 x 0,35 x 0,25 M'
= 0.44 M³
BESI BETON
RASIO SLOOF 15X60 CM = 44.04 : 0.44
= 100.26 Kg/M³

2.11. Pekerjaan Plat Lantai 2; Tbl.10 cm


2.11.a. Pekerjaan Mall 88.98
Luasan Plat Lantai = 88.98

2.11.b. Pek. Pembesian ø9 mm 769.76


Dik : a. Panjang Besi 560.54
- Pjng Besi = 889 cm = 8.89 M'
Jumlah Besi = 889 cm = 26.00 Bh
= 231.14 M'
- Pjng Besi = 816 cm = 8.16 M'
Jumlah Besi = 889 cm = 5.00 Bh
= 40.80 M'
- Pjng Besi = 7.36 cm = 7.36 M'
Jumlah Besi = 889 cm = 5.00 Bh
= 36.80 M'
- Pjng Besi = 985 cm = 9.85 M'
Jumlah Besi = 889 cm = 3.00 Bh
= 29.55 M'
- Pjng Besi = 635 cm = 6.35 M'
Jumlah Besi = 889 cm = 35.00 Bh
= 222.25 M'
b. Koef. Besi = 0.006165
c. Besi = 9.00 mm
d. Berat Besi = 279.91 Kg
2.75 Lapisan Pembesian Tikar = 769.76 Kg

2.11.c. Pekerjaan Pengecoran K-250 (fc'=21.7 Mpa), Slump (12+2) 10.68


Dik : a. Luasan = 88.98 M'
b. Tebal = 0.12 M'
Vol. coran Plat Lantai Tbl. 10 cm = 418,76 * 0,20 M'
= 10.68 M³

2.12. Pekerjaan Plat Meja Dapur


2.12.a. Pekerjaan Mall/ Bekisting 0.54
Dik : 1. Panjang = 0.90 M'
2. Lebar = 0.60 M'
Luasan Meja Dapur = 0,9 x 0,60 M'
= 0.54 M²
2.12.b. Pekerjaan Pembesian Meja Dapur 11.47
Dik : a. Panjang Besi 6.20
- Pjng Besi = 80 cm = 0.80 M'
Jumlah Besi = 80 cm = 4.00 Bh
= 3.20 M'
- Pjng Besi = 60 cm = 0.60 M'
Jumlah Besi = 60cm = 5.00 Bh

Page 124 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
= 3.00 M'
b. Koef. Besi = 0.006165
c. Besi = 10.00 mm
d. Berat Besi = 3.82 Kg
3 Lapisan Pembesian Tikar = 11.47 Kg

2.12.c. Pekerjaan Pengecoran K-175 0.05


Dik : a. Luas Area = 0.54 M²
b. Tebal = 0.10 M'
Vol. Pengecoran = 1,42 M² * 0,10 M'
= 0.05 M³
RASIO BESI : BESI BESI BETON
= 11.47 : 0.05
= 212.35 Kg/Cm³

2.13. Pekerjaan Kolom Fantasi


2.13.a. Pekerjaan Mall/ Bekisting 2.15
Dik : 1. Panjang = 5.38 M'
2. Lebar = 0.40 M'
Luasan = 5,38 x 0,40 M'
= 2.15 M²
2.13.b. Pekerjaan Pembesian 23.82
Dik : a. Panjang Besi 20.13
- Pjng Besi = 538 cm = 5.38 M'
Jumlah Besi = 538 cm = 2.33 Bh
= 12.55 M'
- Pjng Besi = 40 cm = 0.40 M'
Jumlah Besi = 40cm = 18.93 Bh
= 7.57 M'
b. Koef. Besi = 0.006165
c. Besi = 8.00 mm
d. Berat Besi = 7.94 Kg
3 Lapisan Pembesian Tikar = 23.82 Kg

2.13.c. Pekerjaan Pengecoran K-175 0.17


Dik : a. Luas Area = 2.15 M²
b. Tebal = 0.08 M'
Vol. Pengecoran = 1,42 M² * 0,10 M'
= 0.17 M³
RASIO BESI : BESI BESI BETON
= 23.82 : 0.17
= 138.38 Kg/Cm³

IV. PEKERJAAN DINDING


1) Pek.Pasangan Batu; Tebal 1/2 Bata; Spesi 1Pc : 4Psr 224.47
Dik: 1 Luasan Pas.Bata =
Arah X = 1.35+7.99+4.59+3.15+14.25+
= (2*(3.15+14.25))+12.33+5.27+
= (2*9.57)+(2*(2*3.88))+(2*1.58)
= 121.55 M²
Arah Y = (2*8.04)+9,57+1.23+(3*4.61)+3.88+
= (3*1.59)+2.44+(2*2.35)+6.46+4.34+
= (2*4.61)+14.25+6.46+4.34+1.35
= 102.92
Luasan Pas.Dinding Bata Arah Y = 224.47 M²

V. PEKERJAAN PLESTERAN & ACIAN

Page 125 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
1. Pekerjaan Plesteran Spesi 1Pc:3Psr
1.a. Pekerjaan Plesteran Pas. Bata 448.94
2. Pekerjaan Acian
2.1. Pekerjaan Acian Dinding Plesteran 448.94
2.2. Acian Pada Kolom Fantasi 4.70
2.3. Acian Plat Kanopy 13.29

VI. PEKERJAAN KUSEN, DAUN PINTU JENDELA KAYU


Dik : 0.25 = 0.00635 M'
0.50 = 0.01270 M'
1.00 = 0.02540 M'
2.00 = 0.05080 M'
4.00 = 0.10160 M'
6.00 = 0.15240 M'
8.00 = 0.20320 M'
Vol. Kusen Per 1 mtr = 1.00000 M'
= (2 ichi x 6 inchi)x 100 cm
= (0,0508 M x 0,1524 M )x 1 M
= 0.00774192 M³
FAK. BUANG POTONG = 0.1000
FAK. BUANG POTONG = 0.0008
TOT. KUBIKASI KUSEN = 0.0085 m³ per meter

Vol. Kusen Per 1 mtr = 1.00000 M'


= (1 ichi x 4 inchi)x 100 cm
= (0,0254 M x 0,1016 M )x 1 M
= 0.00258064 M³
FAK. BUANG POTONG = 0.1000
FAK. BUANG POTONG = 0.0003
TOT. KUBIKASI KUSEN = 0.0028 m³ per meter

1) Pekerjaan Kusen
1.1. Pekerjaan Kusen Pintu
- Kusen Pintu Gendong 0.46
Dik : 1 Jumlah Kusen = 5.00 Set
2 Panjang Kusen = 10.86 M'
3 Tot. Panjang Kusen = 54.30 M'
1.2. Pekerjaan Kusen Jendela
- Kusen Ventilasi (V= 0,40*0,60 M') 0.09
Dik : 1 Jumlah Kusen = 5.00 Set
2 Panjang Kusen = 2.00 M'
3 Tot. Panjang Kusen = 10.00 M'

2) Pekerjaan Daun Pintu


2.1. Daun Pintu (P-1); Uk.90x2,10 M' 9.45
Dik : 1 Jumlah Daun Pintu = 5.00 Set
2 Pjng Daun Pintu = 2.10 M'
3 Lebar Daun Pintu = 0.90 M'
4 Luasan Pintu = 9.45 M²
2.2. Daun Pintu Kamar Mandi (folding door) 5.00

3) Pekerjaan Daun Jendela


3.1. Daun Jendela(V-1); Uk.40x60 cm (Kombinasi Kaca) 1.20
Dik : 1 Jumlah Daun Pintu = 5.00 Set
2 Pjng Daun Pintu = 0.60 M'
3 Lebar Daun Pintu = 0.40 M'
4 Luasan Jendela = 1.20 M²

Page 126 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
3.2. Daun Jendela(J-1); Uk.40x60 cm (Kombinasi Kaca) 3.88
Dik : 1 Jumlah Daun Pintu = 5.00 Set
2 Pjng Daun Pintu = 1.55 M'
3 Lebar Daun Pintu = 0.50 M'
4 Luasan Jendela = 3.88 M²

VII. PEKERJAAN PENGGANTUNG DAN KACA


1) Handle Pintu Dekkson Type 0820 (Full Set) 5.00
2) Pekerjaan Door Stopper Dekkson Type MDS 889 SN 5.00
3) Pekerjaan Engsel Pintu Dan Jendela
3.1. Pekerjaan Engsel Pintu Dekkson Ecoline 4x3x2MM 2BB SSS 10.00
3.2. Pek. Engsel Jendela Dekkson Ecoline 3x3x2MM 2BB SSS 20.00
4) Pekerjaan Rambuncis Dekkson Type CWH 103Z  10.00
5) Pekerjaan Kait Angin Dekkson Type WS 001 10" SSS 10.00
6) Pekerjaan Engsel Jungkit Dekkson Type ES SL 5" CP 20.00
7) Pekerjaan Kaca
7.1. Kaca Ventilasi 1.20
7.2. Kaca Jendela 3.88

VIII. PEKERJAAN PELAPIS LANTAI DAN DINDING


1) Pek. Lantai Keramik; Asia Tile (setaranya) Uk. 20x20 ; unpolish
1.a. Area Kamar Mandi 8.80
- Jumlah Kamar Mandi = 5.000
- Luas Km.Mandi Kanan = 1.760
Tot.Luasan Km.Mandi = 8.800 M²
1.b. Area Dapur 0.48
- Panjang = 0.800 M'
- Lebar = 0.600 M'
2) Pek. Lantai Keramik; Granit Ex. China; Uk. 60x60 43.80
Dik : 1 Luasan Lantai 1 Kamar = 8.76 M²
2 Jumlah Kamar Kamar = 5.00 Set
3 Tot. Luasan Lt. Kamar = 43.80 M²
3) Pekerjaan Lantai Teras; Granit Ex. China; Uk. 60x60
3.1. Area Teras dan Dapur 35.47
3.2. Area Tangga 11.09
4) Pek. Dinding Keramik; Asia Tile (setaranya) Uk. 20x40
4.1. Area Kamar MAndi 46.05
4.2. Area Dapur 3.84
5) Pek. Pelapis Kolom; Batu Alam Palimanan 19.06

IX. PEKERJAAN PLAFOND


1) Pekerjaan Rangka Plafond Gypsum (Sisi Dalam) 43.80
1.a. Pekerjaan Rangka Plafond
Dik 1 Luasan Plafond = 411.68
1.b. Pekerjaan Plafond Gypsum Jayaboard Tbl.9mm
2) Pekerjaan Plafond Gypsum (Sisi Dalam) 43.80
1.a. Pekerjaan Rangka Plafond
Dik 1 Luasan Plafond = 411.68
1.b. Pekerjaan Plafond Gypsum Jayaboard Tbl.9mm
3) Pekerjaan Rangka Plafond Gypsum (Sisi Luar) 35.47
4) Pekerjaan Plafond Gypsum (Area Selasar) 35.47
1.a. Pekerjaan Rangka Plafond
Dik 1 Luasan Plafond = 78.46

X. PEKERJAAN INSTALASI LISTRIK


1) Pek. Titik Lampu Dalam/ttk Bawah Plafond (Kabel NYM 2x1,5mm) 12.00

Page 127 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
2) Pek. Titik Stop Kontak Biasa /ttk (Kabel NYM 3x1,5mm) 6.00
3) Pek. Titik Stop Kontak Khusus /ttk (Kabel NYM 3x2,5mm) 5.00
4) Pekerjaan Aarde/Pentanahan 2.00
5) Pekerjaan Box Sikring 6 Group 1.00

XI. PEKERJAAN SANITARY


1) Pekerjaan Kloset Duduk Tidy (Setaranya) 5.00
2) Pekerjaan Floor Drain 5.00
3) Pekerjaan Kran Air Onda
3.a. Kran Tembok Onda 5.00
3.b. Kran Flexibel Onda 1.00
4) Pekerjaan Zink Sink 1 Lubang 1.00
5) Pekerjaan Shower
5.1. Spray Closet Onda 5.00
5.2. Shower Spray Onda 5.00
6) Pekerjaan Pipa Air
6.a. Pekerjaan Pipa Air Bersih (1/2") 28.44
6.b. Pekerjaan Air Buangan (2") 31.56
6.c. Pekerjaan Air Kotor (3") 32.90

XII. PEKERJAAN BESI


1) Pekerjaan Railing Besi Tangga 7.38
Dik. - Panjang = 1.00
- Lebar = 7.38

XIII. PEKERJAAN PENGECATAN


1) Pengecatan Dengan Cat Air
1.1. Pekerjaan Pengecatan Dulux Wheatershield (Ekterior) 159.61
1.2. Pekerjaan Pengecatan Catylac (Interior) 316.70
- DInding Kamar Sisi Dalam = 193.20 M²
- Km. Mandi = 36.10 M²
- DInding Kamar Sisi Luar = 22.25 M²
- Area Dapur = 54.24 M²
- Tangga = 10.91 M²
2) Pekerjaan Mendempul Dan Menggosok Kayu
2.1. Bidang Kayu Kusen 14.25
- Kusen Pintu Gendong = 2.49 M²
- Kusen Ventilasi = 0.36 M²
Luasan/ Unit Kamar = 2.85 M²
5 Luasan/ Unit Kamar = 14.25 M²
2.2. Bidang Kayu Daun Pintu dan Jendela 21.40
- Daun Pintu = 3.52 M²
- Daun Jendela = 0.56 M²
- Ventilasi = 0.20 M²
Luasan/ Unit Kamar = 4.28 M²
5 Luasan/ Unit Kamar = 21.40 M²

3) Pengecatan Dengan Cat Kayu/Besi


3.1. Pekerjaan Pengecatan Kusen
3.1.a. Pekerjaan Pengecatan Kusen Pintu
3.1.a.1. Kusen Pintu Gendong 12.45
Dik : 1 Panjang Kusen = 2.49 M'
2 Jumlah = 5.00 M'
3 Luasan Pengecatan = 12.45 M²
3.1.b. Pekerjaan Pengecatan Kusen Jendela
3.1.b.1. Kusen Ventilasi (V= 0,40*0,60 M') 1.80

Page 128 of 135


FASADE 23/BACKUPDATA/ELEVASI/-20,00 - 3,70/METER/GPIBMADUMA/2019

JUMLAHPANJANGLEBAR TINGGI LUASAN KUBIKASI BERAT


NO. URAIAN PEKERJAAN
(Set) (M') (M') (M') (M²) (M³) (Kilogram)
(1) (2) (3) (4) (5) (6) (7) (8) (9)
Dik : 1 Panjang Kusen = 0.36 M'
2 Jumlah = 5.00 M'
3 Luasan Pengecatan = 1.80 M²
3.2. Pekerjaan Pengecatan Daun
3.2.a. Pekerjaan Pengecatan Daun Pintu 17.60
3.2.b. Pekerjaan Pengecatan Daun Jendela 2.80
3.2.c. Pekerjaan Pengecatan Daun Jendela Kamar Mandi 1.00

4) Pekerjaan Pengecatan Plafond 79.27


5) Pengecatan Besi
5.a. Pekerjaan Pengecatan Railing Besi 5.82
Dik: - Handle Railing = 5.82
Panjang ; 428 Cm = 0.68
Panjang ; 14 Cm = 0.10
Panjang ; 312 Cm = 0.55
Panjang ; 10 Cm = 0.50
Panjang ; 125 CM = 1.20
Panjang ; 116 CM = 0.50
Panjang ;35 CM = 0.15
Panjang ;54 CM = 0.20
Panjang ;44 CM = 0.40
- Tiang Railing = 1.54

Page 129 of 135


TABEL DAFTAR HARGA SEWA ALAT,
PERAWATAN ALAT BANTU DAN JASA PEKERJAAN
Periode : November 2008
Jenis Bangunan : Bangunan Umum
Klasifikasi : Menengah
Proyek : Renovasi - Bangun Baru
Lokasi : Jakarta
Wilayah : Jabodetabek

HARGA SATUAN
NO. NAMA ALAT BANTU PEKERJAAN SAT. VOL. KAPASITAS
( Rupiah )
1 Concrete Mixer Jam 1.00 481,250.00
2 Ember Aduk bh 1.00 9,900.00
3 Genzet 1000 Watt unit 1.00 2,475,000.00
4 Mesin Grenda GA 4034 / GA4034 unit 1.00 1,050,500.00 Uk.: 4" / 100 mm
5 Mesin Bor unit 1.00 935,000.00
6 Mesin Bor Untuk Pondasi Jam 1.00 17,600,000.00
7 Mesin Gurinda unit 1.00 495,000.00
8 Pacul Aduk bh 1.00 82,500.00
9 Pahat Besi bh 1.00 27,500.00
10 Pengki bh 1.00 27,500.00
11 Sekop bh 1.00 82,500.00
12 Sendok semen bh 1.00 38,500.00
13 Travo Las unit 1.00 1,155,000.00 Lakoni 900 W (Baru)
14 Vibrator Jam 1.00 96,250.00 Kap. 1-30 M³ (Sewa)
15 Crawler Crane Jam 1.00 1,086,250.00 Kap.35 Ton

Ket :
HH = Hydraulic Hammer, Kapasitas Alat = 7 Ton
DH = Drop Hammer, Kapasitas Alat = 3.5 Ton
SP = Spun Pile
SQ = Square Pile
DAFTAR HARGA SATUAN PEKERJAAN
UPAH & BAHAN

K O TA BK
OOG TOAR B O G O R

TAHUN ANGGARAN 2019


TABEL PERBANDINGAN KOMPOSISI MATERIAL ADUKAN BETON

BERAT MATERIAL PERBANDINGAN VOLUME MATERIALW/C TOTAL HARGA MATERIAL (KG) TOTAL
NO. MUTU BETON SEMEN PASIR SPLITZ AIR SEMEN PASIR SPLITZ AIR RATIOBERAT (KG) SEMEN PASIR SPLITZ AIR HARGA
(KG) (KG) (KG) (KG) (M³) (M³) (M³) (M³) Rp 1,221.23 Rp 85.70 Rp 134.98 Rp 90.00 (Rupiah)
1 K-100 247 869 999 215 1 3.14 3.75 1.09 0.87 2,330.00 301,642.58 74,473.30 134,842.52 19,350.00 530,308.40
2 K-125 276 828 1,012 215 1 2.70 3.40 0.97 0.78 2,331.00 337,058.10 70,959.60 136,597.23 19,350.00 563,964.93
3 K-150 299 799 1,017 215 1 2.39 3.15 0.90 0.72 2,330.00 365,146.28 68,474.30 137,272.12 19,350.00 590,242.69
4 K-175 326 760 1,029 215 1 2.08 2.92 0.82 0.66 2,330.00 398,119.35 65,132.00 138,891.85 19,350.00 621,493.20
5 K-200 352 731 1,031 215 1 1.85 2.71 0.76 0.61 2,329.00 429,871.20 62,646.70 139,161.80 19,350.00 651,029.70
6 K-225 371 698 1,047 215 1 1.68 2.61 0.72 0.58 2,331.00 453,074.48 59,818.60 141,321.44 19,350.00 673,564.52
7 K-250 384 692 1,039 215 1 1.61 2.51 0.70 0.56 2,330.00 468,950.40 59,304.40 140,241.62 19,350.00 687,846.42
8 K-275 406 684 1,026 215 1 1.50 2.34 0.66 0.53 2,331.00 495,817.35 58,618.80 138,486.92 19,350.00 712,273.07
9 K-300 413 681 1,021 215 1 1.47 2.29 0.65 0.52 2,330.00 504,365.93 58,361.70 137,812.03 19,350.00 719,889.65
10 K-325 439 670 1,006 215 1 1.36 2.12 0.61 0.49 2,330.00 536,117.78 57,419.00 135,787.37 19,350.00 748,674.14
11 K-350 448 667 1,000 215 1 1.33 2.07 0.60 0.48 2,330.00 547,108.80 57,161.90 134,977.50 19,350.00 758,598.20

Anda mungkin juga menyukai