Anda di halaman 1dari 20

DAFTAR HARGA SATUAN UPAH

Pekerjaan : Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm


Lokasi : Jalan Putri Hijau Dalam

NO URAIAN SATUAN UPAH (Rp.) KETERANGAN

1 Mandor Org/hr Rp 126,000.00


2 Kepala Tukang Batu Org/hr Rp 157,500.00
3 Kepala Tukang Kayu Org/hr Rp 157,500.00
4 Kepala Tukang Besi Org/hr Rp 157,500.00
5 Kepala Tukang Cat Org/hr Rp 157,500.00
6 Kepala Tukang Listrik Org/hr Rp 157,500.00
7 Kepala Tukang Org/hr Rp 157,500.00
8 Tukang Batu Org/hr Rp 136,500.00
9 Tukang Kayu Org/hr Rp 136,500.00
10 Tukang Besi/Baja Org/hr Rp 136,500.00
11 Tukang Cat Org/hr Rp 136,500.00
12 Tukang Listrik Org/hr Rp 136,500.00
13 Tukang Pipa Org/hr Rp 136,500.00
14 Tukang Plitur Org/hr Rp 136,500.00
15 Tukang Taman Org/hr Rp 136,500.00
16 Tukang Org/hr Rp 136,500.00
17 Pembantu Tukang Org/hr Rp 94,500.00
18 Pekerja Biasa Org/hr Rp 84,000.00
19 Penjaga Malam Org/hr Rp 94,500.00
20 Sopir Org/hr Rp 136,500.00
21 Operator Org/hr Rp 157,500.00
22 Mekanik Org/hr Rp 157,500.00
23 Pembantu Sopir Org/hr Rp 105,000.00
24 Pembantu Operator Org/hr Rp 94,500.00
25 Pembantu Mekanik Org/hr Rp 94,500.00

harga sudah termasuk PPN dan keuntungan


DAFTAR HARGA SATUAN BAHAN BANGUNAN
Proyek : Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm
Lokasi : Jalan Putri Hijau Dalam

NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)


A. AGREGAT KASAR,BAHAN PEREKAT & BAHAN JADINYA
1. Tanah - Urug Pilihan M³ 94,500.00
- liat M³ 53,865.00
2. Pasir - Urug M³ 115,920.00
- Pasang Kali M³ 136,500.00
- Beton M³ 157,500.00
- Pasir Beton (BJ = 1400 Kg/M3) M³ 112.50
4. Sirtu M³ 318,675.00
5. Batu - Pecah Mesin 2/3 M³ 402,675.00
- Splitz (BJ = 1800 Kg/M3) Kg 223.71
- Pecah Mesin 3/5 M³ 376,215.00
- Pecah Mesin 5/7 M³ 335,475.00
- Kerikil M³ 183,750.00
- Belah M³ 288,750.00
- Alam Palimanan M² 126,000.00
- Candi M² 147,000.00
8. Bata Merah Bakar kelas I Bh 735.00
Bakar kelas II Bh 687.75
Oven(Klingker);Uk.4,5x9,5x18 cm Bh 2,100.00
11. Paving Blok Natural Natural Tebal. 8 cm M² 93,670.50
Natural Tebal 6 cm M² 87,780.00
12. Semen Portland Cement 1 Sak = 40 kg Sak 57,750.00
Portland Cement 1Kg Kg 1,443.75
Putih Sak 97,335.00
Warna Kg 16,485.00
13 Air Ltr 55.26

B. LABURAN,PENGISI DAN ALATNYA


1 Cat Tembok Dulux eksterior; weathershield putih Briliant Ltr 98,962.50
Dulux; Interior Putih Glow Ltr 30,450.00
Catylac eksterior Kg 40,950.00
Catylac interior Kg 26,250.00
Cat Tembok Vinilex Kembang Kg 22,470.00
2 Cat Dasar Dulux; Exterior Wheatershield Kg 50,400.00
Dulux; Interior Alkali Sealer Kg 46,147.50
Catylac Sealer Kg 23,625.00
3 Rool Cat Tembok Bh 31,500.00
4 Kape Tembok Bh 8,925.00
5 Kwas 4" Bh 27,300.00
6 Dempul Jadi Kg 37,590.00
Plastik Kg 41,160.00
Duco Kg 37,590.00
7 Tiner Tipe A Kg 25,095.00
Tipe B Kg 22,470.00
8 Ampelas Lbr 6,300.00
9 Cat Kayu Avian High Gloss Enamel (Kayu & Besi) Kg 58,800.00
10 Cat Besi Kg 46,200.00

C. BAHAN KAYU BERIKUT BAHAN JADINYA


1 Dolken Diameter 5 s/d 7 Btg 15,750.00
Diameter 7 s/d 10CM Btg 17,850.00
2 Kayu Papan Terentang M³ 5,053,125.00
3 Kayu Balok Terentang M³ 3,927,000.00

D. BAHAN KAYU LAPIS


1 Triplek Biasa - 4 mm 120 x 240 cm Lbr 65,625.00
- 6 mm 120 x 240 cm Lbr 80,325.00

Page 3 BHN
NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)
- 9 mm 120 x 240 cm Lbr 109,725.00

E. BAHAN LOGAM DAN BAHAN JADINYA


1 Besi Beton U-24 Rata-rata Kg 11,576.25
2 Plat Srip Ø 2 x 30 mm ( 6 m1 ) Btg 34,650.00
3 Plat Srip Ø 3 x 30 mm ( 6 m1 ) Btg 34,755.00
4 Kawat Beton Btg 31,500.00
5 Besi Hollow (20 x 40 x 1,7) mm (600cm) Btg 27,720.00
(40 x 40 x 2,7) mm (600cm) Btg 54,670.00
(50x50x2,7) mm; 25, 434 Kg Btg 70,070.00
(30x60x1,7) mm; 14.4126 Kg Btg 43,312.50

F. BAHAN PAKU DAN MUR BAUT


1 Paku 1/2" s/d 2" Kg 24,990.00
2 Paku 2" s/d 5" Kg 24,570.00
3 Baut Besar Bh 630.00
4 Baut Kecil Bh 315.00

G. BAHAN BAKAR DAN PELUMAS


1 Minyak Solar Ltr 7,507.50
2 Oil Mesran 40 SAE Ltr 57,750.00
3 Minyak Bekisting Ltr 32,025.00

Page 4 BHN
NO MATERIAL SPESIFIKASI SATUAN HARGA (Rp)

Page 5 BHN
DUTAINTERIORMEDAN/AHSP/PEMBANGUNANPAGAR/JALANPUTRIHIJAUDALAM/2020

ANALISA HARGA SATUAN PEKERJAAN


Proyek
Lokasi
:
:
Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm
Jalan Putri Hijau Dalam
A.H.S.P.
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
1 1 M³ Pekerjaan Bobokan Dinding
a. ALAT BANTU
1 Biaya 10% X harga upah Ls 0.1000 379,575.00 Rp 37,957.50
JUMLAH BAHAN Rp 37,957.50
b. UPAH
1 Pekerja Oh 1.5000 94,500.00 Rp 141,750.00
2 Tukang Batu Oh 1.5000 136,500.00 Rp 204,750.00
3 Kepala Tukang Oh 0.1500 157,500.00 Rp 23,625.00
4 Mandor Oh 0.0750 126,000.00 Rp 9,450.00
JUMLAH UPAH Rp 379,575.00
c. JUMLAH UPAH + BAHAN Rp 417,532.50
d. DIBULATKAN Rp 417,533.00

2 1 M³ Pekerjaan Bobokan Beton


a. ALAT BANTU
1 Biaya 20% X harga upah Ls 0.1000 632,625.00 Rp 63,262.50
JUMLAH BAHAN Rp 63,262.50
b. UPAH
1 Pekerja Oh 2.5000 94,500.00 Rp 236,250.00
2 Tukang Batu Oh 2.5000 136,500.00 Rp 341,250.00
3 Kepala Tukang Oh 0.2500 157,500.00 Rp 39,375.00
4 Mandor Oh 0.1250 126,000.00 Rp 15,750.00
JUMLAH UPAH Rp 632,625.00
c. JUMLAH UPAH + BAHAN Rp 695,887.50
d. DIBULATKAN Rp 695,888.00

3 1 M' Pengukuran Dan Pasang Bouwplank


a. BAHAN
1 Kayu kaso 5/7 M3 0.0060 5,053,125.00 Rp 30,318.75
2 Paku Kg 0.0200 24,570.00 Rp 491.40
JUMLAH BAHAN Rp 30,810.15
b. UPAH
1 Pekerja Oh 0.1000 94,500.00 Rp 9,450.00
2 Tukang Kayu Oh 0.1000 136,500.00 Rp 13,650.00
3 Kepala Tukang Oh 0.0100 157,500.00 Rp 1,575.00
4 Mandor Oh 0.0050 126,000.00 Rp 630.00
JUMLAH UPAH Rp 25,305.00
c. JUMLAH UPAH + BAHAN Rp 56,115.15
d. DIBULATKAN Rp 56,115.00

4 1 M³ Galian Tanah Biasa


a. UPAH
1 Pekerja Oh 0.7500 94,500.00 Rp 70,875.00
2 Mandor Oh 0.0750 126,000.00 Rp 9,450.00
JUMLAH UPAH Rp 80,325.00
b. JUMLAH UPAH + BAHAN Rp 80,325.00
c. DIBULATKAN Rp 80,325.00

5 1 M³ Urugan Kembali
a. UPAH
1 Pekerja Oh 0.2500 94,500.00 Rp 23,625.00
2 Mandor Oh 0.0250 126,000.00 Rp 3,150.00
JUMLAH UPAH Rp 26,775.00
b. JUMLAH UPAH + BAHAN Rp 26,775.00
c. DIBULATKAN Rp 26,775.00

6 1 M³ Urugan Pasir
a. BAHAN
1 Pasir Urug M3 1.2000 136,500.00 Rp 163,800.00
JUMLAH BAHAN Rp 163,800.00

Halaman 6 dari 20 Lembar


DUTAINTERIORMEDAN/AHSP/PEMBANGUNANPAGAR/JALANPUTRIHIJAUDALAM/2020

ANALISA HARGA SATUAN PEKERJAAN


Proyek
Lokasi
:
:
Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm
Jalan Putri Hijau Dalam
A.H.S.P.
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
b. UPAH
1 Pekerja Oh 0.3000 94,500.00 Rp 28,350.00
2 Mandor Oh 0.0100 126,000.00 Rp 1,260.00
JUMLAH UPAH Rp 29,610.00
b. JUMLAH UPAH + BAHAN Rp 178,605.00
c. DIBULATKAN Rp 178,605.00

7 1 M³ Membuat Beton Cor ; Spesi 1Pc:3Psr:5Krkl


a. BAHAN
1 Semen Portland Kg 247.0000 1,443.75 Rp 356,606.25
2 Pasir Beton M³ 0.8690 157,500.00 Rp 136,867.50
3 Batu Kerikil M³ 0.9990 183,750.00 Rp 183,566.25
4 Air Ltr 215.0000 55.26 Rp 11,881.58
JUMLAH BAHAN Rp 688,921.58
b. UPAH
1 Pekerja Oh 1.6500 94,500.00 Rp 155,925.00
2 Tukang Batu Oh 0.2500 136,500.00 Rp 34,125.00
3 Kepala Tukang Oh 0.0250 157,500.00 Rp 3,937.50
4 Mandor Oh 0.0800 126,000.00 Rp 10,080.00
JUMLAH UPAH Rp 204,067.50
JUMLAH Rp 892,989.08
DIBULATKAN Rp 892,989.00

8 1 M³ Membuat Beton Cor Mutu K-175 (fc'=14.5 Mpa), Slump (12+2),w/c=0,66


a. BAHAN
1 Semen Portland Kg 326.0000 1,443.75 Rp 470,662.50
2 Pasir Beton M³ 0.7600 157,500.00 Rp 119,700.00
3 Batu Splitz M³ 1.0290 376,215.00 Rp 387,125.24
4 Air Ltr 215.0000 55.26 Rp 11,881.58
JUMLAH BAHAN Rp 989,369.31
b. UPAH
1 Pekerja Oh 1.6500 94,500.00 Rp 155,925.00
2 Tukang Batu Oh 0.2500 136,500.00 Rp 34,125.00
3 Kepala Tukang Oh 0.0250 157,500.00 Rp 3,937.50
4 Mandor Oh 0.0800 126,000.00 Rp 10,080.00
JUMLAH UPAH Rp 204,067.50
JUMLAH Rp 1,193,436.81
DIBULATKAN Rp 1,193,437.00

9 1 Kg Pembesian Dengan Besi Polos/ulir


a. BAHAN
1 Besi Beton ( Polos / Ulir ) Kg 1.0500 11,576.25 Rp 12,155.06
2 Kawat Beton Kg 0.0250 31,500.00 Rp 787.50
JUMLAH BAHAN Rp 12,942.56
b. UPAH
1 Pekerja Oh 0.0095 94,500.00 Rp 897.75
2 Tukang Besi Oh 0.0095 136,500.00 Rp 1,296.75
3 Kepala Tukang Oh 0.0008 157,500.00 Rp 126.00
4 Mandor Oh 0.0004 126,000.00 Rp 50.40
JUMLAH UPAH Rp 2,370.90
JUMLAH Rp 15,313.46
DIBULATKAN Rp 15,313.00

10 1 M² Pasang Bekesting Untuk Pondasi


a. BAHAN
1 Kayu papan terentang M3 0.0400 5,053,125.00 Rp 202,125.00
2 Paku Biasa 2" - 5" Kg 0.3000 24,570.00 Rp 7,371.00
3 Minyak Bekisting Ltr 0.1000 32,025.00 Rp 3,202.50
JUMLAH BAHAN Rp 212,698.50
Jumlah Bahan Mall Untuk 3 x pakai Ls 0.3333 212,698.50 Rp 70,899.50

Halaman 7 dari 20 Lembar


DUTAINTERIORMEDAN/AHSP/PEMBANGUNANPAGAR/JALANPUTRIHIJAUDALAM/2020

ANALISA HARGA SATUAN PEKERJAAN


Proyek
Lokasi
:
:
Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm
Jalan Putri Hijau Dalam
A.H.S.P.
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
b. UPAH
1 Pekerja Oh 0.0520 94,500.00 Rp 4,914.00
2 Tukang Kayu Oh 0.2600 136,500.00 Rp 35,490.00
3 Kepala Tukang Oh 0.0260 157,500.00 Rp 4,095.00
4 Mandor Oh 0.0050 126,000.00 Rp 630.00
JUMLAH UPAH Rp 45,129.00
JUMLAH Rp 116,028.50
DIBULATKAN Rp 116,029.00

11 1 M² Pasang Bekisting Untuk Sloof


a. BAHAN
1 Kayu papan terentang M3 0.0450 5,053,125.00 Rp 227,390.63
2 Paku Biasa 2" - 5" Kg 0.3000 24,570.00 Rp 7,371.00
3 Minyak Bekisting Ltr 0.1000 32,025.00 Rp 3,202.50
JUMLAH BAHAN Rp 237,964.13
Jumlah Bahan Mall Untuk 3 x pakai Ls 0.3333 237,964.13 Rp 79,321.38
b. UPAH
1 Pekerja Oh 0.0520 94,500.00 Rp 4,914.00
2 Tukang Kayu Oh 0.2600 136,500.00 Rp 35,490.00
3 Kepala Tukang Oh 0.0260 157,500.00 Rp 4,095.00
4 Mandor Oh 0.0050 126,000.00 Rp 630.00
JUMLAH UPAH Rp 45,129.00
JUMLAH Rp 124,450.38
DIBULATKAN Rp 124,450.00

12 1 M² Pasang Bekesting Untuk Kolom


a. BAHAN
1 Kayu balok terentang M3 0.0400 3,927,000.00 Rp 157,080.00
2 Paku Biasa 2" - 5" Kg 0.4000 24,570.00 Rp 9,828.00
3 Minyak Bekisting Ltr 0.2000 32,025.00 Rp 6,405.00
4 Kayu balok terentang M3 0.0150 3,927,000.00 Rp 58,905.00
5 Multiplek Tbl.9mm Lbr 0.3500 109,725.00 Rp 38,403.75
6 Dolken Ø-8-10/4m Btg 2.0000 15,750.00 Rp 31,500.00
JUMLAH BAHAN Rp 302,121.75
Jumlah Bahan Mall Untuk 2,5 x pakai Ls 0.4000 302,121.75 Rp 120,848.70
b. UPAH
1 Pekerja Oh 0.6600 94,500.00 Rp 62,370.00
2 Tukang Kayu Oh 0.3300 136,500.00 Rp 45,045.00
3 Kepala Tukang Oh 0.0330 157,500.00 Rp 5,197.50
4 Mandor Oh 0.0330 126,000.00 Rp 4,158.00
JUMLAH UPAH Rp 116,770.50
JUMLAH Rp 237,619.20
DIBULATKAN Rp 237,619.00

13 1 M² Pasang Bekesting Untuk Balok


a. BAHAN
1 Kayu balok terentang M3 0.0400 3,927,000.00 Rp 157,080.00
2 Paku Biasa 2" - 5" Kg 0.4000 24,570.00 Rp 9,828.00
3 Minyak Bekisting Ltr 0.2000 32,025.00 Rp 6,405.00
4 Kayu balok terentang M3 0.0180 3,927,000.00 Rp 70,686.00
5 Multiplek Tbl.9mm Lbr 0.3500 109,725.00 Rp 38,403.75
6 Dolken Ø-8-10/4m Btg 2.0000 15,750.00 Rp 31,500.00
JUMLAH BAHAN Rp 313,902.75
Jumlah Bahan Mall Untuk 2 x pakai Ls 0.4000 313,902.75 Rp 125,561.10
b. UPAH
1 Pekerja Oh 0.6600 94,500.00 Rp 62,370.00
2 Tukang Kayu Oh 0.3300 136,500.00 Rp 45,045.00
3 Kepala Tukang Oh 0.0330 157,500.00 Rp 5,197.50
4 Mandor Oh 0.0330 126,000.00 Rp 4,158.00
JUMLAH UPAH Rp 116,770.50

Halaman 8 dari 20 Lembar


DUTAINTERIORMEDAN/AHSP/PEMBANGUNANPAGAR/JALANPUTRIHIJAUDALAM/2020

ANALISA HARGA SATUAN PEKERJAAN


Proyek
Lokasi
:
:
Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm
Jalan Putri Hijau Dalam
A.H.S.P.
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
JUMLAH Rp 242,331.60
DIBULATKAN Rp 242,332.00

14 1 M² Pasang Bekesting Untuk Lantai


a. BAHAN
1 Kayu balok terentang M3 0.0400 3,927,000.00 Rp 157,080.00
2 Paku Biasa 2" - 5" Kg 0.4000 24,570.00 Rp 9,828.00
3 Minyak Bekisting Ltr 0.2000 32,025.00 Rp 6,405.00
4 Kayu balok terentang M3 0.0150 3,927,000.00 Rp 58,905.00
5 Multiplek Tbl.9mm Lbr 0.3500 109,725.00 Rp 38,403.75
6 Dolken Ø-8-10/4m Btg 6.0000 15,750.00 Rp 94,500.00
JUMLAH BAHAN Rp 365,121.75
Jumlah Bahan Mall Untuk 2.5 x pakai Ls 0.4000 365,121.75 Rp 146,048.70
b. UPAH
1 Pekerja Oh 0.6600 94,500.00 Rp 62,370.00
2 Tukang Kayu Oh 0.3300 136,500.00 Rp 45,045.00
3 Kepala Tukang Oh 0.0330 157,500.00 Rp 5,197.50
4 Mandor Oh 0.0330 126,000.00 Rp 4,158.00
JUMLAH UPAH Rp 116,770.50
JUMLAH Rp 262,819.20
DIBULATKAN Rp 262,819.00

15 1 M² Pasang Bekesting Untuk Dinding


a. BAHAN
1 Kayu balok terentang M3 0.0300 3,927,000.00 Rp 117,810.00
2 Paku Biasa 2" - 5" Kg 0.4000 24,570.00 Rp 9,828.00
3 Minyak Bekisting Ltr 0.2000 32,025.00 Rp 6,405.00
4 Kayu balok terentang M3 0.0200 3,927,000.00 Rp 78,540.00
5 Multiplek Tbl.9mm Lbr 0.3500 109,725.00 Rp 38,403.75
6 Dolken Ø-8-10/4m Btg 3.0000 15,750.00 Rp 47,250.00
7 Formit/ Penjaga Jarak Bekisting Btg 4.0000 15,750.00 Rp 63,000.00
JUMLAH BAHAN Rp 361,236.75
Jumlah Bahan Mall Untuk 2 x pakai Ls 0.4000 361,236.75 Rp 144,494.70
b. UPAH
1 Pekerja Oh 0.6600 94,500.00 Rp 62,370.00
2 Tukang Kayu Oh 0.3300 136,500.00 Rp 45,045.00
3 Kepala Tukang Oh 0.0330 157,500.00 Rp 5,197.50
4 Mandor Oh 0.0330 126,000.00 Rp 4,158.00
JUMLAH UPAH Rp 116,770.50
JUMLAH Rp 261,265.20
DIBULATKAN Rp 261,265.00

16 1 M² Pasang Bata Merah Tebal 1 Bata, 1pc : 3ps


a. BAHAN
- Bata Merah Bh 140.0000 735.00 Rp 102,900.00
- Semen Portland Kg 32.9500 1,443.75 Rp 47,571.56
- Pasir Pasang M3 0.0910 136,500.00 Rp 12,421.50
JUMLAH BAHAN Rp 162,893.06
b. UPAH
- Pekerja Oh 0.6500 94,500.00 Rp 61,425.00
- Tukang Batu Oh 0.2000 136,500.00 Rp 27,300.00
- Kepala Tukang Oh 0.0200 157,500.00 Rp 3,150.00
- Mandor Oh 0.0300 126,000.00 Rp 3,780.00
JUMLAH UPAH Rp 95,655.00
c. JUMLAH BAHAN + UPAH Rp 258,548.06
d. DIBULATKAN Rp 258,548.00

17 1 M² Pasang Bata Merah Tebal 1 Bata, 1pc : 4ps


a. BAHAN
- Bata Merah Bh 140.0000 735.00 Rp 102,900.00

Halaman 9 dari 20 Lembar


DUTAINTERIORMEDAN/AHSP/PEMBANGUNANPAGAR/JALANPUTRIHIJAUDALAM/2020

ANALISA HARGA SATUAN PEKERJAAN


Proyek
Lokasi
:
:
Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm
Jalan Putri Hijau Dalam
A.H.S.P.
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
- Semen Portland Kg 26.5500 1,443.75 Rp 38,331.56
- Pasir Pasang M3 0.0930 136,500.00 Rp 12,694.50
JUMLAH BAHAN Rp 153,926.06
b. UPAH
- Pekerja Oh 0.6500 94,500.00 Rp 61,425.00
- Tukang Batu Oh 0.2000 136,500.00 Rp 27,300.00
- Kepala Tukang Oh 0.0200 157,500.00 Rp 3,150.00
- Mandor Oh 0.0300 126,000.00 Rp 3,780.00
JUMLAH UPAH Rp 95,655.00
c. JUMLAH BAHAN + UPAH Rp 249,581.06
d. DIBULATKAN Rp 249,581.00

18 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 3ps


a. BAHAN
- Bata Merah Bh 70.0000 735.00 Rp 51,450.00
- Semen Portland Kg 14.3700 1,443.75 Rp 20,746.69
- Pasir Pasang M3 0.0400 136,500.00 Rp 5,460.00
JUMLAH BAHAN Rp 77,656.69
b. UPAH
- Pekerja Oh 0.3200 94,500.00 Rp 30,240.00
- Tukang Batu Oh 0.1000 136,500.00 Rp 13,650.00
- Kepala Tukang Oh 0.0100 157,500.00 Rp 1,575.00
- Mandor Oh 0.0150 126,000.00 Rp 1,890.00
JUMLAH UPAH Rp 47,355.00
c. JUMLAH BAHAN + UPAH Rp 125,011.69
d. DIBULATKAN Rp 125,012.00

19 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 4ps


a. BAHAN
- Bata Merah Bh 70.0000 735.00 Rp 51,450.00
- Semen Portland Kg 11.5000 1,443.75 Rp 16,603.13
- Pasir Pasang M3 0.0430 136,500.00 Rp 5,869.50
JUMLAH BAHAN Rp 73,922.63
b. UPAH
- Pekerja Oh 0.3200 94,500.00 Rp 30,240.00
- Tukang Batu Oh 0.1000 136,500.00 Rp 13,650.00
- Kepala Tukang Oh 0.0100 157,500.00 Rp 1,575.00
- Mandor Oh 0.0150 126,000.00 Rp 1,890.00
JUMLAH UPAH Rp 47,355.00
c. JUMLAH BAHAN + UPAH Rp 121,277.63
d. DIBULATKAN Rp 121,278.00

20 1 M² Plesteran adk. 1pc : 2ps Tebal 15 mm


a. BAHAN
- Semen Portland Kg 10.2240 1,443.75 14,760.90
- Pasir Pasang M3 0.0170 136,500.00 2,320.50
JUMLAH BAHAN Rp 17,081.40
b. UPAH
- Pekerja Oh 0.2000 94,500.00 18,900.00
- Tukang Batu Oh 0.1500 136,500.00 20,475.00
- Kepala Tukang Oh 0.0150 157,500.00 2,362.50
- Mandor Oh 0.0100 126,000.00 1,260.00
JUMLAH UPAH Rp 42,997.50
c. JUMLAH BAHAN + UPAH Rp 60,078.90
d. DIBULATKAN Rp 60,079.00

21 1 M² Plesteran adk. 1pc : 3ps Tebal 15 mm


a. BAHAN
- Semen Portland Kg 7.7760 1,443.75 11,226.60
- Pasir Pasang M3 0.0190 136,500.00 2,593.50

Halaman 10 dari 20 Lembar


DUTAINTERIORMEDAN/AHSP/PEMBANGUNANPAGAR/JALANPUTRIHIJAUDALAM/2020

ANALISA HARGA SATUAN PEKERJAAN


Proyek
Lokasi
:
:
Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm
Jalan Putri Hijau Dalam
A.H.S.P.
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
JUMLAH BAHAN Rp 13,820.10
b. UPAH
- Pekerja Oh 0.2000 94,500.00 18,900.00
- Tukang Batu Oh 0.1500 136,500.00 20,475.00
- Kepala Tukang Oh 0.0150 157,500.00 2,362.50
- Mandor Oh 0.0100 126,000.00 1,260.00
JUMLAH UPAH Rp 42,997.50
c. JUMLAH BAHAN + UPAH Rp 56,817.60
d. DIBULATKAN Rp 56,818.00

22 1 M² Plesteran adk. 1pc : 4ps Tebal 15 mm


a. BAHAN
- Semen Portland Kg 6.2400 1,443.75 9,009.00
- Pasir Pasang M3 0.0200 136,500.00 2,730.00
JUMLAH BAHAN Rp 11,739.00
b. UPAH
- Pekerja Oh 0.2000 94,500.00 18,900.00
- Tukang Batu Oh 0.1500 136,500.00 20,475.00
- Kepala Tukang Oh 0.0150 157,500.00 2,362.50
- Mandor Oh 0.0100 126,000.00 1,260.00
JUMLAH UPAH Rp 42,997.50
c. JUMLAH BAHAN + UPAH Rp 54,736.50
d. DIBULATKAN Rp 54,737.00

23 1 M² Plesteran Beton adk. 1pc : 2ps Tebal 15 mm


a. BAHAN
- Semen Portland Kg 9.3000 1,443.75 13,426.88
- Pasir Pasang M3 0.0180 136,500.00 2,457.00
JUMLAH BAHAN Rp 15,883.88
b. UPAH
- Pekerja Oh 0.2600 94,500.00 24,570.00
- Tukang Batu Oh 0.2000 136,500.00 27,300.00
- Kepala Tukang Oh 0.0200 157,500.00 3,150.00
- Mandor Oh 0.0130 126,000.00 1,638.00
JUMLAH UPAH Rp 56,658.00
c. JUMLAH BAHAN + UPAH Rp 72,541.88
d. DIBULATKAN Rp 72,542.00

24 1 M² Plesteran Beton adk. 1pc : 3ps Tebal 15 mm


a. BAHAN
- Semen Portland Kg 7.0700 1,443.75 10,207.31
- Pasir Pasang M3 0.0210 136,500.00 2,866.50
JUMLAH BAHAN Rp 13,073.81
b. UPAH
- Pekerja Oh 0.2600 94,500.00 24,570.00
- Tukang Batu Oh 0.2000 136,500.00 27,300.00
- Kepala Tukang Oh 0.0200 157,500.00 3,150.00
- Mandor Oh 0.0130 126,000.00 1,638.00
JUMLAH UPAH Rp 56,658.00
c. JUMLAH BAHAN + UPAH Rp 69,731.81
d. DIBULATKAN Rp 69,732.00

25 1 M² Acian Plesteran
a. BAHAN
- Semen Portland Kg 2.0000 1,443.75 2,887.50
JUMLAH BAHAN Rp 2,887.50
b. UPAH
- Pekerja Oh 0.0953 94,500.00 9,009.00
- Tukang batu Oh 0.0713 136,500.00 9,737.00
- Kepala Tukang Oh 0.0070 157,500.00 1,102.50

Halaman 11 dari 20 Lembar


DUTAINTERIORMEDAN/AHSP/PEMBANGUNANPAGAR/JALANPUTRIHIJAUDALAM/2020

ANALISA HARGA SATUAN PEKERJAAN


Proyek
Lokasi
:
:
Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm
Jalan Putri Hijau Dalam
A.H.S.P.
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
- Mandor Oh 0.0070 126,000.00 882.00
JUMLAH UPAH Rp 20,730.50
c. JUMLAH BAHAN + UPAH Rp 23,618.00
d. DIBULATKAN Rp 23,618.00

26 1 M² Paving block natural 8 cm


a. BAHAN
- Paving block natural M² 1.050 93,670.50 98,354.03
- Pasir pasang Kg 0.100 136,500.00 13,650.00
JUMLAH BAHAN Rp 112,004.03
b. UPAH
- Pekerja Oh 0.2500 94,500.00 23,625.00
- Tukang batu Oh 0.5000 136,500.00 68,250.00
- Kepala tukang Oh 0.0250 157,500.00 3,937.50
- Mandor Oh 0.00250 126,000.00 315.00
JUMLAH UPAH Rp 96,127.50
c. JUMLAH UPAH + BAHAN Rp 208,131.53
d. DIBULATKAN Rp 208,132.00

27 1 M² Dinding Batu Alam Palimanan Rata Alam


a. BAHAN
- Batu Alam Palimanan M² 1.0500 126,000.00 132,300.00
- Semen portland Kg 12.2500 1,443.75 17,685.94
- Pasir pasang M³ 0.0563 136,500.00 7,678.13
JUMLAH BAHAN Rp 157,664.06
b. UPAH
- Pekerja Oh 0.4800 94,500.00 45,360.00
- Tukang batu Oh 0.2400 136,500.00 32,760.00
- Kepala tukang Oh 0.0240 157,500.00 3,780.00
- Mandor Oh 0.0250 126,000.00 3,150.00
JUMLAH UPAH Rp 85,050.00
c. JUMLAH UPAH + BAHAN Rp 242,714.06
d. DIBULATKAN Rp 242,714.00

28 1 M² Pengecatan Tembok Baru Eksterior Setara ICI


a. BAHAN
- Cat dasar Dulux Kg 0.1200 50,400.00 6,048.00
- Cat Dulux penutup 2x setara ICI Kg 0.2600 98,962.50 25,730.25
JUMLAH BAHAN Rp 31,778.25
b. UPAH
- Pekerja Oh 0.0200 94,500.00 1,890.00
- Tukang cat Oh 0.0630 136,500.00 8,599.50
- Kepala tukang Oh 0.0063 157,500.00 992.25
- Mandor Oh 0.0025 126,000.00 315.00
JUMLAH UPAH Rp 11,796.75
c. JUMLAH UPAH + BAHAN Rp 43,575.00
d. DIBULATKAN Rp 43,575.00

29 1 M² Pengecatan Tembok Baru Eksterior Setara Catylac


a. BAHAN
- Cat dasar Catylac Kg 0.1200 23,625.00 2,835.00
- Cat Catylac penutup 2 x Kg 0.2600 40,950.00 10,647.00
JUMLAH BAHAN Rp 13,482.00
b. UPAH
- Pekerja Oh 0.0280 94,500.00 2,646.00
- Tukang cat Oh 0.0420 136,500.00 5,733.00
- Kepala tukang Oh 0.0042 157,500.00 661.50
- Mandor Oh 0.0025 126,000.00 315.00
JUMLAH UPAH Rp 9,355.50
c. JUMLAH UPAH + BAHAN Rp 22,837.50

Halaman 12 dari 20 Lembar


DUTAINTERIORMEDAN/AHSP/PEMBANGUNANPAGAR/JALANPUTRIHIJAUDALAM/2020

ANALISA HARGA SATUAN PEKERJAAN


Proyek
Lokasi
:
:
Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm
Jalan Putri Hijau Dalam
A.H.S.P.
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
d. DIBULATKAN Rp 22,838.00

30 1 M² Pengecatan Tembok Baru Interior Setara ICI


a. BAHAN
- Cat dasar Dulux Interior Alkali Sealer Kg 0.1200 46,147.50 5,537.70
- Cat Dulux penutup 2x Interior Putih Glow Kg 0.2600 30,450.00 7,917.00
JUMLAH BAHAN Rp 13,454.70
b. UPAH
- Pekerja Oh 0.0200 94,500.00 1,890.00
- Tukang cat Oh 0.0630 136,500.00 8,599.50
- Kepala tukang Oh 0.0063 157,500.00 992.25
- Mandor Oh 0.0025 126,000.00 315.00
JUMLAH UPAH Rp 11,796.75
c. JUMLAH UPAH + BAHAN Rp 25,251.45
d. DIBULATKAN Rp 25,251.00

31 1 M² Pengecatan Tembok Baru Interior Setara Catylac


a. BAHAN
- Cat dasar Catylac Kg 0.2400 23,625.00 5,670.00
- Cat Catylac penutup 2 x Kg 0.1800 26,250.00 4,725.00
JUMLAH BAHAN Rp 10,395.00
b. UPAH
- Pekerja Oh 0.0280 94,500.00 2,646.00
- Tukang cat Oh 0.0420 136,500.00 5,733.00
- Kepala tukang Oh 0.0042 157,500.00 661.50
- Mandor Oh 0.0025 126,000.00 315.00
JUMLAH UPAH Rp 9,355.50
c. JUMLAH UPAH + BAHAN Rp 19,750.50
d. DIBULATKAN Rp 19,751.00

32 1 M² Pengecatan Permukaan Baja dengan Meni Besi


a. BAHAN
- Meni besi Kg 0.2000 46,200.00 9,240.00
- Kuas 3" Bh 0.0200 27,300.00 546.00
JUMLAH BAHAN Rp 9,786.00
b. UPAH
- Pekerja Oh 0.1000 94,500.00 9,450.00
- Tukang cat Oh 0.1000 136,500.00 13,650.00
- Kepala tukang Oh 0.1000 157,500.00 15,750.00
- Mandor Oh 0.0500 126,000.00 6,300.00
JUMLAH UPAH Rp 45,150.00
c. JUMLAH UPAH + BAHAN Rp 54,936.00
d. DIBULATKAN Rp 54,936.00

33 1 M² Pemasangan Pagar Besi Hollow 50x50x2,7 mm dan 30x60x1,7 mm


a. BAHAN
- Hollow 50x50x2,7mm M' 4.2000 70,070.00 294,294.00
- Hollow 30x60x1,7 mm M' 6.3000 43,312.50 272,868.75
- 30% Aksesoris (Perkuatan, las, dll) Ls 0.3000 567,162.75 170,148.83
JUMLAH BAHAN Rp 737,311.58
b. UPAH
- Pekerja Oh 0.4000 94,500.00 37,800.00
- Tukang Besi Oh 0.4000 136,500.00 54,600.00
- Kepala tukang Oh 0.0400 157,500.00 6,300.00
- Mandor Oh 0.0200 126,000.00 2,520.00
JUMLAH UPAH Rp 101,220.00
c. JUMLAH UPAH + BAHAN Rp 838,531.58
d. DIBULATKAN Rp 838,532.00

34 1 M² Pemasangan Pagar Besi Hollow 40x40x2,7 mm dan 20x20x1,7 mm

Halaman 13 dari 20 Lembar


DUTAINTERIORMEDAN/AHSP/PEMBANGUNANPAGAR/JALANPUTRIHIJAUDALAM/2020

ANALISA HARGA SATUAN PEKERJAAN


Proyek
Lokasi
:
:
Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm
Jalan Putri Hijau Dalam
A.H.S.P.
HARGA SATUAN HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp) (Rp)
a. BAHAN
- Hollow 40x40x2,7mm M' 4.2000 54,670.00 229,614.00
- Hollow 20x20x1,7 mm M' 8.4000 27,720.00 232,848.00
- 30% Aksesoris (Perkuatan, las, dll) Ls 0.3000 462,462.00 138,738.60
JUMLAH BAHAN Rp 601,200.60
b. UPAH
- Pekerja Oh 0.4000 94,500.00 37,800.00
- Tukang Besi Oh 0.4000 136,500.00 54,600.00
- Kepala tukang Oh 0.0400 157,500.00 6,300.00
- Mandor Oh 0.0200 126,000.00 2,520.00
JUMLAH UPAH Rp 101,220.00
c. JUMLAH UPAH + BAHAN Rp 702,420.60
d. DIBULATKAN Rp 702,421.00

Halaman 14 dari 20 Lembar


RENCANA ANGGARAN BIAYA
Proyek
Lokasi
:
:
Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm
Jalan Putri Hijau Dalam
RAB
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)
A. PEKERJAAN PERSIAPAN
1) Pekerjaan Bobokan Dinding; h=50 cm 2.63 M³ 417,533.00 Rp 1,096,024.13
2) Pekerjaan Bobokan Kolom 0.95 M³ 695,888.00 Rp 657,614.16
3) Pekerjaan Pembongkaran Pagar 1.00 Ls 500,000.00 Rp 500,000.00
4) Pekerjaan Pengukuran dan Bowplank 35.00 M' 56,115.00 Rp 1,964,025.00
B. PEKERJAAN TANAH
1) Pekerjaan Galian Tanah; Pondasi Rolag Uk.20x20 cm 0.90 M³ 80,325.00 Rp 72,292.50
2) Pekerjaan Galian Tanah; Pondasi Setempat Uk.40x60x60 cm 2.02 M³ 80,325.00 Rp 161,935.20
C. PEKERJAAN PONDASI
1) Pekerjaan Pondasi Rolag; Uk.20x20 cm
a. Pekerjaan Lantai Kerja; Spesi 1Pc:3Psr:5Krkl 0.30 M³ 892,989.00 Rp 267,896.70
b. Pekerjaan Pondai Rolag Bata; Pas. 1 Batu; Spesi 1Pc:3Psr 6.00 M³ 258,548.00 Rp 1,551,288.00
2) Pekerjaan Pondasi Plat Setempat
a. Pekerjaan Lantai Kerja; Spesi 1Pc:3Psr:5Krkl 0.19 M³ 892,989.00 Rp 171,453.89
b. Pekerjaan Bekisting Pondasi 16.00 M² 116,029.00 Rp 1,856,464.00
c. Pekerjaan Pembesian 97.30 Kg 15,313.00 Rp 1,489,954.90
d. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 1.73 M³ 892,989.00 Rp 1,543,084.99
D. PEKERJAAN BETON
1) Pekerjaan Kolom Pagar; Uk. 40x60x200 cm
a. Pekerjaan Bekisting Kolom 38.40 M² 237,619.00 Rp 9,124,569.60
b. Pekerjaan Pembesian
b.1. Pekerjaan Stek Besi 14ø12mm 170.45 Kg 15,313.00 Rp 2,610,099.62
b.2. Pekerjaan Beugel ø8-200 mm 69.44 Kg 15,313.00 Rp 1,063,373.92
c. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 3.84 M³ 892,989.00 Rp 3,429,077.76
2) Pekerjaan Balok Pinggang; Uk. 10x15 cm
a. Pekerjaan Bekisting Kolom 0.45 M² 242,332.00 Rp 109,049.40
b. Pekerjaan Pembesian
- Berat Stek Besi ø8-200 mm 68.88 Kg 15,313.00 Rp 1,054,722.69
c. Pekerjaan Beton; Spesi 1Pc:2Psr:3Krkl 0.45 M³ 892,989.00 Rp 401,845.05
3) Pekerjaan Topi Kolom; Uk.50x70 cm
a. Pekerjaan Bekisting Kolom 3.20 M² 262,819.00 Rp 841,020.80
b. Pekerjaan Pembesian
- Berat Stek Besi ø8-100 mm 25.88 Kg 15,313.00 Rp 396,348.46
c. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 0.84 M³ 892,989.00 Rp 750,110.76
E. PEKERJAAN PASANGAN BATU BATA
1) Pekerjaan Pasangan Bata; Pas.1/2 Batu; Spesi 1Pc:3Psr; Tinggi 50 cm 13.40 M² 125,012.00 Rp 1,675,160.80
F. PEKERJAAN RELIEF
1) Pekerjaan Relief Balok Pinggang - M' - Rp -
2) Pekerjaan Relief Mahkota Kolom - M' - Rp -
G. PEKERJAAN PELAPIS DINDING
1) Pekerjaan Batu Alam Pada Dinding 32.80 M² 242,714.00 Rp 7,961,019.20
2) Pekerjaan Batu Alam Pada Kolom 36.40 M² 242,714.00 Rp 8,834,789.60
H. PEKERJAAN PAGAR BESI HOLLOW
1) Pekerjaan Pagar Besi Hollow 40x40mm dan 20x40mm 30.00 M² 702,421.00 Rp 21,072,630.00
2) Pekerjaan Gerbang Entrance (trmksd tiang, rel dan aksesoris) 1.00 Ls 10,350,000.00 Rp 10,350,000.00
I. PEKERJAAN PENGECATAN
1) Pengecatan Cat Eksterior Setara ICI 16.50 M' 43,575.00 Rp 718,987.50
2) Pengecatan Pagar 92.70 M² 54,936.00 Rp 5,092,567.20
3) Pekerjaan Coating Batu Alam Propan 26.80 M² 35,000.00 Rp 938,000.00
JUMLAH TOTAL BIAYA PEKERJAAN Rp 87,755,405.83
DIBULATKAN Rp 87,755,000.00

Terbilang = SEMBILAN PULUH DUA JUTA SERATUS TIGA PULUH TUJUH RIBU RUPIAH
Medan; 13 Agustus 2020

Dibuat Oleh
Pelaksana
DUTA INTERIOR MEDAN
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)

(RALES SIMAMORA )
RENCANA ANGGARAN BIAYA
Proyek
Lokasi
:
:
Pembangunan Dinding Pagar Besi Hollow 50x50mm dan 30x60 mm
Jalan Putri Hijau Dalam
RAB
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)
A. PEKERJAAN PERSIAPAN
1) Pekerjaan Bobokan Dinding; h=50 cm 2.63 M³ 417,533.00 Rp 1,096,024.13
2) Pekerjaan Bobokan Kolom 0.95 M³ 695,888.00 Rp 657,614.16
3) Pekerjaan Pembongkaran Pagar 1.00 Ls 500,000.00 Rp 500,000.00
4) Pekerjaan Pengukuran dan Bowplank 35.00 M' 56,115.00 Rp 1,964,025.00
B. PEKERJAAN TANAH
1) Pekerjaan Galian Tanah; Pondasi Rolag Uk.20x20 cm 0.90 M³ 80,325.00 Rp 72,292.50
2) Pekerjaan Galian Tanah; Pondasi Setempat Uk.40x60x60 cm 2.02 M³ 80,325.00 Rp 161,935.20
C. PEKERJAAN PONDASI
1) Pekerjaan Pondasi Rolag; Uk.20x20 cm
a. Pekerjaan Lantai Kerja; Spesi 1Pc:3Psr:5Krkl 0.30 M³ 892,989.00 Rp 267,896.70
b. Pekerjaan Pondai Rolag Bata; Pas. 1 Batu; Spesi 1Pc:3Psr 6.00 M³ 258,548.00 Rp 1,551,288.00
2) Pekerjaan Pondasi Plat Setempat
a. Pekerjaan Lantai Kerja; Spesi 1Pc:3Psr:5Krkl 0.19 M³ 892,989.00 Rp 171,453.89
b. Pekerjaan Bekisting Pondasi 16.00 M² 116,029.00 Rp 1,856,464.00
c. Pekerjaan Pembesian 97.30 Kg 15,313.00 Rp 1,489,954.90
d. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 1.73 M³ 892,989.00 Rp 1,543,084.99
D. PEKERJAAN BETON
1) Pekerjaan Kolom Pagar; Uk. 40x60x200 cm
a. Pekerjaan Bekisting Kolom 38.40 M² 237,619.00 Rp 9,124,569.60
b. Pekerjaan Pembesian
b.1. Pekerjaan Stek Besi 14ø12mm 170.45 Kg 15,313.00 Rp 2,610,099.62
b.2. Pekerjaan Beugel ø8-200 mm 69.44 Kg 15,313.00 Rp 1,063,373.92
c. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 3.84 M³ 892,989.00 Rp 3,429,077.76
2) Pekerjaan Balok Pinggang; Uk. 10x15 cm
a. Pekerjaan Bekisting Kolom 0.45 M² 242,332.00 Rp 109,049.40
b. Pekerjaan Pembesian
- Berat Stek Besi ø8-200 mm 68.88 Kg 15,313.00 Rp 1,054,722.69
c. Pekerjaan Beton; Spesi 1Pc:2Psr:3Krkl 0.45 M³ 892,989.00 Rp 401,845.05
3) Pekerjaan Topi Kolom; Uk.50x70 cm
a. Pekerjaan Bekisting Kolom 3.20 M² 262,819.00 Rp 841,020.80
b. Pekerjaan Pembesian
- Berat Stek Besi ø8-100 mm 25.88 Kg 15,313.00 Rp 396,348.46
c. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 0.84 M³ 892,989.00 Rp 750,110.76
E. PEKERJAAN PASANGAN BATU BATA
1) Pekerjaan Pasangan Bata; Pas.1/2 Batu; Spesi 1Pc:3Psr; Tinggi 50 cm 13.40 M² 125,012.00 Rp 1,675,160.80
F. PEKERJAAN RELIEF
1) Pekerjaan Relief Balok Pinggang - M' - Rp -
2) Pekerjaan Relief Mahkota Kolom - M' - Rp -
G. PEKERJAAN PELAPIS DINDING
1) Pekerjaan Batu Alam Pada Dinding 32.80 M² 242,714.00 Rp 7,961,019.20
2) Pekerjaan Batu Alam Pada Kolom 36.40 M² 242,714.00 Rp 8,834,789.60
H. PEKERJAAN PAGAR BESI HOLLOW
1) Pekerjaan Pagar Besi Hollow 50x50mm dan 30x60mm 30.00 M² 838,532.00 Rp 25,155,960.00
2) Pekerjaan Gerbang Entrance (trmksd tiang, rel dan aksesoris) 1.00 Ls 11,500,000.00 Rp 11,500,000.00
I. PEKERJAAN PENGECATAN
1) Pengecatan Cat Eksterior Setara ICI 16.50 M' 43,575.00 Rp 718,987.50
2) Pengecatan Pagar 92.70 M² 54,936.00 Rp 5,092,567.20
3) Pekerjaan Coating Batu Alam Propan 26.80 M² 35,000.00 Rp 938,000.00
JUMLAH TOTAL BIAYA PEKERJAAN Rp 92,988,735.83
DIBULATKAN Rp 92,988,000.00

Terbilang = SEMBILAN PULUH DUA JUTA SEMBILAN RATUS SEMBILAN PULUH DELAPAN RIBU RUPIAH
Medan; 13 Agustus 2020

Dibuat Oleh
Pelaksana
DUTA INTERIOR MEDAN
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)

(RALES SIMAMORA )
RENCANA ANGGARAN BIAYA
Pekerjaan : Pembangunan Dinding Pagar Besi Pipa Hitam; Tinggi 2 Meter RAB
Lokasi : Jalan Putri Hijau Dalam

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)
A. PEKERJAAN PERSIAPAN
1) Pekerjaan Bobokan Dinding; h=50 cm 2.25 M³ 417,533.00 Rp 939,449.25
2) Pekerjaan Bobokan Kolom 0.95 M³ 695,888.00 Rp 657,614.16
3) Pekerjaan Pembongkaran Pagar 1.00 Ls 500,000.00 Rp 500,000.00
4) Pekerjaan Pengukuran dan Bowplank 35.00 M' 56,115.00 Rp 1,964,025.00
B. PEKERJAAN TANAH
1) Pekerjaan Galian Tanah; Pondasi Rolag Uk.20x20 cm 0.90 M³ 80,325.00 Rp 72,292.50
2) Pekerjaan Galian Tanah; Pondasi Setempat Uk.40x60x60 cm 2.02 M³ 80,325.00 Rp 161,935.20
C. PEKERJAAN PONDASI
1) Pekerjaan Pondasi Rolag; Uk.20x20 cm
a. Pekerjaan Lantai Kerja; Spesi 1Pc:3Psr:5Krkl 0.30 M³ 892,989.00 Rp 267,896.70
b. Pekerjaan Pondai Rolag Bata; Pas. 1 Batu; Spesi 1Pc:3Psr 6.00 M³ 258,548.00 Rp 1,551,288.00
2) Pekerjaan Pondasi Plat Setempat
a. Pekerjaan Lantai Kerja; Spesi 1Pc:3Psr:5Krkl 0.19 M³ 892,989.00 Rp 171,453.89
b. Pekerjaan Bekisting Pondasi 16.00 M² 116,029.00 Rp 1,856,464.00
c. Pekerjaan Pembesian 97.30 Kg 15,313.00 Rp 1,489,954.90
d. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 1.73 M³ 892,989.00 Rp 1,543,084.99
D. PEKERJAAN BETON
1) Pekerjaan Kolom Pagar; Uk. 40x60x200 cm
a. Pekerjaan Bekisting Kolom 38.40 M² 237,619.00 Rp 9,124,569.60
b. Pekerjaan Pembesian
b.1. Pekerjaan Stek Besi 14ø12mm 170.45 Kg 15,313.00 Rp 2,610,099.62
b.2. Pekerjaan Beugel ø8-200 mm 69.44 Kg 15,313.00 Rp 1,063,373.92
c. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 3.84 M³ 892,989.00 Rp 3,429,077.76
2) Pekerjaan Balok Pinggang; Uk. 8x30 cm
a. Pekerjaan Bekisting Kolom 12.00 M² 242,332.00 Rp 2,907,984.00
b. Pekerjaan Pembesian
- Berat Stek Besi ø8-200 mm 56.22 Kg 15,313.00 Rp 860,970.36
c. Pekerjaan Beton; Spesi 1Pc:2Psr:3Krkl 0.72 M³ 892,989.00 Rp 642,952.08
3) Pekerjaan Topi Kolom; Uk.50x70 cm
a. Pekerjaan Bekisting Kolom 3.20 M² 262,819.00 Rp 841,020.80
b. Pekerjaan Pembesian
- Berat Stek Besi ø8-100 mm 25.88 Kg 15,313.00 Rp 396,348.46
c. Pekerjaan Beton; Spesi 1Pc:3Psr:5Krkl 0.84 M³ 892,989.00 Rp 750,110.76
E. PEKERJAAN PASANGAN BATU BATA
1) Pekerjaan Pasangan Bata; Pas.1/2 Batu; Spesi 1Pc:3Psr; Tinggi 50 cm 13.40 M² 125,012.00 Rp 1,675,160.80
F. PEKERJAAN RELIEF
1) Pekerjaan Relief Balok Pinggang 66.80 M' 55,000.00 Rp 3,674,000.00
2) Pekerjaan Relief Mahkota Kolom 5.60 M' 55,000.00 Rp 308,000.00
G. PEKERJAAN PELAPIS DINDING
1) Pekerjaan Batu Alam 26.80 M² 242,714.00 Rp 6,504,735.20
2) Pekerjaan Batu Alam Pada Kolom 34.80 M² 242,714.00 Rp 8,446,447.20
H. PEKERJAAN PAGAR BESI HOLLOW
1) Pekerjaan Pagar Besi Hollow 30x60x2mm dan 60x60x3 mm 26.80 M² 1,075,300.00 Rp 28,818,040.00
2) Pekerjaan Gerbang Entrance 1.00 Ls 17,500,000.00 Rp 17,500,000.00
I. PEKERJAAN PENGECATAN
1) Pengecatan Cat Eksterior Setara ICI 16.50 M' 43,575.00 Rp 718,987.50
2) Pengecatan Pagar 92.70 M² 54,936.00 Rp 5,092,567.20
3) Pekerjaan Coating Batu Alam Propan 26.80 M² 35,000.00 Rp 938,000.00
JUMLAH TOTAL BIAYA PEKERJAAN Rp 107,477,903.86
DIBULATKAN Rp 107,477,000.00

Terbilang = SERATUS TUJUH JUTA EMPAT RATUS TUJUH PULUH TUJUH RIBU RUPIAH
Medan; 13 Agustus 2020

Dibuat Oleh
Pelaksana
DUTA INTERIOR MEDAN
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rupiah) (Rupiah)
(1) (2) (3) (4) (5)

(RALES SIMAMORA )

Anda mungkin juga menyukai