SURVEY HARGA SATUAN UPAH DAN BAHAN

Pekerjaan : PERLUASAN APRON DAN FASILITAS PENUNJANGNYA


Lokasi : DI BANDARA INTERNASIONAL LOMBOK

PENYEDIA : …………………………………………

ALAMAT : FOTO TOKO / PENYEDIA


…………………………………………

TGL SURVEY :
…………………………………………

SURVEYOR :
…………………………………………

No. JENIS TENAGA DAN BAHAN SATUAN HARGA SATUAN TOKO / PENYEDIA KETERANGAN
BAHAN / UPAH (SUMBER)
(Rp.)

I. UPAH TENAGA

1 Pekerja hr WAWANCARA

2 Pekerja ME hr WAWANCARA
3 Tukang (batu,kayu ,besi ,las,cat,listrik) hr WAWANCARA

4 Kepala Tukang batu (batu,kayu,besi,las,cat) hr WAWANCARA

5 Mandor hr WAWANCARA
6 Operator hr WAWANCARA

7 Pembantu operator hr WAWANCARA

8 Sopir hr WAWANCARA
9 Pembantu sopir hr WAWANCARA

10 Mandor ME hr WAWANCARA

11 Tenaga pengukuran hr WAWANCARA

12 Staff pengukuran hr WAWANCARA

II. BAHAN DASAR

1 Tanah pilihan m3

2 Sirtu m3

3 Batu Kali Belah m3


4 Bata merah bj

5 Portland Cement (PC) @ 40 kg zak - /per kg

6 Pasir BETON m3 - /per kg


7 Batu pecah 1/2 cm m3 - /per kg

8 Batu pecah 2/3 cm m3 - /per kg

9 Batu pecah 0,5/1 cm m3 - /per kg


10 Lolos Screen ukuran (9,5-19,0) m3

11 Lolos Screen ukuran (5-9,5) m3

12 Lolos Screen ukuran (0-5) m3

13 Agregat kasar m3

14 Agregat halus m3

15 Asphal esso/shell drum pen 60/70 kg


16 Tack coat (lapis perekat) esso/shell kg

17 Minyak Asphal ltr

18 Filler ltr

19 Kayu meranti 5/5 m3

20 #REF! kg
21 #REF! Lembar

22 #REF! m2 182,000.00 riben

23 #REF! batang
24 #REF! m2

25 #REF! kg

26 #REF! m3

27 #REF! ltr

28 #REF! m3
29 #REF! m3
30 Besi UNP 100 bj
31 Besi siku 70.70.7. m'

32 Baut angkur dia. 22 mm panjang 40 cm bj

33 Pipa PVC klas AW dia. 1" batang


34 Box sign acrylic berwarna tebal 3 mm termasuk m

35 Plat tebal 1,5 mm rangka acrylic m2

36 Baut angkur dia. 16 mm panjang 40 cm bj


37 Tarikan kabel dalam pipa jaringan bwh tanah m

38 Baut Angker kg

39 Plat landasan & sayap tebal 2 cm kg

III. BAHAN PENUNJANG


1 Multiplek 9 mm lbr

2 Minyak bekisting ltr

3 Kayu acuan bekisting m3


4 Kayu gelam dia. 10 (360-400) btg - /per m1

5 Pipa PVC btg

6 Grease kg
7 Paku kg

8 Additive ltr

IV. BAHAN FINISHING/CAT

1 Cat thermoplastik kg

2 Cat water based kg


3 Cat water borne kg

3 Glass beed kg

4 Cat besi kg

5 Cat dasar kg

6 Cat minyak kg

7 Thinner ltr

V. BESI & SEALENT

1 Besi beton kg
2 Wiremesh M7 m2

3 Kawat bendrat kg

4 Joint sealent tebal 20 mm m1

5 Joint sealent tebal 10 mm m1

6 Joint filler 20 mm m1

VI. SEWA PERALATAN

1 Asphal Mixing Plant jm


2 Asphal finisher jm

3 Batching plant jm

4 Concrete vibrator jm
5 Concrete paver jm

6 Cargo truck jm

7 Truck mixer jm
7 Dumptruck jm

8 Excavator PC 200 jm

9 Generator set jm
10 Motor grader jm

11 Pneumatic tire roller jm

12 Road marking machine jm

13 Tandem roller jm

14 Vibro roller jm

15 Water tank truck jm


16 Wheel loader jm

17 Walles jm

18 Coldmilling/cutter road jm
19 #REF! jm
20 #REF! jm

21 #REF! jm

22 #REF! jm
23 #REF! jm

24 #REF! jm

LAIN-LAIN

1 #REF! bln

2 #REF! set

No. JENIS TENAGA DAN BAHAN SATUAN HARGA SATUAN TOKO / PENYEDIA KETERANGAN
BAHAN / UPAH (SUMBER)
(Rp.)

VII. ELEKTRIKAL
1 Omni Directional Elevated Light Complete Blue LED 10-15W 6,6A bh

2 Isolating Transformer 10-15W/6,6A/6,6A bh

3 Lampu LED Floodlight min. 550W + housing bh

4 Primary Connector Kit lengkap dengan Resin bh

5 Secondary Connector Kit bh

6 Tiang tunggal BSP, tebal 1 cm, tinggi 24 m, (hot dip galvanized) le bh

7 Obstruction light (red) 60W bh

8 MCB 25 A,3P, 10kA bh

9 MCB 10 A,1P, 6kA bh


10 Box Parking sign acrylic berikut tiang stainless stell bh

11 Running text (timer) bh

12 Lampu LED tube 20W bh


13 Secondary Cable NYYHY 2x4 Sqmm bh

14 Jointing kabel FL2XCY 1x6 Sqmm, 3/6KV (konek dengan existing) bh

15 Series Cable FL2XCY 1x6 Sqmm, 3/6KV bh

16 Kabel NYGBY 4 x 10 mm2 m1

17 Kabel NYY 3 x 2,5 mm2 m1

18 Pipa sparing HDPE dia. 20mm m1

19 Breakable Coupling bh

20 Base plate bh

21 - Box Panel 50 x 60 x 40 outdoor, IP 65 unit

22 - MCB 6 A,1P, 6kA unit

23 - MC 10 A unit

24 - MC 6 A unit

25 - Arrester 3P unit

26 - Timer switch unit

27 - Pentanahan unit

28 - Cos Auto Manual unit

29 BC. 50. BC.60 unit

30 Coper Rod 1 m unit

31 Test / Ijin Binalindung

32 BC.60 unit

33 Fabrikasi Panel unit

34 Grounding bh