Anda di halaman 1dari 13

DAFTAR HARGA SATUAN

UPAH DAN BAHAN

SATUAN KERJA NVT : IRIGASI MALUKU TENGGARA & PULAU-PULAU KECIL MALUKU
SATUAN KEGIATAN : IRIGASI MALUKU TENGGARA BARAT
PEKERJAAN : REHABILITASI EMBUNG & JARINGAN AIR BAKU
LOKASI : DESA KROING & YALTUBUNG (PULAU BABAR)
THN ANGGARAN : 2006

1. SEMEN :

- Harga setempat = Rp. 65,000.00 / zak


- Ongkos angkutan Tual - Lokasi = Rp. 5,000.00 / zak
- Ongkos Bongkar / muat di lokasi (angkut 800 m) = Rp. 3,000.00 / zak
JUMLAH = Rp. 73,000.00 / zak
DIBULATKAN = Rp. 73,000.00 / zak

Analisa ongkos angkutan Saumlaki- Lokasi Pulau Babar :

- Jarak Tual - Lokasi (L) = 5.000 km


- 1 (satu) hari kerja (D) = 8.00 jam
- Isi 1 ( satu ) DumpTruck ( Vt ) = 50.00 zak
- Kecepatan rata-rata (V) = 40.00 km/jam
- Lamanya waktu muat / bongkar (T) = 1.00 jam
- Biaya transport Kapal per hari (B) = 750,000.00
- Jarak angkut rata-rata = 2L = 10.00 km
- Waktu per Trip (t) = 2L/V + T = 1.25 jam
- Jumlah Trip per hari (N) = D/t ( dibulatkan ) = 1 kali
- Produksi per hari (P) = N x Vt = 50.00 zak
- Ongkos angkut ke lokasi = B/P = Rp 15,000.00 / zak

2. BATU KALI :

- Harga Setempat = Rp. 115,000.00 / m3


- Ongkos angkut dengan Tenaga Manusia Quarry - Lokasi = Rp. 46,875.00 / m3
JUMLAH = Rp. 161,875.00 / m3
DIBULATKAN = Rp. 161,000.00 / m3

Analisa ongkos angkut dengan Tenaga Manusia ( Quarry - Lokasi ) :

- Jarak Quarry - Lokasi (L) = 5.00 km


- 1 (satu) hari kerja (D) = 8.00 jam
- Isi 1 ( satu ) Truck ( Vt ) = 2.50 m3
- Kecepatan rata-rata (V) = 40.00 km/jam
- Lamanya waktu muat / bongkar (T) = 1.00 jam
- Biaya Angkut per hari (B) = 750,000.00
- Jarak angkut rata-rata = 2L = 10.00 km
- Waktu per Trip (t) = 2L/V + T = 1.25 jam
- Jumlah Angkut per hari (N) = D/t ( dibulatkan ) = 6 kali
- Produksi per hari (P) = N x Vt = 16.00 m3
- Ongkos angkut ke lokasi = B/P = Rp 46,875.00 / m3
3. PASIR PASANG :

- Harga Setempat = Rp. 113,400.00 / m3


- Ongkos angkut Quarry - Lokasi = Rp. 46,875.00 / m3
JUMLAH = Rp. 160,275.00 / m3
DIBULATKAN = Rp. 160,000.00 / m3

Analisa ongkos ( Quarry - Lokasi ) :

- Jarak Quarry - Lokasi (L) = 5.00 km


- 1 (satu) hari kerja (D) = 8.00 jam
- Isi 1 ( satu ) Truck ( Vt ) = 2.50 m3
- Kecepatan rata-rata (V) = 40.00 km/jam
- Lamanya waktu muat / bongkar (T) = 1.00 jam
- Biaya angkut per hari (B) = 750,000.00
- Jarak angkut rata-rata 2L = 10.00 km
- Waktu per Trip (t) = 2L/V + T = 1.25 jam
- Jumlah Trip per hari (N) = D/t ( dibulatkan ) = 6 kali
- Produksi per hari (P) = N x Vt = 16.00 m3
- Ongkos angkut ke lokasi = B/P = Rp 46,875.00 / m3

4. PASIR URUG :

- Harga Setempat = Rp. 60,000.00 / m3


- Ongkos angkut Quarry - Lokasi = Rp. 46,875.00 / m3
JUMLAH = Rp. 106,875.00 / m3
DIBULATKAN = Rp. 106,000.00 / m3

Analisa ongkos angkut dengan Tenaga Manusia ( Quarry - Lokasi ) :

- Jarak Quarry - Lokasi (L) = 5.00 km


- 1 (satu) hari kerja (D) = 8.00 jam
- Isi 1 ( satu ) Truck ( Vt ) = 2.50 m3
- Kecepatan rata-rata (V) = 40.00 km/jam
- Lamanya waktu muat / bongkar (T) = 1.00 jam
- Biaya angkut per hari (B) = 750,000.00
- Jarak angkut rata-rata 2L = 10.00 km
- Waktu per Trip (t) = 2L/V + T = 1.25 jam
- Jumlah Trip per hari (N) = D/t ( dibulatkan ) = 6 kali
- Produksi per hari (P) = N x Vt = 16.00 m3
- Ongkos angkut ke lokasi = B/P = Rp 46,875.00 / m3

5. BATU KERIKIL :

- Harga Setempat = Rp. 135,000.00 / m3


- Ongkos angkut Quarry - Lokasi = Rp. 46,875.00 / m3
JUMLAH = Rp. 181,875.00 / m3
DIBULATKAN = Rp. 181,000.00 / m3

Analisa ongkos angkutan ( Quarry - Lokasi ) :

- Jarak Quarry - Lokasi (L) = 5.00 km


- 1 (satu) hari kerja (D) = 8.00 jam
- Isi 1 ( satu ) Truck ( Vt ) = 2.50 m3
- Kecepatan rata-rata (V) = 40.00 km/jam
- Lamanya waktu muat / bongkar (T) = 1.00 jam
- Biaya angkut per hari (B) = 750,000.00
- Jarak angkut rata-rata 2L = 10.00 km
- Waktu per Trip (t) = 2L/V + T = 1.25 jam
- Jumlah Trip per hari (N) = D/t ( dibulatkan ) = 6 kali
- Produksi per hari (P) = N x Vt = 16.00 m3
- Ongkos angkut B/P = Rp 46,875.00 / m3
6. BESI BETON

- Harga setempat = Rp. 6,700.00 / kg


- Ongkos angkutan Saumlaki - Lokasi = Rp. 130.43 / kg
- Ongkos Bongkar / muat di lokasi (angkut 450 m) = Rp. 750.00 / kg
JUMLAH = Rp. 7,580.43 / kg
DIBULATKAN = Rp. 7,580.43 / kg

Analisa ongkos angkutan Saumlaki- Lokasi Pulau Babar :

- Jarak Saumlaki - Lokasi (L) = 5.000 km


- 1 (satu) hari kerja (D) = 8.00 jam
- Isi 1 ( satu ) Truck ( Vt ) = 500.00 Staf = 4,991.00 kg
- Kecepatan rata-rata (V) = 40.00 km/jam
- Lamanya waktu muat / bongkar (T) = 1.00 jam
- Biaya transport Kapal per hari (B) = 750,000.00
- Jarak angkut rata-rata = 2L = 10.00 km
- Waktu per Trip (t) = 2L/V + T = 1.25 jam
- Jumlah Trip per hari (N) = D/t ( dibulatkan ) = 6 kali
- Produksi per hari (P) = N x Vt = 500.00 staf
- Ongkos angkut ke lokasi = B/P = Rp 130.43 / kg

7. PIPA HDPE 2"

- Harga setempat (Surabaya) = Rp. 25,550.00 /m


- Ongkas Muat Pelabuhan Surabaya = Rp. 3,000.00 /m
- Ongkos angkutan Surabaya - Tual = Rp. 5,250.00 /m
- Ongkos Bongkar Pelabuhan Tual = Rp. 3,000.00 /m
- Ongkos angkutan Tual - Lokasi = Rp. 5,250.00 /m
- Ongkos Bongkar Kapal Perintis- Motor ke lokasi = Rp. 0.00 /m
JUMLAH = Rp. 42,050.00 /m
DIBULATKAN = Rp. 42,050.00 /m

Analisa ongkos angkutan Surabaya - Saumlaki :

- Jarak Surabaya - Tual (L) = 1,450.000 km


- 7 (tujuh) hari kerja (D) = 168.00 jam
- Isi 1 ( satu ) Kapal ( Vt ) = 100.00 m3 = 10,000.00 m
- Kecepatan rata-rata (V) = 8.63 km/jam
- Lamanya waktu muat / bongkar (T) = 6.00 jam
- Biaya transport Kapal per hari (B) = 7,500,000.00 = 52,500,000.00 /7hr
- Jarak angkut rata-rata = 2L = 2,900.00 km
- Waktu per Trip (t) = 2L/V + T = 342.00 jam
- Jumlah Trip per 7 hari (N) = D/t ( dibulatkan ) = 1 kali
- Produksi per 7 hari (P) = N x Vt = 100.00 /m3
- Ongkos angkut ke lokasi = B/P = Rp 525,000.00 / m3
= Rp 5,250.00 /m

Analisa ongkos angkutan Saumlaki- Lokasi Pulau Babar :


- Jarak Saumlaki-Lokasi (L) = 5.000 km
- 1 (satu) hari kerja (D) = 8.00 jam
- Isi 1 ( satu ) Kapal ( Vt ) = 10.00 m3 = 1,000.00 m
- Kecepatan rata-rata (V) = 8.00 km/jam
- Lamanya waktu muat / bongkar (T) = 3.00 jam
- Biaya transport Kapal Trip (B) = 5,250,000.00
- Jarak angkut rata-rata 2L = 10.00 km
- Waktu per Trip (t) = 2L/V + T = 4.25 jam
- Jumlah Trip per hari (N) = D/t ( dibulatkan ) = 2 kali
- Produksi per hari (P) = N x Vt = 10.00 /m3
- Ongkos angkut ke lokasi = B/P = Rp 525,000.00 / m3
= Rp 5,250.00 /m
8. PIPA HDPE 1,5"

- Harga setempat (Surabaya) = Rp. 15,950.00 /m


- Ongkas Muat Pelabuhan Surabaya = Rp. 3,000.00 /m
- Ongkos angkutan Surabaya - Saumlaki = Rp. 5,250.00 /m
- Ongkos Bongkar Pelabuhan Saumlaki = Rp. 3,000.00 /m
- Ongkos angkutan Saumlaki - Lokasi = Rp. 5,250.00 /m
- Ongkos Bongkar Kapal Perintis- Motor ke lokasi = Rp. 0.00 /m
JUMLAH = Rp. 32,450.00 /m
DIBULATKAN = Rp. 32,450.00 /m

Analisa ongkos angkutan Surabaya - Saumlaki :

- Jarak Surabaya - Saumlaki (L) = 1,450.000 km


- 7 (tujuh) hari kerja (D) = 168.00 jam
- Isi 1 ( satu ) Kapal ( Vt ) = 100.00 m3 = 10,000.00 m
- Kecepatan rata-rata (V) = 8.63 km/jam
- Lamanya waktu muat / bongkar (T) = 6.00 jam
- Biaya transport Kapal per hari (B) = 7,500,000.00 = 52,500,000.00 /7hr
- Jarak angkut rata-rata = 2L = 2,900.00 km
- Waktu per Trip (t) = 2L/V + T = 342.00 jam
- Jumlah Trip per 7 hari (N) = D/t ( dibulatkan ) = 1 kali
- Produksi per 7 hari (P) = N x Vt = 100.00 /m3
- Ongkos angkut ke lokasi = B/P = Rp 525,000.00 / m3
= Rp 5,250.00 /m

Analisa ongkos angkutan Saumlaki- Lokasi Pulau Babar :


- Jarak Saumlaki-Lokasi (L) = 5.000 km
- 1 (satu) hari kerja (D) = 8.00 jam
- Isi 1 ( satu ) Kapal ( Vt ) = 10.00 m3 = 1,000.00 m
- Kecepatan rata-rata (V) = 8.00 km/jam
- Lamanya waktu muat / bongkar (T) = 3.00 jam
- Biaya transport Kapal Trip (B) = 5,250,000.00
- Jarak angkut rata-rata 2L = 10.00 km
- Waktu per Trip (t) = 2L/V + T = 4.25 jam
- Jumlah Trip per hari (N) = D/t ( dibulatkan ) = 2 kali
- Produksi per hari (P) = N x Vt = 10.00 /m3
- Ongkos angkut ke lokasi = B/P = Rp 525,000.00 / m3
= Rp 5,250.00 /m
DAFTAR HARGA UPAH DAN BAHAN P.AMBON

HARGA UPAH SAT. HARGA

1 Kepala Tukang Org/Hr Rp. 56,100.00


2 Mandor Org/Hr Rp. 73,900.00
3 Pekerja Org/Hr Rp. 48,500.00
4 Tukang Batu, Kayu, Besi, Cat & Pipa Org/Hr Rp. 54,500.00

HARGA BAHAN SAT. HARGA

Bahan Beton
1 Tanah Urug /M3 Rp. 47,000.00
2 Pasir Beton / Pasang /M3 Rp. 70,000.00
3 Pasir Urug /M3 Rp. 52,000.00
4 Batu Kali /M3 Rp. 60,000.00
5 Batu Kerikil /M3 Rp. 80,000.00
6 Batu Bata Merah /Buah Rp. 1,100.00
7 Semen PC (50 kg) Zak Rp. 62,000.00
8 Semen Warna /Kg Rp. 10,000.00
9 Keramik Uk. 30 x 30 cm (polos) Dos Rp. 50,000.00
10 Keramik Uk. 20 x 20 cm (polos) Dos Rp. 55,000.00
11 Keramik Uk. 20 x 20 cm (anti slip) Dos Rp. 55,000.00

Bahan Kayu
1 Kayu Klas I (Kayu Besi) /M3 Rp. 4,761,000.00
2 Papan Kayu Klas I (Kayu Besi) /M3 Rp. 5,100,000.00
3 Kayu Klas II (Makila) /M3 Rp. 1,800,000.00
4 Papan Kayu Klas II (Makila) /M3 Rp. 2,836,000.00
5 Tripleks Tebal 3 mm Lbr Rp. 52,000.00
6 Teacwood Lbr Rp. 106,500.00

Bahan Besi dan Atap


1 Besi Beton /Kg Rp. 163,000.00
2 Kawat Bendrat /Kg Rp. 20,000.00
3 Zink Gelombang BJLS 0,25 mm /Lbr Rp. 58,500.00
4 Zink Licin BJS 0,25 mm /Lbr Rp. 60,500.00
5 Paku Zink /Kg Rp. 26,000.00
6 Paku Semua Ukuran /Kg Rp. 20,500.00
7 Paku Tripleks /Kg Rp. 23,500.00
8 Paku Beton 2"-4" /Kg Rp. 22,000.00
9 Bubungan Genteng Metal /M' Rp. 37,500.00
10 Genteng Metal Rainbow /Lbr Rp. 36,500.00

Bahan Penggantung dan Kaca


1 Kunci Pintu 2 Slag /Buah 200,000.00
2 Kunci Pintu WC/KM /Buah 55,000.00
3 Engsel Pintu /Psg 25,000.00
4 Engsel Jendela /Psg 18,000.00
5 Kait Angin Jendela/Ventilasi /Buah 15,000.00
6 Grendel Pintu /Buah 6,500.00
7 Grendel Jendela /Buah Rp. 5,000.00
8 Kaca Bening 5 mm /M2 Rp. 105,000.00
9 Kaca Ray band. 5 mm /M2 Rp. 176,500.00
HARGA BAHAN SAT. HARGA

Bahan Cat
1 Plamir Tembok Boyo /Kg Rp. 19,500.00
2 Dumpul Kayu Kembang /Kg Rp. 19,500.00
3 Cat Dasar Kayu Kembang /Kg 19,500.00
4 Kertas Amplas Semua Ukuran /Lbr 4,000.00
5 Minyak Cat/Tener /Ltr 17,000.00
6 Cat Tembok Metrolate /Kg 15,000.00
7 Cat Kayu Glotex /Kg 41,500.00
8 Politur /Ltr 42,500.00
9 Teakoil /Ltr 42,500.00
10 Minyak Bakesting /Ltr 17,000.00
11 Cat Menie Nippon Paint /Kg 41,500.00

Bahan Instalasi Listrik


1 Titik Cahaya Lampu /Ttk 120,000.00
2 Perbaikan Titik Cahaya Lampu /Ttk Rp. 180,000.00
3 Lampu Neon TL 10 Watt /Ttk Rp. 44,500.00
4 Lampu Neon TL 20 Watt Lengkap /Ttk Rp. 66,500.00
5 Lampu TL Bambu 1 x 20 Watt Lengkap /Buah Rp. 153,900.00
6 Lampu Philips SL 15 Watt (capsul) + Viting Hias /Buah Rp. 121,500.00
6 Lampu Philips SL 18 Watt (tanpa capsul) + Viting Hias /Buah Rp. 109,000.00
7 Lampu Philips SL 11 Watt (tanpa capsul) + Viting Hias /Buah Rp. 70,000.00
8 Saklar Ganda Broco Inbouw /Buah Rp. 30,000.00
9 Saklar Tunggal Broco Inbouw /Buah Rp. 25,000.00
10 Stop Kontak /Buah Rp. 25,000.00
11 Rumah Panel MCB 2 Group/Tanam /Buah Rp. 202,500.00

Bahan Sanitasi
1 Titik Instalasi Air Bersih /Ttk Rp. 202,500.00
2 Perbaikan Titik Instalasi Air Bersih /Ttk Rp. 178,200.00
3 Kran Handle dia. 1/2" Unit Rp. 35,000.00
4 Pipa PVC 4" Staf Rp. 452,500.00
5 Pipa Hawa 2" /M' Rp. 54,000.00
6 Floor Drain Stanlies/Saringan Besi /Buah Rp. 69,000.00
7 Wastafel Warna/Keramik /Buah Rp. 473,500.00
8 Tempat Cuci Aluminium 2 Lobang /Buah Rp. 446,000.00
9 Closet Duduk Porselin Lengkap /Buah Rp. 1,986,000.00
10 Closet Duduk Porselin Engkel /Buah Rp. 1,147,500.00
11 Closet Jongkok /Buah Rp. 528,000.00
12 Bak Air Lapis Keramik /Buah Rp. 1,215,000.00
13 Septictank + Peresapan /Unit Rp. 2,700,000.00
14 Lapis Injuk /M3 Rp. 101,250.00
IV. PEKERJAAN KAYU

1 An. F2 1 M3 Rangka Atap Seng (Gording)


Upah :
18.000 Tukang Kayu @ Rp. 54,500.00 = Rp. 981,000.00
1.800 Kepala Tukang @ Rp. 56,100.00 = Rp. 100,980.00
6.000 Pekerja @ Rp. 48,500.00 = Rp. 291,000.00
0.300 Mandor @ Rp. 73,900.00 = Rp. 22,170.00
Rp. ###
Bahan :
1.100 M3 Kayu Kls. I @ Rp. 10,000.00 = Rp. 11,000.00
0.750 Kg. Paku Campuran @ Rp. 55,000.00 = Rp. 41,250.00
Rp. 52,250.00
Jumlah Upah + Bahan = Rp. ###
Over Head 10 % = Rp. 144,740.00
Total = Rp. ###

2 An. F22 1 M3 Pasang Kuda-Kuda Kayu Kls. I


Upah :
24.000 Tukang Kayu @ Rp. 54,500.00 = @ Rp. 1,308,000.00
2.400 Kepala Tukang @ Rp. 56,100.00 = @ Rp. 134,640.00
8.000 Pekerja @ Rp. 48,500.00 = @ Rp. 388,000.00
0.400 Mandor @ Rp. 73,900.00 = @ Rp. 29,560.00
= Rp. ###
Bahan :
1.100 M3 Kayu Kls. I @ Rp. 10,000.00 = Rp. 11,000.00
Rp. 11,000.00
Jumlah Upah + Bahan = Rp. 40,560.00
Over Head 10 % = Rp. 4,056.00
Total = Rp. 44,616.00

3 An. SK-SNI 1 M3 Pasang Kusen Pintu dan Jendela


Upah :
20.000 Tukang Kayu @ Rp. 54,500.00 = Rp. 1,090,000.00
2.000 Kepala Tukang @ Rp. 56,100.00 = Rp. 112,200.00
6.000 Pekerja @ Rp. 48,500.00 = Rp. 291,000.00
0.300 Mandor @ Rp. 73,900.00 = Rp. 22,170.00
Rp. ###
Bahan :
1.100 M3 Kayu Kls. I @ Rp. 10,000.00 = Rp. 11,000.00
Rp. 11,000.00
Jumlah Upah + Bahan = Rp. 33,170.00
Over Head 10 % = Rp. 3,317.00
Total = Rp. 36,487.00

4 An. SK-SNI 1M2 Pasang Lisplank Ukuran 3 x 20 cm Kayu Klas I


Upah :
0.200 Tukang Kayu @ Rp. 54,500.00 = Rp. 10,900.00
0.020 Kepala Tukang @ Rp. 56,100.00 = Rp. 1,122.00
0.100 Pekerja @ Rp. 48,500.00 = Rp. 4,850.00
0.005 Mandor @ Rp. 73,900.00 = Rp. 369.50
= Rp. 17,241.50
Bahan :
0.007 M3 Kayu Kls. I @ Rp. 10,000.00 = Rp. 70.00
0.050 Kg Paku Campuran @ Rp. 55,000.00 = Rp. 2,750.00
Rp. 2,820.00
Jumlah Upah + Bahan = Rp. 20,061.50
Over Head 10 % = Rp. 2,006.15
Total = Rp. 22,067.65
V. PEKERJAAN ATAP

1 An. SK SNI T 13 1993 03 TABEL 2.27 1M2 Pasang Bubungan Seng BJLS 0.20
Upah :
0.070 Tukang Kayu @ Rp. 54,500.00 = Rp. 3,815.00
0.080 Kepala Tukang @ Rp. 56,100.00 = Rp. 4,488.00
0.150 Pekerja @ Rp. 48,500.00 = Rp. 7,275.00
0.006 Mandor @ Rp. 73,900.00 = Rp. 443.40
= Rp. 16,021.40
Bahan :
0.400 Seng Datar BJLS 0. @ Rp. 1,800,000.00 = Rp. 720,000.00
0.060 Kg. Paku Seng @ Rp. 55,000.00 = Rp. 3,300.00
= Rp. 723,300.00
Jumlah Upah + Bahan = Rp. 739,321.40
Over Head 10 % = Rp. 73,932.14
Total = Rp. 813,253.54

2 An. SK SNI T 13 1993 03 TABEL 2.16 1M2 Pasang Atap Seng Gelombang BJLS 0.20
Upah :
0.070 Tukang Kayu @ Rp. 54,500.00 = Rp. 3,815.00
0.008 Kepala Tukang @ Rp. 56,100.00 = Rp. 448.80
0.150 Pekerja @ Rp. 48,500.00 = Rp. 7,275.00
0.006 Mandor @ Rp. 73,900.00 = Rp. 443.40
Rp. 11,982.20
Bahan :
1.100 M2 Atap Seng Gelo @ Rp. 5,100,000.00 = Rp. 5,610,000.00
0.010 Kg. Paku Seng @ Rp. 55,000.00 = Rp. 550.00
Rp. ###
Jumlah Upah + Bahan = Rp. ###
Over Head 10 % = Rp. 562,253.22
Total = Rp. ###

VI. PEKERJAAN PENGECATAN


1 An. K23 + K18 10 M2 Pengecatan Dengan Cat Menie
Upah :
0.750 Tukang Cat @ Rp. 54,500.00 = Rp. 40,875.00
0.075 Kepala Tukang @ Rp. 56,100.00 = Rp. 4,207.50
0.500 Pekerja @ Rp. 48,500.00 = Rp. 24,250.00
0.025 Mandor @ Rp. 73,900.00 = Rp. 1,847.50
Rp. 71,180.00

Bahan :
1.200 Kg Cat Menie @ Rp. 2,836,000.00 = Rp. 3,403,200.00
Rp. 3,403,200.00
Jumlah Upah + Bahan = Rp. 3,474,380.00

0.100 Untuk 1 M2 @ Rp. 3,474,380.00 = Rp. 347,438.00


Over Head 10 % = Rp. 34,743.80
Total = Rp. 382,181.80

2 An. K23 + K18 10 M2 Pengecatan Dengan Aquaprof


Upah :
0.750 Tukang Cat @ Rp. 56,100.00 = Rp. 42,075.00
0.075 Kepala Tukang @ Rp. 48,500.00 = Rp. 3,637.50
0.500 Pekerja @ Rp. 73,900.00 = Rp. 36,950.00
0.025 Mandor @ Rp. 0.00 = Rp. -
Rp. 82,662.50

Bahan :
1.200 Kg Aquaprof @ Rp. 52,000.00 = Rp. 62,400.00
Rp. 62,400.00
Jumlah Upah + Bahan = Rp. 145,062.50
0.100 Untuk 1 M2 @ Rp. 145,062.50 = Rp. 14,506.25
Over Head 10 % = Rp. 1,450.63
Total = Rp. 15,956.88
RENCANA ANGGARAN BIAYA
( RAB )

PEKERJAAN : PEMBANGUNAN SARANA DAN PRASARANA AIR BAKU DESA URENG


LOKASI : DESA URENG, PULAU AMBON
TAHUN ANGGARAN : 2010

No. Uraian Pekerjaan Satuan Volume Harga Satuan (Rp). Jumlah Harga (Rp.)

1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pembuatan Jalan Masuk Ls 1.00 5,000,000.00 5,000,000.00
2 Fasilitas Direksi Ls 1.00 5,000,000.00 5,000,000.00
3 Mobilisasi Ls 1.00 10,000,000.00 10,000,000.00
4 Adminitrasi, Dokumentasi Ls 1.00 1,500,000.00 1,500,000.00
5 Surfei Detail & Pengukuran Ls 1.00 6,500,000.00 6,500,000.00
6 Papan Proyek Ls 1.00 500,000.00 500,000.00
7 Pembersihan (awal & akhir) Ls 1.00 1,500,000.00 1,500,000.00

JUMLAH I 30,000,000.00
II PENGADAAN PIPA GIP MED. A DAN ACCSSORIES
1 Pipa Med. A dia 3" M' 100.00 180,000.00 18,000,000.00
2 Pipa Med. A dia 2" M' 1,000.00 44,500.00 44,500,000.00
3 Pipa Med. A dia 1,5" M' 100.00 44,500.00 4,450,000.00
4 Pipa Med. A dia 1" M' 50.00 43,500.00 2,175,000.00
5 Sock GIP dia 3" Bh 34.00 1,147,500.00 39,015,000.00
6 Sock GIP dia 2" Bh 334.00 528,000.00 176,352,000.00
7 Sock GIP dia 1,5" Bh 33.33 1,215,000.00 40,500,000.00
8 Sock GIP dia 1" Bh 16.67 2,700,000.00 45,000,000.00
9 Reduser Gip.dia. 3" x 2 " Bh 1.00 69,000.00 69,000.00
10 Reduser Gip.dia. 2" x 1,5 " Bh 1.00 473,500.00 473,500.00
11 Tee Gip. Dia 3" x 3/4 x 3" Bh 1.00 #REF! #REF!
12 Tee Gip. Dia 2" x 3/4 x 2" Bh 1.00 #REF! #REF!
13 Tee Gip. Dia 1,5" x 3/4 x 1,5" Bh 2.00 #REF! #REF!
14 Air Valve Gip. Dia 3/4" Bh 1.00 #REF! #REF!
15 Tee Gip. 1" Bh 4.00 #REF! #REF!
16 Stop Kran KITSZ dia.3" Bh 5.00 446,000.00 2,230,000.00
17 Stop Kran KITSZ dia.1,5" Bh 1.00 473,500.00 473,500.00
18 Stop Kran KITSZ dia.1" Bh 4.00 446,000.00 1,784,000.00
19 Water Mur Gip. 3" Bh 12.00 #REF! #REF!
20 Cat Menie Kg 50.00 2,836,000.00 141,800,000.00
21 Plester Pipa Dos 20.00 #REF! #REF!
22 Bend Gip. 22.5 dia 3" Bh 2.00 35,000.00 70,000.00
23 Bend Gip. 22.5 dia 2" Dos 5.00 452,500.00 2,262,500.00
24 Bend Gip. 22.5 dia 1,5" Bh 2.00 452,500.00 905,000.00
25 Double drat Gip. 3" Bh 5.00 #REF! #REF!
26 Double drat Gip. 2" Bh 4.00 #REF! #REF!
27 Double drat Gip. 1,5" Bh 1.00 #REF! #REF!
28 Double drat Gip. 1" Bh 1.00 #REF! #REF!
29 Water mur Gip. Dia 3" Bh 1.00 #REF! #REF!
30 Water mur Gip. Dia 2" Bh 1.00 #REF! #REF!
31 Water mur Gip. Dia 1,5" Bh 1.00 #REF! #REF!
32 Water mur Gip. Dia 1" Bh 1.00 #REF! #REF!
JUMLAH II #REF!
III PEMASANGAN PIPA DAN ACCESSORIES
1 Galian Tanah untuk Pipa Distribusi M3 84.29 11,787.71 993,586.08
2 Urugan Kembali M3 62.73 #REF! #REF!
3 Pemasangan pipa Med. A dia 3" M' 100.00 56,474.00 5,647,400.00
4 PemasanganPipa Med. A dia 2" M' 1,000.00 92,659.82 92,659,820.00
5 Pemasangan Pipa Med. A dia 1,5" M' 100.00 92,659.82 9,265,982.00
6 Pemasangan Pipa Med. A dia 1" M' 50.00 92,659.82 4,632,991.00
7 Pemasangan Pengaman Stop Kran Bh 13.00 #VALUE! #VALUE!
8 Pemasangan Accessories Ls 1.00 2,500,000.00 2,500,000.00
JUMLAH III #REF!
IV PEMBUATAN SUMUR DANGKAL (3 X 3 X 6)

1 Galian Tanah M3 108.62 11,787.71 1,280,381.06


2 Urugan Kembali M3 17.12 #REF! #REF!
3 Pasangan Batu 1 : 5 M3 46.63 9,515,482.35 443,706,941.98
4 Plestran 1 : 4 M2 203.50 7,831,527.00 1,593,715,744.50
5 Timbunan Tanah Setebal 10 cm M3 1.20 82,817.90 99,381.48
6 Lantai beton, ad 1 : 3 : 5 tebal 6 cm M3 0.80 #REF! #REF!
JUMLAH IV #REF!
No. Uraian Pekerjaan Satuan Volume Harga Satuan (Rp). Jumlah Harga (Rp.)

1 2 3 4 5 6
V RUMAH POMPA (4 X 5) m'
1 Galian Tanah M3 7.23 11,787.71 85,225.14
2 Urugan Kembali M3 1.40 #REF! #REF!
3 Timbunan Tanah M3 3.70 82,817.90 306,426.23
4 Timbunan Pasir M3 0.86 #REF! #REF!
5 Pasangan Pondasi Bt Karang ad. 1 : 5 M3 4.16 9,515,482.35 39,584,406.58
6 Plesteran 1 : 4 M2 36.00 7,831,527.00 281,934,972.00
7 Acian Dinding ad. 1 : 5 M2 36.00 #REF! #REF!
8 Pasangan Dinding Batu Belah ad. 1 : 5 M3 4.21 9,515,482.35 40,060,180.69
9 Kolom (145 Kg) ad. 1 : 2 : 3 M3 0.38 219,018.35 83,226.97
10 Slof Beton (145 Kg) ad. 1 : 2 :3 M3 0.33 219,018.35 72,276.06
11 Ring Balok (145 Kg) ad. 1 : 2 : 3 M3 0.33 219,018.35 72,276.06
12 Lantai beton, ad 1 : 3 : 5 tebal 10 cm M3 1.70 #REF! #REF!
13 Kuda-Kuda Kayu Kls I M3 1.64 44,616.00 73,170.24
14 Gording Kayu Kls I M3 0.52 1,592,140.00 827,912.80
15 Mengerjakan kosen Pintu/jendela/jelusi/ventilasi Kayu Kls I M3 2.56 36,487.00 93,406.72
16 Lisplank M3 34.00 22,067.65 750,300.10
17 Mengerjakan Pintu Panel/jendela panel M3 6.10 36,487.00 222,570.70
18 Atap Zink Bjls 30 M2 62.50 6,184,785.42 386,549,088.75
20 Atap Bumbungan zink plat Bjls 30 M' 17.00 813,253.54 13,825,310.18
21 Cat Dinding M2 46.50 382,181.80 17,771,453.70
22 Cat Kayu M2 96.31 382,181.80 36,807,929.16
23 Cat Meine Zink M2 62.50 382,181.80 23,886,362.50
24 Kunci Taman Merk Sels Bh 1.00 22,000.00 22,000.00
25 Engsel Jendela Bh 2.00 37,500.00 75,000.00
26 Grendel Besar Bh 2.00 36,500.00 73,000.00
27 Kait Angin Kecil Bh 4.00 5,000.00 20,000.00
28 Kait Angin Besar Bh 2.00 105,000.00 210,000.00
29 Sekrup 1 " Dos 2.00 176,500.00 353,000.00
30 Pintu Besi Ukuran 2 x 1,4 M M' 15.00 19,500.00 292,500.00
32 Terari Jendela Ukuran (1,2 x 1)M, Besi dia. 12 mm Bh 20.00 19,500.00 390,000.00
33 Gembok besar Globe RRT Bh 1.00 #REF! #REF!
A Pekerjaan Pondasi Mesin dan Pompa -
34 Galian Tanah M3 1.18 11,787.71 13,909.50
35 Urugan Bekas Galian M3 0.38 #REF! #REF!
36 Beton Truktur Tanpa Tulangan ad. 1 : 2 : 3 M3 0.98 2,217.00 2,172.66
B Rabat Betton -
37 Galian Tanah M3 10.52 11,787.71 124,006.71
38 Urugan Bekas Galian M3 4.30 #REF! #REF!
39 Pasangan Batu Karang ad. 1 : 5 M3 1.37 9,515,482.35 13,036,210.82
40 Timbunan Tanah M3 2.24 82,817.90 185,512.10
41 Beton Tumbuk ad. 1 : 3 : 5 tebal 10 cm M3 2.40 #REF! #REF!

JUMLAH V #REF!
VI PENGADAAN DAN PEMASANGAN POMPA DAN ACCESSORIES
1 Motor penggerak + pompa (komplet) Unit 1.00 20,000,000.00 20,000,000.00
Motor = Yanmar (diesel) atau Kubota
Pompa = Centrifugal Q = 10 ltr/dt
Head = 80 meter
2 Pipa Gip. Med. A dia 2" M' 16.00 92,659.82 1,482,557.12
3 Stop Kran KITZ dia 2" Bh 2.00 4,250.00 8,500.00
4 Bend Gip. Dia 2" Bh 8.00 #VALUE! #VALUE!
5 Saringan Gip.+ Klep dia 2" Ls 1.00 140,500.00 140,500.00
6 Sock Gip. 2" Bh 4.00 24,000.00 96,000.00
7 Water Mur dia 2" Bh 3.00 #REF! #REF!
8 Double Dreat Gip.dia 2" Bh 3.00 #REF! #REF!
9 Reduser Gip. Dia 3 x 2" Bh 3.00 69,000.00 207,000.00
10 Clamp Sadle Gip. /Tee Reduser dia. 3 x 3/4" Bh 1.00 #REF! #REF!
11 Air Valve dia.3/4 Bh 1.00 #REF! #REF!
12 Water Hammer dia 2" Bh 1.00 235,000.00 235,000.00
13 Water Mur dia 3" Bh 1.00 #REF! #REF!
14 Double Dreat Gip.dia 3" Bh 1.00 #REF! #REF!
15 Pemasangan Motor Penggerak + Pompa Ls 1.00 2,000,000.00 2,000,000.00
16 Pengadaan Tangki air Pendingin dan Accessories Ls 1.00 1,000,000.00 1,000,000.00
17 Pengetesan dan Pengujian Pompa Selama 3 Bln Ls 1.00 3,000,000.00 3,000,000.00
18 Pengadaan Kunci Pipa 3" + Snei Pipa dia 3" + Ragon Pipa + Ls 1.00 1,500,000.00 1,500,000.00
19 Gergaji Besi + Kunci Inggris Bh 5.00 15,000.00 75,000.00
JUMLAH VI #VALUE!
No. Uraian Pekerjaan Satuan Volume Harga Satuan (Rp). Jumlah Harga (Rp.)

1 2 3 4 5 6
VII REHAB. RESERVOAR
1 Galian Tanah M3 15.28 11,787.71 180,116.21
2 Urugan Bekas Galian M3 2.92 #REF! #REF!
3 urugan Pasir M3 1.86 #REF! #REF!
4 Ring Balok Beton 17/20 cm ad. 1 : 2 : 3 M3 1.10 219,018.35 240,920.19
5 Sloof Beton 17/20 cm ad. 1 : 2 : 3 M3 1.26 219,018.35 275,963.12
6 Kolom Beton 25/25 cm ad. 1 : 2 : 3 M3 1.40 219,018.35 306,625.69
7 Dinding Beton ad. 1 : 2 : 3 M3 6.76 219,018.35 1,480,564.05
8 Plat Penutup ad 1 : 2 : 3 M3 2.24 219,018.35 490,601.10
9 Plat Lantai ad. 1 : 2 : 3 M3 2.10 219,018.35 459,938.54
10 Pasangan Batu ad. 1 : 5 M3 6.82 9,515,482.35 64,895,589.63
11 Timbrisan Batu Kosong M3 1.78 166,930.50 297,136.29
12 Rabat Keliling ad 1 : 3 : 5 M3 0.38 #REF! #REF!
13 Lantai Kerja ad 1 : 3 : 5 M3 0.82 #REF! #REF!
14 Plesteran Lantai ad 1 : 3 M2 18.00 7,831,527.00 140,967,486.00
15 Plesteran Dinding ad 1 : 3 (untuk dinding) M2 35.00 7,831,527.00 274,103,445.00
16 Plesteran Dinding ad 1 : 3 (untuk plat atap) M2 15.00 7,831,527.00 117,472,905.00
17 Acian M2 64.20 #REF! #REF!
18 Cat Dengan Aquaproof M2 32.00 15,956.88 510,620.00
19 Pengadaan/pemasangan Pipa Gip. Med A dia. 3" M' 4.30 170,000.00 731,000.00
(penguras)
20 Pengadaan/pemasangan Pipa Gip. Med A dia. 2" M' 4.50 100,000.00 450,000.00
(over flouw dan outlet)
21 Pengadaan/pemasangan Pipa Gip. Med A dia. 2" M' 4.50 100,000.00 450,000.00
(Inlet)
22 Stop Kran KITZ dia 3" Bh 1.00 #REF! #REF!
23 Stop Kran KITZ dia 2" Bh 1.00 #REF! #REF!
24 Stop Kran KITZ dia 1,5" Bh 1.00 #REF! #REF!
25 Bend Gip. Dia 2" Bh 1.00 #REF! #REF!
26 Bend Gip. Dia 1,5" Bh 4.00 #REF! #REF!
27 Tee Gip. Dia 2" x 2" x 2" Bh 2.00 #REF! #REF!
28 Saringan Pipa Penguras dia 3" Bh 1.00 #REF! #REF!
29 Tangga Pipa Gip. Dia. 1" dan dia. 3" Bh 1.00 #REF! #REF!
30 Pipa Udara Gip. Dia 2" Ls 1.00 100,000.00 100,000.00
31 Menhole Plat Baja tebal 5 mm Ls 1.00 800,000.00 800,000.00
32 Besi Siku 40 x 40 x 4 mm Ls 1.00 1,000,000.00 1,000,000.00
JUMLAH VII #REF!
VIII KRAN UMUM
28 Galian Tanah M3 1.42 11,787.71 16,738.55
29 Urugan Bekas Galian M3 0.18 #REF! #REF!
30 urugan Pasir M3 0.32 #REF! #REF!
30 Pasangan Batu ad. 1 : 5 M3 0.38 9,515,482.35 3,615,883.29
30 Rabat Keliling ad 1 : 3 : 5 M3 0.38 #REF! #REF!
30 Beton Struktur Tanpa Tulangan 1 : 3 : 5 M3 0.06 #REF! #REF!
30 Plesteran ad 1 : 4 M2 5.48 7,831,527.00 42,916,767.96
30 Pipa Gip. Med. A dia 3/4" M' 2.00 153,900.00 307,800.00
30 Knee Gip dia 3/4" Bh 1.00 202,500.00 202,500.00
30 Tee Gip dia 3/4" Bh 1.00 #REF! #REF!
30 Reduser Gip. Dia 3/4" Bh 1.00 #REF! #REF!
30 Water Mur Gip. Dia 1" x 3/4" Bh 1.00 #REF! #REF!
30 Kran Handle Gip. Dia 3/4 Bh 2.00 #REF! #REF!
JUMLAH VIII #REF!
JUMLAH VIII Untuk Kran Umum Bh 10 #REF! #REF!

JUMLAH KESELURUHAN I s/d VIII #REF!


PPN 10 % #REF!
TOTAL #REF!
DIBULATKAN #REF!

TERBILANG : DELAPAN RATUS JUTA RUPIAH

Ambon, Agustus 2010


KEPALA BIDANG PSDA
DINAS PEKERJAAN UMUM PROV. MALUKU
Ketua

Ir. M.E.E. SAMSON, M.Tech.


NIP. 19630826 199203 2 001
REKAPITULASI
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN SARANA DAN PRASARANA AIR BAKU DESA URENG
LOKASI : DESA URENG, PULAU AMBON
TAHUN : 2010

Jumlah
No. Uraian Pekerjaan Harga
(Rp.)
1 2 3
I PEKERJAAN PERSIAPAN ### 30,000,000.00
II PENGADAAN PIPA GIP MED. A DAN ACCSSORIES #REF!
III PEMASANGAN PIPA DAN ACCESSORIES #REF!
IV PEMBUATAN SUMUR DANGKAL (3 X 3 X 6) #REF!
V RUMAH POMPA (4 X 5) m' #REF!
VI PENGADAAN DAN PEMASANGAN POMPA DAN ACCESSORIES #VALUE!
VII REHAB. RESERVOAR #REF!
VIII KRAN UMUM 10 BUAH #REF!

Jumlah : #REF!
PPN 10 % : #REF!
Total : #REF!
Dibulatkan : #REF!

Terbilang : DELAPAN RATUS JUTA RUPIAH

Ambon, Agustus 2010


KEPALA BIDANG PSDA
DINAS PEKERJAAN UMUM PROV. MALUKU
Ketua

Ir. M.E.E. SAMSON, M.Tech.


NIP. 19630826 199203 2 001

Anda mungkin juga menyukai