SATUAN KERJA NVT : IRIGASI MALUKU TENGGARA & PULAU-PULAU KECIL MALUKU
SATUAN KEGIATAN : IRIGASI MALUKU TENGGARA BARAT
PEKERJAAN : REHABILITASI EMBUNG & JARINGAN AIR BAKU
LOKASI : DESA KROING & YALTUBUNG (PULAU BABAR)
THN ANGGARAN : 2006
1. SEMEN :
2. BATU KALI :
4. PASIR URUG :
5. BATU KERIKIL :
HARGA UPAH
1 Kepala Tukang Org/Hr Rp. 57,000.00
2 Mandor Org/Hr Rp. 67,000.00
3 Pekerja Org/Hr Rp. 40,000.00
4 Tukang Batu, Kayu, Besi, Cat & Pipa Org/Hr Rp. 45,000.00
HARGA BAHAN
1 Batu Kali/ Karang /M3 Rp. 175,000.00
2 Batu Kerikil /M3 Rp. 180,500.00
3 Pasir Urug /M3 Rp. 113,400.00
4 Pasir Pasang /M3 Rp. 164,750.00
5 Buah Batu Bata 5 x 11 x 22 /Buah Rp. 3,500.00
6 Besi Beton Polos /Kg Rp. 8,400.00
7 Kawat Beton/ Bendrat /Kg Rp. 15,500.00
8 Kayu Klas I /M3 Rp. 2,250,000.00
9 Kayu Klas II /M3 Rp. 1,350,000.00
10 Paku Campuran /Kg Rp. 30,000.00
11 Paku Seng /Kg Rp. 29,000.00
12 Semen PC (50 kg) /Zak Rp. 80,000.00
13 Seng Gelombang BJLS 0.02 mm /M2 Rp. 67,500.00
14 Seng Plat Datar BJLS 0.02 mm /M2 Rp. 73,000.00
15 Cat Meni /Kg Rp. 50,000.00
15 Cat Aquaprof /Kg Rp. 122,000.00
15 Tanah Urug /M3 Rp. 75,000.00
17 Ijuk /Kg Rp. 70,000.00
18 Kapur Ayak /Kg Rp. 32,500.00
19 Arang /M2 Rp. 50,000.00
20 Tangga Pipa GIP 25 mm Ls Rp. 285,000.00
21 Air untuk Pengecoran Beton / m3 Rp. 100,000.00
22 Tang/ Alat Pemotong/Alat Bantu /Bh Rp. 45,000.00
23 Palu/ Hammer /Bh Rp. 65,000.00
23 Kunci Taman Merk Royal Bh Rp. 66,250.00
23 Engsel Jendela Bh Rp. 63,000.00
23 Grendel Besar Bh Rp. 32,500.00
23 Kait Angin Kecil Bh Rp. 32,500.00
23 Kait Angin Besar Bh Rp. 32,000.00
23 Sekrup 1 " Dos Rp. 50,000.00
23 Pintu Besi Ukuran 2 x 1,4 M M' Rp. 175,000.00
23 Terari Jendela Ukuran (1,2 x 1)M, Besi dia. 12 mm Bh Rp. 41,000.00
23 Gembok besar Globe RRT Bh Rp. 75,000.00
PIPA DAN ACCESSORIES PIPA
1 Pipa HDPE dia. 100 mm (4") /M' Rp. 122,000.00
2 Pipa HDPE dia. 75 mm (3") /M' Rp. 90,000.00
3 Pipa HDPE dia. 50 mm (2") /M' Rp. 43,000.00
4 Pipa HDPE dia. 37,50 mm (1.5") /M' Rp. 26,000.00
5 Pipa PVC AW dia. 50 mm (2") /M' Rp. 21,000.00
6 Pipa GIP dia. 75 mm (3") /M' Rp. 135,000.00
7 Pipa GIP dia. 37.5 mm (1.5") /M' Rp. 36,900.00
8 Sambungan Flange dia.50 mm (2") /Bh Rp. 185,000.00
9 Sambungan Flange dia.37.5 mm (1.5") /Bh Rp. 165,000.00
10 Gate Valve Flange dia. 100 mm /Bh Rp. 575,000.00
11 Gate Valve Flange dia. 75 mm /Bh Rp. 470,000.00
12 Knie PVC dia. 12,5 mm /Bh Rp. 33,000.00
13 Kran Air 1/2" /Bh Rp. 37,500.00
14 Bend GIP dia. 100 mm 90 Derajat /Bh Rp. 135,000.00
15 Bend GIP dia. 75 mm 90 Derajat /Bh Rp. 115,000.00
16 Main Hole Pipa Plat Baja 0,05 mm /M2 Rp. 446,000.00
17 Reduser 2" x 1,5" /Bh Rp. 280,000.00
18 Stop Kran 20 mm (3/4") /Bh Rp. 225,000.00
19 Stop Kran 50 mm (2") /Bh Rp. 280,000.00
20 Pipa PVC 20 mm (3/4") /M' Rp. 41,500.00
21 Sock GIP 75 mm (3") /M' Rp. 63,000.00
22 Sock GIP 50 mm (2") /Bh Rp. 52,000.00
23 Sock GIP 37 mm (1.5") /Bh Rp. 36,000.00
24 Sock GIP 25 mm (1") /Bh Rp. 35,000.00
25 Sock PVC 20 mm (3/4") /Bh Rp. 34,500.00
26 Bend GIP 50 mm(2") /Bh Rp. 38,000.00
27 Clam Saddle 2" x 3/4" /Bh Rp. 44,000.00
28 Sock PVC 3/4" /Bh Rp. 35,500.00
29 Tee PVC 3/4" /Bh Rp. 40,100.00
30 Bend PVC 3/4" /Bh Rp. 39,100.00
31 Seltip /Rol Rp. 37,400.00
32 Lem Pipa /Kg Rp. 40,000.00
33 Pipa Udara GIP dia. 50 mm / Bh Rp. 90,000.00
34 Tee Gip. Dia 3" x 3/4 x 3" / Bh Rp. 105,000.00
35 Tee Gip. Dia 2" x 3/4 x 2" / Bh Rp. 63,000.00
36 Tee Gip. Dia 1,5" x 3/4 x 1,5" / Bh Rp. 38,750.00
37 Air Valve Gip. Dia 3/4" / Bh Rp. 575,000.00
38 Tee Gip. 1" / Bh Rp. 38,000.00
39 Double drat Gip. 3" / Bh Rp. 63,500.00
40 Double drat Gip. 2" / Bh Rp. 52,500.00
41 Double drat Gip. 1,5" / Bh Rp. 40,000.00
42 Double drat Gip. 1" / Bh Rp. 36,500.00
43 Water mur Gip. Dia 3" / Bh Rp. 105,000.00
44 Water mur Gip. Dia 2" / Bh Rp. 74,500.00
45 Water mur Gip. Dia 1,5" / Bh Rp. 70,000.00
46 Water mur Gip. Dia 1" / Bh Rp. 63,500.00
47 Stop Kran KITZ dia 3" / Bh Rp. 321,000.00
48 Stop Kran KITZ dia 2" / Bh Rp. 172,000.00
49 Stop Kran KITZ dia 1,5" / Bh Rp. 105,000.00
50 Bend Gip. Dia 2" / Bh Rp. 101,000.00
51 Bend Gip. Dia 1,5" / Bh Rp. 92,300.00
52 Tee Gip. Dia 2" x 2" x 2" / Bh Rp. 102,000.00
53 Saringan Pipa Penguras dia 3" / Bh Rp. 225,000.00
54 Tangga Pipa Gip. Dia. 1" dan dia. 3" / Bh Rp. 375,000.00
Tee Gip dia 3/4" / Bh Rp. 37,000.00
Reduser Gip. Dia 3/4" / Bh Rp. 36,970.00
Water Mur Gip. Dia 1" x 3/4" / Bh Rp. 53,300.00
Kran Handle Gip. Dia 3/4 / Bh Rp. 53,300.00
ANALISA HARGA SATUAN DAN BAHAN
Standar Nasional Indonesia
I. PEKERJAAN PERSIAPAN
1 1 M2 Membersihkan Lapangan
Upah
0.100 Pekerja @ Rp. 40,000.00 = Rp. 4,000.00
0.005 Mandor @ Rp. 67,000.00 = Rp. 4,000.00
Jumlah Upah = Rp. 8,000.00
Keuntungan 10% = Rp. 800.00
Jumlah = Rp. 8,800.00
Bahan :
1.200 M3 Tanah Urug @ Rp. 75,000.00 = Rp. 90,000.00
Jumlah Bahan = Rp. 90,000.00
Jumlah Upah + Bahan = Rp. 101,675.00
Keuntungan 10% = Rp. 10,167.50
Jumlah = Rp. 111,842.50
3 An. SK SNI T 01 1991 03 TABEL 1.5. 1M3.Pasangan Batu Kali (ad. 1:4)
Upah :
0.600 Tukang Batu @ Rp. 45,000.00 = Rp. 27,000.00
0.060 Kepala Tukang @ Rp. 57,000.00 = Rp. 3,420.00
1.500 Pekerja @ Rp. 40,000.00 = Rp. 60,000.00
0.075 Mandor @ Rp. 67,000.00 = Rp. 5,025.00
Jumlah Upah = Rp. 95,445.00
Bahan :
1.200 M3 Batu Kali @ Rp. 175,000.00 = Rp. 210,000.00
3.260 Zak Semen (PC) @ Rp. 80,000.00 = Rp. 260,800.00
0.520 M3 Pasir Pasang @ Rp. 164,750.00 = Rp. 85,670.00
Jumlah Bahan = Rp. 556,470.00
Jumlah Upah + Bahan = Rp. 651,915.00
Keuntungan 10% = Rp. 65,191.50
Jumlah = Rp. 717,106.50
4 An. SK SNI T 01 1991 03 TABEL 1.5. 1M3.Pasangan Batu Kali (ad. 1:3)
Upah :
0.600 Tukang Batu @ Rp. 45,000.00 = Rp. 27,000.00
0.060 Kepala Tukang @ Rp. 57,000.00 = Rp. 3,420.00
1.500 Pekerja @ Rp. 40,000.00 = Rp. 60,000.00
0.075 Mandor @ Rp. 67,000.00 = Rp. 5,025.00
Jumlah Upah = Rp. 95,445.00
Bahan :
1.200 M3 Batu Kali @ Rp. 175,000.00 = Rp. 210,000.00
4.040 Zak Semen (PC) @ Rp. 80,000.00 = Rp. 323,200.00
0.485 M3 Pasir Pasang @ Rp. 164,750.00 = Rp. 79,903.75
Jumlah Bahan = Rp. 613,103.75
Jumlah Upah + Bahan = Rp. 708,548.75
Keuntungan 10% = Rp. 70,854.88
Jumlah = Rp. 779,403.63
5 An. SK SNI T 01 1991 03 TABEL 1.5. 1M3.Pasangan Batu Bata Tebal 1/2 Batu (ad. 1:5)
Upah :
0.100 Tukang Batu @ Rp. 45,000.00 = Rp. 4,500.00
0.010 Kepala Tukang @ Rp. 57,000.00 = Rp. 570.00
0.320 Pekerja @ Rp. 40,000.00 = Rp. 12,800.00
0.015 Mandor @ Rp. 67,000.00 = Rp. 1,005.00
Jumlah Upah = Rp. 18,875.00
Bahan :
70.000 Buah Batu Bata 5 x 11 x 22 @ Rp. 3,500.00 = Rp. 245,000.00
0.192 Zak Semen (PC) @ Rp. 80,000.00 = Rp. 15,360.00
0.045 M3 Pasir Pasang @ Rp. 164,750.00 = Rp. 7,413.75
Jumlah Bahan = Rp. 267,773.75
Jumlah Upah + Bahan = Rp. 286,648.75
Keuntungan 10% = Rp. 28,664.88
Jumlah = Rp. 315,313.63
6 An. SK SNI T 01 1991 03 TABEL 1.5. 1M3.Pasangan Batu Tebal 1/2 Batu (ad. 1:3)
Upah :
0.100 Tukang Batu @ Rp. 45,000.00 = Rp. 4,500.00
0.010 Kepala Tukang @ Rp. 57,000.00 = Rp. 570.00
0.320 Pekerja @ Rp. 40,000.00 = Rp. 12,800.00
0.015 Mandor @ Rp. 67,000.00 = Rp. 1,005.00
Jumlah Upah = Rp. 18,875.00
Bahan :
70.000 Buah Batu Bata 5 x 11 x 22 @ Rp. 3,500.00 = Rp. 245,000.00
0.287 Zak Semen (PC) @ Rp. 80,000.00 = Rp. 22,960.00
0.004 M3 Pasir Pasang @ Rp. 164,750.00 = Rp. 659.00
Jumlah Bahan = Rp. 268,619.00
Jumlah Upah + Bahan = Rp. 287,494.00
Keuntungan 10% = Rp. 28,749.40
Jumlah = Rp. 316,243.40
7 An. G441. 1M3 Beton Tumbuk (ad. 1 : 3 : 5)
Upah :
0.250 Tukang Batu @ Rp. 45,000.00 = Rp. 11,250.00
0.025 Kepala Tukang @ Rp. 57,000.00 = Rp. 1,425.00
1.650 Pekerja @ Rp. 40,000.00 = Rp. 66,000.00
0.080 Mandor @ Rp. 67,000.00 = Rp. 5,360.00
Jumlah Upah = Rp. 84,035.00
Bahan :
4.360 Zak Semen (PC) @ Rp. 80,000.00 = Rp. 348,800.00
0.870 M3 Kerikil @ Rp. 180,500.00 = Rp. 157,035.00
0.520 M3 Pasir Pasang @ Rp. 164,750.00 = Rp. 85,670.00
Jumlah Bahan = Rp. 591,505.00
Jumlah Upah + Bahan = Rp. 675,540.00
Keuntungan 10% = Rp. 67,554.00
Jumlah = Rp. 743,094.00
Bahan :
0.016 Zak Semen (PC) @ Rp. 80,000.00 = Rp. 1,280.00
0.050 Kg Kapur Ayak @ Rp. 32,500.00 = Rp. 1,625.00
Jumlah Bahan = Rp. 2,905.00
Jumlah Upah + Bahan = Rp. 6,814.00
Keuntungan 10% = Rp. 681.40
Jumlah = Rp. 7,495.40
12 An. Supl. V. 1M3.Beton Bertulang (ad. 1:2:3)
A. Cor Beton ad. 1:2:3
Upah :
1.000 Tukang Batu @ Rp. 45,000.00 = Rp. 45,000.00
0.100 Kepala Tukang @ Rp. 57,000.00 = Rp. 5,700.00
6.000 Pekerja @ Rp. 40,000.00 = Rp. 240,000.00
0.300 Mandor @ Rp. - = Rp. -
Jumlah Upah = Rp. 290,700.00
Bahan :
0.540 M3 Pasir Pasang @ Rp. 164,750.00 = Rp. 88,965.00
6.816 Zak Semen (PC) @ Rp. 80,000.00 = Rp. 545,280.00
0.820 M3 Kerikil @ Rp. 180,500.00 = Rp. 148,010.00
1.000 M3 Air untuk Pengecoran Beton @ Rp. 100,000.00 = Rp. 100,000.00
Jumlah Bahan = Rp. 882,255.00
Jumlah Upah + Jumlah Bahan = Rp. 1,172,955.00
Bahan :
110.000 Kg. Besi Beton @ Rp. 8,400.00 = Rp. 924,000.00
2.000 Kg Kawat Ikat @ Rp. 15,500.00 = Rp. 31,000.00
Jumlah Bahan = Rp. 955,000.00
Jumlah Upah + Jumlah Bahan = Rp. 1,657,000.00
Bahan :
0.016 Zak Semen (PC) @ Rp. 80,000.00 = Rp. 1,280.00
0.050 Kg Kapur Ayak @ Rp. 32,500.00 = Rp. 1,625.00
Jumlah Bahan = Rp. 2,905.00
Jumlah Upah + Bahan = Rp. 6,814.00
Keuntungan 10% = Rp. 681.40
Jumlah = Rp. 7,495.40
IV. PEKERJAAN PEMASANGAN PIPA DAN ACCESSORIES PIPA
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 33,055.00
Keuntungan 10% = Rp. 3,305.50
Jumlah = Rp. 36,360.50
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 33,055.00
Keuntungan 10% = Rp. 3,305.50
Jumlah = Rp. 36,360.50
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 33,055.00
Keuntungan 10% = Rp. 3,305.50
Jumlah = Rp. 36,360.50
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 24,282.00
Keuntungan 10% = Rp. 2,428.20
Jumlah = Rp. 26,710.20
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 33,055.00
Keuntungan 10% = Rp. 3,305.50
Jumlah = Rp. 36,360.50
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 33,055.00
Keuntungan 10% = Rp. 3,305.50
Jumlah = Rp. 36,360.50
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 45,350.00
Keuntungan 10% = Rp. 4,535.00
Jumlah = Rp. 49,885.00
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 45,350.00
Keuntungan 10% = Rp. 4,535.00
Jumlah = Rp. 49,885.00
Bahan :
120.000 Batu Bata @ Rp. 3,500.00 = Rp. 420,000.00
0.880 Semen @ Rp. 80,000.00 = Rp. 70,400.00
0.070 Pasir Pasang @ Rp. 164,750.00 = Rp. 11,532.50
0.070 Kerikil @ Rp. 180,500.00 = Rp. 12,635.00
Jumlah Bahan = Rp. 514,567.50
Jumlah Upah + Bahan = Rp. 689,400.00
Keuntungan 10% = Rp. 68,940.00
Jumlah = Rp. 758,340.00
11 An. Pemasangan 1 Bh Gate Valve Flange dia 100 mm
Upah :
0.500 Pekerja @ Rp. 40,000.00 = Rp. 20,000.00
0.050 Kepala Tukang @ Rp. 57,000.00 = Rp. 2,850.00
0.150 Tukang @ Rp. 45,000.00 = Rp. 6,750.00
Jumlah Upah = Rp. 29,600.00
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 45,350.00
Keuntungan 10% = Rp. 4,535.00
Jumlah = Rp. 49,885.00
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 45,350.00
Keuntungan 10% = Rp. 4,535.00
Jumlah = Rp. 49,885.00
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 36,210.00
Keuntungan 10% = Rp. 3,621.00
Jumlah = Rp. 39,831.00
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 36,210.00
Keuntungan 10% = Rp. 3,621.00
Jumlah = Rp. 39,831.00
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 33,920.00
Keuntungan 10% = Rp. 3,392.00
Jumlah = Rp. 37,312.00
16 An. Pemasangan 1 Bh Knie dia 12.5 mm
Upah :
0.200 Pekerja @ Rp. 40,000.00 = Rp. 8,000.00
0.060 Kepala Tukang @ Rp. 57,000.00 = Rp. 3,420.00
0.150 Tukang @ Rp. 45,000.00 = Rp. 6,750.00
Jumlah Upah = Rp. 18,170.00
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 33,920.00
Keuntungan 10% = Rp. 3,392.00
Jumlah = Rp. 37,312.00
Bahan :
0.350 Alat Bantu @ Rp. 45,000.00 = Rp. 15,750.00
Jumlah Bahan = Rp. 15,750.00
Jumlah Upah + Bahan = Rp. 22,653.90
Keuntungan 10% = Rp. 2,265.39
Jumlah = Rp. 24,919.29
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
5.00
5.00
PERHITUNGAN VOLUME
Luas = P x L x T
= 14.00 x 0.50 x 0.50
Volume = 3.50
0 0.5
0 0.5
- 0 1
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
5.00
5.00
PERHITUNGAN VOLUME
A. Plesteran Dinding
Pajang = 14.00 M'
Tinggi = 2.00 M'
Luas = Pajang X Tinggi =
= 14.00 X 2.00 = 28.00 M2
B. Plesteran Lantai
Pajang = 4.00 M'
Lebar = 3.00 M'
Luas = Pajang X Lebar =
= 4.00 X 3.00 = 12.00 M2
SKETSA / GAMBAR
PERHITUNGAN VOLUME
Luas = T X L
= 0.10 X 0.50 = 0.05 M2
Volume = Luas X P =
= 0.05 X 18.00 = 0.90 M3
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
5.00
5.00
PERHITUNGAN VOLUME
Luas = T X L
= 1.00 X 0.50 = 0.50 M2
Volume = Luas X P =
= 0.50 X 14.00 = 7.00 M3
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
5.00
5.00
PERHITUNGAN VOLUME
Luas = T X L M2
= 0.50 X 3.00 = 1.50 M2
Volume = Luas X P =
= 1.50 X 4.00 = 6.00 M3
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
Pekerjaan KABUPATEN MALUKU TENGGARA
Lokasi DESA AD KEI BESAR KAB. MALRA
T. A. : 2010
Item : Hidran Umum
Sub. Item : Galian Tanah
SKETSA / GAMBAR
PERHITUNGAN VOLUME
Luas = T X L
= 0.30 X 0.20 = 0.06 M2
Volume = Luas X P =
= 0.06 X 6.00 = 0.36 M3
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
5.00
5.00
PERHITUNGAN VOLUME
A. Balok Slof
Panjang = 14.00 M (. P )
Tinggi = 0.30 M ( T )
Tebal = 0.20 M ( t )
Volume = P X T X t
= 14.00 X 0.30 X 0.20
= 0.84 M3
B. Kolom
Panjang = 0.20 M (. P )
Tinggi = 2.00 M ( T )
Tebal = 0.20 M ( t )
Volume = P X T X t
= 0.20 X 2.00 X 0.20
= 0.08 M3 x 6 = 0.48
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
5.00
4.00'
PERHITUNGAN VOLUME
Panjang = 18 M'
Lebar = 0.40 M'
Tinggi = 0.60 M'
SKETSA / GAMBAR
PERHITUNGAN VOLUME
Luas = T X L
= 0.50 X 0.20 = 0.10 M2
Volume = Luas X P =
= 0.10 X 6.00 = 0.60 M3
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
5.00
2.50
5.00
PERHITUNGAN VOLUME
C. Ring Balok
Panjang = 14.00 M (. P )
Tinggi = 0.30 M ( T )
Tebal = 0.20 M ( t )
Volume = P X T X t
= 14.00 X 0.30 X 0.20
= 0.84 M3
D. Dinding
Panjang = 14.00 M (. P )
Tinggi = 2.00 M ( T )
Tebal = 0.15 M ( t )
Volume = P X T X t
= 14.00 X 2.00 X 0.15
= 4.20 M3
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
5.00
4.00'
PERHITUNGAN VOLUME
Luas = T X L
= 0.50 X 0.40 = 0.20 M2
Volume = Luas X P =
= 0.20 X 18.00 = 3.60 M3
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
Pekerjaan KABUPATEN MALUKU TENGGARA
Lokasi DESA AD KEI BESAR KAB. MALRA
T. A. : 2010
Item : Hidran Umum
Sub. Item : Beton Bertulang 1 : 2 : 3
SKETSA / GAMBAR
PERHITUNGAN VOLUME
Luas = T X L
= 0.15 X 1.50 = 0.23 M2
Volume = Luas X P =
= 0.23 X 1.50 = 0.34 M3
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
5.00
5.00
PERHITUNGAN VOLUME
C. Plat Lantai
Panjang = 4.00 M (. P )
Lebar = 3.00 M ( T )
Tebal = 0.15 M ( t )
Volume = P X T X t
= 4.00 X 3.00 X 0.15
= 1.80 M3
D. Plat Atas
Panjang = 4.00 M (. P )
Lebar = 3.00 M ( T )
Tebal = 0.15 M ( t )
Volume = P X T X t
= 4.00 X 3.00 X 0.15
= 1.80 M3
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
PERHITUNGAN VOLUME
Luas = T X L
= 0.40 X 18.00 = 7.20 M2
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
Pekerjaan KABUPATEN MALUKU TENGGARA
Lokasi DESA AD KEI BESAR KAB. MALRA
T. A. : 2010
Item : Hidran Umum
Sub. Item : Beton Bertulang 1 : 2 : 3
SKETSA / GAMBAR
PERHITUNGAN VOLUME
Luas =
= 0.20 + 0.35
2 = 0.28 x 1.50 = 0.41
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
PERHITUNGAN VOLUME
Luas = T X L
= 0.30 X 0.30 = 0.09 M2
Volume = Luas X P =
= 0.09 X 2,725.00 = 245.25 M3
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
PERHITUNGAN VOLUME
Kolom
Panjang = 2.50 M'
Lebar = 0.20 M'
Tinggi = 0.20 M'
Luas = P X L T
= 0.20 X 2.50 X 0.20 = 0.10 x 6 = 0.60
Slof
Panjang = 18.00 M'
Lebar = 0.15 M'
Tinggi = 0.20 M'
Luas = P X L T
= 0.15 X 18.00 X 0.20 = 0.54
Ring Balok
Panjang = 18.00 M'
Lebar = 0.15 M'
Tinggi = 0.20 M'
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
Pekerjaan KABUPATEN MALUKU TENGGARA
Lokasi DESA AD KEI BESAR KAB. MALRA
T. A. : 2010
Item : Hidran Umum
Sub. Item : Beton Bertulang 1 : 2 : 3
SKETSA / GAMBAR
PERHITUNGAN VOLUME
Luas =
= 0.20 + 0.35
2 = 0.28 x 1.50 = 0.41
PPK : : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
PERHITUNGAN VOLUME
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
SKETSA / GAMBAR
PERHITUNGAN VOLUME
Kuda - kuda
Panjang = 12.00 M'
Lebar = 0.15 M'
Tinggi = 0.10 M'
Luas = P X L T
= 0.15 X 12.00 X 0.10 = 0.18
Gordeng
Panjang = 18.00 M'
Lebar = 0.15 M'
Tinggi = 0.10 M'
Luas = P X L T
= 0.15 X 18.00 X 0.10 = 0.27
PPK : Pengembangan Air Baku & Pendayagunaan Air Tanah
Pekerjaan KABUPATEN MALUKU TENGGARA
Lokasi DESA AD KEI BESAR KAB. MALRA
T. A. : 2010
Item Hidran Umum
Sub. Item Beton Bertulang 1 : 2 : 3
SKETSA / GAMBAR
PERHITUNGAN VOLUME
Luas =
= 0.20 + 0.35
2 = 0.28 x 1.50 = 0.41
REKAPITULASI
RENCANA ANGGARAN BIAYA
Jumlah
No. Uraian Pekerjaan Harga
(Rp.)
1 2 3
Jumlah A + B : 859,636,795.65
PPN 10 % : 85,963,679.57
Total : 945,600,475.22
Dibulatkan : 945,600,000.00
Terbilang : " Sembilan Ratus Empat Puluh Lima Juta enam Ratus Ribu Rupiah "
Harga Satuan
No. Uraian Pekerjaan Satuan Volume Jumlah Harga (Rp.)
(Rp)
I PEKERJAAN PERSIAPAN
1 Pembuatan Jalan Masuk Ls 1.00 2,000,000.00 2,000,000.00
2 Fasilitas Direksi Ls 1.00 3,700,000.00 3,700,000.00
3 Mobilisasi Ls 1.00 3,500,000.00 3,500,000.00
4 Adminitrasi, Dokumentasi Ls 1.00 2,000,000.00 2,000,000.00
5 Surfei Detail & Pengukuran Ls 1.00 2,000,000.00 2,000,000.00
6 Papan Proyek Ls 1.00 1,000,000.00 1,000,000.00
7 Pembersihan (awal & akhir) Ls 1.00 2,557,000.00 2,557,000.00
JUMLAH I 16,757,000.00
II PENGADAAN PIPA DAN ACCSSORIES
1 Pipa GIP dia 3" M' 200.00 135,000.00 27,000,000.00
2 Pipa HDPE dia 2" M' 3,910.00 43,000.00 168,130,000.00
3 Pipa HDPE dia 1,5" M' 2,000.00 26,000.00 52,000,000.00
4 Pipa HDPE dia 1" M' 500.00 50,000.00 25,000,000.00
5 Sock HDPE dia 3" Bh 34.00 63,000.00 2,142,000.00
6 Sock HDPE dia 2" Bh 651.67 52,000.00 33,886,666.67
7 Sock HDPE dia 1,5" Bh 333.33 36,000.00 12,000,000.00
8 Sock HDPE dia 1" Bh 83.33 35,000.00 2,916,666.67
9 Reduser Gip.dia. 3" x 2 " Bh 1.00 280,000.00 280,000.00
10 Reduser Gip.dia. 2" x 1,5 " Bh 1.00 225,000.00 225,000.00
11 Tee Gip. Dia 3" x 3/4 x 3" Bh 1.00 105,000.00 105,000.00
12 Tee Gip. Dia 2" x 3/4 x 2" Bh 1.00 63,000.00 63,000.00
13 Tee Gip. Dia 1,5" x 3/4 x 1,5" Bh 2.00 38,750.00 77,500.00
14 Air Valve Gip. Dia 3/4" Bh 1.00 575,000.00 575,000.00
15 Tee Gip. 1" Bh 4.00 38,000.00 152,000.00
16 Stop Kran KITSZ dia.3" Bh 5.00 280,000.00 1,400,000.00
17 Stop Kran KITSZ dia.1,5" Bh 1.00 225,000.00 225,000.00
18 Stop Kran KITSZ dia.1" Bh 4.00 280,000.00 1,120,000.00
19 Water Mur Gip. 3" Bh 12.00 105,000.00 1,260,000.00
20 Cat Menie Kg 50.00 50,000.00 2,500,000.00
21 Plester Pipa Dos 20.00 37,400.00 748,000.00
22 Bend Gip. 22.5 dia 3" Bh 2.00 135,000.00 270,000.00
23 Bend Gip. 22.5 dia 2" Dos 5.00 115,000.00 575,000.00
24 Bend Gip. 22.5 dia 1,5" Bh 2.00 115,000.00 230,000.00
25 Double drat Gip. 3" Bh 5.00 63,500.00 317,500.00
26 Double drat Gip. 2" Bh 4.00 52,500.00 210,000.00
27 Double drat Gip. 1,5" Bh 1.00 40,000.00 40,000.00
28 Double drat Gip. 1" Bh 1.00 36,500.00 36,500.00
29 Water mur Gip. Dia 3" Bh 1.00 105,000.00 105,000.00
30 Water mur Gip. Dia 2" Bh 1.00 74,500.00 74,500.00
31 Water mur Gip. Dia 1,5" Bh 1.00 70,000.00 70,000.00
32 Water mur Gip. Dia 1" Bh 1.00 63,500.00 63,500.00
JUMLAH II 333,797,833.33
III PEMASANGAN PIPA DAN ACCESSORIES
1 Galian Tanah untuk Pipa Distribusi M3 245.25 46,432.10 11,387,472.53
2 Urugan Kembali M3 65.97 9,848.30 649,692.35
3 Pemasangan pipa HDPE dia 3" M' 200.00 36,360.50 7,272,100.00
4 PemasanganPipa HDPE dia 2" M' 3,910.00 36,360.50 142,169,555.00
5 Pemasangan Pipa HDPE dia 1,5" M' 2,000.00 36,360.50 72,721,000.00
6 Pemasangan Pipa HDPE dia 1" M' 500.00 36,360.50 18,180,250.00
7 Pemasangan Pengaman Stop Kran Bh 13.00 49,885.00 648,505.00
8 Pemasangan Accessories Ls 1.00 5,418,000.00 5,418,000.00
JUMLAH III 258,446,574.88
IV PEMBUATAN SUMUR DANGKAL (3 X 3 X 6)
JUMLAH VI 63,599,781.99
VI PENGADAAN DAN PEMASANGAN POMPA DAN ACCESSORIES
1 Motor penggerak + pompa (komplet) Unit 1.00 57,000,000.00 57,000,000.00
Motor = Yanmar (diesel) atau Kubota
Pompa = Centrifugal Q = 10 ltr/dt
Head = 80 meter
2 Pipa Gip. Med. A dia 2" M' 24.17 36,360.50 878,738.90
3 Stop Kran KITZ dia 2" Bh 2.00 49,885.00 99,770.00
4 Bend Gip. Dia 2" Bh 8.00 39,831.00 318,648.00
5 Saringan Gip.+ Klep dia 2" Ls 1.00 140,500.00 140,500.00
6 Sock Gip. 2" Bh 4.00 24,000.00 96,000.00
7 Water Mur dia 2" Bh 3.00 74,500.00 223,500.00
8 Double Dreat Gip.dia 2" Bh 3.00 52,500.00 157,500.00
9 Reduser Gip. Dia 3 x 2" Bh 3.00 280,000.00 840,000.00
10 Clamp Sadle Gip. /Tee Reduser dia. 3 x 3/4" Bh 1.00 44,000.00 44,000.00
11 Air Valve dia.3/4 Bh 1.00 575,000.00 575,000.00
12 Water Hammer dia 2" Bh 1.00 248,000.00 248,000.00
13 Water Mur dia 3" Bh 1.00 105,000.00 105,000.00
14 Double Dreat Gip.dia 3" Bh 1.00 63,500.00 63,500.00
15 Pemasangan Motor Penggerak + Pompa Ls 1.00 2,716,000.00 2,716,000.00
16 Pengadaan Tangki air Pendingin dan Accessories Ls 1.00 2,000,000.00 2,000,000.00
17 Pengetesan dan Pengujian Pompa Selama 3 Bln Ls 1.00 3,000,000.00 3,000,000.00
18 Pengadaan Kunci Pipa 3" + Snei Pipa dia 3" + Ragon Pipa Ls 1.00 2,000,000.00 2,000,000.00
19 Gergaji Besi + Kunci Inggris Bh 5.00 15,000.00 75,000.00
JUMLAH VI 70,506,156.90
Harga Satuan
No. Uraian Pekerjaan Satuan Volume Jumlah Harga (Rp.)
(Rp)
VII PEMBUATAN RESERVOAR 25 M3
1 Galian Tanah M3 3.50 46,432.10 162,512.35
2 Urugan Bekas Galian M3 2.56 9,848.30 25,211.65
3 urugan Pasir M3 1.80 176,825.00 318,285.00
4 Ring Balok Beton 17/20 cm ad. 1 : 2 : 3 M3 0.84 4,450,000.50 3,738,000.42
5 Sloof Beton 17/20 cm ad. 1 : 2 : 3 M3 0.84 4,450,000.50 3,738,000.42
6 Kolom Beton 25/25 cm ad. 1 : 2 : 3 M3 0.48 4,450,000.50 2,136,000.24
7 Dinding Beton ad. 1 : 2 : 3 M3 4.80 4,450,000.50 21,360,002.40
8 Plat Penutup ad 1 : 2 : 3 M3 1.80 4,450,000.50 8,010,000.90
9 Plat Lantai ad. 1 : 2 : 3 M3 1.80 4,450,000.50 8,010,000.90
10 Pasangan Batu ad. 1 : 5 M3 7.00 673,935.90 4,717,551.30
11 Timbrisan Batu Kosong M3 6.00 327,366.60 1,964,199.60
12 Rabat Keliling ad 1 : 3 : 5 M3 0.90 743,094.00 668,784.60
13 Lantai Kerja ad 1 : 3 : 5 M3 0.80 743,094.00 594,475.20
14 Plesteran Lantai ad 1 : 3 M2 52.00 13,513.50 702,702.00
15 Plesteran Dinding ad 1 : 3 (untuk dinding) M2 52.00 13,513.50 702,702.00
16 Plesteran Dinding ad 1 : 3 (untuk plat atap) M2 52.00 13,513.50 702,702.00
17 Acian M2 4.00 7,495.40 29,981.60
19 Pengadaan/pemasangan Pipa Gip. Med A dia. 3" M' 5.00 200,000.00 1,000,000.00
(penguras)
20 Pengadaan/pemasangan Pipa Gip. Med A dia. 2" M' 5.00 100,000.00 500,000.00
(over flouw dan outlet)
21 Pengadaan/pemasangan Pipa Gip. Med A dia. 2" M' 1.00 100,000.00 100,000.00
(Inlet)
22 Stop Kran KITZ dia 3" Bh 1.00 321,000.00 321,000.00
23 Stop Kran KITZ dia 2" Bh 1.00 172,000.00 172,000.00
24 Stop Kran KITZ dia 1,5" Bh 4.00 105,000.00 420,000.00
25 Bend Gip. Dia 2" Bh 2.00 101,000.00 202,000.00
26 Bend Gip. Dia 1,5" Bh 1.00 92,300.00 92,300.00
27 Tee Gip. Dia 2" x 2" x 2" Bh 1.00 102,000.00 102,000.00
28 Saringan Pipa Penguras dia 3" Bh 1.00 225,000.00 225,000.00
29 Tangga Pipa Gip. Dia. 1" dan dia. 3" Bh 1.00 375,000.00 375,000.00
30 Pipa Udara Gip. Dia 2" Ls 1.00 100,000.00 100,000.00
31 Menhole Plat Baja tebal 5 mm Ls 1.00 800,000.00 800,000.00
32 Besi Siku 40 x 40 x 4 mm Ls 1.00 1,000,000.00 1,000,000.00
JUMLAH VII 62,990,412.58
VII KRAN UMUM
1 Galian Tanah M3 0.36 46,432.10 16,715.56
2 Urugan Bekas Galian M3 0.22 9,848.30 2,166.63
3 urugan Pasir M3 0.31 176,825.00 54,815.75
4 Pasangan Batu ad. 1 : 5 M3 0.60 673,935.90 404,361.54
5 Rabat Keliling ad 1 : 3 : 5 M3 0.34 743,094.00 252,651.96
6 Beton Struktur Tanpa Tulangan 1 : 3 : 5 M3 0.41 743,094.00 304,668.54
7 Plesteran ad 1 : 4 M2 6.20 13,513.50 83,783.70
8 Pipa Gip. Med. A dia 3/4" M' 2.00 26,000.00 52,000.00
9 Knee Gip dia 3/4" Bh 1.00 33,000.00 33,000.00
10 Tee Gip dia 3/4" Bh 1.00 37,000.00 37,000.00
11 Reduser Gip. Dia 3/4" Bh 1.00 36,970.00 36,970.00
12 Water Mur Gip. Dia 1" x 3/4" Bh 1.00 53,300.00 53,300.00
13 Kran Handle Gip. Dia 3/4 Bh 2.00 53,300.00 106,600.00
JUMLAH 1,438,033.67
JUMLAH VII Untuk Kran Umum Bh 10 1,438,033.67 14,380,336.72
TOTAL 859,636,795.65
Ppn (10 %) 85,963,679.57
TOTAL 945,600,475.22
DIBULATKAN 945,600,000.00
TERBILANG : Sembilan Ratus Empat Puluh Lima Juta Enam Ratus Ribu Rupiah