Tanggal : 10-May-19
Section :
I. Data Teknis
1. Beban mati
Pelat sendiri = 2400 x 0.12 = 228 kg/m2
Finishing lantai = 2000 x 0.05 = 100 kg/m2
Ceiling dan plafond = 25 kg/m2
qD = 353 kg/m2
2. Beban hidup
qL = 300 kg/m2
per m lebar pelat qL = 300 kg/m
3. Beban Ultimit
qu = 1.2 qD + 1.6 qL
qu = 1.2 x 353 + 1.6 x 300
qu = 903.6 kg/m
1. Momen Lapangan
2
Mu = 1/14 x qu x L
2
Mu = 1/14 x 904 x 3
Mu = 580.89 kg.m
2. Momen Tumpuan
2
Mu = 1/10 x qu x L
2
Mu = 1/10 x 904 x 3
Mu = 813.24 kg.m
1/3
IV. Desain Tulangan
d
z
As T
d'
es
Es = 200000 MPa
C = 0.85 f'c a b
b
T = As. fy
b1 = a/c
d = 9.5 cm b = 100 cm
d' = 2.5 cm es > ey
lapangan :
cb d
= cb = 4.96 cm
0.003 0.003 e y
tumpuan :
0.003 d cb = 5.7 cm
cb =
0.003 fy Es
note :
Mn
As =
z fy
Lapangan Tumpuan
2 2
As = 0.13335118 cm /m As = 0.2646189 cm /m
2 2
Amin = 2.418181818 cm /m Amin = 3.325 cm /m
V. Kesimpulan
1. Tulangan Lapangan
Luas penampang Union Floor Deck W-1000 > Luas tulangan yang diperlukan
tebal = 0.75 mm TCT
Karena luas penampang Union Floor Deck W-1000 lebih besar daripada luas tulangan yang
diperlukan maka tulangan lapangan dan tulangan pembagi tidak diperlukan lagi.
2
As = 468.9067 mm /m
Karena luas tulangan tumpuan yang direncanakan lebih besar daripada tulangan tumpuan
yang diperlukan maka tulangan tumpuan sepanjang 1/4 bentang tidak diperlukan lagi.
3/3