PERHITUNGAN VOLUME PEKERJAAN

PEMBANGUNAN RUMAH DINAS

1. GALIAN PONDASI BATU KALI

Dimensi Galian Volume


No. SEGMEN Jumlah (bh)
Panjang (m) Lebar (m) Tinggi Galian (m) (m3)
A. VERTIKAL
1 1 7.250 0.800 0.600 3.480
2 1 1.500 0.800 0.600 0.720
3 1 3.000 0.800 0.600 1.440
4 1 3.250 0.800 0.600 1.560
5 1 1.500 0.580 0.600 0.522
6 1 1.000 0.580 0.600 0.348
7 1 4.750 0.800 0.600 2.280
8 1 1.500 0.580 0.600 0.522

B. HORIZONTAL
1 4 3.000 0.800 0.600 5.760
2 1 8.000 0.580 0.600 2.784
3 1 6.000 0.800 0.600 2.880
4 2 3.000 0.580 0.600 2.088

Jumlah 24.384

TOTAL VOLUME
1. Galian Pondasi Batu Kali = 24.384 M3
2. Galian Tangga = 0.144 M3

= 24.528 M3

3. Urugan Kembali = 8.128 M3


1.1 Pondasi Tangga

Dimensi Galian Volume


No. SEGMEN Jumlah (bh)
Panjang (m) Lebar (m) Tinggi Galian (m) (m3)
1 A ↔ 5-6 1 3.320 1.850 0.200 1.228
2 H ↔ 5-6 1 3.320 1.850 0.200 1.228
3 A ↔ 6-7 1 5.330 1.850 0.200 1.972
4 H ↔ 6-7 1 5.330 1.850 0.200 1.972
5 A ↔ 8-9 1 5.330 1.850 0.200 1.972
6 H ↔ 8-9 1 5.330 1.850 0.200 1.972
7 A ↔ 9-10 1 3.320 1.850 0.200 1.228
8 H ↔ 9-10 1 3.320 1.850 0.200 1.228
9 Teras Bulat 1 9.000 1.850 0.200 3.330

Jumlah 16.132

1.2 Pondasi Teras Belakang

Dimensi Galian Volume


No. SEGMEN Jumlah (bh)
Panjang (m) Lebar (m) Tinggi Galian (m) (m3)
1 13-14 ↔ G-I 1 9.000 0.900 0.700 5.670

Jumlah 5.670

TOTAL VOLUME GALIAN PONDASI = 21.802 M3


PERHITUNGAN VOLUME PEKERJAAN
PEMBANGUNAN RUMAH DINAS

1. GALIAN TANAH UNTUK TANGGA PASANGAN BATA

A. TANGGA DEPAN

Dimensi Galian
No. SEGMEN Jumlah (bh)
Panjang (m) Lebar (m)

1 Tangga Atas 1 2.000 0.150


1 0.400 0.150
2 Tangga Bawah 1 2.000 0.150
1 0.400 0.150

TOTAL VOLUME GALIAN = 0.144


EKERJAAN
H DINAS

GAN BATA

mensi Galian Volume


Tinggi Galian (m) (m3)

0.200 0.060
0.200 0.012
0.200 0.060
0.200 0.012

Jumlah 0.144

M3