Tujuh Ratus Dua Puluh Delapan Juta Tiga Ratus Sembilan Puluh Lima Ribu Rupiah
Catatan :
Direncakan Oleh :
A. 2.2.1.3. Pembuatan 1 m2 Pagar sementara dari kawat duri tinggi 1,8 meter
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Page 5
Pekerja L.01 OH 0.200 67,500.00 13,500.00
Tukang Kayu L.02 OH 0.300 72,500.00 21,750.00
Kepala Tukang L.03 OH 0.020 77,500.00 1,550.00
Mandor L.04 OH 0.020 80,000.00 1,600.00
JUMLAH TENAGA KERJA 38,400.00
B. BAHAN
Dolken btg 1.000 - -
Kawat duri kg 25.000 18,500.00 462,500.00
PC kg 2.000 1,125.00 2,250.00
Pasir beton m3 0.005 180,000.00 900.00
Kerikil beton m3 0.009 220,000.00 1,980.00
Paku biasa kg 0.060 15,000.00 900.00
JUMLAH HARGA BAHAN 468,530.00
C. PERALATAN
Page 6
Pasir beton m3 0.100 180,000.00 18,000.00
Koral beton m3 0.150 220,000.00 33,000.00
Bata merah bh 30.000 900.00 27,000.00
Seng plat Lbr 0.250 16,500.00 4,125.00
Jendela nako bh 0.200 18,500.00 3,700.00
Kaca polos m2 0.080 113,100.00 9,048.00
Kunci tanam bh 0.150 108,300.00 16,245.00
Plywood 4 mm Lbr 0.060 62,700.00 3,762.00
JUMLAH HARGA BAHAN 1,117,432.50
C. PERALATAN
Page 7
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 1,448,137.50
E. overhead & Profit 10% * D 144,813.75
F. Harga Satuan Pekerjaan (D+E) 1,592,951.25
Page 8
B. BAHAN
Bambu Ø 6 - 8/600 cm btg 1.250 17,100.00 21,375.00
Tali ijuk m3 0.186 6,800.00 1,264.80
JUMLAH HARGA BAHAN 22,639.80
C. PERALATAN
Page 9
JUMLAH HARGA BAHAN -
C. PERALATAN
Page 10
Semen PC kg 45.000 1,125.00 50,625.00
Pasir beton m3 0.074 180,000.00 13,320.00
Koral beton m3 0.146 220,000.00 32,120.00
JUMLAH HARGA BAHAN 311,190.00
C. PERALATAN
Page 11
JUMLAH HARGA BAHAN -
C. PERALATAN
Page 12
A. 2.3.1.7. Pengerjaan stripping 1 m2 tanah tebing setinggi 1 m
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 67,500.00 3,375.00
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 3,775.00
B. BAHAN
Page 13
A. 2.3.1.9. Pengurugan kembali 1 m3 galian tanah
Pengurugan kembali 1 m3 galian dihitung dari 1/3 dari koefisien pekerjaan galian
1 m3 Urugan kembali galian tanah biasa sedalam 1 meter $ 19,295.83
1 m3 Urugan kembali galian tanah biasa sedalam 2 meter $ 23,595.00
1 m3 Urugan kembali galian tanah biasa sedalam 3 meter $ 27,952.83
1 m3 Urugan kembali galian tanah keras sedalam 1 meter $ 25,688.67
1 m3 Urugan kembali galian tanah cadas sedalam 1 meter $ 38,885.00
1 m3 Urugan kembali galian tanah lumpur sedalam 1 meter $ 31,020.00
Page 14
C. PERALATAN
Page 15
A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI
Page 16
Pasir pasang m3 0.520 180,000.00 93,600.00
JUMLAH HARGA BAHAN 468,975.00
C. PERALATAN
Page 17
Kepala Tukang L.03 OH 0.075 77,500.00 5,812.50
Mandor L.04 OH 0.075 80,000.00 6,000.00
JUMLAH TENAGA KERJA 167,437.50
B. BAHAN
Batu belah (putih) m3 1.200 170,000.00 204,000.00
Semen portland kg 136.000 1,125.00 153,000.00
Pasir pasang m3 0.544 180,000.00 97,920.00
JUMLAH HARGA BAHAN 454,920.00
C. PERALATAN
Page 18
A. 3.2.1.5. Pemasangan 1 m3 Pondasi batu belah (hitam) campuran 1SP : 8PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.500 67,500.00 101,250.00
Tukang Batu L.02 OH 0.750 72,500.00 54,375.00
Kepala Tukang L.03 OH 0.075 77,500.00 5,812.50
Mandor L.04 OH 0.075 80,000.00 6,000.00
JUMLAH TENAGA KERJA 167,437.50
B. BAHAN
Batu belah (hitam) m3 1.200 160,000.00 192,000.00
Semen portland kg 91.000 1,125.00 102,375.00
Pasir pasang m3 0.584 180,000.00 105,120.00
JUMLAH HARGA BAHAN 399,495.00
C. PERALATAN
A. 3.2.1.6. Pemasangan 1 m3 Pondasi batu belah (hitam) campuran 1SP : 1KP : 2PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.500 67,500.00 101,250.00
Tukang Batu L.02 OH 0.750 72,500.00 54,375.00
Kepala Tukang L.03 OH 0.075 77,500.00 5,812.50
Mandor L.04 OH 0.075 80,000.00 6,000.00
JUMLAH TENAGA KERJA 167,437.50
B. BAHAN
Batu belah (hitam) m3 1.200 160,000.00 192,000.00
Semen portland m3 0.170 1,383,750.00 235,237.50
Kapur pasang m3 0.170 137,500.00 23,375.00
Pasir pasang m3 0.340 180,000.00 61,200.00
JUMLAH HARGA BAHAN 511,812.50
Page 19
C. PERALATAN
A. 3.2.1.6. Pemasangan 1 m3 Pondasi batu belah (putih) campuran 1SP : 1KP : 2PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.500 67,500.00 101,250.00
Tukang Batu L.02 OH 0.750 72,500.00 54,375.00
Kepala Tukang L.03 OH 0.075 77,500.00 5,812.50
Mandor L.04 OH 0.075 80,000.00 6,000.00
JUMLAH TENAGA KERJA 167,437.50
B. BAHAN
Batu belah (putih) m3 1.200 170,000.00 204,000.00
Semen portland m3 0.170 1,383,750.00 235,237.50
Kapur pasang m3 0.170 137,500.00 23,375.00
Pasir pasang m3 0.340 180,000.00 61,200.00
JUMLAH HARGA BAHAN 523,812.50
C. PERALATAN
A. 3.2.1.7. Pemasangan 1 m3 Pondasi batu belah (hitam) campuran 1SP : 3KP : 10PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.500 67,500.00 101,250.00
Tukang Batu L.02 OH 0.750 72,500.00 54,375.00
Kepala Tukang L.03 OH 0.075 77,500.00 5,812.50
Mandor L.04 OH 0.075 80,000.00 6,000.00
JUMLAH TENAGA KERJA 167,437.50
B. BAHAN
Batu belah (hitam) m3 1.200 160,000.00 192,000.00
Semen portland kg 61.000 1,125.00 68,625.00
Kapur pasang m3 0.147 137,500.00 20,212.50
Pasir pasang m3 0.492 180,000.00 88,560.00
JUMLAH HARGA BAHAN 369,397.50
C. PERALATAN
A. 3.2.1.7. Pemasangan 1 m3 Pondasi batu belah (putih) campuran 1SP : 3KP : 10PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.500 67,500.00 101,250.00
Tukang Batu L.02 OH 0.750 72,500.00 54,375.00
Kepala Tukang L.03 OH 0.075 77,500.00 5,812.50
Page 20
Mandor L.04 OH 0.075 80,000.00 6,000.00
JUMLAH TENAGA KERJA 167,437.50
B. BAHAN
Batu belah (putih) m3 1.200 170,000.00 204,000.00
Semen portland kg 61.000 1,125.00 68,625.00
Kapur pasang m3 0.147 137,500.00 20,212.50
Pasir pasang m3 0.492 180,000.00 88,560.00
JUMLAH HARGA BAHAN 381,397.50
C. PERALATAN
A. 3.2.1.8. Pemasangan 1 m3 Pondasi batu belah (hitam) campuran 1/4SP : 1KP : 4PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.500 67,500.00 101,250.00
Tukang Batu L.02 OH 0.750 72,500.00 54,375.00
Kepala Tukang L.03 OH 0.075 77,500.00 5,812.50
Mandor L.04 OH 0.075 80,000.00 6,000.00
JUMLAH TENAGA KERJA 167,437.50
B. BAHAN
Batu belah (hitam) m3 1.200 160,000.00 192,000.00
Semen portland kg 41.000 1,125.00 46,125.00
Kapur pasang m3 0.131 137,500.00 18,012.50
Pasir pasang m3 0.523 180,000.00 94,140.00
JUMLAH HARGA BAHAN 350,277.50
C. PERALATAN
A. 3.2.1.8. Pemasangan 1 m3 Pondasi batu belah (putih) campuran 1/4SP : 1KP : 4PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.500 67,500.00 101,250.00
Tukang Batu L.02 OH 0.750 72,500.00 54,375.00
Kepala Tukang L.03 OH 0.075 77,500.00 5,812.50
Mandor L.04 OH 0.075 80,000.00 6,000.00
JUMLAH TENAGA KERJA 167,437.50
B. BAHAN
Batu belah (putih) m3 1.200 170,000.00 204,000.00
Semen portland kg 41.000 1,125.00 46,125.00
Kapur pasang m3 0.131 137,500.00 18,012.50
Pasir pasang m3 0.523 180,000.00 94,140.00
JUMLAH HARGA BAHAN 362,277.50
C. PERALATAN
Page 21
A. 3.2.1.9. Pemasangan 1 m3 batu hitam kosong (anstamping)
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.780 67,500.00 52,650.00
Tukang Batu L.02 OH 0.390 72,500.00 28,275.00
Kepala Tukang L.03 OH 0.039 77,500.00 3,022.50
Mandor L.04 OH 0.039 80,000.00 3,120.00
JUMLAH TENAGA KERJA 87,067.50
B. BAHAN
Batu belah (hitam) m3 1.200 160,000.00 192,000.00
Pasir urug m3 0.432 150,000.00 64,800.00
JUMLAH HARGA BAHAN 256,800.00
C. PERALATAN
A. 3.2.1.10. Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2PB : 3 Kr dan 40% batu belah (hitam).
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 3.400 67,500.00 229,500.00
Tukang Batu L.02 OH 0.850 72,500.00 61,625.00
Kepala Tukang L.03 OH 0.085 77,500.00 6,587.50
Mandor L.04 OH 0.170 80,000.00 13,600.00
JUMLAH TENAGA KERJA 311,312.50
B. BAHAN
Batu belah (hitam) m3 0.480 160,000.00 76,800.00
Semen Portland kg 194.000 1,125.00 218,250.00
Pasir beton m3 0.312 180,000.00 56,160.00
Kerikil beton/ split m3 0.468 220,000.00 102,960.00
Besi beton kg 126.000 9,000.00 1,134,000.00
Kawat beton kg 1.800 22,800.00 41,040.00
Page 22
JUMLAH HARGA BAHAN 1,629,210.00
C. PERALATAN
A. 3.2.1.10. Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2PB : 3 Kr dan 40% batu belah (putih).
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 3.400 67,500.00 229,500.00
Tukang Batu L.02 OH 0.850 72,500.00 61,625.00
Kepala Tukang L.03 OH 0.085 77,500.00 6,587.50
Mandor L.04 OH 0.170 80,000.00 13,600.00
JUMLAH TENAGA KERJA 311,312.50
B. BAHAN
Batu belah (putih) m3 0.480 170,000.00 81,600.00
Semen Portland kg 194.000 1,125.00 218,250.00
Pasir beton m3 0.312 180,000.00 56,160.00
Kerikil beton/ split m3 0.468 220,000.00 102,960.00
Besi beton kg 126.000 9,000.00 1,134,000.00
Kawat beton kg 1.800 22,800.00 41,040.00
JUMLAH HARGA BAHAN 1,634,010.00
C. PERALATAN
A. 3.2.1.11. Pemasangan 1 m3 pondasi sumuran batu belah (hitam), diameter 100 cm.
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 2.400 67,500.00 162,000.00
Tukang Batu L.02 OH 0.800 72,500.00 58,000.00
Kepala Tukang L.03 OH 0.080 77,500.00 6,200.00
Mandor L.04 OH 0.119 80,000.00 9,520.00
JUMLAH TENAGA KERJA 235,720.00
B. BAHAN
Batu belah (hitam) m3 0.450 160,000.00 72,000.00
Semen Portland kg 194.000 1,125.00 218,250.00
Pasir beton m3 0.312 180,000.00 56,160.00
Kerikil beton/ split m3 0.468 220,000.00 102,960.00
JUMLAH HARGA BAHAN 449,370.00
C. PERALATAN
A. 3.2.1.11. Pemasangan 1 m3 pondasi sumuran batu belah (putih), diameter 100 cm.
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Page 23
Pekerja L.01 OH 2.400 67,500.00 162,000.00
Tukang Batu L.02 OH 0.800 72,500.00 58,000.00
Kepala Tukang L.03 OH 0.080 77,500.00 6,200.00
Mandor L.04 OH 0.119 80,000.00 9,520.00
JUMLAH TENAGA KERJA 235,720.00
B. BAHAN
Batu belah (putih) m3 0.450 170,000.00 76,500.00
Semen Portland kg 194.000 1,125.00 218,250.00
Pasir beton m3 0.312 180,000.00 56,160.00
Kerikil beton/ split m3 0.468 220,000.00 102,960.00
JUMLAH HARGA BAHAN 453,870.00
C. PERALATAN
Page 24
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
A. 5.1.1.1. Pemasangan 1 buah clooset duduk / monoblok
Page 25
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 662,725.00
E. Profit 10% * D 66,272.50
F. Harga Satuan Pekerjaan (D+E) 728,997.50
Page 26
Semen portland kg 6.000 1,125.00 6,750.00
Pasir pasang m3 0.010 180,000.00 1,800.00
Perlengkapan % 12.000 36,300.00 36,300.00
JUMLAH HARGA BAHAN 407,850.00
C. PERALATAN
Page 27
B. BAHAN
Bata merah bh 150.000 900.00 135,000.00
Semen portland kg 120.000 1,125.00 135,000.00
Pasir pasang m3 0.300 180,000.00 54,000.00
Porselin 11 x 11 bh 360.000 617.00 222,120.00
Semen warna kg 6.000 14,800.00 88,800.00
JUMLAH HARGA BAHAN 634,920.00
C. PERALATAN
Page 28
Kepala Tukang L.03 OH 0.050
Mandor L.04 OH 0.018 -
JUMLAH TENAGA KERJA -
B. BAHAN
Beton 1:2:3 m3 0.900
Baja tulangan kg 180.000
Kayu bekisting m2 8.000
Ubin porselin bh 500.000
Perlengkapan % 10.000
JUMLAH HARGA BAHAN -
C. PERALATAN
Page 29
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 67,500.00 675.00
Tukang batu L.02 OH 0.100 72,500.00 7,250.00
Kepala Tukang L.03 OH 0.010 77,500.00 775.00
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 9,100.00
B. BAHAN
Floor drain Unit 1.000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00
C. PERALATAN
Page 30
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 518,532.50
E. Profit 10% * D 51,853.25
F. Harga Satuan Pekerjaan (D+E) 570,385.75
Page 31
Kran air bh 1.000 25,000.00 25,000.00
Sealtape bh 0.025 2,500.00 62.50
JUMLAH HARGA BAHAN 25,062.50
C. PERALATAN
Page 32
Pipa galvanis 1 1/2" m 1.200 42,750.00 51,300.00
Perlengkapan % 35%x pipa 14,962.50 14,962.50
JUMLAH HARGA BAHAN 66,262.50
C. PERALATAN
Page 33
Pipa PVC 1/2" m 1.200 6,250.00 7,500.00
Perlengkapan % 35%x pipa 2,187.50 2,187.50
JUMLAH HARGA BAHAN 9,687.50
C. PERALATAN
Page 34
Pipa PVC 1 1/2" m 1.200 19,950.00 23,940.00
Perlengkapan % 35%x pipa 6,982.50 6,982.50
JUMLAH HARGA BAHAN 30,922.50
C. PERALATAN
Page 35
Pipa PVC 2" D m 1.200 15,675.00 18,810.00
Perlengkapan % 35%x pipa 5,486.25 5,486.25
JUMLAH HARGA BAHAN 24,296.25
C. PERALATAN
Page 36
Pipa PVC 3" m 1.200 51,300.00 61,560.00
Perlengkapan % 35%x pipa 17,955.00 17,955.00
JUMLAH HARGA BAHAN 79,515.00
C. PERALATAN
Page 37
Pipa PVC 4" D m 1.200 42,750.00 51,300.00
Perlengkapan % 35%x pipa 14,962.50 14,962.50
JUMLAH HARGA BAHAN 66,262.50
C. PERALATAN
A. 5.1.1.33. Pemasangan 1 m' pipa air limbah jenis pipa tanah diameter 20 cm
A. 5.1.1.34. Pemasangan 1 m' pipa air limbah jenis pipa tanah diameter 15 cm
Page 38
Kepala Tukang L.03 OH 0.007 -
Mandor L.04 OH 0.007 -
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa beton diameter 15 cm bh 1.100
Bata merah m3 0.027
Semen portland kg 3.920
Pasir pasang m3 0.056
Pasir urug m3 0.024
JUMLAH HARGA BAHAN -
C. PERALATAN
Page 39
A.7.1.1 HARGA SATUAN PEKERJAAN LANDSCAPE
A. 7.1.1.1. Pemasangan 1 m1 got U - 20 cm
Page 40
Kepala tukang L.03 OH 0.050 77,500.00 3,875.00
Mandor L,04 OH 0.001 80,000.00 104.00
JUMLAH TENAGA KERJA 57,104.00
B. BAHAN
Paving blok, tebal 6 cm m2 1.010 62,700.00 63,327.00
Pasir Pasang m3 0.050 180,000.00 9,000.00
JUMLAH HARGA BAHAN 72,327.00
C. PERALATAN 10%
Page 41
A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA
Page 42
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 43
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 44
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 45
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 46
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 47
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 48
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 49
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 50
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 51
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 52
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 53
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 54
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 55
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 56
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 57
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 58
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 59
225 kap 0,5 - 1,0 m3
Sewa Tripot/Tackel & hari 0.031
handle crane 2 T
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 60
Operator alat berat L.08 OH 0.293
Mandor L.04 OH 0.201 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa DCI Ø 600 mm m 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa excavator type hari 0.058
225 kap 0,5 - 1,0 m3
Sewa Tripot/Tackel & hari 0.077
handle crane 2 T
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 61
F. Harga Satuan Pekerjaan (D+E) -
Page 62
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa excavator type hari 0.18
225 kap 0,5 - 1,0 m3
Sewa Tripot/Tackel & hari 0.36
handle crane 2 T
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 63
Pipa baja Ø 125 mm m 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa Tripot/Tackel & hari 0.004
handle crane 2 T
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 64
Pipa baja Ø 250 mm m 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa Tripot/Tackel & hari 0.004
handle crane 2 T
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 65
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa baja Ø 450 mm m 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa exavator type hari 0.026
225 kap 0,5-1,0 m3
Sewa Tripot/Tackel & hari 0.037
handle crane 2 T
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 66
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 3.897 - -
Tukang pipa L.02 OH 0.779 - -
Mandor L.04 OH 0.390 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa baja Ø 800 mm m 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa exavator type hari 0.046
225 kap 0,5-1,0 m3
Sewa Tripot/Tackel & hari 0.098
handle crane 2 T
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 67
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 68
B. BAHAN
Pipa PVC Ø 63 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T1/manual hari 0.003
( gergaji ) / saw
Page 69
Tukang pipa L.02 OH 0.015 - -
Mandor L.04 OH 0.0030 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa PVC Ø 150 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T1/manual hari 0.003
( gergaji ) / saw
Page 70
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.155 - -
Tukang pipa L.02 OH 0.077 - -
Mandor L.04 OH 0.0150 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa PVC Ø 300 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T1/manual hari 0.037
( gergaji ) / saw
Page 71
A. 8.4.2.10. Pemotongan 1 buah pipa PVC Ø 500 mm
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.518 - -
Tukang pipa L.02 OH 0.259 - -
Mandor L.04 OH 0.0520 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa PVC Ø 500 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.069
cilinder saw
Page 72
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 73
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 74
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.005
cilinder saw
Page 75
Tukang pipa L.02 OH 0.022 - -
Mandor L.04 OH 0.0040
Operator L.08 OH 0.1710 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa HDPE Ø 200 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.017
cilinder saw
Page 76
A. 8.4.2.24. Pemotongan 1 buah pipa HDPE Ø 400 mm
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.177 - -
Tukang pipa L.02 OH 0.088 - -
Mandor L.04 OH 0.0180
Operator L.08 OH 0.3710 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa HDPE Ø 400 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.055
cilinder saw
Page 77
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 78
Pipa HDPE Ø 900 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.27
cilinder saw
Page 79
Pekerja L.01 OH 0.019 - -
Tukang pipa L.02 OH 0.010 - -
Mandor L.04 OH 0.0020
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa GIP Ø 63 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0
cilinder saw
Page 80
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.092 - -
Tukang pipa L.02 OH 0.046 - -
Mandor L.04 OH 0.0090
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa GIP Ø 125 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0
cilinder saw
Page 81
A. 8.4.2.38. Pemotongan 1 buah pipa GIP Ø 250 mm
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.475 - -
Tukang pipa L.02 OH 0.237 - -
Mandor L.04 OH 0.0470
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa GIP Ø 250 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0
cilinder saw
Page 82
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 83
cilinder saw
Page 84
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0
cilinder saw
Page 85
B. BAHAN
Pipa DCI Ø 100 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa tripot/Tackel & hari 0.003
handle crane 2 T
Page 86
Tukang pipa L.02 OH 0.073 - -
Mandor L.04 OH 0.0370
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa DCI Ø 200 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa tripot/Tackel & hari 0.054
handle crane 2 T
Page 87
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.941 - -
Tukang pipa L.02 OH 0.188 - -
Mandor L.04 OH 0.0940
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa DCI Ø 400 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.158
cilinder saw
Page 88
A. 8.4.2.58. Pemotongan 1 buah pipa DCI Ø 600 mm
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.309 - -
Tukang pipa L.02 OH 0.262 - -
Mandor L.04 OH 0.1310
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa DCI Ø 600 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.192
cilinder saw
Page 89
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 90
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 91
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.042
cilinder saw
Page 92
Pipa baja Ø 250 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.068
cilinder saw
Page 93
Mandor L.04 OH 0.1400
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa baja Ø 450 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.107
cilinder saw
Page 94
A. TENAGA
Pekerja L.01 OH 2.624 - -
Tukang pipa L.02 OH 0.525 - -
Mandor L.04 OH 0.2620
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa baja Ø 800 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.166
cilinder saw
Page 95
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 3.667 - -
Tukang pipa L.02 OH 0.733 - -
Mandor L.04 OH 0.3670
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa baja Ø 1100 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.218
cilinder saw
Page 96
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 97
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 98
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 99
Mobile crane =< 3 ton hari 0.500
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 100
C. PERALATAN
Sewa Tripot/Tackel & hari 1.000
handle crane 2 T
Mobile crane =< 3 ton hari 1.000
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 101
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa Tripot/Tackel & hari 0.029
handle crane 2 T
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 102
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa Tripot/Tackel & hari 0.500
handle crane 2 T
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 103
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa Tripot/Tackel & hari 0.193
handle crane 2 T
Mobile crane =< 3 ton hari 0.096
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 104
B. BAHAN
Tee Ø 900 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa Tripot/Tackel & hari 0.321
handle crane 2 T
Mobile crane =< 3 ton hari 0.161
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 105
Tukang pipa L.02 OH 1.208 - -
Mandor L.04 OH 0.242 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Tee Ø 1200 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Sewa Tripot/Tackel & hari 0.450
handle crane 2 T
Mobile crane =< 3 ton hari 0.225
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 106
handle crane 2 T
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 107
Mandor L.04 OH 0.300 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa Ø 250 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 0.98
cilinder saw
Sewa genset 1500 watt hari 0.789
sewa pompa submersible 3m3/h hari 1.903
Sewa Tripot/Tackel & hari 1.256
handle crane 2 T
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 108
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 109
JUMLAH TENAGA KERJA -
B. BAHAN
Pipa Ø 600 mm bh 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan potong pipa T2/mekanik/ hari 1.75
cilinder saw
Sewa genset 1500 watt hari 2.259
sewa pompa submersible 3m3/h hari 3.828
Sewa Tripot/Tackel & hari 2.061
handle crane 2 T
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 110
D. Jumlah (A+B+C) -
E. Profit 10% * D -
F. Harga Satuan Pekerjaan (D+E) -
Page 111
JUMLAH HARGA BAHAN -
C. PERALATAN
Page 112
Air test ( air bersih ) m3 0.049
Bahan bakar liter 0.060
Oli liter 0.002 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Page 113
Mandor L.04 OH 0.0008 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Air test ( air bersih ) m3 0.158
Bahan bakar liter 0.060
Oli liter 0.002 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Page 114
RANGKUMAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
BIDANG CIPTA KARYA
TAHUN 2019
37 . 1 m3 Pondasi Footplat Beton mutu f'c = 19,3 Mpa, uk. 90x90 cm, tebal 25 cm, tul. Ф 12 mm - 15 cm 2,178,465.00
38 . 1 m3 Pondasi Footplat Beton mutu f'c = 19,3 Mpa, uk. 100x100 cm, tebal 25 cm, tul. Ф 12 mm - 15 cm 2,203,213.00
39 . 1 m3 Pondasi Footplat Beton mutu f'c = 19,3 Mpa, uk. 120x120 cm, t= 30 cm, tul. Ф 16 + Ф 12 mm - 15 cm 1,901,576.00
40 . 1 m3 Pondasi Footplat Beton mutu f'c = 19,3 Mpa, uk. 120x140 cm, t= 30 cm, tul. Ф 16 + Ф 12 mm - 15 cm 1,962,150.00
41 . 1 m3 Pondasi Footplat Beton mutu f'c = 19,3 Mpa, uk. 120x150 cm, t= 30 cm, tul. Ф 16 + Ф 12 mm - 15 cm 1,935,705.00
42 . 1 m3 Pondasi Footplat Beton mutu f'c = 19,3 Mpa, uk. 150x150 cm, t= 35 cm, tul. Ф 16 mm - 15 cm 2,753,828.00
43 . 1 m3 Sloof Beton mutu f'c = 14,5 Mpa, uk. 12x20 cm, tul. 4 Ф 12 mm, begel Ф 8 - 20 cm 3,918,036.00
44 . 1 m3 Sloof Beton mutu f'c = 14,5 Mpa, uk. 15x20 cm, tul. 4 Ф 12 mm, begel Ф 8 - 20 cm 3,365,641.00
45 . 1 m3 Sloof Beton mutu f'c = 19,3 Mpa, uk. 20x25 cm, tul. 6 Ф 16 mm, begel Ф 8 - 20 cm 4,018,232.00
46 . 1 m3 Sloof Beton mutu f'c = 19,3 Mpa, uk. 20x30 cm, tul. 6 Ф 16 mm, begel Ф 8 - 20 cm 3,609,745.00
47 . 1 m3 Sloof Beton mutu f'c = 19,3 Mpa, uk. 20x35 cm, tul. 6 Ф 16 mm, begel Ф 8 - 20 cm 3,317,968.00
48 . 1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 40x50 cm, tul. 18 Ф 16 mm, begel Ф 10 - 15 cm 4,098,575.00
49 . 1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 40x40 cm, tul. 16 Ф 16 mm, begel Ф 10 - 15 cm 4,437,789.00
50 . 1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 30x40 cm, tul. 14 Ф 16 mm, begel Ф 8 - 15 cm 4,789,480.00
51 . 1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 30x30 cm, tul. 10 Ф 16 mm, begel Ф 8 - 15 cm 4,904,944.00
KELOMPOK PEKERJA JENIS PEKERJAAN HARGA SATUAN
LEVEL 1 KET.
(LEVEL 2) (SUB LEVEL 2) (Rp)
52 . 1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 20x20 cm, tul. 8 Ф 12 mm, begel Ф 8 - 15 cm 5,815,366.00
53 . 1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 20x20 cm, tul. 4 Ф 12 mm, begel Ф 8 - 15 cm 4,752,343.00
54 . 1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 15x25 cm, tul. 6 Ф 12 mm, begel Ф 8 - 15 cm 4,179,654.00
55 . 1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 15x20 cm, tul. 4 Ф 12 mm, begel Ф 8 - 15 cm 4,030,541.00
56 . 1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 15x15 cm, tul. 4 Ф 12 mm, begel Ф 8 - 15 cm 4,726,929.00
57 . 1 m3 Kolom Praktis mutu f'c = 14,5 Mpa, uk. 11x11 cm, tul. 4 Ф 10 mm, begel Ф 6 - 20 cm 4,070,219.00
58 . 1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 30x60 cm, tul. 14 Ф 16 mm, begel Ф 10 - 12,5 cm 4,532,319.00
59 . 1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 25x55 cm, tul. 12 Ф 16 mm, begel Ф 10 - 12,5 cm 5,136,062.00
60 . 1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 25x50 cm, tul. 12 Ф 16 mm, begel Ф 10 - 12,5 cm 5,359,811.00
61 . 1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 20x40 cm, tul. 9 Ф 16 mm, begel Ф 8 - 17,5 cm 6,147,088.00
62 . 1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 20x35 cm, tul. 7 Ф 16 mm, begel Ф 8 - 17,5 cm 6,013,401.00
63 . 1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 20x30 cm, tul. 7 Ф 16 mm, begel Ф 8 - 17,5 cm 6,464,206.00
64 . 1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 15x35 cm, tul. 8 Ф 12 mm, begel Ф 8 - 17,5 cm 3,915,293.00
65 . 1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 15x30 cm, tul. 8 Ф 12 mm, begel Ф 8 - 17,5 cm 4,251,601.00
66 . 1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 15x25 cm, tul. 6 Ф 12 mm, begel Ф 8 - 17,5 cm 3,954,373.00
67 . 1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 15x20 cm, tul. 4 Ф 12 mm, begel Ф 8 - 17,5 cm 3,752,530.00
68 . 1 m3 Ring Balok Beton mutu f'c = 14,5 Mpa, uk. 12x20 cm, tul. 4 Ф 12 mm, begel Ф 6 - 20 cm 3,877,326.00
69 . 1 m3 Balok latei mutu f'c = 14,5 Mpa, uk. 12x15 cm, tul. 4 Ф 10 mm, begel Ф 6 - 20 cm 3,637,781.00
70 . 1 m3 Pelat Beton mutu f'c = 19,3 Mpa, tebal 15 cm, tul. Ф 10 - 15 cm 5,695,556.00
71 . 1 m3 Pelat Beton mutu f'c = 19,3 Mpa, tebal 12 cm, tul. Ф 10 - 15 cm 6,821,784.00
72 . 1 m3 Pelat Atap Beton mutu f'c = 19,3 Mpa, tebal 10 cm, tul. Ф 8 - 20 cm 6,806,158.00
73 . 1 m3 Pelat Beton Tutup Saluran mutu f'c = 14,5 Mpa, tebal 10 cm, tul. Ф 10 - 15 cm 2,689,010.00
4.1.2
Pekerjaan Beton Pracet 1 . A. 4.1.2.1. Pembuatan 1 m2 lahan produksi tebal 8 cm beton f'c = 14,5 Mpa (K175), slump (12 ± 2) cm 68,063.28
2 . A. 4.1.2.2. Pembuatan 1 m2 lahan produksi tebal 10 cm beton f'c = 14,5 Mpa (K175), slump (12 ± 2) cm 85,095.59
3 . A. 4.1.2.3. Pembuatan 1 m2 lahan produksi tebal 12 cm beton f'c = 14,5 Mpa (K175), slump (12 ± 2) cm 102,050.91
4 . A. 4.1.2.4. Pembuatan 1 m2 lahan produksi tebal 15 cm beton f'c = 14,5 Mpa (K175), slump (12 ± 2) cm 127,646.14
5 . A. 4.1.2.5. Pembuatan 1 m2 bekisting untuk plat beton pracetak ( 5 kali pakai ) 206,548.81
6 . A. 4.1.2.6. Pembuatan 1 m2 bekisting untuk balok beton pracetak ( 10 - 12 kali pakai ) 59,988.50
7 . A. 4.1.2.7. Pembuatan 1 m2 bekisting untuk kolom beton pracetak ( 10 - 12 kali pakai ) 54,351.00
8 . A. 4.1.2.8. Pemasangan dan membuka bekisting 1 buah komponen plat beton pracetak 5,810.75
9 . A. 4.1.2.9. Pemasangan dan membuka bekisting 1 buah komponen balok beton pracetak 9,440.75
10 . A. 4.1.2.10. Pemasangan dan membuka bekisting 1 buah komponen kolom beton pracetak 7,625.75
11 . A. 4.1.2.11. Penuangan/menebar beton untuk 1 buah komponen plat pracetak 43,741.50
12 . A. 4.1.2.12. Penuangan/menebar beton untuk 1 buah komponen balok pracetak 45,006.50
13 . A. 4.1.2.13. Penuangan/menebar beton untuk 1 buah komponen kolom pracetak 40,482.75
14 . A. 4.1.2.14. Mendirikan 1 buah komponen plat pracetak 767,133.40
15 . A. 4.1.2.15. Mendirikan 1 buah komponen balok pracetak 218,678.35
16 . A. 4.1.2.16. Mendirikan 1 buah komponen kolom pracetak 324,414.81
17 . A. 4.1.2.17. Melangsir 1 buah komponen plat pracetak ( ± 20 m ) 50,080.31
18 . A. 4.1.2.18. Melangsir 1 buah komponen balok pracetak ( ± 20 m ) 50,080.31
19 . A. 4.1.2.19. Melangsir 1 buah komponen kolom pracetak ( ± 20 m ) 50,080.31
20 . A. 4.1.2.20. Bahan 1 m3 grouting campuran 20,434,040.00
21 . A. 4.1.2.21. Bahan 1 m3 grouting tidak campuran 25,439,260.00
22 . A. 4.1.2.22. Upah melakukan 1 titik grouting pada join pracetak 38,832.75
23 . A. 4.1.2.23. Pemasangan 1 titik bekisting join pracetak 121,112.75
24 . A. 4.1.2.24. Upah 1 titik join dengan sling 36,602.50
4.2.1
Pekerjaan Besi & Alumi 1 . A. 4.2.1.1. Pemasangan 1 kg besi profil 23,329.63
2 . A. 4.2.1.2. Pemasangan 1 kg rangka kuda-kuda baja IWF 22,665.50
3 . A. 4.2.1.3. Pengerjaan 100 kg pekerjaan perakitan 113,770.25
4 . A. 4.2.1.4. Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku 711,807.25
5 . A. 4.2.1.5. Pembuatan 10 cm pengelasan dengan las listrik 43,923.00
6 . A. 4.2.1.6. Pembuatan 1 m2 rangka jendela besi scuare tube (25 x 5) cm 614,657.45
7 . A. 4.2.1.7. Pemasangan 1 m2 pintu rolling door besi 365,310.00
8 . A. 4.2.1.8. Pemasangan 1 m2 pintu lipat (folding gate) 821,447.00
9 . A. 4.2.1.9. Pemasangan 1 m2 sunscreen aluminium 148,412.00
10 . A. 4.2.1.10. Pemasangan 1 m2 rolling door aluminium 408,925.00
11 . A. 4.2.1.11. Pemasangan 1 m1 kusen pintu aluminium 178,982.38
12 . A. 4.2.1.12. Pemasangan 1 m2 pintu aluminium strip lebar 8 cm 1,615,861.23
13 . A. 4.2.1.13. Pemasangan 1 m2 pintu kaca rangka aluminium 713,022.75
14 . A. 4.2.1.14. Pemasangan 1 m2 venetions blinds dan vertical blinds 360,967.75
15 . A. 4.2.1.15. Pemasangan 1 m2 terali besi strip ( 2 x 3 ) mm 823,275.75
16 . A. 4.2.1.16. Pemasangan 1 m2 kawat nyamuk 258,692.50
17 . A. 4.2.1.17. Pemasangan 1 m2 jendela nako & tralis 310,434.67
18 . A. 4.2.1.18. Pemasangan 1 m1 talang datar/jurai seng bjls 28 lebar 90 cm 139,125.25
KELOMPOK PEKERJA JENIS PEKERJAAN HARGA SATUAN
LEVEL 1 KET.
(LEVEL 2) (SUB LEVEL 2) (Rp)
19 . A. 4.2.1.19. Pemasangan 1 m1 talang 1/2 lingkaran D - 15 c, seng plat bjls 30 lebar 45 cm 61,502.83
20 . A. 4.2.1.20. Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul 60 x 120 cm, dinding partisi 83,850.25
21 . A. 4.2.1.21. Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul 60 x 60 cm, plafon 105,217.75
A. 4.2.1.22 Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75 191,941.80
A. 4.2.1.22 Pemasangan 1 m2 atap jurai rangka atap baja canai dingin profil C75 215,166.44
A. 4.2.1.21.a Pemasangan 1 m2 Rangka atap baja ringan Main Truss C75 Reng 0,45, penutup atap
22 . 178,665.82
genteng tanah bentuk atap pelana
A. 4.2.1.21.a Pemasangan 1 m2 Rangka atap baja ringan Main Truss C75 Reng 0,45, penutup atap
23 . 185,514.05
genteng tanah bentuk atap limas
A. 4.2.1.21.a Pemasangan 1 m2 Rangka atap baja ringan Main Truss C75 Reng 0,45, penutup atap
24 . 151,306.46
genteng metal bentuk atap pelana
A. 4.2.1.21.a Pemasangan 1 m2 Rangka atap baja ringan Main Truss C75 Reng 0,45, penutup atap
25 . 156,362.72
genteng metal bentuk atap limas
4.4.1
Pekerjaan Dinding Pas 1 . A. 4.4.1.1. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu, camp. 1 SP : 2PP 273,116.25
2 . A. 4.4.1.2. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu, camp. 1 SP : 3PP 262,238.63
3 . A. 4.4.1.3. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu, camp. 1 SP : 4PP 254,714.63
4 . A. 4.4.1.4. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu, camp. 1 SP : 5PP 251,138.25
5 . A. 4.4.1.5. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu, camp. 1 SP : 6PP 250,494.75
6 . A. 4.4.1.6. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu, camp. 1 SP : 3KP : 10PP 238,393.38
7 . A. 4.4.1.7. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 2PP 132,697.13
8 . A. 4.4.1.8. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 3PP 127,425.38
9 . A. 4.4.1.9. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 4PP 124,467.75
10 . A. 4.4.1.10. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 5PP 122,611.50
11 . A. 4.4.1.11. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 6PP 121,720.50
12 . A. 4.4.1.12. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 8PP 119,666.25
13 . A. 4.4.1.13. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 3KP : 10PP 119,460.00
14 . A. 4.4.1.14. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SM : 1KP : 1PP 108,031.28
15 . A. 4.4.1.15. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SM : 1KP : 2PP 114,466.00
16 . A. 4.4.1.16. Pemasangan 1 m2 dinding conblock HB 20, camp. 1 SP : 3PP 300,874.75
17 . A. 4.4.1.17. Pemasangan 1 m2 dinding conblock HB 20, camp. 1 SP : 4PP 302,087.50
18 . A. 4.4.1.18. Pemasangan 1 m2 dinding conblock HB 15, camp. 1 SP : 3PP 273,886.25
19 . A. 4.4.1.19. Pemasangan 1 m2 dinding conblock HB 15, camp. 1 SP : 4PP 274,604.00
20 . A. 4.4.1.20. Pemasangan 1 m2 dinding conblock HB 10, camp. 1 SP : 3PP 224,339.50
21 . A. 4.4.1.21. Pemasangan 1 m2 dinding conblock HB 10, camp. 1 SP : 4PP 225,341.88
22 . A. 4.4.1.22. Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 cm, camp. 1 SP : 3PP 52,965.00
23 . A. 4.4.1.23. Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 cm, camp. 1 SP : 4PP 52,965.00
24 . A. 4.4.1.24. Pemasangan 1 m2 dinding bata berongga ekspose 12x11x24 cm, camp. 1 SP : 3PP 197,557.25
25 . A. 4.4.1.25. Pemasangan 1 m2 dinding bata ringan dengan Semen Instan 135,993.00
26 . Pemasangan 1 m2 batu tempel
4.4.2
Pekerjaan Plesteran 1 . A. 4.4.2.1. Pemasangan 1 m2 plesteran 1SP : 1PP tebal 15 mm 59,190.45
2 . A. 4.4.2.2. Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm 53,448.45
3 . A. 4.4.2.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15 mm 51,013.05
4 . A. 4.4.2.4. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm 49,310.25
5 . A. 4.4.2.5.Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm 48,399.45
6 . A. 4.4.2.6.Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm 47,647.05
7 . A. 4.4.2.7.Pemasangan 1 m2 plesteran 1SP : 7PP tebal 15 mm 47,251.05
8 . A. 4.4.2.8.Pemasangan 1 m2 plesteran 1SP : 8PP tebal 15 mm 46,855.05
9 . A. 4.4.2.9.Pemasangan 1 m2 plesteran 1SP : 1/2KP :3PP tebal 15 mm 49,062.75
10 . A. 4.4.2.10.Pemasangan 1 m2 plesteran 1SP : 2KP :8PP tebal 15 mm 47,335.75
11 . A. 4.4.2.11.Pemasangan 1 m2 plesteran 1SM : 1KP :1PP tebal 15 mm 45,317.25
12 . A. 4.4.2.12.Pemasangan 1 m2 plesteran 1SM : 1KP :2PP tebal 15 mm 45,476.75
13 . A. 4.4.2.13.Pemasangan 1 m2 plesteran 1SP: 1PP tebal 20 mm 71,506.60
14 . A. 4.4.2.14.Pemasangan 1 m2 plesteran 1SP: 3PP tebal 20 mm 57,072.40
15 . A. 4.4.2.15.Pemasangan 1 m2 plesteran 1SP: 4PP tebal 20 mm 65,923.00
16 . A. 4.4.2.16.Pemasangan 1 m2 plesteran 1SP: 5PP tebal 20 mm 64,774.60
17 . A. 4.4.2.17.Pemasangan 1 m2 plesteran 1SP: 6PP tebal 20 mm 63,705.40
18 . A. 4.4.2.18.Pemasangan 1 m2 plesteran 1SM : 1KP :2PP tebal 20 mm 62,218.75
19 . A. 4.4.2.19.Pemasangan 1 m2 berapen 1SP : 5PP tebal 15 mm 30,067.95
20 . A. 4.4.2.20. Pemasangan 1 m1 plesteran skoning 1SP : 3PP lebar 10mm 14,931.58
21 . A. 4.4.2.21.Pemasangan 1 m2 plesteran granit 1SP : 2 granit tebal 1cm 113,091.00
22 . A. 4.4.2.22.Pemasangan 1 m2 plesteran traso 1SP : 2 traso tebal 1cm 113,091.00
23 . A. 4.4.2.23.Pemasangan 1 m2 plesteran ciprat 1SP : 2 PP 38,956.50
24 . A. 4.4.2.24.Pemasangan 1 m2 finishing siar pasangan bata merah 22,350.90
KELOMPOK PEKERJA JENIS PEKERJAAN HARGA SATUAN
LEVEL 1 KET.
(LEVEL 2) (SUB LEVEL 2) (Rp)
25 . A. 4.4.2.25.Pemasangan 1 m2 finishing siar pasangan conblock ekspose 10,661.75
26 . A. 4.4.2.26. Pemasangan 1 m2 finishing siar pasangan batu kali 1SP : 2PP 47,058.00
27 . A. 4.4.2.27. Pemasangan 1 m2 acian 28,579.38
28 . A. 4.4.2.28. Pemasangan 1 m2 plesteran semen Instan 60,397.70
29 . A. 4.4.2.29. Pemasangan 1 m2 Acian semen Instan 30,085.00
30 . A. 4.4.2.30. Pemasangan 1 m1 Sponengan 20,575.50
4.4.3
Pekerjaan Penutup
lantai & Penutup
1 . A. 4.4.3.1. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 40cm x 40cm 144,806.75
dinding
2 . A. 4.4.3.2. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 30cm x30cm 112,961.60
3 . A. 4.4.3.3. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 20cm x20cm 128,127.45
4 . A. 4.4.3.4. Pemasangan 1 m2 lantai ubin warna ukuran 40cm x40cm 154,574.75
5 . A. 4.4.3.5. Pemasangan 1 m2 lantai ubin warna ukuran 30cm x30cm 127,906.65
6 . A. 4.4.3.6. Pemasangan 1 m2 lantai ubin warna ukuran 20cm x20cm 144,407.45
7 . A. 4.4.3.7. Pemasangan 1 m2 lantai ubin traso ukuran 40cm x40cm -
8 . A. 4.4.3.8. Pemasangan 1 m2 lantai ubin traso ukuran 30cm x30cm -
9 . A. 4.4.3.9. Pemasangan 1 m2 lantai ubin granit ukuran 40cm x40cm -
10 . A. 4.4.3.10. Pemasangan 1 m2 lantai ubin granit ukuran 30cm x30cm -
11 . A. 4.4.3.11. Pemasangan 1 m2 lantai ubin teralux marmer ukuran 40cm x40cm -
12 . A. 4.4.3.12. Pemasangan 1 m2 lantai ubin teralux marmer ukuran 30cm x30cm -
13 . A. 4.4.3.13. Pemasangan 1 m2 lantai hemogenus tile ukuran 60cm x60cm 273,595.67
14 . A. 4.4.3.14. Pemasangan 1 m2 lantai ubin teralux marmer ukuran 40cm x40cm -
15 . A. 4.4.3.15. Pemasangan 1 m2 lantai ubin teralux marmer ukuran 30cm x30cm -
16 . A. 4.4.3.16. Pemasangan 1 m1plint ubin PC abu-abu ukuran 15cm x20cm -
17 . A. 4.4.3.17. Pemasangan 1 m1 plint ubin PC abu-abu ukuran 10cm x30cm -
18 . A. 4.4.3.18. Pemasangan 1 m1 plint ubin PC abu-abu ukuran 10cm x40cm -
19 . A. 4.4.3.19. Pemasangan 1 m1 plint ubin warna ukuran 10cm x20cm -
20 . A. 4.4.3.20. Pemasangan 1 m1 plint ubin warna ukuran 10cm x30cm -
21 . A. 4.4.3.21. Pemasangan 1 m1 plint ubin warna ukuran 10cm x40cm -
22 . A. 4.4.3.22. Pemasangan 1 m1 plint ubin teraso ukuran 10cm x30cm -
23 . A. 4.4.3.23. Pemasangan 1 m1 plint ubin teraso ukuran 10cm x40cm -
24 . A. 4.4.3.24. Pemasangan 1 m1 plint ubin granit ukuran 10cm x40cm -
25 . A. 4.4.3.25. Pemasangan 1 m1 plint ubin granit ukuran 10cm x30cm -
26 . A. 4.4.3.26. Pemasangan 1 m1 plint ubin teralux kerang ukuran 10cm x40cm -
27 . A. 4.4.3.27. Pemasangan 1 m1 plint ubin teralux kerang ukuran 10cm x30cm -
28 . A. 4.4.3.28. Pemasangan 1 m1 plint ubin teralux marmer ukuran 10cm x60cm -
29 . A. 4.4.3.29. Pemasangan 1 m1 plint ubin teralux marmer ukuran 10cm x40cm -
30 . A. 4.4.3.30. Pemasangan 1 m1 plint ubin teralux marmer ukuran 10cm x30cm -
31 . A. 4.4.3.31. Pemasangan 1 m2 lantai teraso cor di tempat, tebal 3cm -
32 . A. 4.4.3.32. Pemasangan 1 m2 lantai keramik artistik 10cm x20cm -
33 . A. 4.4.3.33. Pemasangan 1 m2 lantai keramik artistik 10cm x10cm atau 5cm x 20cm -
34 . A. 4.4.3.34. Pemasangan 1 m2 lantai keramik ukuran 40cm x 40cm 200,911.15
35 . A. 4.4.3.34. Pemasangan 1 m2 lantai keramik ukuran 33cm x 33cm 238,222.88
36 . A. 4.4.3.35. Pemasangan 1 m2 lantai keramik ukuran 30cm x 30cm 168,044.25
37 . A. 4.4.3.35. Pemasangan 1 m2 lantai keramik anti slip ukuran 30cm x 30cm 208,573.85
38 . A. 4.4.3.36. Pemasangan 1 m2 lantai hemogenus tile 25 x 25 cm unpolish 209,572.00
5.1.1
Divisi 5
Pekerjaan Sanitasi Ged 1 . A. 5.1.1.1. Pemasangan 1 buah clooset duduk / monoblok 2,341,542.50
2 . A. 5.1.1.2. Pemasangan 1 buah clooset jongkok porslin 1,021,322.50
3 . A. 5.1.1.3. Pemasangan 1 buah clooset jongkok teraso 728,997.50
4 . A. 5.1.1.3. Pemasangan 1 buah clooset jongkok teraso -
5 . A. 5.1.1.4. Pemasangan 1 buah urinoir 1,391,830.00
6 . A. 5.1.1.5. Pemasangan 1 buah wastafel 671,440.00
7 . A. 5.1.1.6. Pemasangan 1 buah bathcuip porselin -
8 . A. 5.1.1.7. Pemasangan 1 buah bak fiberglass vol 1m3 -
9 . A. 5.1.1.8. Pemasangan 1 buah bak mandi batu bata vol 0,30 m3 1,411,377.00
10 . A. 5.1.1.9. Pemasangan 1 buah bak mandi teraso vol 0,30 m3 -
11 . A. 5.1.1.10. Pemasangan 1 buah bak air fiberglass vol 1 m3 -
KELOMPOK PEKERJA JENIS PEKERJAAN HARGA SATUAN
LEVEL 1 KET.
(LEVEL 2) (SUB LEVEL 2) (Rp)
12 . A. 5.1.1.11. Pemasangan 1 buah bak beton volume 1 m3 -
13 . A. 5.1.1.12. Pemasangan 1 buah bak cuci piring stainlessteel 1,084,737.50
14 . A. 5.1.1.13. Pemasangan 1 buah bak cuci piring teraso -
15 . A. 5.1.1.14. Pemasangan 1 buah floor drain 37,510.00
16 . A. 5.1.1.15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm 377,476.00
17 . A. 5.1.1.16. Pemasangan 1 buah bak kontrol pasangan bata 45x45 tinggi 50 cm 570,385.75
18 . A. 5.1.1.17. Pemasangan 1 buah bak kontrol pasangan bata 60x60 tinggi 65 cm 710,696.25
19 . A. 5.1.1.18. Pemasangan 1 m' pipa galvanis diameter 1/2" 43,485.75
20 . A. 5.1.1.19. Pemasangan 1 buah kran diameter 1/2" atau 3/4" 64,061.25
21 . A. 5.1.1.20. Pemasangan 1 m' pipa galvanis diameter 3/4" 51,584.50
22 . A. 5.1.1.21. Pemasangan 1 m' pipa galvanis diameter 1" 59,683.25
23 . A. 5.1.1.22. Pemasangan 1 m' pipa galvanis diameter 1 1/2" 97,237.25
24 . A. 5.1.1.23. Pemasangan 1 m' pipa galvanis diameter 3" 154,781.92
25 . A. 5.1.1.24. Pemasangan 1 m' pipa galvanis diameter 4" 160,124.25
26 . A. 5.1.1.25. Pemasangan 1 m' pipa PVC tipe AW diameter 1/2" 18,801.75
27 . A. 5.1.1.26. Pemasangan 1 m' pipa PVC tipe AW diameter 3/4" 23,661.00
28 . A. 5.1.1.27. Pemasangan 1 m' pipa PVC tipe AW diameter 1" 27,582.50
29 . A. 5.1.1.28. Pemasangan 1 m' pipa PVC tipe AW diameter 1 1/2" 46,233.00
30 . A. 5.1.1.28. Pemasangan 1 m' pipa PVC tipe D diameter 1 1/2" 30,973.25
31 . A. 5.1.1.29. Pemasangan 1 m' pipa PVC tipe AW diameter 2" 55,951.50
32 . A. 5.1.1.29. Pemasangan 1 m' pipa PVC tipe D diameter 2" 38,944.13
33 . A. 5.1.1.30. Pemasangan 1 m' pipa PVC tipe AW diameter 2 1/2" 67,984.13
34 . A. 5.1.1.30. Pemasangan 1 m' pipa PVC tipe D diameter 2 1/2" 49,229.13
35 . A. 5.1.1.31. Pemasangan 1 m' pipa PVC tipe AW diameter 3" 105,749.88
36 . A. 5.1.1.31. Pemasangan 1 m' pipa PVC tipe D diameter 3" 45,009.25
37 . A. 5.1.1.32. Pemasangan 1 m' pipa PVC tipe AW diameter 4" 164,060.88
38 . A. 5.1.1.32. Pemasangan 1 m' pipa PVC tipe D diameter 4" 91,172.13
39 . A. 5.1.1.33. Pemasangan 1 m' pipa air limbah jenis pipa tanah diameter 20 cm -
40 . A. 5.1.1.34. Pemasangan 1 m' pipa air limbah jenis pipa tanah diameter 15 cm -
41 . A. 5.1.1.35. Pemasangan 1 m' pipa beton diameter 15 - 20 cm -
42 . A. 5.1.1.36. Pemasangan 1 m' pipa beton diameter 30 - 100 cm -
43 . A. 5.1.1.37. Pemasangan 1 buah Roof Drain 81,510.00
6.1.1
Divisi 6
Pekerjaan ME 1 . A. 6.1.1.1. Pemasangan 1 titik Stop kontak 148,060.00
2 . A. 6.1.1.2. Pemasangan 1 titik Saklar tunggal 107,937.50
3 . A. 6.1.1.3. Pemasangan 1 titik Saklar ganda 131,037.50
4 . A. 6.1.1.4. Pemasangan 1 buah Lampu TL 20 watt 63,263.75
5 . A. 6.1.1.5. Pemasangan 1 buah Lampu SL 18 watt 64,913.75
Pemasangan 1 buah Lampu SLED 23 watt 174,913.75
6 . A. 6.1.1.6. Pemasangan 1 buah Lampu Pijar 25 watt 31,913.75
7 . A. 6.1.1.7. Pemasangan 1 buah Box Panel Fuse + MCB (2x450 VA) 445,926.25
8 . Pemasangan Listrik Baru 15,000,000.00
7.1.1
Divisi 7
Pekerjaan Landscape 1 . A. 7.1.1.1. Pemasangan 1 m1 got U - 20 cm 102,516.44
2 . A. 7.1.1.2. Pemasangan 1 m1 got U - 25 cm 104,716.44
3 . A. 7.1.1.3. Pemasangan 1 m1 got U - 30 cm 106,916.44
4 . A. 7.1.1.4. Pemasangan 1 m2 paving blok, tebal 6 cm 142,374.10
5 . A. 7.1.1.5. Pemasangan 1 m2 paving blok Press, tebal 8 cm 165,198.00
8.4.1
Divisi 8
Pekerjaan Pemasangan 1 . A. 8.4.1.1. Pemasangan 1 m pipa PVC Ø 63 mm (AW) -
2 . A. 8.4.1.2. Pemasangan 1 m Pipa PVC Æ 90 mm (AW) -
3 . A. 8.4.1.3. Pemasangan 1 m pipa PVC Ø 110 mm (AW) -
4 . A. 8.4.1.4. Pemasangan 1 m pipa PVC Ø 150 mm -
5 . A. 8.4.1.5. Pemasangan 1 m pipa PVC Ø 200 mm -
6 . A. 8.4.1.6. Pemasangan 1 m pipa PVC Ø 250 mm -
7 . A. 8.4.1.7. Pemasangan 1 m pipa PVC Ø 300 mm -
8 . A. 8.4.1.8. Pemasangan 1 m pipa PVC Ø 400 mm -
9 . A. 8.4.1.9. Pemasangan 1 m pipa PVC Ø 450 mm -
10 . A. 8.4.1.10. Pemasangan 1 m pipa PVC Ø 500 mm -
11 . A. 8.4.1.11. Pemasangan 1 m pipa PVC Ø 600 mm -
12 . A. 8.4.1.12. Pemasangan 1 m pipa PVC Ø 800 mm -
13 . A. 8.4.1.13. Pemasangan 1 m pipa PVC Ø 900 mm -
14 . A. 8.4.1.14. Pemasangan 1 m pipa PVC Ø 1000 mm -
15 . A. 8.4.1.15. Pemasangan 1 m pipa PVC Ø 1100 mm -
KELOMPOK PEKERJA JENIS PEKERJAAN HARGA SATUAN
LEVEL 1 KET.
(LEVEL 2) (SUB LEVEL 2) (Rp)
16 . A. 8.4.1.16. Pemasangan 1 m pipa PVC Ø 1200 mm -
17 . A. 8.4.1.17. Pemasangan 1 m pipa HDPE Ø 63 mm -
18 . A. 8.4.1.18. Pemasangan 1 m pipa HDPE Ø 100 mm -
19 . A. 8.4.1.19. Pemasangan 1 m pipa HDPE Ø 125 mm -
20 . A. 8.4.1.20. Pemasangan 1 m pipa HDPE Ø 150 mm -
21 . A. 8.4.1.21. Pemasangan 1 m pipa HDPE Ø 200 mm -
22 . A. 8.4.1.22. Pemasangan 1 m pipa HDPE Ø 250 mm -
23 . A. 8.4.1.23. Pemasangan 1 m pipa HDPE Ø 300 mm -
24 . A. 8.4.1.24. Pemasangan 1 m pipa HDPE Ø 400 mm -
25 . A. 8.4.1.25. Pemasangan 1 m pipa HDPE Ø 450 mm -
26 . A. 8.4.1.26. Pemasangan 1 m pipa HDPE Ø 500 mm -
27 . A. 8.4.1.27. Pemasangan 1 m pipa HDPE Ø 600 mm -
28 . A. 8.4.1.28. Pemasangan 1 m pipa HDPE Ø 800 mm -
29 . A. 8.4.1.29. Pemasangan 1 m pipa HDPE Ø 900 mm -
30 . A. 8.4.1.30. Pemasangan 1 m pipa HDPE Ø 1000 mm -
31 . A. 8.4.1.31. Pemasangan 1 m pipa HDPE Ø 1100 mm -
32 . A. 8.4.1.32. Pemasangan 1 m pipa HDPE Ø 1200 mm -
33 . A. 8.4.1.33. Pemasangan 1 m pipa GIP Ø 63 mm -
34 . A. 8.4.1.34. Pemasangan 1 m pipa GIP Ø 100 mm -
35 . A. 8.4.1.35. Pemasangan 1 m pipa GIP Ø 125 mm -
36 . A. 8.4.1.36. Pemasangan 1 m pipa GIP Ø 150 mm -
37 . A. 8.4.1.37. Pemasangan 1 m pipa GIP Ø 200 mm -
38 . A. 8.4.1.38. Pemasangan 1 m pipa GIP Ø 250 mm -
39 . A. 8.4.1.39. Pemasangan 1 m pipa GIP Ø 300 mm -
40 . A. 8.4.1.40. Pemasangan 1 m pipa GIP Ø 400 mm -
41 . A. 8.4.1.41. Pemasangan 1 m pipa GIP Ø 450 mm -
42 . A. 8.4.1.42. Pemasangan 1 m pipa GIP Ø 500 mm -
43 . A. 8.4.1.43. Pemasangan 1 m pipa GIP Ø 600 mm -
44 . A. 8.4.1.44. Pemasangan 1 m pipa GIP Ø 800 mm -
45 . A. 8.4.1.45. Pemasangan 1 m pipa GIP Ø 900 mm -
46 . A. 8.4.1.46. Pemasangan 1 m pipa GIP Ø 1000 mm -
47 . A. 8.4.1.48. Pemasangan 1 m pipa GIP Ø 1200 mm -
48 . A. 8.4.1.49. Pemasangan 1 m pipa DCI Ø 100 mm -
49 . A. 8.4.1.50. Pemasangan 1 m pipa DCI Ø 125 mm -
50 . A. 8.4.1.51. Pemasangan 1 m pipa DCI Ø 150 mm -
51 . A. 8.4.1.52. Pemasangan 1 m pipa DCI Ø 200 mm -
52 . A. 8.4.1.53. Pemasangan 1 m pipa DCI Ø 250 mm -
53 . A. 8.4.1.54. Pemasangan 1 m pipa DCI Ø 300 mm -
54 . A. 8.4.1.55. Pemasangan 1 m pipa DCI Ø 400 mm -
55 . A. 8.4.1.56. Pemasangan 1 m pipa DCI Ø 450 mm -
56 . A. 8.4.1.57. Pemasangan 1 m pipa DCI Ø 500 mm -
57 . A. 8.4.1.58. Pemasangan 1 m pipa DCI Ø 600 mm -
58 . A. 8.4.1.59. Pemasangan 1 m pipa DCI Ø 800 mm -
59 . A. 8.4.1.60. Pemasangan 1 m pipa DCI Ø 900 mm -
60 . A. 8.4.1.61. Pemasangan 1 m pipa DCI Ø 1000 mm -
61 . A. 8.4.1.62. Pemasangan 1 m pipa DCI Ø 1100 mm -
62 . A. 8.4.1.63. Pemasangan 1 m pipa DCI Ø 1200 mm -
63 . A. 8.4.1.64. Pemasangan 1 m pipa baja Ø 63 mm -
64 . A. 8.4.1.65. Pemasangan 1 m pipa baja Ø 100 mm -
65 . A. 8.4.1.66. Pemasangan 1 m pipa baja Ø 125 mm -
66 . A. 8.4.1.67. Pemasangan 1 m pipa baja Ø 150 mm -
67 . A. 8.4.1.68. Pemasangan 1 m pipa baja Ø 200 mm -
68 . A. 8.4.1.69. Pemasangan 1 m pipa baja Ø 250 mm -
69 . A. 8.4.1.70. Pemasangan 1 m pipa baja Ø 300 mm -
70 . A. 8.4.1.71. Pemasangan 1 m pipa baja Ø 400 mm -
71 . A. 8.4.1.72. Pemasangan 1 m pipa baja Ø 450 mm -
72 . A. 8.4.1.73. Pemasangan 1 m pipa baja Ø 500 mm -
73 . A. 8.4.1.74. Pemasangan 1 m pipa baja Ø 600 mm -
74 . A. 8.4.1.75. Pemasangan 1 m pipa baja Ø 800 mm -
75 . A. 8.4.1.76. Pemasangan 1 m pipa baja Ø 900 mm -
76 . A. 8.4.1.77. Pemasangan 1 m pipa baja Ø 1000 mm -
77 . A. 8.4.1.78. Pemasangan 1 m pipa baja Ø 1100 mm -
78 . A. 8.4.1.79. Pemasangan 1 m pipa baja Ø 1200 mm -
8.4.2
Pekerjaan Pemotongan 1 . A. 8.4.2.1. Pemotongan 1 buah pipa PVC Ø 63 mm -
2 . A. 8.4.2.2. Pemotongan 1 buah pipa PVC Ø 90 mm -
KELOMPOK PEKERJA JENIS PEKERJAAN HARGA SATUAN
LEVEL 1 KET.
(LEVEL 2) (SUB LEVEL 2) (Rp)
3 . A. 8.4.2.3. Pemotongan 1 buah pipa PVC Ø 110 mm -
4 . A. 8.4.2.4. Pemotongan 1 buah pipa PVC Ø 150 mm -
5 . A. 8.4.2.5. Pemotongan 1 buah pipa PVC Ø 200 mm -
6 . A. 8.4.2.6. Pemotongan 1 buah pipa PVC Ø 250 mm -
7 . A. 8.4.2.7. Pemotongan 1 buah pipa PVC Ø 300 mm -
8 . A. 8.4.2.8. Pemotongan 1 buah pipa PVC Ø 400 mm -
9 . A. 8.4.2.9. Pemotongan 1 buah pipa PVC Ø 450 mm -
10 . A. 8.4.2.10. Pemotongan 1 buah pipa PVC Ø 500 mm -
11 . A. 8.4.2.11. Pemotongan 1 buah pipa PVC Ø 600 mm -
12 . A. 8.4.2.12. Pemotongan 1 buah pipa PVC Ø 800 mm -
13 . A. 8.4.2.13. Pemotongan 1 buah pipa PVC Ø 900 mm -
14 . A. 8.4.2.14. Pemotongan 1 buah pipa PVC Ø 1000 mm -
15 . A. 8.4.2.15. Pemotongan 1 buah pipa PVC Ø 1100 mm -
16 . A. 8.4.2.16. Pemotongan 1 buah pipa PVC Ø 1200 mm -
17 . A. 8.4.2.17. Pemotongan 1 buah pipa HDPE Ø 63 mm -
18 . A. 8.4.2.18. Pemotongan 1 buah pipa HDPE Ø 100 mm -
19 . A. 8.4.2.19. Pemotongan 1 buah pipa HDPE Ø 125 mm -
20 . A. 8.4.2.20. Pemotongan 1 buah pipa HDPE Ø 150 mm -
21 . A. 8.4.2.21. Pemotongan 1 buah pipa HDPE Ø 200 mm -
22 . A. 8.4.2.22. Pemotongan 1 buah pipa HDPE Ø 250 mm -
23 . A. 8.4.2.23. Pemotongan 1 buah pipa HDPE Ø 300 mm -
24 . A. 8.4.2.24. Pemotongan 1 buah pipa HDPE Ø 400 mm -
25 . A. 8.4.2.25. Pemotongan 1 buah pipa HDPE Ø 450 mm -
26 . A. 8.4.2.26. Pemotongan 1 buah pipa HDPE Ø 500 mm -
27 . A. 8.4.2.27. Pemotongan 1 buah pipa HDPE Ø 600 mm -
28 . A. 8.4.2.28. Pemotongan 1 buah pipa HDPE Ø 800 mm -
29 . A. 8.4.2.29. Pemotongan 1 buah pipa HDPE Ø 900 mm -
30 . A. 8.4.2.30. Pemotongan 1 buah pipa HDPE Ø 1000 mm -
31 . A. 8.4.2.31. Pemotongan 1 buah pipa HDPE Ø 1100 mm -
32 . A. 8.4.2.32. Pemotongan 1 buah pipa HDPE Ø 1200 mm -
33 . A. 8.4.2.33. Pemotongan 1 buah pipa GIP Ø 63 mm -
34 . A. 8.4.2.34. Pemotongan 1 buah pipa GIP Ø 100 mm -
35 . A. 8.4.2.35. Pemotongan 1 buah pipa GIP Ø 125 mm -
36 . A. 8.4.2.36. Pemotongan 1 buah pipa GIP Ø 150 mm -
37 . A. 8.4.2.37. Pemotongan 1 buah pipa GIP Ø 200 mm -
38 . A. 8.4.2.38. Pemotongan 1 buah pipa GIP Ø 250 mm -
39 . A. 8.4.2.39. Pemotongan 1 buah pipa GIP Ø 300 mm -
40 . A. 8.4.2.40. Pemotongan 1 buah pipa GIP Ø 400 mm -
41 . A. 8.4.2.41. Pemotongan 1 buah pipa GIP Ø 450 mm -
42 . A. 8.4.2.42. Pemotongan 1 buah pipa GIP Ø 500 mm -
43 . A. 8.4.2.43. Pemotongan 1 buah pipa GIP Ø 600 mm -
44 . A. 8.4.2.44. Pemotongan 1 buah pipa GIP Ø 800 mm -
45 . A. 8.4.2.45. Pemotongan 1 buah pipa GIP Ø 900 mm -
46 . A. 8.4.2.46. Pemotongan 1 buah pipa GIP Ø 1000 mm -
47 . A. 8.4.2.47. Pemotongan 1 buah pipa GIP Ø 1100 mm -
48 . A. 8.4.2.48. Pemotongan 1 buah pipa GIP Ø 1200 mm -
49 . A. 8.4.2.49. Pemotongan 1 buah pipa DCI Ø 100 mm -
50 . A. 8.4.2.50. Pemotongan 1 buah pipa DCI Ø 125 mm -
51 . A. 8.4.2.51. Pemotongan 1 buah pipa DCI Ø 150 mm -
52 . A. 8.4.2.52. Pemotongan 1 buah pipa DCI Ø 200 mm -
53 . A. 8.4.2.53. Pemotongan 1 buah pipa DCI Ø 250 mm -
54 . A. 8.4.2.54. Pemotongan 1 buah pipa DCI Ø 300 mm -
55 . A. 8.4.2.55. Pemotongan 1 buah pipa DCI Ø 400 mm -
56 . A. 8.4.2.56. Pemotongan 1 buah pipa DCI Ø 450 mm -
57 . A. 8.4.2.57. Pemotongan 1 buah pipa DCI Ø 500 mm -
58 . A. 8.4.2.58. Pemotongan 1 buah pipa DCI Ø 600 mm -
59 . A. 8.4.2.59. Pemotongan 1 buah pipa DCI Ø 800 mm -
60 . A. 8.4.2.60. Pemotongan 1 buah pipa DCI Ø 900 mm -
61 . A. 8.4.2.61. Pemotongan 1 buah pipa DCI Ø 1000 mm -
62 . A. 8.4.2.62. Pemotongan 1 buah pipa DCI Ø 1100 mm -
63 . A. 8.4.2.63. Pemotongan 1 buah pipa DCI Ø 1200 mm -
64 . A. 8.4.2.64. Pemotongan 1 buah pipa baja Ø 63 mm -
65 . A. 8.4.2.65. Pemotongan 1 buah pipa baja Ø 100 mm -
66 . A. 8.4.2.66. Pemotongan 1 buah pipa baja Ø 125 mm -
67 . A. 8.4.2.67. Pemotongan 1 buah pipa baja Ø 150 mm -
68 . A. 8.4.2.68. Pemotongan 1 buah pipa baja Ø 200 mm -
KELOMPOK PEKERJA JENIS PEKERJAAN HARGA SATUAN
LEVEL 1 KET.
(LEVEL 2) (SUB LEVEL 2) (Rp)
69 . A. 8.4.2.69. Pemotongan 1 buah pipa baja Ø 250 mm -
70 . A. 8.4.2.70. Pemotongan 1 buah pipa baja Ø 300 mm -
71 . A. 8.4.2.71. Pemotongan 1 buah pipa baja Ø 400 mm -
72 . A. 8.4.2.72. Pemotongan 1 buah pipa baja Ø 450 mm -
73 . A. 8.4.2.73. Pemotongan 1 buah pipa baja Ø 500 mm -
74 . A. 8.4.2.74. Pemotongan 1 buah pipa baja Ø 600 mm -
75 . A. 8.4.2.75. Pemotongan 1 buah pipa baja Ø 800 mm -
76 . A. 8.4.2.76. Pemotongan 1 buah pipa baja Ø 900 mm -
77 . A. 8.4.2.77. Pemotongan 1 buah pipa baja Ø 1000 mm -
78 . A. 8.4.2.78. Pemotongan 1 buah pipa baja Ø 1100 mm -
79 . A. 8.4.2.79. Pemotongan 1 buah pipa baja Ø 1200 mm -
8.4.3
Pekerjaan Aksesoris Pi 1 . A. 8.4.3.1. Pemasangan 1 Buah Valve Æ 150 MM -
2 . A. 8.4.3.2. Pemasangan 1 Buah Valve Æ 200 MM -
3 . A. 8.4.3.3. Pemasangan 1 Buah Valve Æ 250 MM -
4 . A. 8.4.3.4. Pemasangan 1 Buah Valve Æ 300 MM -
5 . A. 8.4.3.5. Pemasangan 1 Buah Valve Æ 400 MM -
6 . A. 8.4.3.6. Pemasangan 1 Buah Valve Æ 450 MM -
7 . A. 8.4.3.7. Pemasangan 1 Buah Valve Æ 500 MM -
8 . A. 8.4.3.8. Pemasangan 1 Buah Valve Æ 600 MM -
9 . A. 8.4.3.9. Pemasangan 1 Buah Valve Æ 700 MM -
10 . A. 8.4.3.10. Pemasangan 1 Buah Valve Æ 800 MM -
11 . A. 8.4.3.11. Pemasangan 1 Buah Valve Æ 900 MM -
12 . A. 8.4.3.12. Pemasangan 1 Buah Valve Æ 1000 MM -
13 . A. 8.4.3.13. Pemasangan 1 Buah Valve Æ 1100 MM -
14 . A. 8.4.3.14. Pemasangan 1 Buah Valve Æ 1200 MM -
15 . A. 8.4.3.15. Pemasangan 1 Buah Tee Æ 150 MM -
16 . A. 8.4.3.16. Pemasangan 1 Buah Tee Æ 200 MM -
17 . A. 8.4.3.17. Pemasangan 1 Buah Tee Æ 250 MM -
18 . A. 8.4.3.18. Pemasangan 1 Buah Tee Æ 300 MM -
19 . A. 8.4.3.19. Pemasangan 1 Buah Tee Æ 400 MM -
20 . A. 8.4.3.20. Pemasangan 1 Buah Tee Æ 450 MM -
21 . A. 8.4.3.21. Pemasangan 1 Buah Tee Æ 500 MM -
22 . A. 8.4.3.22. Pemasangan 1 Buah Tee Æ 600 MM -
23 . A. 8.4.3.23. Pemasangan 1 Buah Tee Æ 700 MM -
24 . A. 8.4.3.24. Pemasangan 1 Buah Tee Æ 800 MM -
25 . A. 8.4.3.25. Pemasangan 1 Buah Tee Æ 900 MM -
26 . A. 8.4.3.26. Pemasangan 1 Buah Tee Æ 1000 MM -
27 . A. 8.4.3.27. Pemasangan 1 Buah Tee Æ 1100 MM -
28 . A. 8.4.3.28. Pemasangan 1 Buah Tee Æ 1200 MM -
8.4.4
Pekerjaan Penyambung 1 . A. 8.4.4.1. Penyambungan 1 buah pipa baru ke pipa yang ada Ø 80 mm -
2 . A. 8.4.4.2. Penyambungan 1 buah pipa baru ke pipa yang ada Ø 100 mm -
3 . A. 8.4.4.3. Penyambungan 1 buah pipa baru ke pipa yang ada Ø 150 mm -
4 . A. 8.4.4.4. Penyambungan 1 buah pipa baru ke pipa yang ada Ø 200 mm -
5 . A. 8.4.4.5. Penyambungan 1 buah pipa baru ke pipa yang ada Ø 250 mm -
6 . A. 8.4.4.6. Penyambungan 1 buah pipa baru ke pipa yang ada Ø 300 mm -
7 . A. 8.4.4.7. Penyambungan 1 buah pipa baru ke pipa yang ada Ø 400 mm -
8 . A. 8.4.4.8. Penyambungan 1 buah pipa baru ke pipa yang ada Ø 450 mm -
9 . A. 8.4.4.9. Penyambungan 1 buah pipa baru ke pipa yang ada Ø 500 mm -
10 . A. 8.4.4.10. Penyambungan 1 buah pipa baru ke pipa yang ada Ø 600 mm -
11 . A. 8.4.4.11. Penyambungan 1 buah pipa baru ke pipa yang ada Ø 700 mm -
12 . A. 8.4.4.12. Penyambungan 1 buah pipa baru ke pipa yang ada Ø 800 mm -
8.4.5
Pekerjaan Pengetesan 1 . A. 8.4.5.1. Pengetesan 1 m pipa Ø 50 mm -
2 . A. 8.4.5.2. Pengetesan 1 m pipa Ø 75 mm -
3 . A. 8.4.5.3. Pengetesan 1 m pipa Ø 100 mm -
4 . A. 8.4.5.4. Pengetesan 1 m pipa Ø 150 mm -
5 . A. 8.4.5.5. Pengetesan 1 m pipa Ø 200 mm -
6 . A. 8.4.5.6. Pengetesan 1 m pipa Ø 250 mm -
7 . A. 8.4.5.7. Pengetesan 1 m pipa Ø 300 mm -
8 . A. 8.4.5.8. Pengetesan 1 m pipa Ø 400 mm -
9 . A. 8.4.5.9. Pengetesan 1 m pipa Ø 500 mm -
10 . A. 8.4.5.10. Pengetesan 1 m pipa Ø 600 mm -
BACKUP VOLUME ARSITEKTURAL
Sub Real
NO. ITEM PEKERJAAN P L T n M1 M2 M3 n item Satuan
volume voulme
A.3 ARSITEKTUR
I. Pekerjaan Pasangan dan Plesteran
01 Pasangan dinding bata merah
dinding baru 23.00 5.1 1 114.6200
dnding penggantian jendela lama 2.90 0.2 9
Penambahan tembok baru 13.50
Pengurangan PJ1 & PJ2 5.500 1 5.5000
PJ3 & PJ4 5.700 1 5.7000
J1 5.100 2 10.2000
6 Pengecatan tembok
Tembok baru dalam 114.62
luar 114.62
Tembok lama dalam 19.5 5.8 113.10 48.47
luar 59 5.8 342.20 277.57
pengurangan PJ1 5.77 2 11.5332
PJ3 5.96 3 17.8914
J1 5.03 7 35.21
0.93 4.51 1.41 1.41 1.94 0.21 10.41
pelubang lantai 1 0
sisi
sponengan 11.3 0 2 total m' 0
0
7.44 30.42 37.86
A PEKERJAAN TANAH
1 Galian tanah untuk pondasi stall 23.00
Galian tanah untuk pondasi footplate 1.10 1.10 1.50 9.00
2 Urugan tanah kembali 23.00
3 Urugan tanah peninggian lantai 11.00 6.00 0.10
4 Urug pasir bawah fondasi batu kali 23.00 0.90 0.10
5 Urugan pasir bawah lantai 11.00 6.00 0.05
3.30 M3
12.10 M1
3.89 M3
12.96 M2
1.04 M3
13.80 M2
2.14 M3
42.84 M2
1.22 M3
16.32 M2
54.00 M1
0.45 M3
9.52 M2
45.00 M1
NO NAMA PEKERJAAN
Berat
1 FP FP 1 nÆ Æ (mm) L (mm) n lapis n FP
kg/m
arah Y 8 13 1200.0 2 9.00 1.041948
2 SLOOF S1
Tul utama Fy 400
3 KOLOM K1 15x30
kait
Æ Berat Tinggi ujung 2
Tul utama Fy 400 n Kolom n Lantai nÆ
(mm) kg/m (mm) *12/DB
(mm)
7 1 6 13 1.042 6800.00 312
Keliling
Begel luar Fy 240 n Kolom Æ (mm) B (mm) H (mm) Ts (mm)
(mm)
7 10 150 300 0.617 40 740
n Lantai Æ
Begel dalam Fy 400 n Kolom nÆ kait L
(mm) (mm)
TIDAK ADA NO NO NO 0.000 #VALUE! 70
4 KOLOM K2 30x30
kait
Æ Berat Tinggi ujung 2
Tul utama Fy 400 n Kolom n Lantai nÆ
(mm) kg/m (mm) *12/DB
(mm)
2 1 8 13 1.042 6800.00 312
Keliling
Begel luar Fy 240 n Kolom Æ (mm) B (mm) H (mm) Ts (mm)
(mm)
2 10 300 300 0.617 40 1040
n Lantai Æ
Begel dalam Fy 400 n Kolom nÆ kait L
(mm) (mm)
TIDAK ADA 1 2 10 0.617 120 220
5 BALOK KANTILEVER
Tul utama Fy 400
172.8 180.0487
n kait =
kait ujung over lap
Jumlah
Lapangan Tumpuan 2 *12/DB 12/DB Hasil (m) Hasil (kg)
ujung
(mm) (mm)
balok
2 2 312 2 46.624 48.57981
2 2 312 2 46.624 48.57981
2 2 312 2 46.624 48.57981
Lapangan
Tumpuan (n) Hasil (m) Hasil (kg)
(n)
115 76.6666667 172 105.8801
sambungan
tengah 1.3 Ld Hasil (m) Hasil (kg)
(mm)
0 287.8 299.8561
Tumpuan Lapangan
kait (mm) Hasil (m) Hasil (kg)
(n) (n)
156 34 22.6666667 355 219.1257
Lapangan
Tumpuan (n) Hasil (m) Hasil (kg)
(n)
34 #VALUE! #VALUE!
sambungan
tengah 1.3 Ld Hasil (m) Hasil (kg)
(mm)
0 109.4 114.0142
Tumpuan Lapangan
kait (mm) Hasil (m) Hasil (kg)
(n) (n)
156 34 22.6666667 136 83.56961
Lapangan
Tumpuan (n) Hasil (m) Hasil (kg)
(n)
34 #VALUE! #VALUE!
n kait =
over lap
kait ujung Jumlah
Lapangan Tumpuan 12/DB Hasil (m) Hasil (kg)
41/D (mm) ujung
(mm)
balok
2 2 533 7 27.531 28.68588
0 7 0 0
2 2 533 7 27.531 28.68588
Lapangan
Tumpuan (n) Hasil (m) Hasil (kg)
(n)
59.5 59.5 107 65.7377
KANTOR DISNAKER
VOLUME BESI, BEKISTING, BETON
DIAM
DIMENSI (M2)
NO. TYPE PEKERJAAN BETON Tul Utama Tul Tengah
h b L Dia Jml kg/m' Total Dia
BALOK
KOLOM
LANTAI 1
1 Kolom K1
0.20 0.20 5.50 4.00
Tul Utama D13 - - 5.50 D 12 16.00 0.89 82.03 - -
Tul Sengkang P8 - - 2.75 - - - - - - -
- - 2.75 - - - - - - -
Bekisting - - 22.00 - - - - - - -
Beton - - 22.00 - - - - - - -
PLAT BETON
1 Plat Lantai A elv +4.00
Tulangan P8 A= 0.00 - P 8 147.00 0.39 - - -
Bekisting A= 0.00 - - - - - - -
Beton A= 0.00 - - - - - - -
PONDASI
1 FOOT PLATE TYPE F1 1.20 1.20 9.00
Tul Bawah D13 - - 1.20 D 13 63.00 1.04 78.77 - -
- - 1.20 D 13 63.00 1.04 78.77 - -
Tul Atas D13 - - 1.20 D 13 63.00 1.04 78.77 - -
- - 1.20 D 13 63.00 1.04 78.77 - -
Bekisting - - - - - - - - - -
Beton - - - - - - - - - -
3 PONDASI SUMURAN
DIAMETER 80 CM BUIS BETON
Tul Utama D16 - - D 16 - 1.58 - - -
Tul Sengkang spiral D10 D 10 - - - - -
BUIS Beton
Beton
DIAMETER BESI (KG/M)
Tul Tengah Tul Sengkang VOLUME
Jml kg/m' Total Dia L Jrk Jml kg/m' Total
- - - - - - - - - - 82.03
- - - P 8 0.62 0.10 112.00 0.39 27.40
- - - P 8 0.62 0.15 76.00 0.39 18.59 45.99
- - - - - - - - - 17.60
- - - - - - - - - - 0.88
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - - 157.54
- - - - - - - - - -
- - - - - - - - - - 157.54
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - D 10 2.498 0.15 - 0.62 - -
#DIV/0!
-
KOLOM K2 Lt 1
n Lantai (mm) n Æ
Tul utama Fy 400 n Kolom Æ (mm) Tinggi
kait(mm)
ujung
sambungan
2 *12/DB tengah
(mm) 1.3 Ld (mm)
12 1 8 13 1.041948 4200 0
4 1 8 13 1.041948 1650
Begel luar Fy 400 n Kolom Æ (mm) B (mm) H (mm) Ts (mm)Keliling (mm)kait (mm)Tumpuan (n)
Lapangan (n)
12 8 250 250 0.395 40 840 156 21 14
Hasil (m) Hasil (kg)
403.200 420.11362
52.800 55.014879
Lapangan (n) Hasil (m)
418.320 165.06239
BACKUP VOLUME MEKANIKAL ELEKTRIKAL
PANJANG LEBAR TINGGI VOLUME
NO. ITEM PEKERJAAN n
m m m m3
3
EKTRIKAL
LUAS KELILING
TOTAL
m2 m
A.6.1.1 HARGA SATUAN PEKERJAAN MEKANIKAL ELEKTRIKAL
A. 6.1.1.1. Pemasangan 1 titik Stop kontak
Page 151
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 67,500.00 675.00
Tukang listrik L.02 OH 0.020 72,500.00 1,450.00
Kepala Tukang L.03 OH 0.005 77,500.00 387.50
JUMLAH TENAGA KERJA 2,512.50
B. BAHAN
Lampu TL 20 watt unit 1.000 55,000.00 55,000.00
JUMLAH HARGA BAHAN 55,000.00
C. PERALATAN
Page 152
A. TENAGA
Pekerja L.01 OH 0.010 67,500.00 675.00
Tukang listrik L.02 OH 0.020 72,500.00 1,450.00
Kepala Tukang L.03 OH 0.005 77,500.00 387.50
JUMLAH TENAGA KERJA 2,512.50
B. BAHAN
Lampu pijar 25 watt bh 1.000 10,000.00 10,000.00
Fiting keramik bh 1.000 15,000.00 15,000.00
Roset bh 1.000 1,500.00 1,500.00
JUMLAH HARGA BAHAN 26,500.00
C. PERALATAN
Page 153
`
PINTU PJ1 1 UNIT
Bahan Stainless
Ukuran Tinggi 8 Meter
JUMLAH HARGA BAHAN -
C. PERALATAN
BAHAN
1 Air PDAM m3 Rp 4,000.00 Pemakaian diatas 20 m³
2 Alumnium foil roll Rp 360,000.00
3 Aspal curah kg Rp 10,200.00
4 Aspal drum AC 60/70 kg Rp 11,400.00
5 Asbes gelombang kecil
3000x1050x4 mm lbr Rp 102,600.00
2400x1050x4 mm lbr Rp 82,000.00
2100x1050x4 mm lbr Rp 71,800.00
1800x1050x4 mm lbr Rp 61,500.00
6 Asbes gelombang besar
3000x1020x5 mm lbr
2250x920x5 mm lbr
1500x920x5 mm lbr
3000x920x6 mm lbr
2250x920x6 mm lbr
1500x920x6 mm lbr
7 Asbes plat
1000x1000x3 mm lbr Rp 17,100.00
1000x2000x3 mm lbr Rp 41,000.00
500x2000x3 mm lbr Rp 25,600.00
250x2000x4 mm lbr Rp 17,100.00
1200x2400x4 mm lbr Rp 68,400.00
1000x1000x4 mm lbr Rp 22,800.00
1200x2400x5 mm lbr Rp 102,600.00
1200x2400x6 mm lbr Rp 125,400.00
8 Asbes nok
Gelombang kecil bj Rp 45,600.00
Gelombang besar bj Rp 70,600.00
9 Batu bata apple 4 bj Rp 900.00
10 Batu bata apple 5 bj Rp 850.00
11 Batu bata berongga expose bj Rp 1,780.00
12 Bata Ringan m3 Rp 844,800.00
13 Batu belah hitam
batu belah 15/20 m3 Rp 160,000.00
NO. URAIAN SATUAN EE KETERANGAN
1 2 3 5
batu belah 10/15 m3 Rp 239,400.00
Batu belah 7/10 m3 Rp 239,400.00
batu belah 5/7 m3 Rp 239,400.00
batu belah 4/6 m3 Rp 239,400.00
batu kricak 3/4 (MS) m3 Rp 245,100.00
batu kricak 2/3 (MS) m3 Rp 245,100.00
14 Batu belah putih m3 Rp 170,000.00
15 Batu granit kg Rp 2,750.00
16 Baja dan Besi
Baja IWF kg Rp 10,000.00
Besi profil Siku kg Rp 10,525.00
Besi beton kg Rp 9,000.00
Besi scuare tube m Rp 20,900.00
Profil aluminium m' Rp 132,000.00
Aluminium strip m' Rp 59,950.00
Panil aluminium m2 Rp 125,000.00
Frame pintu aluminium m1 Rp 90,000.00
Frame pintu aluminium m1 Rp 54,000.00
Skrup fixer pak Rp 4,400.00 1 pak = 100 bh
sealant tube Rp 36,500.00
Profil kaca m Rp 9,900.00
Rambuncis jendela bh Rp 28,000.00
Besi hollow 40.40 galvanis m Rp 8,500.00 metal fiuring 19250 utk plafon gipsum
Besi strip tebal 5 mm kg Rp 12,500.00
17 Batako pejal besar bj Rp 3,900.00
Batako pejal kecil bj Rp 3,420.00
18 Bambu
Bambu apus btg Rp 17,100.00
Bambu wulung btg Rp 17,100.00
Bambu petung btg Rp 45,600.00
19 Buis beton
diameter 15 mm x 1 m bj Rp 57,000.00
diameter 20 mm x 1 m bj Rp 62,700.00
diameter 25 mm x 1 m bj Rp 62,700.00
diameter 30 mm x 1 m bj Rp 68,400.00
diameter 40 mm x 1 m bj Rp 91,200.00
diameter 60 mm x 0,5 m bj Rp 85,500.00
diameter 80 mm x 0,5 m bj Rp 108,300.00
diameter 100 mm x 0,5 m bj Rp 142,500.00
20 Cat
cat kayu kg Rp 74,100.00 setara Emco
cat meni kg Rp 34,200.00
cat besi kg Rp 74,100.00 setara Emco
cat tembok interior (Decolith) kg Rp 28,500.00 setara Mowilex,Decolith
cat tembok exterior (Dulux) kg Rp 50,000.00 setara Nipon, Jotun,Dulux
cat tembok exterior (Belazo) kg Rp 80,000.00 setara Envi, Belazo
water Proofing kg Rp 55,000.00
21 Dempul tembok/ plamir kg Rp 25,000.00
22 Dempul kayu kg Rp 34,200.00
23 Dinabolt dia 12 mm ( 10-15 cm) bh Rp 5,000.00
24 Engsel pintu (besar) bh Rp 34,200.00
Engsel pintu (kecil) bh Rp 22,800.00
25 Engsel Jendela (besar) bh Rp 22,800.00
Engsel Jendela (kecil) bh Rp 17,100.00
26 eternit 100 x 100 (polos) lbr Rp 17,100.00
27 Fiberglas lbr Rp 96,900.00
28 Filler kg Rp 33,000.00
29 Formika 120 x 240 cm lbr Rp 102,600.00
30 Gebalan rumput m2 Rp 81,300.00
31 Grendel
Grendel pintu bh Rp 17,100.00
NO. URAIAN SATUAN EE KETERANGAN
1 2 3 5
Grendel jendela bh Rp 8,250.00
32 Genteng
genteng press kecil Rp 2,000.00
genteng beton besar bj Rp 10,800.00
genteng beton kecil bj Rp 5,700.00
genteng murando glassur bj Rp 7,200.00 setara jatiwangi
genteng murando natural bj Rp 4,125.00
genteng tanah paris/press bj Rp 1,900.00
genteng tanah kodok bj Rp 2,800.00
genteng kaca 3 mm bj Rp 14,800.00
genteng kaca kodok bj Rp 22,000.00
Bubungan genteng press Rp 7,000.00
Bubungan genteng beton bj Rp 21,300.00
Bubungan genteng tanah/press bj Rp 6,800.00
Bubungan murando bj Rp 6,600.00
33 Geotekstil m2 Rp 30,250.00
32 Gypsum Board lbr Rp 65,000.00
33 Lisplang GRC m1 Rp 75,000.00
34 GRC Board 6 mm lbr Rp 98,000.00
Handel bh Rp 5,700.00
35 Handel pintu bh Rp 88,000.00
36 Handel jendela bh Rp 11,000.00
37 Hak angin 15 cm bh Rp 11,000.00
38 H.B 20 bh Rp 5,500.00
39 H.B 15 bh Rp 7,150.00
40 H.B 10 bh Rp 7,150.00
41 Ijuk kg Rp 6,800.00
42 Kaca
kaca bening 3 mm m2 Rp 82,300.00
kaca bening 5 mm m2 Rp 113,100.00
Kaca buram 3 mm m2 Rp 113,100.00
kaca buram 5 mm m2 Rp 171,000.00
kaca reyband 3 mm m2 Rp 82,300.00
kaca reyband 5 mm m2 Rp 102,800.00
Glassblok bh Rp 24,750.00
43 Karpet lebar 90 cm m' Rp 19,800.00
44 kayu bakar m3 Rp 128,600.00
45 kayu begisteng m3 Rp 1,500,000.00 dpt untuk begisteng
46 Kayu dolken m3 Rp 823,000.00
46 Kayu dolken, 4 mtran btg Rp 50,000.00
47 Kayu jati Kelas I
papan m3 Rp 17,490,400.00
balok m3 Rp 16,461,600.00
reng m' Rp 5,500.00
48 Kayu kamper
papan m3 Rp 12,540,000.00
balok m3 Rp 11,400,000.00
reng m' Rp 3,000.00
49 Kayu Bangkirei
papan m3 Rp 15,390,000.00
balok m3 Rp 14,820,000.00
reng m' Rp 3,000.00
50 Kayu kruing
papan m3 Rp 10,260,000.00
balok m3 Rp 9,120,000.00
reng m' Rp 2,500.00
51 Kayu meranti
papan m3 Rp 7,980,000.00
balok m3 Rp 6,500,000.00
reng m' Rp 2,000.00
52 Kayu glugu m3 Rp 5,130,000.00 Klas I
NO. URAIAN SATUAN EE KETERANGAN
1 2 3 5
53 Kayu lapis tripleks 3 mm lbr Rp 57,000.00
54 Kayu lapis tripleks 4 mm lbr Rp 64,200.00
55 Kayu lapis tripleks 6 mm lbr Rp 75,500.00
56 Kayu lapis tripleks 9 mm lbr Rp 131,100.00
57 Kayu lapis tripleks 12 mm lbr Rp 182,400.00
58 Kayu lapis teakwood 4 mm lbr Rp 160,000.00
59 Kapur pasang m3 Rp 137,500.00
60 Kapur sirih m3 Rp 225,000.00
61 Kawat ayakan m2 Rp 22,800.00
62 Kawat Las kg Rp 38,500.00
63 Kawat nyamuk aluminium m2 Rp 22,800.00
64 Kawat beton / bendrat kg Rp 22,800.00
65 Kawat bronjong kg Rp 24,000.00
Kawat Bronjong Pabrikasi
2 x 1 x 0,5 dia 2,70 mm unit Rp 335,500.00
2 x 1 x 0,5 dia 3,00 mm unit Rp 378,510.00
3 x 1 x 0,5 dia 2,70 mm unit Rp 482,020.00
3x 1 x 0,5 dia 3,00 mm unit Rp 527,120.00
2 x 1 x 1 dia 2,70 mm unit Rp 482,020.00
2 x 1 x 1 dia 3,00 mm unit Rp 527,120.00
3 x 1 x 3 dia 2,70 mm unit Rp 695,090.00
3 x 1 x 1 dia 3,00 mm unit Rp 758,670.00
66 Kawat duri kg Rp 18,500.00
67 Kawat jaring galvanis, pj. 240 cm unit Rp 285,000.00
68 Split beton m3 Rp 220,000.00
69 Split beton kg Rp 161.76
70 Krokos/ kroco 2-4 cm m3 Rp 218,600.00
71 Kunci / slot tanam besar ( Yale ) bh Rp 162,400.00
72 Kunci / slot tanam kecil ( Yale ) bh Rp 108,300.00
73 Kloset duduk lengkap ( KIA ) standar bh Rp 1,710,000.00
Kloset duduk lengkap ( INA ) standar bh Rp 1,368,000.00
74 Kloset jongkok porselin ( KIA ) bh Rp 456,000.00
Kloset jongkok porselin ( INA ) bh Rp 171,000.00
Kloset jongkok LOLO bh Rp 125,400.00
75 Lem aica aibon kg Rp 68,400.00
76 Lem kayu kg Rp 15,100.00
77 Lis Profil kayu m' Rp 10,000.00
78 Melamin kg Rp 85,500.00
79 Minyak cat/ Thinner ltr Rp 22,800.00
80 Minyak tanah ltr Rp 12,000.00
81 Minyak bekisting ltr Rp 13,200.00
82 Oli gardan ltr Rp 38,250.00
83 Oli mesin ltr Rp 38,000.00 Setara Mesran
84 Pertalite ltr Rp 7,800.00 Non Subsidi
85 Pasir pasang
pasir pasang m3 Rp 180,000.00
pasir pasang kg Rp 130.43
pasir beton m3 Rp 180,000.00
pasir beton kg Rp 130.43
86 Pasir urug m3 Rp 150,000.00
87 Paku besar, sedang kg Rp 15,000.00
88 Paku kecil kg Rp 20,500.00
89 Paku payung kg Rp 35,000.00
89 Paku skrup kg Rp 30,250.00
90 Panel beton pracetak uk. 240x40x5 cm lbr Rp 125,000.00
91 Kolom beton pracetak buah Rp 175,000.00
92 Pipa
galvanis diameter 0,5 " btg Rp 102,600.00 Medium B, Panjang 6 m
galvanis diameter 0,75 " btg Rp 131,100.00 Medium B, Panjang 6 m
galvanis diameter 1" btg Rp 159,600.00 Medium B, Panjang 6 m
galvanis diameter 1.25" btg Rp 205,200.00
NO. URAIAN SATUAN EE KETERANGAN
1 2 3 5
galvanis diameter 1,5 " btg Rp 256,500.00 Medium B, Panjang 6 m
galvanis diameter 3" btg Rp 437,200.00 Medium A, Panjang 6 m
galvanis diameter 4" btg Rp 456,000.00 Medium A, Panjang 6 m
PVC 4 m diameter 0,5" AW btg Rp 25,000.00
PVC 4 m diameter 0,75" AW btg Rp 36,400.00
PVC 4 m diameter 1" AW btg Rp 45,600.00
PVC 4 m diameter 1,5" D btg Rp 44,000.00
PVC 4 m diameter 1,5" AW btg Rp 79,800.00
PVC 4 m diameter 2" D btg Rp 62,700.00
PVC 4 m diameter 2" AW btg Rp 102,600.00
PVC 4 m diameter 2,5" D btg Rp 72,600.00
PVC 4 m diameter 2,5" AW btg Rp 116,600.00
PVC 4 m diameter 3" D btg Rp 62,700.00
PVC 4 m diameter 3" AW btg Rp 205,200.00
PVC 4 m diameter 4" D btg Rp 171,000.00
PVC 4 m diameter 4" AW btg Rp 342,000.00
93 Paving (abu - abu) tebal 6 cm K 200 m2 Rp 62,700.00
94 Paving ( warna ) tebal 8 cm K 300 m2 Rp 68,400.00
95 Paving beton press tebal 8 cm K 300 m2 Rp 100,000.00
96 Plastik gelombang bh Rp 85,000.00
97 Plamuur kayu kg Rp 34,200.00
98 Plywood 900x2100x4 mm lbr Rp 62,700.00
99 Plywood 1200x2400x4 mm lbr Rp 79,800.00
100 Plywood phenol film 12 mm lbr Rp 275,000.00
101 Politur ltr Rp 74,100.00
102 PVC Waterstop 150 mm m' Rp 195,800.00
103 PVC Waterstop 200 mm m' Rp 294,800.00
104 PVC Waterstop 230 - 320 mm m' Rp 961,400.00
105 Residu ltr Rp 14,000.00
106 Rooster
- Roster kayu bh Rp 34,200.00
- Roster tanah liat bh Rp 5,700.00
107 Semen (PC)
Semen Dynamix / Gresik zak Rp 45,000.00 40 kg
Semen putih zak Rp 102,600.00
Semen warna kg Rp 14,800.00
Sika grout 215 kg Rp 12,500.00
Screening kg Rp 5,500.00
108 Semen merah m3 Rp 330,000.00
109 Semen Instant ex Dry mix @40kg zak Rp 174,000.00
110 Plesteran Instant @40 kg zak Rp 85,000.00
111 Acian Instant @40 kg zak Rp 195,500.00
112 Seng plat
seng BJLS 20 lebar 45 cm lbr Rp 16,500.00
seng BJLS 20 lebar 55 cm lbr Rp 18,700.00
seng BJLS 20 lebar 60 cm lbr Rp 22,000.00
NO. URAIAN SATUAN EE KETERANGAN
1 2 3 5
seng BJLS 20 lebar 70 cm lbr Rp 25,300.00
seng BJLS 20 lebar 80 cm lbr Rp 28,600.00
seng BJLS 20 lebar 90 cm lbr Rp 31,900.00
seng BJLS 25 lebar 90 cm lbr Rp 64,800.00
113 Seng gelombang
BJLS 30 90x180 cm lbr Rp 61,700.00
BJLS 25 90x180 cm lbr Rp 51,400.00
BJLS 20 90x240 cm lbr Rp 68,000.00
BJLS 20 90x300 cm lbr Rp 79,620.00
114 Solar (subsidi) ltr Rp 5,150.00
Solar (Non subsidi) ltr Rp 11,850.00
115 Soda api kg Rp 30,000.00
116 Sirlak kg Rp 228,000.00
117 Sirtu m3 Rp 171,000.00
118 Spritus ltr Rp 13,600.00
119 Spacer buah Rp 5,000.00
120 Storox-100 kg Rp 29,000.00
121 Tanah urugan pilihan m3 Rp 120,000.00
122 Tanah liat m3 Rp 132,000.00
123 Teak oil ltr Rp 28,500.00
124 Teer ltr Rp 22,800.00
125 Terpentin ltr Rp 22,800.00
126 Tegel
marmer 40x40 cm m2 Rp 200,000.00
keramik 20x20 cm m2 Rp 62,700.00 Setara Roman
keramik 25x25 cm m2 Rp 85,000.00
keramik 25 x 40 cm m2 Rp 63,500.00 Setara Accura
keramik 30x30 cm m2 Rp 45,600.00
keramik 30x30 cm anti slip m2 Rp 64,800.00
keramik 40x40 cm m2 Rp 108,300.00 Setara Roman
porselin 11x11 cm m2 Rp 61,700.00
teraso 30x30 cm m2 Rp 51,400.00
kembang 20x20 cm m2 Rp 62,700.00
kembang 30x30 cm m2 Rp 51,300.00
warna 20x20 cm m2 Rp 62,700.00
warna 30x30 cm m2 Rp 54,700.00
warna 40x40 cm m3 Rp 76,500.00
abu - abu 20x20 cm m2 Rp 62,700.00
abu - abu 30x30 cm m2 Rp 51,300.00
abu - abu 40x40 cm m2 Rp 76,500.00
hemogenus keramik 60 x 60cm dus Rp 175,000.00
A. 4.1.1.1. Membuat 1 m3 beton mutu f'c = 7,4 Mpa (K100), slump (12 ± 2) cm, w/c = 0,87
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 67,500.00 111,375.00
Tukang Batu L.02 OH 0.275 72,500.00 19,937.50
Kepala Tukang L.03 OH 0.028 77,500.00 2,170.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
JUMLAH TENAGA KERJA 140,122.50
B. BAHAN
Semen portland kg 247.000 1,125.00 277,875.00
Pasir beton kg 869.000 130.43 113,347.83
Kerikil (maks 30 mm) kg 999.000 161.76 161,602.94
Air ltr 215.000 4.00 860.00
JUMLAH HARGA BAHAN 553,685.77
C. PERALATAN
A. 4.1.1.2. Membuat 1 m3 beton mutu f'c = 9,8 Mpa (K125), slump (12 ± 2) cm, w/c = 0,78
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 67,500.00 111,375.00
Tukang Batu L.02 OH 0.275 72,500.00 19,937.50
Kepala Tukang L.03 OH 0.028 77,500.00 2,170.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
JUMLAH TENAGA KERJA 140,122.50
B. BAHAN
Semen portland kg 276.000 1,125.00 310,500.00
Pasir beton kg 828.000 130.43 108,000.00
Kerikil (maks 30 mm) kg 1012.000 161.76 163,705.88
Air ltr 215.000 4.00 860.00
JUMLAH HARGA BAHAN 583,065.88
C. PERALATAN
A. 4.1.1.3. Membuat 1 m3 beton mutu f'c = 12,2 Mpa (K150), slump (12 ± 2) cm, w/c = 0,72
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 67,500.00 111,375.00
Tukang Batu L.02 OH 0.275 72,500.00 19,937.50
Kepala Tukang L.03 OH 0.028 77,500.00 2,170.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
JUMLAH TENAGA KERJA 140,122.50
B. BAHAN
Page 169
Semen portland kg 299.000 1,125.00 336,375.00
Pasir beton kg 799.000 130.43 104,217.39
Kerikil (maks 30 mm) kg 1017.000 161.76 164,514.71
Air ltr 215.000 4.00 860.00
JUMLAH HARGA BAHAN 605,967.10
C. PERALATAN
A. 4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 Mpa (K100), slump (3-6) cm, w/c = 0,87
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.200 67,500.00 81,000.00
Tukang Batu L.02 OH 0.200 72,500.00 14,500.00
Kepala Tukang L.03 OH 0.020 77,500.00 1,550.00
Mandor L.04 OH 0.060 80,000.00 4,800.00
JUMLAH TENAGA KERJA 101,850.00
B. BAHAN
Semen portland kg 230.000 1,125.00 258,750.00
Pasir beton kg 893.000 130.43 116,478.26
Kerikil (maks 30 mm) kg 1027.000 161.76 166,132.35
Air ltr 200.000 4.00 800.00
JUMLAH HARGA BAHAN 542,160.61
C. PERALATAN
A. 4.1.1.5. Membuat 1 m3 beton mutu f'c = 14,5 Mpa (K175), slump (12 ± 2) cm, w/c = 0,66
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 67,500.00 111,375.00
Tukang Batu L.02 OH 0.275 72,500.00 19,937.50
Kepala Tukang L.03 OH 0.028 77,500.00 2,170.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
JUMLAH TENAGA KERJA 140,122.50
B. BAHAN
Semen portland kg 326.000 1,125.00 366,750.00
Pasir beton kg 760.000 130.43 99,130.43
Kerikil (maks 30 mm) kg 1029.000 161.76 166,455.88
Air ltr 215.000 4.00 860.00
JUMLAH HARGA BAHAN 633,196.32
C. PERALATAN
A. 4.1.1.6. Membuat 1 m3 beton mutu f'c = 16,9 Mpa (K200), slump (12 ± 2) cm, w/c = 0,61
Page 170
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 67,500.00 111,375.00
Tukang Batu L.02 OH 0.275 72,500.00 19,937.50
Kepala Tukang L.03 OH 0.028 77,500.00 2,170.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
JUMLAH TENAGA KERJA 140,122.50
B. BAHAN
Semen portland kg 352.000 1,125.00 396,000.00
Pasir beton kg 731.000 130.43 95,347.83
Kerikil (maks 30 mm) kg 1031.000 161.76 166,779.41
Air ltr 215.000 4.00 860.00
JUMLAH HARGA BAHAN 658,987.24
C. PERALATAN
A. 4.1.1.7. Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K225), slump (12 ± 2) cm, w/c = 0,58
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 67,500.00 111,375.00
Tukang Batu L.02 OH 0.275 72,500.00 19,937.50
Kepala Tukang L.03 OH 0.028 77,500.00 2,170.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
JUMLAH TENAGA KERJA 140,122.50
B. BAHAN
Semen portland kg 371.000 1,125.00 417,375.00
Pasir beton kg 698.000 130.43 91,043.48
Kerikil (maks 30 mm) kg 1047.000 161.76 169,367.65
Air ltr 215.000 4.00 860.00
JUMLAH HARGA BAHAN 678,646.13
C. PERALATAN
A. 4.1.1.8. Membuat 1 m3 beton mutu f'c = 21,7 Mpa (K250), slump (12 ± 2) cm, w/c = 0,56
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 67,500.00 111,375.00
Tukang Batu L.02 OH 0.275 72,500.00 19,937.50
Kepala Tukang L.03 OH 0.028 77,500.00 2,170.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
JUMLAH TENAGA KERJA 140,122.50
B. BAHAN
Semen portland kg 384.000 1,125.00 432,000.00
Pasir beton kg 692.000 130.43 90,260.87
Kerikil (maks 30 mm) kg 1039.000 161.76 168,073.53
Air ltr 215.000 4.00 860.00
JUMLAH HARGA BAHAN 691,194.40
Page 171
C. PERALATAN
A. 4.1.1.9. Membuat 1 m3 beton mutu f'c = 24,0 Mpa (K275), slump (12 ± 2) cm, w/c = 0,53
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 67,500.00 111,375.00
Tukang Batu L.02 OH 0.275 72,500.00 19,937.50
Kepala Tukang L.03 OH 0.028 77,500.00 2,170.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
JUMLAH TENAGA KERJA 140,122.50
B. BAHAN
Semen portland kg 406.000 1,125.00 456,750.00
Pasir beton kg 684.000 130.43 89,217.39
Kerikil (maks 30 mm) kg 1026.000 161.76 165,970.59
Air ltr 215.000 4.00 860.00
JUMLAH HARGA BAHAN 712,797.98
C. PERALATAN
A. 4.1.1.10. Membuat 1 m3 beton mutu f'c = 26,4 Mpa (K300), slump (12 ± 2) cm, w/c = 0,52
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 67,500.00 111,375.00
Tukang Batu L.02 OH 0.275 72,500.00 19,937.50
Kepala Tukang L.03 OH 0.028 77,500.00 2,170.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
JUMLAH TENAGA KERJA 140,122.50
B. BAHAN
Semen portland kg 413.000 1,125.00 464,625.00
Pasir beton kg 681.000 130.43 88,826.09
Kerikil (maks 30 mm) kg 1021.000 161.76 165,161.76
Air ltr 215.000 4.00 860.00
JUMLAH HARGA BAHAN 719,472.85
C. PERALATAN
A. 4.1.1.11. Membuat 1 m3 beton mutu f'c = 28,8 Mpa (K325), slump (12 ± 2) cm, w/c = 0,49
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 2.100 67,500.00 141,750.00
Tukang Batu L.02 OH 0.350 72,500.00 25,375.00
Page 172
Kepala Tukang L.03 OH 0.035 77,500.00 2,712.50
Mandor L.04 OH 0.105 80,000.00 8,400.00
JUMLAH TENAGA KERJA 178,237.50
B. BAHAN
Semen portland kg 439.000 1,125.00 493,875.00
Pasir beton kg 670.000 130.43 87,391.30
Kerikil (maks 30 mm) kg 1006.000 161.76 162,735.29
Air ltr 215.000 4.00 860.00
JUMLAH HARGA BAHAN 744,861.60
C. PERALATAN
A. 4.1.1.12. Membuat 1 m3 beton mutu f'c = 31,2 Mpa (K350), slump (12 ± 2) cm, w/c = 0,48
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 2.100 67,500.00 141,750.00
Tukang Batu L.02 OH 0.350 72,500.00 25,375.00
Kepala Tukang L.03 OH 0.035 77,500.00 2,712.50
Mandor L.04 OH 0.105 80,000.00 8,400.00
JUMLAH TENAGA KERJA 178,237.50
B. BAHAN
Semen portland kg 448.000 1,125.00 504,000.00
Pasir beton kg 667.000 130.43 87,000.00
Kerikil (maks 30 mm) kg 1000.000 161.76 161,764.71
Air ltr 215.000 4.00 860.00
JUMLAH HARGA BAHAN 753,624.71
C. PERALATAN
Page 173
F. Harga Satuan Pekerjaan (D+E) 729,552.47
Page 174
A. 4.1.1.15. Membuat 1 m' PVC waterstop lebar 200 mm
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.070 67,500.00 4,725.00
Tukang Batu/Pipa L.02 OH 0.035 72,500.00 2,537.50
Kepala Tukang L.03 OH 0.004 77,500.00 310.00
Mandor L.04 OH 0.007 80,000.00 560.00
JUMLAH TENAGA KERJA 8,132.50
B. BAHAN
Waterstop lebar 200 mm m3 1.050 294,800.00 309,540.00
JUMLAH HARGA BAHAN 309,540.00
C. PERALATAN
Page 175
G. Harga Satuan Pekerjaan Pembesian Tiap 1 Kg (F/10) 11,944.08
Page 176
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 123,865.00
E. Profit 10% *D 12,386.50
F. Harga Satuan Pekerjaan (D+E) 136,251.50
Page 177
Mandor L.04 OH 0.033 80,000.00 2,640.00
JUMLAH TENAGA KERJA 73,672.50
B. BAHAN
Kayu klas III m3 0.040 1,500,000.00 60,000.00
Paku 5 - 10 cm kg 0.400 15,000.00 6,000.00
Minyak bekisting liter 0.200 13,200.00 2,640.00
Balok kayu klas II m3 0.018 6,500,000.00 117,000.00
Plywood tebal 9 mm lbr 0.350 79,800.00 27,930.00
Dolken kayu Ø 8-10 m, panj 4 m batang 2.000 50,000.00 100,000.00
JUMLAH HARGA BAHAN 313,570.00
C. PERALATAN
Page 178
JUMLAH HARGA BAHAN 381,570.00
C. PERALATAN
Page 179
Tukang Batu L.02 OH 0.275 72,500.00 19,937.50
Tukang Kayu L.02 OH 1.300 72,500.00 94,250.00
Tukang Besi L.02 OH 1.050 72,500.00 76,125.00
Kepala Tukang L.03 OH 0.262 77,500.00 20,305.00
Mandor L.04 OH 0.265 80,000.00 21,200.00
JUMLAH TENAGA KERJA 589,567.50
B. BAHAN
Kayu klas III m3 0.200 1,500,000.00 300,000.00
Paku 5 - 10 cm kg 1.500 15,000.00 22,500.00
Minyak bekisting liter 0.400 13,200.00 5,280.00
Besi beton polos kg 157.500 9,000.00 1,417,500.00
Kawat beton kg 2.250 22,800.00 51,300.00
Semen portland kg 336.000 1,125.00 378,000.00
Pasir beton m3 0.540 180,000.00 97,200.00
Kerikil beton (split) m3 0.810 220,000.00 178,200.00
JUMLAH HARGA BAHAN 2,449,980.00
C. PERALATAN
Page 180
A. 4.1.1.29. Membuat 1 m3 Sloof beton bertulang (200 kg besi + bekisting)
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 5.650 67,500.00 381,375.00
Tukang Batu L.02 OH 0.275 72,500.00 19,937.50
Tukang Kayu L.02 OH 1.560 72,500.00 113,100.00
Tukang Besi L.02 OH 1.400 72,500.00 101,500.00
Kepala Tukang L.03 OH 0.323 77,500.00 25,032.50
Mandor L.04 OH 0.283 80,000.00 22,640.00
JUMLAH TENAGA KERJA 663,585.00
B. BAHAN
Kayu klas III m3 0.270 1,500,000.00 405,000.00
Paku 5 - 10 cm kg 2.000 15,000.00 30,000.00
Minyak bekisting liter 0.600 13,200.00 7,920.00
Besi beton polos kg 210.000 9,000.00 1,890,000.00
Kawat beton kg 3.000 22,800.00 68,400.00
Semen portland kg 336.000 1,125.00 378,000.00
Pasir beton m3 0.540 180,000.00 97,200.00
Kerikil beton (split) m3 0.810 220,000.00 178,200.00
JUMLAH HARGA BAHAN 3,054,720.00
C. PERALATAN
Page 181
A. 4.1.1.31. Membuat 1 m3 Balok beton bertulang (200 kg besi + bekisting)
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 6.350 67,500.00 428,625.00
Tukang Batu L.02 OH 0.275 72,500.00 19,937.50
Tukang Kayu L.02 OH 1.650 72,500.00 119,625.00
Tukang Besi L.02 OH 1.400 72,500.00 101,500.00
Kepala Tukang L.03 OH 0.333 77,500.00 25,807.50
Mandor L.04 OH 0.318 80,000.00 25,440.00
JUMLAH TENAGA KERJA 720,935.00
B. BAHAN
Kayu klas III m3 0.320 1,500,000.00 480,000.00
Paku 5 - 10 cm kg 3.200 15,000.00 48,000.00
Minyak bekisting liter 1.600 13,200.00 21,120.00
Besi beton polos kg 210.000 9,000.00 1,890,000.00
Kawat beton kg 3.000 22,800.00 68,400.00
Semen portland kg 336.000 1,125.00 378,000.00
Pasir beton m3 0.540 180,000.00 97,200.00
Kerikil beton (split) m3 0.810 220,000.00 178,200.00
Balok kayu klas II m3 0.140 6,500,000.00 910,000.00
Plywood tebal 9 mm lbr 2.800 79,800.00 223,440.00
Dolken kayu Ø 8-10 m, panj 4 m batang 16.000 50,000.00 800,000.00
JUMLAH HARGA BAHAN 5,094,360.00
C. PERALATAN
Page 182
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,864,560.00
E. Profit 10% *D 586,456.00
F. Harga Satuan Pekerjaan (D+E) 6,451,016.00
Page 183
Dolken kayu Ø 8-10 m, panj 4 m batang 14.000 50,000.00 700,000.00
JUMLAH HARGA BAHAN 4,629,640.00
C. PERALATAN
Page 184
A. 4.1.1.35. Membuat 1 m1 Kolom praktis beton bertulang (11 x 11) cm
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.180 67,500.00 12,150.00
Tukang Batu L.02 OH 0.020 72,500.00 1,450.00
Tukang Kayu L.02 OH 0.020 72,500.00 1,450.00
Tukang Besi L.02 OH 0.020 72,500.00 1,450.00
Kepala Tukang L.03 OH 0.006 77,500.00 465.00
Mandor L.04 OH 0.009 80,000.00 720.00
JUMLAH TENAGA KERJA 17,685.00
B. BAHAN
Kayu klas III m3 0.002 1,500,000.00 3,000.00
Paku 5 - 10 cm kg 0.010 15,000.00 150.00
Minyak bekisting liter 0.000 13,200.00 -
Besi beton polos kg 3.000 9,000.00 27,000.00
Kawat beton kg 0.450 22,800.00 10,260.00
Semen portland kg 4.000 1,125.00 4,500.00
Pasir beton m3 0.006 180,000.00 1,080.00
Kerikil beton (split) m3 0.009 220,000.00 1,980.00
JUMLAH HARGA BAHAN 47,970.00
C. PERALATAN
1 m3 Pondasi Footplat Beton mutu f'c = 19,3 Mpa, uk. 90x90 cm, tebal 25 cm, tul. Ф 12 mm - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Page 185
Besi beton 85.70 kg $ 11,944.08 1,023,651.46
Bekisting untuk pondasi 1.33 m2 $ 136,251.50 181,668.67
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
JUMLAH 2,178,465.62
DIBULATKAN 2,178,465.00
1 m3 Pondasi Footplat Beton mutu f'c = 19,3 Mpa, uk. 100x100 cm, tebal 25 cm, tul. Ф 12 mm - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 89.30 kg $ 11,944.08 1,066,566.08
Bekisting untuk pondasi 1.20 m2 $ 136,251.50 163,501.80
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
JUMLAH 2,203,213.37
DIBULATKAN 2,203,213.00
1 m3 Pondasi Footplat Beton mutu f'c = 19,3 Mpa, uk. 120x120 cm, t= 30 cm, tul. Ф 16 + Ф 12 mm - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 66.32 kg $ 11,944.08 792,179.72
Bekisting untuk pondasi 1.00 m2 $ 136,251.50 136,251.50
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
JUMLAH 1,901,576.70
DIBULATKAN 1,901,576.00
1 m3 Pondasi Footplat Beton mutu f'c = 19,3 Mpa, uk. 120x140 cm, t= 30 cm, tul. Ф 16 + Ф 12 mm - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 72.21 kg $ 11,944.08 862,485.45
Bekisting untuk pondasi 0.93 m2 $ 136,251.50 126,519.25
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
JUMLAH 1,962,150.19
DIBULATKAN 1,962,150.00
1 m3 Pondasi Footplat Beton mutu f'c = 19,3 Mpa, uk. 120x150 cm, t= 30 cm, tul. Ф 16 + Ф 12 mm - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 70.32 kg $ 11,944.08 839,933.90
Bekisting untuk pondasi 0.90 m2 $ 136,251.50 122,626.35
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
JUMLAH 1,935,705.73
DIBULATKAN 1,935,705.00
1 m3 Pondasi Footplat Beton mutu f'c = 19,3 Mpa, uk. 150x150 cm, t= 35 cm, tul. Ф 16 mm - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 138.44 kg $ 11,944.08 1,653,514.99
Bekisting untuk pondasi 0.93 m2 $ 136,251.50 127,168.07
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
JUMLAH 2,753,828.55
DIBULATKAN 2,753,828.00
1 m3 Sloof Beton mutu f'c = 14,5 Mpa, uk. 12x20 cm, tul. 4 Ф 12 mm, begel Ф 8 - 20 cm
Beton mutu f'c = 14,5 Mpa (K175) 1.00 m3 $ 850,650.70 850,650.70
Besi beton 200.33 kg $ 11,944.08 2,392,796.36
Bekisting untuk sloof 4.17 m2 $ 144,501.50 602,089.58
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
JUMLAH 3,918,036.64
DIBULATKAN 3,918,036.00
1 m3 Sloof Beton mutu f'c = 14,5 Mpa, uk. 15x20 cm, tul. 4 Ф 12 mm, begel Ф 8 - 20 cm
Beton mutu f'c = 14,5 Mpa (K175) 1.00 m3 $ 850,650.70 850,650.70
Besi beton 164.17 kg $ 11,944.08 1,960,818.98
Bekisting untuk sloof 3.33 m2 $ 144,501.50 481,671.67
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
Page 186
JUMLAH 3,365,641.34
DIBULATKAN 3,365,641.00
1 m3 Sloof Beton mutu f'c = 19,3 Mpa, uk. 20x25 cm, tul. 6 Ф 16 mm, begel Ф 8 - 20 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 224.70 kg $ 11,944.08 2,683,833.65
Bekisting untuk sloof 2.50 m2 $ 144,501.50 361,253.75
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
JUMLAH 4,018,232.89
DIBULATKAN 4,018,232.00
1 m3 Sloof Beton mutu f'c = 19,3 Mpa, uk. 20x30 cm, tul. 6 Ф 16 mm, begel Ф 8 - 20 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 190.50 kg $ 11,944.08 2,275,346.29
Bekisting untuk sloof 2.50 m2 $ 144,501.50 361,253.75
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
JUMLAH 3,609,745.53
DIBULATKAN 3,609,745.00
1 m3 Sloof Beton mutu f'c = 19,3 Mpa, uk. 20x35 cm, tul. 6 Ф 16 mm, begel Ф 8 - 20 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 166.07 kg $ 11,944.08 1,983,569.60
Bekisting untuk sloof 2.50 m2 $ 144,501.50 361,253.75
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
JUMLAH 3,317,968.84
DIBULATKAN 3,317,968.00
1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 40x50 cm, tul. 18 Ф 16 mm, begel Ф 10 - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 179.40 kg $ 11,944.08 2,142,767.06
Bekisting untuk kolom 2.25 m2 $ 404,516.75 910,162.69
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 4,098,575.23
DIBULATKAN 4,098,575.00
1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 40x40 cm, tul. 16 Ф 16 mm, begel Ф 10 - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 199.33 kg $ 11,944.08 2,380,852.28
Bekisting untuk kolom 2.50 m2 $ 404,516.75 1,011,291.88
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 4,437,789.65
DIBULATKAN 4,437,789.00
1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 30x40 cm, tul. 14 Ф 16 mm, begel Ф 8 - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 214.67 kg $ 11,944.08 2,563,994.77
Bekisting untuk kolom 2.92 m2 $ 404,516.75 1,179,840.52
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 4,789,480.78
DIBULATKAN 4,789,480.00
1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 30x30 cm, tul. 10 Ф 16 mm, begel Ф 8 - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 210.22 kg $ 11,944.08 2,510,909.99
Bekisting untuk kolom 3.33 m2 $ 404,516.75 1,348,389.17
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 4,904,944.64
DIBULATKAN 4,904,944.00
Page 187
1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 20x20 cm, tul. 8 Ф 12 mm, begel Ф 8 - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 230.00 kg $ 11,944.08 2,747,137.25
Bekisting untuk kolom 5.00 m2 $ 404,516.75 2,022,583.75
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 5,815,366.49
DIBULATKAN 5,815,366.00
1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 20x20 cm, tul. 4 Ф 12 mm, begel Ф 8 - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 141.00 kg $ 11,944.08 1,684,114.58
Bekisting untuk kolom 5.00 m2 $ 404,516.75 2,022,583.75
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 4,752,343.81
DIBULATKAN 4,752,343.00
1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 15x25 cm, tul. 6 Ф 12 mm, begel Ф 8 - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 197.87 kg $ 11,944.08 2,363,334.31
Bekisting untuk kolom 5.33 m2 $ 144,501.50 770,674.67
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 4,179,654.46
DIBULATKAN 4,179,654.00
1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 15x20 cm, tul. 4 Ф 12 mm, begel Ф 8 - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 179.33 kg $ 11,944.08 2,141,970.78
Bekisting untuk kolom 5.83 m2 $ 144,501.50 842,925.42
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 4,030,541.69
DIBULATKAN 4,030,541.00
1 m3 Kolom Beton mutu f'c = 19,3 Mpa, uk. 15x15 cm, tul. 4 Ф 12 mm, begel Ф 8 - 15 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 227.56 kg $ 11,944.08 2,717,940.62
Bekisting untuk kolom 6.67 m2 $ 144,501.50 963,343.33
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 4,726,929.44
DIBULATKAN 4,726,929.00
1 m3 Kolom Praktis mutu f'c = 14,5 Mpa, uk. 11x11 cm, tul. 4 Ф 10 mm, begel Ф 6 - 20 cm
Beton mutu f'c = 14,5 Mpa (K175) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 208.89 kg $ 11,944.08 2,494,984.56
Bekisting untuk kolom 4.17 m2 $ 144,501.50 602,089.58
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
JUMLAH 4,070,219.63
DIBULATKAN 4,070,219.00
1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 30x60 cm, tul. 14 Ф 16 mm, begel Ф 10 - 12,5 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 147.16 kg $ 11,944.08 1,757,636.99
Bekisting untuk balok 3.89 m2 $ 425,966.75 1,656,537.36
Membongkar bekisting 0.75 m3 $ 290,000.00 217,500.00
JUMLAH 4,532,319.84
DIBULATKAN 4,532,319.00
1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 25x55 cm, tul. 12 Ф 16 mm, begel Ф 10 - 12,5 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 167.39 kg $ 11,944.08 1,999,307.86
Page 188
Bekisting untuk balok 4.91 m2 $ 425,966.75 2,091,109.50
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 5,136,062.84
DIBULATKAN 5,136,062.00
1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 25x50 cm, tul. 12 Ф 16 mm, begel Ф 10 - 12,5 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 182.88 kg $ 11,944.08 2,184,332.44
Bekisting untuk balok 5.00 m2 $ 425,966.75 2,129,833.75
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 5,359,811.67
DIBULATKAN 5,359,811.00
1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 20x40 cm, tul. 9 Ф 16 mm, begel Ф 8 - 17,5 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 204.21 kg $ 11,944.08 2,439,150.74
Bekisting untuk balok 6.25 m2 $ 425,966.75 2,662,292.19
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 6,147,088.42
DIBULATKAN 6,147,088.00
1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 20x35 cm, tul. 7 Ф 16 mm, begel Ф 8 - 17,5 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 186.65 kg $ 11,944.08 2,229,398.16
Bekisting untuk balok 6.43 m2 $ 425,966.75 2,738,357.68
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 6,013,401.33
DIBULATKAN 6,013,401.00
1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 20x30 cm, tul. 7 Ф 16 mm, begel Ф 8 - 17,5 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 215.90 kg $ 11,944.08 2,578,782.67
Bekisting untuk balok 6.67 m2 $ 425,966.75 2,839,778.33
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 6,464,206.49
DIBULATKAN 6,464,206.00
1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 15x35 cm, tul. 8 Ф 12 mm, begel Ф 8 - 17,5 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 171.70 kg $ 11,944.08 2,050,805.80
Bekisting untuk balok 5.67 m2 $ 144,501.50 818,841.83
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 3,915,293.12
DIBULATKAN 3,915,293.00
1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 15x30 cm, tul. 8 Ф 12 mm, begel Ф 8 - 17,5 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 197.84 kg $ 11,944.08 2,363,030.97
Bekisting untuk balok 5.83 m2 $ 144,501.50 842,925.42
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 4,251,601.87
DIBULATKAN 4,251,601.00
1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 15x25 cm, tul. 6 Ф 12 mm, begel Ф 8 - 17,5 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 170.13 kg $ 11,944.08 2,032,085.29
Bekisting untuk balok 6.07 m2 $ 144,501.50 876,642.43
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 3,954,373.21
Page 189
DIBULATKAN 3,954,373.00
1 m3 Balok Beton mutu f'c = 19,3 Mpa, uk. 15x20 cm, tul. 4 Ф 12 mm, begel Ф 8 - 17,5 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 149.00 kg $ 11,944.08 1,779,667.18
Bekisting untuk balok 6.42 m2 $ 144,501.50 927,217.96
Membongkar bekisting 0.50 m3 $ 290,000.00 145,000.00
JUMLAH 3,752,530.62
DIBULATKAN 3,752,530.00
1 m3 Ring Balok Beton mutu f'c = 14,5 Mpa, uk. 12x20 cm, tul. 4 Ф 12 mm, begel Ф 6 - 20 cm
Beton mutu f'c = 14,5 Mpa (K175) 1.00 m3 $ 850,650.70 850,650.70
Besi beton 174.33 kg $ 11,944.08 2,082,250.41
Bekisting untuk balok 5.83 m2 $ 144,501.50 842,925.42
Membongkar bekisting 0.35 m3 $ 290,000.00 101,500.00
JUMLAH 3,877,326.52
DIBULATKAN 3,877,326.00
1 m3 Balok latei mutu f'c = 14,5 Mpa, uk. 12x15 cm, tul. 4 Ф 10 mm, begel Ф 6 - 20 cm
Beton mutu f'c = 14,5 Mpa (K175) 1.00 m3 $ 850,650.70 850,650.70
Besi beton 154.28 kg $ 11,944.08 1,842,705.35
Bekisting untuk balok 5.83 m2 $ 144,501.50 842,925.42
Membongkar bekisting 0.35 m3 $ 290,000.00 101,500.00
JUMLAH 3,637,781.46
DIBULATKAN 3,637,781.00
1 m3 Pelat Atap Beton mutu f'c = 19,3 Mpa, tebal 10 cm, tul. Ф 8 - 20 cm
Beton mutu f'c = 19,3 Mpa (K225) 1.00 m3 $ 900,645.49 900,645.49
Besi beton 78.00 kg $ 11,944.08 931,637.85
Bekisting untuk pelat 7.50 m2 $ 624,516.75 4,683,875.63
Membongkar bekisting 1.00 m3 $ 290,000.00 290,000.00
JUMLAH 6,806,158.96
DIBULATKAN 6,806,158.00
1 m3 Pelat Beton Tutup Saluran mutu f'c = 14,5 Mpa, tebal 10 cm, tul. Ф 10 - 15 cm
Beton mutu f'c = 14,5 Mpa (K175) 1.00 m3 $ 850,650.70 850,650.70
Besi beton 86.80 kg $ 11,944.08 1,036,745.71
Bekisting untuk pelat 7.50 m2 $ 97,215.25 729,114.38
Membongkar bekisting 0.25 m3 $ 290,000.00 72,500.00
JUMLAH 2,689,010.78
DIBULATKAN 2,689,010.00
Page 190
A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK
A. 4.1.2.1. Pembuatan 1 m2 lahan produksi tebal 8 cm beton f'c = 14,5 Mpa (K175), slump (12 ± 2) cm
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.132 67,500.00 8,910.00
Tukang Batu L.02 OH 0.022 72,500.00 1,595.00
Kepala Tukang L.03 OH 0.002 77,500.00 155.00
Mandor L.04 OH 0.007 80,000.00 560.00
JUMLAH TENAGA KERJA 11,220.00
B. BAHAN
Semen portland kg 26.080 1,125.00 29,340.00
Pasir beton kg 60.800 130.43 7,930.43
Kerikil (maks 30 mm) kg 82.320 161.76 13,316.47
Air ltr 17.200 4.00 68.80
JUMLAH HARGA BAHAN 50,655.71
C. PERALATAN
A. 4.1.2.2. Pembuatan 1 m2 lahan produksi tebal 10 cm beton f'c = 14,5 Mpa (K175), slump (12 ± 2) cm
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.165 67,500.00 11,137.50
Tukang Batu L.02 OH 0.028 72,500.00 2,030.00
Kepala Tukang L.03 OH 0.003 77,500.00 232.50
Mandor L.04 OH 0.008 80,000.00 640.00
JUMLAH TENAGA KERJA 14,040.00
B. BAHAN
Semen portland kg 32.600 1,125.00 36,675.00
Pasir beton kg 76.000 130.43 9,913.04
Kerikil (maks 30 mm) kg 102.900 161.76 16,645.59
Air ltr 21.500 4.00 86.00
JUMLAH HARGA BAHAN 63,319.63
C. PERALATAN
A. 4.1.2.3. Pembuatan 1 m2 lahan produksi tebal 12 cm beton f'c = 14,5 Mpa (K175), slump (12 ± 2) cm
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.198 67,500.00 13,365.00
Tukang Batu L.02 OH 0.033 72,500.00 2,392.50
Kepala Tukang L.03 OH 0.003 77,500.00 232.50
Mandor L.04 OH 0.010 80,000.00 800.00
JUMLAH TENAGA KERJA 16,790.00
B. BAHAN
Semen portland kg 39.120 1,125.00 44,010.00
Page 191
Pasir beton kg 91.200 130.43 11,895.65
Kerikil (maks 30 mm) kg 123.480 161.76 19,974.71
Air ltr 25.800 4.00 103.20
JUMLAH HARGA BAHAN 75,983.56
C. PERALATAN
A. 4.1.2.4. Pembuatan 1 m2 lahan produksi tebal 15 cm beton f'c = 14,5 Mpa (K175), slump (12 ± 2) cm
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.248 67,500.00 16,740.00
Tukang Batu L.02 OH 0.041 72,500.00 2,972.50
Kepala Tukang L.03 OH 0.004 77,500.00 310.00
Mandor L.04 OH 0.013 80,000.00 1,040.00
JUMLAH TENAGA KERJA 21,062.50
B. BAHAN
Semen portland kg 48.900 1,125.00 55,012.50
Pasir beton kg 114.000 130.43 14,869.57
Kerikil (maks 30 mm) kg 154.350 161.76 24,968.38
Air ltr 32.250 4.00 129.00
JUMLAH HARGA BAHAN 94,979.45
C. PERALATAN
Page 192
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.004 67,500.00 270.00
Tukang Batu L.02 OH 0.038 72,500.00 2,755.00
Kepala Tukang L.03 OH 0.004 77,500.00 310.00
Mandor L.04 OH 0.001 80,000.00 80.00
JUMLAH TENAGA KERJA 3,415.00
B. BAHAN
Kayu kaso 5/7 m3 0.005 6,500,000.00 32,500.00
Phenol film 12 mm lbr 0.043 275,000.00 11,825.00
Minyak bekisting liter 0.200 13,200.00 2,640.00
Paku (5 sd 7 cm ) kg 0.046 15,000.00 690.00
Dinabolt dia 12 mm ( 10-15 cm) bh 0.693 5,000.00 3,465.00
JUMLAH HARGA BAHAN 51,120.00
C. PERALATAN
A. 4.1.2.8. Pemasangan dan membuka bekisting 1 buah komponen plat beton pracetak
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.053 67,500.00 3,577.50
Tukang Kayu L.02 OH 0.018 72,500.00 1,305.00
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 5,282.50
B. BAHAN
Page 193
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 5,282.50
E. Profit 10% *D 528.25
F. Harga Satuan Pekerjaan (D+E) 5,810.75
A. 4.1.2.9. Pemasangan dan membuka bekisting 1 buah komponen balok beton pracetak
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.089 67,500.00 6,007.50
Tukang Kayu L.02 OH 0.030 72,500.00 2,175.00
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 8,582.50
B. BAHAN
A. 4.1.2.10. Pemasangan dan membuka bekisting 1 buah komponen kolom beton pracetak
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.071 67,500.00 4,792.50
Tukang Kayu L.02 OH 0.024 72,500.00 1,740.00
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 6,932.50
B. BAHAN
Page 194
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 39,765.00
E. Profit 10% *D 3,976.50
F. Harga Satuan Pekerjaan (D+E) 43,741.50
Page 195
Solar liter 6.676 77,500.00 517,390.00
JUMLAH HARGA BAHAN 517,390.00
C. PERALATAN
Sewa crane UH 0.067 1,500,000.00 100,500.00
Sewa pipe support UH 1.100 35,000.00 38,500.00
JUMLAH HARGA ALAT 139,000.00
D. Jumlah (A+B+C) 697,394.00
E. Profit 10% *D 69,739.40
F. Harga Satuan Pekerjaan (D+E) 767,133.40
Page 196
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.019 67,500.00 1,282.50
Tukang Batu L.02 OH 0.038 72,500.00 2,755.00
Operator crane OH 0.019 88,500.00 1,681.50
Pembantu operator crane OH 0.019 81,000.00 1,539.00
JUMLAH TENAGA KERJA 7,258.00
B. BAHAN
Solar liter 1.897 5,150.00 9,769.55
JUMLAH HARGA BAHAN 9,769.55
C. PERALATAN
Sewa crane UH 0.019 1,500,000.00 28,500.00
JUMLAH HARGA ALAT 28,500.00
D. Jumlah (A+B+C) 45,527.55
E. Profit 10% *D 4,552.76
F. Harga Satuan Pekerjaan (D+E) 50,080.31
Page 197
A. 4.1.2.20. Bahan 1 m3 grouting campuran
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
JUMLAH TENAGA KERJA -
B. BAHAN
Semen grout kg 1200.000 12,500.00 15,000,000.00
Screening kg 650.000 5,500.00 3,575,000.00
Air liter 350.000 4.00 1,400.00
JUMLAH HARGA BAHAN 18,576,400.00
C. PERALATAN
Page 198
Pekerja L.01 OH 0.147 67,500.00 9,922.50
Tukang kayu L.02 OH 0.147 72,500.00 10,657.50
Kepala Tukang L.03 OH 0.015 77,500.00 1,162.50
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 22,142.50
B. BAHAN
Kayu kaso 5/7 m3 0.012 6,500,000.00 78,000.00
Papan cor m3 0.004 1,500,000.00 6,000.00
Paku 5 - 7 cm kg 0.264 15,000.00 3,960.00
JUMLAH HARGA BAHAN 87,960.00
C. PERALATAN
Page 199
A. 4.2.1.2. Pemasangan 1 kg rangka kuda-kuda baja IWF
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.060 67,500.00 4,050.00
Tukang Las konstruksi L.02 OH 0.060 72,500.00 4,350.00
Kepala tukang L.03 OH 0.006 77,500.00 465.00
Mandor L,04 OH 0.003 80,000.00 240.00
JUMLAH TENAGA KERJA 9,105.00
B. BAHAN
Besi baja IWF kg 1.150 10,000.00 11,500.00
JUMLAH HARGA BAHAN 11,500.00
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 20,605.00
E. Profit 10% *D 2,060.50
F. Harga Satuan Pekerjaan (D+E) 22,665.50
A. 4.2.1.4. Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 1.050 67,500.00 70,875.00
Tukang Las biasa L.02 OH 1.050 72,500.00 76,125.00
Kepala tukang L.03 OH 0.105 77,500.00 8,137.50
Mandor L,04 OH 0.052 80,000.00 4,160.00
JUMLAH TENAGA KERJA 159,297.50
B. BAHAN
Besi siku L 30.30.3 kg 15.000 10,525.00 157,875.00
Besi plat baja kg 32.800 10,000.00 328,000.00
Kawat las kg 0.050 38,500.00 1,925.00
JUMLAH HARGA BAHAN 487,800.00
C. PERALATAN
- -
Page 200
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 647,097.50
E. Profit 10% *D 64,709.75
F. Harga Satuan Pekerjaan (D+E) 711,807.25
Page 201
B. BAHAN
Pintu gulung besi' m2 1.000 150,000.00 150,000.00
JUMLAH HARGA BAHAN 150,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 332,100.00
E. Profit 10% *D 33,210.00
F. Harga Satuan Pekerjaan (D+E) 365,310.00
Page 202
JUMLAH TENAGA KERJA 151,750.00
B. BAHAN
Rolling door aluminium m2 1.000 220,000.00 220,000.00
JUMLAH HARGA BAHAN 220,000.00
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 371,750.00
E. Profit 10% *D 37,175.00
F. Harga Satuan Pekerjaan (D+E) 408,925.00
Page 203
A. TENAGA
Pekerja L.01 OH 0.085 67,500.00 5,737.50
Tukang khusus aluminium L.02 OH 0.085 72,500.00 6,162.50
Kepala tukang L.03 OH 0.009 77,500.00 697.50
Mandor L,04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 12,997.50
B. BAHAN
Profil aluminium m 4.400 132,000.00 580,800.00
Profil kaca m 4.500 9,900.00 44,550.00
Sealant tube 0.270 36,500.00 9,855.00
JUMLAH HARGA BAHAN 635,205.00
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 648,202.50
E. Profit 10% *D 64,820.25
F. Harga Satuan Pekerjaan (D+E) 713,022.75
Page 204
A. 4.2.1.16. Pemasangan 1 m2 kawat nyamuk
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 67,500.00 6,750.00
Tukang L.02 OH 0.100 72,500.00 7,250.00
Kepala tukang L.03 OH 0.010 77,500.00 775.00
Mandor L,04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 15,175.00
B. BAHAN
Kawat nyamuk m2 1.100 22,800.00 25,080.00
Pengelasan cm 11.110 16,000.00 177,760.00
Baja strip (0,2 x 2) cm kg 1.716 10,000.00 17,160.00
JUMLAH HARGA BAHAN 220,000.00
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 235,175.00
E. Profit 10% *D 23,517.50
F. Harga Satuan Pekerjaan (D+E) 258,692.50
Page 205
JUMLAH HARGA BAHAN 96,847.50
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 126,477.50
E. Profit 10% *D 12,647.75
F. Harga Satuan Pekerjaan (D+E) 139,125.25
A. 4.2.1.20. Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul 60 x 120 cm, dinding partisi
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 67,500.00 16,875.00
Tukang Besi L.02 OH 0.250 72,500.00 18,125.00
Kepala tukang L.03 OH 0.025 77,500.00 1,937.50
Mandor L,04 OH 0.013 80,000.00 1,040.00
JUMLAH TENAGA KERJA 37,977.50
B. BAHAN
Rangka hollow 40.40.2 mm m 3.500 8,500.00 29,750.00
assesoris (perkuatan, las, dll) Ls 100%xrangka 8,500.00 8,500.00
A. 4.2.1.21. Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul 60 x 60 cm, plafon
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.350 67,500.00 23,625.00
Tukang Besi L.02 OH 0.350 72,500.00 25,375.00
Page 206
Kepala tukang L.03 OH 0.035 77,500.00 2,712.50
Mandor L,04 OH 0.018 80,000.00 1,440.00
JUMLAH TENAGA KERJA 53,152.50
B. BAHAN
Rangka hollow 40.40.2 mm m 4.000 8,500.00 34,000.00
assesoris (perkuatan, las, dll) Ls 100%xrangka 8,500.00 8,500.00
A. 4.2.1.22 Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75
A. 4.2.1.22 Pemasangan 1 m2 atap jurai rangka atap baja canai dingin profil C75
Page 207
JUMLAH HARGA ALAT 17,782.35
D. Jumlah (A+B+C) 195,605.85
E. Profit 10% *D 19,560.59
F. Harga Satuan Pekerjaan (D+E) 215,166.44
A. 4.2.1.21.a Pemasangan 1 m2 Rangka atap baja ringan Main Truss C75 Reng 0,45, penutup atap genteng tanah bentuk
atap pelana
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.247 67,500.00 16,672.50
Tukang Besi profil L.02 OH 0.176 72,500.00 12,760.00
Kepala Tukang Besi profil L.03 OH 0.117 77,500.00 9,067.50
Mandor L,04 OH 0.002 80,000.00 197.60
JUMLAH TENAGA KERJA 38,697.60
B. BAHAN
Main truss C75/75 m' 3.500 15,416.67 53,958.33
Roof bottom RT 33-0,45 m' 6.100 7,500.00 45,750.00
Self drilling screw dia 6x20 mm bh 21.930 500.00 10,964.91
Self drilling screw dia 4x16 mm bh 13.158 250.00 3,289.47
Dinabolt dia 12-120 mm bh 1.053 1,250.00 1,315.79
Bracket bulat bh 0.211 7,500.00 1,578.95
Bracket oval bh 0.211 7,000.00 1,473.68
Cornerplat bh 0.079 5,000.00 394.74
A. 4.2.1.21.a Pemasangan 1 m2 Rangka atap baja ringan Main Truss C75 Reng 0,45, penutup atap genteng tanah bentuk
atap limas
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.247 67,500.00 16,672.50
Tukang Besi profil L.02 OH 0.176 72,500.00 12,760.00
Kepala Tukang Besi profil L.03 OH 0.117 77,500.00 9,067.50
Mandor L,04 OH 0.002 80,000.00 197.60
JUMLAH TENAGA KERJA 38,697.60
B. BAHAN
Main truss C75/75 m' 3.650 15,416.67 56,270.83
Roof bottom RT 33-0,45 m' 6.250 7,500.00 46,875.00
Self drilling screw dia 6x20 mm bh 23.930 500.00 11,964.91
Self drilling screw dia 4x16 mm bh 15.158 250.00 3,789.47
Dinabolt dia 12-120 mm bh 1.553 1,250.00 1,940.79
Bracket bulat bh 0.253 7,500.00 1,894.74
Bracket oval bh 0.253 7,000.00 1,768.42
Cornerplat bh 0.089 5,000.00 447.37
Page 208
JUMLAH HARGA ALAT 5,000.00
D. Jumlah (A+B+C) 168,649.14
E. Profit 10% *D 16,864.91
F. Harga Satuan Pekerjaan (D+E) 185,514.05
A. 4.2.1.21.a Pemasangan 1 m2 Rangka atap baja ringan Main Truss C75 Reng 0,45, penutup atap genteng metal bentuk
atap pelana
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.247 67,500.00 16,672.50
Tukang Besi profil L.02 OH 0.176 72,500.00 12,760.00
Kepala Tukang Besi profil L.03 OH 0.117 77,500.00 9,067.50
Mandor L,04 OH 0.002 80,000.00 197.60
JUMLAH TENAGA KERJA 38,697.60
B. BAHAN
Main truss C75/75 m' 3.000 15,416.67 46,250.00
Roof bottom RT 33-0,45 m' 3.965 7,500.00 29,737.50
Self drilling screw dia 6x20 mm bh 21.930 500.00 10,964.91
Self drilling screw dia 4x16 mm bh 8.553 250.00 2,138.16
Dinabolt dia 12-120 mm bh 1.053 1,250.00 1,315.79
Bracket bulat bh 0.211 7,500.00 1,578.95
Bracket oval bh 0.211 7,000.00 1,473.68
Cornerplat bh 0.079 5,000.00 394.74
A. 4.2.1.21.a Pemasangan 1 m2 Rangka atap baja ringan Main Truss C75 Reng 0,45, penutup atap genteng metal bentuk
atap limas
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.247 67,500.00 16,672.50
Tukang Besi profil L.02 OH 0.176 72,500.00 12,760.00
Kepala Tukang Besi profil L.03 OH 0.117 77,500.00 9,067.50
Mandor L,04 OH 0.002 80,000.00 197.60
JUMLAH TENAGA KERJA 38,697.60
B. BAHAN
Main truss C75/75 m' 3.100 15,416.67 47,791.67
Roof bottom RT 33-0,45 m' 4.063 7,500.00 30,468.75
Self drilling screw dia 6x20 mm bh 23.930 500.00 11,964.91
Self drilling screw dia 4x16 mm bh 8.826 250.00 2,206.58
Dinabolt dia 12-120 mm bh 1.526 1,250.00 1,907.89
Bracket bulat bh 0.253 7,500.00 1,894.74
Bracket oval bh 0.253 7,000.00 1,768.42
Cornerplat bh 0.089 5,000.00 447.37
Page 209
JUMLAH HARGA ALAT 5,000.00
D. Jumlah (A+B+C) 142,147.93
E. Profit 10% *D 14,214.79
F. Harga Satuan Pekerjaan (D+E) 156,362.72
A. 4.4.1.2. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu, camp. 1 SP : 3PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.600 67,500.00 40,500.00
Tukang Batu L.02 OH 0.200 72,500.00 14,500.00
Kepala tukang L.03 OH 0.020 77,500.00 1,550.00
Mandor L,04 OH 0.030 80,000.00 2,400.00
JUMLAH TENAGA KERJA 58,950.00
B. BAHAN
Bata merah buah 140.000 900.00 126,000.00
Semen portland kg 32.950 1,125.00 37,068.75
Pasir pasang m3 0.091 180,000.00 16,380.00
JUMLAH HARGA BAHAN 179,448.75
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 238,398.75
E. Profit 10% *D 23,839.88
F. Harga Satuan Pekerjaan (D+E) 262,238.63
A. 4.4.1.3. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu, camp. 1 SP : 4PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.600 67,500.00 40,500.00
Tukang Batu L.02 OH 0.200 72,500.00 14,500.00
Page 210
Kepala tukang L.03 OH 0.020 77,500.00 1,550.00
Mandor L,04 OH 0.030 80,000.00 2,400.00
JUMLAH TENAGA KERJA 58,950.00
B. BAHAN
Bata merah buah 140.000 900.00 126,000.00
Semen portland kg 26.550 1,125.00 29,868.75
Pasir pasang m3 0.093 180,000.00 16,740.00
JUMLAH HARGA BAHAN 172,608.75
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 231,558.75
E. Profit 10% *D 23,155.88
F. Harga Satuan Pekerjaan (D+E) 254,714.63
A. 4.4.1.4. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu, camp. 1 SP : 5PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.600 67,500.00 40,500.00
Tukang Batu L.02 OH 0.200 72,500.00 14,500.00
Kepala tukang L.03 OH 0.020 77,500.00 1,550.00
Mandor L,04 OH 0.030 80,000.00 2,400.00
JUMLAH TENAGA KERJA 58,950.00
B. BAHAN
Bata merah buah 140.000 900.00 126,000.00
Semen portland kg 22.220 1,125.00 24,997.50
Pasir pasang m3 0.102 180,000.00 18,360.00
JUMLAH HARGA BAHAN 169,357.50
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 228,307.50
E. Profit 10% *D 22,830.75
F. Harga Satuan Pekerjaan (D+E) 251,138.25
A. 4.4.1.5. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu, camp. 1 SP : 6PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.600 67,500.00 40,500.00
Tukang Batu L.02 OH 0.200 72,500.00 14,500.00
Kepala tukang L.03 OH 0.020 77,500.00 1,550.00
Mandor L,04 OH 0.030 80,000.00 2,400.00
JUMLAH TENAGA KERJA 58,950.00
B. BAHAN
Bata merah buah 140.000 900.00 126,000.00
Semen portland kg 18.500 1,125.00 20,812.50
Pasir pasang m3 0.122 180,000.00 21,960.00
JUMLAH HARGA BAHAN 168,772.50
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 227,722.50
E. Profit 10% *D 22,772.25
F. Harga Satuan Pekerjaan (D+E) 250,494.75
Page 211
A. 4.4.1.6. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu, camp. 1 SP : 3KP : 10PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.600 67,500.00 40,500.00
Tukang Batu L.02 OH 0.200 72,500.00 14,500.00
Kepala tukang L.03 OH 0.020 77,500.00 1,550.00
Mandor L,04 OH 0.030 80,000.00 2,400.00
JUMLAH TENAGA KERJA 58,950.00
B. BAHAN
Bata merah buah 140.000 900.00 126,000.00
Semen portland kg 10.080 1,125.00 11,340.00
Kapur padam m3 0.0275 137,500.00 3,781.25
Pasir pasang m3 0.0925 180,000.00 16,650.00
JUMLAH HARGA BAHAN 157,771.25
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 216,721.25
E. Profit 10% *D 21,672.13
F. Harga Satuan Pekerjaan (D+E) 238,393.38
A. 4.4.1.7. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 2PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 67,500.00 20,250.00
Tukang Batu L.02 OH 0.100 72,500.00 7,250.00
Kepala tukang L.03 OH 0.010 77,500.00 775.00
Mandor L,04 OH 0.015 80,000.00 1,200.00
JUMLAH TENAGA KERJA 29,475.00
B. BAHAN
Bata merah buah 70.000 900.00 63,000.00
Semen portland kg 18.950 1,125.00 21,318.75
Pasir pasang m3 0.038 180,000.00 6,840.00
JUMLAH HARGA BAHAN 91,158.75
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 120,633.75
E. Profit 10% *D 12,063.38
F. Harga Satuan Pekerjaan (D+E) 132,697.13
A. 4.4.1.8. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 3PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 67,500.00 20,250.00
Tukang Batu L.02 OH 0.100 72,500.00 7,250.00
Kepala tukang L.03 OH 0.010 77,500.00 775.00
Mandor L,04 OH 0.015 80,000.00 1,200.00
JUMLAH TENAGA KERJA 29,475.00
B. BAHAN
Bata merah buah 70.000 900.00 63,000.00
Semen portland kg 14.370 1,125.00 16,166.25
Page 212
Pasir pasang m3 0.040 180,000.00 7,200.00
JUMLAH HARGA BAHAN 86,366.25
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 115,841.25
E. Profit 10% *D 11,584.13
F. Harga Satuan Pekerjaan (D+E) 127,425.38
A. 4.4.1.9. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 4PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 67,500.00 20,250.00
Tukang Batu L.02 OH 0.100 72,500.00 7,250.00
Kepala tukang L.03 OH 0.010 77,500.00 775.00
Mandor L,04 OH 0.015 80,000.00 1,200.00
JUMLAH TENAGA KERJA 29,475.00
B. BAHAN
Bata merah buah 70.000 900.00 63,000.00
Semen portland kg 11.500 1,125.00 12,937.50
Pasir pasang m3 0.043 180,000.00 7,740.00
JUMLAH HARGA BAHAN 83,677.50
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 113,152.50
E. Profit 10% *D 11,315.25
F. Harga Satuan Pekerjaan (D+E) 124,467.75
A. 4.4.1.10. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 5PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 67,500.00 20,250.00
Tukang Batu L.02 OH 0.100 72,500.00 7,250.00
Kepala tukang L.03 OH 0.010 77,500.00 775.00
Mandor L,04 OH 0.015 80,000.00 1,200.00
JUMLAH TENAGA KERJA 29,475.00
B. BAHAN
Bata merah buah 70.000 900.00 63,000.00
Semen portland kg 9.680 1,125.00 10,890.00
Pasir pasang m3 0.045 180,000.00 8,100.00
JUMLAH HARGA BAHAN 81,990.00
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 111,465.00
E. Profit 10% *D 11,146.50
F. Harga Satuan Pekerjaan (D+E) 122,611.50
A. 4.4.1.11. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 6PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 67,500.00 20,250.00
Page 213
Tukang Batu L.02 OH 0.100 72,500.00 7,250.00
Kepala tukang L.03 OH 0.010 77,500.00 775.00
Mandor L,04 OH 0.015 80,000.00 1,200.00
JUMLAH TENAGA KERJA 29,475.00
B. BAHAN
Bata merah buah 70.000 900.00 63,000.00
Semen portland kg 8.320 1,125.00 9,360.00
Pasir pasang m3 0.049 180,000.00 8,820.00
JUMLAH HARGA BAHAN 81,180.00
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 110,655.00
E. Profit 10% *D 11,065.50
F. Harga Satuan Pekerjaan (D+E) 121,720.50
A. 4.4.1.12. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 8PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 67,500.00 20,250.00
Tukang Batu L.02 OH 0.100 72,500.00 7,250.00
Kepala tukang L.03 OH 0.010 77,500.00 775.00
Mandor L,04 OH 0.015 80,000.00 1,200.00
JUMLAH TENAGA KERJA 29,475.00
B. BAHAN
Bata merah buah 70.000 900.00 63,000.00
Semen portland kg 6.500 1,125.00 7,312.50
Pasir pasang m3 0.050 180,000.00 9,000.00
JUMLAH HARGA BAHAN 79,312.50
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 108,787.50
E. Profit 10% *D 10,878.75
F. Harga Satuan Pekerjaan (D+E) 119,666.25
A. 4.4.1.13. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SP : 3KP : 10PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 67,500.00 20,250.00
Tukang Batu L.02 OH 0.100 72,500.00 7,250.00
Kepala tukang L.03 OH 0.010 77,500.00 775.00
Mandor L,04 OH 0.015 80,000.00 1,200.00
JUMLAH TENAGA KERJA 29,475.00
B. BAHAN
Bata merah buah 70.000 900.00 63,000.00
Semen portland kg 4.500 1,125.00 5,062.50
Kapur padam m3 0.015 137,500.00 2,062.50
Pasir pasang m3 0.050 180,000.00 9,000.00
JUMLAH HARGA BAHAN 79,125.00
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 108,600.00
Page 214
E. Profit 10% *D 10,860.00
F. Harga Satuan Pekerjaan (D+E) 119,460.00
A. 4.4.1.14. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SM : 1KP : 1PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 67,500.00 20,250.00
Tukang Batu L.02 OH 0.100 72,500.00 7,250.00
Kepala tukang L.03 OH 0.010 77,500.00 775.00
Mandor L,04 OH 0.015 80,000.00 1,200.00
JUMLAH TENAGA KERJA 29,475.00
B. BAHAN
Bata merah buah 70.000 900.00 63,000.00
Semen merah m3 0.018 1,125.00 20.25
Kapur padam m3 0.018 137,500.00 2,475.00
Pasir pasang m3 0.018 180,000.00 3,240.00
JUMLAH HARGA BAHAN 68,735.25
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 98,210.25
E. Profit 10% *D 9,821.03
F. Harga Satuan Pekerjaan (D+E) 108,031.28
A. 4.4.1.15. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu, camp. 1 SM : 1KP : 2PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 67,500.00 20,250.00
Tukang Batu L.02 OH 0.100 72,500.00 7,250.00
Kepala tukang L.03 OH 0.010 77,500.00 775.00
Mandor L,04 OH 0.015 80,000.00 1,200.00
JUMLAH TENAGA KERJA 29,475.00
B. BAHAN
Bata merah buah 70.000 900.00 63,000.00
Semen merah m3 0.014 330,000.00 4,620.00
Kapur padam m3 0.014 137,500.00 1,925.00
Pasir pasang m3 0.028 180,000.00 5,040.00
JUMLAH HARGA BAHAN 74,585.00
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 104,060.00
E. Profit 10% *D 10,406.00
F. Harga Satuan Pekerjaan (D+E) 114,466.00
Page 215
B. BAHAN
HB - 20 buah 12.500 5,500.00 68,750.00
Semen portland kg 30.320 1,125.00 34,110.00
Pasir pasang m3 0.728 180,000.00 131,040.00
Besi angker 8 mm kg 0.280 9,000.00 2,520.00
JUMLAH HARGA BAHAN 236,420.00
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 273,522.50
E. Profit 10% *D 27,352.25
F. Harga Satuan Pekerjaan (D+E) 300,874.75
Page 216
A. 4.4.1.19. Pemasangan 1 m2 dinding conblock HB 15, camp. 1 SP : 4PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.320 67,500.00 21,600.00
Tukang Batu L.02 OH 0.120 72,500.00 8,700.00
Kepala tukang L.03 OH 0.012 77,500.00 930.00
Mandor L,04 OH 0.016 80,000.00 1,280.00
JUMLAH TENAGA KERJA 32,510.00
B. BAHAN
HB - 15 buah 12.500 7,150.00 89,375.00
Semen portland kg 18.200 1,125.00 20,475.00
Pasir pasang m3 0.582 180,000.00 104,760.00
Besi angker 8 mm kg 0.280 9,000.00 2,520.00
JUMLAH HARGA BAHAN 217,130.00
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 249,640.00
E. Profit 10% *D 24,964.00
F. Harga Satuan Pekerjaan (D+E) 274,604.00
Page 217
Semen portland kg 12.130 1,125.00 13,646.25
Pasir pasang m3 0.388 180,000.00 69,840.00
Besi angker 8 mm kg 0.280 9,000.00 2,520.00
JUMLAH HARGA BAHAN 175,381.25
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 204,856.25
E. Profit 10% *D 20,485.63
F. Harga Satuan Pekerjaan (D+E) 225,341.88
A. 4.4.1.24. Pemasangan 1 m2 dinding bata berongga ekspose 12x11x24 cm, camp. 1 SP : 3PP
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
Page 218
A. TENAGA
Pekerja L.01 OH 0.300 67,500.00 20,250.00
Tukang Batu L.02 OH 0.150 72,500.00 10,875.00
Kepala tukang L.03 OH 0.015 77,500.00 1,162.50
Mandor L,04 OH 0.015 80,000.00 1,200.00
JUMLAH TENAGA KERJA 33,487.50
B. BAHAN
Bata berongga ekspose buah 70.000 1,780.00 124,600.00
Semen portland kg 14.000 1,125.00 15,750.00
Pasir pasang m3 0.032 180,000.00 5,760.00
JUMLAH HARGA BAHAN 146,110.00
C. PERALATAN
- -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 179,597.50
E. Profit 10% *D 17,959.75
F. Harga Satuan Pekerjaan (D+E) 197,557.25
Page 219
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 107,747.50
E. Profit 10% *D 10,774.75
F. Harga Satuan Pekerjaan (D+E) 118,522.25
B. BAHAN
1. PC Kg 15.504 1,125.00 17,442.00
2. PP m 3
0.016 180,000.00 2,880.00
JUMLAH HARGA BAHAN 20,322.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 53,809.50
E. Profit 10% *D 5,380.95
F. Harga Satuan Pekerjaan (D+E) 59,190.45
Page 220
Kepala Tukang L.03 OH 0.015 77,500.00 1,162.50
Mandor L.04 OH 0.015 80,000.00 1,200.00
JUMLAH TENAGA KERJA 33,487.50
B. BAHAN
1. PC Kg 7.776 1,125.00 8,748.00
2. PP m3 0.023 180,000.00 4,140.00
JUMLAH HARGA BAHAN 12,888.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 46,375.50
E. Profit 10% *D 4,637.55
F. Harga Satuan Pekerjaan (D+E) 51,013.05
Page 222
F. Harga Satuan Pekerjaan (D+E) 46,855.05
Page 223
2. KP m3 0.009 137,500.00 1,237.50
3. PP m3 0.009 180,000.00 1,620.00
JUMLAH HARGA BAHAN 5,827.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 41,197.50
E. Profit 10% *D 4,119.75
F. Harga Satuan Pekerjaan (D+E) 45,317.25
Page 224
Tukang Batu L.03 OH 0.200 72,500.00 14,500.00
Kepala Tukang L.03 OH 0.020 77,500.00 1,550.00
Mandor L.04 OH 0.013 80,000.00 1,040.00
JUMLAH TENAGA KERJA 34,640.00
B. BAHAN
1. PC Kg 10.368 1,125.00 11,664.00
2. PP m3 0.031 180,000.00 5,580.00
JUMLAH HARGA BAHAN 17,244.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 51,884.00
E. Profit 10% *D 5,188.40
F. Harga Satuan Pekerjaan (D+E) 57,072.40
Page 225
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.400 67,500.00 27,000.00
Tukang Batu L.03 OH 0.200 72,500.00 14,500.00
Kepala Tukang L.03 OH 0.020 77,500.00 1,550.00
Mandor L.04 OH 0.022 80,000.00 1,760.00
JUMLAH TENAGA KERJA 44,810.00
B. BAHAN
1. PC Kg 5.888 1,125.00 6,624.00
2. PP m3 0.036 180,000.00 6,480.00
JUMLAH HARGA BAHAN 13,104.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 57,914.00
E. Profit 10% *D 5,791.40
F. Harga Satuan Pekerjaan (D+E) 63,705.40
Page 226
E. Profit 10% *D 2,733.45
F. Harga Satuan Pekerjaan (D+E) 30,067.95
Page 227
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 102,810.00
E. Profit 10% *D 10,281.00
F. Harga Satuan Pekerjaan (D+E) 113,091.00
Page 228
Semen PC Kg 1.600 1,125.00 1,800.00
JUMLAH HARGA BAHAN 1,800.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 9,692.50
E. Profit 10% *D 969.25
F. Harga Satuan Pekerjaan (D+E) 10,661.75
Page 229
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.200 67,500.00 13,500.00
Tukang Batu L.03 OH 0.050 72,500.00 3,625.00
Kepala Tukang L.03 OH 0.015 77,500.00 1,162.50
Mandor L.04 OH 0.015 80,000.00 1,200.00
JUMLAH TENAGA KERJA 19,487.50
B. BAHAN
Plesteran Semen Instant zak 0.417 85,000.00 35,419.50
JUMLAH HARGA BAHAN 35,419.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 54,907.00
E. Profit 10% *D 5,490.70
F. Harga Satuan Pekerjaan (D+E) 60,397.70
Page 230
A. 4.4.3.1. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 40cm x 40cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.250 67,500.00 16,875.00
Tukang Batu L.02 OH 0.125 72,500.00 9,062.50
Kepala Tukang L.03 OH 0.013 77,500.00 1,007.50
Mandor L.04 OH 0.013 80,000.00 1,040.00
JUMLAH TENAGA KERJA 27,985.00
B. BAHAN
Ubin abu-abu Bh 6.630 12,750.00 84,532.50
Semen Portlan Kg 9.800 1,125.00 11,025.00
Pasir pasang m3 0.045 180,000.00 8,100.00
JUMLAH HARGA BAHAN 103,657.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 131,642.50
E. Profit 10% *D 13,164.25
F. Harga Satuan Pekerjaan (D+E) 144,806.75
Page 231
A. 4.4.3.3. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 20cm x20cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.270 67,500.00 18,225.00
Tukang Batu L.02 OH 0.135 72,500.00 9,787.50
Kepala Tukang L.03 OH 0.014 77,500.00 1,085.00
Mandor L.04 OH 0.014 80,000.00 1,120.00
JUMLAH TENAGA KERJA 30,217.50
B. BAHAN
Ubin abu-abu Bh 26.500 2,508.00 66,462.00
Semen Portlan Kg 10.400 1,125.00 11,700.00
Pasir pasang m3 0.045 180,000.00 8,100.00
JUMLAH HARGA BAHAN 86,262.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 116,479.50
E. Profit 10% *D 11,647.95
F. Harga Satuan Pekerjaan (D+E) 128,127.45
Page 232
JUMLAH HARGA BAHAN 87,256.27
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 116,278.77
E. Profit 10% *D 11,627.88
F. Harga Satuan Pekerjaan (D+E) 127,906.65
Page 233
A. TENAGA
Pekerja L.01 OH 0.260 -
Tukang Batu L.02 OH 0.130 -
Kepala Tukang L.03 OH 0.013 -
Mandor L.04 OH 0.013 -
JUMLAH TENAGA KERJA -
B. BAHAN
Ubin traso Bh 11.870 -
Semen Portlan Kg 10.000 -
Semen warna Kg 1.500 -
Pasir pasang m3 0.045 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 234
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 236
JUMLAH TENAGA KERJA -
B. BAHAN
Ubin teralux marmer Bh 11.870 -
Semen Portlan Kg 10.000 -
Semen warna Kg 1.500 -
Pasir pasang m3 0.045 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 237
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 238
A. 4.4.3.20. Pemasangan 1 m1 plint ubin warna ukuran 10cm x30cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.090 -
Tukang Batu L.02 OH 0.090 -
Kepala Tukang L.03 OH 0.009 -
Mandor L.04 OH 0.005 -
JUMLAH TENAGA KERJA -
B. BAHAN
Plint ubin warna Bh 3.530 -
Semen Portlan Kg 1.140 -
Semen warna Kg 0.100 -
Pasir pasang m 3
0.003 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 239
Kepala Tukang L.03 OH 0.009 -
Mandor L.04 OH 0.005 -
JUMLAH TENAGA KERJA -
B. BAHAN
Plint ubin teraso Bh 3.530 -
Semen Portlan Kg 1.140 -
Semen warna Kg 0.100 -
Pasir pasang m3 0.003 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 240
Semen warna Kg 0.100 -
Pasir pasang m 3
0.003 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 241
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 242
A. 4.4.3.29. Pemasangan 1 m1 plint ubin teralux marmer ukuran 10cm x40cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.090 -
Tukang Batu L.02 OH 0.090 -
Kepala Tukang L.03 OH 0.009 -
Mandor L.04 OH 0.005 -
JUMLAH TENAGA KERJA -
B. BAHAN
Plint teralux marmer Bh 2.650 -
Semen Portlan Kg 1.140 -
Semen warna Kg 0.100 -
Pasir pasang m 3
0.003 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 243
Kepala Tukang L.03 OH 0.018 -
Mandor L.04 OH 0.018 -
JUMLAH TENAGA KERJA -
B. BAHAN
Teraso cor m3 0.036 -
Semen warna Kg 0.100 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
A. 4.4.3.33. Pemasangan 1 m2 lantai keramik artistik 10cm x10cm atau 5cm x 20cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.700 -
Tukang Batu L.02 OH 0.350 -
Kepala Tukang L.03 OH 0.035 -
Mandor L.04 OH 0.035 -
JUMLAH TENAGA KERJA -
B. BAHAN
Ubin keramik Bh 106.000 -
Semen Portlan Kg 8.190 -
Pasir pasang m3 0.045 -
Semen warna Kg 3.200 -
Page 244
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 245
A. 4.4.3.35. Pemasangan 1 m2 lantai keramik ukuran 30cm x 30cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.700 67,500.00 47,250.00
Tukang Batu L.02 OH 0.350 72,500.00 25,375.00
Kepala Tukang L.03 OH 0.035 77,500.00 2,712.50
Mandor L.04 OH 0.035 80,000.00 2,800.00
JUMLAH TENAGA KERJA 78,137.50
B. BAHAN
Ubin keramik doos 1.050 45,600.00 47,880.00
Semen Portlan Kg 10.000 1,125.00 11,250.00
Pasir pasang m3 0.045 180,000.00 8,100.00
Semen warna Kg 0.500 14,800.00 7,400.00
JUMLAH HARGA BAHAN 74,630.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 152,767.50
E. Profit 10% *D 15,276.75
F. Harga Satuan Pekerjaan (D+E) 168,044.25
Page 246
D. Jumlah ( A+B+C) 190,520.00
E. Profit 10% *D 19,052.00
F. Harga Satuan Pekerjaan (D+E) 209,572.00
A. 4.4.3.37. Pemasangan 1 m2 lantai keramik ukuran 10cm x 33cm untuk variasi/ border
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 1.050 67,500.00 70,875.00
Tukang Batu L.02 OH 0.525 72,500.00 38,062.50
Kepala Tukang L.03 OH 0.053 77,500.00 4,107.50
Mandor L.04 OH 0.053 80,000.00 4,240.00
JUMLAH TENAGA KERJA 117,285.00
B. BAHAN
Ubin keramik Bh 33.000 1,800.00 59,400.00
Semen Portlan Kg 9.800 1,125.00 11,025.00
Pasir pasang m3 0.045 180,000.00 8,100.00
Semen warna Kg 4.370 14,800.00 64,676.00
Page 247
JUMLAH HARGA BAHAN 143,201.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 260,486.00
E. Profit 10% *D 26,048.60
F. Harga Satuan Pekerjaan (D+E) 286,534.60
Page 248
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 15,712.50
B. BAHAN
Plint keramik Bh 10.600 850.00 9,010.00
Semen Portlan Kg 1.140 1,125.00 1,282.50
Pasir pasang m3 0.003 180,000.00 540.00
Semen warna Kg 0.050 14,800.00 740.00
JUMLAH HARGA BAHAN 11,572.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 27,285.00
E. Profit 10% *D 2,728.50
F. Harga Satuan Pekerjaan (D+E) 30,013.50
Page 249
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.075 67,500.00 5,062.50
Tukang Batu L.02 OH 0.075 72,500.00 5,437.50
Kepala Tukang L.03 OH 0.008 77,500.00 581.25
Mandor L.04 OH 0.038 80,000.00 3,040.00
JUMLAH TENAGA KERJA 14,121.25
B. BAHAN
Plint keramik Bh 5.300 12,500.00 66,250.00
Semen Portlan Kg 1.140 1,125.00 1,282.50
Pasir pasang m3 0.003 180,000.00 540.00
Semen warna Kg 0.100 14,800.00 1,480.00
JUMLAH HARGA BAHAN 69,552.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 83,673.75
E. Profit 10% *D 8,367.38
F. Harga Satuan Pekerjaan (D+E) 92,041.13
Page 250
F. Harga Satuan Pekerjaan (D+E) -
Page 251
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 252
Pasir pasang m3 0.018 -
Semen warna Kg 1.940 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 253
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.900 -
Tukang Batu L.02 OH 0.450 -
Kepala Tukang L.03 OH 0.045 -
Mandor L.04 OH 0.045 -
JUMLAH TENAGA KERJA -
B. BAHAN
Keramik artistik Bh 53.000 -
Semen portlan Kg 9.300 -
Pasir pasang m3 0.018 -
Semen warna Kg 2.750 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 254
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 207,012.00
E. Profit 10% *D 20,701.20
F. Harga Satuan Pekerjaan (D+E) 227,713.20
Page 255
Kepala Tukang L.03 OH 0.035 -
Mandor L.04 OH 0.035 -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata paras Bh 1.100 -
Semen portlan Kg 11.750 -
Pasir pasang m3 0.035 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 256
A. 4.4.3.60. Pemasangan 1 m2 wallpaper lebar 50cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.350 67,500.00 23,625.00
Tukang Batu L.02 OH 0.175 72,500.00 12,687.50
Kepala Tukang L.03 OH 0.017 77,500.00 1,317.50
Mandor L.04 OH 0.002 80,000.00 160.00
JUMLAH TENAGA KERJA 37,790.00
B. BAHAN
Wallpaper m 2.200 22,500.00 49,500.00
Lem Kg 0.250 68,400.00 17,100.00
JUMLAH HARGA BAHAN 66,600.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 104,390.00
E. Profit 10% *D 10,439.00
F. Harga Satuan Pekerjaan (D+E) 114,829.00
Page 257
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 258
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
A. 4.5.1.5. Pemasangan 1 m2 langit-langit tripleks ukuran ( 120 x 240 )cm, tebal 3mm, 4mm dan 6mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.100 67,500.00 6,750.00
Tukang Kayu L.02 OH 0.100 72,500.00 7,250.00
Kepala Tukang L.03 OH 0.010 77,500.00 775.00
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 15,175.00
B. BAHAN
Tripleks Lembar 0.375 57,000.00 21,375.00
Page 259
Paku tripleks Kg 0.030 20,500.00 615.00
JUMLAH HARGA BAHAN 21,990.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 37,165.00
E. Profit 10% *D 3,716.50
F. Harga Satuan Pekerjaan (D+E) 40,881.50
A. 4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board ukuran ( 120x240x9 )cm, tebal 9mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.100 67,500.00 6,750.00
Tukang Kayu L.02 OH 0.050 72,500.00 3,625.00
Kepala Tukang L.03 OH 0.005 77,500.00 387.50
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 11,162.50
B. BAHAN
Gypsum board Lembar 0.364 65,000.00 23,660.00
Paku skrup Kg 0.110 30,250.00 3,327.50
JUMLAH HARGA BAHAN 26,987.50
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 38,150.00
E. Profit 10% *D 3,815.00
F. Harga Satuan Pekerjaan (D+E) 41,965.00
A. 4.5.1.8. Pemasangan 1 m2 langit-langit akustik ukuran ( 60x120 )cm, berikut rangka alluminium
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.500 -
Tukang Besi L.02 OH 0.500 -
Kepala Tukang L.03 OH 0.050 -
Mandor L.04 OH 0.025 -
JUMLAH TENAGA KERJA -
B. BAHAN
Page 260
Profil Allum "T" m 3.600 -
Kawat dia 4mm Kg 0.150 -
Ramset Bh 1.050 -
Akustik 60 x 120 Lembar 1.500 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 261
Kepala Tukang L.03 OH 0.035 77,500.00 2,712.50
Mandor L.04 OH 0.018 80,000.00 1,440.00
JUMLAH TENAGA KERJA 53,152.50
B. BAHAN
Rangka metal hollow 40.40.2mm m1 5.000 8,500.00 42,500.00
Assesoris (perkuatan, las dll) Ls 100%*rangka 8,500.00 8,500.00
JUMLAH HARGA BAHAN 51,000.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 104,152.50
E. Profit 10% *D 10,415.25
F. Harga Satuan Pekerjaan (D+E) 114,567.75
Page 262
A. TENAGA
Pekerja L.01 OH 0.150 67,500.00 10,125.00
Tukang Kayu L.03 OH 0.075 72,500.00 5,437.50
Kepala Tukang L.11 OH 0.008 77,500.00 581.25
Mandor L.15 OH 0.008 80,000.00 640.00
JUMLAH TENAGA KERJA 16,783.75
B. BAHAN
Genteng palentong Bh 25.000 1,900.00 47,500.00
JUMLAH HARGA BAHAN 47,500.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 64,283.75
E. Profit 10% *D 6,428.38
F. Harga Satuan Pekerjaan (D+E) 70,712.13
Page 263
Tukang Kayu L.03 OH 0.075 72,500.00 5,437.50
Kepala Tukang L.11 OH 0.008 77,500.00 581.25
Mandor L.15 OH 0.008 80,000.00 640.00
JUMLAH TENAGA KERJA 16,783.75
B. BAHAN
Genteng morando natural Bh 18.000 4,125.00 74,250.00
JUMLAH HARGA BAHAN 74,250.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 91,033.75
E. Profit 10% *D 9,103.38
F. Harga Satuan Pekerjaan (D+E) 100,137.13
Page 264
Tukang Kayu L.03 OH 0.200 72,500.00 14,500.00
Kepala Tukang L.11 OH 0.020 77,500.00 1,550.00
Mandor L.15 OH 0.002 80,000.00 160.00
JUMLAH TENAGA KERJA 43,210.00
B. BAHAN
Genteng bubung Bh 5.000 6,800.00 34,000.00
Semen portlan Kg 8.000 1,125.00 9,000.00
Pasir pasang m3 0.032 180,000.00 5,760.00
JUMLAH HARGA BAHAN 48,760.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 91,970.00
E. Profit 10% *D 9,197.00
F. Harga Satuan Pekerjaan (D+E) 101,167.00
Page 265
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.140 67,500.00 9,450.00
Tukang Kayu L.03 OH 0.075 72,500.00 5,437.50
Kepala Tukang L.11 OH 0.008 77,500.00 620.00
Mandor L.15 OH 0.008 80,000.00 640.00
JUMLAH TENAGA KERJA 16,147.50
B. BAHAN
Asbes gelombang 92 x 250 Lembar 0.500 - -
Paku pancing 6 x 23 Kg 0.120 35,000.00 4,200.00
JUMLAH HARGA BAHAN 4,200.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 20,347.50
E. Profit 10% *D 2,034.75
F. Harga Satuan Pekerjaan (D+E) 22,382.25
Page 266
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.140 -
Tukang Kayu L.03 OH 0.070 -
Kepala Tukang L.11 OH 0.007 -
Mandor L.15 OH 0.007 -
JUMLAH TENAGA KERJA -
B. BAHAN
Asbes gelombang 92 x 250 Lembar 0.750 -
Paku pancing 6 x 23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 267
A. 4.5.2.14. Pemasangan 1 m2 atap asbes gelombang 1,05m x 2,40m x 4mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.140 67,500.00 9,450.00
Tukang Kayu L.03 OH 0.070 72,500.00 5,075.00
Kepala Tukang L.11 OH 0.007 77,500.00 542.50
Mandor L.15 OH 0.007 80,000.00 560.00
JUMLAH TENAGA KERJA 15,627.50
B. BAHAN
Asbes gelombang 105 x 240 Lembar 0.440 82,000.00 36,080.00
Paku pancing 6 x 23 Kg 0.120 35,000.00 4,200.00
JUMLAH HARGA BAHAN 40,280.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 55,907.50
E. Profit 10% *D 5,590.75
F. Harga Satuan Pekerjaan (D+E) 61,498.25
Page 268
A. 4.5.2.17. Pemasangan 1 m2 atap asbes gelombang 1,08m x 3,00m x 6mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.140 -
Tukang Kayu L.03 OH 0.070 -
Kepala Tukang L.11 OH 0.007 -
Mandor L.15 OH 0.007 -
JUMLAH TENAGA KERJA -
B. BAHAN
Asbes gelombang 92 x 250 Lembar 0.370 -
Paku pancing 6 x 23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 269
F. Harga Satuan Pekerjaan (D+E) -
Page 270
E. Profit 10% *D 18,850.00
F. Harga Satuan Pekerjaan (D+E) 207,350.00
Page 271
D. Jumlah ( A+B+C) 103,780.00
E. Profit 10% *D 10,378.00
F. Harga Satuan Pekerjaan (D+E) 114,158.00
Page 272
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 99,612.50
E. Profit 10% *D 9,961.25
F. Harga Satuan Pekerjaan (D+E) 109,573.75
Page 273
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 125,375.00
E. Profit 10% *D 12,537.50
F. Harga Satuan Pekerjaan (D+E) 137,912.50
A. 4.5.2.32. Pemasangan 1 m2 atap genteng metal berpasir uk. 0,77 x 0,8 m, tebal 0,35 mm Ex. Suryaroof
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.200 67,500.00 13,500.00
Tukang Kayu L.03 OH 0.100 72,500.00 7,250.00
Kepala Tukang L.11 OH 0.010 77,500.00 775.00
Mandor L.15 OH 0.001 80,000.00 80.00
JUMLAH TENAGA KERJA 21,605.00
B. BAHAN
Genteng metal Stone Chip Bh 1.020 117,213.11 119,557.38
Page 274
Paku biasa 1/2"-1" Kg 0.200 15,000.00 3,000.00
JUMLAH HARGA BAHAN 122,557.38
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 144,162.38
E. Profit 10% *D 14,416.24
F. Harga Satuan Pekerjaan (D+E) 158,578.61
A. 4.5.2.32. Pemasangan 1 m2 atap genteng metal berpasir uk. 0,77 x 1 m, tebal 0,4 mm Ex. Multiroof
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.200 67,500.00 13,500.00
Tukang Kayu L.03 OH 0.100 72,500.00 7,250.00
Kepala Tukang L.11 OH 0.010 77,500.00 775.00
Mandor L.15 OH 0.001 80,000.00 80.00
JUMLAH TENAGA KERJA 21,605.00
B. BAHAN
Genteng metal Stone Chip Bh 1.020 162,676.06 165,929.58
Paku biasa 1/2"-1" Kg 0.200 15,000.00 3,000.00
JUMLAH HARGA BAHAN 168,929.58
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 190,534.58
E. Profit 10% *D 19,053.46
F. Harga Satuan Pekerjaan (D+E) 209,588.04
Page 275
Genteng bubung galzuur Ex. KIA Bh 3.000 22,000.00 66,000.00
Semen portlan Kg 8.000 1,125.00 9,000.00
Pasir pasang m3 0.032 180,000.00 5,760.00
JUMLAH HARGA BAHAN 80,760.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 123,970.00
E. Profit 10% *D 12,397.00
F. Harga Satuan Pekerjaan (D+E) 136,367.00
Page 276
Tukang Kayu L.03 OH 0.200 72,500.00 14,500.00
Kepala Tukang L.11 OH 0.020 77,500.00 1,550.00
Mandor L.15 OH 0.020 80,000.00 1,600.00
JUMLAH TENAGA KERJA 44,650.00
B. BAHAN
Nok genteng beton Bh 3.500 21,300.00 74,550.00
Paku biasa 1/2"-1" Kg 0.050 15,000.00 750.00
Semen PC Kg 10.800 1,125.00 12,150.00
Pasir pasang m3 0.032 180,000.00 5,760.00
Semen warna Kg 1.000 14,800.00 14,800.00
JUMLAH HARGA BAHAN 108,010.00
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) 152,660.00
E. Profit 10% *D 15,266.00
F. Harga Satuan Pekerjaan (D+E) 167,926.00
Page 277
A. 4.5.2.38. Pemasangan 1 m1 nok sirap
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja L.01 OH 0.125 -
Tukang Kayu L.03 OH 0.250 -
Kepala Tukang L.11 OH 0.025 -
Mandor L.15 OH 0.006 -
JUMLAH TENAGA KERJA -
B. BAHAN
Seng plat 3 x 6" Lembar 0.400 -
Paku biasa 1/2"-1" Kg 0.050 -
Paku biasa 2"-5" Kg 0.050 -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT -
D. Jumlah ( A+B+C) -
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 278
F. Harga Satuan Pekerjaan (D+E) 39,745.75
Page 279
F. Harga Satuan Pekerjaan (D+E) 24,340.25
A. 4.6.1.2 Pembuatan dan pemasangan 1m3 kusen pintu dan kusen jendela, kayu bengkirei
A. 4.6.1.2 Pembuatan dan pemasangan 1m3 kusen pintu dan kusen jendela, kayu kamper
Page 280
Balok kayu kamper m3 1.200 11,400,000.00 13,680,000.00
Paku 10 cm kg 1.250 15,000.00 18,750.00
Lem kayu kg 1.000 15,100.00 15,100.00
JUMLAH HARGA BAHAN 13,713,850.00
C. PERALATAN
A. 4.6.1.2 Pembuatan dan pemasangan 1m3 kusen pintu dan kusen jendela, kayu lama
A. 4.6.1.3 Pembuatan dan pemasangan 1m2 pintu klamp standar kayu bengkirei
A. 4.6.1.4 Pembuatan dan pemasangan 1m2 pintu klamp sederhana kayu kamper
Page 281
A. TENAGA
Pekerja L.01 OH 0.350 67,500.00 23,625.00
Tukang kayu L.03 OH 1.050 72,500.00 76,125.00
Kepala Tukang L.03 OH 0.105 77,500.00 8,137.50
Mandor L.04 OH 0.018 80,000.00 1,440.00
JUMLAH TENAGA KERJA 109,327.50
B. BAHAN
Papan kayu kamper m3 0.040 12,540,000.00 501,600.00
Paku 5-7 cm kg 0.050 15,000.00 750.00
-
JUMLAH HARGA BAHAN 502,350.00
C. PERALATAN
A. 4.6.1.5 Pembuatan dan pemasangan 1m2 daun pintu panel, kayu jati
A. 4.6.1.5 Pembuatan dan pemasangan 1m2 daun pintu panel, kayu bengkirei
Page 282
A. 4.6.1.5 Pembuatan dan pemasangan 1m2 daun pintu panel, kayu kamper
A. 4.6.1.6 Pembuatan dan pemasangan 1m2 pintu dan jendela kaca, kayu jati
A. 4.6.1.6 Pembuatan dan pemasangan 1m2 pintu dan jendela kaca, kayu bengkirei
Page 283
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 623,690.00
E. Profit 10% *D 62,369.00
F. Harga Satuan Pekerjaan (D+E) 686,059.00
A. 4.6.1.6 Pembuatan dan pemasangan 1m2 pintu dan jendela kaca, kayu kamper
A. 4.6.1.7Pembuatan dan pemasangan 1m2 pintu dan jendela jalusi kayu jati
A. 4.6.1.7Pembuatan dan pemasangan 1m2 pintu dan jendela jalusi kayu bengkirei
Page 284
B. BAHAN
Papan kayu bengkirei m3 0.064 15,390,000.00 984,960.00
Lem Kayu kg 0.500 15,100.00 7,550.00
- -
JUMLAH HARGA BAHAN 992,510.00
C. PERALATAN
A. 4.6.1.7Pembuatan dan pemasangan 1m2 pintu dan jendela jalusi kayu kamper
A. 4.6.1.8 Pembuatan 1m2 daun pintu plywood rangkap, rangka kayu kruing tertutup
A. 4.6.1.9 Pembuatan 1m2 daun pintu plywood rangkap, rangka expose kayu kamper
Page 285
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.800 67,500.00 54,000.00
Tukang Kayu L.03 OH 2.400 72,500.00 174,000.00
Kepala Tukang L.03 OH 0.240 77,500.00 18,600.00
Mandor L.04 OH 0.040 80,000.00 3,200.00
JUMLAH TENAGA KERJA 249,800.00
B. BAHAN
Papan kayu kamper m3 0.026 12,540,000.00 321,024.00
Paku 1-2,5 cm kg 0.030 20,500.00 615.00
Lem Kayu kg 0.500 15,100.00 7,550.00
Plywood tebal 4mm uk 90x220 cm lembar 1.000 62,700.00 62,700.00
JUMLAH HARGA BAHAN 391,889.00
C. PERALATAN
Page 286
D. Jumlah (A+B+C) 68,901.60
E. Profit 10% *D 6,890.16
F. Harga Satuan Pekerjaan (D+E) 75,791.76
A. 4.6.1.12 Pemasangan 1m2 teakwood rangkap lapis formika, rangka expose kayu kamper
Page 287
Papan kayu kamper m3 0.025 12,540,000.00 313,500.00
Paku 1-2,5 cm kg 0.030 20,500.00 615.00
Lem Kayu kg 0.800 15,100.00 12,080.00
Teakwood tebal 4mm uk 90x220 cm lembar 1.000 160,000.00 160,000.00
Formika lembar 0.500 102,600.00 51,300.00
Page 288
A. 4.6.1.13. Pemasangan 1m3 konstruksi kuda kuda konvensional, kayu lama
Page 289
JUMLAH HARGA BAHAN 16,504,875.00
C. PERALATAN
A. 4.6.1.16. Pemasangan 1m2 rangka atap genteng press palentong/kodok, kaso ky bengkirei reng ky bengkirei
Page 290
Tukang kayu L.03 OH 0.100 72,500.00 7,250.00
Kepala Tukang L.03 OH 0.010 77,500.00 775.00
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 15,175.00
B. BAHAN
Kaso-kaso 5 x 7 cm, BK m3 0.014 14,820,000.00 207,480.00
Reng 2 x 3cm, BK m3 0.0036 5,000,000.00 18,000.00
Paku 5 dan 10 cm kg 0.250 15,000.00 3,750.00
- -
JUMLAH HARGA BAHAN 229,230.00
C. PERALATAN
A. 4.6.1.16. Pemasangan 1m2 rangka atap genteng press palentong/kodok, kaso ky kruing reng ky kruing
A. 4.6.1.16. Pemasangan 1m2 rangka atap genteng press palentong/kodok, kaso ky kruing reng ky jati
Page 291
F. Harga Satuan Pekerjaan (D+E) 197,565.50
A. 4.6.1.17. Pemasangan 1m2 rangka atap genteng beton/Morando, kaso ky bengkirei, reng ky bengkirei
A. 4.6.1.17. Pemasangan 1m2 rangka atap genteng beton/Morando, kaso ky kruing, reng ky kruing
A. 4.6.1.17. Pemasangan 1m2 rangka atap genteng beton/Morando, kaso ky kruing, reng ky jati
Page 292
Kaso-kaso 5 x 7 cm, Kruing m3 0.014 9,120,000.00 127,680.00
Reng 3 x 4cm, jati m3 0.0057 9,166,666.67 52,250.00
Paku 5 - 10 cm kg 0.250 15,000.00 3,750.00
- -
JUMLAH HARGA BAHAN 183,680.00
C. PERALATAN
Page 293
Kepala Tukang L.03 OH 0.720 77,500.00 55,800.00
Mandor L.04 OH 0.120 80,000.00 9,600.00
JUMLAH TENAGA KERJA 749,400.00
B. BAHAN
Besi strip tebal 5 mm kg 15.0 12,500.00 187,500.00
Paku 12 cm kg 3.000 15,000.00 45,000.00
Page 294
E. Profit 10% *D 14,330.00
F. Harga Satuan Pekerjaan (D+E) 157,630.00
Page 295
- -
JUMLAH HARGA BAHAN 70,050.00
C. PERALATAN
A. 4.6.1.20. Pemasangan 1m2 rangka langit-langit miring (100 x 100), cm kayu meranti
Page 296
Kepala Tukang L.03 OH 0.020 77,500.00 1,550.00
Mandor L.04 OH 0.005 80,000.00 400.00
JUMLAH TENAGA KERJA 23,200.00
B. BAHAN
Papan kayu bengkirei m3 0.011 15,390,000.00 166,212.00
Paku 5 - 7 cm kg 0.100 15,000.00 1,500.00
- -
JUMLAH HARGA BAHAN 167,712.00
C. PERALATAN
Page 297
A. 4.6.1.22. Pemasangan 1m' lisplank ukuran (2 x 20), cm GRC
A. 4.6.1.23. Pemasangan 1m2 rangka dinding pemisah (60 x 120), cm kayu kruing
Page 298
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 335,875.00
E. Profit 10% *D 33,587.50
F. Harga Satuan Pekerjaan (D+E) 369,462.50
A. 4.6.1.24. Pemasangan 1m2 dinding pemisah teakwood rangkap, rangka kayu kruing
A. 4.6.1.25. Pemasangan 1m2 dinding pemisah plywood rangkap, rangka kayu kruing
Page 299
Kepala Tukang L.03 OH 0.180 77,500.00 13,950.00
Mandor L.04 OH 0.030 80,000.00 2,400.00
JUMLAH TENAGA KERJA 187,350.00
B. BAHAN
Papan kayu jati m3 0.007 17,490,400.00 122,432.80
Paku 5 - 10 cm kg 0.100 15,000.00 1,500.00
Paku skrup 10 cm kg 0.150 30,250.00 4,537.50
A. 4.6.1.27. Pemasangan 1m2 dinding lambrisering dari plywood ukuran (120 x 240)
Page 300
F. Harga Satuan Pekerjaan (D+E) 153,843.25
Page 301
JUMLAH TENAGA KERJA 41,200.00
B. BAHAN
Kunci tanam kecil buah 1.000 108,300.00 108,300.00
Page 302
Kepala Tukang L.03 OH 0.015 77,500.00 1,162.50
Mandor L.04 OH 0.001 80,000.00 64.00
JUMLAH TENAGA KERJA 13,114.00
B. BAHAN
Engsel pintu buah 1.000 34,200.00 34,200.00
JUMLAH HARGA BAHAN 34,200.00
C. PERALATAN
Page 303
Tukang kayu L.02 OH 0.150 72,500.00 10,875.00
Kepala Tukang L.03 OH 0.015 77,500.00 1,162.50
Mandor L.04 OH 0.008 80,000.00 640.00
JUMLAH TENAGA KERJA 13,690.00
B. BAHAN
Spring knip buah 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 15,000.00
C. PERALATAN
Page 304
Pekerja L.01 OH 0.020 67,500.00 1,350.00
Tukang kayu L.02 OH 0.200 72,500.00 14,500.00
Kepala Tukang L.03 OH 0.020 77,500.00 1,550.00
Mandor L.04 OH 0.001 80,000.00 80.00
JUMLAH TENAGA KERJA 17,480.00
B. BAHAN
Kunci slot bh 1.000 125,000.00 125,000.00
JUMLAH HARGA BAHAN 125,000.00
C. PERALATAN
Page 305
A. TENAGA
Pekerja L.01 OH 0.060 67,500.00 4,050.00
Tukang kayu L.02 OH 0.600 72,500.00 43,500.00
Kepala Tukang L.03 OH 0.060 77,500.00 4,650.00
Mandor L.04 OH 0.003 80,000.00 240.00
JUMLAH TENAGA KERJA 52,440.00
B. BAHAN
Rel pintu sorong set 1.000 175,000.00 175,000.00
JUMLAH HARGA BAHAN 175,000.00
C. PERALATAN
Page 306
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.015 67,500.00 1,012.50
Tukang kayu L.02 OH 0.150 72,500.00 10,875.00
Kepala Tukang L.03 OH 0.015 77,500.00 1,162.50
Mandor L.04 OH 0.001 80,000.00 64.00
JUMLAH TENAGA KERJA 13,114.00
B. BAHAN
Kaca tebal 5mm m2 1.100 113,100.00 124,410.00
Sealant kg 0.050 36,500.00 1,825.00
JUMLAH HARGA BAHAN 126,235.00
C. PERALATAN
Page 307
F. Harga Satuan Pekerjaan (D+E) -
Page 308
E. Profit 10% *D -
F. Harga Satuan Pekerjaan (D+E) -
Page 309
D. Jumlah (A+B+C) 1,852.50
E. Profit 10% *D 185.25
F. Harga Satuan Pekerjaan (D+E) 2,037.75
A. 4.7.1.4. 1 M2 Pengecatan bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat)
A. 4.7.1.5. 1 M2 Pengecatan bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 3 lapis cat penutup)
Page 310
B. BAHAN
Cat manie kg 0.200 34,200.00 6,840.00
Plamuur kg 0.150 34,200.00 5,130.00
Cat dasar kg 0.170 74,100.00 12,597.00
Cat penutup kg 0.350 74,100.00 25,935.00
Kuas bh 0.010 12,000.00 120.00
Pengencer kg 0.030 22,800.00 684.00
Ampelas lbr 0.200 2,000.00 400.00
JUMLAH HARGA BAHAN 51,706.00
C. PERALATAN
Page 311
Harga Satuan (Rp) Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 67,500.00 6,750.00
Mandor L.04 OH 0.006 80,000.00 480.00
JUMLAH TENAGA KERJA 7,230.00
B. BAHAN
Residu atau ter liter 0.350 22,800.00 7,980.00
JUMLAH HARGA BAHAN 7,980.00
C. PERALATAN
A. 4.7.1.10. 1 M2 Pengecatan tembok baru Interior(1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
Page 312
F. Harga Satuan Pekerjaan (D+E) 21,346.33
A. 4.7.1.11. 1 M2 Pengecatan tembok lama Interior ( 1 lapis cat dasar, 2 lapis cat penutup)
A. 4.7.1.10. 1 M2 Pengecatan tembok baru Exterior (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
A. 4.7.1.11. 1 M2 Pengecatan tembok lama Exterior ( 1 lapis cat dasar, 2 lapis cat penutup)
Page 313
C. PERALATAN
Page 314
B. BAHAN
Kalkarim kg 0.100 12,000.00 1,200.00
Page 315
A. TENAGA
Pekerja L.01 OH 0.020 67,500.00 1,350.00
Tukang cat L.02 OH 0.200 72,500.00 14,500.00
Kepala Tukang L.03 OH 0.020 77,500.00 1,550.00
Mandor L.04 OH 0.003 80,000.00 200.00
JUMLAH TENAGA KERJA 17,600.00
B. BAHAN
Wallpaper m2 1.200 25,000.00 30,000.00
Lem kg 0.200 68,400.00 13,680.00
Page 316
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 25,420.25
E. Profit 10% *D 2,542.03
F. Harga Satuan Pekerjaan (D+E) 27,962.28
Page 317
A. 4.7.1.19. 1 M2 Pengecatan permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir
A. 4.7.1.21. 1 M2 Pengecatan permukaan baja galvanis secara semprot sistem 3 lapis cat mutakhir
Page 318
Cat dasar kg 0.300
JUMLAH HARGA BAHAN -
C. PERALATAN
Page 319
ANALISA HARGA SATUAN PEKERJAAN KONSTRUKSI
BANGUNAN GEDUNG DAN PERUMAHAN
TAHUN 2019
SNI
Page 320
1 m3 Membongkar beton bertulang SNI : 2002
6.667 OH Pekerja Rp 67,500.00 Rp 450,022.50
TENAGA
0.333 OH Mandor Rp 80,000.00 Rp 26,640.00
JUMLAH Rp 476,662.50
JASA 10% Rp 47,666.25
HARGA SATUAN Rp 524,328.75
Page 321
JUMLAH Rp 26,437.50
JASA 10% Rp 2,643.75
HARGA SATUAN Rp 29,081.25
Page 322
HARGA GYPSUM
HARGA GRC