HARGA UPAH
NO URAIAN SATUAN UPAH UPAH
ORANG/JAM ORANG/HARI
I BAHAN KACA
1 Kaca Polos 2 mm ( ASAHI ) m2 75,900.00
2 Kaca Polos 3 mm ( ASAHI ) m2 96,200.00
3 Kaca Polos 5 mm ( ASAHI ) m2 122,100.00
4 Kaca Polos 8 mm ( ASAHI ) m2 201,500.00
5 Kaca Rayband 5 mm ( ASAHI ) m2 163,600.00
6 Kaca Rayband 8 mm ( ASAHI ) m2 355,800.00
7 Kaca Rayband 12 mm ( ASAHI ) m2 689,700.00
8 Kaca cermin 5 mm m2 165,600.00
9 Kaca cermin 6 mm m2 205,100.00
10 Kaca cermin 8 mm m2 257,800.00
11 Kaca Patri Lokal Terpasang ( ASAHI ) m2 1,783,300.00
12 Kaca Patri Ex Luar Negeri Terpasang m2 3,768,300.00
13 Kaca 6 mm Gravver m2 1,390,300.00
14 Glass Block DN 20 x 20 ( Kedawung ) bh 24,200.00
15 Glass Block DN 20 x 20 Ex LN bh 138,300.00
16 Sealant kg 233,000.00
17 Jendela Nako bh 120,200.00
K BAHAN PERPIPAAN
1 Besi Pipa Untuk Hydrant BSP 1" bt 183,500.00
2 Besi Pipa Untuk Hydrant BSP 1.25" bt 231,300.00
3 Besi Pipa Untuk Hydrant BSP 1.5" bt 327,800.00
4 Besi Pipa Untuk Hydrant BSP 2" bt 387,000.00
5 Besi Pipa Untuk Hydrant BSP 2.5" bt 483,500.00
6 Besi Pipa Untuk Hydrant BSP 3" bt 654,500.00
7 Besi Pipa Untuk Hydrant BSP 4" bt 956,600.00
8 Besi Pipa Untuk Hydrant BSP 6" bt 1,565,800.00
9 Besi Pipa Hitam 1" t = 2 mm bt 189,600.00
10 Besi Pipa Hitam 2" t = 2 mm bt 250,700.00
11 Besi Pipa Hitam 3" t = 2mm bt 402,500.00
12 Besi Pipa Hitam 4" t = 2 mm bt 630,500.00
13 Besi Pipa Hitam 6" t = 2 mm bt 850,000.00
14 Pipa GIP Medium A 1/2" ( 6 m1 ) bt 120,500.00
15 Pipa GIP Medium A 3/4" ( 6 m1 ) bt 175,500.00
16 Pipa GIP Medium A 1" ( 6 m1 ) bt 199,700.00
17 Pipa GIP Medium A 1 1/4" ( 6 m1 ) bt 285,500.00
18 Pipa GIP Medium A 1 1/2" ( 6 m1 ) bt 308,600.00
19 Pipa GIP Medium A 1 3/4" ( 6 m1 ) bt 359,100.00
20 Pipa GIP Medium A 2" ( 6 m1 ) bt 514,200.00
21 Pipa GIP Medium A 2 1/2" ( 6 m1 ) bt 739,500.00
22 Pipa GIP Medium A 3" ( 6 m1 ) bt 934,900.00
23 Pipa GIP Medium A 4" ( 6 m1 ) bt 950,000.00
24 Macam2 Sambungan GIP 1/2" bh 7,000.00
25 Macam2 Sambungan GIP 3/4" bh 9,500.00
26 Macam2 Sambungan GIP 1" bh 18,500.00
27 Macam2 Sambungan GIP 1 1/4" bh 21,800.00
28 Macam2 Sambungan GIP 1 1/2" bh 23,000.00
29 Macam2 Sambungan GIP 1 3/4" bh 25,000.00
30 Macam2 Sambungan GIP 2" bh 56,500.00
31 Macam2 Sambungan GIP 2 1/2" bh 66,500.00
32 Macam2 Sambungan GIP 3" bh 83,500.00
33 Macam2 Sambungan GIP 4" bh 130,500.00
34 Pipa PVC RUCIKA type AW 1/2" bt 42,500.00
35 Pipa PVC RUCIKA type AW 3/4" bt 55,500.00
36 Pipa PVC RUCIKA type AW 1" bt 65,000.00
37 Pipa PVC RUCIKA type AW 1 1/4" bt 82,500.00
38 Pipa PVC RUCIKA type AW 1 1/2" bt 110,000.00
39 Pipa PVC RUCIKA type AW 2" bt 120,000.00
40 Pipa PVC RUCIKA type AW 2 1/2" bt 170,000.00
41 Pipa PVC RUCIKA type AW 3" bt 215,000.00
42 Pipa PVC RUCIKA type AW 4" bt 360,000.00
NO URAIAN SAT. HARGA
L BAHAN SANITAIR
1 Stop Kran 3/4" KIT bh 115,000.00
2 Stop Kran 1" KIT bh 137,500.00
3 Stop Kran 1 1/2" KIT bh 230,000.00
4 Stop Kran 2" KIT bh 295,000.00
5 Stop Kran 2 1/2" KIT bh 785,000.00
6 Stop Kran 3" KIT bh 915,000.00
7 Check Valve 1/2" bh 95,500.00
8 Double Neple 1/2" bh 36,000.00
9 Water Mur 1/2" bh 44,500.00
10 Gate walve 1/2" bh 61,500.00
11 Saringan Air Lt. KM Stainless Steel/Floor Drain bh 73,500.00
12 Apooer Bath Tube bh 295,000.00
13 Kran Stainless Lokal Kait bh 51,500.00
14 Shower Dengan Tiang bh 245,000.00
15 Shower Tanpa Tiang bh 150,000.00
16 Kran Tembok Sun Eui dia. 1/2" bh 55,000.00
17 Kran Tembok ITAP dia. 1/2" bh 45,000.00
18 Kran Bebek Sun Eui 1/2" bh 160,000.00
19 Kran Bebek ITAP 1/2" bh 57,500.00
20 Kran Panas Dingin San Eui Standard bh 252,000.00
21 Bath Cape Washteren unit 2,310,000.00
22 Tempat Sabun Poslin bh 51,500.00
23 Wastafel Lengkap TOTO LW 230 unit 1,115,000.00
24 Wastafel Lengkap INA unit 800,000.00
NO URAIAN SAT. HARGA
N BAHAN MEKANIKAL
1 Jockey Pump kap. 80 gln/menit 100 m1 ( 18.6 kW ) unit 78,536,500.00
2 Electrical Pump kap. 750 gln/menit 120 m1 ( 90 kW ) unit 237,995,000.00
3 Diesel Pump kap. 750 gln/menit 120 m1 ( 105 kW ) unit 650,812,000.00
4 Presure Tank kap. 500 liter lengkap unit 40,698,000.00
5 Hydran Box dlm Gedung ( Lengkap ) unit 7,540,000.00
6 Fire House 1.5 x 30 m + nose unit 5,353,000.00
7 Exhose Fan H 360 W 60 x 60 cm unit 7,550,000.00
8 Exhose Fan H 380 W CFM 55 x 55 cm unit 6,040,500.00
9 Exhose Fan H 100 W 40 x 40 cm unit 1,212,500.00
10 AC Split 3 PK Setara TOSHIBA unit 33,871,500.00
11 AC Split 2 PK Setara TOSHIBA unit 24,119,500.00
12 AC Split 1 PK Setara TOSHIBA unit 5,692,000.00
13 Mesin AC Split DAIKIN ( Indoor / Outdoor Unit ) 1 BTU 5,000,000.00
O BAHAN ELEKTRIKAL
1 Kabel NYA 1 x 1.5 Prima ( 1 rol = 50 m' ) ROLL 105,000.00
2 Kabel NYA 1 x 2.5 Prima ( 1 rol = 50 m' ) ROLL 155,000.00
3 Kabel NYM 2 x 1.5 Prima ( 1 rol = 50 m' ) m' 7,000.00
4 Kabel NYM 3 x 1.5 Prima ( 1 rol = 50 m' ) m' 8,000.00
5 Kabel NYM 2 x 2.5 Prima ( 1 rol = 50 m' ) m' 5,000.00
6 Kabel NYM 3 x 2.5 Prima ( 1 rol = 50 m' ) m' 11,500.00
7 Kabel NYM 4 x 2.5 Prima ( 1 rol = 50 m' ) m' 8,000.00
8 Kabel NYM 2 x 4 Prima ( 1 rol = 50 m' ) m' 6,500.00
9 Kabel NYM 3 x 4 Prima ( 1 rol = 50 m' ) m' 16,000.00
10 Kabel NYM 4 x 4 Prima ( 1 rol = 50 m' ) m' 21,500.00
11 Kabel NYM 2 x 6 Supreme ( 1 rol = 50 m' ) m' 12,500.00
12 Kabel NYM 3 x 6 Supreme ( 1 rol = 50 m' ) m' 14,500.00
13 Kabel NYM 4 x 6 Supreme ( 1 rol = 50 m' ) m' 20,500.00
14 Kabel NYM 2 x 10 Supreme ( 1 rol = 50 m' ) m' 19,500.00
15 Kabel NYM 3 x 10 Supreme ( 1 rol = 50 m' ) m' 132,500.00
16 Kabel NYM 4 x 10 Supreme ( 1 rol = 50 m' ) m' 27,500.00
17 Kabel NYM 4 x 16 Supreme ( 1 rol = 50 m' ) m' 31,500.00
18 Kabel NYY 2 x 4 Supreme ( 1 rol = 50 m' ) m' 13,000.00
19 Kabel NYY 3 x 4 Supreme ( 1 rol = 50 m' ) m' 21,500.00
20 Kabel NYY 4 x 4 Supreme ( 1 rol = 50 m' ) m' 26,500.00
NO URAIAN SAT. HARGA
T ALAT TUKANG
1 Palu 0.5 kg bh 43,500.00
2 Cangkul bh 27,500.00
3 Singkup bh 46,000.00
4 Sekrop bh 55,500.00
5 Pengki bh 14,000.00
6 Linggis bh 46,000.00
7 Rool Meter 30 meter ( Bahan Plastik ) bh 111,100.00
8 Rool Meter 5 meter ( Bahan Besi ) bh 40,000.00
9 Selang Plastik untuk Water Pas dia. 0.5 cm m 1,700.00
10 Water Pas Alumunium 60 cm bh 92,500.00
V BAHAN PAGAR
1 Panel Beton Pracetak lbr 200,900.00
2 Kolom Beton Pracetak btg 290,500.00
B BIDANG PERTAMANAN
1 Aglomena batang 55,000.00
2 Bambu krisik/jepang batang 55,000.00
3 Furadan kg 26,500.00
4 Kompos/pupuk kandang batang 27,500.00
5 Matoa (2 m) batang 42,500.00
6 Palm (botol, ekor tupai, putri, dll) tinggi 2 m batang 110,500.00
7 Philo batang 83,000.00
8 Pohon pelindung (angsana, mahoni, kamboja dll) tinggi 2 m batang 27,500.00
9 Pohon perdu (kaca piring, puring, mawar, melati, dll) batang 10,500.00
10 Rumput gajah mini m2 16,500.00
Keterangan :
Harga material diatas sudah termasuk profit / keuntungan
KONSULTAN PERENCANA
CV. PRISMA CONSULT
NO URAIAN SAT. HARGA
( H. ENDJUN SUDJA'I )
Direktur
ANALISA HARGA SATUAN PEKERJAAN
HARGA SAT. JUMLAH
NO URAIAN SAT VOLUME
Rp. Rp.
1 2 3 4 5 6=4x5
A PEKERJAAN PERSIAPAN SNI 03-2835-2002
A-01 1 M Pagar Sementara dari Kayu Setinggi 2 Meter
Dolken Kayu Ø 8-10/400 Cm Btg 1.2500 30,800.00 38,500.00
Semen Portland Kg 2.5000 1,540.00 3,850.00
Pasir Beton M3 0.0050 264,140.00 1,320.70
Koral Beton 2/3 M3 0.0090 218,260.00 1,964.34
Kayu balok terentang M3 0.0720 2,705,000.00 194,760.00
Paku Biasa 2 " - 5 " Kg 0.0600 24,000.00 1,440.00
Residu Lt 0.4000 9,000.00 3,600.00
Tukang Kayu Oh 0.2000 70,000.00 14,000.00
Pekerja Oh 0.4000 67,000.00 26,800.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0200 85,000.00 1,700.00
Jumlah 289,535.04
Dibulatkan 289,530.00
A-02 1 M Pagar Sementara dari Seng Gelombang Tinggi 2 Meter
Dolken Kayu Ø 8-10/400 Cm Btg 1.2500 30,800.00 38,500.00
Semen Portland Kg 2.5000 1,540.00 3,850.00
Seng Gelombang BJLS-30 Lbr 1.2000 69,500.00 83,400.00
Pasir Beton M3 0.0050 264,140.00 1,320.70
Koral Beton 2/3 M3 0.0090 218,260.00 1,964.34
Kayu balok terentang M3 0.0720 2,705,000.00 194,760.00
Paku Biasa 2 " - 5 " Kg 0.0600 24,000.00 1,440.00
Meni besi Kg 0.4500 33,500.00 15,075.00
Tukang Kayu Oh 0.2000 70,000.00 14,000.00
Pekerja Oh 0.4000 67,000.00 26,800.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0200 85,000.00 1,700.00
Jumlah 384,410.04
Dibulatkan 384,410.00
A-03 1 M Pagar Sementara dari Kawat Duri Tinggi 1,8 Meter
Dolken Kayu Ø 8-10/400 Cm Btg 1.0000 30,800.00 30,800.00
Semen Portland Kg 2.0000 1,540.00 3,080.00
Kawat Duri Kg 2.5000 70,000.00 175,000.00
Pasir Beton M3 0.0050 264,140.00 1,320.70
Koral Beton M3 0.0090 218,260.00 1,964.34
Paku Biasa 2 " - 5 " Kg 0.0600 24,000.00 1,440.00
Tukang Kayu Oh 0.2000 70,000.00 14,000.00
Pekerja Oh 0.3000 67,000.00 20,100.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0200 85,000.00 1,700.00
Jumlah 251,005.04
Dibulatkan 251,000.00
A-04 1 M¹ Pengukuran dan Pasang Bouwplank
Kayu kaso 5/7 Albasia M3 0.0120 2,279,000.00 27,348.00
Paku Biasa 2" - 5 " Kg 0.0200 24,000.00 480.00
Kayu Papan 3/20 Albasia M3 0.0070 2,279,000.00 15,953.00
Tukang Kayu Oh 0.1000 70,000.00 7,000.00
Pekerja Oh 0.1000 67,000.00 6,700.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 58,706.00
Dibulatkan 58,700.00
1 M¹ Pengukuran
1 2 3 4 5 6=4x5
Kayu kaso 5/7 Albasia M3 0.0040 2,058,000.00 8,232.00
Paku Biasa 2" - 5 " Kg 0.0080 24,000.00 192.00
Tukang Kayu Oh 0.1000 70,000.00 7,000.00
Pekerja Oh 0.1000 67,000.00 6,700.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 23,349.00
Dibulatkan 23,340.00
A-05 1 M2 Pembuatan Kantor Sementara, dengan Lantai Plesteran
Dolken Kayu Ø 8-10/400 Cm Btg 1.2500 30,800.00 38,500.00
Kayu terentang M3 0.1800 2,705,000.00 486,900.00
Paku Biasa Kg 0.8500 24,000.00 20,400.00
Besi Strip Kg 1.1000 29,500.00 32,450.00
Semen Portland Kg 35.0000 1,540.00 53,900.00
Pasir Pasang M3 0.1500 241,390.00 36,208.50
Pasir Beton M3 0.1000 264,140.00 26,414.00
Koral Beton 2/3 M3 0.1500 218,260.00 32,739.00
Bata Merah Bh 30.0000 850.00 25,500.00
Seng Plat Lbr 0.2500 17,400.00 4,350.00
Kawat harmonika 4 cm Bh 2.0000 37,000.00 74,000.00
Kaca Polos M2 0.0800 96,200.00 7,696.00
Kunci Tanam Bh 0.1500 104,000.00 15,600.00
Plywood 120 x 240 x 0,4 cm Lbr 0.0600 145,000.00 8,700.00
Tukang Kayu Oh 2.0000 70,000.00 140,000.00
Tukang Batu Oh 1.0000 70,000.00 70,000.00
Pekerja Oh 2.0000 67,000.00 134,000.00
Kepala Tukang Oh 0.3000 80,000.00 24,000.00
Mandor Oh 0.0500 85,000.00 4,250.00
Jumlah 1,235,607.50
Dibulatkan 1,235,600.00
A-06 1 M2 Pembuatan Gudang Semen dan alat - alat
Dolken Kayu Ø 8-10/400 Cm Btg 1.7000 30,800.00 52,360.00
Kayu balok terentang M3 0.2100 2,705,000.00 568,050.00
Paku Biasa Kg 0.3000 24,000.00 7,200.00
Semen Portland Kg 10.5000 1,540.00 16,170.00
Pasir Beton M3 0.0300 264,140.00 7,924.20
Koral Beton 2/3 M3 0.0500 218,260.00 10,913.00
Seng Gelombang Bjls 30 Lbr 1.5000 69,500.00 104,250.00
Tukang Kayu Oh 2.0000 70,000.00 140,000.00
Pekerja Oh 1.0000 67,000.00 67,000.00
Kepala Tukang Oh 0.2000 80,000.00 16,000.00
Mandor Oh 0.0500 85,000.00 4,250.00
Jumlah 994,117.20
Dibulatkan 994,110.00
A-07 1 M2 Pembuatan Bedeng Buruh
Dolken Kayu Ø 8-10/400 Cm Btg 1.2500 30,800.00 38,500.00
Kayu balok terentang M3 0.1860 2,705,000.00 503,130.00
Paku Biasa Kg 0.3000 24,000.00 7,200.00
Semen Portland Kg 18.0000 1,540.00 27,720.00
Pasir Beton M3 0.0300 264,140.00 7,924.20
Koral Beton 2/3 M3 0.0500 218,260.00 10,913.00
Seng Gelombang Bjls 32 Lbr 1.5000 69,500.00 104,250.00
Tukang Kayu Oh 2.0000 70,000.00 140,000.00
Pekerja Oh 1.0000 67,000.00 67,000.00
Kepala Tukang Oh 0.2000 80,000.00 16,000.00
Mandor Oh 0.0500 85,000.00 4,250.00
Jumlah 926,887.20
Dibulatkan 926,880.00
A-08 1 M2 Membersihkan Lapangan dan Perataan
1 2 3 4 5 6=4x5
Pekerja Oh 0.1000 67,000.00 6,700.00
Mandor Oh 0.0500 85,000.00 4,250.00
Jumlah 10,950.00
Dibulatkan 10,950.00
A-09 1 M2 Pembuatan Jalan Sementara
Batu Belah 15/20 M3 0.1500 212,530.00 31,879.50
Batu Pecah 5/7 M3 0.0900 202,660.00 18,239.40
Pasir Pasang M3 0.0100 241,390.00 2,413.90
Pekerja Oh 1.0000 67,000.00 67,000.00
Mandor Oh 0.0500 85,000.00 4,250.00
Jumlah 123,782.80
Dibulatkan 123,780.00
A-10 1 M3 Bongkaran Beton Bertulang
Pekerja Oh 6.6670 67,000.00 446,689.00
Mandor Oh 0.3330 85,000.00 28,305.00
Jumlah 474,994.00
Dibulatkan 474,990.00
A-11 1 M3 Bongkaran Dinding Tembok Bata Merah
Pekerja Oh 6.6670 67,000.00 446,689.00
Mandor Oh 0.0330 85,000.00 2,805.00
Jumlah 449,494.00
Dibulatkan 449,490.00
A-12 1 M Pagar Beton Pracetak (5x50x213) Cm
Panel Beton Pracetak Lbr 0.9860 200,900.00 198,087.40
Kolom Beton Pracetak Btg 0.5250 290,500.00 152,512.50
Pasir Beton M3 0.0740 264,140.00 19,546.36
Koral 2/3 M3 0.1460 218,260.00 31,865.96
Semen Portland Kg 45.0000 1,540.00 69,300.00
Tukang Batu Oh 0.1250 70,000.00 8,750.00
Pekerja Oh 0.3750 67,000.00 25,125.00
Kepala Tukang Oh 0.0120 80,000.00 960.00
Mandor Oh 0.0190 85,000.00 1,615.00
Jumlah 507,762.22
Dibulatkan 507,760.00
A-13 1 M¹ Pagar kawat ayam tiang besi L 50.50.5, tinggi 1 m¹
Kawat ram ayam Lbr 0.4340 15,500.00 6,727.00
Besi siku L 50.50.5 Kg 6.7860 20,200.00 137,077.20
Besi pelat (1,2 x 3) mm Kg 0.0424 20,200.00 856.48
Baut Kg 4.0000 700.00 2,800.00
Semen Portland Kg 2.5000 1,540.00 3,850.00
Pasir Beton M3 0.0050 264,140.00 1,320.70
Koral 2/3 M3 0.0090 218,260.00 1,964.34
Pekerja Oh 0.3750 67,000.00 25,125.00
Tukang Batu Oh 0.1250 70,000.00 8,750.00
Kepala Tukang Oh 0.0120 80,000.00 960.00
Mandor Oh 0.0190 85,000.00 1,615.00
Jumlah 191,045.72
Dibulatkan 191,040.00
A-14 1 M2 Pagar BRC lengkap dengan tiang
BRC lengkap dengan tiang Lbr 0.4340 188,500.00 81,809.00
Semen Portland Kg 2.0000 1,540.00 3,080.00
Kawat Duri Kg 2.5000 70,000.00 175,000.00
Pasir Beton M3 0.0050 264,140.00 1,320.70
Koral Beton 2/3 M3 0.0090 218,260.00 1,964.34
Pekerja Oh 0.3750 67,000.00 25,125.00
Tukang Batu Oh 0.1250 70,000.00 8,750.00
Kepala Tukang Oh 0.0120 80,000.00 960.00
Mandor Oh 0.0190 85,000.00 1,615.00
Jumlah 299,624.04
1 2 3 4 5 6=4x5
Dibulatkan 299,620.00
A-15 1 M2 Pembuatan Stegger dari Bambu, Ukuran (40x50x20) Cm
Bambu Ø 6 -10/600 Cm Btg 1.0000 27,500.00 27,500.00
Tali Ijuk Kg 0.2500 25,800.00 6,450.00
Tukang Kayu Oh 0.0170 70,000.00 1,190.00
Pekerja Oh 0.2000 67,000.00 13,400.00
Kepala Tukang Oh 0.0020 80,000.00 160.00
Mandor Oh 0.0130 85,000.00 1,105.00
Jumlah 49,805.00
Dibulatkan 49,800.00
A-16 1 M¹ Cerucuk Bambu
Bambu Ø 7 -10 ( 400 ) Cm Btg 1.2500 27,500.00 34,375.00
Pekerja Oh 0.5000 67,000.00 33,500.00
Mandor Oh 0.0250 85,000.00 2,125.00
Jumlah 70,000.00
Dibulatkan 70,000.00
17 1 M3 Bongkaran Kuda-kuda, Gording Balok
Pekerja Oh 2.5000 67,000.00 167,500.00
Tukang Kayu Oh 1.2000 70,000.00 84,000.00
Mandor Oh 0.1200 85,000.00 10,200.00
Jumlah 261,700.00
Dibulatkan 261,700.00
18 1 M3 Bongkaran Rangka Atap, Reng dan Kaso
Pekerja Oh 0.0700 67,000.00 4,690.00
Tukang Kayu Oh 0.0200 70,000.00 1,400.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 6,515.00
Dibulatkan 6,510.00
19 1 M3 Bongkaran Genteng Lama
Pekerja Oh 0.0200 67,000.00 1,340.00
Mandor Oh 0.0100 85,000.00 850.00
Jumlah 2,190.00
Dibulatkan 2,190.00
D PEKERJAAN BETON
1 M2 Lantai kerja beton tumbuk, 1 Pc : 3 Ps : 5 Kr. tebal 5 cm
Semen Portland Kg 10.0000 1,540.00 15,400.00
Pasir Beton M3 0.0260 264,140.00 6,867.64
Koral Beton M3 0.0440 218,260.00 9,603.44
Pekerja Oh 1.1500 67,000.00 77,050.00
Tukang Batu Oh 0.0200 70,000.00 1,400.00
Kepala Tukang Oh 0.0020 80,000.00 160.00
Mandor Oh 0.0060 85,000.00 510.00
Jumlah 110,991.08
Dibulatkan 110,990.00
D-01 1 M3 Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr
Semen Portland Kg 218.0000 1,540.00 335,720.00
1 2 3 4 5 6=4x5
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.8700 218,260.00 189,886.20
Pekerja Oh 1.6500 67,000.00 110,550.00
Tukang Batu Oh 0.2500 70,000.00 17,500.00
Kepala Tukang Oh 0.0250 80,000.00 2,000.00
Mandor Oh 0.0800 85,000.00 6,800.00
Jumlah 799,809.00
Dibulatkan 799,800.00
D-02 1 M3 Beton Tumbuk, 1 Pc : 3 Ps : 6 Kr
Semen Portland Kg 197.0000 1,540.00 303,380.00
Pasir Beton M3 0.4700 264,140.00 124,145.80
Koral Beton M3 0.9400 218,260.00 205,164.40
Pekerja Oh 1.6500 67,000.00 110,550.00
Tukang Batu Oh 0.2500 70,000.00 17,500.00
Kepala Tukang Oh 0.0250 80,000.00 2,000.00
Mandor Oh 0.0800 85,000.00 6,800.00
Jumlah 769,540.20
Dibulatkan 769,540.00
D-03 1 M3 Beton Tumbuk, 1 Pc : 2 Ps : 3 Kr
Semen Portland Kg 336.0000 1,540.00 517,440.00
Pasir Beton M3 0.5400 264,140.00 142,635.60
Koral Beton M3 0.8100 218,260.00 176,790.60
Pekerja Oh 2.0000 67,000.00 134,000.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Kepala Tukang Oh 0.0350 80,000.00 2,800.00
Mandor Oh 1.0000 85,000.00 85,000.00
Jumlah 1,083,166.20
Dibulatkan 1,083,160.00
D-04 1 M3 Tiang Pancang Prestressed Beton
Semen Portland Kg 440.0000 1,540.00 677,600.00
Pasir Beton M3 0.5000 264,140.00 132,070.00
Koral Beton M3 0.8000 218,260.00 174,608.00
Rapidrant Gln 2.4600 17,500.00 43,050.00
Pekerja Oh 1.6500 67,000.00 110,550.00
Tukang Batu Oh 0.2500 70,000.00 17,500.00
Kepala Tukang Oh 0.0250 80,000.00 2,000.00
Mandor Oh 0.0800 85,000.00 6,800.00
Jumlah 1,164,178.00
Dibulatkan 1,164,170.00
D-05 1 M3 Beton Tumbuk, 1 Pc : 2 Ps : 4 Kr
Semen Portland Kg 291.0000 1,540.00 448,140.00
Pasir Beton M3 0.4700 264,140.00 124,145.80
Koral Beton M3 0.9300 218,260.00 202,981.80
Pekerja Oh 2.0000 67,000.00 134,000.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Kepala Tukang Oh 0.0350 80,000.00 2,800.00
Mandor Oh 1.0000 85,000.00 85,000.00
Jumlah 1,021,567.60
Dibulatkan 1,021,560.00
D-06 1 M' Memasang PVC Waterstop Lebar 200 mm
Waterstop Lebar 200 mm M1 1.0500 64,500.00 67,725.00
Pekerja Oh 0.0500 67,000.00 3,350.00
Tukang Batu Oh 0.0350 70,000.00 2,450.00
Kepala Tukang Oh 0.0035 80,000.00 280.00
Mandor Oh 0.0020 85,000.00 170.00
Jumlah 73,975.00
Dibulatkan 73,970.00
1 M' Memasang PVC Waterstop Lebar 150 mm
Waterstop Lebar 150 mm M1 1.0500 57,000.00 59,850.00
1 2 3 4 5 6=4x5
Pekerja Oh 0.0500 67,000.00 3,350.00
Tukang Batu Oh 0.0300 70,000.00 2,100.00
Kepala Tukang Oh 0.0030 80,000.00 240.00
Mandor Oh 0.0020 85,000.00 170.00
Jumlah 65,710.00
Dibulatkan 65,710.00
D-07 1 Kg Pembesian Dengan Besi Polos atau Besi Ulir
Besi Beton ( Polos/ Ulir ) Kg 1.0500 16,500.00 17,325.00
Kawat Beton Kg 0.0150 30,500.00 457.50
Pekerja Oh 0.0070 67,000.00 469.00
Tukang Besi Oh 0.0070 70,000.00 490.00
Kepala Tukang Oh 0.0007 80,000.00 56.00
Mandor Oh 0.0003 85,000.00 25.50
Jumlah 18,823.00
Dibulatkan 18,820.00
D-08 1 M2 Pasangan Bekisting untuk Pondasi
Kayu terentang M3 0.0400 2,950,000.00 118,000.00
Paku Biasa 2" - 5" Kg 0.3000 24,000.00 7,200.00
Pekerja Oh 0.3000 67,000.00 20,100.00
Tukang Kayu Oh 0.2600 70,000.00 18,200.00
Kepala Tukang Oh 0.0260 80,000.00 2,080.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 166,005.00
Dibulatkan 166,000.00
D-09 1 M2 Pasangan Bekisting untuk Sloof
Kayu Terentang M3 0.0450 2,950,000.00 132,750.00
Paku Biasa 2" - 5" Kg 0.3000 24,000.00 7,200.00
Pekerja Oh 0.3000 67,000.00 20,100.00
Tukang Kayu Oh 0.2600 70,000.00 18,200.00
Kepala Tukang Oh 0.0260 80,000.00 2,080.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 180,755.00
Dibulatkan 180,750.00
D-10 1 M2 Pasangan Bekisting untuk Kolom
Kayu Terentang M3 0.0400 2,950,000.00 118,000.00
Paku Biasa 2" - 5" Kg 0.4000 24,000.00 9,600.00
Kayu balok terentang M3 0.0150 2,705,000.00 40,575.00
Multiplek 9 mm 120 x 240 Lbr 0.3500 166,500.00 58,275.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 2.0000 30,800.00 61,600.00
Pekerja Oh 0.3300 67,000.00 22,110.00
Tukang Kayu Oh 0.3300 70,000.00 23,100.00
Kepala Tukang Oh 0.0330 80,000.00 2,640.00
Mandor Oh 0.0060 85,000.00 510.00
Jumlah 336,410.00
Dibulatkan 336,410.00
D-11 1 M2 Pasangan Bekisting untuk Balok
Kayu Terentang M3 0.0400 2,950,000.00 118,000.00
Paku Biasa 2" - 5" Kg 0.4000 24,000.00 9,600.00
Kayu balok terentang M3 0.0180 2,705,000.00 48,690.00
Multiplek 9 mm 120 x 240 Lbr 0.3500 166,500.00 58,275.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 2.0000 30,800.00 61,600.00
Pekerja Oh 0.3000 67,000.00 20,100.00
Tukang Kayu Oh 0.3300 70,000.00 23,100.00
Kepala Tukang Oh 0.0330 80,000.00 2,640.00
Mandor Oh 0.0060 85,000.00 510.00
Jumlah 342,515.00
Dibulatkan 342,510.00
D-12 1 M2 Pasangan Bekisting untuk Lantai
Kayu Terentang M3 0.0400 2,950,000.00 118,000.00
1 2 3 4 5 6=4x5
Paku Biasa 2" - 5" Kg 0.4000 24,000.00 9,600.00
Minyak Bekisting Ltr 0.2000 45,000.00 9,000.00
Kayu balok terentang M3 0.0150 2,705,000.00 40,575.00
Multiplek 9 mm 120 x 240 Lbr 0.3500 166,500.00 58,275.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 6.0000 30,800.00 184,800.00
Pekerja Oh 0.3000 67,000.00 20,100.00
Tukang Kayu Oh 0.3300 70,000.00 23,100.00
Kepala Tukang Oh 0.0330 80,000.00 2,640.00
Mandor Oh 0.0060 85,000.00 510.00
Jumlah 466,600.00
Dibulatkan 466,600.00
D-13 1 M2 Pasang Bekisting untuk Tangga
Kayu Terentang M3 0.0300 2,950,000.00 88,500.00
Paku Biasa 2" - 5" Kg 0.4000 24,000.00 9,600.00
Minyak Bekisting Ltr 0.1500 45,000.00 6,750.00
Kayu balok terentang M3 0.0150 2,705,000.00 40,575.00
Multiplek 9 mm 120 x 240 Lbr 0.3500 166,500.00 58,275.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 2.0000 30,800.00 61,600.00
Pekerja Oh 0.3200 67,000.00 21,440.00
Tukang Kayu Oh 0.3300 70,000.00 23,100.00
Kepala Tukang Oh 0.0330 80,000.00 2,640.00
Mandor Oh 0.0060 85,000.00 510.00
Jumlah 312,990.00
Dibulatkan 312,990.00
D-14 1 M3 Membuat Beton Cor Mutu K225
Semen Portland Kg 388.0000 1,540.00 597,520.00
Pasir Beton M3 0.6500 264,140.00 171,691.00
Koral Beton M3 0.6500 218,260.00 141,869.00
Air Ltr 215.0000 350.00 75,250.00
Pekerja Oh 6.0000 67,000.00 402,000.00
Tukang Batu Oh 1.0000 70,000.00 70,000.00
Kepala Tukang Oh 0.1000 80,000.00 8,000.00
Mandor Oh 0.3000 85,000.00 25,500.00
Jumlah 1,491,830.00
Dibulatkan 1,491,830.00
D-15 1 M3 Membuat Beton Cor Mutu K275
Semen Portland Kg 400.0000 1,540.00 616,000.00
Pasir Beton M3 0.4000 264,140.00 105,656.00
Koral Beton M3 0.8200 218,260.00 178,973.20
Air Ltr 215.0000 350.00 75,250.00
Pekerja Oh 6.0000 67,000.00 402,000.00
Tukang Batu Oh 1.0000 70,000.00 70,000.00
Kepala Tukang Oh 0.1000 80,000.00 8,000.00
Mandor Oh 0.3000 85,000.00 25,500.00
Jumlah 1,481,379.20
Dibulatkan 1,481,370.00
D-16 1 KG Besi Beton Polos
Besi Beton Polos U 24 Kg 1.1000 16,500.00 18,150.00
Kawat Beton Kg 0.0188 30,500.00 573.40
Pekerja Oh 0.0080 67,000.00 536.00
Tukang Besi Oh 0.0100 70,000.00 700.00
Kepala Tukang Oh 0.0029 80,000.00 232.00
Mandor Oh 0.0010 85,000.00 85.00
Jumlah 20,276.40
Dibulatkan 20,270.00
D-16 1 KG Besi Beton Ulir
Besi Beton Ulir 32 / 39 Kg 1.1000 22,800.00 25,080.00
Kawat Beton Kg 0.0188 30,500.00 573.40
Pekerja Oh 0.0080 67,000.00 536.00
1 2 3 4 5 6=4x5
Tukang Besi Oh 0.0100 70,000.00 700.00
Kepala Tukang Oh 0.0029 80,000.00 232.00
Mandor Oh 0.0010 85,000.00 85.00
Jumlah 27,206.40
Dibulatkan 27,200.00
D-16 1 M3 Pondasi Beton Tulang (150 kg besi+bekisting)
Kayu Terentang M3 0.2000 2,950,000.00 590,000.00
Paku Biasa 2" - 5" Kg 1.5000 24,000.00 36,000.00
Besi Beton Polos Kg 150.0000 16,500.00 2,475,000.00
Kawat Beton Kg 2.2500 30,500.00 68,625.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Pekerja Oh 3.9000 67,000.00 261,300.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 1.0400 70,000.00 72,800.00
Tukang Besi Oh 1.0500 70,000.00 73,500.00
Kepala Tukang Oh 0.2450 80,000.00 19,600.00
Mandor Oh 0.1650 85,000.00 14,025.00
Jumlah 4,440,365.60
Dibulatkan 4,440,360.00
D-17 1 M3 Sloof Beton Tulang (200 kg besi+bekisting)
Kayu Terentang M3 0.2700 2,950,000.00 796,500.00
Paku Biasa 2" - 5" Kg 2.0000 24,000.00 48,000.00
Besi Beton Polos Kg 200.0000 16,500.00 3,300,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Pekerja Oh 4.8500 67,000.00 324,950.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 1.5600 70,000.00 109,200.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.3310 80,000.00 26,480.00
Mandor Oh 0.1700 85,000.00 14,450.00
Jumlah 5,638,595.60
Dibulatkan 5,638,590.00
1 M3 Sloof Beton Tulang 15/20 cm (150 kg besi+bekisting)
Kayu Terentang M3 0.2700 2,950,000.00 796,500.00
Paku Biasa 2" - 5" Kg 2.0000 24,000.00 48,000.00
Minyak Bekisting Ltr 0.6000 45,000.00 27,000.00
Besi Beton Polos Kg 150.0000 16,500.00 2,475,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Pekerja Oh 4.8500 67,000.00 324,950.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 1.5600 70,000.00 109,200.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.3310 80,000.00 26,480.00
Mandor Oh 0.1700 85,000.00 14,450.00
Jumlah 4,840,595.60
Dibulatkan 4,840,590.00
1 M3 Sloof Beton Tulang 15/20 cm (180 kg besi+bekisting) 4 dia. 12 ring 8-15
Kayu Terentang M3 0.2700 2,950,000.00 796,500.00
Paku Biasa 2" - 5" Kg 2.0000 24,000.00 48,000.00
Besi Beton Polos Kg 180.0000 16,500.00 2,970,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
1 2 3 4 5 6=4x5
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Pekerja Oh 4.8500 67,000.00 324,950.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 1.5600 70,000.00 109,200.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.3310 80,000.00 26,480.00
Mandor Oh 0.1700 85,000.00 14,450.00
Jumlah 5,308,595.60
Dibulatkan 5,308,590.00
1 M3 Sloof Beton Tulang 20/30 cm (150 kg besi+bekisting) 4 dia. 16 ring 8-15
Kayu Terentang M3 0.2700 2,950,000.00 796,500.00
Paku Biasa 2" - 5" Kg 2.0000 24,000.00 48,000.00
Besi Beton Polos Kg 150.0000 16,500.00 2,475,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Pekerja Oh 4.8500 67,000.00 324,950.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 1.5600 70,000.00 109,200.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.3310 80,000.00 26,480.00
Mandor Oh 0.1700 85,000.00 14,450.00
Jumlah 4,813,595.60
Dibulatkan 4,813,590.00
1 M3 Sloof Beton Tulang 20/30 cm (200 kg besi+bekisting) Struktur bertingkat 6 dia. 16, 8-15
Kayu Terentang M3 0.2700 2,950,000.00 796,500.00
Paku Biasa 2" - 5" Kg 2.0000 24,000.00 48,000.00
Besi Beton Polos Kg 200.0000 16,500.00 3,300,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Pekerja Oh 4.8500 67,000.00 324,950.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 1.5600 70,000.00 109,200.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.3310 80,000.00 26,480.00
Mandor Oh 0.1700 85,000.00 14,450.00
Jumlah 5,638,595.60
Dibulatkan 5,638,590.00
1 M3 Sloof Beton Bertulang 20/40 cm (240 kg besi+bekisting) Struktur bertingkat
Kayu Terentang M3 0.2700 2,950,000.00 796,500.00
Paku Biasa 2" - 5" Kg 2.0000 24,000.00 48,000.00
Minyak Bekisting Ltr 0.6000 45,000.00 27,000.00
Besi Beton Polos Kg 240.0000 16,500.00 3,960,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Pekerja Oh 4.8500 67,000.00 324,950.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 1.5600 70,000.00 109,200.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.3310 80,000.00 26,480.00
Mandor Oh 0.1700 85,000.00 14,450.00
Jumlah 6,325,595.60
1 2 3 4 5 6=4x5
Dibulatkan 6,325,590.00
D-18 1 M3 Kolom Beton Tulang (120 kg besi+bekisting)
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Minyak Bekisting Ltr 2.0000 45,000.00 90,000.00
Besi Beton Polos Kg 120.0000 16,500.00 1,980,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 6,768,865.60
Dibulatkan 6,768,860.00
D-19 1 M3 Kolom Beton Tulang (140 kg besi+bekisting)
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Minyak Bekisting Ltr 2.0000 45,000.00 90,000.00
Besi Beton Polos Kg 140.0000 16,500.00 2,310,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 7,098,865.60
Dibulatkan 7,098,860.00
D-20 1 M3 Kolom Beton Tulang (150 kg besi+bekisting)
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Minyak Bekisting Ltr 2.0000 45,000.00 90,000.00
Besi Beton Polos Kg 150.0000 16,500.00 2,475,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
1 2 3 4 5 6=4x5
Jumlah 7,263,865.60
Dibulatkan 7,263,860.00
D-21 1 M3 Kolom Beton Tulang (180 kg besi+bekisting)
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Minyak Bekisting Ltr 2.0000 45,000.00 90,000.00
Besi Beton Polos Kg 180.0000 16,500.00 2,970,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 7,758,865.60
Dibulatkan 7,758,860.00
D-22 1 M3 Kolom Beton Tulang (200 kg besi+bekisting)
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Minyak Bekisting Ltr 2.0000 45,000.00 90,000.00
Besi Beton Polos Kg 200.0000 16,500.00 3,300,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 8,088,865.60
Dibulatkan 8,088,860.00
D-23 1 M3 Kolom Beton Tulang (250 kg besi+bekisting)
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Minyak Bekisting Ltr 2.0000 45,000.00 90,000.00
Besi Beton Polos Kg 250.0000 16,500.00 4,125,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
1 2 3 4 5 6=4x5
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 8,913,865.60
Dibulatkan 8,913,860.00
D-24 1 M3 Kolom Beton Tulang (300 kg besi+bekisting)
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Minyak Bekisting Ltr 2.0000 45,000.00 90,000.00
Besi Beton Polos Kg 300.0000 16,500.00 4,950,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 9,738,865.60
Dibulatkan 9,738,860.00
1 M3 Kolom Beton Tulang 20/20 cm (140 kg besi+bekisting) 4 dia. 12, 8-15
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Besi Beton Polos Kg 140.0000 16,500.00 2,310,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 7,008,865.60
Dibulatkan 7,008,860.00
1 M3 Kolom Beton Tulang 15/20 (180 kg besi+bekisting) 4 dia. 12, 8-15
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Besi Beton Polos Kg 180.0000 16,500.00 2,970,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
1 2 3 4 5 6=4x5
Jumlah 7,668,865.60
Dibulatkan 7,668,860.00
1 M3 Kolom Beton Tulang 20/20 cm (210 kg besi+bekisting) Struktur bertingkat 4 dia. 16, 8-15
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Besi Beton Polos Kg 210.0000 16,500.00 3,465,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 8,163,865.60
Dibulatkan 8,163,860.00
1 M3 Kolom Beton Tulang 20/30cm (230 kg besi+bekisting) Struktur bertingkat 6 dia.16+2 dia.12, 8-15
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Besi Beton Polos Kg 230.0000 16,500.00 3,795,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 8,493,865.60
Dibulatkan 8,493,860.00
1 M3 Kolom Beton Tulang 20/40 cm (250 kg besi+bekisting) Struktur bertingkat
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Minyak Bekisting Ltr 2.0000 45,000.00 90,000.00
Besi Beton Polos Kg 250.0000 16,500.00 4,125,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 8,913,865.60
1 2 3 4 5 6=4x5
Dibulatkan 8,913,860.00
1 M3 Kolom Beton Tulang 30/30 cm (175 kg besi+bekisting) Struktur bertingkat 8 dia. 16, 8-15
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Besi Beton Polos Kg 175.0000 16,500.00 2,887,500.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 7,586,365.60
Dibulatkan 7,586,360.00
1 M3 Kolom Beton Tulang 30/30 cm (210 kg besi bekisting) Struktur bertingkat 10 dia. 16, 8-15
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Besi Beton Polos Kg 210.0000 16,500.00 3,465,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 8,163,865.60
Dibulatkan 8,163,860.00
1 M3 Kolom Beton Tulang 30/40 cm (200 kg besi bekisting) Struktur bertingkat
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Minyak Bekisting Ltr 2.0000 45,000.00 90,000.00
Besi Beton Polos Kg 200.0000 16,500.00 3,300,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 8,088,865.60
Dibulatkan 8,088,860.00
1 2 3 4 5 6=4x5
1 M3 Kolom Beton Tulang Praktis 12/12 cm (175 kg besi+bekisting)
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Besi Beton Polos Kg 175.0000 16,500.00 2,887,500.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 6,597,865.60
Dibulatkan 6,597,860.00
1 M3 Kolom Beton Tulang Praktis 12/12 cm (260 kg besi+bekisting) 4 dia. 10, 8-15
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Besi Beton Polos Kg 260.0000 16,500.00 4,290,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 8,000,365.60
Dibulatkan 8,000,360.00
1 M3 Kolom Beton Tulang (200 kg besi+bekisting)
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Besi Beton Polos Kg 200.0000 16,500.00 3,300,000.00
Kawat Beton Kg 4.5000 30,500.00 137,250.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 8,081,215.60
Dibulatkan 8,081,210.00
1 M3 Kolom Beton Tulang (250 kg besi+bekisting)
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Besi Beton Polos Kg 250.0000 16,500.00 4,125,000.00
Kawat Beton Kg 4.5000 30,500.00 137,250.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
1 2 3 4 5 6=4x5
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 8,906,215.60
Dibulatkan 8,906,210.00
1 M3 Kolom Beton Tulang (300 kg besi+bekisting)
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Besi Beton Polos Kg 300.0000 16,500.00 4,950,000.00
Kawat Beton Kg 4.5000 30,500.00 137,250.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1500 2,705,000.00 405,750.00
Multiplek 9 mm 120 x 240 Lbr 3.5000 166,500.00 582,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 9,731,215.60
Dibulatkan 9,731,210.00
D-25 1 M3 Balok Beton Tulang (120 kg besi+bekisting)
Kayu Terentang M3 0.3200 2,950,000.00 944,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Minyak Bekisting Ltr 1.6000 45,000.00 72,000.00
Besi Beton Polos Kg 120.0000 16,500.00 1,980,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 16.0000 30,800.00 492,800.00
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 6,042,315.60
Dibulatkan 6,042,310.00
D-26 1 M3 Balok Beton Tulang (150 kg besi+bekisting)
Kayu Terentang M3 0.3500 2,950,000.00 1,032,500.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Minyak Bekisting Ltr 1.6000 45,000.00 72,000.00
Besi Beton Polos Kg 150.0000 16,500.00 2,475,000.00
Kawat Beton Kg 2.2500 30,500.00 68,625.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
1 2 3 4 5 6=4x5
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 16.0000 30,800.00 492,800.00
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 6,639,540.60
Dibulatkan 6,639,540.00
D-27 1 M3 Balok Beton Tulang (200 kg besi+bekisting)
Kayu Terentang M3 0.3000 2,950,000.00 885,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Minyak Bekisting Ltr 1.6000 45,000.00 72,000.00
Besi Beton Polos Kg 200.0000 16,500.00 3,300,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 200.0000 1,540.00 308,000.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
Multiplek 9 mm 120 x 240 Lbr 1.5000 166,500.00 249,750.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 12.0000 30,800.00 369,600.00
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 6,810,845.60
Dibulatkan 6,810,840.00
D-28 1 M3 Balok Beton Tulang (230 kg besi+bekisting)
Kayu Terentang M3 0.3200 2,950,000.00 944,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Minyak Bekisting Ltr 1.6000 45,000.00 72,000.00
Besi Beton Polos Kg 230.0000 16,500.00 3,795,000.00
Kawat Beton Kg 3.4500 30,500.00 105,225.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 16.0000 30,800.00 492,800.00
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 7,907,640.60
Dibulatkan 7,907,640.00
1 M3 Balok Beton Tulang 15/20 cm (150 kg besi+bekisting)
Kayu Terentang M3 0.3200 2,950,000.00 944,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Minyak Bekisting Ltr 1.6000 45,000.00 72,000.00
Besi Beton Polos Kg 150.0000 16,500.00 2,475,000.00
Kawat Beton Kg 2.2500 30,500.00 68,625.00
1 2 3 4 5 6=4x5
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 16.0000 30,800.00 492,800.00
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 6,551,040.60
Dibulatkan 6,551,040.00
1 M3 Balok Beton Tulang 15/20 (180 kg besi+bekisting) 4 dia. 12, 8-15
Kayu Terentang M3 0.3200 2,950,000.00 944,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Besi Beton Polos Kg 180.0000 16,500.00 2,970,000.00
Kawat Beton Kg 2.2500 30,500.00 68,625.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 16.0000 30,800.00 492,800.00
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 6,974,040.60
Dibulatkan 6,974,040.00
1 M3 Balok Beton Lintel 11/11 (300 kg besi+bekisting) 4 dia. 10, 8-15
Kayu Terentang M3 0.4000 2,950,000.00 1,180,000.00
Paku Biasa 2" - 5" Kg 4.0000 24,000.00 96,000.00
Besi Beton Polos Kg 300.0000 16,500.00 4,950,000.00
Kawat Beton Kg 1.8000 30,500.00 54,900.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Dolken Kayu Galam Ø-8 Cm / 4m Btg 20.0000 30,800.00 616,000.00
Pekerja Oh 7.3000 67,000.00 489,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 3.3000 70,000.00 231,000.00
Tukang Besi Oh 2.1000 70,000.00 147,000.00
Kepala Tukang Oh 0.5700 80,000.00 45,600.00
Mandor Oh 0.2500 85,000.00 21,250.00
Jumlah 8,660,365.60
Dibulatkan 8,660,360.00
1 M3 Balok Beton Tulang 15/20 sofi-sofi, ring balk+balok portal (180 kg besi+bekisting) 4 dia.12, 8-15
Kayu Terentang M3 0.3200 2,950,000.00 944,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Besi Beton Polos Kg 180.0000 16,500.00 2,970,000.00
Kawat Beton Kg 2.2500 30,500.00 68,625.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
1 2 3 4 5 6=4x5
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken o - 8 Cm/ 4 m Btg 16.0000 30,800.00 492,800.00
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 6,974,040.60
Dibulatkan 6,974,040.00
1 M3 Balok Beton Tulang 15/30 (190 kg besi+bekisting) Struktur bertingkat 4 dia. 16, 8-15
Kayu Terentang M3 0.3200 2,950,000.00 944,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Besi Beton Polos Kg 190.0000 16,500.00 3,135,000.00
Kawat Beton Kg 2.2500 30,500.00 68,625.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 16.0000 30,800.00 492,800.00
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 7,139,040.60
Dibulatkan 7,139,040.00
1 M3 Balok Beton Tulang 20/40 (200 kg besi+bekisting) Struktur bertingkat 7 dia. 16+2 dia. 12, 8-15
Kayu Terentang M3 0.3200 2,950,000.00 944,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Besi Beton Polos Kg 200.0000 16,500.00 3,300,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 16.0000 30,800.00 492,800.00
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 7,326,915.60
Dibulatkan 7,326,910.00
1 M3 Balok Beton Tulang 20/30 (200 kg besi+bekisting) Struktur bertingkat 6 dia. 16, 8-15
Kayu Terentang M3 0.3200 2,950,000.00 944,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Besi Beton Polos Kg 200.0000 16,500.00 3,300,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 16.0000 30,800.00 492,800.00
1 2 3 4 5 6=4x5
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 7,326,915.60
Dibulatkan 7,326,910.00
1 M3 Balok Beton Tulang 20/30 (175 kg besi+bekisting) Struktur bertingkat 5 dia. 16, 8-15
Kayu Terentang M3 0.3200 2,950,000.00 944,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Besi Beton Polos Kg 175.0000 16,500.00 2,887,500.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 16.0000 30,800.00 492,800.00
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 6,914,415.60
Dibulatkan 6,914,410.00
1 M3 Balok Beton Tulang 25/55 (140 kg besi+bekisting) Struktur bertingkat 8 dia. 16+2 dia. 12, 8-15
Kayu Terentang M3 0.3200 2,950,000.00 944,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Besi Beton Polos Kg 140.0000 16,500.00 2,310,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 16.0000 30,800.00 492,800.00
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 6,336,915.60
Dibulatkan 6,336,910.00
1 M3 Balok Beton Tulang 30/60 (110 kg besi+ bekisting) Struktur bertingkat 9 dia. 19+2 dia. 12, 8-15
Kayu Terentang M3 0.3200 2,950,000.00 944,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Besi Beton Polos Kg 110.0000 16,500.00 1,815,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1400 2,705,000.00 378,700.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 16.0000 30,800.00 492,800.00
Pekerja Oh 5.9600 67,000.00 399,320.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
1 2 3 4 5 6=4x5
Tukang Kayu Oh 2.8000 70,000.00 196,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4550 80,000.00 36,400.00
Mandor Oh 0.2080 85,000.00 17,680.00
Jumlah 5,841,915.60
Dibulatkan 5,841,910.00
D-29 1 M3 Tangga Beton Tulang (200 kg besi+bekisting)
Kayu Terentang M3 0.2500 2,950,000.00 737,500.00
Paku Biasa 2" - 5" Kg 3.0000 24,000.00 72,000.00
Minyak Bekisting Ltr 1.2000 45,000.00 54,000.00
Besi Beton Polos Kg 200.0000 16,500.00 3,300,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1050 2,705,000.00 284,025.00
Multiplek 9 mm 120 x 240 Lbr 2.5000 166,500.00 416,250.00
Dolken o - 8 Cm/ 4 m Btg 14.0000 30,800.00 431,200.00
Pekerja Oh 5.6000 67,000.00 375,200.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.3000 70,000.00 161,000.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.4050 80,000.00 32,400.00
Mandor Oh 0.2020 85,000.00 17,170.00
Jumlah 6,899,760.60
Dibulatkan 6,899,760.00
D-30 1 M3 Plat Lantai Tb. 10 Cm Beton Bertulang (90 kg besi+bekisting)
Beton bertulang ad. 1Pc : 2 Ps : 3 Kr M3 1.0000 1,083,160.00 1,083,160.00
Pasang Bekisting untuk lantai M2 10.0000 466,600.00 4,666,000.00
Besi Beton Polos Kg 90.0000 18,820.00 1,693,800.00
Jumlah 7,442,960.00
Dibulatkan 7,442,960.00
D-30.1 1 M3 Plat Lantai 1 lapis Tb. 10 Cm Beton Bertulang (50 kg besi+bekisting)
Beton bertulang ad. 1Pc : 2 Ps : 3 Kr M3 1.0000 1,083,160.00 1,083,160.00
Besi Beton Polos Kg 50.0000 18,820.00 941,000.00
Jumlah 2,024,160.00
Dibulatkan 2,024,160.00
D-31 1 M3 Plat Lantai Tb. 12 Cm Beton Bertulang (110 kg besi+bekisting)
Beton bertulang ad. 1Pc : 2 Ps : 3 Kr M3 1.0000 1,083,160.00 1,083,160.00
Pasang Bekisting untuk lantai M2 8.3300 466,600.00 3,886,778.00
Besi Beton Polos Kg 110.0000 18,820.00 2,070,200.00
Jumlah 7,040,138.00
Dibulatkan 7,040,130.00
D-32 1 M3 Plat Lantai Tb. 12 Cm Beton Bertulang (130 kg besi+bekisting)
Beton bertulang ad. 1Pc : 2 Ps : 3 Kr M3 1.0000 1,083,160.00 1,083,160.00
Pasang Bekisting untuk lantai M2 8.3300 466,600.00 3,886,778.00
Besi Beton Polos Kg 130.0000 18,820.00 2,446,600.00
Jumlah 7,416,538.00
Dibulatkan 7,416,530.00
D-33 1 M3 Plat Lantai Tb. 15 Cm Beton Bertulang (90 kg besi+bekisting)
Beton bertulang ad. 1Pc : 2 Ps : 3 Kr M3 1.0000 1,083,160.00 1,083,160.00
Pasang Bekisting untuk lantai M2 6.6700 466,600.00 3,112,222.00
Besi Beton Polos Kg 90.0000 18,820.00 1,693,800.00
Jumlah 5,889,182.00
Dibulatkan 5,889,180.00
D-34 1 M3 Plat Lantai Tb. 15 Cm Beton Bertulang (115 kg besi+bekisting)
Beton bertulang ad. 1Pc : 2 Ps : 3 Kr M3 1.0000 1,083,160.00 1,083,160.00
Pasang Bekisting untuk lantai M2 6.6700 466,600.00 3,112,222.00
Besi Beton Polos Kg 115.0000 18,820.00 2,164,300.00
1 2 3 4 5 6=4x5
Jumlah 6,359,682.00
Dibulatkan 6,359,680.00
1 M3 Listplang Beton Tulang T= 8 cm (77.5 kg besi+bekisting)
Beton bertulang ad. 1Pc : 2 Ps : 3 Kr M3 1.0000 1,083,160.00 1,083,160.00
Pasang Bekisting untuk lantai M2 8.3300 466,600.00 3,886,778.00
Besi Beton Polos Kg 77.5000 18,820.00 1,458,550.00
Jumlah 6,428,488.00
Dibulatkan 6,428,480.00
D-35 1 M' Kolom Praktis Beton Tulang ( 11 x 11 ) Cm
Kayu Terentang M3 0.0020 2,950,000.00 5,900.00
Paku Biasa 2" - 5" Kg 0.0100 24,000.00 240.00
Besi Beton Polos Kg 3.0000 16,500.00 49,500.00
Kawat Beton Kg 0.0450 30,500.00 1,372.50
Semen Portland Kg 4.0000 1,540.00 6,160.00
Pasir Beton M3 0.0060 264,140.00 1,584.84
Koral Beton M3 0.0090 218,260.00 1,964.34
Pekerja Oh 0.0600 67,000.00 4,020.00
Tukang Batu Oh 0.0200 70,000.00 1,400.00
Tukang Kayu Oh 0.0200 70,000.00 1,400.00
Tukang Besi Oh 0.0200 70,000.00 1,400.00
Kepala Tukang Oh 0.0060 80,000.00 480.00
Mandor Oh 0.0030 85,000.00 255.00
Jumlah 75,676.68
Dibulatkan 75,670.00
D-36 1 M' Ring Balok Beton Tulang ( 10 x 15 ) Cm
Kayu Terentang M3 0.0030 2,950,000.00 8,850.00
Paku Biasa 2" - 5" Kg 0.0200 24,000.00 480.00
Besi Beton Polos Kg 3.6000 16,500.00 59,400.00
Kawat Beton Kg 0.0500 30,500.00 1,525.00
Semen Portland Kg 5.5000 1,540.00 8,470.00
Pasir Beton M3 0.0090 264,140.00 2,377.26
Koral Beton M3 0.0150 218,260.00 3,273.90
Pekerja Oh 0.1000 67,000.00 6,700.00
Tukang Batu Oh 0.0330 70,000.00 2,310.00
Tukang Kayu Oh 0.0330 70,000.00 2,310.00
Tukang Besi Oh 0.0330 70,000.00 2,310.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 99,231.16
Dibulatkan 99,230.00
D-37 1 M2 Pasang Bekisting untuk Dinding
Kayu Terentang M3 0.0300 2,950,000.00 88,500.00
Paku Biasa 2" - 5" Kg 0.4000 24,000.00 9,600.00
Minyak Bekisting Ltr 0.2000 45,000.00 9,000.00
Kayu balok terentang M3 0.0200 2,705,000.00 54,100.00
Multiplek 9 mm 120 x 240 Lbr 0.3500 166,500.00 58,275.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 3.0000 30,800.00 92,400.00
Formtie/ Penjaga jarak Bekisting/ Spacer Bh 4.0000 2,800.00 11,200.00
Pekerja Oh 0.3200 67,000.00 21,440.00
Tukang Kayu Oh 0.3300 70,000.00 23,100.00
Kepala Tukang Oh 0.0330 80,000.00 2,640.00
Mandor Oh 0.0060 85,000.00 510.00
Jumlah 370,765.00
Dibulatkan 370,760.00
D-38 1 M3 Pelat Beton Tulang (150 kg besi+bekisting)
Kayu Terentang M3 0.3200 2,950,000.00 944,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Minyak Bekisting Ltr 1.6000 45,000.00 72,000.00
Besi Beton Polos Kg 150.0000 16,500.00 2,475,000.00
1 2 3 4 5 6=4x5
Kawat Beton Kg 2.2500 30,500.00 68,625.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1200 2,705,000.00 324,600.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 32.0000 30,800.00 985,600.00
Pekerja Oh 5.3000 67,000.00 355,100.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 1.3000 70,000.00 91,000.00
Tukang Besi Oh 1.0500 70,000.00 73,500.00
Kepala Tukang Oh 0.2650 80,000.00 21,200.00
Mandor Oh 0.2650 85,000.00 22,525.00
Jumlah 6,805,665.60
Dibulatkan 6,805,660.00
D-39 1 M3 Dinding Beton Tulang (150 kg besi+bekisting)
Kayu Terentang M3 0.2400 2,950,000.00 708,000.00
Paku Biasa 2" - 5" Kg 3.2000 24,000.00 76,800.00
Minyak Bekisting Ltr 1.6000 45,000.00 72,000.00
Besi Beton Polos Kg 150.0000 16,500.00 2,475,000.00
Kawat Beton Kg 2.2500 30,500.00 68,625.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1600 2,705,000.00 432,800.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken o - 8 Cm/ 4 m Btg 24.0000 30,800.00 739,200.00
Pekerja Oh 5.6000 67,000.00 375,200.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 2.6400 70,000.00 184,800.00
Tukang Besi Oh 1.0500 70,000.00 73,500.00
Kepala Tukang Oh 0.4000 80,000.00 32,000.00
Mandor Oh 0.1930 85,000.00 16,405.00
Jumlah 6,550,045.60
Dibulatkan 6,550,040.00
D-40 1 M3 Dinding Beton Tulang (200 kg besi+bekisting)
Kayu Terentang M3 0.2500 2,950,000.00 737,500.00
Paku Biasa 2" - 5" Kg 3.0000 24,000.00 72,000.00
Minyak Bekisting Ltr 1.2000 45,000.00 54,000.00
Besi Beton Polos Kg 200.0000 16,500.00 3,300,000.00
Kawat Beton Kg 3.0000 30,500.00 91,500.00
Semen Portland Kg 323.0000 1,540.00 497,420.00
Pasir Beton M3 0.5200 264,140.00 137,352.80
Koral Beton M3 0.7800 218,260.00 170,242.80
Kayu Balok Terentang M3 0.1050 2,705,000.00 284,025.00
Multiplek 9 mm 120 x 240 Lbr 2.8000 166,500.00 466,200.00
Dolken o - 8 Cm/ 4 m Btg 14.0000 30,800.00 431,200.00
Pekerja Oh 5.6000 67,000.00 375,200.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Tukang Kayu Oh 1.5600 70,000.00 109,200.00
Tukang Besi Oh 1.4000 70,000.00 98,000.00
Kepala Tukang Oh 0.3230 80,000.00 25,840.00
Mandor Oh 0.2830 85,000.00 24,055.00
Jumlah 6,898,235.60
Dibulatkan 6,898,230.00
D-41 1 M3 Membuat Beton Cor Mutu K300
Semen Portland Kg 413.0000 1,540.00 636,020.00
Pasir Beton M3 0.4256 264,140.00 112,417.98
Koral Beton M3 0.6807 218,260.00 148,569.58
1 2 3 4 5 6=4x5
Pekerja Oh 1.6500 67,000.00 110,550.00
Tukang Batu Oh 0.2750 70,000.00 19,250.00
Kepala Tukang Oh 0.0280 80,000.00 2,240.00
Mandor Oh 0.0830 85,000.00 7,055.00
Jumlah 1,036,102.57
Dibulatkan 1,036,100.00
D-42 1 M3 Membuat Beton Cor Mutu K200
Semen Portland Kg 352.0000 1,540.00 542,080.00
Pasir Beton M3 0.4569 264,140.00 120,685.57
Koral Beton M3 0.6873 218,260.00 150,010.10
Pekerja Oh 1.6500 67,000.00 110,550.00
Tukang Batu Oh 0.2750 70,000.00 19,250.00
Kepala Tukang Oh 0.0280 80,000.00 2,240.00
Mandor Oh 0.0830 85,000.00 7,055.00
Jumlah 951,870.66
Dibulatkan 951,870.00
D-43 1 M3 Membuat Beton Cor Mutu K250
Semen Portland Kg 384.0000 1,540.00 591,360.00
Pasir Beton M3 0.4325 264,140.00 114,240.55
Koral Beton M3 0.6927 218,260.00 151,188.70
Pekerja Oh 1.6500 67,000.00 110,550.00
Tukang Batu Oh 0.2750 70,000.00 19,250.00
Kepala Tukang Oh 0.0280 80,000.00 2,240.00
Mandor Oh 0.0830 85,000.00 7,055.00
Jumlah 995,884.25
Dibulatkan 995,880.00
1 M3 Membuat Beton dengan Puzzdith - 100 XR
Semen Portland Kg 336.0000 1,540.00 517,440.00
Pasir Beton M3 0.5400 264,140.00 142,635.60
Koral Beton M3 0.8100 218,260.00 176,790.60
Puzzdith - 100 XR Ltr 1.0000 0.00 0.00
Pekerja Oh 1.6500 67,000.00 110,550.00
Tukang Batu Oh 0.2500 70,000.00 17,500.00
Kepala Tukang Oh 0.0250 80,000.00 2,000.00
Mandor Oh 0.0800 85,000.00 6,800.00
Jumlah 973,716.20
Dibulatkan 973,710.00
1 M3 Membuat Beton Kedap Air dengan AM - 100
Semen Portland Kg 400.0000 1,540.00 616,000.00
Pasir Beton M3 0.4800 264,140.00 126,787.20
Koral Beton M3 0.8000 218,260.00 174,608.00
AM - 100 Ltr 1.2000 41,500.00 49,800.00
Pekerja Oh 2.0000 67,000.00 134,000.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Kepala Tukang Oh 0.0350 80,000.00 2,800.00
Mandor Oh 1.0000 85,000.00 85,000.00
Jumlah 1,213,495.20
Dibulatkan 1,213,490.00
1 Kg Kabel Presstressed Polos / Strands
Besi Presstressed Polos Kg 1.0500 16,500.00 17,325.00
Kawat Beton Kg 0.0100 30,500.00 305.00
Pekerja Oh 0.0050 67,000.00 335.00
Tukang Besi Oh 0.0050 70,000.00 350.00
Kepala Tukang Oh 0.0005 80,000.00 40.00
Mandor Oh 0.0003 85,000.00 25.50
Jumlah 18,380.50
Dibulatkan 18,380.00
1 Kg Jaring Kawat Baja
Besi Jaring Kawat Baja Kg 1.0200 31,800.00 32,436.00
1 2 3 4 5 6=4x5
Kawat Beton Kg 0.8050 30,500.00 24,552.50
Pekerja Oh 0.0250 67,000.00 1,675.00
Tukang Besi Oh 0.0250 70,000.00 1,750.00
Kepala Tukang Oh 0.0025 80,000.00 200.00
Mandor Oh 0.0015 85,000.00 127.50
Jumlah 60,741.00
Dibulatkan 60,740.00
1 M3 Membuat Beton Cor Mutu K175
Semen Portland Kg 326.0000 1,540.00 502,040.00
Pasir Beton M3 0.5429 264,140.00 143,401.61
Koral Beton M3 0.7622 218,260.00 166,357.77
Air Ltr 215.0000 350.00 75,250.00
Pekerja Oh 1.6500 67,000.00 110,550.00
Tukang Batu Oh 0.2750 70,000.00 19,250.00
Kepala Tukang Oh 0.0280 80,000.00 2,240.00
Mandor Oh 0.0830 85,000.00 7,055.00
Jumlah 1,026,144.38
Dibulatkan 1,026,140.00
1 M2 Pasangan Jembatan Cor
Kayu Albasia M3 0.0264 2,279,000.00 60,165.60
Paku Biasa 2" - 5" Kg 0.6000 24,000.00 14,400.00
Dolken Kayu Galam Ø-8 Cm / 4m Btg 0.5000 30,800.00 15,400.00
Pekerja Oh 0.1500 67,000.00 10,050.00
Tukang Kayu Oh 0.0500 70,000.00 3,500.00
Kepala Tukang Oh 0.0050 80,000.00 400.00
Mandor Oh 0.0070 85,000.00 595.00
Jumlah 104,510.60
Dibulatkan 104,510.00
1 M3 Listplank Beton Tulang T=8 cm ( 77,50 kg besi + bekisting )
Beton bertulang ad. 1Pc : 2 Ps : 3 Kr M3 1.0000 1,083,160.00 1,083,160.00
Pasang Bekisting untuk lantai M2 8.3300 466,600.00 3,886,778.00
Besi Beton Polos Kg 77.5000 18,820.00 1,458,550.00
Jumlah 6,428,488.00
Dibulatkan 6,428,480.00
E PEKERJAAN DINDING
E-01 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 3Ps
Bata Merah Bh 140.0000 850.00 119,000.00
Semen Portland Kg 32.9500 1,540.00 50,743.00
Pasir Pasang M3 0.0910 241,390.00 21,966.49
Pekerja Oh 0.6500 67,000.00 43,550.00
Tukang Batu Oh 0.2000 70,000.00 14,000.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0300 85,000.00 2,550.00
Jumlah 253,409.49
Dibulatkan 253,400.00
E-02 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 4Ps
Bata Merah Bh 140.0000 850.00 119,000.00
Semen Portland Kg 26.5500 1,540.00 40,887.00
Pasir Pasang M3 0.0930 241,390.00 22,449.27
Pekerja Oh 0.6500 67,000.00 43,550.00
Tukang Batu Oh 0.2000 70,000.00 14,000.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0300 85,000.00 2,550.00
Jumlah 244,036.27
Dibulatkan 244,030.00
E-03 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 5Ps
Bata Merah Bh 140.0000 850.00 119,000.00
Semen Portland Kg 22.2000 1,540.00 34,188.00
1 2 3 4 5 6=4x5
Pasir Pasang M3 0.1020 241,390.00 24,621.78
Pekerja Oh 0.6500 67,000.00 43,550.00
Tukang Batu Oh 0.2000 70,000.00 14,000.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0300 85,000.00 2,550.00
Jumlah 239,509.78
Dibulatkan 239,500.00
E-04 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 3Ps
Bata Merah Bh 70.0000 850.00 59,500.00
Semen Portland Kg 14.3700 1,540.00 22,129.80
Pasir Pasang M3 0.0400 241,390.00 9,655.60
Pekerja Oh 0.3200 67,000.00 21,440.00
Tukang Batu Oh 0.1000 70,000.00 7,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0150 85,000.00 1,275.00
Jumlah 121,800.40
Dibulatkan 121,800.00
E-05 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 4Ps
Bata Merah Bh 70.0000 850.00 59,500.00
Semen Portland Kg 11.5000 1,540.00 17,710.00
Pasir Pasang M3 0.0430 241,390.00 10,379.77
Pekerja Oh 0.3200 67,000.00 21,440.00
Tukang Batu Oh 0.1000 70,000.00 7,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0150 85,000.00 1,275.00
Jumlah 118,104.77
Dibulatkan 118,100.00
E-06 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 5Ps
Bata Merah Bh 70.0000 850.00 59,500.00
Semen Portland Kg 9.6800 1,540.00 14,907.20
Pasir Pasang M3 0.0450 241,390.00 10,862.55
Pekerja Oh 0.3200 67,000.00 21,440.00
Tukang Batu Oh 0.1000 70,000.00 7,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0150 85,000.00 1,275.00
Jumlah 115,784.75
Dibulatkan 115,780.00
E-07 1 M2 Pasang Dinding Roster Beton 20 x 20 ad.1pc : 3 ps
Roster Terawang Bh 36.0000 16,000.00 576,000.00
Semen Portland Kg 12.8000 1,540.00 19,712.00
Pasir Pasang M3 0.0350 241,390.00 8,448.65
Pekerja Oh 0.3000 67,000.00 20,100.00
Tukang Batu Oh 0.1000 70,000.00 7,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0150 85,000.00 1,275.00
Jumlah 633,335.65
Dibulatkan 633,330.00
E-08 1 M2 Pasang Dinding Roster Beton 20 x 20 ad.1pc : 4 ps
Roster Terawang Bh 36.0000 16,000.00 576,000.00
Semen Portland Kg 11.0000 1,540.00 16,940.00
Pasir Pasang M3 0.0350 241,390.00 8,448.65
Pekerja Oh 0.3000 67,000.00 20,100.00
Tukang Batu Oh 0.1000 70,000.00 7,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0150 85,000.00 1,275.00
Jumlah 630,563.65
Dibulatkan 630,560.00
E-09 1 M2 Pasang Dinding Roster/terawang (12 x 11 x 24) cm
Roster Terawang Bh 36.0000 16,000.00 576,000.00
1 2 3 4 5 6=4x5
Semen Portland Kg 12.8000 1,540.00 19,712.00
Pasir Pasang M3 0.0350 241,390.00 8,448.65
Pekerja Oh 0.3000 67,000.00 20,100.00
Tukang Batu Oh 0.1000 70,000.00 7,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0150 85,000.00 1,275.00
Jumlah 633,335.65
Dibulatkan 633,330.00
E-10 1 M2 Pasang Dinding Batako Besar Pres uk. 8 x 20 x 30 ad. 1pc : 4ps
Batako Bh 13.0000 2,700.00 35,100.00
Semen Portland Kg 12.0000 1,540.00 18,480.00
Pasir Pasang M3 0.0380 241,390.00 9,172.82
Pekerja Oh 0.3000 67,000.00 20,100.00
Tukang Batu Oh 0.1000 70,000.00 7,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0150 85,000.00 1,275.00
Jumlah 91,927.82
Dibulatkan 91,920.00
E-11 1 M2 Pasang Dinding Hollowblock (HB-20)
HB-20 Bh 12.5000 5,700.00 71,250.00
Semen Portland Kg 13.5000 1,540.00 20,790.00
Pasir Pasang M3 0.0480 241,390.00 11,586.72
Besi angkur Ø 8 mm Kg 1.9500 16,500.00 32,175.00
Pekerja Oh 0.3500 67,000.00 23,450.00
Tukang Batu Oh 0.1500 70,000.00 10,500.00
Kepala Tukang Oh 0.0150 80,000.00 1,200.00
Mandor Oh 0.0170 85,000.00 1,445.00
Jumlah 172,396.72
Dibulatkan 172,390.00
E-12 1 M2 Pasang Dinding Hollowblock (HB-15)
HB-15 Bh 12.5000 6,500.00 81,250.00
Semen Portland Kg 10.4500 1,540.00 16,093.00
Pasir Pasang M3 0.0380 241,390.00 9,172.82
Besi angkur Ø 8 mm Kg 1.9500 16,500.00 32,175.00
Pekerja Oh 0.3200 67,000.00 21,440.00
Tukang Batu Oh 0.1200 70,000.00 8,400.00
Kepala Tukang Oh 0.0120 80,000.00 960.00
Mandor Oh 0.0150 85,000.00 1,275.00
Jumlah 170,765.82
Dibulatkan 170,760.00
E-13 1 M2 Pasang Dinding Hollowblock (HB-10)
HB-10 Bh 12.5000 3,500.00 43,750.00
Semen Portland Kg 7.5000 1,540.00 11,550.00
Pasir Pasang M3 0.0270 241,390.00 6,517.53
Besi angkur Ø 8 mm Kg 1.9500 16,500.00 32,175.00
Pekerja Oh 0.3200 67,000.00 21,440.00
Tukang Batu Oh 0.1200 70,000.00 8,400.00
Kepala Tukang Oh 0.0120 80,000.00 960.00
Mandor Oh 0.0150 85,000.00 1,275.00
Jumlah 126,067.53
Dibulatkan 126,060.00
E-14 1 M2 Pasang Dinding Conblock (CB-20)
CB-20 Bh 12.5000 5,700.00 71,250.00
Semen Portland Kg 14.0500 1,540.00 21,637.00
Pasir Beton M3 0.0040 264,140.00 1,056.56
Pasir Pasang M3 0.0420 241,390.00 10,138.38
Besi angkur Ø 8 mm Kg 3.8700 16,500.00 63,855.00
Paku Biasa 2" - 5" Kg 0.0060 24,000.00 144.00
Kayu Terentang M3 0.0010 2,950,000.00 2,950.00
1 2 3 4 5 6=4x5
Kawat Beton Kg 0.0300 30,500.00 915.00
Koral Beton M3 0.0050 218,260.00 1,091.30
Pekerja Oh 0.3700 67,000.00 24,790.00
Tukang Batu Oh 0.1570 70,000.00 10,990.00
Tukang Besi Oh 0.0070 70,000.00 490.00
Kepala Tukang Oh 0.0164 80,000.00 1,312.00
Mandor Oh 0.0185 85,000.00 1,572.50
Jumlah 212,191.74
Dibulatkan 212,190.00
E-15 1 M2 Pasang Dinding Conblock (CB-15)
CB-15 Bh 12.5000 6,500.00 81,250.00
Semen Portland Kg 10.4600 1,540.00 16,108.40
Pasir Beton M3 0.0030 264,140.00 792.42
Pasir Pasang M3 0.0320 241,390.00 7,724.48
Besi angkur Ø 8 mm Kg 0.8700 16,500.00 14,355.00
Paku Biasa 2" - 5" Kg 0.0040 24,000.00 96.00
Kayu Terentang M3 0.0010 2,950,000.00 2,950.00
Kawat Beton Kg 0.0200 30,500.00 610.00
Koral Beton M3 0.0040 218,260.00 873.04
Pekerja Oh 0.3400 67,000.00 22,780.00
Tukang Batu Oh 0.1300 70,000.00 9,100.00
Tukang Besi Oh 0.0070 70,000.00 490.00
Kepala Tukang Oh 0.0137 80,000.00 1,096.00
Mandor Oh 0.0170 85,000.00 1,445.00
Jumlah 159,670.34
Dibulatkan 159,670.00
E-16 1 M2 Pasang Dinding Conblock (CB-10)
CB-10 Bh 12.5000 3,500.00 43,750.00
Semen Portland Kg 10.4600 1,540.00 16,108.40
Pasir Beton M3 0.0030 264,140.00 792.42
Pasir Pasang M3 0.0320 241,390.00 7,724.48
Besi angkur Ø 8 mm Kg 0.8700 16,500.00 14,355.00
Paku Biasa 2" - 5" Kg 0.0040 24,000.00 96.00
Kayu Terentang M3 0.0010 2,950,000.00 2,950.00
Kawat Beton Kg 0.0200 30,500.00 610.00
Koral Beton M3 0.0040 218,260.00 873.04
Pekerja Oh 0.3400 67,000.00 22,780.00
Tukang Batu Oh 0.1300 70,000.00 9,100.00
Tukang Besi Oh 0.0070 70,000.00 490.00
Kepala Tukang Oh 0.0137 80,000.00 1,096.00
Mandor Oh 0.0170 85,000.00 1,445.00
Jumlah 122,170.34
Dibulatkan 122,170.00
E-17 1 M2 Pasang Dinding Keramik 10 x 20 Cm Corak setara Mulia
Keramik 10x20 Cm Corak m2 1.0000 62,500.00 62,500.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 123,370.52
Dibulatkan 123,370.00
E-18 1 M2 Pasang Dinding Keramik 10 x 20 Cm Polos setara Mulia
Keramik 10x20 Cm Polos m2 1.0000 60,000.00 60,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
1 2 3 4 5 6=4x5
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 120,870.52
Dibulatkan 120,870.00
E-19 1 M2 Pasang Dinding Keramik 20 x 20 Cm Corak setara Mulia
Keramik 20x20 Cm Corak m2 1.0000 65,000.00 65,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 125,870.52
Dibulatkan 125,870.00
E-20 1 M2 Pasang Dinding Keramik 20 x 20 Cm polos setara Mulia
Keramik 20x20 Cm polos m2 1.0000 60,000.00 60,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 120,870.52
Dibulatkan 120,870.00
E-21 1 M2 Pasang Dinding Keramik 20 x 25 Cm polos setara Mulia
Keramik 20x25 Cm Corak m2 1.0000 60,000.00 60,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 120,870.52
Dibulatkan 120,870.00
E-22 1 M2 Pasang Dinding Keramik 20 x 25 Cm Corak setara Mulia
Keramik 20x25 Cm Corak m2 1.0000 65,000.00 65,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 125,870.52
Dibulatkan 125,870.00
E-23 1 M2 Pasang Dinding Keramik 30 x 30 Cm polos setara Mulia
Keramik 30x30 Cm polos m2 1.0000 55,500.00 55,500.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
1 2 3 4 5 6=4x5
Jumlah 116,370.52
Dibulatkan 116,370.00
E-24 1 M2 Pasang Dinding Keramik 30 x 30 Cm corak setara Mulia
Keramik 30x30 Cm corak m2 1.0000 60,500.00 60,500.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 121,370.52
Dibulatkan 121,370.00
E-25 1 M2 Pasang Dinding Keramik 40 x 40 Cm polos setara Mulia
Keramik 40x40 Cm polos m2 1.0000 67,500.00 67,500.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 128,370.52
Dibulatkan 128,370.00
E-26 1 M2 Pasang Dinding Keramik 40 x 40 Cm corak setara Mulia
Keramik 40x40 Cm corak m2 1.0000 66,000.00 66,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 126,870.52
Dibulatkan 126,870.00
1 M2 Pasang Dinding Granito uk. 60 x 60 set. Essenza polis
Granito 60 x 60 essenza polis M2 1.0500 395,000.00 414,750.00
Paku Pancing 60x230 Bh 2.0000 1,000.00 2,000.00
Semen Abu - Abu Kg 10.4400 1,540.00 16,077.60
Pasir Pasang M3 0.0200 241,390.00 4,827.80
Semen Warna Kg 1.5000 15,000.00 22,500.00
Pekerja Oh 0.5000 67,000.00 33,500.00
Tukang Batu Oh 0.2500 70,000.00 17,500.00
Kepala Tukang Oh 0.0250 80,000.00 2,000.00
Mandor Oh 0.0250 85,000.00 2,125.00
Jumlah 515,280.40
Dibulatkan 515,280.00
E-27 1 M2 Pasang Dinding Keramik 10 x 20 Cm Corak setara Roman
Keramik 10x20 Cm Corak m2 1.0000 80,000.00 80,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 140,870.52
Dibulatkan 140,870.00
E-28 1 M2 Pasang Dinding Keramik 10 x 20 Cm Polos setara Roman
1 2 3 4 5 6=4x5
Keramik 10x20 Cm Polos m2 1.0000 65,500.00 65,500.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 126,370.52
Dibulatkan 126,370.00
E-29 1 M2 Pasang Dinding Keramik 20 x 20 Cm Corak setara Roman
Keramik 20x20 Cm Corak m2 1.0000 83,000.00 83,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 143,870.52
Dibulatkan 143,870.00
E-30 1 M2 Pasang Dinding Keramik 20 x 20 Cm polos setara Roman
Keramik 20x20 Cm polos m2 1.0000 65,500.00 65,500.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 126,370.52
Dibulatkan 126,370.00
E-31 1 M2 Pasang Dinding Keramik 20 x 25 Cm polos setara Roman
Keramik 20x25 Cm m2 1.0000 76,000.00 76,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 136,870.52
Dibulatkan 136,870.00
E-32 1 M2 Pasang Dinding Keramik 20 x 25 Cm Corak setara Roman
Keramik 20x25 Cm Corak m2 1.0000 81,500.00 81,500.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 142,370.52
Dibulatkan 142,370.00
E-33 1 M2 Pasang Dinding Keramik 30 x 30 Cm polos setara Roman
Keramik 30x30 Cm polos m2 1.0000 76,000.00 76,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
1 2 3 4 5 6=4x5
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 136,870.52
Dibulatkan 136,870.00
E-34 1 M2 Pasang Dinding Keramik 30 x 30 Cm corak setara Roman
Keramik 30x30 Cm corak m2 1.0000 80,000.00 80,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 140,870.52
Dibulatkan 140,870.00
E-35 1 M2 Pasang Dinding Keramik 40 x 40 Cm polos setara Roman
Keramik 40x40 Cm polos m2 1.0000 80,000.00 80,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 140,870.52
Dibulatkan 140,870.00
E-36 1 M2 Pasang Dinding Keramik 40 x 40 Cm corak setara Roman
Keramik 40x40 Cm corak m2 1.0000 85,000.00 85,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 145,870.52
Dibulatkan 145,870.00
E-36 1 M2 Pasang Dinding Keramik 20 x 40 Cm corak setara Roman
Keramik 20x40 Cm corak m2 1.0000 83,000.00 83,000.00
Semen Abu - Abu Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 143,870.52
Dibulatkan 143,870.00
E-37 1 M2 Pasang Dinding Marmer
Marmer M2 1.0500 605,000.00 635,250.00
Paku Pancing 60x230 Bh 2.0000 1,000.00 2,000.00
Semen Abu - Abu Kg 12.4400 1,540.00 19,157.60
Pasir Pasang M3 0.0250 241,390.00 6,034.75
Semen Warna Kg 1.5000 15,000.00 22,500.00
Pekerja Oh 0.9000 67,000.00 60,300.00
Tukang Batu Oh 0.6500 70,000.00 45,500.00
Kepala Tukang Oh 0.0650 80,000.00 5,200.00
1 2 3 4 5 6=4x5
Mandor Oh 0.0350 85,000.00 2,975.00
Jumlah 798,917.35
Dibulatkan 798,910.00
E-38 1 M2 Pasang Dinding Batu Tempel Hitam
Batu Tempel Hitam M2 0.0500 100,110.00 5,005.50
Semen Abu - Abu Kg 11.7500 1,540.00 18,095.00
Pasir Pasang M3 0.0350 241,390.00 8,448.65
Pekerja Oh 0.6200 67,000.00 41,540.00
Tukang Batu Oh 0.3500 70,000.00 24,500.00
Kepala Tukang Oh 0.0350 80,000.00 2,800.00
Mandor Oh 0.0300 85,000.00 2,550.00
Jumlah 102,939.15
Dibulatkan 102,930.00
E-39 1 M2 Pasang Dinding Poslin 11 x 11 Cm
Poslin m2 1.0000 70,000.00 70,000.00
Semen Portland Kg 8.0000 1,540.00 12,320.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Semen Warna Kg 0.0130 15,000.00 195.00
Pekerja Oh 0.1875 67,000.00 12,562.50
Tukang Batu Oh 0.3750 70,000.00 26,250.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0188 85,000.00 1,598.00
Jumlah 130,870.52
Dibulatkan 130,870.00
E-40 1 M2 Wall paper
Wall paper m2 1.0500 61,500.00 64,575.00
Lem Kg 0.2500 39,300.00 9,825.00
Pekerja Oh 0.3500 67,000.00 23,450.00
Tukang Batu Oh 0.1750 70,000.00 12,250.00
Kepala Tukang Oh 0.0170 80,000.00 1,360.00
Mandor Oh 0.0020 85,000.00 170.00
Jumlah 111,630.00
Dibulatkan 111,630.00
E-41 1 M2 Dinding Pemisah Teakwood Rangkap, Rangka Kayu Kamper Medan
Kayu Balok Kamper Medan M3 0.0280 6,262,000.00 175,336.00
Paku Biasa 2" - 5" Kg 0.1500 24,000.00 3,600.00
Lem Kayu Lt 0.5600 26,300.00 14,728.00
Teak Wood 4 mm 120 x 240 Lbr 0.8600 145,000.00 124,700.00
Pekerja Oh 0.1500 67,000.00 10,050.00
Tukang Kayu Oh 0.4500 70,000.00 31,500.00
Kepala Tukang Oh 0.0450 80,000.00 3,600.00
Mandor Oh 0.0080 85,000.00 680.00
Jumlah 364,194.00
Dibulatkan 364,190.00
E-42 1 M2 Dinding Pemisah Plywood Rangkap, Rangka Kayu Kamper Medan
Kayu Balok Kamper Medan M3 0.0280 6,262,000.00 175,336.00
Paku Biasa 2" - 5" Kg 0.1500 24,000.00 3,600.00
Lem Kayu Lt 0.5600 26,300.00 14,728.00
Plywood 120 x 240 x 9 mm Lbr 0.8600 260,000.00 223,600.00
Pekerja Oh 0.2000 67,000.00 13,400.00
Tukang Kayu Oh 0.6000 70,000.00 42,000.00
Kepala Tukang Oh 0.0600 80,000.00 4,800.00
Mandor Oh 0.0100 85,000.00 850.00
Jumlah 478,314.00
Dibulatkan 478,310.00
E-43 1 M2 Dinding Pemisah Triplek Rangkap, Rangka Kayu Kamper Medan
Kayu Balok Kamper Medan M3 0.0280 6,262,000.00 175,336.00
Paku Biasa 2" - 5" Kg 0.1500 24,000.00 3,600.00
Lem Kayu Lt 0.5600 26,300.00 14,728.00
1 2 3 4 5 6=4x5
Triplek 120 x 240 x 4 mm Lbr 0.8600 68,500.00 58,910.00
Pekerja Oh 0.2000 67,000.00 13,400.00
Tukang Kayu Oh 0.6000 70,000.00 42,000.00
Kepala Tukang Oh 0.0600 80,000.00 4,800.00
Mandor Oh 0.0100 85,000.00 850.00
Jumlah 313,624.00
Dibulatkan 313,620.00
E-44 1 M2 Dinding Pemisah GRC tb. 4 mm + rangka besi hollow
Hollow 4/4 Zincromate Btg 0.4150 32,200.00 13,363.00
Hollow 2/4 Zincromate Btg 0.1500 25,000.00 3,750.00
GRC ( 120 x 240 x 4 ) mm Lbr 0.3640 74,500.00 27,118.00
Paku GRC kg 0.1100 38,500.00 4,235.00
Ramset / dina bolt Bh 4.0000 8,000.00 32,000.00
Cotton plaster Bh 0.0720 16,500.00 1,188.00
Compoun Zak 0.1250 83,000.00 10,375.00
Pekerja Oh 0.1000 67,000.00 6,700.00
Tukang besi Oh 0.0500 70,000.00 3,500.00
Kepala tukang Oh 0.0050 80,000.00 400.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 103,054.00
Dibulatkan 103,050.00
E-45 1 M2 Dinding Pemisah Gypsum dobel tb. 9 mm + rangka besi hollow
Hollow 4/4 Zincromate Btg 0.8300 32,200.00 26,726.00
Hollow 2/4 Zincromate Btg 0.3000 25,000.00 7,500.00
Gypsum Lbr 0.7280 87,800.00 63,918.40
Paku Gypsum kg 0.2200 38,500.00 8,470.00
Ramset / dina bolt Bh 8.0000 8,000.00 64,000.00
Cotton plaster Bh 0.1440 16,500.00 2,376.00
Compoun Zak 0.2500 83,000.00 20,750.00
Pekerja Oh 0.2000 67,000.00 13,400.00
Tukang besi Oh 0.1000 70,000.00 7,000.00
Kepala tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0100 85,000.00 850.00
Jumlah 215,790.40
Dibulatkan 215,790.00
E-46 1 M2 Dinding Plywood tb. 4 mm + rangka besi hollow
Hollow 4/4 Zincromate Btg 0.4150 32,200.00 13,363.00
Hollow 2/4 Zincromate Btg 0.1500 25,000.00 3,750.00
Plywood 120 x 240 x 9 mm Lbr 0.3640 260,000.00 94,640.00
Paku kg 0.1100 24,000.00 2,640.00
Ramset / dina bolt Bh 4.0000 8,000.00 32,000.00
Pekerja Oh 0.1000 67,000.00 6,700.00
Tukang besi Oh 0.0500 70,000.00 3,500.00
Kepala tukang Oh 0.0050 80,000.00 400.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 157,418.00
Dibulatkan 157,410.00
E-47 1 M2 Dinding Teakwood tb. 4 mm + rangka besi hollow
Hollow 4/4 Zincromate Btg 0.4150 32,200.00 13,363.00
Hollow 2/4 Zincromate Btg 0.1500 25,000.00 3,750.00
Teakwood (120 x 240 x 4) mm Lbr 0.3640 145,000.00 52,780.00
Paku kg 0.1100 24,000.00 2,640.00
Ramset / dina bolt Bh 4.0000 8,000.00 32,000.00
Pekerja Oh 0.1000 67,000.00 6,700.00
Tukang besi Oh 0.0500 70,000.00 3,500.00
Kepala tukang Oh 0.0050 80,000.00 400.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 115,558.00
Dibulatkan 115,550.00
1 2 3 4 5 6=4x5
E-48 1 M2 Pasang Dinding Glass Block 20 x 20 ad. 1pc : 4 ps
Glass block 20 x 20 bh 36.0000 24,200.00 871,200.00
Semen Abu - Abu Kg 11.0000 1,540.00 16,940.00
Pasir Pasang M3 0.0350 241,390.00 8,448.65
Pekerja Oh 0.3000 67,000.00 20,100.00
Tukang Batu Oh 0.1000 70,000.00 7,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0150 85,000.00 1,275.00
Jumlah 925,763.65
Dibulatkan 925,760.00
E-49 1 M2 Pasang Dinding Anyaman Bambu, rangka kayu
Bilik bambu M2 1.5000 25,000.00 37,500.00
Kayu kaso 5/7 M3 0.0140 3,692,500.00 51,695.00
Paku Kg 0.0112 24,000.00 268.80
List kayu 2/4 M3 0.0030 5,810,000.00 17,430.00
Pekerja Oh 0.1000 67,000.00 6,700.00
Tukang Kayu Oh 0.0500 70,000.00 3,500.00
Kepala Tukang Oh 0.0050 80,000.00 400.00
Mandor Oh 0.0020 85,000.00 170.00
Jumlah 117,663.80
Dibulatkan 117,660.00
F PEKERJAAN PLESTERAN
F-01 1 M2 Plesteran 1 Pc : 2 Ps, Tebal 15 mm
Semen Portland Kg 8.5200 1,540.00 13,120.80
Pasir Pasang M3 0.0170 241,390.00 4,103.63
Pekerja Oh 0.2000 67,000.00 13,400.00
Tukang Batu Oh 0.1500 70,000.00 10,500.00
Kepala Tukang Oh 0.0150 80,000.00 1,200.00
Mandor Oh 0.0100 85,000.00 850.00
Jumlah 43,174.43
Dibulatkan 43,170.00
F-02 1 M2 Plesteran 1 Pc : 3 Ps, Tebal 15 mm
Semen Portland Kg 6.4800 1,540.00 9,979.20
Pasir Pasang M3 0.0190 241,390.00 4,586.41
Pekerja Oh 0.2000 67,000.00 13,400.00
Tukang Batu Oh 0.1500 70,000.00 10,500.00
Kepala Tukang Oh 0.0150 80,000.00 1,200.00
Mandor Oh 0.0100 85,000.00 850.00
Jumlah 40,515.61
Dibulatkan 40,510.00
F-03 1 M2 Plesteran 1 Pc : 4 Ps, Tebal 15 mm
Semen Portland Kg 5.2000 1,540.00 8,008.00
Pasir Pasang M3 0.0200 241,390.00 4,827.80
Pekerja Oh 0.2000 67,000.00 13,400.00
Tukang Batu Oh 0.1500 70,000.00 10,500.00
Kepala Tukang Oh 0.0150 80,000.00 1,200.00
Mandor Oh 0.0100 85,000.00 850.00
Jumlah 38,785.80
Dibulatkan 38,780.00
1 M2 Plesteran 1 Pc : 5 Ps, Tebal 15 mm + Acian
Semen Portland Kg 4.3200 1,540.00 6,652.80
Pasir Pasang M3 0.0220 241,390.00 5,310.58
Pekerja Oh 0.2000 67,000.00 13,400.00
Tukang Batu Oh 0.1500 70,000.00 10,500.00
Kepala Tukang Oh 0.0150 80,000.00 1,200.00
Mandor Oh 0.0100 85,000.00 850.00
Jumlah 37,913.38
Dibulatkan 37,910.00
1 2 3 4 5 6=4x5
F-04 1 M2 Plesteran 1 Pc : 3 Ps, Tebal 20 mm
Semen Portland Kg 10.8000 1,540.00 16,632.00
Pasir Pasang M3 0.0260 241,390.00 6,276.14
Pekerja Oh 0.2500 67,000.00 16,750.00
Tukang Batu Oh 0.2000 70,000.00 14,000.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0125 85,000.00 1,062.50
Jumlah 56,320.64
Dibulatkan 56,320.00
F-05 1 M2 Plesteran 1 Pc : 4 Ps, Tebal 20 mm
Semen Portland Kg 8.6800 1,540.00 13,367.20
Pasir Pasang M3 0.0280 241,390.00 6,758.92
Pekerja Oh 0.2500 67,000.00 16,750.00
Tukang Batu Oh 0.2000 70,000.00 14,000.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0125 85,000.00 1,062.50
Jumlah 53,538.62
Dibulatkan 53,530.00
F-06 1 M2 Plesteran 1 Pc : 5 Ps, Tebal 20 mm
Semen Portland Kg 7.2900 1,540.00 11,226.60
Pasir Pasang M3 0.0260 241,390.00 6,276.14
Pekerja Oh 0.2500 67,000.00 16,750.00
Tukang Batu Oh 0.2000 70,000.00 14,000.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0125 85,000.00 1,062.50
Jumlah 50,915.24
Dibulatkan 50,910.00
F-07 1 M2 Barapen 1 Pc : 5 Ps, Tebal 15 mm
Semen Portland Kg 5.6700 1,540.00 8,731.80
Pasir Pasang M3 0.0230 241,390.00 5,551.97
Pekerja Oh 0.1500 67,000.00 10,050.00
Tukang Batu Oh 0.0700 70,000.00 4,900.00
Kepala Tukang Oh 0.0070 80,000.00 560.00
Mandor Oh 0.0080 85,000.00 680.00
Jumlah 30,473.77
Dibulatkan 30,470.00
F-08 1 M2 Plesteran Beton 1 Pc : 2 Ps, Tebal 15 mm
Semen Portland Kg 9.3000 1,540.00 14,322.00
Pasir Pasang M3 0.0180 241,390.00 4,345.02
Pekerja Oh 0.2600 67,000.00 17,420.00
Tukang Batu Oh 0.2000 70,000.00 14,000.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0130 85,000.00 1,105.00
Jumlah 52,792.02
Dibulatkan 52,790.00
F-09 1 M2 Plesteran Beton 1 Pc : 3 Ps, Tebal 15 mm
Semen Portland Kg 7.0700 1,540.00 10,887.80
Pasir Pasang M3 0.0210 241,390.00 5,069.19
Pekerja Oh 0.2600 67,000.00 17,420.00
Tukang Batu Oh 0.2000 70,000.00 14,000.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0130 85,000.00 1,105.00
Jumlah 50,081.99
Dibulatkan 50,080.00
F-10 1 M2 Plesteran Skoning 1 Pc : 2 Ps, Tebal 10 mm
Semen Portland Kg 0.5000 1,540.00 770.00
Pasir Pasang M3 0.0130 241,390.00 3,138.07
Pekerja Oh 0.0800 67,000.00 5,360.00
Tukang Batu Oh 0.4000 70,000.00 28,000.00
1 2 3 4 5 6=4x5
Kepala Tukang Oh 0.0400 80,000.00 3,200.00
Mandor Oh 0.0040 85,000.00 340.00
Jumlah 40,808.07
Dibulatkan 40,800.00
F-11 1 M2 Acian Plesteran
Semen Portland Kg 4.0000 1,540.00 6,160.00
Pekerja Oh 0.1430 67,000.00 9,581.00
Tukang Batu Oh 0.1070 70,000.00 7,490.00
Kepala Tukang Oh 0.0105 80,000.00 840.00
Mandor Oh 0.0105 85,000.00 892.50
Jumlah 24,963.50
Dibulatkan 24,960.00
F-12 1 M2 Plesteran Siar Adukan 1 Pc : 2 Ps batu belah
Semen Portland Kg 6.3400 1,540.00 9,763.60
Pasir Pasang M3 0.0120 241,390.00 2,896.68
Pekerja Oh 0.3000 67,000.00 20,100.00
Tukang Batu Oh 0.1500 70,000.00 10,500.00
Kepala Tukang Oh 0.0150 80,000.00 1,200.00
Mandor Oh 0.0150 85,000.00 1,275.00
Jumlah 45,735.28
Dibulatkan 45,730.00
F-13 1 M2 Plesteran Siar Adukan 1 Pc : 2 Ps dinding bata merah
Semen Portland Kg 4.3200 1,540.00 6,652.80
Pasir Pasang M3 0.0160 241,390.00 3,862.24
Pekerja Oh 0.1500 67,000.00 10,050.00
Tukang Batu Oh 0.0700 70,000.00 4,900.00
Kepala Tukang Oh 0.0070 80,000.00 560.00
Mandor Oh 0.0080 85,000.00 680.00
Jumlah 26,705.04
Dibulatkan 26,700.00
J PEKERJAAN KAYU
J-01 1 M3 Pasang Kusen Pintu dan Jendela Kayu Kamper Samarinda
Kayu Balok Kamper Samarinda M3 1.2000 9,500,000.00 11,400,000.00
Pekerja Oh 6.0000 67,000.00 402,000.00
Tukang Kayu Oh 18.0000 70,000.00 1,260,000.00
Kepala Tukang Oh 2.0000 80,000.00 160,000.00
Mandor Oh 0.3000 85,000.00 25,500.00
Jumlah 13,247,500.00
Dibulatkan 13,247,500.00
J-02 1 M3 Pasang Kusen Pintu dan Jendela Kayu Kamper Medan/Kruing
Kayu Balok Kamper Medan M3 1.2000 6,262,000.00 7,514,400.00
Pekerja Oh 6.0000 67,000.00 402,000.00
Tukang Kayu Oh 18.0000 70,000.00 1,260,000.00
Kepala Tukang Oh 2.0000 80,000.00 160,000.00
1 2 3 4 5 6=4x5
Mandor Oh 0.3000 85,000.00 25,500.00
Jumlah 9,361,900.00
Dibulatkan 9,361,900.00
J-03 1 M3 Pasang Kusen Pintu dan Jendela Kayu Borneo Super
Kayu Balok Borneo Super M3 1.2000 5,810,000.00 6,972,000.00
Pekerja Oh 6.0000 67,000.00 402,000.00
Tukang Kayu Oh 18.0000 70,000.00 1,260,000.00
Kepala Tukang Oh 2.0000 80,000.00 160,000.00
Mandor Oh 0.3000 85,000.00 25,500.00
Jumlah 8,819,500.00
Dibulatkan 8,819,500.00
J-04 1 M2 Pasang Pintu Panel Kayu Kamper Samarinda
Kayu Papan Kamper Samarinda M3 0.0400 9,596,800.00 383,872.00
Paku biasa 2" - 5" Kg 0.0500 24,000.00 1,200.00
Pekerja Oh 1.0000 67,000.00 67,000.00
Tukang Kayu Oh 2.5000 70,000.00 175,000.00
Kepala Tukang Oh 0.2500 80,000.00 20,000.00
Mandor Oh 0.0500 85,000.00 4,250.00
Jumlah 651,322.00
Dibulatkan 651,320.00
J-05 1 M2 Pasang Pintu Panel Kayu Kamper Medan/Kruing
Kayu Papan Kamper Medan M3 0.0400 6,405,800.00 256,232.00
Paku biasa 2" - 5" Kg 0.0500 24,000.00 1,200.00
Pekerja Oh 1.0000 67,000.00 67,000.00
Tukang Kayu Oh 2.5000 70,000.00 175,000.00
Kepala Tukang Oh 0.2500 80,000.00 20,000.00
Mandor Oh 0.0500 85,000.00 4,250.00
Jumlah 523,682.00
Dibulatkan 523,680.00
J-06 1 M2 Pasang Daun Jendela Kaca Kayu Kamper Medan
Kayu Papan Kamper Medan M3 0.0150 6,405,800.00 96,087.00
Pekerja Oh 0.8000 67,000.00 53,600.00
Tukang Kayu Oh 2.0000 70,000.00 140,000.00
Kepala Tukang Oh 0.2000 80,000.00 16,000.00
Mandor Oh 0.0400 85,000.00 3,400.00
Jumlah 309,087.00
Dibulatkan 309,080.00
J-07 1 M2 Pasang Pintu dan Jendela Kaca Kayu Borneo
Kayu Papan Borneo Super M3 0.0350 6,155,500.00 215,442.50
Pekerja Oh 0.8000 67,000.00 53,600.00
Tukang Kayu Oh 2.0000 70,000.00 140,000.00
Kepala Tukang Oh 0.2000 80,000.00 16,000.00
Mandor Oh 0.0400 85,000.00 3,400.00
Jumlah 428,442.50
Dibulatkan 428,440.00
J-08 1 M2 Pasang Pintu dan Jendela Jalusi Kayu Kamper Medan
Kayu Papan Kamper Medan M3 0.0640 6,405,800.00 409,971.20
Pekerja Oh 1.0000 67,000.00 67,000.00
Tukang Kayu Oh 3.0000 70,000.00 210,000.00
Kepala Tukang Oh 0.3000 80,000.00 24,000.00
Mandor Oh 0.5000 85,000.00 42,500.00
Jumlah 753,471.20
Dibulatkan 753,470.00
J-09 1 M2 Pasang Pintu Triplek Rangkap, Rangka Tertutup Kayu Kamper Medan/Kruing
Kayu Papan Kamper Medan M3 0.0196 6,405,800.00 125,553.68
Paku Biasa 1/2" - 1 " Kg 0.0300 24,000.00 720.00
Lem Kayu Lt 0.3000 26,300.00 7,890.00
Triplek 4 mm 120 x 240 Lbr 1.0000 68,500.00 68,500.00
Pekerja Oh 0.6000 67,000.00 40,200.00
1 2 3 4 5 6=4x5
Tukang Kayu Oh 2.0000 70,000.00 140,000.00
Kepala Tukang Oh 0.2000 80,000.00 16,000.00
Mandor Oh 0.0300 85,000.00 2,550.00
Jumlah 401,413.68
Dibulatkan 401,410.00
J-10 1 M2 Pasang Jalusi Mati Kusen kayu Kamper Medan
Kayu Papan Kamper Medan M3 0.0600 6,405,800.00 384,348.00
Paku Biasa 1/2" - 1" Kg 0.1500 24,000.00 3,600.00
Pekerja Oh 0.5000 67,000.00 33,500.00
Tukang Kayu Oh 2.0000 70,000.00 140,000.00
Kepala Tukang Oh 0.3000 80,000.00 24,000.00
Mandor Oh 0.0250 85,000.00 2,125.00
Jumlah 587,573.00
Dibulatkan 587,570.00
J-11 1 M2 Pasang Daun Pintu Triplek Rangkap, Rangka Kayu Kamper
Kayu Papan Kamper Medan M3 0.0196 6,405,800.00 125,553.68
Paku Biasa 1/2" - 1 " Kg 0.0300 24,000.00 720.00
Lem Kayu Lt 0.3000 26,300.00 7,890.00
Triplek 4 mm 120 x 240 Lbr 1.0000 68,500.00 68,500.00
Pekerja Oh 0.6000 67,000.00 40,200.00
Tukang Kayu Oh 2.0000 70,000.00 140,000.00
Kepala Tukang Oh 0.2000 80,000.00 16,000.00
Mandor Oh 0.0300 85,000.00 2,550.00
Jumlah 401,413.68
Dibulatkan 401,410.00
J-12 1 M2 Pasang Daun Pintu Teakwood Rangkap, Rangka Kayu Kamper Medan
Kayu Papan Kamper Medan M3 0.0196 6,405,800.00 125,553.68
Paku Biasa 1/2" - 1 " Kg 0.3000 24,000.00 7,200.00
Lem Kayu Lt 0.3000 26,300.00 7,890.00
Teak Wood 4 mm 120 x 240 Lbr 1.0000 145,000.00 145,000.00
Pekerja Oh 0.6000 67,000.00 40,200.00
Tukang Kayu Oh 2.0000 70,000.00 140,000.00
Kepala Tukang Oh 0.2000 80,000.00 16,000.00
Mandor Oh 0.0300 85,000.00 2,550.00
Jumlah 484,393.68
Dibulatkan 484,390.00
J-13 1 M2 Pasang Pintu dobel Plywood lapis HPL, Rangka Kayu Kamper Medan
Kayu Papan Kamper Medan M3 0.0196 6,405,800.00 125,553.68
Paku Biasa 1/2" - 1 " Kg 0.3000 24,000.00 7,200.00
Lem Kayu Ltr 0.8000 26,300.00 21,040.00
Triplek 4 mm 120 x 240 Lbr 1.0000 68,500.00 68,500.00
HPL Lbr 0.5000 175,000.00 87,500.00
Pekerja Oh 0.8000 67,000.00 53,600.00
Tukang Kayu Oh 2.5000 70,000.00 175,000.00
Kepala Tukang Oh 0.2500 80,000.00 20,000.00
Mandor Oh 0.0400 85,000.00 3,400.00
Jumlah 561,793.68
Dibulatkan 561,790.00
J-14 1 M2 Pasang Pintu Teakwood lapis HPL , Rangka Kayu Kamper Medan
Kayu Papan Kamper Medan M3 0.0196 6,405,800.00 125,553.68
Paku Biasa 1/2" - 1 " Kg 0.3000 24,000.00 7,200.00
Lem Kayu Ltr 0.8000 26,300.00 21,040.00
Teak Wood 4 mm 120 x 240 Lbr 1.0000 145,000.00 145,000.00
Politur Ltr 0.5000 55,000.00 27,500.00
Formika Warna 4" x 8" Lbr 0.5000 262,500.00 131,250.00
Pekerja Oh 0.8000 67,000.00 53,600.00
Tukang Kayu Oh 2.5000 70,000.00 175,000.00
Kepala Tukang Oh 0.2500 80,000.00 20,000.00
Mandor Oh 0.0400 85,000.00 3,400.00
1 2 3 4 5 6=4x5
Jumlah 709,543.68
Dibulatkan 709,540.00
J-15 1 M3 Pasang Konstruksi Kuda - Kuda Kayu Kamper Medan
Kayu Balok Kamper Medan M3 1.1000 6,262,000.00 6,888,200.00
Besi Strip Kg 15.0000 29,500.00 442,500.00
Paku Biasa 2" - 5" Kg 0.8000 24,000.00 19,200.00
Pekerja Oh 4.0000 67,000.00 268,000.00
Tukang Kayu Oh 12.0000 70,000.00 840,000.00
Kepala Tukang Oh 1.2000 80,000.00 96,000.00
Mandor Oh 0.2000 85,000.00 17,000.00
Jumlah 8,570,900.00
Dibulatkan 8,570,900.00
J-16 1 M3 Pasang Konstruksi Kuda - Kuda Kayu Borneo
Kayu Balok Borneo Super M3 1.1000 5,810,000.00 6,391,000.00
Besi Strip Kg 15.0000 29,500.00 442,500.00
Paku Biasa 2" - 5" Kg 0.8000 24,000.00 19,200.00
Pekerja Oh 4.0000 67,000.00 268,000.00
Tukang Kayu Oh 12.0000 70,000.00 840,000.00
Kepala Tukang Oh 1.2000 80,000.00 96,000.00
Mandor Oh 0.2000 85,000.00 17,000.00
Jumlah 8,073,700.00
Dibulatkan 8,073,700.00
J-17 1 M2 Pasang Kaso dan Reng Genteng Plentong kayu Kamper Medan
Kayu Balok Kamper medan M3 0.0120 6,262,000.00 75,144.00
Paku Biasa 2" - 5" Kg 0.1500 24,000.00 3,600.00
Pekerja Oh 0.1000 67,000.00 6,700.00
Tukang Kayu Oh 0.1000 70,000.00 7,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 93,669.00
Dibulatkan 93,660.00
J-18 1 M2 Pasang Kaso dan Reng Genteng Beton kayu Kamper
Kayu Balok Kamper Medan M3 0.0140 6,262,000.00 87,668.00
Paku Biasa 2" - 5" Kg 0.1500 24,000.00 3,600.00
Pekerja Oh 0.1000 67,000.00 6,700.00
Tukang Kayu Oh 0.1000 70,000.00 7,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 106,193.00
Dibulatkan 106,190.00
J-19 1 M' Pasang Lisplang (3x20) Cm, Kayu Kamper Medan
Kayu Papan Kamper Medan M3 0.0072 6,405,800.00 46,121.76
Paku Biasa 2" - 5" Kg 0.0500 24,000.00 1,200.00
Pekerja Oh 0.1000 67,000.00 6,700.00
Tukang Kayu Oh 0.2000 70,000.00 14,000.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 70,046.76
Dibulatkan 70,040.00
J-20 1 M' Pasang Lisplang (3x30) Cm, Kayu Kamper Medan
Kayu Papan Kamper Medan M3 0.0110 6,405,800.00 70,463.80
Paku Biasa 2" - 5" Kg 0.0500 24,000.00 1,200.00
Pekerja Oh 0.1100 67,000.00 7,370.00
Tukang Kayu Oh 0.2200 70,000.00 15,400.00
Kepala Tukang Oh 0.0220 80,000.00 1,760.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 96,618.80
Dibulatkan 96,610.00
J-21 1 M' Pasang List Plafon - Kayu Profil 10 cm
1 2 3 4 5 6=4x5
Kayu Profil M' 1.0500 32,400.00 34,020.00
Pekerja Oh 0.0210 67,000.00 1,407.00
Tukang Kayu Oh 0.0210 70,000.00 1,470.00
Kepala Tukang Oh 0.0020 80,000.00 160.00
Mandor Oh 0.0010 85,000.00 85.00
Jumlah 37,142.00
Dibulatkan 37,140.00
J-22 7,26 M2 Kusen Partisi Dobel Triplek
Kayu Balok Borneo Super M3 0.1050 5,810,000.00 610,050.00
Triplek 4 mm 120 x 240 Lbr 5.0000 68,500.00 342,500.00
Paku Biasa 1 s/d 3 cm Kg 2.0000 24,000.00 48,000.00
Ampelas Lbr 2.0000 5,500.00 11,000.00
Engsel Bh 4.0000 23,100.00 92,400.00
Slot Bh 4.0000 35,000.00 140,000.00
Pekerja Oh 0.3000 67,000.00 20,100.00
Tukang Kayu Oh 1.3000 70,000.00 91,000.00
Kepala Tukang Oh 0.1300 80,000.00 10,400.00
Mandor Oh 0.0130 85,000.00 1,105.00
Jumlah 1,366,555.00
1 M2 Pekerjaan partisi 188,230.72
Dibulatkan 188,230.00
J-23 1 M2 Pasang Rangka Langit - langit (1.00x1.00) m, Kayu Kamper
Kayu Balok Kamper M3 0.0120 6,262,000.00 75,144.00
Paku Biasa 5" - 7" Kg 0.1000 24,000.00 2,400.00
Pekerja Oh 0.1500 67,000.00 10,050.00
Tukang Kayu Oh 0.2500 70,000.00 17,500.00
Kepala Tukang Oh 0.0250 80,000.00 2,000.00
Mandor Oh 0.0750 85,000.00 6,375.00
Jumlah 113,469.00
Dibulatkan 113,460.00
J-24 1 M2 Pasang Rangka Langit - langit (0.50 x 1.00) m, Kayu Borneo
Kayu Balok Borneo Super M3 0.0154 5,810,000.00 89,474.00
Paku Biasa 5" - 7" Kg 0.2000 24,000.00 4,800.00
Pekerja Oh 0.1500 67,000.00 10,050.00
Tukang Kayu Oh 0.3000 70,000.00 21,000.00
Kepala Tukang Oh 0.0300 80,000.00 2,400.00
Mandor Oh 0.0750 85,000.00 6,375.00
Jumlah 134,099.00
Dibulatkan 134,090.00
J-25 1 M1 Reuter Kayu Kamper Medan
Kayu Kamper Medan M3 0.0040 6,262,000.00 25,048.00
Pekerja Oh 0.1000 67,000.00 6,700.00
Tukang Kayu Oh 0.2000 70,000.00 14,000.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 47,773.00
Dibulatkan 47,770.00
J-26 1 M3 Gording kayu kelas II
Balok kayu M3 1.1000 6,262,000.00 6,888,200.00
Besi Strip Kg 15.0000 29,500.00 442,500.00
Paku Biasa 2" - 5" Kg 3.0000 24,000.00 72,000.00
Pekerja Oh 2.4000 67,000.00 160,800.00
Tukang Kayu Oh 7.2000 70,000.00 504,000.00
Kepala Tukang Oh 0.7200 80,000.00 57,600.00
Mandor Oh 0.1200 85,000.00 10,200.00
Jumlah 8,135,300.00
Dibulatkan 8,135,300.00
J-27 1 M2 Dinding bilik, rangka kayu borneo
Bilik bambu m2 1.1000 25,000.00 27,500.00
1 2 3 4 5 6=4x5
Kaso 5/7 m3 0.0140 2,705,000.00 37,870.00
Paku Biasa 2" - 5" Kg 0.0120 24,000.00 288.00
List kayu 2/4 m3 0.0030 10,500.00 31.50
Pekerja Oh 0.1000 67,000.00 6,700.00
Tukang Kayu Oh 0.0500 70,000.00 3,500.00
Kepala Tukang Oh 0.0050 80,000.00 400.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 76,714.50
Dibulatkan 76,710.00
1 M2 Pasang Pintu Panel Multiplek 9 mm rangka kayu Kamper Medan / Kruing
Kayu Papan Kamper Medan/Kruing M3 0.0230 6,405,800.00 147,333.40
Multiplek 9 mm lbr 0.2300 166,500.00 38,295.00
List kayu profil 1 cm m' 3.6000 9,800.00 35,280.00
Paku biasa ½" - 1" kg 0.3000 24,000.00 7,200.00
Lem putih FOX kg 0.1500 26,300.00 3,945.00
Pekerja Oh 1.0000 67,000.00 67,000.00
Tukang Kayu Oh 2.5000 70,000.00 175,000.00
Kepala Tukang Oh 0.2500 80,000.00 20,000.00
Mandor Oh 0.0500 85,000.00 4,250.00
Jumlah 498,303.40
Dibulatkan 498,300.00
M PEKERJAAN SANITASI
M-01 1 Buah Closet Jongkok Proselen Standar
Kloset jongkok porselen Bh 1.0000 207,500.00 207,500.00
Semen PC Kg 6.0000 1,540.00 9,240.00
Pasir Pasang M3 0.0100 241,390.00 2,413.90
Pekerja Oh 1.0000 67,000.00 67,000.00
Tukang Batu Oh 1.5000 70,000.00 105,000.00
Kepala Tukang Oh 0.1500 80,000.00 12,000.00
Mandor Oh 0.1600 85,000.00 13,600.00
Jumlah 416,753.90
Dibulatkan 416,750.00
M-02 1 Buah Urinoir
Urinoir Bh 1.0000 1,952,500.00 1,952,500.00
Semen PC Kg 6.0000 1,540.00 9,240.00
Pasir Pasang M3 0.0100 241,390.00 2,413.90
Pekerja Oh 1.0000 67,000.00 67,000.00
Tukang Batu Oh 1.0000 70,000.00 70,000.00
Kepala Tukang Oh 0.1000 80,000.00 8,000.00
Mandor Oh 0.0010 85,000.00 85.00
Perlengkapan 30 % Ls 0.3000 1,952,500.00 585,750.00
Jumlah 2,694,988.90
Dibulatkan 2,694,980.00
M-03 1 Buah Wastafel
Wastafel Bh 1.0000 800,000.00 800,000.00
Semen PC Kg 6.0000 1,540.00 9,240.00
Pasir Pasang M3 0.0100 241,390.00 2,413.90
Pekerja Oh 1.2000 67,000.00 80,400.00
Tukang Batu Oh 1.4500 70,000.00 101,500.00
Kepala Tukang Oh 0.1500 80,000.00 12,000.00
Mandor Oh 0.1000 85,000.00 8,500.00
Perlengkapan 12 % Ls 0.1200 800,000.00 96,000.00
Jumlah 1,110,053.90
Dibulatkan 1,110,050.00
M-04 1 Buah Bak Mandi Fibreflass volume 0,30 M3
Bak Fibreglass Bh 1.0000 281,000.00 281,000.00
Pekerja Oh 1.8000 67,000.00 120,600.00
Tukang Batu Oh 2.7000 70,000.00 189,000.00
Kepala Tukang Oh 0.5400 80,000.00 43,200.00
Mandor Oh 0.1100 85,000.00 9,350.00
Perlengkapan 18 % Ls 0.1800 281,000.00 50,580.00
Jumlah 693,730.00
Dibulatkan 693,730.00
M-05 1 M' Saluran Air Limbah Buis beton d = 30 cm - 60 cm
Buis beton Ø 30 cm bh 1.1000 68,000.00 74,800.00
Bata merah bh 25.0000 850.00 21,250.00
P.C (50 gk) Kg 10.3000 1,540.00 15,862.00
Pasir pasang m3 0.0610 241,390.00 14,724.79
Pasir urug m3 0.0690 181,230.00 12,504.87
Pekerja org 0.3800 67,000.00 25,460.00
Tukang batu org 0.1900 70,000.00 13,300.00
Kepala Tukang org 0.0190 80,000.00 1,520.00
Mandor org 0.0190 85,000.00 1,615.00
Jumlah 181,036.66
Dibulatkan 181,030.00
M-06 1 Buah Bak kontrol Pas. Bata Merah Uk (60 x 60) cm
1 2 3 4 5 6=4x5
Bata Merah bh 186.0000 850.00 158,100.00
Semen PC Kg 114.0000 1,540.00 175,560.00
Pasir Pasang M3 0.1840 241,390.00 44,415.76
Batu pecah 2/3 M3 0.0330 218,260.00 7,202.58
Besi Beton Kg 4.8500 16,500.00 80,025.00
Pasir Beton M3 0.1200 264,140.00 31,696.80
Pekerja Oh 2.1600 67,000.00 144,720.00
Tukang Batu Oh 0.7200 70,000.00 50,400.00
Kepala Tukang Oh 0.0720 80,000.00 5,760.00
Tukang Gali Oh 0.1000 67,000.00 6,700.00
Mandor Oh 0.1080 85,000.00 9,180.00
Jumlah 713,760.14
Dibulatkan 713,760.00
M-07 1 Buah Bak kontrol Pas. Bata Merah Uk (30 x 30) cm
Bata Merah bh 53.0000 850.00 45,050.00
Semen PC Kg 44.0000 1,540.00 67,760.00
Pasir Pasang M3 0.0700 241,390.00 16,897.30
Batu pecah 2/3 M3 0.0700 218,260.00 15,278.20
Besi Beton Kg 1.6000 16,500.00 26,400.00
Pasir Beton M3 0.0600 264,140.00 15,848.40
Pekerja Oh 3.2000 67,000.00 214,400.00
Tukang Batu Oh 1.0150 70,000.00 71,050.00
Kepala Tukang Oh 0.0015 80,000.00 120.00
Mandor Oh 0.0160 85,000.00 1,360.00
Jumlah 474,163.90
Dibulatkan 474,160.00
M-08 1 M¹ Pipa PVC Type AW Ø ½"
Pipa PVC M1 1.2000 10,625.00 12,750.00
Pekerja Oh 0.0360 67,000.00 2,412.00
Tukang Batu Oh 0.0600 70,000.00 4,200.00
Kepala Tukang Oh 0.0060 80,000.00 480.00
Mandor Oh 0.0018 85,000.00 153.00
Perlengkapan 35% Ls 0.3500 12,750.00 4,462.50
Jumlah 24,457.50
Dibulatkan 24,450.00
M-09 1 M¹ Pipa PVC Type AW Ø 1"
Pipa PVC M1 1.2000 16,250.00 19,500.00
Pekerja Oh 0.0360 67,000.00 2,412.00
Tukang Batu Oh 0.0600 70,000.00 4,200.00
Kepala Tukang Oh 0.0060 80,000.00 480.00
Mandor Oh 0.0018 85,000.00 153.00
Perlengkapan 35% Ls 0.3500 19,500.00 6,825.00
Jumlah 33,570.00
Dibulatkan 33,570.00
M-10 1 M¹ Pipa PVC Type AW Ø 1½"
Pipa PVC M1 1.2000 27,500.00 33,000.00
Pekerja Oh 0.0360 67,000.00 2,412.00
Tukang Batu Oh 0.0600 70,000.00 4,200.00
Kepala Tukang Oh 0.0060 80,000.00 480.00
Mandor Oh 0.0018 85,000.00 153.00
Perlengkapan 35% Ls 0.3500 33,000.00 11,550.00
Jumlah 51,795.00
Dibulatkan 51,790.00
M-11 1 M¹ Pipa PVC Type AW Ø 2"
Pipa PVC M1 1.2000 30,000.00 36,000.00
Pekerja Oh 0.0360 67,000.00 2,412.00
Tukang Batu Oh 0.0600 70,000.00 4,200.00
Kepala Tukang Oh 0.0060 80,000.00 480.00
Mandor Oh 0.0018 85,000.00 153.00
1 2 3 4 5 6=4x5
Perlengkapan 35% Ls 0.3500 36,000.00 12,600.00
Jumlah 55,845.00
Dibulatkan 55,840.00
1 M¹ Pipa PVC Type AW Ø 2½"
Pipa PVC M1 1.2000 42,500.00 51,000.00
Perlengkapan 35% Ls 1.0000 17,850.00 17,850.00
Pekerja Oh 0.0540 67,000.00 3,618.00
Tukang Batu Oh 0.0900 70,000.00 6,300.00
Kepala Tukang Oh 0.0090 80,000.00 720.00
Mandor Oh 0.0027 85,000.00 229.50
Jumlah 79,717.50
Dibulatkan 79,710.00
1 M¹ Pipa PVC Type AW Ø 3"
Pipa PVC M1 1.2000 53,750.00 64,500.00
Perlengkapan 35% Ls 1.0000 22,575.00 22,575.00
Pekerja Oh 0.0810 67,000.00 5,427.00
Tukang Batu Oh 0.1350 70,000.00 9,450.00
Kepala Tukang Oh 0.0135 80,000.00 1,080.00
Mandor Oh 0.0041 85,000.00 348.50
Jumlah 103,380.50
Dibulatkan 103,380.00
M-12 1 M¹ Pipa PVC Type AW Ø 4"
Pipa PVC M1 1.2000 90,000.00 108,000.00
Pekerja Oh 0.0810 67,000.00 5,427.00
Tukang Batu Oh 0.1350 70,000.00 9,450.00
Kepala Tukang Oh 0.0135 80,000.00 1,080.00
Mandor Oh 0.0041 85,000.00 348.50
Perlengkapan 35% Ls 0.3500 108,000.00 37,800.00
Jumlah 162,105.50
Dibulatkan 162,100.00
M-13 1 M¹ Pipa PVC Type AW Ø ¾"
Pipa PVC M1 1.2000 13,875.00 16,650.00
Pekerja Oh 0.0810 67,000.00 5,427.00
Tukang Batu Oh 0.1350 70,000.00 9,450.00
Kepala Tukang Oh 0.0135 80,000.00 1,080.00
Mandor Oh 0.0041 85,000.00 348.50
Perlengkapan 35% Ls 0.3500 16,650.00 5,827.50
Jumlah 38,783.00
Dibulatkan 38,780.00
M-14 1 Buah Bak Cuci Piring Stainles Steel
Bak cuci stainles steel Bh 1.0000 438,500.00 438,500.00
Pekerja Oh 0.0300 67,000.00 2,010.00
Tukang Batu Oh 0.3000 70,000.00 21,000.00
Kepala Tukang Oh 0.0300 80,000.00 2,400.00
Mandor Oh 0.0015 85,000.00 127.50
Jumlah 464,037.50
Dibulatkan 464,030.00
M-15 1 Buah Kran Ø ½" atau ¾"
Kran Air Bh 1.0000 45,000.00 45,000.00
Seal Tape Bh 0.0250 4,500.00 112.50
Pekerja Oh 0.0100 67,000.00 670.00
Tukang Batu Oh 0.1000 70,000.00 7,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 54,007.50
Dibulatkan 54,000.00
M-16 1 Buah Floor Drain
Floor Drain Bh 1.0000 73,500.00 73,500.00
Pekerja Oh 0.0100 67,000.00 670.00
1 2 3 4 5 6=4x5
Tukang Batu Oh 0.1000 70,000.00 7,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.0050 85,000.00 425.00
Jumlah 82,395.00
Dibulatkan 82,390.00
M-17 1 M' Grafel beton U 20 cm -60 cm
Pipa beton U bh 1.1000 48,000.00 52,800.00
Bata merah bh 12.0000 850.00 10,200.00
P.C (50 gk) zak 0.1030 1,540.00 158.62
Pasir pasang m3 0.0305 241,390.00 7,362.40
Pasir urug m3 0.0345 181,230.00 6,252.44
Pekerja org 0.0100 67,000.00 670.00
Tukang batu org 0.1000 70,000.00 7,000.00
Kepala Tukang org 0.0100 80,000.00 800.00
Mandor org 0.0050 85,000.00 425.00
Jumlah 85,668.45
Dibulatkan 85,660.00
M-18 1 M' Pasang Talang Plastik PVC U 15 cm (AW)
Talang plastik PVC m' 1.0500 66,000.00 69,300.00
Perlengkapan 35 % harga talang lot 0.3500 69,300.00 24,255.00
Pekerja org 0.1500 67,000.00 10,050.00
Tukang batu org 0.4000 70,000.00 28,000.00
Kepala Tukang org 0.0250 80,000.00 2,000.00
Mandor org 0.0013 85,000.00 106.25
Jumlah 133,711.25
Dibulatkan 133,710.00
M-19 1 M' Saluran Air Limbah Buis beton Ø 60 cm
Buis beton Ø 60 cm bh 1.1000 135,000.00 148,500.00
Bata merah bh 25.0000 850.00 21,250.00
P.C (50 gk) Kg 0.2060 1,540.00 317.24
Pasir pasang m3 0.0610 241,390.00 14,724.79
Pasir urug m3 0.0690 181,230.00 12,504.87
Pekerja org 0.3800 67,000.00 25,460.00
Tukang batu org 0.1900 70,000.00 13,300.00
Kepala Tukang org 0.0190 80,000.00 1,520.00
Mandor org 0.0190 85,000.00 1,615.00
Jumlah 239,191.90
Dibulatkan 239,190.00
M-20 1 M' Pasang Talang Seng Datar
Seng pelat 3" x 6" lbr 0.5000 17,400.00 8,700.00
Paku kg 0.0150 24,000.00 360.00
Kayu kelas II m3 0.0096 2,950,000.00 28,320.00
Meni besi kg 0.2500 33,500.00 8,375.00
Pekerja org 0.1500 67,000.00 10,050.00
Tukang batu org 0.4000 70,000.00 28,000.00
Kepala Tukang org 0.0250 80,000.00 2,000.00
Mandor org 0.0013 85,000.00 106.25
Jumlah 85,911.25
Dibulatkan 85,910.00
M-21 1 Buah Closet Duduk
Closet duduk Bh 1.0000 1,399,500.00 1,399,500.00
Pekerja Oh 3.3000 67,000.00 221,100.00
Tukang Batu Oh 1.1000 70,000.00 77,000.00
Kepala Tukang Oh 0.0100 80,000.00 800.00
Mandor Oh 0.1600 85,000.00 13,600.00
Perlengkapan 6 % Ls 0.0600 1,399,500.00 83,970.00
Jumlah 1,795,970.00
Dibulatkan 1,795,970.00
M-22 1 Buah Tangki Air fibreglass Volume 1 m3
1 2 3 4 5 6=4x5
Bak fibreglass kapasitas 1 m3 bh 1.0000 1,448,500.00 1,448,500.00
Pekerja org 3.3000 67,000.00 221,100.00
Tukang batu org 1.1000 70,000.00 77,000.00
Kepala Tukang org 0.0010 80,000.00 80.00
Mandor org 0.1600 85,000.00 13,600.00
Perlengkapan 6 % harga bak lot 0.0600 1,448,500.00 86,910.00
Jumlah 1,847,190.00
Dibulatkan 1,847,190.00
M-23 1 Unit Septictank 2 x 1,50 x 1,50 M + Rembesannya
Galian tanah M3 4.5000 39,713.00 178,708.50
Pasir urug M3 0.2142 181,230.00 38,819.47
Lantai kerja M3 2.2500 799,800.00 1,799,550.00
Pas bata 1pc : 3ps M2 15.0000 253,400.00 3,801,000.00
Plesteran M2 15.0000 43,170.00 647,550.00
Plat beton penutup & balok M3 0.3000 7,442,960.00 2,232,888.00
Pipa PVC 4" jenis AW + sambungan M1 5.4000 66,250.00 357,750.00
Pipa GIP 1 1/2" M1 5.0000 51,433.33 257,166.67
Galian tanah untuk rembesan M3 3.3750 39,713.00 134,031.38
Pas. Injuk KG 5.4000 25,800.00 139,320.00
Urugan kerikil 3.5 cm M3 1.0500 211,970.00 222,568.50
Pipa PVC 4" berlobang jenis AW M1 9.0000 40,500.00 364,500.00
Urugan kembali perataan tanah M3 1.1250 52,229.00 58,757.63
Jumlah 10,232,610.13
Dibulatkan 10,232,610.00
M-24 1 Unit Septictank 1 x 1,50 x 1,50 M + Rembesannya
Galian tanah M3 2.2500 30,200.00 67,950.00
Pasir urug M3 0.1070 181,230.00 19,391.61
Lantai kerja M3 1.1250 799,800.00 899,775.00
Pas bata 1pc : 3ps M2 7.5000 253,400.00 1,900,500.00
Plesteran M2 7.5000 43,170.00 323,775.00
Plat beton penutup & balok M3 0.1500 7,442,960.00 1,116,444.00
Pipa PVC 4" jenis AW + sambungan M1 9.0000 66,250.00 596,250.00
Pipa GIP 1 1/2" M1 2.5000 9,250.00 23,125.00
Galian tanah untuk rembesan M3 1.6880 30,200.00 50,977.60
Pas. Injuk KG 2.7000 25,800.00 69,660.00
Urugan kerikil 3.5 cm M3 0.5250 211,970.00 111,284.25
Pipa PVC 4" berlobang jenis AW M1 9.0000 40,500.00 364,500.00
Urugan kembali perataan tanah M3 0.5630 52,229.00 29,404.93
Jumlah 5,573,037.39
Dibulatkan 5,573,030.00
1 M¹ Pipa Galvanis Ø ½"
Pipa Galvanis M1 1.2000 20,083.33 24,100.00
Perlengkapan 35% Ls 1.0000 8,435.00 8,435.00
Pekerja Oh 0.0540 67,000.00 3,618.00
Tukang Batu Oh 0.0900 70,000.00 6,300.00
Kepala Tukang Oh 0.0090 80,000.00 720.00
Mandor Oh 0.0270 85,000.00 2,295.00
Jumlah 45,468.00
Dibulatkan 45,460.00
1 M¹ Pipa Galvanis Ø ¾"
Pipa Galvanis M1 1.2000 29,250.00 35,100.00
Perlengkapan 35% Ls 1.0000 12,285.00 12,285.00
Pekerja Oh 0.0540 67,000.00 3,618.00
Tukang Batu Oh 0.0900 70,000.00 6,300.00
Kepala Tukang Oh 0.0090 80,000.00 720.00
Mandor Oh 0.0270 85,000.00 2,295.00
Jumlah 60,318.00
Dibulatkan 60,310.00
1 M¹ Pipa Galvanis Ø 1"
1 2 3 4 5 6=4x5
Pipa Galvanis M1 1.2000 33,283.33 39,940.00
Perlengkapan 35% Ls 1.0000 13,979.00 13,979.00
Pekerja Oh 0.0540 67,000.00 3,618.00
Tukang Batu Oh 0.0900 70,000.00 6,300.00
Kepala Tukang Oh 0.0090 80,000.00 720.00
Mandor Oh 0.0270 85,000.00 2,295.00
Jumlah 66,852.00
Dibulatkan 66,850.00
1 M¹ Pipa Galvanis Ø 1½"
Pipa Galvanis M1 1.2000 51,433.33 61,720.00
Perlengkapan 35% Ls 1.0000 21,602.00 21,602.00
Pekerja Oh 0.1080 67,000.00 7,236.00
Tukang Batu Oh 0.1800 70,000.00 12,600.00
Kepala Tukang Oh 0.0180 80,000.00 1,440.00
Mandor Oh 0.0054 85,000.00 459.00
Jumlah 105,057.00
Dibulatkan 105,050.00
1 M¹ Pipa Galvanis Ø 3"
Pipa Galvanis M1 1.2000 155,816.67 186,980.00
Perlengkapan 35% Ls 1.0000 65,443.00 65,443.00
Pekerja Oh 0.1080 67,000.00 7,236.00
Tukang Batu Oh 0.1800 70,000.00 12,600.00
Kepala Tukang Oh 0.0180 80,000.00 1,440.00
Mandor Oh 0.0054 85,000.00 459.00
Jumlah 274,158.00
Dibulatkan 274,150.00
1 M¹ Pipa Galvanis Ø 4"
Pipa Galvanis M1 1.2000 158,333.33 190,000.00
Perlengkapan 35% Ls 1.0000 66,500.00 66,500.00
Pekerja Oh 0.1350 67,000.00 9,045.00
Tukang Batu Oh 0.2250 70,000.00 15,750.00
Kepala Tukang Oh 0.0225 80,000.00 1,800.00
Mandor Oh 0.0068 85,000.00 578.00
Jumlah 283,673.00
Dibulatkan 283,670.00
1 Buah Bak kontrol Pas. Batu Bata (45 x 45) cm, Tinggi 50 cm
Batu Bata M2 0.2500 59,500.00 14,875.00
Semen PC Kg 77.0000 1,540.00 118,580.00
Pasir Pasang M3 0.1300 241,390.00 31,380.70
Batu Kerikil M3 0.0200 178,600.00 3,572.00
Besi Beton Kg 2.6000 16,500.00 42,900.00
Pasir Beton M3 0.0900 264,140.00 23,772.60
Pekerja Oh 1.4200 67,000.00 95,140.00
Tukang Batu Oh 0.4730 70,000.00 33,110.00
Kepala Tukang Oh 0.0470 80,000.00 3,760.00
Mandor Oh 0.0710 85,000.00 6,035.00
Jumlah 373,125.30
Dibulatkan 373,120.00
1 M' Saluran Air Hujan Lbr. 20 cm
Galian tanah M3 0.1000 30,200.00 3,020.00
Urugan pasir M3 0.0100 238,420.00 2,384.20
Pas. Bata merah ad. 1 : 5 M2 0.3500 115,780.00 40,523.00
Pas. Plesteran ad. 1 : 5 M2 0.4000 56,320.00 22,528.00
Pas. Beton tumbuk ad. 1 : 3 : 5 M3 0.0150 799,800.00 11,997.00
Perapihan 5% - 4,022.61 4,022.61
Jumlah 84,474.81
Dibulatkan 84,470.00
1 M' Perbaikan Saluran Air Hujan Lbr. 20 cm
Pas. Plesteran ad. 1 : 5 M2 0.4000 56,320.00 22,528.00
1 2 3 4 5 6=4x5
Pas. Beton tumbuk ad. 1 : 3 : 5 M3 0.0150 799,800.00 11,997.00
Perapihan 5% - 1,726.25 1,726.25
Jumlah 36,251.25
Dibulatkan 36,250.00
N PEKERJAAN PENGECATAN
N-01 1 M2 Mengikis / Mengerok Permukaan Cat Tembok Lama
Soda Api Kg 0.0500 39,500.00 1,975.00
Pekerja Oh 0.1500 67,000.00 10,050.00
Mandor Oh 0.0025 85,000.00 212.50
Jumlah 12,237.50
Dibulatkan 12,230.00
N-02 1 M2 Mendempul dan Menggosok Kayu
Dempul Jadi Kg 0.0800 40,000.00 3,200.00
Minyak Cat Kg 0.0200 42,300.00 846.00
Batu Apung Kg 0.0100 30,640.00 306.40
Pekerja Oh 0.0400 67,000.00 2,680.00
Tukang Cat Oh 0.0400 70,000.00 2,800.00
Kepala Tukang Oh 0.0040 80,000.00 320.00
Mandor Oh 0.0025 85,000.00 212.50
Jumlah 10,364.90
Dibulatkan 10,360.00
N-03 1 M2 Pengecatan Bidang Kayu dan Besi lama Setara Glotex
Plamir Kg 0.1500 27,500.00 4,125.00
Cat Dasar Kg 0.1700 35,000.00 5,950.00
Cat Penutup setara Glotex 2X Kg 0.1700 45,900.00 7,803.00
Pekerja Oh 0.0700 67,000.00 4,690.00
Tukang Cat Oh 0.0750 70,000.00 5,250.00
Kepala Tukang Oh 0.0075 80,000.00 600.00
Mandor Oh 0.0025 85,000.00 212.50
Jumlah 28,630.50
Dibulatkan 28,630.00
N-03 1 M2 Pengecatan Bidang Kayu lama Setara Pinotex
Plamir Kg 0.1500 27,500.00 4,125.00
Cat Dasar Kg 0.1700 35,000.00 5,950.00
Cat Penutup setara Pinotex 2X Kg 0.1700 52,500.00 8,925.00
Pekerja Oh 0.0700 67,000.00 4,690.00
Tukang Cat Oh 0.0750 70,000.00 5,250.00
Kepala Tukang Oh 0.0075 80,000.00 600.00
Mandor Oh 0.0025 85,000.00 212.50
Jumlah 29,752.50
Dibulatkan 29,750.00
N-04 1 M2 Pengecatan Bidang Kayu Baru Setara Glotex 3 X laburan
Cat Meni Kg 0.2000 33,500.00 6,700.00
Plamir Kg 0.1500 27,500.00 4,125.00
Cat Dasar Kg 0.1700 35,000.00 5,950.00
Cat Penutup setara Glotex 3X Kg 0.3500 45,900.00 16,065.00
Pekerja Oh 0.0700 67,000.00 4,690.00
Tukang Cat Oh 0.1050 70,000.00 7,350.00
Kepala Tukang Oh 0.0040 80,000.00 320.00
Mandor Oh 0.0025 85,000.00 212.50
Jumlah 45,412.50
Dibulatkan 45,410.00
1 M2 Pengecatan Bidang Kayu Baru Setara Sieve 2 X laburan
Cat Meni Kg 0.2000 33,500.00 6,700.00
Plamir Kg 0.1500 27,500.00 4,125.00
Cat Dasar Kg 0.1700 35,000.00 5,950.00
Cat Penutup setara Sieve 2X Kg 0.2600 45,900.00 11,934.00
Pekerja Oh 0.0700 67,000.00 4,690.00
1 2 3 4 5 6=4x5
Tukang Cat Oh 0.0090 70,000.00 630.00
Kepala Tukang Oh 0.0060 80,000.00 480.00
Mandor Oh 0.0025 85,000.00 212.50
Jumlah 34,721.50
Dibulatkan 34,720.00
N-05 1 M2 Pelaburan Bidang Kayu dengan Politur
Politur Ltr 0.1500 55,000.00 8,250.00
Politur Jadi Ltr 0.3720 125,000.00 46,500.00
Ampelas Lbr 2.0000 5,500.00 11,000.00
Tukang Cat Oh 0.0600 70,000.00 4,200.00
Kepala Tukang Oh 0.0160 80,000.00 1,280.00
Mandor Oh 0.0025 85,000.00 212.50
Jumlah 71,442.50
Dibulatkan 71,440.00
N-06 1 M2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter
Residu atau Ter Ltr 0.3500 9,000.00 3,150.00
Pekerja Oh 0.1000 67,000.00 6,700.00
Mandor Oh 0.0060 85,000.00 510.00
Jumlah 10,360.00
Dibulatkan 10,360.00
N-07 1 M2 Pengecatan Tembok Setara ICI Exterior (weather shield)
Plamir Kg 0.1000 27,500.00 2,750.00
Cat Dasar Kg 0.1000 35,000.00 3,500.00
Cat Penutup setara ICI Exterior 2X Kg 0.2600 135,000.00 35,100.00
Pekerja Oh 0.0200 67,000.00 1,340.00
Tukang Cat Oh 0.0630 70,000.00 4,410.00
Kepala Tukang Oh 0.0063 80,000.00 504.00
Mandor Oh 0.0025 85,000.00 212.50
Jumlah 47,816.50
Dibulatkan 47,810.00
N-07 1 M2 Pengecatan Tembok Setara ICI Interior
Plamir Kg 0.1000 27,500.00 2,750.00
Cat Dasar Kg 0.1000 35,000.00 3,500.00
Cat Penutup setara ICI Interior 2X Kg 0.2600 92,500.00 24,050.00
Pekerja Oh 0.0200 67,000.00 1,340.00
Tukang Cat Oh 0.0630 70,000.00 4,410.00
Kepala Tukang Oh 0.0063 80,000.00 504.00
Mandor Oh 0.0025 85,000.00 212.50
Jumlah 36,766.50
Dibulatkan 36,760.00
N-08 1 M2 Pengecatan Tembok Lama Setara ICI Weather Shield
Cat Dasar Kg 0.1200 35,000.00 4,200.00
Cat Penutup setara ICI 2X Kg 0.1800 135,000.00 24,300.00
Pekerja Oh 0.0280 67,000.00 1,876.00
Tukang Cat Oh 0.0420 70,000.00 2,940.00
Kepala Tukang Oh 0.0042 80,000.00 336.00
Mandor Oh 0.0025 85,000.00 212.50
Jumlah 33,864.50
Dibulatkan 33,860.00
N-09 1 M2 Pengecatan Plafond ( 3x ) setara ICI
Cat tembok setara ICI Kg 0.2000 92,500.00 18,500.00
Plamir tembok Kg 0.1600 27,500.00 4,400.00
Rol cat Bh 0.0100 35,000.00 350.00
Steger werk Ls 1.0000 1,000.00 1,000.00
Ampelas Lbr 0.5000 5,500.00 2,750.00
Pekerja setengah trampil Oh 0.2000 67,000.00 13,400.00
Tukang cat Oh 0.3000 70,000.00 21,000.00
Kepala tukang Oh 0.0300 80,000.00 2,400.00
Mandor Oh 0.0100 85,000.00 850.00
1 2 3 4 5 6=4x5
Jumlah 64,650.00
Dibulatkan 64,650.00
N-10 1 M2 Pengecatan Plafond ( 3x ) setara Vinilex
Cat tembok setara Vinilex Kg 0.2000 27,500.00 5,500.00
Plamir tembok Kg 0.1600 27,500.00 4,400.00
Rol cat Bh 0.0100 35,000.00 350.00
Steger werk Ls 1.0000 1,000.00 1,000.00
Ampelas Lbr 0.5000 5,500.00 2,750.00
Pekerja setengah trampil Oh 0.2000 67,000.00 13,400.00
Tukang cat Oh 0.3000 70,000.00 21,000.00
Kepala tukang Oh 0.0300 80,000.00 2,400.00
Mandor Oh 0.0100 85,000.00 850.00
Jumlah 51,650.00
Dibulatkan 51,650.00
N-10r 1 M2 Pengecatan Plafond ( 2x ) setara Vinilex
Cat tembok setara Vinilex Kg 0.1300 27,500.00 3,575.00
Plamir tembok Kg 0.1100 27,500.00 3,025.00
Rol cat Bh 0.0100 35,000.00 350.00
Steger werk Ls 0.6700 1,000.00 670.00
Ampelas Lbr 0.3300 5,500.00 1,815.00
Pekerja setengah trampil Oh 0.1300 67,000.00 8,710.00
Tukang cat Oh 0.2000 70,000.00 14,000.00
Kepala tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0100 85,000.00 850.00
Jumlah 34,595.00
Dibulatkan 34,590.00
N-11 1 M2 Pemasangan Wall Paper
Wall Paper M3 1.2000 61,500.00 73,800.00
Perekat Kg 0.2500 39,300.00 9,825.00
Pekerja Oh 0.3500 67,000.00 23,450.00
Tukang Cat Oh 0.1750 70,000.00 12,250.00
Kepala Tukang Oh 0.0170 80,000.00 1,360.00
Mandor Oh 0.0017 85,000.00 144.50
Jumlah 120,829.50
Dibulatkan 120,820.00
N-12 1 M2 Pengecatan Permukaan Baja dengan Meni Besi
Meni Besi Kg 0.1000 33,500.00 3,350.00
Kuas Bh 0.0100 16,500.00 165.00
Pekerja Oh 0.0200 67,000.00 1,340.00
Tukang Cat Oh 0.2000 70,000.00 14,000.00
Kepala Tukang Oh 0.0200 80,000.00 1,600.00
Mandor Oh 0.0100 85,000.00 850.00
Jumlah 21,305.00
Dibulatkan 21,300.00
N-13 1 M2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah
Meni Besi Kg 0.1000 33,500.00 3,350.00
Kuas Bh 0.0100 16,500.00 165.00
Perancah Kayu M3 0.0020 2,276,800.00 4,553.60
Pekerja Oh 0.2500 67,000.00 16,750.00
Tukang Cat Oh 0.2250 70,000.00 15,750.00
Kepala Tukang Oh 0.0225 80,000.00 1,800.00
Mandor Oh 0.0075 85,000.00 637.50
Jumlah 43,006.10
Dibulatkan 43,000.00
N-14 1 M2 Pengecatan Permukaan Baja Lapis seng (galbani) secara manual 1 lps cat 2 um
Cat besi setara ICI Kg 0.3000 74,500.00 22,350.00
Pekerja Oh 0.0060 67,000.00 402.00
Tukang Cat Oh 0.0600 70,000.00 4,200.00
Kepala Tukang Oh 0.0120 80,000.00 960.00
1 2 3 4 5 6=4x5
Mandor Oh 0.0060 85,000.00 510.00
Jumlah 28,422.00
Dibulatkan 28,420.00
N-15 1 M2 Pengecatan Tembok Baru Setara Vinilex (3 x laburan)
Plamir Kg 0.1600 27,500.00 4,400.00
Cat Dasar Kg 0.1000 35,000.00 3,500.00
Cat Penutup setara Vinilex 3X Kg 0.3900 27,500.00 10,725.00
Pekerja Oh 0.0300 67,000.00 2,010.00
Tukang Cat Oh 0.1890 70,000.00 13,230.00
Kepala Tukang Oh 0.0189 80,000.00 1,512.00
Mandor Oh 0.0019 85,000.00 160.65
Jumlah 35,537.65
Dibulatkan 35,530.00
N-15r 1 M2 Pengecatan Tembok Setara Vinilex (2 x laburan)
Plamir Kg 0.1000 27,500.00 2,750.00
Cat Dasar Kg 0.1000 35,000.00 3,500.00
Cat Penutup setara Vinilex 2X Kg 0.3900 27,500.00 10,725.00
Pekerja Oh 0.0300 67,000.00 2,010.00
Tukang Cat Oh 0.0945 70,000.00 6,615.00
Kepala Tukang Oh 0.0095 80,000.00 760.00
Mandor Oh 0.0038 85,000.00 323.00
Jumlah 26,683.00
Dibulatkan 26,680.00
N-16 1 M2 Pengecatan Tembok Lama Setara Vinilex
Cat Dasar Kg 0.1200 35,000.00 4,200.00
Cat Penutup setara Vinilex 2X Kg 0.1800 27,500.00 4,950.00
Pekerja Oh 0.0280 67,000.00 1,876.00
Tukang Cat Oh 0.0420 70,000.00 2,940.00
Kepala Tukang Oh 0.0042 80,000.00 336.00
Mandor Oh 0.0025 85,000.00 212.50
Jumlah 14,514.50
Dibulatkan 14,510.00
D PEKERJAAN BETON
1 M2 Lantai kerja beton tumbuk, 1 Pc : 3 Ps : 5 Kr. tebal 5 cm 110,990.00
1 1 M3 Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr D-01 799,800.00
2 1 M3 Beton Tumbuk, 1 Pc : 3 Ps : 6 Kr D-02 769,540.00
3 1 M3 Beton Tumbuk, 1 Pc : 2 Ps : 3 Kr D-03 1,083,160.00
4 1 M3 Tiang Pancang Prestressed Beton D-04 1,164,170.00
5 1 M3 Beton Tumbuk, 1 Pc : 2 Ps : 4 Kr D-05 1,021,560.00
6 1 M' Memasang PVC Waterstop Lebar 200 mm D-06 73,970.00
1 M' Memasang PVC Waterstop Lebar 150 mm 65,710.00
7 1 Kg Pembesian Dengan Besi Polos atau Besi Ulir D-07 18,820.00
8 1 M2 Pasangan Bekisting untuk Pondasi D-08 166,000.00
9 1 M2 Pasangan Bekisting untuk Sloof D-09 180,750.00
KODE HARGA
No. URAIAN SATUAN
ANAL SATUAN
10 1 M2 Pasangan Bekisting untuk Kolom D-10 336,410.00
11 1 M2 Pasangan Bekisting untuk Balok D-11 342,510.00
12 1 M2 Pasangan Bekisting untuk Lantai D-12 466,600.00
13 1 M2 Pasang Bekisting untuk Tangga D-13 312,990.00
14 1 M3 Membuat Beton Cor Mutu K225 D-14 1,491,830.00
15 1 M3 Membuat Beton Cor Mutu K275 D-15 1,481,370.00
16 1 M3 Pondasi Beton Tulang (150 kg besi+bekisting) D-16 4,440,360.00
17 1 M3 Sloof Beton Tulang (200 kg besi+bekisting) D-17 5,638,590.00
1 M3 Sloof Beton Tulang 15/20 cm (150 kg besi+bekisting) 4,840,590.00
1 M3 Sloof Beton Tulang 15/20 cm (180 kg besi+bekisting) 4 dia. 12 ring 8-15 5,308,590.00
1 M3 Sloof Beton Tulang 20/30 cm (150 kg besi+bekisting) 4 dia. 16 ring 8-15 4,813,590.00
1 M3 Sloof Beton Tulang 20/30 cm (200 kg besi+bekisting) Struktur bertingkat 6 dia. 16, 8-15 5,638,590.00
1 M3 Sloof Beton Bertulang 20/40 cm (240 kg besi+bekisting) Struktur bertingkat 6,325,590.00
18 1 M3 Kolom Beton Tulang (120 kg besi+bekisting) D-18 6,768,860.00
19 1 M3 Kolom Beton Tulang (140 kg besi+bekisting) D-19 7,098,860.00
20 1 M3 Kolom Beton Tulang (150 kg besi+bekisting) D-20 7,263,860.00
21 1 M3 Kolom Beton Tulang (180 kg besi+bekisting) D-21 7,758,860.00
22 1 M3 Kolom Beton Tulang (200 kg besi+bekisting) D-22 8,088,860.00
23 1 M3 Kolom Beton Tulang (250 kg besi+bekisting) D-23 8,913,860.00
24 1 M3 Kolom Beton Tulang (300 kg besi+bekisting) D-24 9,738,860.00
1 M3 Kolom Beton Tulang 20/20 cm (140 kg besi+bekisting) 4 dia. 12, 8-15 7,008,860.00
1 M3 Kolom Beton Tulang 15/20 (180 kg besi+bekisting) 4 dia. 12, 8-15 7,668,860.00
1 M3 Kolom Beton Tulang 20/20 cm (210 kg besi+bekisting) Struktur bertingkat 4 dia. 16, 8-15 8,163,860.00
1 M3 Kolom Beton Tulang 20/30cm (230 kg besi+bekisting) Struktur bertingkat 6 dia.16+2 dia.12, 8-15 8,493,860.00
1 M3 Kolom Beton Tulang 20/40 cm (250 kg besi+bekisting) Struktur bertingkat 8,913,860.00
1 M3 Kolom Beton Tulang 30/30 cm (175 kg besi+bekisting) Struktur bertingkat 8 dia. 16, 8-15 7,586,360.00
1 M3 Kolom Beton Tulang 30/30 cm (210 kg besi bekisting) Struktur bertingkat 10 dia. 16, 8-15 8,163,860.00
1 M3 Kolom Beton Tulang 30/40 cm (200 kg besi bekisting) Struktur bertingkat 8,088,860.00
1 M3 Kolom Beton Tulang Praktis 12/12 cm (175 kg besi+bekisting) 6,597,860.00
1 M3 Kolom Beton Tulang Praktis 12/12 cm (260 kg besi+bekisting) 4 dia. 10, 8-15 8,000,360.00
1 M3 Kolom Beton Tulang (200 kg besi+bekisting) 8,081,210.00
1 M3 Kolom Beton Tulang (250 kg besi+bekisting) 8,906,210.00
1 M3 Kolom Beton Tulang (300 kg besi+bekisting) 9,731,210.00
25 1 M3 Balok Beton Tulang (120 kg besi+bekisting) D-25 6,042,310.00
26 1 M3 Balok Beton Tulang (150 kg besi+bekisting) D-26 6,639,540.00
27 1 M3 Balok Beton Tulang (200 kg besi+bekisting) D-27 6,810,840.00
28 1 M3 Balok Beton Tulang (230 kg besi+bekisting) D-28 7,907,640.00
1 M3 Balok Beton Tulang 15/20 cm (150 kg besi+bekisting) 6,551,040.00
1 M3 Balok Beton Tulang 15/20 (180 kg besi+bekisting) 4 dia. 12, 8-15 6,974,040.00
1 M3 Balok Beton Lintel 11/11 (300 kg besi+bekisting) 4 dia. 10, 8-15 8,660,360.00
1 M3 Balok Beton Tulang 15/20 sofi-sofi, ring balk+balok portal (180 kg besi+bekisting) 4 dia.12, 8-15 6,974,040.00
1 M3 Balok Beton Tulang 15/30 (190 kg besi+bekisting) Struktur bertingkat 4 dia. 16, 8-15 7,139,040.00
1 M3 Balok Beton Tulang 20/40 (200 kg besi+bekisting) Struktur bertingkat 7 dia. 16+2 dia. 12, 8-15 7,326,910.00
1 M3 Balok Beton Tulang 20/30 (200 kg besi+bekisting) Struktur bertingkat 6 dia. 16, 8-15 7,326,910.00
1 M3 Balok Beton Tulang 20/30 (175 kg besi+bekisting) Struktur bertingkat 5 dia. 16, 8-15 6,914,410.00
1 M3 Balok Beton Tulang 25/55 (140 kg besi+bekisting) Struktur bertingkat 8 dia. 16+2 dia. 12, 8-15 6,336,910.00
1 M3 Balok Beton Tulang 30/60 (110 kg besi+ bekisting) Struktur bertingkat 9 dia. 19+2 dia. 12, 8-15 5,841,910.00
29 1 M3 Tangga Beton Tulang (200 kg besi+bekisting) D-29 6,899,760.00
30 1 M3 Plat Lantai Tb. 10 Cm Beton Bertulang (90 kg besi+bekisting) D-30 7,442,960.00
31 1 M3 Plat Lantai Tb. 12 Cm Beton Bertulang (110 kg besi+bekisting) D-31 7,040,130.00
32 1 M3 Plat Lantai Tb. 12 Cm Beton Bertulang (130 kg besi+bekisting) D-32 7,416,530.00
33 1 M3 Plat Lantai Tb. 15 Cm Beton Bertulang (90 kg besi+bekisting) D-33 5,889,180.00
34 1 M3 Plat Lantai Tb. 15 Cm Beton Bertulang (115 kg besi+bekisting) D-34 6,359,680.00
35 1 M' Kolom Praktis Beton Tulang ( 11 x 11 ) Cm D-35 75,670.00
36 1 M' Ring Balok Beton Tulang ( 10 x 15 ) Cm D-36 99,230.00
37 1 M2 Pasang Bekisting untuk Dinding D-37 370,760.00
38 1 M3 Pelat Beton Tulang (150 kg besi+bekisting) D-38 6,805,660.00
39 1 M3 Dinding Beton Tulang (150 kg besi+bekisting) D-39 6,550,040.00
40 1 M3 Dinding Beton Tulang (200 kg besi+bekisting) D-40 6,898,230.00
41 1 M3 Membuat Beton Cor Mutu K300 D-41 1,036,100.00
42 1 M3 Membuat Beton Cor Mutu K200 D-42 951,870.00
43 1 M3 Membuat Beton Cor Mutu K250 D-43 995,880.00
1 M3 Membuat Beton dengan Puzzdith - 100 XR 973,710.00
1 M3 Membuat Beton Kedap Air dengan AM - 100 1,213,490.00
1 Kg Kabel Presstressed Polos / Strands 18,380.00
1 Kg Jaring Kawat Baja 60,740.00
1 M3 Membuat Beton Cor Mutu K175 1,026,140.00
1 M2 Pasangan Jembatan Cor 104,510.00
1 M3 Listplank Beton Tulang T=8 cm ( 77,50 kg besi + bekisting ) 6,428,480.00
KODE HARGA
No. URAIAN SATUAN
ANAL SATUAN
E PEKERJAAN DINDING
1 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 3Ps E-01 253,400.00
2 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 4Ps E-02 244,030.00
3 1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 Pc : 5Ps E-03 239,500.00
4 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 3Ps E-04 121,800.00
5 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 4Ps E-05 118,100.00
6 1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 5Ps E-06 115,780.00
7 1 M2 Pasang Dinding Roster Beton 20 x 20 ad.1pc : 3 ps E-07 633,330.00
8 1 M2 Pasang Dinding Roster Beton 20 x 20 ad.1pc : 4 ps E-08 630,560.00
9 1 M2 Pasang Dinding Roster/terawang (12 x 11 x 24) cm E-09 633,330.00
10 1 M2 Pasang Dinding Batako Besar Pres uk. 8 x 20 x 30 ad. 1pc : 4ps E-10 91,920.00
11 1 M2 Pasang Dinding Hollowblock (HB-20) E-11 172,390.00
12 1 M2 Pasang Dinding Hollowblock (HB-15) E-12 170,760.00
13 1 M2 Pasang Dinding Hollowblock (HB-10) E-13 126,060.00
14 1 M2 Pasang Dinding Conblock (CB-20) E-14 212,190.00
15 1 M2 Pasang Dinding Conblock (CB-15) E-15 159,670.00
16 1 M2 Pasang Dinding Conblock (CB-10) E-16 122,170.00
17 1 M2 Pasang Dinding Keramik 10 x 20 Cm Corak setara Mulia E-17 123,370.00
18 1 M2 Pasang Dinding Keramik 10 x 20 Cm Polos setara Mulia E-18 120,870.00
19 1 M2 Pasang Dinding Keramik 20 x 20 Cm Corak setara Mulia E-19 125,870.00
20 1 M2 Pasang Dinding Keramik 20 x 20 Cm polos setara Mulia E-20 120,870.00
21 1 M2 Pasang Dinding Keramik 20 x 25 Cm polos setara Mulia E-21 120,870.00
22 1 M2 Pasang Dinding Keramik 20 x 25 Cm Corak setara Mulia E-22 125,870.00
23 1 M2 Pasang Dinding Keramik 30 x 30 Cm corak setara Mulia E-23 116,370.00
24 1 M2 Pasang Dinding Keramik 30 x 30 Cm corak setara Mulia E-24 121,370.00
25 1 M2 Pasang Dinding Keramik 40 x 40 Cm polos setara Mulia E-25 128,370.00
26 1 M2 Pasang Dinding Keramik 40 x 40 Cm corak setara Mulia E-26 126,870.00
27 1 M2 Pasang Dinding Keramik 10 x 20 Cm Corak setara Roman E-27 140,870.00
28 1 M2 Pasang Dinding Keramik 10 x 20 Cm Polos setara Roman E-28 126,370.00
29 1 M2 Pasang Dinding Keramik 20 x 20 Cm Corak setara Roman E-29 143,870.00
30 1 M2 Pasang Dinding Keramik 20 x 20 Cm polos setara Roman E-30 126,370.00
31 1 M2 Pasang Dinding Keramik 20 x 25 Cm polos setara Roman E-31 136,870.00
32 1 M2 Pasang Dinding Keramik 20 x 25 Cm Corak setara Roman E-32 142,370.00
33 1 M2 Pasang Dinding Keramik 30 x 30 Cm polos setara Roman E-33 136,870.00
34 1 M2 Pasang Dinding Keramik 30 x 30 Cm corak setara Roman E-34 140,870.00
35 1 M2 Pasang Dinding Keramik 40 x 40 Cm polos setara Roman E-35 140,870.00
36 1 M2 Pasang Dinding Keramik 40 x 40 Cm corak setara Roman E-36 145,870.00
36 1 M2 Pasang Dinding Keramik 20 x 40 Cm corak setara Roman E-36 143,870.00
37 1 M2 Pasang Dinding Marmer E-37 798,910.00
38 1 M2 Pasang Dinding Batu Tempel Hitam E-38 102,930.00
39 1 M2 Pasang Dinding Poslin 11 x 11 Cm E-39 130,870.00
40 1 M2 Wall paper E-40 111,630.00
41 1 M2 Dinding Pemisah Teakwood Rangkap, Rangka Kayu Kamper Medan E-41 364,190.00
42 1 M2 Dinding Pemisah Plywood Rangkap, Rangka Kayu Kamper Medan E-42 478,310.00
43 1 M2 Dinding Pemisah Triplek Rangkap, Rangka Kayu Kamper Medan E-43 313,620.00
44 1 M2 Dinding Pemisah GRC tb. 4 mm + rangka besi hollow E-44 103,050.00
45 1 M2 Dinding Pemisah Gypsum dobel tb. 9 mm + rangka besi hollow E-45 215,790.00
46 1 M2 Dinding Plywood tb. 4 mm + rangka besi hollow E-46 157,410.00
47 1 M2 Dinding Teakwood tb. 4 mm + rangka besi hollow E-47 115,550.00
48 1 M2 Pasang Dinding Glass Block 20 x 20 ad. 1pc : 4 ps E-48 925,760.00
49 1 M2 Pasang Dinding Anyaman Bambu, rangka kayu E-49 117,660.00
F PEKERJAAN PLESTERAN
1 1 M2 Plesteran 1 Pc : 2 Ps, Tebal 15 mm F-01 43,170.00
2 1 M2 Plesteran 1 Pc : 3 Ps, Tebal 15 mm F-02 40,510.00
3 1 M2 Plesteran 1 Pc : 4 Ps, Tebal 15 mm F-03 38,780.00
1 M2 Plesteran 1 Pc : 5 Ps, Tebal 15 mm + Acian 37,910.00
4 1 M2 Plesteran 1 Pc : 3 Ps, Tebal 20 mm F-04 56,320.00
5 1 M2 Plesteran 1 Pc : 4 Ps, Tebal 20 mm F-05 53,530.00
6 1 M2 Plesteran 1 Pc : 5 Ps, Tebal 20 mm F-06 50,910.00
7 1 M2 Barapen 1 Pc : 5 Ps, Tebal 15 mm F-07 30,470.00
8 1 M2 Plesteran Beton 1 Pc : 2 Ps, Tebal 15 mm F-08 52,790.00
9 1 M2 Plesteran Beton 1 Pc : 3 Ps, Tebal 15 mm F-09 50,080.00
10 1 M2 Plesteran Skoning 1 Pc : 2 Ps, Tebal 10 mm F-10 40,800.00
11 1 M2 Acian Plesteran F-11 24,960.00
12 1 M2 Plesteran Siar Adukan 1 Pc : 2 Ps batu belah F-12 45,730.00
13 1 M2 Plesteran Siar Adukan 1 Pc : 2 Ps dinding bata merah F-13 26,700.00
KODE HARGA
No. URAIAN SATUAN
ANAL SATUAN
G PEKERJAAN PENUTUP ATAP
1 1 M2 Pasang Atap Genteng Pelentong G-01 66,620.00
1 M2 Pasang Atap Genteng Pelentong Existing (Lama) 16,620.00
2 1 M2 Pasang Genteng Bubungan Palentong G-02 95,110.00
3 1 M2 Pasang Roof Ligt Fiberglass ( 180 x 90 ) Cm G-03 82,420.00
4 1 M2 Pasang Atap Asbes Gelombang ( 3.00 x 1.05 m ) x 4 mm G-04 49,110.00
5 1 M2 Pasang Atap Asbes Gelombang ( 2.70 x 1.05 m ) x 4 mm G-05 52,330.00
6 1 M2 Pasang Atap Asbes Gelombang ( 2.40 x 1.05 m ) x 4 mm G-06 50,210.00
7 1 M2 Pasang Atap Asbes Gelombang ( 2.10 x 1.05 m ) x 4 mm G-07 51,510.00
8 1 M2 Pasang Atap Asbes Gelombang besar 80 x 180 x 5 mm G-08 103,750.00
9 1 M' Pasang Nok Stel Gelombang 1.05 m G-09 102,750.00
10 1 M2 Pasang Atap Genteng Beton G-10 123,420.00
11 1 M2 Pasang Atap Genteng Morando Natural G-11 70,620.00
12 1 M2 Pasang Atap Genteng Morando Glasur G-12 97,620.00
13 1 M2 Pasang Atap Genteng Metal G-13 255,580.00
14 1 M' Pasang Nok Genteng Beton G-14 123,150.00
15 1 M' Pasang Nok Genteng Metal G-15 198,500.00
16 1 M2 Pasang Atap Seng Gelombang G-16 77,760.00
17 1 M2 Pasang Atap Nok Seng G-17 33,710.00
18 1 M2 Pasang Alluminium Foil / Sisalation G-18 35,630.00
19 1 M2 Pasang Atap Alluminium Natural G-19 226,810.00
20 1 M2 Pasang Atap Alluminium Warna G-20 255,690.00
21 1 M2 Pasang Nol Alluminium G-21 173,280.00
22 1 M' Pasang Listplang GRC lebar 30 Cm G-22 49,230.00
1 M' Pasang Listplang GRC lebar 30 Cm , tebal 9 mm 67,070.00
23 1 M' Pasang Nok Pinggir Morando Natural G-23 32,720.00
1 M' Pasang Bubungan Stel Gelombang 0.92 m 40,050.00
1 M' Pasang Nok Sirap 79,840.00
1 M' Pasang Genteng Bubungan Morando Naatural 96,610.00
1 M' Pasang Genteng Bubungan Morando Glazur 110,610.00
1 M2 Pasang Water Proofing Membrance tb. 3 mm 137,620.00
J PEKERJAAN KAYU
1 1 M3 Pasang Kusen Pintu dan Jendela Kayu Kamper Samarinda J-01 13,247,500.00
2 1 M3 Pasang Kusen Pintu dan Jendela Kayu Kamper Medan/Kruing J-02 9,361,900.00
3 1 M3 Pasang Kusen Pintu dan Jendela Kayu Borneo Super J-03 8,819,500.00
4 1 M2 Pasang Pintu Panel Kayu Kamper Samarinda J-04 651,320.00
5 1 M2 Pasang Pintu Panel Kayu Kamper Medan/Kruing J-05 523,680.00
6 1 M2 Pasang Daun Jendela Kaca Kayu Kamper Medan J-06 309,080.00
7 1 M2 Pasang Pintu dan Jendela Kaca Kayu Borneo J-07 428,440.00
8 1 M2 Pasang Pintu dan Jendela Jalusi Kayu Kamper Medan J-08 753,470.00
9 1 M2 Pasang Pintu Triplek Rangkap, Rangka Tertutup Kayu Kamper Medan/Kruing J-09 401,410.00
10 1 M2 Pasang Jalusi Mati Kusen kayu Kamper Medan J-10 587,570.00
11 1 M2 Pasang Daun Pintu Triplek Rangkap, Rangka Kayu Kamper J-11 401,410.00
12 1 M2 Pasang Daun Pintu Teakwood Rangkap, Rangka Kayu Kamper Medan J-12 484,390.00
13 1 M2 Pasang Pintu dobel Plywood lapis HPL, Rangka Kayu Kamper Medan J-13 561,790.00
14 1 M2 Pasang Pintu Teakwood lapis HPL , Rangka Kayu Kamper Medan J-14 709,540.00
15 1 M3 Pasang Konstruksi Kuda - Kuda Kayu Kamper Medan J-15 8,570,900.00
16 1 M3 Pasang Konstruksi Kuda - Kuda Kayu Borneo J-16 8,073,700.00
17 1 M2 Pasang Kaso dan Reng Genteng Plentong kayu Kamper Medan J-17 93,660.00
18 1 M2 Pasang Kaso dan Reng Genteng Beton kayu Kamper J-18 106,190.00
19 1 M' Pasang Lisplang (3x20) Cm, Kayu Kamper Medan J-19 70,040.00
20 1 M' Pasang Lisplang (3x30) Cm, Kayu Kamper Medan J-20 96,610.00
21 1 M' Pasang List Plafon - Kayu Profil 10 cm J-21 37,140.00
22 7,26 M2 Kusen Partisi Dobel Triplek J-22 188,230.00
23 1 M2 Pasang Rangka Langit - langit (1.00x1.00) m, Kayu Kamper J-23 113,460.00
24 1 M2 Pasang Rangka Langit - langit (0.50 x 1.00) m, Kayu Borneo J-24 134,090.00
25 1 M1 Reuter Kayu Kamper Medan J-25 47,770.00
26 1 M3 Gording kayu kelas II J-26 8,135,300.00
27 1 M2 Dinding bilik, rangka kayu borneo J-27 76,710.00
1 M2 Pasang Pintu Panel Multiplek 9 mm rangka kayu Kamper Medan / Kruing 498,300.00
M PEKERJAAN SANITASI
1 1 Buah Closet Jongkok Proselen Standar M-01 416,750.00
2 1 Buah Urinoir M-02 2,694,980.00
3 1 Buah Wastafel M-03 1,110,050.00
4 1 Buah Bak Mandi Fibreflass volume 0,30 M3 M-04 693,730.00
5 1 M' Saluran Air Limbah Buis beton d = 30 cm - 60 cm M-05 181,030.00
6 1 Buah Bak kontrol Pas. Bata Merah Uk (60 x 60) cm M-06 713,760.00
7 1 Buah Bak kontrol Pas. Bata Merah Uk (30 x 30) cm M-07 474,160.00
8 1 M¹ Pipa PVC Type AW Ø ½" M-08 24,450.00
9 1 M¹ Pipa PVC Type AW Ø 1" M-09 33,570.00
10 1 M¹ Pipa PVC Type AW Ø 1½" M-10 51,790.00
11 1 M¹ Pipa PVC Type AW Ø 2" M-11 55,840.00
1 M¹ Pipa PVC Type AW Ø 2½" 79,710.00
1 M¹ Pipa PVC Type AW Ø 3" 103,380.00
12 1 M¹ Pipa PVC Type AW Ø 4" M-12 162,100.00
13 1 M¹ Pipa PVC Type AW Ø ¾" M-13 38,780.00
14 1 Buah Bak Cuci Piring Stainles Steel M-14 464,030.00
15 1 Buah Kran Ø ½" atau ¾" M-15 54,000.00
16 1 Buah Floor Drain M-16 82,390.00
17 1 M' Grafel beton U 20 cm -60 cm M-17 85,660.00
18 1 M' Pasang Talang Plastik PVC U 15 cm (AW) M-18 133,710.00
19 1 M' Saluran Air Limbah Buis beton Ø 60 cm M-19 239,190.00
20 1 M' Pasang Talang Seng Datar M-20 85,910.00
21 1 Buah Closet Duduk M-21 1,795,970.00
22 1 Buah Tangki Air fibreglass Volume 1 m3 M-22 1,847,190.00
23 1 Unit Septictank 2 x 1,50 x 1,50 M + Rembesannya M-23 10,232,610.00
24 1 Unit Septictank 1 x 1,50 x 1,50 M + Rembesannya M-24 5,573,030.00
1 M¹ Pipa Galvanis Ø ½" 45,460.00
KODE HARGA
No. URAIAN SATUAN
ANAL SATUAN
1 M¹ Pipa Galvanis Ø ¾" 60,310.00
1 M¹ Pipa Galvanis Ø 1" 66,850.00
1 M¹ Pipa Galvanis Ø 1½" 105,050.00
1 M¹ Pipa Galvanis Ø 3" 274,150.00
1 M¹ Pipa Galvanis Ø 4" 283,670.00
1 Buah Bak kontrol Pas. Batu Bata (45 x 45) cm, Tinggi 50 cm 373,120.00
1 M' Saluran Air Hujan Lbr. 20 cm 84,470.00
1 M' Perbaikan Saluran Air Hujan Lbr. 20 cm 36,250.00
N PEKERJAAN PENGECATAN
1 1 M2 Mengikis / Mengerok Permukaan Cat Tembok Lama N-01 12,230.00
2 1 M2 Mendempul dan Menggosok Kayu N-02 10,360.00
3 1 M2 Pengecatan Bidang Kayu dan Besi lama Setara Glotex N-03 28,630.00
1 M2 Pengecatan Bidang Kayu lama Setara Pinotex 29,750.00
4 1 M2 Pengecatan Bidang Kayu Baru Setara Glotex 3 X laburan N-04 45,410.00
1 M2 Pengecatan Bidang Kayu Baru Setara Sieve 2 X laburan 34,720.00
5 1 M2 Pelaburan Bidang Kayu dengan Politur N-05 71,440.00
6 1 M2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter N-06 10,360.00
7 1 M2 Pengecatan Tembok Setara ICI Exterior (weather shield) N-07 47,810.00
8 1 M2 Pengecatan Tembok Lama Setara ICI Weather Shield N-08 33,860.00
9 1 M2 Pengecatan Plafond ( 3x ) setara ICI N-09 64,650.00
10 1 M2 Pengecatan Plafond ( 3x ) setara Vinilex N-10 51,650.00
1 M2 Pengecatan Plafond ( 2x ) setara Vinilex N-10r 34,590.00
11 1 M2 Pemasangan Wall Paper N-11 120,820.00
12 1 M2 Pengecatan Permukaan Baja dengan Meni Besi N-12 21,300.00
13 1 M2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah N-13 43,000.00
14 1 M2 Pengecatan Permukaan Baja Lapis seng (galbani) secara manual 1 lps cat 2 um N-14 28,420.00
15 1 M2 Pengecatan Tembok Baru Setara Vinilex (3 x laburan) N-15 35,530.00
1 M2 Pengecatan Tembok Setara Vinilex (2 x laburan) N-15r 26,680.00
16 1 M2 Pengecatan Tembok Lama Setara Vinilex 16 14,510.00