Minggu ke- 1 2 3 4

Cumulative Cost 21,225,000 53,229,167 82,037,500 121,500,000


Progress Kumulatif(%) 4% 10% 15% 22%

Kurva-S Rencana
600,000,000

500,000,000

400,000,000

Cumulative cost
300,000,000

200,000,000

100,000,000

0
1 2 3 4 5 6 7 8 9 10 11
Minggu ke-
5 6 7 8 9 10 11
156,376,786 188,562,500 237,742,857 283,869,643 319,927,083 351,835,417 456,562,500
29% 35% 44% 52% 59% 65% 84%

Kurva-S Rencana Kurva-S Rencana

4 5 6 7 8 9 10 11 12 13 14 15
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Minggu ke-
Minggu ke-
12 13 14 15
521,976,250 532,019,375 540,497,500 543,535,000
96% 98% 99% 100%

Progress kumulatif
va-S Rencana
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
8 9 10 11 12 13 14 15
Minggu ke-