Nama : Tomi Mulyana

NPM : 2020210013

TUGAS 5

1. Latihan
Kegiatan Optimistis Pesimistis Paling Mungkin Predecessor Waktu
(Jam) (Jam) (Jam) Harapan
(Hari)

A 28 32 30 - 4

B 12 15 14 - 2

C 30 34 31 B 4

D 27 29 28 A 4

E 14 17 16 B 2

F 22 25 24 C,D 3

G 40 35 38 E 5

H 26 29 28 F 4

1) Hitung waktu harapan (gunakan rumus PERT, asumsi 1 hari = 8 jam)


28+ ( 4.30 )+32
A= /8=4
6
12+ ( 4.14 )+15
B= /8=2
6
30+ ( 4.31 ) +34
C= /8=4
6
27+ ( 4.28 )+ 29
D= /8=4
6
14+ ( 4.16 ) +17
E= /8=2
6
22+ ( 4.24 )+ 25
F= /8=3
6
40+ ( 4.38 ) +35
G= /8=5
6
Nama : Tomi Mulyana
NPM : 2020210013

26+ ( 4.28 )+ 29
H= /8=4
6

2) Buat gant chart


Kegiata 1 2 3 4 5 6 7 8 9 1 1 12 1 1 1 16
n 0 1 3 4 5
A
B
C
D
E
F
G
H

3) Buat diagram pert / AOA

D=4
F=3
2 4 H=4
A=4 6
8
1 C=4

B=2 3 5 7
E=2 G=5

4) Tentukan lama proyek dan jalur kritis


- A, D, F, H = 4 + 4 + 3 + 4 = 15  Jalur Kritis
- B, C, F, H = 2 + 4 + 3 + 4 = 13
- B, E, G, H = 2 + 2 + 5 + 4 = 13

2. Latihan
Kegiatan Durasi Predecessor/ Sebelum Successor
A 2 - A
B 3 A B
C 12 B,D C
D 8 - D
Nama : Tomi Mulyana
NPM : 2020210013

E 3 D E
F 4 E F
G 4 D G
H 4 - H
I 2 H I
J 5 G,I J

1) Ditabel, buat kolom successor / setelah dari setiap kegiatan


2) Buatlah diagram network – nya

B=3
2 5
A=2
C = 12
1 D=8
E=3 F=4
3 6 8

H=4
G=4
7 J=5

4
I=2

3) Ada berapa jalur dalam network diagram? Ada 5


4) Berapa lama setiap jalur harus dilalui?
- A, B = 2 + 3 = 5
- D, C = 8 + 12 = 20  Jalur Kritis
- D, E, F = 8 + 3 + 4 = 15
- D, G, J = 8 + 4 + 5 = 17
- H, I, J = 4 + 2 + 5 = 11
5) Tentukanlah critical path? Berapa lama waktu terpendek untuk dapat menyelesaikan
proyek ini?

2 20

17 20
0 B=3
2 5
A=2
0
Nama : Tomi Mulyana
NPM : 2020210013

C = 12
1 D=8 20
E=3 F=4
3 6 8
20
11
H=4 8
G=4 16
8 J=5
7

4 12
I=2
4 15

13