( MC – 1 )
PERHITUNGAN VOLUME
Weir koalgulator
1.8 2 0.008 1 0.0288 7850
1 2 0.008 1 0.016 7850
2 2 0.008 1 0.032 7850
Flokulator p L T Jlh Volume Bj
Dinding lebar 4.1 4 0.008 4 0.5248 7850
Dinding panjang 6 4 0.008 4 0.768 7850
Lantai 6 4.1 0.008 1 0.1968 7850
Insert Flokulator 2 4.1 0.003 4 0.0984 7850
Flokulator
1. Pengadaan Pipa GIP Dia 100 mm
Volume
2. Pengadaan Bend GIP Dia. 100 mm x 90 °
Volume
3. Pengadaan Butterfly Valve Dia. 100 mm
Volume
4. Pengadaan Loose Flange Dia. 100 mm
Volume
C. Pekerjaan Pemasangan Baja & Fasilitas Treatment
Pekerjaan Baja
1. Pekerjaan Cleaning Baja
Volume
2. Pekerjaan Pemotongan dan Pabrikasi Plat Existing & Plat Baru
Volume
3. Pekerjaan Pengelasan
Volume
Pekerjaan Pengecatan
1. Pekerjaan Pengecatan Bagian Dalam
Volume 4 x 4.25 x 2
Volume 4 x 4 x 2
Volume 4 x 4.1 x 6
Volume 4 x 6 x 2
Volume 4 x 2 x 4 x 2
Volume 1.8 x 1.8 x 4
Volume 4 x 4.1 x 1
Volume 4 x 6 x 2
Volume 0.05 x 4 x 48
Volume 0.1 x 2 x 48
Volume 0.05 x 1.8 x 4 x 8
Volume 0.1 x 1.8 x 2 x 8
Volume 0.2 x 2 x 3 x 4
Volume 1.8 x 1.8 x 4
Volume 0.1 x 2 x 3
Flokulator
1. Pemasangan Pipa GIP Dia 100 mm
Volume
2. Pemasangan Bend GIP Dia. 100 mm x 90 °
Volume
3. Pemasangan Butterfly Valve Dia. 100 mm
Volume
4. Pemasangan Loose Flange Dia. 100 mm
Volume
III. Pekerjaan Tanah & Pondasi
3.1 Pekerjaan Galian Tanah
Volume 6 x 4 x 1
6 x 4 x 0.6
3.2 Pekerjaan Pembuangan Tanah
Volume 6 x 4 x 1
6 x 4 x 0.6
3.3 Pekerjaan Urugan Sirtu Dipadatkan
Volume 6 x 4 x 0.1
3.4 Pekerjaan Lantai Kerja Beton 1 : 3 : 5
Volume 6 x 4 x 0.05
3.5 Pekerjaan Plat Lantai Pondasi Beton Bertulang K.250
Volume 6 x 4 x 0.4
Pekerjaan Plat Lantai Pondasi Beton Bertulang K.200
Volume 6 x 4 x 0.4
3.6 Pekerjaan Saluran Terbuka Dari Pasangan Batu Bata 1 : 3
Volume 8 x 0.5 x 4
Volume 5.5 x 0.5 x 4
Pekerjaan Pembesian
Volume
Volume 0.62 x 37.74
Pekerjaan Bekisting
Volume
Volume 0.3 x 0.2 x 6.25 X 4
2. Pemasangan
a. Pemasangan Besi Support Mixer Dosing (UNP 50 x 38 x 5)
Cleaning
Volume
Volume 9.37 x 2.8 x 4
9.37 x 0.191 x 6
9.37 x 0.1938 x 7
Pemasangan dan Pemotongan Beserta Pabrikasi Plat Exsisting & Plat Baru
Volume
Volume
Pekerjaan Pengelasan
Volume
Volume
c. Pekerjaan Kanopi Depan Rungan Kimia (Lebar = 120 cm) Zinc Alum Dengan Rangka Baja
Volume
Volume 1.2 x 12
1.2 x 6.2
PERHITUNGAN VOLUME
Perhitungan Volume
= 1 Buah Tetap
gan Bowplank
= 24.2 M Tetap
n
= 1 Ls Tetap
reatment
u Hoisting dan Lain – Lain
= 1 Ls Tetap
Safaty
1.25 = 565.2 Kg
1.25 = 508.68 Kg
1.25 = 282.6 Kg
1.25 = 282.60 Kg
1.25 = 157.00 Kg
1.25 = 314.00 Kg
= 2,795.00
= 381.27
= 66.96
= 825.84
= 2 Buah Tetap
= 50 M Semula
= 35 M Menjadi
= 1 Buah Tetap
= 1 Buah Tetap
= 2 Buah Tetap
= 12 M Tetap
= 6 Buah Tetap
= 6 Buah Tetap
= 12 Buah Tetap
= 21,761.40 Kg Tetap
= 21,761.40 Kg Tetap
= 21,761.40 Kg Tetap
= 34 M²
= 32 M²
Total = 66 M² Tetap
= 98.4 M²
= 48 M²
= 64 M²
= 12.96 M²
= 34 M²
= 32 M²
Total = 66 M² Tetap
= 16.4 M²
= 48 M²
= 9.6 M²
= 9.6 M²
= 2.88 M²
= 2.88 M²
= 4.8 M²
= 12.96 M²
= 0.6
Total = 107.12 M² Menjadi
= - Ls Semula
= 1.00 Ls Menjadi
= 2 Buah Tetap
= 50 M Semula
= 35 M Menjadi
= 4 Buah Tetap
= 1 Buah Tetap
= 2 Buah Tetap
= 12 M Tetap
= 6 Buah Tetap
= 6 Buah Semula
= 8 Buah Menjadi
= 12 Buah Tetap
= 24 M³ Semula
= 14.4 M³ Menjadi
= 24 M³ Semula
= 14.4 M³ Menjadi
= 2.4 M³ Tetap
= 1.2 M³ Tetap
= 9.6 M³ Semula
= 9.6 M³ Menjadi
= 16 M²
= 11 M²
Total = 27 M² Tetap
= 1.4 M²
= 1 M²
Total = 2.4 M² Tetap
x
= 4.13 M³ Semula
= 2.16 M³ Menjadi
x
= 4.13 M³ Semula
= 2.16 M³ Menjadi
gan Pompa Alum Dosing Pump Q = 200 l/h, P = 0,5 Kw, 1400 Rpm, 50 Hz
= 1 Unit Tetap
gan Pompa Kaporit Dosing Pump Q = 100 l/h, P = 0,15 Kw, 1400 Rpm, 50 Hz
= 1 Unit Tetap
gan Pompa Utilitas
= - Unit Semula
= 1 Unit Menjadi
= 0 M³ Semula
= 1.69 M³ Menjadi
Akses Pintu (P1)
= 0 M³ Semula
= 0.53 M³ Menjadi
Akses Pintu (P2)
= 0 M³ Semula
= 0.53 M³ Menjadi
= 0 M³ Semula
= 1.35 M³
= 0.26 M³
= 0.15 M³
Total = 1.76 Menjadi
= 0 Kg Semula
= 201.11 Kg Menjadi
= 0 M² Semula
= 9.00 M²
= 2.20 M²
= 1.00 M²
Total = 12.20 Menjadi
= 0 M³ Semula
= 0.13 M³ Menjadi
= 0 Kg Semula
= 6.61 Kg Menjadi
= 0 M² Semula
= 0.32 M²
Total = 0.32 Menjadi
= 0 M³ Semula
= 3.72 M³ Menjadi
gki Kimia
= 0 M³ Semula
= 0.16 M³
= 0.15 M³
Total = 0.31 M³ Menjadi
= 0 M² Semula
= 1.82 M²
= 1.20 M²
Total = 3.02 M² Menjadi
= 0 M³ Semula
= 1.04 M³ Menjadi
= 0 M³ Semula
= 0.15 M³ Menjadi
= 0 Kg Semula
= 23.40 Kg Menjadi
= 0 M² Semula
= 1.50 M² Menjadi
= 0 M² Semula
= 11.20 M²
= 3.36 M²
Total = 14.56 M² Menjadi
= 0 M² Semula
= 12.80 M²
= 9.60 M²
= 6.70 M²
Total = 29.10 M² Menjadi
= 0 M² Semula
= 3.60 M² Menjadi
= 0 M² Semula
= 44.00 M²
= 22.40 M²
Total = 66.40 M² Menjadi
= 0 Kg Semula
= 104.94 Kg
= 10.73 Kg
Total = 115.67 Menjadi
= 0 Kg Semula
1.25 = 12.72 Kg Menjadi
= 0 Buah Semula
= 4.00 Buah Menjadi
= 0 Buah Semula
= 2.00 Buah Menjadi
= 0 Kg Semula
= 104.94 Kg
= 10.74 Kg
= 12.71 Kg
Total = 128.39 Menjadi
= 0 Kg Semula
= 128.39 Kg Menjadi
= 0 Kg Semula
= 128.39 Kg Menjadi
= 0 Buah Semula
= 4.00 Buah Menjadi
= 0 Buah Semula
= 2.00 Buah Menjadi
= 0 Set Semula
= 3.00 Set Menjadi
= 0 Buah Semula
= 3.00 Buah Menjadi
= 0 Buah Semula
= 2.00 Buah Menjadi
= 0 M² Semula
= 6.45 M² Menjadi
= 0 M³ Semula
= 0.28 M³ Menjadi
mpas
= 0 M³ Semula
= 0.56 M³ Menjadi
= 0 M² Semula
= 2.60 M²
= 7.15 M²
Total = 9.75 M² Menjadi
as
= 0 M² Semula
= 4.00 M²
= 11.57 M²
Total = 15.57 M² Menjadi
= 0 Titik Semula
= 7.00 Titik Menjadi
= 3 Hari Tetap
Sisa Pekerjaan dan Lain – Lain
= 1 Ls Tetap
Dibuat Oleh,
CV. ARG CAHAYA NUSANTARA
Ir.Project
ACHMAD Manager
DANIAL