TRIAL PERHITUNGAN PLAT BETON

Tebal Panjang Lebar Luas Volume


PLAT BETON TEBAL 12 cm
0.12 4.00 3.00 12.00 1.44

Jarak Dim Kg/m Panjang Qty Volume


Tul. Bawah 0.20 10.00 0.62 4.00 15.00 36.99
Tul. Atas / Kuda-kuda 0.20 10.00 0.62 4.25 15.00 39.30
Tul. Ekstra 0.20 10.00 0.62 2.00 15.00 18.50
Tul. Dudukan 0.20 10.00 0.62 0.60 3.00 1.11
Tulangan Double
Tul. Bawah 0.20 10.00 0.62 3.00 20.00 36.99
Tul. Atas / Kuda-kuda 0.20 10.00 0.62 3.25 20.00 40.07
Tul. Ekstra 0.20 10.00 0.62 1.50 20.00 18.50
Tul. Dudukan 0.20 10.00 0.62 0.60 4.00 1.48

Berat Total 192.93

Berat Tulangan per M3 Untuk Plat Beton Tebal 12 cm 133.98172 Kg/m3

Tebal Panjang Lebar Luas Volume


PLAT BETON TEBAL 10 cm
0.10 4.00 3.00 12.00 1.20

Jarak Dim Kg/m Panjang Qty Volume


Tul. Bawah 0.20 10.00 0.62 4.00 15.00 36.99
Tul. Atas / Kuda-kuda 0.20 10.00 0.62 4.25 15.00 39.30
Tul. Ekstra 0.20 10.00 0.62 2.00 15.00 18.50
Tul. Dudukan 0.20 10.00 0.62 0.60 3.00 1.11
Tulangan Double
Tul. Bawah 0.20 10.00 0.62 3.00 20.00 36.99
Tul. Atas / Kuda-kuda 0.20 10.00 0.62 3.25 20.00 40.07
Tul. Ekstra 0.20 10.00 0.62 1.50 20.00 18.50
Tul. Dudukan 0.20 10.00 0.62 0.60 4.00 1.48

Berat Total 192.93

Berat Tulangan per M3 Untuk Plat Beton Tebal 10 cm 160.77806 Kg/m3


WILAYAH I WILAYAH II WILAYAH III
KEC. BOYOLALI KEC. SIMO KEC. WONOSEGORO *
KEC. AMPEL KEC. KLEGO KEC. KEMUSU *
KEC. BANYUDONO KEC. KARANGGEDE
KEC. SAWIT KEC. NOGOSARI
KEC. MOJOSONGO KEC. ANDONG
KEC. SAMBI KEC. MUSUK
KEC. NGEMPLAK KEC. CEPOGO
KEC. TERAS KEC. SELO *

*) ada sebagian desa yang masuk wilayah IV dan V

CK Boyolali
Plumbing Panjang
Lantai 1 kran dinding 25.00
Saluran air besih floor drain 31.00
Pipa dia 3/4" 85 M'
Pipa dia 1" 54 M'
Pipa dia 2" dr lantai 3 rooftank 15 M'
Pipa dari GWT ke Roof Tank dia 1" 18 M'

Saluran air Kotor Floor drain dia 3"


Wastafel
124 M'
Kolam Rendam
Urinoir
Pipa dia 3" dr lantai2/ 3 24 M'
Limbah Padat dia 4" 56 M'
Pipa dia 4" dr lantai 2/ 3 24 M'
Lantai 2
Saluran air besih
Pipa dia 3/4" 118 M'
Pipa dia 1" 54 M'
Pipa dia 2" dr lantai 3 rooftank 8 M'

Saluran air Kotor Floor drain dia 3"


Wastafel
163 M'
Kolam Rendam
Urinoir
Limbah Padat dia 4" 52 M'
Lantai 3
Saluran air besih
Pipa dia 3/4" 8 M'
Pipa dia 1" 4 M'
Pipa dia 2" dr lantai 3 rooftank 6 M'

Saluran air Kotor Floor drain dia 3"


Wastafel
10.5 M'
Kolam Rendam
Urinoir
Limbah Padat dia 4" 5 M'

pipa 3/4 85.00


pipa 1 54.00
pipa 2 15.00
pipa 3 124.00
pipa 4 80.00
AS VERTIKAL
A B C D E F G H
1 FP 1

2 FP 2

3 FP 3

4 FP 4

5 SLOOF S1 20x40 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
Pengurang 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70

6 SLOOF S2 20x30 6.00 6.00 6.00 6.00 6.00 6.00 6.00 6.00
Pengurang 1.10 1.10 1.10 1.10 1.10 1.10 1.10 1.10

7 SLOOF S3 15x20 11.90 12.05 5.80 16.40 5.80


Pengurang

8 K1 50x80

9 K2 50x50

10 K3 40x40

11 K4 40x60

12 Kp 11x11 2.00 4.00 4.00 4.00 11.00 2.00 2.00 2.00

13 Pondasi T: 80 cm T : 80 6.00 14.50 15.00 21.00 30.00 12.00 30.00 18.00


1.55 1.55 1.55 0.85 1.55 0.85

14 Pondasi T: 320 cm T : 320

15 Pondasi T: 240 cm T : 240 15.00


1.10

16 Pondasi T: 205cm T : 205 3.00 3.00 1.50 6.00 4.50 4.50


0.30 0.30

17 Pondasi T: 135cm T : 135

14 Pondasi T: 105cm T : 105

15
AS HORISONTAL
I J 1 2 3 4 JUMLAH
10.00 10.00 UNIT #REF!

10.00 10.00 UNIT

10.00 10.00 UNIT

5.00 5.00 UNIT

3.00 3.00 54.00 54.00 138.00 30.00 108.00


0.70 0.70 3.60 4.50 15.10 7.00 8.10
122.90 M 23.00 99.90
6.00 6.00 54.00 54.00 168.00 60.00 108.00
1.10 1.10 4.50 3.60 19.10 11.00 8.10
148.90 M 49.00 99.90
11.30 9.20 3.85 12.33 25.10 113.73 72.45 41.28
- - -
113.73 M
10.00 10.00 UNIT
-
10.00 10.00 UNIT
-
10.00 10.00 UNIT
-
10.00 10.00 UNIT
-
3.00 4.00 9.00 7.00 8.00 8.00 70.00 UNIT
-
14.50 9.00 13.25 52.00 18.00 253.25 M 146.50 83.25
0.95 1.25 3.25 13.35 7.90 4.50
239.90 M 138.60 78.75
46.50 46.50 M
2.40 2.40
44.10 M
15.00 30.00 M
1.10 2.20
27.80 M
3.00 3.00 42.50 71.00 M
0.30 0.90
70.10 M
20.00 20.00 M
0.60 0.60
19.40 M
64.00 64.00 M - 64.00
4.00 4.00 - 4.00
60.00 M - 60.00
M - -
- -
M - -
M
-
- M
1 FP 1 10.00 UNIT
2 FP 2 10.00 UNIT
3 FP 3 10.00 UNIT
4 FP 4 5.00 UNIT

5 SLOOF S1 122.90 M
6 SLOOF S2 148.90 M
7 SLOOF S3 113.73 M

9 K1 10.00 UNIT
10 K2 10.00 UNIT
11 K3 10.00 UNIT
12 K4 10.00 UNIT
13 Kp 70.00 UNIT
14
15
16
17
18
19
20
21
Lantai. 2
22
23
24
25
26
27

B PEKERJAAN GEDUNG

V PEKERJAAN BETON
1 Sloof So1 Dimensi 20 x 40 cm
a. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, 9.832 m3

b. Pembesian 1,695.218 kg
172.418
c. Begesting 98.320 m2

2 Sloof So2 Dimensi 20 x 30 cm


a. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, 8.934 m3

b. Pembesian 1,442.422 kg
161.453

c. Begesting 89.340 m2

3. Sloof So3 Dimensi 15 x 20 cm


a. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, 3.412 m3
b. Pembesian 589.687 kg
172.832

c. Begesting 45.492 m2

4 Footplate FP1 Dimensi 550 x 200 cm


a. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, 49.500 m3

b. Pembesian 5,605.687 kg
113.246
D16

c. Begesting 60.000 m2

5 Footplate FP2 Dimensi 160 x 160 cm


a. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, 8.960 m3

b. Pembesian 1,484.582 kg
165.690
D16
c. Begesting 19.200 m2

6 Footplate FP3 Dimensi 140 x 140 cm


a. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, 6.860 m3

b. Pembesian 1,110.912 kg
161.941
D16

c. Begesting 16.800 m2

7 Footplate FP4 Dimensi 100 x 100 cm


a. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, 1.875 m3

b. Pembesian 343.373 kg
183.132
D16

c. Begesting 6.000 m2

5 Kolom Struktur K1 Dimensi 50 x 80 cm


a. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, 24.120 m3

b. Pembesian 4,074.816 kg
168.939
c. Begesting 190.250 m2

6 Kolom Struktur K2 Dimensi 50 x 50 cm


a. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, 15.998 m3

b. Pembesian 2,591.225 kg
161.977

c. Begesting 142.200 m2

7 Kolom Struktur K3 Dimensi 40 x 40 cm


a. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, 8.480 m3

b. Pembesian 1,392.070 kg
164.159

c. Begesting 84.800 m2

8 Kolom Struktur K4 Dimensi 40 x 60 cm


c. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, 13.400 m3
a. Pembesian 2,320.165 kg
173.147

b. Begesting 120.600 m2

8 Kolom Struktur KP Dimensi 11 x 11 cm


Beton 3.261 m'

Besi 633.318 kg
194.213

Begesting 59.290 m2

9 Plat Tangga Beton Bertulang tebal 10 cm ( lantai 1 )


Beton mutu f'c = 14,5 MPa (K 225), slump (12 ± 2) 7.343 m3

Pembesian 1,915.938 kg
260.906

D12

Begesting 113.394 m2

Pas Bata 1/2 batu ( anak tangga ) 4.995 m2

10 Plat Tangga Beton Bertulang tebal 10 cm ( lantai 1 ) b


- Beton mutu f'c = 14,5 MPa (K 225), slump (12 ± 2) 2.429 m3

- Pembesian 324.527 kg
133.587

D12

- Begesting 31.372 m2

d. Pas Bata 1/2 batu ( anak tangga ) 0.885 m2

11 Plat Tangga Beton Bertulang tebal 10 cm ( lantai 2 )


- Beton mutu f'c = 14,5 MPa (K 225), slump (12 ± 2) 1.859 m3

- Pembesian 254.214 kg
D12

- Begesting 398.672 m2

d. Pas Bata 1/2 batu ( anak tangga ) 47.510 m2

12 Pondasi t :80 cm, l :80 cm


a Pas pondasi 1 : 5 105.556 m3

b Urug pasir bawah pondasi 19.192 m3

13 Pondasi t :320 cm, l :80 cm


a Pas pondasi 1 : 5 97.020 m3
b Urug pasir bawah pondasi 3.528 m3

14 Pondasi t :240 cm, l :85 cm


a Pas pondasi 1 : 5 56.295 m3

b Urug pasir bawah pondasi 2.363 m3

14 Pondasi t :205 cm, l :60 cm


a Pas pondasi 1 : 5 83.594 m3

b Urug pasir bawah pondasi 4.206 m3

c Plester 35.050 m2

d Acian 35.050 m2

15 Pondasi t :135 cm, l :80 cm


a Pas pondasi 1 : 5 14.850 m3

b Urug pasir bawah pondasi 1.600 m3

16 Pondasi t :105 cm, l :50 cm


a Pas pondasi 1 : 5 34.800 m3

b Urug pasir bawah pondasi 3.000 m3

17 Plat Beton Tebal 10 cm (bawah lantai)


a Beton mutu f'c = 14,5 MPa (K 225), slump (12 ± 2) 83.537 m3
18 Pasir urug bawah lantai)
a Pasir urug t :10 cm 83.537 m3
panjang stek : 0.85

Ket. Panjang Dimensi unit jumlah


A,B,C,D,E,F,G,H,I,J 23.00 0.20 0.40 1.00 1.840
1,2,3,4 99.90 0.20 0.40 1.00 7.992

Ket. Panjang jml batang berat/m' unit jumlah


D16 ###
Tul atas D16 138.00 2.00 1.578 1.00 435.528
Tul tengah D16 138.00 2.00 1.578 1.00 435.528
Tul bawah D16 138.00 2.00 1.578 1.00 435.528

Ket. Panj begel jml begel berat/m' unit jumlah


Ø8
1.12 154.33 0.395 1.00 68.277
1.12 667.00 0.395 1.00 295.081
angkur d10 0.50 81.93 0.617 1.00 25.276
Ket. Panjang keliling unit jumlah
A,B,C,D,E,F,G,H,I,J 23.00 0.80 1.00 18.400
1,2,3,4 99.90 0.80 1.00 79.920

Ket. Panjang Dimensi unit jumlah


A,B,C,D,E,F,G,H,I,J 49.00 0.20 0.30 1.00 2.940
1,2,3,4 99.90 0.20 0.30 1.00 5.994
-
-
-
-
-

Ket. Panjang jml batang berat/m' unit jumlah


D13 ###
Tul atas D13 168.00 2.00 1.042 1.00 350.112
Tul tengah D13 168.00 2.00 1.042 1.00 350.112
Tul bawah D13 168.00 2.00 1.042 1.00 350.112
- - -
- - -
- - -
- - -

Ket. Panj begel jml begel berat/m' unit jumlah


Ø8
A,B,C,D,E,F,G,H,I,J 0.92 327.67 0.395 1.00 119.074
1,2,3,4 0.92 667.00 0.395 1.00 242.388
angkur d10 0.50 99.27 0.617 1.00 30.624
- - -
- - -
- - -
- - -

Ket. Panjang keliling unit jumlah


A,B,C,D,E,F,G,H,I,J 49.00 0.60 1.00 29.400
1,2,3,4 99.90 0.60 1.00 59.940

- - - -
- - - -
- - - -
- - - -

A,B,C,D,E,F,G,H,I,J 72.45 0.15 0.20 1.00 2.174


1,2,3,4 41.28 0.15 0.20 1.00 1.238
-
-
-
-
-
Ket. Panjang jml batang berat/m' unit jumlah
D12
Tul atas D12 113.73 2.00 0.887 1.00 201.757
Tul bawah D12 113.73 2.00 0.887 1.00 201.757
- - -
- - -
- - -
- - -
- - -

Ket. Panj begel jml begel berat/m' unit jumlah


Ø8
Tul atas D12 0.62 484.00 0.395 1.00 118.532
Tul bawah D12 0.62 276.20 0.395 1.00 67.641
- -
- - -
- - -
- - -
- - -

Ket. Panjang keliling unit jumlah


Tul atas D12 72.45 0.40 1.00 28.980
Tul bawah D12 41.28 0.40 1.00 16.512
- - - -
- - - -
- - - -
- - - -
- - - -
###

Ket. tebal Dimensi unit jumlah


bawah 0.40 5.50 2.00 10.00 44.000
atas 0.05 5.50 2.00 10.00 5.500

Ket. Panjang jml batang berat/m' unit jumlah


Plat. 1 X atas 6.48 14.00 1.578 10.00 1,431.56###
Y atas 2.88 38.00 1.578 10.00 1,726.96
Plat. 1 X bawah 5.54 14.00 1.578 10.00 1,223.90
Y bawah 2.04 38.00 1.578 10.00 1,223.27

Ket. tinggi keliling unit jumlah


0.40 15.00 10.00 60.000

Ket. tebal Dimensi unit jumlah


bawah 0.30 1.60 1.60 10.00 7.680
atas 0.05 1.60 1.60 10.00 1.280

Ket. Panjang jml batang berat/m' unit jumlah


Plat. 1 X atas 2.28 12.00 1.578 10.00 431.74
Y atas 2.28 12.00 1.578 10.00 431.74
Plat. 1 X bawah 1.64 12.00 1.578 10.00 310.55
Y bawah 1.64 12.00 1.578 10.00 310.55

Ket. tinggi keliling unit jumlah


0.30 6.40 10.00 19.200

Ket. tebal Dimensi unit jumlah


bawah 0.30 1.40 1.40 10.00 5.880
atas 0.05 1.40 1.40 10.00 0.980

Ket. Panjang jml batang berat/m' unit jumlah


Plat. 1 X atas 2.08 10.00 1.578 10.00 328.22
Y atas 2.08 10.00 1.578 10.00 328.22
Plat. 1 X bawah 1.44 10.00 1.578 10.00 227.23
Y bawah 1.44 10.00 1.578 10.00 227.23

Ket. tinggi keliling unit jumlah


0.30 5.60 10.00 16.800

Ket. tebal Dimensi unit jumlah


bawah 0.30 1.00 1.00 5.00 1.500
atas 0.08 1.00 1.00 5.00 0.375

Ket. Panjang jml batang berat/m' unit jumlah


Plat. 1 X atas 1.68 8.00 1.578 5.00 106.04
Y atas 1.68 8.00 1.578 5.00 106.04
Plat. 1 X bawah 1.04 8.00 1.578 5.00 65.64
Y bawah 1.04 8.00 1.578 5.00 65.64

Ket. tinggi keliling unit jumlah


0.30 4.00 5.00 6.000

Ket. Panjang Dimensi unit jumlah


Lantai 1 6.70 0.45 0.80 10.00 24.120###
### 9.00

Ket. Panjang jml batang berat/m' unit jumlah


Tul pokok D19 7.61 20.00 2.226 10.00 3,387.972###

Ket. Panj begel jml begel berat/m' unit


begel Ø10
2.42 46.00 0.617 10.00 686.844
Ket. Panjang keliling unit jumlah
7.61 2.50 10.00 190.250

Ket. Panjang Dimensi unit jumlah


Lantai 1 7.90 0.45 0.45 10.00 15.998###

### 5.50
Ket. Panjang jml batang berat/m' unit jumlah
Lantai 1 ###

Tul pokok D16 8.81 16.00 1.578 10.00 2,224.349

Ket. Panj begel jml begel berat/m' unit


begel Ø8
Lantai 1 1.72 54.00 0.395 10.00 366.876

Ket. Panjang keliling unit jumlah


Lantai 1 7.90 1.80 10.00 142.200

Ket. Panjang Dimensi unit jumlah


Lantai 1 5.30 0.40 0.40 10.00 8.480###
### 4.50

Ket. Panjang jml batang berat/m' unit jumlah


Lantai 1 6.21 12.00 1.578 10.00 1,175.926###
Tul pokok D16

Ket. Panj begel jml begel berat/m' unit


begel Ø8
Lantai 1 1.52 36.00 0.395 10.00 216.144

Ket. Panjang keliling unit jumlah


Lantai 1 5.30 1.60 10.00 84.800

Ket. Panjang Dimensi unit jumlah


Lantai 1 6.70 0.40 0.50 10.00 13.400
Ket. Panjang jml batang berat/m' unit jumlah
Tul pokok D19 7.61 8.00 2.226 10.00 1,355.189
Tul pokok D16 7.61 4.00 1.578 10.00 480.343
Ket. Panj begel jml begel berat/m' unit
begel Ø10
1.72 45.67 0.617 10.00 484.633

Ket. Panjang keliling unit jumlah


Lantai 1 6.70 1.80 10.00 120.600

Ket. Panjang Dimensi unit jumlah


Lantai 1 3.85 0.11 0.11 70.00 3.261###

o8 4.19 4.00 0.395 70.00 463.414


o6 0.41 26.67 0.222 70.00 169.904

3.85 0.22 70.00 59.290

Ket. tebal Lebar panjang Unit jumlah


Plat Bawah 0.10 1.85 4.16 3.00 2.309
Bordes 0.10 3.85 2.36 3.00 2.726
Plat 3 0.10 1.85 4.16 3.00 2.309

Ket. Panjang jml batang berat/m' unit jumlah


Plat. 1 X 1.85 30.73 0.887 6.00 302.591
Y 4.46 13.33 0.887 6.00 316.482
Plat. 2 X 3.85 16.73 0.887 6.00 342.861
Y 2.36 26.67 0.887 6.00 334.931
Plat. 3 X 1.85 30.73 0.887 6.00 302.591
Y 4.46 13.33 0.887 6.00 316.482

Ket. Panjang Lebar Unit jumlah


Plat Bawah 4.16 1.85 3.00 23.088
Bordes 2.36 3.85 3.00 27.258
Plat 3 4.16 1.85 3.00 23.088

Ket. Panjang Lebar tinggi Unit jumlah


Tangga bawah 22.20 0.15 0.17 6.00 19.980
Tangga atas 22.20 0.15 0.17 6.00 19.980

Ket. tebal Lebar panjang Unit jumlah


Plat Bawah 0.10 1.43 4.16 1.00 0.595
Bordes 0.10 2.85 1.67 1.00 0.476
0.10 1.43 1.18 1.00 0.169
Plat 3 0.10 1.43 4.16 2.00 1.190

Ket. Panjang jml batang berat/m' unit jumlah


Plat. 1 X 1.43 30.73 0.887 1.00 38.982
Y 4.46 10.53 0.887 1.00 41.670
Plat. 2 X 2.85 12.13 0.887 1.00 30.672
Y 1.67 20.00 0.887 1.00 29.626
Plat. 2 X 1.43 8.87 0.887 1.00 11.247
Y 1.18 10.53 0.887 1.00 11.025
Plat. 1 X 1.43 30.73 0.887 2.00 77.965
Y 4.46 10.53 0.887 2.00 83.340

Ket. Panjang Lebar Unit jumlah


Plat Bawah 4.16 1.43 1.00 5.949
Bordes 1.67 2.85 1.00 4.760
1.18 1.43 1.00 1.687
Plat 3 4.16 1.43 2.00 11.898

Ket. Panjang Lebar tinggi Unit jumlah


Tangga bawah 15.73 0.15 0.18 1.00 2.360
Tangga atas 31.46 0.15 0.18 1.00 4.719

Ket. tebal Lebar panjang Unit jumlah


Plat Bawah 0.10 1.85 3.35 3.00 1.859

Ket. Panjang jml batang berat/m' unit jumlah


Plat. 1 X 1.85 25.33 0.887 3.00 124.712
Y 3.65 13.33 0.887 3.00 129.502

Ket. Panjang Lebar Unit jumlah


Plat Bawah 3.35 1.85 3.00 18.593

Ket. Panjang Lebar tinggi Unit jumlah


Tangga bawah 18.50 0.15 0.18 3.00 8.325

Ket. tebal Lebar panjang Unit jumlah


Pas batu 1:5 0.80 0.30 239.90 1.00 57.576
0.80 0.25 239.90 1.00 47.980

Ket. tebal Lebar panjang Unit jumlah


Urug pasir 0.10 0.80 239.900 1.00 19.192

Ket. tebal Lebar panjang Unit jumlah


Pas batu 1:5 3.20 0.30 44.10 1.00 42.336
0.80 0.80 44.10 1.00 28.224
2.40 0.25 44.10 1.00 26.460
Ket. tebal Lebar panjang Unit jumlah
Urug pasir 0.10 0.80 44.100 1.00 3.528

Ket. tebal Lebar panjang Unit jumlah


Pas batu 1:5 2.40 0.30 27.80 1.00 20.016
0.90 0.85 27.80 1.00 21.267
2.40 0.23 27.80 1.00 15.012
Ket. tebal Lebar panjang Unit jumlah
Urug pasir 0.10 0.85 27.800 1.00 2.363

Ket. tebal Lebar panjang Unit jumlah


Pas batu 1:5 2.05 0.30 70.10 1.00 43.112
0.60 0.60 70.10 1.00 25.236
1.45 0.15 70.10 1.00 15.247
Ket. tebal Lebar panjang Unit jumlah
Urug pasir 0.10 0.60 70.100 1.00 4.206

Plester 0.50 70.100 35.050


-
Acian 0.50 70.100 35.050

Ket. tebal Lebar panjang Unit jumlah


Pas batu 1:5 1.35 0.30 20.00 1.00 8.100

1.35 0.25 20.00 1.00 6.750


Ket. tebal Lebar panjang Unit jumlah
Urug pasir 0.10 0.80 20.000 1.00 1.600

Ket. tebal Lebar panjang Unit jumlah


Pas batu 1:5 1.05 0.30 60.00 1.00 18.900
0.40 0.50 60.00 1.00 12.000
0.65 0.10 60.00 1.00 3.900
Ket. tebal Lebar panjang Unit jumlah
Urug pasir 0.10 0.50 60.000 1.00 3.000

Ket. tebal luas unit jumlah


R Pemanas 0.10 69.09 2.00 13.818
Coach & tim 0.10 16.52 2.00 3.304
R Ganti 0.10 54.28 2.00 10.856
Mushola 0.10 11.60 2.00 2.320
Pantry 0.10 9.95 1.00 0.995
R Medis 0.10 12.98 1.00 1.298
R shower 0.10 41.30 2.00 8.260
R toilet 0.10 26.17 2.00 5.234
Selasar 0.10 39.54 2.00 7.908
Hall Team 0.10 40.59 1.00 4.059
R lobby 0.10 61.45 1.00 6.145
Direksi & wasit 0.10 23.84 1.00 2.384
Aula & kp 0.10 50.82 1.00 5.082
lorong 0.10 32.24 1.00 3.224
Gudang + selasar 0.10 62.80 1.00 6.280
selasar 0.10 13.44 1.00 1.344
selasar 0.10 10.26 1.00 1.026

Ket. tebal luas unit jumlah


R Pemanas 0.10 69.09 2.00 13.818
Coach & tim 0.10 16.52 2.00 3.304
R Ganti 0.10 54.28 2.00 10.856
Mushola 0.10 11.60 2.00 2.320
Pantry 0.10 9.95 1.00 0.995
R Medis 0.10 12.98 1.00 1.298
R shower 0.10 41.30 2.00 8.260
R toilet 0.10 26.17 2.00 5.234
Selasar 0.10 39.54 2.00 7.908
Hall Team 0.10 40.59 1.00 4.059
R lobby 0.10 61.45 1.00 6.145
Direksi & wasit 0.10 23.84 1.00 2.384
Aula & kp 0.10 50.82 1.00 5.082
lorong 0.10 32.24 1.00 3.224
Gudang + selasar 0.10 62.80 1.00 6.280
selasar 0.10 13.44 1.00 1.344
selasar 0.10 10.26 1.00 1.026
BESI MEMANJANG
Dia. Besi Koefi (Kg/m3) Dia. Besi (m) berat per m' Kg) berat per m' Kg)
mm a b = a x b kuadrat PEMBULATAN
6 6,162.25 0.006 0.2218 0.222
8 6,162.25 0.008 0.3944 0.395 0.395 7.58
10 6,162.25 0.010 0.6162 0.617 0.617 9.39
12 6,162.25 0.012 0.8874 0.887 0.887 11.71
13 6,162.25 0.013 1.0414 1.042 1.042 12.68
16 6,162.25 0.016 1.5775 1.578 1.578 15.32
17 6,163.25 0.017 1.7812 1.782
18 6,164.25 0.018 1.9972 1.998
19 6,165.25 0.019 2.2257 2.226
22 6,166.25 0.022 2.9845 2.985
-
-

-
2.41
-

338.80
-

68.68
-
-
-

0.2025
0.00405 0.00011304 0.00393696
diameter panjang massa
7.64 7.41 0.0075 1.010 0.3318 0.329
9.17 9.76 0.0094 1.009 0.5340 0.529
11.89 11.85 0.0118 1.013 0.8806 0.869
12.21 12.12 0.0123 0.996 0.9844 0.988
15.13 15.64 0.0154 1.012 1.5272 1.509
HITUNGAN VOLUME

IX PEKERJAAN BETON
Balok B7 Dimensi 15 x 52 cm
Beton 25.272 m3 panjang lebar tinggi unit Jumlah
54.00 0.15 0.52 6.00 25.27

Besi 3,119.798 kg panjang jml bj unit Jumlah


123.45 d10 54.06 8.00 0.617 6.00 1,601.04
d8 1.26 361.40 0.395 6.00 1,079.21
d12 1.50 55.06 0.89 6.00 439.54

Begesting 385.560 m2 panjang lebar tinggi unit Jumlah


54.00 1.19 6.00 385.56

Plat Lantai Tribun


Beton 34.344 m3 panjang lebar tinggi unit Jumlah
tempat duduk 54.00 0.70 0.12 6.00 27.22
bawah + tengah 54.00 1.10 0.12 1.00 7.13
atas 54.00 1.75 0.12 - -

Besi 4,852.799 kg panjang jml bj unit Jumlah


141.30 d10 memanjang 54.06 4.50 0.617 12.00 1,801.17
54.06 6.50 0.617 2.00 433.62
54.06 9.75 0.617 - -

d10 melebar 1.06 271.30 0.617 12.00 2,129.23


1.46 271.30 0.617 2.00 488.78
2.11 271.30 0.62 - -

Begesting 286.200 m2 panjang lebar tinggi unit Jumlah


54.00 0.70 6.00 226.80
54.00 1.10 1.00 59.40
54.00 1.75 - -

Waterprofing 345.60 m2 54.00 0.85 6.00 275.40


54.00 1.30 1.00 70.20

Pek. Galian Tanah Biasa Sedalam 2 m untuk Foot Plate dengan Ala 671.950 m3 panjang lebar tinggi unit Jumlah

FP1 3.05 2.20 5.30 10.00 355.63


FP2 2.90 1.80 3.60 10.00 187.92
FP3 2.20 1.60 2.40 10.00 84.48
FP4 3.05 1.20 2.40 5.00 43.92

Pek. Galian Tanah Biasa Sedalam 1 m untuk Pondasi dan Talud de 540.561 m3 panjang lebar tinggi unit Jumlah

P1 239.90 1.80 0.70 302.27


P2 44.10 1.80 0.80 63.50
P3 27.80 1.85 0.90 46.29
P4 70.10 1.60 0.60 67.30
P5 20.00 1.80 0.70 25.20
P6 60.00 1.50 0.40 36.00

Pek. Galian Tanah Penyiapan Lahan dengan Alat 532.000 m3 panjang lebar tinggi unit Jumlah

Sisi Utara 40.00 19.00 0.70 532.00


-
-
Pek. Urugan Tanah Peninggian Lantai Bangunan Menggunakan Bek 524.400 m3 panjang lebar tinggi unit Jumlah

Sisi Selatan 23.00 19.00 1.20 524.40


-
-
Rabat Beton Bawah Footplate tebal 5 cm ( K100 ) 17.280 m3
FP1 3.05 2.20 0.10 10.00 6.71
FP2 2.90 1.80 0.10 10.00 5.22
FP3 2.20 1.60 0.10 10.00 3.52
FP4 3.05 1.20 0.10 5.00 1.83

Rabat Beton Bawah Sloof tebal 5 cm ( K100 ) 6.349 m3


S1 122.9 0.25 0.07 2.15
S2 148.9 0.25 0.07 2.61
S3 113.73 0.20 0.07 1.59

### 18.000 unt


Lt 01 18 18.00
Lt 02 -
Lt 03 -

### 20.000 unt


Lt 01 20 20.00
Lt 02 13 -
Lt 03 3 -

### 25.000 unt


Lt 01 25 25.00
Lt 02 16 -
Lt 03 2 -

### 37.000 unt


Lt 01 37 37.00
Lt 02 12 -
Lt 03 7 -

### 22.000 unt


Lt 01 22 22.00
Lt 02 10 -
Lt 03 3 -

### 32.000 unt


Lt 01 20 20.00
Lt 02 9 9.00
Lt 03 3 3.00

### 13.000 unt


Lt 01 7 7.00
Lt 02 5 5.00
Lt 03 1 1.00

### 20.000 unt


Lt 01 20 20.00
Lt 02 3 -
Lt 03 3 -

Pek. Dinding Bata


Lantai 01 1,250.241 m2 1-2 2-3 3-4 h Jumlah
A 3.03 5.20 5.45 54.37
B 3.15 6.28 36.78
C 7.08 10.16 5.45 89.18
D 2.2 5.20 11.61 76.54
E 5.35 13.83 8.63 110.50
F 5.20 4.08 37.53
G 1 5.20 5.45 46.85
H 2.58 11.60 57.88

- RAB - 30
I 4.93 8.88 53.76
J 5.35 11.48 5.45 88.06

1 33.23 3.70 122.95


2 15.75 3.60 56.70
3 43.34 4.40 190.70
4 60.12 3.80 228.46

Pintu 144.945 m2
PU1 3.23 2.35 1.00 7.59
PU2 3.23 2.35 4.00 30.36
P1 4.66 2.15 2.00 20.04
P2 2.63 2.15 6.00 33.93
P3 2.43 2.15 1.00 5.22
P4 0.85 2.15 5.00 9.14
P5 1.3 2.15 1.00 2.80
PKM 0.8 2.05 15.00 24.60
JD1 1.00 -
JD2 2.00 -
BV1 0.7 0.70 23.00 11.27

Plester 2,210.593 m2

Acian 2,488.973 m2
Pas Bata 2,210.593 2,210.59
Kolom
K1 4 0.45 0.80 10.00 100.00
K2 5.2 0.45 0.45 10.00 93.60
K3 3.3 0.40 0.40 10.00 52.80
K4 4 0.40 0.50 10.00 72.00

Pengurang
K1 -4 6.00 0.30 (7.20)
K2 -5.2 7.00 0.30 (10.92)
K3 -3.3 10.00 0.30 (9.90)
K4 -4 10.00 0.30 (12.00)

- RAB - 31
Ring Balok RB Dimensi 15 x 20 cm panjang lebar tinggi unit Jumlah
Beton 11.808 m3 atas pas bata 316.2635 0.15 0.20 1.00 9.49
atas kusen 77.33 0.15 0.20 1.00 2.32

Besi 1,617.842 kg D10 316.8235 4.00 0.617 1.00 781.92


137.015 o8 0.62 2,109.42 0.395 1.00 516.60

D10 78.13 4.00 0.617 1.00 192.82


o8 0.62 516.53 0.395 1.00 126.50

Begesting 157.437 m2 atas pas bata 316.2635 0.40 126.51

atas kusen 77.33 0.40 30.93

Pembuatan Bor Pile Diameter 40 cm panjang dia luas unit Jumlah


Beton 124.972 m3
As 1 15.00 0.40 0.13 17.00 32.03
As 2 15.00 0.40 0.13 30.00 56.52
As 3 11.00 0.40 0.13 20.00 27.63
As 4 7.00 0.40 0.13 10.00 8.79

Besi 18,499.769 kg Pokok panjang bj btg unit


148.031 D19 As 1 15.16 2.226 8.00 17.00 4,589.48
As 2 15.16 2.226 8.00 30.00 8,099.08
As 3 11.16 2.226 8.00 20.00 3,974.75
As 4 7.16 2.226 8.00 10.00 1,275.05

Spiral kell bj btg unit


dia 0.340 D10 As 1 0.09 0.617 151.00 17.00 143.73
As 2 0.09 0.617 151.00 30.00 253.64
As 3 0.09 0.617 111.00 20.00 124.30
As 4 0.09 0.617 71.00 10.00 39.75

Pengeboran 995.000 m'


As 1 15.00 17.00 255.00
As 2 15.00 30.00 450.00
As 3 11.00 20.00 220.00
As 4 7.00 10.00 70.00

Pek. Pemasangan Pagar Pipa Besi Galvanis Medium 3" 70.800 m'
depan 54 54.00
samping 8.4 2.00 16.80

- RAB - 32
BETON

BALOK LT.2 AS VERTIKAL


1 A B C D E F G H I J

Balok B.1 30x60 7.65 7.65 7.65 7.65 7.65 7.65 7.65 7.65 7.65 7.65

Balok B.2 25x50 - - - - - - - - - -

Balok B.3 20x40 5.88 5.90 - 5.88 7.62 3.81 3.81 7.62 5.88 -

Balok B.4 20x30 2.75 2.75 2.75 2.75 2.75 - 5.31 2.75 2.75 -

Balok B.5 15x30 - - 4.50 - - - - - - -

BALOK LT.3 AS VERTIKAL


2 A B C D E F G H I J

Balok B.1 30x60 - - - 2.30 2.30 2.30 2.30 - - -

Balok B.2 25x50 - - - - - - - - - -

Balok B.3 20x40 - - - - - - - - - -

Balok B.4 20x30 - - - 7.44 4.71 1.98 1.98 - - -

Balok B.5 15x30 - - - 2.35 5.63 2.35 - - - -

BALOK LT.ATAP AS VERTIKAL


3 A B C D E F G H I J

Balok B.1 30x60 - - - 2.30 2.30 2.30 2.30 - - -

Balok B.2 25x50 - - - - - - - - - -

Balok B.3 20x40 - - - - - - - - - -

Balok B.4 20x30 - - - - - - - - - -

Balok B.5 15x30 - - - - - - - - - -

BALOK TRIBUN AS VERTIKAL


4 A B C D E F G H I J

Balok B.1 30x60 6.18 6.18 6.18 6.18 6.18 6.18 6.18 6.18 6.18 6.18

Balok B.2 25x50 - - - - - - - - - -


Balok B.3 20x40 2.25 2.25 2.25 2.25 3.90 2.25 2.25 2.25 2.25 1.10

Balok B.4 20x30 - - - - 5.30 - - - - -

Balok B.6 25x60 6.33 6.33 6.33 6.33 - 6.33 6.33 6.33 6.33 -

BESI

BALOK LT.2 AS VERTIKAL


1 A B C D E F G H I J

Balok B.1 9.55 9.55 9.55 9.55 9.55 9.55 9.55 9.55 9.55 9.55

* Begel 25x55cm Jmlh Tumpuan 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00 15.00
Jmlh Lapangan 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
Jmlh Tumpuan 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00
Jmlh Lapangan 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00

Balok B.2 - - - - - - - - - -

* Begel 20x45cm Jmlh Tumpuan - - - - - - - - - -


Jmlh Lapangan - - - - - - - - - -

Balok B.3 6.13 6.40 - 6.13 8.12 4.06 5.56 8.12 6.13 -

* Begel 15x35cm Jmlh Tumpuan 30.00 29.50 - 30.00 38.10 19.05 19.05 38.10 30.00 -
Jmlh Lapangan 20.00 19.67 - 20.00 25.40 12.70 12.70 25.40 20.00 -

Balok B.4 3.25 3.25 3.25 3.25 3.25 - 6.25 3.25 3.25 -

* Begel 15x25cm Jmlh Tumpuan 15.00 15.00 15.00 15.00 15.00 - 22.50 15.00 15.00 -
Jmlh Lapangan 10.00 10.00 10.00 10.00 10.00 - 15.00 10.00 10.00 -

Balok B.5 - - 4.50 - - - - - - -

* Begel 10x25cm Jmlh Tumpuan - - 22.50 - - - - - - -


Jmlh Lapangan - - 15.00 - - - - - - -

BALOK LT.3 AS VERTIKAL


2 A B C D E F G H I J

Balok B.1 - - - 3.30 3.30 3.30 3.30 - - -

* Begel 25x55cm Jmlh Tumpuan 0 0 0 15.00 15.00 15.00 15.00 - - -


Jmlh Lapangan 0 0 0 10.00 10.00 10.00 10.00 - - -

Balok B.2 - - - - - - - - - -

* Begel 20x45cm Jmlh Tumpuan - - - - - - - - - -


Jmlh Lapangan - - - - - - - - - -

Balok B.4 - - - 7.44 4.71 1.98 1.98 - - -

* Begel 15x25cm Jmlh Tumpuan - - - 37.20 23.55 9.90 9.90 - - -


Jmlh Lapangan - - - 24.80 15.70 6.60 6.60 - - -

Balok B.5 - - - 2.58 5.86 2.58 - - - -

* Begel 10x25cm Jmlh Tumpuan - - - 11.75 28.15 11.75 - - - -


Jmlh Lapangan - - - 7.83 18.77 7.83 - - - -

BALOK LT.ATAP AS VERTIKAL


3 A B C D E F G H I J

Balok B.1 - - - 3.30 3.30 3.30 3.30 - - -

* Begel 25x55cm Jmlh Tumpuan 0 0 0 15.00 15.00 15.00 15.00 - - -


Jmlh Lapangan 0 0 0 10.00 10.00 10.00 10.00 - - -

BALOK TRIBUN AS VERTIKAL


4 A B C D E F G H I J

Balok B.1 6.20 6.20 6.20 6.20 6.20 6.20 6.20 6.20 6.20 6.20

* Begel 25x55cm Jmlh Tumpuan - - - - - - - - - -


Jmlh Lapangan - - - - - - - - - -
Jmlh Tumpuan 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00
Jmlh Lapangan 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00

Balok B.2 - - - - - - - - - -

* Begel 20x45cm Jmlh Tumpuan - - - - - - - - - -


Jmlh Lapangan - - - - - - - - - -

Balok B.3 3.35 3.35 3.35 3.35 4.60 3.35 3.35 3.35 3.35 1.70

* Begel 15x35cm Jmlh Tumpuan 14.00 14.00 14.00 14.00 31.00 14.00 14.00 14.00 14.00 7.00
Jmlh Lapangan 9.33 9.33 9.33 9.33 20.67 9.33 9.33 9.33 9.33 4.67

Balok B.4 - - - - 5.60 - - - - -

* Begel 15x25cm Jmlh Tumpuan - - - - 26.50 - - - - -


Jmlh Lapangan - - - - 17.67 - - - - -

Balok B.6 6.00 6.00 6.00 6.00 - 6.00 6.00 6.00 6.00 -

* Begel 20x55cm Jmlh Tumpuan - - - - - - - - - -


Jmlh Lapangan - - - - - - - - - -
Jmlh Tumpuan 28.50 28.50 28.50 28.50 - 28.50 28.50 28.50 28.50 -
Jmlh Lapangan 19.00 19.00 19.00 19.00 - 19.00 19.00 19.00 19.00 -

BEKESTING

BALOK LT.2 AS VERTIKAL


1 A B C D E F G H I J

Balok B.1 7.65 7.65 7.65 7.65 7.65 7.65 7.65 7.65 7.65 7.65

Balok B.2 - - - - - - - - - -

Balok B.3 5.88 5.90 - 5.88 7.62 3.81 3.81 7.62 5.88 -

Balok B.4 2.75 2.75 2.75 2.75 2.75 - 5.31 2.75 2.75 -

Balok B.5 - - 4.50 - - - - - - -

BALOK LT.3 AS VERTIKAL


2 A B C D E F G H I J

Balok B.1 - - - 2.30 2.30 2.30 2.30 - - -

Balok B.2 - - - - - - - - - -

Balok B.3 - - - - - - - - - -

Balok B.4 - - - 7.44 4.71 1.98 1.98 - - -

Balok B.5 - - - 2.35 5.63 2.35 - - - -

BALOK LT.ATAP AS VERTIKAL


3 A B C D E F G H I J

Balok B.1 - - - 2.30 2.30 2.30 2.30 - - -


Balok B.2 - - - - - - - - - -

Balok B.3 - - - - - - - - - -

Balok B.4 - - - - - - - - - -

Balok B.5 - - - - - - - - - -

BALOK TRIBUN AS VERTIKAL


4 A B C D E F G H I J

Balok B.1 6.18 6.18 6.18 6.18 6.18 6.18 6.18 6.18 6.18 6.18

Balok B.2 - - - - - - - - - -

Balok B.3 2.25 2.25 2.25 2.25 3.90 2.25 2.25 2.25 2.25 1.10

Balok B.4 - - - - 5.00 - - - - -

Balok B.6 6.33 6.33 6.33 6.33 - 6.33 6.33 6.33 6.33 -
BETON

AS HORIZONTAL Dimensi
JUMLAH Volume
1 2 3 4 Balok

- - - - 76.50 M 0.3 0.48 11.016

50.40 49.50 37.90 - 137.80 M 0.25 0.38 13.091

- 5.40 - - 51.79 M 0.2 0.28 2.89996

- 3.68 - - 28.24 M 0.2 0.18 1.01664

- 13.28 17.78 M 0.15 0.18 0.48006

AS HORIZONTAL Dimensi
JUMLAH Volume
1 2 3 4 Balok

16.8 - - - 26.00 M 0.3 0.48 0

- 16.50 - - 16.50 M 0.25 0.38 0

- - - - 0.00 M 0.2 0.28 0

- 18.20 - - 34.31 M 0.2 0.18 0

- 7.00 - - 17.33 M 0.15 0.18 0

AS HORIZONTAL Dimensi
JUMLAH Volume
1 2 3 4 Balok

16.8 16.5 - - 42.50 M 0.3 0.48 0

- - - - 0.00 M 0.25 0.38 0

- - - - 0.00 M 0.2 0.28 0

- - - - 0.00 M 0.2 0.18 0

- - - - 0.00 M 0.15 0.18 0

AS HORIZONTAL Dimensi
JUMLAH Volume
1 2 3 4 Balok

49.5 50.4 161.70 M 0.3 0.6 29.106

- - - - 0.00 M 0.25 0.5 0


- - - 48.20 71.20 M 0.2 0.4 5.696

- - - 11.30 16.60 M 0.2 0.3 0.996

- - - - 50.64 M 0.25 0.6 7.596

BESI

AS HORIZONTAL dipakai Jumlah BJ


JUMLAH
1 2 3 4 Besi Besi Besi

- - - - 95.50 M D19 mm 12 2.226


D16 mm 2 1.578
- - - - 150.00 bh Ø 10 mm 1.80 0.617
- - - - 100.00 bh Ø 10 mm 1.80 0.617
- - - - 300.00 bh Ø 10 mm 1.80 0.617
- - - - 200.00 bh Ø 10 mm 1.80 0.617

54.40 54.40 40.35 - 149.15 M D19 mm 8 2.226


D13 mm 4 1.042
270.00 270.00 200.00 - 740.00 bh Ø 8 mm 1.50 0.395
180.00 180.00 133.33 - 493.33 bh Ø 8 mm 1.50 0.395

- 6.60 - - 57.24 M D19 mm 6 2.226


D13 mm 2 1.042
- 30.00 - - 263.80 bh Ø 8 mm 1.20 0.395
- 20.00 - - 175.87 bh Ø 8 mm 1.20 0.395

- 3.88 - - 32.88 M D16 mm 6 1.578


D12 mm 2 0.887
- 19.40 - - 146.90 bh Ø 8 mm 0.96 0.395
- 12.93 - - 97.93 bh Ø 8 mm 0.96 0.395

- 13.28 - - 17.78 M D16 mm 6 1.578

- 66.40 - - 88.90 bh Ø 8 mm 0.86 0.395


- 44.27 - - 59.27 bh Ø 8 mm 0.86 0.395

AS HORIZONTAL dipakai Jumlah BJ


JUMLAH
1 2 3 4 Besi Besi Besi

18.40 - - - 31.60 M D19 mm 10 2.226


D16 mm 4 1.578
90.00 - - - 150.00 bh Ø 8 mm 1.80 0.617
60.00 - - - 100.00 bh Ø 8 mm 1.80 0.617

- 18.50 - - 18.50 M D19 mm 6 2.226


D16 mm 4 1.578
- 90.00 - - 90.00 bh Ø 8 mm 1.50 0.617
- 60.00 - - 60.00 bh Ø 8 mm 1.50 0.617

- 18.20 - - 34.31 M D16 mm 4 1.578


D10 mm 4 0.887
- 90.00 - - 170.55 bh Ø 8 mm 0.96 0.395
- 60.00 - - 113.70 bh Ø 8 mm 0.96 0.395

- 7.15 - - 18.16 M D13 mm 6 1.578

- 35.00 - - 86.65 bh Ø 8 mm 0.86 0.395


- 23.33 - - 57.77 bh Ø 8 mm 0.86 0.395

AS HORIZONTAL dipakai Jumlah BJ


JUMLAH
1 2 3 4 Besi Besi Besi

18.40 18.40 - - 50.00 M D19 mm 10 2.226


D16 mm 4 1.578
90.00 90.00 - - 240.00 bh Ø 8 mm 1.80 0.617
60.00 60.00 - - 160.00 bh Ø 8 mm 1.80 0.617

AS HORIZONTAL dipakai Jumlah BJ


JUMLAH
1 2 3 4 Besi Besi Besi

- - 54.40 54.40 170.80 M D19 mm 12 2.226


D16 mm 2 1.578
- - 270.00 270.00 540.00 bh Ø 10 mm 1.8 0.617
- - 180.00 180.00 360.00 bh Ø 10 mm 1.8 0.617
300.00 bh Ø 10 mm 1.8 0.617
200.00 bh Ø 10 mm 1.8 0.617

- - - - 0.00 M D19 mm 8 2.226


D13 mm 4 1.042
- - - - - bh Ø 8 mm 1.5 0.395
- - - - - bh Ø 8 mm 1.5 0.395

- - - 48.80 81.90 M D19 mm 6 2.226


D13 mm 2 1.042
- - - 240.00 390.00 bh Ø 8 mm 1.2 0.395
- - - 160.00 260.00 bh Ø 8 mm 1.2 0.395

- - - 11.90 17.50 M D16 mm 6 1.578


D12 mm 2 0.887
- - - 56.50 83.00 bh Ø 8 mm 0.96 0.395
- - - 37.67 55.33 bh Ø 8 mm 0.96 0.395

- - - - 48.00 M D19 mm 10 2.226


D13 mm 2 1.042
- - - - - bh Ø 10 mm 1.70 0.617
- - - - - bh Ø 10 mm 1.70 0.617
- - - - 228.00 bh Ø 10 mm 1.70 0.617
- - - - 152.00 bh Ø 10 mm 1.70 0.617

EKESTING

AS HORIZONTAL Dimensi
JUMLAH Volume
1 2 3 4 Bekesting

- - - - 76.50 M 0.3 0.48 96.39

50.40 49.50 37.90 - 137.80 M 0.25 0.38 139.178

- 5.40 - - 51.79 M 0.2 0.28 39.3566

- 3.68 - - 28.24 M 0.2 0.18 15.8144

- 13.28 17.78 M 0.15 0.18 9.0678

AS HORIZONTAL Dimensi
JUMLAH Volume
1 2 3 4 Bekesting

16.8 - - - 26.00 M 0.3 0.48 0

- 16.50 - - 16.50 M 0.25 0.38 0

- - - - 0.00 M 0.2 0.28 0

- 18.20 - - 34.31 M 0.2 0.18 0

- 7.00 - - 17.33 M 0.15 0.18 0

AS HORIZONTAL Dimensi
JUMLAH Volume
1 2 3 4 Bekesting

16.8 16.5 - - 42.50 M 0.3 0.48 0


- - - - 0.00 M 0.25 0.38 0

- - - - 0.00 M 0.2 0.28 0

- - - - 0.00 M 0.2 0.18 0

- - - - 0.00 M 0.15 0.18 0

AS HORIZONTAL Dimensi
JUMLAH Volume
1 2 3 4 Bekesting

0 0 49.5 50.4 161.70 M 0.3 0.6 242.55

- - - - 0.00 M 0.25 0.5 0

- - - 48.20 71.20 M 0.2 0.4 71.2

- - - 11.30 16.30 M 0.2 0.3 13.04

- - - - 50.64 M 0.25 0.6 73.428


BESI MEMANJANG
Sat.
Dia. Besi Koefi (Kg/m3) Dia. Besi (m) berat per m' Kg) berat per m' Kg)
mm a b = a x b kuadrat PEMBULATAN
m3 6 ### 0.006 0.2218 0.222
8 ### 0.008 0.3944 0.395
m3 10 ### 0.010 0.6162 0.617
12 ### 0.012 0.8874 0.887
m3 13 ### 0.013 1.0414 1.042
16 ### 0.016 1.5775 1.578
m3 17 ### 0.017 1.7812 1.782
18 ### 0.018 1.9972 1.998
m3 19 ### 0.019 2.2257 2.226
22 ### 0.022 2.9845 2.985
25 ### 0.03 3.8539 3.854

Sat.

m3

m3

m3

m3

m3

Sat.

m3

m3

m3

m3

m3

Sat.

m3

m3
m3

m3

m3

Volume Sat.

2,550.996 kg
301.398 kg
166.590 kg
111.060 kg
333.180 kg
222.120 kg
3,685.344 kg

2,656.063 kg
621.657 kg
438.450 kg
292.300 kg
4,008.470 kg

764.431 kg
119.278 kg
125.041 kg
83.361 kg
1,092.110 kg

311.308 kg
58.329 kg
55.704 kg
37.136 kg
462.478 kg

168.341 kg

30.199 kg
20.133 kg
218.673 kg

Volume Sat.

703.416 kg
199.459 kg
166.590 kg
111.060 kg
- kg

247.086 kg
116.772 kg
83.295 kg
55.530 kg
- kg

216.565 kg
121.732 kg
64.673 kg
43.115 kg
- kg

171.892 kg

29.435 kg
19.623 kg
- kg

Volume Sat.

1,113.000 kg
315.600 kg
266.544 kg
177.696 kg
- kg

Volume Sat.

4,562.410 kg
539.045 kg
599.724 kg
399.816 kg
333.180 kg
222.120 kg
6,656.294 kg

- kg
- kg
- kg
- kg
- kg

1,093.856 kg
170.680 kg
184.860 kg
123.240 kg
1,572.636 kg

165.690 kg
31.045 kg
31.474 kg
20.982 kg
249.191 kg

1,068.480 kg
100.032 kg
- kg
- kg
239.149 kg
159.433 kg
1,567.094 kg

BESI MEMANJANG
Sat.
Dia. Besi Koefi (Kg/m3) Dia. Besi (m) berat per m' Kg) berat per m' Kg)
mm a b = a x b kuadrat PEMBULATAN
m2 6 ### 0.006 0.2218 0.222
8 ### 0.008 0.3944 0.395
m2 10 ### 0.010 0.6162 0.617
12 ### 0.012 0.8874 0.887
m2 13 ### 0.013 1.0414 1.042
16 ### 0.016 1.5775 1.578
m2 17 ### 0.017 1.7812 1.782
18 ### 0.018 1.9972 1.998
m2 19 ### 0.019 2.2257 2.226
22 ### 0.022 2.9845 2.985
25 ### 0.03 3.8539 3.854

Sat.

m2

m2

m2

m2

m2

Sat.

m2
m2

m2

m2

m2

Sat.

m2

m2

m2

m2

m2
BETON

KOLOM LT.2 AS HORIZONTAL


JUMLAH
1 1 2 3 4

Kolom K.1 - 49.00 - - 49.00 M

Kolom K.2 - - 11.80 - 11.80 M

Kolom K.2' - - 23.00 - 23.00 M

Kolom K.3 - - - - 0.00 M

Kolom K.4 49.00 - - - 49.00 M

Kolom Kp 7.38 277.24 4.28 - 288.90 M

KOLOM LT.3 AS HORIZONTAL


JUMLAH
2 1 2 3 4

Kolom K.1 - 41.30 - - 41.30 M

Kolom K.2 - - - - 0.00 M

Kolom K.3 - - - - 0.00 M

Kolom K.4 41.30 - - - 41.30 M

Kolom Kp 24.35 10.50 - - 34.85 M

BESI

KOLOM LT.2 AS HORIZONTAL


JUMLAH
1 1 2 3 4

Kolom K.1 - 49.00 - - 49.00 M


* Begel 45x75cm 32.67 10.00

Kolom K.2 - - 11.80 - 11.80 M


* Begel 45x45cm 7.87 10.00

Kolom K.2' - - 23.00 - 23.00 M


* Begel 15x25cm 15.33 10.00

Kolom K.3 - - - - 0.00 M


Kolom K.4 49.00 - - - 49.00 M

* Begel 35x55cm 32.67 10.00

Kolom Kp 7.38 249.40 4.28 - 261.06 M


* Begel 7x7cm 5.47 9.00
* Begel 7x7cm 28.67 58.00
* Begel 7x7cm 13.67 4.00

KOLOM LT.3 AS HORIZONTAL


JUMLAH
2 1 2 3 4

Kolom K.1 - 41.30 - - 41.30 M


* Begel 45x75cm 27.53 10.00

Kolom K.2 - - - - 0.00 M

Kolom K.3 - - - - 0.00 M

Kolom K.4 41.30 - - - 41.30 M

* Begel 35x55cm 27.53 10.00

Kolom Kp 24.35 10.50 - - 34.85 M


* Begel 7x7cm 5.47 10.00
* Begel 7x7cm 21.53 5.00
* Begel 7x7cm 20.00 3.00
* Begel 7x7cm 3.33 3.00

BEKESTING

KOLOM LT.2 AS HORIZONTAL


JUMLAH
1 1 2 3 4

Kolom K.1 - 49.00 - - 49.00 M

Kolom K.2 - - 11.80 - 11.80 M

Kolom K.2' - - 23.00 - 23.00 M

Kolom K.3 - - - - 0.00 M

Kolom K.4 49.00 - - - 49.00 M


Kolom Kp 7.38 249.40 8.20 - 264.98 M

KOLOM LT.3 AS HORIZONTAL


JUMLAH
2 1 2 3 4

Kolom K.1 - 41.30 - - 41.30 M

Kolom K.2 - - - - 0.00 M

Kolom K.3 - - - - 0.00 M

Kolom K.4 41.30 - - - 41.30 M

Kolom Kp 23.35 10.50 - - 33.85 M


Dimensi BESI MEMANJANG
Volume Sat.
Kolom Dia. Besi Koefi (Kg/m3) Dia. Besi (m) berat per m' Kg)
mm a b = a x b kuadrat
0.5 0.8 0 m3 6 6,162.25 0.006 0.2218
8 6,162.25 0.008 0.3944
0.5 0.5 2.95 m3 10 6,162.25 0.010 0.6162
12 6,162.25 0.012 0.8874
0.2 0.3 0 m3 13 6,162.25 0.013 1.0414
16 6,162.25 0.016 1.5775
0.4 0.4 0 m3 17 6,163.25 0.017 1.7812
18 6,164.25 0.018 1.9972
0.4 0.6 0 m3 19 6,165.25 0.019 2.2257
22 6,166.25 0.022 2.9845
0.11 0.11 0.00 m' 25 6,166.25 0.03 3.8539

Dimensi
Volume Sat.
Kolom

0.5 0.8 0 m3

0.5 0.5 0 m3

0.4 0.4 0 m3

0.4 0.6 0 m3

0.11 0.11 0.00 m'

Dipake Jumlah
BJ Besi Volume Sat.
Besi Besi

D19 mm 16 2.226 1,745.184 kg


Ø 8 mm 2.60 0.395 335.487 kg
- kg

D16 mm 14 1.578 260.686 kg


Ø 8 mm 2.00 0.395 62.147 kg
322.832 kg

D13 mm 6 1.042 143.796 kg


Ø 8 mm 0.96 0.395 58.144 kg
- kg
D19 mm 4 2.226 436.296 kg
D16 mm 10 1.578 773.220 kg
Ø 8 mm 2.00 0.395 258.067 kg
- kg

Ø 10 mm 4 0.617 644.296 kg
Ø 6 mm 0.40 0.222 4.369 kg
Ø 6 mm 0.40 0.222 147.645 kg
Ø 6 mm 0.40 0.222 4.854 kg
- kg

Dipake Jumlah
BJ Besi Volume Sat.
Besi Besi

D19 mm 16 2.226 1,470.941 kg


Ø 8 mm 2.60 0.395 282.767 kg
- kg

D19 mm 4 2.226 367.735 kg


D16 mm 10 1.578 651.714 kg
Ø 8 mm 2.00 0.395 217.513 kg
- kg

Ø 10 mm 4 0.617 86.010 kg
Ø 6 mm 0.40 0.222 4.854 kg
Ø 6 mm 0.40 0.222 9.561 kg
Ø 6 mm 0.40 0.222 5.328 kg
Ø 6 mm 0.40 0.222 0.888 kg
- kg

NG

Dimensi
Volume Sat.
Kolom

0.5 0.8 0 m2

0.5 0.5 23.6 m2

0.2 0.3 0 m2

0.4 0.4 0 m2

0.4 0.6 0 m2
0.11 0.11 0.000 m2

Dimensi
Volume Sat.
Kolom

0.5 0.8 0 m2

0.5 0.5 0 m2

0.4 0.4 0 m2

0.4 0.6 0 m2

0.11 0.11 0 m2
berat per m' Kg)
PEMBULATAN
0.222
0.395
0.617
0.887
1.042
1.578
1.782
1.998
2.226
2.985
3.854
1 Pek. Urugan Pasir bawah lantai dipadatkan 97.297 m3
2 Lantai Beton Rabat bawah lantai (tebal 7 cm) Elv. 0 97.297 m3
BETON
3 Plat Beton lantai 2. Elv. +4.00
a. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 34.073 m3
19.152
6.656
-
18.000
2.812
6.968
-
38.700
-
18.900
7.817
-
27.120
5.574
3.806
-
25.200
-
34.200
-
18.000
8.736
6.968
2.812
-
18.900
6.656

276.977

3 Plat Beton lantai 3. Elv. +8.90


a. Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 - m3
BEKESTING
1 Plat Beton lantai 2. Elv. +4.00
238.640 M2

2 Plat Beton lantai 3. Elv. +8.90


- M2
BESI MEMANJANG
Dia. Besi Koefi (Kg/m3) Dia. Besi (m) berat per m' Kg) berat per m' Kg)
mm a b = a x b kuadrat PEMBULATAN
6 6,162.25 0.006 0.2218 0.222
8 6,162.25 0.008 0.3944 0.395
10 6,162.25 0.010 0.6162 0.617
12 6,162.25 0.012 0.8874 0.887
13 6,162.25 0.013 1.0414 1.042
16 6,162.25 0.016 1.5775 1.578
17 6,163.25 0.017 1.7812 1.782
18 6,164.25 0.018 1.9972 1.998
19 6,165.25 0.019 2.2257 2.226
22 6,166.25 0.022 2.9845 2.985
25 6,166.25 0.03 3.8539 3.854

Ket. tebal lebar panjang unit jumlah


Ruas A-B 0.10 2.39 3.73 1.00 0.891
0.10 9.20 5.93 1.00 5.456
0.10 5.78 5.93 1.00 3.428
0.10 2.09 5.93 1.00 1.239
pengurangan 0.10 0.15 16.80 1.00 0.252
10.762
Ruas B-C 0.10 8.70 5.83 1.00 5.072
0.10 5.78 5.93 1.00 3.428
0.10 2.09 5.93 1.00 1.239
pengurangan 0.10 0.15 13.13 1.00 0.197
9.542
Ruas C-D 0.10 14.85 5.85 1.00 8.687
0.10 3.50 5.85 1.00 2.048
pengurangan 0.10 0.15 6.00 1.00 0.090
10.645
Ruas D-E 0.10 2.39 3.73 1.00 0.891
0.10 1.58 1.68 1.00 0.265
0.10 2.60 5.85 1.00 1.521
0.10 11.85 5.85 1.00 6.932
0.10 3.50 5.85 1.00 2.048
pengurangan 0.10 0.15 15.03 1.00 0.225
11.432
Ruas E-F 0.10 2.60 5.60 1.00 1.456
0.10 11.70 5.85 1.00 6.845
0.10 1.70 5.85 1.00 0.995
0.10 3.23 5.85 1.00 1.890
0.10 2.03 6.00 1.00 1.218
12.403
Ruas F-G 0.10 6.00 1.65 1.00 0.990
0.10 14.90 5.85 1.00 8.717
0.10 2.29 6.00 1.00 1.374
pengurangan 0.10 0.15 11.70 1.00 0.176
10.905
Ruas G-H 0.10 1.65 4.00 1.00 0.660
0.10 14.85 5.85 1.00 8.687
0.10 3.50 5.85 1.00 2.048
pengurangan 0.10 0.15 6.00 1.00 0.090
11.305
Ruas H-I 0.10 8.70 5.83 1.00 5.072
0.10 5.78 5.93 1.00 3.428
0.10 2.09 5.93 1.00 1.239
pengurangan 0.10 0.15 13.13 1.00 0.197
9.542
Ruas I-J 0.10 2.39 3.73 1.00 0.891
0.10 9.20 5.93 1.00 5.456
0.10 5.78 5.93 1.00 3.428
0.10 2.09 5.93 1.00 1.239
pengurangan 0.10 0.15 16.80 1.00 0.252
10.762

Ket. Panjang Lebar tebal unit jumlah


Ruas A-B 0.10 2.39 3.73 1.00 0.891
0.10 9.20 5.93 1.00 5.456
0.10 5.78 5.93 1.00 3.428
0.10 2.09 5.93 1.00 1.239
pengurangan 0.10 0.15 16.80 1.00 0.252
10.762
Ruas B-C 0.10 8.70 5.83 1.00 5.072
0.10 5.78 5.93 1.00 3.428
0.10 2.09 5.93 1.00 1.239
pengurangan 0.10 0.15 13.13 1.00 0.197
9.542
Ruas C-D 0.10 14.85 5.85 1.00 8.687
0.10 3.50 5.85 1.00 2.048
pengurangan 0.10 0.15 6.00 1.00 0.090
10.645
Ruas D-E 0.10 2.39 3.73 1.00 0.891
0.10 1.58 1.68 1.00 0.265
0.10 2.60 5.85 1.00 1.521
0.10 11.85 5.85 1.00 6.932
0.10 3.50 5.85 1.00 2.048
pengurangan 0.10 0.15 15.03 1.00 0.225
11.432
Ruas E-F 0.10 2.60 5.60 1.00 1.456
0.10 11.70 5.85 1.00 6.845
0.10 1.70 5.85 1.00 0.995
0.10 3.23 5.85 1.00 1.890
0.10 2.03 6.00 1.00 1.218
12.403
Ruas F-G 0.10 6.00 1.65 1.00 0.990
0.10 14.90 5.85 1.00 8.717
0.10 2.29 6.00 1.00 1.374
pengurangan 0.10 0.15 11.70 1.00 0.176
10.905
Ruas G-H 0.10 1.65 4.00 1.00 0.660
0.10 14.85 5.85 1.00 8.687
0.10 3.50 5.85 1.00 2.048
pengurangan 0.10 0.15 6.00 1.00 0.090
11.305
Ruas H-I 0.10 8.70 5.83 1.00 5.072
0.10 5.78 5.93 1.00 3.428
0.10 2.09 5.93 1.00 1.239
pengurangan 0.10 0.15 13.13 1.00 0.197
9.542
Ruas I-J 0.10 2.39 3.73 1.00 0.891
0.10 9.20 5.93 1.00 5.456
0.10 5.78 5.93 1.00 3.428
0.10 2.09 5.93 1.00 1.239
pengurangan 0.10 0.15 16.80 1.00 0.252
10.762

BETON
Ket. Panjang Lebar tebal Unit jumlah 3 Plat Beton lantai 2. E
RUAS A - B a.
Luas 1 6.08 3.15 0.12 1.00 2.298
Luas 2 3.20 2.08 0.12 1.00 0.799
RUAS B - C
Luas 1 6.00 3.00 0.12 1.00 2.160
Luas 2 1.85 1.52 0.12 1.00 0.337
Luas 3 3.35 2.08 0.12 2.00 1.672
RUAS C - D
Luas 1 6.45 6.00 0.12 1.00 4.644
RUAS D - E
Luas 1 6.00 3.15 0.12 1.00 2.268
Luas 2 4.05 1.93 0.12 1.00 0.938
RUAS E - F
Luas 1 6.00 4.52 0.12 1.00 3.254
Luas 2 2.68 2.08 0.12 1.00 0.669
Luas 3 2.08 1.83 0.12 1.00 0.457
RUAS F - G
Luas 1 6.00 4.20 0.12 1.00 3.024
RUAS G - H
Luas 1 6.00 5.70 0.12 1.00 4.104
RUAS H - I
Luas 1 6.00 3.00 0.12 1.00 2.160
Luas 2 4.20 2.08 0.12 1.00 1.048
Luas 3 3.35 2.08 0.12 1.00 0.836
Luas 4 1.85 1.52 0.12 1.00 0.337
RUAS I - J
Luas 1 6.00 3.15 0.12 1.00 2.268
Luas 2 3.20 2.08 0.12 1.00 0.799
Bordes
tangga 1 4.15 2.35 0.12 3.00
tangga 2 2.85 1.75 0.12 1.00
tangga 3 1.30 1.10 0.12 1.00
tangga 4 2.85 1.55 0.12 1.00
Plat Miring Tangga
tangga 1 8.32 1.85 0.12 3.00
tangga 2 3.86 1.41 0.12 1.00

34.073

Ket. Panjang Lebar tebal Unit jumlah 3 Plat Beton lantai 3. E


RUAS D - E a.
Luas 1 6.08 5.65 0.12 1.00 4.122
RUAS E - F
Luas 1 6.00 5.66 0.12 1.00 4.075
RUAS F - G
Luas 1 6.08 2.65 0.12 1.00 1.933
Plat Miring Tangga 3.40 1.85 0.12 3.00
10.131

EKESTING
Ket. Luas Panjang Lebar Unit jumlah
RUAS 1-2
Blok 1 7.52 6.00 45.120
Blok 2 7.52 6.00 45.120
Blok 3 10.26 1.00 10.260
Blok 4 4.76 1.00 4.760
Blok 5 2.09 2.00 4.180
Blok 6 2.91 1.00 2.910
RUAS 2-3
Blok 1 4.64 2.00 9.280
Blok 2 2.45 2.00 4.900
Blok 3 2.41 2.00 4.820
Blok 4 5.13 2.00 10.260
Blok 5 2.48 3.00 7.440
Blok 6 1.98 2.00 3.960
Blok 7 3.43 1.00 3.430
Blok 8 8.15 1.00 8.150
Blok 9 6.62 3.00 19.860
Blok 10 10.43 4.00 41.720
Blok 11 1.15 2.00 2.300
Blok 12 1.93 1.00 1.930
Blok 13 3.03 1.00 3.030
Blok 14 5.21 1.00 5.210
238.640

Ket. Luas Panjang Lebar Unit jumlah


RUAS 1-2
Blok 1 4.04 2.00 8.080
Blok 2 6.27 1.00 6.270
7.45 2.00 14.900
RUAS 2-3
Blok 1 6.58 4.00 26.320
Blok 2 1.88 1.00 1.880
Blok 3 4.35 1.00 4.350
Blok 4 6.58 1.00 6.580

68.380
BESI PLAT
Plat Beton lantai 2. Elv. +4.00 Ket.
Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 3,503.885 kg RUAS A - B
Luas 1
Luas 2
RUAS B - C
Luas 1
Luas 2
Luas 3
RUAS C - D
Luas 1
RUAS D - E
Luas 1
Luas 2
RUAS E - F
Luas 1
Luas 2
Luas 3
RUAS F - G
Luas 1
RUAS G - H
Luas 1
RUAS H - I
Luas 1
Luas 2
Luas 3
Luas 4
RUAS I - J
Luas 1
Luas 2
Bordes
tangga 1
tangga 2
tangga 3
tangga 4
Plat Miring Tangga
tangga 1
tangga 2

Plat Beton lantai 3. Elv. +8.90 Ket.


Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 - kg RUAS D - E
Luas 1
RUAS E - F
Luas 1
RUAS F - G
Luas 1
Plat Miring Tangga
BESI PLAT
Panjang 1 Lebar 2 n1 n2 L1 L2 Ʃ panjang lapis Unit

6.08 3.15 15.75 30.40 95.76 95.76 191.52 2.00 1.00


3.20 2.08 10.40 16.00 33.28 33.28 66.56 2.00 1.00

6.00 3.00 15.00 30.00 90.00 90.00 180.00 2.00 1.00


1.85 1.52 7.60 9.25 14.06 14.06 28.12 2.00 1.00
3.35 2.08 10.40 16.75 34.84 34.84 69.68 2.00 2.00

6.45 6.00 30.00 32.25 193.50 193.50 387.00 2.00 1.00

6.00 3.15 15.75 30.00 94.50 94.50 189.00 2.00 1.00


4.05 1.93 9.65 20.25 39.08 39.08 78.17 2.00 1.00

6.00 4.52 22.60 30.00 135.60 135.60 271.20 2.00 1.00


2.68 2.08 10.40 13.40 27.87 27.87 55.74 2.00 1.00
2.08 1.83 9.15 10.40 19.03 19.03 38.06 2.00 1.00

6.00 4.20 21.00 30.00 126.00 126.00 252.00 2.00 1.00

6.00 5.70 28.50 30.00 171.00 171.00 342.00 2.00 1.00

6.00 3.00 15.00 30.00 90.00 90.00 180.00 2.00 1.00


4.20 2.08 10.40 21.00 43.68 43.68 87.36 2.00 1.00
3.35 2.08 10.40 16.75 34.84 34.84 69.68 2.00 1.00
1.85 1.52 7.60 9.25 14.06 14.06 28.12 2.00 1.00

6.00 3.15 15.75 30.00 94.50 94.50 189.00 2.00 1.00


3.20 2.08 10.40 16.00 33.28 33.28 66.56 2.00 1.00

4.15 2.35 11.75 20.75 48.76 48.76 97.53 2.00 3.00


2.85 1.75 8.75 14.25 24.94 24.94 49.88 2.00 1.00
1.30 1.10 5.50 6.50 7.15 7.15 14.30 2.00 1.00
2.85 1.55 7.75 14.25 22.09 22.09 44.18 2.00 1.00

8.32 1.85 9.25 41.60 76.96 76.96 153.92 2.00 3.00


3.86 1.41 7.05 19.30 27.21 27.21 54.43 2.00 1.00

Panjang 1 Lebar 2 n1 n2 L1 L2 Ʃ panjang lapis Unit

6.08 5.65 28.25 30.40 171.76 171.76 343.52 2.00 1.00

6.00 5.66 28.30 30.00 169.80 169.80 339.60 2.00 1.00

6.08 2.65 13.25 30.40 80.56 80.56 161.12 2.00 1.00


3.40 1.85 9.25 17.00 31.45 31.45 62.90 2.00 3.00
bj besi jumlah (KG)

0.617 236.336
0.617 82.135

0.617 222.120
0.617 34.700
0.617 171.970

0.617 477.558

0.617 233.226
0.617 96.456

0.617 334.661
0.617 68.788
0.617 46.971

0.617 310.968

0.617 422.028

0.617 222.120
0.617 107.802
0.617 85.985
0.617 34.700

0.617 233.226
0.617 82.135

0.617
0.617
0.617
0.617

0.617
0.617

3,503.885

bj besi jumlah (KG)

0.617 423.904

0.617 419.066

0.617 198.822
0.617
1041.79216
Dimensi
Sloof
S1
S2
S3

Kolom
K1 50 80
K2 50 50
K3 40 40
K4 40 60

Balok
B1 30.00 60.00 1800.00
btg dia Luas rasio 2.11
o19 12.00 1.90 34.01
o16 2.00 1.60 4.02
B2
B3
B4
B5
B6 25.00 60.00 1500.00
btg dia Luas rasio 1.89
o19 10.00 1.90 28.34
B7 15.00 52.00 780.00
btg dia Luas rasio 1.70
o13 10.00 1.30 13.27
PEMERINTAH KABUPATEN BOYOLALI
DINAS PEMUDA DAN OLAHRAGA DAN
PARIWISATA
Komplek Perkantoran Terpadu Kabupaten Boyolali
Jl. Ahmad Yani No. 1, Kemiri, Boyolali 57321 Provinsi Jawa Tengah

HARGA PERKIRAAN SENDIRI


(HPS)

PEKERJAAN :
STIMULAN MENJAGA DUNIA EKONOMI DAERAH
AGAR TETAP BERJALAN MELALUI PEKERJAAN PEMBANGUNAN
TRIBUN VVIP STADION TAHAP I

LOKASI :
KECAMATAN CEPOGO - KABUPATEN BOYOLALI

TAHUN ANGGARAN
2020
PEMERINTAH KABUPATEN BOYOLALI
DINAS PEMUDA DAN OLAHRAGA DAN
PARIWISATA
Komplek Perkantoran Terpadu Kabupaten Boyolali
Jl. Ahmad Yani No. 1, Kemiri, Boyolali 57321 Provinsi Jawa Tengah
REKAPITULASI ANGGARAN BIAYA (HPS)
KEGIATAN : STIMULAN MENJAGA DUNIA EKONOMI DAERAH
AGAR TETAP BERJALAN MELALUI PEKERJAAN PEMBANGUNAN
TRIBUN VVIP STADION TAHAP I
LOKASI : KECAMATAN CEPOGO - KABUPATEN BOYOLALI
ANGGARAN : 2020

No. Uraian Pekerjaan Jumlah

A PEKERJAAN PERSIAPAN Rp 53,932,837.48


JUMLAH A Rp 53,932,837.48

B PEKERJAAN GEDUNG
I PEKERJAAN TANAH Rp 132,200,381.93
II PEKERJAAN PONDASI Rp 336,982,238.18
III PEKERJAAN DINDING Rp 131,577,186.33
IV PEKERJAAN PLESTERAN Rp 184,935,377.17
V PEKERJAAN BETON Rp 2,459,654,476.37
VI PEKERJAAN BESI ALUMUNIUM Rp 62,041,317.25
VII PEKERJAAN SANITASI DAN PLUMBING Rp 19,899,324.50
VIII PEKERJAAN MEKANIKAL DAN ELEKTRIKAL Rp 17,322,580.00

JUMLAH C Rp 3,344,612,881.73

JUMLAH Rp 3,398,545,719.21
PPN 10% Rp 339,854,571.92
JUMLAH TOTAL Rp 3,738,400,291.13
Dibulatkan Rp 3,738,400,000.00
Terbilang : Tiga Milyard Tujuh Ratus Tiga Puluh Delapan Juta Empat Ratus Ribu Rupiah

Boyolali,………………………2020
Mengetahui / Menyetujui, Dibuat Oleh,
KEPALA DINAS PEMUDA, OLAH RAGA DAN PARIWISATA KEPALA BIDANG CIPTA KARYA DPU PR
KABUPATEN BOYOLALI KABUPATEN BOYOLALI
Selaku PPKom

Drs. SUSILO HARTONO KUNAWI, ST.


NIP. 19680529 198803 1 002 NIP. 19760808 200501 1 009

Mengetahui,
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
KABUPATEN BOYOLALI

ARIEF GUNARTO, ST, MT.


NIP. 19710828 199903 1 004
PEMERINTAH KABUPATEN BOYOLALI
DINAS PEMUDA DAN OLAHRAGA DAN
PARIWISATA
Komplek Perkantoran Terpadu Kabupaten Boyolali
Jl. Ahmad Yani No. 1, Kemiri, Boyolali 57321 Provinsi Jawa Tengah
RENCANA ANGGARAN BIAYA ( HPS )
KEGIATAN : STIMULAN MENJAGA DUNIA EKONOMI DAERAH
AGAR TETAP BERJALAN MELALUI PEKERJAAN PEMBANGUNAN
TRIBUN VVIP STADION TAHAP I
LOKASI : KECAMATAN CEPOGO - KABUPATEN BOYOLALI
ANGGARAN : 2020

Volume Nomer
No. Uraian Pekerjaan Harga Satuan Jumlah
m' m2 m3 Analis

A PEKERJAAN PERSIAPAN
1 Uitzet / bouwplank 1.000 Ls Survey 2,200,000.00 2,200,000.00
2 Air kerja dan Listrik kerja 1.000 Ls Survey 3,600,000.00 3,600,000.00
3 Papan nama proyek 1.000 Ls Survey 329,000.00 329,000.00
4 Direksi keet ( Buat ) 1.000 Ls Survey 2,200,000.00 2,200,000.00
5 Andang/Stegerwerk 1.000 Ls Survey 6,800,000.00 6,800,000.00
6 Kesehatan Keselamatan Kerja (K3) 1.000 Ls HITUNG K3 15,477,000.00 15,477,000.00
7 Pagar Sementara dari Seng Gelombang Tinggi 2,40 m 54.000 m HITUNG PR1 246,793.29 13,326,837.48
8 Mobilisasi Alat Berat dan Alat Pemancangan 1.000 Ls Survey 10,000,000.00 10,000,000.00

Jumlah A 53,932,837.48

B PEKERJAAN GEDUNG
I PEKERJAAN TANAH
1 Pek. Galian Tanah Biasa Sedalam 2 m untuk Foot Plate dengan Alat 671.95 m3 HITUNG TA8 22,266.86 14,962,216.58
2 Pek. Galian Tanah Biasa Sedalam 1 m untuk Pondasi dan Talud dengan Alat 540.56 m3 HITUNG TA8 22,266.86 12,036,596.11
3 Pek. Galian Tanah Penyiapan Lahan dengan Alat 532.00 m3 HITUNG TA1 20,229.00 10,761,828.00
4 Pek. Urugan Tanah Peninggian Lantai Bangunan Menggunakan Bekas Galian 524.40 m3 HITUNG TA2 20,075.00 10,527,330.00
5 Pek. Pemadatan Tanah menggunakan alat berat 524.40 m3 HITUNG TA5a 22,988.13 12,054,975.37
6 Pek. Membuang Tanah Keluar Lokasi Proyek 591.96 m3 HITUNG TA7 42,043.97 24,888,236.70
7 Pek. Urugan Tanah Kembali 628.15 m3 HITUNG TA2 20,075.00 12,610,184.86
8 Pek. Urugan Pasir 131.19 m3 A.2.3.1.11 261,910.00 34,359,014.31

Jumlah I 132,200,381.93

II PEKERJAAN PONDASI
1 Pek. Pondasi Batu Belah Camp. 1pc : 6ps 105.56 m3 A.3.2.1.4 859,395.90 90,714,393.62
2 Pek. Talud Batu Belah Camp. 1pc : 6ps 286.56 m3 A.3.2.1.4 859,395.90 246,267,844.56

Jumlah II 336,982,238.18

III PEKERJAAN DINDING


1 Pek. dinding bata merah tb. 1/2 bata, camp. 1 PC : 6 PP 1,105.30 m2 A.4.4.1.11 119,042.44 131,577,186.33

Jumlah III 131,577,186.33

IV PEKERJAAN PLESTERAN
1 Pek. plesteran 1 PC : 6 PP, tebal 15 mm 2,210.59 m2 A.4.5.2.6 50,896.69 112,511,865.97
2 Pek. Acian 2,488.97 m2 A.4.5.2.27 29,097.75 72,423,511.20

Jumlah IV 184,935,377.17

V PEKERJAAN BETON
Lantai 01
1 Pengeboran Bor Pile 995.00 m' Survey 142,000.00 141,290,000.00
2 Pembuatan Bor Pile Diameter 40 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 124.97 m3 A.4.1.1.10 1,070,159.24 133,739,940.63
b. Pembesian 18,499.77 kg HITUNG BT1 15,332.90 283,655,109.90
3 Footplate FP1 Dimensi 200 x 550 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 49.50 m3 A.4.1.1.10 1,070,159.24 52,972,882.42
b. Pembesian 5,605.69 kg HITUNG BT1 15,332.90 85,951,441.27
c. Begesting 60.00 m2 HITUNG BT3 115,821.20 6,949,272.00
4 Footplate FP2 Dimensi 160 x 160 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 8.96 m3 A.4.1.1.10 1,070,159.24 9,588,626.80
b. Pembesian 1,484.58 kg HITUNG BT1 15,332.90 22,762,953.48
c. Begesting 19.20 m2 HITUNG BT3 115,821.20 2,223,767.04
5 Footplate FP3 Dimensi 140 x 140 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 6.86 m3 A.4.1.1.10 1,070,159.24 7,341,292.39
b. Pembesian 1,110.91 kg HITUNG BT1 15,332.90 17,033,502.60
c. Begesting 16.80 m2 HITUNG BT3 115,821.20 1,945,796.16
6 Sloof S1 Dimensi 20 x 40 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 9.83 m3 A.4.1.1.10 1,070,159.24 10,521,805.65

- RAB - 72
Volume Nomer
No. Uraian Pekerjaan Harga Satuan Jumlah
m' m2 m3 Analis

b. Pembesian 1,695.22 kg HITUNG BT1 15,332.90 25,992,612.67


c. Begesting 98.32 m2 HITUNG BT4 123,068.00 12,100,045.76
7 Sloof S2 Dimensi 20 x 30 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 8.93 m3 A.4.1.1.10 1,070,159.24 9,560,802.66
b. Pembesian 1,442.42 kg HITUNG BT1 15,332.90 22,116,506.66
c. Begesting 89.34 m2 HITUNG BT4 123,068.00 10,994,895.12
8 Sloof S3 Dimensi 15 x20 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 3.41 m3 A.4.1.1.10 1,070,159.24 3,651,276.31
b. Pembesian 589.69 kg HITUNG BT1 15,332.90 9,041,612.11
c. Begesting 45.49 m2 HITUNG BT4 123,068.00 5,598,609.46
9 Kolom Struktur K1 Dimensi 45 x 80 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 24.12 m3 A.4.1.1.10 1,070,159.24 25,812,240.89
b. Pembesian 4,074.82 kg HITUNG BT1 15,332.90 62,478,752.38
c. Begesting 190.25 m2 HITUNG BT5 161,444.80 30,714,873.20
10 Kolom Struktur K2 Dimensi 45 x 45 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 16.00 m3 A.4.1.1.10 1,070,159.24 17,119,872.45
b. Pembesian 2,591.22 kg HITUNG BT1 15,332.90 39,730,990.74
c. Begesting 142.20 m2 HITUNG BT5 161,444.80 22,957,450.56
11 Kolom Struktur K3 Dimensi 40 x 40 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 8.48 m3 A.4.1.1.10 1,070,159.24 9,074,950.36
b. Pembesian 1,392.07 kg HITUNG BT1 15,332.90 21,344,463.97
c. Begesting 84.80 m2 HITUNG BT5 161,444.80 13,690,519.04
12 Kolom Struktur K4 Dimensi 40 x 50 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 13.40 m3 A.4.1.1.10 1,070,159.24 14,340,133.83
b. Pembesian 2,320.16 kg HITUNG BT1 15,332.90 35,574,856.91
c. Begesting 120.60 m2 HITUNG BT5 161,444.80 19,470,242.88
13 Kolom Praktis KP Dimensi 11 x 11 cm
a. Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 3.26 m3 A.4.1.1.5 976,572.06 3,184,552.64
b. Pembesian 633.32 kg HITUNG BT1 15,332.90 9,710,601.56
c. Begesting 59.29 m2 HITUNG BT4 123,068.00 7,296,701.72
14 Ring Balok RB Dimensi 15 x 20 cm
a. Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 11.81 m3 A.4.1.1.5 976,572.06 11,531,172.40
b. Pembesian 1,617.84 kg HITUNG BT1 15,332.90 24,806,210.00
c. Begesting 157.44 m2 HITUNG BT4 123,068.00 19,375,505.94
15 Plat Lantai Tangga
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 9.77 m3 A.4.1.1.10 1,070,159.24 10,458,377.32
b. Pembesian 2,240.47 kg HITUNG BT1 15,332.90 34,352,826.13
c. Begesting 144.77 m2 HITUNG BT9 261,691.65 37,884,001.07
16 Rabat Beton Lantai tebal 10 cm ( K100 ) 97.30 m3 A.4.1.1.1 890,664.50 86,659,286.68
16 Rabat Beton Bawah Footplate tebal 5 cm ( K100 ) 17.28 m3 A.4.1.1.1 890,664.50 15,390,682.56
17 Rabat Beton Bawah Sloof tebal 5 cm ( K100 ) 6.35 m3 A.4.1.1.1 890,664.50 5,654,579.52

Lantai 02
1 Balok B1 Dimensi 30 x 60 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 11.02 m3 A.4.1.1.10 1,070,159.24 11,788,874.20
b. Pembesian 3,685.34 kg HITUNG BT1 15,332.90 56,507,011.02
c. Begesting 96.39 m2 HITUNG BT6 179,507.90 17,302,766.48
2 Balok B2 Dimensi 25 x 50 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 13.09 m3 A.4.1.1.10 1,070,159.24 14,009,454.62
b. Pembesian 4,008.47 kg HITUNG BT1 15,332.90 61,461,475.80
c. Begesting 139.18 m2 HITUNG BT6 179,507.90 24,983,550.51
3 Balok B3 Dimensi 20 x 40 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 2.90 m3 A.4.1.1.10 1,070,159.24 3,103,418.99
b. Pembesian 1,092.11 kg HITUNG BT1 15,332.90 16,745,219.55
c. Begesting 39.36 m2 HITUNG BT6 179,507.90 7,064,820.62
4 Balok B4 Dimensi 20 x 30 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 1.02 m3 A.4.1.1.10 1,070,159.24 1,087,966.69
b. Pembesian 462.48 kg HITUNG BT1 15,332.90 7,091,125.25
c. Begesting 15.81 m2 HITUNG BT6 179,507.90 2,838,809.73
5 Balok B5 Dimensi 15 x 30 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 0.48 m3 A.4.1.1.10 1,070,159.24 513,740.65
b. Pembesian 218.67 kg HITUNG BT1 15,332.90 3,352,895.18
c. Begesting 9.07 m2 HITUNG BT6 179,507.90 1,627,741.74
6 Plat Lantai
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 34.07 m3 A.4.1.1.10 1,070,159.24 36,464,002.40
b. Pembesian 3,503.89 kg HITUNG BT1 15,332.90 53,724,718.35
c. Begesting 238.64 m2 HITUNG BT7 294,155.40 70,197,244.66
7 Concrete Pump 1.00 ls Survey 2,200,000.00 2,200,000.00

Lantai Tribun
1 Balok B1 Dimensi 30 x 60 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 29.11 m3 A.4.1.1.10 1,070,159.24 31,148,054.86
b. Pembesian 6,656.29 kg HITUNG BT1 15,332.90 102,060,296.41
c. Begesting 242.55 m2 HITUNG BT6 179,507.90 43,539,641.15
2 Balok B3 Dimensi 20 x 40 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 5.70 m3 A.4.1.1.10 1,070,159.24 6,095,627.04
b. Pembesian 1,572.64 kg HITUNG BT1 15,332.90 24,113,070.52

- RAB - 73
Volume Nomer
No. Uraian Pekerjaan Harga Satuan Jumlah
m' m2 m3 Analis

c. Begesting 71.20 m2 HITUNG BT6 179,507.90 12,780,962.48


3 Balok B4 Dimensi 20 x 30 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 1.00 m3 A.4.1.1.10 1,070,159.24 1,065,878.60
b. Pembesian 249.19 kg HITUNG BT1 15,332.90 3,820,820.68
c. Begesting 13.04 m2 HITUNG BT6 179,507.90 2,340,783.02
4 Balok B6 Dimensi 25 x 60 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 7.60 m3 A.4.1.1.10 1,070,159.24 8,128,929.59
b. Pembesian 1,567.09 kg HITUNG BT1 15,332.90 24,028,095.59
c. Begesting 73.43 m2 HITUNG BT6 179,507.90 13,180,906.08
5 Balok B7 Dimensi 15 x 52 cm
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 25.27 m3 A.4.1.1.10 1,070,159.24 27,045,064.33
b. Pembesian 3,119.80 kg HITUNG BT1 15,332.90 47,835,544.93
c. Begesting 385.56 m2 HITUNG BT6 179,507.90 69,211,065.92
6 Plat Lantai Tribun
a. Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 34.34 m3 A.4.1.1.10 1,070,159.24 36,753,548.96
b. Pembesian 4,852.80 kg HITUNG BT1 15,332.90 74,407,478.48
c. Begesting 286.20 m2 HITUNG BT7 294,155.40 84,187,275.48
7 Concrete Pump 1.00 ls Survey 2,200,000.00 2,200,000.00

Jumlah V 2,459,654,476.37

VI PEKERJAAN BESI ALUMUNIUM


1 Pek. Pemasangan Pagar Pipa Besi Galvanis Medium 3" 70.80 m' HITUNG B5 876,289.79 62,041,317.25

Jumlah VI 62,041,317.25

VI PEKERJAAN SANITASI DAN PLUMBING


A PEKERJAAN SANITASI
1 Pek. Pasang Kran Air dinding Ex. Onda 12.00 Unit A.5.1.1.19 99,503.25 1,194,039.00

B PEKERJAAN PLUMBING
1 Pek. Pipa PVC Type AW 3/4" Air Bersih Ex. Wavin 85.00 m' HITUNG SN17 18,078.50 1,536,672.50
2 Pek. Pipa PVC Type AW 1" Air Bersih cair Ex. Wavin 54.00 m' HITUNG SN21 19,976.00 1,078,704.00
3 Pek. Pipa PVC Type AW 2" Air Bersih cair Ex. Wavin 15.00 m' HITUNG SN18 33,891.00 508,365.00
4 Pek. Pipa PVC Type AW 3" Air Kotor cair Ex. Wavin 124.00 m' HITUNG SN19 62,986.00 7,810,264.00
5 Pek. Pipa PVC Type AW 4" Air Kotor Padat Ex. Wavin 80.00 m' HITUNG SN20 97,141.00 7,771,280.00

Jumlah VI 19,899,324.50

VII PEKERJAAN MEKANIKAL DAN ELEKTRIKAL


A PEKERJAAN LISTRIK
1 Instalasi Titik Lampu kabel dalam conduit NYM 3x2,5 mm Ex. Eterna 100.00 Ttk HITUNG EL1 121,990.00 12,199,000.00
2 Instalasi Stop kontak kabel dalam conduit NYM 3x2,5 mm Ex. Eterna 22.00 Ttk HITUNG EL1 121,990.00 2,683,780.00
3 Instalasi Stop kontak AC kabel dalam conduit NYM 3x2,5 mm Ex. Eterna 20.00 Ttk HITUNG EL1 121,990.00 2,439,800.00

Jumlah VII 17,322,580.00

- RAB - 74
DAFTAR HARGA SATUAN PEKERJAAN
TAHUN 2020
PEKERJAAN : STIMULAN MENJAGA DUNIA EKONOMI DAERAH
AGAR TETAP BERJALAN MELALUI PEKERJAAN PEMBANGUNAN
TRIBUN VVIP STADION TAHAP I
LOKASI : KECAMATAN CEPOGO - KABUPATEN BOYOLALI
TAHUN ANGGARAN : 2020

HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
1 HITUNG PR1 Pagar Sementara dari Seng Gelombang Tinggi 2,40 m m' 246,793.29
2 HITUNG K3 Biaya K3 Unit 15,477,000.00

I A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


4 A.2.3.1.11 Urugan Pasir m3 261,910.00
5 HITUNG TA1 Galian tanah dengan menggunakan alat berat dan membuang di lokasi proyek m3 20,229.00
HITUNG TA8 Galian tanah pondasi dan footplat dengan alat berat dan membuang di lokasi proyek m3 22,266.86
6 HITUNG TA2 Mengurug Tanah Padat ( Bekas Galian Tanah ) m3 20,075.00
7 HITUNG TA5a Pemadatan Tanah menggunakan alat berat m3 22,988.13
10 HITUNG TA7 Membuang tanah bekas galian ke luar lokasi proyek sejauh 1 km m3 42,043.97

II A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


1 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 859,395.90

III A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


1 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP m2 119,042.44

IV A.4.5.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A.4.5.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 50,896.69
3 A.4.5.2.27 Pemasangan Acian m2 29,097.75

VI A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N


1 A.4.1.1.1 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87 m3 890,664.50
5 A.4.1.1.5 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 m3 976,572.06
10 A.4.1.1.10 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 m3 1,070,159.24
4 HITUNG BT1 Pembesian dg Besi Polos atau Besi Ulir kg 15,332.90
5 HITUNG BT3 Memasang Bekisting untuk Pondasi m2 115,821.20
6 HITUNG BT4 Memasang Bekisting untuk Sloof m2 123,068.00
7 HITUNG BT5 Memasang Bekisting untuk Kolom m2 161,444.80
8 HITUNG BT6 Memasang Bekisting untuk Balok m2 179,507.90
9 HITUNG BT7 Memasang Bekisting untuk Lantai m2 294,155.40
HITUNG BT9 Memasang Bekisting untuk Tangga m2 261,691.65

VIII A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


6 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾" bh 99,503.25
10 HITUNG SN17 Pemasangan Pipa PVC tipe AW Ø 3/4" m' 18,078.50
11 HITUNG SN21 Pemasangan Pipa PVC tipe AW Ø 1" m' 19,976.00
12 HITUNG SN18 Pemasangan Pipa PVC tipe AW Ø 2" m' 33,891.00
13 HITUNG SN19 Pemasangan Pipa PVC tipe AW Ø 3" m' 62,986.00
14 HITUNG SN20 Pemasangan Pipa PVC tipe AW Ø 4" m' 97,141.00

IX A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


HITUNG B5 Pemasangan Pagar Pipa Besi Galvanis Medium 3" m' 876,289.79

CK Boyolali
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)

XII HITUNG HARGA SATUAN ELEKTRIKAL


1 HITUNG EL1 Pek. Instalasi Listrik Kabel NYM 3x2,5 mm Ex. Eterna Ttk 121,990.00

CK Boyolali
DAFTAR UPAH PEKERJA
TAHUN 2020

PEKERJAAN : STIMULAN MENJAGA DUNIA EKONOMI DAERAH


AGAR TETAP BERJALAN MELALUI PEKERJAAN PEMBANGUNAN
TRIBUN VVIP STADION TAHAP I
LOKASI : KECAMATAN CEPOGO - KABUPATEN BOYOLALI
TAHUN ANGGARAN : 2020
WILAYAH : II (DUA)

HARGA
NO. JENIS BAHAN SATUAN KET.
(Rp)

1 Pekerja Hr 65,000
2 Mandor Hr 80,000
3 Tukang listrik Hr 80,000
4 Tukang kayu Hr 80,000
5 Kep. tk. kayu Hr 85,000
6 Tukang batu Hr 80,000
7 Kep. tk. batu Hr 85,000
8 Tukang besi Hr 80,000
9 Kep. tk. besi Hr 85,000
10 T u k a n g c a t Hr 80,000
11 K e p . t k . c a t Hr 85,000
12 T u k a n g p l i t u r Hr 80,000
13 T u k a n g j a l a n Hr 80,000
14 T u k a n g g a l i Hr 80,000
15 Tukang masak aspal Hr 80,000

CK Boyolali
DAFTAR HARGA SATUAN BAHAN BANGUNAN
TAHUN 2020

PEKERJAAN : STIMULAN MENJAGA DUNIA EKONOMI DAERAH


AGAR TETAP BERJALAN MELALUI PEKERJAAN PEMBANGUNAN
TRIBUN VVIP STADION TAHAP I
LOKASI : KECAMATAN CEPOGO - KABUPATEN BOYOLALI
TAHUN ANGGARAN : 2020
WILAYAH : II (DUA)

HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

I BAHAN DASAR
1 BATU BELAH
Batu Gunung Belah m3 272,000.00

2 KERIKIL
Beton 2 - 3 cm m3 287,000.00 Pecah Mesin
-
3 BATU BATA ex lokal bh 800.00
-
4 PASIR Urug m3 181,500.00
Pasang m3 264,000.00
Beton m3 266,000.00
-
5 PORTLAND CEMENT -
Portland Cement kg 1,170.00
-
II BAHAN PENUTUP ATAP -
SENG GELOMBANG ukuran 0,2x2,4x0,8 lbr 91,000.00
-
II BAHAN KAYU -
1 KRUING Balok/pesagen m3 6,367,000.00
-
2 SENGON Papan m3 3,294,000.00
Balok/pesagen m3 2,744,500.00
-
3 BAMBU Bambu Apus btg 15,500.00 Panjang 4 meter
-
IV B A H A N B E S I -
1 BESI
Besi beton polos / Ulir / Tulangan kg 12,000.00
3 KAWAT -
Kawat Ikat Beton / Bendrat kg 15,500.00
4 PAKU
Paku kg 15,000.00
-
V BAHAN PIPA -
1 Pipa PVC SII SCJ , S - 12,5 (10 bar) Ex Wavin -
Pipa PVC AW Wavin 3/4" m' 7,500.00
Pipa PVC AW Wavin 1" m' 9,000.00
Pipa PVC AW Wavin 2" m' 20,000.00
Pipa PVC AW Wavin 3" m' 43,000.00
Pipa PVC AW Wavin 4" m' 70,000.00

3 Pipa Galvanis Med. A 3" btg 1,189,000.00 panjang 6 m


-

CK Boyolali
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

VI B A H A N L A N G I T - L A N G I T -
2 PLY WOOD -
1200 x 2400 x 9 mm lbr 113,000.00

IX BAHAN INSTALASI LISTRIK -


KABEL NYM 3 x 2.5 mm m' 10,500.00

2 Klem Unit 350.00

8 Tee Dos bh 6,000.00


9 Pipa Clipsal m' 3,000.00
10 Sock Unit 350.00
-
XI BAHAN SANITAIR -
5 Kran Air Onda CLS 01 bh 54,000.00 3/4"
6 Seal tape bh 3,000.00
-
XII LAIN-LAIN -
1 Minyak Beton & bekisting ltr 5,800.00
2 Air Liter 23.00
-

XII Bahan K3
1 Helm Safety ASA Unit 88,500.00
2 Pelindung mata Unit 29,500.00
3 Tameng Muka Unit 88,500.00
4 Pelindung Telinga Unit 59,000.00
5 Masker Pelindung Pernafasan dan mulut Box 53,000.00
6 Sarung Tangan Psg 54,500.00
7 Sepatu Keselamatan Psg 319,000.00
8 Sepatu Keselamatan (rubber safety) Psg 171,000.00
9 Rompi keselamatan Unit 29,500.00
10 Pelindung Jatuh Unit 118,000.00

CK Boyolali
DAFTAR SEWA PERALATAN
TAHUN 2020

PEKERJAAN : STIMULAN MENJAGA DUNIA EKONOMI DAERAH


AGAR TETAP BERJALAN MELALUI PEKERJAAN PEMBANGUNAN
TRIBUN VVIP STADION TAHAP I
LOKASI : KECAMATAN CEPOGO - KABUPATEN BOYOLALI
TAHUN ANGGARAN : 2020
WILAYAH : II (DUA)

HARGA
NO. PERALATAN SATUAN (Rp) KET.

1 Dump Truck 6 - 8 m3 Jam 344,000.00


2 Excavator 80-140 Hp Jam 392,500.00
3 Bulldozer 100-150 Hp Jam 595,500.00
4 Vibratory Roller 5-8 T. Jam 327,000.00
5 Water Tanker 3000-4500 L. Jam 196,500.00
6 Motor Grader >100 Hp Jam 550,000.00
7 Wheel Loader 1.0-1.6 M3 Jam 427,000.00
8 Three Wheel Roller 6-8 T Jam 168,000.00
9 Asphalt Mixing Plant ( AMP ) Jam 6,581,000.00
10 Asphalt Finisher Jam 835,000.00
11 Asphalt Distributor Jam 348,500.00
12 Compresor 4000-6500 L/M Jam 142,500.00
13 Tandem Roller 6-8 T. Jam 331,500.00
14 Tyre Roller 8-10 T. Jam 419,500.00
15 Generator Set Jam 268,500.00
16 Tripod tinggi 5 m hari 49,500.00
17 Pile Driver Hammer (3.5-5.0) ton; 300 HP Jam 141,000.00
18 Crane On Track (10-15) Ton; 260 HP Jam 188,000.00
19 Welding Set Jam 36,000.00
20 Stamper Jam 38,000.00
1 HITUNG TP1 1.000 m Penyediaan Tiang Pancang Beton Bertulang Pracetak Ukuran 40 x 40 cm 417,246.40
A Tenaga 171,200.00
L.01 - OH Pekerja 65,000.00 -
L.02 1.430 OH Tukang 80,000.00 114,400.00
L.03 - OH Kepala Tukang 85,000.00 -
L.04 0.710 OH Mandor 80,000.00 56,800.00
B Bahan 180,000.00
1.000 m Tiang Pancang 40x40 cm 180,000.00 180,000.00
C PERALATAN 28,114.91
0.020 Jam Crane 1 Kapasitas 35 Ton 277,116.00 5,542.32
0.050 Jam Trailer 20 ton; 320 HP 340,605.39 17,030.27
0.020 Jam Crane 2 Kapasitas 35 Ton 277,116.00 5,542.32
D Jumlah A + B + C 379,314.91
E Overhead & Profit 10% 37,931.49
F Harga Satuan Pekerjaan (D+E) 417,246.40

2 HITUNG TP2 1.000 m Pemancangan Tiang Pancang Beton Bertulang Pracetak Ukuran 40 x 40 cm 161,535.00
A Tenaga 65,250.00
L.01 0.770 OH Pekerja 65,000.00 50,050.00
L.02 - OH Tukang 80,000.00 -
L.03 - OH Kepala Tukang 85,000.00 -
L.04 0.190 OH Mandor 80,000.00 15,200.00
B Bahan -
-
C PERALATAN 81,600.00
1.000 m Injack Hydraulic Kapasitas 120 Ton 70,000.00 70,000.00
1.000 m Handling Kapasitas 35 Ton 8,000.00 8,000.00
0.100 Jam Welding Set 36,000.00 3,600.00
D Jumlah A + B + C 146,850.00
E Overhead & Profit 10% 14,685.00
F Harga Satuan Pekerjaan (D+E) 161,535.00
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp

I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

1 HITUNG PR1 1.000 m' Pagar Sementara dari Seng Gelombang Tinggi 2,40 m 246,793.29
A TENAGA 21,900.00
L.01 0.300 OH Pekerja 65,000.00 19,500.00
L.04 0.030 OH Mandor 80,000.00 2,400.00
B BAHAN 202,457.53
1.333 Lbr Seng Gelombang 0,2.2,4.0,8 m 91,000.00 121,333.33
0.013 m3 Kayu 5/7X4m Kayu Kruing 6,367,000.00 80,224.20
0.060 Kg Paku Biasa 2" - 5" 15,000.00 900.00
C PERALATAN
D Jumlah A + B + C 224,357.53
E Overhead & Profit 10% 22,435.75
F Harga Satuan Pekerjaan (D+E) 246,793.29

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
HARGA SATUAN BIAYA K3
1 HITUNG K3 1.000 Unit Biaya K3 15,477,000.00
A Tenaga -
B Bahan 14,070,000.00
20.000 Unit Helm Safety ASA 88,500.00 1,770,000.00
10.000 Unit Pelindung mata 29,500.00 295,000.00
10.000 Unit Tameng Muka 88,500.00 885,000.00
10.000 Unit Pelindung Telinga 59,000.00 590,000.00
20.000 Box Masker Pelindung Pernafasan dan mulut 53,000.00 1,060,000.00
20.000 Psg Sarung Tangan 54,500.00 1,090,000.00
10.000 Psg Sepatu Keselamatan 319,000.00 3,190,000.00
20.000 Psg Sepatu Keselamatan (rubber safety) 171,000.00 3,420,000.00
20.000 Unit Rompi keselamatan 29,500.00 590,000.00
10.000 Unit Pelindung Jatuh 118,000.00 1,180,000.00
C PERALATAN -
D Jumlah A + B + C 14,070,000.00
E Overhead & Profit 10% 1,407,000.00
F Harga Satuan Pekerjaan (D+E) 15,477,000.00

CK Boyolali
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

I A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


3 A.2.3.1.11 1.000 m3 Urugan Pasir 261,910.00
A TENAGA 20,300.00
L.01 0.300 OH Pekerja 65,000.00 19,500.00
L.04 0.010 OH Mandor 80,000.00 800.00
B BAHAN 217,800.00
1.200 m3 Pasir Urug 181,500.00 217,800.00
C PERALATAN
D Jumlah A + B + C 238,100.00
E Overhead & Profit 10% 23,810.00
F Harga Satuan Pekerjaan (D+E) 261,910.00

4 HITUNG TA1 1.000 m3 Galian tanah dengan menggunakan alat berat dan membuang di lokasi proyek 20,229.00
A TENAGA 5,045.00
L.01 0.069 OH Pekerja 65,000.00 4,485.00
L.02 0.007 OH Mandor 80,000.00 560.00
B BAHAN -
C PERALATAN 13,345.00
0.034 jam Excavator 392,500.00 13,345.00
D Jumlah A + B + C 18,390.00
E Overhead & Profit 10% 1,839.00
F Harga Satuan Pekerjaan (D+E) 20,229.00

HITUNG TA8 1.000 m3 Galian tanah pondasi dan footplat dengan alat berat dan membuang di lokasi proyek 22,266.86
A TENAGA 5,045.00
L.01 0.069 OH Pekerja 65,000.00 4,485.00
L.02 0.007 OH Mandor 80,000.00 560.00
B BAHAN -
C PERALATAN 15,197.60
0.039 jam Excavator 392,500.00 15,197.60
D Jumlah A + B + C 20,242.60
E Overhead & Profit 10% 2,024.26
F Harga Satuan Pekerjaan (D+E) 22,266.86

5 HITUNG TA2 1.000 m3 Mengurug Tanah Padat ( Bekas Galian Tanah ) 20,075.00
A TENAGA 18,250.00
L.01 0.250 OH Pekerja 65,000.00 16,250.00
L.04 0.025 OH Mandor 80,000.00 2,000.00
B BAHAN -

C PERALATAN
D Jumlah A + B + C 18,250.00
E Overhead & Profit 10% 1,825.00
F Harga Satuan Pekerjaan (D+E) 20,075.00

6 HITUNG TA5a 1.000 m3 Pemadatan Tanah menggunakan alat berat 22,988.13


A TENAGA 1,635.00
L.01 0.019 OH Pekerja 65,000.00 1,235.00
L.02 0.005 OH Mandor 80,000.00 400.00
B BAHAN -
C PERALATAN 19,263.30
0.020 jam Bulldozer 100-150 HP 595,500.00 11,910.00
0.018 jam Vibro Roller 327,000.00 5,820.60
0.008 jam Water Tank Truck 196,500.00 1,532.70
D Jumlah A + B + C 20,898.30
E Overhead & Profit 10% 2,089.83
F Harga Satuan Pekerjaan (D+E) 22,988.13

CK Boyolali
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

I A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


9 HITUNG TA7 1.000 m3 Membuang tanah bekas galian ke luar lokasi proyek sejauh 1 km 42,043.97
A TENAGA 767.07
L.01 0.007 OH Pekerja 65,000.00 474.50
L.02 0.004 OH Mandor 80,000.00 292.57
B BAHAN -
C PERALATAN 37,454.72
0.1089 jam Dumptruck 344,000.00 37,454.72
D Jumlah A + B + C 38,221.79
E Overhead & Profit 10% 3,822.18
F Harga Satuan Pekerjaan (D+E) 42,043.97

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

II A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


1 A.3.2.1.4 1.000 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP 859,395.90
A TENAGA 169,875.00
L.01 1.500 OH Pekerja 65,000.00 97,500.00
L.02 0.750 OH Tukang Batu 80,000.00 60,000.00
L.03 0.075 OH Kepala Tukang 85,000.00 6,375.00
L.04 0.075 OH Mandor 80,000.00 6,000.00
B BAHAN 611,394.00
1.200 m3 Batu Belah 15/20 272,000.00 326,400.00
117.000 Kg Portland Cement 1,170.00 136,890.00
0.561 m3 Pasir Pasang 264,000.00 148,104.00
C PERALATAN
D Jumlah A + B + C 781,269.00
E Overhead & Profit 10% 78,126.90
F Harga Satuan Pekerjaan (D+E) 859,395.90

CK Boyolali
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
III A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

1 A.4.4.1.11 1.000 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6P 119,042.44
A Tenaga 29,550.00
L.01 0.300 OH Pekerja 65,000.00 19,500.00
L.02 0.100 OH Tukang Batu 80,000.00 8,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.015 OH Mandor 80,000.00 1,200.00
B Bahan 78,670.40
70.000 Buah Bata Merah 5 x 11 x 22 800.00 56,000.00
8.320 Kg Portland Semen 1,170.00 9,734.40
0.049 m3 Pasir Pasang 264,000.00 12,936.00
C PERALATAN
D Jumlah A + B + C 108,220.40
E Overhead & Profit 10% 10,822.04
F Harga Satuan Pekerjaan (D+E) 119,042.44

CK Boyolali
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

IV A.4.5.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A.4.5.2.6 1.000 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 50,896.69
TENAGA 33,975.00
L.01 0.300 OH Pekerja 65,000.00 19,500.00
L.02 0.150 OH Tukang batu 80,000.00 12,000.00
L.03 0.015 OH Kepala Tukang 85,000.00 1,275.00
L.04 0.015 OH Mandor 80,000.00 1,200.00
BAHAN 12,294.72
4.416 Kg Portland Cement 1,170.00 5,166.72
0.027 m3 Pasir Pasang 264,000.00 7,128.00
C PERALATAN
D Jumlah A + B + C 46,269.72
E Overhead & Profit 10% 4,626.97
F Harga Satuan Pekerjaan (D+E) 50,896.69

3 A.4.5.2.27 1.000 m2 Pemasangan Acian 29,097.75


TENAGA 22,650.00
L.01 0.200 OH Pekerja 65,000.00 13,000.00
L.02 0.100 OH Tukang batu 80,000.00 8,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.010 OH Mandor 80,000.00 800.00
BAHAN 3,802.50
3.250 Kg Portland Cement 1,170.00 3,802.50
C PERALATAN
D Jumlah A + B + C 26,452.50
E Overhead & Profit 10% 2,645.25
F Harga Satuan Pekerjaan (D+E) 29,097.75

CK Boyolali
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
VI A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
1 A.4.1.1.1 1.000 m3 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87 890,664.50
A TENAGA 138,270.00
L.01 1.650 OH Pekerja 65,000.00 107,250.00
L.02 0.275 OH Tukang Batu 80,000.00 22,000.00
L.03 0.028 OH Kepala Tukang 85,000.00 2,380.00
L.04 0.083 OH Mandor 80,000.00 6,640.00
B BAHAN 671,425.00
247.000 Kg Portland Semen 1,170.00 288,990.00
869.000 Kg Pasir Beton 190.00 165,110.00
999.000 Kg Kerikil (maksimum 30 mm) 212.59 212,380.00
215.000 ltr Air 23.00 4,945.00
C PERALATAN
D Jumlah A + B + C 809,695.00
E Overhead & Profit 10% 80,969.50
F Harga Satuan Pekerjaan (D+E) 890,664.50

5 A.4.1.1.5 1.000 m3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 976,572.06
A TENAGA 138,270.00
L.01 1.650 OH Pekerja 65,000.00 107,250.00
L.02 0.275 OH Tukang Batu 80,000.00 22,000.00
L.03 0.028 OH Kepala Tukang 85,000.00 2,380.00
L.04 0.083 OH Mandor 80,000.00 6,640.00
B BAHAN 749,522.78
326.000 Kg Portland Semen 1,170.00 381,420.00
760.000 Kg Pasir Beton 190.00 144,400.00
1,029.000 Kg Kerikil (maksimum 30 mm) 212.59 218,757.78
215.000 ltr Air 23.00 4,945.00
C PERALATAN
D Jumlah A + B + C 887,792.78
E Overhead & Profit 10% 88,779.28
F Harga Satuan Pekerjaan (D+E) 976,572.06

10 A.4.1.1.10 1.000 m3 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 1,070,159.24
A Tenaga 138,270.00
L.01 1.650 OH Pekerja 65,000.00 107,250.00
L.02 0.275 OH Tukang Batu 80,000.00 22,000.00
L.03 0.028 OH Kepala Tukang 85,000.00 2,380.00
L.04 0.083 OH Mandor 80,000.00 6,640.00
B Bahan 834,602.04
413.000 Kg Portland Semen 1,170.00 483,210.00
681.000 Kg Pasir Beton 190.00 129,390.00
1,021.000 Kg Kerikil (maksimum 30 mm) 212.59 217,057.04
215.000 ltr Air 23.00 4,945.00
C PERALATAN
D Jumlah A + B + C 972,872.04
E Overhead & Profit 10% 97,287.20
F Harga Satuan Pekerjaan (D+E) 1,070,159.24

3 HITUNG BT1 1.000 Kg Pembesian dg Besi Polos atau Besi Ulir 15,332.90
A TENAGA 1,106.50
L.01 0.007 OH Pekerja 65,000.00 455.00
L.02 0.007 OH Tukang Besi 80,000.00 560.00
L.03 0.001 OH Kepala Tukang 85,000.00 59.50
L.04 0.000 OH Mandor 80,000.00 32.00
B BAHAN 12,832.50
1.050 Kg Besi Beton (polos/ulir) 12,000.00 12,600.00
0.015 Kg Kawat Beton 15,500.00 232.50
C PERALATAN
D Jumlah A + B + C 13,939.00
E Overhead & Profit 10% 1,393.90
F Harga Satuan Pekerjaan (D+E) 15,332.90

CK Boyolali
4 HITUNG BT3 1.000 m2 Memasang Bekisting untuk Pondasi 115,821.20
A TENAGA 58,890.00
L.01 0.520 OH Pekerja 65,000.00 33,800.00
L.02 0.260 OH Tukang Kayu 80,000.00 20,800.00
L.03 0.026 OH Kepala Tukang 85,000.00 2,210.00
L.04 0.026 OH Mandor 80,000.00 2,080.00
B BAHAN 46,402.00
0.013 m3 Kayu Klas III 3,294,000.00 42,822.00
0.200 Kg Paku Biasa 2" - 5" 15,000.00 3,000.00
0.100 Ltr Minyak Bekisting 5,800.00 580.00
C PERALATAN
D Jumlah A + B + C 105,292.00
E Overhead & Profit 10% 10,529.20
F Harga Satuan Pekerjaan (D+E) 115,821.20

5 HITUNG BT4 1.000 m2 Memasang Bekisting untuk Sloof 123,068.00


A TENAGA 58,890.00
L.01 0.520 OH Pekerja 65,000.00 33,800.00
L.02 0.260 OH Tukang Kayu 80,000.00 20,800.00
L.03 0.026 OH Kepala Tukang 85,000.00 2,210.00
L.04 0.026 OH Mandor 80,000.00 2,080.00
B BAHAN 52,990.00
0.015 m3 Papan Kayu Klas III 3,294,000.00 49,410.00
0.200 Kg Paku Biasa 2" - 5" 15,000.00 3,000.00
0.100 Ltr Minyak Bekisting 5,800.00 580.00
C PERALATAN
D Jumlah A + B + C 111,880.00
E Overhead & Profit 10% 11,188.00
F Harga Satuan Pekerjaan (D+E) 123,068.00

6 HITUNG BT5 1.000 m2 Memasang Bekisting untuk Kolom 161,444.80


A TENAGA 74,745.00
L.01 0.660 OH Pekerja 65,000.00 42,900.00
L.02 0.330 OH Tukang Kayu 80,000.00 26,400.00
L.03 0.033 OH Kepala Tukang 85,000.00 2,805.00
L.04 0.033 OH Mandor 80,000.00 2,640.00
B BAHAN 72,023.00
0.010 m3 Papan Kayu Klas III (Sengon) 3,294,000.00 32,940.00
0.200 Kg Paku Biasa 2" - 5" 15,000.00 3,000.00
0.200 Ltr Minyak Bekisting 5,800.00 1,160.00
0.004 m3 Balok Kayu Klas III 2,744,500.00 10,978.00
0.120 Lbr Plywood tebal 9mm 113,000.00 13,560.00
0.670 Btg Bambu 8 - 10 cm x 4 m 15,500.00 10,385.00
C PERALATAN
D Jumlah A + B + C 146,768.00
E Memasang Bekisting untuk Kolom 10% 14,676.80
F Harga Satuan Pekerjaan (D+E) 161,444.80

7 HITUNG BT6 1.000 m2 Memasang Bekisting untuk Balok 179,507.90


A Tenaga 74,745.00
L.01 0.660 OH Pekerja 65,000.00 42,900.00
L.02 0.330 OH Tukang Kayu 80,000.00 26,400.00
L.03 0.033 OH Kepala Tukang 85,000.00 2,805.00
L.04 0.033 OH Mandor 80,000.00 2,640.00
B BAHAN 88,444.00
0.013 m3 Papan Kayu Klas III 3,294,000.00 42,822.00
0.270 Kg Paku Biasa 2" - 5" 15,000.00 4,050.00
0.200 Ltr Minyak Bekisting 5,800.00 1,160.00
0.006 m3 Balok Kayu Klas III 2,744,500.00 16,467.00
0.120 Lbr Plywood tebal 9mm 113,000.00 13,560.00
0.670 Btg Bambu 8 - 10 cm x 4 m 15,500.00 10,385.00
C PERALATAN
D Jumlah A + B + C 163,189.00
E Memasang Bekisting untuk Kolom 10% 16,318.90
F Harga Satuan Pekerjaan (D+E) 179,507.90

CK Boyolali
8 HITUNG BT7 1.000 m2 Memasang Bekisting untuk Lantai 294,155.40
A TENAGA 74,745.00
L.01 0.660 OH Pekerja 65,000.00 42,900.00
L.02 0.330 OH Tukang Kayu 80,000.00 26,400.00
L.03 0.033 OH Kepala Tukang 85,000.00 2,805.00
L.04 0.033 OH Mandor 80,000.00 2,640.00
B BAHAN 192,669.00
0.020 m3 Kayu Klas III (Terentang) 2,744,500.00 54,890.00
0.400 Kg Paku Biasa 2" - 5" 15,000.00 6,000.00
0.200 Ltr Minyak Bekisting 5,800.00 1,160.00
0.007 m3 Balok Kayu Klas II (Borneo) 6,367,000.00 44,569.00
0.350 Lbr Plywood tebal 9mm 113,000.00 39,550.00
3.000 Btg Bambu 8 - 10 cm x 4 m 15,500.00 46,500.00
C PERALATAN
D Jumlah A + B + C 267,414.00
E Memasang Bekisting untuk Kolom 10% 26,741.40
F Harga Satuan Pekerjaan (D+E) 294,155.40

22 HITUNG BT9 1.000 m2 Memasang Bekisting untuk Tangga 261,691.65


A Tenaga 74,745.00
L.01 0.660 OH Pekerja 65,000.00 42,900.00
L.02 0.330 OH Tukang Kayu 80,000.00 26,400.00
L.03 0.033 OH Kepala Tukang 85,000.00 2,805.00
L.04 0.033 OH Mandor 80,000.00 2,640.00
B Bahan 163,156.50
0.015 m3 Kayu Klas III (Terentang) 2,744,500.00 41,167.50
0.400 Kg Paku Biasa 2" - 5" 15,000.00 6,000.00
0.150 Ltr Minyak Bekisting 5,800.00 870.00
0.007 m3 Minyak Bekisting 6,367,000.00 44,569.00
0.350 Lbr Plywood tebal 9mm 113,000.00 39,550.00
2.000 Btg Bambu 8 - 10 cm x 4 m 15,500.00 31,000.00
C PERALATAN
D PERALATAN 237,901.50
E Jumlah A + B + C 10% 23,790.15
F Harga Satuan Pekerjaan (D+E) 261,691.65

CK Boyolali
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

VII A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT


1 HITUNG PF1 1.000 m2 Memasang Langit-langit Gypsum Board tebal 9 mm + Rangka Hollow Galvanis 191,453.68
A Tenaga 39,415.00
L.01 0.250 OH Pekerja 65,000.00 16,250.00
L.02 0.250 OH Tukang Besi 80,000.00 20,000.00
L.03 0.025 OH Kepala Tukang 85,000.00 2,125.00
L.04 0.013 OH Mandor 80,000.00 1,040.00
B Bahan 134,633.80
0.364 Lbr Gypsum Board 97,800.00 35,599.20
1.580 m' Besi Hollow 40 x 40 x 3.5 mm 32,500.00 51,350.00
0.700 m' Besi Hollow 20 x 40 x 3.5 mm 6,900.00 4,830.00
0.310 kg Compound 2,800.00 868.00
3.500 bh Dinabolt 1,800.00 6,300.00
1.38 m' Cotton Plaster 320.00 441.60
39.750 Buah Sekrup 180.00 7,155.00
0.500 Perkuatan dan Penggantung (50% x rangka) 56,180.00 28,090.00
C PERALATAN
D Jumlah A + B + C 174,048.80
E Overhead & Profit 10% 17,404.88
F Harga Satuan Pekerjaan (D+E) 191,453.68

2 HITUNG PF2 1.000 m2 Memasang Langit-langit GRC Board tebal 4 mm + Rangka Hollow Galvanis 179,922.16
A Tenaga 39,415.00
L.01 0.250 OH Pekerja 65,000.00 16,250.00
L.02 0.250 OH Tukang Besi 80,000.00 20,000.00
L.03 0.025 OH Kepala Tukang 85,000.00 2,125.00
L.04 0.013 OH Mandor 80,000.00 1,040.00
B Bahan 124,150.60
0.364 Lbr GRC Board 120 x240 x 0.4 cm 69,000.00 25,116.00
1.580 m' Besi Hollow 40 x 40 x 3.5 mm 32,500.00 51,350.00
0.700 m' Besi Hollow 20 x 40 x 3.5 mm 6,900.00 4,830.00
0.310 zak Compoun 2,800.00 868.00
3.500 bh Dinabolt 1,800.00 6,300.00
1.38 m' Cotton Plaster 320.00 441.60
39.750 Buah Sekrup 180.00 7,155.00
0.500 Perkuatan dan Penggantung (50% x rangka) 56,180.00 28,090.00
C PERALATAN
D Jumlah A + B + C 163,565.60
E Overhead & Profit 10% 16,356.56
F Harga Satuan Pekerjaan (D+E) 179,922.16

3 HITUNG PF5 1.000 m2 Memasang ACP ( Alumunium Composite Panel ) merk Seven 992,750.00
A Tenaga 181,750.00
L.01 1.250 OH Pekerja 65,000.00 81,250.00
L.02 1.100 OH Tukang 80,000.00 88,000.00
L.03 0.100 OH Kepala Tukang 85,000.00 8,500.00
L.04 0.050 OH Mandor 80,000.00 4,000.00
B Bahan 720,750.00
1.100 m2 ACP merk Seven 315,000.00 346,500.00
1.100 m2 Rangka besi hollow + bracing 240,000.00 264,000.00
0.350 Perlengkapan 25 % 315,000.00 110,250.00
C PERALATAN
D Jumlah A + B + C 902,500.00
E Overhead & Profit 10% 90,250.00
F Harga Satuan Pekerjaan (D+E) 992,750.00

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

VIII A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


5 A.5.1.1.19 1.000 bh Pemasangan Kran Ø ½" atau Ø ¾" 99,503.25
A Tenaga 36,450.00
L.01 0.010 OH Pekerja 65,000.00 650.00
L.02 0.400 OH Tukang Batu 80,000.00 32,000.00
L.03 0.040 OH Kepala Tukang 85,000.00 3,400.00
L.04 0.005 OH Mandor 80,000.00 400.00
B Bahan 54,007.50
1.000 bh Kran Air 54,000.00 54,000.00
0.003 bh Sealtape 3,000.00 7.50
C PERALATAN
D Jumlah A + B + C 90,457.50
E Overhead & Profit 10% 9,045.75
F Harga Satuan Pekerjaan (D+E) 99,503.25

11 HITUNG SN17 1.000 m' Pemasangan Pipa PVC tipe AW Ø 3/4" 18,078.50
A Tenaga 7,810.00
L.01 0.036 OH Pekerja 65,000.00 2,340.00
L.02 0.060 OH Tukang Batu 80,000.00 4,800.00
L.03 0.006 OH Kepala Tukang 85,000.00 510.00
L.04 0.002 OH Mandor 80,000.00 160.00
B Bahan 8,625.00
1.050 m' Pipa PVC Ø ¾" 7,500.00 7,875.00
0.100 Ls Perlengkapan 10% x pipa 7,500.00 750.00
C PERALATAN
D PERALATAN 16,435.00
E Jumlah A + B + C 10% 1,643.50
F Harga Satuan Pekerjaan (D+E) 18,078.50

12 HITUNG SN21 1.000 m' Pemasangan Pipa PVC tipe AW Ø 1" 19,976.00
A Tenaga 7,810.00
L.01 0.036 OH Pekerja 65,000.00 2,340.00
L.02 0.060 OH Tukang Batu 80,000.00 4,800.00
L.03 0.006 OH Kepala Tukang 85,000.00 510.00
L.04 0.002 OH Mandor 80,000.00 160.00
B Bahan 10,350.00
1.050 m' Pipa PVC Ø 1" 9,000.00 9,450.00
0.100 Ls Perlengkapan 10% x pipa 9,000.00 900.00
C PERALATAN
D PERALATAN 18,160.00
E Jumlah A + B + C 10% 1,816.00
F Harga Satuan Pekerjaan (D+E) 19,976.00

13 HITUNG SN18 1.000 m' Pemasangan Pipa PVC tipe AW Ø 2" 33,891.00
A Tenaga 7,810.00
L.01 0.036 OH Pekerja 65,000.00 2,340.00
L.02 0.060 OH Tukang Batu 80,000.00 4,800.00
L.03 0.006 OH Kepala Tukang 85,000.00 510.00
L.04 0.002 OH Mandor 80,000.00 160.00
B Bahan 23,000.00
1.050 m' Pipa PVC Ø 2" 20,000.00 21,000.00
0.100 Ls Perlengkapan 10% x pipa 20,000.00 2,000.00
C PERALATAN
D PERALATAN 30,810.00
E Jumlah A + B + C 10% 3,081.00
F Harga Satuan Pekerjaan (D+E) 33,891.00

CK Boyolali
14 HITUNG SN19 1.000 m' Pemasangan Pipa PVC tipe AW Ø 3" 62,986.00
A Tenaga 7,810.00
L.01 0.036 OH Pekerja 65,000.00 2,340.00
L.02 0.060 OH Tukang Batu 80,000.00 4,800.00
L.03 0.006 OH Kepala Tukang 85,000.00 510.00
L.04 0.002 OH Mandor 80,000.00 160.00
B Bahan 49,450.00
1.050 m' Pipa PVC Ø 3" 43,000.00 45,150.00
0.100 Ls Perlengkapan 10% x pipa 43,000.00 4,300.00
C PERALATAN
D PERALATAN 57,260.00
E Jumlah A + B + C 10% 5,726.00
F Harga Satuan Pekerjaan (D+E) 62,986.00

15 HITUNG SN20 1.000 m' Pemasangan Pipa PVC tipe AW Ø 4" 97,141.00
A Tenaga 7,810.00
L.01 0.036 OH Pekerja 65,000.00 2,340.00
L.02 0.060 OH Tukang Batu 80,000.00 4,800.00
L.03 0.006 OH Kepala Tukang 85,000.00 510.00
L.04 0.002 OH Mandor 80,000.00 160.00
B Bahan 80,500.00
1.050 m' Pipa PVC Ø 4" 70,000.00 73,500.00
0.100 Ls Perlengkapan 10% x pipa 70,000.00 7,000.00
C PERALATAN
D PERALATAN 88,310.00
E Jumlah A + B + C 10% 8,831.00
F Harga Satuan Pekerjaan (D+E) 97,141.00

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
HARGA SATUAN PEKERJAAN SALURAN U-DITCH
HITUNG DR5 1.000 m' Pekerjaan Saluran U-Ditch 400x500x1200 606,145.10
A 94,585.00
L.01 0.870 OH Pekerja 65,000.00 56,550.00
L.02 0.390 OH Tukang Batu 80,000.00 31,200.00
L.03 0.039 OH Kepala Tukang 85,000.00 3,315.00
L.04 0.044 OH Mandor 80,000.00 3,520.00
B Bahan 456,456.00
0.88 Buah U-Ditch 400x500x1200 Type HD 518,700.00 456,456.00
C PERALATAN -
D Jumlah A + B + C 551,041.00
E Overhead & Profit 10% 55,104.10
F Harga Satuan Pekerjaan (D+E) 606,145.10

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
IX A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM
1 A.4.2.1.1 1.000 Kg Pemasangan Besi Profil 33,345.40
A Tenaga 9,450.00
L.01 0.060 OH Pekerja 65,000.00 3,900.00
L.02 0.060 OH Tukang Besi 80,000.00 4,800.00
L.03 0.006 OH Kepala Tukang 85,000.00 510.00
L.04 0.003 OH Mandor 80,000.00 240.00
B Bahan 20,864.00
1.150 Kg Besi Profil 15,800.00 18,170.00
0.060 Kg Meni Besi 44,900.00 2,694.00
C PERALATAN
D Jumlah A + B + C 30,314.00
E Overhead & Profit 10% 3,031.40
F Harga Satuan Pekerjaan (D+E) 33,345.40

2 HITUNG AL12 1.000 m1 Pemasangan Handrail Tangga dan Tiang Bahan Stainless Steel 1,306,588.25
A TENAGA 167,500.00
L.01 0.500 OH Pekerja 65,000.00 32,500.00
L.02 1.000 OH Tukang Khusus 80,000.00 80,000.00
L.03 0.333 OH Kepala Tukang 85,000.00 28,333.33
L.04 0.333 OH Mandor 80,000.00 26,666.67
B BAHAN 1,020,307.50
2.182 m' Pipa Stainless Steel 2 inch 148,000.00 322,996.80
2.200 m' Pipa Stainless Steel 1 inch 120,000.00 264,000.00
4.514 m' Pipa Stainless Steel 3/4 inch 96,000.00 433,310.70
C PERALATAN
D Jumlah A + B + C 1,187,807.50
E Overhead & Profit 10% 118,780.75
F Harga Satuan Pekerjaan (D+E) 1,306,588.25

3 HITUNG AL13 1.000 m1 Pemasangan Handrail Tangga Bahan Stainless Steel 228,244.14
A TENAGA 29,894.68
L.01 0.300 OH Pekerja 65,000.00 19,500.00
L.02 0.112 OH Tukang Khusus 80,000.00 8,999.04
L.03 0.011 OH Kepala Tukang 85,000.00 956.15
L.04 0.005 OH Mandor 80,000.00 439.49
B BAHAN 177,600.00
1.200 m' Pipa Stainless Steel 2 inch 148,000.00 177,600.00
- m' Pipa Stainless Steel 1 inch 120,000.00 -
- m' Pipa Stainless Steel 3/4 inch 96,000.00 -
C PERALATAN
D Jumlah A + B + C 207,494.68
E Overhead & Profit 10% 20,749.47
F Harga Satuan Pekerjaan (D+E) 228,244.14

4 HITUNG BP1 1.000 Kg Pemasangan Besi Profil 35,952.40


A Tenaga 9,450.00
L.01 0.060 OH Pekerja 65,000.00 3,900.00
L.02 0.060 OH Tukang Besi 80,000.00 4,800.00
L.03 0.006 OH Kepala Tukang 85,000.00 510.00
L.04 0.003 OH Mandor 80,000.00 240.00
B Bahan 23,234.00
1.300 Kg Besi Profil 15,800.00 20,540.00
0.060 Kg Meni Besi 44,900.00 2,694.00
C PERALATAN
D Jumlah A + B + C 32,684.00
E Overhead & Profit 10% 3,268.40
F Harga Satuan Pekerjaan (D+E) 35,952.40

5 HITUNG BS01 1.000 m' Pemasangan Pagar Pipa Besi Med. 3" 875,744.83
A TENAGA 80,750.00
L.01 0.500 OH Pekerja 65,000.00 32,500.00
L.02 0.500 OH Tukang Khusus 80,000.00 40,000.00
L.03 0.050 OH Kepala Tukang 85,000.00 4,250.00
L.04 0.050 OH Mandor 80,000.00 4,000.00
B BAHAN 715,381.67
3.410 m' Pipa Besi Med. 3" 198,166.67 675,748.33

CK Boyolali
0.100 Bahan Las (10%) 198,166.67 19,816.67
0.100 Asesoris (10%) 198,166.67 19,816.67
C PERALATAN
D Jumlah A + B + C 796,131.67
E Overhead & Profit 10% 79,613.17
F Harga Satuan Pekerjaan (D+E) 875,744.83

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM
1 HITUNG B1 1.000 bh Pemasangan Plat Plendes t = 20 mm 1,591,580.83
A Tenaga 22,116.67
L.01 0.083 OH Pekerja 65,000.00 5,416.67
L.02 0.167 OH Tukang Besi 80,000.00 13,333.33
L.03 0.033 OH Kepala Tukang 85,000.00 2,833.33
L.04 0.007 OH Mandor 80,000.00 533.33
B Bahan 1,424,775.00
86.350 Kg Plat Baja t = 20 mm 16,500.00 1,424,775.00
C PERALATAN -
D Jumlah A + B + C 1,446,891.67
E Overhead & Profit 10% 144,689.17
F Harga Satuan Pekerjaan (D+E) 1,591,580.83

CK Boyolali
HARGA BAHAN/UPAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp
HARGA SATUAN PEKERJAAN PINTU DAN JENDELA ALUMUNIUM
1 HITUNG P1 1.000 Unit Pemasangan Pintu Rangka Alumunium ( P1 ) 5,527,429.68
A TENAGA 255,375.87
L.01 1.060 OH Pekerja 65,000.00 68,890.90
L.02 2.060 OH Tukang Besi 80,000.00 164,788.80
L.03 0.206 OH Kepala Tukang 85,000.00 17,508.81
L.04 0.052 OH Mandor 80,000.00 4,187.36
B BAHAN 4,769,560.20
13.020 m' Kusen Alm Coating White 4" Tbl 1 mm Ex. Alexindo 90,000.00 1,171,800.00
11.340 m' Daun Pintu Frame Alumunium Ex. Alexindo 90,000.00 1,020,600.00
- m' Daun Jendela Frame Alumunium 90,000.00 -
3.024 m2 Kaca Bening 5 mm 120,800.00 365,299.20
1.092 m2 Stiker sandblas 150,000.00 163,800.00
2.000 set Handle Pintu Ex. Dekson 602,400.00 1,204,800.00
6.000 Bh Engsel Pintu 4" Ex. Dekson 30,000.00 180,000.00
2.000 unit Door Closer Ex. Dekson DCL 300 Serie NHO 318,000.00 636,000.00
- Set Cesement 12" 120,000.00 -
- Bh Rambuncis 67,800.00 -
26.000 buah Skrup Fixer 72.00 1,872.00
0.781 Tube Sealant Kusen 32,500.00 25,389.00
C PERALATAN
D Jumlah A + B + C 5,024,936.07
E Overhead & Profit 10% 502,493.61
F Harga Satuan Pekerjaan (D+E) 5,527,429.68

2 HITUNG P2 1.000 Unit Pemasangan Pintu Rangka Alumunium ( P2 ) 3,469,191.18


A TENAGA 236,897.87
L.01 0.942 OH Pekerja 65,000.00 61,260.55
L.02 1.942 OH Tukang Besi 80,000.00 155,397.60
L.03 0.194 OH Kepala Tukang 85,000.00 16,511.00
L.04 0.047 OH Mandor 80,000.00 3,728.72
B BAHAN 2,916,912.30
10.290 m' Kusen Alm Coating White 4" Tbl 1 mm Ex. Alexindo 90,000.00 926,100.00
6.615 m' Daun Pintu Frame Alumunium Ex. Alexindo 90,000.00 595,350.00
- m' Daun Jendela Frame Alumunium 90,000.00 -
2.331 m2 Kaca Bening 5 mm 120,800.00 281,584.80
0.546 m2 Stiker sandblas 150,000.00 81,900.00
1.000 set Handle Pintu Ex. Dekson 602,400.00 602,400.00
3.000 Bh Engsel Pintu 4" Ex. Dekson 30,000.00 90,000.00
1.000 unit Door Closer Ex. Dekson DCL 300 Serie NHO 318,000.00 318,000.00
- Set Cesement 12" 120,000.00 -
- Bh Rambuncis 67,800.00 -
21.000 buah Skrup Fixer 72.00 1,512.00
0.617 Tube Sealant Kusen 32,500.00 20,065.50
C PERALATAN
D Jumlah A + B + C 3,153,810.17
E Overhead & Profit 10% 315,381.02
F Harga Satuan Pekerjaan (D+E) 3,469,191.18

3 HITUNG P3 1.000 Unit Pemasangan Pintu Rangka Alumunium ( P3 ) 4,868,203.25


A TENAGA 222,684.02
L.01 0.852 OH Pekerja 65,000.00 55,391.05
L.02 1.852 OH Tukang Besi 80,000.00 148,173.60
L.03 0.185 OH Kepala Tukang 85,000.00 15,743.45
L.04 0.042 OH Mandor 80,000.00 3,375.92
B BAHAN 4,202,955.30
8.190 m' Kusen Alm Coating White 4" Tbl 1 mm Ex. Alexindo 90,000.00 737,100.00
11.340 m' Daun Pintu Frame Alumunium Ex. Alexindo 90,000.00 1,020,600.00
- m' Daun Jendela Frame Alumunium 90,000.00 -
2.016 m2 Kaca Bening 5 mm 120,800.00 243,532.80
1.092 m2 Stiker sandblas 150,000.00 163,800.00
2.000 set Handle Pintu Ex. Dekson 602,400.00 1,204,800.00
6.000 Bh Engsel Pintu 4" Ex. Dekson 30,000.00 180,000.00
2.000 unit Door Closer Ex. Dekson DCL 300 Serie NHO 318,000.00 636,000.00
- Set Cesement 12" 120,000.00 -
- Bh Rambuncis 67,800.00 -
16.000 buah Skrup Fixer 72.00 1,152.00
0.491 Tube Sealant Kusen 32,500.00 15,970.50
C PERALATAN
D Jumlah A + B + C 4,425,639.32
E Overhead & Profit 10% 442,563.93
F Harga Satuan Pekerjaan (D+E) 4,868,203.25
4 HITUNG P4 1.000 Unit Pemasangan Pintu Rangka Alumunium ( P4 ) 2,809,964.75
A TENAGA 204,206.01
L.01 0.735 OH Pekerja 65,000.00 47,760.70
L.02 1.735 OH Tukang Besi 80,000.00 138,782.40
L.03 0.173 OH Kepala Tukang 85,000.00 14,745.63
L.04 0.036 OH Mandor 80,000.00 2,917.28
B BAHAN 2,350,307.40
5.460 m' Kusen Alm Coating White 4" Tbl 1 mm Ex. Alexindo 90,000.00 491,400.00
6.615 m' Daun Pintu Frame Alumunium Ex. Alexindo 90,000.00 595,350.00
- m' Daun Jendela Frame Alumunium 90,000.00 -
1.323 m2 Kaca Bening 5 mm 120,800.00 159,818.40
0.546 m2 Stiker sandblas 150,000.00 81,900.00
1.000 set Handle Pintu Ex. Dekson 602,400.00 602,400.00
3.000 Bh Engsel Pintu 4" Ex. Dekson 30,000.00 90,000.00
1.000 unit Door Closer Ex. Dekson DCL 300 Serie NHO 318,000.00 318,000.00
- Set Cesement 12" 120,000.00 -
- Bh Rambuncis 67,800.00 -
11.000 buah Skrup Fixer 72.00 792.00
0.328 Tube Sealant Kusen 32,500.00 10,647.00
C PERALATAN
D Jumlah A + B + C 2,554,513.41
E Overhead & Profit 10% 255,451.34
F Harga Satuan Pekerjaan (D+E) 2,809,964.75

5 HITUNG P5 1.000 Unit Pemasangan Pintu Rangka Alumunium ( P5 ) 4,538,669.23


A TENAGA 206,338.09
L.01 0.748 OH Pekerja 65,000.00 48,641.13
L.02 1.748 OH Tukang Besi 80,000.00 139,866.00
L.03 0.175 OH Kepala Tukang 85,000.00 14,860.76
L.04 0.037 OH Mandor 80,000.00 2,970.20
B BAHAN 3,919,724.85
5.775 m' Kusen Alm Coating White 4" Tbl 1 mm Ex. Alexindo 90,000.00 519,750.00
11.340 m' Daun Pintu Frame Alumunium Ex. Alexindo 90,000.00 1,020,600.00
- m' Daun Jendela Frame Alumunium 90,000.00 -
1.512 m2 Kaca Bening 5 mm 120,800.00 182,649.60
1.092 m2 Stiker sandblas 150,000.00 163,800.00
2.000 set Handle Pintu Ex. Dekson 602,400.00 1,204,800.00
6.000 Bh Engsel Pintu 4" Ex. Dekson 30,000.00 180,000.00
2.000 unit Door Closer Ex. Dekson DCL 300 Serie NHO 318,000.00 636,000.00
- Set Cesement 12" 120,000.00 -
- Bh Rambuncis 67,800.00 -
12.000 buah Skrup Fixer 72.00 864.00
0.347 Tube Sealant Kusen 32,500.00 11,261.25
C PERALATAN
D Jumlah A + B + C 4,126,062.94
E Overhead & Profit 10% 412,606.29
F Harga Satuan Pekerjaan (D+E) 4,538,669.23

6 HITUNG PKM 1.000 Unit Pemasangan Pintu Spandek PVC Rangka Alumunium ( PKM ) 2,358,099.66
A TENAGA 201,718.59
L.01 0.719 OH Pekerja 65,000.00 46,733.54
L.02 1.719 OH Tukang Besi 80,000.00 137,518.20
L.03 0.172 OH Kepala Tukang 85,000.00 14,611.31
L.04 0.036 OH Mandor 80,000.00 2,855.54
B BAHAN 1,942,008.38
5.093 m' Kusen Alm Coating White 4" Tbl 1 mm Ex. Alexindo 90,000.00 458,325.00
5.933 m' Frame Pintu Alumunium Ex. Alexindo 90,000.00 533,925.00
0.751 m2 Spandek PVC 288,000.00 216,216.00
0.231 m2 Kaca Buram 5 mm 132,000.00 30,492.00
1.000 set Handle Pintu Ex. Dekson 602,400.00 602,400.00
3.000 Bh Engsel Pintu 4" Ex. Dekson 30,000.00 90,000.00
10.000 buah Skrup Fixer 72.00 720.00
0.306 Tube Sealant Kusen 32,500.00 9,930.38
C PERALATAN
D Jumlah A + B + C 2,143,726.96
E Overhead & Profit 10% 214,372.70
F Harga Satuan Pekerjaan (D+E) 2,358,099.66
7 HITUNG PP 1.000 Unit Pemasangan Partisi Kaca Rangka Alumunium ( PP ) 2,002,389.40
A TENAGA 250,441.48
L.01 1.027 OH Pekerja 65,000.00 66,748.53
L.02 2.027 OH Tukang Besi 80,000.00 162,152.04
L.03 0.203 OH Kepala Tukang 85,000.00 17,228.65
L.04 0.051 OH Mandor 85,000.00 4,312.25
B BAHAN 1,569,912.53
12.254 m' Kusen Alm Coating White 4" Tbl 1 mm Ex. Alexindo 90,000.00 1,102,815.00
- m' Daun Pintu Frame Alumunium Ex. Alexindo 90,000.00 -
3.654 m2 Kaca Bening 5 mm 120,800.00 441,403.20
1.827 m2 Stiker Sandblas 150,000.00
- set Handle Pintu Ex. Dekson 602,400.00 -
- Bh Engsel Pintu 4" Ex. Dekson 30,000.00 -
- unit Door Closer Ex. Dekson DCL 300 Serie NHO 318,000.00 -
- Set Cesement 12" 120,000.00 -
- Bh Rambuncis 67,800.00 -
25.000 buah Skrup Fixer 72.00 1,800.00
0.735 Tube Sealant Kusen 32,500.00 23,894.33
C PERALATAN
D Jumlah A + B + C 1,820,354.00
E Overhead & Profit 10% 182,035.40
F Harga Satuan Pekerjaan (D+E) 2,002,389.40

8 HITUNG PU1 1.000 Unit Pemasangan Pintu Utama Besi Sliding ( PU1 ) 7,728,619.25
A TENAGA 165,335.00
L.01 1.050 OH Pekerja 65,000.00 68,250.00
L.02 1.050 OH Tukang Besi 80,000.00 84,000.00
L.03 0.105 OH Kepala Tukang 85,000.00 8,925.00
L.04 0.052 OH Mandor 80,000.00 4,160.00
B BAHAN 6,860,682.50
39.690 m' Pipa Besi Galvanis 2" 38,000.00 1,508,220.00
90.169 kg Pipa Besi Galvanis 1,5" 30,000.00 2,705,062.50
- m' Daun Pintu Hollow 4x4 cm 32,500.00 -
- kg Penutup Daun Pintu Besi Plat tbl 2 mm 16,500.00 -
2.000 set Handle Pintu 602,400.00 1,204,800.00
2.000 set Engsel Pintu Sliding 720,000.00 1,440,000.00
0.050 kg Kawat Las 52,000.00 2,600.00
C PERALATAN
D Jumlah A + B + C 7,026,017.50
E Overhead & Profit 10% 702,601.75
F Harga Satuan Pekerjaan (D+E) 7,728,619.25

9 HITUNG PU2 1.000 Unit Pemasangan Pintu Utama Besi Sliding ( PU2 ) 6,511,249.25
A TENAGA 165,335.00
L.01 1.050 OH Pekerja 65,000.00 68,250.00
L.02 1.050 OH Tukang Besi 80,000.00 84,000.00
L.03 0.105 OH Kepala Tukang 85,000.00 8,925.00
L.04 0.052 OH Mandor 80,000.00 4,160.00
B BAHAN 5,753,982.50
31.290 m' Pipa Besi Galvanis 2" 38,000.00 1,189,020.00
63.919 kg Pipa Besi Galvanis 1,5" 30,000.00 1,917,562.50
- m' Daun Pintu Hollow 4x4 cm 32,500.00 -
- kg Penutup Daun Pintu Besi Plat tbl 2 mm 16,500.00 -
2.000 set Handle Pintu 602,400.00 1,204,800.00
2.000 set Engsel Pintu Sliding 720,000.00 1,440,000.00
0.050 kg Kawat Las 52,000.00 2,600.00
C PERALATAN
D Jumlah A + B + C 5,919,317.50
E Overhead & Profit 10% 591,931.75
F Harga Satuan Pekerjaan (D+E) 6,511,249.25

10 HITUNG PB1 1.000 Unit Pemasangan Pintu Besi Swing ( PB1 ) 3,645,467.45
A TENAGA 165,335.00
L.01 1.050 OH Pekerja 65,000.00 68,250.00
L.02 1.050 OH Tukang Besi 80,000.00 84,000.00
L.03 0.105 OH Kepala Tukang 85,000.00 8,925.00
L.04 0.052 OH Mandor 80,000.00 4,160.00
B BAHAN 3,148,726.32
6.090 m' Kusen Besi Hollow 40.60.2 mm 47,666.67 290,290.00
36.286 kg Frame Besi Siku L 40.40.2 mm 14,000.00 508,007.50
22.076 m' Daun Pintu Hollow 40.40.2 mm 32,500.00 717,478.13
14.882 kg Penutup Daun Pintu Besi Plat tbl 2 mm 16,500.00 245,550.69
2.000 set Handle Pintu 602,400.00 1,204,800.00
6.000 Bh Engsel Pintu 4" 30,000.00 180,000.00
0.050 kg Kawat Las 52,000.00 2,600.00
C PERALATAN
D Jumlah A + B + C 3,314,061.32
E Overhead & Profit 10% 331,406.13
F Harga Satuan Pekerjaan (D+E) 3,645,467.45
11 HITUNG PB2 1.000 Unit Pemasangan Pintu Besi Swing ( PB2 ) 3,407,978.13
A TENAGA 165,335.00
L.01 1.050 OH Pekerja 65,000.00 68,250.00
L.02 1.050 OH Tukang Besi 80,000.00 84,000.00
L.03 0.105 OH Kepala Tukang 85,000.00 8,925.00
L.04 0.052 OH Mandor 80,000.00 4,160.00
B BAHAN 2,932,826.93
5.775 m' Kusen Besi Hollow 4x6 cm 47,666.67 275,275.00
41.615 kg Frame Besi Siku L 40.40.4 cm 14,000.00 582,610.00
- m' Daun Pintu Hollow 4x4 cm 32,500.00 -
41.669 kg Penutup Daun Pintu Besi Plat tbl 2 mm 16,500.00 687,541.93
2.000 set Handle Pintu 602,400.00 1,204,800.00
6.000 Bh Engsel Pintu 4" 30,000.00 180,000.00
0.050 kg Kawat Las 52,000.00 2,600.00
C PERALATAN
D Jumlah A + B + C 3,098,161.93
E Overhead & Profit 10% 309,816.19
F Harga Satuan Pekerjaan (D+E) 3,407,978.13

12 HITUNG PB3 1.000 Unit Pemasangan Pintu Besi Swing ( PB3 ) 2,229,729.09
A TENAGA 165,335.00
L.01 1.050 OH Pekerja 65,000.00 68,250.00
L.02 1.050 OH Tukang Besi 80,000.00 84,000.00
L.03 0.105 OH Kepala Tukang 85,000.00 8,925.00
L.04 0.052 OH Mandor 80,000.00 4,160.00
B BAHAN 1,861,691.45
5.460 m' Kusen Besi Hollow 4x6 cm 47,666.67 260,260.00
27.913 kg Frame Besi Siku L 40.40.4 cm 14,000.00 390,775.00
- m' Daun Pintu Hollow 4x4 cm 32,500.00 -
31.252 kg Penutup Daun Pintu Besi Plat tbl 2 mm 16,500.00 515,656.45
1.000 set Handle Pintu 602,400.00 602,400.00
3.000 Bh Engsel Pintu 4" 30,000.00 90,000.00
0.050 kg Kawat Las 52,000.00 2,600.00
C PERALATAN
D Jumlah A + B + C 2,027,026.45
E Overhead & Profit 10% 202,702.64
F Harga Satuan Pekerjaan (D+E) 2,229,729.09

13 HITUNG PB4 1.000 Unit Pemasangan Pintu Besi Sliding ( PB4 ) 2,827,026.13
A TENAGA 165,335.00
L.01 1.050 OH Pekerja 65,000.00 68,250.00
L.02 1.050 OH Tukang Besi 80,000.00 84,000.00
L.03 0.105 OH Kepala Tukang 85,000.00 8,925.00
L.04 0.052 OH Mandor 80,000.00 4,160.00
B BAHAN 2,404,688.75
6.195 m' Kusen Besi Hollow 4x6 cm 47,666.67 295,295.00
22.838 kg Frame Besi Siku L 40.40.4 cm 14,000.00 319,725.00
14.298 m' Daun Pintu Hollow 4x4 cm 32,500.00 464,668.75
- kg Penutup Daun Pintu Besi Plat tbl 2 mm 16,500.00 -
1.000 set Handle Pintu 602,400.00 602,400.00
1.000 set Engsel Pintu Sliding 720,000.00 720,000.00
0.050 kg Kawat Las 52,000.00 2,600.00
C PERALATAN
D Jumlah A + B + C 2,570,023.75
E Overhead & Profit 10% 257,002.38
F Harga Satuan Pekerjaan (D+E) 2,827,026.13

4 HITUNG JD1 1.000 Unit Pemasangan Jendela Kaca Rangka Alumunium ( JD1 ) 36,211,974.52
A TENAGA 632,753.59
L.01 3.457 OH Pekerja 65,000.00 224,726.13
L.02 4.457 OH Tukang Besi 80,000.00 356,586.00
L.03 0.446 OH Kepala Tukang 85,000.00 37,887.26
L.04 0.169 OH Mandor 80,000.00 13,554.20
B BAHAN 32,287,223.25
68.775 m' Kusen Alm Coating White 4" Tbl 1 mm Ex. Alexindo 90,000.00 6,189,750.00
21.735 m' Daun Jendela Frame Alumunium Ex. Alexindo 90,000.00 1,956,150.00
18.000 bh Engsel Jendela 3" Ex. Dekson 25,500.00 459,000.00
5.670 m2 Kaca Bening 5 mm 120,800.00 684,936.00
26.460 m2 Kaca Tempered 10 mm 759,000.00 20,083,140.00
18.000 Set Cesement 12" Ex. Dekson 120,000.00 2,160,000.00
9.000 Bh Rambuncis Ex. Dekson 400 67,800.00 610,200.00
138.000 buah Skrup Fixer 72.00 9,936.00
4.127 Tube Sealant Kusen 32,500.00 134,111.25
C PERALATAN
D Jumlah A + B + C 32,919,976.84
E Overhead & Profit 10% 3,291,997.68
F Harga Satuan Pekerjaan (D+E) 36,211,974.52

5 HITUNG JD2 1.000 Unit Pemasangan Jendela Kaca Rangka Alumunium ( JD2 ) 3,910,446.45
A TENAGA 224,460.75
L.01 0.863 OH Pekerja 65,000.00 56,124.74
L.02 1.863 OH Tukang Besi 80,000.00 149,076.60
L.03 0.186 OH Kepala Tukang 85,000.00 15,839.39
L.04 0.043 OH Mandor 80,000.00 3,420.02
B BAHAN 3,330,490.58
8.453 m' Kusen Alm Coating White 4" Tbl 1 mm Ex. Alexindo 90,000.00 760,725.00
4.830 m' Daun Jendela Frame Alumunium Ex. Alexindo 90,000.00 434,700.00
4.000 bh Engsel Jendela 3" Ex. Dekson 25,500.00 102,000.00
0.504 m2 Kaca Bening 5 mm 120,800.00 60,883.20
1.764 m2 Kaca Tempered 10 mm 759,000.00 1,338,876.00
4.000 Set Cesement 12" Ex. Dekson 120,000.00 480,000.00
2.000 Bh Rambuncis Ex. Dekson 400 67,800.00 135,600.00
17.000 buah Skrup Fixer 72.00 1,224.00
0.507 Tube Sealant Kusen 32,500.00 16,482.38
C PERALATAN
D Jumlah A + B + C 3,554,951.32
E Overhead & Profit 10% 355,495.13
F Harga Satuan Pekerjaan (D+E) 3,910,446.45

14 HITUNG BV1 1.000 Unit Pemasangan Bouven Kaca Es Rangka Alumunium ( BV1 ) 531,051.30
A TENAGA 185,728.01
L.01 0.617 OH Pekerja 65,000.00 40,130.35
L.02 1.617 OH Tukang Besi 80,000.00 129,391.20
L.03 0.162 OH Kepala Tukang 85,000.00 13,747.82
L.04 0.031 OH Mandor 80,000.00 2,458.64
B BAHAN 297,045.90
2.730 m' Kusen Alm Coating White 4" Tbl 1 mm Ex. Alexindo 90,000.00 245,700.00
- m' Daun Jendela Frame Alumunium Ex. Alexindo 90,000.00 -
- bh Engsel Jendela 3" Ex. Dekson 25,500.00 -
0.378 m2 Kaca Bening 5 mm 120,800.00 45,662.40
- m2 Kaca Buram 5 mm 132,000.00 -
- Set Cesement 12" Ex. Dekson 120,000.00 -
- Bh Rambuncis Ex. Dekson 400 67,800.00 -
5.000 buah Skrup Fixer 72.00 360.00
0.164 Tube Sealant Kusen 32,500.00 5,323.50
C PERALATAN
D Jumlah A + B + C 482,773.91
E Overhead & Profit 10% 48,277.39
F Harga Satuan Pekerjaan (D+E) 531,051.30
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
X A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING
1 HITUNG LT1 1.000 m2 Pemasangan Lantai Homogenous Tile 60 x 60 cm 232,947.00
A Tenaga 56,625.00
L.01 0.500 OH Pekerja 65,000.00 32,500.00
L.02 0.250 OH Tukang Batu 80,000.00 20,000.00
L.03 0.025 OH Kepala Tukang 85,000.00 2,125.00
L.04 0.025 OH Mandor 80,000.00 2,000.00
B Bahan 155,145.00
2.920 Buah Lantai Granite 60 x 60 cm 43,875.00 128,115.00
10.000 Kg Portland Semen 1,170.00 11,700.00
0.045 m3 Pasir Pasang 264,000.00 11,880.00
0.150 Kg Pengisi Nat AM 50 23,000.00 3,450.00
C PERALATAN
D Jumlah A + B + C 211,770.00
E Overhead & Profit 10% 21,177.00
F Harga Satuan Pekerjaan (D+E) 232,947.00

2 HITUNG LT2 1.000 m2 Pemasangan Lantai Keramik 25 x 25 cm ( Un Polish/ tekstur ) 161,064.20


A Tenaga 42,050.00
L.01 0.350 OH Pekerja 65,000.00 22,750.00
L.02 0.200 OH Tukang Batu 80,000.00 16,000.00
L.03 0.020 OH Kepala Tukang 85,000.00 1,700.00
L.04 0.020 OH Mandor 80,000.00 1,600.00
B Bahan 104,372.00
16.800 Buah Keramik 25 x 25 cm Unpolish Ex. Platinum 4,375.00 73,500.00
8.400 Kg Portland Semen 1,170.00 9,828.00
0.048 m3 Pasir Pasang 264,000.00 12,672.00
0.36 Kg Pengisi Nat AM 50 23,000.00 8,372.00
C PERALATAN
D Jumlah A + B + C 146,422.00
E Overhead & Profit 10% 14,642.20
F Harga Satuan Pekerjaan (D+E) 161,064.20

3 HITUNG LT3 1.000 m' Pemasangan Keramik Lantai Motif 30 x 60 cm 208,906.50


A Tenaga 29,445.00
L.01 0.260 OH Pekerja 65,000.00 16,900.00
L.02 0.130 OH Tukang Batu 80,000.00 10,400.00
L.03 0.013 OH Kepala Tukang 85,000.00 1,105.00
L.04 0.013 OH Mandor 80,000.00 1,040.00
B Bahan 160,470.00
5.560 Buah Keramik Lantai Motif 30 x 60 cm 24,000.00 133,440.00
10.000 Kg Portland Semen 1,170.00 11,700.00
0.045 m3 Pasir Pasang 264,000.00 11,880.00
0.150 Kg Pengisi Nat AM 50 23,000.00 3,450.00
C PERALATAN
D Jumlah A + B + C 189,915.00
E Overhead & Profit 10% 18,991.50
F Harga Satuan Pekerjaan (D+E) 208,906.50

CK Boyolali
4 HITUNG LT4 1.000 m' Pemasangan Step Nosing 10 x 30 cm 109,054.88
A Tenaga 14,215.00
L.01 0.090 OH Pekerja 65,000.00 5,850.00
L.02 0.090 OH Tukang Batu 80,000.00 7,200.00
L.03 0.009 OH Kepala Tukang 85,000.00 765.00
L.04 0.005 OH Mandor 80,000.00 400.00
B Bahan 84,925.80
3.500 Buah Step Nosing 10 x 30 cm 23,000.00 80,500.00
1.140 Kg Portland Semen 1,170.00 1,333.80
0.003 m3 Pasir Pasang 264,000.00 792.00
0.100 Kg Pengisi Nat AM 50 23,000.00 2,300.00
C PERALATAN
D Jumlah A + B + C 99,140.80
E Overhead & Profit 10% 9,914.08
F Harga Satuan Pekerjaan (D+E) 109,054.88

5 HITUNG LT5 1.000 m2 Pemasangan Dinding Keramik 25 x 40 cm 171,455.35


A Tenaga 45,300.00
L.01 0.400 OH Pekerja 65,000.00 26,000.00
L.02 0.200 OH Tukang Batu 80,000.00 16,000.00
L.03 0.020 OH Kepala Tukang 85,000.00 1,700.00
L.04 0.020 OH Mandor 80,000.00 1,600.00
B Bahan 110,568.50
10.50 Buah Keramik Dinding 25 x 40 cm 7,800.00 81,900.00
9.450 Kg Portland Semen 1,170.00 11,056.50
0.048 m3 Pasir Pasang 264,000.00 12,672.00
0.26 Kg Semen Warna 19,000.00 4,940.00
C PERALATAN
D Jumlah A + B + C 155,868.50
E Overhead & Profit 10% 15,586.85
F Harga Satuan Pekerjaan (D+E) 171,455.35

6 HITUNG LT12 1.000 m2 Pemasangan Dinding Batu Lempeng Acak Finish Coating Clear 246,639.25
A Tenaga 85,150.00
L.01 0.260 OH Pekerja 65,000.00 16,900.00
L.02 0.750 OH Tukang Batu 80,000.00 60,000.00
L.03 0.050 OH Kepala Tukang 85,000.00 4,250.00
L.04 0.050 OH Mandor 80,000.00 4,000.00
B Bahan 139,067.50
1.300 m2 Batu Lempeng Acak 74,800.00 97,240.00
11.750 Kg Portland Semen 1,170.00 13,747.50
0.035 m3 Pasir Pasang 264,000.00 9,240.00
0.200 Liter Coating Clear 94,200.00 18,840.00
C PERALATAN
D Jumlah A + B + C 224,217.50
E Overhead & Profit 10% 22,421.75
F Harga Satuan Pekerjaan (D+E) 246,639.25

CK Boyolali
7 HITUNG LT13 1.000 m2 Pemasangan Dinding Batu Andesit 20 x 40 finish Coating 321,153.25
A Tenaga 74,450.00
L.01 0.700 OH Pekerja 65,000.00 45,500.00
L.02 0.300 OH Tukang Batu 80,000.00 24,000.00
L.03 0.030 OH Kepala Tukang 85,000.00 2,550.00
L.04 0.030 OH Mandor 80,000.00 2,400.00
B Bahan 217,507.50
1.200 m2 Batu Andesit 20 x 40 161,000.00 193,200.00
11.750 Kg Portland Semen 1,170.00 13,747.50
0.035 m3 Pasir Pasang 264,000.00 9,240.00
0.200 Liter Coating 6,600.00 1,320.00
C PERALATAN
D Jumlah A + B + C 291,957.50
E Overhead & Profit 10% 29,195.75
F Harga Satuan Pekerjaan (D+E) 321,153.25

CK Boyolali
HARGA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH JUMLAH
Rp Rp

XI A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

1 A.4.7.1.10 1.000 m2 Pengecat Tembok Baru ( 1lap Cat Dasar 2 lap. Cat penutup ) Ex. Catylac 17,608.25
A Tenaga 7,115.50
L.01 0.020 OH Pekerja 65,000.00 1,300.00
L.02 0.063 OH Tukang Cat 80,000.00 5,040.00
L.03 0.006 OH Kepala Tukang 85,000.00 535.50
L.04 0.003 OH Mandor 80,000.00 240.00
B Bahan 8,892.00
0.100 Kg Plamir 33,400.00
0.100 Kg Cat Dasar 24,700.00 2,470.00
0.260 Kg Cat Penutup 2 kali 24,700.00 6,422.00
C PERALATAN
D Jumlah A + B + C 16,007.50
E Overhead & Profit 10% 1,600.75
F Harga Satuan Pekerjaan (D+E) 17,608.25

2 HITUNG CT1 1.000 m2 Pengecat Tembok Baru ( 1lap Cat Dasar 2 lap. Cat penutup ) Exterior Ex. Mowilex 36,097.05
A Tenaga 7,115.50
L.01 0.020 OH Pekerja 65,000.00 1,300.00
L.02 0.063 OH Tukang Cat 80,000.00 5,040.00
L.03 0.006 OH Kepala Tukang 85,000.00 535.50
L.04 0.003 OH Mandor 80,000.00 240.00
B Bahan 25,700.00
0.100 Kg Cat Dasar 49,000.00 4,900.00
0.260 Kg Cat Penutup 2 kali 80,000.00 20,800.00
C PERALATAN
D Jumlah A + B + C 32,815.50
E Overhead & Profit 10% 3,281.55
F Harga Satuan Pekerjaan (D+E) 36,097.05

3 HITUNG CT2 1.000 m2 Pek. Coumpond 14,938.00


A Tenaga 12,180.00
L.01 0.050 OH Pekerja 65,000.00 3,250.00
L.02 0.100 OH Tukang Cat 80,000.00 8,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.001 OH Mandor 80,000.00 80.00
B Bahan 1,400.00
0.500 Kg Coumpond Aplus 2,800.00 1,400.00
C PERALATAN
D Jumlah A + B + C 13,580.00
E Overhead & Profit 10% 1,358.00
F Harga Satuan Pekerjaan (D+E) 14,938.00

CK Boyolali
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
XI A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM
2 HITUNG B5 1.000 m' Pemasangan Pagar Pipa Besi Galvanis Medium 3" 876,289.79
A TENAGA 80,750.00
L.01 0.500 OH Pekerja 65,000.00 32,500.00
L.02 0.500 OH Tukang Khusus 80,000.00 40,000.00
L.03 0.050 OH Kepala Tukang 85,000.00 4,250.00
L.04 0.050 OH Mandor 80,000.00 4,000.00
B BAHAN 715,877.08
3.413 m' Pipa Besi Galvanis Medium 3" 198,166.67 676,243.75
0.100 Bahan Las (10%) 198,166.67 19,816.67
0.100 Asesoris (10%) 198,166.67 19,816.67
C PERALATAN
D Jumlah A + B + C 796,627.08
E Overhead & Profit 10% 79,662.71
F Harga Satuan Pekerjaan (D+E) 876,289.79

CK Boyolali
HARGA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH JUMLAH
Rp Rp

HARGA SATUAN PEKERJAAN ELEKTRIKAL


1 HITUNG EL1 1.000 Ttk Pek. Instalasi Listrik Kabel NYM 3x2,5 mm Ex. Eterna 121,990.00
A Tenaga 18,100.00
L.02 0.200 OH Tukang 80,000.00 16,000.00
L.03 0.020 OH Kepala Tukang 85,000.00 1,700.00
L.04 0.005 OH Mandor 80,000.00 400.00
B Bahan 92,800.00
6.000 m' Kabel NYM ukr 3 x 2,5 mm2 10,500.00 63,000.00
6.000 m' Pipa Clipsal 3,000.00 18,000.00
1.500 unit Tee Doos 6,000.00 9,000.00
2.000 unit Sock (1 Sock per 3 m) 350.00 700.00
6.000 unit Klem 350.00 2,100.00
C PERALATAN
D Jumlah A + B + C 110,900.00
E Overhead + Profit 10% 11,090.00
F Harga Satuan Pekerjaan (D+E) 121,990.00

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

VIII A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


HITUNG AT3b 1.000 m' Pasang Lisplank GRC 9/300 54,241.00
A TENAGA 12,180.00
L.01 0.050 OH Pekerja 65,000.00 3,250.00
L.02 0.100 OH Tukang Atap 80,000.00 8,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.001 OH Mandor 80,000.00 80.00
B BAHAN 37,130.00
1.050 m' Lisplank GRC 30,333.33 31,850.00
4.000 pcs Sekrup 1,320.00 5,280.00
C PERALATAN
D Jumlah A + B + C 49,310.00
E Overhead & Profit 10% 4,931.00
F Harga Satuan Pekerjaan (D+E) 54,241.00

HITUNG AT5 1.000 m2 Pasang Atap Galvalume 0.3 mm 78,705.00


A TENAGA 13,590.00
L.01 0.120 OH Pekerja 65,000.00 7,800.00
L.02 0.060 OH Tukang Atap 80,000.00 4,800.00
L.03 0.006 OH Kepala Tukang 85,000.00 510.00
L.04 0.006 OH Mandor 80,000.00 480.00
B BAHAN 57,960.00
1.05 m2 Galvalume tebal 0,3 mm 48,300.00 50,715.00
0.15 set Asesories 15% dari harga Bahan 48,300.00 7,245.00
C PERALATAN
D Jumlah A + B + C 71,550.00
E Overhead & Profit 10% 7,155.00
F Harga Satuan Pekerjaan (D+E) 78,705.00

HITUNG AT7 1.000 m2 Pasang Nok Galvalume 0.3 mm 38,923.50


A TENAGA 16,425.00
L.01 0.150 OH Pekerja 65,000.00 9,750.00
L.02 0.070 OH Tukang Atap 80,000.00 5,600.00
L.03 0.007 OH Kepala Tukang 85,000.00 595.00
L.04 0.006 OH Mandor 80,000.00 480.00
B BAHAN 18,960.00
1.05 m2 Nok Galvalume tebal 0,3 mm 15,800.00 16,590.00
0.15 set Asesories 15% dari harga Bahan 15,800.00 2,370.00
C PERALATAN
D Jumlah A + B + C 35,385.00
E Overhead & Profit 10% 3,538.50
F Harga Satuan Pekerjaan (D+E) 38,923.50

CK Boyolali
HARGA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH JUMLAH
Rp Rp

HARGA SATUAN PEKERJAAN FLOORING SEMEN FIBER NON ASBES


HITUNG CW1 1.000 m2 Pek. Flooring Conwood Deck 4" Finish Coating Err:509
A Tenaga 81,200.00
L.01 0.250 OH Pekerja 65,000.00 16,250.00
L.02 0.750 OH Tukang 80,000.00 60,000.00
L.03 0.030 OH Kepala Tukang 85,000.00 2,550.00
L.04 0.030 OH Mandor 80,000.00 2,400.00
B Bahan Err:509
3.200 Lembar Conwood Deck 4" Err:509 Err:509
10.000 Bh Screw Err:509 Err:509
0.500 Kg Tile Grout Err:509 Err:509
0.200 Kg FPS Sealer Err:509 Err:509
0.200 Kg Use Clear Err:509 Err:509
0.200 Liter Coating 94,200.00 18,840.00
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead + Profit 10% Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
HITUNG HARGA SATUAN PEKERJAAN PARTISI DAN FURNITURE
HITUNG PT 1.000 M2 Pemasangan Dinding Partisi Rangkap Gypsumboard 9mm Rangka Metal Stud Err:509
A TENAGA 37,875.00
L.01 0.150 OH Pekerja 65,000.00 9,750.00
L.02 0.250 OH Tukang Kayu 80,000.00 20,000.00
L.03 0.025 OH Kepala Tukang 85,000.00 2,125.00
L.04 0.075 OH Mandor 80,000.00 6,000.00
B BAHAN Err:509
0.718 Lbr Gypsumboard 9mm 97,800.00 70,220.40
2.000 m Metal Stud MS.76 24,000.00 48,000.00
2.000 Bh Angel Clip Err:509 Err:509
2.000 Bh Gording Clip Err:509 Err:509
0.700 Btg Hanger Rod Err:509 Err:509
3.000 Bh Furring Joint Err:509 Err:509
3.000 Bh Ramset Err:509 Err:509
18.000 Pcs Sekrup Gypsum Err:509 Err:509
0.400 Kg Cornice Adhesive Err:509 Err:509
1.300 m' Textile Tape Err:509 Err:509
2.000 m2 Cat 17,608.25 35,216.50
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 10% Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

HITUNG BD 1.000 Unit Pembuatan Back Drop Uk. 440 x 360 cm Err:509
A TENAGA 6,650,000.00
L.01 40.000 OH Pekerja 65,000.00 2,600,000.00
L.02 35.000 OH Tukang Kayu 80,000.00 2,800,000.00
L.03 10.000 OH Kepala Tukang 85,000.00 850,000.00
L.04 5.000 OH Mandor 80,000.00 400,000.00
B BAHAN Err:509
18.928 m2 Triplek / Blockboard 18 mm Err:509 Err:509
24.990 m2 Triplek / Blockboard 9 mm Err:509 Err:509
13.671 m2 Triplek / Blockboard 6 mm Err:509 Err:509
2.160 m2 MDF 6 mm Err:509 Err:509
6.000 Pasang Engsel sendok Err:509 Err:509
6.000 Unit Handle P. 12 cm Err:509 Err:509
4.800 m' Strip plat stainless Err:509 Err:509
1.000 Buah Saklar Tunggal 29,400.00 29,400.00
2.000 Buah Stop Kontak 31,800.00 63,600.00
8.490 m2 HPL Ardenas Maple Err:509 Err:509
17.862 m2 HPL Red Sapelle (TH-275B) Err:509 Err:509
7.980 m2 HPL Cloud Saw cut (TH-927J) Err:509 Err:509
8.904 m2 HPL white Glossy (dalam almari) Err:509 Err:509
2.000 Kg Paku Err:509 Err:509
3.000 Kg Lem Kayu Err:509 Err:509
25.000 Kg Lem Fox Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 10% Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

HITUNG MR 1.000 Unit Pembuatan Meja Receptionist Err:509


A TENAGA 1,835,000.00
L.01 12.000 OH Pekerja 65,000.00 780,000.00
L.02 8.000 OH Tukang Kayu 80,000.00 640,000.00
L.03 3.000 OH Kepala Tukang 85,000.00 255,000.00
L.04 2.000 OH Mandor 80,000.00 160,000.00
B BAHAN Err:509
21.672 m2 Triplek / Blockboard 18 mm Err:509 Err:509
15.874 m2 Triplek / Blockboard 9 mm Err:509 Err:509
1.120 m2 Triplek / Blockboard 6 mm Err:509 Err:509
0.900 m2 Kaca 8 mm Finishing Polin Err:509 Err:509
6.000 Unit Rel Almari Huben Err:509 Err:509
4.000 Pasang Engsel sendok Err:509 Err:509
8.000 Unit Handle P. 12 cm Err:509 Err:509
26.040 m2 HPL Ardenas Maple Err:509 Err:509

CK Boyolali
5.040 m2 HPL Cloud Saw cut (TH-927J) Err:509 Err:509
3.300 m2 HPL white Glossy Err:509 Err:509
1.250 Kg Paku Err:509 Err:509
1.000 Kg Lem Kayu Err:509 Err:509
12.500 Kg Lem Fox Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 10% Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

HITUNG RB 1.000 Unit Pembuatan Rak Buku Err:509


A TENAGA 1,250,000.00
L.01 8.000 OH Pekerja 65,000.00 520,000.00
L.02 6.000 OH Tukang Kayu 80,000.00 480,000.00
L.03 2.000 OH Kepala Tukang 85,000.00 170,000.00
L.04 1.000 OH Mandor 80,000.00 80,000.00
B BAHAN Err:509
9.152 m2 Triplek / Blockboard 18 mm Err:509 Err:509
1.800 m2 Triplek / Blockboard 9 mm Err:509 Err:509
1.800 m2 Triplek / Blockboard 6 mm Err:509 Err:509
6.000 Unit Tiang Bracket Err:509 Err:509
12.000 Unit Gantungan Bracket Err:509 Err:509
1.000 m' Strip plat stainless Err:509 Err:509
3.760 m2 HPL Ardenas Maple Err:509 Err:509
2.662 m2 HPL Cloud Saw cut (TH-927J) Err:509 Err:509
0.924 m2 HPL Alumunium Brush Err:509 Err:509
1.000 Kg Paku Err:509 Err:509
2.000 Kg Lem Kayu Err:509 Err:509
8.000 Kg Lem Fox Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 10% Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

HITUNG MB 1.000 Unit Pembuatan Meja Baca Err:509


A TENAGA 1,110,000.00
L.01 7.000 OH Pekerja 65,000.00 455,000.00
L.02 4.000 OH Tukang Kayu 80,000.00 320,000.00
L.03 3.000 OH Kepala Tukang 85,000.00 255,000.00
L.04 1.000 OH Mandor 80,000.00 80,000.00
B BAHAN Err:509
5.590 m2 Triplek / Blockboard 18 mm Err:509 Err:509
4.602 m2 Triplek / Blockboard 9 mm Err:509 Err:509
2.800 m2 Triplek / Blockboard 6 mm Err:509 Err:509
0.500 m2 Kaca 8 mm Finishing Polin Err:509 Err:509
2.200 m' Strip plat stainless Err:509 Err:509
4.200 m2 HPL Ardenas Maple Err:509 Err:509
2.000 m2 HPL Cloud Saw cut (TH-927J) Err:509 Err:509
3.180 m2 HPL white Glossy Err:509 Err:509
1.500 Kg Paku Err:509 Err:509
1.000 Kg Lem Kayu Err:509 Err:509
10.000 Kg Lem Fox Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 10% Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

CK Boyolali
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
VI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
1 A.4.6.1.1 1.000 m3 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I Err:509
A Tenaga 2,341,500.00
L.01 7.000 OH Pekerja 65,000.00 455,000.00
L.02 21.000 OH Tukang Kayu 80,000.00 1,680,000.00
L.03 2.100 OH Kepala Tukang 85,000.00 178,500.00
L.04 0.350 OH Mandor 80,000.00 28,000.00
B Bahan Err:509
1.100 m3 Kayu Klas I (Jati) , Balok 36,225,000.00 39,847,500.00
1.250 kg Paku Biasa 2" - 5 " Err:509 Err:509
1.000 kg Lem Kayu Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

2 A.4.6.1.2 1.000 m3 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas II atau III Err:509
Tenaga 2,007,000.00
L.01 6.000 OH Pekerja 65,000.00 390,000.00
L.02 18.000 OH Tukang Kayu 80,000.00 1,440,000.00
L.03 1.800 OH Kepala Tukang 85,000.00 153,000.00
L.04 0.300 OH Mandor 80,000.00 24,000.00
Bahan Err:509
1.200 m3 Kayu Klas II (Bangkirai) , Balok 15,698,000.00 18,837,600.00
1.250 kg Paku Biasa 2" - 5 " Err:509 Err:509
1.000 kg Lem Kayu Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

3 A.4.6.1.3 1.000 m2 Pembuatan & Pemasangan Pintu KlampStandard Kayu Klas II (Kayu Kamfer) Err:509
A Tenaga 117,115.00
L.01 0.350 OH Pekerja 65,000.00 22,750.00
L.02 1.050 OH Tukang Kayu 80,000.00 84,000.00
L.03 0.105 OH Kepala Tukang 85,000.00 8,925.00
L.04 0.018 OH Mandor 80,000.00 1,440.00
B Bahan Err:509
0.040 m3 Kayu Klas II (Kamfer), papan 8,453,000.00 338,120.00
0.050 Kg Paku Biasa 2" - 5 " Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

4 A.4.6.1.4 1.000 m2 Pembuatan & Pemasangan Daun Pintu Klamp Sederhana Kayu Klas III Err:509
Tenaga 117,115.00
L.01 0.350 OH Pekerja 65,000.00 22,750.00
L.02 1.050 OH Tukang Kayu 80,000.00 84,000.00
L.03 0.105 OH Kepala Tukang 85,000.00 8,925.00
L.04 0.018 OH Mandor 80,000.00 1,440.00
Bahan Err:509
0.040 m3 Kayu Klas II (Kamfer), papan 8,453,000.00 338,120.00
0.050 Kg Paku Biasa 2" - 5 " Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

5 A.4.6.1.5 1.000 m2 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II Err:509
A Tenaga 334,500.00
L.01 1.000 OH Pekerja 65,000.00 65,000.00
L.02 3.000 OH Tukang Kayu 80,000.00 240,000.00
L.03 0.300 OH Kepala Tukang 85,000.00 25,500.00
L.04 0.050 OH Mandor 80,000.00 4,000.00
B Bahan Err:509
0.040 m3 Kayu Klas I (Jati), papan 42,263,000.00 1,690,520.00
0.050 kg Lem Kayu Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

6 A.4.6.1.6 1.000 m2 Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Klas I atau II Err:509

CK Boyolali
A Tenaga 267,600.00
L.01 0.800 OH Pekerja 65,000.00 52,000.00
L.02 2.400 OH Tukang Kayu 80,000.00 192,000.00
L.03 0.240 OH Kepala Tukang 85,000.00 20,400.00
L.04 0.040 OH Mandor 80,000.00 3,200.00
B Bahan Err:509
0.024 m3 Kayu Klas I (Jati), papan 42,263,000.00 1,014,312.00
0.300 kg Lem Kayu Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

7 A.4.6.1.7 1.000 m2 Pembuatan & Pemasangan Pintu & Jendela Jalusi Kayu Klas I atau II (jati) Err:509
A Tenaga 334,500.00
L.01 1.000 OH Pekerja 65,000.00 65,000.00
L.02 3.000 OH Tukang Kayu 80,000.00 240,000.00
L.03 0.300 OH Kepala Tukang 85,000.00 25,500.00
L.04 0.050 OH Mandor 80,000.00 4,000.00
B Bahan Err:509
0.064 m3 Kayu Klas I (Jati), papan 42,263,000.00 2,704,832.00
0.500 kg Lem Kayu Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

8 A.4.6.1.8 1.000 m2 Pembuatan&Pemasangan Pintu kayu lapis (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 9 Err:509
A Tenaga 234,150.00
L.01 0.700 OH Pekerja 65,000.00 45,500.00
L.02 2.100 OH Tukang Kayu 80,000.00 168,000.00
L.03 0.210 OH Kepala Tukang 85,000.00 17,850.00
L.04 0.035 OH Mandor 80,000.00 2,800.00
B Bahan Err:509
0.025 m3 Kayu Klas II (Kamfer), papan 8,453,000.00 211,325.00
0.030 Kg Paku Biasa 1/2" - 1" Err:509 Err:509
0.500 Ltr Lem Kayu Err:509 Err:509
1.000 Lbr Plywood tebal 4 mm uk.90x220cm Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

9 A.4.6.1.9 1.000 m2 Pembuatan&Pemasangan Pintu Plywood rangkap, rangka expose kayu klas I atau II Err:509
A Tenaga 267,600.00
L.01 0.800 OH Pekerja 65,000.00 52,000.00
L.02 2.400 OH Tukang Kayu 80,000.00 192,000.00
L.03 0.240 OH Kepala Tukang 85,000.00 20,400.00
L.04 0.040 OH Mandor 80,000.00 3,200.00
B Bahan Err:509
0.026 m3 Kayu Klas II (Kamfer), papan 8,453,000.00 216,396.80
0.030 Kg Paku Biasa 1/2" - 1" Err:509 Err:509
0.500 Ltr Lem Kayu Err:509 Err:509
1.000 Lbr Plywood tebal 4 mm uk.90x220cm Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

10 A.4.6.1.10 1.000 m2 Pembuatan & Pemasangan Jalusi mati Kosen Kayu Klas I atau II Err:509
A Tenaga 247,350.00
L.01 0.670 OH Pekerja 65,000.00 43,550.00
L.02 2.000 OH Tukang Kayu 80,000.00 160,000.00
L.03 0.200 OH Kepala Tukang 85,000.00 17,000.00
L.04 0.335 OH Mandor 80,000.00 26,800.00
B Bahan Err:509
0.060 m3 Kayu Klas I (Jati), papan 42,263,000.00 2,535,780.00
0.150 Kg Paku Biasa 1/2" - 1" Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

11 A.4.6.1.11 1.000 m2 Pembuatan & Pemasangan Pintu Teakwood Rangkap, Rangka Expose Kayu Klas I Err:509
A Tenaga 267,600.00
L.01 0.800 OH Pekerja 65,000.00 52,000.00
L.02 2.400 OH Tukang Kayu 80,000.00 192,000.00

CK Boyolali
L.03 0.240 OH Kepala Tukang 85,000.00 20,400.00
L.04 0.040 OH Mandor 80,000.00 3,200.00
B Bahan Err:509
0.025 m3 Kayu Klas I (Jati), papan 42,263,000.00 1,056,575.00
0.030 Kg Paku Biasa 1/2" - 1" Err:509 Err:509
0.300 kg Lem Kayu Err:509 Err:509
1.000 Lbr Teakwood (90 x 220) cm x 4 mm Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

12 A.4.6.1.12 1.000 m2 Pembuatan&Pemasangan Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas Err:509
A Tenaga 284,365.00
L.01 0.850 OH Pekerja 65,000.00 55,250.00
L.02 2.550 OH Tukang Kayu 80,000.00 204,000.00
L.03 0.255 OH Kepala Tukang 85,000.00 21,675.00
L.04 0.043 OH Mandor 80,000.00 3,440.00
B Bahan Err:509
0.025 m3 Kayu Klas II (Kamfer), papan 8,453,000.00 211,325.00
0.030 Kg Paku Biasa 1/2" - 1" Err:509 Err:509
0.080 kg Lem Kayu Err:509 Err:509
1.000 Lbr Teakwood (90 x 220) cm x 4 mm Err:509 Err:509
0.500 Lbr Formika Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

13 A.4.6.1.13 1.000 m3 Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu I; II & III Bentang 6 meter Err:509
A Tenaga 1,338,000.00
L.01 4.000 OH Pekerja 65,000.00 260,000.00
L.02 12.000 OH Tukang Kayu 80,000.00 960,000.00
L.03 1.200 OH Kepala Tukang 85,000.00 102,000.00
L.04 0.200 OH Mandor 80,000.00 16,000.00
B Bahan Err:509
1.100 m3 Kayu Kamfer, balok 7,849,000.00 8,633,900.00
15.000 Kg Besi Strip 16,500.00 247,500.00
5.600 Kg Paku Biasa 2" - 5" Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

15 A.4.6.1.15 1.000 m3 Pemasangan konstruksi Gording, Kayu Klas II Err:509


A Tenaga 802,800.00
L.01 2.400 OH Pekerja 65,000.00 156,000.00
L.02 7.200 OH Tukang Kayu 80,000.00 576,000.00
L.03 0.720 OH Kepala Tukang 85,000.00 61,200.00
L.04 0.120 OH Mandor 80,000.00 9,600.00
B Bahan Err:509
1.100 m3 Kayu Klas II (BK), balok 15,698,000.00 17,267,800.00
15.000 Kg Besi Strip 16,500.00 247,500.00
3.000 Kg Paku Biasa 2" - 5" Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

16 A.4.6.1.16 1.000 m2 Pemasangan Rangka Atap Genteng Keramik, Kayu Klas II Err:509
A Tenaga 15,750.00
L.01 0.100 OH Pekerja 65,000.00 6,500.00
L.02 0.100 OH Tukang Kayu 80,000.00 8,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.005 OH Mandor 80,000.00 400.00
B Bahan Err:509
0.014 m3 Kayu Klas II (Kruing), Kaso-kaso (5x7) cm 6,367,000.00 89,138.00
0.004 m3 Reng (2x3) cm Jati 12,075,000.00 43,470.00
0.250 Kg Paku Biasa 2" - 5" Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

HITUNG KY1 1.000 m2 Pemasangan Rangka Atap Genteng Keramik Reng Baru, Kayu Jati Err:509
A Tenaga 15,750.00
L.01 0.100 OH Pekerja 65,000.00 6,500.00

CK Boyolali
L.02 0.100 OH Tukang Kayu 80,000.00 8,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.005 OH Mandor 80,000.00 400.00
B Bahan Err:509
0.004 m3 Reng (2x3) cm Kayu Jati 12,075,000.00 43,470.00
0.250 Kg Paku Biasa 2" - 5" Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 0.10 Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

CK Boyolali
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
1 A.4.6.2.2 1.000 Buah Pemasangan Kunci Tanam Biasa 46,090.00
A Tenaga 41,900.00
L.01 0.010 OH Pekerja 65,000.00 650.00
L.02 0.500 OH Tukang Kayu 80,000.00 40,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.005 OH Mandor 80,000.00 400.00
B Bahan -
1.000 Buah Kunci Tanam Biasa - -
C PERALATAN
D Jumlah A + B + C 41,900.00
E Overhead & Profit 10% 4,190.00
F Harga Satuan Pekerjaan (D+E) 46,090.00
Overhead & Profit
HITUNG KK1 1.000 Buah Pemasangan Kunci Tanam Besar 257,290.00
A Tenaga 41,900.00
L.01 0.010 OH Pekerja 65,000.00 650.00
L.02 0.500 OH Tukang Kayu 80,000.00 40,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.005 OH Mandor 80,000.00 400.00
B Bahan 192,000.00
1.000 Buah Kunci Tanam Tebal Ex. Bellucci 192,000.00 192,000.00
C PERALATAN
D Jumlah A + B + C 233,900.00
E Overhead & Profit 10% 23,390.00
F Harga Satuan Pekerjaan (D+E) 257,290.00

2 A.4.6.2.3 1.000 Buah Pemasangan Kunci Kamar Mandi Err:509


A Tenaga 40,950.00
L.01 0.005 OH Pekerja 65,000.00 325.00
L.02 0.500 OH Tukang Kayu 80,000.00 40,000.00
L.03 0.005 OH Kepala Tukang 85,000.00 425.00
L.04 0.003 OH Mandor 80,000.00 200.00
B Bahan Err:509
1.000 Buah Kunci Tanam Kamar Mandi Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 10% Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

3 A.4.6.2.4 1.000 Buah Pemasangan Kunci Selinder Err:509


A Tenaga 40,950.00
L.01 0.005 OH Pekerja 65,000.00 325.00
L.02 0.500 OH Tukang Kayu 80,000.00 40,000.00
L.03 0.005 OH Kepala Tukang 85,000.00 425.00
L.04 0.003 OH Mandor 80,000.00 200.00
B Bahan Err:509
1.000 Buah Kunci Selinder Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 10% Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

4 A.4.6.2.5 1.000 Buah Pemasangan Engsel Pintu 52,085.00


A Tenaga 14,850.00
L.01 0.015 OH Pekerja 65,000.00 975.00
L.02 0.150 OH Tukang Kayu 80,000.00 12,000.00
L.03 0.015 OH Kepala Tukang 85,000.00 1,275.00
L.04 0.008 OH Mandor 80,000.00 600.00
B Bahan 32,500.00
1.000 Buah Engsel pintu 4" 32,500.00 32,500.00
C PERALATAN
D Jumlah A + B + C 47,350.00
E Overhead & Profit 10% 4,735.00
F Harga Satuan Pekerjaan (D+E) 52,085.00

5 A.4.6.2.6 1.000 Buah Pemasangan Engsel Jendela Kupu-kupu 26,620.00


A Tenaga 9,900.00

CK Boyolali
L.01 0.010 OH Pekerja 65,000.00 650.00
L.02 0.100 OH Tukang Kayu 80,000.00 8,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.005 OH Mandor 80,000.00 400.00
B Bahan 14,300.00
1.000 Buah Engsel Jendela 3" 14,300.00 14,300.00
C PERALATAN
D Jumlah A + B + C 24,200.00
E Overhead & Profit 10% 2,420.00
F Harga Satuan Pekerjaan (D+E) 26,620.00

6 A.4.6.2.7 1.000 Buah Pemasangan Engsel Angin 55,264.00


A Tenaga 24,240.00
L.01 0.100 OH Pekerja 65,000.00 6,500.00
L.02 0.200 OH Tukang Kayu 80,000.00 16,000.00
L.03 0.020 OH Kepala Tukang 85,000.00 1,700.00
L.04 0.001 OH Mandor 80,000.00 40.00
B Bahan 26,000.00
1.000 Buah Engsel Angin 26,000.00 26,000.00
C PERALATAN
D Jumlah A + B + C 50,240.00
E Overhead & Profit 10% 5,024.00
F Harga Satuan Pekerjaan (D+E) 55,264.00

7 A.4.6.2.9 1.000 Buah Pemasangan Kait Angin 67,144.00


A Tenaga 14,890.00
L.01 0.015 OH Pekerja 65,000.00 975.00
L.02 0.150 OH Tukang Kayu 80,000.00 12,000.00
L.03 0.015 OH Kepala Tukang 85,000.00 1,275.00
L.04 0.008 OH Mandor 80,000.00 640.00
B Bahan 46,150.00
1.000 Buah Kait Angin 46,150.00 46,150.00
C PERALATAN
D Jumlah A + B + C 61,040.00
E Overhead & Profit 10% 6,104.00
F Harga Satuan Pekerjaan (D+E) 67,144.00

HITUNG KK2 1.000 Buah Pemasangan Hak Angin Kuningan 67,144.00


A Tenaga 14,890.00
L.01 0.015 OH Pekerja 65,000.00 975.00
L.02 0.150 OH Tukang Kayu 80,000.00 12,000.00
L.03 0.015 OH Kepala Tukang 85,000.00 1,275.00
L.04 0.008 OH Mandor 80,000.00 640.00
B Bahan 46,150.00
1.000 Buah Hak Angin 46,150.00 46,150.00
C PERALATAN
D Jumlah A + B + C 61,040.00
E Overhead & Profit 10% 6,104.00
F Harga Satuan Pekerjaan (D+E) 67,144.00

8 A.4.6.2.10 1.000 Buah Pasang Door Closer 52,470.00


A Tenaga 47,700.00
L.01 0.050 OH Pekerja 65,000.00 3,250.00
L.02 0.500 OH Tukang Kayu 80,000.00 40,000.00
L.03 0.050 OH Kepala Tukang 85,000.00 4,250.00
L.04 0.003 OH Mandor 80,000.00 200.00
B Bahan -
1.000 Buah Door Closer - -
C PERALATAN
D Jumlah A + B + C 47,700.00
E Overhead & Profit 10% 4,770.00
F Harga Satuan Pekerjaan (D+E) 52,470.00

9 A.4.6.2.11 1.000 Buah Pemasangan Kunci Selot 20,988.00


A Tenaga 19,080.00
L.01 0.020 OH Pekerja 65,000.00 1,300.00
L.02 0.200 OH Tukang Kayu 80,000.00 16,000.00
L.03 0.020 OH Kepala Tukang 85,000.00 1,700.00
L.04 0.001 OH Mandor 80,000.00 80.00
B Bahan -
1.000 Buah Kunci Selot - -
C PERALATAN

CK Boyolali
D Jumlah A + B + C 19,080.00
E Overhead & Profit 10% 1,908.00
F Harga Satuan Pekerjaan (D+E) 20,988.00

10 A.4.6.2.13 1.000 Buah Pemasangan Door Stop 10,494.00


A Tenaga 9,540.00
L.01 0.010 OH Pekerja 65,000.00 650.00
L.02 0.100 OH Tukang Kayu 80,000.00 8,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.001 OH Mandor 80,000.00 40.00
B Bahan -
1.000 Buah Door Stop - -
C PERALATAN
D Jumlah A + B + C 9,540.00
E Overhead & Profit 10% 954.00
F Harga Satuan Pekerjaan (D+E) 10,494.00

11 A.4.6.2.14 1.000 Buah Pemasangan Rel Pintu Dorong Err:509


A Tenaga 57,240.00
L.01 0.060 OH Pekerja 65,000.00 3,900.00
L.02 0.600 OH Tukang Kayu 80,000.00 48,000.00
L.03 0.060 OH Kepala Tukang 85,000.00 5,100.00
L.04 0.003 OH Mandor 80,000.00 240.00
B Bahan Err:509
1.000 Buah Rel Pintu Dorong Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 10% Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

12 A.4.6.2.15 1.000 Buah Pemasangan Kunci Lemari 31,739.40


A Tenaga 23,854.00
L.01 0.025 OH Pekerja 65,000.00 1,625.00
L.02 0.250 OH Tukang Kayu 80,000.00 20,000.00
L.03 0.025 OH Kepala Tukang 85,000.00 2,125.00
L.04 0.001 OH Mandor 80,000.00 104.00
B Bahan 5,000.00
1.000 Buah Kunci Lemari 5,000.00 5,000.00
C PERALATAN
D Jumlah A + B + C 28,854.00
E Overhead & Profit 10% 2,885.40
F Harga Satuan Pekerjaan (D+E) 31,739.40

13 A.4.6.2.16 1.000 m2 Pemasangan Kaca tebal 3 mm 15,741.00


A Tenaga 14,310.00
L.01 0.015 OH Pekerja 65,000.00 975.00
L.02 0.150 OH Tukang Kayu 80,000.00 12,000.00
L.03 0.015 OH Kepala Tukang 85,000.00 1,275.00
L.04 0.001 OH Mandor 80,000.00 60.00
B Bahan -
1.100 m2 Kaca tebal 3mm - -
C PERALATAN
D Jumlah A + B + C 14,310.00
E Overhead & Profit 10% 1,431.00
F Harga Satuan Pekerjaan (D+E) 15,741.00

14 A.4.6.2.17 1.000 m2 Pemasangan Kaca tebal 5 mm 161,909.00


A Tenaga 14,310.00
L.01 0.015 OH Pekerja 65,000.00 975.00
L.02 0.150 OH Tukang Kayu 80,000.00 12,000.00
L.03 0.015 OH Kepala Tukang 85,000.00 1,275.00
L.04 0.001 OH Mandor 80,000.00 60.00
B Bahan 132,880.00
1.100 m2 Kaca tebal 5mm 120,800.00 132,880.00
C PERALATAN
D Jumlah A + B + C 147,190.00
E Overhead & Profit 10% 14,719.00
F Harga Satuan Pekerjaan (D+E) 161,909.00

15 A.4.6.2.18 1.000 m2 Pemasangan Kaca Cermin tebal 5 mm Err:509


A Tenaga 14,310.00
L.01 0.015 OH Pekerja 65,000.00 975.00

CK Boyolali
L.02 0.150 OH Tukang Kayu 80,000.00 12,000.00
L.03 0.015 OH Kepala Tukang 85,000.00 1,275.00
L.04 0.001 OH Mandor 80,000.00 60.00
B Bahan Err:509
1.100 m2 Kaca Cermin Err:509 Err:509
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead & Profit 10% Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
HARGA SATUAN PEKERJAAN AKSESORIES
HITUNG AS1 1.000 m' Pemasangan Handrail Tangga Bahan Stainless Steel 329,933.44
A Tenaga 53,789.49
L.01 0.500 OH Pekerja 65,000.00 32,500.00
L.02 0.250 OH Tukang Besi 80,000.00 20,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.005 OH Mandor 80,000.00 439.49
B Bahan 182,333.33
2.000 m' Pipa Stainless Steel 2 inch (Arah Memanjang) 24,666.67 49,333.33
1.500 m' Pipa Stainless Steel 2 inch (Tiang) 24,666.67 37,000.00
6.000 m' Pipa Stainless Steel 3/4 inch (Ornamen) 16,000.00 96,000.00
C PERALATAN 63,816.67
0.350 Peralatan 35% dari bahan 182,333.33 63,816.67
D Jumlah A + B + C 299,939.49
E Overhead & Profit 10% 29,993.95
F Harga Satuan Pekerjaan (D+E) 329,933.44

CK Boyolali
No Uraian Pekerjaan Satuan Kuantita Harga Satuan Jumlah Harga
s
1 2 4 5 6 7=5x6

A Keselamatn dan Kesehatan Kerja (K3)


1 K3 : Petugas K3 Konstruksi ( potensi Resiko Rendah ) Orang-Bulan 7 1,800,000.00 12,600,000.00
2 K3 : Ahli K3 Konstruksi ( Potensi Resiko Tinggi/Sedang ) Orang-Bulan 1 5,000,000.00 5,000,000.00

3 K3 : Laporan Rencana Keselamatan dan Kesehatan Kerja Konstruksi (RK3K) Buku 2 50,000.00 100,000.00
4 K3 : Laporan Bulanan / Periodik Inspeksi K3 Konstruksi (RK3K) Buku 12 50,000.00 600,000.00

Pengadaan Peralatan dan Fasilitas Penunjang K3 Konstruksi :


5 K3 : Alat Pelindung Diri / APD ( Helm, Sepatu, Kaos Tangan, Rompi, dll ) Set 15 300,000.00 4,500,000.00
6 K3 : Fasilitas Pertolongan Pertama pada Kecelakaan (P3K) Set 1 500,000.00 500,000.00
7 K3 : Tanda Peringatan dan Panduan K3 Konstruksi Lapangan Buah 3 250,000.00 750,000.00

JUMLAH Keselamatn dan Kesehatan Kerja (K3) 24,050,000.00


HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
XI A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM
1 A.4.2.1.1 1.000 Kg Pemasangan Besi Profil 33,604.45
A Tenaga 9,685.50
L.01 0.060 OH Pekerja 66,000.00 3,960.00
L.02 0.060 OH Tukang Besi 82,500.00 4,950.00
L.03 0.006 OH Kepala Tukang 88,000.00 528.00
L.04 0.003 OH Mandor 82,500.00 247.50
B Bahan 20,864.00
1.150 Kg Besi Profil 15,800.00 18,170.00
0.060 Kg Meni Besi 44,900.00 2,694.00
C PERALATAN
D Jumlah A + B + C 30,549.50
E Overhead & Profit 10% 3,054.95
F Harga Satuan Pekerjaan (D+E) 33,604.45

2 HITUNG. B2 1.000 m' Pemasangan Pipa besi Galvanis 2" 120,739.70


A Tenaga 51,408.00
L.01 0.326 OH Pekerja 65,000.00 21,216.00
L.02 0.326 OH Tukang Besi 80,000.00 26,112.00
L.03 0.033 OH Kepala Tukang 85,000.00 2,774.40
L.04 0.016 OH Mandor 80,000.00 1,305.60
B Bahan 58,355.36
1.150 m' Pipa Besi Galvanis 2" 38,000.00 43,700.00
0.326 Kg Meni Besi 44,900.00 14,655.36
C PERALATAN
D Jumlah A + B + C 109,763.36
E Overhead & Profit 10% 10,976.34
F Harga Satuan Pekerjaan (D+E) 120,739.70

3 HITUNG. B3 1.000 m' Pemasangan Pipa besi Galvanis 4" 298,928.61


A Tenaga 86,184.00
L.01 0.547 OH Pekerja 65,000.00 35,568.00
L.02 0.547 OH Tukang Besi 80,000.00 43,776.00
L.03 0.055 OH Kepala Tukang 85,000.00 4,651.20
L.04 0.027 OH Mandor 80,000.00 2,188.80
B Bahan 185,569.28
1.150 m' Pipa Besi Galvanis 4" 140,000.00 161,000.00
0.547 Kg Meni Besi 44,900.00 24,569.28
C PERALATAN
D Jumlah A + B + C 271,753.28
E Overhead & Profit 10% 27,175.33
F Harga Satuan Pekerjaan (D+E) 298,928.61

2 A.4.2.1.2 1.000 kg Pemasangan Rangka Kuda-kuda Baja IWF 30,641.05


A Tenaga 9,685.50
L.01 0.060 OH Pekerja 66,000.00 3,960.00
L.02 0.060 OH Tukang Besi 82,500.00 4,950.00
L.03 0.006 OH Kepala Tukang 88,000.00 528.00
L.04 0.003 OH Mandor 82,500.00 247.50
B Bahan 18,170.00
1.150 kg Besi Baja IWF 15,800.00 18,170.00
C PERALATAN
D Jumlah A + B + C 27,855.50
E Overhead & Profit 10% 2,785.55
F Harga Satuan Pekerjaan (D+E) 30,641.05

3 HITUNG BS1 1.000 m1 Pemasangan Grill Besi strip 50.5 - 300 836,171.64
A Tenaga 266,674.10
L.01 1.652 OH Pekerja 66,000.00 109,032.00
L.02 1.652 OH Tukang Besi 82,500.00 136,290.00
L.03 0.165 OH Kepala Tukang 88,000.00 14,537.60
L.04 0.083 OH Mandor 82,500.00 6,814.50
B Bahan 493,481.93
8.663 Kg Besi Profil / Siku 50.50.5 13,900.00 120,420.33
23.000 Kg Besi strip 50.5 10,200.00 234,600.00
34.000 cm Pengelasan ` 4,072.40 138,461.60
C PERALATAN
CK Boyolali
D Jumlah A + B + C 760,156.03
E Overhead & Profit 10% 76,015.60
F Harga Satuan Pekerjaan (D+E) 836,171.64

3 HITUNG AL9 1.000 m1 Pemasangan Handrail Tangga Bahan Stainless Steel 1,311,904.92
A TENAGA 172,333.33
L.01 0.500 OH Pekerja 66,000.00 33,000.00
L.02 1.000 OH Tukang Khusus 82,500.00 82,500.00
L.03 0.333 OH Kepala Tukang 88,000.00 29,333.33
L.04 0.333 OH Mandor 82,500.00 27,500.00
B BAHAN 1,020,307.50
2.182 m' Pipa Stainless Steel 2 inch 148,000.00 322,996.80
2.200 m' Pipa Stainless Steel 1 inch 120,000.00 264,000.00
4.514 m' Pipa Stainless Steel 3/4 inch 96,000.00 433,310.70
C PERALATAN
D Jumlah A + B + C 1,192,640.84
E Overhead & Profit 10% 119,264.08
F Harga Satuan Pekerjaan (D+E) 1,311,904.92

CK Boyolali
HARGA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH JUMLAH
Rp Rp

HARGA SATUAN PEKERJAAN ASPAL ( ADOPSI DARI ANALISA BINA MARGA )


HITUNG ASP1 1.0000 m3 Pek. Lapis Pondasi Agregat Kelas B 443,921.57
A Tenaga 833.50
L.01 0.0111 jam Pekerja 65,000.00 721.50
L.04 0.0014 jam Mandor 80,000.00 112.00
B Bahan 303,432.86
1.1702 m3 Agregat Klas B 259,300.00 303,432.86
C PERALATAN 99,298.70
0.0082 jam Wheel Loader 427,000.00 3,501.40
0.2691 jam Dump Truck 344,000.00 92,570.40
0.0001 jam Motor Grader 550,000.00 55.00
0.0097 jam Vibratory Roller 327,000.00 3,171.90
D Jumlah A + B + C 403,565.06
E Overhead + Profit 10% 40,356.51
F Harga Satuan Pekerjaan (D+E) 443,921.57

HITUNG ASP2 1.0000 Liter Pek. Lapis Resap Pengikat - Aspal Cair 15,130.84
A Tenaga 47.00
L.01 0.0006 jam Pekerja 65,000.00 39.00
L.04 0.0001 jam Mandor 80,000.00 8.00
B Bahan 13,318.76
0.8528 Kg Aspal 11,200.00 9,551.36
0.3220 liter Kerosene 11,700.00 3,767.40
C PERALATAN 389.55
0.0003 Jam Asp. Distributor 348,500.00 104.55
0.0020 Jam Compresor 142,500.00 285.00
D Jumlah A + B + C 13,755.31
E Overhead + Profit 10% 1,375.53
F Harga Satuan Pekerjaan (D+E) 15,130.84

HITUNG ASP3 1.0000 Liter Pek. Lapis Perekat - Aspal Cair 14,243.16
A Tenaga 40.50
L.01 0.0005 jam Pekerja 65,000.00 32.50
L.04 0.0001 jam Mandor 80,000.00 8.00
B Bahan 12,725.68
0.9064 Kg Aspal 11,200.00 10,151.68
0.2200 liter Kerosene 11,700.00 2,574.00
C PERALATAN 182.15
0.0004 Jam Asp. Distributor 348,500.00 139.40
0.0003 Jam Compresor 142,500.00 42.75
D Jumlah A + B + C 12,948.33
E Overhead + Profit 10% 1,294.83
F Harga Satuan Pekerjaan (D+E) 14,243.16

HITUNG ASP4 1.0000 Ton Pek. Laston Lapis Antara ( AC-BC ) 1,531,037.92
A Tenaga 2,040.00
L.01 0.0272 jam Pekerja 65,000.00 1,768.00
L.04 0.0034 jam Mandor 80,000.00 272.00
B Bahan 826,874.90
0.3720 m3 Agr Pch Mesin 5-10 & 10-20 224,900.00 83,662.80
0.3719 m3 Agr Pch Mesin 0 - 5 246,400.00 91,636.16
9.6820 Kg Semen 1,170.00 11,327.94
57.1650 Kg Aspal 11,200.00 640,248.00
C PERALATAN 562,937.75
0.4293 jam Wheel Loader 427,000.00 183,311.10
0.0238 jam Asphalt Mixing Plant ( AMP ) 1406900 6,581,000.00 156,627.80
0.0238 jam Genset 268,500.00 6,390.30
0.4577 jam Dump Truck 344,000.00 157,448.80
0.0124 jam Asphalt Finisher 835,000.00 10,354.00
0.1266 jam Tandem Roller 331,500.00 41,967.90
0.0163 jam P. Tyre Roller 419,500.00 6,837.85
D Jumlah A + B + C 1,391,852.65
E Overhead + Profit 10% 139,185.27
F Harga Satuan Pekerjaan (D+E) 1,531,037.92

HITUNG ASP5 1.0000 Ton Pek. Laston Lapis Aus ( AC-WC ) 1,545,001.50

CK Boyolali
A Tenaga 2,040.00
L.01 0.0272 jam Pekerja 65,000.00 1,768.00
L.04 0.0034 jam Mandor 80,000.00 272.00
B Bahan 865,015.32
0.2918 m3 Agr Pch Mesin 5-10 & 10-20 224,900.00 65,625.82
0.3815 m3 Agr Pch Mesin 0 - 5 246,400.00 94,001.60
9.8700 Kg Semen 1,170.00 11,547.90
61.9500 Kg Aspal 11,200.00 693,840.00
C PERALATAN 537,491.50
0.3963 jam Wheel Loader 427,000.00 169,220.10
0.0238 jam Asphalt Mixing Plant ( AMP ) 1406900 6,581,000.00 156,627.80
0.0238 jam Genset 268,500.00 6,390.30
0.4666 jam Dump Truck 344,000.00 160,510.40
0.0184 jam Asphalt Finisher 835,000.00 15,364.00
0.0580 jam Tandem Roller 331,500.00 19,227.00
0.0242 jam P. Tyre Roller 419,500.00 10,151.90
D Jumlah A + B + C 1,404,546.82
E Overhead + Profit 10% 140,454.68
F Harga Satuan Pekerjaan (D+E) 1,545,001.50

HITUNG ASP6 1.0000 Ton Pek. Latasir Kelas B ( SS-B ) 1,814,690.89


A Tenaga 2,040.00
L.01 0.0272 jam Pekerja 65,000.00 1,768.00
L.04 0.0034 jam Mandor 80,000.00 272.00
B Bahan 1,267,749.00
0.3300 m3 Pasir Kasar 291,900.00 96,327.00
0.3300 m3 Pasir Halus 291,900.00 96,327.00
31.5000 Kg Semen 1,170.00 36,855.00
92.7000 Kg Aspal 11,200.00 1,038,240.00
C PERALATAN 379,929.99
0.0588 jam Wheel Loader 427,000.00 25,111.04
0.0238 jam Asphalt Mixing Plant ( AMP ) 1406900 6,581,000.00 156,690.48
0.0238 jam Genset 268,500.00 6,392.86
0.5361 jam Dump Truck 344,000.00 184,419.34
0.0221 jam Tandem Roller 331,500.00 7,316.28
D Jumlah A + B + C 1,649,718.99
E Overhead + Profit 10% 164,971.90
F Harga Satuan Pekerjaan (D+E) 1,814,690.89

CK Boyolali
HARGA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp
HARGA SATUAN PEKERJAAN PINTU DAN JENDELA ALUMUNIUM
HITUNG PJ1 1.000 Unit Pemasangan Pintu & Jendela Kaca Tempered 12 mm ( PU ) 19,541,324.00
A TENAGA 660,800.00
L.01 4.000 OH Pekerja 65,000.00 260,000.00
L.02 4.000 OH Tukang Besi 80,000.00 320,000.00
L.03 0.800 OH Kepala Tukang 85,000.00 68,000.00
L.04 0.160 OH Mandor 80,000.00 12,800.00
B BAHAN 17,104,040.00
3.780 m2 Pintu Kaca Tempered 12 mm 862,500.00 3,260,250.00
25.100 m2 Jendela Kaca Tempered 12 mm 287,500.00 7,216,250.00
2.000 set Floor Hinge Dekson FH 84 SSS 1,231,200.00 2,462,400.00
2.000 Bh Patch Fitting Dekson PT 20 PSS 435,600.00 871,200.00
2.000 set Pull Handle 586,800.00 1,173,600.00
5.052 Tube Sealant 32,500.00 164,190.00
0.600 Ls Finishing Kaca Tempered 60% ( Total Harga Kaca ) 3,260,250.00 1,956,150.00
C PERALATAN
D Jumlah A + B + C 17,764,840.00
E Overhead & Profit 10% 1,776,484.00
F Harga Satuan Pekerjaan (D+E) 19,541,324.00

HITUNG PJ2 1.000 Unit Pemasangan Pintu & Jendela Kaca Rangka Alumunium ( PJ1 ) 3,151,602.45
A TENAGA 239,740.64
L.01 0.961 OH Pekerja 65,000.00 62,434.45
L.02 1.961 OH Tukang Besi 80,000.00 156,842.40
L.03 0.196 OH Kepala Tukang 85,000.00 16,664.51
L.04 0.047 OH Mandor 80,000.00 3,799.28
B BAHAN 2,625,352.50
10.710 m' Kusen Alumunium Coklat 1 mm Ex. Alexindo 72,000.00 771,120.00
6.510 m' Daun Pintu Frame Alumunium 72,000.00 468,720.00
3.360 m' Daun Jendela Frame Alumunium 72,000.00 241,920.00
1.995 m2 Kaca Bening 5 mm 120,800.00 240,996.00
1.000 set Handle Pintu 602,400.00 602,400.00
3.000 Bh Engsel Pintu 4" 30,000.00 90,000.00
1.000 Set Cesement 12" 120,000.00 120,000.00
1.000 Bh Rambuncis 67,800.00 67,800.00
21.000 buah Skrup Fixer 72.00 1,512.00
0.643 Tube Sealant Kusen 32,500.00 20,884.50
C PERALATAN
D Jumlah A + B + C 2,865,093.14
E Overhead & Profit 10% 286,509.31
F Harga Satuan Pekerjaan (D+E) 3,151,602.45

HITUNG PJ3 1.000 Unit Pemasangan Pintu Kaca Rangka Alumunium ( P1 ) 2,677,146.63
A TENAGA 215,577.09
L.01 0.807 OH Pekerja 65,000.00 52,456.30
L.02 1.807 OH Tukang Besi 80,000.00 144,561.60
L.03 0.181 OH Kepala Tukang 85,000.00 15,359.67
L.04 0.040 OH Mandor 80,000.00 3,199.52
B BAHAN 2,218,192.57
7.140 m' Kusen Alumunium Coating White 1 mm Ex. Alexindo 90,000.00 642,600.00
6.951 m' Daun Pintu Frame Alumunium 90,000.00 625,590.00
1.415 m2 Kaca Bening 5 mm 120,800.00 170,980.32
1.000 set Handle Pintu 602,400.00 602,400.00
3.000 Bh Engsel Pintu 4" 30,000.00 90,000.00
143.000 buah Skrup Fixer 72.00 10,296.00
2.349 Tube Sealant Kusen 32,500.00 76,326.25
C PERALATAN
D Jumlah A + B + C 2,433,769.66
E Overhead & Profit 10% 243,376.97
F Harga Satuan Pekerjaan (D+E) 2,677,146.63

HITUNG PJ4 1.000 Unit Pemasangan Pintu Kaca Double Rangka Alumunium ( P2 ) 3,131,905.02
A TENAGA 230,501.63

CK Boyolali
L.01 0.902 OH Pekerja 65,000.00 58,619.28
L.02 1.902 OH Tukang Besi 80,000.00 152,146.80
L.03 0.190 OH Kepala Tukang 85,000.00 16,165.60
L.04 0.045 OH Mandor 80,000.00 3,569.96
B BAHAN 2,616,684.75
9.345 m' Kusen Alumunium Coklat 1 mm Ex. Alexindo 72,000.00 672,840.00
12.600 m' Daun Pintu Frame Alumunium 72,000.00 907,200.00
1.943 m2 Kaca Bening 5 mm 120,800.00 234,654.00
1.000 set Handle Pintu 602,400.00 602,400.00
6.000 Bh Engsel Pintu 4" 30,000.00 180,000.00
19.000 buah Skrup Fixer 72.00 1,368.00
0.561 Tube Sealant Kusen 32,500.00 18,222.75
C PERALATAN
D Jumlah A + B + C 2,847,186.38
E Overhead & Profit 10% 284,718.64
F Harga Satuan Pekerjaan (D+E) 3,131,905.02

HITUNG PKM 1.000 Unit Pemasangan Pintu Spandek PVC Rangka Alumunium ( PKM ) 2,086,297.79
A TENAGA 201,769.35
L.01 0.719 OH Pekerja 65,000.00 46,754.50
L.02 1.719 OH Tukang Besi 80,000.00 137,544.00
L.03 0.172 OH Kepala Tukang 85,000.00 14,614.05
L.04 0.036 OH Mandor 80,000.00 2,856.80
B BAHAN 1,694,865.00
5.100 m' Kusen Alumunium Dark Brown 1 mm Ex. Alexindo 72,000.00 367,200.00
4.000 m' Frame Pintu Alumunium 90,000.00 360,000.00
0.850 m2 Spandek PVC 288,000.00 244,800.00
0.150 m2 Kaca Buram 5 mm 132,000.00 19,800.00
1.000 set Handle Pintu 602,400.00 602,400.00
3.000 Bh Engsel Pintu 4" 30,000.00 90,000.00
10.000 buah Skrup Fixer 72.00 720.00
0.306 Tube Sealant Kusen 32,500.00 9,945.00
C PERALATAN
D Jumlah A + B + C 1,896,634.35
E Overhead & Profit 10% 189,663.44
F Harga Satuan Pekerjaan (D+E) 2,086,297.79

HITUNG PJ5 1.000 Unit Pemasangan Jendela Kaca Rangka Alumunium ( J1 ) 2,395,434.61
A TENAGA 231,212.33
L.01 0.906 OH Pekerja 65,000.00 58,912.75
L.02 1.906 OH Tukang Besi 80,000.00 152,508.00
L.03 0.191 OH Kepala Tukang 85,000.00 16,203.98
L.04 0.045 OH Mandor 80,000.00 3,587.60
B BAHAN 1,946,455.50
9.450 m' Kusen Alumunium Dark Brown 1 mm Ex. Alexindo 72,000.00 680,400.00
7.560 m' Daun Jendela Frame Alumunium 90,000.00 680,400.00
1.575 m2 Kaca Bening 5 mm 120,800.00 190,260.00
2.000 Set Cesement 12" 120,000.00 240,000.00
2.000 Bh Rambuncis 67,800.00 135,600.00
19.000 buah Skrup Fixer 72.00 1,368.00
0.567 Tube Sealant Kusen 32,500.00 18,427.50
C PERALATAN
D Jumlah A + B + C 2,177,667.83
E Overhead & Profit 10% 217,766.78
F Harga Satuan Pekerjaan (D+E) 2,395,434.61

HITUNG BV1 1.000 Unit Pemasangan Bouvenlicht Kaca Rangka Alumunium ( BV1 ) 610,784.46
A TENAGA 39,514.50
L.01 0.251 OH Pekerja 65,000.00 16,317.21
L.02 0.251 OH Tukang Besi 80,000.00 20,082.72

CK Boyolali
L.03 0.025 OH Kepala Tukang 85,000.00 2,133.79
L.04 0.012 OH Mandor 80,000.00 980.78
B BAHAN 515,744.10
5.838 m' Kusen Alumunium Dark Brown 1 mm Ex. Alexindo 72,000.00 420,336.00
0.630 m2 Kaca Buram 5 mm 132,000.00 83,160.00
12.000 buah Skrup Fixer 72.00 864.00
0.350 Tube Sealant Kusen 32,500.00 11,384.10
C PERALATAN
D Jumlah A + B + C 555,258.60
E Overhead & Profit 10% 55,525.86
F Harga Satuan Pekerjaan (D+E) 610,784.46

HITUNG BV2 1.000 Unit Pemasangan Bouvenlicht Kaca Rangka Alumunium ( BV2 ) 296,977.71
A TENAGA 15,635.24
L.01 0.099 OH Pekerja 65,000.00 6,456.45
L.02 0.099 OH Tukang Besi 80,000.00 7,946.40
L.03 0.010 OH Kepala Tukang 85,000.00 844.31
L.04 0.005 OH Mandor 80,000.00 388.08
B BAHAN 254,344.50
2.310 m' Kusen Alumunium Dark Brown 1 mm Ex. Alexindo 72,000.00 166,320.00
0.630 m2 Kaca Buram 5 mm 132,000.00 83,160.00
5.000 buah Skrup Fixer 72.00 360.00
0.139 Tube Sealant Kusen 32,500.00 4,504.50
C PERALATAN
D Jumlah A + B + C 269,979.74
E Overhead & Profit 10% 26,997.97
F Harga Satuan Pekerjaan (D+E) 296,977.71

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
HARGA SATUAN PEKERJAAN PAVING
HITUNG PV1 1.000 m2 Pemasangan Paving Holland Natural Uk. 20 x 10,5 x 8 cm K-250 Ex. MASTER BETON 149,872.29
A Tenaga 20,483.33
L.01 0.167 OH Pekerja 65,000.00 10,833.33
L.02 0.100 OH Tukang Batu 80,000.00 8,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.010 OH Mandor 80,000.00 800.00
B Bahan 114,053.40
1.050 m2 Paving holland 20 x 10,5 x 8 cm 108,000.00 113,400.00
0.004 m3 Pasir Urug Pengisi Nat 181,500.00 653.40
C PERALATAN 1,710.80
0.015 m2 Sewa Peralatan 1.5% dari bahan 114,053.40 1,710.80
D Jumlah A + B + C 136,247.53
E Overhead & Profit 10% 13,624.75
F Harga Satuan Pekerjaan (D+E) 149,872.29

HITUNG PV2 1.000 m2 Pemasangan Paving Holland Natural Uk. 20 x 10 x 6 cm K-250 Ex. MASTER BETON 121,736.49
A Tenaga 20,483.33
L.01 0.167 OH Pekerja 65,000.00 10,833.33
L.02 0.100 OH Tukang Batu 80,000.00 8,000.00
L.03 0.010 OH Kepala Tukang 85,000.00 850.00
L.04 0.010 OH Mandor 80,000.00 800.00
B Bahan 88,853.40
1.050 m2 Paving holland 20 x 10,5 x 6 cm 84,000.00 88,200.00
0.004 m3 Pasir Urug 181,500.00 653.40
C PERALATAN 1,332.80
0.015 m2 Sewa Peralatan 1.5% dari bahan 88,853.40 1,332.80
D Jumlah A + B + C 110,669.53
E Overhead & Profit 10% 11,066.95
F Harga Satuan Pekerjaan (D+E) 121,736.49

HITUNG PV2 1.000 m1 Pemasangan Kerb Standard K-250 Uk. 10/12 x 35 x 50 cm Ex. MASTER BETON 114,738.86
A Tenaga 7,550.00
L.01 0.067 OH Pekerja 65,000.00 4,333.33
L.02 0.033 OH Tukang Batu 80,000.00 2,666.67
L.03 0.003 OH Kepala Tukang 85,000.00 283.33
L.04 0.003 OH Mandor 80,000.00 266.67
B Bahan 96,758.06
2.000 Buah Kerb Standard Uk. 10/12 x 35 x 50 48,000.00 96,000.00
0.302 Kg Portland Cement 1,170.00 353.81
0.002 m3 Pasir Pasang 264,000.00 404.25
C PERALATAN
D Jumlah A + B + C 104,308.06
E Overhead & Profit 10% 10,430.81
F Harga Satuan Pekerjaan (D+E) 114,738.86

HITUNG PV3 1.000 m1 Pemasangan Kanstein Besar K-300 Uk. 60 x 30 x 20 cm K-300 151,132.39
A Tenaga 10,135.00
L.01 0.099 OH Pekerja 65,000.00 6,435.00
L.02 0.037 OH Tukang Batu 80,000.00 2,960.00
L.03 0.004 OH Kepala Tukang 85,000.00 340.00
L.04 0.005 OH Mandor 80,000.00 400.00
B Bahan 127,258.08
1.750 Buah Kanstein besar K-300 Uk. 60 x 30 x 20 cm 66,000.00 115,500.00
0.302 Kg Portland Cement 1,170.00 353.81
0.002 m3 Pasir Pasang 264,000.00 404.25
0.029 m3 Pasir Urug 181,500.00 5,263.50
13.035 kg Pasir Beton 190.00 2,476.65
14.985 kg Kerikil (maksimum 30 mm) 212.59 3,185.70
3.225 ltr Air 23.00 74.18
C PERALATAN
D Jumlah A + B + C 137,393.08
E Overhead & Profit 10% 13,739.31
F Harga Satuan Pekerjaan (D+E) 151,132.39

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
HARGA SATUAN PEKERJAAN SULING-SULING
HITUNG SL1 1.000 m' Pemasangan Sulingan Pipa PVC tipe AW Ø 2" Ex. Wavin 33,231.00
A Tenaga 7,810.00
L.01 0.036 OH Pekerja 65,000.00 2,340.00
L.02 0.060 OH Tukang Batu 80,000.00 4,800.00
L.03 0.006 OH Kepala Tukang 85,000.00 510.00
L.04 0.002 OH Mandor 80,000.00 160.00
B Bahan 22,400.00
1.100 m' Pipa PVC Ø 2" 20,000.00 22,000.00
0.200 Kg Ijuk 2,000.00 400.00
C PERALATAN -
D Jumlah A + B + C 30,210.00
E Overhead & Profit 10% 3,021.00
F Harga Satuan Pekerjaan (D+E) 33,231.00

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
HARGA SATUAN PEKERJAAN BRONJONG & TRUCUK
Pasangan Batu Bronjong kawat uk. L=2,0m x B=1,0 m x T= 0,5 m berisi batu Kali 15-20 cm
HITUNG BJG 1.000 Bh kawat anyaman tiga lilitan ukuran 3,0 mm, kawat sisi 4,0 mm dan kawat pengikat 2,0 mm, 856,457.03
ukuran lubang heksagonal 100 x 120 mm (adopsi Bidang PSDA Kode P.06a.4.b)

A 155,965.00
L.01 1.140 OH Pekerja 65,000.00 74,100.00
L.02 0.380 OH Tukang Batu 80,000.00 30,400.00
L.03 0.325 OH Kepala Tukang 85,000.00 27,625.00
L.04 0.298 OH Mandor 80,000.00 23,840.00
B Bahan 622,632.30
1.30 m3 Batu / batu belah Uk. 15/20 272,000.00 353,600.00
15.55 Kg Kawat Bronjong Galvanis dia 3 mm 17,300.00 269,032.30
C PERALATAN -
D Jumlah A + B + C 778,597.30
E Overhead & Profit 10% 77,859.73
F Harga Satuan Pekerjaan (D+E) 856,457.03

HITUNG TCK 1.000 m' 1 m panjang cerucuk bambu ø 8 – 10 cm (adopsi Bidang PSDA Kode Analisa P.07.b) 32,441.75
A Tenaga 12,160.00
L.01 0.120 OH Pekerja 65,000.00 7,800.00
L.02 - OH Tukang Kayu 80,000.00 -
L.03 0.040 OH Kepala Tukang 85,000.00 3,400.00
L.04 0.012 OH Mandor 80,000.00 960.00
B Bahan 9,712.50
1.050 m' Bambu Petung diameter 8 – 10 cm 9,250.00 9,712.50
C PERALATAN 7,620.00
0.040 Sewa-hari Tripod tinggi 5 m 49,500.00 1,980.00
0.040 Sewa-hari Alat pancang Hammer 0.5 ton 141,000.00 5,640.00
D Jumlah A + B + C 29,492.50
E Overhead & Profit 10% 2,949.25
F Harga Satuan Pekerjaan (D+E) 32,441.75

CK Boyolali
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
HARGA SATUAN PEKERJAAN TAMAN
HITUNG TM1 1.000 m3 Pek. Media Tanam ( Tanah Merah Dan Pupuk ) 143,330.00
A Tenaga 20,300.00
L.01 0.300 OH Pekerja 65,000.00 19,500.00
L.04 0.010 OH Mandor 80,000.00 800.00
B Bahan 110,000.00
1.000 m3 Tanah Subur 110,000.00 110,000.00
C PERALATAN -
D Jumlah A + B + C 130,300.00
E Overhead & Profit 10% 13,030.00
F Harga Satuan Pekerjaan (D+E) 143,330.00

HITUNG TM2 1.000 m2 Pek. Tanaman Kacang Hias /m2 isi 15 polybag 48,081.00
A Tenaga 1,460.00
L.01 0.020 OH Pekerja 65,000.00 1,300.00
L.04 0.002 OH Mandor 80,000.00 160.00
B Bahan 42,250.00
15.000 polybag Tanaman Kacang hias 2,750.00 41,250.00
0.040 Kg Pupuk kandang 25,000.00 1,000.00
C PERALATAN
D Jumlah A + B + C 43,710.00
E Overhead & Profit 10% 4,371.00
F Harga Satuan Pekerjaan (D+E) 48,081.00

HITUNG TM3 1.000 m1 Pek. Tanaman Pangkas ( Hijau & Merah ) 42,031.00
A Tenaga 1,460.00
L.01 0.020 OH Pekerja 65,000.00 1,300.00
L.04 0.002 OH Mandor 80,000.00 160.00
B Bahan 36,750.00
6.000 polybag Tanaman Pangkas ( Hijau ) 2,750.00 16,500.00
6.000 polybag Tanaman Pangkas ( Merah ) 2,750.00 16,500.00
0.040 Kg Pupuk kandang 25,000.00 1,000.00
C PERALATAN
D Jumlah A + B + C 38,210.00
E Overhead & Profit 10% 3,821.00
F Harga Satuan Pekerjaan (D+E) 42,031.00

HITUNG TM4 1.000 m2 Pek. Tanam Pohon Ketapang Kencana Tinggi 1.00 m 140,206.00
A Tenaga 1,460.00
L.01 0.020 OH Pekerja 65,000.00 1,300.00
L.04 0.002 OH Mandor 80,000.00 160.00
B Bahan 126,000.00
1.000 bh Pohon Ketapang Kencana 125,000.00 125,000.00
0.040 Kg Pupuk kandang 25,000.00 1,000.00
C PERALATAN
D Jumlah A + B + C 127,460.00
E Overhead & Profit 10% 12,746.00
F Harga Satuan Pekerjaan (D+E) 140,206.00

HITUNG TM5 1.000 bh Pek. Tanam Pohon Pucuk Merah Tinggi min 60 cm 102,531.00
A Tenaga 1,460.00
L.01 0.020 OH Pekerja 65,000.00 1,300.00
L.04 0.002 OH Mandor 80,000.00 160.00
B Bahan 91,750.00
1.000 bh Tanaman Pucuk Merah Tinggi Min 60 cm 90,750.00 90,750.00
0.040 Kg Pupuk kandang 25,000.00 1,000.00
C PERALATAN
D Jumlah A + B + C 93,210.00
E Overhead & Profit 10% 9,321.00
F Harga Satuan Pekerjaan (D+E) 102,531.00