WILAYAH I WILAYAH II WILAYAH III

KEC. BOYOLALI KEC. KEMUSU * KEC. JUWANGI

KEC. AMPEL KEC. SELO * - DESA NGLESES

KEC. BANYUDONO KEC. WONOSEGORO - KELURAHAN SAMBENG

KEC. SAWIT KEC. JUWANGI * KEC. SELO

KEC. MOJOSONGO KEC. WONOSAMUDRO * - DESA TLOGOLELE

KEC. SAMBI KEC. TAMANSARI * - DESA SUROTELENG

KEC. NGEMPLAK KEC. KLEGO KEC. TAMANSARI

KEC. TERAS - DESA GONDANGLEGI - DESA SANGUP

KEC. GLADAGSARI - DESA KARANGGATAK - DESA MRIYAN

KEC. SIMO KEC. KARANGGEDE KEC. KEMUSU

KEC. KLEGO * - DESA BANGKOK - DESA KEDUNGMULYO

KEC. KARANGGEDE * - DESA DOLOGAN - DESA WONOHARJO

KEC. NOGOSARI KEC. ANDONG KEC. WONOSAMUDRO

KEC. ANDONG * - DESA PAKANG - DESA BERCAK

KEC. MUSUK - DESA PRANGGONG - DESA BENGLE

KEC. CEPOGO - DESA KUNTI - DESA JATILAWANG

- DESA PELEMREJO

- DESA SEMAWUNG

- DESA KADIPATEN

*) ada sebagian desa yang masuk wilayah II dan III

CK Boyolali
WILAYAH I WILAYAH II WILAYAH III
KEC. BOYOLALI KEC. SIMO KEC. KEMUSU *
KEC. AMPEL KEC. KLEGO KEC. SELO
KEC. BANYUDONO KEC. KARANGGEDE - DESA TLOGOLELE

KEC. SAWIT KEC. NOGOSARI - DESA SUROTELENG

KEC. MOJOSONGO KEC. ANDONG KEC. WONOSEGORO


KEC. SAMBI KEC. MUSUK
KEC. NGEMPLAK KEC. CEPOGO
KEC. TERAS KEC. SELO *
KEC. GLADAKSARI KEC. TAMANSARI

*) ada sebagian desa yang masuk wilayah III, IV dan V

CK Boyolali
TRIAL PERHITUNGAN PLAT BETON

Tebal Panjang Lebar Luas Volume


PLAT BETON TEBAL 12 cm Jarak 20 cm
0.12 4.00 3.00 12.00 1.44

Jarak Dim Kg/m Panjang Qty Volume


Tul. Bawah 0.20 10.00 0.62 4.00 15.00 36.99
Tul. Atas / Kuda-kuda 0.20 10.00 0.62 4.25 15.00 39.30
Tul. Ekstra 0.20 10.00 0.62 2.00 15.00 18.50
Tul. Dudukan 0.20 10.00 0.62 0.60 3.00 1.11
Tulangan Double
Tul. Bawah 0.20 10.00 0.62 3.00 20.00 36.99
Tul. Atas / Kuda-kuda 0.20 10.00 0.62 3.25 20.00 40.07
Tul. Ekstra 0.20 10.00 0.62 1.50 20.00 18.50
Tul. Dudukan 0.20 10.00 0.62 0.60 4.00 1.48

Berat Total 192.93

Berat Tulangan per M3 Untuk Plat Beton Tebal 12 cm 133.98172 Kg/m3

Tebal Panjang Lebar Luas Volume


PLAT BETON TEBAL 10 cm Jarak 20 cm
0.10 4.00 3.00 12.00 1.20

Jarak Dim Kg/m Panjang Qty Volume


Tul. Bawah 0.20 10.00 0.62 4.00 15.00 36.99
Tul. Atas / Kuda-kuda 0.20 10.00 0.62 4.25 15.00 39.30
Tul. Ekstra 0.20 10.00 0.62 2.00 15.00 18.50
Tul. Dudukan 0.20 10.00 0.62 0.60 3.00 1.11
Tulangan Double
Tul. Bawah 0.20 10.00 0.62 3.00 20.00 36.99
Tul. Atas / Kuda-kuda 0.20 10.00 0.62 3.25 20.00 40.07
Tul. Ekstra 0.20 10.00 0.62 1.50 20.00 18.50
Tul. Dudukan 0.20 10.00 0.62 0.60 4.00 1.48

Berat Total 192.93

Berat Tulangan per M3 Untuk Plat Beton Tebal 10 cm 160.77806 Kg/m3

Tebal Panjang Lebar Luas Volume


PLAT BETON TEBAL 10 cm Jarak 15 cm
0.10 4.00 3.00 12.00 1.20

Jarak Dim Kg/m Panjang Qty Volume


Tul. Bawah 0.15 10.00 0.62 4.00 20.00 49.32
Tul. Atas / Kuda-kuda
Tul. Ekstra
Tul. Dudukan
Tulangan Single
Tul. Bawah 0.15 10.00 0.62 3.00 26.67 49.32
Tul. Atas / Kuda-kuda
Tul. Ekstra
Tul. Dudukan

Berat Total 98.64

Berat Tulangan per M3 Untuk Plat Beton Tebal 10 cm 82.20 Kg/m3


HARGA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp
HARGA SATUAN PEKERJAAN PINTU DAN JENDELA ALUMUNIUM
1 HITUNG PT1 1.000 Unit Pemasangan Pintu & Jendela Kaca Tempered 12 mm ( PT1 ) 11,318,270.10
A TENAGA 780,800.00
L.01 4.000 OH Pekerja 80,000.00 320,000.00
L.02 4.000 OH Tukang Besi 90,000.00 360,000.00
L.03 0.800 OH Kepala Tukang 105,000.00 84,000.00
L.04 0.160 OH Mandor 105,000.00 16,800.00
B BAHAN 9,061,174.00
3.528 m2 Pintu Kaca Tempered 12 mm 1,039,500.00 3,667,356.00
2.000 set Floor Hinge Dekson FH 84 SSS 918,700.00 1,837,400.00
2.000 Bh Patch Fitting Dekson PT 20 PSS 834,700.00 1,669,400.00
2.000 set Pull Handle 354,900.00 709,800.00
0.192 Tube Sealant 33,600.00 6,451.20
1.344 m2 Sticker Sandblast 52,500.00 70,560.00
0.300 Ls Finishing Kaca Tempered 60% ( Total Harga Kaca ) 3,667,356.00 1,100,206.80
C PERALATAN
D Jumlah A + B + C 9,841,974.00
E Overhead & Profit 15% 1,476,296.10
F Harga Satuan Pekerjaan (D+E) 11,318,270.10

2 HITUNG P1 1.000 Unit Pemasangan Kusen dan Pintu Kaca Rangka Alumunium ( P1 ) 2,551,742.02
A TENAGA 280,765.63
L.01 0.518 OH Pekerja 80,000.00 41,420.00
L.02 2.089 OH Tukang Besi 90,000.00 187,987.50
L.03 0.343 OH Kepala Tukang 105,000.00 35,988.75
L.04 0.146 OH Mandor 105,000.00 15,369.38
B BAHAN 1,938,140.48
5.355 m' Profil open back warna coklat 57,900.00 310,054.50
2.163 m' Profil tiang engsel warna coklat (belakang) 99,000.00 214,137.00
2.163 m' Profil tiang swing warna coklat (depan) 92,800.00 200,726.40
1.680 m' Profil ambang atas warna coklat + tutup warna coklat 74,500.00 125,160.00
0.840 m' Profil ambang bawah warna coklat + tutup warna coklat 110,600.00 92,904.00
5.355 m' Profil stoper pintu warna coklat 21,300.00 114,061.50
5.355 m' Karet tatapan 3,400.00 18,207.00
1.282 m2 Kaca Bening 5 mm 157,500.00 201,922.88
1.000 set Handle Pintu 420,000.00 420,000.00
3.000 Bh Engsel Pintu 4" 54,600.00 163,800.00
11.000 buah Skrup Fixer 475.00 5,225.00
0.803 Tube Sealant Kusen + kaca 33,600.00 26,989.20
0.440 m' Profil Spigot 12,200.00 5,368.00
0.594 m2 Sticker Sandblast 52,500.00 31,185.00
2.100 m' Bulu Moher 4,000.00 8,400.00
C PERALATAN
D Jumlah A + B + C 2,218,906.10
E Overhead & Profit 15% 332,835.92
F Harga Satuan Pekerjaan (D+E) 2,551,742.02

5 HITUNG J2 1.000 Unit Pemasangan Kusen dan Jendela Kaca Mati Rangka Alumunium ( J2) 1,991,057.19
A TENAGA 251,476.15
L.01 1.383 OH Pekerja 80,000.00 110,671.68
L.02 1.383 OH Tukang Besi 90,000.00 124,505.64
L.03 0.081 OH Kepala Tukang 105,000.00 8,537.14
L.04 0.074 OH Mandor 105,000.00 7,761.69
B BAHAN 1,479,877.93
8.232 m' Alumunium Warna Coklat 4" tipe Z tbl 1 mm 106,375.00 875,679.00
7.854 m' Tutup profil Z Alumunium warna coklat 36,725.00 288,438.15
1.600 m2 Kaca Bening 5 mm 157,500.00 252,031.50
16.000 buah Skrup Fixer 475.00 7,600.00
1.235 Tube Sealant Kusen + Kaca 33,600.00 41,489.28
1.200 m' Profil Spigot 12,200.00 14,640.00
C PERALATAN
D Jumlah A + B + C 1,731,354.08
E Overhead & Profit 15% 259,703.11
F Harga Satuan Pekerjaan (D+E) 1,991,057.19
6 HITUNG J3 1.000 Unit Pemasangan Kusen dan Jendela Kaca Rangka Alumunium ( J3 ) 2,960,873.41
A TENAGA 259,082.82
L.01 0.854 OH Pekerja 80,000.00 68,318.08
L.02 1.854 OH Tukang Besi 90,000.00 166,857.84
L.03 0.185 OH Kepala Tukang 105,000.00 19,466.75
L.04 0.042 OH Mandor 105,000.00 4,440.16
B BAHAN 2,315,589.71
8.232 m' Profil open back warna coklat 57,900.00 476,632.80
3.654 m' Rangka casement 3 profil warna coklat 51,600.00 188,546.40
1.176 m' Alumunium Warna Coklat 4" tipe Z tbl 1 mm 95,800.00 112,660.80
7.728 m' Tutup profil Z Alumunium warna coklat 33,000.00 255,024.00
3.654 m' Karet tatapan 3,400.00 12,423.60
1.304 m2 Kaca Bening 5 mm 157,500.00 205,428.83
4.000 Set Cesement 12" 229,900.00 919,600.00
2.000 Bh Rambuncis 31,500.00 63,000.00
16.000 buah Skrup Fixer 475.00 7,600.00
1.235 Tube Sealant Kusen + Kaca 33,600.00 41,489.28
2.720 m' Profil Spigot 12,200.00 33,184.00
C PERALATAN
D Jumlah A + B + C 2,574,672.53
E Overhead & Profit 15% 386,200.88
F Harga Satuan Pekerjaan (D+E) 2,960,873.41
7 HITUNG J4 1.000 Unit Pemasangan Kusen dan Jendela Kaca Rangka Alumunium ( J4 ) 1,624,335.57
A TENAGA 259,082.82
L.01 0.854 OH Pekerja 80,000.00 68,318.08
L.02 1.854 OH Tukang Besi 90,000.00 166,857.84
L.03 0.185 OH Kepala Tukang 105,000.00 19,466.75
L.04 0.042 OH Mandor 105,000.00 4,440.16
B BAHAN 1,153,382.89
3.906 m' Profil open back warna coklat 57,900.00 226,157.40
2.489 m' Rangka casement 3 profil warna coklat 51,600.00 128,406.60
0.536 m' Alumunium Warna Coklat 4" tipe Z tbl 1 mm 95,800.00 51,300.90
4.158 m' Tutup profil Z Alumunium warna coklat 33,000.00 137,214.00
2.489 m' Karet tatapan 3,400.00 8,460.90
0.478 m2 Kaca Bening 5 mm 157,500.00 75,344.85
2.000 Set Cesement 12" 229,900.00 459,800.00
1.000 Bh Rambuncis 31,500.00 31,500.00
8.000 buah Skrup Fixer 475.00 3,800.00
0.586 Tube Sealant Kusen + Kaca 33,600.00 19,686.24
0.960 m' Profil Spigot 12,200.00 11,712.00
C PERALATAN
D Jumlah A + B + C 1,412,465.71
E Overhead & Profit 15% 211,869.86
F Harga Satuan Pekerjaan (D+E) 1,624,335.57

8 HITUNG J5 1.000 Unit Pemasangan Kusen dan Jendela Kaca Mati Rangka Alumunium ( J5 ) 10,785,989.70
A TENAGA 259,082.82
L.01 0.854 OH Pekerja 80,000.00 68,318.08
L.02 1.854 OH Tukang Besi 90,000.00 166,857.84
L.03 0.185 OH Kepala Tukang 105,000.00 19,466.75
L.04 0.042 OH Mandor 105,000.00 4,440.16
B BAHAN 9,120,038.66
29.416 m' Alumunium Warna Coklat 4" tipe Z tbl 1 mm 95,800.00 2,818,028.85
32.099 m' Tutup profil Z Alumunium warna coklat 33,000.00 1,059,250.50
29.416 m' Karet tatapan 3,400.00 100,013.55
16.249 m2 Kaca Bening 8 mm 303,700.00 4,934,745.38
59.000 buah Skrup Fixer 475.00 28,025.00
4.412 Tube Sealant Kusen + Kaca 33,600.00 148,255.38
2.600 m' Profil Spigot 12,200.00 31,720.00
C PERALATAN
D Jumlah A + B + C 9,379,121.48
E Overhead & Profit 15% 1,406,868.22
F Harga Satuan Pekerjaan (D+E) 10,785,989.70
9 HITUNG J6 1.000 Unit Pemasangan Kusen dan Jendela Kaca Mati Rangka Alumunium ( J6 ) 1,669,486.99
A TENAGA 259,082.82
L.01 0.854 OH Pekerja 80,000.00 68,318.08
L.02 1.854 OH Tukang Besi 90,000.00 166,857.84
L.03 0.185 OH Kepala Tukang 105,000.00 19,466.75
L.04 0.042 OH Mandor 105,000.00 4,440.16
B BAHAN 1,192,644.99
6.636 m' Alumunium Warna Coklat 4" tipe Z tbl 1 mm 95,800.00 635,728.80
6.447 m' Tutup profil Z Alumunium warna coklat 33,000.00 212,751.00
6.636 m' Karet tatapan 3,400.00 22,562.40
1.759 m2 Kaca Bening 5 mm 157,500.00 277,102.35
13.000 buah Skrup Fixer 475.00 6,175.00
0.995 Tube Sealant Kusen + Kaca 33,600.00 33,445.44
0.400 m' Profil Spigot 12,200.00 4,880.00
C PERALATAN
D Jumlah A + B + C 1,451,727.81
E Overhead & Profit 15% 217,759.17
F Harga Satuan Pekerjaan (D+E) 1,669,486.99

10 HITUNG PJ1 1.000 Unit Pemasangan Kusen dan Pintu Jendela Kaca Rangka Alumunium ( PJ1 ) 5,761,758.36
A TENAGA 280,765.63
L.01 0.518 OH Pekerja 80,000.00 41,420.00
L.02 2.089 OH Tukang Besi 90,000.00 187,987.50
L.03 0.343 OH Kepala Tukang 105,000.00 35,988.75
L.04 0.146 OH Mandor 105,000.00 15,369.38
B BAHAN 4,729,459.04
6.132 m' Profil open back warna coklat 57,900.00 355,042.80
9.500 m' Alumunium Warna Coklat 4" tipe Z tbl 1 mm 95,800.00 910,100.00
11.720 m' Tutup profil Z Alumunium warna coklat 33,000.00 386,760.00
2.567 m' Profil tiang engsel warna coklat (belakang) 99,000.00 254,157.75
2.567 m' Profil tiang swing warna coklat (depan) 92,800.00 238,240.80
1.806 m' Profil ambang atas warna coklat + tutup warna coklat 74,500.00 134,547.00
0.903 m' Profil ambang bawah warna coklat + tutup warna coklat 110,600.00 99,871.80
6.132 m' Profil stoper pintu warna coklat 21,300.00 130,611.60
15.632 m' Karet tatapan 3,400.00 53,148.80
9.103 m2 Kaca Bening 5 mm 157,500.00 1,433,755.21
1.000 set Handle Pintu 420,000.00 420,000.00
3.000 Bh Engsel Pintu 4" 54,600.00 163,800.00
31.000 buah Skrup Fixer 475.00 14,725.00
2.345 Tube Sealant Kusen + kaca 33,600.00 78,785.28
1.240 m' Profil Spigot 12,200.00 15,128.00
0.594 m2 Sticker Sandblast 52,500.00 31,185.00
2.400 m' Bulu Moher 4,000.00 9,600.00
C PERALATAN
D Jumlah A + B + C 5,010,224.66
E Overhead & Profit 15% 751,533.70
F Harga Satuan Pekerjaan (D+E) 5,761,758.36
11 HITUNG BV 1.000 Unit Pemasangan Boven ( BV1 ) 622,129.39
A TENAGA 211,981.04
L.01 0.600 OH Pekerja 80,000.00 48,018.64
L.02 1.600 OH Tukang Besi 90,000.00 144,020.97
L.03 0.160 OH Kepala Tukang 105,000.00 16,802.45
L.04 0.030 OH Mandor 105,000.00 3,138.99
B BAHAN 329,001.04
2.331 m' Profil open back warna coklat 57,900.00 134,964.90
1.974 m' Glassbead casement 33,000.00 65,142.00
1.890 m' Profil tutup polos 32,500.00 61,425.00
2.331 m' Karet tatapan 3,400.00 7,925.40
0.231 m2 Kaca es kabur t : 5 mm 175,500.00 40,540.50
5.000 buah Skrup Fixer 475.00 2,375.00
0.350 Tube Sealant Kusen + Kaca 33,600.00 11,748.24
0.400 m' Profil Spigot 12,200.00 4,880.00
C PERALATAN
D Jumlah A + B + C 540,982.08
E Overhead & Profit 15% 81,147.31
F Harga Satuan Pekerjaan (D+E) 622,129.39

12 HITUNG PKM 1.000 Unit Pemasangan Kusen dan Pintu Kamar Mandi Rangka Alumunium ( PKM ) 2,529,740.67
A TENAGA 280,765.63
L.01 0.518 OH Pekerja 80,000.00 41,420.00
L.02 2.089 OH Tukang Besi 90,000.00 187,987.50
L.03 0.343 OH Kepala Tukang 105,000.00 35,988.75
L.04 0.146 OH Mandor 105,000.00 15,369.38
B BAHAN 1,919,008.87
5.250 m' Profil open back warna coklat 57,900.00 303,975.00
2.210 m' Profil tiang engsel warna coklat (belakang) 99,000.00 218,814.75
2.210 m' Profil tiang swing warna coklat (depan) 92,800.00 205,111.20
1.470 m' Profil ambang atas warna coklat + tutup warna coklat 74,500.00 109,515.00
0.735 m' Profil ambang bawah warna coklat + tutup warna coklat 110,600.00 81,291.00
5.250 m' Profil stoper pintu warna coklat 21,300.00 111,825.00
0.588 m' Glassbead casement 33,000.00 19,404.00
9.639 m' sprandell warna coklat lebar 10 cm 15,000.00 144,585.00
1.176 m' hollow 1x2 15,000.00 17,640.00
5.250 m' Karet tatapan 3,400.00 17,850.00
0.162 m2 Kaca es kabur t : 5 mm 175,500.00 28,359.92
1.000 set Handle Pintu 420,000.00 420,000.00
3.000 Bh Engsel Pintu 4" 54,600.00 163,800.00
11.000 buah Skrup Fixer 475.00 5,225.00
0.788 Tube Sealant Kusen + kaca 33,600.00 26,460.00
0.440 m' Profil Spigot 12,200.00 5,368.00
0.594 m2 Sticker Sandblast 52,500.00 31,185.00
2.150 m' Bulu Moher 4,000.00 8,600.00
C PERALATAN
D Jumlah A + B + C 2,199,774.50
E Overhead & Profit 15% 329,966.17
F Harga Satuan Pekerjaan (D+E) 2,529,740.67
OE
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
CK #REF!
#REF! A. 1.1.1 HARGA SATUAN PEKERJAAN PERSIAPAN
1 Err:509 Err:509 m2 Err:509
2 #REF! #REF! m2 #REF!

II A.1.5.1 HARGA SATUAN PEKERJAAN TANAH


1 A.1.5.1.13 Pemasangan 1 m2 Lapisan Ijuk tebal 10 cm unt Bidang Resapan m2 160,511.25

III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


1 A.3.2.1.9. Pemasangan 1 m3 Batu Kosong (Aanstamping) untuk Pondasi Gedung m3 518,983.50

IV A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N


1 A.4.1.1.1 Membuat 1 m3 Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87 m3 994,089.90
2 A.4.1.1.2 Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 m3 1,038,090.05
3 A.4.1.1.3 Membuat 1 m3 Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72 m3 1,072,611.90
4 A.4.1.1.4 Membuat 1 m3 Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 m3 915,006.14
5 A.4.1.1.5 Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 m3 1,113,401.25
6 A.4.1.1.6 Membuat 1 m3 Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61 m3 1,152,425.35
7 A.4.1.1.7 Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 m3 1,181,558.30
8 A.4.1.1.8 Membuat 1 m3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 1,200,913.95
9 A.4.1.1.9 Membuat 1 m3 Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53 m3 1,234,181.15
10 A.4.1.1.10 Membuat 1 m3 Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 m3 1,244,511.60
12 A.4.1.1.17 Pemasangan 1 kg Jaring Anyaman Tulangan Tunggal (Wiremesh) M6-M8 secara manual 1kg 20,846.05
13 A.4.1.1.18 Memasang 1 m2 Bekisting untuk Pondasi Telapak Beton Bangunan Gedung m2 141,306.25
14 A.4.1.1.19 Memasang 1 m2 Bekisting untuk Sloof, Balok Latei, Ring Balk, Kolom Praktis Beton bangunan Gedung m2 147,947.50
15 A.4.1.1.20 Memasang 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung m2 322,856.08
HITUNG BK1 Memasang 1 m2 Bekisting untuk Kolom Beton Bangunan Gedung m2 210,101.41
16 A.4.1.1.21 Memasang 1 m2 Bekisting untuk Balok Bangunan Gedung m2 331,629.29
HITUNG BK2 Memasang 1 m2 Bekisting untuk Balok Bangunan Gedung m2 213,189.59
17 A.4.1.1.22 Memasang 1 m2 Bekisting untuk Plat Lantai m2 443,376.08
HITUNG BK3 Memasang 1 m2 Bekisting untuk Plat Lantai m2 302,866.88
18 A.4.1.1.23 Memasang 1 m2 Bekisting untuk Dinding Sheerwall m2 380,315.60
HITUNG BK4 Memasang 1 m2 Bekisting untuk Dinding Sheerwall m2 337,535.60
19 A.4.1.1.25 Memasang 1 m2 Bekisting untuk Tangga Beton Bangunan Gedung m2 466,668.85
20 A.4.1.1.28 Memasang Bekisting 1 m2 Jembatan untuk Pengecoran Beton m2 136,315.25

V A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK


1 A.4.1.2.5 Membuat 1m2 Begesting untuk Pelat Beton Pracetak Komponen Modular Bangunan Gedung ( 5x Pakai) m2 384,227.25
2 A.4.1.2.6 Membuat 1 m2 Begesting untuk Balok Beton Pracetak (10-12 kali pakai) m2 34,458.43
3 A.4.1.2.7 Membuat 1 m2 Begesting untuk Kolom Beton Pracetak (10-12 kali pakai) m2 32,043.43
4 A.4.1.2.8 Pemasangan dan Membuka 1 Unit Cetakan 1 buah Komponen Pelat Beton Pracetak unit 7,342.75
5 A.4.1.2.9 Pemasangan dan Membuka 1 unit Cetakan 1 buah Komponen Balok Beton Pracetak unit 11,896.75
6 A.4.1.2.10 Pemasangan dan Membuka1 unit Cetakan 1 buah Komponen Kolom Beton Pracetak unit 9,619.75
7 A.4.1.2.11 Penuangan/menebar 1 m3 beton untuk Pelat Beton Pracetak m3 57,015.85
8 A.4.1.2.12 Penuangan/menebar 1 m3 beton untuk Balok Beton Pracetak m3 58,643.10
9 A.4.1.2.13 Penuangan/menebar 1 m3 beton untuk Kolom Beton Pracetak m3 52,803.40
10 A.4.1.2.14 Pemasangan Komponen untuk 1 Unit Pelat Beton Pracetak beserta Indeks Kenaikan Lantai Ereksi Pelat hingga 24 Lantai unit 354,774.14
11 A.4.1.2.15 Pemasangan Komponen untuk 1 unit Balok Beton Pracetak beserta Indeks Kenaikan Lantai Ereksi Pelat hingga 24 Lantai unit 372,124.83
12 A.4.1.2.17 Pemindahan komponen untuk 1 Unit pelat pracetak (± 20m) unit 89,528.34
13 A.4.1.2.18 Pemindahan komponen untuk 1 Unit balok pracetak (± 20m) unit 89,528.34
14 A.4.1.2.19 Pemindahan komponen untuk 1 Unit kolom pracetak (± 20m) unit 89,528.34
15 A.4.1.2.22 Pekerjaan Grout pada 1 titik Joint Beton Pracetak ttk 45,890.75
16 A.4.1.2.23 Pemasangan 1 titik Begesting Joint Pracetak ttk 89,762.79
17 A.4.1.2.24 Pemasangan 1 titik Joint dengan Sling ttk 46,615.25

VI A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.1 Pembuatan 1 kg Besi Profil + Meni kg 38,350.20
HITUNG BP1 Pembuatan 1 kg Besi Profil + Meni kg 34,283.80
2 A.4.2.1.2 Pemasangan 1kg Rangka Kuda-kuda Baja IWF kg 36,363.00
3 A.4.2.1.3 Pengerjaan 100 kg Pekerjaan Perakitan (Kuda-kuda Baja) 100kg 94,859.13
4 A.4.2.1.4 Pembuatan 1 m2 Pintu Besi Plat Baja tebal 2 mm rangkap, rangka baja Siku m2 304,021.13
5 A.4.2.1.7 Pemasangan 1 m2 Pintu Rolling Door Besi m2 1,020,958.50
6 A.4.2.1.8 Pemasangan 1 m2 Pintu Lipat (Folding Door) bahan plastik / PVC m2 979,489.50
7 A.4.2.1.9 Pemasangan 1 m2 Sunscreen Allumunium m2 870,803.00
8 A.4.2.1.9 Pemasangan 1 m2 Rolling Door Allumunium m2 1,112,107.50
9 A.4.2.1.15 Pemasangan 1 m2 Teralis Besi Strip (20x3) mm m2 503,583.39
10 A.4.2.1.16 Pemasangan 1 m2 Kawat Nyamuk m2 108,022.28
11 A.4.2.1.17 Pemasangan 1 m2 Jendela Nako & Tralis m2 432,683.48
12 A.4.2.1.18 Pemasangan 1 m' Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm m 186,620.28

Harsat Pekerjaan 11
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
13 A.4.2.1.19 Pemasangan 1 m' Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm m 86,225.85
16 A.4.2.1.22 Pemasangan 1 m2 Atap Pelana Rangka Atap Baja Ringan profil C75 m2 177,872.49
17 A.4.2.1.23 Pemasangan 1 m2 Atap Limasan Rangka Atap Baja Ringan profil C75 m2 194,564.97
18 A.4.2.1.24 Pemasangan 1 m2 Kusen Aluminium m2 101,519.70
19 A.4.2.1.25 Pemasangan 1 m2 Pintu Aluminium Strip lbr 8 cm m2 1,112,031.03
20 A.4.2.1.26 Pemasangan 1 m2 Pintu Kaca rangka Aluminium m2 574,536.55
21 A.4.2.1.27 Pemasangan 1 m2 Venetions Blinds dan Vertical Blinds m2 352,549.75

VII A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


1 A.4.4.1.1. Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 batu dengan Mortar tipe M, fc' 17,2 Mpa (Setara Camp. 1SP: 2PP) m2 297,487.18
2 A.4.4.1.2. Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 batu dengan Mortar tipe M, fc' 12,5 Mpa (Setara Camp. 1SP: 3PP) m2 282,481.00
3 A.4.4.1.3. Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 batu dengan Mortar tipe M, fc' 5,2 Mpa (Setara Camp. 1SP: 4PP) m2 272,150.32
4 A.4.4.1.4. Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 batu dengan Mortar tipe M, fc' 2,4 Mpa (Setara Camp. 1SP: 5PP) m2 267,135.57
5 A.4.4.1.5. Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 batu Campuran 1SP: 6PP) m2 266,112.65
6 A.4.4.1.7. Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu dengan Mortar tipe M, fc' 17.7 Mpa (Setara Camp. 1SP: 2PP) m2 143,468.77
7 A.4.4.1.8 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu dengan Mortar tipe S, fc' 12,5 Mpa (Setara Camp. 1SP: 3PP) m2 136,225.26
8 A.4.4.1.9 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu dengan Mortar tipe N, fc' 5,2 Mpa (Setara Camp. 1SP: 4PP) m2 132,145.01
9 A.4.4.1.10 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu dengan Mortar tipe O, fc' 2,4 Mpa (Setara Camp. 1SP: 5PP) m2 129,583.15
10 A.4.4.1.11 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu Campuran 1SP: 6PP) m2 128,326.89
11 A.4.4.1.12 Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP m2 125,502.38
12 A.4.4.1.13 Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP m2 125,732.38
13 A.4.4.1.14 Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1SM : 1PP m2 110,729.13
14 A.4.4.1.15 Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1KP : 1SM : 2PP m2 112,320.73
11 A.4.4.1.16 Pemasangan 1 m2 Dinding Conblock HB20 dengan mortar Camp. 1SP : 3PP m2 342,118.33
12 A.4.4.1.17 Pemasangan 1 m2 Dinding Conblock HB20 dengan mortar Camp. 1SP : 4PP m2 343,396.10
13 A.4.4.1.18 Pemasangan 1 m2 Dinding HB/CB 15, speci camp. 1SP : 3PP m2 276,038.53
14 A.4.4.1.19 Pemasangan 1 m2 Dinding HB/CB 15, speci camp. 1SP : 4PP m2 276,742.67
15 A.4.4.1.20 Pemasangan 1 m2 Dinding Conblock HB10, dengan mortar camp. 1SP : 3PP m2 210,053.94
16 A.4.4.1.21 Pemasangan 1 m2 Dinding Conblock HB10, dengan mortar camp. 1SP : 4PP m2 211,218.14
17 A.4.4.1.22 Pemasangan 1 m2 Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 3PP m2 586,320.60
18 A.4.4.1.23 Pemasangan 1 m2 Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP m2 586,320.60
19 A.4.4.1.24 Pemasangan 1 m2 Dinding bata berongga ekspose Uk, (12x11x24)cm Camp. 1SP : 3PP m2 215,750.12
20 A.4.4.1.25 Pemasangan 1 m2 Dinding bata ringan tbl. 7,5cm dengan mortar siap pakai m2 154,790.72
21 A.4.4.1.26 Pemasangan 1 m2 Dinding bata ringan tbl. 10cm dengan mortar siap pakai m2 179,295.96

VIII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A.4.4.2.19 Pemasangan 1 m2 Berapen 1 Pc : 5Pp Tebal 15 mm m2 39,117.02
2 A.4.4.2.20 Pemasangan 1 m2 Plesteran Skoning 1 Pc : 3Pp, lebar 10 mm m2 58,335.71
3 A.4.4.2.23 Pemasangan 1 m2 Plesteran Ciprat 1Pc : 2 Pp m2 49,872.51
4 A.4.4.2.24 Pemasangan 1 m2 Finishing Siar Pasangan Dinding Bata Merah (=20 m') m2 28,766.45
5 A.4.4.2.25 Pemasangan 1 m2 Finishing Siar Pasangan Dinding Conblock ekspose (=8 m') m2 13,742.50
6 A.4.4.2.26 Pemasangan 1 m2 Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp m2 60,653.65

IX A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING


1 A.4.4.3.1 Pemasangan 1 m2 lantai Ubin PC Abu-abu Uk. 40 x 40 cm m2 134,615.55
2 A.4.4.3.2 Pemasangan 1 m2 lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 142,936.95
3 A.4.4.3.3 Pemasangan 1 m2 lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 254,504.20
4 A.4.4.3.5 Pemasangan 1 m2 lantai Ubin PC Warna Uk. 30 x 30 cm m2 188,850.70
5 A.4.4.3.6 Pemasangan 1 m2 lantai Ubin PC Warna Uk. 20 x 20 cm m2 271,754.20
6 A.4.4.3.9 Pemasangan 1 m2 lantai Ubin Granit Uk. 40 x 40 cm m2 337,741.20
7 A.4.4.3.10 Pemasangan 1 m2 lantai Ubin Granit Uk. 30 x 30 cm m2 538,812.95
8 A.4.4.3.12 Pemasangan 1 m2 lantai Ubin Teralux Uk. 30 x 30 cm m2 641,191.70
9 A.4.4.3.13 Pemasangan 1 m2 lantai Ubin Teralux Marmer Uk. 60 x 60 cm m2 440,746.70
10 A.4.4.3.14 Pemasangan 1 m2 lantai Ubin Teralux Marmer Uk. 40 x 40 cm m2 397,058.20
11 A.4.4.3.15 Pemasangan 1 m2 lantai Ubin Teralux Marmer Uk. 30 x 30 cm m2 665,376.20
27 A.4.4.3.31 Pemasangan 1 m2 Lantai Teraso cor di tempat tebal 3cm m2 57,956.55
28 A.4.4.3.32 Pemasangan 1 m2 Lantai Keramik Artistik 10 s.d <20 cm m2 476,454.49
29 A.4.4.3.33 Pemasangan 1 m2 lantai Keramik Artistik Uk. 20 s.d <30 cm m2 468,691.99
30 A.4.4.3.34 Pemasangan 1 m2 Lantai Keramik 33 x 33 cm m2 321,284.70
31 A.4.4.3.35 Pemasangan 1 m2 Lantai Keramik Uk. 20 s.d <30 cm m2 209,832.45
32 A.4.4.3.36 Pemasangan 1 m2 Lantai Keramik Uk. 30 s.d <40 cm m2 221,591.20
33 A.4.4.3.37 Pemasangan 1 m2 Lantai Keramik uk. 30 s.d <40 cm, untuk variasi / border m2 546,494.95
37 A.4.4.3.42 Pemasangan 1 m2 Lantai Marmer Ukuran 100x100 cm m2 1,225,058.49
38 A.4.4.3.43 Pemasangan 1 m2 Lantai Karpet m2 205,344.00
39 A.4.4.3.46 Pemasangan 1 m2 Lantai Kayu Gymfloor m2 554,610.50
40 A.4.4.3.48 Pemasangan 1 m2 Dinding Porselen 10 x 20 cm m2 391,033.01
41 A.4.4.3.52 Pemasangan 1 m2 Dinding Keramik 10x20 cm, m2 294,893.01
42 A.4.4.3.53 Pemasangan 1 m2 Dinding Keramik 20x20 cm, m2 271,950.51
43 A.4.4.3.54 Pemasangan 1 m2 Dinding Marmer Ukuran 100x100 cm m2 1,742,072.90

Harsat Pekerjaan 12
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
44 A.4.4.3.57 Pemasangan 1 m2 Dinding Batu Paros / Batu Tempel Hitam m2 323,144.54
46 A.4.4.3.59 Pemasangan 1 m2 Wallpaper lbr 50cm m2 297,717.75
47 A.4.4.3.60 Pemasangan 1 m2 Floor Hardener m2 60,133.50
50 A.4.4.3.63 Pemasangan 1 m2 Paving Block (Block Beton) Natural tbl. 6cm m2 189,399.25
51 A.4.4.3.64 Pemasangan 1 m2 Paving Block (Block Beton) Natural tbl. 8cm m2 247,958.40
52 A.4.4.3.65 Pemasangan 1 m2 Paving Block (Block Beton) berwarna tbl. 6cm m2 203,836.70
53 A.4.4.3.66 Pemasangan 1 m2 Paving Block (Block Beton) berwarna tbl. 8cm m2 269,806.22

X A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT


1 A.4.5.1.1 Pemasangan 1 m2 Langit-langit Asbes (1,00x1,00) m, tebal 4 mm m2 36,341.04
2 A.4.5.1.2 Pemasangan 1 m2 Langit-langit Akustik Ukuran (30x30) cm m2 678,080.25
3 A.4.5.1.3 Pemasangan 1 m2 Langit-langit Akustik Ukuran (30x60) cm m2 432,923.25
4 A.4.5.1.4 Pemasangan 1 m2 Langit-langit Akustik Ukuran (60x120) cm m2 140,093.00
5 A.4.5.1.5 Memasang 1 m2 Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm, 4 mm & 6 mm m2 48,276.43
6 A.4.5.1.6 Memasang 1 m2 Langit-langit Lambriziring Kayu Jati, tebal 9 mm m2 841,269.85
7 A.4.5.1.7 Memasang 1 m2 Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm m2 50,917.17
8 A.4.5.1.10 Memasang 1m list Langit-langit kayu profil m2 23,395.60
9 A.4.5.1.12 Memasang 1 m2 Langit-langit Akustik uk. 60cm x 120cm + rangka aluminium m2 537,866.50
HITUNG Memasang 1 m2 Langit-Langit Gypsum Board tbl 9mm + Rangka Hollow Galvanis m2 233,302.28
HITUNG PF.1 Memasang 1 m2 Langit-langit GRC Board tebal 4 mm + Rangka Hollow Galvanis m2 132,587.81

XI A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


1 A.4.5.2.1 Pemasangan 1 m2 Atap Genteng Plentong Kecil m2 70,871.63
2 A.4.5.2.2 Pemasangan 1 m2 Atap Genteng Kodok Glasur m2 194,557.00
3 A.4.5.2.3 Pemasangan 1 m2 Atap Genteng Plentong Besar / Morando m2 102,844.50
4 A.4.5.2.4 Pemasangan 1m Genteng Plentong Kecil m 103,119.12
5 A.4.5.2.5 Pemasangan 1 m Genteng Bubung Kodok Glasur m 246,006.62
6 A.4.5.2.6 Pemasangan 1 m Genteng Bubung Plentong Besar m 140,091.62
7 A.4.5.2.7 Pemasangan 1 m2 Roof Light Fiberglass 90cm x 180cm m2 166,489.81
16 A.4.5.2.19 Pemasangan 1 m2 Atap Asbes Gelombang 300cmx108cmx6mm m2 61,740.05
17 A.4.5.2.20 Pemasangan 1 m2 Atap Asbes Gelombang 270cmx108cmx6mm m2 62,748.60
18 A.4.5.2.21 Pemasangan 1 m2 Atap Asbes Gelombang 240cmx108cmx6mm m2 66,056.00
19 A.4.5.2.22 Pemasangan 1 m2 Atap Asbes Gelombang 210cmx108cmx6mm m2 62,854.40
20 A.4.5.2.23 Pemasangan 1 m2 Atap Asbes Gelombang 180cmx108cmx6mm m2 61,918.30
21 A.4.5.2.24 Pemasangan 1m Nok/Bubung Setel Gelombang 92 cm m 140,190.75
22 A.4.5.2.25 Pemasangan 1m Nok/Bubung Setel Gelombang 105 cm m 201,773.25
23 A.4.5.2.26 Pemasangan 1m Nok/Bubung Setel Gelombang 108 cm m 196,770.75
27 A.4.5.2.30 Pemasangan 1m Nok/Bubung Setel Rata 92 cm m 74,755.75
28 A.4.5.2.31 Pemasangan 1m Nok/Bubung Setel Rata 105 cm m 90,683.25
29 A.4.5.2.32 Pemasangan 1 m2 Genteng Beton m2 106,452.05
30 A.4.5.2.33 Pemasangan 1 m2 Genteng Aspal 80cm x 100cm m2 362,108.55
31 A.4.5.2.35 Pemasangan 1 m2 Atap Sirap kayu m2 134,003.75
32 A.4.5.2.36 Pemasangan 1m Nok/Bubung Genteng Beton m 197,953.87
33 A.4.5.2.37 Pemasangan 1m Nok/Bubung Genteng Aspal m 282,222.48
34 HITUNG AT.1 Pemasangan 1 m Nok/Bubung Genteng Tanah Liat lokal m 49,634.00
35 A.4.5.2.39 Pemasangan 1m Nok/Bubung atap Sirap m 100,165.00
36 A.4.5.2.40 Pemasangan 1 m2 atap seng gelombang 105cmx180cm m2 90,134.70
37 A.4.5.2.41 Pemasangan 1m Nok/Bubung atap seng m 66,954.15
38 A.4.5.2.42 Pemasangan 1 m2 atap aluminium gelombang 95cm x 180cm m2 236,621.70
39 A.4.5.2.43 Pemasangan 1m nok/bubung atap aluminium gelombang m 190,863.20
40 A.4.5.2.44 Pemasangan 1 m2 Lapisan Aluminium Foil m2 35,759.25
41 A.4.5.2.45 Pemasangan 1 m2 atap asbes gelombang 105cm x 270cm x 4mm m2 66,782.80

XII A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U


1 HITUNG K.1 Pembuatan & Pemasangan 1m3 Kusen Pintu & Kusen Jendela, Kayu kruing m3 13,599,537.75
2 A.4.6.1.2 Pembuatan & Pemasangan 1m3 Kusen Pintu & Kusen Jendela, Kayu klas II atau III m3 18,626,187.75
3 A.4.6.1.3 Pembuatan & Pemasangan 1m2 Pintu Klamp Standard Kayu Klas II (Kayu Kamfer) m2 512,234.73
4 A.4.6.1.4 Pembuatan & Pemasangan 1m2 Pintu Klamp Sederhana Kayu Klas III m2 506,740.60
5 A.4.6.1.5 Pembuatan 1m2 Daun Pintu Panel, Kayu Klas I atau II m2 835,744.10
6 A.4.6.1.6 Pembuatan 1m2 Pintu & Jendela Kaca, Kayu Klas I atau II m2 590,398.96
7 A.4.6.1.7 Pembuatan 1m2 Pintu & Jendela Jalusi Kayu Kruing m2 1,104,057.50
8 A.4.6.1.8 Pembuatan 1m2 Daun Pintu kayu lapis (Plywood) Rangkap, Rangka Kayu Kelas II (lbr s/d 90 cm) m2 641,779.93
9 A.4.6.1.9 Pembuatan 1m2 Pintu Plywood rangkap, rangka expose kayu klas I atau II m2 691,505.07
10 A.4.6.1.10 Pembuatan & Pemasangan 1m2 Jalusi mati Kosen Kayu Klas I atau II m2 3,017,151.50
11 A.4.6.1.11 Pembuatan 1m2 Pintu Teakwood Rangkap, Rangka Expose Kayu Klas I m2 1,568,067.55
12 A.4.6.1.12 Pembuatan 1m2 Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas II m2 769,297.68
13 A.4.6.1.13 Pemasangan 1m3 Konstruksi Kuda-kuda Konvensional Kayu I; II & III Bentang 6 meter m3 11,860,122.50
14 A.4.6.1.14 Pemasangan 1m3 Konstruksi Kuda-kuda Expose, Kayu Klas I m3 42,560,999.75
15 A.4.6.1.15 Pemasangan 1m3 konstruksi Gording, Kayu Klas II m3 15,996,649.50
16 HITUNG K.4 Pemasangan 1m2 Rangka Atap Usuk & Reng kayu kelas II m2 109,131.21

Harsat Pekerjaan 13
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
17 A.4.6.1.17 Pemasangan 1m2 Rangka Atap Genteng Beton, Kayu Klas II m2 200,889.94
18 A.4.6.1.18 Pemasangan 1m2 Rangka Atap Sirap, Kayu Klas II m2 1,473,427.73
19 A.4.6.1.19 Pemasangan 1m2 Rangka Langit-langit (50x1,00) m, kayu Klas II atau III m2 196,597.49
20 A.4.6.1.20 Pemasangan 1m2 Rangka Langit-langit (60x60) cm, kayu Klas II atau III m2 202,308.84
21 A.4.6.1.21 Pemasangan 1m' Lisplank Uk. (3x20)cm, Kayu klas I atau II m 517,609.25
22 A.4.6.1.22 Pemasangan 1m' Lisplank Uk. (3x30)cm Kayu klas I atau klas II m2 130,235.32
23 A.4.6.1.23 Pemasangan 1m2 Rangka Dinding Pemisah (60x120) cm Kayu klas II atau III m2 314,983.62
24 A.4.6.1.24 Pemasangan 1m2 Dinding Pemisah Teakwood Rangkap Rangka Kayu Klas II m2 421,764.00
25 A.4.6.1.25 Pemasangan 1m2 Dinding Pemisah Plywood Rangkap Rangka Kayu Klas II m2 421,195.32
26 A.4.6.1.26 Pemasangan 1m2 Dinding Lambrisering dari Papan klas I m2 581,812.31
27 A.4.6.1.27 Pemasangan 1m2 Dinding Lambrisering dari Plywood ukuran (120x240) cm m2 40,250.00
28 A.4.6.1.28 Pemasangan 1m2 Dinding Bilik, Rangka Kayu Klas III atau IV m2 151,740.55

XIII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA


1 A.4.6.2.1 Pemasangan 1 Buah Kunci Tanam Antik bh 264,977.25
2 A.4.6.2.2 Pemasangan 1 Buah Kunci Tanam Biasa bh 143,836.25
3 A.4.6.2.3 Pemasangan 1 Buah Kunci Kamar Mandi bh 143,074.38
4 A.4.6.2.4 Pemasangan 1 Buah Kunci Selinder bh 314,539.38
5 A.4.6.2.5 Pemasangan 1 Buah Engsel Pintu bh 156,011.88
6 A.4.6.2.6 Pemasangan 1 Buah Engsel Jendela Kupu-kupu bh 56,007.88
7 A.4.6.2.7 Pemasangan 1 Buah Engsel Angin bh 121,730.38
8 A.4.6.2.8 Pemasangan 1 Buah Spring Knip untuk Jendela bh 173,782.25
9 A.4.6.2.9 Pemasangan 1 Buah Kait Angin bh 90,867.25
10 A.4.6.2.10 Pasang 1 Buah Door Closer bh 683,344.38
11 A.4.6.2.11 Pemasangan 1 Buah Kunci Selot bh 109,600.75
12 A.4.6.2.12 Pemasangan 1 Buah Doorholder bh 133,934.75
13 A.4.6.2.13 Pemasangan 1 Buah Door Stop bh 69,776.25
14 A.4.6.2.14 Pemasangan 1 Buah Rel Pintu Dorong bh 1,088,262.25
15 A.4.6.2.15 Pemasangan 1 Buah Kunci Lemari bh 190,740.73
16 A.4.6.2.16 Pemasangan 1 m2 Kaca tebal 3 mm m2 160,147.85
17 A.4.6.2.17 Pemasangan 1 m2 Kaca tebal 5 mm m2 219,982.35
18 A.4.6.2.18 Pemasangan 1 m2 Kaca Polos tebal 8 mm m2 408,205.73
19 A.4.6.2.19 Pemasangan 1 m2 Kaca Buram tebal 12 mm m2 344,866.03

XIV A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


1 A.4.7.1.22 Pengecatan 1 m2 Permukaan Baja Galvanis Secara Semprot Sistem 3 Lapis Cat Terakhir m2 135,654.00

XV A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DAN PERPIPAAN DALAM GEDUNG


1 A.5.1.1.1 Memasang 1 Buah Closet Duduk / Mono Blok Ex. Toto Seri CW702J/SW784JP bh 4,954,591.00
2 A.5.1.1.2 Memasang 1 Buah Closet Jongkok Porselen bh 743,152.21
4 A.5.1.1.4 Memasang 1 Buah Urinoir bh 1,409,766.60
5 A.5.1.1.5 Memasang 1 Buah Wastafel Seri CE-7 White Ex. Toto bh 1,023,136.60
6 A.5.1.1.6 Pemasangan 1 Buah Bak Mandi Teraso bh 2,060,742.50
7 A.5.1.1.7 Pemasangan 1 Buah Bak Fibreglass vol.1 m3 bh 1,099,894.50
8 A.5.1.1.8 Memasang 1 Buah Bak Mandi Batu Bata Vol. 0,30 m3 bh 1,914,370.50
9 A.5.1.1.9 Memasang 1 Buah Bathup Porselen bh 2,883,268.50
10 A.5.1.1.10 Memasang 1 Buah Bak Beton bh 6,178,721.29
11 A.5.1.1.11 Memasang 1 Buah Bak Air Fiberglass bh 324,852.00
12 A.5.1.1.16 Pemasangan 1 Buah Bak Kontrol Pas.Batu Bata 30x30 tinggi 35 cm dengan Tutup Beton bh 471,664.45
13 A.5.1.1.17 Pemasangan 1 Buah Bak Kontrol Pas.Batu Bata 45x45 tinggi 50 cm dengan Tutup Beton bh 713,968.30
14 A.5.1.1.18 Pemasangan 1 Buah Bak Kontrol Pas.Batu Bata 60x60 tinggi 65 cm dengan Tutup Beton bh 885,259.19
15 A.5.1.1.19 Pemasangan 1 m' Pipa Galvanis Ø ½" m' 87,642.46
HITUNG PG1 Pemasangan 1 m' Pipa Galvanis Ø ½" m' 69,832.79
16 A.5.1.1.20 Pemasangan 1 m' Pipa Galvanis Ø ¾" m' 107,042.00
HITUNG PG2 Pemasangan 1 m' Pipa Galvanis Ø ¾" m' 84,226.00
17 A.5.1.1.21 Pemasangan 1 m' Pipa Galvanis Ø 1" m' 151,961.00
HITUNG PG3 Pemasangan 1 m' Pipa Galvanis Ø 1" m' 117,553.00
18 A.5.1.1.22 Pemasangan 1 m' Pipa Galvanis Ø 1½ " m' 231,518.00
HITUNG PG4 Pemasangan 1 m' Pipa Galvanis Ø 1½ " m' 179,860.00
19 A.5.1.1.23 Pemasangan 1 m' Pipa Galvanis Ø 3" m' 494,194.29
HITUNG PG5 Pemasangan 1 m' Pipa Galvanis Ø 3" m' 376,809.96
20 A.5.1.1.24 Pemasangan 1 m' Pipa Galvanis Ø 4" m' 1,017,387.75
HITUNG PG6 Pemasangan 1 m' Pipa Galvanis Ø 4" m' 764,985.75
21 A.5.1.1.25 Pemasangan 1 m' Pipa PVC tipe AW Ø ½" m' 21,316.69
HITUNG PG7 Pemasangan 1 m' Pipa PVC tipe AW Ø ½" m' 18,522.19
22 A.5.1.1.26 Pemasangan 1 m' Pipa PVC tipe AW Ø ¾" m' 33,838.75
HITUNG PG8 Pemasangan 1 m' Pipa PVC tipe AW Ø ¾" m' 27,812.75
23 A.5.1.1.27 Pemasangan 1 m' Pipa PVC tipe AW Ø 1" m' 27,466.31
HITUNG PG9 Pemasangan 1 m' Pipa PVC tipe AW Ø 1" m' 23,084.81

Harsat Pekerjaan 14
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
24 A.5.1.1.28 Pemasangan 1 m' Pipa PVC tipe AW Ø 1½" m' 57,056.29
HITUNG PG10 Pemasangan 1 m' Pipa PVC tipe AW Ø 1½" m' 46,391.96
25 A.5.1.1.29 Pemasangan 1 m' Pipa PVC tipe AW Ø 2" m' 72,682.88
HITUNG PG11 Pemasangan 1 m' Pipa PVC tipe AW Ø 2" m' 57,985.88
26 A.5.1.1.30 Pemasangan 1 m' Pipa PVC tipe AW Ø 2½" m' 80,488.50
HITUNG PG12 Pemasangan 1 m' Pipa PVC tipe AW Ø 2½" m' 65,791.50
27 A.5.1.1.31 Pemasangan 1 m' Pipa PVC tipe AW Ø 3" m' 170,237.38
HITUNG PG13 Pemasangan 1 m' Pipa PVC tipe AW Ø 3" m' 132,379.38
28 A.5.1.1.32 Pemasangan 1 m' Pipa PVC tipe AW Ø 4" m' 237,437.63
HITUNG PG14 Pemasangan 1 m' Pipa PVC tipe AW Ø 4" m' 182,237.63
29 A.5.1.1.33 Pemasangan 1 Buah Bak Cuci Piring Stainless stell bh 332,378.75
30 A.5.1.1.34 Pemasangan 1 Buah Bak Cuci Piring Teraso bh 1,159,769.25
31 A.5.1.1.35 Pemasangan 1 Buah Kran Ø ½" atau Ø ¾" bh 144,437.13
32 A.5.1.1.36 Pemasangan 1 Buah Floor Drain bh 115,661.25
33 A.5.1.1.37 Pemasangan 1 m' Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm m' 137,761.49
34 A.5.1.1.38 Pemasangan 1 m' Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm m' 61,267.34
35 A.5.1.1.39 Pemasangan 1 m' Pipa Beton Ø 15-20 cm m' 127,445.47
36 A.5.1.1.40 Pemasangan 1 m' Pipa Beton Ø 30-100 cm m' 650,543.39

XVIII HARGA SATUAN ASPAL (Mengikuti Analisa Harga Terbaru Bina Marga)

Harsat Pekerjaan 15
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
UM #REF!
#REF! 1.1 HARGA SATUAN PEKERJAAN PERSIAPAN
1 1.1.a.(c) Pembuatan 1m' Pagar Sementara dari Kayu Tinggi 2 m m' 796,561.53
2 1.1.b.(c) Pembuatan 1 m' Pagar Sementara dari Seng Gelombang Tinggi 2 m m' 961,376.66
3 1.1.c.(c) Membuat 1 m' Pagar Sementara dari Kawat Duri Tinggi 1.8 m m' 460,809.60
4 1.7.4.d.(a) Pasang 1m' Bouwplank sebagai acuan dalam pembuatan infrastruktur m' 69,416.76
5 1.1.e.(c) Pembuatan 1 m2 Kantor Sementara/ Gudang dg Lantai Plesteran, dinding setengah tembok m2 2,765,961.60
6 1.1.f.(c) Pembersihan dan Pengupasan 1 m2 Permukaan Tanah (Striping) s.d Tanaman Ø 2cm m2 9,803.75
7 1.1.h.(a) Pembongkaran 1 m3 Dinding Tembok Bata m3 617,348.75
8 1.1.2.a Pemagaran 1 m' daerah kerja dengan seng gelombang BJLS-30, tinggi 1,8 m dengan rangka baja L,40.40.4 m' 598,363.53
9 1.1.2.b Pemagaran 1 m' daerah kerja dengan seng gelombang BJLS-30, tinggi 1,8 m dengan rangka Kayu m' 435,537.90
10 1.1.3.(a) Pembuatan 1 unit Direksi Keet dan Gudang m2 1,627,904.78
11 1.1.4.a.(a) Pembuatan 1 buah Papan Nama pekerjaan dengan multiflex 18mm, frame Aluminium siku dan tiang kayu 8/12, printing ban bh 980,561.88
12 1.1.4.b.(a) Pembuatan 1 buah Papan Nama pekerjaan dengan multiflex 10mm, frame Aluminium siku dan tiang kayu 5/7, printing bann bh 416,320.13
13 1.1.5.a.(a) Investigasi Lapangan ls 77,625.00
14 2.1.2.a.5.c Pembongkaran 1m3 Pasangan batu dengan alat m3 38,120.83
15 2.1.4.b Pembongkaran 1m3 Pasangan bata merah dengan alat m3 20,803.00
16 2.2.10.a Pembongkaran 1m3 beton dengan alat m3 38,120.83

II 1.6 HARGA SATUAN PEKERJAAN BATU MUKA DAN BATU CANDI


1 1.6.1.a.(a) Pemasangan 1 m2 Pasangan Batu Muka m2 127,207.25
2 1.6.1.b.(a) Pemasangan 1 m2 Pasangan Batu Candi m2 170,228.75
3 1.6.3.(a) Pemasangan 1 m2 Pasangan Pipa Suling-suling m' 62,554.25

III 1.7 HARGA SATUAN PEKERJAAN TANAH


1 1.7.1.a.(c) Penggalian 1 m3 Tanah Biasa Sedalam s.d 1 m untuk volume s.d. 200 m3 Dalam Satu Lokasi m3 72,018.75
2 1.7.1.b.(c) Penggalian 1 m3 Tanah Lumpur Sedalam s.d 1 m m3 115,833.75
3 1.7.2.a.(c) Pengurugan Kembali 1 m3 Galian Tanah untuk Striping Tanaman Ø 2 cm m3 52,037.50
4 1.7.2.c.(c) Pemadatan Tanah 1 m3 per 20 cm dengan Alat Timbris untuk Striping Tanaman Ø 2 cm m3 52,037.50
5 1.7.2.d.(c) Pengurugan 1 m3 dengan Pasir Urug untuk Striping Tanaman Ø 2 cm m3 270,307.50
6 1.7.2.c.(c) Pengurugan dan Pemadatan 1 m3 Sirtu untuk Striping Tanaman Ø 2 cm m3 216,458.75
7 1.7.3.1.a.(a) 1 m2 Pembersihan dan Pengupasan Permukaan Tanah (striping) s.d. Tanaman Ø 2 cm m2 5,203.75
8 1.7.3.1.b.1.(a) Tebas Tebang 1 m2 Tanaman / Tumbuhan Ø < 5 cm m2 3,122.25
9 1.7.3.1.b.2.(a) Tebas Tebang 1 m2 Tanaman / Tumbuhan Ø > 5 s.d. 15 cm m2 5,203.75
10 1.7.3.1.b.3.(a) Tebas Tebang 1 m2 Tanaman / Tumbuhan Ø > 15 s.d. 30 cm m2 30,906.25
11 1.7.3.1.b.4.(a) Tebas Tebang 1 m2 Tanaman / Tumbuhan Ø > 30 s.d. 50 cm m2 40,780.15
12 1.7.3.1.b.5.(a) Tebas Tebang 1 m2 Tanaman / Tumbuhan Ø > 50 s.d. 75 cm m2 68,292.75
13 1.7.3.1.b.6.(a) Tebas Tebang 1 m2 Tanaman / Tumbuhan Ø > 75 cm m2 82,943.75
14 1.7.7.1.1.a.(a) Penggalian 1 m3 Tanah Biasa Sedalam s.d 1 m untuk volume 200 m3 s.d. 2000 m3 m3 58,594.23
15 1.7.7.1.1.b.(a) Penggalian 1 m3 Tanah Biasa Sedalam s.d 1 m untuk volume > 2000 m3 m3 41,630.00
16 1.7.7.1.1.c.(a) Penggalian 1 m3 Tanah Biasa Sedalam s.d 1 m untuk volume s.d. 200 m3 m3 72,018.75
17 1.7.7.1.1.d.(a) Penggalian 1 m3 Tanah Biasa Sedalam> 1 m s.d 2 m untuk volume 200 s.d. 2000 m3 m3 70,250.63
18 1.7.7.1.1.e.(a) Penggalian 1 m3 Tanah Biasa Sedalam > 1 m s.d 2 m untuk volume s.d. 200 m3 m3 88,233.75
19 1.7.7.1.1.f.(a) Penggalian 1 m3 Tanah Biasa Sedalam > 2 m s.d 3 m untuk volume 200 s.d. 2000 m3 m3 79,097.00
20 1.7.7.1.1.g.(a) Penggalian 1 m3 Tanah Biasa Sedalam > 2 m s.d 3 m untuk volume s.d. 200 m3 m3 104,690.25
21 1.7.7.1.1.h.(a) Penggalian 1 m3 Tanah Biasa > 3 m, setiap tambah kedalaman 1 m m3 7,805.63
22 1.7.8.2.a.(a) 1 m3 Menggali Tanah Berbatu Sedalam > 0 s.d. 1m untuk volume 200 m3 s.d 2000 m3 dengan alat m3 57,633.87
23 1.7.8.2.b.(a) 1 m3 Menggali Tanah Berbatu Sedalam > 1m s.d. 2 m untuk volume 200 m3 s.d 2000 m3 dengan alat m3 68,038.84
24 1.7.8.2.c.(a) 1 m3 Menggali Tanah Berbatu Sedalam > 2m s.d 3m untuk volume 200 m3 s.d 2000 m3 dengan alat m3 81,527.60
25 1.7.8.2.d.(a) 1 m3 Menggali Tanah Berbatu > 3m, setiap tambah dalam 1 m untuk volume 200 m3 s.d 2000 m3 dengan alat m3 16,301.08
26 1.7.9.2.a.(a) 1 m3 Menggali Tanah Cadas/Keras Sedalam > 0 s.d 1m untuk volume 200 m3 s.d 2000 m3 dengan alat m3 45,409.56
27 1.7.9.2.b.(a) 1 m3 Menggali Tanah Cadas/Keras Sedalam > 1 s.d 2m untuk volume 200 m3 s.d 2000 m3 dengan alat m3 54,281.60
28 1.7.9.2.c.(a) 1 m3 Menggali Tanah Cadas/Keras Sedalam > 2 s.d 3m untuk volume 200 m3 s.d 2000 m3 dengan alat m3 65,025.56
29 1.7.9.2.d.(a) 1 m3 Menggali Tanah Cadas/Keras Sedalam > 3m untuk volume 200 m3 s.d 2000 m3 dengan alat m3 11,791.97
30 1.7.10.2.a.(a) 1 m3 Menggali Tanah Lumpur Sedalam > 0 s.d 1m dengan alat m3 25,898.00
31 1.7.10.2.b.(a) 1 m3 Menggali Tanah Lumpur Sedalam >1 m s.d 2 m dengan alat m3 31,780.25
32 1.7.10.2.c.(a) 1 m3 Menggali Tanah Lumpur Sedalam > 2 s.d 3m dengan alat m3 32,616.88
33 1.7.10.2.d.(a) 1 m3 Menggali Tanah Lumpur Sedalam > 3 m setiap tambah kedalaman 1 m m3 2,507.00
34 1.7.11.2.a.(a) Penggalian 1 m3 Tanah Pasir Sedalam > 0 s.d. 1 m dengan alat m3 27,720.75
35 1.7.11.2.b.(a) Penggalian 1 m3 Tanah Pasir Sedalam > 1 s.d. 2 m dengan alat m3 29,920.13
36 1.7.11.2.c.(a) Penggalian 1 m3 Tanah Pasir Sedalam > 2 s.d. 3 m m3 32,204.60
37 1.7.11.2.d.(a) Penggalian 1 m3 Tanah Pasir Sedalam > 3 m untuk setiap tambah dalam 1 m m3 3,205.63
38 1.7.14.a.(a) 1 m3 Timbunan atau Urugan Kembali Tanah biasa/ liat berpasir, termasuk perataan dan perapihan m3 98,313.50

Harsat Pekerjaan 16
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
39 1.7.14.b(a) 1 m3 Timbunan atau Urugan Kembali Tanah Liat termasuk perataan dan perapihan m3 113,473.38
40 1.7.14.c.(a) 1 m3 Pemadatan Tanah m3 16,019.09
41 1.7.14.d.(a) 1 m3 Pemadatan Tanah 1 m3 per 20 cm dengan alat timbris m3 52,037.50
42 1.7.2.d(c) 1 m3 Timbunan Pasir m3 274,595.85
43 1.7.14.f.(a) 1 m3 Pemadatan Pasir m3 8,558.88
44 1.7.15.1.a.(a) Mengangkut 1 m3 tanah lepas, jarak angkut s.d. 10 m m3 20,624.68
45 1.7.15.1.b.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 10 s.d. 20 m m3 22,089.20
46 1.7.15.1.c.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 20 s.d. 30 m m3 23,164.45
47 1.7.15.1.d.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 30 s.d. 40 m m3 24,555.38
48 1.7.15.1.e.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 40 s.d. 50 m m3 26,684.60
49 1.7.15.1.f.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 50 s.d. 100 m m3 33,724.90
50 1.7.15.1.g.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 100 s.d. 200 m m3 47,477.75
51 1.7.15.1.h.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 200 s.d. 300 m m3 63,843.98
52 1.7.15.1.i.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 300 s.d. 400 m m3 83,077.73
53 1.7.15.1.j.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 400 s.d. 500 m m3 107,222.55
54 1.7.15.1.k.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 500 s.d. 600 m m3 135,056.00
55 1.7.15.1.l.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 600 untuk setiap penambahan jarak angkut 100 m m3 26,954.28
56 1.7.15.2.a.(a) Menurunkan 1 m3 material, sampai beda tinggi > 0 s.d. 1 m m3 3,921.50
57 1.7.15.2.b.(a) Menurunkan 1 m3 material, sampai beda tinggi > 1 s.d. 2 m m3 5,686.18
58 1.7.15.2.c.(a) Menurunkan 1 m3 material, sampai beda tinggi > 2 s.d. 3 m m3 7,542.85
59 1.7.15.2.d.(a) Menurunkan 1 m3 material, sampai beda tinggi > 3 s.d. 4 m m3 9,607.68
60 1.7.15.2.e.(a) Menurunkan 1 m3 material, sampai beda tinggi > 4 s.d. 5 m m3 11,764.50
61 1.7.15.2.f.(a) Menurunkan 1 m3 material, sampai beda tinggi > 5 s.d. 6 m m3 13,921.33
62 1.7.15.2.g.(a) Menurunkan 1 m3 material, sampai beda tinggi > 6 s.d. 7 m m3 16,274.23
63 1.7.15.2.h.(a) Menurunkan 1 m3 material, sampai beda tinggi > 7 s.d. 8 m m3 18,627.13
64 1.7.15.2.i.(a) Menurunkan 1 m3 material, sampai beda tinggi > 8 s.d. 9 m m3 21,176.10
65 1.7.15.2.j.(a) Menurunkan 1 m3 material, sampai beda tinggi > 9 s.d. 10 m m3 23,621.00
66 1.7.15.2.k.(a) Menurunkan 1 m3 material, sampai beda tinggi > 10 m untuk setiap tambahan 1 m m3 2,352.90
67 1.7.15.3.a.(a) Menaikkan 1 m3 material, sampai beda tinggi > 0 s.d. 1 m m3 19,607.50
68 1.7.15.3.b.(a) Menaikkan 1 m3 material, sampai beda tinggi > 1 s.d. 2 m m3 28,626.95
69 1.7.15.3.c.(a) Menaikkan 1 m3 material, sampai beda tinggi > 2 s.d. 3 m m3 38,038.55
70 1.7.15.3.d.(a) Menaikkan 1 m3 material, sampai beda tinggi > 3 s.d. 4 m m3 48,234.45
71 1.7.15.3.e.(a) Menaikkan 1 m3 material, sampai beda tinggi > 4 s.d. 5 m m3 58,626.43
72 1.7.15.3.f.(a) Menaikkan 1 m3 material, sampai beda tinggi > 5 s.d. 6 m m3 69,606.63
73 1.7.15.3.g.(a) Menaikkan 1 m3 material, sampai beda tinggi > 6 s.d. 7 m m3 81,175.05
74 1.7.15.3.h.(a) Menaikkan 1 m3 material, sampai beda tinggi > 7 s.d. 8 m m3 93,135.63
75 1.7.15.3.i.(a) Menaikkan 1 m3 material, sampai beda tinggi > 8 s.d. 9 m m3 105,684.43
76 1.7.15.3.j.(a) Menaikkan 1 m3 material, sampai beda tinggi > 9 s.d. 10 m m3 118,429.30
77 1.7.16.a.(a) 1 m3 Pencampuran Tanah dan Semen m3 236,560.75
78 1.7.16.b.(a) 1 m3 Pencampuran Tanah dan Semen + Pemadat Timbris m3 109,710.00
79 1.7.16.c.(a) 1 m3 Pencampuran Tanah dan Semen + Pemadat Stamper m3 54,954.40

IV 2.1 HARGA SATUAN PEKERJAAN PONDASI


1 2.1.1.a.(a) Pemasangan 1 m3 Pondasi Batu Belah Mortar Tipe S (12,5 Mpa), Campuran 1SP : 3PP m3 1,014,270.10
2 2.1.1.b.(a) Pemasangan 1 m3 Pondasi Batu Belah Mortar Tipe N (5,2 Mpa), Campuran 1SP : 4PP m3 957,309.45
3 2.1.1.c.(a) Pemasangan 1 m3 Pondasi Batu Belah Mortar Tipe O (2,4 Mpa), Campuran 1SP : 5PP m3 917,814.54
4 2.1.1.d.(a) Pemasangan 1 m3 Pondasi Batu Belah Campuran 1SP : 6PP m3 890,051.01
5 2.1.1.e.(a) Pemasangan 1 m3 Pondasi Sumuran, Diameter 100 cm Masif m3 978,875.17
6 2.1.2.a.1.b.(a) Pasangan 1m3 Batu Belah dengan Mortar tipe M, fc' 17,2 MPA dengan molen untuk beda tinggi > 0 s.d. 1 m' m3 1,014,916.40
7 2.1.2.a.2.a.(c) Pemasangan 1 m3 Pondasi Batu Belah Mortar Tipe S m3 988,395.10
8 2.1.2.a.2.c.(a) Pasangan 1m3 Batu untuk tembok penahan tanah dengan Mortar tipe S, fc' 12,5 Mpa dengan molen untuk beda tinggi > 0 s m3 941,923.60
9 2.1.2.a.3.a.(a) Pasangan 1m3 Batu untuk tembok penahan tanah dengan Mortar tipe N, fc' 5,2 Mpa (setara 1PC : 4PP) untuk beda tinggi > m3 931,434.45
10 2.1.2.a.3.c.(a) Pasangan Batu 1m3 untuk tembok penahan tanah dengan Mortar tipe N, fc' 5,2 Mpa dengan molen untuk beda tinggi > 0 s. m3 884,962.95
11 2.1.2.a.4.a.(a) Pasangan 1m3 Batu untuk tembok penahan tanah dengan Mortar tipe O, fc' 2,4 Mpa (setara 1PC : 5PP) untuk beda tinggi > m3 890,243.29
12 2.1.2.a.4.c.(a) Pasangan Batu 1m3 untuk tembok penahan tanah dengan Mortar tipe O (setara 1 PC : 5 PP), fc' 2,4 Mpa dengan molen untuk m3 843,771.79
13 2.1.2.a.5.c.(a) Bongkar 1m3 Pasangan batu dan pembersihan batu dengan jack hammer m3 38,120.83
14 2.1.2.a.5.d.(a) Pembersihan 1m3 bongkaran pasangan batu untuk pemanfaatan kembali material batu m3 21,027.34

V 2.1.3.(a) HARGA SATUAN PASANGAN BATA MERAH


1 2.1.3.1.b.(c) Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 bata Camp. 1SP: 2PP m2 297,487.18
2 2.1.3.1.c.(a) Pasangan Bata Merah 1m3 Pondasi Mortar tipe M, fc' = 17,2 Mpa (setara 1 PC : 2 PP) dengan molen, untuk beda tinggi > 0 s m3 949,047.47
3 2.1.3.2.b.(c) Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP m2 282,481.00
4 2.1.3.2.c.(a) Pemasangan Bata Merah 1 m3 Pondasi dengan Mortar tipe S, fc' = 12,5 Mpa (setara 1 PC : 3 PP) dengan molen, untuk beda t m3 881,361.92

Harsat Pekerjaan 17
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
5 2.1.3.3.b.(c) Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP m2 272,150.32
6 2.1.3.3.c.(a) Mortar tipe N, fc' = 5,2 Mpa (setara 1 PC : 4 PP) dengan molen, untuk beda tinggi > 0 s.d. 1 m' m3 843,360.74
7 2.1.3.3.b.(c) Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP m2 267,135.57
8 2.1.3.4.b.(a) Pemasangan Bata Merah 1 m3 dengan Mortar tipe O, fc' = 2,4 Mpa (setara 1 PC : 5 PP) dengan molen, untuk beda tinggi > 0 m3 824,182.77
9 2.1.3.5.b.(a) Pemasangan bata merah 1 m3 dengan Mortar campuran 1 PC : 6 PP dengan molen, untuk beda tinggi > 0 s.d. 1 m' m3 821,448.07
10 2.1.4.b.(a) Bongkar 1 m3 Pasangan Bata Merah dengan Jack Hammer m3 20,803.00

VI 2.2.2 HARGA SATUAN PEKERJAAN BETON


1 2.2.2.1.b Membuat 1 m3 Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87 m3 994,029.53
2 2.2.2.1.c Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 m3 1,038,029.68
3 2.2.2.1.e Membuat 1 m3 Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72 m3 1,072,551.53
4 2.2.2.1.f Membuat 1 m3 Beton mutu f'c=14,5 Mpa (K175), slum (12±2)cm, w/c = 0,66 m3 1,113,340.88
5 2.2.2.1.g Membuat 1 m3 Beton mutu f'c=16,9 Mpa (K200), slum (12±2)cm, w/c = 0,61 m3 1,152,364.98
6 2.2.2.1.i Membuat 1 m3 Beton mutu f'c=19,3 Mpa (K225), slum (12±2)cm, w/c = 0,58 m3 1,181,497.93
2.2.1.2 HARGA SATUAN PEKERJAAN BETON secara SEMI MEKANIS
7 2.2.1.2.a Membuat 1 m3 Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87 m3 951,835.07
8 2.2.1.2.b Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 m3 995,639.72
9 2.2.1.2.c Membuat 1 m3 Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72 m3 1,030,161.57
10 A.4.1.1.5 Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 m3 1,070,950.92
11 2.2.1.2.e Membuat 1 m3 Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61 m3 1,103,937.52
12 2.2.1.2.f Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 m3 1,133,070.47
13 2.2.1.2.g Membuat 1 m3 Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 1,152,426.12
14 2.2.1.2.h Membuat 1 m3 Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53 m3 1,185,693.32
15 TM.04.2.b.7 Pembuatan dan Pengecoran 1 m3 Campuran Beton fc' = 26,4 Mpa (K-300), slum (12±2)cm m3 1,149,009.33
16 2.2.3.a 1 m3 Pengecoran Beton menggunakan Ready Mixed dan Pompa Beton m3 1,444,005.76
17 2.2.5.a.(a) Pemadatan 1 m3 beton saat pengecoran dengan vibrator m3 11,441.48
18 2.2.6.1.a.(a) Penulangan Pelat untuk 100 kg Besi Beton Ø ≤ 12 mm, Cara Manual 100kg 1,923,260.00
19 2.2.6.1.c.(a) Penulangan Pelat untuk 100 kg Besi Beton Ø ≥ 12 mm, Cara Semi Mekanis 100kg 1,821,131.00
20 2.2.6.1.d.(a) Pembesian kolom, balok, ring balk dan sloof untuk 100 kg Besi Beton Ø ≤ 12 mm 100kg 2,147,556.00
HITUNG PB Pembesian kolom, balok, ring balk dan sloof untuk 100 kg Besi Beton Ø ≤ 12 mm (semi mekanis) 100kg 1,851,068.01
21 2.2.6.1.e.(a) Pembesian kolom, balok, ring balk dan sloof untuk 100 kg Besi Beton Ø > 12 mm, semi mekanis 100kg 1,875,218.01
22 2.2.7.b.(a) Pembesian 100 kg Jaring Kawat (Wiremesh M6) untuk Pelat atau Dinding atau Ferrocement, Cara Semi Mekanis 100kg 2,016,511.25
23 2.2.8.c.(a) Menaikkan 100 kg tulangan setiap Kenaikan Vertikal 4 m atau Tambahan Jarak Horisontal 25 m ke Tapak Pemasangan Me 100kg 116,955.00
24 2.2.8.1.a.(a) Menggenangi 100 m2 Permukaan Beton dengan Air Selama 4 hari 100 m2 27,042,767.50
25 2.2.8.1.c.(a) Menyirami 100 m2 Permukaan Beton Menggunakan Media Karung Goni Selama 4 hari 100 m2 841,225.00
26 2.2.10.a.(a) Bongkar 1 m3 Beton dengan Jack Hammer m3 20,815.00
27 2.2.11.a.(a) Pemasangan 1m' waterstop PVC lebar 150 mm m' 283,777.45
28 2.2.11.c.(a) Pemasangan 1m' waterstop PVC lebar 200 mm m' 356,397.08
29 2.2.11.e.(a) Pemasangan 1m' waterstop PVC lebar 230-320 mm m' 222,292.70
30 2.2.11.f.(a) Pemasangan 1m' waterstop rubber lebar 150-200 mm m' 16,957.33
31 2.2.11.g.(a) Pemasangan 1m' PVC waterstop lebar 150 mm m' 13,153.13
32 2.2.11.h.(a) Pemasangan 1m' PVC waterstop lebar 200 mm m' 15,194.38
33 2.2.11.i.(a) Pemasangan 1m' PVC waterstop lebar 230 mm - 320 mm m' 16,269.63
34 2.2.12.a.(a) Pemasangan 1m3 Pondasi Siklop bertulang, 60% beton (fc' 14,5MPa / K-175) : 40% batu belah, secara manual m3 972,900.58
35 2.2.12.b.(a) Pemasangan 1m3 Pondasi Siklop bertulang, 60% beton (fc' 14,5MPa / K-175) : 40% batu belah, pakai molen m3 925,732.37
36 2.2.12.c.(a) Pemasangan 1m3 Pondasi Siklop bertulang, 70% beton (fc' 14,5MPa / K-175) : 30% batu belah, secara manual m3 1,139,429.78
37 2.2.12.d.(a) Pemasangan 1m3 Pondasi Siklop bertulang, 70% beton (fc' 14,5MPa / K-175) : 30% batu belah, pakai molen m3 1,075,506.64

VI 3.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 3.1.1.(c) Pengerjaan 1 kg Pekerjaan Perakitan Baja Profil m2 1,087,666.10
2 3.1.2.(c) Pembuatan 1 m2 Pintu Besi Plat Baja tebal 2 mm rangkap, rangka baja Siku m2 1,298,407.50
3 3.1.1.(c) Pengerjaan 1 m Pengelasan dengan Las Listrik 10 cm2 26,224.50
4 3.1.2.(c) Pembuatan 1m2 Rangka Jendela Besi Pipa Persegi 10 cm2 288,227.95

VII 3.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 3.2.1.(c) Pemasangan 1 m2 Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 77,248.72
2 3.2.2.(c) Pemasangan 1 m2 Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 69,343.16
3 3.2.1.(c) Pemasangan 1 m2 Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 65,978.72
4 3.2.2.(c) Pemasangan 1 m2 Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 63,635.94
5 3.2.1.(c) Pemasangan 1 m2 Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 62,370.02
6 3.2.2.(c) Pemasangan 1 m2 Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 61,329.96
7 3.2.1.(c) Pemasangan 1 m2 Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 60,778.42
8 3.2.2.1.1.a.(a) Siaran dengan Mortar Tipe M, fc' = 17,2 Mpa (setara 1 PC : 2 PP) m2 49,212.53

Harsat Pekerjaan 18
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
9 3.2.2.1.2.a.(a) Siaran dengan Mortar Tipe S, fc' = 12,5 Mpa (setara 1 PC : 3 PP) m2 48,435.54
10 3.2.2.2.1.(a) Trasraam Tebal 1 cm, dengan Mortar Campuran fc' = 25 Mpa (setara 1 PC : 1 PP) m2 42,307.90
11 3.2.2.2.2.(a) Trasraam Tebal 1 cm, dengan Mortar tipe M, fc' = 17,2 Mpa (setara 1 PC : 2 PP) m2 37,046.28
12 3.2.2.2.3.(a) Plesteran Tebal 1 cm, dengan Mortar tipe S, fc' = 12,5 Mpa (setara 1 PC : 3 PP) m2 34,803.32
13 3.2.2.2.4.(a) Plesteran Tebal 1 cm, dengan Mortar tipe N, fc' = 5,2 Mpa (setara 1 PC : 4 PP) m2 33,407.82
14 3.2.2.2.5.(a) Plesteran Tebal 1 cm, dengan Mortar tipe O, fc' = 2,4 Mpa (setara 1 PC : 5 PP) m2 32,397.52
15 3.2.2.2.6.(a) Plesteran Tebal 1 cm, dengan Mortar tipe fc' = 2,0 Mpa (setara 1 PC : 6 PP) m2 31,686.64
16 3.2.2.2.7.(a) Trasraam Tebal 1,5 cm, dengan Mortar tipe fc' = 25 Mpa (setara 1 PC : 1 PP) m2 59,055.72
17 3.2.2.2.8.(a) Pemasangan 1 m2 Plesteran 1 SP : 1 PP Tebal 15 mm m2 77,248.72
18 3.2.2.2.9.(a) Trasraam Tebal 1,5 cm, dengan Mortar tipe M, fc' = 17,2 Mpa (setara 1 PC : 2 PP) m2 51,150.16
19 3.2.2.2.10.(a) Pemasangan 1 m2 Plesteran 1 SP : 2 PP Tebal 15 mm m2 69,343.16
20 3.2.2.2.11.(a) Plesteran Tebal 1,5 cm, dengan Mortar tipe S, fc' = 12,5 Mpa (setara 1 PC : 3 PP) m2 47,785.72
21 3.2.2.2.12.(c) Pemasangan 1 m2 Plesteran 1 SP : 3 PP Tebal 15 mm m2 65,978.72
22 3.2.2.2.13.(a) Plesteran Tebal 1,5 cm, dengan Mortar tipe N, fc' = 5,2 Mpa (setara 1 PC : 4 PP) m2 45,705.60
23 3.2.2.2.14.(c) Pemasangan 1 m2 Plesteran 1 SP : 4 PP Tebal 15 mm m2 63,635.94
24 3.2.2.2.15.(a) Plesteran Tebal 1,5 cm, dengan Mortar tipe O, fc' = 2,4 Mpa (setara 1 PC : 5 PP) m2 44,177.02
25 3.2.2.2.16.(c) Pemasangan 1 m2 Plesteran 1 SP : 5 PP Tebal 15 mm m2 62,370.02
26 3.2.2.2.17.(a) Plesteran Tebal 1,5 cm, dengan Mortar Campuran (setara 1 PC : 6 PP) m2 43,136.96
27 3.2.2.2.18.(c) Pemasangan 1 m2 Plesteran 1 SP : 6 PP Tebal 15 mm m2 61,329.96
28 3.2.2.2.19.(a) Trasraam Tebal 2,0 cm, dengan Mortar Campuran fc' = 25 Mpa (setara 1 PC : 1 PP) m2 75,829.80
29 3.2.2.2.20.(a) Trasraam Tebal 2,0 cm, dengan Mortar Tipe M, Campuran fc' = 17,2 Mpa (setara 1 PC : 2 PP) m2 65,306.57
30 3.2.2.2.21.(a) Plesteran Tebal 2,0 cm, fc' = 12,5 Mpa (setara 1 PC : 3 PP) m2 60,820.65
31 3.2.2.2.22.(c) Pemasangan 1 m2 Plesteran 1SP : 3PP tebal 20 mm m2 74,333.93
32 3.2.2.2.23.(a) Plesteran tebal 2,0 cm dengan mortar tipe N, fc'= 5,2 Mpa (setara 1PC : 4PP) m2 58,029.64
33 3.2.2.2.24.(c) Pemasangan 1 m2 Plesteran 1SP : 4PP tebal 20 mm m2 85,089.42
34 3.2.2.2.25.(a) Plesteran tebal 2,0 cm dengan mortar tipe O, fc'= 2,4 Mpa (setara 1PC : 5PP) m2 56,009.05
35 3.2.2.2.26.(c) Pemasangan 1 m2 Plesteran 1SP : 5PP tebal 20 mm m2 83,489.08
36 3.2.2.2.27.(a) Plesteran tebal 2,0 cm dengan mortar campuran (setara 1PC : 6PP) m2 54,587.28
37 3.2.2.2.28.(c) Pemasangan 1 m2 Plesteran 1SP : 5PP tebal 20 mm m2 82,014.78
38 3.2.2.2.29.(a) Trasraam Tebal 2,5 cm, dengan Mortar Campuran (setara 1 PC : 1 PP) m2 92,603.89
39 3.2.2.2.30.(a) Trasraam Tebal 2,5 cm, dengan Mortar Tipe M, fc' = 17,2 MPa (setara 1 PC : 2 PP) m2 79,436.71
40 3.2.2.2.31.(a) Plesteran Tebal 2,5 cm, dengan Mortar Tipe S, fc' = 12,5 MPa (setara 1 PC : 3 PP) m2 73,829.31
41 3.2.2.2.32.(a) Plesteran Tebal 2,5 cm, dengan Mortar Tipe N, fc' = 5,2 MPa (setara 1 PC : 4 PP) m2 70,353.69
42 3.2.2.2.33.(a) Trasraam Tebal 2,5 cm, dengan Mortar Tipe O, fc' = 2,4 MPa (setara 1 PC : 5 PP) m2 67,814.81
43 3.2.2.2.34.(a) Trasraam Tebal 2,5 cm, fc' = 1,2 Mpa dengan Mortar Campuran (setara 1 PC : 6 PP) m2 66,037.60
44 3.2.2.2.35.(a) Pemasangan 1 m2 Acian m2 27,477.81

VIII 3.3 HARGA SATUAN PEKERJAAN PENGECATAN


1 Err:509 ### m2 Err:509
2 Err:509 ### m2 Err:509
3 Err:509 ### m2 Err:509
4 HITUNG PC.1 1 m2 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup) m2 50,397.60
5 3.3.5.(c) 1 m2 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 3 Lp Cat Penutup) m2 59,841.40
6 3.3.6.(c) 1 m2 Pelaburan Bidang Kayu dg Teak Oil m2 42,057.80
7 3.3.7.(c) 1 m2 Pelaburan Bidang Kayu dg Politur m2 45,595.89
8 3.3.8.(c) 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 13,305.50
9 3.3.9.(c) 1 m2 Pelaburan Bidang Kayu dg Vernis m2 42,872.00
10 HITUNG PC.2 1 m2 Pengecat Tembok Baru ( 1 Lap Plamuur, 1 Lap Cat Dasar, 2 lap. Cat penutup ) Ex. Envi m2 24,985.48
11 HITUNG PC.4 1 m2 Pengecatan Tembok Lama (1 lap Cat Dasar, 2 lap Cat Penutup) m2 21,081.80
12 3.3.12.(c) 1 m2 Peleburan Tembok Baru dengan Kapur Padam (Kapur Pemutih) m2 21,870.13
13 3.3.13.(c) 1 m2 Pelaburan Tembok Lama dengan Kapur Padam (Kapur Pemutih) m2 16,025.25
14 3.3.14.(c) 1 m2 Pengecatan Permukaan Baja dengan Menie Besi (Zinc Chromate) m2 30,848.18
15 3.3.15.(c) 1 m2 Pengecatan Permukaan Baja dengan Menie Besi (Zinc Chromate) dengan perancah m2 61,664.61
16 3.3.16.(c) 1 m2 Pengecatan Permukaan Baja Galvanis secara manual 4 lapis m2 68,408.33
17 3.3.17.(c) 1 m2 Pengecatan Permukaan Baja Galvanis secara Manual sistem 1 Lapis Cat Penutup m2 35,694.85
18 3.3.18.(c) 1 m2 Pengecatan Permukaan Baja Galvanis secara Manual sistem 3 Lapis m2 155,784.75
19 3.3.19.(c) 1 m2 Pengecatan Permukaan Baja Galvanis secara Semprot sistem 3 Lapis Cat Terakhir m2 135,654.00

IX 4.1 HARGA SATUAN PEKERJAAN PEKERJAAN PEMASANGAN PIPA DILUAR GEDUNG


1 4.1.1.(c) Pemasangan 1 m' Pipa PVC Ø 63 mm m' 50,068.70
2 4.1.2.(c) Pemasangan 1m' Pipa PVC Ø 90 mm m' 119,060.65
3 4.1.3.(c) Pemasangan 1m' Pipa PVC Ø 110 mm m' 132,310.18

Harsat Pekerjaan 19
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
4 4.1.4.(c) Pemasangan 1 m' Pipa PVC Ø 150 mm m' 178,052.97
5 4.1.5.(c) Pemasangan 1m' Pipa PVC Ø 200 mm m' 553,454.75
6 4.1.6.(c) Pemasangan 1m' Pipa PVC Ø 250 mm m' 875,434.43
7 4.1.7.(c) Pemasangan 1m' Pipa PVC Ø 300 mm m' 1,352,036.98
17 4.1.17.(c) Pemasangan 1m' Pipa HDPE Ø 63 mm m' 63,826.15
18 4.1.18.(c) Pemasangan 1m' Pipa HDPE Ø 100 mm m' 186,265.50
19 4.1.19.(c) Pemasangan 1m' Pipa HDPE Ø 125 mm m' 236,024.85
20 4.1.20.(c) Pemasangan 1m' Pipa HDPE Ø 150 mm m' 383,189.20
21 4.1.21.(c) Pemasangan 1m' Pipa HDPE Ø 200 mm m' 597,641.20
22 4.1.22.(c) Pemasangan 1m' Pipa HDPE Ø 250 mm m' 926,579.15
23 4.1.23.(c) Pemasangan 1m' Pipa HDPE Ø 300 mm m' 1,467,417.25
24 4.1.24.(c) Pemasangan 1m' Pipa HDPE Ø 400 mm m' 2,368,568.75
25 4.1.25.(c) Pemasangan 1m' Pipa HDPE Ø 450 mm m' 3,000,741.00
26 4.1.26.(c) Pemasangan 1m' Pipa HDPE Ø 500 mm m' 3,691,641.45
27 4.1.27.(c) Pemasangan 1m' Pipa HDPE Ø 600 mm m' 5,828,329.95
28 4.1.28.(c) Pemasangan 1m' Pipa HDPE Ø 800 mm m' 13,463,352.45
29 4.1.29.(c) Pemasangan 1m' Pipa HDPE Ø 900 mm m' 17,142,384.15
30 4.1.30.(c) Pemasangan 1m' Pipa HDPE Ø 1000 mm m' 21,114,943.00
31 4.1.31.(c) Pemasangan 1m' Pipa HDPE Ø 1100 mm m' 21,153,665.80
32 4.1.32.(c) Pemasangan 1m' Pipa HDPE Ø 1200 mm m' 29,185,050.75

X 4.2 HARGA SATUAN PEKERJAAN PEMOTONGAN PIPA


1 4.2.1.(c) Pemotongan 1 Buah Pipa PVC Ø 63 mm bh 1,007.40
2 4.2.2.(c) Pemotongan 1 m' Pipa PVC Ø 90 mm bh 2,401.78
3 4.2.3.(c) Pemotongan 1 Buah Pipa PVC Ø 110 mm bh 3,663.33
4 4.2.4.(c) Pemotongan 1 Buah Pipa PVC Ø 150 mm bh 5,016.88
5 4.2.5.(c) Pemotongan 1 Buah Pipa PVC Ø 200 mm bh 14,078.88
6 4.2.6.(c) Pemotongan 1 Buah Pipa PVC Ø 250 mm bh 22,668.80
7 4.2.7.(c) Pemotongan 1 Buah Pipa PVC Ø 300 mm bh 27,374.03
8 4.2.8.(c) Pemotongan 1 Buah Pipa PVC Ø 400 mm bh 59,395.20
9 4.2.9.(c) Pemotongan 1 Buah Pipa PVC Ø 450 mm bh 75,210.00
10 4.2.10.(c) Pemotongan 1 Buah Pipa PVC Ø 500 mm bh 93,238.55
11 4.2.11.(c) Pemotongan 1 Buah Pipa PVC Ø 600 mm bh 112,594.20
12 4.2.12.(c) Pemotongan 1 Buah Pipa PVC Ø 800 mm bh 198,863.75
13 4.2.13.(c) Pemotongan 1 Buah Pipa PVC Ø 900 mm bh 208,400.70
14 4.2.14.(c) Pemotongan 1 Buah Pipa PVC Ø 1000 mm bh 235,110.60
15 4.2.15.(c) Pemotongan 1 Buah Pipa PVC Ø 1100 mm bh 261,510.00
16 4.2.16.(c) Pemotongan 1 Buah Pipa PVC Ø 1200 mm bh 288,099.15
17 4.2.17.(c) Pemotongan 1 Buah Pipa HDPE Ø 63 mm bh 4,509.15
18 4.2.18.(c) Pemotongan 1 Buah Pipa HDPE Ø 100 mm bh 9,110.30
19 4.2.19.(c) Pemotongan 1 Buah Pipa HDPE Ø 125 mm bh 12,308.45
20 4.2.20.(c) Pemotongan 1 Buah Pipa HDPE Ø 150 mm bh 16,476.05
21 4.2.21.(c) Pemotongan 1 Buah Pipa HDPE Ø 200 mm bh 27,288.35
22 4.2.22.(c) Pemotongan 1 Buah Pipa HDPE Ø 250 mm bh 37,078.30
23 4.2.23.(c) Pemotongan 1 Buah Pipa HDPE Ø 300 mm bh 47,038.45
24 4.2.24.(c) Pemotongan 1 Buah Pipa HDPE Ø 400 mm bh 75,344.55
25 4.2.25.(c) Pemotongan 1 Buah Pipa HDPE Ø 450 mm bh 90,800.55
26 4.2.26.(c) Pemotongan 1 Buah Pipa HDPE Ø 500 mm bh 106,725.75
27 4.2.27.(c) Pemotongan 1 Buah Pipa HDPE Ø 600 mm bh 128,471.10
28 4.2.28.(c) Pemotongan 1 Buah Pipa HDPE Ø 800 mm bh 204,988.65
29 4.2.29.(c) Pemotongan 1 Buah Pipa HDPE Ø 900 mm bh 280,509.15
30 4.2.30.(c) Pemotongan 1 Buah Pipa HDPE Ø 1000 mm bh 335,160.60
31 4.2.31.(c) Pemotongan 1 Buah Pipa HDPE Ø 1100 mm bh 369,155.75
32 4.2.32.(c) Pemotongan 1 Buah Pipa HDPE Ø 1200 mm bh 459,396.25
33 4.2.33.(c) Pemotongan 1 Buah Pipa GIP Ø 63 mm bh 3,001.50
34 4.2.34.(c) Pemotongan 1 Buah Pipa GIP Ø 100 mm bh 8,995.30
35 4.2.35.(c) Pemotongan 1 Buah Pipa GIP Ø 125 mm bh 14,205.95
36 4.2.36.(c) Pemotongan 1 Buah Pipa GIP Ø 150 mm bh 20,300.95
37 4.2.37.(c) Pemotongan 1 Buah Pipa GIP Ø 200 mm bh 52,589.50
38 4.2.38.(c) Pemotongan 1 Buah Pipa GIP Ø 250 mm bh 73,359.65
39 4.2.39.(c) Pemotongan 1 Buah Pipa GIP Ø 300 mm bh 77,907.90
40 4.2.40.(c) Pemotongan 1 Buah Pipa GIP Ø 400 mm bh 114,174.30
41 4.2.41.(c) Pemotongan 1 Buah Pipa GIP Ø 450 mm bh 131,188.55

Harsat Pekerjaan 20
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
42 4.2.42.(c) Pemotongan 1 Buah Pipa GIP Ø 500 mm bh 145,587.70
43 4.2.43.(c) Pemotongan 1 Buah Pipa GIP Ø 600 mm bh 133,590.90
44 4.2.44.(c) Pemotongan 1 Buah Pipa GIP Ø 800 mm bh 242,361.35
45 4.2.45.(c) Pemotongan 1 Buah Pipa GIP Ø 900 mm bh 273,774.75
46 4.2.46.(c) Pemotongan 1 Buah Pipa GIP Ø 1000 mm bh 305,280.15
47 4.2.47.(c) Pemotongan 1 Buah Pipa GIP Ø 1100 mm bh 336,906.30
48 4.2.48.(c) Pemotongan 1 Buah Pipa GIP Ø 1200 mm bh 368,411.70
49 4.2.49.(c) Pemotongan 1 Buah Pipa DCI Ø 100 mm bh 9,363.30
50 4.2.50.(c) Pemotongan 1 Buah Pipa DCI Ø 125 mm bh 15,756.15
51 4.2.51.(c) Pemotongan 1 Buah Pipa DCI Ø 150 mm bh 23,213.90
52 4.2.52.(c) Pemotongan 1 Buah Pipa DCI Ø 200 mm bh 55,773.85
53 4.2.53.(c) Pemotongan 1 Buah Pipa DCI Ø 250 mm bh 73,053.75
54 4.2.54.(c) Pemotongan 1 Buah Pipa DCI Ø 300 mm bh 78,574.90
55 4.2.55.(c) Pemotongan 1 Buah Pipa DCI Ø 400 mm bh 146,928.60
56 4.2.56.(c) Pemotongan 1 Buah Pipa DCI Ø 450 mm bh 174,737.90
57 4.2.57.(c) Pemotongan 1 Buah Pipa DCI Ø 500 mm bh 199,468.65
58 4.2.58.(c) Pemotongan 1 Buah Pipa DCI Ø 600 mm bh 199,192.65
59 4.2.59.(c) Pemotongan 1 Buah Pipa DCI Ø 800 mm bh 381,857.50
60 4.2.60.(c) Pemotongan 1 Buah Pipa DCI Ø 900 mm bh 491,236.30
61 4.2.61.(c) Pemotongan 1 Buah Pipa DCI Ø 1000 mm bh 583,518.05
62 4.2.62.(c) Pemotongan 1 Buah Pipa DCI Ø 1100 mm bh 684,115.45
63 4.2.63.(c) Pemotongan 1 Buah Pipa DCI Ø 1200 mm bh 793,212.50
64 4.2.64.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 63 mm bh 10,566.20
65 4.2.65.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 100 mm bh 18,096.40
66 4.2.66.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 125 mm bh 24,507.65
67 4.2.67.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 150 mm bh 31,384.65
68 4.2.68.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 200 mm bh 70,587.00
69 4.2.69.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 250 mm bh 95,328.10
70 4.2.70.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 300 mm bh 106,216.30
71 4.2.71.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 400 mm bh 198,937.35
72 4.2.72.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 450 mm bh 194,252.25
73 4.2.73.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 500 mm bh 214,050.65
74 4.2.74.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 600 mm bh 200,078.15
75 4.2.75.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 800 mm bh 357,673.00
76 4.2.76.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 900 mm bh 404,031.80
77 4.2.77.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 1000 mm bh 450,773.55
78 4.2.78.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 1100 mm bh 497,224.35
79 4.2.79.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 1200 mm bh 543,966.10

XI 4.3 HARGA SATUAN PEKERJAAN PEMASANGAN AKSESORIS PIPA


1 4.3.1.(c) Pemasangan 1 Buah Valve Ø 150 mm bh 233,743.25
2 4.3.2.(c) Pemasangan 1 Buah Valve Ø 200 mm bh 312,502.15
3 4.3.3.(c) Pemasangan 1 Buah Valve Ø 250 mm bh 328,314.65
4 4.3.4.(c) Pemasangan 1 Buah Valve Ø 300 mm bh 388,412.50
5 4.3.5.(c) Pemasangan 1 Buah Valve Ø 400 mm bh 688,568.25
6 4.3.6.(c) Pemasangan 1 Buah Valve Ø 450 mm bh 688,568.25
7 4.3.7.(c) Pemasangan 1 Buah Valve Ø 500 mm bh 776,825.00
8 4.3.8.(c) Pemasangan 1 Buah Valve Ø 600 mm bh 314,706.70
9 4.3.9.(c) Pemasangan 1 Buah Valve Ø 700 mm bh 300,155.75
10 4.3.10.(c) Pemasangan 1 Buah Valve Ø 800 mm bh 355,360.35
11 4.3.11.(c) Pemasangan 1 Buah Valve Ø 900 mm bh 383,658.40
12 4.3.12.(c) Pemasangan 1 Buah Valve Ø 1000 mm bh 555,832.95
13 4.3.13.(c) Pemasangan 1 Buah Valve Ø 1100 mm bh 622,150.00
14 4.3.14.(c) Pemasangan 1 Buah Valve Ø 1200 mm bh 622,150.00
15 4.3.15.(c) Pemasangan 1 Buah Tee Ø 150 mm bh 471,901.35
16 4.3.16.(c) Pemasangan 1 Buah Tee Ø 200 mm bh 972,533.73
17 4.3.17.(c) Pemasangan 1 Buah Tee Ø 250 mm bh 56,639.23
18 4.3.18.(c) Pemasangan 1 Buah Tee Ø 300 mm bh 146,549.10
19 4.3.19.(c) Pemasangan 1 Buah Tee Ø 400 mm bh 180,577.60
20 4.3.20.(c) Pemasangan 1 Buah Tee Ø 450 mm bh 197,591.85
21 4.3.21.(c) Pemasangan 1 Buah Tee Ø 500 mm bh 230,418.60
22 4.3.22.(c) Pemasangan 1 Buah Tee Ø 600 mm bh 200,090.23
23 4.3.23.(c) Pemasangan 1 Buah Tee Ø 700 mm bh 239,178.73

Harsat Pekerjaan 21
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
24 4.3.24.(c) Pemasangan 1 Buah Tee Ø 800 mm bh 278,267.23
25 4.3.25.(c) Pemasangan 1 Buah Tee Ø 900 mm bh 322,415.73
26 4.3.26.(c) Pemasangan 1 Buah Tee Ø 1000 mm bh 363,559.85
27 4.3.27.(c) Pemasangan 1 Buah Tee Ø 1100 mm bh 400,750.85
28 4.3.28.(c) Pemasangan 1 Buah Tee Ø 1200 mm bh 444,899.35

XII 4.4 HARGA SATUAN PEKERJAAN PENYAMBUNGAN PIPA BARU KE PIPA LAMA
1 4.4.1.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 80 mm bh 1,334,535.40
2 4.4.2.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 100 mm bh 1,500,222.71
3 4.4.3.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 150 mm bh 1,914,440.98
4 4.4.4.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 200 mm bh 2,328,659.25
5 4.4.5.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 250 mm bh 2,742,877.53
6 4.4.6.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 300 mm bh 3,157,095.80
7 4.4.7.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 400 mm bh 3,985,532.34
8 4.4.8.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 450 mm bh 4,399,750.62
9 4.4.9.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 500 mm bh 4,813,968.89
10 4.4.10.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 600 mm bh 5,642,405.43
11 4.4.11.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 700 mm bh 6,470,841.98
12 4.4.12.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 800 mm bh 7,299,278.52

Harsat Pekerjaan 22
DAFTAR SEWA PERALATAN

SUMBER DATA :
PEKERJAAN : REHABILITASI SMP N 1 TERAS
LOKASI : SMP N 1 TERAS, BOYOLALI
TAHUN ANGGARAN : 2022
WILAYAH : I (SATU)

HARGA
NO. PERALATAN SATUAN (Rp) KET.

1 ASPHALT MIXING PLANT Jam 6,945,948.26


2 ASPHALT FINISHER Jam 235,842.34
3 POWER BROOM Jam 46,079.83
4 BULLDOZER 100-150 HP Jam 667,878.79
5 COMPRESSOR 4000-6500 L\M Jam 107,298.14
6 CONCRETE MIXER 0.3-0.6 M3 Jam 60,891.87
7 CRANE 10-15 TON Jam 548,200.96
8 DUMP TRUCK 3 - 4 M3 Jam 247,264.84
9 DUMP TRUCK 6-8 M3 Jam 256,955.38
10 EXCAVATOR 80-140 HP Jam 389,179.47
11 FLAT BED TRUCK 3-4 TON Jam 275,864.37
12 GENERATOR SET Jam 268,439.53
13 MOTOR GRADER >100 HP Jam 402,450.55
14 TRACK LOADER 75-100 HP Jam 309,736.47
15 WHEEL LOADER 1.0-1.6 M3 Jam 423,918.91
16 THREE WHEEL ROLLER 6-8 T Jam 200,727.38
17 TANDEM ROLLER 6-8 T. Jam 377,841.79
18 TANDEM ROLLER 8-10 T. Jam 387,506.18
19 TIRE ROLLER 8-10 T. Jam 538,694.35
20 VIBRATORY ROLLER 5-8 T. Jam 243,181.86
21 CONCRETE VIBRATOR Jam 33,863.95
22 STONE CRUSHER Jam 677,946.63
23 WATER PUMP 70-100 mm Jam 33,655.18
24 WATER TANKER 3000-4500 L. Jam 312,829.17
25 PEDESTRIAN ROLLER Jam 196,571.84
26 TAMPER Jam 57,825.61
27 JACK HAMMER Jam 32,531.45
28 FULVI MIXER Jam 567,876.11
29 CONCRETE PUMP Jam 344,530.86
30 MOLEN KAPASITAS 0.3 m3 Hari 66,666.67
31 TRAILER 20 TON Jam 472,863.44
32 PILE DRIVER + HAMMER Jam 127,512.81
33 CRANE ON TRACK 35 TON Jam 1,160,208.27
34 WELDING SET Jam 38,758.96
35 BORE PILE MACHINE Jam 582,140.82
36 ASPHALT LIQUID MIXER Jam 60,968.02
38 COLD MILLING Jam 1,299,835.57
39 ROCK DRILL BREAKER Jam 465,034.88
40 COLD RECYCLER Jam 2,508,531.56
41 HOT RECYCLER Jam 3,419,626.53
42 AGGREGAT (CHIP) SPREADER Jam 275,204.84
43 ASPHALT DISTRIBUTOR Jam 286,484.23
44 SLIP FORM PAVER Jam 364,878.22
45 CONCRETE PAN MIXER Jam 68,122.49
46 CONCRETE BREAKER Jam 574,162.56
47 ASPAHLT TANKER Jam 383,410.18
48 CEMENT TANKER Jam 345,810.18
49 CONDRETE MIXER (350) Jam 60,702.64
50 VIBRATING RAMMER Jam 31,178.65
51 TRUK MIXER (AGITATOR) Jam 284,358.95
52 BORE PILE MACHINE Jam 351,772.13
53 CRANE ON TRACK 75-100 TON Jam 2,165,835.83
54 BLENDING EQUIPMENT Jam 160,312.39
55 ASPHALT LIQUID MIXER Jam 105,103.02
56 BAR BENDER Jam 45,114.92
57 BAR CUTTER Jam 45,114.92
58 BREAKER Jam 534,426.84
59 GROUTING PUMP Jam 154,687.84
60 JACK HIDROLIC Jam 39,046.78
61 MESIN LAS Jam 68,514.18
62 PILE DRIVER LEADER, 75 kw Jam 1,161,198.81
63 PILE HAMMER Jam 1,229,537.51
64 PILE HAMMER, 2,5 Ton Jam 835,881.63
65 STRESSING JACK Jam 190,678.43
66 WELDING MACHINE, 300 A Jam 39,128.14
67 ASPHALT MIXING PLANT (WARM MIX) Jam 6,494,748.26
68 ASPHALT MIXING PLANT (MODIFIKASI, ASBUT Jam 7,397,148.26
69 CONCRETE BATHING PLANT Jam 461,742.37
70 Trailer Tronton 30 T; 200 HP Jam 451,880.02
71 MINI EXCAVATOR 40-60 HP Jam 200,977.14
72 BABY VIBRATORY ROLLER 1-2 T. Jam 65,182.76
73 WATER JET BLASTING Jam 37,352.22
74 MESIN POTONG RUMPUT Jam 36,908.54
75 Ponton + Tug Boat; 40 Ton; 80 HP Jam 743,575.84
76 Silicon Seal pump Jam 24,290.42
77 Pompa (+Mixer) pengisi bahan perekat epoxy Jam 27,006.63
78 Gerinda tangan GWS 750-100 4"; 1 HP Jam 29,350.92
79 Hand Mixer Jam 25,805.28
80 Mesin Bor Jam 737,362.08
81 Mesin Amplas kayu Jam 22,000.00
82 KUNCI TORSI 200-1000N.M Jam 31,883.52
83 POMPA + MIXER EPOXY, 810 Watt Jam 29,003.16
84 CONCRETE CUTTER 130 feet/mnt Jam 51,560.24
85 SAND BLASTING Jam 109,459.62
86 MOBILE CRANE 1 TON Jam 436,985.42
87 DRUM MIXER Jam 349,897.91
88 CONCRETE MIXING PLANT Jam 234,700.00
89 STAMPER Jam 63,351.32
90 JACK HIDROLIK JEMBATAN Jam 68,562.62
91 HYDROLIC PUMP Jam 52,509.19
92 MANIFOLD Jam 26,818.32
93 THERMOPLASTIC ROAD MARKING MACHINE Jam 62,904.26
94 COLD PAINT SRAY MACHINE Jam 49,299.66
95 ASPHALT SPRAYER Jam 112,799.60
96 CHAINSAW Jam 550,000.00
97 WATERPASS Hari 90,900.00
98 TEODOLITH Hari 772,700.00
99 MESIN LAS Jam 68,514.00
100 VIBRATOR Hari 33,863.95
101 JACK HAMMER 5 KW + GENSET 12 HP Hari 300,970.99
102 POMPA LUMPUR 7.5 KW; 4" Hari 32,000.00
103 POMPA LUMPUR 7.5 KW; 5" Hari 37,000.00
104 POMPA LUMPUR 7.5 KW; 6" Hari 65,000.00
113 TRIPOT / TACKEL Hari 110,000.00
114 TRIPOT / TACKEL & HANDLE CRANE 2 T Hari 137,500.00
115 PEMOTONG PIPA T1/ GERGAJI / SAW Hari 82,500.00
116 PEMOTONG PIPA T2 / CILINDER SAW Hari 165,000.00
117 MOBILE CRANE ≤ 3 TON Hari 357,142.86
119 PALU/GODAM Hari 39,285.71
120 PAHAT BETON Hari 35,357.14
121 LINGGIS Hari 19,800.00
122 TOWER CRANE Hari 3,200,000.00
123 PIPE SUPPORT Hari 1,100.00
124 SCAFOLDING Hari 39,500.00
125 TIMBRIS Jam 16,500.00
126 Loader Wheel 1,62 m3; 170 HP Jam 423,918.91
127 Batching Plant Beton Kap 25-75 m3/jam Jam 461,742.37
128 Truck Mixer Beton 7 m3; 130 HP Jam 284,358.95
129 Pompa Beton Ø6", 90 KW, 130 bar, T=50 m / Jam 344,530.86
130 Concrete Vibrator Ø45 mm; 10 HP Jam 33,863.95
DAFTAR UPAH PEKERJA
TAHUN 2022

SUMBER DATA : SK BUPATI


PEKERJAAN : REHABILITASI SMP N 1 TERAS
LOKASI : SMP N 1 TERAS, BOYOLALI
TAHUN ANGGARAN : 2022
WILAYAH : I (SATU)

HARGA
NO. JENIS TENAGA KERJA SATUAN KET.
(Rp)

1 Pekerja Hr 80,000
2 Mandor Hr 105,000
3 Tukang listrik Hr 90,000
4 Tukang kayu Hr 90,000
5 Kep. tk. kayu Hr 105,000
6 Tukang batu Hr 90,000
7 Kep. tk. batu Hr 105,000
8 Tukang besi Hr 90,000
9 Kep. tk. besi Hr 105,000
10 T u k a n g c a t Hr 90,000
11 K e p . t k . c a t Hr 105,000
12 T u k a n g p l i t u r Hr 88,000
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

I BAHAN DASAR

1 BATU BELAH
Batu Gunung Belah m3 225,000.00
kg 167.00
-
2 KERIKIL -
Beton 5 - 7 cm m3 230,000.00 Pecah mesin
Beton 3 - 5 cm m3 230,000.00 Pecah mesin
Beton 2 - 3 cm m3 230,000.00 Pecah mesin
Beton 1 - 2 cm m3 230,000.00 Pecah mesin
Beton 0.5 - 1 cm m3 230,000.00 Pecah Mesin
kg 170.00 Pecah Mesin

3 BATU BATA
ex lokal bh 750.00
Bata Ekspose bh 1,700.00 dim 4.5 x 11 x 22
Bata Pelapis bh 1,700.00 dim 3 x 7 x 24
Batu paras bh 108,000.00 dim 20 x 20
Concrete Block ( CB 15 ) / Batako (lubang 2) bh 3,000.00
Roster Beton Abu Uk 20x20 bh 15,000.00
Bata ringan 60x20x10 cm m3 800,000.00 Ex. Grand Elephant
bh 9,600.00 Ex. Grand Elephant
Bata ringan 60x20x7.5 cm m3 800,000.00
bh 7,200.00
4 PASIR
Urug m3 175,000.00
Pasang m3 228,400.00
Beton m3 230,000.00
kg 164.00
5 TANAH -
Sirtu m3 138,000.00
Tanah Padas m3 58,000.00
Tanah Biasa m3 54,600.00
Sirtu (Quarry) m3 58,000.00
Tanah Padas (Quarry) m3 36,800.00
Tanah Biasa (Quarry) m3 32,700.00
Tanah Subur m3 58,000.00
Tanah Liat m3 58,000.00
-
6 KAPUR Pasang m3 210,000.00
-
7 PORTLAND CEMENT
Portland Cement 40 kg Ex. GRESIK zak 59,000.00
Ex. TIGARODA zak 57,000.00
Ex. DYNAMIX zak 54,000.00
Portland Cement Ex. GRESIK kg 1,475.00
Ex. TIGARODA kg 1,425.00
Ex. DYNAMIX kg 1,350.00
Semen warna kg 15,000.00
Semen Putih kg 5,500.00
Pengisi Nat Sika kg 18,500.00
MU mortar utama plester plus kg 2,050.00
MU mortar utama aci kg 3,600.00
Thin bed perekat bata ringan kg 2,100.00 Ex Grand Elephant
Plester instan bata merah kg 2,000.00 Ex Grand Elephant
Aci instan kg 2,350.00 Ex Grand Elephant
Perekat keramik kg 2,750.00 Ex Grand Elephant
Render kg 2,400.00 Ex Grand Elephant
Grouting kg 2,350.00 Ex Grand Elephant
-
8 Plastik Plastik tebal 0,08 gulung 126,000.00 uk 1,5x25 m
Plastik tebal 0,08 m2 3,350.00
-
II BAHAN PENUTUP ATAP -
1 GENTENG TANAH LIAT -
Genteng Lokal Tipe Plenthong bh 1,650.00
Genteng Kebumen Tipe Plentong Kecil bh 3,650.00
Genteng Kebumen Tipe Morando bh 5,750.00
Genteng Keramik Kanmuri bh 10,500.00
Genteng Keramik KIA Kw I bh 10,800.00
Genteng Keramik Glazur Super Jatiwangi Bh 5,950.00
Genteng Jatiwangi Maridional bh 7,350.00
Genteng Jatiwangi Morando 18 bh 5,750.00
Genteng Jatiwangi Tipe Morando SE bh 6,300.00
Genteng Jatiwangi Tipe Alto bh 4,300.00
Genteng Kerpus Lokal bh 1,650.00
Genteng Kerpus Kebumen bh 12,600.00
Genteng Kerpus Keramik bh 28,500.00
Genteng Sirap Keramik bh 2,450.00 Isi 50 bh/m2

GENTENG BETON Genteng beton bh 5,900.00


Genteng Aspal/Bitumen bh 151,800.00
-
5 ASBES Asbes Gelombang Besar -
200 x 102 x 0.5 cm bh 94,500.00
240 x 102 x 0.5 cm bh 107,100.00
180 x 102 x 0.5 cm bh 86,100.00 djabesmen
250 x 102 x 0.5 cm bh 110,200.00 djabesmen
300 x 102 x 0.5 cm bh 136,500.00 djabesmen

- Harsat Bahan - -28


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Asbes Gelombang Kecil -


180 cm X 102 cm X 0.5 cm bh 57,200.00 elephant
210 cm X 105 cm X 0.5 cm bh 68,200.00 elephant
240 cm X 102 cm X 0.5 cm bh 78,700.00 elephant
300 cm X 102 cm X 0.5 cm bh 87,700.00 elephant
-
NOK ASBES Gelombang Kecil bh 42,000.00
Gelombang Besar bh 73,500.00
-
5 ASBES PLAT 100 cm X 100 cm X 4 mm bh 17,800.00
120 cm X 240 cm X 4 mm bh 56,700.00
6 SENG PLAT BJLS 0,25 lebar 45 cm m' 21,000.00
BJLS 0,25 lebar 60 cm m' 27,300.00
BJLS 0,25 lebar 90 cm m' 36,700.00
BJLS 0,25 lebar 120 cm m' 52,500.00
-
7 SENG GELOMBANG BJLS 0,30 panjang ( 90x180 ) cm lbr 42,000.00
BJLS 0,30 panjang ( 90x240 ) cm lbr 107,100.00
BJLS 0,20 panjang ( 90x180 ) cm lbr 75,600.00
BJLS 0,20 panjang ( 90x210 ) cm lbr 88,200.00
BJLS 0,20 panjang ( 90x240 ) cm lbr 100,800.00
BJLS 0,20 panjang ( 90x300 ) cm lbr 126,000.00
Nok seng bh 126,000.00
-
8 SENG TALANG BJLS 0,2 lebar 60 cm m' 24,800.00 galvalum
BJLS 0,2 lebar 90 cm m' 36,900.00 galvalum
BJLS 0,2 lebar 120 cm m' 60,000.00 galvalum
-
10 Lisplank GRC -
Lisplank GRC 9/200 lbr 68,200.00 Panjang 400 cm
Lisplank GRC 9/300 lbr 120,700.00 Panjang 400 cm
Lisplank conwood texture 300 lbr 137,000.00 Panjang 300 cm
Skrup 3 cm pcs 225.00
-
10 ATAP GALVALUME Atap Galvalume tebal 0,4 mm m2 77,900.00
Nok Atap Galvalume tebal 0,4 mm m' 43,200.00
Atap Galvalume tebal 0,3 mm m2 53,900.00 Fortuna BSI
Nok Atap Galvalume tebal 0,3 mm m' 34,300.00
Atap Galvalume tebal 0,25 mm m2 38,700.00 Fortuna
Nok Atap Galvalume tebal 0,25 mm m' 23,600.00
Atap Spandek Transparan 0,3 mm m2 105,000.00
Atap Galvalume pasir tebal 0,25 mm m2 49,200.00 Fortuna
Atap Galvalume pasir tebal 0,28 mm m2 54,300.00 Fortuna
Atap Galvalume pasir tebal 0,3 mm m2 61,900.00 Fortuna
-
11 ATAP METAL Genteng Ex. Sakura Roof Elang lbr 68,200.00 Type Classic
Genteng Multiroof 0.25 77x80 lbr 61,900.00 Fortuna
Genteng Multiroof 0.3 77x80 lbr 68,200.00 Fortuna
Genteng Pasir 0.25 b Ex. Sakura bh 36,400.00
Genteng Pasir 0.3 Ex. Sakura bh 82,900.00
Nok Atap Metal Pasir bh 26,200.00
Nok Atap Metal bh 50,400.00
Penutup Nok bh 15,700.00 Type Ratu
Skrup pcs 725.00
Nok Atap Bitumen bh 90,000.00
Nok Genteng Beton bh 22,500.00
-
12 ATAP POLYCARBONATE Polycarbonate tebal 6 mm lbr 1,942,500.00 Uk. 2,1 x 11,8 m
Polycarbonate tebal 6 mm m2 78,300.00 Ex. Twinlite
-
13 ATAP UPVC -
Atap uPVC Alderon White / Blue m2 226,800.00 Lebar Efektif 86 cm
Atap uPVC Alderon Translucent m2 285,600.00 Lebar Efektif 86 cm
Nok uPVC Alderon White / Blue m' 173,200.00
Sekrup alderon bh 3,150.00
Atap solarlite 0,5 mm m2 124,900.00
Atap xtuff transparan m2 105,000.00 Lebar Efektif 75 cm
Atap twinwall Rooftop White / Blue Doff m2 168,000.00 Lebar Efektif 77 cm
Atap twinwall Rooftop White / Blue Transp m2 264,600.00 Lebar Efektif 77 cm
Atap twinwall Rooftop C-series White / Grey Doff m2 170,100.00 Lebar Efektif 77 cm
Wuwungan Rooftop White / Blue bh 121,800.00 Lebar Efektif 77 cm
Talang Rooftop White / Blue m' 110,200.00 Lebar Efektif 77 cm
Penutup talang Rooftop White / Blue bh 87,600.00 Lebar Efektif 77 cm
Roof seal Rooftop White / Blue bh 1,050.00 Lebar Efektif 77 cm
13 WATER STOP -
Water Stop PVC lebar 150 mm m' 226,800.00
Water Stop PVC lebar 200 mm m' 285,600.00
Water Stop PVC lebar 250 mm m' 173,200.00
Water Stop Rubber m' 3,150.00
-
III BAHAN KAYU -
1 JATI Papan m3 38,850,000.00
Balok/pesagen m3 28,350,000.00
Reng 2/3 m3 7,875,000.00
-
2 KAMPER Papan m3 7,607,100.00
-
3 KRUING Papan m3 8,400,000.00
Balok/pesagen m3 8,203,100.00
-
4 MERANTI Papan m3 5,460,000.00

- Harsat Bahan - -29


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Balok/pesagen m3 4,357,500.00
Papan Begesting m3 3,570,000.00
-
5 LANAN Papan m3 1,778,200.00
Balok/pesagen m3 1,874,900.00
-
6 SENGON Papan m3 2,887,500.00
m2 57,700.00
Balok/pesagen m3 2,887,500.00
-
7 BENGKIRAI Papan m3 14,437,500.00
Balok/pesagen m3 11,484,300.00
Reng 2/3 m3 7,875,000.00
-
8 DOLKEN Sedang 8/10 panjang 4 m btg 26,200.00
Kayu bakar m3 813,700.00
-
9 BAMBU Bambu Apus btg 13,800.00 Panjang 4 meter
Bambu Petung btg 31,600.00 Panjang 4 meter
Anyaman Bambu m2 27,800.00
-
10 KAYU LIST List Polos m' 6,900.00
List Profil m' 10,300.00
-
IV BAHAN PENUTUP DINDING / LANTAI -
1 UBIN -
PC polos 30 X 30 cm m2 3,600.00
20 X 20 cm m2 1,250.00
-
PC abu2 40 X 40 cm buah 8,800.00
30 X 30 cm buah 5,500.00
20 X 20 cm buah 6,000.00
Warna 40 X 40 cm buah 11,900.00
30 X 30 cm buah 8,000.00
20 X 20 cm buah 6,000.00
Teraso 40 X 40 cm buah 62,300.00
30 X 30 cm buah 32,000.00
Teralux 30 X 30 cm buah 40,000.00
Taralux Marmer 60 X 60 cm buah 98,000.00
40 X 40 cm buah 40,500.00
30 X 30 cm buah 42,000.00
-
2 KERAMIK LANTAI -
Keramik lantai 20/20 KIA ( Textur) bh 2,350.00
Keramik lantai 20/20 Platinum (unpolish) bh 2,750.00
Keramik lantai 30/30 Impresso bh 4,350.00
Keramik lantai 30/30 Asia Tile bh 4,700.00
Keramik lantai 30/30 Asia Tile dus 51,900.00
Keramik lantai 30/30 Roman bh 13,300.00
Keramik lantai 30/30 Mulia bh 3,800.00
Keramik lantai 40/40 Hercules bh 10,300.00
Keramik lantai 40/40 Asia Tile Murano bh 10,300.00
Keramik lantai 40/40 Asia Tile Murano dus 62,200.00
Keramik lantai 40/40 Oscar bh 9,900.00
Keramik lantai 60/60 Hercules bh 24,400.00
Keramik lantai 40/40 Platinum bh 11,300.00
Keramik lantai 50/50 Platinum bh 17,000.00
Keramik lantai 50/50 Hercules bh 19,100.00
Keramik lantai 30/30 Platinum bh 5,100.00
Keramik lantai 25/25 Platinum (unpolish) bh 4,300.00
Keramik lantai 25/25 Asia Tile bh 3,250.00
Marmer 100/100 bh 1,177,000.00
Ubin Lantai 40/40 Granito bh 32,500.00
Ubin Lantai 30/30 Granito bh 32,500.00
Teraso Cor m3 3,250.00
Pengisi Nat Sika kg 19,400.00
-
3 KERAMIK DINDING -
Keramik dinding 30/30 KIA bh 6,500.00
Keramik dinding 10/20 KIA bh 1,450.00
Keramik dinding 10/10 KIA bh 1,450.00
Keramik dinding 20/20 Asia Tile bh 2,600.00
Keramik dinding 20/25 Asia Tile bh 3,350.00
Keramik dinding 25/40 KIA bh 6,850.00
Keramik dinding 30/60 KIA bh 21,500.00
Keramik dinding 25/40 Platinum bh 6,900.00
Keramik dinding 25/50 Platinum bh 9,700.00
Keramik dinding 20/20 Spectrum bh 2,100.00
Mozaic dinding 30x30 bh 31,500.00
-
3 KERAMIK DINDING ARTISTIK -
Keramik dinding artistik 5/20 bh 6,500.00
Keramik dinding artistik 10/20 bh 9,800.00
-
4 HOMOGENOUS TILE -
Homogenous Tile 60/60 Indogress TPZ bh 49,300.00
Homogenous Tile 60/60 Top Gress bh 37,800.00
Step Nosing Homogenous Tile 10/60 bh 24,100.00
-
5 PLINT DINDING -
Keramik Dinding 10/20 bh 6,800.00

- Harsat Bahan - -30


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Keramik Dinding 10/30 bh 7,350.00


Keramik Dinding 10/40 bh 8,900.00
Keramik Dinding 10/60 bh 13,100.00
Plint Granit 10/60 bh 26,200.00
Plint Granit 10/30 bh 6,600.00
-
6 MARMER Marmer 100/100 bh 892,500.00
-
7 KARPET Karpet Lantai 100/100 m2 120,700.00
Underlayer karpet 100/100 m2 120,700.00
-
8 PARQUET Parquet Kayu 30/30 tbl. 2,5 cm bh 257,200.00
Parquet GymFLOOR bh 336,000.00
Vinyl 30x30 bh 7,200.00
Lem vinyl kg 75,000.00
-
9 BATU ALAM -
Batu Andesit 20x40 m2 146,200.00
Batu Andesit 20x20 m2 134,900.00
Batu Andesit Alur 40x40 m2 157,500.00
Batu Lempeng Acak m2 68,200.00
Batu Sikat m2 42,200.00
Susun Sirih 3 x 30 cm m2 123,700.00
Batu Muka m2 51,000.00
Batu Candi 15x15 m2 84,300.00
Batu Candi 20x20 m2 95,600.00
-
10 FLOOR HARDENER -
FLOOR Hardener kg 6,000.00
-
11 PORSELEN -
Dinding porselen 11x11 dus 157,500.00
Dinding porselen 10x20 bh 3,000.00
Dinding porselen 20x20 bh 3,500.00
-
12 GEOMEMBRANE -
Geomembrane 1 mm m2 60,900.00
Geomembrane 1.5 mm m2 91,300.00
-
13 GEOTEXTILE -
non woven 200 gr/m2 m2 16,800.00
non woven 250 gr/m2 m2 21,000.00
woven 150 gr/m2 m2 7,450.00
woven 200 gr/m2 m2 9,100.00
woven 250 gr/m2 m2 12,100.00
-
14 PANEL Panel Lantai GEF 150 A - 325 A m3 3,150,000.00 Ex. Grand Elephant
Panel Dinding GEF 150 A - 325 A m3 3,255,000.00 Ex. Grand Elephant
-
15 BILIK BAMBU Bilik Bambu 2x3 m2 m2 3,150,000.00
-
V BAHAN CETAK -
1 BUIS BETON -
Ø 20 cm t 4 Panjang 100 cm bh 48,400.00
Ø 30 cm t 4 Panjang 100 cm bh 55,000.00
Ø 60 cm t 6 Panjang 50 cm bh 105,000.00
Ø 60 cm t 6 Panjang 50 cm bertulang bh 147,000.00
Ø 80 cm t 8 Panjang 50 cm bh 126,000.00
Ø 100 cm t 10 Panjang 50 cm bh 204,700.00
U 10 cm - 100 cm bh 17,500.00
U 15 cm - 100 cm bh 21,400.00
U 20 cm t 4 - 100 cm bh 23,100.00 Ex.Master Beton
U 30 cm t 4 - 100 cm bh 28,800.00 Ex.Master Beton
U 40 cm t 4 - 100 cm bh 44,600.00 Ex.Master Beton
Tutup buis beton 100 t 6, bertulang bh 110,200.00 Ex.Master Beton
Tutup buis beton 80 t 6, bertulang bh 89,200.00 Ex.Master Beton
-
2 LUBANG ANGIN (ROSTER) PC + PASIR -
20 X 20 cm bh 7,850.00
-
3 PAVING -
Holland 20 x 10 x 6 cm K.300 Natural m2 73,500.00 Ex.Master Beton
Holland 20 x 10 x 6 cm K.300 Merah m2 84,800.00 Ex.Master Beton
Holland 21 x 10,5 x 8 cm K.300 Natural m2 94,500.00 Ex.Master Beton
Holland 21 x 10,5 x 8 cm K.300 Merah m2 111,600.00 Ex.Master Beton
Kubus 20 x 20 x 6 cm K.300 Natural m2 73,500.00 Ex.Master Beton
Kubus 20 x 20 x 6 cm K.300 Merah m2 84,000.00 Ex.Master Beton
Kubus 20 x 20 x 8 cm K.300 Natural m2 94,500.00 Ex.Master Beton
Kubus 20 x 20 x 8 cm K.300 Merah m2 105,000.00 Ex.Master Beton
Hexagon 20 x 20 x 6 cm K.300 Natural m2 73,500.00 Ex.Master Beton
Hexagon 20 x 20 x 6 cm K.300 Merah m2 84,000.00 Ex.Master Beton
Grass Block Kotak 30 x 30 x 8 cm Natural m2 84,000.00 Ex.Master Beton
Grass Block Kotak 30 x 30 x 8 cm Merah m2 94,500.00 Ex.Master Beton
Topi Uskup 30 x 21 x 6 cm K.300 Natural m' 5,250.00 Ex.Master Beton
Topi Uskup 30 x 21 x 6 cm K.300 Merah m' 5,750.00 Ex.Master Beton
Kanstein Besar/Kerb 20 x 30 x 60 cm bh 60,900.00 Ex.Master Beton
Kanstein Lock Kecil 10 x 20 x 40 cm bh 24,100.00 Ex.Master Beton
Kanstein Lock Besar 10 x 20 x 50 cm bh 29,400.00 Ex.Master Beton
Kanstein L Profil 39,5x43x42 cm bh 63,000.00 Ex.Master Beton
Kerb Standart 10/12x35x50 bh 42,000.00 Ex.Master Beton
-

- Harsat Bahan - -31


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

6 Glass Block -
Glassblock ex Mulia Bh 27,300.00 Ex. Mulia

7 Guilding block 30,000.00


-
-
VI BAHAN BESI -
1 BESI -
Besi beton Tulangan Polos kg 14,400.00
Besi beton Tulangan Ulir kg 14,600.00
Wiremesh kg 17,000.00
-
2 BAJA -
Baja Profil / Konstruksi ≤355 kg/m kg 19,500.00 termasuk fin. Meni
Baja Profil / Konstruksi >355 kg/m kg 21,700.00 termasuk fin. Meni
Baut mur 8.8 3/4x2 Bh 6,600.00
Angkur Bolt NC M16x30 Bh 37,800.00
-
3 KAWAT -
Kawat Ikat Beton / Bendrat kg 17,800.00
Kawat Duri unit 12,800.00
Kawat Bronjong 1x2x0.5 unit 353,800.00
Kawat Harmonika Galvanis dia.1,6mm m2 21,100.00 Uk.45x45mm
Kawat Sling 6mm m1 8,400.00
Kawat Las kg 39,300.00
Ramset bh 39,300.00
3 PAKU -
Paku kg 18,900.00
4 HOLLOW -
Hollow Rangka Plafond Baja Ringan 15x35x0,25 m' 5,700.00 Ex. Fortuna
Hollow Rangka Plafond Baja Ringan 35x35x0,25 m' 8,000.00 Ex. Fortuna
Hollow Non Galvanis 2.4. 400 btg 20,300.00 panjang 4m
Hollow Non Galvanis 4.4. 400 btg 27,300.00 panjang 4m
Hollow Galvanis 2.4. 400 btg 21,300.00 panjang 4m
Hollow Galvanis 4.4. 400 btg 29,100.00 panjang 4m
Hollow 50.50.3 Kg 29,100.00 panjang 4m
-
5 BAJA RINGAN -
Baja Ringan C.75.75 Ex. Fortuna m' 19,100.00 Ex. Fortuna
Baja Ringan C.75.75 Ex. Kencana m' 20,700.00 Ex. Kencana
Baja Ringan Reng 30.45 Ex. Fortuna m' 6,800.00 Ex. Fortuna
Baja Ringan Reng 30.45 Ex. Kencana m' 9,100.00 Ex. Kencana
Baja Ringan CNP 150.2,3 Ex. Fortuna m' 80,400.00 Ex. Fortuna
Baja Ringan CNP 150.3,2 Ex. Fortuna m' 114,700.00 Ex. Fortuna
Baja Ringan CNP 125.2,3 Ex. Fortuna m' 73,300.00 Ex. Fortuna
-
6 METAL STUD MS.75.30.0,35 Ex. Kencana m' 10,300.00 Ex. Kencana
-
7 PAGAR BRC Pagar BRC 6 mm Biasa (2.4x1.2 m) lbr 278,200.00
Pagar BRC 6 mm Galvanis (2.4x1.2 m) lbr 368,500.00
Pagar BRC 7 mm Biasa (2.4x1.2 m) lbr 412,600.00
Pagar BRC 7 mm Galvanis (2.4x1.2 m) lbr 499,800.00
-
8 TALANG Talang Jurai m' 141,700.00
X-tuff m' 102,300.00
Woodplank m' 47,200.00
-
9 FLOORDECK FLOORdeck 0.75 m' 156,500.00 Ex. Kencana
FLOORdeck 0.70 m' 145,900.00 Ex. Kencana
FLOORdeck 0.65 m' 135,400.00 Ex. Kencana
-
10 ALUMINIUM STRIP Alumunium strip 4 cm m' 17,100.00
Alumunium strip 3 cm m' 10,600.00
Alumunium strip 2.5 cm m' 11,000.00
Aluminium L.30.30.3 kg 8,500.00 panjang 6 m
Aluminium L.10.10.1 kg 5,700.00 panjang 6 m
-
VII BAHAN PIPA -
1 Pipa PVC SII SCJ , S - 12,5 (10 bar) Ex Maspion pjg.6m -
Pipa PVC DN 16 ( ½" ) AW JIS 22 mm btg 24,300.00 panjang 4 m
Pipa PVC DN 20 ( ¾" ) AW JIS 26 mm btg 32,300.00 panjang 4 m
Pipa PVC DN 25 ( 1" ) AW JIS 32 mm btg 38,100.00 panjang 4 m
Pipa PVC DN 40 ( 1 1/4" ) D standar 42 mm btg 139,100.00 panjang 6 m
Pipa PVC DN 50 ( 1½" ) D standar 48 mm btg 177,700.00 panjang 6 m
Pipa PVC DN 63 ( 2" ) D standar 60 mm btg 200,400.00 panjang 6 m
Pipa PVC DN 65 ( 2½" ) D standar 76 mm btg 191,700.00 panjang 6 m
Pipa PVC DN 75 ( 3" ) D standar 89 mm btg 406,700.00 panjang 6 m
Pipa PVC DN 90 ( 3" ) D standar btg 540,300.00 panjang 6 m
Pipa PVC DN 110 ( 4" ) D standar btg 598,400.00 panjang 6 m
Pipa PVC DN 125 D standar btg 626,000.00 panjang 6 m
Pipa PVC DN 150 ( 5½" ) D standar btg 825,700.00 panjang 6 m
Pipa PVC DN 160 ( 6" ) D standar btg 1,266,300.00 panjang 6 m
Pipa PVC DN 200 D standar btg 2,718,900.00 panjang 6 m
Pipa PVC DN 250 D standar btg 4,338,200.00 panjang 6 m
Pipa PVC DN 300 D standar btg 6,790,700.00 panjang 6 m
-
Pipa PVC AW Wavin 3/4" m' 11,000.00
Pipa PVC AW Wavin 1" m' 15,100.00
Pipa PVC AW Wavin 2" m' 33,300.00
Pipa PVC AW Wavin 3" m' 68,500.00
Pipa PVC AW Wavin 4" m' 113,400.00

- Harsat Bahan - -32


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

-
2 Pipa PVC SII SCJ , S - 12,5 (8 bar) Ex Maspion pjg.6m -
Pipa PVC DN 40 ( 1 1/2" ) btg 128,700.00 panjang 6 m
3 Pipa PVC AW abu panjang 4m -
Pipa PVC AW Maspion 1/2" m' 10,700.00 panjang 4 m
Pipa PVC AW Maspion 3/4" m' 13,100.00 panjang 4 m
Pipa PVC AW Maspion 1" m' 16,400.00 panjang 4 m
Pipa PVC AW Maspion 1 1/4" m' 23,200.00 panjang 4 m
Pipa PVC AW Maspion 1 1/2" m' 30,300.00 panjang 4 m
Pipa PVC AW Maspion 2" m' 45,000.00 panjang 4 m
Pipa PVC AW Maspion 2 1/2" m' 57,700.00 panjang 4 m
Pipa PVC AW Maspion 3" m' 82,300.00 panjang 4 m
Pipa PVC AW Maspion 4" m' 120,000.00 panjang 4 m
Pipa PVC AW Maspion 5" m' 189,300.00 panjang 4 m
Pipa PVC AW Maspion 6" m' 252,100.00 panjang 4 m
4 Pipa Medium A Galvanis - panjang 6m -
Pipa Medium A Galvanis DN ½" btg 232,300.00 panjang 6 m
Pipa Medium A Galvanis DN 25 ( ¾" ) btg 297,600.00 panjang 6 m
Pipa Medium A Galvanis DN 32 ( 1" ) btg 448,800.00 panjang 6 m
Pipa Medium A Galvanis DN 40 ( 1 1/4" ) btg 587,200.00 panjang 6 m
Pipa Medium A Galvanis DN 50 ( 1½" ) btg 673,800.00 panjang 6 m
Pipa Medium A Galvanis DN 63 ( 2" ) btg 920,200.00 panjang 6 m
Pipa Medium A Galvanis DN 65 ( 2 1/2" ) btg 1,187,100.00 panjang 6 m
Pipa Medium A Galvanis DN 90 ( 3" ) btg 1,531,100.00 panjang 6 m
Pipa Medium A Galvanis DN 110 ( 4" ) btg 2,194,800.00 panjang 6 m
Pipa Medium A Galvanis DN 125 ( 5" ) btg 2,982,600.00 panjang 6 m
Pipa Medium A Galvanis DN 160 ( 6" ) btg 3,516,700.00 panjang 6 m
-
5 Pipa Besi Stainless Steel Ex Star -
dia. 3/4" btg 227,200.00 panjang 6 m
dia. 1" btg 284,000.00 panjang 6 m
dia. 2" btg 454,200.00 panjang 6 m
dia. 3" btg 826,500.00 panjang 6 m
dia. 4" btg 1,106,000.00 panjang 6 m
-
6 Pipa HDPE SDR 17 -
Dia. 50 mm m' 30,600.00 Ex. Maspion
Dia. 63 mm m' 48,800.00 Ex. Maspion
Dia. 75 mm m' 68,900.00 Ex. Maspion
Dia. 90 mm m' 99,100.00 Ex. Maspion
Dia. 100 mm m' 154,500.00 Ex. Maspion
Dia. 110 mm m' 147,400.00 Ex. Maspion
Dia. 125 mm m' 197,000.00 Ex. Maspion
Dia. 150 mm m' 322,800.00 Ex. Maspion
Dia. 200 mm m' 503,900.00 Ex. Maspion
Dia. 250 mm m' 783,200.00 Ex. Maspion
Dia. 300 mm m' 1,246,000.00 Ex. Maspion
Dia. 400 mm m' 2,003,900.00 Ex. Maspion
Dia. 450 mm m' 2,539,000.00 Ex. Maspion
Dia. 500 mm m' 3,127,500.00 Ex. Maspion
Dia. 600 mm m' 4,965,500.00 Ex. Maspion
Dia. 800 mm m' 11,524,200.00 Ex. Maspion
Dia. 900 mm m' 14,627,300.00 Ex. Maspion
Dia. 1000 mm m' 18,017,400.00 Ex. Maspion
Dia. 1200 mm m' 24,885,300.00 Ex. Maspion
7 Bend All Flange -
Bend all flange Ø 2" x 90 bh 338,100.00 Ex. Maspion
Bend all flange Ø 3" x 90 bh 367,800.00 Ex. Maspion
Bend all flange Ø 4" x 90 bh 595,800.00 Ex. Maspion
Bend all flange Ø 2" x 45 bh 315,400.00 Ex. Maspion
Bend all flange Ø 3" x 45 bh 385,700.00 Ex. Maspion
Bend all flange Ø 4" x 45 bh 538,100.00 Ex. Maspion
8 Cek Valve -
Cek Valve Ø 1/2" bh 123,000.00 Ex. Onda kuningan drat
Cek Valve Ø 1 1/2" bh 523,100.00 Ex. Onda kuningan drat
Cek Valve Ø 2" bh 828,600.00 Ex. Onda kuningan drat
Cek Valve Ø 3" bh 2,295,700.00 Ex. Onda kuningan drat
Cek Valve Ø 4" bh 1,843,000.00 Ex. Onda kuningan drat
9 Flange Steel -
Dia. 1.5" bh 65,600.00
Dia. 2" bh 67,800.00
10 Gate Valve -
Dia. 1.5" bh 481,600.00
Dia. 2" bh 925,400.00
11 Keni Galvanis -
Keni Galvanis Ø 1.5" x 90 bh 31,400.00
Keni Galvanis Ø 2" x 90 bh 49,600.00
12 Pressure Gauge -
Dia. 2 1/2" bh 119,800.00
13 Pipa Udara bh 366,100.00
14 Manhole bh 585,700.00
Water Meter 1/2" ex. Nankai bh 133,600.00
Socket PVC 3/4" x 3/4" bh 3,050.00
Clamp Saddle CI 2" x 3/4" bh 36,800.00
Tee PVC 1/2" bh 3,750.00
Fix Coupling 1/2" (Kuningan) bh 32,300.00
Kran Air 1/2" (Kuningan) bh 34,300.00
Gate Valve 1/2" (Kuningan) bh 79,500.00
16 Tee -
Tee Ø 150 mm bh 392,200.00
Tee Ø 200 mm bh 812,600.00

- Harsat Bahan - -33


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

-
VIII B A H A N L A N G I T - L A N G I T -
1 SOFT BOARD ( 1.2 m x 2.4 m ) -
Soft Board Tebal 9 mm Jayaboard lbr 78,700.00
Soft Board Tebal 9 mm Jayaboard WR lbr 94,500.00
Soft Board Tebal 9 mm Elephant lbr 63,000.00
Soft Board Tebal 9 mm Knauf lbr 51,400.00
Soft Board Tebal 9 mm Star lbr 52,500.00
Soft Board Tebal 9 mm Aplus lbr 49,300.00
Sekrup Gypsum Sunray 6 x 2" bh 225.00
Compound Compound Knauf kg 3,150.00
Compound Aplus kg 3,150.00
GRC Board tebal 4mm 1200 x 2400 x 0.4 cm lbr 63,000.00
Dinabolt Bh 3,650.00
Cotton Plaster 50 m m' 325.00
List Gypsum Lebar 10 cm m' 12,600.00
List Kayu Profil m' 10,500.00
Tepung Gypsum kg 3,650.00
Cornice Adhesive Kg 4,200.00
Textile Tape m' 1,050.00
-
3 HARDFLEX 1200 x 2400 x 4 mm lbr 63,000.00 GRC
1000 x 1000 x 4 mm lbr 33,500.00 GRC
900 x 1800 x 4 mm lbr 45,300.00 GRC
4 PLY WOOD -
1200 x 2400 x 3 mm lbr 47,200.00
1200 x 2400 x 4 mm lbr 60,900.00
1200 x 2400 x 5 mm lbr 68,200.00
1200 x 2400 x 6 mm lbr 120,700.00
1200 x 2400 x 9 mm lbr 131,200.00
1200 x 2400 x 12 mm lbr 157,500.00
1201 x 2400 x 15 mm lbr 189,000.00
Urat Jati (Teakwood) 200 x 4000 x 4 mm lbr 68,200.00
Lapis Formika m2 62,800.00
Skrup pcs 275.00
5 AKUSTIK -
30x30 lbr 47,200.00
30x60 lbr 60,900.00
60x120 lbr 68,200.00
6 PVC Polos lebar 20 cm m' 15,700.00 Ex. Wifon
Texture lebar 20 cm m' 17,300.00 Ex. Wifon
List PVC Polos m' 13,600.00
-
6 Alumunium Composit Panel Lbr 493,500.00 Ex. Seven indoor
Lbr 771,700.00 Ex. Seven outdoor
Rangka Besi Hollow + Bracing m2 206,100.00
Rangka Hollow 1x2 m' 15,000.00
7 Exhaust Fan FLOOR Panasonic 10" FV25TGU Unit 590,600.00
Panasonic 8" FV20TGU Unit 474,100.00
Maspion 10" MV-250NEX Unit 460,400.00
Maspion 8" CEF-20MP Unit 319,200.00
-
IX BAHAN FINISHING -
1 KAYU -
Menie Kayu kg 38,800.00
Dempul plamur kg 36,500.00
Ambril/amplas lbr 4,400.00
Batu Apung kg 19,700.00
Cat Kayu Danalac kg 66,100.00
Waterproofing No Drop kg 49,800.00
Siralax ons 10,500.00
Spiritus ltr 21,000.00
Melamik kg 54,600.00
Lem Kayu Fox Kuning kg 71,400.00
HPL Motif Serat Kayu (2,4 x 1.2 m) lbr 187,400.00
Foam Sheet 3 mm m2 6,400.00

- Harsat Bahan - -34


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Minyak bekisting Ltr 6,600.00


-
2 TEMBOK -
Plamur Plamur kg 28,600.00
Cat Dasar -
Ex. Catylac kg 28,300.00
Ex. Jotun Jotashield Primer Kg 54,600.00
Envi Kg 43,800.00
Cat Tembok -
Ex. Catylac kg 28,200.00
Ex. Jotun Jotashield Antifade kg 115,500.00
Ex. Nippon Weatherbond Kg 157,500.00
Ex. Mowilex kg 89,200.00
Ex. Dulux kg 57,300.00
Coating welstone liter 80,800.00 Ex. Propan Stone Care
Envi (eksterior) kg 45,600.00
Envi (Interior) kg 35,000.00
3 BESI -
Menie nusatex kg 44,100.00
Cat Ex. Decolux kg 63,000.00
Ex. Danagloos kg 115,500.00
Cat Poxy Ex. Penta kg 47,200.00
Thinner A ltr 28,000.00
Thinner ND ltr 34,600.00
Minyak cat ltr 31,500.00
Lem Aica Aibon kg 57,700.00
Teak Oil ltr 57,700.00
-
X BAHAN KACA -
1 BENING/POLOS -
3 mm m2 110,200.00
5 mm m2 157,500.00
6 mm m2 203,600.00
8 mm m2 303,700.00
10 mm m2 406,100.00
12 mm m2 606,300.00
2 ES KABUR -
3 mm m2 127,000.00
5 mm m2 175,500.00
3 RAY BAND -
5 mm m2 138,600.00
8 mm m2 404,200.00
12 mm m2 245,700.00
4 TEMPERED -
5 mm m2 259,800.00
8 mm m2 606,300.00
10 mm m2 895,100.00
12 mm m2 1,039,500.00
5 CERMIN -
3 mm m2 168,700.00
5 mm m2 312,700.00
8 STOPSOL Dark Blue 8 mm m2 460,600.00
Dark Green 8 mm m2 479,000.00
-
XI BAHAN INSTALASI LISTRIK -
1 KABEL NYY 3 x 2.5 mm m' 20,400.00
NYM 3 x 2.5 mm m' 16,200.00
NYFGBY 3 x 2,5 mm m' 42,000.00
NYM 2 x 2.5 mm m' 12,600.00
NYY 2 x 2.5 mm m' 16,200.00
2 Kabel penghantar BC 6 mm m1 18,900.00
3 Kabel inpure LVTC 2 x 25 mm m1 15,700.00
4 Kabel Seling NYM 3 x 4 mm m1 26,200.00
5 Pipa Inpure ( galvanis 2" ) bh 189,000.00
6 Knee Pipa Inpure ( galvanis 2" ) bh 18,900.00
7 Klem Pipa Inpure bh 24,500.00
8 Pole band Inpure bh 66,100.00
9 Pole band Box bh 66,100.00
10 Kanal C m1 42,500.00
11 Timer bh 525,000.00 Ex. Panasonic
12 Kontaktor bh 567,000.00 Ex. Schneider
13 Terminal komplit unit 36,700.00 blusbar
14 Ground Rood bh 63,000.00 16 mm, 2.4 m
15 Pipa Flexibel m1 5,650.00
16 MCB 10A bh 36,700.00
17 Isolasi bh 7,850.00
18 MCB bh 47,200.00 Ex. Broco
19 MCCB 200 A bh 892,500.00 Ex. Schneider
20 Box MCB bh 154,500.00 Ex. Schneider utk 8 ttk
bh 100,500.00 Ex. Broco utk 6 ttk
21 Isolasi bh 9,400.00
22 Box Panel MCB 30x40x20 cm bh 220,500.00
23 Box Panel MCB 60x80x20 cm bh 635,200.00
24 Rel MCB bh 15,700.00
25 Lampu Indikator bh 10,500.00
26 Sekun 4mm bh 1,750.00
27 Material Pendukung ( Isolasi, Kabel Ties dll ) Paket 343,600.00

- Harsat Bahan - -35


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

28 Pipa PVC 2" AW m1 11,500.00


29 Klem Unit 300.00
-
30 Lampu -
Baret / Plafond Kecil Unit 185,400.00 Ex. Panasonic Kecil
Baret / Plafond Besar Unit 250,400.00 Ex. Panasonic Besar
LED 12 watt 35,000.00 Ex . Osram
Philips LED 11 Watt bh 47,200.00
Philips LED 9 Watt bh 36,700.00
Philips LED 7 Watt bh 31,500.00
Lampu Tornado 15 watt Philips cdl(15 Watt) bh 68,200.00
Kap Lampu bh 34,200.00
31 Armateur Downlight -
TL 2x20 RM Armateur In Bow Unit 156,100.00
Silver Chrome 4" In Bow Unit 57,700.00 Ex. Panasonic NLP72332
White / Black 4" Out Bow Unit 94,500.00 Ex. Panasonic
Silver Chrome 4" Unit 52,500.00 Ex. Meiwa
Armateur Downlight Silver Chrome 3" Unit 34,600.00 Ex. Meiwa
Fitting Lampu Bh 10,500.00 Ex. Broco
32 Stop Kontak Dinding -
Ex. Broco IB 6100 Standart bh 14,700.00
Ex. Broco Galileo bh 17,300.00
Panasonic WEJP 11217 bh 15,200.00
Clipsal bh 27,300.00
Stop Kontak Lantai Panasonic bh 315,000.00
Stop Kontak AC Panasonic WBJ1214W3K bh 68,200.00
-
32 Saklar Double Switch -
Ex. Broco Standar bh 21,000.00
Ex. Broco Galileo bh 22,000.00
Ex. Panasonic Seri WEJ78029W bh 25,700.00
Clipsal bh 30,300.00
33 Saklar Single Switch -
Ex. Broco Standar bh 13,600.00
Ex. Broco Galileo bh 16,800.00
Ex. Panasonic Seri WEJ78019W bh 14,700.00
Clipsal bh 20,400.00
34 Tee Dos bh 3,150.00
35 L Bow bh 3,500.00
36 Pipa Clipsal m' 5,250.00
37 Sock Unit 1,050.00
38 Klem Unit 1,050.00
39 Listrik kwh 1,500.00
-
XII ALAT - ALAT PENGUNCI & PENGGANTUNG -
1 KUNCI TANAM -
Solid 2 X slag bh 171,100.00 Seri HP.858.43BZ
Muller ( Putih ) 2 X slag bh 178,500.00 Seri 952184 SN/CP
Muller ( Kuning ) 2 X slag bh 178,500.00 Seri 952184 SN/GP
-
2 ENGSEL DAN GERENDEL -
Engsel Pintu Panel Kuning dimensi 3" Tebal ES IR 2B GP bh 77,700.00 Ex. Dekkson
Kuning dimensi 4" Tebal ES IR 4BB GP bh 118,600.00 Ex. Dekkson
Kuning dimensi 5" Tebal ES IR 4BB GP bh 139,600.00 Ex. Dekkson
-
Engsel Ram Jendela Kuningan 2" bh 6,800.00 Ex. Soligen
Kuningan 2.5" bh 10,500.00 Ex. Axell
Kuningan 3" bh 37,800.00 Ex. Axell
-
Nylon kupu-kupu 3" ES IR 4NR bh 42,000.00 Ex. Dekkson
4" ES IR 4NR bh 50,400.00 Ex. Dekkson
-
Espagnoled - EPLH AL 874A bh 138,600.00 Ex. Dekkson
Spring knip SK 018 BR PB bh 134,000.00 Ex. Dekkson
Grendel Tanam FB 040 B SSS bh 103,900.00 Ex. Dekkson
Grendel biasa DB AL805 bh 73,500.00 Ex. Dekkson
Grendel antik bh 165,000.00
Hak Angin WS 011Z bh 61,900.00 Ex. Dekkson
Door Stop MDS 001 for wood bh 49,300.00 Ex. Dekkson
-
Handle Pintu Baja Set 236,200.00 Ex. Solid
Barrel Hinges / Engsel Bubut ES IR 34x90-39x90 GALV Set 296,100.00 Ex. Dekkson
Engsel Kupu-kupu Baja ES IR 2B set 77,700.00 Ex. Dekkson
Kunci Gembok Besar PL 100 50mm Bh 126,000.00 Ex. Solid
-
39 Petanahan/arde BCC 50 mm2 m 64,300.00
40 BCC 16 mm2 m 19,700.00
41 BCC 10 mm2 m 11,100.00
42 Penangkal Petir electro static non radioaktif unit 6,872,600.00
XIII BAHAN SANITAIR -
1 KLOSET DUDUK bh 1,847,000.00 Ex. INA
Seri CW863NPJ unit 4,381,200.00 Ex. Toto
Seri CW702J/SW784JP unit 3,916,500.00 Ex. Toto
Amstad My Winston Unit 1,386,000.00 Ex. Amstad
URINAL/URINOIR seri L102 bh 1,029,000.00 Ex. Sandimas
2 KLOSET JONGKOK Toto Seri CE-7 PIV bh 388,500.00
BATHTUB seri XD 03218 bh 2,425,500.00 Ex. Ceramax
3 WASTAFEL GANTUNG BULAT bh 231,000.00 ex icepool
4 WASTAFEL BAK CUCI -
Studio 45 bh 420,000.00 Ex. American Standart
5 TEMPAT SABUN GANTUNG bh 47,200.00

- Harsat Bahan - -36


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

6 TEMPAT SABUN TANAM bh 63,000.00


7 ZINC WASHBAK Besar bh 212,100.00
Kecil bh 157,500.00 Ex. OKI
Teraso bh 867,900.00
Bak Mandi Fiber bh 189,000.00
Bak Mandi Teraso bh 935,000.00
8 WATER DRAIN set 42,800.00
9 Shop Holder Toto S 156 N bh 123,600.00
Motif Biasa bh 42,000.00 Ex. Ina
10 Paper Holder Biasa bh 66,900.00
11 Shower Mandi SAN-EI Seri SK30P bh 1,224,700.00
12 Jet Washer SAN-EI Seri PSN 75 C bh 184,200.00
Onda bh 105,000.00
13 Tandon Air TB110 Kapasitas 1050 liter Unit 1,785,000.00 Ex. Penguin
TB110 Kapasitas 1050 liter Unit 1,642,700.00 Jungle Bird Eco
TB110 Kapasitas 1050 liter Unit 2,289,000.00 Chaba
TB55 Kapasitas 520 liter Unit 1,039,500.00 Jungle Bird Eco
TB55 Kapasitas 520 liter Unit 1,363,900.00 Chaba
TB32 Kapasitas 300 liter Unit 703,500.00 Ex. Penguin
TB32 Kapasitas 300 liter Unit 682,500.00 Jungle Bird Eco
TB300 Kapasitas 3000 liter Unit 5,019,000.00 Ex. Penguin
Tangki Pendam Penguin TP 200 Unit 7,216,200.00 Ex. Penguin
14 Ember Plastik 80 liter + tutup, 215,000.00 Ex. Lion star
Gayung 1,5 ltr 11,500.00 Ex. Lion star

-
15 Grease Trap Grease trap 15 L Unit 838,900.00
Grease trap 40 L Unit 1,363,900.00
-
16 SEPTIC TANK (Hero) -
8 Pemakai 800 liter unit 3,150,000.00
10 Pemakai 1.000 liter unit 3,675,000.00
-
17 AKSESORIS -
Kran Air Biasa bh 28,800.00 1/2"
Onda CLS 01 bh 84,000.00 3/4"
Kran Air Leher Angsa Flexible bh 120,700.00 Onda
Seal tape bh 2,900.00
FLOOR drain SAN-EI Seri HN508P bh 225,700.00
Onda bh 89,200.00
Pompa Air Shimizu PS 130 BIT Unit 661,500.00
-
XIV LAIN-LAIN -
Minyak Beton & bekisting ltr 5,450.00
Kapur Sirih kg 19,800.00
Alang Alang ikat 12,600.00
Allumunium Foil m2 12,600.00
Sabun kg 24,100.00
Soda api kg 28,300.00
Solar ltr 9,000.00
Residu/Ter Ltr 8,400.00
Air Liter 90.00
Spacer/Penjaga Jarak bh 5,650.00
Kuas bh 8,400.00
Ijuk Kg 21,000.00
WATER PROOFING -
LEMKRA DS 105 5 kg 80,000.00 Putih
5 kg 73,000.00 Abu-abu
LEMKRA TG 301 20 Ltr 661,500.00
LEMKRA TG 300 5 Ltr 122,800.00
Primer Waterproofing Membrane Bitumen ltr 55,700.00
Membrane Bitumen Lembar 508,900.00
Membran Bitumen Selulosa ( 1 x 10 m ) Lbr / Roll 1,030,800.00 Bituline
Kristalisasi Penetron kg 1,732,500.00
Printing MMT m2 17,800.00
Seng Galvalume 0,25 m2 38,700.00
Logo Tulisan Untuk Papan Nama Unit 10,500.00
Vertical Blinds Box Op Ex. Sharp Point Deluxe m2 241,500.00
Ex. Sharp Point Blackout m2 367,500.00
Kawat Nyamuk Nylon m2 11,600.00
Wallpaper m2 78,700.00
Lem Wallpaper Kg 160,000.00
Karung Goni m2 5,500.00
-
XVIII BAHAN ALUMUNIUM -
1 Alumunium Profil Warna Silver 4" tipe M tebal 1 mm m' 63,500.00 Ex. Alexindo
Warna Coklat 4" tipe M tebal 1 mm m' 67,700.00 Ex. Alexindo
Alumunium Coating White 4" tipe M tbl 1 mm m' 70,300.00 Ex. Alexindo
Warna Silver 4" tutup M tebal 1 mm m' 30,700.00 Ex. Alexindo
Warna Coklat 4" tutup Mtebal 1 mm m' 32,800.00 Ex. Alexindo
Alumunium Coating White 4" tutup M tbl 1 mm m' 34,000.00 Ex. Alexindo
Warna Silver 4" openback tebal 1 mm m' 54,200.00 Ex. Alexindo
Warna Coklat 4" openback tebal 1 mm m' 57,900.00 Ex. Alexindo
Alumunium Coating White 4" openback tbl 1 mm m' 60,100.00 Ex. Alexindo
Warna Silver 3" tipe M tebal 1 mm m' 51,700.00 Ex. Alexindo
Warna Coklat 3" tipe M tebal 1 mm m' 55,200.00 Ex. Alexindo
Alumunium Coating White 3" tipe M tbl 1 mm m' 57,200.00 Ex. Alexindo
Warna Silver 3" tutup M tebal 1 mm m' 25,200.00 Ex. Alexindo
Warna Coklat 3" tutup Mtebal 1 mm m' 26,900.00 Ex. Alexindo
Alumunium Coating White 3" tutup M tbl 1 mm m' 27,900.00 Ex. Alexindo
Warna Silver 3" openback tebal 1 mm m' 42,600.00 Ex. Alexindo

- Harsat Bahan - -37


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Warna Coklat 3" openback tebal 1 mm m' 45,500.00 Ex. Alexindo


Alumunium Coating White 3" openback tbl 1 mm m' 47,300.00 Ex. Alexindo
Warna Silver Ambang Atas m' 69,800.00 Ex. Alexindo
Warna Coklat Ambang Atas m' 74,500.00 Ex. Alexindo
Coating White Ambang Atas m' 77,300.00 Ex. Alexindo
Warna Silver Ambang Bawah m' 103,600.00 Ex. Alexindo
Warna Coklat Ambang Bawah m' 110,600.00 Ex. Alexindo
Coating White AmbangBawah m' 114,800.00 Ex. Alexindo
Warna Silver Tiang Swing m' 86,900.00 Ex. Alexindo
Warna Coklat Tiang Swing m' 92,800.00 Ex. Alexindo
Coating WhiteTiang Swing m' 96,300.00 Ex. Alexindo
Warna Silver Tiang Engsel m' 92,700.00 Ex. Alexindo
Warna Coklat Tiang Engsel m' 99,000.00 Ex. Alexindo
Coating WhiteTiang Engsel m' 102,700.00 Ex. Alexindo
Warna Silver Siku 3/8 (12 mm) m' 20,700.00 Ex. Alexindo
Warna Coklat Siku 3/8 (12 mm) m' 24,200.00 Ex. Alexindo
Coating White Siku 3/8 (12 mm) m' 28,800.00 Ex. Alexindo
Warna Silver Siku 4/8 (18 mm) m' 26,500.00 Ex. Alexindo
Warna Coklat Siku 4/8 (18 mm) m' 30,000.00 Ex. Alexindo
Coating White Siku 4/8 (18 mm) m' 34,600.00 Ex. Alexindo
Warna Silver Stoper Kaki Casement m' 29,100.00 Ex. Alexindo
Warna Coklat Stoper Kaki Casement m' 31,100.00 Ex. Alexindo
Coating White Stoper Kaki Casement m' 32,300.00 Ex. Alexindo
Warna Silver Stoper Pintu m' 20,000.00 Ex. Alexindo
Warna Coklat Stoper Pintu m' 21,300.00 Ex. Alexindo
Coating White Stoper Pintu m' 22,100.00 Ex. Alexindo
Warna Silver Daun Casement m' 48,400.00 Ex. Alexindo
Warna Coklat Daun Casement m' 51,600.00 Ex. Alexindo
Coating White Daun Casement m' 53,600.00 Ex. Alexindo
Warna Silver Glassbead Casement m' 14,700.00 Ex. Alexindo
Warna Coklat Glassbead Casement m' 15,600.00 Ex. Alexindo
Coating White Glassbead Casement m' 16,300.00 Ex. Alexindo
Spigot Uk. 14x27x1,4 mm m' 12,200.00 Ex. Alexindo
Aluminium Warna Coklat 4" tipe Z tbl 1 mm m' 95,800.00 Ex. Alexindo
Tutup Profil Z Aluminium warna Coklat m' 33,000.00 Ex. Alexindo
Warna Coklat profil 4" tutup polos tebal 1 mm m' 32,500.00 Ex. Alexindo
Hand Railling 2" m' 138,700.00
-
2 Aksesoris Engsel 4" ES AL 2005 for alum bh 54,600.00 Ex. Dekson
Engsel 4" ES IR 4NR for iron bh 50,400.00 Ex. Dekson
Engsel 10" bh 61,700.00 Ex. Dekson
Engsel 3" ES AL 2005 for alum bh 21,800.00 Ex. Dekson
Engsel 3" ES IR 4NR for iron bh 42,000.00 Ex. Dekson
Engsel Sliding / Rel Geser Panjang 200 cm Set 701,400.00 Ex. Dekson
Cesement 12" set 229,900.00 Ex. Dekson
Kait Angin WS 011Z bh 61,900.00 Ex. Dekson
Rambuncis CK 428 bh 31,500.00 Ex. Dekson
Sealant tube 33,600.00
Skrup Fixer bh 475.00
Profil Kaca m' 5,050.00
Handle Pintu + Lockset KC 909 BA/WH set 420,000.00 Ex. Dekson
Spagnolet Tanam bh 20,400.00
Door Closer DCL 300 NHO set 539,700.00 Ex. Dekson
Spandek PVC m2 47,200.00
Sindik Pintu bh 12,800.00
FLOOR Hinge set 918,700.00 Ex. Dekson
Patch Fitting PT 20 PSS bh 834,700.00 Ex. Dekson PT 20 PSS
Pull Handle PH EL801 set 354,900.00 Ex. Dekson
Pull Handle PH D855 set 372,700.00 Ex. Dekson
Rel Pintu Sliding 1,8 mm SR 8701 Unit 880,900.00 Ex. Dekson
Sticker Sandblast m2 52,500.00
Glass Curtain Wall m' 111,600.00
kunci silinder DCDL60 bh 222,600.00 Ex. Dekson
karet tatapan m' 3,400.00
tatapan pintu kusen 4" btg 86,100.00
spigot 1,6 btg 59,800.00
tatapan sliding btg 153,300.00
Bulu Moher m' 4,000.00
Sunscreen / Jalusi Alumunium m2 670,000.00
Skrup 1" (2,5 cm) bh 75.00
Skrup 1 1/4" (3,5 cm) bh 75.00
Skrup 1 1/2" (3,8 cm) bh 75.00
Skrup 2" (5 cm) bh 100.00
sprandell warna coklat lebar 10 cm m' 15,000.00
-
3 Panel Pintu Angzdoor -
economy -
36 x 720 x 2000 Unit 503,800.00
36 x 820 x 2100 Unit 515,000.00
36 x 920 x 2100 Unit 535,800.00
Trimable panel -
36 x 720 x 2100 Unit 604,600.00
36 x 820 x 2100 Unit 630,600.00
36 x 920 x 2100 Unit 656,400.00
Solid block groove with standard router -
36 x 720 x 2100 Unit 881,800.00
36 x 820 x 2100 Unit 892,500.00
36 x 920 x 2100 Unit 937,600.00
-
3 Panel Pintu Teakwood Tebal 9 mm m2 558,300.00
-

- Harsat Bahan - -38


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

XX TAMAN -
1 Tanah Subur m3 177,400.00
2 Pupuk Kandang kg 10,500.00
3 Tanaman Kacang Hias / polybag 3,150.00
4 Tanaman Lantana / polybag 3,150.00
4 Tanaman Pangkas Hijau / polybag 5,250.00
5 Tanaman Pangkas Kuning / polybag 3,150.00
6 Tanaman Pangkas Merah / polybag 4,700.00
7 Pohon Ketapang Kencana 1 m bh 105,000.00
8 Pucuk Merah t. Min 60cm bh 77,900.00
-
XIX BAHAN ASPAL -
1 Aspal Drum drum 2,038,600.00
Drum Kg 13,200.00
Curah Kg 10,900.00
Aspal Emulsi CSS-1 atau SS1 Ltr 12,500.00
-
XX ALAT PELINDUNG DIRI Helm Savety Star Will Unit 93,000.00
Pelindung mata Unit 31,000.00
Tameng muka Unit 93,000.00
Pelindung telinga Unit 57,200.00
Masker pelindung pernafasan dan mulut Box 55,800.00
Sarung tangan Psg 6,150.00
Sepatu keselamatan Psg 335,000.00
Sepatu keselamatan ( rubber safety ) Psg 110,200.00
Penunjang seluruh tubuh Unit 930,700.00
Rompi keselamatan Unit 31,000.00
Pelindung jatuh Unit 124,100.00
-
XXI PINTU-JENDELA PABRIKASI -
1 Pintu UPVC -
Pintu Swing Kaca (90x210) Unit 2,984,100.00 Ex. Prysma
Pintu Swing Panel (90x210) Unit 3,347,900.00 Ex. Prysma
Pintu Swing Combi (90x210) Unit 3,644,500.00 Ex. Prysma
Pintu Double Swing Kaca (155x210) Unit 4,831,300.00 Ex. Prysma
Pintu Double Swing Panel (155x210) Unit 5,478,100.00 Ex. Prysma
Pintu Double Swing Combi (155X210) Unit 6,969,100.00 Ex. Prysma
Pintu Sliding (Gantung) (100X210) Unit 3,332,700.00 Ex. Prysma
Pintu Sliding (BT. Track) (100X210) Unit 2,948,400.00 Ex. Prysma
Pintu Sliding 2 Daun (Gantung) (155X210) Unit 4,726,000.00 Ex. Prysma
Pintu Sliding 2 Daun (220X240) Unit 6,142,500.00 Ex. Prysma
Pintu Sliding 4 Daun (350X240) Unit 11,155,200.00 Ex. Prysma
Pintu Sliding 6 Daun (530X240) Unit 16,414,600.00 Ex. Prysma
-
2 Jendela UPVC -
Jendela Swing (70x135) Unit 1,961,100.00 Ex. Prysma
Jendela Cesement (60x125) Unit 1,626,400.00 Ex. Prysma
Jendela Double Swing (130x125) Unit 3,325,300.00 Ex. Prysma
Jendela Pivot (Putar) (60x120) Unit 4,038,300.00 Ex. Prysma
Jendela Sliding 2 Daun (145x120) Unit 3,316,400.00 Ex. Prysma
Jendela Sliding 3 Daun (245x120) Unit 4,932,300.00 Ex. Prysma
Jendela Sliding 4 Daun (260x120) Unit 6,284,200.00 Ex. Prysma
-
3 Jendela UPVC -
Rolling Door One Sheet Polos Besi Unit 675,000.00
Rolling Door One Sheet Polos Alumunium Unit 785,000.00
Rolling Door One Sheet Perforate 3 baris Unit 830,000.00
Rolling Door One Sheet Perforate 7 baris Unit 850,000.00
Rolling Door One Sheet Full Perforate Unit 880,000.00
Rolling Door Industrial Polos 0.8 mm Unit 1,305,000.00
Rolling Door Industrial Polos 1.0 mm Unit 1,465,000.00
Rolling Door Industrial Polos 1.2 mm Unit 1,620,000.00
Rolling Door Industrial Perforate 1.2 mm Unit 1,750,000.00
Folding Gate PVC Unit 770,000.00
Folding Gate 0.4 mm Unit 605,000.00
Folding Gate 0.5 mm Unit 685,000.00
Folding Gate 0.8 mm Unit 760,000.00
Rangka Folding Gate Tanpa Daun Unit 550,000.00
Pintu Harmonika 0.6 mm Unit 1,110,000.00
Pintu Harmonika 0.8 mm Unit 1,235,000.00
Pintu Harmonika 1.0 mm Unit 1,315,000.00
Pintu Harmonika 1.2 mm Unit 1,475,000.00
Pintu Duco Lipat 1.2 mm Unit 1,085,000.00
Pintu Duco Lipat 1.6 mm Unit 1,195,000.00
Pintu Duco Lipat 1.8 mm Unit 1,305,000.00
Pintu Duco Lipat 2.0 mm Unit 1,380,000.00
Pintu Besi Plat Polos Lipat / Swing 1.2 mm Unit 800,000.00
Pintu Besi Plat Polos Lipat / Swing 1.6 mm Unit 850,000.00
Pintu Besi Plat Polos Lipat / Swing 1.8 mm Unit 900,000.00
Pintu Besi Plat Polos Lipat / Swing 2.0 mm Unit 950,000.00
-
4 Jendela Nako -
Jendela UPVC m2 960,000.00
Jendela Aluminium m2 250,000.00

- Harsat Bahan - -39


PEMERINTAH KABUPATEN BOYOLALI
DINAS PENDIDIKAN DAN KEBUDAYAAN
Komplek Perkantoran Terpadu Kabupaten Boyolali
Jalan Ahmad Yani, Kemiri, Boyolali 57321, Provinsi Jawa Tengah
Telp. (0276) 321048, Faks 321048, Email: info@disdikpora-boyolali.info

RENCANA ANGGARAN BIAYA


OWNER ESTIMATE (OE)

KEGIATAN
REHABILITASI SMP N 1 TERAS

TAHUN ANGGARAN
2022
REKAPITULASI RENCANA ANGGARAN BIAYA
KEGIATAN : REHABILITASI SMP N 1 TERAS
LOKASI : KECAMATAN TERAS
ANGGARAN : 2022

* LOKASI 1
A PEKERJAAN PERSIAPAN 5,791,171.46
B RUANG GURU
I PEKERJAAN BONGKARAN Rp 10,861,920.90
II PEKERJAAN PONDASI Rp 106,806.12
III PEKERJAAN PASANGAN Rp 20,848,758.56
IV PEKERJAAN BETON Rp 38,199,654.57
V PEKERJAAN ATAP Rp 2,707,831.40
VI PEKERJAAN LANGIT-LANGIT Rp 24,940,706.39
VII PEKERJAAN PENUTUP LANTAI Rp 3,527,731.90
VIII PEKERJAAN PENGECATAN Rp 21,299,230.22
IX PEKERJAAN MEKANIKAL ELEKTRIKAL Rp 6,379,998.75
JUMLAH A+B Rp 134,663,810.27

* LOKASI 2
A RUANG KELAS
I PEKERJAAN BONGKARAN Rp 9,241,979.53
II PEKERJAAN TANAH Rp 2,571,856.30
III PEKERJAAN PONDASI Rp 2,760,938.23
IV PEKERJAAN PASANGAN Rp 15,053,353.19
V PEKERJAAN BETON Rp 20,805,874.98
VI PEKERJAAN ATAP Rp 54,764,877.09
VII PEKERJAAN LANGIT-LANGIT Rp 19,758,989.59
VIII PEKERJAAN PENUTUP LANTAI Rp 22,241,652.00
IX PEKERJAAN PENGECATAN Rp 15,535,530.44
X PEKERJAAN PINTU DAN JENDELA Rp 24,295,720.12
XI PEKERJAAN MEKANIKAL ELEKTRIKAL Rp 4,429,081.25
XII PEKERJAAN RAMP & AKSES DIFABLE Rp 6,714,384.90
XIII PEKERJAAN LOKASI 3 Rp 3,321,385.65
JUMLAH A Rp 201,495,623.27

* LOKASI 3
A TOILET
I PEKERJAAN BONGKARAN Rp 1,335,689.82
II PEKERJAAN TANAH Rp 556,679.31
III PEKERJAAN PONDASI Rp 1,827,986.76
IV PEKERJAAN PASANGAN Rp 4,705,223.63
V PEKERJAAN BETON Rp 10,133,321.96
VI PEKERJAAN ATAP Rp 4,166,295.90
VII PEKERJAAN LANGIT-LANGIT Rp 1,930,478.55
VIII PEKERJAAN PENUTUP LANTAI Rp 7,444,107.51
IX PEKERJAAN PENGECATAN Rp 3,528,460.27
X PEKERJAAN PINTU DAN JENDELA Rp 3,003,725.48
XI PEKERJAAN MEKANIKAL ELEKTRIKAL Rp 2,645,201.25
XII PEKERJAAN SANITASI DAN PLUMBING Rp 13,416,510.99
XIII PEKERJAAN LOKASI 1 Rp 85,568,480.87
XIV PEKERJAAN LOKASI 2 Rp 1,134,365.13
JUMLAH A Rp 141,396,527.45

A JUMLAH TOTAL Rp 477,555,960.99


B PPN 11% x (A) Rp 52,531,155.71
C JUMLAH TOTAL (A+B) Rp 530,087,116.70
DIBULATKAN Rp 530,087,000.00
Terbilang : Lima Ratus Sepuluh Juta Tiga Ratus Ribu Rupiah

Boyolali, 2022

Dibuat oleh,
Pejabat Pembuat Komitmen
Dinas Pendidikan dan Kebudayaan
Kabupaten Boyolali

LASNO, S.Pd. M.M


NIP. 19710420 199802 1 002
BACKUP VOLUME GEDUNG
KEGIATAN : REHABILITASI RUANG GURU (LOKASI 1)
LOKASI : SMP N 1 TERAS, BOYOLALI
ANGGARAN : 2022

A PEKERJAAN GEDUNG
I PEKERJAAN PERSIAPAN
VOLUME SAT KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
1 Pek. pembongkaran genteng 227.21 m2 depan 122.21 122.21
belakang 105.00 105.00
JUMLAH 227.21
2 Pek. Pembongkaran rangka atap/kaso/reng 227.21 m2 depan 122.21 122.21
belakang 105.00 105.00
JUMLAH 227.21
3 Pek. Pembongkaran plafond 146.68 m2 R. Guru 7.02 13.20 92.66
Gudang & toilet 7.02 2.68 18.81
Teras timur 5.75 4.00 23.00
Teras barat 3.05 4.00 12.20
JUMLAH 146.68
4 Pek. Pembongkaran dinding bata merah 66.38 m2 As 3 3.25 16.80 54.60
As A & D kolom 3.25 0.20 4.00 2.60
As A & D sloof 0.25 7.25 2.00 3.63
As A & D RB 0.20 7.25 2.00 2.90
As B RB 0.20 7.25 1.45
tambahan kolom 0.60 0.20 10.00 1.20
JUMLAH 66.38
5 Pek. Pembongkaran batu dengan alat 3.00 m3 Pondasi 0.50 0.40 0.40 15.00 3.00
JUMLAH 3.00
6 Pek. Pembongkaran keramik & rabat beton 16.64 m3 dinding selatan 0.80 16.80 13.44
kolom teras 0.80 0.80 5.00 3.20
JUMLAH 16.64

II PEKERJAAN PONDASI
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pasangan Pondasi Batu Belah 1 Pc : 6 Pp 0.12 m3 Bekas galian untuk kolom 0.40 0.10 0.20 15.00 0.12
JUMLAH 0.12

III PEKERJAAN PASANGAN


VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pasangan Batu Bata 1/2 batu 57.07 m2 As 3 3.25 15.77 1.00 51.25
Dinding 15cm
As A & D 3.25 0.05 4.00 0.65
Gunungan As A & D 6.50 2.00 13.00
JUMLAH 64.90
PENGURANG J1 1.45 1.35 4.00 7.83
JUMLAH 7.83
JUMLAH TOTAL 57.07
2 Pekerjaan Pasangan Batu Bata 1 batu 10.25 m2 Dinding 30cm As 2 2.50 4.10 10.25
JUMLAH 10.25
3 Plesteran 133.67 m2 As 3 3.25 15.77 51.25
Dinding 15cm
As A & D 3.25 0.05 0.16
Dinding 30cm As 2 2.50 4.10 10.25
Gunungan As A & D 6.50 2.00 13.00
JUMLAH 74.67
PENGURANG J1 1.45 1.35 4.00 7.83
JUMLAH 7.83
JUMLAH TOTAL x 2 133.67
4 Acian 183.10 m2 As 3 3.25 15.77 51.25
Dinding 15cm
As A & D 3.25 0.05 4.00 0.65
Dinding 30cm As 2 2.50 4.10 10.25
Gunungan As A & D 6.50 2.00 13.00
Kolom 4.25 5.70 24.23
JUMLAH 99.38
KET TINGGI LEBAR PANJANG QTY JUMLAH
PENGURANG J1 1.45 1.35 4.00 7.83
JUMLAH 7.83
JUMLAH TOTAL x 2 183.10

IV PEKERJAAN BETON
1 Pekerjaan Sloof Struktur (SL) 20 x 25 cm Elv. 0.00
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 225 1.21 m3 SL 0.25 0.20 24.20 1.00 1.21
JUMLAH 1.21
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø12 150.60 Kg UTAMA 25.10 0.89 6.00 1.00 150.60
Pekerjaan Pembesian Begel Ø8 49.89 Kg BEGEL 0.76 0.39 168 1.00 49.89

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 12.10 m2 0.50 24.20 1.00 12.10
JUMLAH 12.10
2 Pekerjaan Kolom Praktis (Kp) 15 x 15 cm R.Guru
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 225 0.90 m3 Kp 0.15 0.15 4.00 10.00 0.90
JUMLAH 0.90
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø12 146.42 Kg UTAMA 4.10 0.89 4.00 10.00 146.42
Pekerjaan Pembesian Begel Ø8 50.83 Kg BEGEL 0.46 0.39 28 10.00 50.83

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 14.40 m2 BEGESTING 4.00 3.60 14.40
JUMLAH 14.40
3 Pekerjaan Kolom Praktis (Kp) 15 x 15 cm Teras
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 225 0.39 m3 Kp 0.15 0.15 3.50 5.00 0.39
JUMLAH 0.39
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø12 64.28 Kg UTAMA 3.60 0.89 4.00 5.00 64.28
Pekerjaan Pembesian Begel Ø8 22.43 Kg BEGEL 0.46 0.39 25 5.00 22.43

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 10.50 m2 BEGESTING 3.50 3.00 10.50
JUMLAH 10.50
4 Pekerjaan Balok Latei (BLT) 15 x 20 cm Elv. + 2.75
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 225 0.50 m3 BLT 0.15 0.20 16.80 1.00 0.50
JUMLAH 0.50
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø10 42.90 Kg UTAMA 17.30 0.62 4.00 1.00 42.90
Pekerjaan Pembesian Begel Ø8 25.41 Kg BEGEL 0.56 0.39 116.3 1.00 25.41

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 6.72 m2 BEGESTING 0.40 16.80 1.00 6.72
JUMLAH 6.72
5 Pekerjaan Balok Ring (BR) 15 x 20 cm Elv. + 3.25
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 225 2.32 m3 BR 0.20 0.15 77.20 1.00 2.32
JUMLAH 2.32
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø12 282.84 Kg UTAMA 79.20 0.89 4.00 1.00 282.84
Pekerjaan Pembesian Begel Ø8 115.53 Kg BEGEL 0.56 0.39 529 1.00 115.53

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 50.18 m2 BEGESTING 0.65 77.20 1.00 50.18
JUMLAH 50.18
6 Pekerjaan Rabat Beton Bawah Lantai Tebal 5 cm
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 125 0.67 m3 lantai bongkaran 0.05 0.80 16.80 0.67
JUMLAH TOTAL 0.67

VI PEKERJAAN ATAP KAYU


VOLUME SAT KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Kuda - Kuda Kayu Kruing 8/12 Bentang 7.47 met 1.81 m3 Tiang kuda-kuda 0.01 2.12 4.00 0.08
Kaki kuda-kuda 0.01 8.20 4.00 0.31
Balok tarik 0.01 10.32 4.00 0.40
Balok sokong 0.01 1.80 4.00 0.07
Balok skoor 0.01 3.58 4.00 0.14
Balok gapit 0.01 8.30 4.00 0.24
ikatan angin 0.01 82.20 0.49
Gording penyangga 0.01 3.85 2.00 0.07

JUMLAH 1.81
Begel plat besi 4x40mm 10.00 4.00 40.00
Angkur d12 2.00 4.00 8.00
Mur baut d12 38.00 4.00 152.00

2 Pekerjaan Rangka Atap Kayu Kruing 8/12 (Nok, Gording, M 1.21 m3 NOK 0.01 19.15 0.18
GORDING 0.01 19.15 4.00 0.74
MURPLAT 0.01 16.80 2.00 0.20
SKOOR ANGIN 0.01 0.08 16.00 0.01
PAPAN RUITER 0.00 19.15 0.08

JUMLAH 1.21
3 Pekerjaan Rangka Atap Kayu Kruing 8/12 untuk teras 0.38 m3 Konsul 1 0.01 6.55 4.00 0.06
Konsul 2 0.01 4.75 4.00 0.18
Balok horizontal at 0.01 7.00 0.07
gording ujung 0.01 7.00 0.07

JUMLAH 0.38
4 Pekerjaan Usuk Kayu Kruing 5/7 Dan Reng Kayu Kruing 2/ 227.21 m2 depan 122.21 122.21
belakang 105.00 105.00

JUMLAH 227.21
5 Pekerjaan Pemasangan Atap Genteng Plentong kecil Tana 79.52 m2 DEPAN 42.77 42.77
BELAKANG 36.75 36.75

JUMLAH 79.52
6 Pekerjaan Pemasangan Kembali Atap Genteng Plentong ke 147.69 m2 DEPAN 79.44 79.44
BELAKANG 68.25 68.25

JUMLAH 147.69
7 Pekerjaan Pemasangan Talang 17.00 m' 8.50 2.00 17.00

JUMLAH 17.00
8 Pekerjaan Pemasangan Bubungan Atap Genteng Tanah Li 19.15 m' 19.15 19.15

JUMLAH 19.15
9 Pekerjaan Pemasangan Listplang GRC 9/200 49.60 m' DEPAN 6.30 1.00 6.30
BELAKANG 18.30 1.00 18.30
MIRING 12.50 2.00 25.00

JUMLAH 49.60

VII PEKERJAAN LANGIT - LANGIT


VOLUME SAT KET DIMENSI LEBAR PANJANG JUMLAH
1 Pekerjaan Langit-langit GRC + Rangka Hollow 181.00 m2 R. Guru 6.95 13.20 91.74
Gudang & toilet 6.95 2.70 18.77
Teras timur 5.75 2.22 12.77
Teras barat 3.05 2.22 6.77
Tritisan timur 0.75 12.50 9.38
Tritisan barat 1.35 12.50 16.88
Tritisan selatan 1.35 18.30 24.71

JUMLAH 181.00
2 Pekerjaan List Plafond kayu profil 40.30 m' R. Guru 0 6.95 13.20 40.30

JUMLAH 40.30

VIII PEKERJAAN PENUTUP LANTAI


VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Keramik uk. 40x40 motif 15.92 m2 Ruang guru 0.80 15.90 12.72
Teras 0.80 0.80 5.00 3.20
JUMLAH 15.92
IX PEKERJAAN PENGECATAN
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pengecatan Dinding Lama Interior, Ex. Envi 128.62 m2 Dinding 15cm As 2 3.25 12.90 41.93
As A 3.25 6.95 22.59
As B 3.25 6.95 24.05
As C 3.25 13.55 44.04
As D 3.25 7.25 24.05
JUMLAH 156.65
PENGURANG J1 1.45 1.35 2.00 3.92
P1 2.40 1.40 2.00 6.72
P2 2.00 0.80 4.00 6.40
Void 2.50 4.40 11.00
JUMLAH 28.04
JUMLAH 128.62
2 Pekerjaan Pengecatan Dinding Lama Eksterior, Ex. Envi 132.03 m2 Dinding 15cm As 2 3.25 13.50 43.88
As A 3.25 7.40 24.05
As B 3.25 7.40 24.05
As C 3.25 13.55 44.04
As D 3.25 7.40 24.05
JUMLAH 160.06
PENGURANG J1 1.45 1.35 2.00 3.92
P1 2.40 1.40 2.00 6.72
P2 2.00 0.80 4.00 6.40
Void 2.50 4.40 11.00
JUMLAH 28.04
JUMLAH 132.03

3 Pekerjaan Pengecatan Dinding Baru Interior, Ex. Envi 173.25 m2 As 3 3.25 15.90 51.68
Dinding 30cm As 2 2.50 4.10 2.00 20.50
Kolom 3.25 1.65 5.36
JUMLAH 181.08
PENGURANG J1 1.45 1.35 4.00 7.83
JUMLAH 7.83
JUMLAH 173.25
4 Pekerjaan Pengecatan Dinding Baru Eksterior, Ex. Envi 146.87 m2 As 3 3.25 16.80 54.60
Gunungan As A & D 6.50 2.00 13.00
Kolom 3.25 3.00 9.75
JUMLAH 154.70
PENGURANG J1 1.45 1.35 4.00 7.83
JUMLAH 7.83
JUMLAH 146.87
KET DIMENSI PANJANG ISI QTY JUMLAH
5 Pekerjaan Pengecatan Kayu 57.96 m2 Kusen P1 0.01 8.20 4.00 11.81
Daun P1 1.30 2.25 4.00 11.70
Jalusi P1 1.25 6.00 4.00 7.20
Kusen J1 0.01 9.30 6.00 20.09
Daun J1 4.80 6.00 28.80
Jalusi J1 0.35 18.00 6.00 9.07
JUMLAH 57.96
KET DIMENSI PANJANG ISI QTY JUMLAH
6 Pekerjaan Pengecatan Plafond 156.29 m2 R. Guru 6.95 13.20 91.74
Gudang & toilet 6.95 2.70 18.77
Teras timur 5.75 2.22 12.77
Teras barat 3.05 2.22 6.77
Tritisan timur 0.75 12.50 9.38
Tritisan barat 1.35 12.50 16.88
Tritisan selatan 1.35 18.30 24.71
JUMLAH 156.29
KET DIMENSI PANJANG ISI QTY JUMLAH
7 Pekerjaan Pengecatan List Plafond Ex. Envi 4.03 m2 R. Guru 0.10 6.95 13.20 2.00 4.03

JUMLAH 4.03
8 Pekerjaan Pengecatan Listplank Ex. Envi 9.92 m2 0.20 49.60 9.92
JUMLAH 9.92

X PEKERJAAN PINTU DAN JENDELA


VOLUME SAT KET DIMENSI PANJANG JUMLAH QTY L. Kaca JUMLAH
1 Pemasangan Kunci Tanam Biasa untuk Pintu 2.00 Bh P1 2.00 2.00
2 Pemasangan Engsel Jendela Kupu-kupu 16.00 Bh J1 4.00 4.00 16.00
3 Pemasangan Kait Angin 16.00 Bh J1 4.00 4.00 16.00
4 Pemasangan Kunci Selot 16.00 Bh J1 4.00 4.00 16.00

XI PEKERJAAN MEKANIKAL ELEKTRIKAL


VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Panel box MCB 1.00 Bh 1.00 1.00
2 TL 2x20 RM Armateur In Bow 15.00 Bh 15.00 15.00
3 Lampu 12 watt LED, Ex. Osram 5.00 Bh 5.00 5.00
4 Stop kontak 8.00 Bh 8.00 8.00
5 Saklar tunggal, ex broco 5.00 Bh 5.00 5.00
6 Saklar ganda, ex broco 2.00 Bh 2.00 2.00
BACKUP VOLUME GEDUNG
KEGIATAN : REHABILITASI RUANG KELAS (LOKASI 2)
LOKASI : SMP N 1 TERAS
ANGGARAN : 2022

A PEKERJAAN GEDUNG
I PEKERJAAN PERSIAPAN
VOLUME SAT KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
1 Pek. pembongkaran genteng 194.74 m2 depan 7.25 15.25 110.56
belakang 5.52 15.25 84.18
JUMLAH 194.74
2 Pek. Pembongkaran rangka atap/kaso/reng 194.74 m2 depan 7.25 15.25 110.56
belakang 5.52 15.25 84.18
JUMLAH 194.74
3 Pek. Pembongkaran plafond 142.69 m2 R. Kelas 7.05 10.90 76.85
Teras 2.88 15.25 43.92
Belakang kelas 1.18 11.20 13.22
Samping miring 1.00 8.71 8.71
JUMLAH 142.69
4 Pek. Pembongkaran dinding bata merah 22.91 m3 As B 3.25 7.05 22.91
JUMLAH 22.91
5 Pek. Pembongkaran keramik 101.80 m2 R. Kelas 7.05 10.90 76.85
Teras 24.95
JUMLAH 101.80

II PEKERJAAN TANAH
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pek. GalianTanah Biasa untuk Pondasi Batu kali 7.76 m3 P. Batu belah 1.10 1.00 7.05 7.76
JUMLAH 7.76
2 Pek. Urugan Pasir Bawah Footplate, Pondasi & Lantai 5.73 m3 P. Batu belah 0.05 1.00 7.05 0.35
Lantai R. Kelas 0.05 7.05 10.90 3.84
Teras 0.05 1.75 14.25 1.25
Barat kelas 0.05 0.80 7.20 0.29
JUMLAH 5.73
3 Pek. Urugan Tanah bekas galian 2.59 m3 1/3 vol pondasi 1.10 1.00 7.05 2.59

JUMLAH 2.59

III PEKERJAAN PONDASI


VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pasangan Pondasi Batu Belah 1 Pc : 6 Pp 3.10 m3 0.80 0.80 7.05 3.10
JUMLAH 3.10

IV PEKERJAAN PASANGAN
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pasangan Batu Bata 49.20 m2 As 1 B-C 3.60 2.55 9.18
Dinding 15cm As 2 B-C 3.60 2.55 9.18
As B 3.60 7.35 26.46
Gunungan As A & D 2.40 7.35 8.82
pintu dinding eksisting 1.21 1.00 1.21
jendela dinding eksisting 1.30 0.25 5.00 0.33
JUMLAH 55.18
PENGURANG J1 1.30 2.30 2.00 5.98
JUMLAH 5.98
JUMLAH TOTAL 49.20
2 Plesteran 97.75 m2 As 1 B-C 3.60 2.55 9.18
Dinding 15cm As 2 B-C 3.60 2.55 9.18
As B 3.60 6.90 24.84
Gunungan As A & D 2.40 7.35 8.82
pintu dinding eksisting 1.21 1.00 1.21
jendela dinding eksisting 1.30 0.25 5.00 1.63
JUMLAH 54.86
PENGURANG J1 1.30 2.30 2.00 5.98
JUMLAH 5.98
JUMLAH TOTAL x 2 97.75
3 Acian 99.91 m2 As 1 B-C 3.60 2.55 9.18
Dinding 15cm As 2 B-C 3.60 2.55 9.18
As B 3.60 6.90 24.84
Gunungan As A & D 2.40 7.35 8.82
pintu dinding eksisting 1.21 1.00 1.21
jendela dinding eksisting 1.30 0.25 5.00 1.63
Kolom 3.60 0.30 1.08
JUMLAH 55.94
KET TINGGI LEBAR PANJANG QTY JUMLAH
PENGURANG J1 1.30 2.30 2.00 5.98
JUMLAH 5.98
JUMLAH TOTAL x 2 99.91

V PEKERJAAN BETON
1 Pekerjaan Sloof Struktur (SL) 20 x 25 cm
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 225 0.35 m3 SL 0.25 0.20 7.05 1.00 0.35
JUMLAH 0.35
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø12 42.90 Kg UTAMA 7.15 0.89 6.00 1.00 42.90
Pekerjaan Pembesian Begel Ø8 14.42 Kg BEGEL 0.76 0.39 49 1.00 14.42

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 3.53 m2 0.50 7.05 1.00 3.53
JUMLAH 3.53
2 Pekerjaan Kolom 15 x 15 cm
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 225 0.08 m3 Kp 0.15 0.15 3.60 1.00 0.08
JUMLAH 0.08
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø12 13.21 Kg UTAMA 3.70 0.89 4.00 1.00 13.21
Pekerjaan Pembesian Begel Ø8 4.60 Kg BEGEL 0.46 0.39 26 1.00 4.60

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 1.08 m2 BEGESTING 3.60 0.30 1.00 1.08
JUMLAH 1.08
3 Pekerjaan Balok Latei (BLT) 15 x 20 cm Elv. + 2.45
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 225 1.32 m3 BLT 0.15 0.20 22.00 2.00 1.32
JUMLAH 1.32
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø10 113.09 Kg UTAMA 22.80 0.62 4.00 2.00 113.09
Pekerjaan Pembesian Begel Ø8 66.83 Kg BEGEL 0.56 0.39 153.0 2.00 66.83

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 17.60 m2 BEGESTING 0.40 22.00 2.00 17.60
JUMLAH 17.60
4 Pekerjaan Balok Ring (BR) 15 x 20 cm Elv. + 3.40
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 225 0.76 m3 BR 0.20 0.15 25.24 1.00 0.76
JUMLAH 0.76
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø12 91.57 Kg UTAMA 25.64 0.89 4.00 1.00 91.57
Pekerjaan Pembesian Begel Ø8 37.55 Kg BEGEL 0.56 0.39 172 1.00 37.55

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 12.62 m2 BEGESTING 0.50 25.24 1.00 12.62
JUMLAH 12.62
5 Pekerjaan Lantai Kerja Pondasi Tebal 5 cm
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 125 0.28 m3 FP 0.05 0.80 7.05 1.00 0.28
JUMLAH TOTAL 0.28
6 Pekerjaan Rabat Beton Bawah Lantai Tebal 5 cm
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 125 5.38 m3 R. Kelas 0.05 7.05 10.90 3.84
Teras 0.05 1.75 14.25 1.25
Barat kelas 0.05 0.80 7.20 0.29
JUMLAH TOTAL 5.38

VI PEKERJAAN ATAP KAYU


VOLUME SAT KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Kuda-Kuda Kayu Kruing 8/12 Bentang 7.35 mete 0.61 m3 Tiang kuda-kuda 0.01 2.40 2.00 0.05
Kaki kuda-kuda 0.01 8.26 2.00 0.16
Balok tarik 0.01 8.35 2.00 0.16
Balok skoor 0.01 3.60 2.00 0.07
Balok gapit 0.01 7.00 2.00 0.10
Gording penyangga 0.01 3.85 2.00 0.07

JUMLAH 0.61
Begel plat besi 4x40mm 10.00 2.00
Angkur d12 2.00 2.00 4.00
Mur baut d12 16.00 2.00 32.00

2 Pekerjaan Rangka Atap Kayu kruing 8/12 (Nok, Gording, M 0.74 m3 NOK 0.01 15.25 0.15
GORDING 0.01 11.00 4.00 0.42
MURPLAT 0.01 5.50 2.00 0.11
SKOOR ANGIN 0.01 0.08 4.00 0.00
PAPAN RUITER 0.00 15.25 0.06

JUMLAH 0.74
3 Pekerjaan Usuk 5/7, Reng 2/3 Kayu Kruing 194.74 m2 depan 7.25 15.25 110.56
usuk baru 35%, reng baru total belakang 5.52 15.25 84.18

JUMLAH 194.74
4 Pekerjaan Pemasangan Atap Genteng Plentong kecil Tanah 194.74 m2 DEPAN 7.25 15.25 110.56
BELAKANG 5.52 15.25 84.18

JUMLAH 194.74
5 Pekerjaan Pemasangan Bubungan Atap Genteng Tanah Li 15.25 m' 15.25 15.25

JUMLAH 15.25
6 Pekerjaan Pemasangan Listplang GRC 9/200 56.04 m' DEPAN 15.25 1.00 15.25
BELAKANG 15.25 1.00 15.25
MIRING 12.77 2.00 25.54

JUMLAH 56.04

VII PEKERJAAN LANGIT - LANGIT


VOLUME SAT KET DIMENSI LEBAR PANJANG JUMLAH
1 Pekerjaan Plafond GRC + Rangka hollow 142.69 m2 R. Kelas 7.05 10.90 76.85
Teras 2.88 15.25 43.92
Belakang kelas 1.18 11.20 13.22
Samping miring 1.00 8.71 8.71

JUMLAH 142.69
2 Pekerjaan List Plafond kayu profil 35.90 m' R. Kelas 0 7.05 10.90 35.90

JUMLAH 35.90

VIII PEKERJAAN PENUTUP LANTAI


VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Keramik Lantai Uk 40 x 40 cm putih 96.97 m2 R. Kelas 7.05 10.90 76.85
Teras 20.12

JUMLAH TOTAL 96.97


2 Paving difable (Guilding block) 4.83 m2 Teras 0.30 16.10 4.83

JUMLAH TOTAL 4.83

IX PEKERJAAN PENGECATAN
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pengecatan Dinding Lama Interior, Ex. Envi 92.64 m2 DINDING As 1 3.60 7.35 26.46
As 2 3.60 7.35 26.46
As B 3.60 6.75 24.30
As F 2.40 6.75 16.20
Gunungan 2.40 7.35 17.64
JUMLAH 111.06
PENGURANG P1 2.50 1.00 2.50
JP 1.30 0.75 0.98
J1 1.30 2.30 5.00 14.95
JUMLAH 18.43
JUMLAH 92.64
2 Pekerjaan Pengecatan Dinding Lama Eksterior, Ex. Envi 99.19 m2 DINDING As 1 3.60 7.65 27.54
As 2 3.60 7.35 26.46
As B 3.60 6.75 24.30
As F 2.40 6.75 16.20
Kolom struktur 3.60 0.20 7.60 5.47
Gunungan 2.40 7.35 17.64
JUMLAH 117.61
PENGURANG P1 2.50 1.00 2.50
JP 1.30 0.75 0.98
J1 1.30 2.30 5.00 14.95
JUMLAH 18.43
JUMLAH 99.19
3 Pekerjaan Pengecatan Dinding Baru Interior, Ex. Envi 71.24 m2 DINDING As 1 3.60 2.25 8.10
As 2 3.60 2.25 8.10
As B 3.60 6.75 24.30
Kolom praktis 2.66 0.15 3.60 1.44
Gunungan 2.40 7.35 2.00 35.28
JUMLAH 77.22
PENGURANG J1 1.30 2.30 2.00 5.98

JUMLAH 5.98
JUMLAH 71.24
4 Pekerjaan Pengecatan Dinding Baru Eksterior, Ex. Envi 74.48 m2 DINDING As 1 3.60 2.55 9.18
As 2 3.60 2.55 9.18
As B 3.60 7.05 25.38
Kolom praktis 2.66 0.15 3.60 1.44
Gunungan 2.40 7.35 2.00 35.28
JUMLAH 80.46
PENGURANG J1 1.30 2.30 2.00 5.98

JUMLAH 5.98
JUMLAH 74.48
KET DIMENSI PANJANG ISI QTY JUMLAH
5 Pekerjaan Pengecatan Kayu Ex. Decolux 57.96 m2 Kusen P1 0.01 10.40 1.00 3.74
Daun P1 0.90 2.20 1.00 1.98
Jalusi P1 1.60 3.00 1.00 1.15
Kusen J1 0.01 9.30 6.00 20.09
Daun J1 4.80 6.00 28.80
Jalusi J1 0.35 18.00 6.00 9.07
JUMLAH 57.96
KET DIMENSI PANJANG ISI QTY JUMLAH
6 Pekerjaan Pengecatan Plafond Ex. Decolux 142.69 m2 R. Kelas 7.05 10.90 76.85
Teras 2.88 15.25 43.92
Belakang kelas 1.18 11.20 13.22
Samping miring 1.00 8.71 8.71
JUMLAH 142.69
KET DIMENSI PANJANG ISI QTY JUMLAH
7 Pekerjaan Pengecatan List Plafond Ex. Decolux 3.59 m2 R. Kelas 0.10 7.05 10.90 2.00 3.59

JUMLAH 3.59
8 Pekerjaan Pengecatan Listplank 11.21 m2 0.20 56.04 11.21
JUMLAH 11.21

X PEKERJAAN PINTU DAN JENDELA KAYU


VOLUME SAT KET DIMENSI PANJANG JUMLAH QTY L. Kaca JUMLAH
1 Pek. Kusen Pintu Kayu Kruing 6/12 (1 Unit) 0.07 m3 P1 0.01 10.40 1.00 0.07
2 Pek. Kusen Jendela kayu Kruing 6/12 0.58 m3 J1 0.01 11.50 7.00 0.58
3 Pek. Daun Pintu Kayu Kruing (1 Unit) 1.98 m2 P1 0.90 2.20 1.00 1.00 1.98
4 Pek. Daun Jendela Kayu Kruing 2.77 m2 J1 0.06 6.60 7.00 2.77
5 Pek. Jalusi 3/5 0.01 m3 P1 0.00 1.60 3.00 1.00 0.01
6 Pek. Jalusi 3/5 0.09 m2 J1 0.00 0.70 9.00 7.00 0.09
7 Pek. Kaca bening 5mm (1 unit) 0.67 m2 P1 0.70 0.95 1.00 0.67
8 Pek. Kaca bening 5 mm 11.39 m2 J1 1.63 7.00 11.39
9 Pemasangan Kunci Tanam Biasa 1.00 Bh P1 1.00 1.00
10 Pemasangan Engsel Pintu 3.00 Bh P1 3.00 1.00 3.00
11 Pemasangan Engsel Jendela Kupu-kupu 28.00 Bh J1 4.00 7.00 28.00
12 Pemasangan Kait Angin 28.00 Bh J1 4.00 7.00 28.00
13 Pemasangan Kunci Selot 28.00 Bh J1 4.00 7.00 28.00

XI PEKERJAAN MEKANIKAL ELEKTRIKAL


VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Panel box MCB 1.00 Bh 1.00 1.00
2 TL 2x20 RM Armateur In Bow 9.00 Bh 9.00 9.00
3 Stop kontak 1.00 Bh 8.00 8.00
4 Saklar tunggal, ex broco 1.00 Bh 5.00 5.00
5 Saklar ganda, ex broco 1.00 Bh 2.00 2.00

XII PEKERJAAN RAMP & AKSES DIFABLE


VOLUME SAT KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
1 Urugan tanah 1.50 m3 1.15 1.30 1.50
2 Pasir urug 0.30 m3 0.23 1.30 0.30
3 Cor beton K-175 0.66 m3 0.51 1.30 0.66
4 Rollag 4.20 m2 2.10 2.00 4.20
5 Railling Alumunium 27.20 m' 27.20 27.20
BACKUP VOLUME GEDUNG
KEGIATAN : REHABILITASI TOILET (LOKASI 3)
LOKASI : SMP N 1 TERAS
ANGGARAN : 2022

A PEKERJAAN GEDUNG
I PEKERJAAN PERSIAPAN
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pek. pembongkaran genteng 26.00 m2 4.00 6.50 26.00
JUMLAH 26.00
2 Pek. Pembongkaran rangka atap/kaso/reng 26.00 m2 4.00 6.50 26.00
JUMLAH 26.00
3 Pek. Pembongkaran dinding 22.80 m2 Dinding urinoir 1.50 12.00 18.00
Dinding Bak KM 1.00 1.20 4.00 4.80
JUMLAH 22.80
4 Pek. Pembongkaran keramik 10.56 m2 lantai t. eksisting 1.30 1.60 4.00 8.32
lantai selasar t. eksisting 0.70 3.20 2.24
JUMLAH 10.56

II PEKERJAAN TANAH
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pek. Galian Pondasi 3.65 m3 0.70 0.80 6.52 3.65
JUMLAH 3.65
2 Pek. Urugan Pasir Bawah Footplate, Pondasi & Lantai 0.26 m3 P. batu belah 0.05 0.80 6.52 0.26
Lantai Toilet 0.05
JUMLAH 0.26
3 Pek. Urugan Tanah bekas galian 0.84 m3 1/3 vol pondasi 0.70 0.80 6.52 0.84

JUMLAH 0.84

III PEKERJAAN PONDASI


VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pasangan Pondasi Batu Belah 1 Pc : 6 Pp 2.05 m3 0.70 0.60 6.52 2.05
JUMLAH 2.05

IV PEKERJAAN PASANGAN
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pasangan Batu Bata 15.11 m2 Toilet difable 2.20 6.10 13.42
Dinding 15cm
dinding belakang 0.20 6.50 1.30
Septic tank 1.50 2.50 3.75

JUMLAH 18.47
P1 2.00 0.70 1.00 1.40
PENGURANG P2 2.00 0.90 1.00 1.80
roaster 0.20 0.20 4.00 0.16
JUMLAH 3.36
JUMLAH TOTAL 15.11
2 Plesteran 30.22 m2 Toilet difable 2.20 6.10 13.42
Dinding 15cm
dinding belakang 0.20 6.50 1.30
Septic tank 1.50 2.50 3.75

JUMLAH 18.47
P1 2.00 0.70 1.00 1.40
PENGURANG P2 2.00 0.90 1.00 1.80
roaster 0.20 0.20 4.00 0.16
JUMLAH 3.36
JUMLAH TOTAL x 2 30.22
3 Acian 33.22 m2 Toilet difable 2.20 6.10 13.42
Dinding 15cm
dinding belakang 0.20 6.50 1.30
Septic tank 1.50 2.50 3.75
Kolom 2.50 0.30 2.00 1.50

JUMLAH 19.97
P1 2.00 0.70 1.00 1.40
PENGURANG P2 2.00 0.90 1.00 1.80
roaster 0.20 0.20 4.00 0.16
JUMLAH 3.36
JUMLAH TOTAL x 2 33.22

V PEKERJAAN BETON
1 Pekerjaan Sloof Struktur (SL) 15/20 cm
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 175 0.18 m3 SL 0.20 0.15 6.07 0.18
JUMLAH 0.18
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian D12 26.28 Kg UTAMA 6.57 0.89 4.00 1.00 26.28
Pekerjaan Pembesian Begel Ø8 9.78 Kg BEGEL 0.56 0.39 45 1.00 9.78

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 3.04 m2 0.50 6.07 3.04
JUMLAH 3.04
2 Pekerjaan Kolom 15 x 15 cm
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 175 0.11 m3 Kp 0.15 0.15 2.50 2.00 0.11
JUMLAH 0.11
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø12 19.28 Kg UTAMA 2.70 0.89 4.00 2.00 19.28
Pekerjaan Pembesian Begel Ø8 6.82 Kg BEGEL 0.46 0.39 19 2.00 6.82

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 1.50 m2 BEGESTING 2.50 0.30 2.00 1.50
JUMLAH 1.50
3 Pekerjaan Balok Latei (BLT) 15 x 15 cm Elv. + 2m
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 175 0.14 m3 BLT 0.15 0.15 6.10 1.00 0.14
JUMLAH 0.14
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø10 15.62 Kg UTAMA 6.30 0.62 4.00 1.00 15.62
Pekerjaan Pembesian Begel Ø8 7.71 Kg BEGEL 0.46 0.39 43.0 1.00 7.71

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 1.83 m2 BEGESTING 0.30 6.10 1.00 1.83
JUMLAH 1.83
4 Pekerjaan Balok Ring (BR) 15 x 20 cm Elv. + 2.3
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 175 0.95 m3 BR 0.20 0.15 31.52 1.00 0.95
JUMLAH 0.95
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø12 116.14 Kg UTAMA 32.52 0.89 4.00 1.00 116.14
Pekerjaan Pembesian Begel Ø8 47.57 Kg BEGEL 0.56 0.39 218 1.00 47.57

KET TINGGI LEBAR PANJANG QTY JUMLAH


c. Pekerjaan Begesting 12.61 m2 BEGESTING 0.40 31.52 1.00 12.61
JUMLAH 12.61
5 Pekerjaan Lantai Kerja Pondasi Tebal 5 cm
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 125 0.26 m3 FP 0.05 0.80 6.52 0.26
JUMLAH TOTAL 0.26
6 Pekerjaan Rabat Beton Bawah Lantai Tebal 5 cm
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 125 0.94 m3 lantai difable 0.05 1.50 1.75 0.13
lantai t. baru 0.05 1.10 1.90 0.10
lantai t. eksisting 0.05 1.30 1.60 4.00 0.42
lantai selasar difable 0.05 1.10 3.20 0.18
lantai selasar t. eksisting 0.05 0.70 3.20 0.11

JUMLAH TOTAL 0.94

VI PEKERJAAN ATAP
VOLUME SAT KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan atap baja ringan C.75.75, reng 30.45 26.00 m2 4.00 6.50 26.00

JUMLAH 26.00

2 Pekerjaan atap galvalume 26.00 m2 4.00 6.50 26.00

JUMLAH 26.00
3 Pekerjaan talang seng 3.25 m2 0.50 6.50 3.25

JUMLAH 3.25
4 Pekerjaan Pemasangan Listplang GRC 9/200 6.50 m' 6.50 6.50

JUMLAH 6.50

VII PEKERJAAN LANGIT - LANGIT


VOLUME SAT KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Plafond GRC 14.56 m2 toilet eksisting 1.05 1.25 4.00 5.25
selasar toilet eksisting 0.65 2.75 1.79
toilet difable 1.50 1.75 2.63
toilet baru 1.07 1.75 1.87
selasar toilet difable 1.10 2.75 3.03
JUMLAH 14.56

VIII PEKERJAAN PENUTUP LANTAI DAN DINDING


VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Keramik Lantai Uk 30x30cm unpolish motif 22.50 m2 dinding toilet 0.90 10.52 9.47
lantai difable 1.50 1.75 2.63
lantai t. baru 1.10 1.90 2.09
lantai t. eksisting 1.30 1.60 4.00 8.32

JUMLAH TOTAL 22.50


2 Keramik Lantai Uk 40x40cm unpolish motif 12.29 lantai selasar difable 1.10 3.20 3.52
lantai selasar t. eksisting 0.70 3.20 2.24
dinding toilet bekas bak 0.90 7.25 6.53

JUMLAH TOTAL 12.29

IX PEKERJAAN PENGECATAN
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pengecatan Dinding Interior Ex. Envi 111.94 m2 DINDING As A 2.40 5.25 12.60
As B 2.40 2.57 2.00 12.34
As C 2.40 2.42 2.00 11.62
As D 2.40 2.42 2.00 11.62
As E 2.40 2.42 2.00 11.62
As F 2.40 2.42 5.81
As 2 2.40 3.85 9.24
As 3 2.40 3.85 2.00 18.48
As 4 3.69 4.95 18.27
Kolom 2.40 4.05 9.72

JUMLAH 121.30
PENGURANG P1 0.70 2.00 5.00 7.00
P2 0.90 2.00 1.00 1.80
Roaster 0.20 0.20 14.00 0.56
JUMLAH 9.36
JUMLAH 111.94
2 Pekerjaan Pengecatan Dinding Eksterior Ex. Envi 10.14 m2 DINDING As A 2.40 5.25 12.60
As F 2.40 2.42 5.81
As 2 2.40 3.85 5.81
As 4 3.69 4.95 18.27
Dinding kelas depan toilet 3.25 6.00 19.50
JUMLAH 61.98
PENGURANG P1 0.70 2.00 5.00 7.00
P2 0.90 2.00 1.00 1.80
Roaster 0.20 0.20 14.00 0.56
JUMLAH 9.36
JUMLAH 10.14
KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
3 Pekerjaan Pengecatan Plafond Ex. Envi 14.56 m2 toilet eksisting 1.05 1.25 4.00 5.25
selasar toilet eksisting 0.65 2.75 1.79
toilet difable 1.50 1.75 2.63
toilet baru 1.07 1.75 1.87
selasar toilet difable 1.10 2.75 3.03

JUMLAH 14.56
4 Pekerjaan Pengecatan Listplank 1.30 m2 0.20 6.50 1.30
JUMLAH 1.30

X PEKERJAAN PINTU DAN ROASTER


VOLUME SAT KET LEBAR PANJANG JUMLAH QTY L. Kaca JUMLAH
1 Pekerjaan pintu kamar mandi (P1) 7.00 m2 P1 0.70 2.00 5.00 7.00
2 Pekerjaan pintu kamar mandi (P2) 1.80 m2 P2 0.90 2.00 1.00 1.80
3 Roaster 0.56 m2 R 0.20 0.20 14.00 0.56

XI PEKERJAAN MEKANIKAL ELEKTRIKAL


VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Panel box MCB 1.00 Bh 1.00 1.00
2 LED 15 watt 8.00 Bh 8.00 8.00
3 Saklar tunggal, ex broco 2.00 Bh 2.00 2.00
4 Saklar ganda, ex broco 3.00 Bh 3.00 3.00

XI PEKERJAAN SANITASI DAN PLUMBING VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
A PEKERJAAN SANITASI
1 Pek Pasangan Closet Jongkok Porselen 1.00 Bh
2 Pek. Pasangan Closet Duduk Mono Blok Ex. Toto Seri CW702J/SW784J 1.00 Bh
3 Pek. Pasang Floordrain 6.00 Bh
4 Pemasangan Kran Ø ½" atau Ø ¾" 6.00 Bh
B PEKERJAAN PLUMBING
1 Pipa PVC AW 3" (Pipa Air Hujan) 15.00 m'
2 Pipa PVC AW 3" (Pipa Air Kotor Padat) 10.00 m'
3 Pipa PVC AW 3" (Pipa Air Kotor Cair) 10.00 m'
4 Pipa PVC AW 1" (Pipa Air Bersih) 16.50 m'

XII PEKERJAAN RAMP & AKSES DIFABLE


VOLUME SAT KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
1 Urugan tanah 1.13 m3 1.33 0.85 1.13
2 Pasir urug 0.74 m3 0.64 1.15 0.74
3 Cor beton K-175 0.48 m3 0.42 1.15 0.48
4 Rollag 2.56 m2 1.28 2.00 2.56
5 Railling Alumunium 17.26 m' 17.26 17.26
DAFTAR HARGA SATUAN BAHAN BANGUNAN
TAHUN 2022

PEKERJAAN : REHABILITASI SMP N 1 TERAS


LOKASI : SMP N 1 TERAS, BOYOLALI
TAHUN ANGGARAN : 2022
WILAYAH : I (SATU)

HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

I BAHAN DASAR

1 BATU BELAH
Batu Gunung Belah m3 247,500.00

2 KERIKIL
Beton 5 - 7 cm m3 253,000.00 Pecah mesin
Beton 3 - 5 cm m3 253,000.00 Pecah mesin
Beton 2 - 3 cm m3 253,000.00 Pecah mesin
Beton 1 - 2 cm m3 253,000.00 Pecah mesin
Beton 0.5 - 1 cm m3 253,000.00 Pecah Mesin
-
3 BATU BATA
ex lokal bh 800.00
Bata Ekspose bh 1,200.00 dim 4.5 x 11 x 22
Concrete Block ( CB 15 ) / Batako (lubang 2 bh 3,300.00
Roster Beton Abu Uk 20x20 bh 19,800.00
Bata ringan m3 -
4 PASIR
Urug m3 192,500.00
Pasang m3 251,200.00
Beton m3 253,000.00
5 TANAH -
Sirtu m3 151,800.00
Tanah Padas m3 63,800.00
Tanah Biasa m3 60,100.00
Sirtu (Quarry) m3 63,800.00
Tanah Padas (Quarry) m3 40,500.00
Tanah Biasa (Quarry) m3 36,000.00
Tanah Subur m3 63,800.00
-
6 KAPUR Pasang m3 231,000.00
-
7 PORTLAND CEMENT -
Portland Cement 40 kg zak 52,800.00
Portland Cement kg 1,260.00
Semen Putih 40 kg zak 112,800.00
Semen warna kg 16,500.00
Semen Putih kg 6,100.00
Pengisi Nat AM 50 kg 22,000.00
-
8 Plastik Plastik tebal 0,08 gulung 132,000.00 uk 1,5x25 m
Plastik tebal 0,08 m2 39,600.00
Plastik tebal 0,125

II BAHAN PENUTUP ATAP -

- Harsat Bahan - -51


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

1 GENTENG TANAH LIAT -


Genteng Lokal Tipe Plenthong bh 1,500.00
Genteng Kebumen Tipe Plentong Kecil bh 3,900.00
Genteng Kebumen Tipe Morando bh 5,500.00
Genteng Keramik Kanmuri bh 8,800.00
Genteng Keramik KIA Kw I bh 11,300.00
Genteng Keramik Glazur Super Jatiwangi Bh 6,200.00
Genteng Kerpus Lokal bh 1,800.00
Genteng Kerpus Kebumen bh 13,200.00
Genteng Kerpus Keramik bh 29,900.00
Genteng Sirap Keramik bh 2,520.00 Isi 50 bh/m2

5 ASBES Asbes Gelombang Besar -


200 x 102 x 0.5 cm bh 93,500.00
240 x 102 x 0.5 cm bh 112,200.00
Asbes Gelombang Kecil -
180 cm X 102 cm X 0.5 cm bh 71,500.00
240 cm X 102 cm X 0.5 cm bh 82,500.00
-
NOK ASBES Gelombang Kecil bh 37,000.00
Gelombang Besar bh 38,500.00
-
5 ASBES PLAT 100 cm X 100 cm X 4 mm bh 17,600.00
-
6 SENG PLAT BJLS 0,25 lebar 45 cm m' 22,000.00
BJLS 0,25 lebar 60 cm m' 28,600.00
BJLS 0,25 lebar 90 cm m' 38,500.00

7 SENG GELOMBANG BJLS 0,30 panjang ( 90x180 ) cm lbr 44,000.00


BJLS 0,30 panjang ( 90x240 ) cm lbr 112,200.00
BJLS 0,20 panjang ( 90x180 ) cm lbr 58,300.00
BJLS 0,20 panjang ( 90x210 ) cm lbr 69,300.00
BJLS 0,20 panjang ( 90x240 ) cm lbr 79,200.00
BJLS 0,20 panjang ( 90x300 ) cm lbr 95,200.00

8 SENG TALANG BJLS 0,2 lebar 60 cm m' 26,000.00


BJLS 0,2 lebar 90 cm m' 35,500.00
BJLS 0,2 lebar 120 cm m' 63,300.00
-
9 ASPAL BITUMEN Atap Onduvila lbr 44,900.00 106 x 40 x 0.30 cm
Atap Onduline lbr 156,400.00 200 x 95 x 0.30 cm
Atap Sirap Bardoline m2 151,100.00
Nok Onduvila / Onduline lbr 67,400.00 100 x 50 x 0.30 cm
Skrup pcs 1,200.00

10 Lisplank GRC
Lisplank GRC 9/200 lbr 60,500.00 Panjang 400 cm
Lisplank GRC 9/300 lbr 99,200.00 Panjang 400 cm
Skrup 3 cm pcs 200.00
-
10 ATAP GALVALUME Atap Galvalume tebal 0,4 mm m2 81,200.00
Nok Atap Galvalume tebal 0,4 mm m' 26,800.00
Atap Galvalume tebal 0,3 mm m2 40,700.00
Nok Atap Galvalume tebal 0,3 mm m' 41,400.00
Atap Galvalume tebal 0,25 mm m2 34,700.00
Atap Spandek Transparan 0,3 mm m2 81,100.00

- Harsat Bahan - -52


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

11 ATAP METAL Genteng Ex. Sakura Roof Elang lbr 78,700.00 Type Classic
Nok Atap Metal bh 45,300.00 Type Ratu
Penutup Nok bh 16,200.00 Type Ratu
Skrup pcs 800.00

12 ATAP POLYCARBONATE Polycarbonate tebal 6 mm lbr 1,925,000.00 Uk. 2,1 x 11,8 m


Polycarbonate tebal 6 mm m2 77,700.00 Ex. Twinlite
-
10 ATAP UPVC -
Atap uPVC Alderon White / Blue m2 205,600.00 Lebar Efektif 86 cm
Atap uPVC Alderon Translucent m2 259,900.00 Lebar Efektif 86 cm
Nok uPVC Alderon White / Blue m' 155,900.00
Sekrup alderon bh 2,300.00

III BAHAN KAYU -


1 JATI Papan m3 40,700,000.00
Balok/pesagen m3 29,700,000.00
Reng 2/3 m3 8,250,000.00
-
2 KAMPER Papan m3 7,244,900.00
Balok/pesagen m3 6,727,400.00
-
3 KRUING Papan m3 8,800,000.00
Balok/pesagen m3 7,150,000.00
-
4 MERANTI Papan m3 5,175,000.00
Balok/pesagen m3 4,140,000.00
Papan Begesting m3 3,420,000.00

5 LANAN Papan m3 1,863,000.00


Balok/pesagen m3 1,785,800.00

6 SENGON Papan m3 3,025,000.00


Balok/pesagen m3 2,750,000.00
-
7 BENGKIRAI Papan m3 13,750,000.00
Balok/pesagen m3 11,000,000.00
-
8 DOLKEN Sedang 8 - 10 x 400 cm bt 3,100.00
Kayu bakar m3 776,200.00
-
9 BAMBU Bambu Apus btg 14,400.00 Panjang 4 meter
Bambu Petung btg 31,000.00 Panjang 4 meter
Anyaman Bambu m2 28,900.00
-
10 KAYU LIST List Polos m' 6,600.00
List Profil m' 9,900.00

IV BAHAN PENUTUP DINDING / LANTAI -


1 UBIN (TEGEL BIASA) -
PC polos 30 X 30 cm m2 3,800.00
20 X 20 cm m2 1,300.00
-
2 KERAMIK LANTAI
Keramik lantai 20/20 KIA ( Textur) bh 2,500.00

- Harsat Bahan - -53


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Keramik lantai 20/20 Platinum (unpolish) bh 2,600.00


Keramik lantai 30/30 Mulia ( Polish ) bh 4,000.00
Keramik lantai 30/30 Mulia ( Unpolish ) bh 5,100.00
Keramik lantai 40/40 Hercules bh 10,900.00
Keramik lantai 40/40 Asia Tile Murano bh 8,300.00
Keramik lantai 40/40 Oscar bh 10,100.00
Keramik lantai 60/60 Hercules bh 23,400.00
Keramik lantai 40/40 Platinum bh 10,700.00
Keramik lantai 50/50 Platinum bh 17,900.00
Keramik lantai 30/30 Platinum bh 5,200.00
Keramik lantai 25/25 Platinum (unpolish) bh 4,300.00
Pengisi Nat AM 50 kg 19,800.00
-
3 KERAMIK DINDING
Keramik dinding 30/30 KIA bh 6,400.00
Keramik dinding 10/20 KIA bh 1,500.00
Keramik dinding 20/20 KIA bh 2,700.00
Keramik dinding 20/25 KIA bh 2,800.00
Keramik dinding 25/40 KIA bh 6,800.00
Keramik dinding 25/40 Platinum bh 6,800.00
Keramik dinding 25/50 Platinum bh 9,900.00

4 HOMOGENOUS TILE
Homogenous Tile 60/60 Indogress TPZ bh 51,700.00
Homogenous Tile 60/60 Top Gress bh 38,000.00
Homogenous Tile 60/60 Cove bh 38,000.00
Homogenous Tile 60/60 Chivas bh 37,300.00
Step Nosing 10/30 m1 20,700.00

PLINT DINDING
Keramik Dinding 10/20
Keramik Dinding 10/30
Keramik Dinding 10/40
Keramik Dinding 10/60

5 BATU ALAM
Batu Andesit 20x40 m2 150,200.00
Batu Andesit 20x20 m2 138,600.00
Batu Andesit Alur 40x40 m2 161,700.00
Batu Lempeng Acak m2 67,300.00
Batu Sikat m2 129,300.00
Susun Sirih 3 x 30 cm m2 127,100.00

6 GEOMEMBRANE
Geomembrane 1 mm m2 51,300.00
Geomembrane 1.5 mm m2 71,100.00
Geomembrane 2 mm m2 97,100.00
-
V BAHAN CETAK -
1 BUIS BETON
Ø 20 cm Panjang 100 cm bh 48,400.00
Ø 30 cm Panjang 100 cm bh 60,500.00
Ø 40 cm Panjang 100 cm bh 93,500.00
Ø 50 cm Panjang 100 cm bh 132,000.00
Ø 60 cm Panjang 100 cm bh 99,000.00

- Harsat Bahan - -54


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Ø 60 cm Panjang 50 cm bh 13,200.00
Ø 80 cm Panjang 100 cm bh 214,500.00
Ø 80 cm Panjang 50 cm bh 143,000.00
Ø 100 cm Panjang 100 cm bh 236,500.00
Ø 100 cm Panjang 50 cm bh 187,000.00
U 10 cm - 100 cm bh 18,400.00
U 15 cm - 100 cm bh 22,400.00
U 20 cm - 100 cm bh 24,200.00
U 30 cm - 100 cm bh 30,300.00

2 LUBANG ANGIN (ROSTER) PC + PASIR


20 X 20 cm bh 8,200.00

3 PAVING -
Holland 20 x 10 x 6 cm K.250 - K.300 m2 80,500.00 Natural Ex.Master Beton
m2 92,000.00 Warna Ex.Master Beton
Holland 21 x 10,5 x 8 cm K.300 m2 103,500.00 Ex.Master Beton
m2 115,000.00 Warna Ex.Master Beton
Kubus 20 x 20 x 6 cm K.250 - K.300 m2 80,500.00 Natural
m2 92,000.00 Warna
Kubus 20 x 20 x 8 cm K.250 - K.300 m2 103,500.00 Natural
Warna
Hexagon 20 x 20 x 6 cm K.250 - K.300 m2 103,500.00 Natural
115,000.00 Warna
Grass Block Kotak 30 x 30 x 8 cm m2 80,500.00 Natural
103,500.00 Warna
Topi Uskup 30 x 21 x 6 cm K.250 - K.300 m' 5,750.00 Natural
6,325.00 Warna
Kanstein Besar/Kerb 20 x 30 x 60 cm bh 63,250.00 Ex.Master Beton
Kanstein Lock Kecil 10 x 20 x 40 cm bh 23,000.00 Ex.Master Beton
Kanstein Lock Besar 10 x 20 x 50 cm bh 28,750.00 Ex.Master Beton
Kanstein L Profil 39,5x43x42 cm bh 69,000.00 Ex.Master Beton
Kerb Standart 10/12x35x50 bh 46,000.00 Ex.Master Beton
-
4 U-DITCH -
U-Ditch 300x300x1200 Type LD Bh 354,000.00
Cover U-Ditch 300x1200 10 cm Type LD bh 230,100.00

VI BAHAN BESI -
1 BESI
Besi beton polos / Ulir / Tulangan kg 14,200.00
Besi siku kg 12,800.00
Besi Strip kg 12,800.00
Besi Plat kg 17,300.00
Wiremesh kg 12,900.00
2 BAJA -
Baja Profil / Konstruksi kg 14,900.00
Baja Teralis kg 10,600.00
Baja Konstruksi kg 12,600.00
Baut mur 8.8 3/4x2 Bh 7,300.00
Angkur Bolt NC M16x30 Bh 41,600.00

3 KAWAT -
Kawat Ikat Beton / Bendrat kg 17,300.00
Kawat Duri kg 12,300.00
Kawat Bronjong kg 17,300.00

- Harsat Bahan - -55


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Kawat Harmonika Galvanis dia.1,2mm m2 20,200.00 Uk.40x40mm


Kawat Sling 6mm m1 8,300.00
Kawat Las kg 41,300.00
3 PAKU
Paku kg 18,700.00
4 HOLLOW GALVANIS
Hollow Galvanis 2.4. 400 m' 4,500.00
Hollow Galvanis 4.4. 400 m' 6,400.00
5 BAJA RINGAN
Baja Ringan C.75.75 Ex. Fortuna m' 17,100.00
Baja Ringan Reng 30.45 Ex. Fortuna m' 6,400.00
-
6 METAL STUD MS.76 m' 24,000.00

7 PAGAR BRC Pagar BRC 6 mm Biasa (2.4x1.2 m) lbr 262,100.00


Pagar BRC 6,8 mm Galvanis (2.4x1.2 m) lbr 544,500.00
Pagar BRC 7 mm Biasa (2.4x1.2 m) lbr 432,300.00
Pagar BRC 7 mm Galvanis (2.4x1.2 m) lbr 639,300.00
-
VII B A H A N P I P A -
1 Pipa PVC SII SCJ , S - 12,5 (10 bar) Ex Maspion pjg.6m -
Pipa PVC DN 20 ( ½" ) AW JIS btg 13,500.00 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 21,300.00 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 33,800.00 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 84,900.00 panjang 6 m
Pipa PVC DN 63 ( 2" ) btg 191,400.00 panjang 6 m
Pipa PVC DN 90 ( 3" ) btg 384,100.00 panjang 6 m
Pipa PVC DN 110 ( 4" ) btg 564,300.00 panjang 6 m
Pipa PVC DN 160 ( 6" ) btg 1,192,000.00 panjang 6 m
-
Pipa PVC AW Wavin 3/4" m' 10,600.00
Pipa PVC AW Wavin 1" m' 14,400.00
Pipa PVC AW Wavin 2" m' 31,700.00
Pipa PVC AW Wavin 3" m' 58,500.00
Pipa PVC AW Wavin 4" m' 96,800.00
-
2 Pipa PVC SII SCJ , S - 12,5 (8 bar) Ex Maspion pjg.6m btg - panjang 6 m
Pipa PVC DN 40 ( 1 1/2" ) btg 122,800.00 panjang 6 m
3 Pipa PVC AW panjang 4m -
Pipa PVC AW Wavin 1/2" m' 7,300.00 panjang 4 m
Pipa PVC AW Wavin 3/4" m' 9,900.00 panjang 4 m
Pipa PVC AW Wavin 1" m' 13,000.00 panjang 4 m
Pipa PVC AW Wavin 1 1/4" m' 19,400.00 panjang 4 m
Pipa PVC AW Wavin 1 1/2" m' 22,400.00 panjang 4 m
Pipa PVC AW Wavin 2" m' 28,500.00 panjang 4 m
Pipa PVC AW Wavin 2 1/2" m' 41,600.00 panjang 4 m
Pipa PVC AW Wavin 3" m' 58,500.00 panjang 4 m
Pipa PVC AW Wavin 4" m' 96,800.00 panjang 4 m
Pipa PVC AW Wavin 6" m' 216,300.00 panjang 4 m
4 Pipa Medium A Galvanis - panjang 6m -
Pipa Medium B Galvanis DN ½" btg 217,800.00 panjang 6 m
Pipa Medium B Galvanis DN 25 ( ¾" ) btg 277,200.00 panjang 6 m
Pipa Medium B Galvanis DN 32 ( 1" ) btg 415,800.00 panjang 6 m
Pipa Medium B Galvanis DN 50 ( 1½" ) btg 621,700.00 panjang 6 m
Pipa Medium B Galvanis DN 63 ( 2" ) btg 843,500.00 panjang 6 m
Pipa Medium B Galvanis DN 90 ( 3" ) btg 1,390,000.00 panjang 6 m

- Harsat Bahan - -56


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Pipa Medium B Galvanis DN 110 ( 4" ) btg 2,015,600.00 panjang 6 m


Pipa Medium B Galvanis DN 160 ( 6" ) btg 3,227,400.00 panjang 6 m
-
5 Pipa Besi Stainless Steel -
dia. 3/4" btg 215,900.00 panjang 6 m
dia. 1" btg 269,900.00 panjang 6 m
dia. 2" btg 431,700.00 panjang 6 m
dia. 3" btg 785,400.00 panjang 6 m
dia. 4" btg 1,051,100.00 panjang 6 m

6 Pipa HDPE SDR 17 - Ex. Maspion


Dia. 50 mm m' 28,400.00
Dia. 63 mm m' 44,900.00
Dia. 75 mm m' 61,400.00
Dia. 90 mm m' 88,400.00
Dia. 110 mm m' 131,300.00
7 Bend All Flange -
Bend all flange Ø 2" x 90 bh 292,200.00
Bend all flange Ø 3" x 90 bh 347,900.00
Bend all flange Ø 4" x 90 bh 514,900.00
Bend all flange Ø 2" x 45 bh 272,600.00
Bend all flange Ø 3" x 45 bh 333,300.00
Bend all flange Ø 4" x 45 bh 464,900.00
8 Cek Valve - Ex. Onda kuningan drat
Cek Valve Ø 1/2" bh 117,000.00
Cek Valve Ø 1 1/2" bh 497,100.00
Cek Valve Ø 2" bh 787,500.00
Cek Valve Ø 3" bh 2,181,500.00
Cek Valve Ø 4" bh 1,751,400.00
9 Flange Steel -
Dia. 1.5" bh 56,900.00
Dia. 2" bh 58,800.00
10 Gate Valve -
Dia. 1.5" bh 416,200.00
Dia. 2" bh 799,500.00
11 Keni Galvanis -
Keni Galvanis Ø 1.5" x 90 bh 27,200.00
Keni Galvanis Ø 2" x 90 bh 42,900.00
12 Pressure Gauge -
Dia. 2 1/2" bh 103,700.00
13 Pipa Udara bh 316,300.00
14 Manhole bh 506,000.00
Water Meter 1/2" ex. Nankai bh 115,500.00
Socket PVC 3/4" x 3/4" bh 2,800.00
Clamp Saddle CI 2" x 3/4" bh 31,900.00
Tee PVC 1/2" bh 3,300.00
Fix Coupling 1/2" (Kuningan) bh 28,100.00
Kran Air 1/2" (Kuningan) bh 29,700.00
Gate Valve 1/2" (Kuningan) bh 68,800.00
-
-
VIII B A H A N L A N G I T - L A N G I T -
1 SOFT BOARD ( 1.2 m x 2.4 m ) -
Soft Board Tebal 9 mm Jayaboard lbr 82,000.00
Soft Board Tebal 9 mm Jayaboard WR lbr 99,000.00
Soft Board Tebal 9 mm Elephant lbr 77,600.00

- Harsat Bahan - -57


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Soft Board Tebal 9 mm Knauf lbr 73,200.00


Soft Board Tebal 9 mm Star lbr 93,500.00
Soft Board Tebal 9 mm Aplus lbr 82,500.00
-
Sekrup Gypsum Sunray 6 x 2" bh 200.00
Compound Compound Knauf kg 5,500.00
Compound Aplus kg 5,800.00
GRC Board tebal 4mm 1200 x 2400 x 0.4 cm lbr 60,500.00
Dinabolt Bh 3,900.00
Cotton Plaster 75 m m' 200.00
List Gypsum Lebar 10 cm m' 13,200.00
List Kayu Profil m' 9,900.00
Tepung Gypsum kg 3,900.00
Cornice Adhesive Kg 4,400.00
Textile Tape m' 1,100.00

3 HARDFLEX 1200 x 2400 x 5 mm lbr 60,500.00


1000 x 1000 x 5 mm lbr 35,100.00
900 x 1800 x 5 mm lbr 47,500.00
4 PLY WOOD -
1200 x 2400 x 3 mm lbr 55,000.00
1200 x 2400 x 4 mm lbr 64,900.00
1200 x 2400 x 6 mm lbr 10,500.00
1200 x 2400 x 8 mm lbr 115,500.00
1200 x 2400 x 12 mm lbr 181,100.00
1201 x 2400 x 15 mm lbr 208,600.00
Urat Jati (Teakwood) lbr 96,300.00
Lapis Formika lbr 60,000.00

Skrup pcs 200.00


-
6 PVC Polos m2 90,600.00 Ex. Wifon
-
6 Alumunium Composit Panel m2 244,300.00 Ex. Seven
Rangka Besi Hollow + Bracing m2 215,900.00
-
7 Exhaust Fan Ceiling Panasonic 10" FV25TGU Unit 415,800.00
Panasonic 8" FV20TGU Unit 496,800.00
Maspion 10" MV-250NEX Unit 420,000.00
Maspion 8" CEF-20MP Unit 323,900.00

IX BAHAN FINISHING -
1 KAYU -
Menie Kayu kg 40,700.00
Dempul plamur kg 38,300.00
Ambril/amplas lbr 4,600.00
Batu Apung kg 20,700.00
Cat Kayu Decolux kg 60,000.00
Siralax ons 10,300.00
Spiritus ltr 26,400.00
Melamik kg 53,700.00
Lem Kayu Fox Kuning kg 74,300.00
HPL Motif Serat Kayu (2,4 x 1.2 m) lbr 170,800.00
Foam Sheet 3 mm m2 6,700.00
-
2 TEMBOK -

- Harsat Bahan - -58


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Plamur Plamur kg 30,000.00


Cat Dasar
Ex. Catylac kg 29,700.00
Ex. Jotun Jotashield Primer Kg 44,100.00
Cat Tembok
Ex. Catylac kg 29,500.00
Ex. Jotun Jotashield Antifade kg 91,600.00
Ex. Nippon Weatherbond Kg 72,500.00
Ex. Mowilex kg 71,900.00
Ex. Envi -
Coating welstone liter 84,700.00 Ex. Propan Stone Care
-
3 BESI -
Menie nusatex kg 46,200.00
Cat Ex. Decolux kg 66,000.00
Ex. Danagloos kg 82,500.00
Cat Poxy Ex. Penta kg 49,500.00
Thinner A ltr 29,400.00
Minyak cat ltr 25,900.00
Lem Aica Aibon kg 38,600.00
-
X BAHAN KACA -
1 BENING/POLOS
5 mm m2 108,700.00
8 mm m2 139,700.00
12 mm m2 258,700.00
2 ES KABUR
3 mm m2 94,400.00
5 mm m2 118,800.00
3 RAY BAND -
5 mm m2 110,800.00
8 mm m2 206,900.00
12 mm m2 234,000.00
4 TEMPERED
10 mm m2 683,100.00
12 mm m2 776,200.00

-
5 STOPSOL Dark Blue 8 mm m2 438,700.00
Dark Green 8 mm m2 456,300.00
-
XI BAHAN INSTALASI LISTRIK -
1 KABEL NYY 3 x 2.5 mm m' 12,700.00
NYM 3 x 2.5 mm m' 16,500.00
NYFGBY 3 x 2,5 mm m' 21,300.00
NYM 2 x 2.5 mm m' 11,000.00
NYY 2 x 2.5 mm m' 9,300.00

2 Kabel penghantar BC 6 mm m1 19,800.00


3 Kabel inpure LVTC 2 x 25 mm m1 13,400.00
4 Kabel Seling NYM 3 x 4 mm m1 22,300.00
5 Pipa Inpure ( galvanis 2" ) bh 198,000.00
6 Knee Pipa Inpure ( galvanis 2" ) bh 19,800.00
7 Klem Pipa Inpure bh 25,700.00
8 Pole band Inpure bh 69,300.00
9 Pole band Box bh 69,300.00

- Harsat Bahan - -59


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

10 Kanal C m1 44,600.00
11 Timer bh 742,500.00
12 Kontaktor bh 594,000.00
13 Terminal komplit unit 29,700.00
14 Ground Rood bh 59,400.00
15 Pipa Flexibel m1 5,900.00
16 MCB 10A bh 59,400.00
17 Isolasi bh 7,700.00
18 MCB bh 54,000.00
19 MCCB 200 A bh 1,100,000.00
20 Box MCB bh 161,900.00 Ex. Schneider
21 Isolasi bh 7,200.00
22 Box Panel MCB 30x40x20 cm bh 214,100.00
23 Box Panel MCB 60x80x20 cm bh 665,500.00
24 Rel MCB bh 22,000.00
25 Lampu Indikator bh 18,800.00
26 Sekun 4mm bh 1,900.00
27 Material Pendukung ( Isolasi, Kabel Ties dll ) Paket 360,000.00
28 Pipa PVC 2" AW m1 12,400.00
29 Klem Unit 300.00

30 Lampu
Baret / Plafond Kecil Unit 194,300.00 Ex. Panasonic Kecil
Baret / Plafond Besar Unit 262,400.00 Ex. Panasonic Besar

Philips LED 11 Watt bh 57,200.00


Philips LED 9 Watt bh 49,500.00
Philips LED 7 Watt bh 40,700.00
Lampu Tornado 15 watt Philips cdl(15 Watt bh 48,000.00
Kap Lampu bh 36,000.00
31 Armateur Downlight
Silver Chrome 4" In Bow Unit 44,000.00 Ex. Panasonic NLP72332
White / Black 4" Out Bow Unit 86,300.00 Ex. Panasonic
Silver Chrome 4" Unit 32,300.00 Ex. Meiwa
Armateur Downlight Silver Chrome 3" Unit 33,000.00 Ex. Meiwa
Fitting Lampu Bh 14,300.00 Ex. Broco
32 Stop Kontak Dinding
Ex. Broco IB 6100 Standart bh 10,800.00
Panasonic WEJP 11217 bh 18,800.00
Clipsal bh 28,600.00
-
Stop Kontak Lantai Panasonic bh 323,900.00
-
Stop Kontak AC Panasonic WBJ1214W3K bh 66,000.00

32 Saklar Double Switch -


Ex. Broco Standar bh 19,800.00
Ex. Broco Seri Galileo bh 18,300.00
Ex. Panasonic Seri WEJ78029W bh 24,300.00
Clipsal bh 31,800.00
33 Saklar Single Switch -
Ex. Broco Standar bh 16,500.00
Ex. Broco Seri Galileo bh 16,100.00
Ex. Panasonic Seri WEJ78019W bh 17,800.00
Clipsal bh 26,400.00

- Harsat Bahan - -60


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

34 Tee Dos bh 3,300.00


35 Pipa Clipsal m' 3,100.00
36 Sock Unit 300.00
37 Klem Unit 300.00
38 Listrik kwh 600.00
-
XII ALAT - ALAT PENGUNCI & PENGGANTUNG -
1 KUNCI TANAM -
Bellucci 2 X slag bh 169,500.00 Seri HP.858.43BZ
-
Muller ( Putih ) 2 X slag bh 172,800.00 Seri 952184 SN/CP
Muller ( Kuning ) 2 X slag bh 172,800.00 Seri 952184 SN/GP
-
2 ENGSEL DAN GERENDEL -
Engsel Pintu Panel Kuning dimensi 3" Tebal bh 27,500.00 Ex. Axell
Kuning dimensi 4" Tebal bh 44,000.00 Ex. Axell
Kuning dimensi 5" Tebal bh 55,000.00 Ex. Axell
-
Engsel Ram Jendela Kuningan 2" bh 8,100.00 Ex. Axell
Kuningan 2.5" bh 10,500.00 Ex. Axell
Kuningan 3" bh 11,000.00 Ex. Axell
-
Nylon kupu-kupu 3" bh 6,900.00 Ex. RCH
4" bh 10,500.00 Ex. RCH
-
Espagnoled - dalam negeri bh 13,400.00
Grendel Tanam luar negeri bh -
Grendel biasa bh 10,800.00
Hak Angin Kuningan bh 44,000.00
Door Stop bh 23,300.00 Ex. Dekson karet
-
Handle Pintu Baja Set 110,000.00
Barrel Hinges / Engsel Bubut Set 26,400.00
Engsel Kupu-kupu Baja set 22,000.00
Kunci Gembok Besar Ex. Gradino Bh 88,000.00
-
-
-
38 Petanahan/arde BCC 50 mm2 m 67,400.00
39 BCC 16 mm2 m 20,700.00
40 BCC 10 mm2 m 11,700.00
41 Penangkal Petir electro static non radioaktif unit 7,199,900.00
XIII BAHAN SANITAIR -
1 KLOSET DUDUK bh 1,935,000.00 ex ina
Seri CW863NPJ unit 4,589,900.00 Ex. Toto
Seri CW702J/SW784JP unit 2,812,500.00 Ex. Toto
Amstad Winplus White Unit 1,501,100.00 Ex. Amstad

2 KLOSET JONGKOK Toto Seri CE-7 PIV bh 374,000.00

5 WASTAFEL GANTUNG BULAT bh 223,100.00 ex ina


8 WASTAFEL BAK CUCI bh -
Seri CE7-white bh 257,400.00 Ex. Toto
9 TEMPAT SABUN GANTUNG bh -
10 TEMPAT SABUN TANAM bh 66,000.00
3 ZINC WASHBAK Besar bh 222,300.00

- Harsat Bahan - -61


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Kecil bh 134,900.00 Ex. OKI

4 WATER DRAIN set 44,900.00


Shop Holder Toto S 156 N bh 129,600.00
Motif Biasa bh 37,700.00
Paper Holder Biasa bh 70,200.00
Shower Mandi SAN-EI Seri SK30P bh 1,283,000.00
Jet Washer SAN-EI Seri PSN 75 C bh 193,100.00
Onda bh 107,900.00
Tandon Air TB110 Kapasitas 1050 liter Unit 1,815,000.00 Ex. Penguin
TB32 Kapasitas 300 liter Unit 726,000.00 Ex. Penguin
TB300 Kapasitas 3000 liter Unit 5,258,000.00 Ex. Penguin
Tangki Pendam Penguin TP 200 Unit 7,559,900.00 Ex. Penguin
-
11 SEPTIC TANK (ETERNIT GRESIK) -
5 Pemakai 500 liter unit -
10 Pemakai 1.000 liter unit -
-
12 LAIN - LAIN -
Kran Air Biasa bh 26,900.00 1/2"
Onda CLS 01 bh 53,700.00 3/4"
Kran Air Leher Angsa Flexible Vicenzo bh 98,300.00
Seal tape bh 3,100.00
Floor drain SAN-EI Seri HN508P bh 269,900.00
Onda bh 71,900.00
Pompa Air Shimizu PS 130 BIT Unit 660,000.00
-
XIV LAIN-LAIN -
Minyak Beton & bekisting ltr 5,700.00
Allumunium Foil m2 7,700.00
Soda api kg 9,400.00
Air Liter 85.00
Spacer/Penjaga Jarak bh 5,900.00
Ijuk Kg 5,100.00
WATER PROOFING -
LEMKRA DS 105 5 kg 70,600.00 Putih
5 kg 63,900.00 Abu-abu
LEMKRA TG 301 20 Ltr 472,400.00
Primer Waterproofing Membrane Bitumen ltr 58,400.00
Membrane Bitumen Lembar 533,200.00
Membran Bitumen Selulosa ( 1 x 10 m ) Lbr / Roll 1,080,000.00 Bituline
Kristalisasi Penetron kg 1,815,000.00
Printing MMT m2 17,600.00
Seng Galvalume 0,25 m2 34,700.00
Logo Tulisan Untuk Papan Nama Unit 11,000.00
-
XVIII BAHAN ALUMUNIUM -
1 Alumunium Profil Warna Silver 4" tebal 1.2 mm m' 113,900.00 Ex. Alexindo
Warna Coklat 4" tebal 1.2 mm m' 126,500.00 Ex. Alexindo
Alumunium Coating White 4" tbl 1 mm m' 139,200.00 Ex. Alexindo
2 Aksesoris Engsel 4" bh 25,100.00 Ex. Dekson
Engsel 10" bh 64,700.00 Ex. Dekson
Engsel 3" bh 22,900.00 Ex. Dekson
Engsel Sliding / Rel Geser S6 Panjang 244 Set 648,000.00 Ex. Henderson J3
Cesement 12" set 67,400.00 Ex. Dekson
Kait Angin bh 26,900.00 Ex. Dekson

- Harsat Bahan - -62


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Rambuncis bh 31,500.00 Ex. Dekson


Sealant tube 31,500.00
Skrup Fixer bh 500.00
Profil Kaca m' 5,300.00
Handle Pintu + Kunci set 224,900.00 Ex. Dekson
Spagnolet Tanam bh 22,400.00
Door Closer set 409,400.00 Ex. Dekson DCL 300 Serie NHO
Spandek PVC m2 49,500.00
Sindik Pintu bh 13,400.00
Floor Hinge set 1,341,000.00 Ex. Dekson FH 84 SSS
Patch Fitting bh 573,200.00 Ex. Dekson PT 20 PSS
Pull Handle set 233,900.00
Rel Pintu Sliding Unit 302,300.00 Ex. Henderson J3
Sticker Sandblast m2 134,900.00
Glass Curtain Wall m' 116,900.00
kunci silinder bh 64,700.00
-
3 Panel Pintu Angzdoor -
economy -
36 x 720 x 2000 Unit -
36 x 820 x 2100 Unit -
36 x 920 x 2100 Unit -
Trimable panel -
36 x 720 x 2100 Unit -
36 x 820 x 2100 Unit -
36 x 920 x 2100 Unit -
Solid block groove with standard router -
36 x 720 x 2100 Unit -
36 x 820 x 2100 Unit -
36 x 920 x 2100 Unit -
-
3 Panel Pintu Teakwood Tebal 9 mm m2 585,000.00

4 Alumunium Composit Panel 324,000.00 Merk Seven


-
XX TAMAN -
1 Tanah Subur m3 99,000.00
2 Pupuk Kandang kg 22,400.00
3 Tanaman Kacang Hias / polybag 2,500.00
4 Tanaman Lantana / polybag 2,600.00
4 Tanaman Pangkas Hijau / polybag 5,000.00
5 Tanaman Pangkas Kuning / polybag 2,500.00
6 Tanaman Pangkas Merah / polybag 5,000.00
7 Pohon Ketapang Kencana 1 m bh 112,500.00
8 Pucuk Merah t. Min 60cm bh 81,700.00

XIX BAHAN ASPAL -


1 Aspal Drum Kg 1,815,000.00
Drum Kg 11,700.00
Curah Kg 10,500.00
Aspal Emulsi CSS-1 atau SS1 Ltr 11,000.00
2 Agregat Kelas B m3 220,300.00
Kelas A m3 234,400.00
Pasir Kasar m3 253,000.00
Pasir Halus m3 253,000.00
Lolos screen2 ukuran ( 9.5 - 19,0) m3 176,400.00

- Harsat Bahan - -63


HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Lolos screen2 ukuran ( 0 - 5) m3 213,400.00


Agregat 5-10 & 10-20 m3 192,900.00
-
Kerosene Liter 10,900.00
3 Kayu Bakar m3 811,800.00
-
XX ALAT PELINDUNG DIRI Helm Savety ASA Unit 97,500.00
Pelindung mata Unit 32,500.00
Tameng muka Unit 97,500.00
Pelindung telinga Unit 60,000.00
Masker pelindung pernafasan dan mulut Box 58,500.00
Sarung tangan Psg 6,500.00
Sepatu keselamatan Psg 351,000.00
Sepatu keselamatan ( rubber safety ) Psg 188,500.00
Penunjang seluruh tubuh Unit 975,000.00
Rompi keselamatan Unit 32,500.00
Pelindung jatuh Unit 130,000.00

- Harsat Bahan - -64


HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp

1 HITUNG K3 1.000 Unit Biaya K3 1,184,040.00


A Tenaga -
B Bahan 1,029,600.00
2.000 Unit Helm Safety ASA 93,000.00 186,000.00
2.000 Box Masker Pelindung Pernafasan dan mulut 55,800.00 111,600.00
2.000 Psg Sepatu Keselamatan (rubber safety) 335,000.00 670,000.00
2.000 Unit Rompi keselamatan 31,000.00 62,000.00
C PERALATAN -
D Jumlah A + B + C 1,029,600.00
E Overhead & Profit 15% 154,440.00
F Harga Satuan Pekerjaan (D+E) 1,184,040.00

2 HITUNG AKL 1.000 Unit Air kerja dan Listrik 1,098,721.50


A Tenaga 24,000.00
L.01 0.300 OH Pekerja 80,000.00 24,000.00
B Bahan 931,410.00
8,199.00 ltr Air 90.00 737,910.00
129.00 kwh Listrik 1,500.00 193,500.00
C PERALATAN
D Jumlah A + B + C 955,410.00
E Overhead & Profit 15% 143,311.50
F Harga Satuan Pekerjaan (D+E) 1,098,721.50
RENCANA ANGGARAN BIAYA (OE)
KEGIATAN : REHABILITASI SMP N 1 TERAS
LOKASI : SMP N 1 TERAS, BOYOLALI
ANGGARAN : 2022

* LOKASI 1
A PEKERJAAN PERSIAPAN
1 Pembuatan 1 unit Direksi Keet dan Gudang 1.00 Unit 1.1.3.(a)
2 Pembuatan 1 buah Papan Nama pekerjaan dengan multiflex 10mm, frame Aluminium siku dan tiang kayu 5 1.00 bh 1.1.4.b.(a)
3 Biaya K3 1.00 Unit HITUNG K3
4 Air kerja dan Listrik 1.00 Unit HITUNG AKL
5 Pasang 1m' Bouwplank sebagai acuan dalam pembuatan infrastruktur 16.00 m' 1.7.4.d.(a)
6 Pembuatan steger / perancah bambu 1.00 Unit A.1.1.1.11
Jumlah A

B PEKERJAAN FISIK
B.1 (RUANG GURU)
I PEKERJAAN BONGKARAN
1 Pembongkaran 1m3 Pasangan batu dengan alat 3.00 m3 2.1.2.a.5.c
2 Pembongkaran genteng 227.21 m2 HITUNG PS.4
3 Pembongkaran rangka atap/kaso/reng 227.21 m2 HITUNG PS.5
4 Pembongkaran plafond 146.68 m2 HITUNG PS.6
5 Pembongkaran dinding bata merah tebal 30cm 66.38 m2 HITUNG PS.1
6 Pembongkaran keramik & rabat 16.64 m3 HITUNG PS.3
Jumlah I
II PEKERJAAN PONDASI
1 Pemasangan 1 m3 Pondasi Batu Belah Campuran 1SP : 6PP 0.12 m3 2.1.1.d.(a)
Jumlah II
III PEKERJAAN PASANGAN
1 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu Campuran 1SP: 6PP) 57.07 m2 A.4.4.1.11
2 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 batu Campuran 1SP: 6PP) 10.25 m2 A.4.4.1.5.
3 Plesteran Tebal 1,5 cm, dengan Mortar Campuran (setara 1 PC : 6 PP) 133.67 m2 3.2.2.2.17.(a)
4 Pemasangan 1 m2 Acian 183.10 m2 3.2.2.2.35.(a)
Jumlah III
IV PEKERJAAN BETON
1 Pekerjaan Sloof 20/25
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 1.21 m3 2.2.1.2.f
b. Pembesian Ø12 150.60 kg HITUNG PB 1
Pembesian Ø8 49.89 kg HITUNG PB 1
c. Begesting 12.10 m2 A.4.1.1.19
2 Pekerjaan Kolom 15/15 R.Guru
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 0.90 m3 2.2.1.2.f
b. Pembesian Ø12 146.42 kg HITUNG PB 1
Pembesian Ø8 50.83 kg HITUNG PB 1
c. Begesting 14.40 m2 A.4.1.1.19
3 Pekerjaan Kolom 15/15 Teras
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 0.39 m3 2.2.1.2.f
b. Pembesian Ø12 64.28 kg HITUNG PB 1
Pembesian Ø8 22.43 kg HITUNG PB 1
c. Begesting 10.50 m2 A.4.1.1.19
4 Pekerjaan Balok Latei 15/20
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 0.50 m3 2.2.1.2.f
b. Pembesian Ø10 42.90 kg HITUNG PB 1
Pembesian Ø8 25.41 kg HITUNG PB 1
c. Begesting 6.72 m2 A.4.1.1.19
5 Pekerjaan Ring Balk 15/20
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 2.32 m3 2.2.1.2.f
b. Pembesian Ø12 282.84 kg HITUNG PB 1
Pembesian Ø8 115.53 kg HITUNG PB 1
c. Begesting 50.18 m2 A.4.1.1.19
6 Pekerjaan Rabat Beton Bawah Lantai Tebal 5 cm
a. Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 0.67 m3 2.2.1.2.b
Jumlah IV
V PEKERJAAN ATAP
1 Pekerjaan Pemasangan Listplang GRC 9/200 49.60 m' HITUNG K.6
Jumlah V
VI PEKERJAAN LANGIT-LANGIT
1 Pekerjaan Langit-langit GRC + Rangka Hollow 181.00 m2 HITUNG PF.1
2 Pekerjaan List Plafond kayu profil 40.30 m' A.4.5.1.10
Jumlah VI
VII PEKERJAAN PENUTUP LANTAI
1 Pemasangan keramik motif 40x40 15.92 m2 A.4.4.3.36
Jumlah VII
VIII PEKERJAAN PENGECATAN
1 Pengecatan Tembok Lama Interior ( 1 Lap Cat Dasar 2 lap. Cat penutup ), Ex. Envi 128.62 m2 HITUNG PC.4
2 Pengecatan Tembok Lama Eksterior ( 1 Lap Cat Dasar 2 lap. Cat penutup ), Ex. Envi 132.03 m2 HITUNG PC.5
3 Pengecatan Tembok Baru Interior ( 1 Lap Plamur, 1 Cat Dasar 2 lap. Cat penutup ), Ex. Envi 173.25 m2 HITUNG PC.2
4 Pengecatan Tembok Baru Eksterior ( 1 Lap Plamur, 1 Cat Dasar 2 lap. Cat penutup ), Ex. Envi 146.87 m2 HITUNG PC.3
5 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup) 57.96 m2 HITUNG PC.1
6 Pengecatan Plafond Baru (2 lapisan cat penutup), Ex. Envi 156.29 m2 HITUNG PC.6
7 Pengecatan List plafond 4.03 m2 HITUNG PC.1
8 Pengecatan Listplank 9.92 m2 HITUNG PC.1
Jumlah VIII
IX PEKERJAAN MEKANIKAL ELEKTRIKAL
1 Pemasangan MCB 1 phase 10A ex schneider + box ex presto 1.00 bh HITUNG DL.1
2 Pemasangan TL 2x20 RM Armateur In Bow 15.00 bh HITUNG PC.1
3 Pemasangan LED 12 watt, Ex. Osram 5.00 bh HITUNG PC.2
4 Pemasangan Instalasi titik kabel dalam NYM 3x2.5 ex eterna 8.00 titik HITUNG DL.5
5 Pemasangan Stop kontak ex broco 8.00 bh HITUNG DL.4
6 Pemasangan Saklar tunggal ex broco 5.00 bh HITUNG DL.2
7 Pemasangan Saklar ganda ex broco 2.00 bh HITUNG DL.3
Jumlah IX
JUMLAH A+B

* LOKASI 2
A RUANG KELAS
I PEKERJAAN BONGKARAN
1 Pembongkaran genteng 194.74 m2 HITUNG PS.4
2 Pembongkaran rangka atap/kaso/reng 194.74 m2 HITUNG PS.5
3 Pembongkaran plafond 142.69 m2 HITUNG PS.6
4 Pembongkaran dinding bata merah tebal 15 cm 22.91 m2 HITUNG PS.2
5 Pembongkaran keramik & rabat 101.80 m2 HITUNG PS.5
Jumlah I
II PEKERJAAN TANAH
1 Penggalian tanah biasa untuk pondasi 7.76 m3 1.7.1.a.(c)
2 Pengurugan tanah kembali 2.59 m3 1.7.2.a.(c)
3 Mengangkut 1 m3 tanah lepas, jarak angkut > 200 s.d. 300 m 5.17 m3 1.7.15.1.h.(a)
4 Pengurugan 1 m3 dengan Pasir Urug untuk Striping Tanaman Ø 2 cm 5.73 m3 1.7.2.d.(c)
Jumlah II
III PEKERJAAN PONDASI
1 Pemasangan 1 m3 Pondasi Batu Belah Campuran 1SP : 6PP 3.10 m3 2.1.1.d.(a)
Jumlah III
IV PEKERJAAN PASANGAN
1 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu Campuran 1SP: 6PP) 49.20 m2 A.4.4.1.11
2 Pemasangan 1 m2 Plesteran 1 Pc : 6 Pp Tebal 15 mm 97.75 m2 3.2.2.(c)
3 Pemasangan 1 m2 Acian 99.91 m2 3.2.2.2.35.(a)
Jumlah IV
V PEKERJAAN BETON
1 Pekerjaan Sloof 20/25
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 0.35 m3 2.2.1.2.f
b. Pembesian Ø12 42.90 kg HITUNG PB 1
Pembesian Ø8 14.42 kg HITUNG PB 1
c. Begesting 3.53 m2 A.4.1.1.19
2 Pekerjaan Kolom 15/15
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 0.08 m3 2.2.1.2.f
b. Pembesian Ø12 13.21 kg HITUNG PB 1
Pembesian Ø8 4.60 kg HITUNG PB 1
c. Begesting 1.08 m2 A.4.1.1.19
3 Pekerjaan Balok Latei 15/20
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 1.32 m3 2.2.1.2.f
b. Pembesian Ø10 113.09 kg HITUNG PB 1
Pembesian Ø8 66.83 kg HITUNG PB 1
c. Begesting 17.60 m2 A.4.1.1.19
4 Pekerjaan Ring Balk 15/20
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 0.76 m3 2.2.1.2.f
b. Pembesian Ø12 91.57 kg HITUNG PB 1
Pembesian Ø8 37.55 kg HITUNG PB 1
c. Begesting 12.62 m2 A.4.1.1.19
5 Pekerjaan Lantai Kerja Pondasi Tebal 5 cm
a. Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 0.28 m3 2.2.1.2.b
6 Pekerjaan Rabat Beton Bawah Lantai Tebal 5 cm
a. Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 5.38 m3 2.2.1.2.b
Jumlah V
VI PEKERJAAN ATAP
1 Pekerjaan Kuda-Kuda Kayu Kruing 8/12 Bentang 7.35 meter (2 Buah) 0.61 m3 HITUNG K.2
2 Pekerjaan Rangka Atap Kayu kruing 8/12 (Nok, Gording, Murplat, Skoor Angin) 0.74 m3 HITUNG K.3
3 Pekerjaan Usuk 5/7, Reng 2/3 Kayu Kruing 194.74 m2 HITUNG K.5
4 Pekerjaan Pemasangan Atap Genteng Plentong kecil Tanah Liat 194.74 m2 A.4.5.2.1
5 Pekerjaan Pemasangan Bubungan Atap Genteng Tanah Liat 15.25 m' HITUNG AT.1
6 Pekerjaan Pemasangan Listplang GRC 9/200 56.04 m' HITUNG K.6
Jumlah VI
VII PEKERJAAN LANGIT-LANGIT
1 Pekerjaan Plafond GRC + Rangka hollow 142.69 m2 HITUNG PF.1
2 Pekerjaan List Plafond kayu profil 35.90 m' A.4.5.1.10
Jumlah VII
VIII PEKERJAAN PENUTUP LANTAI
1 Pemasangan keramik putih polos, Uk. 40x40 96.97 m2 A.4.4.3.36
2 Pemasangan Paving difable (Guilding block) 4.83 m2 HITUNG LD.1
Jumlah VIII
IX PEKERJAAN PENGECATAN
1 Pengecatan Tembok Lama Interior ( 1 Lap Cat Dasar 2 lap. Cat penutup ), Ex. Catylac 92.64 m2 HITUNG PC.4
2 Pengecatan Tembok Lama Eksterior ( 1 Lap Cat Dasar 2 lap. Cat penutup ), Ex. Catylac 99.19 m2 HITUNG PC.5
3 Pengecatan Tembok Baru Interior ( 1 Lap Plamur, 1 Cat Dasar 2 lap. Cat penutup ), Ex. Catylac 71.24 m2 HITUNG PC.2
4 Pengecatan Tembok Baru Eksterior ( 1 Lap Plamur, 1 Cat Dasar 2 lap. Cat penutup ), Ex. Catylac 74.48 m2 HITUNG PC.3
5 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup) 57.96 m2 HITUNG PC.1
6 Pengecatan Plafond Baru (2 lapisan cat penutup), Ex. Catylac 142.69 m2 HITUNG PC.6
7 Pengecatan List plafond 3.59 m2 HITUNG PC.1
8 Pengecatan Listplank 11.21 m2 HITUNG PC.1
Jumlah IX
X PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu & Jendela, Kayu kruing 6/12 0.65 m3 HITUNG K.1
2 Pek. Daun Pintu & Jendela, Kayu kruing 4.75 m2 A.4.6.1.5
3 Pek. Jalusi 3/5 0.10 m3 A.4.6.1.7
4 Pek. Kaca Pintu & Jendela, tebal 5mm 12.06 m2 A.4.6.2.17
5 Pemasangan Kunci Tanam Biasa 1.00 Bh A.4.6.2.2
6 Pemasangan Engsel Pintu 3.00 Bh A.4.6.2.5
7 Pemasangan Engsel Jendela Kupu-kupu 28.00 Bh A.4.6.2.6
8 Pemasangan Kait Angin 28.00 Bh A.4.6.2.7
9 Pemasangan Kunci Selot 28.00 Bh A.4.6.2.11
Jumlah X
XI PEKERJAAN MEKANIKAL ELEKTRIKAL
1 Pemasangan MCB 1 phase 10A ex schneider + box ex presto 1.00 bh HITUNG DL.1
1 Pemasangan TL 2x20 RM Armateur In Bow 9.00 bh HITUNG PC.1
3 Pemasangan Instalasi titik kabel dalam NYM 3x2.5 ex eterna 9.00 titik HITUNG DL.5
4 Pemasangan Stop kontak ex broco 1.00 bh HITUNG DL.4
5 Pemasangan Saklar tunggal ex broco 1.00 bh HITUNG DL.2
6 Pemasangan Saklar ganda ex broco 1.00 bh HITUNG DL.3
Jumlah XI
XII PEKERJAAN RAMP & AKSES DIFABLE
1 Pengurugan tanah kembali 1.50 m3 1.7.2.a.(c)
2 Pengurugan pasir 0.30 m3 1.7.2.d.(c)
3 Beton K-175 0.66 m3 2.2.2.1.f
4 Rollag 4.20 m2 HITUNG D.1
5 Railling alumunium 27.20 m' HITUNG BA.1
Jumlah XII
XIII PEKERJAAN LOKASI 3
XII PEKERJAAN RAMP & AKSES DIFABLE
1 Pengurugan tanah kembali 1.13 m3 1.7.2.a.(c)
2 Pengurugan pasir 0.74 m3 1.7.2.d.(c)
3 Railling alumunium 17.26 m' HITUNG BA.1
Jumlah XIII
JUMLAH A

* LOKASI 3
A TOILET
I PEKERJAAN BONGKARAN
1 Pembongkaran genteng 26.00 m2 HITUNG PS.4
2 Pembongkaran rangka atap/kaso/reng 26.00 m2 HITUNG PS.5
3 Pembongkaran dinding bata merah tebal 15cm 22.80 m2 HITUNG PS.2
4 Pembongkaran keramik & rabat 10.56 m2 HITUNG PS.6
Jumlah I
II PEKERJAAN TANAH
1 Penggalian tanah biasa untuk pondasi 3.65 m3 1.7.1.a.(c)
2 Pengurugan tanah kembali 0.84 m3 1.7.2.a.(c)
3 Mengangkut 1 m3 tanah lepas, jarak angkut > 200 s.d. 300 m 2.81 m3 1.7.15.1.h.(a)
4 Pengurugan 1 m3 dengan Pasir Urug untuk Striping Tanaman Ø 2 cm 0.26 m3 1.7.2.d.(c)
Jumlah II
III PEKERJAAN PONDASI
1 Pemasangan 1 m3 Pondasi Batu Belah Campuran 1SP : 6PP 2.05 m3 2.1.1.d.(a)
Jumlah III
IV PEKERJAAN PASANGAN
1 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu Campuran 1SP: 6PP) 15.11 m2 A.4.4.1.11
2 Pemasangan 1 m2 Plesteran 1 Pc : 6 Pp Tebal 15 mm 30.22 m2 3.2.2.(c)
3 Pemasangan 1 m2 Acian 33.22 m2 3.2.2.2.35.(a)
Jumlah IV
V PEKERJAAN BETON
1 Pekerjaan Sloof 15/20
a. Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 0.18 m3 A.4.1.1.5
b. Pembesian Ø12 26.28 kg HITUNG PB 1
Pembesian Ø8 9.78 kg HITUNG PB 1
c. Begesting 3.04 m2 A.4.1.1.19
2 Pekerjaan Kolom 15/15
a. Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 0.11 m3 A.4.1.1.5
b. Pembesian Ø12 19.28 kg HITUNG PB 1
Pembesian Ø8 6.82 kg HITUNG PB 1
c. Begesting 1.50 m2 A.4.1.1.19
3 Pekerjaan Balok Latei 15/15
a. Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 0.14 m3 A.4.1.1.5
b. Pembesian Ø10 15.62 kg HITUNG PB 1
Pembesian Ø8 7.71 kg HITUNG PB 1
c. Begesting 1.83 m2 A.4.1.1.19
4 Pekerjaan Ring Balk 15/20
a. Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 0.95 m3 A.4.1.1.5
b. Pembesian Ø12 116.14 kg HITUNG PB 1
Pembesian Ø8 47.57 kg HITUNG PB 1
c. Begesting 12.61 m2 A.4.1.1.19
5 Pekerjaan Lantai Kerja Pondasi Tebal 5 cm
a. Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 0.26 m3 2.2.1.2.b
6 Pekerjaan Rabat Beton Bawah Lantai Tebal 5 cm
a. Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 0.94 m3 2.2.1.2.b
Jumlah V
VI PEKERJAAN ATAP
1 Pekerjaan atap baja ringan C.75.75, reng 30.45 26.00 m2 HITUNG AT.4
2 Pekerjaan atap galvalume 26.00 m2 HITUNG AT.5
3 Pekerjaan talang seng 3.25 m2 A.4.5.2.41
4 Pekerjaan Pemasangan Listplang GRC 9/200 6.50 m' HITUNG K.6
Jumlah VI
VII PEKERJAAN LANGIT-LANGIT
1 Pekerjaan Plafond GRC + Rangka hollow 14.56 m2 HITUNG PF.1
Jumlah VII
VIII PEKERJAAN PENUTUP LANTAI
1 Pemasangan keramik unpolish, Uk. 30x30 22.50 m2 A.4.4.3.35
2 Pemasangan keramik motif unpolish, Uk. 40x40 12.29 m2 A.4.4.3.36
Jumlah VIII

IX PEKERJAAN PENGECATAN
1 Pengecatan Tembok Interior ( 1 Lap Plamur, 1 Cat Dasar 2 lap. Cat penutup ), Ex. Envi 111.94 m2 HITUNG PC.2
2 Pengecatan Tembok Eksterior ( 1 Lap Plamur, 1 Cat Dasar 2 lap. Cat penutup ), Ex. Envi 10.14 m2 HITUNG PC.3
3 Pengecatan Plafond Baru (2 lapisan cat penutup), Ex.Envi 14.56 m2 HITUNG PC.6
4 Pengecatan Listplank 1.30 m2 HITUNG PC.1
Jumlah IX
X PEKERJAAN PINTU DAN JENDELA
1 Pekerjaan pintu kamar mandi (P1) 7.00 m2 A.4.2.1.4
2 Pekerjaan pintu kamar mandi (P2) 1.80 m2 A.4.2.1.4
3 Roaster 0.56 m2 A.4.4.1.23
Jumlah X
XI PEKERJAAN MEKANIKAL ELEKTRIKAL
1 Pemasangan MCB 1 phase 10A ex schneider + box ex presto 1.00 bh HITUNG DL.1
2 Pemasangan LED 12 watt, Ex. Osram 8.00 bh HITUNG PC.2
3 Pemasangan Instalasi titik kabel dalam NYM 3x2.5 ex eterna 6.00 titik HITUNG DL.5
4 Pemasangan Saklar tunggal ex broco 2.00 bh HITUNG DL.2
5 Pemasangan Saklar ganda ex broco 3.00 bh HITUNG DL.3
Jumlah XI
XII PEKERJAAN SANITASI DAN PLUMBING
1 Pek Pasangan Closet Jongkok Porselen 1.00 Bh A.5.1.1.2
2 Pek. Pasangan Closet Duduk Mono Blok Ex. Toto Seri CW702J/SW784JP 1.00 Bh A.5.1.1.1
3 Pek. Pasang Floordrain 6.00 Bh A.5.1.1.36
4 Pemasangan Kran Ø ½" atau Ø ¾" 6.00 Bh A.5.1.1.35
5 Pipa PVC AW 3" (Pipa Air Hujan) 15.00 m' HITUNG PG13
6 Pipa PVC AW 3" (Pipa Air Kotor Padat) 10.00 m' HITUNG PG13
7 Pipa PVC AW 3" (Pipa Air Kotor Cair) 10.00 m' HITUNG PG13
8 Pipa PVC AW 1" (Pipa Air Bersih) 16.50 m' HITUNG PG9
9 Ember Plastik 80 liter + tutup, Ex. Lion star 5.00 Bh Survei
10 Gayung 1,5 Liter, Ex. Lion star 6.00 Bh Survei
Jumlah XII
XIII PEKERJAAN LOKASI 1
XIII.1 PEKERJAAN ATAP
1 Pekerjaan Kuda - Kuda Kayu Kruing 8/12 Bentang 7.47 meter (4 Buah) 1.81 m3 HITUNG K.2
2 Pekerjaan Rangka Atap Kayu Kruing 8/12 (Nok, Gording, Murplat, Skoor Angin) 1.21 m3 HITUNG K.3
3 Pekerjaan Rangka Atap Kayu Kruing 8/12 untuk teras 0.38 m3 HITUNG K.3
4 Pekerjaan Usuk Kayu Kruing 5/7 Dan Reng Kayu Kruing 2/3 50% baru 227.21 m2 HITUNG K.4
5 Pekerjaan Pemasangan Atap Genteng Plentong kecil Tanah Liat 35% 79.52 m2 HITUNG AT.2
6 Pekerjaan Pemasangan Kembali Atap Genteng Plentong kecil Tanah Liat 65% 147.69 m2 HITUNG AT.3
7 Pekerjaan Pemasangan Talang 17.00 m' A.4.2.1.18
8 Pekerjaan Pemasangan Bubungan Atap Genteng Tanah Liat 19.15 m' HITUNG AT.1
9 Pemasangan Kunci Selot 16.00 bh A.4.6.2.11
Jumlah XIII
XIII.2 PEKERJAAN PINTU DAN JENDELA
1 Pemasangan Kunci Tanam Biasa untuk Pintu 2.00 bh A.4.6.2.2
2 Pemasangan kembali J1 4.00 bh HITUNG PKJ.1
3 Pemasangan Engsel Jendela Kupu-kupu 16.00 bh A.4.6.2.6
4 Pemasangan Kait Angin 16.00 bh A.4.6.2.7
Jumlah XIII.2
Jumlah XIII
XIV PEKERJAAN LOKASI 2
PEKERJAAN RAMP & AKSES DIFABLE
1 Beton K-175 0.48 m3 2.2.2.1.f
2 Rollag 2.56 m2 HITUNG D.1
Jumlah XIV
JUMLAH A
1,627,904.78 1,627,904.78
416,320.13 416,320.13
1,184,040.00 1,184,040.00
1,098,721.50 1,098,721.50
69,416.76 1,110,668.16
353,516.90 353,516.90
5,791,171.46

38,120.83 114,362.50
7,383.00 1,677,491.43
25,355.78 5,761,085.64
7,647.50 1,121,716.95
29,411.25 1,952,171.72
14,128.17 235,092.67
10,861,920.90

890,051.01 106,806.12
106,806.12

128,326.89 7,323,936.43
266,112.65 2,727,654.61
43,136.96 5,766,117.44
27,477.81 5,031,050.08
20,848,758.56

1,133,070.47 1,371,015.26
18,510.68 2,787,708.42
18,510.68 923,571.87
147,947.50 1,790,164.75

1,133,070.47 1,019,763.42
18,510.68 2,710,318.97
18,510.68 940,897.87
147,947.50 2,130,444.00

1,133,070.47 446,146.50
18,510.68 1,189,896.13
18,510.68 415,102.00
147,947.50 1,553,448.75

1,133,070.47 571,067.52
18,510.68 794,182.22
18,510.68 470,304.55
147,947.50 994,207.20

1,133,070.47 2,624,191.20
18,510.68 5,235,542.99
18,510.68 2,138,605.51
147,947.50 7,424,005.55

995,639.72 669,069.89
38,199,654.57

54,593.38 2,707,831.40
2,707,831.40

132,587.81 23,997,863.71
23,395.60 942,842.68
24,940,706.39

221,591.20 3,527,731.90
3,527,731.90
21,081.80 2,711,435.71
23,276.00 3,073,072.09
24,985.48 3,669,616.71
28,154.88 4,135,106.49
50,397.60 2,921,044.90
26,142.95 4,085,907.80
50,397.60 203,102.33
50,397.60 499,944.19
21,299,230.22

1,307,607.50 1,307,607.50
223,330.00 3,349,950.00
60,950.00 304,750.00
111,607.50 892,860.00
37,173.75 297,390.00
29,238.75 146,193.75
40,623.75 81,247.50
6,379,998.75
134,663,810.27

7,383.00 1,437,783.88
25,355.78 4,937,847.01
7,647.50 1,091,229.42
14,705.63 336,942.63
14,128.17 1,438,176.58
9,241,979.53

72,018.75 558,505.41
52,037.50 134,516.94
63,843.98 330,073.35
270,307.50 1,548,760.61
2,571,856.30

890,051.01 2,760,938.23
2,760,938.23

128,326.89 6,313,041.35
61,329.96 5,995,003.59
27,477.81 2,745,308.25
15,053,353.19

1,133,070.47 399,407.34
18,752.18 804,468.53
18,510.68 267,012.86
147,947.50 521,514.94

1,133,070.47 91,778.71
18,752.18 247,780.81
18,510.68 85,234.28
147,947.50 159,783.30

1,133,070.47 1,495,653.02
18,752.18 2,120,646.54
18,510.68 1,237,076.15
147,947.50 2,603,876.00

1,133,070.47 857,960.96
18,752.18 1,717,054.02
18,510.68 695,080.48
147,947.50 1,867,097.45

995,639.72 280,770.40

995,639.72 5,353,679.21
20,805,874.98
12,860,450.00 7,829,853.49
11,845,931.50 8,747,888.73
105,621.97 20,569,086.20
70,871.63 13,801,717.43
49,634.00 756,918.50
54,593.38 3,059,412.74
54,764,877.09

132,587.81 18,919,087.55
23,395.60 839,902.04
19,758,989.59

221,591.20 21,486,590.71
156,327.39 755,061.29
22,241,652.00

21,081.80 1,952,912.54
23,276.00 2,308,676.61
24,985.48 1,779,875.29
28,154.88 2,096,873.73
50,397.60 2,921,044.90
26,142.95 3,730,363.68
50,397.60 180,927.38
50,397.60 564,856.30
15,535,530.44

13,599,537.75 8,900,625.47
835,744.10 3,971,455.96
1,104,057.50 113,375.66
219,982.35 2,652,899.15
143,836.25 143,836.25
156,011.88 468,035.63
56,007.88 1,568,220.50
121,730.38 3,408,450.50
109,600.75 3,068,821.00
24,295,720.12

1,307,607.50 1,307,607.50
223,330.00 2,009,970.00
111,607.50 1,004,467.50
37,173.75 37,173.75
29,238.75 29,238.75
40,623.75 40,623.75
4,429,081.25

52,037.50 77,796.06
270,307.50 80,821.94
1,113,340.88 738,145.00
235,555.94 989,334.94
177,510.55 4,828,286.96
6,714,384.90

52,037.50 58,607.23
270,307.50 198,946.32
177,510.55 3,063,832.09
3,321,385.65
201,495,623.27

7,383.00 191,958.00
25,355.78 659,250.15
14,705.63 335,288.25
14,128.17 149,193.42
1,335,689.82

72,018.75 262,954.86
52,037.50 43,541.51
63,843.98 179,686.74
270,307.50 70,496.20
556,679.31
890,051.01 1,827,986.76
1,827,986.76

128,326.89 1,939,019.31
61,329.96 1,853,391.39
27,477.81 912,812.93
4,705,223.63

1,070,950.92 195,020.16
18,752.18 492,807.29
18,510.68 181,114.42
147,947.50 449,020.66

1,070,950.92 120,481.98
18,752.18 361,626.04
18,510.68 126,191.01
147,947.50 221,921.25

1,070,950.92 146,988.01
18,752.18 292,984.06
18,510.68 142,795.09
147,947.50 270,743.93

1,070,950.92 1,012,691.19
18,752.18 2,177,792.39
18,510.68 880,507.15
147,947.50 1,865,322.08

995,639.72 259,662.84

995,639.72 935,652.42
10,133,321.96

66,389.50 1,726,127.00
71,835.04 1,867,710.98
66,954.15 217,600.99
54,593.38 354,856.94
4,166,295.90

132,587.81 1,930,478.55
1,930,478.55

209,832.45 4,721,859.62
221,591.20 2,722,247.89
7,444,107.51

24,985.48 2,796,811.61
28,154.88 285,490.43
26,142.95 380,641.35
50,397.60 65,516.88
3,528,460.27

304,021.13 2,128,147.91
304,021.13 547,238.03
586,320.60 328,339.54
3,003,725.48

1,307,607.50 1,307,607.50
60,950.00 487,600.00
111,607.50 669,645.00
29,238.75 58,477.50
40,623.75 121,871.25
2,645,201.25

743,152.21 743,152.21
4,954,591.00 4,954,591.00
115,661.25 693,967.50
144,437.13 866,622.75
132,379.38 1,985,690.63
132,379.38 1,323,793.75
132,379.38 1,323,793.75
23,084.81 380,899.41
215,000.00 1,075,000.00
11,500.00 69,000.00
13,416,510.99

12,860,450.00 23,217,330.48
11,845,931.50 14,329,881.18
11,845,931.50 4,497,663.27
109,131.21 24,795,701.09
70,871.63 5,635,959.67
23,434.13 3,460,903.90
186,620.28 3,172,544.68
49,634.00 950,491.10
109,600.75 1,753,612.00
81,814,087.37

143,836.25 287,672.50
155,727.25 622,909.00
56,007.88 896,126.00
121,730.38 1,947,686.00
3,754,393.50
85,568,480.87

1,113,340.88 531,341.93
235,555.94 603,023.20
1,134,365.13
141,396,527.45
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
A. 1.1.1 HARGA SATUAN PEKERJAAN PERSIAPAN

A.1.1.1.11 Pembuatan 1m2 Steger/Perancah dari bambu s.d tinggi 6m 353,516.90


A Tenaga 286,250.00
L.01 1.000 OH Pekerja 80,000.00 80,000.00
L.02 2.000 OH Tukang kayu 90,000.00 180,000.00
L.03 0.200 OH Kepala tukang 105,000.00 21,000.00
L.04 0.050 OH Mandor 105,000.00 5,250.00
B Bahan 21,156.00
1.250 m' Bambu diameter 6-8/600cm 13,800.00 17,250.00
0.186 kg Tali ijuk 21,000.00 3,906.00
C PERALATAN
D Jumlah A + B + C 307,406.00
E Overhead & Profit 15% 46,110.90
F Harga Satuan Pekerjaan (D+E) 353,516.90

HITUNG PS.1 1.000 Unit Bongkaran Dinding 30 cm (Pas. Bata, Pintu, Jendela) buangan keluar loka 29,411.25
A Tenaga 25,575.00
L.01 0.300 OH Pekerja 80,000.00 24,000.00
L.04 0.015 OH Mandor 105,000.00 1,575.00
B Bahan
C PERALATAN
D Jumlah A + B + C 25,575.00
E Overhead & Profit 15% 3,836.25
F Harga Satuan Pekerjaan (D+E) 29,411.25

HITUNG PS.2 1.000 Unit Bongkaran Dinding 15 cm (Pas. Bata, Pintu, Jendela) buangan keluar loka 14,705.63
A Tenaga 12,787.50
L.01 0.150 OH Pekerja 80,000.00 12,000.00
L.04 0.008 OH Mandor 105,000.00 787.50
B Bahan
C PERALATAN
D Jumlah A + B + C 12,787.50
E Overhead & Profit 15% 1,918.13
F Harga Satuan Pekerjaan (D+E) 14,705.63

HITUNG PS.3 1.000 Unit Pembongkaran Lantai Keramik + Rabat 14,128.17


A Tenaga 10,870.95
L.01 0.128 OH Pekerja 80,000.00 10,200.00
L.04 0.006 OH Mandor 105,000.00 670.95
B Bahan
C PERALATAN 1,626.57
0.050 jam Jack Hammer 32,531.45 1,626.57
D Jumlah A + B + C 10,870.95
E Overhead & Profit 15% 1,630.64
F Harga Satuan Pekerjaan (D+E) 12,501.59
HITUNG PS.4 1.000 Unit Pembongkaran Genteng 7,383.00
A Tenaga 6,420.00
L.01 0.075 OH Pekerja 80,000.00 6,000.00
L.04 0.004 OH Mandor 105,000.00 420.00
B Bahan
C PERALATAN
D Jumlah A + B + C 6,420.00
E Overhead & Profit 15% 963.00
F Harga Satuan Pekerjaan (D+E) 7,383.00

HITUNG PS.5 1.000 Unit Pembongkaran Rangka Atap ( Kuda-kuda, Usuk dan Reng ) 25,355.78
A Tenaga 22,048.50
L.01 0.255 OH Pekerja 80,000.00 20,400.00
L.04 0.016 OH Mandor 105,000.00 1,648.50
B Bahan
C PERALATAN
D Jumlah A + B + C 22,048.50
E Overhead & Profit 15% 3,307.28
F Harga Satuan Pekerjaan (D+E) 25,355.78

HITUNG PS.6 1.000 m2 Pembongkaran 1 m2 plafond 7,647.50


A Tenaga 6,650.00
L.01 0.070 OH Pekerja 80,000.00 5,600.00
L.04 0.010 OH Mandor 105,000.00 1,050.00
B Bahan
C PERALATAN
D Jumlah A + B + C 6,650.00
E Overhead & Profit 15% 997.50
F Harga Satuan Pekerjaan (D+E) 7,647.50
HARGA JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.7 HARGA SATUAN PEKERJAAN TANAH

1.7.1.a.(c) Penggalian 1 m3 Tanah Biasa Sedalam s.d 1 m untuk volume s.d. 200 m3 Dalam Satu Lokasi 72,018.75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 62,625.00
Pekerja L.01 OH 0.7500 80,000.00 60,000.00
Mandor L.04 OH 0.0250 105,000.00 2,625.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 62,625.00
E Overhead & Profit 15% 9,393.75
F Harga Satuan Pekerjaan (D+E) 72,018.75

1.7.2.a.(c) Pengurugan Kembali 1 m3 Galian Tanah untuk Striping Tanaman Ø 2 cm 52,037.50


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 45,250.00
Pekerja L.01 OH 0.500 80,000.00 40,000.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 45,250.00
E Overhead & Profit 15% 6,787.50
F Harga Satuan Pekerjaan (D+E) 52,037.50

1.7.2.d.(c) Pengurugan 1 m3 dengan Pasir Urug untuk Striping Tanaman Ø 2 cm 270,307.50


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 25,050.00
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Mandor L.04 OH 0.010 105,000.00 1,050.00
B BAHAN 210,000.00
Pasir Urug m3 1.200 175,000.00 210,000.00
C PERALATAN
D Jumlah A + B + C 235,050.00
E Overhead & Profit 15% 35,257.50
F Harga Satuan Pekerjaan (D+E) 270,307.50

1.7.15.1.h.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 200 s.d. 300 m 63,843.98
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 55,516.50
Pekerja OH 0.6513 80,000.00 52,104.00
Mandor OH 0.0325 105,000.00 3,412.50
B BAHAN
C PERALATAN
D Jumlah A + B + C 55,516.50
E Overhead & Profit 15% 8,327.48
F Harga Satuan Pekerjaan (D+E) 63,843.98

78
HARGA
BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
2.1 HARGA SATUAN PEKERJAAN PONDASI
2.1.1.d.(a) Pemasangan 1 m3 Pondasi Batu Belah Campuran 1SP : 6PP 890,051.01
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 203,250.00
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Tukang Batu L.02 OH 0.750 90,000.00 67,500.00
Kepala Tukang L.03 OH 0.075 105,000.00 7,875.00
Mandor L.04 OH 0.075 105,000.00 7,875.00
B Bahan 570,707.40
Batu Belah 15/20 m3 1.200 225,000.00 270,000.00
Portland Semen, Ex. Gresik Kg 117.000 1,475.00 172,575.00
Pasir Pasang m3 0.561 228,400.00 128,132.40
C PERALATAN
D Jumlah A + B + C 773,957.40
E Overhead & Profit 15% 116,093.61
F Harga Satuan Pekerjaan (D+E) 890,051.01

79
HARGA BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.5. Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 batu Campuran 1SP: 6PP) 266,112.65

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 71,250.00
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
B Bahan 160,152.30
Bata Merah Buah 140.000 750.00 105,000.00
Portland Semen, Ex. Gresik Kg 18.500 1,475.00 27,287.50
Pasir Pasang (PP) m3 0.122 228,400.00 27,864.80
C PERALATAN
D Jumlah A + B + C 231,402.30
E Overhead & Profit 15% 34,710.35
F Harga Satuan Pekerjaan (D+E) 266,112.65

A.4.4.1.11 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu Campuran 1SP: 6PP) 128,326.89
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 35,625.00
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang Batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B Bahan 75,963.60
Bata Merah 5 x 11 x 22 Buah 70.000 750.00 52,500.00
Portland Semen, Ex. Gresik Kg 8.320 1,475.00 12,272.00
Pasir Pasang m3 0.049 228,400.00 11,191.60
C PERALATAN
D Jumlah A + B + C 111,588.60
E Overhead & Profit 15% 16,738.29
F Harga Satuan Pekerjaan (D+E) 128,326.89

A.4.4.1.23 Pemasangan 1 m2 Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP 586,320.60
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 35,625.00
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang Batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B Bahan 474,219.00
Terawang / Roster Buah 30.000 15,000.00 450,000.00
Portland Semen, Ex. Gresik kg 11.000 1,475.00 16,225.00
Pasir Pasang m3 0.035 228,400.00 7,994.00
C PERALATAN
D Jumlah A + B + C 509,844.00
E Overhead & Profit 15% 76,476.60
F Harga Satuan Pekerjaan (D+E) 586,320.60

HITUNG D.1 Pemasangan 1 m2 Rollag 235,555.94


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 71,250.00
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
B Bahan 121,437.50
batu bata Buah 118.650 750.00 88,987.50
Portland Semen, Ex. Gresik kg 22.000 1,475.00 32,450.00
C PERALATAN 12,143.75
10% dari harga bahan 0.100 121,437.50 12,143.75
D Jumlah A + B + C 204,831.25
E Overhead & Profit 15% 30,724.69
F Harga Satuan Pekerjaan (D+E) 235,555.94

80
HARGA
BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
3.2 HARGA SATUAN PEKERJAAN PLESTERAN
3.2.2.(c) Pemasangan 1 m2 Plesteran 1 Pc : 6 Pp Tebal 15 mm 61,329.96
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 40,650.00
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B BAHAN 12,680.40
Portland Semen, Ex. Gresik Kg 4.416 1,475.00 6,513.60
Pasir Pasang m3 0.027 228,400.00 6,166.80
C PERALATAN
D Jumlah A + B + C 53,330.40
E Overhead & Profit 15% 7,999.56
F Harga Satuan Pekerjaan (D+E) 61,329.96

3.2.2.2.17.(a) Plesteran Tebal 1,5 cm, dengan Mortar Campuran (setara 1 PC : 6 PP) 43,136.96
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 24,830.00
Pekerja L.01 OH 0.130 80,000.00 10,400.00
Tukang batu L.02 OH 0.130 90,000.00 11,700.00
Kepala Tukang L.03 OH 0.013 105,000.00 1,365.00
Mandor L.04 OH 0.013 105,000.00 1,365.00
B Bahan 12,680.40
Pasir Pasang m3 0.027 228,400.00 6,166.80
Portland Cement Kg 4.416 1,475.00 6,513.60
C PERALATAN
D Jumlah A + B + C 37,510.40
E Overhead & Profit 15% 5,626.56
F Harga Satuan Pekerjaan (D+E) 43,136.96

3.2.2.2.35.(a) Pemasangan 1 m2 Acian 27,477.81


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 19,100.00
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.010 105,000.00 1,050.00
B BAHAN 4,793.75
Portland Semen, Ex. Gresik Kg 3.250 1,475.00 4,793.75
C PERALATAN
D Jumlah A + B + C 23,893.75
E Overhead & Profit 15% 3,584.06
F Harga Satuan Pekerjaan (D+E) 27,477.81

81
HARGA
JUMLAH
SNI #REF! KODE SAT. KOEF BAHAN/UPAH
Rp Rp

2.2.1.2 HARGA SATUAN PEKERJAAN BETON secara SEMI MEKANIS


2.2.1.2.b Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 995,639.72
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 115,625.00
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang Batu L.02 OH 0.250 90,000.00 22,500.00
Kepala Tukang L.03 OH 0.025 105,000.00 2,625.00
Mandor L.04 OH 0.100 105,000.00 10,500.00
B Bahan 734,282.00
Portland Semen, Ex. Gresik Kg 276.000 1,475.00 407,100.00
Pasir Beton kg 828.000 164.00 135,792.00
Kerikil (maksimum 30 mm) kg 1,012.000 170.00 172,040.00
Air ltr 215.000 90.00 19,350.00
C PERALATAN 15,866.67
Molen Kapasitas 0,35 m3 hari 0.238 66,666.67 15,866.67
D Jumlah A + B + C 865,773.67
E Overhead & Profit 15% 129,866.05
F Harga Satuan Pekerjaan (D+E) 995,639.72

A.4.1.1.5 Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 1,070,950.92
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 115,625.00
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang Batu L.02 OH 0.250 90,000.00 22,500.00
Kepala Tukang L.03 OH 0.025 105,000.00 2,625.00
Mandor L.04 OH 0.100 105,000.00 10,500.00
B BAHAN 799,770.00
Portland Semen, Ex. Gresik Kg 326.000 1,475.00 480,850.00
Pasir Beton Kg 760.000 164.00 124,640.00
Kerikil (maksimum 30 mm) Kg 1,029.000 170.00 174,930.00
Air ltr 215.000 90.00 19,350.00
C PERALATAN 15,866.67
Molen Kapasitas 0,35 m3 hari 0.238 66,666.67 15,866.67
D Jumlah A + B + C 931,261.67
E Overhead & Profit 15% 139,689.25
F Harga Satuan Pekerjaan (D+E) 1,070,950.92

2.2.1.2.f Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 1,133,070.47
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 110,375.00
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang Batu L.02 OH 0.250 90,000.00 22,500.00
Kepala Tukang L.03 OH 0.025 105,000.00 2,625.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
B BAHAN 859,037.00
Portland Semen, Ex. Gresik Kg 371.000 1,475.00 547,225.00
Pasir Beton Kg 698.000 164.00 114,472.00
Kerikil (maksimum 30 mm) Kg 1,047.000 170.00 177,990.00
Air ltr 215.000 90.00 19,350.00
C PERALATAN 15,866.67
Molen Kapasitas 0,35 m3 hari 0.238 66,666.67 15,866.67
D Jumlah A + B + C 985,278.67
E Overhead & Profit 15% 147,791.80
F Harga Satuan Pekerjaan (D+E) 1,133,070.47

HITUNG PB 1 Pembesian tul. polos kolom, balok, ring balk dan sloof untuk 100 kg Besi Beton Ø ≤ 12 mm (semi mekanis) 1,851,068.01
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 22,520.00
Pekerja L.01 OH 0.160 80,000.00 12,800.00
Tukang Besi L.02 OH 0.080 90,000.00 7,200.00
Kepala Tukang L.03 OH 0.008 105,000.00 840.00
Mandor L.04 OH 0.016 105,000.00 1,680.00
B Bahan 1,561,840.00
Besi beton polos Kg 105.000 14,400.00 1,512,000.00
Kawat Tali Beton Kg 2.800 17,800.00 49,840.00
C PERALATAN 25,264.36
Cutter besi beton Hari 0.040 315,804.44 12,632.18
Bender besi beton Hari 0.040 315,804.44 12,632.18
D Jumlah A + B + C 1,609,624.36
E Overhead & Profit 15% 241,443.65
F Harga Satuan Pekerjaan (D+E) 1,851,068.01

82
HARGA BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
HITUNG K.1 Pembuatan & Pemasangan 1m3 Kusen Pintu & Kusen Jendela, Kayu kruing 13,599,537.75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 2,707,250.00
Pekerja L.01 OH 7.000 80,000.00 560,000.00
Tukang Kayu L.02 OH 21.000 90,000.00 1,890,000.00
Kepala Tukang L.03 OH 2.100 105,000.00 220,500.00
Mandor L.04 OH 0.350 105,000.00 36,750.00
B Bahan 9,118,435.00
Kayu kruing , Balok m3 1.100 8,203,100.00 9,023,410.00
Paku Biasa 2" - 5 " kg 1.250 18,900.00 23,625.00
Lem Kayu kg 1.000 71,400.00 71,400.00
C PERALATAN
D Jumlah A + B + C 11,825,685.00
E Overhead & Profit 0.15 1,773,852.75
F Harga Satuan Pekerjaan (D+E) 13,599,537.75

A.4.6.1.5 Pembuatan 1m2 Daun Pintu Panel, Kayu Klas I atau II 835,744.10
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 386,750.00
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang Kayu L.02 OH 3.000 90,000.00 270,000.00
Kepala Tukang L.03 OH 0.300 105,000.00 31,500.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
B Bahan 339,984.00
Kayu Klas II (Kamfer), papan m3 0.040 7,607,100.00 304,284.00
Lem Kayu kg 0.500 71,400.00 35,700.00
C PERALATAN
D Jumlah A + B + C 726,734.00
E Overhead & Profit 0.15 109,010.10
F Harga Satuan Pekerjaan (D+E) 835,744.10

A.4.6.1.7 Pembuatan 1m2 Pintu & Jendela Jalusi Kayu Kruing 1,104,057.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 386,750.00
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang Kayu L.02 OH 3.000 90,000.00 270,000.00
Kepala Tukang L.03 OH 0.300 105,000.00 31,500.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
B Bahan 573,300.00
Kayu Kruing, papan m3 0.064 8,400,000.00 537,600.00
Lem Kayu kg 0.500 71,400.00 35,700.00
C PERALATAN
D Jumlah A + B + C 960,050.00
E Overhead & Profit 0.15 144,007.50
F Harga Satuan Pekerjaan (D+E) 1,104,057.50

HITUNG K.2 Pemasangan 1m3 Konstruksi Kuda-kuda Konvensional Kayu Kruing, Bentang 7.5 meter 12,860,450.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 1,933,750.00
Pekerja L.01 OH 5.000 80,000.00 400,000.00
Tukang Kayu L.02 OH 15.000 90,000.00 1,350,000.00
Kepala Tukang L.03 OH 1.500 105,000.00 157,500.00
Mandor L.04 OH 0.250 105,000.00 26,250.00
B Bahan 9,249,250.00
Kayu Kruing, balok m3 1.100 8,203,100.00 9,023,410.00
Besi Strip Kg 15.000 8,000.00 120,000.00
Paku Biasa 12 cm Kg 5.600 18,900.00 105,840.00
C PERALATAN
D Jumlah A + B + C 11,183,000.00
E Overhead & Profit 0.15 1,677,450.00
F Harga Satuan Pekerjaan (D+E) 12,860,450.00

83
HITUNG K.3 Pemasangan 1m3 konstruksi Gording, Kayu Kruing 11,845,931.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 928,200.00
Pekerja L.01 OH 2.400 80,000.00 192,000.00
Tukang Kayu L.02 OH 7.200 90,000.00 648,000.00
Kepala Tukang L.03 OH 0.720 105,000.00 75,600.00
Mandor L.04 OH 0.120 105,000.00 12,600.00
B Bahan 9,372,610.00
Kayu Kruing, balok m3 1.100 8,203,100.00 9,023,410.00
Besi Strip Kg 15.000 19,500.00 292,500.00
Paku Biasa 12 cm Kg 3.000 18,900.00 56,700.00
C PERALATAN
D Jumlah A + B + C 10,300,810.00
E Overhead & Profit 0.15 1,545,121.50
F Harga Satuan Pekerjaan (D+E) 11,845,931.50

HITUNG K.4 Pemasangan 1m2 Rangka Atap Usuk & Reng kayu kelas II 109,131.21
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 18,575.00
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 76,321.70
Kayu Klas II (Kruing), Kaso-kaso (5x7) cm 50% m3 0.014 8,203,100.00 57,421.70
Reng (2x3) cm Jati 50% m3 0.004 7,875,000.00 14,175.00
Paku Biasa 5 - 10 cm Kg 0.250 18,900.00 4,725.00
C PERALATAN
D Jumlah A + B + C 94,896.70
E Overhead & Profit 0.15 14,234.51
F Harga Satuan Pekerjaan (D+E) 109,131.21

HITUNG K.5 Pemasangan 1m2 Rangka Atap Genteng, Kayu Kruing 105,621.97
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 18,575.00
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 73,270.19
Kayu Klas II (Kruing), Kaso-kaso (5x7) cm 35% m3 0.014 8,203,100.00 40,195.19
Reng (2x3) cm Jati m3 0.004 7,875,000.00 28,350.00
Paku Biasa 5 - 10 cm Kg 0.250 18,900.00 4,725.00
C PERALATAN
D Overhead & Profit 91,845.19
E Harga Satuan Pekerjaan (D+E) 0.15 13,776.78
F Harga Satuan Pekerjaan (D+E) 105,621.97

84
HITUNG K.6 Pemasangan 1m' Lisplank GRC 9/20 54,593.38
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 28,625.00
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 18,847.50
Listplank GRC 9/20 m' 1.050 17,050.00 17,902.50
Paku Biasa 5 - 7 cm Kg 0.050 18,900.00 945.00
C PERALATAN
D Jumlah A + B + C 47,472.50
E Overhead & Profit 0.15 7,120.88
F Harga Satuan Pekerjaan (D+E) 54,593.38

HITUNG PKJ.1 Pemasangan kembali Jendela 1 155,727.25


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 135,415.00
Pekerja L.01 OH 0.350 80,000.00 28,000.00
Tukang Kayu L.02 OH 1.050 90,000.00 94,500.00
Kepala Tukang L.03 OH 0.105 105,000.00 11,025.00
Mandor L.04 OH 0.018 105,000.00 1,890.00
B Bahan
C PERALATAN
D Jumlah A + B + C 135,415.00
E Overhead & Profit 0.15 20,312.25
F Harga Satuan Pekerjaan (D+E) 155,727.25

85
HARGA
BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


A.4.5.2.1 Pemasangan 1 m2 Atap Genteng Plentong Kecil 70,871.63
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 20,377.50
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang Kayu L.02 OH 0.075 90,000.00 6,750.00
Kepala Tukang L.03 OH 0.0075 105,000.00 787.50
Mandor L.04 OH 0.008 105,000.00 840.00
B Bahan 41,250.00
Genteng Plentong Buah 25.000 1,650.00 41,250.00
C PERALATAN
D Jumlah A + B + C 61,627.50
E Overhead & Profit 15% 9,244.13
F Harga Satuan Pekerjaan (D+E) 70,871.63

HITUNG AT.1 Pemasangan 1 m Nok/Bubung Genteng Tanah Liat lokal 49,634.00


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 36,440.00
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang Kayu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.013 105,000.00 1,365.00
B Bahan 6,720.00
Bubungan genteng tanah liat lokal bh 3.500 1,650.00 5,775.00
paku biasa kg 0.050 18,900.00 945.00
C PERALATAN
D Jumlah A + B + C 43,160.00
E Overhead & Profit 15% 6,474.00
F Harga Satuan Pekerjaan (D+E) 49,634.00

A.4.5.2.41 Pemasangan 1m Nok/Bubung atap seng 66,954.15


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 19,665.00
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang Kayu L.02 OH 0.070 90,000.00 6,300.00
Kepala Tukang L.03 OH 0.007 105,000.00 735.00
Mandor L.04 OH 0.006 105,000.00 630.00
B Bahan 38,556.00
seng plat 3'x6' bjls 28 bh 0.300 126,000.00 37,800.00
paku biasa kg 0.040 18,900.00 756.00
C PERALATAN
D Jumlah A + B + C 58,221.00
E Overhead & Profit 15% 8,733.15
F Harga Satuan Pekerjaan (D+E) 66,954.15

HITUNG AT.2 Pemasangan 1 m2 Atap Genteng Plentong Kecil 70,871.63


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 20,377.50
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang Kayu L.02 OH 0.075 90,000.00 6,750.00
Kepala Tukang L.03 OH 0.0075 105,000.00 787.50
Mandor L.04 OH 0.008 105,000.00 840.00
B Bahan 41,250.00
Genteng Plentong Buah 25.000 1,650.00 41,250.00
C PERALATAN
D Jumlah A + B + C 61,627.50
E Overhead & Profit 15% 9,244.13
F Harga Satuan Pekerjaan (D+E) 70,871.63

86
HITUNG AT.3 Pemasangan kembali 1 m2 Atap Genteng Plentong Kecil 23,434.13
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 20,377.50
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang Kayu L.02 OH 0.075 90,000.00 6,750.00
Kepala Tukang L.03 OH 0.0075 105,000.00 787.50
Mandor L.04 OH 0.008 105,000.00 840.00
B Bahan
C PERALATAN
D Jumlah A + B + C 20,377.50
E Overhead & Profit 15% 3,056.63
F Harga Satuan Pekerjaan (D+E) 23,434.13

HITUNG AT.4 Pemasangan 1 m2 rangka usuk C.75.075 & reng baja ringan, Ex. Fortuna 66,389.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 23,350.00
Pekerja L.01 OH 0.125 80,000.00 10,000.00
Tukang Kayu L.02 OH 0.125 90,000.00 11,250.00
Kepala Tukang L.03 OH 0.0130 105,000.00 1,365.00
Mandor L.04 OH 0.007 105,000.00 735.00
B Bahan 27,504.00
Usuk baja ringan c.75 m' 1.440 19,100.00 27,504.00
Reng baja ringan dari bahan m' 3.680 9,100.00 33,488.00
C PERALATAN 6,876.00
Aksesories 25% dari bahan 25% 0.250 27,504.00 6,876.00
D Jumlah A + B + C 57,730.00
E Overhead & Profit 15% 8,659.50
F Harga Satuan Pekerjaan (D+E) 66,389.50

HITUNG AT.5 Pemasangan 1 m2 atap seng galvalume 0.25mm 71,835.04


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 15,735.00
Pekerja L.01 OH 0.120 80,000.00 9,600.00
Tukang Kayu L.02 OH 0.060 90,000.00 5,400.00
Kepala Tukang L.03 OH 0.0060 105,000.00 630.00
Mandor L.04 OH 0.001 105,000.00 105.00
B Bahan 40,635.00
Seng galvalume 0.25mm m' 1.050 38,700.00 40,635.00
C PERALATAN 6,095.25
Aksesories 15% dari bahan 25% 0.150 40,635.00 6,095.25
D Jumlah A + B + C 62,465.25
E Overhead & Profit 15% 9,369.79
F Harga Satuan Pekerjaan (D+E) 71,835.04

87
HARGA JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT


A.4.5.1.10 Memasang 1m list Langit-langit kayu profil 23,395.60
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 9,340.00
Pekerja L.01 OH 0.050 80,000.00 4,000.00
Tukang Kayu L.02 OH 0.050 90,000.00 4,500.00
Kepala Tukang L.03 OH 0.005 105,000.00 525.00
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan 11,004.00
list kayu profil m' 1.050 10,300.00 10,815.00
paku kg 0.010 18,900.00 189.00
C PERALATAN
D Jumlah A + B + C 20,344.00
E Overhead & Profit 15% 3,051.60
F Harga Satuan Pekerjaan (D+E) 23,395.60

HITUNG PF.1 Memasang 1 m2 Langit-langit GRC Board tebal 4 mm + Rangka Hollow Galvanis 132,587.81
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 46,385.00
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang besi L.02 OH 0.250 90,000.00 22,500.00
Kepala Tukang L.03 OH 0.025 105,000.00 2,625.00
Mandor L.04 OH 0.012 105,000.00 1,260.00
B Bahan 68,908.75
GRC Board 120 x240 x 0.4 cm Lbr 0.364 63,000.00 22,932.00
Besi Hollow 40 x 40 x 3.5 mm m' 1.580 7,275.00 11,494.50
Besi Hollow 20 x 40 x 3.5 mm m' 0.700 5,325.00 3,727.50
Compoun zak 0.310 3,150.00 976.50
Dinabolt bh 3.500 3,650.00 12,775.00
Cotton Plaster m' 1.38 325.00 448.50
Sekrup Buah 39.750 225.00 8,943.75
Perkuatan dan Penggantung (50% x rangka) 0.500 15,222.00 7,611.00
C PERALATAN
D Jumlah A + B + C 115,293.75
E Overhead & Profit 15% 17,294.06
F Harga Satuan Pekerjaan (D+E) 132,587.81

88
HARGA
BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING
A.4.4.3.35 Pemasangan 1 m2 Lantai Keramik Uk. 20 s.d <30 cm 209,832.45
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 94,850.00
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang Batu L.02 OH 0.350 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.035 105,000.00 3,675.00
B Bahan 87,613.00
Ubin Keramik Dus 1.050 51,900.00 54,495.00
Portland Semen Kg 10.400 1,475.00 15,340.00
Pasir Pasang m3 0.045 228,400.00 10,278.00
Semen Warna Kg 0.500 15,000.00 7,500.00
C PERALATAN
D Jumlah A + B + C 182,463.00
E Overhead & Profit 15% 27,369.45
F Harga Satuan Pekerjaan (D+E) 209,832.45

A.4.4.3.36 Pemasangan 1 m2 Lantai Keramik Uk. 30 s.d <40 cm 221,591.20


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 94,850.00
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang Batu L.02 OH 0.350 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.035 105,000.00 3,675.00
B Bahan 97,838.00
Ubin Keramik Dus 1.050 62,200.00 65,310.00
Portland Semen Kg 10.000 1,475.00 14,750.00
Semen Warna Kg 0.500 15,000.00 7,500.00
Pasir Pasang m3 0.045 228,400.00 10,278.00
C PERALATAN
D Jumlah A + B + C 192,688.00
E Overhead & Profit 15% 28,903.20
F Harga Satuan Pekerjaan (D+E) 221,591.20

HITUNG LD.1 Pemasangan 1 m2 Guilding Block uk. 30x30 156,327.39


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 11,260.00
Pekerja L.01 OH 0.083 80,000.00 6,640.00
Tukang L.02 OH 0.042 90,000.00 3,780.00
Kepala Tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.0040 105,000.00 420.00
B Bahan 113,342.60
Guilding block 30x30x6 m2 3.524 30,000.00 105,720.00
portland semen m3 3.000 1,475.00 4,425.00
pasir pasang m3 0.014 228,400.00 3,197.60
C PERALATAN 11,334.26
10% dari bahan 0.100 113,342.60 11,334.26
D Jumlah A + B + C 135,936.86
E Overhead & Profit 15% 20,390.53
F Harga Satuan Pekerjaan (D+E) 156,327.39

CK Boyolali
HARGA
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH JUMLAH
Rp Rp

3.3 HARGA SATUAN PEKERJAAN PENGECATAN


HITUNG PC.1 1 m2 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup) 50,397.60
Harga Satuan Jumlah Harga
No Uraian Kode Satuan
Koefisien
(Rp) (Rp)
A Tenaga 7,355.00
Pekerja L.01 OH 0.070 80,000.00 5,600.00
Tukang Cat L.02 OH 0.009 90,000.00 810.00
Kepala Tukang L.03 OH 0.006 105,000.00 630.00
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan 36,469.00
Cat Menie kg 0.200 38,800.00 7,760.00
Plamuur kg 0.150 36,500.00 5,475.00
Cat Kayu Danalac kg 0.170 66,100.00 11,237.00
Menie Kayu kg 0.260 38,800.00 10,088.00
Kuas bh 0.010 8,400.00 84.00
Pengencer kg 0.030 31,500.00 945.00
Amplas lbr 0.200 4,400.00 880.00
C PERALATAN
D Jumlah A + B + C 43,824.00
E Overhead & Profit ### 6,573.60
F Harga Satuan Pekerjaan (D+E) 50,397.60

HITUNG PC.2 1 m2 Pengecat Tembok Baru ( 1 Lap Plamuur, 1 Lap Cat Dasar, 2 lap. Cat penutup ) Ex. Envi 24,985.48
Harga Satuan Jumlah Harga
No Uraian Kode Satuan
Koefisien
(Rp) (Rp)
A Tenaga 8,246.50
Pekerja L.01 OH 0.020 80,000.00 1,600.00
Tukang Cat L.02 OH 0.063 90,000.00 5,670.00
Kepala Tukang L.03 OH 0.0063 105,000.00 661.50
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan 13,480.00
Plamir Kg 0.100 28,600.00
Cat Dasar, Ex. envi Kg 0.100 43,800.00 4,380.00
Cat Penutup 2 kali Interior, Ex. Envi Kg 0.260 35,000.00 9,100.00
C PERALATAN
D Jumlah A + B + C 21,726.50
E Overhead & Profit ### 3,258.98
F Harga Satuan Pekerjaan (D+E) 24,985.48

HITUNG PC.3 1 m2 Pengecat Tembok Baru ( 1 Lap Plamuur, 1 Lap Cat Dasar, 2 lap. Cat penutup ) Ex. Envi 28,154.88
Harga Satuan Jumlah Harga
No Uraian Kode Satuan
Koefisien
(Rp) (Rp)
A Tenaga 8,246.50
Pekerja L.01 OH 0.020 80,000.00 1,600.00
Tukang Cat L.02 OH 0.063 90,000.00 5,670.00
Kepala Tukang L.03 OH 0.0063 105,000.00 661.50
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan 16,236.00
Plamir Kg 0.100 28,600.00
Cat Dasar, Ex. envi Kg 0.100 43,800.00 4,380.00
Cat Penutup 2 kali Eksterior, Ex. Envi Kg 0.260 45,600.00 11,856.00
C PERALATAN
D Jumlah A + B + C 24,482.50
E Overhead & Profit ### 3,672.38
F Harga Satuan Pekerjaan (D+E) 28,154.88

CK Boyolali
HITUNG PC.4 1 m2 Pengecatan Tembok Lama (1 lap Cat Dasar, 2 lap Cat Penutup) 21,081.80
Harga Satuan Jumlah Harga
No Uraian Kode Satuan
Koefisien
(Rp) (Rp)
A Tenaga 6,776.00
Pekerja L.01 OH 0.028 80,000.00 2,240.00
Tukang Cat L.02 OH 0.042 90,000.00 3,780.00
Kepala Tukang L.03 OH 0.004 105,000.00 441.00
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan 11,556.00
Cat Dasar, Ex. envi Kg 0.120 43,800.00 5,256.00
Cat Penutup 2 kali Interior, Ex. Envi Kg 0.180 35,000.00 6,300.00
C PERALATAN
D Jumlah A + B + C 18,332.00
E Overhead & Profit ### 2,749.80
F Harga Satuan Pekerjaan (D+E) 21,081.80

HITUNG PC.5 1 m2 Pengecatan Tembok Lama (1 lap Cat Dasar, 2 lap Cat Penutup) 23,276.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan
Koefisien
(Rp) (Rp)
A Tenaga 6,776.00
Pekerja L.01 OH 0.028 80,000.00 2,240.00
Tukang Cat L.02 OH 0.042 90,000.00 3,780.00
Kepala Tukang L.03 OH 0.004 105,000.00 441.00
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan 13,464.00
Cat Dasar, Ex. envi Kg 0.120 43,800.00 5,256.00
Cat Penutup 2 kali Eksterior, Ex. Envi Kg 0.180 45,600.00 8,208.00
C PERALATAN
D Jumlah A + B + C 20,240.00
E Overhead & Profit ### 3,036.00
F Harga Satuan Pekerjaan (D+E) 23,276.00

HITUNG PC.6 Pengecatan 1 m2 Langit-langit 26,142.95


Harga Satuan Jumlah Harga
No Uraian Kode Satuan
Koefisien
(Rp) (Rp)
A Tenaga 11,345.00
Pekerja L.01 OH ### 80,000.00 3,200.00
Tukang Cat L.02 OH ### 90,000.00 7,200.00
Kepala Tukang L.03 OH ### 105,000.00 630.00
Mandor L.04 OH ### 105,000.00 315.00
B Bahan 11,388.00
Cat Dasar, Ex. envi Kg ### 43,800.00 11,388.00
C PERALATAN
D Jumlah A + B + C 22,733.00
E Overhead & Provit 15% 3,409.95
F Harga Satuan Pekerjaan (D+E) 26,142.95

CK Boyolali
HARGA JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
A.4.6.2.2 Pemasangan 1 Buah Kunci Tanam Biasa 143,836.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 51,575.00
Pekerja L.01 OH 0.010 80,000.00 800.00
Tukang Kayu L.02 OH 0.500 90,000.00 45,000.00
Kepala Tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 73,500.00
Kunci Tanam Biasa Buah 1.000 73,500.00 73,500.00
C PERALATAN
D Jumlah A + B + C 125,075.00
E Overhead & Profit 15% 18,761.25
F Harga Satuan Pekerjaan (D+E) 143,836.25

A.4.6.2.5 Pemasangan 1 Buah Engsel Pintu 156,011.88


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 17,062.50
Pekerja L.01 OH 0.015 80,000.00 1,200.00
Tukang Kayu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.008 105,000.00 787.50
B Bahan 118,600.00
Engsel pintu 4" Buah 1.000 118,600.00 118,600.00
C PERALATAN
D Jumlah A + B + C 135,662.50
E Overhead & Profit 15% 20,349.38
F Harga Satuan Pekerjaan (D+E) 156,011.88

A.4.6.2.6 Pemasangan 1 Buah Engsel Jendela Kupu-kupu 56,007.88


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 10,902.50
Pekerja L.01 OH 0.010 80,000.00 800.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.0005 105,000.00 52.50
B Bahan 37,800.00
Engsel Jendela 3" Buah 1.000 37,800.00 37,800.00
C PERALATAN
D Jumlah A + B + C 48,702.50
E Overhead & Profit 15% 7,305.38
F Harga Satuan Pekerjaan (D+E) 56,007.88

CK Boyolali
A.4.6.2.7 Pemasangan 1 Buah Engsel Angin 121,730.38
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 28,152.50
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.001 105,000.00 52.50
B Bahan 77,700.00
Engsel Angin Buah 1.000 77,700.00 77,700.00
C PERALATAN
D Jumlah A + B + C 105,852.50
E Overhead & Profit 15% 15,877.88
F Harga Satuan Pekerjaan (D+E) 121,730.38

A.4.6.2.11 Pemasangan 1 Buah Kunci Selot 109,600.75


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 21,805.00
Pekerja L.01 OH 0.020 80,000.00 1,600.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.001 105,000.00 105.00
B Bahan 73,500.00
Kunci Selot Buah 1.000 73,500.00 73,500.00
C PERALATAN
D Jumlah A + B + C 95,305.00
E Overhead & Profit 15% 14,295.75
F Harga Satuan Pekerjaan (D+E) 109,600.75

A.4.6.2.17 Pemasangan 1 m2 Kaca tebal 5 mm 219,982.35


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 16,359.00
Pekerja L.01 OH 0.015 80,000.00 1,200.00
Tukang Kayu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.0008 105,000.00 84.00
B Bahan 174,930.00
Kaca tebal 5mm m2 1.100 157,500.00 173,250.00
Silicone sealant 300 ml Tube 0.050 33,600.00 1,680.00
C PERALATAN
D Jumlah A + B + C 191,289.00
E Overhead & Profit 15% 28,693.35
F Harga Satuan Pekerjaan (D+E) 219,982.35

CK Boyolali
HARGA
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH JUMLAH
Rp Rp

A.6.1.1 HARGA SATUAN PEKERJAAN DISTRIBUSI JARINGAN LISTRIK


HITUNG DL.1 Pemasangan 1 buah MCB 1,307,607.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 90,000.00
Upah OH 1.000 90,000.00 90,000.00
B Bahan 1,047,050.00
Pipa listrik 5/8" btg 3.000 189,000.00 567,000.00
Kabel m' 15.000 16,200.00 243,000.00
T Dus buah 1.000 3,150.00 3,150.00
L Bow buah 2.000 3,500.00 7,000.00
Klem buah 24.000 1,050.00 25,200.00
MCCB (Boks MCB) buah 1.000 154,500.00 154,500.00
MCB, Ex Broco buah 1.000 47,200.00 47,200.00
C PERALATAN
D Jumlah A + B + C 1,137,050.00
E Overhead + Profit 15% 170,557.50
F Harga Satuan Pekerjaan (D+E) 1,307,607.50

HITUNG DL.2 Pemasangan Saklar tunggal, ex clipsal 29,238.75


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 5,025.00
Tukang Listrik OH 0.050 90,000.00 4,500.00
Mandor OH 0.005 105,000.00 525.00
B Bahan 20,400.00
Saklar tunggal buah 1.000 20,400.00 20,400.00
C PERALATAN
D Jumlah A + B + C 25,425.00
E Overhead + Profit 15% 3,813.75
F Harga Satuan Pekerjaan (D+E) 29,238.75

HITUNG DL.3 Pemasangan Saklar ganda, ex clipsal 40,623.75


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 5,025.00
Tukang Listrik OH 0.050 90,000.00 4,500.00
Mandor OH 0.005 105,000.00 525.00
B Bahan 30,300.00
Saklar ganda buah 1.000 30,300.00 30,300.00
C PERALATAN
D Jumlah A + B + C 35,325.00
E Overhead + Profit 15% 5,298.75
F Harga Satuan Pekerjaan (D+E) 40,623.75

HITUNG DL.4 Pemasangan stop kontak dinding, ex clipsal 37,173.75


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 5,025.00
Tukang Listrik OH 0.050 90,000.00 4,500.00
Mandor OH 0.005 105,000.00 525.00
B Bahan 27,300.00
Stop kontak buah 1.000 27,300.00 27,300.00
C PERALATAN
D Jumlah A + B + C 32,325.00
E Overhead + Profit 15% 4,848.75
F Harga Satuan Pekerjaan (D+E) 37,173.75
HITUNG DL.5 Pek. Instalasi kabel NYM 3x2.5 mm, ex eterna 111,607.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 25,350.00
Tukang Listrik OH 0.2 90,000.00 18,000.00
Kepala tukang OH 0.02 105,000.00 2,100.00
Mandor OH 0.05 105,000.00 5,250.00
B Bahan 71,700.00
Kabel NYM ukr 3x2.5 mm m' 3 16,200.00 48,600.00
Pipa clipsal m' 3 5,250.00 15,750.00
Tee doos unit 1 3,150.00 3,150.00
Sock (1 sock per 3m) unit 1 1,050.00 1,050.00
Klem unit 3 1,050.00 3,150.00
C PERALATAN
D Jumlah A + B + C 97,050.00
E Overhead + Profit 15% 14,557.50
F Harga Satuan Pekerjaan (D+E) 111,607.50

HITUNG PC.1 Pemasangan TL 2x20 RM Armateur In Bow 223,330.00


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 38,100.00
tukang listrik OH 0.400 90,000.00 36,000.00
mandor OH 0.020 105,000.00 2,100.00
B Bahan 156,100.00
TL 2x20 RM Armateur In Bow bh 1.000 156,100.00 156,100.00
C PERALATAN
D Jumlah A + B + C 194,200.00
E Overhead + Profit 15% 29,130.00
F Harga Satuan Pekerjaan (D+E) 223,330.00

HITUNG PC.2 Pemasangan LED 12 watt, Ex. Osram 60,950.00


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 18,000.00
Tukang Listrik OH 0.200 90,000.00 18,000.00
B Bahan 35,000.00
LED 12 watt, Ex. Osram bh 1.000 35,000.00 35,000.00
C PERALATAN
D Jumlah A + B + C 53,000.00
E Overhead + Profit 15% 7,950.00
F Harga Satuan Pekerjaan (D+E) 60,950.00
HARGA
BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM
A.4.2.1.4 Pembuatan 1 m2 Pintu Besi Plat Baja tebal 2 mm rangkap, rangka baja Siku 304,021.13
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 194,985.00
Pekerja L.01 OH 1.050 80,000.00 84,000.00
Tukang Besi L.02 OH 1.050 90,000.00 94,500.00
Kepala Tukang L.03 OH 0.105 105,000.00 11,025.00
Mandor L.04 OH 0.052 105,000.00 5,460.00
B Bahan 14,570.00
Solar ltr 1.000 9,000.00 9,000.00
Minyak Pelumas ltr 0.100 55,700.00 5,570.00
C PERALATAN 54,811.20
Sewa Alat jam 0.800 68,514.00 54,811.20
D Jumlah A + B + C 264,366.20
E Overhead & Profit 15% 39,654.93
F Harga Satuan Pekerjaan (D+E) 304,021.13

A.4.2.1.18 Pemasangan 1 m' Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm 186,620.28


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 36,205.00
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.001 105,000.00 105.00
B Bahan 126,073.50
Seng Plat Lbr 1.050 21,000.00 22,050.00
Paku Biasa 1 - 2,5 cm Kg 0.015 18,900.00 283.50
Kayu Papan Klas II atau III m3 0.019 5,460,000.00 103,740.00
C PERALATAN
D Jumlah A + B + C 162,278.50
E Overhead & Profit 15% 24,341.78
F Harga Satuan Pekerjaan (D+E) 186,620.28

HITUNG BA.1 Pemasangan 1 m' Railing alumunium 177,510.55


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 8,722.00
Pekerja L.01 OH 0.0080 80,000.00 640.00
Tukang L.02 OH 0.0800 90,000.00 7,200.00
Kepala Tukang L.03 OH 0.0080 105,000.00 840.00
Mandor L.04 OH 0.0004 105,000.00 42.00
B Bahan 145,635.00
Railing alumunium m' 1.050 138,700.00 145,635.00
C PERALATAN
D Jumlah A + B + C 154,357.00
E Overhead & Profit 15% 23,153.55
F Harga Satuan Pekerjaan (D+E) 177,510.55

96
HARGA JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DAN PERPIPAAN DALAM GEDUNG


A.5.1.1.1 Memasang 1 Buah Closet Duduk / Mono Blok Ex. Toto Seri CW702J/SW784JP 4,954,591.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 156,850.00
Pekerja L.01 OH 0.500 80,000.00 40,000.00
Tukang Batu L.02 OH 1.100 90,000.00 99,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.160 105,000.00 16,800.00
B Bahan 4,151,490.00
Kloset Duduk / Monoblok Buah 1.000 3,916,500.00 3,916,500.00
Kelengkapan 6% dari harga Kloset 0.060 3,916,500.00 234,990.00
C PERALATAN
D Jumlah A + B + C 4,308,340.00
E Overhead & Profit 15% 646,251.00
F Harga Satuan Pekerjaan (D+E) 4,954,591.00

A.5.1.1.2 Memasang 1 Buah Closet Jongkok Porselen 743,152.21


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 247,550.00
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang Batu L.02 OH 1.500 90,000.00 135,000.00
Kepala Tukang L.03 OH 0.150 105,000.00 15,750.00
Mandor L.04 OH 0.160 105,000.00 16,800.00
B Bahan 398,669.32
Kloset Jongkok CE7 WHITE Ex Toto Buah 1.000 388,500.00 388,500.00
Pasangan bata 1 PC:3PS Kg 0.036 282,481.00 10,169.32
C PERALATAN
D Jumlah A + B + C 646,219.32
E Overhead & Profit 15% 96,932.90
F Harga Satuan Pekerjaan (D+E) 743,152.21

HITUNG PG9 Pemasangan 1 m' Pipa PVC tipe AW Ø 1" 23,084.81


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 9,120.00
Pekerja L.01 OH 0.036 80,000.00 2,880.00
Tukang Batu L.02 OH 0.060 90,000.00 5,400.00
Kepala Tukang L.03 OH 0.006 105,000.00 630.00
Mandor L.04 OH 0.002 105,000.00 210.00
B Bahan 10,953.75
Pipa PVC Ø 1" m' 1.050 9,525.00 10,001.25
Perlengkapan 10% x pipa Ls 0.100 9,525.00 952.50
C PERALATAN
D Jumlah A + B + C 20,073.75
E Overhead & Profit 15% 3,011.06
F Harga Satuan Pekerjaan (D+E) 23,084.81

HITUNG PG13 Pemasangan 1 m' Pipa PVC tipe AW Ø 3" 132,379.38


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 20,467.50
Pekerja L.01 OH 0.081 80,000.00 6,480.00
Tukang Batu L.02 OH 0.135 90,000.00 12,150.00
Kepala Tukang L.03 OH 0.0135 105,000.00 1,417.50
Mandor L.04 OH 0.004 105,000.00 420.00
B Bahan 94,645.00
Pipa PVC Ø 3" m' 1.050 82,300.00 86,415.00
Perlengkapan 10% x pipa Ls 0.100 82,300.00 8,230.00
C PERALATAN
D Jumlah A + B + C 115,112.50
E Overhead & Profit 15% 17,266.88
F Harga Satuan Pekerjaan (D+E) 132,379.38

97
A.5.1.1.35 Pemasangan 1 Buah Kran Ø ½" atau Ø ¾" 144,437.13
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 41,525.00
Pekerja L.01 OH 0.010 80,000.00 800.00
Tukang Batu L.02 OH 0.400 90,000.00 36,000.00
Kepala Tukang L.03 OH 0.040 105,000.00 4,200.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 84,072.50
Kran Air bh 1.000 84,000.00 84,000.00
Sealtape bh 0.025 2,900.00 72.50
C PERALATAN
D Jumlah A + B + C 125,597.50
E Overhead & Profit 15% 18,839.63
F Harga Satuan Pekerjaan (D+E) 144,437.13

A.5.1.1.36 Pemasangan 1 Buah Floor Drain 115,661.25


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 11,375.00
Pekerja L.01 OH 0.010 80,000.00 800.00
Tukang Batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 89,200.00
Floor Drain bh 1.000 89,200.00 89,200.00
C PERALATAN
D Jumlah A + B + C 100,575.00
E Overhead & Profit 15% 15,086.25
F Harga Satuan Pekerjaan (D+E) 115,661.25

98
HARGA JUMLAH
SNI #REF! KODE SAT. KOEF BAHAN/UPAH
Rp Rp

A.1.5.1 HARGA SATUAN PEKERJAAN TANAH


A.1.5.1.13 Pemasangan 1 m2 Lapisan Ijuk tebal 10 cm unt Bidang Resapan 160,511.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA 13,575.00
Pekerja OH 0.150 80,000.00 12,000.00
Mandor OH 0.015 105,000.00 1,575.00
B BAHAN 126,000.00
Ijuk kg 6.000 21,000.00 126,000.00
C PERALATAN
D Jumlah (A+B+C) 139,575.00
E Overhead & Profit 15% 20,936.25
F Harga Satuan Pekerjaan (D+E) 160,511.25

99
HARGA
JUMLAH
SNI #REF! KODE SAT. KOEF BAHAN/UPAH
Rp Rp

A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.9. Pemasangan 1 m3 Batu Kosong (Aanstamping) untuk Pondasi Gedung 518,983.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 105,690.00
Pekerja L.01 OH 0.780 80,000.00 62,400.00
Tukang Batu L.02 OH 0.390 90,000.00 35,100.00
Kepala Tukang L.03 OH 0.039 105,000.00 4,095.00
Mandor L.04 OH 0.039 105,000.00 4,095.00
B Bahan 345,600.00
Batu Belah 15/20 m3 1.200 225,000.00 270,000.00
Pasir Urug m3 0.432 175,000.00 75,600.00
C PERALATAN
D Jumlah A + B + C 451,290.00
E Overhead & Profit 15% 67,693.50
F Harga Satuan Pekerjaan (D+E) 518,983.50

100
HARGA
BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
A.4.1.1.2 Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 1,038,090.05
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 168,405.00
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 105,000.00 8,715.00
B Bahan 734,282.00
Portland Semen Kg 276.000 1,475.00 407,100.00
Pasir Beton kg 828.000 164.00 135,792.00
Kerikil (maksimum 30 mm) kg 1,012.000 170.00 172,040.00
Air ltr 215.000 90.00 19,350.00
C PERALATAN
D Jumlah A + B + C 902,687.00
E Overhead & Profit 15% 135,403.05
F Harga Satuan Pekerjaan (D+E) 1,038,090.05

A.4.1.1.5 Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 1,113,401.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 168,405.00
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 105,000.00 8,715.00
B BAHAN 799,770.00
Portland Semen Kg 326.000 1,475.00 480,850.00
Pasir Beton Kg 760.000 164.00 124,640.00
Kerikil (maksimum 30 mm) Kg 1,029.000 170.00 174,930.00
Air ltr 215.000 90.00 19,350.00
C PERALATAN
D Jumlah A + B + C 968,175.00
E Overhead & Profit 15% 145,226.25
F Harga Satuan Pekerjaan (D+E) 1,113,401.25

A.4.1.1.7 Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 1,181,558.30
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 168,405.00
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 105,000.00 8,715.00
B BAHAN 859,037.00
Portland Semen Kg 371.000 1,475.00 547,225.00
Pasir Beton Kg 698.000 164.00 114,472.00
Kerikil (maksimum 30 mm) Kg 1,047.000 170.00 177,990.00
Air ltr 215.000 90.00 19,350.00
C PERALATAN
D Jumlah A + B + C 1,027,442.00
E Overhead & Profit 15% 154,116.30
F Harga Satuan Pekerjaan (D+E) 1,181,558.30

A.4.1.1.19 Memasang 1 m2 Bekisting untuk Sloof, Balok Latei, Ring Balk, Kolom Praktis Beton bangunan Gedung 147,947.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 70,460.00
Pekerja L.01 OH 0.520 80,000.00 41,600.00
Tukang Kayu L.02 OH 0.260 90,000.00 23,400.00
Kepala Tukang L.03 OH 0.026 105,000.00 2,730.00
Mandor L.04 OH 0.026 105,000.00 2,730.00
B Bahan 58,190.00
Kayu Klas III m3 0.018 2,887,500.00 51,975.00
Paku Biasa 2" - 5" Kg 0.300 18,900.00 5,670.00
Minyak Bekisting Ltr 0.100 5,450.00 545.00
C PERALATAN
D Jumlah A + B + C 128,650.00
E Overhead & Profit 15% 19,297.50
F Harga Satuan Pekerjaan (D+E) 147,947.50

101
HARGA JUMLAH
BAHAN/UPAH
SNI #REF! KODE SAT. KOEF
Rp Rp
A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK
A.4.1.2.5 Membuat 1m2 Begesting untuk Pelat Beton Pracetak Komponen Modular Bangunan Gedung ( 5x Pakai) 384,227.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 8,345.00
Pekerja L.01 OH 0.007 80,000.00 560.00
Tukang Kayu L.02 OH 0.076 90,000.00 6,840.00
Kepala Tukang L.03 OH 0.008 105,000.00 840.00
Mandor L.04 OH 0.001 105,000.00 105.00
B BAHAN 325,765.65
Lantai Kerja t=10cm m3 0.008 1,234,181.15 9,873.45
Besi Hollow (50x50x3) mm kg 9.394 29,100.00 273,365.40
Kayu kaso 5/7 (lebar 5cm, tinggi 7cm) m3 0.005 2,887,500.00 14,437.50
Phenol film 12mm lbr 0.080 157,500.00 12,600.00
Minyak Begesting Ltr 0.200 6,600.00 1,320.00
Dinabolt Ø12 mm bh 3.882 3,650.00 14,169.30
C PERALATAN
D Jumlah A + B + C 334,110.65
E Overhead & Profit 15% 50,116.60
F Harga Satuan Pekerjaan (D+E) 384,227.25

A.4.1.2.6 Membuat 1 m2 Begesting untuk Balok Beton Pracetak (10-12 kali pakai) 34,458.43
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 4,265.00
Pekerja L.01 OH 0.004 80,000.00 320.00
Tukang Kayu L.02 OH 0.038 90,000.00 3,420.00
Kepala Tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.001 105,000.00 105.00
B BAHAN 25,698.85
Kayu Kaso 5/7 cm m3 0.005 2,887,500.00 14,437.50
Phenol film 12 mm lbr 0.043 157,500.00 6,772.50
minyak begesting ltr 0.200 5,450.00 1,090.00
paku 5-7 cm kg 0.046 18,900.00 869.40
Dinabolt Ø12 mm bh 0.693 3,650.00 2,529.45
C PERALATAN
D Jumlah A + B + C 29,963.85
E Overhead & Profit 15% 4,494.58
F Harga Satuan Pekerjaan (D+E) 34,458.43

A.4.1.2.7 Membuat 1 m2 Begesting untuk Kolom Beton Pracetak (10-12 kali pakai) 32,043.43
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 4,265.00
Pekerja L.01 OH 0.004 80,000.00 320.00
Tukang Kayu L.02 OH 0.038 90,000.00 3,420.00
Kepala Tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.001 105,000.00 105.00
B BAHAN 23,598.85
Kayu Kaso 5/7 cm m3 0.004 2,887,500.00 11,550.00
Phenol film 12 mm lbr 0.048 157,500.00 7,560.00
minyak begesting ltr 0.200 5,450.00 1,090.00
paku 5-7 cm kg 0.046 18,900.00 869.40
Dinabolt Ø12 mm bh 0.693 3,650.00 2,529.45
C PERALATAN
D Jumlah A + B + C 27,863.85
E Overhead & Profit 15% 4,179.58
F Harga Satuan Pekerjaan (D+E) 32,043.43

A.4.1.2.8 Pemasangan dan Membuka 1 Unit Cetakan 1 buah Komponen Pelat Beton Pracetak 7,342.75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 6,385.00
Pekerja L.01 OH 0.053 80,000.00 4,240.00
Tukang Kayu L.02 OH 0.018 90,000.00 1,620.00
Mandor L.04 OH 0.005 105,000.00 525.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 6,385.00
E Overhead & Profit 15% 957.75
F Harga Satuan Pekerjaan (D+E) 7,342.75

A.4.1.2.9 Pemasangan dan Membuka 1 unit Cetakan 1 buah Komponen Balok Beton Pracetak 11,896.75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 10,345.00
Pekerja L.01 OH 0.089 80,000.00 7,120.00
Tukang Kayu L.02 OH 0.030 90,000.00 2,700.00
Mandor L.04 OH 0.005 105,000.00 525.00
B BAHAN

102
C PERALATAN
D Jumlah A + B + C 10,345.00
E Overhead & Profit 15% 1,551.75
F Harga Satuan Pekerjaan (D+E) 11,896.75

A.4.1.2.10 Pemasangan dan Membuka1 unit Cetakan 1 buah Komponen Kolom Beton Pracetak 9,619.75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 8,365.00
Pekerja L.01 OH 0.071 80,000.00 5,680.00
Tukang Kayu L.02 OH 0.024 90,000.00 2,160.00
Mandor L.04 OH 0.005 105,000.00 525.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 8,365.00
E Overhead & Profit 15% 1,254.75
F Harga Satuan Pekerjaan (D+E) 9,619.75

A.4.1.2.11 Penuangan/menebar 1 m3 beton untuk Pelat Beton Pracetak 57,015.85


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 49,579.00
Pekerja L.01 OH 0.064 80,000.00 5,120.00
Tukang batu L.02 OH 0.244 90,000.00 21,960.00
Tukang Vibrator L.02 OH 0.128 88,000.00 11,264.00
Kepala tukang L.03 OH 0.034 105,000.00 3,570.00
Mandor L.04 OH 0.073 105,000.00 7,665.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 49,579.00
E Overhead & Profit 15% 7,436.85
F Harga Satuan Pekerjaan (D+E) 57,015.85

A.4.1.2.12 Penuangan/menebar 1 m3 beton untuk Balok Beton Pracetak 58,643.10


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 50,994.00
Pekerja L.01 OH 0.069 80,000.00 5,520.00
Tukang batu L.02 OH 0.242 90,000.00 21,780.00
Tukang Vibrator L.02 OH 0.138 88,000.00 12,144.00
Kepala tukang L.03 OH 0.037 105,000.00 3,885.00
Mandor L.04 OH 0.073 105,000.00 7,665.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 50,994.00
E Overhead & Profit 15% 7,649.10
F Harga Satuan Pekerjaan (D+E) 58,643.10

A.4.1.2.13 Penuangan/menebar 1 m3 beton untuk Kolom Beton Pracetak 52,803.40


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 45,916.00
Pekerja L.01 OH 0.061 80,000.00 4,880.00
Tukang batu L.02 OH 0.213 90,000.00 19,170.00
Tukang Vibrator L.02 OH 0.122 88,000.00 10,736.00
Kepala tukang L.03 OH 0.033 105,000.00 3,465.00
Mandor L.04 OH 0.073 105,000.00 7,665.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 45,916.00
E Overhead & Profit 15% 6,887.40
F Harga Satuan Pekerjaan (D+E) 52,803.40

A.4.1.2.14 Pemasangan Komponen untuk 1 Unit Pelat Beton Pracetak beserta Indeks Kenaikan Lantai Ereksi Pelat hingga 24 Lantai 354,774.14
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 50,183.00
Pekerja L.01 OH 0.067 80,000.00 5,360.00
Tukang batu L.02 OH 0.067 90,000.00 6,030.00
Tukang Ereksi L.02 OH 0.134 88,000.00 11,792.00
Kepala tukang L.03 OH 0.067 105,000.00 7,035.00
Mandor L.04 OH 0.067 105,000.00 7,035.00
Operator Crane L.08 OH 0.067 105,000.00 7,035.00
Pembantu Operator Crane L.09 OH 0.067 88,000.00 5,896.00
B BAHAN
C PERALATAN 258,316.25
sewa crane unit hari 0.067 3,837,406.72 257,106.25
sewa pipe support buah hari 1.100 1,100.00 1,210.00
D Jumlah A + B + C 308,499.25
E Overhead & Profit 15% 46,274.89
F Harga Satuan Pekerjaan (D+E) 354,774.14

Indeks Pengali Menurut Tingkat Lantai Pemasangan Komponen untuk Pelat Pracetak

103
Indeks kenaikan lantai ereksi pelat Lantai Lantai Indeks kenaikan lantai
ereksi pelat

1.000 13 1 1.114
1.000 14 2 1.134
1.000 15 3 1.155
1.000 16 4 1.176
1.000 17 5 1.197
1.000 18 6 1.219
1.000 19 7 1.241
1.018 20 8 1.264
1.037 21 9 1.287
1.055 22 10 1.31
1.075 23 11 1.334
1.094 24 12 1.358

A.4.1.2.15 Pemasangan Komponen untuk 1 unit Balok Beton Pracetak beserta Indeks Kenaikan Lantai Ereksi Pelat hingga 24 Lantai 372,124.83
A TENAGA 46,055.00
Pekerja L.01 OH 0.061 80,000.00 4,880.00
Tukang batu L.02 OH 0.061 90,000.00 5,490.00
Tukang Ereksi L.02 OH 0.122 90,000.00 10,980.00
Kepala tukang L.03 OH 0.061 105,000.00 6,405.00
Mandor L.04 OH 0.061 105,000.00 6,405.00
Operator Crane L.08 OH 0.061 105,000.00 6,405.00
Pembantu Operator Crane L.09 OH 0.061 90,000.00 5,490.00
B BAHAN
C PERALATAN 277,531.81
sewa crane unit hari 0.061 3,837,406.72 234,081.81
sewa Scaffolding buah hari 1.100 39,500.00 43,450.00
D Jumlah A + B + C 323,586.81
E Overhead & Profit 15% 48,538.02
F Harga Satuan Pekerjaan (D+E) 372,124.83

Indeks Pengali Menurut Tingkat Lantai Pemasangan Komponen untuk Pelat Pracetak
Indeks kenaikan balok
Indeks kenaikan balok ereksi pelat Lantai Lantai
ereksi pelat

1.000 13 1 1.068
1.000 14 2 1.08
1.000 15 3 1.092
1.000 16 4 1.104
1.000 17 5 1.116
1.000 18 6 1.129
1.000 19 7 1.141
1.011 20 8 1.154
1.022 21 9 1.166
1.034 22 10 1.179
1.045 23 11 1.192
1.057 24 12 1.206

A.4.1.2.17 Pemindahan komponen untuk 1 Unit pelat pracetak (± 20m) 89,528.34


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 4,940.00
Pekerja L.01 OH 0.019 80,000.00 1,520.00
Tukang batu L.02 OH 0.038 90,000.00 3,420.00
B BAHAN
C PERALATAN 72,910.73
sewa crane unit hari 0.019 3,837,406.72 72,910.73
D Jumlah A + B + C 77,850.73
E Overhead & Profit 15% 11,677.61
F Harga Satuan Pekerjaan (D+E) 89,528.34

A.4.1.2.18 Pemindahan komponen untuk 1 Unit balok pracetak (± 20m) 89,528.34


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 4,940.00
Pekerja L.01 OH 0.019 80,000.00 1,520.00
Tukang batu L.02 OH 0.038 90,000.00 3,420.00
B BAHAN
C PERALATAN 72,910.73
sewa crane unit hari 0.019 3,837,406.72 72,910.73
D Jumlah A + B + C 77,850.73
E Overhead & Profit 15% 11,677.61
F Harga Satuan Pekerjaan (D+E) 89,528.34

A.4.1.2.19 Pemindahan komponen untuk 1 Unit kolom pracetak (± 20m) 89,528.34


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 4,940.00
Pekerja L.01 OH 0.019 80,000.00 1,520.00
Tukang batu L.02 OH 0.038 90,000.00 3,420.00
B BAHAN
C PERALATAN 72,910.73
sewa crane unit hari 0.019 3,837,406.72 72,910.73

104
D Jumlah A + B + C 77,850.73
E Overhead & Profit 15% 11,677.61
F Harga Satuan Pekerjaan (D+E) 89,528.34

A.4.1.2.22 Pekerjaan Grout pada 1 titik Joint Beton Pracetak 45,890.75


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 39,905.00
Pekerja L.01 OH 0.367 80,000.00 29,360.00
Tukang batu L.02 OH 0.074 90,000.00 6,660.00
Mandor L.04 OH 0.037 105,000.00 3,885.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 39,905.00
E Overhead & Profit 15% 5,985.75
F Harga Satuan Pekerjaan (D+E) 45,890.75

A.4.1.2.23 Pemasangan 1 titik Begesting Joint Pracetak 89,762.79


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 26,865.00
Pekerja L.01 OH 0.147 80,000.00 11,760.00
Tukang batu L.02 OH 0.147 90,000.00 13,230.00
Kepala Tukang L.03 OH 0.015 90,000.00 1,350.00
Mandor L.04 OH 0.005 105,000.00 525.00
B BAHAN 51,189.60
Kayu Kaso 5/7 m3 0.012 2,887,500.00 34,650.00
Papan Cor m3 0.004 2,887,500.00 11,550.00
Paku 5-7 cm kg 0.264 18,900.00 4,989.60
C PERALATAN
D Jumlah A + B + C 78,054.60
E Overhead & Profit 15% 11,708.19
F Harga Satuan Pekerjaan (D+E) 89,762.79

A.4.1.2.24 Pemasangan 1 titik Joint dengan Sling 46,615.25


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA 40,535.00
Pekerja L.01 OH 0.220 80,000.00 17,600.00
Tukang batu L.02 OH 0.022 90,000.00 1,980.00
Kepala Tukang L.03 OH 0.220 90,000.00 19,800.00
Mandor L.04 OH 0.011 105,000.00 1,155.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 40,535.00
E Overhead & Profit 15% 6,080.25
F Harga Satuan Pekerjaan (D+E) 46,615.25

105
HARGA
JUMLAH
SNI #REF! KODE SAT. KOEF BAHAN/UPAH
Rp Rp

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.19 Pemasangan 1 m2 Berapen 1 Pc : 5Pp Tebal 15 mm 39,117.02
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 20,430.00
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang batu L.02 OH 0.075 90,000.00 6,750.00
Kepala Tukang L.03 OH 0.008 105,000.00 840.00
Mandor L.04 OH 0.008 105,000.00 840.00
B Bahan 13,584.80
Portland Cement Kg 5.184 1,475.00 7,646.40
Pasir Pasang m3 0.026 228,400.00 5,938.40
C PERALATAN
D Jumlah (A+B+C) 34,014.80
E Overhead & Profit 15% 5,102.22
F Harga Satuan Pekerjaan (D+E) 39,117.02

A.4.4.2.20 Pemasangan 1 m2 Plesteran Skoning 1 Pc : 3Pp, lebar 10 mm 58,335.71


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 47,020.00
Pekerja L.01 OH 0.080 80,000.00 6,400.00
Tukang batu L.02 OH 0.400 90,000.00 36,000.00
Kepala Tukang L.03 OH 0.040 105,000.00 4,200.00
Mandor L.04 OH 0.004 105,000.00 420.00
B Bahan 3,706.70
Portland Cement Kg 0.500 1,475.00 737.50
Pasir Pasang m3 0.013 228,400.00 2,969.20
C PERALATAN
D Jumlah (A+B+C) 50,726.70
E Overhead & Profit 15% 7,609.01
F Harga Satuan Pekerjaan (D+E) 58,335.71

A.4.4.2.23 Pemasangan 1 m2 Plesteran Ciprat 1Pc : 2 Pp 49,872.51


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 35,625.00
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B Bahan 7,742.40
Portland Cement Kg 4.320 1,475.00 6,372.00
Pasir Pasang m3 0.006 228,400.00 1,370.40
C PERALATAN
D Jumlah (A+B+C) 43,367.40
E Overhead & Profit 15% 6,505.11
F Harga Satuan Pekerjaan (D+E) 49,872.51

A.4.4.2.24 Pemasangan 1 m2 Finishing Siar Pasangan Dinding Bata Merah (=20 m') 28,766.45
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 20,430.00
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang batu L.02 OH 0.075 90,000.00 6,750.00
Kepala Tukang L.03 OH 0.008 105,000.00 840.00
Mandor L.04 OH 0.008 105,000.00 840.00
B Bahan 4,584.30
Portland Cement Kg 3.108 1,475.00 4,584.30
C PERALATAN
D Jumlah (A+B+C) 25,014.30
E Overhead & Profit 15% 3,752.15
F Harga Satuan Pekerjaan (D+E) 28,766.45

A.4.4.2.25 Pemasangan 1 m2 Finishing Siar Pasangan Dinding Conblock ekspose (=8 m') 13,742.50

106
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 9,590.00
Pekerja L.01 OH 0.070 80,000.00 5,600.00
Tukang batu L.02 OH 0.035 90,000.00 3,150.00
Kepala Tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.004 105,000.00 420.00
B Bahan 2,360.00
Portland Cement Kg 1.600 1,475.00 2,360.00
C PERALATAN
D Jumlah (A+B+C) 11,950.00
E Overhead & Profit 15% 1,792.50
F Harga Satuan Pekerjaan (D+E) 13,742.50

A.4.4.2.26 Pemasangan 1 m2 Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp 60,653.65
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 40,650.00
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B Bahan 12,092.30
Portland Cement Kg 6.340 1,475.00 9,351.50
Pasir Pasang m3 0.012 228,400.00 2,740.80
C PERALATAN
D Jumlah (A+B+C) 52,742.30
E Overhead & Profit 15% 7,911.35
F Harga Satuan Pekerjaan (D+E) 60,653.65

107
HARGA
SNI #REF! KODE SAT. KOEF BAHAN/UPAH JUMLAH
Rp Rp

A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


A.4.7.1.22 Pengecatan 1 m2 Permukaan Baja Galvanis Secara Semprot Sistem 3 Lapis Cat Terakhir 135,654.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 104,450.00
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang Cat L.02 OH 0.700 90,000.00 63,000.00
Kepala Tukang L.03 OH 0.070 105,000.00 7,350.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
B Bahan 13,510.00
Cat Dasar Kg 0.300 44,100.00 13,230.00
Pengencer Liter 0.010 28,000.00 280.00
C PERALATAN
D Jumlah A + B + C 117,960.00
E Overhead & Provit 15% 17,694.00
F Harga Satuan Pekerjaan (D+E) 135,654.00

CK Boyolali
HARGA
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH JUMLAH
Rp Rp

A.6.1.1 HARGA SATUAN PEKERJAAN DISTRIBUSI JARINGAN LISTRIK


A.6.1.1.1. Pemasangan 1 buah MCB 1,359,357.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 90,000.00
Upah OH 1.000 90,000.00 90,000.00
B Bahan 1,092,050.00
Pipa listrik 5/8" btg 3.000 189,000.00 567,000.00
Kabel m' 15.000 20,400.00 306,000.00
T Dus buah 1.000 3,150.00 3,150.00
L Bow buah 2.000 3,500.00 7,000.00
Klem buah 24.000 300.00 7,200.00
MCCB (Boks MCB) buah 1.000 154,500.00 154,500.00
MCB buah 1.000 47,200.00 47,200.00
C PERALATAN
D Jumlah A + B + C 1,182,050.00
E Overhead + Profit 15% 177,307.50
F Harga Satuan Pekerjaan (D+E) 1,359,357.50

109
HARGA
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH JUMLAH
Rp Rp

A.6.2.1 HARGA SATUAN PEKERJAAN SISTEM PENCAHAYAAN


A.6.2.1.1. Pemasangan 1 Buah Titik Lampu 265,362.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 90,000.00
Upah OH 1.000 90,000.00 90,000.00
B Bahan 140,750.00
Pipa listrik 5/8" btg 3.000 11,500.00 34,500.00
Kabel m' 4.000 16,200.00 64,800.00
T Dus buah 3.000 3,150.00 9,450.00
L Bow buah 4.000 3,500.00 14,000.00
Las Dop buah 3.000 - -
Klem buah 4.000 300.00 1,200.00
Mongkok buah 1.000 - -
Saklar buah 1.000 16,800.00 16,800.00
Fitting buah 1.000 - -
C PERALATAN
D Jumlah A + B + C 230,750.00
E Overhead + Profit 15% 34,612.50
F Harga Satuan Pekerjaan (D+E) 265,362.50

110
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.1 HARGA SATUAN PEKERJAAN PERSIAPAN

1.1.a.(c) Pembuatan 1m' Pagar Sementara dari Kayu Tinggi 2 m 796,561.53


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 54,200.00
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
B BAHAN 638,462.20
Kayu Dolken diameter 8 - 10 / 400 cm Btg 1.250 26,200.00 32,750.00
Portland Semen Kg 5.000 1,475.00 7,375.00
Pasir Beton m3 0.005 230,000.00 1,150.00
Koral Beton m3 0.009 230,000.00 2,070.00
Kayu 5/7x 4m Kayu Kruing m3 0.072 8,203,100.00 590,623.20
Paku Biasa 2" - 5" Kg 0.060 18,900.00 1,134.00
Residu Liter 0.400 8,400.00 3,360.00
C PERALATAN
D Jumlah A + B + C 692,662.20
E Overhead & Profit 15% 103,899.33
F Harga Satuan Pekerjaan (D+E) 796,561.53

1.1.b.(c) Pembuatan 1 m' Pagar Sementara dari Seng Gelombang Tinggi 2 m 961,376.66
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 56,200.00
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang Kayu L.02 OH 0.400 90,000.00 36,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
B BAHAN 779,779.70
Kayu Dolken diameter 8 - 10 / 400 cm Btg 1.250 26,200.00 32,750.00
Portland Semen Kg 2.500 1,475.00 3,687.50
Seng gelombang BJLS 28 Lbr 1.200 107,100.00 128,520.00
Pasir Beton m3 0.005 230,000.00 1,150.00
Koral Beton m3 0.009 230,000.00 2,070.00
Kayu 5/7x 4m Kayu Kruing m3 0.072 8,203,100.00 590,623.20
Paku Biasa 2" - 5" Kg 0.060 18,900.00 1,134.00
Meni Besi Liter 0.450 44,100.00 19,845.00
C PERALATAN
D Jumlah A + B + C 835,979.70
E Overhead & Profit 15% 125,396.96
F Harga Satuan Pekerjaan (D+E) 961,376.66

1.1.c.(c) Membuat 1 m' Pagar Sementara dari Kawat Duri Tinggi 1.8 m 460,809.60
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 47,200.00
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang Kayu L.02 OH 0.300 90,000.00 27,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
B BAHAN 353,504.00
Kayu Dolken diameter 8 - 10 / 400 cm m' 1.000 26,200.00 26,200.00
Portland Semen Kg 2.000 1,475.00 2,950.00
Kawat duri 1.2 mm m' 25.000 12,800.00 320,000.00
Pasir Beton m3 0.005 230,000.00 1,150.00
Koral Beton m3 0.009 230,000.00 2,070.00
Paku Biasa 2" - 5" Kg 0.060 18,900.00 1,134.00
C PERALATAN
D Jumlah A + B + C 400,704.00
E Overhead & Profit 15% 60,105.60
F Harga Satuan Pekerjaan (D+E) 460,809.60

1.7.4.d.(a) Pasang 1m' Bouwplank sebagai acuan dalam pembuatan infrastruktur 69,416.76

CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.1 HARGA SATUAN PEKERJAAN PERSIAPAN

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 1,689.00
Pekerja L.01 OH 0.0120 80,000.00 960.00
Tukang Kayu L.02 OH 0.0060 90,000.00 540.00
Kepala Tukang L.03 OH 0.0006 105,000.00 63.00
Mandor L.04 OH 0.0012 105,000.00 126.00
B Bahan 58,128.00
Kaso 5/7 cm m3 0.013 2,887,500.00 37,537.50
Paku Biasa 5 dan 7 cm Kg 0.020 18,900.00 378.00
Papan 3/20 cm m3 0.007 2,887,500.00 20,212.50
C PERALATAN 545.40
Waterpass hari 0.006 90,900.00 545.40
D Jumlah A + B + C 60,362.40
E Overhead & Profit 15% 9,054.36
F Harga Satuan Pekerjaan (D+E) 69,416.76

1.1.e.(c) Pembuatan 1 m2 Kantor Sementara/ Gudang dg Lantai Plesteran, dinding setengah tembok 2,765,961.60
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 466,750.00
Pekerja L.01 OH 2.000 80,000.00 160,000.00
Tukang Kayu L.02 OH 2.000 90,000.00 180,000.00
Tukang Batu L.02 OH 1.000 90,000.00 90,000.00
Kepala Tukang L.03 OH 0.300 105,000.00 31,500.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
B Bahan 1,938,434.00
Kayu Dolken Ø 8 - 10 / 4 m m' 1.250 26,200.00 32,750.00
Kayu m3 0.180 8,203,100.00 1,476,558.00
Paku Biasa 2" - 5" Kg 0.080 18,900.00 1,512.00
Besi Strip Kg 1.100 19,500.00 21,450.00
Portland Sement Kg 35.000 1,475.00 51,625.00
Pasir pasang m3 0.150 228,400.00 34,260.00
Pasir Beton m3 0.100 230,000.00 23,000.00
Koral Beton m3 0.150 230,000.00 34,500.00
Batu bata Merah buah 30.000 750.00 22,500.00
Seng Plat Lbr 0.250 21,000.00 5,250.00
Jendela naco buah 0.200 960,000.00 192,000.00
Kaca polos m2 0.080 157,500.00 12,600.00
Kunci Tanam buah 0.150 178,500.00 26,775.00
Plywood 4 mm Lbr 0.060 60,900.00 3,654.00
C PERALATAN
D Jumlah A + B + C 2,405,184.00
E Overhead & Profit 15% 360,777.60
F Harga Satuan Pekerjaan (D+E) 2,765,961.60

1.1.f.(c) Pembersihan dan Pengupasan 1 m2 Permukaan Tanah (Striping) s.d Tanaman Ø 2cm 9,803.75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 8,525.00
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan
C PERALATAN
D Jumlah A + B + C 8,525.00
E Overhead & Profit 15% 1,278.75
F Harga Satuan Pekerjaan (D+E) 9,803.75

1.1.g.(b) Pembuatan 1m2 Jalan Sementara 103,941.60


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 34,100.00
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Mandor L.04 OH 0.020 105,000.00 2,100.00

CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.1 HARGA SATUAN PEKERJAAN PERSIAPAN

B Bahan 56,284.00
Batu Belah m3 0.150 225,000.00 33,750.00
Batu Pecah m3 0.090 225,000.00 20,250.00
Pasir Pasang m3 0.010 228,400.00 2,284.00
C PERALATAN
D Jumlah A + B + C 90,384.00
E Overhead & Profit 15% 13,557.60
F Harga Satuan Pekerjaan (D+E) 103,941.60

1.1.h.(a) Pembongkaran 1 m3 Dinding Tembok Bata 617,348.75


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 536,825.00
Pekerja L.01 OH 6.667 80,000.00 533,360.00
Mandor L.04 OH 0.033 105,000.00 3,465.00
B Bahan
C PERALATAN
D Jumlah A + B + C 536,825.00
E Overhead & Profit 15% 80,523.75
F Harga Satuan Pekerjaan (D+E) 617,348.75

Pemagaran 1 m' daerah kerja dengan seng gelombang BJLS-30, tinggi 1,8 m dengan rangka baja
1.1.2.a L,40.40.4 598,363.53
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 37,600.00
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.100 105,000.00 10,500.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
B Bahan 482,716.11
Baja L.40.40.4 kg 13.500 19,500.00 263,250.00
Kawat Seng 3mm kg 0.300 17,800.00 5,340.00
Pasangan Batu 20/50, t= 40cm Kg 0.150 570,707.40 85,606.11
Seng Gelombang BJLS 32 Lbr 1.200 107,100.00 128,520.00
C PERALATAN
D Jumlah A + B + C 520,316.11
E Overhead & Profit 15% 78,047.42
F Harga Satuan Pekerjaan (D+E) 598,363.53

1.1.2.b Pemagaran 1 m' daerah kerja dengan seng gelombang BJLS-30, tinggi 1,8 m dengan rangka Kayu 435,537.90
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 35,190.00
Pekerja L.01 OH 0.180 80,000.00 14,400.00
Tukang L.02 OH 0.100 105,000.00 10,500.00
Kepala Tukang L.03 OH 0.080 105,000.00 8,400.00
Mandor L.04 OH 0.018 105,000.00 1,890.00
B Bahan 343,538.61
Kaso 5/7 Kayu kelas II m3 0.035 2,887,500.00 101,062.50
Paku Seng kg 0.300 18,900.00 5,670.00
Paku 7 cm kg 1.200 18,900.00 22,680.00
Pasangan Batu 20/50, t= 40cm m3 0.150 570,707.40 85,606.11
Seng Gelombang BJLS 32 Lbr 1.200 107,100.00 128,520.00
C PERALATAN
D Jumlah A + B + C 378,728.61

CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.1 HARGA SATUAN PEKERJAAN PERSIAPAN

E Overhead & Profit 15% 56,809.29


F Harga Satuan Pekerjaan (D+E) 435,537.90

1.1.3.(a) Pembuatan 1 unit Direksi Keet dan Gudang 1,627,904.78


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 148,800.00
Pekerja L.01 OH 1.200 80,000.00 96,000.00
Tukang Kayu L.02 OH 0.400 90,000.00 36,000.00
Kepala Tukang L.03 OH 0.040 105,000.00 4,200.00
Mandor L.04 OH 0.120 105,000.00 12,600.00
B Bahan 1,266,769.37
Kaso 5/7 Kayu kelas II m3 0.350 481,250.00 168,437.50
Dinding Triplek 4mm lbr 1.000 60,900.00 60,900.00
Pondasi Pasangan batu m3 0.170 957,309.45 162,742.61
GRC plat tebal 4mm uk. 122x244 cm lbr 1.240 63,000.00 78,120.00
Paku kg 0.750 18,900.00 14,175.00
Asbes Gelombang lbr 0.300 87,700.00 26,310.00
Paku Asbes kg 0.100 18,900.00 1,890.00
lantai kerja beton m3 0.150 1,234,181.15 185,127.17
Pintu Double Teakwood rangka kayu m2 0.100 1,568,067.55 156,806.76
cat dinding & plafon m2 16.500 24,985.48 412,260.34
C PERALATAN
D Jumlah A + B + C 1,415,569.37
E Overhead & Profit 15% 212,335.41
F Harga Satuan Pekerjaan (D+E) 1,627,904.78

1.1.4.a.(a) Pembuatan 1 buah Papan Nama pekerjaan dengan multiflex 18mm, frame Aluminium siku dan tiang kayu 8 980,561.88
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 326,000.00
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang Kayu L.02 OH 1.000 90,000.00 90,000.00
Kepala Tukang L.03 OH 0.100 105,000.00 10,500.00
Tukang Cat dan tulis L.02 OH 1.500 90,000.00 135,000.00
Mandor L.04 OH 0.100 105,000.00 10,500.00
B Bahan 526,662.50
Multiflex 18mm, uk. 0,8m x 1,2m Lbr 0.350 189,000.00 66,150.00
Tiang Kayu 8/12 kelas II, tinggi 4m m3 0.077 2,887,500.00 222,337.50
Frame Aluminium L.30.30.3 kg 5.800 8,500.00 49,300.00
Paku Campuran 5 - 7 cm kg 1.250 18,900.00 23,625.00
Cat Kayu kg 2.500 66,100.00 165,250.00
C PERALATAN
D Jumlah A + B + C 852,662.50
E Overhead & Profit 15% 127,899.38
F Harga Satuan Pekerjaan (D+E) 980,561.88

1.1.4.b.(a) Pembuatan 1 buah Papan Nama pekerjaan dengan multiflex 10mm, frame Aluminium siku dan tiang kayu 5 416,320.13
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 145,875.00
Pekerja L.01 OH 0.750 80,000.00 60,000.00
Tukang Kayu L.02 OH 0.750 90,000.00 67,500.00
Kepala Tukang L.03 OH 0.100 105,000.00 10,500.00
Mandor L.04 OH 0.075 105,000.00 7,875.00
B Bahan 216,142.50
Multiflex 10mm, 0,6m x 0,8m Lbr 0.180 131,200.00 23,616.00
Tiang Kayu 5/7 kelas II, tinggi 3m m3 0.021 2,887,500.00 60,637.50
Frame Aluminium L.10.1 kg 0.100 5,700.00 570.00
Banner Plastik 0,6 x 0,8 m2 m2 0.480 17,800.00 8,544.00
Paku Campuran 5 - 7 cm kg 1.250 18,900.00 23,625.00

CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.1 HARGA SATUAN PEKERJAAN PERSIAPAN

Cat Kayu kg 1.500 66,100.00 99,150.00


C PERALATAN
D Jumlah A + B + C 362,017.50
E Overhead & Profit 15% 54,302.63
F Harga Satuan Pekerjaan (D+E) 416,320.13

2.1.2.a.5.c Pembongkaran 1m3 Pasangan batu dengan alat 38,120.83


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 18,100.00
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
B Bahan
C PERALATAN 15,048.55
Jack Hammer 5KW + Genset 12HP L.04 OH 0.050 300,970.99 15,048.55
D Jumlah A + B + C 33,148.55
E Overhead & Profit 15% 4,972.28
F Harga Satuan Pekerjaan (D+E) 38,120.83

2.1.4.b Pembongkaran 1m3 Pasangan bata merah dengan alat 20,803.00


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 13,575.00
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B Bahan
C PERALATAN 4,514.56
Jack Hammer 5KW + Genset 12HP L.04 OH 0.015 300,970.99 4,514.56
D Jumlah A + B + C 18,089.56
E Overhead & Profit 15% 2,713.43
F Harga Satuan Pekerjaan (D+E) 20,803.00

2.2.10.a Pembongkaran 1m3 beton dengan alat 38,120.83


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 18,100.00
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
B Bahan
C PERALATAN 15,048.55
Jack Hammer 5KW + Genset 12HP L.04 OH 0.050 300,970.99 15,048.55
D Jumlah A + B + C 33,148.55
E Overhead & Profit 15% 4,972.28
F Harga Satuan Pekerjaan (D+E) 38,120.83

CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.3.1 HARGA SATUAN PEKERJAAN SUMUR AIR TANAH

1.3.1.1.1.a.(a) Pengeboran Sumur Air Tanah Dangkal Ø1" - 1,25" pada tanah biasa 20,671.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 17,975.00
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Juru Bor L.14 OH 0.050 88,000.00 4,400.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor dan mata bor Ø1,25" Hari 0.050 -
D Jumlah A + B + C 17,975.00
E Overhead & Profit 15% 2,696.25
F Harga Satuan Pekerjaan (D+E) 20,671.25

1.3.1.1.1.b.(a) Pengeboran Sumur Air Tanah Dangkal Ø1" - 1,25" pada tanah keras / cadas 81,859.88
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 71,182.50
Pekerja L.01 OH 0.750 80,000.00 60,000.00
Juru Bor L.14 OH 0.250 - -
Mandor L.04 OH 0.107 105,000.00 11,182.50
B BAHAN -
C PERALATAN -
Stang bor, batang bor dan mata bor Ø1,25" Hari 0.250 -
D Jumlah A + B + C 71,182.50
E Overhead & Profit 15% 10,677.38
F Harga Satuan Pekerjaan (D+E) 81,859.88

1.3.1.1.1.c.(a) Pengeboran Sumur Air Tanah Dangkal Ø1" - 1,25" pada tanah berbatu lunak 124,890.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 108,600.00
Pekerja L.01 OH 1.200 80,000.00 96,000.00
Juru Bor L.14 OH 0.400 - -
Mandor L.04 OH 0.120 105,000.00 12,600.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor dan mata bor Ø1,25" Hari 0.400 -
D Jumlah A + B + C 108,600.00
E Overhead & Profit 15% 16,290.00
F Harga Satuan Pekerjaan (D+E) 124,890.00

1.3.1.1.1.d.(a) Pengeboran Sumur Air Tanah Dangkal Ø1" - 1,25" pada tanah berbatu keras 312,225.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 271,500.00
Pekerja L.01 OH 3.000 80,000.00 240,000.00
Juru Bor L.14 OH 1.000 - -
Mandor L.04 OH 0.300 105,000.00 31,500.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor dan mata bor Ø1,25" Hari 1.000 -
D Jumlah A + B + C 271,500.00
E Overhead & Profit 15% 40,725.00
F Harga Satuan Pekerjaan (D+E) 312,225.00

1.3.1.1.1.e.(a) Pemasangan 1m' Sumur Bor Air Tanah Dangkal Ø1" - 1,25" 312,225.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 271,500.00
Pekerja L.01 OH 3.000 80,000.00 240,000.00
Juru Bor L.14 OH 1.000 - -
Mandor L.04 OH 0.300 105,000.00 31,500.00
B BAHAN -

CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.3.1 HARGA SATUAN PEKERJAAN SUMUR AIR TANAH

C PERALATAN -
Stang bor, batang bor dan mata bor Ø1,25" Hari 1.000 -
D Jumlah A + B + C 271,500.00
E Overhead & Profit 15% 40,725.00
F Harga Satuan Pekerjaan (D+E) 312,225.00

1.3.1.1.2.a.(a) Pengeboran Sumur Air Tanah Dangkal Ø2" pada tanah biasa 24,978.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 21,720.00
Pekerja L.01 OH 0.240 80,000.00 19,200.00
Juru Bor L.14 OH 0.080 - -
Mandor L.04 OH 0.024 105,000.00 2,520.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor Ø1,25" Hari 0.080 -
mata bor Ø2" Hari 0.080 -
D Jumlah A + B + C 21,720.00
E Overhead & Profit 15% 3,258.00
F Harga Satuan Pekerjaan (D+E) 24,978.00

1.3.1.1.2.b.(a) Pengeboran Sumur Air Tanah Dangkal Ø2" pada tanah Keras / Cadas 124,890.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 108,600.00
Pekerja L.01 OH 1.200 80,000.00 96,000.00
Juru Bor L.14 OH 0.400 - -
Mandor L.04 OH 0.120 105,000.00 12,600.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor Ø1,25" Hari 0.400 -
mata bor Ø4" Hari 0.400 -
D Jumlah A + B + C 108,600.00
E Overhead & Profit 15% 16,290.00
F Harga Satuan Pekerjaan (D+E) 124,890.00

1.3.1.1.2.c.(a) Pengeboran Sumur Air Tanah Dangkal Ø2" pada tanah berbatu lunak 199,824.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 173,760.00
Pekerja L.01 OH 1.920 80,000.00 153,600.00
Juru Bor L.14 OH 0.640 - -
Mandor L.04 OH 0.192 105,000.00 20,160.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor Ø1,25" Hari 0.640 -
mata bor Ø4" Hari 0.640 -
D Jumlah A + B + C 173,760.00
E Overhead & Profit 15% 26,064.00
F Harga Satuan Pekerjaan (D+E) 199,824.00

1.3.1.1.2.d.(a) Pengeboran Sumur Air Tanah Dangkal Ø2" pada tanah berbatu Keras 499,560.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 434,400.00
Pekerja L.01 OH 4.800 80,000.00 384,000.00
Juru Bor L.14 OH 1.600 - -
Mandor L.04 OH 0.480 105,000.00 50,400.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor Ø1,25" Hari 1.600 -
mata bor Ø4" Hari 1.600 -
D Jumlah A + B + C 434,400.00
E Overhead & Profit 15% 65,160.00

CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.3.1 HARGA SATUAN PEKERJAAN SUMUR AIR TANAH

F Harga Satuan Pekerjaan (D+E) 499,560.00

1.3.1.1.2.e.(a) Pemasangan 1m' Sumur Air Tanah Dangkal GIP Ø2" 15,611.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 13,575.00
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Juru Bor L.14 OH 0.050 - -
Mandor L.04 OH 0.015 105,000.00 1,575.00
B BAHAN -
Pipa GI Medium Ø2" m' 1.000 -
Pipa GI Medium Ø2" - Peloksok bh 0.167 -
C PERALATAN -
Stang bor Ø1,25" Hari 0.050 -
D Jumlah A + B + C 13,575.00
E Overhead & Profit 15% 2,036.25
F Harga Satuan Pekerjaan (D+E) 15,611.25

1.3.1.1.3.a.(a) Pengeboran Sumur Air Tanah Dangkal Ø4" pada tanah biasa 49,956.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 43,440.00
Pekerja L.01 OH 0.480 80,000.00 38,400.00
Juru Bor L.14 OH 0.160 - -
Mandor L.04 OH 0.048 105,000.00 5,040.00
B BAHAN -
C PERALATAN -
Stang bor , batang bor Ø1,25" Hari 0.160 -
Mata Bor 4" Hari 0.160 -
D Jumlah A + B + C 43,440.00
E Overhead & Profit 15% 6,516.00
F Harga Satuan Pekerjaan (D+E) 49,956.00

1.3.1.1.3.b.(a) Pengeboran Sumur Air Tanah Dangkal Ø4" pada tanah Keras / Cadas 249,780.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 217,200.00
Pekerja L.01 OH 2.400 80,000.00 192,000.00
Juru Bor L.14 OH 0.800 - -
Mandor L.04 OH 0.240 105,000.00 25,200.00
B BAHAN -
C PERALATAN -
Stang bor , batang bor Ø1,25" Hari 0.800 -
Mata Bor 4" Hari 0.800 -
D Jumlah A + B + C 217,200.00
E Overhead & Profit 15% 32,580.00
F Harga Satuan Pekerjaan (D+E) 249,780.00

1.3.1.1.3.d.(a) Pengeboran Sumur Air Tanah Dangkal Ø4" pada tanah batuan keras 999,120.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 868,800.00
Pekerja L.01 OH 9.600 80,000.00 768,000.00
Juru Bor L.14 OH 3.200 - -
Mandor L.04 OH 0.960 105,000.00 100,800.00
B BAHAN -
C PERALATAN -

CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.3.1 HARGA SATUAN PEKERJAAN SUMUR AIR TANAH

Stang bor , batang bor Ø1,25" Hari 3.200 -


Mata Bor 4" Hari 3.200 -
D Jumlah A + B + C 868,800.00
E Overhead & Profit 15% 130,320.00
F Harga Satuan Pekerjaan (D+E) 999,120.00

1.3.1.1.3.e.(a) Pemasangan 1m' Pipa Casing GIP Ø4" 39,028.13


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 33,937.50
Pekerja L.01 OH 0.375 80,000.00 30,000.00
Juru Bor L.14 OH 0.125 - -
Mandor L.04 OH 0.038 105,000.00 3,937.50
B BAHAN -
Pipa GI Medium Ø4" m' 1.000 -
Pipa GI Medium Ø4" - Peloksok bh 0.167 -
C PERALATAN -
Stang bor Ø1,25" + reducer Hari 0.125 -
D Jumlah A + B + C 33,937.50
E Overhead & Profit 15% 5,090.63
F Harga Satuan Pekerjaan (D+E) 39,028.13

1.3.1.1.4.a.(a) Pengeboran Sumur Air Tanah Dangkal Ø6" pada tanah biasa 74,934.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 65,160.00
Pekerja L.01 OH 0.720 80,000.00 57,600.00
Juru Bor L.14 OH 0.240 - -
Mandor L.04 OH 0.072 105,000.00 7,560.00
B BAHAN -
C PERALATAN -
Stang bor , batang bor Ø1,25" Hari 0.240 -
Mata Bor 6" Hari 0.240 -
D Jumlah A + B + C 65,160.00
E Overhead & Profit 15% 9,774.00
F Harga Satuan Pekerjaan (D+E) 74,934.00

1.3.1.1.4.b.(a) Pengeboran Sumur Air Tanah Dangkal Ø6" pada tanah keras / cadas 187,335.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 162,900.00
Pekerja L.01 OH 1.800 80,000.00 144,000.00
Juru Bor L.14 OH 0.600 - -
Mandor L.04 OH 0.180 105,000.00 18,900.00
B BAHAN -
C PERALATAN -
Stang bor , batang bor Ø1,25" Hari 0.600 -
Mata Bor 6" Hari 0.600 -
D Jumlah A + B + C 162,900.00
E Overhead & Profit 15% 24,435.00
F Harga Satuan Pekerjaan (D+E) 187,335.00

1.3.1.1.4.c.(a) Pengeboran Sumur Air Tanah Dangkal Ø6" pada tanah batuan lunak 299,736.00

CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.3.1 HARGA SATUAN PEKERJAAN SUMUR AIR TANAH

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 260,640.00
Pekerja L.01 OH 2.880 80,000.00 230,400.00
Juru Bor L.14 OH 0.960 - -
Mandor L.04 OH 0.288 105,000.00 30,240.00
B BAHAN -
C PERALATAN -
Stang bor , batang bor Ø1,25" Hari 0.960 -
Mata Bor 6" Hari 0.960 -
D Jumlah A + B + C 260,640.00
E Overhead & Profit 15% 39,096.00
F Harga Satuan Pekerjaan (D+E) 299,736.00

1.3.1.1.4.d.(a) Pengeboran Sumur Air Tanah Dangkal Ø6" pada tanah batuan keras 374,670.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 325,800.00
Pekerja L.01 OH 3.600 80,000.00 288,000.00
Juru Bor L.14 OH 1.200 - -
Mandor L.04 OH 0.360 105,000.00 37,800.00
B BAHAN -
C PERALATAN -
Stang bor , batang bor Ø1,25" Hari 1.200 -
Mata Bor 6" Hari 1.200 -
D Jumlah A + B + C 325,800.00
E Overhead & Profit 15% 48,870.00
F Harga Satuan Pekerjaan (D+E) 374,670.00

1.3.1.1.3.e.(a) Pemasangan 1m' Pipa Casing GIP Ø6" 78,056.25


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 67,875.00
Pekerja L.01 OH 0.750 80,000.00 60,000.00
Juru Bor L.14 OH 0.250 - -
Mandor L.04 OH 0.075 105,000.00 7,875.00
B BAHAN -
Pipa GI Medium Ø6" m' 1.000 -
Pipa GI Medium Ø6" - Peloksok bh 0.167 -
C PERALATAN -
Stang bor Ø1,25" + reducer Hari 0.250 -
D Jumlah A + B + C 67,875.00
E Overhead & Profit 15% 10,181.25
F Harga Satuan Pekerjaan (D+E) 78,056.25

1.4.1.a.(a) Pengadaan dan Pemasangan Reducer 23,477.25


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 20,415.00
Pekerja L.01 OH 0.225 80,000.00 18,000.00
Juru Bor L.14 OH 0.075 - -
Mandor L.04 OH 0.023 105,000.00 2,415.00
B BAHAN -

CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.3.1 HARGA SATUAN PEKERJAAN SUMUR AIR TANAH

Pipa GI Medium Reducer Ø1" ls 1.000 -


Pipa GI Medium Ø2" - Peloksok btg 1.000 -
C PERALATAN -
Stang bor Ø1,25" + reducer Hari 1.000 -
D Jumlah A + B + C 20,415.00
E Overhead & Profit 15% 3,062.25
F Harga Satuan Pekerjaan (D+E) 23,477.25

1.4.1.b.(a) Pengadaan dan Pemasangan 1 set Pompa Jet Pump dan Perpipaan 23,477.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 20,415.00
Pekerja L.01 OH 0.225 80,000.00 18,000.00
Juru Bor L.14 OH 0.075 - -
Mandor L.04 OH 0.023 105,000.00 2,415.00
B BAHAN -
Pipa GI Medium Class Ø1" btg 7.000 -
Jet Pump 500 watt hari 1.000 -
Aksesoris ls 1.000 -
C PERALATAN -
Stang bor Ø1,25" + reducer Hari 1.000 -
D Jumlah A + B + C 20,415.00
E Overhead & Profit 15% 3,062.25
F Harga Satuan Pekerjaan (D+E) 23,477.25

CK Boyolali
HARGA JUMLAH
SNI #REF! KODE SAT. KOEF BAHAN/UPAH
Rp Rp

1.6 HARGA SATUAN PEKERJAAN BATU DAN BATU CANDI


1.5.1.b.(a) Pemasangan 1 m3 Batu Kosong (aanstamping) 450,012.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 105,690.00
Pekerja L.01 OH 0.780 80,000.00 62,400.00
Tukang Batu L.02 OH 0.390 90,000.00 35,100.00
Kepala Tukang L.03 OH 0.039 105,000.00 4,095.00
Mandor L.04 OH 0.039 105,000.00 4,095.00
B BAHAN 285,625.00
Batu Belah m3 1.250 225,000.00 281,250.00
Pasir Urug m3 0.025 175,000.00 4,375.00
C PERALATAN
D Jumlah A + B + C 391,315.00
E Overhead & Profit 15% 58,697.25
F Harga Satuan Pekerjaan (D+E) 450,012.25

1.6.1.a.(a) Pemasangan 1 m2 Pasangan Batu Muka 127,207.25


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 33,780.00
Pekerja L.01 OH 0.240 80,000.00 19,200.00
Tukang Batu L.02 OH 0.120 90,000.00 10,800.00
Kepala Tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.024 105,000.00 2,520.00
B BAHAN 76,835.00
Batu Muka m2 1.250 51,000.00 63,750.00
Pasir Pasang m3 0.025 228,400.00 5,710.00
Portland Cement kg 5.000 1,475.00 7,375.00
C PERALATAN
D Jumlah A + B + C 110,615.00
E Overhead & Profit 15% 16,592.25
F Harga Satuan Pekerjaan (D+E) 127,207.25

1.6.1.b.(a) Pemasangan 1 m2 Pasangan Batu Candi 170,228.75


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 33,780.00
Pekerja L.01 OH 0.240 80,000.00 19,200.00
Tukang Batu L.02 OH 0.120 90,000.00 10,800.00
Kepala Tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.024 105,000.00 2,520.00
B BAHAN 114,245.00
Batu Candi m2 1.200 84,300.00 101,160.00
Pasir Pasang m3 0.025 228,400.00 5,710.00
Portland Cement kg 5.000 1,475.00 7,375.00
C PERALATAN
D Jumlah A + B + C 148,025.00
E Overhead & Profit 15% 22,203.75
F Harga Satuan Pekerjaan (D+E) 170,228.75

1.6.3.(a) Pemasangan 1 m2 Pasangan Pipa Suling-suling 62,554.25


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 905.00
Pekerja L.01 OH 0.010 80,000.00 800.00
Mandor L.04 OH 0.001 105,000.00 105.00
B BAHAN 53,490.00
Pipa PVC Ø1" s.d Ø2" m' 1.050 45,000.00 47,250.00
Ijuk kg 0.100 21,000.00 2,100.00
Kerikil m3 0.018 230,000.00 4,140.00
C PERALATAN
D Jumlah A + B + C 54,395.00
E Overhead & Profit 15% 8,159.25
F Harga Satuan Pekerjaan (D+E) 62,554.25

122
HARGA BAHAN/UPAH JUMLAH
SNI #REF! KODE SAT. KOEF
Rp Rp
2.1.3.(a) HARGA SATUAN PASANGAN BATA MERAH
2.1.3.1.b.(c) Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 bata Camp. 1SP: 2PP 297,487.18
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 71,250.00
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
B Bahan 187,434.50
Bata Merah Buah 140.000 750.00 105,000.00
Portland Semen (PC) Kg 43.500 1,475.00 64,162.50
Pasir Pasang (PP) m3 0.080 228,400.00 18,272.00
C PERALATAN
D Jumlah A + B + C 258,684.50
E Overhead & Profit 15% 38,802.68
F Harga Satuan Pekerjaan (D+E) 297,487.18
Overhead & Profit
2.1.3.1.c.(a) Pasangan Bata Merah 1m3 Pondasi Mortar tipe M, fc' = 17,2 Mpa (setara 1 PC : 2 PP) dengan molen, untuk beda tinggi > 0 s. 949,047.47
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 115,175.00
Pekerja L.01 OH 0.850 80,000.00 68,000.00
Tukang Batu L.02 OH 0.425 90,000.00 38,250.00
Mandor L.04 OH 0.085 105,000.00 8,925.00
B Bahan 708,497.00
Bata Merah Buah 500.000 750.00 375,000.00
Portland Semen (PC) Kg 175.000 1,475.00 258,125.00
Pasir Pasang (PP) m3 0.330 228,400.00 75,372.00
C PERALATAN 1,586.67
Molen Kapasitas 0,3 m3 hari 0.0238 66,666.67 1,586.67
D Jumlah A + B + C 825,258.67
E Overhead & Profit 15% 123,788.80
F Harga Satuan Pekerjaan (D+E) 949,047.47
Overhead & Profit
2.1.3.2.b.(c) Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP 282,481.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 71,250.00
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
B Bahan 174,385.65
Bata Merah Buah 140.000 750.00 105,000.00
Portland Semen (PC) Kg 32.950 1,475.00 48,601.25
Pasir Pasang (PP) m3 0.091 228,400.00 20,784.40
C PERALATAN
D Jumlah A + B + C 245,635.65
E Overhead & Profit 15% 36,845.35
F Harga Satuan Pekerjaan (D+E) 282,481.00
Overhead & Profit
Pemasangan Bata Merah 1 m3 Pondasi dengan Mortar tipe S, fc' = 12,5 Mpa (setara 1 PC : 3 PP) dengan molen, untuk beda
2.1.3.2.c.(a) tinggi > 0 s.d. 1 m' 881,361.92
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 115,175.00
Pekerja L.01 OH 0.850 80,000.00 68,000.00
Tukang Batu L.02 OH 0.425 90,000.00 38,250.00
Mandor L.04 OH 0.085 105,000.00 8,925.00
B Bahan 649,640.00
Bata Merah Buah 500.000 750.00 375,000.00
Portland Semen (PC) Kg 132.000 1,475.00 194,700.00
Pasir Pasang (PP) m3 0.350 228,400.00 79,940.00
C PERALATAN 1,586.67
Molen Kapasitas 0,3 m3 hari 0.0238 66,666.67 1,586.67
D Jumlah A + B + C 766,401.67
E Overhead & Profit 15% 114,960.25
F Harga Satuan Pekerjaan (D+E) 881,361.92

2.1.3.3.b.(c) Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP 272,150.32
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

123
A Tenaga 71,250.00
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
B Bahan 165,402.45
Bata Merah Buah 140.000 750.00 105,000.00
Portland Semen (PC) Kg 26.550 1,475.00 39,161.25
Pasir Pasang (PP) m3 0.093 228,400.00 21,241.20
C PERALATAN
D Jumlah A + B + C 236,652.45
E Overhead & Profit 15% 35,497.87
F Harga Satuan Pekerjaan (D+E) 272,150.32
Overhead & Profit
2.1.3.3.c.(a) Mortar tipe N, fc' = 5,2 Mpa (setara 1 PC : 4 PP) dengan molen, untuk beda tinggi > 0 s.d. 1 m' 843,360.74
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 115,175.00
Pekerja L.01 OH 0.850 80,000.00 68,000.00
Tukang Batu L.02 OH 0.425 90,000.00 38,250.00
Mandor L.04 OH 0.085 105,000.00 8,925.00
B Bahan 616,595.50
Bata Merah Buah 500.000 750.00 375,000.00
Portland Semen (PC) Kg 106.500 1,475.00 157,087.50
Pasir Pasang (PP) m3 0.370 228,400.00 84,508.00
C PERALATAN 1,586.67
Molen Kapasitas 0,3 m3 hari 0.0238 66,666.67 1,586.67
D Jumlah A + B + C 733,357.17
E Overhead & Profit 15% 110,003.58
F Harga Satuan Pekerjaan (D+E) 843,360.74

2.1.3.3.b.(c) Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP 267,135.57
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 71,250.00
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
B Bahan 161,041.80
Bata Merah Buah 140.000 750.00 105,000.00
Portland Semen (PC) Kg 22.200 1,475.00 32,745.00
Pasir Pasang (PP) m3 0.102 228,400.00 23,296.80
C PERALATAN
D Jumlah A + B + C 232,291.80
E Overhead & Profit 15% 34,843.77
F Harga Satuan Pekerjaan (D+E) 267,135.57
Overhead & Profit
Pemasangan Bata Merah 1 m3 dengan Mortar tipe O, fc' = 2,4 Mpa (setara 1 PC : 5 PP) dengan molen, untuk beda tinggi > 0
2.1.3.4.b.(a) 824,182.77
s.d. 1 m'
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 115,175.00
Pekerja L.01 OH 0.850 80,000.00 68,000.00
Tukang Batu L.02 OH 0.425 90,000.00 38,250.00
Mandor L.04 OH 0.085 105,000.00 8,925.00
B Bahan 599,919.00
Bata Merah Buah 500.000 750.00 375,000.00
Portland Semen (PC) Kg 89.000 1,475.00 131,275.00
Pasir Pasang (PP) m3 0.410 228,400.00 93,644.00
C PERALATAN 1,586.67
Molen Kapasitas 0,3 m3 hari 0.0238 66,666.67 1,586.67
D Jumlah A + B + C 716,680.67
E Overhead & Profit 15% 107,502.10
F Harga Satuan Pekerjaan (D+E) 824,182.77

2.1.3.5.b.(a) Pemasangan bata merah 1 m3 dengan Mortar campuran 1 PC : 6 PP dengan molen, untuk beda tinggi > 0 s.d. 1 m' 821,448.07
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 115,175.00
Pekerja L.01 OH 0.850 80,000.00 68,000.00
Tukang Batu L.02 OH 0.425 90,000.00 38,250.00
Mandor L.04 OH 0.085 105,000.00 8,925.00
B Bahan 597,541.00
Bata Merah Buah 500.000 750.00 375,000.00
Portland Semen (PC) Kg 75.000 1,475.00 110,625.00
Pasir Pasang (PP) m3 0.490 228,400.00 111,916.00
C PERALATAN 1,586.67

124
Molen Kapasitas 0,3 m3 hari 0.0238 66,666.67 1,586.67
D Jumlah A + B + C 714,302.67
E Overhead & Profit 15% 107,145.40
F Harga Satuan Pekerjaan (D+E) 821,448.07

2.1.4.a.(a) Bongkar 1 m3 Pasangan Bata Merah 35,375.90


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 27,150.00
Pekerja 0 OH 0.300 80,000.00 24,000.00
Mandor 0 OH 0.030 105,000.00 3,150.00
B Bahan
C PERALATAN 3,611.65
Palu / Godam (baja keras) buah 0.0020 300,970.99 601.94
Pahat beton (baja keras) buah 0.0030 300,970.99 902.91
Linggis (baja keras) buah 0.0070 300,970.99 2,106.80
D Jumlah A + B + C 30,761.65
E Overhead & Profit 15% 4,614.25
F Harga Satuan Pekerjaan (D+E) 35,375.90

2.1.4.b.(a) Bongkar 1 m3 Pasangan Bata Merah dengan Jack Hammer 20,803.00


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 13,575.00
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B Bahan
C PERALATAN 4,514.56
Jack hammer buah 0.0150 300,970.99 4,514.56
D Jumlah A + B + C 18,089.56
E Overhead & Profit 15% 2,713.43
F Harga Satuan Pekerjaan (D+E) 20,803.00

125
HARGA
BAHAN/UPAH JUMLAH
SNI #REF! KODE SAT. KOEF
Rp Rp
3.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM
3.1.1.(c) Pengerjaan 1 kg Pekerjaan Perakitan Baja Profil 1,087,666.10
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 17,630.00
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang Besi L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.001 105,000.00 105.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan
C PERALATAN 928,166.61
sewa alat crane jam 0.800 1,160,208.27 928,166.61
D Jumlah A + B + C 945,796.61
E Overhead & Profit 15% 141,869.49
F Harga Satuan Pekerjaan (D+E) 1,087,666.10

3.1.2.(c) Pembuatan 1 m2 Pintu Besi Plat Baja tebal 2 mm rangkap, rangka baja Siku 1,298,407.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 194,985.00
Pekerja L.01 OH 1.050 80,000.00 84,000.00
Tukang Besi L.02 OH 1.050 90,000.00 94,500.00
Kepala Tukang L.03 OH 0.105 105,000.00 11,025.00
Mandor L.04 OH 0.052 105,000.00 5,460.00
B Bahan 934,065.00
Besi Siku L.30.30.3 Kg 15.000 19,500.00 292,500.00
Besi Plat Baja Kg 32.800 19,500.00 639,600.00
Kawat Las Kg 0.050 39,300.00 1,965.00
C PERALATAN
D Jumlah A + B + C 1,129,050.00
E Overhead & Profit 15% 169,357.50
F Harga Satuan Pekerjaan (D+E) 1,298,407.50

3.1.1.(c) Pengerjaan 1 m Pengelasan dengan Las Listrik 26,224.50


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 5,420.00
Pekerja L.01 OH 0.040 80,000.00 3,200.00
Tukang Besi L.02 OH 0.020 90,000.00 1,800.00
Kepala Tukang L.03 OH 0.002 105,000.00 210.00
Mandor L.04 OH 0.002 105,000.00 210.00
B Bahan 15,720.00
Kawat Las kg 0.400 39,300.00 15,720.00
C PERALATAN 1,663.91
Sewa Alat jam 0.170 9,787.71 1,663.91
D Jumlah A + B + C 22,803.91
E Overhead & Profit 15% 3,420.59
F Harga Satuan Pekerjaan (D+E) 26,224.50

3.1.2.(c) Pembuatan 1m2 Rangka Jendela Besi Pipa Persegi 288,227.95


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 120,685.00
Pekerja L.01 OH 0.650 80,000.00 52,000.00
Tukang Besi L.02 OH 0.650 90,000.00 58,500.00
Kepala Tukang L.03 OH 0.065 105,000.00 6,825.00
Mandor L.04 OH 0.032 105,000.00 3,360.00
B Bahan 129,948.00
Besi scuare tube m 4.760 27,300.00 129,948.00
Besi Lis Kaca (1 x 1) m 4.522 19,500.00 88,179.00
Pengelasan kg 20.000 2,622.45 52,449.00
C PERALATAN
D Jumlah A + B + C 250,633.00
E Overhead & Profit 15% 37,594.95
F Harga Satuan Pekerjaan (D+E) 288,227.95

126
HARGA
No. SNI KODE KOEF SAT. #VALUE! BAHAN/UPAH
Rp
HARGA SATUAN PEKERJAAN PINTU DAN JENDELA ALUMUNIUM
HITUNG PJ1 1.000 Unit Pemasangan Pintu & Jendela Kaca Tempered 12 mm ( PU1 ) 24,348,569.24
A TENAGA 780,800.00
L.01 4.000 OH Pekerja 80,000.00 320,000.00
L.02 4.000 OH Tukang Besi 90,000.00 360,000.00
L.03 0.800 OH Kepala Tukang 105,000.00 84,000.00
L.04 0.160 OH Mandor 105,000.00 16,800.00
B BAHAN 20,391,868.90
3.969 m2 Pintu Kaca Tempered 12 mm 1,039,500.00 4,125,775.50
16.433 m2 Jendela Kaca Bening 12 mm 606,300.00 9,963,024.75
2.000 set Floor Hinge Dekson FH 84 SSS 918,700.00 1,837,400.00
2.000 Bh Patch Fitting Dekson PT 20 PSS 834,700.00 1,669,400.00
2.000 set Pull Handle 354,900.00 709,800.00
25.260 Tube Sealant 33,600.00 848,736.00
0.300 Ls Finishing Kaca Tempered 60% ( Total Harga Kaca ) 4,125,775.50 1,237,732.65
C PERALATAN
D Jumlah A + B + C 21,172,668.90
E Overhead & Profit 15% 3,175,900.34
F Harga Satuan Pekerjaan (D+E) 24,348,569.24

HITUNG P1 1.000 Unit Pemasangan Kusen dan Pintu Kaca Rangka Alumunium ( P1 ) 2,553,492.61
A TENAGA 277,517.19
L.01 0.513 OH Pekerja 80,000.00 41,042.00
L.02 2.065 OH Tukang Besi 90,000.00 185,861.25
L.03 0.338 OH Kepala Tukang 105,000.00 35,492.63
L.04 0.144 OH Mandor 105,000.00 15,121.31
B BAHAN 1,942,911.17
5.261 m' Profil open back 60,100.00 316,156.05
2.158 m' Profil tiang engsel (belakang) 102,700.00 221,600.93
2.158 m' Profil tiang swing(depan) 96,300.00 207,791.33
1.701 m' Profil ambang atas + tutup 77,300.00 131,487.30
0.851 m' Profil ambang bawah + tutup 114,800.00 97,637.40
5.261 m' Profil stoper pintu 22,100.00 116,257.05
5.261 m' Karet tatapan 3,400.00 17,885.70
1.357 m2 Kaca Bening 5 mm 157,500.00 213,664.50
1.000 set Handle Pintu 420,000.00 420,000.00
3.000 Bh Engsel Pintu 4" 54,600.00 163,800.00
10.000 buah Skrup Fixer 475.00 4,750.00
0.789 Tube Sealant Kusen + kaca 33,600.00 26,512.92
0.440 m' Profil Spigot 12,200.00 5,368.00
2.100 m' Bulu Moher 4,000.00 8,400.00
C PERALATAN
D Jumlah A + B + C 2,220,428.36
E Overhead & Profit 15% 333,064.25
F Harga Satuan Pekerjaan (D+E) 2,553,492.61

HITUNG J1 1.000 Unit Pemasangan Kusen dan Jendela Kaca Rangka Alumunium ( J1 ) 1,464,732.99
A TENAGA 237,233.97
L.01 0.663 OH Pekerja 80,000.00 53,075.44
L.02 1.663 OH Tukang Besi 90,000.00 149,709.87
L.03 0.295 OH Kepala Tukang 105,000.00 30,985.54
L.04 0.033 OH Mandor 105,000.00 3,463.12
B BAHAN 1,036,446.89
3.801 m' Profil open back 60,100.00 228,440.10
3.612 m' Rangka casement 3 profil 53,600.00 193,603.20
3.612 m' Karet tatapan 3,400.00 12,280.80
0.515 m2 Kaca Bening 5 mm 157,500.00 81,033.75
2.000 Set Cesement 12" 229,900.00 459,800.00
1.000 Bh Rambuncis 31,500.00 31,500.00
8.000 buah Skrup Fixer 475.00 3,800.00
0.570 Tube Sealant Kusen + Kaca 33,600.00 19,157.04
0.560 m' Profil Spigot 12,200.00 6,832.00
C PERALATAN
D Jumlah A + B + C 1,273,680.86
E Overhead & Profit 15% 191,052.13
F Harga Satuan Pekerjaan (D+E) 1,464,732.99

CK Boyolali
HITUNG J2 1.000 Unit Pemasangan Kusen dan Jendela Kaca Mati Rangka Alumunium ( J2) 636,320.83
A TENAGA 82,751.40
L.01 0.453 OH Pekerja 80,000.00 36,264.48
L.02 0.453 OH Tukang Besi 90,000.00 40,797.54
L.03 0.017 OH Kepala Tukang 105,000.00 1,831.73
L.04 0.037 OH Mandor 105,000.00 3,857.65
B BAHAN 470,571.06
3.990 m' Profil M 70,300.00 280,497.00
1.281 m' Profil tutup M 34,000.00 43,554.00
0.747 m2 Kaca Bening 5 mm 157,500.00 117,730.46
8.000 buah Skrup Fixer 475.00 3,800.00
0.599 Tube Sealant Kusen + Kaca 33,600.00 20,109.60
0.400 m' Profil Spigot 12,200.00 4,880.00
C PERALATAN
D Jumlah A + B + C 553,322.46
E Overhead & Profit 15% 82,998.37
F Harga Satuan Pekerjaan (D+E) 636,320.83

CK Boyolali
HARGA JUMLAH
No. SNI KODE KOEF SAT. #REF! BAHAN/UPAH
Rp Rp
HITUNG HARGA SATUAN PEKERJAAN PARTISI DAN FURNITURE
HITUNG PT 1.000 M2 Pemasangan Dinding Partisi Rangkap Gypsumboard 9mm Rangka Metal Stud 159,092.84
A TENAGA 50,600.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.200 OH Tukang Kayu 90,000.00 18,000.00
L.03 0.060 OH Kepala Tukang 105,000.00 6,300.00
L.04 0.060 OH Mandor 105,000.00 6,300.00
B BAHAN 87,741.60
0.718 Lbr Gypsumboard 9mm 78,700.00 56,506.60
2.300 m Metal Stud MS.76 10,300.00 23,690.00
20.000 Pcs Sekrup Gypsum 225.00 4,500.00
0.400 Kg Cornice Adhesive 4,200.00 1,680.00
1.300 m' Textile Tape 1,050.00 1,365.00
C PERALATAN
D Jumlah A + B + C 138,341.60
E Overhead & Profit 15% 20,751.24
F Harga Satuan Pekerjaan (D+E) 159,092.84

129
HARGA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH JUMLAH
Rp Rp

HARGA SATUAN PEKERJAAN FLOORING SEMEN FIBER NON ASBES


HITUNG CW1 1.000 m2 Pek. Flooring Conwood Deck 4" Finish Coating Err:509
A Tenaga 93,800.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.750 OH Tukang 90,000.00 67,500.00
L.03 0.030 OH Kepala Tukang 105,000.00 3,150.00
L.04 0.030 OH Mandor 105,000.00 3,150.00
B Bahan Err:509
3.200 Lembar Conwood Deck 4" Err:509 Err:509
10.000 Bh Screw Err:509 Err:509
0.500 Kg Tile Grout Err:509 Err:509
0.200 Kg FPS Sealer Err:509 Err:509
0.200 Kg Use Clear Err:509 Err:509
0.200 Liter Coating 80,800.00 16,160.00
C PERALATAN
D Jumlah A + B + C Err:509
E Overhead + Profit 10% Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

CK Boyolali
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. #VALUE!
Rp Rp
HARGA SATUAN PEKERJAAN AKSESORIES
HITUNG AS1 1.000 m' Pemasangan Handrail Tangga Bahan Stainless Steel 858,375.47
A Tenaga 64,126.83
L.01 0.500 OH Pekerja 80,000.00 40,000.00
L.02 0.250 OH Tukang Besi 90,000.00 22,500.00
L.03 0.010 OH Kepala Tukang 105,000.00 1,050.00
L.04 0.005 OH Mandor 105,000.00 576.83
B Bahan 505,397.50
0.350 btg Pipa Stainless Steel 2 inch (Arah Memanjang) 454,200.00 158,970.00
0.263 btg Pipa Stainless Steel 2 inch (Tiang) 454,200.00 119,227.50
1.000 btg Pipa Stainless Steel 3/4 inch (Ornamen) 227,200.00 227,200.00
C PERALATAN 176,889.13
0.350 Peralatan 35% dari bahan 505,397.50 176,889.13
D Jumlah A + B + C 746,413.45
E Overhead & Profit 15% 111,962.02
F Harga Satuan Pekerjaan (D+E) 858,375.47

HITUNG AS2 1.000 m2 Pemasangan Roster Ukuran 20x20 485,141.88


A Tenaga 44,650.00
L.01 0.350 OH Pekerja 80,000.00 28,000.00
L.02 0.150 OH Tukang Besi 90,000.00 13,500.00
L.03 0.015 OH Kepala Tukang 105,000.00 1,575.00
L.04 0.015 OH Mandor 105,000.00 1,575.00
B Bahan 377,212.50
25.000 Buah Roster Beton Abu Uk20x20 15,000.00 375,000.00
1.500 Kg Portland Semen 1,475.00 2,212.50
C PERALATAN
D Jumlah A + B + C 421,862.50
E Overhead & Profit 15% 63,279.38
F Harga Satuan Pekerjaan (D+E) 485,141.88

HITUNG AS3 1.000 m' Pemasangan Tiang Bahan Stainless Steel 4" 298,186.38
A Tenaga 36,710.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.125 OH Tukang Besi 90,000.00 11,250.00
L.03 0.050 OH Kepala Tukang 105,000.00 5,250.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 193,550.00
0.175 btg Pipa Stainless Steel 4" 1,106,000.00 193,550.00
C PERALATAN 29,032.50
0.150 Peralatan 15% dari bahan 193,550.00 29,032.50
D Jumlah A + B + C 259,292.50
E Overhead & Profit 15% 38,893.88
F Harga Satuan Pekerjaan (D+E) 298,186.38

HITUNG AS4 1.000 m' Pemasangan Tiang Bahan Stainless Steel 3" 233,499.59
A Tenaga 36,710.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.125 OH Tukang Besi 90,000.00 11,250.00
L.03 0.050 OH Kepala Tukang 105,000.00 5,250.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 144,637.50
0.175 btg Pipa Stainless Steel 3" 826,500.00 144,637.50
C PERALATAN 21,695.63
0.150 Peralatan 15% dari bahan 144,637.50 21,695.63
D Jumlah A + B + C 203,043.13
E Overhead & Profit 15% 30,456.47
F Harga Satuan Pekerjaan (D+E) 233,499.59

131
HARGA
JUMLAH
No. SNI KODE KOEF SAT. #VALUE! BAHAN/UPAH
Rp Rp
A.4.4.3 HARGA SATUAN PEKERJAAN PAVING
A.4.4.3.63 1.000 m2 Pemasangan Paving Holland Natural Uk. 20 x 10,5 x 8 cm K-250 Ex. MASTER BETON #DIV/0!
A Tenaga #DIV/0!
L.01 #DIV/0! OH Pekerja 80,000.00 #DIV/0!
L.02 #DIV/0! OH Tukang Batu 90,000.00 #DIV/0!
L.03 #DIV/0! OH Kepala Tukang 105,000.00 #DIV/0!
L.04 #DIV/0! OH Mandor 105,000.00 #DIV/0!
B Bahan 99,225.00
1.050 m2 Paving holland 20 x 10,5 x 8 cm 94,500.00 99,225.00
- m3 Pasir Urug Pengisi Nat 175,000.00 -
C PERALATAN 1,488.38
0.015 m2 Sewa Peralatan 1.5% dari bahan 99,225.00 1,488.38
D Jumlah A + B + C #DIV/0!
E Overhead & Profit 15% #DIV/0!
F Harga Satuan Pekerjaan (D+E) #DIV/0!

HITUNG PV1 1.000 m2 Pemasangan Paving Holland Natural Uk. 20 x 10,5 x 8 cm K-250 Ex. MASTER BETON 144,654.08
A Tenaga 24,433.33
L.01 0.167 OH Pekerja 80,000.00 13,333.33
L.02 0.100 OH Tukang Batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 105,000.00 1,050.00
L.04 0.010 OH Mandor 105,000.00 1,050.00

132
B Bahan 99,855.00
1.050 m2 Paving holland 20 x 10,5 x 8 cm 94,500.00 99,225.00
0.004 m3 Pasir Urug Pengisi Nat 175,000.00 630.00
C PERALATAN 1,497.83
0.015 m2 Sewa Peralatan 1.5% dari bahan 99,855.00 1,497.83
D Jumlah A + B + C 125,786.16
E Overhead & Profit 15% 18,867.92
F Harga Satuan Pekerjaan (D+E) 144,654.08

HITUNG PV2 1.000 m2 Pemasangan Paving Holland Natural Uk. 20 x 10 x 6 cm K-250 Ex. MASTER BETON 118,916.22
A Tenaga 24,433.33
L.01 0.167 OH Pekerja 80,000.00 13,333.33
L.02 0.100 OH Tukang Batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 105,000.00 1,050.00
L.04 0.010 OH Mandor 105,000.00 1,050.00
B Bahan 77,805.00
1.050 m2 Paving holland 20 x 10,5 x 6 cm 73,500.00 77,175.00
0.004 m3 Pasir Urug 175,000.00 630.00
C PERALATAN 1,167.08
0.015 m2 Sewa Peralatan 1.5% dari bahan 77,805.00 1,167.08
D Jumlah A + B + C 103,405.41
E Overhead & Profit 15% 15,510.81
F Harga Satuan Pekerjaan (D+E) 118,916.22

HITUNG PV2 1.000 m1 Pemasangan Kerb Standard K-250 Uk. 10/12 x 35 x 50 cm Ex. MASTER BETON 107,903.48
A Tenaga 9,033.33
L.01 0.067 OH Pekerja 80,000.00 5,333.33
L.02 0.033 OH Tukang Batu 90,000.00 3,000.00
L.03 0.003 OH Kepala Tukang 105,000.00 350.00
L.04 0.003 OH Mandor 105,000.00 350.00
B Bahan 84,795.78
2.000 Buah Kerb Standard Uk. 10/12 x 35 x 50 42,000.00 84,000.00
0.302 Kg Portland Cement 1,475.00 446.04
0.002 m3 Pasir Pasang 228,400.00 349.74
C PERALATAN
D Jumlah A + B + C 93,829.11
E Overhead & Profit 15% 14,074.37
F Harga Satuan Pekerjaan (D+E) 107,903.48

HITUNG PV3 1.000 m1 Pemasangan Kanstein Besar K-300 Uk. 60 x 30 x 20 cm K-300 195,145.35
A Tenaga 9,033.33
L.01 0.067 OH Pekerja 80,000.00 5,333.33
L.02 0.033 OH Tukang Batu 90,000.00 3,000.00
L.03 0.003 OH Kepala Tukang 105,000.00 350.00
L.04 0.003 OH Mandor 105,000.00 350.00
B Bahan 160,658.28
2.625 Buah Kanstein besar K-300 Uk. 60 x 30 x 20 cm 60,900.00 159,862.50
0.302 Kg Portland Cement 1,475.00 446.04
0.002 m3 Pasir Pasang 228,400.00 349.74
C PERALATAN
D Jumlah A + B + C 169,691.61
E Overhead & Profit 15% 25,453.74
F Harga Satuan Pekerjaan (D+E) 195,145.35

133
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. #VALUE!
Rp Rp
HARGA SATUAN PEKERJAAN TAMAN
HITUNG TM1 1.000 m3 Pek. Media Tanam ( Tanah Merah Dan Pupuk ) 232,817.50
A Tenaga 25,050.00
L.01 0.300 OH Pekerja 80,000.00 24,000.00
L.04 0.010 OH Mandor 105,000.00 1,050.00
B Bahan 177,400.00
1.000 m3 Tanah Subur 177,400.00 177,400.00
C PERALATAN -

D Jumlah A + B + C 202,450.00
E Overhead & Profit 15% 30,367.50
F Harga Satuan Pekerjaan (D+E) 232,817.50

HITUNG TM2 1.000 m2 Pek. Tanaman Kacang Hias /m2 isi 15 polybag 56,902.00
A Tenaga 1,810.00
L.01 0.020 OH Pekerja 80,000.00 1,600.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 47,670.00
15.000 polybag Tanaman Kacang hias 3,150.00 47,250.00
0.040 Kg Pupuk kandang 10,500.00 420.00
C PERALATAN
D Jumlah A + B + C 49,480.00
E Overhead & Profit 15% 7,422.00
F Harga Satuan Pekerjaan (D+E) 56,902.00

HITUNG TM3 1.000 m2 Tanaman Lantana 1 m2 isi 25 polybag 93,127.00


A Tenaga 1,810.00
L.01 0.020 OH Pekerja 80,000.00 1,600.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 79,170.00
25.000 polybag Tanaman Lantana 3,150.00 78,750.00
0.040 Kg Pupuk kandang 10,500.00 420.00
C PERALATAN
D Jumlah A + B + C 80,980.00
E Overhead & Profit 15% 12,147.00
F Harga Satuan Pekerjaan (D+E) 93,127.00

HITUNG TM3 1.000 m1 Pek. Tanaman Pangkas ( Hijau & Merah ) 74,842.00
A Tenaga 1,810.00
L.01 0.020 OH Pekerja 80,000.00 1,600.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 63,270.00
6.000 polybag Tanaman Pangkas ( Hijau ) 5,250.00 31,500.00
1.000 polybag Tanaman Pangkas ( Kuning ) 3,150.00 3,150.00
6.000 polybag Tanaman Pangkas ( Merah ) 4,700.00 28,200.00
0.040 Kg Pupuk kandang 10,500.00 420.00
C PERALATAN
D Jumlah A + B + C 65,080.00
E Overhead & Profit 15% 9,762.00
F Harga Satuan Pekerjaan (D+E) 74,842.00

HITUNG TM4 1.000 m2 Pek. Tanam Pohon Ketapang Kencana Tinggi 1.00 m 123,314.50
A Tenaga 1,810.00
L.01 0.020 OH Pekerja 80,000.00 1,600.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 105,420.00
1.000 bh Pohon Ketapang Kencana 105,000.00 105,000.00
0.040 Kg Pupuk kandang 10,500.00 420.00
C PERALATAN
D Jumlah A + B + C 107,230.00
E Overhead & Profit 15% 16,084.50
F Harga Satuan Pekerjaan (D+E) 123,314.50

HITUNG TM5 1.000 bh Pek. Tanam Pohon Pucuk Merah Tinggi min 60 cm 92,149.50
A Tenaga 1,810.00
L.01 0.020 OH Pekerja 80,000.00 1,600.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 78,320.00
1.000 bh Tanaman Pucuk Merah Tinggi Min 60 cm 77,900.00 77,900.00
0.040 Kg Pupuk kandang 10,500.00 420.00
C PERALATAN
D Jumlah A + B + C 80,130.00
E Overhead & Profit 15% 12,019.50

134
F Harga Satuan Pekerjaan (D+E) 92,149.50

135
HARGA JUMLAH
BAHAN/UPAH
SNI #REF! KODE SAT. KOEF
Rp Rp

4.1 HARGA SATUAN PEKERJAAN PEKERJAAN PEMASANGAN PIPA DILUAR GEDUNG


4.1.1.(c) Pemasangan 1 m' Pipa PVC Ø 63 mm 50,068.70
Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 10,928.00
Pekerja L.01 OH 0.081 80,000.00 6,480.00
Tukang Pipa L.02 OH 0.041 88,000.00 3,608.00
Mandor L.04 OH 0.008 105,000.00 840.00
B Bahan 31,950.00
Pipa PVC Ø 63 mm m' 1.000 31,950.00 31,950.00
C PERALATAN 660.00
Sewa Tripot / Tackel hari 0.006 110,000.00 660.00
D Jumlah A + B + C 43,538.00
E Overhead & Profit 6,530.70
F Harga Satuan Pekerjaan (D+E) 50,068.70

4.1.2.(c) Pemasangan 1m' Pipa PVC Ø 90 mm 119,060.65


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 12,601.00
Pekerja L.01 OH 0.094 80,000.00 7,520.00
Tukang Pipa L.02 OH 0.047 88,000.00 4,136.00
Mandor L.04 OH 0.009 105,000.00 945.00
B Bahan 90,050.00
Pipa PVC Ø 90 mm m' 1.000 90,050.00 90,050.00
C PERALATAN 880.00
Sewa Tripot / Tackel hari 0.008 110,000.00 880.00
D Jumlah A + B + C 103,531.00
E Overhead & Profit 15,529.65
F Harga Satuan Pekerjaan (D+E) 119,060.65

4.1.3.(c) Pemasangan 1m' Pipa PVC Ø 110 mm 132,310.18


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 14,219.00
Pekerja L.01 OH 0.105 80,000.00 8,400.00
Tukang Pipa L.02 OH 0.053 88,000.00 4,664.00
Mandor L.04 OH 0.011 105,000.00 1,155.00
B Bahan 99,733.33
Pipa PVC Ø 110 mm m' 1.000 99,733.33 99,733.33
C PERALATAN 1,100.00
Sewa Tripot / Tackel hari 0.010 110,000.00 1,100.00
D Jumlah A + B + C 115,052.33
E Overhead & Profit 17,257.85
F Harga Satuan Pekerjaan (D+E) 132,310.18

4.1.4.(c) Pemasangan 1 m' Pipa PVC Ø 150 mm 178,052.97


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 15,892.00
Pekerja L.01 OH 0.118 80,000.00 9,440.00
Tukang Pipa L.02 OH 0.059 88,000.00 5,192.00
Mandor L.04 OH 0.012 105,000.00 1,260.00
B Bahan 137,616.67
Pipa PVC Ø 150 mm m' 1.000 137,616.67 137,616.67
C PERALATAN 1,320.00
Sewa Tripot / Tackel hari 0.012 110,000.00 1,320.00
D Jumlah A + B + C 154,828.67
E Overhead & Profit 23,224.30
F Harga Satuan Pekerjaan (D+E) 178,052.97

4.1.5.(c) Pemasangan 1m' Pipa PVC Ø 200 mm 553,454.75


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 25,475.00
Pekerja L.01 OH 0.189 80,000.00 15,120.00

136
Tukang Pipa L.02 OH 0.095 88,000.00 8,360.00
Mandor L.04 OH 0.019 105,000.00 1,995.00
B Bahan 453,150.00
Pipa PVC Ø 200 mm m' 1.000 453,150.00 453,150.00
C PERALATAN 2,640.00
Sewa Tripot / Tackel hari 0.024 110,000.00 2,640.00
D Jumlah A + B + C 481,265.00
E Overhead & Profit 72,189.75
F Harga Satuan Pekerjaan (D+E) 553,454.75

4.1.6.(c) Pemasangan 1m' Pipa PVC Ø 250 mm 875,434.43


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 34,474.00
Pekerja L.01 OH 0.256 80,000.00 20,480.00
Tukang Pipa L.02 OH 0.128 88,000.00 11,264.00
Mandor L.04 OH 0.026 105,000.00 2,730.00
B Bahan 723,033.33
Pipa PVC Ø 250 mm m' 1.000 723,033.33 723,033.33
C PERALATAN 3,740.00
Sewa Tripot / Tackel hari 0.034 110,000.00 3,740.00
D Jumlah A + B + C 761,247.33
E Overhead & Profit 114,187.10
F Harga Satuan Pekerjaan (D+E) 875,434.43

4.1.7.(c) Pemasangan 1m' Pipa PVC Ø 300 mm 1,352,036.98


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 39,501.00
Pekerja L.01 OH 0.294 80,000.00 23,520.00
Tukang Pipa L.02 OH 0.147 88,000.00 12,936.00
Mandor L.04 OH 0.029 105,000.00 3,045.00
B Bahan 1,131,783.33
Pipa PVC Ø 300 mm m' 1.000 1,131,783.33 1,131,783.33
C PERALATAN 4,400.00
Sewa Tripot / Tackel hari 0.040 110,000.00 4,400.00
D Jumlah A + B + C 1,175,684.33
E Overhead & Profit 176,352.65
F Harga Satuan Pekerjaan (D+E) 1,352,036.98

4.1.17.(c) Pemasangan 1m' Pipa HDPE Ø 63 mm 63,826.15


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 4,611.00
Pekerja L.01 OH 0.035 80,000.00 2,800.00
Tukang Pipa L.02 OH 0.017 88,000.00 1,496.00
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan 48,800.00
Pipa HDPE Ø 63 mm m' 1.000 48,800.00 48,800.00
C PERALATAN 2,090.00
Sewa Tripot / Tackel hari 0.019 110,000.00 2,090.00
D Jumlah A + B + C 55,501.00
E Overhead & Profit 8,325.15
F Harga Satuan Pekerjaan (D+E) 63,826.15

4.1.18.(c) Pemasangan 1m' Pipa HDPE Ø 100 mm 186,265.50


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 5,380.00
Pekerja L.01 OH 0.040 80,000.00 3,200.00
Tukang Pipa L.02 OH 0.020 88,000.00 1,760.00
Mandor L.04 OH 0.004 105,000.00 420.00
B Bahan 154,500.00
Pipa HDPE Ø 100 mm m' 1.000 154,500.00 154,500.00
C PERALATAN 2,090.00
Sewa Tripot / Tackel hari 0.019 110,000.00 2,090.00
D Jumlah A + B + C 161,970.00
E Overhead & Profit 24,295.50
F Harga Satuan Pekerjaan (D+E) 186,265.50

137
4.1.19.(c) Pemasangan 1m' Pipa HDPE Ø 125 mm 236,024.85
Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 6,149.00
Pekerja L.01 OH 0.045 80,000.00 3,600.00
Tukang Pipa L.02 OH 0.023 88,000.00 2,024.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 197,000.00
Pipa HDPE Ø 125 mm m' 1.000 197,000.00 197,000.00
C PERALATAN 2,090.00
Sewa Tripot / Tackel hari 0.019 110,000.00 2,090.00
D Jumlah A + B + C 205,239.00
E Overhead & Profit 30,785.85
F Harga Satuan Pekerjaan (D+E) 236,024.85

4.1.20.(c) Pemasangan 1m' Pipa HDPE Ø 150 mm 383,189.20


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 8,318.00
Pekerja L.01 OH 0.062 80,000.00 4,960.00
Tukang Pipa L.02 OH 0.031 88,000.00 2,728.00
Mandor L.04 OH 0.006 105,000.00 630.00
B Bahan 322,800.00
Pipa HDPE Ø 150 mm m' 1.000 322,800.00 322,800.00
C PERALATAN 2,090.00
Sewa Tripot / Tackel hari 0.019 110,000.00 2,090.00
D Jumlah A + B + C 333,208.00
E Overhead & Profit 49,981.20
F Harga Satuan Pekerjaan (D+E) 383,189.20

4.1.21.(c) Pemasangan 1m' Pipa HDPE Ø 200 mm 597,641.20


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 13,698.00
Pekerja L.01 OH 0.102 80,000.00 8,160.00
Tukang Pipa L.02 OH 0.051 88,000.00 4,488.00
Mandor L.04 OH 0.010 105,000.00 1,050.00
B Bahan 503,900.00
Pipa HDPE Ø 200 mm m' 1.000 503,900.00 503,900.00
C PERALATAN 2,090.00
Sewa Tripot / Tackel hari 0.019 110,000.00 2,090.00
D Jumlah A + B + C 519,688.00
E Overhead & Profit 77,953.20
F Harga Satuan Pekerjaan (D+E) 597,641.20

4.1.22.(c) Pemasangan 1m' Pipa HDPE Ø 250 mm 926,579.15


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 17,901.00
Pekerja L.01 OH 0.133 80,000.00 10,640.00
Tukang Pipa L.02 OH 0.067 88,000.00 5,896.00
Mandor L.04 OH 0.013 105,000.00 1,365.00
B Bahan 783,200.00
Pipa HDPE Ø 250 mm m' 1.000 783,200.00 783,200.00
C PERALATAN 4,620.00
Sewa Tripot / Tackel hari 0.042 110,000.00 4,620.00
D Jumlah A + B + C 805,721.00
E Overhead & Profit 120,858.15
F Harga Satuan Pekerjaan (D+E) 926,579.15

4.1.23.(c) Pemasangan 1m' Pipa HDPE Ø 300 mm 1,467,417.25


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 22,865.00
Pekerja L.01 OH 0.170 80,000.00 13,600.00
Tukang Pipa L.02 OH 0.085 88,000.00 7,480.00
Mandor L.04 OH 0.017 105,000.00 1,785.00
B Bahan 1,246,000.00
Pipa HDPE Ø 300 mm m' 1.000 1,246,000.00 1,246,000.00
C PERALATAN 7,150.00

138
Sewa Tripot / Tackel hari 0.065 110,000.00 7,150.00
D Jumlah A + B + C 1,276,015.00
E Overhead & Profit 191,402.25
F Harga Satuan Pekerjaan (D+E) 1,467,417.25

4.1.24.(c) Pemasangan 1m' Pipa HDPE Ø 400 mm 2,368,568.75


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 39,005.00
Pekerja L.01 OH 0.290 80,000.00 23,200.00
Tukang Pipa L.02 OH 0.145 88,000.00 12,760.00
Mandor L.04 OH 0.029 105,000.00 3,045.00
B Bahan 2,003,900.00
Pipa HDPE Ø 400 mm m' 1.000 2,003,900.00 2,003,900.00
C PERALATAN 16,720.00
Sewa Tripot / Tackel hari 0.152 110,000.00 16,720.00
D Jumlah A + B + C 2,059,625.00
E Overhead & Profit 308,943.75
F Harga Satuan Pekerjaan (D+E) 2,368,568.75

4.1.25.(c) Pemasangan 1m' Pipa HDPE Ø 450 mm 3,000,741.00


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 48,340.00
Pekerja L.01 OH 0.359 80,000.00 28,720.00
Tukang Pipa L.02 OH 0.180 88,000.00 15,840.00
Mandor L.04 OH 0.036 105,000.00 3,780.00
B Bahan 2,539,000.00
Pipa HDPE Ø 450 mm m' 1.000 2,539,000.00 2,539,000.00
C PERALATAN 22,000.00
Sewa Tripot / Tackel hari 0.200 110,000.00 22,000.00
D Jumlah A + B + C 2,609,340.00
E Overhead & Profit 391,401.00
F Harga Satuan Pekerjaan (D+E) 3,000,741.00

4.1.26.(c) Pemasangan 1m' Pipa HDPE Ø 500 mm 3,691,641.45


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 55,013.00
Pekerja L.01 OH 0.433 80,000.00 34,640.00
Tukang Pipa L.02 OH 0.216 88,000.00 19,008.00
Mandor L.04 OH 0.013 105,000.00 1,365.00
B Bahan 3,127,500.00
Pipa HDPE Ø 500 mm m' 1.000 3,127,500.00 3,127,500.00
C PERALATAN 27,610.00
Sewa Tripot / Tackel hari 0.251 110,000.00 27,610.00
D Jumlah A + B + C 3,210,123.00
E Overhead & Profit 481,518.45
F Harga Satuan Pekerjaan (D+E) 3,691,641.45

4.1.27.(c) Pemasangan 1m' Pipa HDPE Ø 600 mm 5,828,329.95


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 68,843.00
Pekerja L.01 OH 0.512 80,000.00 40,960.00
Tukang Pipa L.02 OH 0.256 88,000.00 22,528.00
Mandor L.04 OH 0.051 105,000.00 5,355.00
B Bahan 4,965,500.00
Pipa HDPE Ø 600 mm m' 1.000 4,965,500.00 4,965,500.00
C PERALATAN 33,770.00
Sewa Tripot / Tackel hari 0.307 110,000.00 33,770.00
D Jumlah A + B + C 5,068,113.00
E Overhead & Profit 760,216.95
F Harga Satuan Pekerjaan (D+E) 5,828,329.95

4.1.28.(c) Pemasangan 1m' Pipa HDPE Ø 800 mm 13,463,352.45


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 120,033.00
Pekerja L.01 OH 0.893 80,000.00 71,440.00

139
Tukang Pipa L.02 OH 0.446 88,000.00 39,248.00
Mandor L.04 OH 0.089 105,000.00 9,345.00
B Bahan 11,524,200.00
Pipa HDPE Ø 800 mm m' 1.000 11,524,200.00 11,524,200.00
C PERALATAN 63,030.00
Sewa Tripot / Tackel hari 0.573 110,000.00 63,030.00
D Jumlah A + B + C 11,707,263.00
E Overhead & Profit 1,756,089.45
F Harga Satuan Pekerjaan (D+E) 13,463,352.45

4.1.29.(c) Pemasangan 1m' Pipa HDPE Ø 900 mm 17,142,384.15


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 181,991.00
Pekerja L.01 OH 1.353 80,000.00 108,240.00
Tukang Pipa L.02 OH 0.677 88,000.00 59,576.00
Mandor L.04 OH 0.135 105,000.00 14,175.00
B Bahan 14,627,300.00
Pipa HDPE Ø 900 mm m' 1.000 14,627,300.00 14,627,300.00
C PERALATAN 97,130.00
Sewa Tripot / Tackel hari 0.883 110,000.00 97,130.00
D Jumlah A + B + C 14,906,421.00
E Overhead & Profit 2,235,963.15
F Harga Satuan Pekerjaan (D+E) 17,142,384.15

4.1.30.(c) Pemasangan 1m' Pipa HDPE Ø 1000 mm 21,114,943.00


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 223,190.00
Pekerja L.01 OH 1.659 80,000.00 132,720.00
Tukang Pipa L.02 OH 0.830 88,000.00 73,040.00
Mandor L.04 OH 0.166 105,000.00 17,430.00
B Bahan 18,017,400.00
Pipa HDPE Ø 1000 mm m' 1.000 18,017,400.00 18,017,400.00
C PERALATAN 120,230.00
Sewa Tripot / Tackel hari 1.093 110,000.00 120,230.00
D Jumlah A + B + C 18,360,820.00
E Overhead & Profit 2,754,123.00
F Harga Satuan Pekerjaan (D+E) 21,114,943.00

4.1.31.(c) Pemasangan 1m' Pipa HDPE Ø 1100 mm 21,153,665.80


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 244,542.00
Pekerja L.01 OH 1.818 80,000.00 145,440.00
Tukang Pipa L.02 OH 0.909 88,000.00 79,992.00
Mandor L.04 OH 0.182 105,000.00 19,110.00
B Bahan 18,017,400.00
Pipa HDPE Ø 1100 mm m' 1.000 18,017,400.00 18,017,400.00
C PERALATAN 132,550.00
Sewa Tripot / Tackel hari 1.205 110,000.00 132,550.00
D Jumlah A + B + C 18,394,492.00
E Overhead & Profit 2,759,173.80
F Harga Satuan Pekerjaan (D+E) 21,153,665.80

4.1.32.(c) Pemasangan 1m' Pipa HDPE Ø 1200 mm 29,185,050.75


Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 318,765.00
Pekerja L.01 OH 2.370 80,000.00 189,600.00
Tukang Pipa L.02 OH 1.185 88,000.00 104,280.00
Mandor L.04 OH 0.237 105,000.00 24,885.00
B Bahan 24,885,300.00
Pipa HDPE Ø 1200 mm m' 1.000 24,885,300.00 24,885,300.00
C PERALATAN 174,240.00
Sewa Tripot / Tackel hari 1.584 110,000.00 174,240.00
D Jumlah A + B + C 25,378,305.00
E Overhead & Profit 3,806,745.75
F Harga Satuan Pekerjaan (D+E) 29,185,050.75

140
HARGA SATUAN JUMLAH HARGA
URAIAN KODE SAT KOEF
Rp Rp
4.2 HARGA SATUAN PEKERJAAN PEMOTONGAN PIPA
4.2.1.(c) Pemotongan 1 Buah Pipa PVC Ø 63 mm 1,007.40

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A TENAGA 628.50
Pekerja L.01 OH 0.005 80,000.00 400.00
Tukang pipa L.02 OH 0.002 88,000.00 176.00
Mandor L.04 OH 0.0005 105,000.00 52.50
B BAHAN
C PERALATAN 247.50
Peralatan potong pipa T1 /manual (gergaji)/ saw hari 0.003 82,500.00 247.50
D Jumlah A + B + C 876.00
E Overhead & Profit 15% 131.40
F Harga Satuan Pekerjaan (D+E) 1,007.40

4.2.2.(c) Pemotongan 1 m' Pipa PVC Ø 90 mm 2,401.78

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 1,841.00
Pekerja L.01 OH 0.014 80,000.00 1,120.00
Tukang pipa L.02 OH 0.007 88,000.00 616.00
Mandor L.04 OH 0.001 105,000.00 105.00
B Bahan
C PERALATAN 247.50
Peralatan potong pipa T1 /manual (gergaji)/ saw hari 0.003 82,500.00 247.50
D Jumlah A + B + C 2,088.50
E Overhead & Profit 15% 313.28
F Harga Satuan Pekerjaan (D+E) 2,401.78

4.2.3.(c) Pemotongan 1 Buah Pipa PVC Ø 110 mm 3,663.33

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 2,938.00
Pekerja L.01 OH 0.022 80,000.00 1,760.00
Tukang pipa L.02 OH 0.011 88,000.00 968.00
Mandor L.04 OH 0.002 105,000.00 210.00
B Bahan
C PERALATAN 247.50
Peralatan potong pipa T1 /manual (gergaji)/ saw hari 0.003 82,500.00 247.50
D Jumlah A + B + C 3,185.50
E Overhead & Profit 15% 477.83
F Harga Satuan Pekerjaan (D+E) 3,663.33

4.2.4.(c) Pemotongan 1 Buah Pipa PVC Ø 150 mm 5,016.88

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 4,115.00
Pekerja L.01 OH 0.031 80,000.00 2,480.00
Tukang pipa L.02 OH 0.015 88,000.00 1,320.00
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan
C PERALATAN 247.50
Peralatan potong pipa T1 /manual (gergaji)/ saw hari 0.003 82,500.00 247.50
D Jumlah A + B + C 4,362.50
E Overhead & Profit 15% 654.38
F Harga Satuan Pekerjaan (D+E) 5,016.88

141
4.2.5.(c) Pemotongan 1 Buah Pipa PVC Ø 200 mm 14,078.88

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 10,840.00
Pekerja L.01 OH 0.081 80,000.00 6,480.00
Tukang pipa L.02 OH 0.040 88,000.00 3,520.00
Mandor L.04 OH 0.008 105,000.00 840.00
B Bahan
C PERALATAN 1,402.50
Peralatan potong pipa T1 /manual (gergaji)/ saw hari 0.017 82,500.00 1,402.50
D Jumlah A + B + C 12,242.50
E Overhead & Profit 15% 1,836.38
F Harga Satuan Pekerjaan (D+E) 14,078.88

4.2.6.(c) Pemotongan 1 Buah Pipa PVC Ø 250 mm 22,668.80

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 17,237.00
Pekerja L.01 OH 0.128 80,000.00 10,240.00
Tukang pipa L.02 OH 0.064 88,000.00 5,632.00
Mandor L.04 OH 0.013 105,000.00 1,365.00
B Bahan
C PERALATAN 2,475.00
Peralatan potong pipa T1 /manual (gergaji)/ saw hari 0.030 82,500.00 2,475.00
D Jumlah A + B + C 19,712.00
E Overhead & Profit 15% 2,956.80
F Harga Satuan Pekerjaan (D+E) 22,668.80

4.2.7.(c) Pemotongan 1 Buah Pipa PVC Ø 300 mm 27,374.03

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 20,751.00
Pekerja L.01 OH 0.155 80,000.00 12,400.00
Tukang pipa L.02 OH 0.077 88,000.00 6,776.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B Bahan
C PERALATAN 3,052.50
Peralatan potong pipa T1 /manual (gergaji)/ saw hari 0.037 82,500.00 3,052.50
D Jumlah A + B + C 23,803.50
E Overhead & Profit 15% 3,570.53
F Harga Satuan Pekerjaan (D+E) 27,374.03

4.2.8.(c) Pemotongan 1 Buah Pipa PVC Ø 400 mm 59,395.20

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 44,553.00
Pekerja L.01 OH 0.331 80,000.00 26,480.00
Tukang pipa L.02 OH 0.166 88,000.00 14,608.00
Mandor L.04 OH 0.033 105,000.00 3,465.00
B Bahan
C PERALATAN 7,095.00
Peralatan potong pipa T1 /manual (gergaji)/ saw hari 0.086 82,500.00 7,095.00
D Jumlah A + B + C 51,648.00
E Overhead & Profit 15% 7,747.20
F Harga Satuan Pekerjaan (D+E) 59,395.20

4.2.9.(c) Pemotongan 1 Buah Pipa PVC Ø 450 mm 75,210.00

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp

142
A Tenaga 56,490.00
Pekerja L.01 OH 0.420 80,000.00 33,600.00
Tukang pipa L.02 OH 0.210 88,000.00 18,480.00
Mandor L.04 OH 0.042 105,000.00 4,410.00
B Bahan
C PERALATAN 8,910.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.054 165,000.00 8,910.00
D Jumlah A + B + C 65,400.00
E Overhead & Profit 15% 9,810.00
F Harga Satuan Pekerjaan (D+E) 75,210.00

4.2.10.(c) Pemotongan 1 Buah Pipa PVC Ø 500 mm 93,238.55

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 69,692.00
Pekerja L.01 OH 0.518 80,000.00 41,440.00
Tukang pipa L.02 OH 0.259 88,000.00 22,792.00
Mandor L.04 OH 0.052 105,000.00 5,460.00
B Bahan
C PERALATAN 11,385.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.069 165,000.00 11,385.00
D Jumlah A + B + C 81,077.00
E Overhead & Profit 15% 12,161.55
F Harga Satuan Pekerjaan (D+E) 93,238.55

4.2.11.(c) Pemotongan 1 Buah Pipa PVC Ø 600 mm 112,594.20

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 83,718.00
Pekerja L.01 OH 0.623 80,000.00 49,840.00
Tukang pipa L.02 OH 0.311 88,000.00 27,368.00
Mandor L.04 OH 0.062 105,000.00 6,510.00
B Bahan
C PERALATAN 14,190.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.086 165,000.00 14,190.00
D Jumlah A + B + C 97,908.00
E Overhead & Profit 15% 14,686.20
F Harga Satuan Pekerjaan (D+E) 112,594.20

4.2.12.(c) Pemotongan 1 Buah Pipa PVC Ø 800 mm 198,863.75

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 146,525.00
Pekerja L.01 OH 1.089 80,000.00 87,120.00
Tukang pipa L.02 OH 0.545 88,000.00 47,960.00
Mandor L.04 OH 0.109 105,000.00 11,445.00
B Bahan
C PERALATAN 26,400.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.160 165,000.00 26,400.00
D Jumlah A + B + C 172,925.00
E Overhead & Profit 15% 25,938.75
F Harga Satuan Pekerjaan (D+E) 198,863.75

4.2.13.(c) Pemotongan 1 Buah Pipa PVC Ø 900 mm 208,400.70

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 153,498.00
Pekerja L.01 OH 1.141 80,000.00 91,280.00
Tukang pipa L.02 OH 0.571 88,000.00 50,248.00
Mandor L.04 OH 0.114 105,000.00 11,970.00

143
B Bahan
C PERALATAN 27,720.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.168 165,000.00 27,720.00
D Jumlah A + B + C 181,218.00
E Overhead & Profit 15% 27,182.70
F Harga Satuan Pekerjaan (D+E) 208,400.70

4.2.14.(c) Pemotongan 1 Buah Pipa PVC Ø 1000 mm 235,110.60

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 172,929.00
Pekerja L.01 OH 1.285 80,000.00 102,800.00
Tukang pipa L.02 OH 0.643 88,000.00 56,584.00
Mandor L.04 OH 0.129 105,000.00 13,545.00
B Bahan
C PERALATAN 31,515.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.191 165,000.00 31,515.00
D Jumlah A + B + C 204,444.00
E Overhead & Profit 15% 30,666.60
F Harga Satuan Pekerjaan (D+E) 235,110.60

4.2.15.(c) Pemotongan 1 Buah Pipa PVC Ø 1100 mm 261,510.00

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 192,255.00
Pekerja L.01 OH 1.429 80,000.00 114,320.00
Tukang pipa L.02 OH 0.715 88,000.00 62,920.00
Mandor L.04 OH 0.143 105,000.00 15,015.00
B Bahan
C PERALATAN 35,145.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.213 165,000.00 35,145.00
D Jumlah A + B + C 227,400.00
E Overhead & Profit 15% 34,110.00
F Harga Satuan Pekerjaan (D+E) 261,510.00

4.2.16.(c) Pemotongan 1 Buah Pipa PVC Ø 1200 mm 288,099.15

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 211,581.00
Pekerja L.01 OH 1.573 80,000.00 125,840.00
Tukang pipa L.02 OH 0.787 88,000.00 69,256.00
Mandor L.04 OH 0.157 105,000.00 16,485.00
B Bahan
C PERALATAN 38,940.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.236 165,000.00 38,940.00
D Jumlah A + B + C 250,521.00
E Overhead & Profit 15% 37,578.15
F Harga Satuan Pekerjaan (D+E) 288,099.15

4.2.17.(c) Pemotongan 1 Buah Pipa HDPE Ø 63 mm 4,509.15

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 3,261.00
Pekerja L.01 OH 0.002 80,000.00 160.00
Tukang pipa L.02 OH 0.001 88,000.00 88.00
Mandor L.04 OH 0.0002 105,000.00 21.00
Operator L.08 OH 0.034 88,000.00 2,992.00
B Bahan
C PERALATAN 660.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.004 165,000.00 660.00

144
D Jumlah A + B + C 3,921.00
E Overhead & Profit 15% 588.15
F Harga Satuan Pekerjaan (D+E) 4,509.15

4.2.18.(c) Pemotongan 1 Buah Pipa HDPE Ø 100 mm 9,110.30

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 7,097.00
Pekerja L.01 OH 0.006 80,000.00 480.00
Tukang pipa L.02 OH 0.003 88,000.00 264.00
Mandor L.04 OH 0.001 105,000.00 105.00
Operator L.08 OH 0.071 88,000.00 6,248.00
B Bahan
C PERALATAN 825.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.005 165,000.00 825.00
D Jumlah A + B + C 7,922.00
E Overhead & Profit 15% 1,188.30
F Harga Satuan Pekerjaan (D+E) 9,110.30

4.2.19.(c) Pemotongan 1 Buah Pipa HDPE Ø 125 mm 12,308.45

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 9,713.00
Pekerja L.01 OH 0.009 80,000.00 720.00
Tukang pipa L.02 OH 0.005 88,000.00 440.00
Mandor L.04 OH 0.001 105,000.00 105.00
Operator L.08 OH 0.096 88,000.00 8,448.00
B Bahan
C PERALATAN 990.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.006 165,000.00 990.00
D Jumlah A + B + C 10,703.00
E Overhead & Profit 15% 1,605.45
F Harga Satuan Pekerjaan (D+E) 12,308.45

4.2.20.(c) Pemotongan 1 Buah Pipa HDPE Ø 150 mm 16,476.05

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 12,842.00
Pekerja L.01 OH 0.016 80,000.00 1,280.00
Tukang pipa L.02 OH 0.008 88,000.00 704.00
Mandor L.04 OH 0.002 105,000.00 210.00
Operator L.08 OH 0.121 88,000.00 10,648.00
B Bahan
C PERALATAN 1,485.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.009 165,000.00 1,485.00
D Jumlah A + B + C 14,327.00
E Overhead & Profit 15% 2,149.05
F Harga Satuan Pekerjaan (D+E) 16,476.05

4.2.21.(c) Pemotongan 1 Buah Pipa HDPE Ø 200 mm 27,288.35

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 20,924.00
Pekerja L.01 OH 0.044 80,000.00 3,520.00
Tukang pipa L.02 OH 0.022 88,000.00 1,936.00
Mandor L.04 OH 0.004 105,000.00 420.00
Operator L.08 OH 0.171 88,000.00 15,048.00
B Bahan
C PERALATAN 2,805.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.017 165,000.00 2,805.00

145
D Jumlah A + B + C 23,729.00
E Overhead & Profit 15% 3,559.35
F Harga Satuan Pekerjaan (D+E) 27,288.35

4.2.22.(c) Pemotongan 1 Buah Pipa HDPE Ø 250 mm 37,078.30

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 28,447.00
Pekerja L.01 OH 0.067 80,000.00 5,360.00
Tukang pipa L.02 OH 0.033 88,000.00 2,904.00
Mandor L.04 OH 0.007 105,000.00 735.00
Operator L.08 OH 0.221 88,000.00 19,448.00
B Bahan
C PERALATAN 3,795.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.023 165,000.00 3,795.00
D Jumlah A + B + C 32,242.00
E Overhead & Profit 15% 4,836.30
F Harga Satuan Pekerjaan (D+E) 37,078.30

4.2.23.(c) Pemotongan 1 Buah Pipa HDPE Ø 300 mm 47,038.45

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 35,953.00
Pekerja L.01 OH 0.090 80,000.00 7,200.00
Tukang pipa L.02 OH 0.045 88,000.00 3,960.00
Mandor L.04 OH 0.009 105,000.00 945.00
Operator L.08 OH 0.271 88,000.00 23,848.00
B Bahan
C PERALATAN 4,950.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.030 165,000.00 4,950.00
D Jumlah A + B + C 40,903.00
E Overhead & Profit 15% 6,135.45
F Harga Satuan Pekerjaan (D+E) 47,038.45

4.2.24.(c) Pemotongan 1 Buah Pipa HDPE Ø 400 mm 75,344.55

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 56,442.00
Pekerja L.01 OH 0.177 80,000.00 14,160.00
Tukang pipa L.02 OH 0.088 88,000.00 7,744.00
Mandor L.04 OH 0.018 105,000.00 1,890.00
Operator L.08 OH 0.371 88,000.00 32,648.00
B Bahan
C PERALATAN 9,075.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.055 165,000.00 9,075.00
D Jumlah A + B + C 65,517.00
E Overhead & Profit 15% 9,827.55
F Harga Satuan Pekerjaan (D+E) 75,344.55

4.2.25.(c) Pemotongan 1 Buah Pipa HDPE Ø 450 mm 90,800.55

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 67,407.00
Pekerja L.01 OH 0.225 80,000.00 18,000.00
Tukang pipa L.02 OH 0.113 88,000.00 9,944.00
Mandor L.04 OH 0.023 105,000.00 2,415.00
Operator L.08 OH 0.421 88,000.00 37,048.00
B Bahan
C PERALATAN 11,550.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.070 165,000.00 11,550.00

146
D Jumlah A + B + C 78,957.00
E Overhead & Profit 15% 11,843.55
F Harga Satuan Pekerjaan (D+E) 90,800.55

4.2.26.(c) Pemotongan 1 Buah Pipa HDPE Ø 500 mm 106,725.75

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 78,780.00
Pekerja L.01 OH 0.277 80,000.00 22,160.00
Tukang pipa L.02 OH 0.139 88,000.00 12,232.00
Mandor L.04 OH 0.028 105,000.00 2,940.00
Operator L.08 OH 0.471 88,000.00 41,448.00
B Bahan
C PERALATAN 14,025.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.085 165,000.00 14,025.00
D Jumlah A + B + C 92,805.00
E Overhead & Profit 15% 13,920.75
F Harga Satuan Pekerjaan (D+E) 106,725.75

4.2.27.(c) Pemotongan 1 Buah Pipa HDPE Ø 600 mm 128,471.10

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 95,049.00
Pekerja L.01 OH 0.333 80,000.00 26,640.00
Tukang pipa L.02 OH 0.167 88,000.00 14,696.00
Mandor L.04 OH 0.033 105,000.00 3,465.00
Operator L.08 OH 0.571 88,000.00 50,248.00
B Bahan
C PERALATAN 16,665.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.101 165,000.00 16,665.00
D Jumlah A + B + C 111,714.00
E Overhead & Profit 15% 16,757.10
F Harga Satuan Pekerjaan (D+E) 128,471.10

4.2.28.(c) Pemotongan 1 Buah Pipa HDPE Ø 800 mm 204,988.65

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 148,716.00
Pekerja L.01 OH 0.601 80,000.00 48,080.00
Tukang pipa L.02 OH 0.301 88,000.00 26,488.00
Mandor L.04 OH 0.060 105,000.00 6,300.00
Operator L.08 OH 0.771 88,000.00 67,848.00
B Bahan
C PERALATAN 29,535.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.179 165,000.00 29,535.00
D Jumlah A + B + C 178,251.00
E Overhead & Profit 15% 26,737.65
F Harga Satuan Pekerjaan (D+E) 204,988.65

4.2.29.(c) Pemotongan 1 Buah Pipa HDPE Ø 900 mm 280,509.15

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 199,371.00
Pekerja L.01 OH 0.913 80,000.00 73,040.00
Tukang pipa L.02 OH 0.456 88,000.00 40,128.00
Mandor L.04 OH 0.091 105,000.00 9,555.00
Operator L.08 OH 0.871 88,000.00 76,648.00
B Bahan
C PERALATAN 44,550.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.270 165,000.00 44,550.00

147
D Jumlah A + B + C 243,921.00
E Overhead & Profit 15% 36,588.15
F Harga Satuan Pekerjaan (D+E) 280,509.15

4.2.30.(c) Pemotongan 1 Buah Pipa HDPE Ø 1000 mm 335,160.60

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 236,664.00
Pekerja L.01 OH 1.125 80,000.00 90,000.00
Tukang pipa L.02 OH 0.562 88,000.00 49,456.00
Mandor L.04 OH 0.112 105,000.00 11,760.00
Operator L.08 OH 0.971 88,000.00 85,448.00
B Bahan
C PERALATAN 54,780.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.332 165,000.00 54,780.00
D Jumlah A + B + C 291,444.00
E Overhead & Profit 15% 43,716.60
F Harga Satuan Pekerjaan (D+E) 335,160.60

4.2.31.(c) Pemotongan 1 Buah Pipa HDPE Ø 1100 mm 369,155.75

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 260,780.00
Pekerja L.01 OH 1.238 80,000.00 99,040.00
Tukang pipa L.02 OH 0.619 88,000.00 54,472.00
Mandor L.04 OH 0.124 105,000.00 13,020.00
Operator L.08 OH 1.071 88,000.00 94,248.00
B Bahan
C PERALATAN 60,225.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.365 165,000.00 60,225.00
D Jumlah A + B + C 321,005.00
E Overhead & Profit 15% 48,150.75
F Harga Satuan Pekerjaan (D+E) 369,155.75

4.2.32.(c) Pemotongan 1 Buah Pipa HDPE Ø 1200 mm 459,396.25

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 320,770.00
Pekerja L.01 OH 1.619 80,000.00 129,520.00
Tukang pipa L.02 OH 0.809 88,000.00 71,192.00
Mandor L.04 OH 0.162 105,000.00 17,010.00
Operator L.08 OH 1.171 88,000.00 103,048.00
B Bahan
C PERALATAN 78,705.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.477 165,000.00 78,705.00
D Jumlah A + B + C 399,475.00
E Overhead & Profit 15% 59,921.25
F Harga Satuan Pekerjaan (D+E) 459,396.25

4.2.33.(c) Pemotongan 1 Buah Pipa GIP Ø 63 mm 3,001.50

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 2,610.00
Pekerja L.01 OH 0.019 80,000.00 1,520.00
Tukang pipa L.02 OH 0.010 88,000.00 880.00
Mandor L.04 OH 0.002 105,000.00 210.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 2,610.00

148
E Overhead & Profit 15% 391.50
F Harga Satuan Pekerjaan (D+E) 3,001.50

4.2.34.(c) Pemotongan 1 Buah Pipa GIP Ø 100 mm 8,995.30

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 7,822.00
Pekerja L.01 OH 0.058 80,000.00 4,640.00
Tukang pipa L.02 OH 0.029 88,000.00 2,552.00
Mandor L.04 OH 0.006 105,000.00 630.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 7,822.00
E Overhead & Profit 15% 1,173.30
F Harga Satuan Pekerjaan (D+E) 8,995.30

4.2.35.(c) Pemotongan 1 Buah Pipa GIP Ø 125 mm 14,205.95

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 12,353.00
Pekerja L.01 OH 0.092 80,000.00 7,360.00
Tukang pipa L.02 OH 0.046 88,000.00 4,048.00
Mandor L.04 OH 0.009 105,000.00 945.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 12,353.00
E Overhead & Profit 15% 1,852.95
F Harga Satuan Pekerjaan (D+E) 14,205.95

4.2.36.(c) Pemotongan 1 Buah Pipa GIP Ø 150 mm 20,300.95

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 17,653.00
Pekerja L.01 OH 0.131 80,000.00 10,480.00
Tukang pipa L.02 OH 0.066 88,000.00 5,808.00
Mandor L.04 OH 0.013 105,000.00 1,365.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 17,653.00
E Overhead & Profit 15% 2,647.95
F Harga Satuan Pekerjaan (D+E) 20,300.95

4.2.37.(c) Pemotongan 1 Buah Pipa GIP Ø 200 mm 52,589.50

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 45,730.00
Pekerja L.01 OH 0.340 80,000.00 27,200.00
Tukang pipa L.02 OH 0.170 88,000.00 14,960.00
Mandor L.04 OH 0.034 105,000.00 3,570.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 45,730.00
E Overhead & Profit 15% 6,859.50
F Harga Satuan Pekerjaan (D+E) 52,589.50

4.2.38.(c) Pemotongan 1 Buah Pipa GIP Ø 250 mm 73,359.65

149
HARGA SATUAN JUMLAH HARGA
URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 63,791.00
Pekerja L.01 OH 0.475 80,000.00 38,000.00
Tukang pipa L.02 OH 0.237 88,000.00 20,856.00
Mandor L.04 OH 0.047 105,000.00 4,935.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 63,791.00
E Overhead & Profit 15% 9,568.65
F Harga Satuan Pekerjaan (D+E) 73,359.65

4.2.39.(c) Pemotongan 1 Buah Pipa GIP Ø 300 mm 77,907.90

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 67,746.00
Pekerja L.01 OH 0.504 80,000.00 40,320.00
Tukang pipa L.02 OH 0.252 88,000.00 22,176.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 67,746.00
E Overhead & Profit 15% 10,161.90
F Harga Satuan Pekerjaan (D+E) 77,907.90

4.2.40.(c) Pemotongan 1 Buah Pipa GIP Ø 400 mm 114,174.30

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 99,282.00
Pekerja L.01 OH 0.738 80,000.00 59,040.00
Tukang pipa L.02 OH 0.369 88,000.00 32,472.00
Mandor L.04 OH 0.074 105,000.00 7,770.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 99,282.00
E Overhead & Profit 15% 14,892.30
F Harga Satuan Pekerjaan (D+E) 114,174.30

4.2.41.(c) Pemotongan 1 Buah Pipa GIP Ø 450 mm 131,188.55

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 114,077.00
Pekerja L.01 OH 0.848 80,000.00 67,840.00
Tukang pipa L.02 OH 0.424 88,000.00 37,312.00
Mandor L.04 OH 0.085 105,000.00 8,925.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 114,077.00
E Overhead & Profit 15% 17,111.55
F Harga Satuan Pekerjaan (D+E) 131,188.55

4.2.42.(c) Pemotongan 1 Buah Pipa GIP Ø 500 mm 145,587.70

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 126,598.00

150
Pekerja L.01 OH 0.941 80,000.00 75,280.00
Tukang pipa L.02 OH 0.471 88,000.00 41,448.00
Mandor L.04 OH 0.094 105,000.00 9,870.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 126,598.00
E Overhead & Profit 15% 18,989.70
F Harga Satuan Pekerjaan (D+E) 145,587.70

4.2.43.(c) Pemotongan 1 Buah Pipa GIP Ø 600 mm 133,590.90

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 116,166.00
Pekerja L.01 OH 0.864 80,000.00 69,120.00
Tukang pipa L.02 OH 0.432 88,000.00 38,016.00
Mandor L.04 OH 0.086 105,000.00 9,030.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 116,166.00
E Overhead & Profit 15% 17,424.90
F Harga Satuan Pekerjaan (D+E) 133,590.90

4.2.44.(c) Pemotongan 1 Buah Pipa GIP Ø 800 mm 242,361.35

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 210,749.00
Pekerja L.01 OH 1.567 80,000.00 125,360.00
Tukang pipa L.02 OH 0.783 88,000.00 68,904.00
Mandor L.04 OH 0.157 105,000.00 16,485.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 210,749.00
E Overhead & Profit 15% 31,612.35
F Harga Satuan Pekerjaan (D+E) 242,361.35

4.2.45.(c) Pemotongan 1 Buah Pipa GIP Ø 900 mm 273,774.75

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 238,065.00
Pekerja L.01 OH 1.770 80,000.00 141,600.00
Tukang pipa L.02 OH 0.885 88,000.00 77,880.00
Mandor L.04 OH 0.177 105,000.00 18,585.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 238,065.00
E Overhead & Profit 15% 35,709.75
F Harga Satuan Pekerjaan (D+E) 273,774.75

4.2.46.(c) Pemotongan 1 Buah Pipa GIP Ø 1000 mm 305,280.15

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 265,461.00
Pekerja L.01 OH 1.974 80,000.00 157,920.00
Tukang pipa L.02 OH 0.987 88,000.00 86,856.00
Mandor L.04 OH 0.197 105,000.00 20,685.00
B Bahan

151
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 265,461.00
E Overhead & Profit 15% 39,819.15
F Harga Satuan Pekerjaan (D+E) 305,280.15

4.2.47.(c) Pemotongan 1 Buah Pipa GIP Ø 1100 mm 336,906.30

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 292,962.00
Pekerja L.01 OH 2.178 80,000.00 174,240.00
Tukang pipa L.02 OH 1.089 88,000.00 95,832.00
Mandor L.04 OH 0.218 105,000.00 22,890.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 292,962.00
E Overhead & Profit 15% 43,944.30
F Harga Satuan Pekerjaan (D+E) 336,906.30

4.2.48.(c) Pemotongan 1 Buah Pipa GIP Ø 1200 mm 368,411.70

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 320,358.00
Pekerja L.01 OH 2.382 80,000.00 190,560.00
Tukang pipa L.02 OH 1.191 88,000.00 104,808.00
Mandor L.04 OH 0.238 105,000.00 24,990.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 320,358.00
E Overhead & Profit 15% 48,053.70
F Harga Satuan Pekerjaan (D+E) 368,411.70

4.2.49.(c) Pemotongan 1 Buah Pipa DCI Ø 100 mm 9,363.30

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 7,647.00
Pekerja L.01 OH 0.071 80,000.00 5,680.00
Tukang pipa L.02 OH 0.014 88,000.00 1,232.00
Mandor L.04 OH 0.007 105,000.00 735.00
B Bahan
C PERALATAN 495.00
Sewa Tripot/ Tackel hari 0.003 165,000.00 495.00
D Jumlah A + B + C 8,142.00
E Overhead & Profit 15% 1,221.30
F Harga Satuan Pekerjaan (D+E) 9,363.30

4.2.50.(c) Pemotongan 1 Buah Pipa DCI Ø 125 mm 15,756.15

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 12,051.00
Pekerja L.01 OH 0.112 80,000.00 8,960.00
Tukang pipa L.02 OH 0.022 88,000.00 1,936.00
Mandor L.04 OH 0.011 105,000.00 1,155.00
B Bahan
C PERALATAN 1,650.00
Sewa Tripot/ Tackel hari 0.010 165,000.00 1,650.00
D Jumlah A + B + C 13,701.00
E Overhead & Profit 15% 2,055.15

152
F Harga Satuan Pekerjaan (D+E) 15,756.15

4.2.51.(c) Pemotongan 1 Buah Pipa DCI Ø 150 mm 23,213.90

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 17,216.00
Pekerja L.01 OH 0.159 80,000.00 12,720.00
Tukang pipa L.02 OH 0.032 88,000.00 2,816.00
Mandor L.04 OH 0.016 105,000.00 1,680.00
B Bahan
C PERALATAN 2,970.00
Sewa Tripot/ Tackel hari 0.018 165,000.00 2,970.00
D Jumlah A + B + C 20,186.00
E Overhead & Profit 15% 3,027.90
F Harga Satuan Pekerjaan (D+E) 23,213.90

4.2.52.(c) Pemotongan 1 Buah Pipa DCI Ø 200 mm 55,773.85

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 39,589.00
Pekerja L.01 OH 0.366 80,000.00 29,280.00
Tukang pipa L.02 OH 0.073 88,000.00 6,424.00
Mandor L.04 OH 0.037 105,000.00 3,885.00
B Bahan
C PERALATAN 8,910.00
Sewa Tripot/ Tackel hari 0.054 165,000.00 8,910.00
D Jumlah A + B + C 48,499.00
E Overhead & Profit 15% 7,274.85
F Harga Satuan Pekerjaan (D+E) 55,773.85

4.2.53.(c) Pemotongan 1 Buah Pipa DCI Ø 250 mm 73,053.75

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 51,480.00
Pekerja L.01 OH 0.476 80,000.00 38,080.00
Tukang pipa L.02 OH 0.095 88,000.00 8,360.00
Mandor L.04 OH 0.048 105,000.00 5,040.00
B Bahan
C PERALATAN 12,045.00
Sewa Tripot/ Tackel hari 0.073 165,000.00 12,045.00
D Jumlah A + B + C 63,525.00
E Overhead & Profit 15% 9,528.75
F Harga Satuan Pekerjaan (D+E) 73,053.75

4.2.54.(c) Pemotongan 1 Buah Pipa DCI Ø 300 mm 78,574.90

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 55,291.00
Pekerja L.01 OH 0.512 80,000.00 40,960.00
Tukang pipa L.02 OH 0.102 88,000.00 8,976.00
Mandor L.04 OH 0.051 105,000.00 5,355.00
B Bahan
C PERALATAN 13,035.00
Sewa Tripot/ Tackel hari 0.079 165,000.00 13,035.00
D Jumlah A + B + C 68,326.00
E Overhead & Profit 15% 10,248.90
F Harga Satuan Pekerjaan (D+E) 78,574.90

4.2.55.(c) Pemotongan 1 Buah Pipa DCI Ø 400 mm 146,928.60

HARGA SATUAN JUMLAH HARGA

153
HARGA SATUAN JUMLAH HARGA
URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 101,694.00
Pekerja L.01 OH 0.941 80,000.00 75,280.00
Tukang pipa L.02 OH 0.188 88,000.00 16,544.00
Mandor L.04 OH 0.094 105,000.00 9,870.00
B Bahan
C PERALATAN 26,070.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.158 165,000.00 26,070.00
D Jumlah A + B + C 127,764.00
E Overhead & Profit 15% 19,164.60
F Harga Satuan Pekerjaan (D+E) 146,928.60

4.2.56.(c) Pemotongan 1 Buah Pipa DCI Ø 450 mm 174,737.90

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 122,906.00
Pekerja L.01 OH 1.137 80,000.00 90,960.00
Tukang pipa L.02 OH 0.227 88,000.00 19,976.00
Mandor L.04 OH 0.114 105,000.00 11,970.00
B Bahan
C PERALATAN 29,040.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.176 165,000.00 29,040.00
D Jumlah A + B + C 151,946.00
E Overhead & Profit 15% 22,791.90
F Harga Satuan Pekerjaan (D+E) 174,737.90

4.2.57.(c) Pemotongan 1 Buah Pipa DCI Ø 500 mm 199,468.65

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 141,771.00
Pekerja L.01 OH 1.312 80,000.00 104,960.00
Tukang pipa L.02 OH 0.262 88,000.00 23,056.00
Mandor L.04 OH 0.131 105,000.00 13,755.00
B Bahan
C PERALATAN 31,680.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.192 165,000.00 31,680.00
D Jumlah A + B + C 173,451.00
E Overhead & Profit 15% 26,017.65
F Harga Satuan Pekerjaan (D+E) 199,468.65

4.2.58.(c) Pemotongan 1 Buah Pipa DCI Ø 600 mm 199,192.65

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 141,531.00
Pekerja L.01 OH 1.309 80,000.00 104,720.00
Tukang pipa L.02 OH 0.262 88,000.00 23,056.00
Mandor L.04 OH 0.131 105,000.00 13,755.00
B Bahan
C PERALATAN 31,680.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.192 165,000.00 31,680.00
D Jumlah A + B + C 173,211.00
E Overhead & Profit 15% 25,981.65
F Harga Satuan Pekerjaan (D+E) 199,192.65

4.2.59.(c) Pemotongan 1 Buah Pipa DCI Ø 800 mm 381,857.50

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 280,900.00
Pekerja L.01 OH 2.598 80,000.00 207,840.00

154
Tukang pipa L.02 OH 0.520 88,000.00 45,760.00
Mandor L.04 OH 0.260 105,000.00 27,300.00
B Bahan
C PERALATAN 51,150.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.310 165,000.00 51,150.00
D Jumlah A + B + C 332,050.00
E Overhead & Profit 15% 49,807.50
F Harga Satuan Pekerjaan (D+E) 381,857.50

4.2.60.(c) Pemotongan 1 Buah Pipa DCI Ø 900 mm 491,236.30

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 364,297.00
Pekerja L.01 OH 3.370 80,000.00 269,600.00
Tukang pipa L.02 OH 0.674 88,000.00 59,312.00
Mandor L.04 OH 0.337 105,000.00 35,385.00
B Bahan
C PERALATAN 62,865.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.381 165,000.00 62,865.00
D Jumlah A + B + C 427,162.00
E Overhead & Profit 15% 64,074.30
F Harga Satuan Pekerjaan (D+E) 491,236.30

4.2.61.(c) Pemotongan 1 Buah Pipa DCI Ø 1000 mm 583,518.05

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 434,642.00
Pekerja L.01 OH 4.021 80,000.00 321,680.00
Tukang pipa L.02 OH 0.804 88,000.00 70,752.00
Mandor L.04 OH 0.402 105,000.00 42,210.00
B Bahan
C PERALATAN 72,765.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.441 165,000.00 72,765.00
D Jumlah A + B + C 507,407.00
E Overhead & Profit 15% 76,111.05
F Harga Satuan Pekerjaan (D+E) 583,518.05

4.2.62.(c) Pemotongan 1 Buah Pipa DCI Ø 1100 mm 684,115.45

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 511,393.00
Pekerja L.01 OH 4.731 80,000.00 378,480.00
Tukang pipa L.02 OH 0.946 88,000.00 83,248.00
Mandor L.04 OH 0.473 105,000.00 49,665.00
B Bahan
C PERALATAN 83,490.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.506 165,000.00 83,490.00
D Jumlah A + B + C 594,883.00
E Overhead & Profit 15% 89,232.45
F Harga Satuan Pekerjaan (D+E) 684,115.45

4.2.63.(c) Pemotongan 1 Buah Pipa DCI Ø 1200 mm 793,212.50

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 594,710.00
Pekerja L.01 OH 5.502 80,000.00 440,160.00
Tukang pipa L.02 OH 1.100 88,000.00 96,800.00
Mandor L.04 OH 0.550 105,000.00 57,750.00
B Bahan
C PERALATAN 95,040.00

155
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.576 165,000.00 95,040.00
D Jumlah A + B + C 689,750.00
E Overhead & Profit 15% 103,462.50
F Harga Satuan Pekerjaan (D+E) 793,212.50

4.2.64.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 63 mm 10,566.20

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 3,083.00
Pekerja L.01 OH 0.028 80,000.00 2,240.00
Tukang pipa L.02 OH 0.006 88,000.00 528.00
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan
C PERALATAN 6,105.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.037 165,000.00 6,105.00
D Jumlah A + B + C 9,188.00
E Overhead & Profit 15% 1,378.20
F Harga Satuan Pekerjaan (D+E) 10,566.20

4.2.65.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 100 mm 18,096.40

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 9,136.00
Pekerja L.01 OH 0.085 80,000.00 6,800.00
Tukang pipa L.02 OH 0.017 88,000.00 1,496.00
Mandor L.04 OH 0.008 105,000.00 840.00
B Bahan
C PERALATAN 6,600.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.040 165,000.00 6,600.00
D Jumlah A + B + C 15,736.00
E Overhead & Profit 15% 2,360.40
F Harga Satuan Pekerjaan (D+E) 18,096.40

4.2.66.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 125 mm 24,507.65

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 14,381.00
Pekerja L.01 OH 0.133 80,000.00 10,640.00
Tukang pipa L.02 OH 0.027 88,000.00 2,376.00
Mandor L.04 OH 0.013 105,000.00 1,365.00
B Bahan
C PERALATAN 6,930.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.042 165,000.00 6,930.00
D Jumlah A + B + C 21,311.00
E Overhead & Profit 15% 3,196.65
F Harga Satuan Pekerjaan (D+E) 24,507.65

4.2.67.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 150 mm 31,384.65

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 19,866.00
Pekerja L.01 OH 0.184 80,000.00 14,720.00
Tukang pipa L.02 OH 0.037 88,000.00 3,256.00
Mandor L.04 OH 0.018 105,000.00 1,890.00
B Bahan
C PERALATAN 7,425.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.045 165,000.00 7,425.00
D Jumlah A + B + C 27,291.00
E Overhead & Profit 15% 4,093.65
F Harga Satuan Pekerjaan (D+E) 31,384.65

156
4.2.68.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 200 mm 70,587.00

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 51,480.00
Pekerja L.01 OH 0.476 80,000.00 38,080.00
Tukang pipa L.02 OH 0.095 88,000.00 8,360.00
Mandor L.04 OH 0.048 105,000.00 5,040.00
B Bahan
C PERALATAN 9,900.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.060 165,000.00 9,900.00
D Jumlah A + B + C 61,380.00
E Overhead & Profit 15% 9,207.00
F Harga Satuan Pekerjaan (D+E) 70,587.00

4.2.69.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 250 mm 95,328.10

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 71,674.00
Pekerja L.01 OH 0.663 80,000.00 53,040.00
Tukang pipa L.02 OH 0.133 88,000.00 11,704.00
Mandor L.04 OH 0.066 105,000.00 6,930.00
B Bahan
C PERALATAN 11,220.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.068 165,000.00 11,220.00
D Jumlah A + B + C 82,894.00
E Overhead & Profit 15% 12,434.10
F Harga Satuan Pekerjaan (D+E) 95,328.10

4.2.70.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 300 mm 106,216.30

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 80,482.00
Pekerja L.01 OH 0.745 80,000.00 59,600.00
Tukang pipa L.02 OH 0.149 88,000.00 13,112.00
Mandor L.04 OH 0.074 105,000.00 7,770.00
B Bahan
C PERALATAN 11,880.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.072 165,000.00 11,880.00
D Jumlah A + B + C 92,362.00
E Overhead & Profit 15% 13,854.30
F Harga Satuan Pekerjaan (D+E) 106,216.30

4.2.71.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 400 mm 198,937.35

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 155,664.00
Pekerja L.01 OH 1.440 80,000.00 115,200.00
Tukang pipa L.02 OH 0.288 88,000.00 25,344.00
Mandor L.04 OH 0.144 105,000.00 15,120.00
B Bahan
C PERALATAN 17,325.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.105 165,000.00 17,325.00
D Jumlah A + B + C 172,989.00
E Overhead & Profit 15% 25,948.35
F Harga Satuan Pekerjaan (D+E) 198,937.35

4.2.72.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 450 mm 194,252.25

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF

157
Rp Rp
A Tenaga 151,260.00
Pekerja L.01 OH 1.399 80,000.00 111,920.00
Tukang pipa L.02 OH 0.280 88,000.00 24,640.00
Mandor L.04 OH 0.140 105,000.00 14,700.00
B Bahan
C PERALATAN 17,655.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.107 165,000.00 17,655.00
D Jumlah A + B + C 168,915.00
E Overhead & Profit 15% 25,337.25
F Harga Satuan Pekerjaan (D+E) 194,252.25

4.2.73.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 500 mm 214,050.65

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 168,476.00
Pekerja L.01 OH 1.558 80,000.00 124,640.00
Tukang pipa L.02 OH 0.312 88,000.00 27,456.00
Mandor L.04 OH 0.156 105,000.00 16,380.00
B Bahan
C PERALATAN 17,655.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.107 165,000.00 17,655.00
D Jumlah A + B + C 186,131.00
E Overhead & Profit 15% 27,919.65
F Harga Satuan Pekerjaan (D+E) 214,050.65

4.2.74.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 600 mm 200,078.15

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 155,336.00
Pekerja L.01 OH 1.437 80,000.00 114,960.00
Tukang pipa L.02 OH 0.287 88,000.00 25,256.00
Mandor L.04 OH 0.144 105,000.00 15,120.00
B Bahan
C PERALATAN 18,645.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.113 165,000.00 18,645.00
D Jumlah A + B + C 173,981.00
E Overhead & Profit 15% 26,097.15
F Harga Satuan Pekerjaan (D+E) 200,078.15

4.2.75.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 800 mm 357,673.00

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 283,630.00
Pekerja L.01 OH 2.624 80,000.00 209,920.00
Tukang pipa L.02 OH 0.525 88,000.00 46,200.00
Mandor L.04 OH 0.262 105,000.00 27,510.00
B Bahan
C PERALATAN 27,390.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.166 165,000.00 27,390.00
D Jumlah A + B + C 311,020.00
E Overhead & Profit 15% 46,653.00
F Harga Satuan Pekerjaan (D+E) 357,673.00

4.2.76.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 900 mm 404,031.80

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 321,137.00
Pekerja L.01 OH 2.971 80,000.00 237,680.00
Tukang pipa L.02 OH 0.594 88,000.00 52,272.00

158
Mandor L.04 OH 0.297 105,000.00 31,185.00
B Bahan
C PERALATAN 30,195.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.183 165,000.00 30,195.00
D Jumlah A + B + C 351,332.00
E Overhead & Profit 15% 52,699.80
F Harga Satuan Pekerjaan (D+E) 404,031.80

4.2.77.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 1000 mm 450,773.55

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 358,812.00
Pekerja L.01 OH 3.319 80,000.00 265,520.00
Tukang pipa L.02 OH 0.664 88,000.00 58,432.00
Mandor L.04 OH 0.332 105,000.00 34,860.00
B Bahan
C PERALATAN 33,165.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.201 165,000.00 33,165.00
D Jumlah A + B + C 391,977.00
E Overhead & Profit 15% 58,796.55
F Harga Satuan Pekerjaan (D+E) 450,773.55

4.2.78.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 1100 mm 497,224.35

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 396,399.00
Pekerja L.01 OH 3.667 80,000.00 293,360.00
Tukang pipa L.02 OH 0.733 88,000.00 64,504.00
Mandor L.04 OH 0.367 105,000.00 38,535.00
B Bahan
C PERALATAN 35,970.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.218 165,000.00 35,970.00
D Jumlah A + B + C 432,369.00
E Overhead & Profit 15% 64,855.35
F Harga Satuan Pekerjaan (D+E) 497,224.35

4.2.79.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 1200 mm 543,966.10

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 434,074.00
Pekerja L.01 OH 4.015 80,000.00 321,200.00
Tukang pipa L.02 OH 0.803 88,000.00 70,664.00
Mandor L.04 OH 0.402 105,000.00 42,210.00
B Bahan
C PERALATAN 38,940.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.236 165,000.00 38,940.00
D Jumlah A + B + C 473,014.00
E Overhead & Profit 15% 70,952.10
F Harga Satuan Pekerjaan (D+E) 543,966.10

159
HARGA SATUAN JUMLAH HARGA
URAIAN KODE SAT KOEF
Rp Rp
4.3 HARGA SATUAN PEKERJAAN PEMASANGAN AKSESORIS PIPA
4.3.1.(c) Pemasangan 1 Buah Valve Ø 150 mm 233,743.25

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 192,255.00
Pekerja L.01 OH 1.429 80,000.00 114,320.00
Tukang pipa L.02 OH 0.715 88,000.00 62,920.00
Mandor L.04 OH 0.143 105,000.00 15,015.00
B Bahan -
Valve Ø 150 mm Buah 1.000 - -
C PERALATAN 11,000.00
Sewa Tripot/ Tackel hari 0.100 110,000.00 11,000.00
D Jumlah A + B + C 203,255.00
E Overhead & Profit 15% 30,488.25
F Harga Satuan Pekerjaan (D+E) 233,743.25

4.3.2.(c) Pemasangan 1 Buah Valve Ø 200 mm 312,502.15

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 230,491.00
OH Pekerja L.01 OH 1.714 80,000.00 137,120.00
OH Tukang pipa L.02 OH 0.857 88,000.00 75,416.00
OH Mandor L.04 OH 0.171 105,000.00 17,955.00
B Bahan -
Buah Valve Ø 200 mm Buah 1.000 - -
C PERALATAN 41,250.00
hari Sewa Tripot/ Tackel&handle crane 2 T hari 0.300 137,500.00 41,250.00
D Jumlah A + B + C 271,741.00
E Overhead & Profit 15% 40,761.15
F Harga Satuan Pekerjaan (D+E) 312,502.15

4.3.3.(c) Pemasangan 1 Buah Valve Ø 250 mm 328,314.65

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 230,491.00
Pekerja L.01 OH 1.714 80,000.00 137,120.00
Tukang pipa L.02 OH 0.857 88,000.00 75,416.00
Mandor L.04 OH 0.171 105,000.00 17,955.00
B Bahan -
Valve Ø 250 mm Buah 1.000 - -
C PERALATAN 55,000.00
Sewa Tripot/ Tackel hari 0.400 137,500.00 55,000.00
D Jumlah A + B + C 285,491.00
E Overhead & Profit 15% 42,823.65
F Harga Satuan Pekerjaan (D+E) 328,314.65

4.3.4.(c) Pemasangan 1 Buah Valve Ø 300 mm 388,412.50

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 269,000.00
Pekerja L.01 OH 2.000 80,000.00 160,000.00
Tukang pipa L.02 OH 1.000 88,000.00 88,000.00
Mandor L.04 OH 0.200 105,000.00 21,000.00
B Bahan -
Valve Ø 300 mm Buah 1.000 - -
C PERALATAN 68,750.00
Sewa Tripot/ Tackel&handle crane 2 T hari 0.500 137,500.00 68,750.00

160
D Jumlah A + B + C 337,750.00
E Overhead & Profit 15% 50,662.50
F Harga Satuan Pekerjaan (D+E) 388,412.50

4.3.5.(c) Pemasangan 1 Buah Valve Ø 400 mm 688,568.25

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 461,255.00
Pekerja L.01 OH 3.429 80,000.00 274,320.00
Tukang pipa L.02 OH 1.715 88,000.00 150,920.00
Mandor L.04 OH 0.343 105,000.00 36,015.00
B Bahan -
Valve Ø 400 mm Buah 1.000 - -
C PERALATAN 137,500.00
Sewa Tripot/ Tackel hari 1.000 137,500.00 137,500.00
D Jumlah A + B + C 598,755.00
E Overhead & Profit 15% 89,813.25
F Harga Satuan Pekerjaan (D+E) 688,568.25

4.3.6.(c) Pemasangan 1 Buah Valve Ø 450 mm 688,568.25

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 461,255.00
Pekerja L.01 OH 3.429 80,000.00 274,320.00
Tukang pipa L.02 OH 1.715 88,000.00 150,920.00
Mandor L.04 OH 0.343 105,000.00 36,015.00
B Bahan -
Valve Ø 450 mm Buah 1.000 - -
C PERALATAN 137,500.00
Sewa Tripot/ Tackel hari 1.000 137,500.00 137,500.00
D Jumlah A + B + C 598,755.00
E Overhead & Profit 15% 89,813.25
F Harga Satuan Pekerjaan (D+E) 688,568.25

4.3.7.(c) Pemasangan 1 Buah Valve Ø 500 mm 776,825.00

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 538,000.00
Pekerja L.01 OH 4.000 80,000.00 320,000.00
Tukang pipa L.02 OH 2.000 88,000.00 176,000.00
Mandor L.04 OH 0.400 105,000.00 42,000.00
B Bahan -
Valve Ø 500 mm Buah 1.000 - -
C PERALATAN 137,500.00
Sewa Tripot/ Tackel hari 1.000 137,500.00 137,500.00
D Jumlah A + B + C 675,500.00
E Overhead & Profit 15% 101,325.00
F Harga Satuan Pekerjaan (D+E) 776,825.00

4.3.8.(c) Pemasangan 1 Buah Valve Ø 600 mm 314,706.70

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 191,158.00
Pekerja L.01 OH 1.421 80,000.00 113,680.00
Tukang pipa L.02 OH 0.711 88,000.00 62,568.00
Mandor L.04 OH 0.142 105,000.00 14,910.00
B Bahan -
Valve Ø 600 mm Buah 1.000 - -
C PERALATAN 82,500.00
Sewa Tripot/ Tackel hari 0.600 137,500.00 82,500.00

161
Mobile crane ≤ 3 ton hari 0.300 357,142.86 107,142.86
D Jumlah A + B + C 273,658.00
E Overhead & Profit 15% 41,048.70
F Harga Satuan Pekerjaan (D+E) 314,706.70

4.3.9.(c) Pemasangan 1 Buah Valve Ø 700 mm 300,155.75

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 192,255.00
Pekerja L.01 OH 1.429 80,000.00 114,320.00
Tukang pipa L.02 OH 0.715 88,000.00 62,920.00
Mandor L.04 OH 0.143 105,000.00 15,015.00
B Bahan -
Valve Ø 700 mm Buah 1.000 - -
C PERALATAN 68,750.00
Sewa Tripot/ Tackel&handle crane 2 T hari 0.500 137,500.00 68,750.00
Mobile crane ≤ 3 ton hari 0.500 357,142.86 178,571.43
D Jumlah A + B + C 261,005.00
E Overhead & Profit 15% 39,150.75
F Harga Satuan Pekerjaan (D+E) 300,155.75

4.3.10.(c) Pemasangan 1 Buah Valve Ø 800 mm 355,360.35

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 240,259.00
Pekerja L.01 OH 1.786 80,000.00 142,880.00
Tukang pipa L.02 OH 0.893 88,000.00 78,584.00
Mandor L.04 OH 0.179 105,000.00 18,795.00
B Bahan -
Valve Ø 800 mm Buah 1.000 - -
C PERALATAN 68,750.00
Sewa Tripot/ Tackel hari 0.500 137,500.00 68,750.00
Mobile crane ≤ 3 ton hari 0.500 357,142.86 178,571.43
D Jumlah A + B + C 309,009.00
E Overhead & Profit 15% 46,351.35
F Harga Satuan Pekerjaan (D+E) 355,360.35

4.3.11.(c) Pemasangan 1 Buah Valve Ø 900 mm 383,658.40

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 230,491.00
Pekerja L.01 OH 1.714 80,000.00 137,120.00
Tukang pipa L.02 OH 0.857 88,000.00 75,416.00
Mandor L.04 OH 0.171 105,000.00 17,955.00
B Bahan -
Valve Ø 900 mm Buah 1.000 - -
C PERALATAN 103,125.00
Sewa Tripot/ Tackel hari 0.750 137,500.00 103,125.00
Mobile crane ≤ 3 ton hari 0.750 357,142.86 267,857.14
D Jumlah A + B + C 333,616.00
E Overhead & Profit 15% 50,042.40
F Harga Satuan Pekerjaan (D+E) 383,658.40

4.3.12.(c) Pemasangan 1 Buah Valve Ø 1000 mm 555,832.95

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 345,833.00
Pekerja L.01 OH 2.571 80,000.00 205,680.00
Tukang pipa L.02 OH 1.286 88,000.00 113,168.00
Mandor L.04 OH 0.257 105,000.00 26,985.00

162
B Bahan -
Valve Ø 1000 mm Buah 1.000 - -
C PERALATAN 137,500.00
Sewa Tripot/ Tackel hari 1.000 137,500.00 137,500.00
Mobile crane ≤ 3 ton hari 1.000 357,142.86 357,142.86
D Jumlah A + B + C 483,333.00
E Overhead & Profit 15% 72,499.95
F Harga Satuan Pekerjaan (D+E) 555,832.95

4.3.13.(c) Pemasangan 1 Buah Valve Ø 1100 mm 622,150.00

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 403,500.00
Pekerja L.01 OH 3.000 80,000.00 240,000.00
Tukang pipa L.02 OH 1.500 88,000.00 132,000.00
Mandor L.04 OH 0.300 105,000.00 31,500.00
B Bahan -
Valve Ø 1100 mm Buah 1.000 - -
C PERALATAN 137,500.00
Sewa Tripot/ Tackel hari 1.000 137,500.00 137,500.00
Mobile crane ≤ 3 ton hari 1.000 357,142.86 357,142.86
D Jumlah A + B + C 541,000.00
E Overhead & Profit 15% 81,150.00
F Harga Satuan Pekerjaan (D+E) 622,150.00

4.3.14.(c) Pemasangan 1 Buah Valve Ø 1200 mm 622,150.00

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 403,500.00
Pekerja L.01 OH 3.000 80,000.00 240,000.00
Tukang pipa L.02 OH 1.500 88,000.00 132,000.00
Mandor L.04 OH 0.300 105,000.00 31,500.00
B Bahan -
Valve Ø 1200 mm Buah 1.000 - -
C PERALATAN 137,500.00
Sewa Tripot/ Tackel hari 1.000 137,500.00 137,500.00
Mobile crane ≤ 3 ton hari 1.000 357,142.86 357,142.86
D Jumlah A + B + C 541,000.00
E Overhead & Profit 15% 81,150.00
F Harga Satuan Pekerjaan (D+E) 622,150.00

4.3.15.(c) Pemasangan 1 Buah Tee Ø 150 mm 471,901.35

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 14,299.00
Pekerja L.01 OH 0.106 80,000.00 8,480.00
Tukang pipa L.02 OH 0.053 88,000.00 4,664.00
Mandor L.04 OH 0.011 105,000.00 1,155.00
B Bahan 392,200.00
Tee Ø 150 mm Buah 1.000 392,200.00 392,200.00
C PERALATAN 3,850.00
Sewa Tripot/ Tackel hari 0.028 137,500.00 3,850.00
D Jumlah A + B + C 410,349.00
E Overhead & Profit 15% 61,552.35
F Harga Satuan Pekerjaan (D+E) 471,901.35

4.3.16.(c) Pemasangan 1 Buah Tee Ø 200 mm 972,533.73

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 29,094.00

163
Pekerja L.01 OH 0.216 80,000.00 17,280.00
Tukang pipa L.02 OH 0.108 88,000.00 9,504.00
Mandor L.04 OH 0.022 105,000.00 2,310.00
B Bahan 812,600.00
Tee Ø 200 mm Buah 1.000 812,600.00 812,600.00
C PERALATAN 3,987.50
Sewa Tripot/ Tackel hari 0.029 137,500.00 3,987.50
D Jumlah A + B + C 845,681.50
E Overhead & Profit 15% 126,852.23
F Harga Satuan Pekerjaan (D+E) 972,533.73

4.3.17.(c) Pemasangan 1 Buah Tee Ø 250 mm 56,639.23

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 43,889.00
Pekerja L.01 OH 0.326 80,000.00 26,080.00
Tukang pipa L.02 OH 0.163 88,000.00 14,344.00
Mandor L.04 OH 0.033 105,000.00 3,465.00
B Bahan -
Tee Ø 250 mm Buah 1.000 - -
C PERALATAN 5,362.50
Sewa Tripot/ Tackel hari 0.039 137,500.00 5,362.50
D Jumlah A + B + C 49,251.50
E Overhead & Profit 15% 7,387.73
F Harga Satuan Pekerjaan (D+E) 56,639.23

4.3.18.(c) Pemasangan 1 Buah Tee Ø 300 mm 146,549.10

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 58,684.00
Pekerja L.01 OH 0.436 80,000.00 34,880.00
Tukang pipa L.02 OH 0.218 88,000.00 19,184.00
Mandor L.04 OH 0.044 105,000.00 4,620.00
B Bahan -
Tee Ø 300 mm Buah 1.000 - -
C PERALATAN 68,750.00
Sewa Tripot/ Tackel hari 0.500 137,500.00 68,750.00
D Jumlah A + B + C 127,434.00
E Overhead & Profit 15% 19,115.10
F Harga Satuan Pekerjaan (D+E) 146,549.10

4.3.19.(c) Pemasangan 1 Buah Tee Ø 400 mm 180,577.60

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 88,274.00
Pekerja L.01 OH 0.656 80,000.00 52,480.00
Tukang pipa L.02 OH 0.328 88,000.00 28,864.00
Mandor L.04 OH 0.066 105,000.00 6,930.00
B Bahan -
Tee Ø 400 mm Buah 1.000 - -
C PERALATAN 68,750.00
Sewa Tripot/ Tackel hari 0.500 137,500.00 68,750.00
D Jumlah A + B + C 157,024.00
E Overhead & Profit 15% 23,553.60
F Harga Satuan Pekerjaan (D+E) 180,577.60

4.3.20.(c) Pemasangan 1 Buah Tee Ø 450 mm 197,591.85

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 103,069.00

164
Pekerja L.01 OH 0.766 80,000.00 61,280.00
Tukang pipa L.02 OH 0.383 88,000.00 33,704.00
Mandor L.04 OH 0.077 105,000.00 8,085.00
B Bahan -
Tee Ø 450 mm Buah 1.000 - -
C PERALATAN 68,750.00
Sewa Tripot/ Tackel hari 0.500 137,500.00 68,750.00
D Jumlah A + B + C 171,819.00
E Overhead & Profit 15% 25,772.85
F Harga Satuan Pekerjaan (D+E) 197,591.85

4.3.21.(c) Pemasangan 1 Buah Tee Ø 500 mm 230,418.60

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 117,864.00
Pekerja L.01 OH 0.876 80,000.00 70,080.00
Tukang pipa L.02 OH 0.438 88,000.00 38,544.00
Mandor L.04 OH 0.088 105,000.00 9,240.00
B Bahan -
Tee Ø 500 mm Buah 1.000 - -
C PERALATAN 82,500.00
Sewa Tripot/ Tackel hari 0.600 137,500.00 82,500.00
D Jumlah A + B + C 200,364.00
E Overhead & Profit 15% 30,054.60
F Harga Satuan Pekerjaan (D+E) 230,418.60

4.3.22.(c) Pemasangan 1 Buah Tee Ø 600 mm 200,090.23

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 147,454.00
Pekerja L.01 OH 1.096 80,000.00 87,680.00
Tukang pipa L.02 OH 0.548 88,000.00 48,224.00
Mandor L.04 OH 0.110 105,000.00 11,550.00
B Bahan -
Tee Ø 600 mm Buah 1.000 - -
C PERALATAN 26,537.50
Sewa Tripot/ Tackel hari 0.193 137,500.00 26,537.50
Mobile crane ≤ 3 ton hari 0.096 357,142.86 34,285.71
D Jumlah A + B + C 173,991.50
E Overhead & Profit 15% 26,098.73
F Harga Satuan Pekerjaan (D+E) 200,090.23

4.3.23.(c) Pemasangan 1 Buah Tee Ø 700 mm 239,178.73

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 177,044.00
Pekerja L.01 OH 1.316 80,000.00 105,280.00
Tukang pipa L.02 OH 0.658 88,000.00 57,904.00
Mandor L.04 OH 0.132 105,000.00 13,860.00
B Bahan -
Tee Ø 700 mm Buah 1.000 - -
C PERALATAN 30,937.50
Sewa Tripot/ Tackel hari 0.225 137,500.00 30,937.50
Mobile crane ≤ 3 ton hari 0.113 357,142.86 40,357.14
D Jumlah A + B + C 207,981.50
E Overhead & Profit 15% 31,197.23
F Harga Satuan Pekerjaan (D+E) 239,178.73

4.3.24.(c) Pemasangan 1 Buah Tee Ø 800 mm 278,267.23

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF

165
Rp Rp
A Tenaga 206,634.00
Pekerja L.01 OH 1.536 80,000.00 122,880.00
Tukang pipa L.02 OH 0.768 88,000.00 67,584.00
Mandor L.04 OH 0.154 105,000.00 16,170.00
B Bahan -
Tee Ø 800 mm Buah 1.000 - -
C PERALATAN 35,337.50
Sewa Tripot/ Tackel hari 0.257 137,500.00 35,337.50
Mobile crane ≤ 3 ton hari 0.129 357,142.86 46,071.43
D Jumlah A + B + C 241,971.50
E Overhead & Profit 15% 36,295.73
F Harga Satuan Pekerjaan (D+E) 278,267.23

4.3.25.(c) Pemasangan 1 Buah Tee Ø 900 mm 322,415.73

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 236,224.00
Pekerja L.01 OH 1.756 80,000.00 140,480.00
Tukang pipa L.02 OH 0.878 88,000.00 77,264.00
Mandor L.04 OH 0.176 105,000.00 18,480.00
B Bahan -
Tee Ø 900 mm Buah 1.000 - -
C PERALATAN 44,137.50
Sewa Tripot/ Tackel hari 0.321 137,500.00 44,137.50
Mobile crane ≤ 3 ton hari 0.161 357,142.86 57,500.00
D Jumlah A + B + C 280,361.50
E Overhead & Profit 15% 42,054.23
F Harga Satuan Pekerjaan (D+E) 322,415.73

4.3.26.(c) Pemasangan 1 Buah Tee Ø 1000 mm 363,559.85

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 265,814.00
Pekerja L.01 OH 1.976 80,000.00 158,080.00
Tukang pipa L.02 OH 0.988 88,000.00 86,944.00
Mandor L.04 OH 0.198 105,000.00 20,790.00
B Bahan -
Tee Ø 1000 mm Buah 1.000 - -
C PERALATAN 50,325.00
Sewa Tripot/ Tackel hari 0.366 137,500.00 50,325.00
Mobile crane ≤ 3 ton hari 0.183 357,142.86 65,357.14
D Jumlah A + B + C 316,139.00
E Overhead & Profit 15% 47,420.85
F Harga Satuan Pekerjaan (D+E) 363,559.85

4.3.27.(c) Pemasangan 1 Buah Tee Ø 1100 mm 400,750.85

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 295,404.00
Pekerja L.01 OH 2.196 80,000.00 175,680.00
Tukang pipa L.02 OH 1.098 88,000.00 96,624.00
Mandor L.04 OH 0.220 105,000.00 23,100.00
B Bahan -
Tee Ø 1100 mm Buah 1.000 - -
C PERALATAN 53,075.00
Sewa Tripot/ Tackel hari 0.386 137,500.00 53,075.00
Mobile crane ≤ 3 ton hari 0.193 357,142.86 68,928.57
D Jumlah A + B + C 348,479.00
E Overhead & Profit 15% 52,271.85
F Harga Satuan Pekerjaan (D+E) 400,750.85

166
4.3.28.(c) Pemasangan 1 Buah Tee Ø 1200 mm 444,899.35

HARGA SATUAN JUMLAH HARGA


URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 324,994.00
Pekerja L.01 OH 2.416 80,000.00 193,280.00
Tukang pipa L.02 OH 1.208 88,000.00 106,304.00
Mandor L.04 OH 0.242 105,000.00 25,410.00
B Bahan -
Tee Ø 1200 mm Buah 1.000 - -
C PERALATAN 61,875.00
Sewa Tripot/ Tackel hari 0.450 137,500.00 61,875.00
Mobile crane ≤ 3 ton hari 0.225 357,142.86 80,357.14
D Jumlah A + B + C 386,869.00
E Overhead & Profit 15% 58,030.35
F Harga Satuan Pekerjaan (D+E) 444,899.35

167
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
4.4 HARGA SATUAN PEKERJAAN PENYAMBUNGAN PIPA BARU KE PIPA LAMA
4.4.1.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 80 mm 1,334,535.40
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 197,219.00
Pekerja L.01 OH 1.466 80,000.00 117,280.00
Tukang pipa L.02 OH 0.733 88,000.00 64,504.00
Mandor L.04 OH 0.147 105,000.00 15,435.00
B Bahan -
Pipa Ø 80 mm Buah - 99,100.00 -
C PERALATAN 963,246.57
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.606 165,000.00 99,990.00
Sewa Genset 1500 watt hari 0.075 268,439.53 20,132.97
Sewa Pompa Submersible 3 m³ / h hari 0.968 772,700.00 747,973.60
Sewa Tripot/ Tackel hari 0.865 110,000.00 95,150.00
D Jumlah A + B + C 1,160,465.57
E Overhead & Profit 15% 174,069.83
F Harga Satuan Pekerjaan (D+E) 1,334,535.40

4.4.2.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 100 mm 1,500,222.71
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 221,429.00
Pekerja L.01 OH 1.646 80,000.00 131,680.00
Tukang pipa L.02 OH 0.823 88,000.00 72,424.00
Mandor L.04 OH 0.165 105,000.00 17,325.00
B Bahan
C PERALATAN 1,083,112.49
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.650 165,000.00 107,250.00
Sewa Genset 1500 watt hari 0.159 268,439.53 42,681.89
Sewa Pompa Submersible 3 m³ / h hari 1.078 772,700.00 832,970.60
Sewa Tripot/ Tackel hari 0.911 110,000.00 100,210.00
D Jumlah A + B + C 1,304,541.49
E Overhead & Profit 15% 195,681.22
F Harga Satuan Pekerjaan (D+E) 1,500,222.71

4.4.3.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 150 mm 1,914,440.98
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 281,954.00
Pekerja L.01 OH 2.096 80,000.00 167,680.00
Tukang pipa L.02 OH 1.048 88,000.00 92,224.00
Mandor L.04 OH 0.210 105,000.00 22,050.00
B Bahan
C PERALATAN 1,382,777.29
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.760 165,000.00 125,400.00
Sewa Genset 1500 watt hari 0.369 268,439.53 99,054.19
Sewa Pompa Submersible 3 m³ / h hari 1.353 772,700.00 1,045,463.10
Sewa Tripot/ Tackel hari 1.026 110,000.00 112,860.00
D Jumlah A + B + C 1,664,731.29
E Overhead & Profit 15% 249,709.69
F Harga Satuan Pekerjaan (D+E) 1,914,440.98

4.4.4.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 200 mm 2,328,659.25
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 342,479.00
Pekerja L.01 OH 2.546 80,000.00 203,680.00
Tukang pipa L.02 OH 1.273 88,000.00 112,024.00
Mandor L.04 OH 0.255 105,000.00 26,775.00
B Bahan
C PERALATAN 1,682,442.09
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.870 165,000.00 143,550.00
Sewa Genset 1500 watt hari 0.579 268,439.53 155,426.49
Sewa Pompa Submersible 3 m³ / h hari 1.628 772,700.00 1,257,955.60
Sewa Tripot/ Tackel hari 1.141 110,000.00 125,510.00
D Jumlah A + B + C 2,024,921.09
E Overhead & Profit 15% 303,738.16
F Harga Satuan Pekerjaan (D+E) 2,328,659.25

168
4.4.5.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 250 mm 2,742,877.53
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 403,004.00
Pekerja L.01 OH 2.996 80,000.00 239,680.00
Tukang pipa L.02 OH 1.498 88,000.00 131,824.00
Mandor L.04 OH 0.300 105,000.00 31,500.00
B Bahan
C PERALATAN 1,982,106.89
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.980 165,000.00 161,700.00
Sewa Genset 1500 watt hari 0.789 268,439.53 211,798.79
Sewa Pompa Submersible 3 m³ / h hari 1.903 772,700.00 1,470,448.10
Sewa Tripot/ Tackel hari 1.256 110,000.00 138,160.00
D Jumlah A + B + C 2,385,110.89
E Overhead & Profit 15% 357,766.63
F Harga Satuan Pekerjaan (D+E) 2,742,877.53

4.4.6.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 300 mm 3,157,095.80
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 463,529.00
Pekerja L.01 OH 3.446 80,000.00 275,680.00
Tukang pipa L.02 OH 1.723 88,000.00 151,624.00
Mandor L.04 OH 0.345 105,000.00 36,225.00
B Bahan
C PERALATAN 2,281,771.69
Peralatan potong pipa T2 /mekanik / cilinder saw hari 1.090 165,000.00 179,850.00
Sewa Genset 1500 watt hari 0.999 268,439.53 268,171.09
Sewa Pompa Submersible 3 m³ / h hari 2.178 772,700.00 1,682,940.60
Sewa Tripot/ Tackel hari 1.371 110,000.00 150,810.00
D Jumlah A + B + C 2,745,300.69
E Overhead & Profit 15% 411,795.10
F Harga Satuan Pekerjaan (D+E) 3,157,095.80

4.4.7.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 400 mm 3,985,532.34
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 584,579.00
Pekerja L.01 OH 4.346 80,000.00 347,680.00
Tukang pipa L.02 OH 2.173 88,000.00 191,224.00
Mandor L.04 OH 0.435 105,000.00 45,675.00
B Bahan
C PERALATAN 2,881,101.30
Peralatan potong pipa T2 /mekanik / cilinder saw hari 1.310 165,000.00 216,150.00
Sewa Genset 1500 watt hari 1.419 268,439.53 380,915.70
Sewa Pompa Submersible 3 m³ / h hari 2.728 772,700.00 2,107,925.60
Sewa Tripot/ Tackel hari 1.601 110,000.00 176,110.00
D Jumlah A + B + C 3,465,680.30
E Overhead & Profit 15% 519,852.04
F Harga Satuan Pekerjaan (D+E) 3,985,532.34

4.4.8.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 450 mm 4,399,750.62
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 645,104.00
Pekerja L.01 OH 4.796 80,000.00 383,680.00
Tukang pipa L.02 OH 2.398 88,000.00 211,024.00
Mandor L.04 OH 0.480 105,000.00 50,400.00
B Bahan
C PERALATAN 3,180,766.10
Peralatan potong pipa T2 /mekanik / cilinder saw hari 1.420 165,000.00 234,300.00
Sewa Genset 1500 watt hari 1.629 268,439.53 437,288.00
Sewa Pompa Submersible 3 m³ / h hari 3.003 772,700.00 2,320,418.10
Sewa Tripot/ Tackel hari 1.716 110,000.00 188,760.00
D Jumlah A + B + C 3,825,870.10
E Overhead & Profit 15% 573,880.52
F Harga Satuan Pekerjaan (D+E) 4,399,750.62

4.4.9.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 500 mm 4,813,968.89
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp

169
A Tenaga 705,629.00
Pekerja L.01 OH 5.246 80,000.00 419,680.00
Tukang pipa L.02 OH 2.623 88,000.00 230,824.00
Mandor L.04 OH 0.525 105,000.00 55,125.00
B Bahan
C PERALATAN 3,480,430.90
Peralatan potong pipa T2 /mekanik / cilinder saw hari 1.530 165,000.00 252,450.00
Sewa Genset 1500 watt hari 1.839 268,439.53 493,660.30
Sewa Pompa Submersible 3 m³ / h hari 3.278 772,700.00 2,532,910.60
Sewa Tripot/ Tackel hari 1.831 110,000.00 201,410.00
D Jumlah A + B + C 4,186,059.90
E Overhead & Profit 15% 627,908.99
F Harga Satuan Pekerjaan (D+E) 4,813,968.89

4.4.10.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 600 mm 5,642,405.43
HARGA
JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 826,679.00
Pekerja L.01 OH 6.146 80,000.00 491,680.00
Tukang pipa L.02 OH 3.073 88,000.00 270,424.00
Mandor L.04 OH 0.615 105,000.00 64,575.00
B Bahan
C PERALATAN 4,079,760.51
Peralatan potong pipa T2 /mekanik / cilinder saw hari 1.750 165,000.00 288,750.00
Sewa Genset 1500 watt hari 2.259 268,439.53 606,404.91
Sewa Pompa Submersible 3 m³ / h hari 3.828 772,700.00 2,957,895.60
Sewa Tripot/ Tackel hari 2.061 110,000.00 226,710.00
D Jumlah A + B + C 4,906,439.51
E Overhead & Profit 15% 735,965.93
F Harga Satuan Pekerjaan (D+E) 5,642,405.43

4.4.11.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 700 mm 6,470,841.98
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 947,729.00
Pekerja L.01 OH 7.046 80,000.00 563,680.00
Tukang pipa L.02 OH 3.523 88,000.00 310,024.00
Mandor L.04 OH 0.705 105,000.00 74,025.00
B Bahan
C PERALATAN 4,679,090.11
Peralatan potong pipa T2 /mekanik / cilinder saw hari 1.970 165,000.00 325,050.00
Sewa Genset 1500 watt hari 2.679 268,439.53 719,149.51
Sewa Pompa Submersible 3 m³ / h hari 4.378 772,700.00 3,382,880.60
Sewa Tripot/ Tackel hari 2.291 110,000.00 252,010.00
D Jumlah A + B + C 5,626,819.11
E Overhead & Profit 15% 844,022.87
F Harga Satuan Pekerjaan (D+E) 6,470,841.98

4.4.12.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 800 mm 7,299,278.52
HARGA
JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 1,068,779.00
Pekerja L.01 OH 7.946 80,000.00 635,680.00
Tukang pipa L.02 OH 3.973 88,000.00 349,624.00
Mandor L.04 OH 0.795 105,000.00 83,475.00
B Bahan
C PERALATAN 5,278,419.72
Peralatan potong pipa T2 /mekanik / cilinder saw hari 2.190 165,000.00 361,350.00
Sewa Genset 1500 watt hari 3.099 268,439.53 831,894.12
Sewa Pompa Submersible 3 m³ / h hari 4.928 772,700.00 3,807,865.60
Sewa Tripot/ Tackel hari 2.521 110,000.00 277,310.00
D Jumlah A + B + C 6,347,198.72
E Overhead & Profit 15% 952,079.81
F Harga Satuan Pekerjaan (D+E) 7,299,278.52