TRIAL PERHITUNGAN PLAT BETON
2 HITUNG P1 1.000 Unit Pemasangan Kusen dan Pintu Kaca Rangka Alumunium ( P1 ) 2,551,742.02
A TENAGA 280,765.63
L.01 0.518 OH Pekerja 80,000.00 41,420.00
L.02 2.089 OH Tukang Besi 90,000.00 187,987.50
L.03 0.343 OH Kepala Tukang 105,000.00 35,988.75
L.04 0.146 OH Mandor 105,000.00 15,369.38
B BAHAN 1,938,140.48
5.355 m' Profil open back warna coklat 57,900.00 310,054.50
2.163 m' Profil tiang engsel warna coklat (belakang) 99,000.00 214,137.00
2.163 m' Profil tiang swing warna coklat (depan) 92,800.00 200,726.40
1.680 m' Profil ambang atas warna coklat + tutup warna coklat 74,500.00 125,160.00
0.840 m' Profil ambang bawah warna coklat + tutup warna coklat 110,600.00 92,904.00
5.355 m' Profil stoper pintu warna coklat 21,300.00 114,061.50
5.355 m' Karet tatapan 3,400.00 18,207.00
1.282 m2 Kaca Bening 5 mm 157,500.00 201,922.88
1.000 set Handle Pintu 420,000.00 420,000.00
3.000 Bh Engsel Pintu 4" 54,600.00 163,800.00
11.000 buah Skrup Fixer 475.00 5,225.00
0.803 Tube Sealant Kusen + kaca 33,600.00 26,989.20
0.440 m' Profil Spigot 12,200.00 5,368.00
0.594 m2 Sticker Sandblast 52,500.00 31,185.00
2.100 m' Bulu Moher 4,000.00 8,400.00
C PERALATAN
D Jumlah A + B + C 2,218,906.10
E Overhead & Profit 15% 332,835.92
F Harga Satuan Pekerjaan (D+E) 2,551,742.02
5 HITUNG J2 1.000 Unit Pemasangan Kusen dan Jendela Kaca Mati Rangka Alumunium ( J2) 1,991,057.19
A TENAGA 251,476.15
L.01 1.383 OH Pekerja 80,000.00 110,671.68
L.02 1.383 OH Tukang Besi 90,000.00 124,505.64
L.03 0.081 OH Kepala Tukang 105,000.00 8,537.14
L.04 0.074 OH Mandor 105,000.00 7,761.69
B BAHAN 1,479,877.93
8.232 m' Alumunium Warna Coklat 4" tipe Z tbl 1 mm 106,375.00 875,679.00
7.854 m' Tutup profil Z Alumunium warna coklat 36,725.00 288,438.15
1.600 m2 Kaca Bening 5 mm 157,500.00 252,031.50
16.000 buah Skrup Fixer 475.00 7,600.00
1.235 Tube Sealant Kusen + Kaca 33,600.00 41,489.28
1.200 m' Profil Spigot 12,200.00 14,640.00
C PERALATAN
D Jumlah A + B + C 1,731,354.08
E Overhead & Profit 15% 259,703.11
F Harga Satuan Pekerjaan (D+E) 1,991,057.19
6 HITUNG J3 1.000 Unit Pemasangan Kusen dan Jendela Kaca Rangka Alumunium ( J3 ) 2,960,873.41
A TENAGA 259,082.82
L.01 0.854 OH Pekerja 80,000.00 68,318.08
L.02 1.854 OH Tukang Besi 90,000.00 166,857.84
L.03 0.185 OH Kepala Tukang 105,000.00 19,466.75
L.04 0.042 OH Mandor 105,000.00 4,440.16
B BAHAN 2,315,589.71
8.232 m' Profil open back warna coklat 57,900.00 476,632.80
3.654 m' Rangka casement 3 profil warna coklat 51,600.00 188,546.40
1.176 m' Alumunium Warna Coklat 4" tipe Z tbl 1 mm 95,800.00 112,660.80
7.728 m' Tutup profil Z Alumunium warna coklat 33,000.00 255,024.00
3.654 m' Karet tatapan 3,400.00 12,423.60
1.304 m2 Kaca Bening 5 mm 157,500.00 205,428.83
4.000 Set Cesement 12" 229,900.00 919,600.00
2.000 Bh Rambuncis 31,500.00 63,000.00
16.000 buah Skrup Fixer 475.00 7,600.00
1.235 Tube Sealant Kusen + Kaca 33,600.00 41,489.28
2.720 m' Profil Spigot 12,200.00 33,184.00
C PERALATAN
D Jumlah A + B + C 2,574,672.53
E Overhead & Profit 15% 386,200.88
F Harga Satuan Pekerjaan (D+E) 2,960,873.41
7 HITUNG J4 1.000 Unit Pemasangan Kusen dan Jendela Kaca Rangka Alumunium ( J4 ) 1,624,335.57
A TENAGA 259,082.82
L.01 0.854 OH Pekerja 80,000.00 68,318.08
L.02 1.854 OH Tukang Besi 90,000.00 166,857.84
L.03 0.185 OH Kepala Tukang 105,000.00 19,466.75
L.04 0.042 OH Mandor 105,000.00 4,440.16
B BAHAN 1,153,382.89
3.906 m' Profil open back warna coklat 57,900.00 226,157.40
2.489 m' Rangka casement 3 profil warna coklat 51,600.00 128,406.60
0.536 m' Alumunium Warna Coklat 4" tipe Z tbl 1 mm 95,800.00 51,300.90
4.158 m' Tutup profil Z Alumunium warna coklat 33,000.00 137,214.00
2.489 m' Karet tatapan 3,400.00 8,460.90
0.478 m2 Kaca Bening 5 mm 157,500.00 75,344.85
2.000 Set Cesement 12" 229,900.00 459,800.00
1.000 Bh Rambuncis 31,500.00 31,500.00
8.000 buah Skrup Fixer 475.00 3,800.00
0.586 Tube Sealant Kusen + Kaca 33,600.00 19,686.24
0.960 m' Profil Spigot 12,200.00 11,712.00
C PERALATAN
D Jumlah A + B + C 1,412,465.71
E Overhead & Profit 15% 211,869.86
F Harga Satuan Pekerjaan (D+E) 1,624,335.57
8 HITUNG J5 1.000 Unit Pemasangan Kusen dan Jendela Kaca Mati Rangka Alumunium ( J5 ) 10,785,989.70
A TENAGA 259,082.82
L.01 0.854 OH Pekerja 80,000.00 68,318.08
L.02 1.854 OH Tukang Besi 90,000.00 166,857.84
L.03 0.185 OH Kepala Tukang 105,000.00 19,466.75
L.04 0.042 OH Mandor 105,000.00 4,440.16
B BAHAN 9,120,038.66
29.416 m' Alumunium Warna Coklat 4" tipe Z tbl 1 mm 95,800.00 2,818,028.85
32.099 m' Tutup profil Z Alumunium warna coklat 33,000.00 1,059,250.50
29.416 m' Karet tatapan 3,400.00 100,013.55
16.249 m2 Kaca Bening 8 mm 303,700.00 4,934,745.38
59.000 buah Skrup Fixer 475.00 28,025.00
4.412 Tube Sealant Kusen + Kaca 33,600.00 148,255.38
2.600 m' Profil Spigot 12,200.00 31,720.00
C PERALATAN
D Jumlah A + B + C 9,379,121.48
E Overhead & Profit 15% 1,406,868.22
F Harga Satuan Pekerjaan (D+E) 10,785,989.70
9 HITUNG J6 1.000 Unit Pemasangan Kusen dan Jendela Kaca Mati Rangka Alumunium ( J6 ) 1,669,486.99
A TENAGA 259,082.82
L.01 0.854 OH Pekerja 80,000.00 68,318.08
L.02 1.854 OH Tukang Besi 90,000.00 166,857.84
L.03 0.185 OH Kepala Tukang 105,000.00 19,466.75
L.04 0.042 OH Mandor 105,000.00 4,440.16
B BAHAN 1,192,644.99
6.636 m' Alumunium Warna Coklat 4" tipe Z tbl 1 mm 95,800.00 635,728.80
6.447 m' Tutup profil Z Alumunium warna coklat 33,000.00 212,751.00
6.636 m' Karet tatapan 3,400.00 22,562.40
1.759 m2 Kaca Bening 5 mm 157,500.00 277,102.35
13.000 buah Skrup Fixer 475.00 6,175.00
0.995 Tube Sealant Kusen + Kaca 33,600.00 33,445.44
0.400 m' Profil Spigot 12,200.00 4,880.00
C PERALATAN
D Jumlah A + B + C 1,451,727.81
E Overhead & Profit 15% 217,759.17
F Harga Satuan Pekerjaan (D+E) 1,669,486.99
10 HITUNG PJ1 1.000 Unit Pemasangan Kusen dan Pintu Jendela Kaca Rangka Alumunium ( PJ1 ) 5,761,758.36
A TENAGA 280,765.63
L.01 0.518 OH Pekerja 80,000.00 41,420.00
L.02 2.089 OH Tukang Besi 90,000.00 187,987.50
L.03 0.343 OH Kepala Tukang 105,000.00 35,988.75
L.04 0.146 OH Mandor 105,000.00 15,369.38
B BAHAN 4,729,459.04
6.132 m' Profil open back warna coklat 57,900.00 355,042.80
9.500 m' Alumunium Warna Coklat 4" tipe Z tbl 1 mm 95,800.00 910,100.00
11.720 m' Tutup profil Z Alumunium warna coklat 33,000.00 386,760.00
2.567 m' Profil tiang engsel warna coklat (belakang) 99,000.00 254,157.75
2.567 m' Profil tiang swing warna coklat (depan) 92,800.00 238,240.80
1.806 m' Profil ambang atas warna coklat + tutup warna coklat 74,500.00 134,547.00
0.903 m' Profil ambang bawah warna coklat + tutup warna coklat 110,600.00 99,871.80
6.132 m' Profil stoper pintu warna coklat 21,300.00 130,611.60
15.632 m' Karet tatapan 3,400.00 53,148.80
9.103 m2 Kaca Bening 5 mm 157,500.00 1,433,755.21
1.000 set Handle Pintu 420,000.00 420,000.00
3.000 Bh Engsel Pintu 4" 54,600.00 163,800.00
31.000 buah Skrup Fixer 475.00 14,725.00
2.345 Tube Sealant Kusen + kaca 33,600.00 78,785.28
1.240 m' Profil Spigot 12,200.00 15,128.00
0.594 m2 Sticker Sandblast 52,500.00 31,185.00
2.400 m' Bulu Moher 4,000.00 9,600.00
C PERALATAN
D Jumlah A + B + C 5,010,224.66
E Overhead & Profit 15% 751,533.70
F Harga Satuan Pekerjaan (D+E) 5,761,758.36
11 HITUNG BV 1.000 Unit Pemasangan Boven ( BV1 ) 622,129.39
A TENAGA 211,981.04
L.01 0.600 OH Pekerja 80,000.00 48,018.64
L.02 1.600 OH Tukang Besi 90,000.00 144,020.97
L.03 0.160 OH Kepala Tukang 105,000.00 16,802.45
L.04 0.030 OH Mandor 105,000.00 3,138.99
B BAHAN 329,001.04
2.331 m' Profil open back warna coklat 57,900.00 134,964.90
1.974 m' Glassbead casement 33,000.00 65,142.00
1.890 m' Profil tutup polos 32,500.00 61,425.00
2.331 m' Karet tatapan 3,400.00 7,925.40
0.231 m2 Kaca es kabur t : 5 mm 175,500.00 40,540.50
5.000 buah Skrup Fixer 475.00 2,375.00
0.350 Tube Sealant Kusen + Kaca 33,600.00 11,748.24
0.400 m' Profil Spigot 12,200.00 4,880.00
C PERALATAN
D Jumlah A + B + C 540,982.08
E Overhead & Profit 15% 81,147.31
F Harga Satuan Pekerjaan (D+E) 622,129.39
12 HITUNG PKM 1.000 Unit Pemasangan Kusen dan Pintu Kamar Mandi Rangka Alumunium ( PKM ) 2,529,740.67
A TENAGA 280,765.63
L.01 0.518 OH Pekerja 80,000.00 41,420.00
L.02 2.089 OH Tukang Besi 90,000.00 187,987.50
L.03 0.343 OH Kepala Tukang 105,000.00 35,988.75
L.04 0.146 OH Mandor 105,000.00 15,369.38
B BAHAN 1,919,008.87
5.250 m' Profil open back warna coklat 57,900.00 303,975.00
2.210 m' Profil tiang engsel warna coklat (belakang) 99,000.00 218,814.75
2.210 m' Profil tiang swing warna coklat (depan) 92,800.00 205,111.20
1.470 m' Profil ambang atas warna coklat + tutup warna coklat 74,500.00 109,515.00
0.735 m' Profil ambang bawah warna coklat + tutup warna coklat 110,600.00 81,291.00
5.250 m' Profil stoper pintu warna coklat 21,300.00 111,825.00
0.588 m' Glassbead casement 33,000.00 19,404.00
9.639 m' sprandell warna coklat lebar 10 cm 15,000.00 144,585.00
1.176 m' hollow 1x2 15,000.00 17,640.00
5.250 m' Karet tatapan 3,400.00 17,850.00
0.162 m2 Kaca es kabur t : 5 mm 175,500.00 28,359.92
1.000 set Handle Pintu 420,000.00 420,000.00
3.000 Bh Engsel Pintu 4" 54,600.00 163,800.00
11.000 buah Skrup Fixer 475.00 5,225.00
0.788 Tube Sealant Kusen + kaca 33,600.00 26,460.00
0.440 m' Profil Spigot 12,200.00 5,368.00
0.594 m2 Sticker Sandblast 52,500.00 31,185.00
2.150 m' Bulu Moher 4,000.00 8,600.00
C PERALATAN
D Jumlah A + B + C 2,199,774.50
E Overhead & Profit 15% 329,966.17
F Harga Satuan Pekerjaan (D+E) 2,529,740.67
OE
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
CK #REF!
#REF! A. 1.1.1 HARGA SATUAN PEKERJAAN PERSIAPAN
1 Err:509 Err:509 m2 Err:509
2 #REF! #REF! m2 #REF!
Harsat Pekerjaan 11
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
13 A.4.2.1.19 Pemasangan 1 m' Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm m 86,225.85
16 A.4.2.1.22 Pemasangan 1 m2 Atap Pelana Rangka Atap Baja Ringan profil C75 m2 177,872.49
17 A.4.2.1.23 Pemasangan 1 m2 Atap Limasan Rangka Atap Baja Ringan profil C75 m2 194,564.97
18 A.4.2.1.24 Pemasangan 1 m2 Kusen Aluminium m2 101,519.70
19 A.4.2.1.25 Pemasangan 1 m2 Pintu Aluminium Strip lbr 8 cm m2 1,112,031.03
20 A.4.2.1.26 Pemasangan 1 m2 Pintu Kaca rangka Aluminium m2 574,536.55
21 A.4.2.1.27 Pemasangan 1 m2 Venetions Blinds dan Vertical Blinds m2 352,549.75
Harsat Pekerjaan 12
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
44 A.4.4.3.57 Pemasangan 1 m2 Dinding Batu Paros / Batu Tempel Hitam m2 323,144.54
46 A.4.4.3.59 Pemasangan 1 m2 Wallpaper lbr 50cm m2 297,717.75
47 A.4.4.3.60 Pemasangan 1 m2 Floor Hardener m2 60,133.50
50 A.4.4.3.63 Pemasangan 1 m2 Paving Block (Block Beton) Natural tbl. 6cm m2 189,399.25
51 A.4.4.3.64 Pemasangan 1 m2 Paving Block (Block Beton) Natural tbl. 8cm m2 247,958.40
52 A.4.4.3.65 Pemasangan 1 m2 Paving Block (Block Beton) berwarna tbl. 6cm m2 203,836.70
53 A.4.4.3.66 Pemasangan 1 m2 Paving Block (Block Beton) berwarna tbl. 8cm m2 269,806.22
Harsat Pekerjaan 13
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
17 A.4.6.1.17 Pemasangan 1m2 Rangka Atap Genteng Beton, Kayu Klas II m2 200,889.94
18 A.4.6.1.18 Pemasangan 1m2 Rangka Atap Sirap, Kayu Klas II m2 1,473,427.73
19 A.4.6.1.19 Pemasangan 1m2 Rangka Langit-langit (50x1,00) m, kayu Klas II atau III m2 196,597.49
20 A.4.6.1.20 Pemasangan 1m2 Rangka Langit-langit (60x60) cm, kayu Klas II atau III m2 202,308.84
21 A.4.6.1.21 Pemasangan 1m' Lisplank Uk. (3x20)cm, Kayu klas I atau II m 517,609.25
22 A.4.6.1.22 Pemasangan 1m' Lisplank Uk. (3x30)cm Kayu klas I atau klas II m2 130,235.32
23 A.4.6.1.23 Pemasangan 1m2 Rangka Dinding Pemisah (60x120) cm Kayu klas II atau III m2 314,983.62
24 A.4.6.1.24 Pemasangan 1m2 Dinding Pemisah Teakwood Rangkap Rangka Kayu Klas II m2 421,764.00
25 A.4.6.1.25 Pemasangan 1m2 Dinding Pemisah Plywood Rangkap Rangka Kayu Klas II m2 421,195.32
26 A.4.6.1.26 Pemasangan 1m2 Dinding Lambrisering dari Papan klas I m2 581,812.31
27 A.4.6.1.27 Pemasangan 1m2 Dinding Lambrisering dari Plywood ukuran (120x240) cm m2 40,250.00
28 A.4.6.1.28 Pemasangan 1m2 Dinding Bilik, Rangka Kayu Klas III atau IV m2 151,740.55
Harsat Pekerjaan 14
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
24 A.5.1.1.28 Pemasangan 1 m' Pipa PVC tipe AW Ø 1½" m' 57,056.29
HITUNG PG10 Pemasangan 1 m' Pipa PVC tipe AW Ø 1½" m' 46,391.96
25 A.5.1.1.29 Pemasangan 1 m' Pipa PVC tipe AW Ø 2" m' 72,682.88
HITUNG PG11 Pemasangan 1 m' Pipa PVC tipe AW Ø 2" m' 57,985.88
26 A.5.1.1.30 Pemasangan 1 m' Pipa PVC tipe AW Ø 2½" m' 80,488.50
HITUNG PG12 Pemasangan 1 m' Pipa PVC tipe AW Ø 2½" m' 65,791.50
27 A.5.1.1.31 Pemasangan 1 m' Pipa PVC tipe AW Ø 3" m' 170,237.38
HITUNG PG13 Pemasangan 1 m' Pipa PVC tipe AW Ø 3" m' 132,379.38
28 A.5.1.1.32 Pemasangan 1 m' Pipa PVC tipe AW Ø 4" m' 237,437.63
HITUNG PG14 Pemasangan 1 m' Pipa PVC tipe AW Ø 4" m' 182,237.63
29 A.5.1.1.33 Pemasangan 1 Buah Bak Cuci Piring Stainless stell bh 332,378.75
30 A.5.1.1.34 Pemasangan 1 Buah Bak Cuci Piring Teraso bh 1,159,769.25
31 A.5.1.1.35 Pemasangan 1 Buah Kran Ø ½" atau Ø ¾" bh 144,437.13
32 A.5.1.1.36 Pemasangan 1 Buah Floor Drain bh 115,661.25
33 A.5.1.1.37 Pemasangan 1 m' Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm m' 137,761.49
34 A.5.1.1.38 Pemasangan 1 m' Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm m' 61,267.34
35 A.5.1.1.39 Pemasangan 1 m' Pipa Beton Ø 15-20 cm m' 127,445.47
36 A.5.1.1.40 Pemasangan 1 m' Pipa Beton Ø 30-100 cm m' 650,543.39
XVIII HARGA SATUAN ASPAL (Mengikuti Analisa Harga Terbaru Bina Marga)
Harsat Pekerjaan 15
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
UM #REF!
#REF! 1.1 HARGA SATUAN PEKERJAAN PERSIAPAN
1 1.1.a.(c) Pembuatan 1m' Pagar Sementara dari Kayu Tinggi 2 m m' 796,561.53
2 1.1.b.(c) Pembuatan 1 m' Pagar Sementara dari Seng Gelombang Tinggi 2 m m' 961,376.66
3 1.1.c.(c) Membuat 1 m' Pagar Sementara dari Kawat Duri Tinggi 1.8 m m' 460,809.60
4 1.7.4.d.(a) Pasang 1m' Bouwplank sebagai acuan dalam pembuatan infrastruktur m' 69,416.76
5 1.1.e.(c) Pembuatan 1 m2 Kantor Sementara/ Gudang dg Lantai Plesteran, dinding setengah tembok m2 2,765,961.60
6 1.1.f.(c) Pembersihan dan Pengupasan 1 m2 Permukaan Tanah (Striping) s.d Tanaman Ø 2cm m2 9,803.75
7 1.1.h.(a) Pembongkaran 1 m3 Dinding Tembok Bata m3 617,348.75
8 1.1.2.a Pemagaran 1 m' daerah kerja dengan seng gelombang BJLS-30, tinggi 1,8 m dengan rangka baja L,40.40.4 m' 598,363.53
9 1.1.2.b Pemagaran 1 m' daerah kerja dengan seng gelombang BJLS-30, tinggi 1,8 m dengan rangka Kayu m' 435,537.90
10 1.1.3.(a) Pembuatan 1 unit Direksi Keet dan Gudang m2 1,627,904.78
11 1.1.4.a.(a) Pembuatan 1 buah Papan Nama pekerjaan dengan multiflex 18mm, frame Aluminium siku dan tiang kayu 8/12, printing ban bh 980,561.88
12 1.1.4.b.(a) Pembuatan 1 buah Papan Nama pekerjaan dengan multiflex 10mm, frame Aluminium siku dan tiang kayu 5/7, printing bann bh 416,320.13
13 1.1.5.a.(a) Investigasi Lapangan ls 77,625.00
14 2.1.2.a.5.c Pembongkaran 1m3 Pasangan batu dengan alat m3 38,120.83
15 2.1.4.b Pembongkaran 1m3 Pasangan bata merah dengan alat m3 20,803.00
16 2.2.10.a Pembongkaran 1m3 beton dengan alat m3 38,120.83
Harsat Pekerjaan 16
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
39 1.7.14.b(a) 1 m3 Timbunan atau Urugan Kembali Tanah Liat termasuk perataan dan perapihan m3 113,473.38
40 1.7.14.c.(a) 1 m3 Pemadatan Tanah m3 16,019.09
41 1.7.14.d.(a) 1 m3 Pemadatan Tanah 1 m3 per 20 cm dengan alat timbris m3 52,037.50
42 1.7.2.d(c) 1 m3 Timbunan Pasir m3 274,595.85
43 1.7.14.f.(a) 1 m3 Pemadatan Pasir m3 8,558.88
44 1.7.15.1.a.(a) Mengangkut 1 m3 tanah lepas, jarak angkut s.d. 10 m m3 20,624.68
45 1.7.15.1.b.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 10 s.d. 20 m m3 22,089.20
46 1.7.15.1.c.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 20 s.d. 30 m m3 23,164.45
47 1.7.15.1.d.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 30 s.d. 40 m m3 24,555.38
48 1.7.15.1.e.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 40 s.d. 50 m m3 26,684.60
49 1.7.15.1.f.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 50 s.d. 100 m m3 33,724.90
50 1.7.15.1.g.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 100 s.d. 200 m m3 47,477.75
51 1.7.15.1.h.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 200 s.d. 300 m m3 63,843.98
52 1.7.15.1.i.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 300 s.d. 400 m m3 83,077.73
53 1.7.15.1.j.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 400 s.d. 500 m m3 107,222.55
54 1.7.15.1.k.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 500 s.d. 600 m m3 135,056.00
55 1.7.15.1.l.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 600 untuk setiap penambahan jarak angkut 100 m m3 26,954.28
56 1.7.15.2.a.(a) Menurunkan 1 m3 material, sampai beda tinggi > 0 s.d. 1 m m3 3,921.50
57 1.7.15.2.b.(a) Menurunkan 1 m3 material, sampai beda tinggi > 1 s.d. 2 m m3 5,686.18
58 1.7.15.2.c.(a) Menurunkan 1 m3 material, sampai beda tinggi > 2 s.d. 3 m m3 7,542.85
59 1.7.15.2.d.(a) Menurunkan 1 m3 material, sampai beda tinggi > 3 s.d. 4 m m3 9,607.68
60 1.7.15.2.e.(a) Menurunkan 1 m3 material, sampai beda tinggi > 4 s.d. 5 m m3 11,764.50
61 1.7.15.2.f.(a) Menurunkan 1 m3 material, sampai beda tinggi > 5 s.d. 6 m m3 13,921.33
62 1.7.15.2.g.(a) Menurunkan 1 m3 material, sampai beda tinggi > 6 s.d. 7 m m3 16,274.23
63 1.7.15.2.h.(a) Menurunkan 1 m3 material, sampai beda tinggi > 7 s.d. 8 m m3 18,627.13
64 1.7.15.2.i.(a) Menurunkan 1 m3 material, sampai beda tinggi > 8 s.d. 9 m m3 21,176.10
65 1.7.15.2.j.(a) Menurunkan 1 m3 material, sampai beda tinggi > 9 s.d. 10 m m3 23,621.00
66 1.7.15.2.k.(a) Menurunkan 1 m3 material, sampai beda tinggi > 10 m untuk setiap tambahan 1 m m3 2,352.90
67 1.7.15.3.a.(a) Menaikkan 1 m3 material, sampai beda tinggi > 0 s.d. 1 m m3 19,607.50
68 1.7.15.3.b.(a) Menaikkan 1 m3 material, sampai beda tinggi > 1 s.d. 2 m m3 28,626.95
69 1.7.15.3.c.(a) Menaikkan 1 m3 material, sampai beda tinggi > 2 s.d. 3 m m3 38,038.55
70 1.7.15.3.d.(a) Menaikkan 1 m3 material, sampai beda tinggi > 3 s.d. 4 m m3 48,234.45
71 1.7.15.3.e.(a) Menaikkan 1 m3 material, sampai beda tinggi > 4 s.d. 5 m m3 58,626.43
72 1.7.15.3.f.(a) Menaikkan 1 m3 material, sampai beda tinggi > 5 s.d. 6 m m3 69,606.63
73 1.7.15.3.g.(a) Menaikkan 1 m3 material, sampai beda tinggi > 6 s.d. 7 m m3 81,175.05
74 1.7.15.3.h.(a) Menaikkan 1 m3 material, sampai beda tinggi > 7 s.d. 8 m m3 93,135.63
75 1.7.15.3.i.(a) Menaikkan 1 m3 material, sampai beda tinggi > 8 s.d. 9 m m3 105,684.43
76 1.7.15.3.j.(a) Menaikkan 1 m3 material, sampai beda tinggi > 9 s.d. 10 m m3 118,429.30
77 1.7.16.a.(a) 1 m3 Pencampuran Tanah dan Semen m3 236,560.75
78 1.7.16.b.(a) 1 m3 Pencampuran Tanah dan Semen + Pemadat Timbris m3 109,710.00
79 1.7.16.c.(a) 1 m3 Pencampuran Tanah dan Semen + Pemadat Stamper m3 54,954.40
Harsat Pekerjaan 17
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
5 2.1.3.3.b.(c) Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP m2 272,150.32
6 2.1.3.3.c.(a) Mortar tipe N, fc' = 5,2 Mpa (setara 1 PC : 4 PP) dengan molen, untuk beda tinggi > 0 s.d. 1 m' m3 843,360.74
7 2.1.3.3.b.(c) Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP m2 267,135.57
8 2.1.3.4.b.(a) Pemasangan Bata Merah 1 m3 dengan Mortar tipe O, fc' = 2,4 Mpa (setara 1 PC : 5 PP) dengan molen, untuk beda tinggi > 0 m3 824,182.77
9 2.1.3.5.b.(a) Pemasangan bata merah 1 m3 dengan Mortar campuran 1 PC : 6 PP dengan molen, untuk beda tinggi > 0 s.d. 1 m' m3 821,448.07
10 2.1.4.b.(a) Bongkar 1 m3 Pasangan Bata Merah dengan Jack Hammer m3 20,803.00
Harsat Pekerjaan 18
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
9 3.2.2.1.2.a.(a) Siaran dengan Mortar Tipe S, fc' = 12,5 Mpa (setara 1 PC : 3 PP) m2 48,435.54
10 3.2.2.2.1.(a) Trasraam Tebal 1 cm, dengan Mortar Campuran fc' = 25 Mpa (setara 1 PC : 1 PP) m2 42,307.90
11 3.2.2.2.2.(a) Trasraam Tebal 1 cm, dengan Mortar tipe M, fc' = 17,2 Mpa (setara 1 PC : 2 PP) m2 37,046.28
12 3.2.2.2.3.(a) Plesteran Tebal 1 cm, dengan Mortar tipe S, fc' = 12,5 Mpa (setara 1 PC : 3 PP) m2 34,803.32
13 3.2.2.2.4.(a) Plesteran Tebal 1 cm, dengan Mortar tipe N, fc' = 5,2 Mpa (setara 1 PC : 4 PP) m2 33,407.82
14 3.2.2.2.5.(a) Plesteran Tebal 1 cm, dengan Mortar tipe O, fc' = 2,4 Mpa (setara 1 PC : 5 PP) m2 32,397.52
15 3.2.2.2.6.(a) Plesteran Tebal 1 cm, dengan Mortar tipe fc' = 2,0 Mpa (setara 1 PC : 6 PP) m2 31,686.64
16 3.2.2.2.7.(a) Trasraam Tebal 1,5 cm, dengan Mortar tipe fc' = 25 Mpa (setara 1 PC : 1 PP) m2 59,055.72
17 3.2.2.2.8.(a) Pemasangan 1 m2 Plesteran 1 SP : 1 PP Tebal 15 mm m2 77,248.72
18 3.2.2.2.9.(a) Trasraam Tebal 1,5 cm, dengan Mortar tipe M, fc' = 17,2 Mpa (setara 1 PC : 2 PP) m2 51,150.16
19 3.2.2.2.10.(a) Pemasangan 1 m2 Plesteran 1 SP : 2 PP Tebal 15 mm m2 69,343.16
20 3.2.2.2.11.(a) Plesteran Tebal 1,5 cm, dengan Mortar tipe S, fc' = 12,5 Mpa (setara 1 PC : 3 PP) m2 47,785.72
21 3.2.2.2.12.(c) Pemasangan 1 m2 Plesteran 1 SP : 3 PP Tebal 15 mm m2 65,978.72
22 3.2.2.2.13.(a) Plesteran Tebal 1,5 cm, dengan Mortar tipe N, fc' = 5,2 Mpa (setara 1 PC : 4 PP) m2 45,705.60
23 3.2.2.2.14.(c) Pemasangan 1 m2 Plesteran 1 SP : 4 PP Tebal 15 mm m2 63,635.94
24 3.2.2.2.15.(a) Plesteran Tebal 1,5 cm, dengan Mortar tipe O, fc' = 2,4 Mpa (setara 1 PC : 5 PP) m2 44,177.02
25 3.2.2.2.16.(c) Pemasangan 1 m2 Plesteran 1 SP : 5 PP Tebal 15 mm m2 62,370.02
26 3.2.2.2.17.(a) Plesteran Tebal 1,5 cm, dengan Mortar Campuran (setara 1 PC : 6 PP) m2 43,136.96
27 3.2.2.2.18.(c) Pemasangan 1 m2 Plesteran 1 SP : 6 PP Tebal 15 mm m2 61,329.96
28 3.2.2.2.19.(a) Trasraam Tebal 2,0 cm, dengan Mortar Campuran fc' = 25 Mpa (setara 1 PC : 1 PP) m2 75,829.80
29 3.2.2.2.20.(a) Trasraam Tebal 2,0 cm, dengan Mortar Tipe M, Campuran fc' = 17,2 Mpa (setara 1 PC : 2 PP) m2 65,306.57
30 3.2.2.2.21.(a) Plesteran Tebal 2,0 cm, fc' = 12,5 Mpa (setara 1 PC : 3 PP) m2 60,820.65
31 3.2.2.2.22.(c) Pemasangan 1 m2 Plesteran 1SP : 3PP tebal 20 mm m2 74,333.93
32 3.2.2.2.23.(a) Plesteran tebal 2,0 cm dengan mortar tipe N, fc'= 5,2 Mpa (setara 1PC : 4PP) m2 58,029.64
33 3.2.2.2.24.(c) Pemasangan 1 m2 Plesteran 1SP : 4PP tebal 20 mm m2 85,089.42
34 3.2.2.2.25.(a) Plesteran tebal 2,0 cm dengan mortar tipe O, fc'= 2,4 Mpa (setara 1PC : 5PP) m2 56,009.05
35 3.2.2.2.26.(c) Pemasangan 1 m2 Plesteran 1SP : 5PP tebal 20 mm m2 83,489.08
36 3.2.2.2.27.(a) Plesteran tebal 2,0 cm dengan mortar campuran (setara 1PC : 6PP) m2 54,587.28
37 3.2.2.2.28.(c) Pemasangan 1 m2 Plesteran 1SP : 5PP tebal 20 mm m2 82,014.78
38 3.2.2.2.29.(a) Trasraam Tebal 2,5 cm, dengan Mortar Campuran (setara 1 PC : 1 PP) m2 92,603.89
39 3.2.2.2.30.(a) Trasraam Tebal 2,5 cm, dengan Mortar Tipe M, fc' = 17,2 MPa (setara 1 PC : 2 PP) m2 79,436.71
40 3.2.2.2.31.(a) Plesteran Tebal 2,5 cm, dengan Mortar Tipe S, fc' = 12,5 MPa (setara 1 PC : 3 PP) m2 73,829.31
41 3.2.2.2.32.(a) Plesteran Tebal 2,5 cm, dengan Mortar Tipe N, fc' = 5,2 MPa (setara 1 PC : 4 PP) m2 70,353.69
42 3.2.2.2.33.(a) Trasraam Tebal 2,5 cm, dengan Mortar Tipe O, fc' = 2,4 MPa (setara 1 PC : 5 PP) m2 67,814.81
43 3.2.2.2.34.(a) Trasraam Tebal 2,5 cm, fc' = 1,2 Mpa dengan Mortar Campuran (setara 1 PC : 6 PP) m2 66,037.60
44 3.2.2.2.35.(a) Pemasangan 1 m2 Acian m2 27,477.81
Harsat Pekerjaan 19
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
4 4.1.4.(c) Pemasangan 1 m' Pipa PVC Ø 150 mm m' 178,052.97
5 4.1.5.(c) Pemasangan 1m' Pipa PVC Ø 200 mm m' 553,454.75
6 4.1.6.(c) Pemasangan 1m' Pipa PVC Ø 250 mm m' 875,434.43
7 4.1.7.(c) Pemasangan 1m' Pipa PVC Ø 300 mm m' 1,352,036.98
17 4.1.17.(c) Pemasangan 1m' Pipa HDPE Ø 63 mm m' 63,826.15
18 4.1.18.(c) Pemasangan 1m' Pipa HDPE Ø 100 mm m' 186,265.50
19 4.1.19.(c) Pemasangan 1m' Pipa HDPE Ø 125 mm m' 236,024.85
20 4.1.20.(c) Pemasangan 1m' Pipa HDPE Ø 150 mm m' 383,189.20
21 4.1.21.(c) Pemasangan 1m' Pipa HDPE Ø 200 mm m' 597,641.20
22 4.1.22.(c) Pemasangan 1m' Pipa HDPE Ø 250 mm m' 926,579.15
23 4.1.23.(c) Pemasangan 1m' Pipa HDPE Ø 300 mm m' 1,467,417.25
24 4.1.24.(c) Pemasangan 1m' Pipa HDPE Ø 400 mm m' 2,368,568.75
25 4.1.25.(c) Pemasangan 1m' Pipa HDPE Ø 450 mm m' 3,000,741.00
26 4.1.26.(c) Pemasangan 1m' Pipa HDPE Ø 500 mm m' 3,691,641.45
27 4.1.27.(c) Pemasangan 1m' Pipa HDPE Ø 600 mm m' 5,828,329.95
28 4.1.28.(c) Pemasangan 1m' Pipa HDPE Ø 800 mm m' 13,463,352.45
29 4.1.29.(c) Pemasangan 1m' Pipa HDPE Ø 900 mm m' 17,142,384.15
30 4.1.30.(c) Pemasangan 1m' Pipa HDPE Ø 1000 mm m' 21,114,943.00
31 4.1.31.(c) Pemasangan 1m' Pipa HDPE Ø 1100 mm m' 21,153,665.80
32 4.1.32.(c) Pemasangan 1m' Pipa HDPE Ø 1200 mm m' 29,185,050.75
Harsat Pekerjaan 20
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
42 4.2.42.(c) Pemotongan 1 Buah Pipa GIP Ø 500 mm bh 145,587.70
43 4.2.43.(c) Pemotongan 1 Buah Pipa GIP Ø 600 mm bh 133,590.90
44 4.2.44.(c) Pemotongan 1 Buah Pipa GIP Ø 800 mm bh 242,361.35
45 4.2.45.(c) Pemotongan 1 Buah Pipa GIP Ø 900 mm bh 273,774.75
46 4.2.46.(c) Pemotongan 1 Buah Pipa GIP Ø 1000 mm bh 305,280.15
47 4.2.47.(c) Pemotongan 1 Buah Pipa GIP Ø 1100 mm bh 336,906.30
48 4.2.48.(c) Pemotongan 1 Buah Pipa GIP Ø 1200 mm bh 368,411.70
49 4.2.49.(c) Pemotongan 1 Buah Pipa DCI Ø 100 mm bh 9,363.30
50 4.2.50.(c) Pemotongan 1 Buah Pipa DCI Ø 125 mm bh 15,756.15
51 4.2.51.(c) Pemotongan 1 Buah Pipa DCI Ø 150 mm bh 23,213.90
52 4.2.52.(c) Pemotongan 1 Buah Pipa DCI Ø 200 mm bh 55,773.85
53 4.2.53.(c) Pemotongan 1 Buah Pipa DCI Ø 250 mm bh 73,053.75
54 4.2.54.(c) Pemotongan 1 Buah Pipa DCI Ø 300 mm bh 78,574.90
55 4.2.55.(c) Pemotongan 1 Buah Pipa DCI Ø 400 mm bh 146,928.60
56 4.2.56.(c) Pemotongan 1 Buah Pipa DCI Ø 450 mm bh 174,737.90
57 4.2.57.(c) Pemotongan 1 Buah Pipa DCI Ø 500 mm bh 199,468.65
58 4.2.58.(c) Pemotongan 1 Buah Pipa DCI Ø 600 mm bh 199,192.65
59 4.2.59.(c) Pemotongan 1 Buah Pipa DCI Ø 800 mm bh 381,857.50
60 4.2.60.(c) Pemotongan 1 Buah Pipa DCI Ø 900 mm bh 491,236.30
61 4.2.61.(c) Pemotongan 1 Buah Pipa DCI Ø 1000 mm bh 583,518.05
62 4.2.62.(c) Pemotongan 1 Buah Pipa DCI Ø 1100 mm bh 684,115.45
63 4.2.63.(c) Pemotongan 1 Buah Pipa DCI Ø 1200 mm bh 793,212.50
64 4.2.64.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 63 mm bh 10,566.20
65 4.2.65.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 100 mm bh 18,096.40
66 4.2.66.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 125 mm bh 24,507.65
67 4.2.67.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 150 mm bh 31,384.65
68 4.2.68.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 200 mm bh 70,587.00
69 4.2.69.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 250 mm bh 95,328.10
70 4.2.70.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 300 mm bh 106,216.30
71 4.2.71.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 400 mm bh 198,937.35
72 4.2.72.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 450 mm bh 194,252.25
73 4.2.73.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 500 mm bh 214,050.65
74 4.2.74.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 600 mm bh 200,078.15
75 4.2.75.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 800 mm bh 357,673.00
76 4.2.76.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 900 mm bh 404,031.80
77 4.2.77.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 1000 mm bh 450,773.55
78 4.2.78.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 1100 mm bh 497,224.35
79 4.2.79.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 1200 mm bh 543,966.10
Harsat Pekerjaan 21
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
24 4.3.24.(c) Pemasangan 1 Buah Tee Ø 800 mm bh 278,267.23
25 4.3.25.(c) Pemasangan 1 Buah Tee Ø 900 mm bh 322,415.73
26 4.3.26.(c) Pemasangan 1 Buah Tee Ø 1000 mm bh 363,559.85
27 4.3.27.(c) Pemasangan 1 Buah Tee Ø 1100 mm bh 400,750.85
28 4.3.28.(c) Pemasangan 1 Buah Tee Ø 1200 mm bh 444,899.35
XII 4.4 HARGA SATUAN PEKERJAAN PENYAMBUNGAN PIPA BARU KE PIPA LAMA
1 4.4.1.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 80 mm bh 1,334,535.40
2 4.4.2.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 100 mm bh 1,500,222.71
3 4.4.3.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 150 mm bh 1,914,440.98
4 4.4.4.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 200 mm bh 2,328,659.25
5 4.4.5.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 250 mm bh 2,742,877.53
6 4.4.6.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 300 mm bh 3,157,095.80
7 4.4.7.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 400 mm bh 3,985,532.34
8 4.4.8.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 450 mm bh 4,399,750.62
9 4.4.9.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 500 mm bh 4,813,968.89
10 4.4.10.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 600 mm bh 5,642,405.43
11 4.4.11.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 700 mm bh 6,470,841.98
12 4.4.12.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 800 mm bh 7,299,278.52
Harsat Pekerjaan 22
DAFTAR SEWA PERALATAN
SUMBER DATA :
PEKERJAAN : REHABILITASI SMP N 1 TERAS
LOKASI : SMP N 1 TERAS, BOYOLALI
TAHUN ANGGARAN : 2022
WILAYAH : I (SATU)
HARGA
NO. PERALATAN SATUAN (Rp) KET.
HARGA
NO. JENIS TENAGA KERJA SATUAN KET.
(Rp)
1 Pekerja Hr 80,000
2 Mandor Hr 105,000
3 Tukang listrik Hr 90,000
4 Tukang kayu Hr 90,000
5 Kep. tk. kayu Hr 105,000
6 Tukang batu Hr 90,000
7 Kep. tk. batu Hr 105,000
8 Tukang besi Hr 90,000
9 Kep. tk. besi Hr 105,000
10 T u k a n g c a t Hr 90,000
11 K e p . t k . c a t Hr 105,000
12 T u k a n g p l i t u r Hr 88,000
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)
I BAHAN DASAR
1 BATU BELAH
Batu Gunung Belah m3 225,000.00
kg 167.00
-
2 KERIKIL -
Beton 5 - 7 cm m3 230,000.00 Pecah mesin
Beton 3 - 5 cm m3 230,000.00 Pecah mesin
Beton 2 - 3 cm m3 230,000.00 Pecah mesin
Beton 1 - 2 cm m3 230,000.00 Pecah mesin
Beton 0.5 - 1 cm m3 230,000.00 Pecah Mesin
kg 170.00 Pecah Mesin
3 BATU BATA
ex lokal bh 750.00
Bata Ekspose bh 1,700.00 dim 4.5 x 11 x 22
Bata Pelapis bh 1,700.00 dim 3 x 7 x 24
Batu paras bh 108,000.00 dim 20 x 20
Concrete Block ( CB 15 ) / Batako (lubang 2) bh 3,000.00
Roster Beton Abu Uk 20x20 bh 15,000.00
Bata ringan 60x20x10 cm m3 800,000.00 Ex. Grand Elephant
bh 9,600.00 Ex. Grand Elephant
Bata ringan 60x20x7.5 cm m3 800,000.00
bh 7,200.00
4 PASIR
Urug m3 175,000.00
Pasang m3 228,400.00
Beton m3 230,000.00
kg 164.00
5 TANAH -
Sirtu m3 138,000.00
Tanah Padas m3 58,000.00
Tanah Biasa m3 54,600.00
Sirtu (Quarry) m3 58,000.00
Tanah Padas (Quarry) m3 36,800.00
Tanah Biasa (Quarry) m3 32,700.00
Tanah Subur m3 58,000.00
Tanah Liat m3 58,000.00
-
6 KAPUR Pasang m3 210,000.00
-
7 PORTLAND CEMENT
Portland Cement 40 kg Ex. GRESIK zak 59,000.00
Ex. TIGARODA zak 57,000.00
Ex. DYNAMIX zak 54,000.00
Portland Cement Ex. GRESIK kg 1,475.00
Ex. TIGARODA kg 1,425.00
Ex. DYNAMIX kg 1,350.00
Semen warna kg 15,000.00
Semen Putih kg 5,500.00
Pengisi Nat Sika kg 18,500.00
MU mortar utama plester plus kg 2,050.00
MU mortar utama aci kg 3,600.00
Thin bed perekat bata ringan kg 2,100.00 Ex Grand Elephant
Plester instan bata merah kg 2,000.00 Ex Grand Elephant
Aci instan kg 2,350.00 Ex Grand Elephant
Perekat keramik kg 2,750.00 Ex Grand Elephant
Render kg 2,400.00 Ex Grand Elephant
Grouting kg 2,350.00 Ex Grand Elephant
-
8 Plastik Plastik tebal 0,08 gulung 126,000.00 uk 1,5x25 m
Plastik tebal 0,08 m2 3,350.00
-
II BAHAN PENUTUP ATAP -
1 GENTENG TANAH LIAT -
Genteng Lokal Tipe Plenthong bh 1,650.00
Genteng Kebumen Tipe Plentong Kecil bh 3,650.00
Genteng Kebumen Tipe Morando bh 5,750.00
Genteng Keramik Kanmuri bh 10,500.00
Genteng Keramik KIA Kw I bh 10,800.00
Genteng Keramik Glazur Super Jatiwangi Bh 5,950.00
Genteng Jatiwangi Maridional bh 7,350.00
Genteng Jatiwangi Morando 18 bh 5,750.00
Genteng Jatiwangi Tipe Morando SE bh 6,300.00
Genteng Jatiwangi Tipe Alto bh 4,300.00
Genteng Kerpus Lokal bh 1,650.00
Genteng Kerpus Kebumen bh 12,600.00
Genteng Kerpus Keramik bh 28,500.00
Genteng Sirap Keramik bh 2,450.00 Isi 50 bh/m2
Balok/pesagen m3 4,357,500.00
Papan Begesting m3 3,570,000.00
-
5 LANAN Papan m3 1,778,200.00
Balok/pesagen m3 1,874,900.00
-
6 SENGON Papan m3 2,887,500.00
m2 57,700.00
Balok/pesagen m3 2,887,500.00
-
7 BENGKIRAI Papan m3 14,437,500.00
Balok/pesagen m3 11,484,300.00
Reng 2/3 m3 7,875,000.00
-
8 DOLKEN Sedang 8/10 panjang 4 m btg 26,200.00
Kayu bakar m3 813,700.00
-
9 BAMBU Bambu Apus btg 13,800.00 Panjang 4 meter
Bambu Petung btg 31,600.00 Panjang 4 meter
Anyaman Bambu m2 27,800.00
-
10 KAYU LIST List Polos m' 6,900.00
List Profil m' 10,300.00
-
IV BAHAN PENUTUP DINDING / LANTAI -
1 UBIN -
PC polos 30 X 30 cm m2 3,600.00
20 X 20 cm m2 1,250.00
-
PC abu2 40 X 40 cm buah 8,800.00
30 X 30 cm buah 5,500.00
20 X 20 cm buah 6,000.00
Warna 40 X 40 cm buah 11,900.00
30 X 30 cm buah 8,000.00
20 X 20 cm buah 6,000.00
Teraso 40 X 40 cm buah 62,300.00
30 X 30 cm buah 32,000.00
Teralux 30 X 30 cm buah 40,000.00
Taralux Marmer 60 X 60 cm buah 98,000.00
40 X 40 cm buah 40,500.00
30 X 30 cm buah 42,000.00
-
2 KERAMIK LANTAI -
Keramik lantai 20/20 KIA ( Textur) bh 2,350.00
Keramik lantai 20/20 Platinum (unpolish) bh 2,750.00
Keramik lantai 30/30 Impresso bh 4,350.00
Keramik lantai 30/30 Asia Tile bh 4,700.00
Keramik lantai 30/30 Asia Tile dus 51,900.00
Keramik lantai 30/30 Roman bh 13,300.00
Keramik lantai 30/30 Mulia bh 3,800.00
Keramik lantai 40/40 Hercules bh 10,300.00
Keramik lantai 40/40 Asia Tile Murano bh 10,300.00
Keramik lantai 40/40 Asia Tile Murano dus 62,200.00
Keramik lantai 40/40 Oscar bh 9,900.00
Keramik lantai 60/60 Hercules bh 24,400.00
Keramik lantai 40/40 Platinum bh 11,300.00
Keramik lantai 50/50 Platinum bh 17,000.00
Keramik lantai 50/50 Hercules bh 19,100.00
Keramik lantai 30/30 Platinum bh 5,100.00
Keramik lantai 25/25 Platinum (unpolish) bh 4,300.00
Keramik lantai 25/25 Asia Tile bh 3,250.00
Marmer 100/100 bh 1,177,000.00
Ubin Lantai 40/40 Granito bh 32,500.00
Ubin Lantai 30/30 Granito bh 32,500.00
Teraso Cor m3 3,250.00
Pengisi Nat Sika kg 19,400.00
-
3 KERAMIK DINDING -
Keramik dinding 30/30 KIA bh 6,500.00
Keramik dinding 10/20 KIA bh 1,450.00
Keramik dinding 10/10 KIA bh 1,450.00
Keramik dinding 20/20 Asia Tile bh 2,600.00
Keramik dinding 20/25 Asia Tile bh 3,350.00
Keramik dinding 25/40 KIA bh 6,850.00
Keramik dinding 30/60 KIA bh 21,500.00
Keramik dinding 25/40 Platinum bh 6,900.00
Keramik dinding 25/50 Platinum bh 9,700.00
Keramik dinding 20/20 Spectrum bh 2,100.00
Mozaic dinding 30x30 bh 31,500.00
-
3 KERAMIK DINDING ARTISTIK -
Keramik dinding artistik 5/20 bh 6,500.00
Keramik dinding artistik 10/20 bh 9,800.00
-
4 HOMOGENOUS TILE -
Homogenous Tile 60/60 Indogress TPZ bh 49,300.00
Homogenous Tile 60/60 Top Gress bh 37,800.00
Step Nosing Homogenous Tile 10/60 bh 24,100.00
-
5 PLINT DINDING -
Keramik Dinding 10/20 bh 6,800.00
6 Glass Block -
Glassblock ex Mulia Bh 27,300.00 Ex. Mulia
-
2 Pipa PVC SII SCJ , S - 12,5 (8 bar) Ex Maspion pjg.6m -
Pipa PVC DN 40 ( 1 1/2" ) btg 128,700.00 panjang 6 m
3 Pipa PVC AW abu panjang 4m -
Pipa PVC AW Maspion 1/2" m' 10,700.00 panjang 4 m
Pipa PVC AW Maspion 3/4" m' 13,100.00 panjang 4 m
Pipa PVC AW Maspion 1" m' 16,400.00 panjang 4 m
Pipa PVC AW Maspion 1 1/4" m' 23,200.00 panjang 4 m
Pipa PVC AW Maspion 1 1/2" m' 30,300.00 panjang 4 m
Pipa PVC AW Maspion 2" m' 45,000.00 panjang 4 m
Pipa PVC AW Maspion 2 1/2" m' 57,700.00 panjang 4 m
Pipa PVC AW Maspion 3" m' 82,300.00 panjang 4 m
Pipa PVC AW Maspion 4" m' 120,000.00 panjang 4 m
Pipa PVC AW Maspion 5" m' 189,300.00 panjang 4 m
Pipa PVC AW Maspion 6" m' 252,100.00 panjang 4 m
4 Pipa Medium A Galvanis - panjang 6m -
Pipa Medium A Galvanis DN ½" btg 232,300.00 panjang 6 m
Pipa Medium A Galvanis DN 25 ( ¾" ) btg 297,600.00 panjang 6 m
Pipa Medium A Galvanis DN 32 ( 1" ) btg 448,800.00 panjang 6 m
Pipa Medium A Galvanis DN 40 ( 1 1/4" ) btg 587,200.00 panjang 6 m
Pipa Medium A Galvanis DN 50 ( 1½" ) btg 673,800.00 panjang 6 m
Pipa Medium A Galvanis DN 63 ( 2" ) btg 920,200.00 panjang 6 m
Pipa Medium A Galvanis DN 65 ( 2 1/2" ) btg 1,187,100.00 panjang 6 m
Pipa Medium A Galvanis DN 90 ( 3" ) btg 1,531,100.00 panjang 6 m
Pipa Medium A Galvanis DN 110 ( 4" ) btg 2,194,800.00 panjang 6 m
Pipa Medium A Galvanis DN 125 ( 5" ) btg 2,982,600.00 panjang 6 m
Pipa Medium A Galvanis DN 160 ( 6" ) btg 3,516,700.00 panjang 6 m
-
5 Pipa Besi Stainless Steel Ex Star -
dia. 3/4" btg 227,200.00 panjang 6 m
dia. 1" btg 284,000.00 panjang 6 m
dia. 2" btg 454,200.00 panjang 6 m
dia. 3" btg 826,500.00 panjang 6 m
dia. 4" btg 1,106,000.00 panjang 6 m
-
6 Pipa HDPE SDR 17 -
Dia. 50 mm m' 30,600.00 Ex. Maspion
Dia. 63 mm m' 48,800.00 Ex. Maspion
Dia. 75 mm m' 68,900.00 Ex. Maspion
Dia. 90 mm m' 99,100.00 Ex. Maspion
Dia. 100 mm m' 154,500.00 Ex. Maspion
Dia. 110 mm m' 147,400.00 Ex. Maspion
Dia. 125 mm m' 197,000.00 Ex. Maspion
Dia. 150 mm m' 322,800.00 Ex. Maspion
Dia. 200 mm m' 503,900.00 Ex. Maspion
Dia. 250 mm m' 783,200.00 Ex. Maspion
Dia. 300 mm m' 1,246,000.00 Ex. Maspion
Dia. 400 mm m' 2,003,900.00 Ex. Maspion
Dia. 450 mm m' 2,539,000.00 Ex. Maspion
Dia. 500 mm m' 3,127,500.00 Ex. Maspion
Dia. 600 mm m' 4,965,500.00 Ex. Maspion
Dia. 800 mm m' 11,524,200.00 Ex. Maspion
Dia. 900 mm m' 14,627,300.00 Ex. Maspion
Dia. 1000 mm m' 18,017,400.00 Ex. Maspion
Dia. 1200 mm m' 24,885,300.00 Ex. Maspion
7 Bend All Flange -
Bend all flange Ø 2" x 90 bh 338,100.00 Ex. Maspion
Bend all flange Ø 3" x 90 bh 367,800.00 Ex. Maspion
Bend all flange Ø 4" x 90 bh 595,800.00 Ex. Maspion
Bend all flange Ø 2" x 45 bh 315,400.00 Ex. Maspion
Bend all flange Ø 3" x 45 bh 385,700.00 Ex. Maspion
Bend all flange Ø 4" x 45 bh 538,100.00 Ex. Maspion
8 Cek Valve -
Cek Valve Ø 1/2" bh 123,000.00 Ex. Onda kuningan drat
Cek Valve Ø 1 1/2" bh 523,100.00 Ex. Onda kuningan drat
Cek Valve Ø 2" bh 828,600.00 Ex. Onda kuningan drat
Cek Valve Ø 3" bh 2,295,700.00 Ex. Onda kuningan drat
Cek Valve Ø 4" bh 1,843,000.00 Ex. Onda kuningan drat
9 Flange Steel -
Dia. 1.5" bh 65,600.00
Dia. 2" bh 67,800.00
10 Gate Valve -
Dia. 1.5" bh 481,600.00
Dia. 2" bh 925,400.00
11 Keni Galvanis -
Keni Galvanis Ø 1.5" x 90 bh 31,400.00
Keni Galvanis Ø 2" x 90 bh 49,600.00
12 Pressure Gauge -
Dia. 2 1/2" bh 119,800.00
13 Pipa Udara bh 366,100.00
14 Manhole bh 585,700.00
Water Meter 1/2" ex. Nankai bh 133,600.00
Socket PVC 3/4" x 3/4" bh 3,050.00
Clamp Saddle CI 2" x 3/4" bh 36,800.00
Tee PVC 1/2" bh 3,750.00
Fix Coupling 1/2" (Kuningan) bh 32,300.00
Kran Air 1/2" (Kuningan) bh 34,300.00
Gate Valve 1/2" (Kuningan) bh 79,500.00
16 Tee -
Tee Ø 150 mm bh 392,200.00
Tee Ø 200 mm bh 812,600.00
-
VIII B A H A N L A N G I T - L A N G I T -
1 SOFT BOARD ( 1.2 m x 2.4 m ) -
Soft Board Tebal 9 mm Jayaboard lbr 78,700.00
Soft Board Tebal 9 mm Jayaboard WR lbr 94,500.00
Soft Board Tebal 9 mm Elephant lbr 63,000.00
Soft Board Tebal 9 mm Knauf lbr 51,400.00
Soft Board Tebal 9 mm Star lbr 52,500.00
Soft Board Tebal 9 mm Aplus lbr 49,300.00
Sekrup Gypsum Sunray 6 x 2" bh 225.00
Compound Compound Knauf kg 3,150.00
Compound Aplus kg 3,150.00
GRC Board tebal 4mm 1200 x 2400 x 0.4 cm lbr 63,000.00
Dinabolt Bh 3,650.00
Cotton Plaster 50 m m' 325.00
List Gypsum Lebar 10 cm m' 12,600.00
List Kayu Profil m' 10,500.00
Tepung Gypsum kg 3,650.00
Cornice Adhesive Kg 4,200.00
Textile Tape m' 1,050.00
-
3 HARDFLEX 1200 x 2400 x 4 mm lbr 63,000.00 GRC
1000 x 1000 x 4 mm lbr 33,500.00 GRC
900 x 1800 x 4 mm lbr 45,300.00 GRC
4 PLY WOOD -
1200 x 2400 x 3 mm lbr 47,200.00
1200 x 2400 x 4 mm lbr 60,900.00
1200 x 2400 x 5 mm lbr 68,200.00
1200 x 2400 x 6 mm lbr 120,700.00
1200 x 2400 x 9 mm lbr 131,200.00
1200 x 2400 x 12 mm lbr 157,500.00
1201 x 2400 x 15 mm lbr 189,000.00
Urat Jati (Teakwood) 200 x 4000 x 4 mm lbr 68,200.00
Lapis Formika m2 62,800.00
Skrup pcs 275.00
5 AKUSTIK -
30x30 lbr 47,200.00
30x60 lbr 60,900.00
60x120 lbr 68,200.00
6 PVC Polos lebar 20 cm m' 15,700.00 Ex. Wifon
Texture lebar 20 cm m' 17,300.00 Ex. Wifon
List PVC Polos m' 13,600.00
-
6 Alumunium Composit Panel Lbr 493,500.00 Ex. Seven indoor
Lbr 771,700.00 Ex. Seven outdoor
Rangka Besi Hollow + Bracing m2 206,100.00
Rangka Hollow 1x2 m' 15,000.00
7 Exhaust Fan FLOOR Panasonic 10" FV25TGU Unit 590,600.00
Panasonic 8" FV20TGU Unit 474,100.00
Maspion 10" MV-250NEX Unit 460,400.00
Maspion 8" CEF-20MP Unit 319,200.00
-
IX BAHAN FINISHING -
1 KAYU -
Menie Kayu kg 38,800.00
Dempul plamur kg 36,500.00
Ambril/amplas lbr 4,400.00
Batu Apung kg 19,700.00
Cat Kayu Danalac kg 66,100.00
Waterproofing No Drop kg 49,800.00
Siralax ons 10,500.00
Spiritus ltr 21,000.00
Melamik kg 54,600.00
Lem Kayu Fox Kuning kg 71,400.00
HPL Motif Serat Kayu (2,4 x 1.2 m) lbr 187,400.00
Foam Sheet 3 mm m2 6,400.00
-
15 Grease Trap Grease trap 15 L Unit 838,900.00
Grease trap 40 L Unit 1,363,900.00
-
16 SEPTIC TANK (Hero) -
8 Pemakai 800 liter unit 3,150,000.00
10 Pemakai 1.000 liter unit 3,675,000.00
-
17 AKSESORIS -
Kran Air Biasa bh 28,800.00 1/2"
Onda CLS 01 bh 84,000.00 3/4"
Kran Air Leher Angsa Flexible bh 120,700.00 Onda
Seal tape bh 2,900.00
FLOOR drain SAN-EI Seri HN508P bh 225,700.00
Onda bh 89,200.00
Pompa Air Shimizu PS 130 BIT Unit 661,500.00
-
XIV LAIN-LAIN -
Minyak Beton & bekisting ltr 5,450.00
Kapur Sirih kg 19,800.00
Alang Alang ikat 12,600.00
Allumunium Foil m2 12,600.00
Sabun kg 24,100.00
Soda api kg 28,300.00
Solar ltr 9,000.00
Residu/Ter Ltr 8,400.00
Air Liter 90.00
Spacer/Penjaga Jarak bh 5,650.00
Kuas bh 8,400.00
Ijuk Kg 21,000.00
WATER PROOFING -
LEMKRA DS 105 5 kg 80,000.00 Putih
5 kg 73,000.00 Abu-abu
LEMKRA TG 301 20 Ltr 661,500.00
LEMKRA TG 300 5 Ltr 122,800.00
Primer Waterproofing Membrane Bitumen ltr 55,700.00
Membrane Bitumen Lembar 508,900.00
Membran Bitumen Selulosa ( 1 x 10 m ) Lbr / Roll 1,030,800.00 Bituline
Kristalisasi Penetron kg 1,732,500.00
Printing MMT m2 17,800.00
Seng Galvalume 0,25 m2 38,700.00
Logo Tulisan Untuk Papan Nama Unit 10,500.00
Vertical Blinds Box Op Ex. Sharp Point Deluxe m2 241,500.00
Ex. Sharp Point Blackout m2 367,500.00
Kawat Nyamuk Nylon m2 11,600.00
Wallpaper m2 78,700.00
Lem Wallpaper Kg 160,000.00
Karung Goni m2 5,500.00
-
XVIII BAHAN ALUMUNIUM -
1 Alumunium Profil Warna Silver 4" tipe M tebal 1 mm m' 63,500.00 Ex. Alexindo
Warna Coklat 4" tipe M tebal 1 mm m' 67,700.00 Ex. Alexindo
Alumunium Coating White 4" tipe M tbl 1 mm m' 70,300.00 Ex. Alexindo
Warna Silver 4" tutup M tebal 1 mm m' 30,700.00 Ex. Alexindo
Warna Coklat 4" tutup Mtebal 1 mm m' 32,800.00 Ex. Alexindo
Alumunium Coating White 4" tutup M tbl 1 mm m' 34,000.00 Ex. Alexindo
Warna Silver 4" openback tebal 1 mm m' 54,200.00 Ex. Alexindo
Warna Coklat 4" openback tebal 1 mm m' 57,900.00 Ex. Alexindo
Alumunium Coating White 4" openback tbl 1 mm m' 60,100.00 Ex. Alexindo
Warna Silver 3" tipe M tebal 1 mm m' 51,700.00 Ex. Alexindo
Warna Coklat 3" tipe M tebal 1 mm m' 55,200.00 Ex. Alexindo
Alumunium Coating White 3" tipe M tbl 1 mm m' 57,200.00 Ex. Alexindo
Warna Silver 3" tutup M tebal 1 mm m' 25,200.00 Ex. Alexindo
Warna Coklat 3" tutup Mtebal 1 mm m' 26,900.00 Ex. Alexindo
Alumunium Coating White 3" tutup M tbl 1 mm m' 27,900.00 Ex. Alexindo
Warna Silver 3" openback tebal 1 mm m' 42,600.00 Ex. Alexindo
XX TAMAN -
1 Tanah Subur m3 177,400.00
2 Pupuk Kandang kg 10,500.00
3 Tanaman Kacang Hias / polybag 3,150.00
4 Tanaman Lantana / polybag 3,150.00
4 Tanaman Pangkas Hijau / polybag 5,250.00
5 Tanaman Pangkas Kuning / polybag 3,150.00
6 Tanaman Pangkas Merah / polybag 4,700.00
7 Pohon Ketapang Kencana 1 m bh 105,000.00
8 Pucuk Merah t. Min 60cm bh 77,900.00
-
XIX BAHAN ASPAL -
1 Aspal Drum drum 2,038,600.00
Drum Kg 13,200.00
Curah Kg 10,900.00
Aspal Emulsi CSS-1 atau SS1 Ltr 12,500.00
-
XX ALAT PELINDUNG DIRI Helm Savety Star Will Unit 93,000.00
Pelindung mata Unit 31,000.00
Tameng muka Unit 93,000.00
Pelindung telinga Unit 57,200.00
Masker pelindung pernafasan dan mulut Box 55,800.00
Sarung tangan Psg 6,150.00
Sepatu keselamatan Psg 335,000.00
Sepatu keselamatan ( rubber safety ) Psg 110,200.00
Penunjang seluruh tubuh Unit 930,700.00
Rompi keselamatan Unit 31,000.00
Pelindung jatuh Unit 124,100.00
-
XXI PINTU-JENDELA PABRIKASI -
1 Pintu UPVC -
Pintu Swing Kaca (90x210) Unit 2,984,100.00 Ex. Prysma
Pintu Swing Panel (90x210) Unit 3,347,900.00 Ex. Prysma
Pintu Swing Combi (90x210) Unit 3,644,500.00 Ex. Prysma
Pintu Double Swing Kaca (155x210) Unit 4,831,300.00 Ex. Prysma
Pintu Double Swing Panel (155x210) Unit 5,478,100.00 Ex. Prysma
Pintu Double Swing Combi (155X210) Unit 6,969,100.00 Ex. Prysma
Pintu Sliding (Gantung) (100X210) Unit 3,332,700.00 Ex. Prysma
Pintu Sliding (BT. Track) (100X210) Unit 2,948,400.00 Ex. Prysma
Pintu Sliding 2 Daun (Gantung) (155X210) Unit 4,726,000.00 Ex. Prysma
Pintu Sliding 2 Daun (220X240) Unit 6,142,500.00 Ex. Prysma
Pintu Sliding 4 Daun (350X240) Unit 11,155,200.00 Ex. Prysma
Pintu Sliding 6 Daun (530X240) Unit 16,414,600.00 Ex. Prysma
-
2 Jendela UPVC -
Jendela Swing (70x135) Unit 1,961,100.00 Ex. Prysma
Jendela Cesement (60x125) Unit 1,626,400.00 Ex. Prysma
Jendela Double Swing (130x125) Unit 3,325,300.00 Ex. Prysma
Jendela Pivot (Putar) (60x120) Unit 4,038,300.00 Ex. Prysma
Jendela Sliding 2 Daun (145x120) Unit 3,316,400.00 Ex. Prysma
Jendela Sliding 3 Daun (245x120) Unit 4,932,300.00 Ex. Prysma
Jendela Sliding 4 Daun (260x120) Unit 6,284,200.00 Ex. Prysma
-
3 Jendela UPVC -
Rolling Door One Sheet Polos Besi Unit 675,000.00
Rolling Door One Sheet Polos Alumunium Unit 785,000.00
Rolling Door One Sheet Perforate 3 baris Unit 830,000.00
Rolling Door One Sheet Perforate 7 baris Unit 850,000.00
Rolling Door One Sheet Full Perforate Unit 880,000.00
Rolling Door Industrial Polos 0.8 mm Unit 1,305,000.00
Rolling Door Industrial Polos 1.0 mm Unit 1,465,000.00
Rolling Door Industrial Polos 1.2 mm Unit 1,620,000.00
Rolling Door Industrial Perforate 1.2 mm Unit 1,750,000.00
Folding Gate PVC Unit 770,000.00
Folding Gate 0.4 mm Unit 605,000.00
Folding Gate 0.5 mm Unit 685,000.00
Folding Gate 0.8 mm Unit 760,000.00
Rangka Folding Gate Tanpa Daun Unit 550,000.00
Pintu Harmonika 0.6 mm Unit 1,110,000.00
Pintu Harmonika 0.8 mm Unit 1,235,000.00
Pintu Harmonika 1.0 mm Unit 1,315,000.00
Pintu Harmonika 1.2 mm Unit 1,475,000.00
Pintu Duco Lipat 1.2 mm Unit 1,085,000.00
Pintu Duco Lipat 1.6 mm Unit 1,195,000.00
Pintu Duco Lipat 1.8 mm Unit 1,305,000.00
Pintu Duco Lipat 2.0 mm Unit 1,380,000.00
Pintu Besi Plat Polos Lipat / Swing 1.2 mm Unit 800,000.00
Pintu Besi Plat Polos Lipat / Swing 1.6 mm Unit 850,000.00
Pintu Besi Plat Polos Lipat / Swing 1.8 mm Unit 900,000.00
Pintu Besi Plat Polos Lipat / Swing 2.0 mm Unit 950,000.00
-
4 Jendela Nako -
Jendela UPVC m2 960,000.00
Jendela Aluminium m2 250,000.00
KEGIATAN
REHABILITASI SMP N 1 TERAS
TAHUN ANGGARAN
2022
REKAPITULASI RENCANA ANGGARAN BIAYA
KEGIATAN : REHABILITASI SMP N 1 TERAS
LOKASI : KECAMATAN TERAS
ANGGARAN : 2022
* LOKASI 1
A PEKERJAAN PERSIAPAN 5,791,171.46
B RUANG GURU
I PEKERJAAN BONGKARAN Rp 10,861,920.90
II PEKERJAAN PONDASI Rp 106,806.12
III PEKERJAAN PASANGAN Rp 20,848,758.56
IV PEKERJAAN BETON Rp 38,199,654.57
V PEKERJAAN ATAP Rp 2,707,831.40
VI PEKERJAAN LANGIT-LANGIT Rp 24,940,706.39
VII PEKERJAAN PENUTUP LANTAI Rp 3,527,731.90
VIII PEKERJAAN PENGECATAN Rp 21,299,230.22
IX PEKERJAAN MEKANIKAL ELEKTRIKAL Rp 6,379,998.75
JUMLAH A+B Rp 134,663,810.27
* LOKASI 2
A RUANG KELAS
I PEKERJAAN BONGKARAN Rp 9,241,979.53
II PEKERJAAN TANAH Rp 2,571,856.30
III PEKERJAAN PONDASI Rp 2,760,938.23
IV PEKERJAAN PASANGAN Rp 15,053,353.19
V PEKERJAAN BETON Rp 20,805,874.98
VI PEKERJAAN ATAP Rp 54,764,877.09
VII PEKERJAAN LANGIT-LANGIT Rp 19,758,989.59
VIII PEKERJAAN PENUTUP LANTAI Rp 22,241,652.00
IX PEKERJAAN PENGECATAN Rp 15,535,530.44
X PEKERJAAN PINTU DAN JENDELA Rp 24,295,720.12
XI PEKERJAAN MEKANIKAL ELEKTRIKAL Rp 4,429,081.25
XII PEKERJAAN RAMP & AKSES DIFABLE Rp 6,714,384.90
XIII PEKERJAAN LOKASI 3 Rp 3,321,385.65
JUMLAH A Rp 201,495,623.27
* LOKASI 3
A TOILET
I PEKERJAAN BONGKARAN Rp 1,335,689.82
II PEKERJAAN TANAH Rp 556,679.31
III PEKERJAAN PONDASI Rp 1,827,986.76
IV PEKERJAAN PASANGAN Rp 4,705,223.63
V PEKERJAAN BETON Rp 10,133,321.96
VI PEKERJAAN ATAP Rp 4,166,295.90
VII PEKERJAAN LANGIT-LANGIT Rp 1,930,478.55
VIII PEKERJAAN PENUTUP LANTAI Rp 7,444,107.51
IX PEKERJAAN PENGECATAN Rp 3,528,460.27
X PEKERJAAN PINTU DAN JENDELA Rp 3,003,725.48
XI PEKERJAAN MEKANIKAL ELEKTRIKAL Rp 2,645,201.25
XII PEKERJAAN SANITASI DAN PLUMBING Rp 13,416,510.99
XIII PEKERJAAN LOKASI 1 Rp 85,568,480.87
XIV PEKERJAAN LOKASI 2 Rp 1,134,365.13
JUMLAH A Rp 141,396,527.45
Boyolali, 2022
Dibuat oleh,
Pejabat Pembuat Komitmen
Dinas Pendidikan dan Kebudayaan
Kabupaten Boyolali
A PEKERJAAN GEDUNG
I PEKERJAAN PERSIAPAN
VOLUME SAT KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
1 Pek. pembongkaran genteng 227.21 m2 depan 122.21 122.21
belakang 105.00 105.00
JUMLAH 227.21
2 Pek. Pembongkaran rangka atap/kaso/reng 227.21 m2 depan 122.21 122.21
belakang 105.00 105.00
JUMLAH 227.21
3 Pek. Pembongkaran plafond 146.68 m2 R. Guru 7.02 13.20 92.66
Gudang & toilet 7.02 2.68 18.81
Teras timur 5.75 4.00 23.00
Teras barat 3.05 4.00 12.20
JUMLAH 146.68
4 Pek. Pembongkaran dinding bata merah 66.38 m2 As 3 3.25 16.80 54.60
As A & D kolom 3.25 0.20 4.00 2.60
As A & D sloof 0.25 7.25 2.00 3.63
As A & D RB 0.20 7.25 2.00 2.90
As B RB 0.20 7.25 1.45
tambahan kolom 0.60 0.20 10.00 1.20
JUMLAH 66.38
5 Pek. Pembongkaran batu dengan alat 3.00 m3 Pondasi 0.50 0.40 0.40 15.00 3.00
JUMLAH 3.00
6 Pek. Pembongkaran keramik & rabat beton 16.64 m3 dinding selatan 0.80 16.80 13.44
kolom teras 0.80 0.80 5.00 3.20
JUMLAH 16.64
II PEKERJAAN PONDASI
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pasangan Pondasi Batu Belah 1 Pc : 6 Pp 0.12 m3 Bekas galian untuk kolom 0.40 0.10 0.20 15.00 0.12
JUMLAH 0.12
IV PEKERJAAN BETON
1 Pekerjaan Sloof Struktur (SL) 20 x 25 cm Elv. 0.00
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 225 1.21 m3 SL 0.25 0.20 24.20 1.00 1.21
JUMLAH 1.21
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø12 150.60 Kg UTAMA 25.10 0.89 6.00 1.00 150.60
Pekerjaan Pembesian Begel Ø8 49.89 Kg BEGEL 0.76 0.39 168 1.00 49.89
JUMLAH 1.81
Begel plat besi 4x40mm 10.00 4.00 40.00
Angkur d12 2.00 4.00 8.00
Mur baut d12 38.00 4.00 152.00
2 Pekerjaan Rangka Atap Kayu Kruing 8/12 (Nok, Gording, M 1.21 m3 NOK 0.01 19.15 0.18
GORDING 0.01 19.15 4.00 0.74
MURPLAT 0.01 16.80 2.00 0.20
SKOOR ANGIN 0.01 0.08 16.00 0.01
PAPAN RUITER 0.00 19.15 0.08
JUMLAH 1.21
3 Pekerjaan Rangka Atap Kayu Kruing 8/12 untuk teras 0.38 m3 Konsul 1 0.01 6.55 4.00 0.06
Konsul 2 0.01 4.75 4.00 0.18
Balok horizontal at 0.01 7.00 0.07
gording ujung 0.01 7.00 0.07
JUMLAH 0.38
4 Pekerjaan Usuk Kayu Kruing 5/7 Dan Reng Kayu Kruing 2/ 227.21 m2 depan 122.21 122.21
belakang 105.00 105.00
JUMLAH 227.21
5 Pekerjaan Pemasangan Atap Genteng Plentong kecil Tana 79.52 m2 DEPAN 42.77 42.77
BELAKANG 36.75 36.75
JUMLAH 79.52
6 Pekerjaan Pemasangan Kembali Atap Genteng Plentong ke 147.69 m2 DEPAN 79.44 79.44
BELAKANG 68.25 68.25
JUMLAH 147.69
7 Pekerjaan Pemasangan Talang 17.00 m' 8.50 2.00 17.00
JUMLAH 17.00
8 Pekerjaan Pemasangan Bubungan Atap Genteng Tanah Li 19.15 m' 19.15 19.15
JUMLAH 19.15
9 Pekerjaan Pemasangan Listplang GRC 9/200 49.60 m' DEPAN 6.30 1.00 6.30
BELAKANG 18.30 1.00 18.30
MIRING 12.50 2.00 25.00
JUMLAH 49.60
JUMLAH 181.00
2 Pekerjaan List Plafond kayu profil 40.30 m' R. Guru 0 6.95 13.20 40.30
JUMLAH 40.30
3 Pekerjaan Pengecatan Dinding Baru Interior, Ex. Envi 173.25 m2 As 3 3.25 15.90 51.68
Dinding 30cm As 2 2.50 4.10 2.00 20.50
Kolom 3.25 1.65 5.36
JUMLAH 181.08
PENGURANG J1 1.45 1.35 4.00 7.83
JUMLAH 7.83
JUMLAH 173.25
4 Pekerjaan Pengecatan Dinding Baru Eksterior, Ex. Envi 146.87 m2 As 3 3.25 16.80 54.60
Gunungan As A & D 6.50 2.00 13.00
Kolom 3.25 3.00 9.75
JUMLAH 154.70
PENGURANG J1 1.45 1.35 4.00 7.83
JUMLAH 7.83
JUMLAH 146.87
KET DIMENSI PANJANG ISI QTY JUMLAH
5 Pekerjaan Pengecatan Kayu 57.96 m2 Kusen P1 0.01 8.20 4.00 11.81
Daun P1 1.30 2.25 4.00 11.70
Jalusi P1 1.25 6.00 4.00 7.20
Kusen J1 0.01 9.30 6.00 20.09
Daun J1 4.80 6.00 28.80
Jalusi J1 0.35 18.00 6.00 9.07
JUMLAH 57.96
KET DIMENSI PANJANG ISI QTY JUMLAH
6 Pekerjaan Pengecatan Plafond 156.29 m2 R. Guru 6.95 13.20 91.74
Gudang & toilet 6.95 2.70 18.77
Teras timur 5.75 2.22 12.77
Teras barat 3.05 2.22 6.77
Tritisan timur 0.75 12.50 9.38
Tritisan barat 1.35 12.50 16.88
Tritisan selatan 1.35 18.30 24.71
JUMLAH 156.29
KET DIMENSI PANJANG ISI QTY JUMLAH
7 Pekerjaan Pengecatan List Plafond Ex. Envi 4.03 m2 R. Guru 0.10 6.95 13.20 2.00 4.03
JUMLAH 4.03
8 Pekerjaan Pengecatan Listplank Ex. Envi 9.92 m2 0.20 49.60 9.92
JUMLAH 9.92
A PEKERJAAN GEDUNG
I PEKERJAAN PERSIAPAN
VOLUME SAT KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
1 Pek. pembongkaran genteng 194.74 m2 depan 7.25 15.25 110.56
belakang 5.52 15.25 84.18
JUMLAH 194.74
2 Pek. Pembongkaran rangka atap/kaso/reng 194.74 m2 depan 7.25 15.25 110.56
belakang 5.52 15.25 84.18
JUMLAH 194.74
3 Pek. Pembongkaran plafond 142.69 m2 R. Kelas 7.05 10.90 76.85
Teras 2.88 15.25 43.92
Belakang kelas 1.18 11.20 13.22
Samping miring 1.00 8.71 8.71
JUMLAH 142.69
4 Pek. Pembongkaran dinding bata merah 22.91 m3 As B 3.25 7.05 22.91
JUMLAH 22.91
5 Pek. Pembongkaran keramik 101.80 m2 R. Kelas 7.05 10.90 76.85
Teras 24.95
JUMLAH 101.80
II PEKERJAAN TANAH
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pek. GalianTanah Biasa untuk Pondasi Batu kali 7.76 m3 P. Batu belah 1.10 1.00 7.05 7.76
JUMLAH 7.76
2 Pek. Urugan Pasir Bawah Footplate, Pondasi & Lantai 5.73 m3 P. Batu belah 0.05 1.00 7.05 0.35
Lantai R. Kelas 0.05 7.05 10.90 3.84
Teras 0.05 1.75 14.25 1.25
Barat kelas 0.05 0.80 7.20 0.29
JUMLAH 5.73
3 Pek. Urugan Tanah bekas galian 2.59 m3 1/3 vol pondasi 1.10 1.00 7.05 2.59
JUMLAH 2.59
IV PEKERJAAN PASANGAN
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pasangan Batu Bata 49.20 m2 As 1 B-C 3.60 2.55 9.18
Dinding 15cm As 2 B-C 3.60 2.55 9.18
As B 3.60 7.35 26.46
Gunungan As A & D 2.40 7.35 8.82
pintu dinding eksisting 1.21 1.00 1.21
jendela dinding eksisting 1.30 0.25 5.00 0.33
JUMLAH 55.18
PENGURANG J1 1.30 2.30 2.00 5.98
JUMLAH 5.98
JUMLAH TOTAL 49.20
2 Plesteran 97.75 m2 As 1 B-C 3.60 2.55 9.18
Dinding 15cm As 2 B-C 3.60 2.55 9.18
As B 3.60 6.90 24.84
Gunungan As A & D 2.40 7.35 8.82
pintu dinding eksisting 1.21 1.00 1.21
jendela dinding eksisting 1.30 0.25 5.00 1.63
JUMLAH 54.86
PENGURANG J1 1.30 2.30 2.00 5.98
JUMLAH 5.98
JUMLAH TOTAL x 2 97.75
3 Acian 99.91 m2 As 1 B-C 3.60 2.55 9.18
Dinding 15cm As 2 B-C 3.60 2.55 9.18
As B 3.60 6.90 24.84
Gunungan As A & D 2.40 7.35 8.82
pintu dinding eksisting 1.21 1.00 1.21
jendela dinding eksisting 1.30 0.25 5.00 1.63
Kolom 3.60 0.30 1.08
JUMLAH 55.94
KET TINGGI LEBAR PANJANG QTY JUMLAH
PENGURANG J1 1.30 2.30 2.00 5.98
JUMLAH 5.98
JUMLAH TOTAL x 2 99.91
V PEKERJAAN BETON
1 Pekerjaan Sloof Struktur (SL) 20 x 25 cm
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 225 0.35 m3 SL 0.25 0.20 7.05 1.00 0.35
JUMLAH 0.35
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian Ø12 42.90 Kg UTAMA 7.15 0.89 6.00 1.00 42.90
Pekerjaan Pembesian Begel Ø8 14.42 Kg BEGEL 0.76 0.39 49 1.00 14.42
JUMLAH 0.61
Begel plat besi 4x40mm 10.00 2.00
Angkur d12 2.00 2.00 4.00
Mur baut d12 16.00 2.00 32.00
2 Pekerjaan Rangka Atap Kayu kruing 8/12 (Nok, Gording, M 0.74 m3 NOK 0.01 15.25 0.15
GORDING 0.01 11.00 4.00 0.42
MURPLAT 0.01 5.50 2.00 0.11
SKOOR ANGIN 0.01 0.08 4.00 0.00
PAPAN RUITER 0.00 15.25 0.06
JUMLAH 0.74
3 Pekerjaan Usuk 5/7, Reng 2/3 Kayu Kruing 194.74 m2 depan 7.25 15.25 110.56
usuk baru 35%, reng baru total belakang 5.52 15.25 84.18
JUMLAH 194.74
4 Pekerjaan Pemasangan Atap Genteng Plentong kecil Tanah 194.74 m2 DEPAN 7.25 15.25 110.56
BELAKANG 5.52 15.25 84.18
JUMLAH 194.74
5 Pekerjaan Pemasangan Bubungan Atap Genteng Tanah Li 15.25 m' 15.25 15.25
JUMLAH 15.25
6 Pekerjaan Pemasangan Listplang GRC 9/200 56.04 m' DEPAN 15.25 1.00 15.25
BELAKANG 15.25 1.00 15.25
MIRING 12.77 2.00 25.54
JUMLAH 56.04
JUMLAH 142.69
2 Pekerjaan List Plafond kayu profil 35.90 m' R. Kelas 0 7.05 10.90 35.90
JUMLAH 35.90
IX PEKERJAAN PENGECATAN
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pengecatan Dinding Lama Interior, Ex. Envi 92.64 m2 DINDING As 1 3.60 7.35 26.46
As 2 3.60 7.35 26.46
As B 3.60 6.75 24.30
As F 2.40 6.75 16.20
Gunungan 2.40 7.35 17.64
JUMLAH 111.06
PENGURANG P1 2.50 1.00 2.50
JP 1.30 0.75 0.98
J1 1.30 2.30 5.00 14.95
JUMLAH 18.43
JUMLAH 92.64
2 Pekerjaan Pengecatan Dinding Lama Eksterior, Ex. Envi 99.19 m2 DINDING As 1 3.60 7.65 27.54
As 2 3.60 7.35 26.46
As B 3.60 6.75 24.30
As F 2.40 6.75 16.20
Kolom struktur 3.60 0.20 7.60 5.47
Gunungan 2.40 7.35 17.64
JUMLAH 117.61
PENGURANG P1 2.50 1.00 2.50
JP 1.30 0.75 0.98
J1 1.30 2.30 5.00 14.95
JUMLAH 18.43
JUMLAH 99.19
3 Pekerjaan Pengecatan Dinding Baru Interior, Ex. Envi 71.24 m2 DINDING As 1 3.60 2.25 8.10
As 2 3.60 2.25 8.10
As B 3.60 6.75 24.30
Kolom praktis 2.66 0.15 3.60 1.44
Gunungan 2.40 7.35 2.00 35.28
JUMLAH 77.22
PENGURANG J1 1.30 2.30 2.00 5.98
JUMLAH 5.98
JUMLAH 71.24
4 Pekerjaan Pengecatan Dinding Baru Eksterior, Ex. Envi 74.48 m2 DINDING As 1 3.60 2.55 9.18
As 2 3.60 2.55 9.18
As B 3.60 7.05 25.38
Kolom praktis 2.66 0.15 3.60 1.44
Gunungan 2.40 7.35 2.00 35.28
JUMLAH 80.46
PENGURANG J1 1.30 2.30 2.00 5.98
JUMLAH 5.98
JUMLAH 74.48
KET DIMENSI PANJANG ISI QTY JUMLAH
5 Pekerjaan Pengecatan Kayu Ex. Decolux 57.96 m2 Kusen P1 0.01 10.40 1.00 3.74
Daun P1 0.90 2.20 1.00 1.98
Jalusi P1 1.60 3.00 1.00 1.15
Kusen J1 0.01 9.30 6.00 20.09
Daun J1 4.80 6.00 28.80
Jalusi J1 0.35 18.00 6.00 9.07
JUMLAH 57.96
KET DIMENSI PANJANG ISI QTY JUMLAH
6 Pekerjaan Pengecatan Plafond Ex. Decolux 142.69 m2 R. Kelas 7.05 10.90 76.85
Teras 2.88 15.25 43.92
Belakang kelas 1.18 11.20 13.22
Samping miring 1.00 8.71 8.71
JUMLAH 142.69
KET DIMENSI PANJANG ISI QTY JUMLAH
7 Pekerjaan Pengecatan List Plafond Ex. Decolux 3.59 m2 R. Kelas 0.10 7.05 10.90 2.00 3.59
JUMLAH 3.59
8 Pekerjaan Pengecatan Listplank 11.21 m2 0.20 56.04 11.21
JUMLAH 11.21
A PEKERJAAN GEDUNG
I PEKERJAAN PERSIAPAN
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pek. pembongkaran genteng 26.00 m2 4.00 6.50 26.00
JUMLAH 26.00
2 Pek. Pembongkaran rangka atap/kaso/reng 26.00 m2 4.00 6.50 26.00
JUMLAH 26.00
3 Pek. Pembongkaran dinding 22.80 m2 Dinding urinoir 1.50 12.00 18.00
Dinding Bak KM 1.00 1.20 4.00 4.80
JUMLAH 22.80
4 Pek. Pembongkaran keramik 10.56 m2 lantai t. eksisting 1.30 1.60 4.00 8.32
lantai selasar t. eksisting 0.70 3.20 2.24
JUMLAH 10.56
II PEKERJAAN TANAH
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pek. Galian Pondasi 3.65 m3 0.70 0.80 6.52 3.65
JUMLAH 3.65
2 Pek. Urugan Pasir Bawah Footplate, Pondasi & Lantai 0.26 m3 P. batu belah 0.05 0.80 6.52 0.26
Lantai Toilet 0.05
JUMLAH 0.26
3 Pek. Urugan Tanah bekas galian 0.84 m3 1/3 vol pondasi 0.70 0.80 6.52 0.84
JUMLAH 0.84
IV PEKERJAAN PASANGAN
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pasangan Batu Bata 15.11 m2 Toilet difable 2.20 6.10 13.42
Dinding 15cm
dinding belakang 0.20 6.50 1.30
Septic tank 1.50 2.50 3.75
JUMLAH 18.47
P1 2.00 0.70 1.00 1.40
PENGURANG P2 2.00 0.90 1.00 1.80
roaster 0.20 0.20 4.00 0.16
JUMLAH 3.36
JUMLAH TOTAL 15.11
2 Plesteran 30.22 m2 Toilet difable 2.20 6.10 13.42
Dinding 15cm
dinding belakang 0.20 6.50 1.30
Septic tank 1.50 2.50 3.75
JUMLAH 18.47
P1 2.00 0.70 1.00 1.40
PENGURANG P2 2.00 0.90 1.00 1.80
roaster 0.20 0.20 4.00 0.16
JUMLAH 3.36
JUMLAH TOTAL x 2 30.22
3 Acian 33.22 m2 Toilet difable 2.20 6.10 13.42
Dinding 15cm
dinding belakang 0.20 6.50 1.30
Septic tank 1.50 2.50 3.75
Kolom 2.50 0.30 2.00 1.50
JUMLAH 19.97
P1 2.00 0.70 1.00 1.40
PENGURANG P2 2.00 0.90 1.00 1.80
roaster 0.20 0.20 4.00 0.16
JUMLAH 3.36
JUMLAH TOTAL x 2 33.22
V PEKERJAAN BETON
1 Pekerjaan Sloof Struktur (SL) 15/20 cm
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
a. Pekerjaan Beton K - 175 0.18 m3 SL 0.20 0.15 6.07 0.18
JUMLAH 0.18
KET PANJANG w/m' ISI QTY JUMLAH
b. Pekerjaan Pembesian D12 26.28 Kg UTAMA 6.57 0.89 4.00 1.00 26.28
Pekerjaan Pembesian Begel Ø8 9.78 Kg BEGEL 0.56 0.39 45 1.00 9.78
VI PEKERJAAN ATAP
VOLUME SAT KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan atap baja ringan C.75.75, reng 30.45 26.00 m2 4.00 6.50 26.00
JUMLAH 26.00
JUMLAH 26.00
3 Pekerjaan talang seng 3.25 m2 0.50 6.50 3.25
JUMLAH 3.25
4 Pekerjaan Pemasangan Listplang GRC 9/200 6.50 m' 6.50 6.50
JUMLAH 6.50
IX PEKERJAAN PENGECATAN
VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
1 Pekerjaan Pengecatan Dinding Interior Ex. Envi 111.94 m2 DINDING As A 2.40 5.25 12.60
As B 2.40 2.57 2.00 12.34
As C 2.40 2.42 2.00 11.62
As D 2.40 2.42 2.00 11.62
As E 2.40 2.42 2.00 11.62
As F 2.40 2.42 5.81
As 2 2.40 3.85 9.24
As 3 2.40 3.85 2.00 18.48
As 4 3.69 4.95 18.27
Kolom 2.40 4.05 9.72
JUMLAH 121.30
PENGURANG P1 0.70 2.00 5.00 7.00
P2 0.90 2.00 1.00 1.80
Roaster 0.20 0.20 14.00 0.56
JUMLAH 9.36
JUMLAH 111.94
2 Pekerjaan Pengecatan Dinding Eksterior Ex. Envi 10.14 m2 DINDING As A 2.40 5.25 12.60
As F 2.40 2.42 5.81
As 2 2.40 3.85 5.81
As 4 3.69 4.95 18.27
Dinding kelas depan toilet 3.25 6.00 19.50
JUMLAH 61.98
PENGURANG P1 0.70 2.00 5.00 7.00
P2 0.90 2.00 1.00 1.80
Roaster 0.20 0.20 14.00 0.56
JUMLAH 9.36
JUMLAH 10.14
KET DIMENSI TINGGI LEBAR PANJANG QTY JUMLAH
3 Pekerjaan Pengecatan Plafond Ex. Envi 14.56 m2 toilet eksisting 1.05 1.25 4.00 5.25
selasar toilet eksisting 0.65 2.75 1.79
toilet difable 1.50 1.75 2.63
toilet baru 1.07 1.75 1.87
selasar toilet difable 1.10 2.75 3.03
JUMLAH 14.56
4 Pekerjaan Pengecatan Listplank 1.30 m2 0.20 6.50 1.30
JUMLAH 1.30
XI PEKERJAAN SANITASI DAN PLUMBING VOLUME SAT KET TINGGI LEBAR PANJANG QTY JUMLAH
A PEKERJAAN SANITASI
1 Pek Pasangan Closet Jongkok Porselen 1.00 Bh
2 Pek. Pasangan Closet Duduk Mono Blok Ex. Toto Seri CW702J/SW784J 1.00 Bh
3 Pek. Pasang Floordrain 6.00 Bh
4 Pemasangan Kran Ø ½" atau Ø ¾" 6.00 Bh
B PEKERJAAN PLUMBING
1 Pipa PVC AW 3" (Pipa Air Hujan) 15.00 m'
2 Pipa PVC AW 3" (Pipa Air Kotor Padat) 10.00 m'
3 Pipa PVC AW 3" (Pipa Air Kotor Cair) 10.00 m'
4 Pipa PVC AW 1" (Pipa Air Bersih) 16.50 m'
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)
I BAHAN DASAR
1 BATU BELAH
Batu Gunung Belah m3 247,500.00
2 KERIKIL
Beton 5 - 7 cm m3 253,000.00 Pecah mesin
Beton 3 - 5 cm m3 253,000.00 Pecah mesin
Beton 2 - 3 cm m3 253,000.00 Pecah mesin
Beton 1 - 2 cm m3 253,000.00 Pecah mesin
Beton 0.5 - 1 cm m3 253,000.00 Pecah Mesin
-
3 BATU BATA
ex lokal bh 800.00
Bata Ekspose bh 1,200.00 dim 4.5 x 11 x 22
Concrete Block ( CB 15 ) / Batako (lubang 2 bh 3,300.00
Roster Beton Abu Uk 20x20 bh 19,800.00
Bata ringan m3 -
4 PASIR
Urug m3 192,500.00
Pasang m3 251,200.00
Beton m3 253,000.00
5 TANAH -
Sirtu m3 151,800.00
Tanah Padas m3 63,800.00
Tanah Biasa m3 60,100.00
Sirtu (Quarry) m3 63,800.00
Tanah Padas (Quarry) m3 40,500.00
Tanah Biasa (Quarry) m3 36,000.00
Tanah Subur m3 63,800.00
-
6 KAPUR Pasang m3 231,000.00
-
7 PORTLAND CEMENT -
Portland Cement 40 kg zak 52,800.00
Portland Cement kg 1,260.00
Semen Putih 40 kg zak 112,800.00
Semen warna kg 16,500.00
Semen Putih kg 6,100.00
Pengisi Nat AM 50 kg 22,000.00
-
8 Plastik Plastik tebal 0,08 gulung 132,000.00 uk 1,5x25 m
Plastik tebal 0,08 m2 39,600.00
Plastik tebal 0,125
10 Lisplank GRC
Lisplank GRC 9/200 lbr 60,500.00 Panjang 400 cm
Lisplank GRC 9/300 lbr 99,200.00 Panjang 400 cm
Skrup 3 cm pcs 200.00
-
10 ATAP GALVALUME Atap Galvalume tebal 0,4 mm m2 81,200.00
Nok Atap Galvalume tebal 0,4 mm m' 26,800.00
Atap Galvalume tebal 0,3 mm m2 40,700.00
Nok Atap Galvalume tebal 0,3 mm m' 41,400.00
Atap Galvalume tebal 0,25 mm m2 34,700.00
Atap Spandek Transparan 0,3 mm m2 81,100.00
11 ATAP METAL Genteng Ex. Sakura Roof Elang lbr 78,700.00 Type Classic
Nok Atap Metal bh 45,300.00 Type Ratu
Penutup Nok bh 16,200.00 Type Ratu
Skrup pcs 800.00
4 HOMOGENOUS TILE
Homogenous Tile 60/60 Indogress TPZ bh 51,700.00
Homogenous Tile 60/60 Top Gress bh 38,000.00
Homogenous Tile 60/60 Cove bh 38,000.00
Homogenous Tile 60/60 Chivas bh 37,300.00
Step Nosing 10/30 m1 20,700.00
PLINT DINDING
Keramik Dinding 10/20
Keramik Dinding 10/30
Keramik Dinding 10/40
Keramik Dinding 10/60
5 BATU ALAM
Batu Andesit 20x40 m2 150,200.00
Batu Andesit 20x20 m2 138,600.00
Batu Andesit Alur 40x40 m2 161,700.00
Batu Lempeng Acak m2 67,300.00
Batu Sikat m2 129,300.00
Susun Sirih 3 x 30 cm m2 127,100.00
6 GEOMEMBRANE
Geomembrane 1 mm m2 51,300.00
Geomembrane 1.5 mm m2 71,100.00
Geomembrane 2 mm m2 97,100.00
-
V BAHAN CETAK -
1 BUIS BETON
Ø 20 cm Panjang 100 cm bh 48,400.00
Ø 30 cm Panjang 100 cm bh 60,500.00
Ø 40 cm Panjang 100 cm bh 93,500.00
Ø 50 cm Panjang 100 cm bh 132,000.00
Ø 60 cm Panjang 100 cm bh 99,000.00
Ø 60 cm Panjang 50 cm bh 13,200.00
Ø 80 cm Panjang 100 cm bh 214,500.00
Ø 80 cm Panjang 50 cm bh 143,000.00
Ø 100 cm Panjang 100 cm bh 236,500.00
Ø 100 cm Panjang 50 cm bh 187,000.00
U 10 cm - 100 cm bh 18,400.00
U 15 cm - 100 cm bh 22,400.00
U 20 cm - 100 cm bh 24,200.00
U 30 cm - 100 cm bh 30,300.00
3 PAVING -
Holland 20 x 10 x 6 cm K.250 - K.300 m2 80,500.00 Natural Ex.Master Beton
m2 92,000.00 Warna Ex.Master Beton
Holland 21 x 10,5 x 8 cm K.300 m2 103,500.00 Ex.Master Beton
m2 115,000.00 Warna Ex.Master Beton
Kubus 20 x 20 x 6 cm K.250 - K.300 m2 80,500.00 Natural
m2 92,000.00 Warna
Kubus 20 x 20 x 8 cm K.250 - K.300 m2 103,500.00 Natural
Warna
Hexagon 20 x 20 x 6 cm K.250 - K.300 m2 103,500.00 Natural
115,000.00 Warna
Grass Block Kotak 30 x 30 x 8 cm m2 80,500.00 Natural
103,500.00 Warna
Topi Uskup 30 x 21 x 6 cm K.250 - K.300 m' 5,750.00 Natural
6,325.00 Warna
Kanstein Besar/Kerb 20 x 30 x 60 cm bh 63,250.00 Ex.Master Beton
Kanstein Lock Kecil 10 x 20 x 40 cm bh 23,000.00 Ex.Master Beton
Kanstein Lock Besar 10 x 20 x 50 cm bh 28,750.00 Ex.Master Beton
Kanstein L Profil 39,5x43x42 cm bh 69,000.00 Ex.Master Beton
Kerb Standart 10/12x35x50 bh 46,000.00 Ex.Master Beton
-
4 U-DITCH -
U-Ditch 300x300x1200 Type LD Bh 354,000.00
Cover U-Ditch 300x1200 10 cm Type LD bh 230,100.00
VI BAHAN BESI -
1 BESI
Besi beton polos / Ulir / Tulangan kg 14,200.00
Besi siku kg 12,800.00
Besi Strip kg 12,800.00
Besi Plat kg 17,300.00
Wiremesh kg 12,900.00
2 BAJA -
Baja Profil / Konstruksi kg 14,900.00
Baja Teralis kg 10,600.00
Baja Konstruksi kg 12,600.00
Baut mur 8.8 3/4x2 Bh 7,300.00
Angkur Bolt NC M16x30 Bh 41,600.00
3 KAWAT -
Kawat Ikat Beton / Bendrat kg 17,300.00
Kawat Duri kg 12,300.00
Kawat Bronjong kg 17,300.00
IX BAHAN FINISHING -
1 KAYU -
Menie Kayu kg 40,700.00
Dempul plamur kg 38,300.00
Ambril/amplas lbr 4,600.00
Batu Apung kg 20,700.00
Cat Kayu Decolux kg 60,000.00
Siralax ons 10,300.00
Spiritus ltr 26,400.00
Melamik kg 53,700.00
Lem Kayu Fox Kuning kg 74,300.00
HPL Motif Serat Kayu (2,4 x 1.2 m) lbr 170,800.00
Foam Sheet 3 mm m2 6,700.00
-
2 TEMBOK -
-
5 STOPSOL Dark Blue 8 mm m2 438,700.00
Dark Green 8 mm m2 456,300.00
-
XI BAHAN INSTALASI LISTRIK -
1 KABEL NYY 3 x 2.5 mm m' 12,700.00
NYM 3 x 2.5 mm m' 16,500.00
NYFGBY 3 x 2,5 mm m' 21,300.00
NYM 2 x 2.5 mm m' 11,000.00
NYY 2 x 2.5 mm m' 9,300.00
10 Kanal C m1 44,600.00
11 Timer bh 742,500.00
12 Kontaktor bh 594,000.00
13 Terminal komplit unit 29,700.00
14 Ground Rood bh 59,400.00
15 Pipa Flexibel m1 5,900.00
16 MCB 10A bh 59,400.00
17 Isolasi bh 7,700.00
18 MCB bh 54,000.00
19 MCCB 200 A bh 1,100,000.00
20 Box MCB bh 161,900.00 Ex. Schneider
21 Isolasi bh 7,200.00
22 Box Panel MCB 30x40x20 cm bh 214,100.00
23 Box Panel MCB 60x80x20 cm bh 665,500.00
24 Rel MCB bh 22,000.00
25 Lampu Indikator bh 18,800.00
26 Sekun 4mm bh 1,900.00
27 Material Pendukung ( Isolasi, Kabel Ties dll ) Paket 360,000.00
28 Pipa PVC 2" AW m1 12,400.00
29 Klem Unit 300.00
30 Lampu
Baret / Plafond Kecil Unit 194,300.00 Ex. Panasonic Kecil
Baret / Plafond Besar Unit 262,400.00 Ex. Panasonic Besar
* LOKASI 1
A PEKERJAAN PERSIAPAN
1 Pembuatan 1 unit Direksi Keet dan Gudang 1.00 Unit 1.1.3.(a)
2 Pembuatan 1 buah Papan Nama pekerjaan dengan multiflex 10mm, frame Aluminium siku dan tiang kayu 5 1.00 bh 1.1.4.b.(a)
3 Biaya K3 1.00 Unit HITUNG K3
4 Air kerja dan Listrik 1.00 Unit HITUNG AKL
5 Pasang 1m' Bouwplank sebagai acuan dalam pembuatan infrastruktur 16.00 m' 1.7.4.d.(a)
6 Pembuatan steger / perancah bambu 1.00 Unit A.1.1.1.11
Jumlah A
B PEKERJAAN FISIK
B.1 (RUANG GURU)
I PEKERJAAN BONGKARAN
1 Pembongkaran 1m3 Pasangan batu dengan alat 3.00 m3 2.1.2.a.5.c
2 Pembongkaran genteng 227.21 m2 HITUNG PS.4
3 Pembongkaran rangka atap/kaso/reng 227.21 m2 HITUNG PS.5
4 Pembongkaran plafond 146.68 m2 HITUNG PS.6
5 Pembongkaran dinding bata merah tebal 30cm 66.38 m2 HITUNG PS.1
6 Pembongkaran keramik & rabat 16.64 m3 HITUNG PS.3
Jumlah I
II PEKERJAAN PONDASI
1 Pemasangan 1 m3 Pondasi Batu Belah Campuran 1SP : 6PP 0.12 m3 2.1.1.d.(a)
Jumlah II
III PEKERJAAN PASANGAN
1 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu Campuran 1SP: 6PP) 57.07 m2 A.4.4.1.11
2 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 batu Campuran 1SP: 6PP) 10.25 m2 A.4.4.1.5.
3 Plesteran Tebal 1,5 cm, dengan Mortar Campuran (setara 1 PC : 6 PP) 133.67 m2 3.2.2.2.17.(a)
4 Pemasangan 1 m2 Acian 183.10 m2 3.2.2.2.35.(a)
Jumlah III
IV PEKERJAAN BETON
1 Pekerjaan Sloof 20/25
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 1.21 m3 2.2.1.2.f
b. Pembesian Ø12 150.60 kg HITUNG PB 1
Pembesian Ø8 49.89 kg HITUNG PB 1
c. Begesting 12.10 m2 A.4.1.1.19
2 Pekerjaan Kolom 15/15 R.Guru
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 0.90 m3 2.2.1.2.f
b. Pembesian Ø12 146.42 kg HITUNG PB 1
Pembesian Ø8 50.83 kg HITUNG PB 1
c. Begesting 14.40 m2 A.4.1.1.19
3 Pekerjaan Kolom 15/15 Teras
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 0.39 m3 2.2.1.2.f
b. Pembesian Ø12 64.28 kg HITUNG PB 1
Pembesian Ø8 22.43 kg HITUNG PB 1
c. Begesting 10.50 m2 A.4.1.1.19
4 Pekerjaan Balok Latei 15/20
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 0.50 m3 2.2.1.2.f
b. Pembesian Ø10 42.90 kg HITUNG PB 1
Pembesian Ø8 25.41 kg HITUNG PB 1
c. Begesting 6.72 m2 A.4.1.1.19
5 Pekerjaan Ring Balk 15/20
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 2.32 m3 2.2.1.2.f
b. Pembesian Ø12 282.84 kg HITUNG PB 1
Pembesian Ø8 115.53 kg HITUNG PB 1
c. Begesting 50.18 m2 A.4.1.1.19
6 Pekerjaan Rabat Beton Bawah Lantai Tebal 5 cm
a. Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 0.67 m3 2.2.1.2.b
Jumlah IV
V PEKERJAAN ATAP
1 Pekerjaan Pemasangan Listplang GRC 9/200 49.60 m' HITUNG K.6
Jumlah V
VI PEKERJAAN LANGIT-LANGIT
1 Pekerjaan Langit-langit GRC + Rangka Hollow 181.00 m2 HITUNG PF.1
2 Pekerjaan List Plafond kayu profil 40.30 m' A.4.5.1.10
Jumlah VI
VII PEKERJAAN PENUTUP LANTAI
1 Pemasangan keramik motif 40x40 15.92 m2 A.4.4.3.36
Jumlah VII
VIII PEKERJAAN PENGECATAN
1 Pengecatan Tembok Lama Interior ( 1 Lap Cat Dasar 2 lap. Cat penutup ), Ex. Envi 128.62 m2 HITUNG PC.4
2 Pengecatan Tembok Lama Eksterior ( 1 Lap Cat Dasar 2 lap. Cat penutup ), Ex. Envi 132.03 m2 HITUNG PC.5
3 Pengecatan Tembok Baru Interior ( 1 Lap Plamur, 1 Cat Dasar 2 lap. Cat penutup ), Ex. Envi 173.25 m2 HITUNG PC.2
4 Pengecatan Tembok Baru Eksterior ( 1 Lap Plamur, 1 Cat Dasar 2 lap. Cat penutup ), Ex. Envi 146.87 m2 HITUNG PC.3
5 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup) 57.96 m2 HITUNG PC.1
6 Pengecatan Plafond Baru (2 lapisan cat penutup), Ex. Envi 156.29 m2 HITUNG PC.6
7 Pengecatan List plafond 4.03 m2 HITUNG PC.1
8 Pengecatan Listplank 9.92 m2 HITUNG PC.1
Jumlah VIII
IX PEKERJAAN MEKANIKAL ELEKTRIKAL
1 Pemasangan MCB 1 phase 10A ex schneider + box ex presto 1.00 bh HITUNG DL.1
2 Pemasangan TL 2x20 RM Armateur In Bow 15.00 bh HITUNG PC.1
3 Pemasangan LED 12 watt, Ex. Osram 5.00 bh HITUNG PC.2
4 Pemasangan Instalasi titik kabel dalam NYM 3x2.5 ex eterna 8.00 titik HITUNG DL.5
5 Pemasangan Stop kontak ex broco 8.00 bh HITUNG DL.4
6 Pemasangan Saklar tunggal ex broco 5.00 bh HITUNG DL.2
7 Pemasangan Saklar ganda ex broco 2.00 bh HITUNG DL.3
Jumlah IX
JUMLAH A+B
* LOKASI 2
A RUANG KELAS
I PEKERJAAN BONGKARAN
1 Pembongkaran genteng 194.74 m2 HITUNG PS.4
2 Pembongkaran rangka atap/kaso/reng 194.74 m2 HITUNG PS.5
3 Pembongkaran plafond 142.69 m2 HITUNG PS.6
4 Pembongkaran dinding bata merah tebal 15 cm 22.91 m2 HITUNG PS.2
5 Pembongkaran keramik & rabat 101.80 m2 HITUNG PS.5
Jumlah I
II PEKERJAAN TANAH
1 Penggalian tanah biasa untuk pondasi 7.76 m3 1.7.1.a.(c)
2 Pengurugan tanah kembali 2.59 m3 1.7.2.a.(c)
3 Mengangkut 1 m3 tanah lepas, jarak angkut > 200 s.d. 300 m 5.17 m3 1.7.15.1.h.(a)
4 Pengurugan 1 m3 dengan Pasir Urug untuk Striping Tanaman Ø 2 cm 5.73 m3 1.7.2.d.(c)
Jumlah II
III PEKERJAAN PONDASI
1 Pemasangan 1 m3 Pondasi Batu Belah Campuran 1SP : 6PP 3.10 m3 2.1.1.d.(a)
Jumlah III
IV PEKERJAAN PASANGAN
1 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu Campuran 1SP: 6PP) 49.20 m2 A.4.4.1.11
2 Pemasangan 1 m2 Plesteran 1 Pc : 6 Pp Tebal 15 mm 97.75 m2 3.2.2.(c)
3 Pemasangan 1 m2 Acian 99.91 m2 3.2.2.2.35.(a)
Jumlah IV
V PEKERJAAN BETON
1 Pekerjaan Sloof 20/25
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 0.35 m3 2.2.1.2.f
b. Pembesian Ø12 42.90 kg HITUNG PB 1
Pembesian Ø8 14.42 kg HITUNG PB 1
c. Begesting 3.53 m2 A.4.1.1.19
2 Pekerjaan Kolom 15/15
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 0.08 m3 2.2.1.2.f
b. Pembesian Ø12 13.21 kg HITUNG PB 1
Pembesian Ø8 4.60 kg HITUNG PB 1
c. Begesting 1.08 m2 A.4.1.1.19
3 Pekerjaan Balok Latei 15/20
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 1.32 m3 2.2.1.2.f
b. Pembesian Ø10 113.09 kg HITUNG PB 1
Pembesian Ø8 66.83 kg HITUNG PB 1
c. Begesting 17.60 m2 A.4.1.1.19
4 Pekerjaan Ring Balk 15/20
a. Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 0.76 m3 2.2.1.2.f
b. Pembesian Ø12 91.57 kg HITUNG PB 1
Pembesian Ø8 37.55 kg HITUNG PB 1
c. Begesting 12.62 m2 A.4.1.1.19
5 Pekerjaan Lantai Kerja Pondasi Tebal 5 cm
a. Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 0.28 m3 2.2.1.2.b
6 Pekerjaan Rabat Beton Bawah Lantai Tebal 5 cm
a. Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 5.38 m3 2.2.1.2.b
Jumlah V
VI PEKERJAAN ATAP
1 Pekerjaan Kuda-Kuda Kayu Kruing 8/12 Bentang 7.35 meter (2 Buah) 0.61 m3 HITUNG K.2
2 Pekerjaan Rangka Atap Kayu kruing 8/12 (Nok, Gording, Murplat, Skoor Angin) 0.74 m3 HITUNG K.3
3 Pekerjaan Usuk 5/7, Reng 2/3 Kayu Kruing 194.74 m2 HITUNG K.5
4 Pekerjaan Pemasangan Atap Genteng Plentong kecil Tanah Liat 194.74 m2 A.4.5.2.1
5 Pekerjaan Pemasangan Bubungan Atap Genteng Tanah Liat 15.25 m' HITUNG AT.1
6 Pekerjaan Pemasangan Listplang GRC 9/200 56.04 m' HITUNG K.6
Jumlah VI
VII PEKERJAAN LANGIT-LANGIT
1 Pekerjaan Plafond GRC + Rangka hollow 142.69 m2 HITUNG PF.1
2 Pekerjaan List Plafond kayu profil 35.90 m' A.4.5.1.10
Jumlah VII
VIII PEKERJAAN PENUTUP LANTAI
1 Pemasangan keramik putih polos, Uk. 40x40 96.97 m2 A.4.4.3.36
2 Pemasangan Paving difable (Guilding block) 4.83 m2 HITUNG LD.1
Jumlah VIII
IX PEKERJAAN PENGECATAN
1 Pengecatan Tembok Lama Interior ( 1 Lap Cat Dasar 2 lap. Cat penutup ), Ex. Catylac 92.64 m2 HITUNG PC.4
2 Pengecatan Tembok Lama Eksterior ( 1 Lap Cat Dasar 2 lap. Cat penutup ), Ex. Catylac 99.19 m2 HITUNG PC.5
3 Pengecatan Tembok Baru Interior ( 1 Lap Plamur, 1 Cat Dasar 2 lap. Cat penutup ), Ex. Catylac 71.24 m2 HITUNG PC.2
4 Pengecatan Tembok Baru Eksterior ( 1 Lap Plamur, 1 Cat Dasar 2 lap. Cat penutup ), Ex. Catylac 74.48 m2 HITUNG PC.3
5 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup) 57.96 m2 HITUNG PC.1
6 Pengecatan Plafond Baru (2 lapisan cat penutup), Ex. Catylac 142.69 m2 HITUNG PC.6
7 Pengecatan List plafond 3.59 m2 HITUNG PC.1
8 Pengecatan Listplank 11.21 m2 HITUNG PC.1
Jumlah IX
X PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu & Jendela, Kayu kruing 6/12 0.65 m3 HITUNG K.1
2 Pek. Daun Pintu & Jendela, Kayu kruing 4.75 m2 A.4.6.1.5
3 Pek. Jalusi 3/5 0.10 m3 A.4.6.1.7
4 Pek. Kaca Pintu & Jendela, tebal 5mm 12.06 m2 A.4.6.2.17
5 Pemasangan Kunci Tanam Biasa 1.00 Bh A.4.6.2.2
6 Pemasangan Engsel Pintu 3.00 Bh A.4.6.2.5
7 Pemasangan Engsel Jendela Kupu-kupu 28.00 Bh A.4.6.2.6
8 Pemasangan Kait Angin 28.00 Bh A.4.6.2.7
9 Pemasangan Kunci Selot 28.00 Bh A.4.6.2.11
Jumlah X
XI PEKERJAAN MEKANIKAL ELEKTRIKAL
1 Pemasangan MCB 1 phase 10A ex schneider + box ex presto 1.00 bh HITUNG DL.1
1 Pemasangan TL 2x20 RM Armateur In Bow 9.00 bh HITUNG PC.1
3 Pemasangan Instalasi titik kabel dalam NYM 3x2.5 ex eterna 9.00 titik HITUNG DL.5
4 Pemasangan Stop kontak ex broco 1.00 bh HITUNG DL.4
5 Pemasangan Saklar tunggal ex broco 1.00 bh HITUNG DL.2
6 Pemasangan Saklar ganda ex broco 1.00 bh HITUNG DL.3
Jumlah XI
XII PEKERJAAN RAMP & AKSES DIFABLE
1 Pengurugan tanah kembali 1.50 m3 1.7.2.a.(c)
2 Pengurugan pasir 0.30 m3 1.7.2.d.(c)
3 Beton K-175 0.66 m3 2.2.2.1.f
4 Rollag 4.20 m2 HITUNG D.1
5 Railling alumunium 27.20 m' HITUNG BA.1
Jumlah XII
XIII PEKERJAAN LOKASI 3
XII PEKERJAAN RAMP & AKSES DIFABLE
1 Pengurugan tanah kembali 1.13 m3 1.7.2.a.(c)
2 Pengurugan pasir 0.74 m3 1.7.2.d.(c)
3 Railling alumunium 17.26 m' HITUNG BA.1
Jumlah XIII
JUMLAH A
* LOKASI 3
A TOILET
I PEKERJAAN BONGKARAN
1 Pembongkaran genteng 26.00 m2 HITUNG PS.4
2 Pembongkaran rangka atap/kaso/reng 26.00 m2 HITUNG PS.5
3 Pembongkaran dinding bata merah tebal 15cm 22.80 m2 HITUNG PS.2
4 Pembongkaran keramik & rabat 10.56 m2 HITUNG PS.6
Jumlah I
II PEKERJAAN TANAH
1 Penggalian tanah biasa untuk pondasi 3.65 m3 1.7.1.a.(c)
2 Pengurugan tanah kembali 0.84 m3 1.7.2.a.(c)
3 Mengangkut 1 m3 tanah lepas, jarak angkut > 200 s.d. 300 m 2.81 m3 1.7.15.1.h.(a)
4 Pengurugan 1 m3 dengan Pasir Urug untuk Striping Tanaman Ø 2 cm 0.26 m3 1.7.2.d.(c)
Jumlah II
III PEKERJAAN PONDASI
1 Pemasangan 1 m3 Pondasi Batu Belah Campuran 1SP : 6PP 2.05 m3 2.1.1.d.(a)
Jumlah III
IV PEKERJAAN PASANGAN
1 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu Campuran 1SP: 6PP) 15.11 m2 A.4.4.1.11
2 Pemasangan 1 m2 Plesteran 1 Pc : 6 Pp Tebal 15 mm 30.22 m2 3.2.2.(c)
3 Pemasangan 1 m2 Acian 33.22 m2 3.2.2.2.35.(a)
Jumlah IV
V PEKERJAAN BETON
1 Pekerjaan Sloof 15/20
a. Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 0.18 m3 A.4.1.1.5
b. Pembesian Ø12 26.28 kg HITUNG PB 1
Pembesian Ø8 9.78 kg HITUNG PB 1
c. Begesting 3.04 m2 A.4.1.1.19
2 Pekerjaan Kolom 15/15
a. Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 0.11 m3 A.4.1.1.5
b. Pembesian Ø12 19.28 kg HITUNG PB 1
Pembesian Ø8 6.82 kg HITUNG PB 1
c. Begesting 1.50 m2 A.4.1.1.19
3 Pekerjaan Balok Latei 15/15
a. Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 0.14 m3 A.4.1.1.5
b. Pembesian Ø10 15.62 kg HITUNG PB 1
Pembesian Ø8 7.71 kg HITUNG PB 1
c. Begesting 1.83 m2 A.4.1.1.19
4 Pekerjaan Ring Balk 15/20
a. Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 0.95 m3 A.4.1.1.5
b. Pembesian Ø12 116.14 kg HITUNG PB 1
Pembesian Ø8 47.57 kg HITUNG PB 1
c. Begesting 12.61 m2 A.4.1.1.19
5 Pekerjaan Lantai Kerja Pondasi Tebal 5 cm
a. Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 0.26 m3 2.2.1.2.b
6 Pekerjaan Rabat Beton Bawah Lantai Tebal 5 cm
a. Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 0.94 m3 2.2.1.2.b
Jumlah V
VI PEKERJAAN ATAP
1 Pekerjaan atap baja ringan C.75.75, reng 30.45 26.00 m2 HITUNG AT.4
2 Pekerjaan atap galvalume 26.00 m2 HITUNG AT.5
3 Pekerjaan talang seng 3.25 m2 A.4.5.2.41
4 Pekerjaan Pemasangan Listplang GRC 9/200 6.50 m' HITUNG K.6
Jumlah VI
VII PEKERJAAN LANGIT-LANGIT
1 Pekerjaan Plafond GRC + Rangka hollow 14.56 m2 HITUNG PF.1
Jumlah VII
VIII PEKERJAAN PENUTUP LANTAI
1 Pemasangan keramik unpolish, Uk. 30x30 22.50 m2 A.4.4.3.35
2 Pemasangan keramik motif unpolish, Uk. 40x40 12.29 m2 A.4.4.3.36
Jumlah VIII
IX PEKERJAAN PENGECATAN
1 Pengecatan Tembok Interior ( 1 Lap Plamur, 1 Cat Dasar 2 lap. Cat penutup ), Ex. Envi 111.94 m2 HITUNG PC.2
2 Pengecatan Tembok Eksterior ( 1 Lap Plamur, 1 Cat Dasar 2 lap. Cat penutup ), Ex. Envi 10.14 m2 HITUNG PC.3
3 Pengecatan Plafond Baru (2 lapisan cat penutup), Ex.Envi 14.56 m2 HITUNG PC.6
4 Pengecatan Listplank 1.30 m2 HITUNG PC.1
Jumlah IX
X PEKERJAAN PINTU DAN JENDELA
1 Pekerjaan pintu kamar mandi (P1) 7.00 m2 A.4.2.1.4
2 Pekerjaan pintu kamar mandi (P2) 1.80 m2 A.4.2.1.4
3 Roaster 0.56 m2 A.4.4.1.23
Jumlah X
XI PEKERJAAN MEKANIKAL ELEKTRIKAL
1 Pemasangan MCB 1 phase 10A ex schneider + box ex presto 1.00 bh HITUNG DL.1
2 Pemasangan LED 12 watt, Ex. Osram 8.00 bh HITUNG PC.2
3 Pemasangan Instalasi titik kabel dalam NYM 3x2.5 ex eterna 6.00 titik HITUNG DL.5
4 Pemasangan Saklar tunggal ex broco 2.00 bh HITUNG DL.2
5 Pemasangan Saklar ganda ex broco 3.00 bh HITUNG DL.3
Jumlah XI
XII PEKERJAAN SANITASI DAN PLUMBING
1 Pek Pasangan Closet Jongkok Porselen 1.00 Bh A.5.1.1.2
2 Pek. Pasangan Closet Duduk Mono Blok Ex. Toto Seri CW702J/SW784JP 1.00 Bh A.5.1.1.1
3 Pek. Pasang Floordrain 6.00 Bh A.5.1.1.36
4 Pemasangan Kran Ø ½" atau Ø ¾" 6.00 Bh A.5.1.1.35
5 Pipa PVC AW 3" (Pipa Air Hujan) 15.00 m' HITUNG PG13
6 Pipa PVC AW 3" (Pipa Air Kotor Padat) 10.00 m' HITUNG PG13
7 Pipa PVC AW 3" (Pipa Air Kotor Cair) 10.00 m' HITUNG PG13
8 Pipa PVC AW 1" (Pipa Air Bersih) 16.50 m' HITUNG PG9
9 Ember Plastik 80 liter + tutup, Ex. Lion star 5.00 Bh Survei
10 Gayung 1,5 Liter, Ex. Lion star 6.00 Bh Survei
Jumlah XII
XIII PEKERJAAN LOKASI 1
XIII.1 PEKERJAAN ATAP
1 Pekerjaan Kuda - Kuda Kayu Kruing 8/12 Bentang 7.47 meter (4 Buah) 1.81 m3 HITUNG K.2
2 Pekerjaan Rangka Atap Kayu Kruing 8/12 (Nok, Gording, Murplat, Skoor Angin) 1.21 m3 HITUNG K.3
3 Pekerjaan Rangka Atap Kayu Kruing 8/12 untuk teras 0.38 m3 HITUNG K.3
4 Pekerjaan Usuk Kayu Kruing 5/7 Dan Reng Kayu Kruing 2/3 50% baru 227.21 m2 HITUNG K.4
5 Pekerjaan Pemasangan Atap Genteng Plentong kecil Tanah Liat 35% 79.52 m2 HITUNG AT.2
6 Pekerjaan Pemasangan Kembali Atap Genteng Plentong kecil Tanah Liat 65% 147.69 m2 HITUNG AT.3
7 Pekerjaan Pemasangan Talang 17.00 m' A.4.2.1.18
8 Pekerjaan Pemasangan Bubungan Atap Genteng Tanah Liat 19.15 m' HITUNG AT.1
9 Pemasangan Kunci Selot 16.00 bh A.4.6.2.11
Jumlah XIII
XIII.2 PEKERJAAN PINTU DAN JENDELA
1 Pemasangan Kunci Tanam Biasa untuk Pintu 2.00 bh A.4.6.2.2
2 Pemasangan kembali J1 4.00 bh HITUNG PKJ.1
3 Pemasangan Engsel Jendela Kupu-kupu 16.00 bh A.4.6.2.6
4 Pemasangan Kait Angin 16.00 bh A.4.6.2.7
Jumlah XIII.2
Jumlah XIII
XIV PEKERJAAN LOKASI 2
PEKERJAAN RAMP & AKSES DIFABLE
1 Beton K-175 0.48 m3 2.2.2.1.f
2 Rollag 2.56 m2 HITUNG D.1
Jumlah XIV
JUMLAH A
1,627,904.78 1,627,904.78
416,320.13 416,320.13
1,184,040.00 1,184,040.00
1,098,721.50 1,098,721.50
69,416.76 1,110,668.16
353,516.90 353,516.90
5,791,171.46
38,120.83 114,362.50
7,383.00 1,677,491.43
25,355.78 5,761,085.64
7,647.50 1,121,716.95
29,411.25 1,952,171.72
14,128.17 235,092.67
10,861,920.90
890,051.01 106,806.12
106,806.12
128,326.89 7,323,936.43
266,112.65 2,727,654.61
43,136.96 5,766,117.44
27,477.81 5,031,050.08
20,848,758.56
1,133,070.47 1,371,015.26
18,510.68 2,787,708.42
18,510.68 923,571.87
147,947.50 1,790,164.75
1,133,070.47 1,019,763.42
18,510.68 2,710,318.97
18,510.68 940,897.87
147,947.50 2,130,444.00
1,133,070.47 446,146.50
18,510.68 1,189,896.13
18,510.68 415,102.00
147,947.50 1,553,448.75
1,133,070.47 571,067.52
18,510.68 794,182.22
18,510.68 470,304.55
147,947.50 994,207.20
1,133,070.47 2,624,191.20
18,510.68 5,235,542.99
18,510.68 2,138,605.51
147,947.50 7,424,005.55
995,639.72 669,069.89
38,199,654.57
54,593.38 2,707,831.40
2,707,831.40
132,587.81 23,997,863.71
23,395.60 942,842.68
24,940,706.39
221,591.20 3,527,731.90
3,527,731.90
21,081.80 2,711,435.71
23,276.00 3,073,072.09
24,985.48 3,669,616.71
28,154.88 4,135,106.49
50,397.60 2,921,044.90
26,142.95 4,085,907.80
50,397.60 203,102.33
50,397.60 499,944.19
21,299,230.22
1,307,607.50 1,307,607.50
223,330.00 3,349,950.00
60,950.00 304,750.00
111,607.50 892,860.00
37,173.75 297,390.00
29,238.75 146,193.75
40,623.75 81,247.50
6,379,998.75
134,663,810.27
7,383.00 1,437,783.88
25,355.78 4,937,847.01
7,647.50 1,091,229.42
14,705.63 336,942.63
14,128.17 1,438,176.58
9,241,979.53
72,018.75 558,505.41
52,037.50 134,516.94
63,843.98 330,073.35
270,307.50 1,548,760.61
2,571,856.30
890,051.01 2,760,938.23
2,760,938.23
128,326.89 6,313,041.35
61,329.96 5,995,003.59
27,477.81 2,745,308.25
15,053,353.19
1,133,070.47 399,407.34
18,752.18 804,468.53
18,510.68 267,012.86
147,947.50 521,514.94
1,133,070.47 91,778.71
18,752.18 247,780.81
18,510.68 85,234.28
147,947.50 159,783.30
1,133,070.47 1,495,653.02
18,752.18 2,120,646.54
18,510.68 1,237,076.15
147,947.50 2,603,876.00
1,133,070.47 857,960.96
18,752.18 1,717,054.02
18,510.68 695,080.48
147,947.50 1,867,097.45
995,639.72 280,770.40
995,639.72 5,353,679.21
20,805,874.98
12,860,450.00 7,829,853.49
11,845,931.50 8,747,888.73
105,621.97 20,569,086.20
70,871.63 13,801,717.43
49,634.00 756,918.50
54,593.38 3,059,412.74
54,764,877.09
132,587.81 18,919,087.55
23,395.60 839,902.04
19,758,989.59
221,591.20 21,486,590.71
156,327.39 755,061.29
22,241,652.00
21,081.80 1,952,912.54
23,276.00 2,308,676.61
24,985.48 1,779,875.29
28,154.88 2,096,873.73
50,397.60 2,921,044.90
26,142.95 3,730,363.68
50,397.60 180,927.38
50,397.60 564,856.30
15,535,530.44
13,599,537.75 8,900,625.47
835,744.10 3,971,455.96
1,104,057.50 113,375.66
219,982.35 2,652,899.15
143,836.25 143,836.25
156,011.88 468,035.63
56,007.88 1,568,220.50
121,730.38 3,408,450.50
109,600.75 3,068,821.00
24,295,720.12
1,307,607.50 1,307,607.50
223,330.00 2,009,970.00
111,607.50 1,004,467.50
37,173.75 37,173.75
29,238.75 29,238.75
40,623.75 40,623.75
4,429,081.25
52,037.50 77,796.06
270,307.50 80,821.94
1,113,340.88 738,145.00
235,555.94 989,334.94
177,510.55 4,828,286.96
6,714,384.90
52,037.50 58,607.23
270,307.50 198,946.32
177,510.55 3,063,832.09
3,321,385.65
201,495,623.27
7,383.00 191,958.00
25,355.78 659,250.15
14,705.63 335,288.25
14,128.17 149,193.42
1,335,689.82
72,018.75 262,954.86
52,037.50 43,541.51
63,843.98 179,686.74
270,307.50 70,496.20
556,679.31
890,051.01 1,827,986.76
1,827,986.76
128,326.89 1,939,019.31
61,329.96 1,853,391.39
27,477.81 912,812.93
4,705,223.63
1,070,950.92 195,020.16
18,752.18 492,807.29
18,510.68 181,114.42
147,947.50 449,020.66
1,070,950.92 120,481.98
18,752.18 361,626.04
18,510.68 126,191.01
147,947.50 221,921.25
1,070,950.92 146,988.01
18,752.18 292,984.06
18,510.68 142,795.09
147,947.50 270,743.93
1,070,950.92 1,012,691.19
18,752.18 2,177,792.39
18,510.68 880,507.15
147,947.50 1,865,322.08
995,639.72 259,662.84
995,639.72 935,652.42
10,133,321.96
66,389.50 1,726,127.00
71,835.04 1,867,710.98
66,954.15 217,600.99
54,593.38 354,856.94
4,166,295.90
132,587.81 1,930,478.55
1,930,478.55
209,832.45 4,721,859.62
221,591.20 2,722,247.89
7,444,107.51
24,985.48 2,796,811.61
28,154.88 285,490.43
26,142.95 380,641.35
50,397.60 65,516.88
3,528,460.27
304,021.13 2,128,147.91
304,021.13 547,238.03
586,320.60 328,339.54
3,003,725.48
1,307,607.50 1,307,607.50
60,950.00 487,600.00
111,607.50 669,645.00
29,238.75 58,477.50
40,623.75 121,871.25
2,645,201.25
743,152.21 743,152.21
4,954,591.00 4,954,591.00
115,661.25 693,967.50
144,437.13 866,622.75
132,379.38 1,985,690.63
132,379.38 1,323,793.75
132,379.38 1,323,793.75
23,084.81 380,899.41
215,000.00 1,075,000.00
11,500.00 69,000.00
13,416,510.99
12,860,450.00 23,217,330.48
11,845,931.50 14,329,881.18
11,845,931.50 4,497,663.27
109,131.21 24,795,701.09
70,871.63 5,635,959.67
23,434.13 3,460,903.90
186,620.28 3,172,544.68
49,634.00 950,491.10
109,600.75 1,753,612.00
81,814,087.37
143,836.25 287,672.50
155,727.25 622,909.00
56,007.88 896,126.00
121,730.38 1,947,686.00
3,754,393.50
85,568,480.87
1,113,340.88 531,341.93
235,555.94 603,023.20
1,134,365.13
141,396,527.45
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
A. 1.1.1 HARGA SATUAN PEKERJAAN PERSIAPAN
HITUNG PS.1 1.000 Unit Bongkaran Dinding 30 cm (Pas. Bata, Pintu, Jendela) buangan keluar loka 29,411.25
A Tenaga 25,575.00
L.01 0.300 OH Pekerja 80,000.00 24,000.00
L.04 0.015 OH Mandor 105,000.00 1,575.00
B Bahan
C PERALATAN
D Jumlah A + B + C 25,575.00
E Overhead & Profit 15% 3,836.25
F Harga Satuan Pekerjaan (D+E) 29,411.25
HITUNG PS.2 1.000 Unit Bongkaran Dinding 15 cm (Pas. Bata, Pintu, Jendela) buangan keluar loka 14,705.63
A Tenaga 12,787.50
L.01 0.150 OH Pekerja 80,000.00 12,000.00
L.04 0.008 OH Mandor 105,000.00 787.50
B Bahan
C PERALATAN
D Jumlah A + B + C 12,787.50
E Overhead & Profit 15% 1,918.13
F Harga Satuan Pekerjaan (D+E) 14,705.63
HITUNG PS.5 1.000 Unit Pembongkaran Rangka Atap ( Kuda-kuda, Usuk dan Reng ) 25,355.78
A Tenaga 22,048.50
L.01 0.255 OH Pekerja 80,000.00 20,400.00
L.04 0.016 OH Mandor 105,000.00 1,648.50
B Bahan
C PERALATAN
D Jumlah A + B + C 22,048.50
E Overhead & Profit 15% 3,307.28
F Harga Satuan Pekerjaan (D+E) 25,355.78
1.7.1.a.(c) Penggalian 1 m3 Tanah Biasa Sedalam s.d 1 m untuk volume s.d. 200 m3 Dalam Satu Lokasi 72,018.75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 62,625.00
Pekerja L.01 OH 0.7500 80,000.00 60,000.00
Mandor L.04 OH 0.0250 105,000.00 2,625.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 62,625.00
E Overhead & Profit 15% 9,393.75
F Harga Satuan Pekerjaan (D+E) 72,018.75
1.7.15.1.h.(a) Mengangkut 1 m3 tanah lepas, jarak angkut > 200 s.d. 300 m 63,843.98
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 55,516.50
Pekerja OH 0.6513 80,000.00 52,104.00
Mandor OH 0.0325 105,000.00 3,412.50
B BAHAN
C PERALATAN
D Jumlah A + B + C 55,516.50
E Overhead & Profit 15% 8,327.48
F Harga Satuan Pekerjaan (D+E) 63,843.98
78
HARGA
BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
2.1 HARGA SATUAN PEKERJAAN PONDASI
2.1.1.d.(a) Pemasangan 1 m3 Pondasi Batu Belah Campuran 1SP : 6PP 890,051.01
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 203,250.00
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Tukang Batu L.02 OH 0.750 90,000.00 67,500.00
Kepala Tukang L.03 OH 0.075 105,000.00 7,875.00
Mandor L.04 OH 0.075 105,000.00 7,875.00
B Bahan 570,707.40
Batu Belah 15/20 m3 1.200 225,000.00 270,000.00
Portland Semen, Ex. Gresik Kg 117.000 1,475.00 172,575.00
Pasir Pasang m3 0.561 228,400.00 128,132.40
C PERALATAN
D Jumlah A + B + C 773,957.40
E Overhead & Profit 15% 116,093.61
F Harga Satuan Pekerjaan (D+E) 890,051.01
79
HARGA BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.5. Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 batu Campuran 1SP: 6PP) 266,112.65
A.4.4.1.11 Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal ½ batu Campuran 1SP: 6PP) 128,326.89
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 35,625.00
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang Batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B Bahan 75,963.60
Bata Merah 5 x 11 x 22 Buah 70.000 750.00 52,500.00
Portland Semen, Ex. Gresik Kg 8.320 1,475.00 12,272.00
Pasir Pasang m3 0.049 228,400.00 11,191.60
C PERALATAN
D Jumlah A + B + C 111,588.60
E Overhead & Profit 15% 16,738.29
F Harga Satuan Pekerjaan (D+E) 128,326.89
A.4.4.1.23 Pemasangan 1 m2 Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP 586,320.60
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 35,625.00
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang Batu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B Bahan 474,219.00
Terawang / Roster Buah 30.000 15,000.00 450,000.00
Portland Semen, Ex. Gresik kg 11.000 1,475.00 16,225.00
Pasir Pasang m3 0.035 228,400.00 7,994.00
C PERALATAN
D Jumlah A + B + C 509,844.00
E Overhead & Profit 15% 76,476.60
F Harga Satuan Pekerjaan (D+E) 586,320.60
80
HARGA
BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
3.2 HARGA SATUAN PEKERJAAN PLESTERAN
3.2.2.(c) Pemasangan 1 m2 Plesteran 1 Pc : 6 Pp Tebal 15 mm 61,329.96
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 40,650.00
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B BAHAN 12,680.40
Portland Semen, Ex. Gresik Kg 4.416 1,475.00 6,513.60
Pasir Pasang m3 0.027 228,400.00 6,166.80
C PERALATAN
D Jumlah A + B + C 53,330.40
E Overhead & Profit 15% 7,999.56
F Harga Satuan Pekerjaan (D+E) 61,329.96
3.2.2.2.17.(a) Plesteran Tebal 1,5 cm, dengan Mortar Campuran (setara 1 PC : 6 PP) 43,136.96
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 24,830.00
Pekerja L.01 OH 0.130 80,000.00 10,400.00
Tukang batu L.02 OH 0.130 90,000.00 11,700.00
Kepala Tukang L.03 OH 0.013 105,000.00 1,365.00
Mandor L.04 OH 0.013 105,000.00 1,365.00
B Bahan 12,680.40
Pasir Pasang m3 0.027 228,400.00 6,166.80
Portland Cement Kg 4.416 1,475.00 6,513.60
C PERALATAN
D Jumlah A + B + C 37,510.40
E Overhead & Profit 15% 5,626.56
F Harga Satuan Pekerjaan (D+E) 43,136.96
81
HARGA
JUMLAH
SNI #REF! KODE SAT. KOEF BAHAN/UPAH
Rp Rp
A.4.1.1.5 Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 1,070,950.92
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 115,625.00
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang Batu L.02 OH 0.250 90,000.00 22,500.00
Kepala Tukang L.03 OH 0.025 105,000.00 2,625.00
Mandor L.04 OH 0.100 105,000.00 10,500.00
B BAHAN 799,770.00
Portland Semen, Ex. Gresik Kg 326.000 1,475.00 480,850.00
Pasir Beton Kg 760.000 164.00 124,640.00
Kerikil (maksimum 30 mm) Kg 1,029.000 170.00 174,930.00
Air ltr 215.000 90.00 19,350.00
C PERALATAN 15,866.67
Molen Kapasitas 0,35 m3 hari 0.238 66,666.67 15,866.67
D Jumlah A + B + C 931,261.67
E Overhead & Profit 15% 139,689.25
F Harga Satuan Pekerjaan (D+E) 1,070,950.92
2.2.1.2.f Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 1,133,070.47
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 110,375.00
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang Batu L.02 OH 0.250 90,000.00 22,500.00
Kepala Tukang L.03 OH 0.025 105,000.00 2,625.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
B BAHAN 859,037.00
Portland Semen, Ex. Gresik Kg 371.000 1,475.00 547,225.00
Pasir Beton Kg 698.000 164.00 114,472.00
Kerikil (maksimum 30 mm) Kg 1,047.000 170.00 177,990.00
Air ltr 215.000 90.00 19,350.00
C PERALATAN 15,866.67
Molen Kapasitas 0,35 m3 hari 0.238 66,666.67 15,866.67
D Jumlah A + B + C 985,278.67
E Overhead & Profit 15% 147,791.80
F Harga Satuan Pekerjaan (D+E) 1,133,070.47
HITUNG PB 1 Pembesian tul. polos kolom, balok, ring balk dan sloof untuk 100 kg Besi Beton Ø ≤ 12 mm (semi mekanis) 1,851,068.01
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 22,520.00
Pekerja L.01 OH 0.160 80,000.00 12,800.00
Tukang Besi L.02 OH 0.080 90,000.00 7,200.00
Kepala Tukang L.03 OH 0.008 105,000.00 840.00
Mandor L.04 OH 0.016 105,000.00 1,680.00
B Bahan 1,561,840.00
Besi beton polos Kg 105.000 14,400.00 1,512,000.00
Kawat Tali Beton Kg 2.800 17,800.00 49,840.00
C PERALATAN 25,264.36
Cutter besi beton Hari 0.040 315,804.44 12,632.18
Bender besi beton Hari 0.040 315,804.44 12,632.18
D Jumlah A + B + C 1,609,624.36
E Overhead & Profit 15% 241,443.65
F Harga Satuan Pekerjaan (D+E) 1,851,068.01
82
HARGA BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
HITUNG K.1 Pembuatan & Pemasangan 1m3 Kusen Pintu & Kusen Jendela, Kayu kruing 13,599,537.75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 2,707,250.00
Pekerja L.01 OH 7.000 80,000.00 560,000.00
Tukang Kayu L.02 OH 21.000 90,000.00 1,890,000.00
Kepala Tukang L.03 OH 2.100 105,000.00 220,500.00
Mandor L.04 OH 0.350 105,000.00 36,750.00
B Bahan 9,118,435.00
Kayu kruing , Balok m3 1.100 8,203,100.00 9,023,410.00
Paku Biasa 2" - 5 " kg 1.250 18,900.00 23,625.00
Lem Kayu kg 1.000 71,400.00 71,400.00
C PERALATAN
D Jumlah A + B + C 11,825,685.00
E Overhead & Profit 0.15 1,773,852.75
F Harga Satuan Pekerjaan (D+E) 13,599,537.75
A.4.6.1.5 Pembuatan 1m2 Daun Pintu Panel, Kayu Klas I atau II 835,744.10
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 386,750.00
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang Kayu L.02 OH 3.000 90,000.00 270,000.00
Kepala Tukang L.03 OH 0.300 105,000.00 31,500.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
B Bahan 339,984.00
Kayu Klas II (Kamfer), papan m3 0.040 7,607,100.00 304,284.00
Lem Kayu kg 0.500 71,400.00 35,700.00
C PERALATAN
D Jumlah A + B + C 726,734.00
E Overhead & Profit 0.15 109,010.10
F Harga Satuan Pekerjaan (D+E) 835,744.10
A.4.6.1.7 Pembuatan 1m2 Pintu & Jendela Jalusi Kayu Kruing 1,104,057.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 386,750.00
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang Kayu L.02 OH 3.000 90,000.00 270,000.00
Kepala Tukang L.03 OH 0.300 105,000.00 31,500.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
B Bahan 573,300.00
Kayu Kruing, papan m3 0.064 8,400,000.00 537,600.00
Lem Kayu kg 0.500 71,400.00 35,700.00
C PERALATAN
D Jumlah A + B + C 960,050.00
E Overhead & Profit 0.15 144,007.50
F Harga Satuan Pekerjaan (D+E) 1,104,057.50
HITUNG K.2 Pemasangan 1m3 Konstruksi Kuda-kuda Konvensional Kayu Kruing, Bentang 7.5 meter 12,860,450.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 1,933,750.00
Pekerja L.01 OH 5.000 80,000.00 400,000.00
Tukang Kayu L.02 OH 15.000 90,000.00 1,350,000.00
Kepala Tukang L.03 OH 1.500 105,000.00 157,500.00
Mandor L.04 OH 0.250 105,000.00 26,250.00
B Bahan 9,249,250.00
Kayu Kruing, balok m3 1.100 8,203,100.00 9,023,410.00
Besi Strip Kg 15.000 8,000.00 120,000.00
Paku Biasa 12 cm Kg 5.600 18,900.00 105,840.00
C PERALATAN
D Jumlah A + B + C 11,183,000.00
E Overhead & Profit 0.15 1,677,450.00
F Harga Satuan Pekerjaan (D+E) 12,860,450.00
83
HITUNG K.3 Pemasangan 1m3 konstruksi Gording, Kayu Kruing 11,845,931.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 928,200.00
Pekerja L.01 OH 2.400 80,000.00 192,000.00
Tukang Kayu L.02 OH 7.200 90,000.00 648,000.00
Kepala Tukang L.03 OH 0.720 105,000.00 75,600.00
Mandor L.04 OH 0.120 105,000.00 12,600.00
B Bahan 9,372,610.00
Kayu Kruing, balok m3 1.100 8,203,100.00 9,023,410.00
Besi Strip Kg 15.000 19,500.00 292,500.00
Paku Biasa 12 cm Kg 3.000 18,900.00 56,700.00
C PERALATAN
D Jumlah A + B + C 10,300,810.00
E Overhead & Profit 0.15 1,545,121.50
F Harga Satuan Pekerjaan (D+E) 11,845,931.50
HITUNG K.4 Pemasangan 1m2 Rangka Atap Usuk & Reng kayu kelas II 109,131.21
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 18,575.00
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 76,321.70
Kayu Klas II (Kruing), Kaso-kaso (5x7) cm 50% m3 0.014 8,203,100.00 57,421.70
Reng (2x3) cm Jati 50% m3 0.004 7,875,000.00 14,175.00
Paku Biasa 5 - 10 cm Kg 0.250 18,900.00 4,725.00
C PERALATAN
D Jumlah A + B + C 94,896.70
E Overhead & Profit 0.15 14,234.51
F Harga Satuan Pekerjaan (D+E) 109,131.21
HITUNG K.5 Pemasangan 1m2 Rangka Atap Genteng, Kayu Kruing 105,621.97
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 18,575.00
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang Kayu L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 73,270.19
Kayu Klas II (Kruing), Kaso-kaso (5x7) cm 35% m3 0.014 8,203,100.00 40,195.19
Reng (2x3) cm Jati m3 0.004 7,875,000.00 28,350.00
Paku Biasa 5 - 10 cm Kg 0.250 18,900.00 4,725.00
C PERALATAN
D Overhead & Profit 91,845.19
E Harga Satuan Pekerjaan (D+E) 0.15 13,776.78
F Harga Satuan Pekerjaan (D+E) 105,621.97
84
HITUNG K.6 Pemasangan 1m' Lisplank GRC 9/20 54,593.38
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 28,625.00
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 18,847.50
Listplank GRC 9/20 m' 1.050 17,050.00 17,902.50
Paku Biasa 5 - 7 cm Kg 0.050 18,900.00 945.00
C PERALATAN
D Jumlah A + B + C 47,472.50
E Overhead & Profit 0.15 7,120.88
F Harga Satuan Pekerjaan (D+E) 54,593.38
85
HARGA
BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
86
HITUNG AT.3 Pemasangan kembali 1 m2 Atap Genteng Plentong Kecil 23,434.13
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 20,377.50
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang Kayu L.02 OH 0.075 90,000.00 6,750.00
Kepala Tukang L.03 OH 0.0075 105,000.00 787.50
Mandor L.04 OH 0.008 105,000.00 840.00
B Bahan
C PERALATAN
D Jumlah A + B + C 20,377.50
E Overhead & Profit 15% 3,056.63
F Harga Satuan Pekerjaan (D+E) 23,434.13
HITUNG AT.4 Pemasangan 1 m2 rangka usuk C.75.075 & reng baja ringan, Ex. Fortuna 66,389.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 23,350.00
Pekerja L.01 OH 0.125 80,000.00 10,000.00
Tukang Kayu L.02 OH 0.125 90,000.00 11,250.00
Kepala Tukang L.03 OH 0.0130 105,000.00 1,365.00
Mandor L.04 OH 0.007 105,000.00 735.00
B Bahan 27,504.00
Usuk baja ringan c.75 m' 1.440 19,100.00 27,504.00
Reng baja ringan dari bahan m' 3.680 9,100.00 33,488.00
C PERALATAN 6,876.00
Aksesories 25% dari bahan 25% 0.250 27,504.00 6,876.00
D Jumlah A + B + C 57,730.00
E Overhead & Profit 15% 8,659.50
F Harga Satuan Pekerjaan (D+E) 66,389.50
87
HARGA JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
HITUNG PF.1 Memasang 1 m2 Langit-langit GRC Board tebal 4 mm + Rangka Hollow Galvanis 132,587.81
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 46,385.00
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang besi L.02 OH 0.250 90,000.00 22,500.00
Kepala Tukang L.03 OH 0.025 105,000.00 2,625.00
Mandor L.04 OH 0.012 105,000.00 1,260.00
B Bahan 68,908.75
GRC Board 120 x240 x 0.4 cm Lbr 0.364 63,000.00 22,932.00
Besi Hollow 40 x 40 x 3.5 mm m' 1.580 7,275.00 11,494.50
Besi Hollow 20 x 40 x 3.5 mm m' 0.700 5,325.00 3,727.50
Compoun zak 0.310 3,150.00 976.50
Dinabolt bh 3.500 3,650.00 12,775.00
Cotton Plaster m' 1.38 325.00 448.50
Sekrup Buah 39.750 225.00 8,943.75
Perkuatan dan Penggantung (50% x rangka) 0.500 15,222.00 7,611.00
C PERALATAN
D Jumlah A + B + C 115,293.75
E Overhead & Profit 15% 17,294.06
F Harga Satuan Pekerjaan (D+E) 132,587.81
88
HARGA
BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING
A.4.4.3.35 Pemasangan 1 m2 Lantai Keramik Uk. 20 s.d <30 cm 209,832.45
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 94,850.00
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang Batu L.02 OH 0.350 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.035 105,000.00 3,675.00
B Bahan 87,613.00
Ubin Keramik Dus 1.050 51,900.00 54,495.00
Portland Semen Kg 10.400 1,475.00 15,340.00
Pasir Pasang m3 0.045 228,400.00 10,278.00
Semen Warna Kg 0.500 15,000.00 7,500.00
C PERALATAN
D Jumlah A + B + C 182,463.00
E Overhead & Profit 15% 27,369.45
F Harga Satuan Pekerjaan (D+E) 209,832.45
CK Boyolali
HARGA
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH JUMLAH
Rp Rp
HITUNG PC.2 1 m2 Pengecat Tembok Baru ( 1 Lap Plamuur, 1 Lap Cat Dasar, 2 lap. Cat penutup ) Ex. Envi 24,985.48
Harga Satuan Jumlah Harga
No Uraian Kode Satuan
Koefisien
(Rp) (Rp)
A Tenaga 8,246.50
Pekerja L.01 OH 0.020 80,000.00 1,600.00
Tukang Cat L.02 OH 0.063 90,000.00 5,670.00
Kepala Tukang L.03 OH 0.0063 105,000.00 661.50
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan 13,480.00
Plamir Kg 0.100 28,600.00
Cat Dasar, Ex. envi Kg 0.100 43,800.00 4,380.00
Cat Penutup 2 kali Interior, Ex. Envi Kg 0.260 35,000.00 9,100.00
C PERALATAN
D Jumlah A + B + C 21,726.50
E Overhead & Profit ### 3,258.98
F Harga Satuan Pekerjaan (D+E) 24,985.48
HITUNG PC.3 1 m2 Pengecat Tembok Baru ( 1 Lap Plamuur, 1 Lap Cat Dasar, 2 lap. Cat penutup ) Ex. Envi 28,154.88
Harga Satuan Jumlah Harga
No Uraian Kode Satuan
Koefisien
(Rp) (Rp)
A Tenaga 8,246.50
Pekerja L.01 OH 0.020 80,000.00 1,600.00
Tukang Cat L.02 OH 0.063 90,000.00 5,670.00
Kepala Tukang L.03 OH 0.0063 105,000.00 661.50
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan 16,236.00
Plamir Kg 0.100 28,600.00
Cat Dasar, Ex. envi Kg 0.100 43,800.00 4,380.00
Cat Penutup 2 kali Eksterior, Ex. Envi Kg 0.260 45,600.00 11,856.00
C PERALATAN
D Jumlah A + B + C 24,482.50
E Overhead & Profit ### 3,672.38
F Harga Satuan Pekerjaan (D+E) 28,154.88
CK Boyolali
HITUNG PC.4 1 m2 Pengecatan Tembok Lama (1 lap Cat Dasar, 2 lap Cat Penutup) 21,081.80
Harga Satuan Jumlah Harga
No Uraian Kode Satuan
Koefisien
(Rp) (Rp)
A Tenaga 6,776.00
Pekerja L.01 OH 0.028 80,000.00 2,240.00
Tukang Cat L.02 OH 0.042 90,000.00 3,780.00
Kepala Tukang L.03 OH 0.004 105,000.00 441.00
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan 11,556.00
Cat Dasar, Ex. envi Kg 0.120 43,800.00 5,256.00
Cat Penutup 2 kali Interior, Ex. Envi Kg 0.180 35,000.00 6,300.00
C PERALATAN
D Jumlah A + B + C 18,332.00
E Overhead & Profit ### 2,749.80
F Harga Satuan Pekerjaan (D+E) 21,081.80
HITUNG PC.5 1 m2 Pengecatan Tembok Lama (1 lap Cat Dasar, 2 lap Cat Penutup) 23,276.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan
Koefisien
(Rp) (Rp)
A Tenaga 6,776.00
Pekerja L.01 OH 0.028 80,000.00 2,240.00
Tukang Cat L.02 OH 0.042 90,000.00 3,780.00
Kepala Tukang L.03 OH 0.004 105,000.00 441.00
Mandor L.04 OH 0.003 105,000.00 315.00
B Bahan 13,464.00
Cat Dasar, Ex. envi Kg 0.120 43,800.00 5,256.00
Cat Penutup 2 kali Eksterior, Ex. Envi Kg 0.180 45,600.00 8,208.00
C PERALATAN
D Jumlah A + B + C 20,240.00
E Overhead & Profit ### 3,036.00
F Harga Satuan Pekerjaan (D+E) 23,276.00
CK Boyolali
HARGA JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
A.4.6.2.2 Pemasangan 1 Buah Kunci Tanam Biasa 143,836.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 51,575.00
Pekerja L.01 OH 0.010 80,000.00 800.00
Tukang Kayu L.02 OH 0.500 90,000.00 45,000.00
Kepala Tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 73,500.00
Kunci Tanam Biasa Buah 1.000 73,500.00 73,500.00
C PERALATAN
D Jumlah A + B + C 125,075.00
E Overhead & Profit 15% 18,761.25
F Harga Satuan Pekerjaan (D+E) 143,836.25
CK Boyolali
A.4.6.2.7 Pemasangan 1 Buah Engsel Angin 121,730.38
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 28,152.50
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang Kayu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.001 105,000.00 52.50
B Bahan 77,700.00
Engsel Angin Buah 1.000 77,700.00 77,700.00
C PERALATAN
D Jumlah A + B + C 105,852.50
E Overhead & Profit 15% 15,877.88
F Harga Satuan Pekerjaan (D+E) 121,730.38
CK Boyolali
HARGA
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH JUMLAH
Rp Rp
96
HARGA JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
97
A.5.1.1.35 Pemasangan 1 Buah Kran Ø ½" atau Ø ¾" 144,437.13
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 41,525.00
Pekerja L.01 OH 0.010 80,000.00 800.00
Tukang Batu L.02 OH 0.400 90,000.00 36,000.00
Kepala Tukang L.03 OH 0.040 105,000.00 4,200.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 84,072.50
Kran Air bh 1.000 84,000.00 84,000.00
Sealtape bh 0.025 2,900.00 72.50
C PERALATAN
D Jumlah A + B + C 125,597.50
E Overhead & Profit 15% 18,839.63
F Harga Satuan Pekerjaan (D+E) 144,437.13
98
HARGA JUMLAH
SNI #REF! KODE SAT. KOEF BAHAN/UPAH
Rp Rp
99
HARGA
JUMLAH
SNI #REF! KODE SAT. KOEF BAHAN/UPAH
Rp Rp
100
HARGA
BAHAN/UPAH JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N
A.4.1.1.2 Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 1,038,090.05
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 168,405.00
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 105,000.00 8,715.00
B Bahan 734,282.00
Portland Semen Kg 276.000 1,475.00 407,100.00
Pasir Beton kg 828.000 164.00 135,792.00
Kerikil (maksimum 30 mm) kg 1,012.000 170.00 172,040.00
Air ltr 215.000 90.00 19,350.00
C PERALATAN
D Jumlah A + B + C 902,687.00
E Overhead & Profit 15% 135,403.05
F Harga Satuan Pekerjaan (D+E) 1,038,090.05
A.4.1.1.5 Membuat 1 m3 Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 1,113,401.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 168,405.00
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 105,000.00 8,715.00
B BAHAN 799,770.00
Portland Semen Kg 326.000 1,475.00 480,850.00
Pasir Beton Kg 760.000 164.00 124,640.00
Kerikil (maksimum 30 mm) Kg 1,029.000 170.00 174,930.00
Air ltr 215.000 90.00 19,350.00
C PERALATAN
D Jumlah A + B + C 968,175.00
E Overhead & Profit 15% 145,226.25
F Harga Satuan Pekerjaan (D+E) 1,113,401.25
A.4.1.1.7 Membuat 1 m3 Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 1,181,558.30
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 168,405.00
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang Batu L.02 OH 0.275 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 105,000.00 8,715.00
B BAHAN 859,037.00
Portland Semen Kg 371.000 1,475.00 547,225.00
Pasir Beton Kg 698.000 164.00 114,472.00
Kerikil (maksimum 30 mm) Kg 1,047.000 170.00 177,990.00
Air ltr 215.000 90.00 19,350.00
C PERALATAN
D Jumlah A + B + C 1,027,442.00
E Overhead & Profit 15% 154,116.30
F Harga Satuan Pekerjaan (D+E) 1,181,558.30
A.4.1.1.19 Memasang 1 m2 Bekisting untuk Sloof, Balok Latei, Ring Balk, Kolom Praktis Beton bangunan Gedung 147,947.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 70,460.00
Pekerja L.01 OH 0.520 80,000.00 41,600.00
Tukang Kayu L.02 OH 0.260 90,000.00 23,400.00
Kepala Tukang L.03 OH 0.026 105,000.00 2,730.00
Mandor L.04 OH 0.026 105,000.00 2,730.00
B Bahan 58,190.00
Kayu Klas III m3 0.018 2,887,500.00 51,975.00
Paku Biasa 2" - 5" Kg 0.300 18,900.00 5,670.00
Minyak Bekisting Ltr 0.100 5,450.00 545.00
C PERALATAN
D Jumlah A + B + C 128,650.00
E Overhead & Profit 15% 19,297.50
F Harga Satuan Pekerjaan (D+E) 147,947.50
101
HARGA JUMLAH
BAHAN/UPAH
SNI #REF! KODE SAT. KOEF
Rp Rp
A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK
A.4.1.2.5 Membuat 1m2 Begesting untuk Pelat Beton Pracetak Komponen Modular Bangunan Gedung ( 5x Pakai) 384,227.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 8,345.00
Pekerja L.01 OH 0.007 80,000.00 560.00
Tukang Kayu L.02 OH 0.076 90,000.00 6,840.00
Kepala Tukang L.03 OH 0.008 105,000.00 840.00
Mandor L.04 OH 0.001 105,000.00 105.00
B BAHAN 325,765.65
Lantai Kerja t=10cm m3 0.008 1,234,181.15 9,873.45
Besi Hollow (50x50x3) mm kg 9.394 29,100.00 273,365.40
Kayu kaso 5/7 (lebar 5cm, tinggi 7cm) m3 0.005 2,887,500.00 14,437.50
Phenol film 12mm lbr 0.080 157,500.00 12,600.00
Minyak Begesting Ltr 0.200 6,600.00 1,320.00
Dinabolt Ø12 mm bh 3.882 3,650.00 14,169.30
C PERALATAN
D Jumlah A + B + C 334,110.65
E Overhead & Profit 15% 50,116.60
F Harga Satuan Pekerjaan (D+E) 384,227.25
A.4.1.2.6 Membuat 1 m2 Begesting untuk Balok Beton Pracetak (10-12 kali pakai) 34,458.43
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 4,265.00
Pekerja L.01 OH 0.004 80,000.00 320.00
Tukang Kayu L.02 OH 0.038 90,000.00 3,420.00
Kepala Tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.001 105,000.00 105.00
B BAHAN 25,698.85
Kayu Kaso 5/7 cm m3 0.005 2,887,500.00 14,437.50
Phenol film 12 mm lbr 0.043 157,500.00 6,772.50
minyak begesting ltr 0.200 5,450.00 1,090.00
paku 5-7 cm kg 0.046 18,900.00 869.40
Dinabolt Ø12 mm bh 0.693 3,650.00 2,529.45
C PERALATAN
D Jumlah A + B + C 29,963.85
E Overhead & Profit 15% 4,494.58
F Harga Satuan Pekerjaan (D+E) 34,458.43
A.4.1.2.7 Membuat 1 m2 Begesting untuk Kolom Beton Pracetak (10-12 kali pakai) 32,043.43
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 4,265.00
Pekerja L.01 OH 0.004 80,000.00 320.00
Tukang Kayu L.02 OH 0.038 90,000.00 3,420.00
Kepala Tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.001 105,000.00 105.00
B BAHAN 23,598.85
Kayu Kaso 5/7 cm m3 0.004 2,887,500.00 11,550.00
Phenol film 12 mm lbr 0.048 157,500.00 7,560.00
minyak begesting ltr 0.200 5,450.00 1,090.00
paku 5-7 cm kg 0.046 18,900.00 869.40
Dinabolt Ø12 mm bh 0.693 3,650.00 2,529.45
C PERALATAN
D Jumlah A + B + C 27,863.85
E Overhead & Profit 15% 4,179.58
F Harga Satuan Pekerjaan (D+E) 32,043.43
A.4.1.2.8 Pemasangan dan Membuka 1 Unit Cetakan 1 buah Komponen Pelat Beton Pracetak 7,342.75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 6,385.00
Pekerja L.01 OH 0.053 80,000.00 4,240.00
Tukang Kayu L.02 OH 0.018 90,000.00 1,620.00
Mandor L.04 OH 0.005 105,000.00 525.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 6,385.00
E Overhead & Profit 15% 957.75
F Harga Satuan Pekerjaan (D+E) 7,342.75
A.4.1.2.9 Pemasangan dan Membuka 1 unit Cetakan 1 buah Komponen Balok Beton Pracetak 11,896.75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 10,345.00
Pekerja L.01 OH 0.089 80,000.00 7,120.00
Tukang Kayu L.02 OH 0.030 90,000.00 2,700.00
Mandor L.04 OH 0.005 105,000.00 525.00
B BAHAN
102
C PERALATAN
D Jumlah A + B + C 10,345.00
E Overhead & Profit 15% 1,551.75
F Harga Satuan Pekerjaan (D+E) 11,896.75
A.4.1.2.10 Pemasangan dan Membuka1 unit Cetakan 1 buah Komponen Kolom Beton Pracetak 9,619.75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 8,365.00
Pekerja L.01 OH 0.071 80,000.00 5,680.00
Tukang Kayu L.02 OH 0.024 90,000.00 2,160.00
Mandor L.04 OH 0.005 105,000.00 525.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 8,365.00
E Overhead & Profit 15% 1,254.75
F Harga Satuan Pekerjaan (D+E) 9,619.75
A TENAGA 49,579.00
Pekerja L.01 OH 0.064 80,000.00 5,120.00
Tukang batu L.02 OH 0.244 90,000.00 21,960.00
Tukang Vibrator L.02 OH 0.128 88,000.00 11,264.00
Kepala tukang L.03 OH 0.034 105,000.00 3,570.00
Mandor L.04 OH 0.073 105,000.00 7,665.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 49,579.00
E Overhead & Profit 15% 7,436.85
F Harga Satuan Pekerjaan (D+E) 57,015.85
A TENAGA 50,994.00
Pekerja L.01 OH 0.069 80,000.00 5,520.00
Tukang batu L.02 OH 0.242 90,000.00 21,780.00
Tukang Vibrator L.02 OH 0.138 88,000.00 12,144.00
Kepala tukang L.03 OH 0.037 105,000.00 3,885.00
Mandor L.04 OH 0.073 105,000.00 7,665.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 50,994.00
E Overhead & Profit 15% 7,649.10
F Harga Satuan Pekerjaan (D+E) 58,643.10
A TENAGA 45,916.00
Pekerja L.01 OH 0.061 80,000.00 4,880.00
Tukang batu L.02 OH 0.213 90,000.00 19,170.00
Tukang Vibrator L.02 OH 0.122 88,000.00 10,736.00
Kepala tukang L.03 OH 0.033 105,000.00 3,465.00
Mandor L.04 OH 0.073 105,000.00 7,665.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 45,916.00
E Overhead & Profit 15% 6,887.40
F Harga Satuan Pekerjaan (D+E) 52,803.40
A.4.1.2.14 Pemasangan Komponen untuk 1 Unit Pelat Beton Pracetak beserta Indeks Kenaikan Lantai Ereksi Pelat hingga 24 Lantai 354,774.14
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 50,183.00
Pekerja L.01 OH 0.067 80,000.00 5,360.00
Tukang batu L.02 OH 0.067 90,000.00 6,030.00
Tukang Ereksi L.02 OH 0.134 88,000.00 11,792.00
Kepala tukang L.03 OH 0.067 105,000.00 7,035.00
Mandor L.04 OH 0.067 105,000.00 7,035.00
Operator Crane L.08 OH 0.067 105,000.00 7,035.00
Pembantu Operator Crane L.09 OH 0.067 88,000.00 5,896.00
B BAHAN
C PERALATAN 258,316.25
sewa crane unit hari 0.067 3,837,406.72 257,106.25
sewa pipe support buah hari 1.100 1,100.00 1,210.00
D Jumlah A + B + C 308,499.25
E Overhead & Profit 15% 46,274.89
F Harga Satuan Pekerjaan (D+E) 354,774.14
Indeks Pengali Menurut Tingkat Lantai Pemasangan Komponen untuk Pelat Pracetak
103
Indeks kenaikan lantai ereksi pelat Lantai Lantai Indeks kenaikan lantai
ereksi pelat
1.000 13 1 1.114
1.000 14 2 1.134
1.000 15 3 1.155
1.000 16 4 1.176
1.000 17 5 1.197
1.000 18 6 1.219
1.000 19 7 1.241
1.018 20 8 1.264
1.037 21 9 1.287
1.055 22 10 1.31
1.075 23 11 1.334
1.094 24 12 1.358
A.4.1.2.15 Pemasangan Komponen untuk 1 unit Balok Beton Pracetak beserta Indeks Kenaikan Lantai Ereksi Pelat hingga 24 Lantai 372,124.83
A TENAGA 46,055.00
Pekerja L.01 OH 0.061 80,000.00 4,880.00
Tukang batu L.02 OH 0.061 90,000.00 5,490.00
Tukang Ereksi L.02 OH 0.122 90,000.00 10,980.00
Kepala tukang L.03 OH 0.061 105,000.00 6,405.00
Mandor L.04 OH 0.061 105,000.00 6,405.00
Operator Crane L.08 OH 0.061 105,000.00 6,405.00
Pembantu Operator Crane L.09 OH 0.061 90,000.00 5,490.00
B BAHAN
C PERALATAN 277,531.81
sewa crane unit hari 0.061 3,837,406.72 234,081.81
sewa Scaffolding buah hari 1.100 39,500.00 43,450.00
D Jumlah A + B + C 323,586.81
E Overhead & Profit 15% 48,538.02
F Harga Satuan Pekerjaan (D+E) 372,124.83
Indeks Pengali Menurut Tingkat Lantai Pemasangan Komponen untuk Pelat Pracetak
Indeks kenaikan balok
Indeks kenaikan balok ereksi pelat Lantai Lantai
ereksi pelat
1.000 13 1 1.068
1.000 14 2 1.08
1.000 15 3 1.092
1.000 16 4 1.104
1.000 17 5 1.116
1.000 18 6 1.129
1.000 19 7 1.141
1.011 20 8 1.154
1.022 21 9 1.166
1.034 22 10 1.179
1.045 23 11 1.192
1.057 24 12 1.206
A TENAGA 4,940.00
Pekerja L.01 OH 0.019 80,000.00 1,520.00
Tukang batu L.02 OH 0.038 90,000.00 3,420.00
B BAHAN
C PERALATAN 72,910.73
sewa crane unit hari 0.019 3,837,406.72 72,910.73
D Jumlah A + B + C 77,850.73
E Overhead & Profit 15% 11,677.61
F Harga Satuan Pekerjaan (D+E) 89,528.34
A TENAGA 4,940.00
Pekerja L.01 OH 0.019 80,000.00 1,520.00
Tukang batu L.02 OH 0.038 90,000.00 3,420.00
B BAHAN
C PERALATAN 72,910.73
sewa crane unit hari 0.019 3,837,406.72 72,910.73
D Jumlah A + B + C 77,850.73
E Overhead & Profit 15% 11,677.61
F Harga Satuan Pekerjaan (D+E) 89,528.34
A TENAGA 4,940.00
Pekerja L.01 OH 0.019 80,000.00 1,520.00
Tukang batu L.02 OH 0.038 90,000.00 3,420.00
B BAHAN
C PERALATAN 72,910.73
sewa crane unit hari 0.019 3,837,406.72 72,910.73
104
D Jumlah A + B + C 77,850.73
E Overhead & Profit 15% 11,677.61
F Harga Satuan Pekerjaan (D+E) 89,528.34
A TENAGA 39,905.00
Pekerja L.01 OH 0.367 80,000.00 29,360.00
Tukang batu L.02 OH 0.074 90,000.00 6,660.00
Mandor L.04 OH 0.037 105,000.00 3,885.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 39,905.00
E Overhead & Profit 15% 5,985.75
F Harga Satuan Pekerjaan (D+E) 45,890.75
A TENAGA 26,865.00
Pekerja L.01 OH 0.147 80,000.00 11,760.00
Tukang batu L.02 OH 0.147 90,000.00 13,230.00
Kepala Tukang L.03 OH 0.015 90,000.00 1,350.00
Mandor L.04 OH 0.005 105,000.00 525.00
B BAHAN 51,189.60
Kayu Kaso 5/7 m3 0.012 2,887,500.00 34,650.00
Papan Cor m3 0.004 2,887,500.00 11,550.00
Paku 5-7 cm kg 0.264 18,900.00 4,989.60
C PERALATAN
D Jumlah A + B + C 78,054.60
E Overhead & Profit 15% 11,708.19
F Harga Satuan Pekerjaan (D+E) 89,762.79
A TENAGA 40,535.00
Pekerja L.01 OH 0.220 80,000.00 17,600.00
Tukang batu L.02 OH 0.022 90,000.00 1,980.00
Kepala Tukang L.03 OH 0.220 90,000.00 19,800.00
Mandor L.04 OH 0.011 105,000.00 1,155.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 40,535.00
E Overhead & Profit 15% 6,080.25
F Harga Satuan Pekerjaan (D+E) 46,615.25
105
HARGA
JUMLAH
SNI #REF! KODE SAT. KOEF BAHAN/UPAH
Rp Rp
A.4.4.2.24 Pemasangan 1 m2 Finishing Siar Pasangan Dinding Bata Merah (=20 m') 28,766.45
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 20,430.00
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang batu L.02 OH 0.075 90,000.00 6,750.00
Kepala Tukang L.03 OH 0.008 105,000.00 840.00
Mandor L.04 OH 0.008 105,000.00 840.00
B Bahan 4,584.30
Portland Cement Kg 3.108 1,475.00 4,584.30
C PERALATAN
D Jumlah (A+B+C) 25,014.30
E Overhead & Profit 15% 3,752.15
F Harga Satuan Pekerjaan (D+E) 28,766.45
A.4.4.2.25 Pemasangan 1 m2 Finishing Siar Pasangan Dinding Conblock ekspose (=8 m') 13,742.50
106
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 9,590.00
Pekerja L.01 OH 0.070 80,000.00 5,600.00
Tukang batu L.02 OH 0.035 90,000.00 3,150.00
Kepala Tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.004 105,000.00 420.00
B Bahan 2,360.00
Portland Cement Kg 1.600 1,475.00 2,360.00
C PERALATAN
D Jumlah (A+B+C) 11,950.00
E Overhead & Profit 15% 1,792.50
F Harga Satuan Pekerjaan (D+E) 13,742.50
A.4.4.2.26 Pemasangan 1 m2 Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp 60,653.65
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 40,650.00
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.150 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B Bahan 12,092.30
Portland Cement Kg 6.340 1,475.00 9,351.50
Pasir Pasang m3 0.012 228,400.00 2,740.80
C PERALATAN
D Jumlah (A+B+C) 52,742.30
E Overhead & Profit 15% 7,911.35
F Harga Satuan Pekerjaan (D+E) 60,653.65
107
HARGA
SNI #REF! KODE SAT. KOEF BAHAN/UPAH JUMLAH
Rp Rp
CK Boyolali
HARGA
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH JUMLAH
Rp Rp
109
HARGA
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH JUMLAH
Rp Rp
110
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
1.1.b.(c) Pembuatan 1 m' Pagar Sementara dari Seng Gelombang Tinggi 2 m 961,376.66
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 56,200.00
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang Kayu L.02 OH 0.400 90,000.00 36,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
B BAHAN 779,779.70
Kayu Dolken diameter 8 - 10 / 400 cm Btg 1.250 26,200.00 32,750.00
Portland Semen Kg 2.500 1,475.00 3,687.50
Seng gelombang BJLS 28 Lbr 1.200 107,100.00 128,520.00
Pasir Beton m3 0.005 230,000.00 1,150.00
Koral Beton m3 0.009 230,000.00 2,070.00
Kayu 5/7x 4m Kayu Kruing m3 0.072 8,203,100.00 590,623.20
Paku Biasa 2" - 5" Kg 0.060 18,900.00 1,134.00
Meni Besi Liter 0.450 44,100.00 19,845.00
C PERALATAN
D Jumlah A + B + C 835,979.70
E Overhead & Profit 15% 125,396.96
F Harga Satuan Pekerjaan (D+E) 961,376.66
1.1.c.(c) Membuat 1 m' Pagar Sementara dari Kawat Duri Tinggi 1.8 m 460,809.60
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 47,200.00
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang Kayu L.02 OH 0.300 90,000.00 27,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
B BAHAN 353,504.00
Kayu Dolken diameter 8 - 10 / 400 cm m' 1.000 26,200.00 26,200.00
Portland Semen Kg 2.000 1,475.00 2,950.00
Kawat duri 1.2 mm m' 25.000 12,800.00 320,000.00
Pasir Beton m3 0.005 230,000.00 1,150.00
Koral Beton m3 0.009 230,000.00 2,070.00
Paku Biasa 2" - 5" Kg 0.060 18,900.00 1,134.00
C PERALATAN
D Jumlah A + B + C 400,704.00
E Overhead & Profit 15% 60,105.60
F Harga Satuan Pekerjaan (D+E) 460,809.60
1.7.4.d.(a) Pasang 1m' Bouwplank sebagai acuan dalam pembuatan infrastruktur 69,416.76
CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
1.1.e.(c) Pembuatan 1 m2 Kantor Sementara/ Gudang dg Lantai Plesteran, dinding setengah tembok 2,765,961.60
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 466,750.00
Pekerja L.01 OH 2.000 80,000.00 160,000.00
Tukang Kayu L.02 OH 2.000 90,000.00 180,000.00
Tukang Batu L.02 OH 1.000 90,000.00 90,000.00
Kepala Tukang L.03 OH 0.300 105,000.00 31,500.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
B Bahan 1,938,434.00
Kayu Dolken Ø 8 - 10 / 4 m m' 1.250 26,200.00 32,750.00
Kayu m3 0.180 8,203,100.00 1,476,558.00
Paku Biasa 2" - 5" Kg 0.080 18,900.00 1,512.00
Besi Strip Kg 1.100 19,500.00 21,450.00
Portland Sement Kg 35.000 1,475.00 51,625.00
Pasir pasang m3 0.150 228,400.00 34,260.00
Pasir Beton m3 0.100 230,000.00 23,000.00
Koral Beton m3 0.150 230,000.00 34,500.00
Batu bata Merah buah 30.000 750.00 22,500.00
Seng Plat Lbr 0.250 21,000.00 5,250.00
Jendela naco buah 0.200 960,000.00 192,000.00
Kaca polos m2 0.080 157,500.00 12,600.00
Kunci Tanam buah 0.150 178,500.00 26,775.00
Plywood 4 mm Lbr 0.060 60,900.00 3,654.00
C PERALATAN
D Jumlah A + B + C 2,405,184.00
E Overhead & Profit 15% 360,777.60
F Harga Satuan Pekerjaan (D+E) 2,765,961.60
1.1.f.(c) Pembersihan dan Pengupasan 1 m2 Permukaan Tanah (Striping) s.d Tanaman Ø 2cm 9,803.75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 8,525.00
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan
C PERALATAN
D Jumlah A + B + C 8,525.00
E Overhead & Profit 15% 1,278.75
F Harga Satuan Pekerjaan (D+E) 9,803.75
CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
B Bahan 56,284.00
Batu Belah m3 0.150 225,000.00 33,750.00
Batu Pecah m3 0.090 225,000.00 20,250.00
Pasir Pasang m3 0.010 228,400.00 2,284.00
C PERALATAN
D Jumlah A + B + C 90,384.00
E Overhead & Profit 15% 13,557.60
F Harga Satuan Pekerjaan (D+E) 103,941.60
Pemagaran 1 m' daerah kerja dengan seng gelombang BJLS-30, tinggi 1,8 m dengan rangka baja
1.1.2.a L,40.40.4 598,363.53
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 37,600.00
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.100 105,000.00 10,500.00
Mandor L.04 OH 0.020 105,000.00 2,100.00
B Bahan 482,716.11
Baja L.40.40.4 kg 13.500 19,500.00 263,250.00
Kawat Seng 3mm kg 0.300 17,800.00 5,340.00
Pasangan Batu 20/50, t= 40cm Kg 0.150 570,707.40 85,606.11
Seng Gelombang BJLS 32 Lbr 1.200 107,100.00 128,520.00
C PERALATAN
D Jumlah A + B + C 520,316.11
E Overhead & Profit 15% 78,047.42
F Harga Satuan Pekerjaan (D+E) 598,363.53
1.1.2.b Pemagaran 1 m' daerah kerja dengan seng gelombang BJLS-30, tinggi 1,8 m dengan rangka Kayu 435,537.90
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 35,190.00
Pekerja L.01 OH 0.180 80,000.00 14,400.00
Tukang L.02 OH 0.100 105,000.00 10,500.00
Kepala Tukang L.03 OH 0.080 105,000.00 8,400.00
Mandor L.04 OH 0.018 105,000.00 1,890.00
B Bahan 343,538.61
Kaso 5/7 Kayu kelas II m3 0.035 2,887,500.00 101,062.50
Paku Seng kg 0.300 18,900.00 5,670.00
Paku 7 cm kg 1.200 18,900.00 22,680.00
Pasangan Batu 20/50, t= 40cm m3 0.150 570,707.40 85,606.11
Seng Gelombang BJLS 32 Lbr 1.200 107,100.00 128,520.00
C PERALATAN
D Jumlah A + B + C 378,728.61
CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
1.1.4.a.(a) Pembuatan 1 buah Papan Nama pekerjaan dengan multiflex 18mm, frame Aluminium siku dan tiang kayu 8 980,561.88
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 326,000.00
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang Kayu L.02 OH 1.000 90,000.00 90,000.00
Kepala Tukang L.03 OH 0.100 105,000.00 10,500.00
Tukang Cat dan tulis L.02 OH 1.500 90,000.00 135,000.00
Mandor L.04 OH 0.100 105,000.00 10,500.00
B Bahan 526,662.50
Multiflex 18mm, uk. 0,8m x 1,2m Lbr 0.350 189,000.00 66,150.00
Tiang Kayu 8/12 kelas II, tinggi 4m m3 0.077 2,887,500.00 222,337.50
Frame Aluminium L.30.30.3 kg 5.800 8,500.00 49,300.00
Paku Campuran 5 - 7 cm kg 1.250 18,900.00 23,625.00
Cat Kayu kg 2.500 66,100.00 165,250.00
C PERALATAN
D Jumlah A + B + C 852,662.50
E Overhead & Profit 15% 127,899.38
F Harga Satuan Pekerjaan (D+E) 980,561.88
1.1.4.b.(a) Pembuatan 1 buah Papan Nama pekerjaan dengan multiflex 10mm, frame Aluminium siku dan tiang kayu 5 416,320.13
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 145,875.00
Pekerja L.01 OH 0.750 80,000.00 60,000.00
Tukang Kayu L.02 OH 0.750 90,000.00 67,500.00
Kepala Tukang L.03 OH 0.100 105,000.00 10,500.00
Mandor L.04 OH 0.075 105,000.00 7,875.00
B Bahan 216,142.50
Multiflex 10mm, 0,6m x 0,8m Lbr 0.180 131,200.00 23,616.00
Tiang Kayu 5/7 kelas II, tinggi 3m m3 0.021 2,887,500.00 60,637.50
Frame Aluminium L.10.1 kg 0.100 5,700.00 570.00
Banner Plastik 0,6 x 0,8 m2 m2 0.480 17,800.00 8,544.00
Paku Campuran 5 - 7 cm kg 1.250 18,900.00 23,625.00
CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
1.3.1.1.1.a.(a) Pengeboran Sumur Air Tanah Dangkal Ø1" - 1,25" pada tanah biasa 20,671.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 17,975.00
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Juru Bor L.14 OH 0.050 88,000.00 4,400.00
Mandor L.04 OH 0.015 105,000.00 1,575.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor dan mata bor Ø1,25" Hari 0.050 -
D Jumlah A + B + C 17,975.00
E Overhead & Profit 15% 2,696.25
F Harga Satuan Pekerjaan (D+E) 20,671.25
1.3.1.1.1.b.(a) Pengeboran Sumur Air Tanah Dangkal Ø1" - 1,25" pada tanah keras / cadas 81,859.88
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 71,182.50
Pekerja L.01 OH 0.750 80,000.00 60,000.00
Juru Bor L.14 OH 0.250 - -
Mandor L.04 OH 0.107 105,000.00 11,182.50
B BAHAN -
C PERALATAN -
Stang bor, batang bor dan mata bor Ø1,25" Hari 0.250 -
D Jumlah A + B + C 71,182.50
E Overhead & Profit 15% 10,677.38
F Harga Satuan Pekerjaan (D+E) 81,859.88
1.3.1.1.1.c.(a) Pengeboran Sumur Air Tanah Dangkal Ø1" - 1,25" pada tanah berbatu lunak 124,890.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 108,600.00
Pekerja L.01 OH 1.200 80,000.00 96,000.00
Juru Bor L.14 OH 0.400 - -
Mandor L.04 OH 0.120 105,000.00 12,600.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor dan mata bor Ø1,25" Hari 0.400 -
D Jumlah A + B + C 108,600.00
E Overhead & Profit 15% 16,290.00
F Harga Satuan Pekerjaan (D+E) 124,890.00
1.3.1.1.1.d.(a) Pengeboran Sumur Air Tanah Dangkal Ø1" - 1,25" pada tanah berbatu keras 312,225.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 271,500.00
Pekerja L.01 OH 3.000 80,000.00 240,000.00
Juru Bor L.14 OH 1.000 - -
Mandor L.04 OH 0.300 105,000.00 31,500.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor dan mata bor Ø1,25" Hari 1.000 -
D Jumlah A + B + C 271,500.00
E Overhead & Profit 15% 40,725.00
F Harga Satuan Pekerjaan (D+E) 312,225.00
1.3.1.1.1.e.(a) Pemasangan 1m' Sumur Bor Air Tanah Dangkal Ø1" - 1,25" 312,225.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 271,500.00
Pekerja L.01 OH 3.000 80,000.00 240,000.00
Juru Bor L.14 OH 1.000 - -
Mandor L.04 OH 0.300 105,000.00 31,500.00
B BAHAN -
CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
C PERALATAN -
Stang bor, batang bor dan mata bor Ø1,25" Hari 1.000 -
D Jumlah A + B + C 271,500.00
E Overhead & Profit 15% 40,725.00
F Harga Satuan Pekerjaan (D+E) 312,225.00
1.3.1.1.2.a.(a) Pengeboran Sumur Air Tanah Dangkal Ø2" pada tanah biasa 24,978.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 21,720.00
Pekerja L.01 OH 0.240 80,000.00 19,200.00
Juru Bor L.14 OH 0.080 - -
Mandor L.04 OH 0.024 105,000.00 2,520.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor Ø1,25" Hari 0.080 -
mata bor Ø2" Hari 0.080 -
D Jumlah A + B + C 21,720.00
E Overhead & Profit 15% 3,258.00
F Harga Satuan Pekerjaan (D+E) 24,978.00
1.3.1.1.2.b.(a) Pengeboran Sumur Air Tanah Dangkal Ø2" pada tanah Keras / Cadas 124,890.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 108,600.00
Pekerja L.01 OH 1.200 80,000.00 96,000.00
Juru Bor L.14 OH 0.400 - -
Mandor L.04 OH 0.120 105,000.00 12,600.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor Ø1,25" Hari 0.400 -
mata bor Ø4" Hari 0.400 -
D Jumlah A + B + C 108,600.00
E Overhead & Profit 15% 16,290.00
F Harga Satuan Pekerjaan (D+E) 124,890.00
1.3.1.1.2.c.(a) Pengeboran Sumur Air Tanah Dangkal Ø2" pada tanah berbatu lunak 199,824.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 173,760.00
Pekerja L.01 OH 1.920 80,000.00 153,600.00
Juru Bor L.14 OH 0.640 - -
Mandor L.04 OH 0.192 105,000.00 20,160.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor Ø1,25" Hari 0.640 -
mata bor Ø4" Hari 0.640 -
D Jumlah A + B + C 173,760.00
E Overhead & Profit 15% 26,064.00
F Harga Satuan Pekerjaan (D+E) 199,824.00
1.3.1.1.2.d.(a) Pengeboran Sumur Air Tanah Dangkal Ø2" pada tanah berbatu Keras 499,560.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 434,400.00
Pekerja L.01 OH 4.800 80,000.00 384,000.00
Juru Bor L.14 OH 1.600 - -
Mandor L.04 OH 0.480 105,000.00 50,400.00
B BAHAN -
C PERALATAN -
Stang bor, batang bor Ø1,25" Hari 1.600 -
mata bor Ø4" Hari 1.600 -
D Jumlah A + B + C 434,400.00
E Overhead & Profit 15% 65,160.00
CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
1.3.1.1.2.e.(a) Pemasangan 1m' Sumur Air Tanah Dangkal GIP Ø2" 15,611.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 13,575.00
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Juru Bor L.14 OH 0.050 - -
Mandor L.04 OH 0.015 105,000.00 1,575.00
B BAHAN -
Pipa GI Medium Ø2" m' 1.000 -
Pipa GI Medium Ø2" - Peloksok bh 0.167 -
C PERALATAN -
Stang bor Ø1,25" Hari 0.050 -
D Jumlah A + B + C 13,575.00
E Overhead & Profit 15% 2,036.25
F Harga Satuan Pekerjaan (D+E) 15,611.25
1.3.1.1.3.a.(a) Pengeboran Sumur Air Tanah Dangkal Ø4" pada tanah biasa 49,956.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 43,440.00
Pekerja L.01 OH 0.480 80,000.00 38,400.00
Juru Bor L.14 OH 0.160 - -
Mandor L.04 OH 0.048 105,000.00 5,040.00
B BAHAN -
C PERALATAN -
Stang bor , batang bor Ø1,25" Hari 0.160 -
Mata Bor 4" Hari 0.160 -
D Jumlah A + B + C 43,440.00
E Overhead & Profit 15% 6,516.00
F Harga Satuan Pekerjaan (D+E) 49,956.00
1.3.1.1.3.b.(a) Pengeboran Sumur Air Tanah Dangkal Ø4" pada tanah Keras / Cadas 249,780.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 217,200.00
Pekerja L.01 OH 2.400 80,000.00 192,000.00
Juru Bor L.14 OH 0.800 - -
Mandor L.04 OH 0.240 105,000.00 25,200.00
B BAHAN -
C PERALATAN -
Stang bor , batang bor Ø1,25" Hari 0.800 -
Mata Bor 4" Hari 0.800 -
D Jumlah A + B + C 217,200.00
E Overhead & Profit 15% 32,580.00
F Harga Satuan Pekerjaan (D+E) 249,780.00
1.3.1.1.3.d.(a) Pengeboran Sumur Air Tanah Dangkal Ø4" pada tanah batuan keras 999,120.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 868,800.00
Pekerja L.01 OH 9.600 80,000.00 768,000.00
Juru Bor L.14 OH 3.200 - -
Mandor L.04 OH 0.960 105,000.00 100,800.00
B BAHAN -
C PERALATAN -
CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
1.3.1.1.4.a.(a) Pengeboran Sumur Air Tanah Dangkal Ø6" pada tanah biasa 74,934.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 65,160.00
Pekerja L.01 OH 0.720 80,000.00 57,600.00
Juru Bor L.14 OH 0.240 - -
Mandor L.04 OH 0.072 105,000.00 7,560.00
B BAHAN -
C PERALATAN -
Stang bor , batang bor Ø1,25" Hari 0.240 -
Mata Bor 6" Hari 0.240 -
D Jumlah A + B + C 65,160.00
E Overhead & Profit 15% 9,774.00
F Harga Satuan Pekerjaan (D+E) 74,934.00
1.3.1.1.4.b.(a) Pengeboran Sumur Air Tanah Dangkal Ø6" pada tanah keras / cadas 187,335.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 162,900.00
Pekerja L.01 OH 1.800 80,000.00 144,000.00
Juru Bor L.14 OH 0.600 - -
Mandor L.04 OH 0.180 105,000.00 18,900.00
B BAHAN -
C PERALATAN -
Stang bor , batang bor Ø1,25" Hari 0.600 -
Mata Bor 6" Hari 0.600 -
D Jumlah A + B + C 162,900.00
E Overhead & Profit 15% 24,435.00
F Harga Satuan Pekerjaan (D+E) 187,335.00
1.3.1.1.4.c.(a) Pengeboran Sumur Air Tanah Dangkal Ø6" pada tanah batuan lunak 299,736.00
CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
1.3.1.1.4.d.(a) Pengeboran Sumur Air Tanah Dangkal Ø6" pada tanah batuan keras 374,670.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 325,800.00
Pekerja L.01 OH 3.600 80,000.00 288,000.00
Juru Bor L.14 OH 1.200 - -
Mandor L.04 OH 0.360 105,000.00 37,800.00
B BAHAN -
C PERALATAN -
Stang bor , batang bor Ø1,25" Hari 1.200 -
Mata Bor 6" Hari 1.200 -
D Jumlah A + B + C 325,800.00
E Overhead & Profit 15% 48,870.00
F Harga Satuan Pekerjaan (D+E) 374,670.00
CK Boyolali
HARGA
JUMLAH
SNI URAIAN PEKERJAAN KODE SAT. KOEF BAHAN/UPAH
Rp Rp
1.4.1.b.(a) Pengadaan dan Pemasangan 1 set Pompa Jet Pump dan Perpipaan 23,477.25
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA 20,415.00
Pekerja L.01 OH 0.225 80,000.00 18,000.00
Juru Bor L.14 OH 0.075 - -
Mandor L.04 OH 0.023 105,000.00 2,415.00
B BAHAN -
Pipa GI Medium Class Ø1" btg 7.000 -
Jet Pump 500 watt hari 1.000 -
Aksesoris ls 1.000 -
C PERALATAN -
Stang bor Ø1,25" + reducer Hari 1.000 -
D Jumlah A + B + C 20,415.00
E Overhead & Profit 15% 3,062.25
F Harga Satuan Pekerjaan (D+E) 23,477.25
CK Boyolali
HARGA JUMLAH
SNI #REF! KODE SAT. KOEF BAHAN/UPAH
Rp Rp
122
HARGA BAHAN/UPAH JUMLAH
SNI #REF! KODE SAT. KOEF
Rp Rp
2.1.3.(a) HARGA SATUAN PASANGAN BATA MERAH
2.1.3.1.b.(c) Pemasangan 1 m2 Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 bata Camp. 1SP: 2PP 297,487.18
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 71,250.00
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
B Bahan 187,434.50
Bata Merah Buah 140.000 750.00 105,000.00
Portland Semen (PC) Kg 43.500 1,475.00 64,162.50
Pasir Pasang (PP) m3 0.080 228,400.00 18,272.00
C PERALATAN
D Jumlah A + B + C 258,684.50
E Overhead & Profit 15% 38,802.68
F Harga Satuan Pekerjaan (D+E) 297,487.18
Overhead & Profit
2.1.3.1.c.(a) Pasangan Bata Merah 1m3 Pondasi Mortar tipe M, fc' = 17,2 Mpa (setara 1 PC : 2 PP) dengan molen, untuk beda tinggi > 0 s. 949,047.47
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 115,175.00
Pekerja L.01 OH 0.850 80,000.00 68,000.00
Tukang Batu L.02 OH 0.425 90,000.00 38,250.00
Mandor L.04 OH 0.085 105,000.00 8,925.00
B Bahan 708,497.00
Bata Merah Buah 500.000 750.00 375,000.00
Portland Semen (PC) Kg 175.000 1,475.00 258,125.00
Pasir Pasang (PP) m3 0.330 228,400.00 75,372.00
C PERALATAN 1,586.67
Molen Kapasitas 0,3 m3 hari 0.0238 66,666.67 1,586.67
D Jumlah A + B + C 825,258.67
E Overhead & Profit 15% 123,788.80
F Harga Satuan Pekerjaan (D+E) 949,047.47
Overhead & Profit
2.1.3.2.b.(c) Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP 282,481.00
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 71,250.00
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
B Bahan 174,385.65
Bata Merah Buah 140.000 750.00 105,000.00
Portland Semen (PC) Kg 32.950 1,475.00 48,601.25
Pasir Pasang (PP) m3 0.091 228,400.00 20,784.40
C PERALATAN
D Jumlah A + B + C 245,635.65
E Overhead & Profit 15% 36,845.35
F Harga Satuan Pekerjaan (D+E) 282,481.00
Overhead & Profit
Pemasangan Bata Merah 1 m3 Pondasi dengan Mortar tipe S, fc' = 12,5 Mpa (setara 1 PC : 3 PP) dengan molen, untuk beda
2.1.3.2.c.(a) tinggi > 0 s.d. 1 m' 881,361.92
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 115,175.00
Pekerja L.01 OH 0.850 80,000.00 68,000.00
Tukang Batu L.02 OH 0.425 90,000.00 38,250.00
Mandor L.04 OH 0.085 105,000.00 8,925.00
B Bahan 649,640.00
Bata Merah Buah 500.000 750.00 375,000.00
Portland Semen (PC) Kg 132.000 1,475.00 194,700.00
Pasir Pasang (PP) m3 0.350 228,400.00 79,940.00
C PERALATAN 1,586.67
Molen Kapasitas 0,3 m3 hari 0.0238 66,666.67 1,586.67
D Jumlah A + B + C 766,401.67
E Overhead & Profit 15% 114,960.25
F Harga Satuan Pekerjaan (D+E) 881,361.92
2.1.3.3.b.(c) Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP 272,150.32
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
123
A Tenaga 71,250.00
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
B Bahan 165,402.45
Bata Merah Buah 140.000 750.00 105,000.00
Portland Semen (PC) Kg 26.550 1,475.00 39,161.25
Pasir Pasang (PP) m3 0.093 228,400.00 21,241.20
C PERALATAN
D Jumlah A + B + C 236,652.45
E Overhead & Profit 15% 35,497.87
F Harga Satuan Pekerjaan (D+E) 272,150.32
Overhead & Profit
2.1.3.3.c.(a) Mortar tipe N, fc' = 5,2 Mpa (setara 1 PC : 4 PP) dengan molen, untuk beda tinggi > 0 s.d. 1 m' 843,360.74
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 115,175.00
Pekerja L.01 OH 0.850 80,000.00 68,000.00
Tukang Batu L.02 OH 0.425 90,000.00 38,250.00
Mandor L.04 OH 0.085 105,000.00 8,925.00
B Bahan 616,595.50
Bata Merah Buah 500.000 750.00 375,000.00
Portland Semen (PC) Kg 106.500 1,475.00 157,087.50
Pasir Pasang (PP) m3 0.370 228,400.00 84,508.00
C PERALATAN 1,586.67
Molen Kapasitas 0,3 m3 hari 0.0238 66,666.67 1,586.67
D Jumlah A + B + C 733,357.17
E Overhead & Profit 15% 110,003.58
F Harga Satuan Pekerjaan (D+E) 843,360.74
2.1.3.3.b.(c) Pemasangan 1 m2 Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP 267,135.57
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 71,250.00
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang Batu L.02 OH 0.200 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 105,000.00 3,150.00
B Bahan 161,041.80
Bata Merah Buah 140.000 750.00 105,000.00
Portland Semen (PC) Kg 22.200 1,475.00 32,745.00
Pasir Pasang (PP) m3 0.102 228,400.00 23,296.80
C PERALATAN
D Jumlah A + B + C 232,291.80
E Overhead & Profit 15% 34,843.77
F Harga Satuan Pekerjaan (D+E) 267,135.57
Overhead & Profit
Pemasangan Bata Merah 1 m3 dengan Mortar tipe O, fc' = 2,4 Mpa (setara 1 PC : 5 PP) dengan molen, untuk beda tinggi > 0
2.1.3.4.b.(a) 824,182.77
s.d. 1 m'
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 115,175.00
Pekerja L.01 OH 0.850 80,000.00 68,000.00
Tukang Batu L.02 OH 0.425 90,000.00 38,250.00
Mandor L.04 OH 0.085 105,000.00 8,925.00
B Bahan 599,919.00
Bata Merah Buah 500.000 750.00 375,000.00
Portland Semen (PC) Kg 89.000 1,475.00 131,275.00
Pasir Pasang (PP) m3 0.410 228,400.00 93,644.00
C PERALATAN 1,586.67
Molen Kapasitas 0,3 m3 hari 0.0238 66,666.67 1,586.67
D Jumlah A + B + C 716,680.67
E Overhead & Profit 15% 107,502.10
F Harga Satuan Pekerjaan (D+E) 824,182.77
2.1.3.5.b.(a) Pemasangan bata merah 1 m3 dengan Mortar campuran 1 PC : 6 PP dengan molen, untuk beda tinggi > 0 s.d. 1 m' 821,448.07
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 115,175.00
Pekerja L.01 OH 0.850 80,000.00 68,000.00
Tukang Batu L.02 OH 0.425 90,000.00 38,250.00
Mandor L.04 OH 0.085 105,000.00 8,925.00
B Bahan 597,541.00
Bata Merah Buah 500.000 750.00 375,000.00
Portland Semen (PC) Kg 75.000 1,475.00 110,625.00
Pasir Pasang (PP) m3 0.490 228,400.00 111,916.00
C PERALATAN 1,586.67
124
Molen Kapasitas 0,3 m3 hari 0.0238 66,666.67 1,586.67
D Jumlah A + B + C 714,302.67
E Overhead & Profit 15% 107,145.40
F Harga Satuan Pekerjaan (D+E) 821,448.07
125
HARGA
BAHAN/UPAH JUMLAH
SNI #REF! KODE SAT. KOEF
Rp Rp
3.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM
3.1.1.(c) Pengerjaan 1 kg Pekerjaan Perakitan Baja Profil 1,087,666.10
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 17,630.00
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang Besi L.02 OH 0.100 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.001 105,000.00 105.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan
C PERALATAN 928,166.61
sewa alat crane jam 0.800 1,160,208.27 928,166.61
D Jumlah A + B + C 945,796.61
E Overhead & Profit 15% 141,869.49
F Harga Satuan Pekerjaan (D+E) 1,087,666.10
3.1.2.(c) Pembuatan 1 m2 Pintu Besi Plat Baja tebal 2 mm rangkap, rangka baja Siku 1,298,407.50
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 194,985.00
Pekerja L.01 OH 1.050 80,000.00 84,000.00
Tukang Besi L.02 OH 1.050 90,000.00 94,500.00
Kepala Tukang L.03 OH 0.105 105,000.00 11,025.00
Mandor L.04 OH 0.052 105,000.00 5,460.00
B Bahan 934,065.00
Besi Siku L.30.30.3 Kg 15.000 19,500.00 292,500.00
Besi Plat Baja Kg 32.800 19,500.00 639,600.00
Kawat Las Kg 0.050 39,300.00 1,965.00
C PERALATAN
D Jumlah A + B + C 1,129,050.00
E Overhead & Profit 15% 169,357.50
F Harga Satuan Pekerjaan (D+E) 1,298,407.50
126
HARGA
No. SNI KODE KOEF SAT. #VALUE! BAHAN/UPAH
Rp
HARGA SATUAN PEKERJAAN PINTU DAN JENDELA ALUMUNIUM
HITUNG PJ1 1.000 Unit Pemasangan Pintu & Jendela Kaca Tempered 12 mm ( PU1 ) 24,348,569.24
A TENAGA 780,800.00
L.01 4.000 OH Pekerja 80,000.00 320,000.00
L.02 4.000 OH Tukang Besi 90,000.00 360,000.00
L.03 0.800 OH Kepala Tukang 105,000.00 84,000.00
L.04 0.160 OH Mandor 105,000.00 16,800.00
B BAHAN 20,391,868.90
3.969 m2 Pintu Kaca Tempered 12 mm 1,039,500.00 4,125,775.50
16.433 m2 Jendela Kaca Bening 12 mm 606,300.00 9,963,024.75
2.000 set Floor Hinge Dekson FH 84 SSS 918,700.00 1,837,400.00
2.000 Bh Patch Fitting Dekson PT 20 PSS 834,700.00 1,669,400.00
2.000 set Pull Handle 354,900.00 709,800.00
25.260 Tube Sealant 33,600.00 848,736.00
0.300 Ls Finishing Kaca Tempered 60% ( Total Harga Kaca ) 4,125,775.50 1,237,732.65
C PERALATAN
D Jumlah A + B + C 21,172,668.90
E Overhead & Profit 15% 3,175,900.34
F Harga Satuan Pekerjaan (D+E) 24,348,569.24
HITUNG P1 1.000 Unit Pemasangan Kusen dan Pintu Kaca Rangka Alumunium ( P1 ) 2,553,492.61
A TENAGA 277,517.19
L.01 0.513 OH Pekerja 80,000.00 41,042.00
L.02 2.065 OH Tukang Besi 90,000.00 185,861.25
L.03 0.338 OH Kepala Tukang 105,000.00 35,492.63
L.04 0.144 OH Mandor 105,000.00 15,121.31
B BAHAN 1,942,911.17
5.261 m' Profil open back 60,100.00 316,156.05
2.158 m' Profil tiang engsel (belakang) 102,700.00 221,600.93
2.158 m' Profil tiang swing(depan) 96,300.00 207,791.33
1.701 m' Profil ambang atas + tutup 77,300.00 131,487.30
0.851 m' Profil ambang bawah + tutup 114,800.00 97,637.40
5.261 m' Profil stoper pintu 22,100.00 116,257.05
5.261 m' Karet tatapan 3,400.00 17,885.70
1.357 m2 Kaca Bening 5 mm 157,500.00 213,664.50
1.000 set Handle Pintu 420,000.00 420,000.00
3.000 Bh Engsel Pintu 4" 54,600.00 163,800.00
10.000 buah Skrup Fixer 475.00 4,750.00
0.789 Tube Sealant Kusen + kaca 33,600.00 26,512.92
0.440 m' Profil Spigot 12,200.00 5,368.00
2.100 m' Bulu Moher 4,000.00 8,400.00
C PERALATAN
D Jumlah A + B + C 2,220,428.36
E Overhead & Profit 15% 333,064.25
F Harga Satuan Pekerjaan (D+E) 2,553,492.61
HITUNG J1 1.000 Unit Pemasangan Kusen dan Jendela Kaca Rangka Alumunium ( J1 ) 1,464,732.99
A TENAGA 237,233.97
L.01 0.663 OH Pekerja 80,000.00 53,075.44
L.02 1.663 OH Tukang Besi 90,000.00 149,709.87
L.03 0.295 OH Kepala Tukang 105,000.00 30,985.54
L.04 0.033 OH Mandor 105,000.00 3,463.12
B BAHAN 1,036,446.89
3.801 m' Profil open back 60,100.00 228,440.10
3.612 m' Rangka casement 3 profil 53,600.00 193,603.20
3.612 m' Karet tatapan 3,400.00 12,280.80
0.515 m2 Kaca Bening 5 mm 157,500.00 81,033.75
2.000 Set Cesement 12" 229,900.00 459,800.00
1.000 Bh Rambuncis 31,500.00 31,500.00
8.000 buah Skrup Fixer 475.00 3,800.00
0.570 Tube Sealant Kusen + Kaca 33,600.00 19,157.04
0.560 m' Profil Spigot 12,200.00 6,832.00
C PERALATAN
D Jumlah A + B + C 1,273,680.86
E Overhead & Profit 15% 191,052.13
F Harga Satuan Pekerjaan (D+E) 1,464,732.99
CK Boyolali
HITUNG J2 1.000 Unit Pemasangan Kusen dan Jendela Kaca Mati Rangka Alumunium ( J2) 636,320.83
A TENAGA 82,751.40
L.01 0.453 OH Pekerja 80,000.00 36,264.48
L.02 0.453 OH Tukang Besi 90,000.00 40,797.54
L.03 0.017 OH Kepala Tukang 105,000.00 1,831.73
L.04 0.037 OH Mandor 105,000.00 3,857.65
B BAHAN 470,571.06
3.990 m' Profil M 70,300.00 280,497.00
1.281 m' Profil tutup M 34,000.00 43,554.00
0.747 m2 Kaca Bening 5 mm 157,500.00 117,730.46
8.000 buah Skrup Fixer 475.00 3,800.00
0.599 Tube Sealant Kusen + Kaca 33,600.00 20,109.60
0.400 m' Profil Spigot 12,200.00 4,880.00
C PERALATAN
D Jumlah A + B + C 553,322.46
E Overhead & Profit 15% 82,998.37
F Harga Satuan Pekerjaan (D+E) 636,320.83
CK Boyolali
HARGA JUMLAH
No. SNI KODE KOEF SAT. #REF! BAHAN/UPAH
Rp Rp
HITUNG HARGA SATUAN PEKERJAAN PARTISI DAN FURNITURE
HITUNG PT 1.000 M2 Pemasangan Dinding Partisi Rangkap Gypsumboard 9mm Rangka Metal Stud 159,092.84
A TENAGA 50,600.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.200 OH Tukang Kayu 90,000.00 18,000.00
L.03 0.060 OH Kepala Tukang 105,000.00 6,300.00
L.04 0.060 OH Mandor 105,000.00 6,300.00
B BAHAN 87,741.60
0.718 Lbr Gypsumboard 9mm 78,700.00 56,506.60
2.300 m Metal Stud MS.76 10,300.00 23,690.00
20.000 Pcs Sekrup Gypsum 225.00 4,500.00
0.400 Kg Cornice Adhesive 4,200.00 1,680.00
1.300 m' Textile Tape 1,050.00 1,365.00
C PERALATAN
D Jumlah A + B + C 138,341.60
E Overhead & Profit 15% 20,751.24
F Harga Satuan Pekerjaan (D+E) 159,092.84
129
HARGA
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH JUMLAH
Rp Rp
CK Boyolali
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. #VALUE!
Rp Rp
HARGA SATUAN PEKERJAAN AKSESORIES
HITUNG AS1 1.000 m' Pemasangan Handrail Tangga Bahan Stainless Steel 858,375.47
A Tenaga 64,126.83
L.01 0.500 OH Pekerja 80,000.00 40,000.00
L.02 0.250 OH Tukang Besi 90,000.00 22,500.00
L.03 0.010 OH Kepala Tukang 105,000.00 1,050.00
L.04 0.005 OH Mandor 105,000.00 576.83
B Bahan 505,397.50
0.350 btg Pipa Stainless Steel 2 inch (Arah Memanjang) 454,200.00 158,970.00
0.263 btg Pipa Stainless Steel 2 inch (Tiang) 454,200.00 119,227.50
1.000 btg Pipa Stainless Steel 3/4 inch (Ornamen) 227,200.00 227,200.00
C PERALATAN 176,889.13
0.350 Peralatan 35% dari bahan 505,397.50 176,889.13
D Jumlah A + B + C 746,413.45
E Overhead & Profit 15% 111,962.02
F Harga Satuan Pekerjaan (D+E) 858,375.47
HITUNG AS3 1.000 m' Pemasangan Tiang Bahan Stainless Steel 4" 298,186.38
A Tenaga 36,710.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.125 OH Tukang Besi 90,000.00 11,250.00
L.03 0.050 OH Kepala Tukang 105,000.00 5,250.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 193,550.00
0.175 btg Pipa Stainless Steel 4" 1,106,000.00 193,550.00
C PERALATAN 29,032.50
0.150 Peralatan 15% dari bahan 193,550.00 29,032.50
D Jumlah A + B + C 259,292.50
E Overhead & Profit 15% 38,893.88
F Harga Satuan Pekerjaan (D+E) 298,186.38
HITUNG AS4 1.000 m' Pemasangan Tiang Bahan Stainless Steel 3" 233,499.59
A Tenaga 36,710.00
L.01 0.250 OH Pekerja 80,000.00 20,000.00
L.02 0.125 OH Tukang Besi 90,000.00 11,250.00
L.03 0.050 OH Kepala Tukang 105,000.00 5,250.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 144,637.50
0.175 btg Pipa Stainless Steel 3" 826,500.00 144,637.50
C PERALATAN 21,695.63
0.150 Peralatan 15% dari bahan 144,637.50 21,695.63
D Jumlah A + B + C 203,043.13
E Overhead & Profit 15% 30,456.47
F Harga Satuan Pekerjaan (D+E) 233,499.59
131
HARGA
JUMLAH
No. SNI KODE KOEF SAT. #VALUE! BAHAN/UPAH
Rp Rp
A.4.4.3 HARGA SATUAN PEKERJAAN PAVING
A.4.4.3.63 1.000 m2 Pemasangan Paving Holland Natural Uk. 20 x 10,5 x 8 cm K-250 Ex. MASTER BETON #DIV/0!
A Tenaga #DIV/0!
L.01 #DIV/0! OH Pekerja 80,000.00 #DIV/0!
L.02 #DIV/0! OH Tukang Batu 90,000.00 #DIV/0!
L.03 #DIV/0! OH Kepala Tukang 105,000.00 #DIV/0!
L.04 #DIV/0! OH Mandor 105,000.00 #DIV/0!
B Bahan 99,225.00
1.050 m2 Paving holland 20 x 10,5 x 8 cm 94,500.00 99,225.00
- m3 Pasir Urug Pengisi Nat 175,000.00 -
C PERALATAN 1,488.38
0.015 m2 Sewa Peralatan 1.5% dari bahan 99,225.00 1,488.38
D Jumlah A + B + C #DIV/0!
E Overhead & Profit 15% #DIV/0!
F Harga Satuan Pekerjaan (D+E) #DIV/0!
HITUNG PV1 1.000 m2 Pemasangan Paving Holland Natural Uk. 20 x 10,5 x 8 cm K-250 Ex. MASTER BETON 144,654.08
A Tenaga 24,433.33
L.01 0.167 OH Pekerja 80,000.00 13,333.33
L.02 0.100 OH Tukang Batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 105,000.00 1,050.00
L.04 0.010 OH Mandor 105,000.00 1,050.00
132
B Bahan 99,855.00
1.050 m2 Paving holland 20 x 10,5 x 8 cm 94,500.00 99,225.00
0.004 m3 Pasir Urug Pengisi Nat 175,000.00 630.00
C PERALATAN 1,497.83
0.015 m2 Sewa Peralatan 1.5% dari bahan 99,855.00 1,497.83
D Jumlah A + B + C 125,786.16
E Overhead & Profit 15% 18,867.92
F Harga Satuan Pekerjaan (D+E) 144,654.08
HITUNG PV2 1.000 m2 Pemasangan Paving Holland Natural Uk. 20 x 10 x 6 cm K-250 Ex. MASTER BETON 118,916.22
A Tenaga 24,433.33
L.01 0.167 OH Pekerja 80,000.00 13,333.33
L.02 0.100 OH Tukang Batu 90,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 105,000.00 1,050.00
L.04 0.010 OH Mandor 105,000.00 1,050.00
B Bahan 77,805.00
1.050 m2 Paving holland 20 x 10,5 x 6 cm 73,500.00 77,175.00
0.004 m3 Pasir Urug 175,000.00 630.00
C PERALATAN 1,167.08
0.015 m2 Sewa Peralatan 1.5% dari bahan 77,805.00 1,167.08
D Jumlah A + B + C 103,405.41
E Overhead & Profit 15% 15,510.81
F Harga Satuan Pekerjaan (D+E) 118,916.22
HITUNG PV2 1.000 m1 Pemasangan Kerb Standard K-250 Uk. 10/12 x 35 x 50 cm Ex. MASTER BETON 107,903.48
A Tenaga 9,033.33
L.01 0.067 OH Pekerja 80,000.00 5,333.33
L.02 0.033 OH Tukang Batu 90,000.00 3,000.00
L.03 0.003 OH Kepala Tukang 105,000.00 350.00
L.04 0.003 OH Mandor 105,000.00 350.00
B Bahan 84,795.78
2.000 Buah Kerb Standard Uk. 10/12 x 35 x 50 42,000.00 84,000.00
0.302 Kg Portland Cement 1,475.00 446.04
0.002 m3 Pasir Pasang 228,400.00 349.74
C PERALATAN
D Jumlah A + B + C 93,829.11
E Overhead & Profit 15% 14,074.37
F Harga Satuan Pekerjaan (D+E) 107,903.48
HITUNG PV3 1.000 m1 Pemasangan Kanstein Besar K-300 Uk. 60 x 30 x 20 cm K-300 195,145.35
A Tenaga 9,033.33
L.01 0.067 OH Pekerja 80,000.00 5,333.33
L.02 0.033 OH Tukang Batu 90,000.00 3,000.00
L.03 0.003 OH Kepala Tukang 105,000.00 350.00
L.04 0.003 OH Mandor 105,000.00 350.00
B Bahan 160,658.28
2.625 Buah Kanstein besar K-300 Uk. 60 x 30 x 20 cm 60,900.00 159,862.50
0.302 Kg Portland Cement 1,475.00 446.04
0.002 m3 Pasir Pasang 228,400.00 349.74
C PERALATAN
D Jumlah A + B + C 169,691.61
E Overhead & Profit 15% 25,453.74
F Harga Satuan Pekerjaan (D+E) 195,145.35
133
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. #VALUE!
Rp Rp
HARGA SATUAN PEKERJAAN TAMAN
HITUNG TM1 1.000 m3 Pek. Media Tanam ( Tanah Merah Dan Pupuk ) 232,817.50
A Tenaga 25,050.00
L.01 0.300 OH Pekerja 80,000.00 24,000.00
L.04 0.010 OH Mandor 105,000.00 1,050.00
B Bahan 177,400.00
1.000 m3 Tanah Subur 177,400.00 177,400.00
C PERALATAN -
D Jumlah A + B + C 202,450.00
E Overhead & Profit 15% 30,367.50
F Harga Satuan Pekerjaan (D+E) 232,817.50
HITUNG TM2 1.000 m2 Pek. Tanaman Kacang Hias /m2 isi 15 polybag 56,902.00
A Tenaga 1,810.00
L.01 0.020 OH Pekerja 80,000.00 1,600.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 47,670.00
15.000 polybag Tanaman Kacang hias 3,150.00 47,250.00
0.040 Kg Pupuk kandang 10,500.00 420.00
C PERALATAN
D Jumlah A + B + C 49,480.00
E Overhead & Profit 15% 7,422.00
F Harga Satuan Pekerjaan (D+E) 56,902.00
HITUNG TM3 1.000 m1 Pek. Tanaman Pangkas ( Hijau & Merah ) 74,842.00
A Tenaga 1,810.00
L.01 0.020 OH Pekerja 80,000.00 1,600.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 63,270.00
6.000 polybag Tanaman Pangkas ( Hijau ) 5,250.00 31,500.00
1.000 polybag Tanaman Pangkas ( Kuning ) 3,150.00 3,150.00
6.000 polybag Tanaman Pangkas ( Merah ) 4,700.00 28,200.00
0.040 Kg Pupuk kandang 10,500.00 420.00
C PERALATAN
D Jumlah A + B + C 65,080.00
E Overhead & Profit 15% 9,762.00
F Harga Satuan Pekerjaan (D+E) 74,842.00
HITUNG TM4 1.000 m2 Pek. Tanam Pohon Ketapang Kencana Tinggi 1.00 m 123,314.50
A Tenaga 1,810.00
L.01 0.020 OH Pekerja 80,000.00 1,600.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 105,420.00
1.000 bh Pohon Ketapang Kencana 105,000.00 105,000.00
0.040 Kg Pupuk kandang 10,500.00 420.00
C PERALATAN
D Jumlah A + B + C 107,230.00
E Overhead & Profit 15% 16,084.50
F Harga Satuan Pekerjaan (D+E) 123,314.50
HITUNG TM5 1.000 bh Pek. Tanam Pohon Pucuk Merah Tinggi min 60 cm 92,149.50
A Tenaga 1,810.00
L.01 0.020 OH Pekerja 80,000.00 1,600.00
L.04 0.002 OH Mandor 105,000.00 210.00
B Bahan 78,320.00
1.000 bh Tanaman Pucuk Merah Tinggi Min 60 cm 77,900.00 77,900.00
0.040 Kg Pupuk kandang 10,500.00 420.00
C PERALATAN
D Jumlah A + B + C 80,130.00
E Overhead & Profit 15% 12,019.50
134
F Harga Satuan Pekerjaan (D+E) 92,149.50
135
HARGA JUMLAH
BAHAN/UPAH
SNI #REF! KODE SAT. KOEF
Rp Rp
136
Tukang Pipa L.02 OH 0.095 88,000.00 8,360.00
Mandor L.04 OH 0.019 105,000.00 1,995.00
B Bahan 453,150.00
Pipa PVC Ø 200 mm m' 1.000 453,150.00 453,150.00
C PERALATAN 2,640.00
Sewa Tripot / Tackel hari 0.024 110,000.00 2,640.00
D Jumlah A + B + C 481,265.00
E Overhead & Profit 72,189.75
F Harga Satuan Pekerjaan (D+E) 553,454.75
137
4.1.19.(c) Pemasangan 1m' Pipa HDPE Ø 125 mm 236,024.85
Harga Satuan Jumlah
Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga 6,149.00
Pekerja L.01 OH 0.045 80,000.00 3,600.00
Tukang Pipa L.02 OH 0.023 88,000.00 2,024.00
Mandor L.04 OH 0.005 105,000.00 525.00
B Bahan 197,000.00
Pipa HDPE Ø 125 mm m' 1.000 197,000.00 197,000.00
C PERALATAN 2,090.00
Sewa Tripot / Tackel hari 0.019 110,000.00 2,090.00
D Jumlah A + B + C 205,239.00
E Overhead & Profit 30,785.85
F Harga Satuan Pekerjaan (D+E) 236,024.85
138
Sewa Tripot / Tackel hari 0.065 110,000.00 7,150.00
D Jumlah A + B + C 1,276,015.00
E Overhead & Profit 191,402.25
F Harga Satuan Pekerjaan (D+E) 1,467,417.25
139
Tukang Pipa L.02 OH 0.446 88,000.00 39,248.00
Mandor L.04 OH 0.089 105,000.00 9,345.00
B Bahan 11,524,200.00
Pipa HDPE Ø 800 mm m' 1.000 11,524,200.00 11,524,200.00
C PERALATAN 63,030.00
Sewa Tripot / Tackel hari 0.573 110,000.00 63,030.00
D Jumlah A + B + C 11,707,263.00
E Overhead & Profit 1,756,089.45
F Harga Satuan Pekerjaan (D+E) 13,463,352.45
140
HARGA SATUAN JUMLAH HARGA
URAIAN KODE SAT KOEF
Rp Rp
4.2 HARGA SATUAN PEKERJAAN PEMOTONGAN PIPA
4.2.1.(c) Pemotongan 1 Buah Pipa PVC Ø 63 mm 1,007.40
141
4.2.5.(c) Pemotongan 1 Buah Pipa PVC Ø 200 mm 14,078.88
142
A Tenaga 56,490.00
Pekerja L.01 OH 0.420 80,000.00 33,600.00
Tukang pipa L.02 OH 0.210 88,000.00 18,480.00
Mandor L.04 OH 0.042 105,000.00 4,410.00
B Bahan
C PERALATAN 8,910.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.054 165,000.00 8,910.00
D Jumlah A + B + C 65,400.00
E Overhead & Profit 15% 9,810.00
F Harga Satuan Pekerjaan (D+E) 75,210.00
143
B Bahan
C PERALATAN 27,720.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.168 165,000.00 27,720.00
D Jumlah A + B + C 181,218.00
E Overhead & Profit 15% 27,182.70
F Harga Satuan Pekerjaan (D+E) 208,400.70
144
D Jumlah A + B + C 3,921.00
E Overhead & Profit 15% 588.15
F Harga Satuan Pekerjaan (D+E) 4,509.15
145
D Jumlah A + B + C 23,729.00
E Overhead & Profit 15% 3,559.35
F Harga Satuan Pekerjaan (D+E) 27,288.35
146
D Jumlah A + B + C 78,957.00
E Overhead & Profit 15% 11,843.55
F Harga Satuan Pekerjaan (D+E) 90,800.55
147
D Jumlah A + B + C 243,921.00
E Overhead & Profit 15% 36,588.15
F Harga Satuan Pekerjaan (D+E) 280,509.15
148
E Overhead & Profit 15% 391.50
F Harga Satuan Pekerjaan (D+E) 3,001.50
149
HARGA SATUAN JUMLAH HARGA
URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 63,791.00
Pekerja L.01 OH 0.475 80,000.00 38,000.00
Tukang pipa L.02 OH 0.237 88,000.00 20,856.00
Mandor L.04 OH 0.047 105,000.00 4,935.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 63,791.00
E Overhead & Profit 15% 9,568.65
F Harga Satuan Pekerjaan (D+E) 73,359.65
150
Pekerja L.01 OH 0.941 80,000.00 75,280.00
Tukang pipa L.02 OH 0.471 88,000.00 41,448.00
Mandor L.04 OH 0.094 105,000.00 9,870.00
B Bahan
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 126,598.00
E Overhead & Profit 15% 18,989.70
F Harga Satuan Pekerjaan (D+E) 145,587.70
151
C PERALATAN -
Peralatan potong pipa T2 /mekanik / cilinder saw hari - 165,000.00 -
D Jumlah A + B + C 265,461.00
E Overhead & Profit 15% 39,819.15
F Harga Satuan Pekerjaan (D+E) 305,280.15
152
F Harga Satuan Pekerjaan (D+E) 15,756.15
153
HARGA SATUAN JUMLAH HARGA
URAIAN KODE SAT KOEF
Rp Rp
A Tenaga 101,694.00
Pekerja L.01 OH 0.941 80,000.00 75,280.00
Tukang pipa L.02 OH 0.188 88,000.00 16,544.00
Mandor L.04 OH 0.094 105,000.00 9,870.00
B Bahan
C PERALATAN 26,070.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.158 165,000.00 26,070.00
D Jumlah A + B + C 127,764.00
E Overhead & Profit 15% 19,164.60
F Harga Satuan Pekerjaan (D+E) 146,928.60
154
Tukang pipa L.02 OH 0.520 88,000.00 45,760.00
Mandor L.04 OH 0.260 105,000.00 27,300.00
B Bahan
C PERALATAN 51,150.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.310 165,000.00 51,150.00
D Jumlah A + B + C 332,050.00
E Overhead & Profit 15% 49,807.50
F Harga Satuan Pekerjaan (D+E) 381,857.50
155
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.576 165,000.00 95,040.00
D Jumlah A + B + C 689,750.00
E Overhead & Profit 15% 103,462.50
F Harga Satuan Pekerjaan (D+E) 793,212.50
156
4.2.68.(c) Pemotongan 1 Buah Pipa Baja Karbon Ø 200 mm 70,587.00
157
Rp Rp
A Tenaga 151,260.00
Pekerja L.01 OH 1.399 80,000.00 111,920.00
Tukang pipa L.02 OH 0.280 88,000.00 24,640.00
Mandor L.04 OH 0.140 105,000.00 14,700.00
B Bahan
C PERALATAN 17,655.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.107 165,000.00 17,655.00
D Jumlah A + B + C 168,915.00
E Overhead & Profit 15% 25,337.25
F Harga Satuan Pekerjaan (D+E) 194,252.25
158
Mandor L.04 OH 0.297 105,000.00 31,185.00
B Bahan
C PERALATAN 30,195.00
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.183 165,000.00 30,195.00
D Jumlah A + B + C 351,332.00
E Overhead & Profit 15% 52,699.80
F Harga Satuan Pekerjaan (D+E) 404,031.80
159
HARGA SATUAN JUMLAH HARGA
URAIAN KODE SAT KOEF
Rp Rp
4.3 HARGA SATUAN PEKERJAAN PEMASANGAN AKSESORIS PIPA
4.3.1.(c) Pemasangan 1 Buah Valve Ø 150 mm 233,743.25
160
D Jumlah A + B + C 337,750.00
E Overhead & Profit 15% 50,662.50
F Harga Satuan Pekerjaan (D+E) 388,412.50
161
Mobile crane ≤ 3 ton hari 0.300 357,142.86 107,142.86
D Jumlah A + B + C 273,658.00
E Overhead & Profit 15% 41,048.70
F Harga Satuan Pekerjaan (D+E) 314,706.70
162
B Bahan -
Valve Ø 1000 mm Buah 1.000 - -
C PERALATAN 137,500.00
Sewa Tripot/ Tackel hari 1.000 137,500.00 137,500.00
Mobile crane ≤ 3 ton hari 1.000 357,142.86 357,142.86
D Jumlah A + B + C 483,333.00
E Overhead & Profit 15% 72,499.95
F Harga Satuan Pekerjaan (D+E) 555,832.95
163
Pekerja L.01 OH 0.216 80,000.00 17,280.00
Tukang pipa L.02 OH 0.108 88,000.00 9,504.00
Mandor L.04 OH 0.022 105,000.00 2,310.00
B Bahan 812,600.00
Tee Ø 200 mm Buah 1.000 812,600.00 812,600.00
C PERALATAN 3,987.50
Sewa Tripot/ Tackel hari 0.029 137,500.00 3,987.50
D Jumlah A + B + C 845,681.50
E Overhead & Profit 15% 126,852.23
F Harga Satuan Pekerjaan (D+E) 972,533.73
164
Pekerja L.01 OH 0.766 80,000.00 61,280.00
Tukang pipa L.02 OH 0.383 88,000.00 33,704.00
Mandor L.04 OH 0.077 105,000.00 8,085.00
B Bahan -
Tee Ø 450 mm Buah 1.000 - -
C PERALATAN 68,750.00
Sewa Tripot/ Tackel hari 0.500 137,500.00 68,750.00
D Jumlah A + B + C 171,819.00
E Overhead & Profit 15% 25,772.85
F Harga Satuan Pekerjaan (D+E) 197,591.85
165
Rp Rp
A Tenaga 206,634.00
Pekerja L.01 OH 1.536 80,000.00 122,880.00
Tukang pipa L.02 OH 0.768 88,000.00 67,584.00
Mandor L.04 OH 0.154 105,000.00 16,170.00
B Bahan -
Tee Ø 800 mm Buah 1.000 - -
C PERALATAN 35,337.50
Sewa Tripot/ Tackel hari 0.257 137,500.00 35,337.50
Mobile crane ≤ 3 ton hari 0.129 357,142.86 46,071.43
D Jumlah A + B + C 241,971.50
E Overhead & Profit 15% 36,295.73
F Harga Satuan Pekerjaan (D+E) 278,267.23
166
4.3.28.(c) Pemasangan 1 Buah Tee Ø 1200 mm 444,899.35
167
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
4.4 HARGA SATUAN PEKERJAAN PENYAMBUNGAN PIPA BARU KE PIPA LAMA
4.4.1.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 80 mm 1,334,535.40
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 197,219.00
Pekerja L.01 OH 1.466 80,000.00 117,280.00
Tukang pipa L.02 OH 0.733 88,000.00 64,504.00
Mandor L.04 OH 0.147 105,000.00 15,435.00
B Bahan -
Pipa Ø 80 mm Buah - 99,100.00 -
C PERALATAN 963,246.57
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.606 165,000.00 99,990.00
Sewa Genset 1500 watt hari 0.075 268,439.53 20,132.97
Sewa Pompa Submersible 3 m³ / h hari 0.968 772,700.00 747,973.60
Sewa Tripot/ Tackel hari 0.865 110,000.00 95,150.00
D Jumlah A + B + C 1,160,465.57
E Overhead & Profit 15% 174,069.83
F Harga Satuan Pekerjaan (D+E) 1,334,535.40
4.4.2.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 100 mm 1,500,222.71
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 221,429.00
Pekerja L.01 OH 1.646 80,000.00 131,680.00
Tukang pipa L.02 OH 0.823 88,000.00 72,424.00
Mandor L.04 OH 0.165 105,000.00 17,325.00
B Bahan
C PERALATAN 1,083,112.49
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.650 165,000.00 107,250.00
Sewa Genset 1500 watt hari 0.159 268,439.53 42,681.89
Sewa Pompa Submersible 3 m³ / h hari 1.078 772,700.00 832,970.60
Sewa Tripot/ Tackel hari 0.911 110,000.00 100,210.00
D Jumlah A + B + C 1,304,541.49
E Overhead & Profit 15% 195,681.22
F Harga Satuan Pekerjaan (D+E) 1,500,222.71
4.4.3.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 150 mm 1,914,440.98
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 281,954.00
Pekerja L.01 OH 2.096 80,000.00 167,680.00
Tukang pipa L.02 OH 1.048 88,000.00 92,224.00
Mandor L.04 OH 0.210 105,000.00 22,050.00
B Bahan
C PERALATAN 1,382,777.29
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.760 165,000.00 125,400.00
Sewa Genset 1500 watt hari 0.369 268,439.53 99,054.19
Sewa Pompa Submersible 3 m³ / h hari 1.353 772,700.00 1,045,463.10
Sewa Tripot/ Tackel hari 1.026 110,000.00 112,860.00
D Jumlah A + B + C 1,664,731.29
E Overhead & Profit 15% 249,709.69
F Harga Satuan Pekerjaan (D+E) 1,914,440.98
4.4.4.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 200 mm 2,328,659.25
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 342,479.00
Pekerja L.01 OH 2.546 80,000.00 203,680.00
Tukang pipa L.02 OH 1.273 88,000.00 112,024.00
Mandor L.04 OH 0.255 105,000.00 26,775.00
B Bahan
C PERALATAN 1,682,442.09
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.870 165,000.00 143,550.00
Sewa Genset 1500 watt hari 0.579 268,439.53 155,426.49
Sewa Pompa Submersible 3 m³ / h hari 1.628 772,700.00 1,257,955.60
Sewa Tripot/ Tackel hari 1.141 110,000.00 125,510.00
D Jumlah A + B + C 2,024,921.09
E Overhead & Profit 15% 303,738.16
F Harga Satuan Pekerjaan (D+E) 2,328,659.25
168
4.4.5.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 250 mm 2,742,877.53
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 403,004.00
Pekerja L.01 OH 2.996 80,000.00 239,680.00
Tukang pipa L.02 OH 1.498 88,000.00 131,824.00
Mandor L.04 OH 0.300 105,000.00 31,500.00
B Bahan
C PERALATAN 1,982,106.89
Peralatan potong pipa T2 /mekanik / cilinder saw hari 0.980 165,000.00 161,700.00
Sewa Genset 1500 watt hari 0.789 268,439.53 211,798.79
Sewa Pompa Submersible 3 m³ / h hari 1.903 772,700.00 1,470,448.10
Sewa Tripot/ Tackel hari 1.256 110,000.00 138,160.00
D Jumlah A + B + C 2,385,110.89
E Overhead & Profit 15% 357,766.63
F Harga Satuan Pekerjaan (D+E) 2,742,877.53
4.4.6.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 300 mm 3,157,095.80
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 463,529.00
Pekerja L.01 OH 3.446 80,000.00 275,680.00
Tukang pipa L.02 OH 1.723 88,000.00 151,624.00
Mandor L.04 OH 0.345 105,000.00 36,225.00
B Bahan
C PERALATAN 2,281,771.69
Peralatan potong pipa T2 /mekanik / cilinder saw hari 1.090 165,000.00 179,850.00
Sewa Genset 1500 watt hari 0.999 268,439.53 268,171.09
Sewa Pompa Submersible 3 m³ / h hari 2.178 772,700.00 1,682,940.60
Sewa Tripot/ Tackel hari 1.371 110,000.00 150,810.00
D Jumlah A + B + C 2,745,300.69
E Overhead & Profit 15% 411,795.10
F Harga Satuan Pekerjaan (D+E) 3,157,095.80
4.4.7.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 400 mm 3,985,532.34
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 584,579.00
Pekerja L.01 OH 4.346 80,000.00 347,680.00
Tukang pipa L.02 OH 2.173 88,000.00 191,224.00
Mandor L.04 OH 0.435 105,000.00 45,675.00
B Bahan
C PERALATAN 2,881,101.30
Peralatan potong pipa T2 /mekanik / cilinder saw hari 1.310 165,000.00 216,150.00
Sewa Genset 1500 watt hari 1.419 268,439.53 380,915.70
Sewa Pompa Submersible 3 m³ / h hari 2.728 772,700.00 2,107,925.60
Sewa Tripot/ Tackel hari 1.601 110,000.00 176,110.00
D Jumlah A + B + C 3,465,680.30
E Overhead & Profit 15% 519,852.04
F Harga Satuan Pekerjaan (D+E) 3,985,532.34
4.4.8.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 450 mm 4,399,750.62
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 645,104.00
Pekerja L.01 OH 4.796 80,000.00 383,680.00
Tukang pipa L.02 OH 2.398 88,000.00 211,024.00
Mandor L.04 OH 0.480 105,000.00 50,400.00
B Bahan
C PERALATAN 3,180,766.10
Peralatan potong pipa T2 /mekanik / cilinder saw hari 1.420 165,000.00 234,300.00
Sewa Genset 1500 watt hari 1.629 268,439.53 437,288.00
Sewa Pompa Submersible 3 m³ / h hari 3.003 772,700.00 2,320,418.10
Sewa Tripot/ Tackel hari 1.716 110,000.00 188,760.00
D Jumlah A + B + C 3,825,870.10
E Overhead & Profit 15% 573,880.52
F Harga Satuan Pekerjaan (D+E) 4,399,750.62
4.4.9.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 500 mm 4,813,968.89
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
169
A Tenaga 705,629.00
Pekerja L.01 OH 5.246 80,000.00 419,680.00
Tukang pipa L.02 OH 2.623 88,000.00 230,824.00
Mandor L.04 OH 0.525 105,000.00 55,125.00
B Bahan
C PERALATAN 3,480,430.90
Peralatan potong pipa T2 /mekanik / cilinder saw hari 1.530 165,000.00 252,450.00
Sewa Genset 1500 watt hari 1.839 268,439.53 493,660.30
Sewa Pompa Submersible 3 m³ / h hari 3.278 772,700.00 2,532,910.60
Sewa Tripot/ Tackel hari 1.831 110,000.00 201,410.00
D Jumlah A + B + C 4,186,059.90
E Overhead & Profit 15% 627,908.99
F Harga Satuan Pekerjaan (D+E) 4,813,968.89
4.4.10.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 600 mm 5,642,405.43
HARGA
JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 826,679.00
Pekerja L.01 OH 6.146 80,000.00 491,680.00
Tukang pipa L.02 OH 3.073 88,000.00 270,424.00
Mandor L.04 OH 0.615 105,000.00 64,575.00
B Bahan
C PERALATAN 4,079,760.51
Peralatan potong pipa T2 /mekanik / cilinder saw hari 1.750 165,000.00 288,750.00
Sewa Genset 1500 watt hari 2.259 268,439.53 606,404.91
Sewa Pompa Submersible 3 m³ / h hari 3.828 772,700.00 2,957,895.60
Sewa Tripot/ Tackel hari 2.061 110,000.00 226,710.00
D Jumlah A + B + C 4,906,439.51
E Overhead & Profit 15% 735,965.93
F Harga Satuan Pekerjaan (D+E) 5,642,405.43
4.4.11.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 700 mm 6,470,841.98
HARGA JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 947,729.00
Pekerja L.01 OH 7.046 80,000.00 563,680.00
Tukang pipa L.02 OH 3.523 88,000.00 310,024.00
Mandor L.04 OH 0.705 105,000.00 74,025.00
B Bahan
C PERALATAN 4,679,090.11
Peralatan potong pipa T2 /mekanik / cilinder saw hari 1.970 165,000.00 325,050.00
Sewa Genset 1500 watt hari 2.679 268,439.53 719,149.51
Sewa Pompa Submersible 3 m³ / h hari 4.378 772,700.00 3,382,880.60
Sewa Tripot/ Tackel hari 2.291 110,000.00 252,010.00
D Jumlah A + B + C 5,626,819.11
E Overhead & Profit 15% 844,022.87
F Harga Satuan Pekerjaan (D+E) 6,470,841.98
4.4.12.(c) Penyambungan 1 Buah Pipa Baru ke Pipa Yang Ada Ø 800 mm 7,299,278.52
HARGA
JUMLAH
URAIAN KODE SAT KOEF BAHAN/UPAH
Rp Rp
A Tenaga 1,068,779.00
Pekerja L.01 OH 7.946 80,000.00 635,680.00
Tukang pipa L.02 OH 3.973 88,000.00 349,624.00
Mandor L.04 OH 0.795 105,000.00 83,475.00
B Bahan
C PERALATAN 5,278,419.72
Peralatan potong pipa T2 /mekanik / cilinder saw hari 2.190 165,000.00 361,350.00
Sewa Genset 1500 watt hari 3.099 268,439.53 831,894.12
Sewa Pompa Submersible 3 m³ / h hari 4.928 772,700.00 3,807,865.60
Sewa Tripot/ Tackel hari 2.521 110,000.00 277,310.00
D Jumlah A + B + C 6,347,198.72
E Overhead & Profit 15% 952,079.81
F Harga Satuan Pekerjaan (D+E) 7,299,278.52