RINCIAN BAHAN

NAMA PROYEK PENGGANTIAN JENDELA


LOKASI KOTA BANDUNG
TAHUN 2021

NO. URAIAN BAHAN SATUAN HARGA DASAR MERK SPESIFIKASI SUMBER


1 Cat Kayu kg Rp 86,830.05 EMCO Standar IKK BPS 2021
2 Cathment 12 " set Rp 105,000.20 Xolani / Lainnya Window Casement 12 Inch HD FrictSurvey
3 Frame daun jendela m1 Rp 118,000.20 Alexindo Warna silver Survey
4 Handle jendela alumunium set Rp 151,000.00 Weldom Rambuncis Handle Jendela AlumunSurvey
5 Kaca tebal 5 mm m2 Rp 125,000.00 Standar Bening Survey
6 Kayu papan kelas III m3 Rp 2,505,046.82 Kamper Standar IKK BPS 2021
7 Paku biasa kg Rp 31,475.89 Standar 1 3/4 "- (reng kayu) IKK BPS 2021
8 Sealent m1 Rp 50,000.00 Standar Standar Survey
9 Seng plat BJLS 30 lebar 45 m1 Rp 28,762.45 Standar Standar Estimator.id
10 Test SWAB Anti Gen 2x1 Bulan bh Rp 525,000.00 Standar Standar Survey
RINCIAN UPAH

NAMA PROYEK PENGGANTIAN JENDELA


LOKASI KOTA BANDUNG
TAHUN 2021

NO. URAIAN UPAH SATUAN HARGA DASAR MERK SPESIFIKASI SUMBER


1 Kepala Tukang Alumunium OH Rp 130,245.07 Standar Standar Estimator.id
2 Mandor OH Rp 141,098.82 Standar Standar IKK BPS 2021
3 Pekerja OH Rp 108,537.56 Standar Standar IKK BPS 2021
4 Tukang Alumunium OH Rp 119,391.31 Standar Standar Estimator.id
5 Tukang cat OH Rp 124,818.19 Standar Standar IKK BPS 2021
6 Tukang Kayu OH Rp 124,818.19 Standar Kasar IKK BPS 2021
RINCIAN ALAT

NAMA PROYEK PENGGANTIAN JENDELA


LOKASI KOTA BANDUNG
TAHUN 2021

NO. URAIAN ALAT SATUAN HARGA DASAR MERK SPESIFIKASI SUMBER


1 Desinfektan ls Rp 700,000.00 Standar Standar Survey
2 Face Shield bh Rp 50,000.00 Standar Standar Survey
3 Hand Sanitizer liter Rp 90,000.00 Standar Standar Survey
4 Helm Pelindung bh Rp 35,000.00 Standar Standar Survey
5 Kotak P3k obat Luka, Perban DLL ls Rp 700,000.00 Standar Standar Survey
6 Masker Medis psg Rp 100,000.00 Standar Standar Survey
7 Rompi Keselamatan psg Rp 40,000.00 Standar Standar Survey
8 Sarung Tangan psg Rp 20,000.00 Standar Standar Survey
9 Sepatu Keselamatan psg Rp 50,000.00 Standar Standar Survey
10 Sewa Scafolding set Rp 3,500,000.00 Standar Standar Survey
11 Thermogun buah Rp 229,000.00 Standar Standar Survey
RINCIAN HARGA SATUAN

NAMA PROYEK PENGGANTIAN JENDELA


LOKASI KOTA BANDUNG
TAHUN 2021

NO NAMA KATEGORI SATUAN KOEFISIEN HARGA DASAR HARGA SATUAN SUMBER


1 Pekerjaan bongkar jendela alumunium unit Rp 98,226.49 Empiris
A BAHAN
B UPAH
- Kepala Tukang Alumunium OH 0.1000 Rp 130,245.07 Rp 13,024.51
- Mandor OH 0.2000 Rp 141,098.82 Rp 28,219.76
- Pekerja OH 0.2500 Rp 108,537.56 Rp 27,134.39
- Tukang Alumunium OH 0.2500 Rp 119,391.31 Rp 29,847.83
JUMLAH HARGA Rp 98,226.49
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 98,226.49
C ALAT
2 Jendela aluminium Type J2 unit Rp 1,678,253.10 Empiris
A BAHAN
- Cathment 12 " set 2.0000 Rp 105,000.20 Rp 210,000.40
- Frame daun jendela m1 3.6000 Rp 118,000.20 Rp 424,800.72
- Handle jendela alumunium set 2.0000 Rp 151,000.00 Rp 302,000.00
- Kaca tebal 5 mm m2 3.8100 Rp 125,000.00 Rp 476,250.00
- Sealent m1 3.6000 Rp 50,000.00 Rp 180,000.00
JUMLAH HARGA Rp 1,593,051.12
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 1,593,051.12
B UPAH
- Kepala Tukang Alumunium OH 0.2500 Rp 130,245.07 Rp 32,561.27
- Mandor OH 0.2500 Rp 141,098.82 Rp 35,274.71
- Pekerja OH 0.0500 Rp 108,537.56 Rp 5,426.88
- Tukang Alumunium OH 0.1000 Rp 119,391.31 Rp 11,939.13
JUMLAH HARGA Rp 85,201.98
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 85,201.98
C ALAT
3 Jendela aluminium Type J3 unit Rp 1,826,173.85 Empiris
A BAHAN
- Cathment 12 " set 2.0000 Rp 105,000.20 Rp 210,000.40
- Frame daun jendela m1 4.6000 Rp 118,000.20 Rp 542,800.92
- Handle jendela alumunium set 2.0000 Rp 151,000.00 Rp 302,000.00
- Kaca tebal 5 mm m2 3.8100 Rp 125,000.00 Rp 476,250.00
- Sealent m1 4.6000 Rp 50,000.00 Rp 230,000.00
JUMLAH HARGA Rp 1,761,051.32
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 1,761,051.32
B UPAH
- Kepala Tukang Alumunium OH 0.2500 Rp 130,245.07 Rp 32,561.27
- Mandor OH 0.1500 Rp 141,098.82 Rp 21,164.82
- Pekerja OH 0.0500 Rp 108,537.56 Rp 5,426.88
- Tukang Alumunium OH 0.0500 Rp 119,391.31 Rp 5,969.57
JUMLAH HARGA Rp 65,122.53
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 65,122.53
C ALAT
4 Jendela aluminium Type J4 unit Rp 1,792,573.81 Empiris
A BAHAN
- Cathment 12 " set 2.0000 Rp 105,000.20 Rp 210,000.40
- Frame daun jendela m1 4.4000 Rp 118,000.20 Rp 519,200.88
- Handle jendela alumunium set 2.0000 Rp 151,000.00 Rp 302,000.00
- Kaca tebal 5 mm m2 3.8100 Rp 125,000.00 Rp 476,250.00
- Sealent m1 4.4000 Rp 50,000.00 Rp 220,000.00
JUMLAH HARGA Rp 1,727,451.28
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 1,727,451.28
B UPAH
- Kepala Tukang Alumunium OH 0.2500 Rp 130,245.07 Rp 32,561.27
- Mandor OH 0.1500 Rp 141,098.82 Rp 21,164.82
- Pekerja OH 0.0500 Rp 108,537.56 Rp 5,426.88
- Tukang Alumunium OH 0.0500 Rp 119,391.31 Rp 5,969.57
JUMLAH HARGA Rp 65,122.53
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 65,122.53
C ALAT
5 Jendela aluminium Type J5 unit Rp 1,624,573.61 Empiris
A BAHAN
- Cathment 12 " set 2.0000 Rp 105,000.20 Rp 210,000.40
- Frame daun jendela m1 3.4000 Rp 118,000.20 Rp 401,200.68
- Handle jendela alumunium set 2.0000 Rp 151,000.00 Rp 302,000.00
- Kaca tebal 5 mm m2 3.8100 Rp 125,000.00 Rp 476,250.00
- Sealent m1 3.4000 Rp 50,000.00 Rp 170,000.00
JUMLAH HARGA Rp 1,559,451.08
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 1,559,451.08
B UPAH
- Kepala Tukang Alumunium OH 0.2500 Rp 130,245.07 Rp 32,561.27
- Mandor OH 0.1500 Rp 141,098.82 Rp 21,164.82
- Pekerja OH 0.0500 Rp 108,537.56 Rp 5,426.88
- Tukang Alumunium OH 0.0500 Rp 119,391.31 Rp 5,969.57
JUMLAH HARGA Rp 65,122.53
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 65,122.53
C ALAT
6 Jendela aluminium Type J6 unit Rp 1,658,173.65 Empiris
A BAHAN
- Cathment 12 " set 2.0000 Rp 105,000.20 Rp 210,000.40
- Frame daun jendela m1 3.6000 Rp 118,000.20 Rp 424,800.72
- Handle jendela alumunium set 2.0000 Rp 151,000.00 Rp 302,000.00
- Kaca tebal 5 mm m2 3.8100 Rp 125,000.00 Rp 476,250.00
- Sealent m1 3.6000 Rp 50,000.00 Rp 180,000.00
JUMLAH HARGA Rp 1,593,051.12
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 1,593,051.12
B UPAH
- Kepala Tukang Alumunium OH 0.2500 Rp 130,245.07 Rp 32,561.27
- Mandor OH 0.1500 Rp 141,098.82 Rp 21,164.82
- Pekerja OH 0.0500 Rp 108,537.56 Rp 5,426.88
- Tukang Alumunium OH 0.0500 Rp 119,391.31 Rp 5,969.57
JUMLAH HARGA Rp 65,122.53
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 65,122.53
C ALAT
7 Jendela aluminium Type J7 unit Rp 1,422,973.37 Empiris
A BAHAN
- Cathment 12 " set 2.0000 Rp 105,000.20 Rp 210,000.40
- Frame daun jendela m1 2.2000 Rp 118,000.20 Rp 259,600.44
- Handle jendela alumunium set 2.0000 Rp 151,000.00 Rp 302,000.00
- Kaca tebal 5 mm m2 3.8100 Rp 125,000.00 Rp 476,250.00
- Sealent m1 2.2000 Rp 50,000.00 Rp 110,000.00
JUMLAH HARGA Rp 1,357,850.84
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 1,357,850.84
B UPAH
- Kepala Tukang Alumunium OH 0.2500 Rp 130,245.07 Rp 32,561.27
- Mandor OH 0.1500 Rp 141,098.82 Rp 21,164.82
- Pekerja OH 0.0500 Rp 108,537.56 Rp 5,426.88
- Tukang Alumunium OH 0.0500 Rp 119,391.31 Rp 5,969.57
JUMLAH HARGA Rp 65,122.53
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 65,122.53
C ALAT
8 Jendela aluminium Type J8 unit Rp 1,624,573.61 Empiris
A BAHAN
- Cathment 12 " set 2.0000 Rp 105,000.20 Rp 210,000.40
- Frame daun jendela m1 3.4000 Rp 118,000.20 Rp 401,200.68
- Handle jendela alumunium set 2.0000 Rp 151,000.00 Rp 302,000.00
- Kaca tebal 5 mm m2 3.8100 Rp 125,000.00 Rp 476,250.00
- Sealent m1 3.4000 Rp 50,000.00 Rp 170,000.00
JUMLAH HARGA Rp 1,559,451.08
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 1,559,451.08
B UPAH
- Kepala Tukang Alumunium OH 0.2500 Rp 130,245.07 Rp 32,561.27
- Mandor OH 0.1500 Rp 141,098.82 Rp 21,164.82
- Pekerja OH 0.0500 Rp 108,537.56 Rp 5,426.88
- Tukang Alumunium OH 0.0500 Rp 119,391.31 Rp 5,969.57
JUMLAH HARGA Rp 65,122.53
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 65,122.53
C ALAT
9 Pekerjaan bongkar kaca unit Rp 62,409.10 Empiris
A BAHAN
B UPAH
- Mandor OH 0.2500 Rp 141,098.82 Rp 35,274.71
- Pekerja OH 0.2500 Rp 108,537.56 Rp 27,134.39
JUMLAH HARGA Rp 62,409.10
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 62,409.10
C ALAT
10 Keselamatan dan Kesehatan Kerja Bulan Rp 1,425,000.00 Empiris
A BAHAN
B UPAH
C ALAT
- Helm Pelindung bh 5.0000 Rp 35,000.00 Rp 175,000.00
- Kotak P3k obat Luka, Perban DLL ls 1.0000 Rp 700,000.00 Rp 700,000.00
- Rompi Keselamatan psg 5.0000 Rp 40,000.00 Rp 200,000.00
- Sarung Tangan psg 5.0000 Rp 20,000.00 Rp 100,000.00
- Sepatu Keselamatan psg 5.0000 Rp 50,000.00 Rp 250,000.00
JUMLAH HARGA Rp 1,425,000.00
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 1,425,000.00
11 Pencenggahan Covid - 19 Bulan Rp 5,503,000.00 Empiris
A BAHAN
- Test SWAB Anti Gen 2x1 Bulan bh 5.0000 Rp 525,000.00 Rp 2,625,000.00
JUMLAH HARGA Rp 2,625,000.00
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 2,625,000.00
B UPAH
C ALAT
- Desinfektan ls 2.0000 Rp 700,000.00 Rp 1,400,000.00
- Face Shield bh 5.0000 Rp 50,000.00 Rp 250,000.00
- Hand Sanitizer liter 3.0000 Rp 90,000.00 Rp 270,000.00
- Masker Medis psg 5.0000 Rp 100,000.00 Rp 500,000.00
- Thermogun buah 2.0000 Rp 229,000.00 Rp 458,000.00
JUMLAH HARGA Rp 2,878,000.00
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 2,878,000.00
12 Mob De Mob Atat Bandu, Pekerja Dan Material Ls Rp 3,858,173.94 Empiris
A BAHAN
B UPAH
- Mandor OH 1.0000 Rp 141,098.82 Rp 141,098.82
- Pekerja OH 2.0000 Rp 108,537.56 Rp 217,075.12
JUMLAH HARGA Rp 358,173.94
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 358,173.94
C ALAT
- Sewa Scafolding set 1.0000 Rp 3,500,000.00 Rp 3,500,000.00
JUMLAH HARGA Rp 3,500,000.00
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 3,500,000.00
13 Pembersihan lapangan dan perataan m2 Rp 1,790.87 Permen PUPR Nomor 28/PRT/M/2016
A BAHAN
B UPAH
- Mandor OH 0.0050 Rp 141,098.82 Rp 705.49
- Pekerja OH 0.0100 Rp 108,537.56 Rp 1,085.38
JUMLAH HARGA Rp 1,790.87
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 1,790.87
C ALAT
AHSP SNI Data Pembaharuan dan
14 Pembersihan Lokasi m2 Rp 1,790.87
Penyesuaian 2017-2018
A BAHAN
B UPAH
- Mandor OH 0.0050 Rp 141,098.82 Rp 705.49
- Pekerja OH 0.0100 Rp 108,537.56 Rp 1,085.38
JUMLAH HARGA Rp 1,790.87
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 1,790.87
C ALAT
AHSP SNI Data Pembaharuan dan
15 Papan Nama Proyek 80 x 120 cm, t = 250 cm unit Rp 1,035,839.03
Penyesuaian 2017-2018
A BAHAN
- Cat Kayu kg 1.5000 Rp 86,830.05 Rp 130,245.08
- Kayu papan kelas III m3 0.0700 Rp 2,505,046.82 Rp 175,353.28
- Paku biasa kg 0.6000 Rp 31,475.89 Rp 18,885.53
- Seng plat BJLS 30 lebar 45 m1 3.6000 Rp 28,762.45 Rp 103,544.82
JUMLAH HARGA Rp 428,028.71
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 428,028.71
B UPAH
- Mandor OH 1.0000 Rp 141,098.82 Rp 141,098.82
- Pekerja OH 2.0000 Rp 108,537.56 Rp 217,075.12
- Tukang cat OH 1.0000 Rp 124,818.19 Rp 124,818.19
- Tukang Kayu OH 1.0000 Rp 124,818.19 Rp 124,818.19
JUMLAH HARGA Rp 607,810.32
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 607,810.32
C ALAT
16 Jendela aluminium Type J1 unit Rp 1,592,058.95 Empiris
A BAHAN
- Cathment 12 " set 2.0000 Rp 105,000.20 Rp 210,000.40
- Frame daun jendela m1 3.2000 Rp 118,000.20 Rp 377,600.64
- Handle jendela alumunium set 2.0000 Rp 151,000.00 Rp 302,000.00
- Kaca tebal 5 mm m2 3.8100 Rp 125,000.00 Rp 476,250.00
- Sealent m1 3.2000 Rp 50,000.00 Rp 160,000.00
JUMLAH HARGA Rp 1,525,851.04
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 1,525,851.04
B UPAH
- Kepala Tukang Alumunium OH 0.1500 Rp 130,245.07 Rp 19,536.76
- Mandor OH 0.2500 Rp 141,098.82 Rp 35,274.71
- Pekerja OH 0.0500 Rp 108,537.56 Rp 5,426.88
- Tukang Alumunium OH 0.0500 Rp 119,391.31 Rp 5,969.57
JUMLAH HARGA Rp 66,207.91
JASA 0.00 % Rp 0.00
TOTAL HARGA Rp 66,207.91
C ALAT
RINCIAN VOLUME

NAMA PROYEK PENGGANTIAN JENDELA


LOKASI KOTA BANDUNG
TAHUN 2021

NO URAIAN PEKERJAAN JUMLAH PANJANG LEBAR TINGGI LUAS VOLUME TOTAL VOLUME SATUAN
A PEKERJAAN PERSIAPAN
A.1 Papan Nama Proyek 80 x 120 cm, t = 250 cm 1.00 unit
1.00 1.00
A.2 Pembersihan Lokasi 1,298.00 m2
1.00 1,298.00 1,298.00
A.3 Mob De Mob Atat Bandu, Pekerja Dan Material 1.00 Ls
1.00 1.00
A.4 Pencenggahan Covid - 19 2.00 Bulan
2.00 2.00
B KESELAMATAN DAN KESEHATAN KERJA (K3)
B.1 Keselamatan dan Kesehatan Kerja 2.00 Bulan
2.00 2.00
C PEKERJAAN BONGLARAN
C.1 Pekerjaan bongkar jendela alumunium 56.00 unit
56.00 56.00
C.2 Pekerjaan bongkar kaca 56.00 unit
56.00 56.00
D PEKERJAAN JENDELA
D.1 Jendela aluminium Type J1 6.00 unit
+ J1 6.00 6.00
D.2 Jendela aluminium Type J2 1.00 unit
+ J2 1.00 1.00
D.3 Jendela aluminium Type J3 5.00 unit
+ J3 5.00 5.00
D.4 Jendela aluminium Type J4 15.00 unit
+ J4 15.00 15.00
D.5 Jendela aluminium Type J5 3.00 unit
+ J5 3.00 3.00
D.6 Jendela aluminium Type J6 19.00 unit
+ J6 19.00 19.00
D.7 Jendela aluminium Type J7 2.00 unit
+ J7 2.00 2.00
D.8 Jendela aluminium Type J8 6.00 unit
+ J8 6.00 6.00
E PEKERJAAN PERAPIHAN
E.1 Pembersihan lapangan dan perataan 1,298.00 m2
+ Pembersihan Lokasi [PEKERJAAN PERSIAPAN] 1.00 1,298.00 1,298.00 m2
RENCANA ANGGARAN BIAYA

NAMA PROYEK PENGGANTIAN JENDELA


LOKASI KOTA BANDUNG
TAHUN 2021

NO URAIAN PEKERJAAN TOTAL VOLUME SATUAN HARGA SATUAN HARGA %


A PEKERJAAN PERSIAPAN Rp 18,224,561.84 14.17
A.1 Papan Nama Proyek 80 x 120 cm, t = 250 cm 1.00 unit Rp 1,035,839.03 Rp 1,035,839.03 0.81
A.2 Pembersihan Lokasi 1,298.00 m2 Rp 1,790.87 Rp 2,324,548.87 1.81
A.3 Mob De Mob Atat Bandu, Pekerja Dan Material 1.00 Ls Rp 3,858,173.94 Rp 3,858,173.94 3.00
A.4 Pencenggahan Covid - 19 2.00 Bulan Rp 5,503,000.00 Rp 11,006,000.00 8.56
B KESELAMATAN DAN KESEHATAN KERJA (K3) Rp 2,850,000.00 2.22
B.1 Keselamatan dan Kesehatan Kerja 2.00 Bulan Rp 1,425,000.00 Rp 2,850,000.00 2.22
C PEKERJAAN BONGLARAN Rp 8,995,592.68 6.99
C.1 Pekerjaan bongkar jendela alumunium 56.00 unit Rp 98,226.49 Rp 5,500,683.36 4.28
C.2 Pekerjaan bongkar kaca 56.00 unit Rp 62,409.10 Rp 3,494,909.32 2.72
D PEKERJAAN JENDELA Rp 96,222,491.98 74.81
D.1 Jendela aluminium Type J1 6.00 unit Rp 1,592,058.95 Rp 9,552,353.69 7.43
D.2 Jendela aluminium Type J2 1.00 unit Rp 1,678,253.10 Rp 1,678,253.10 1.30
D.3 Jendela aluminium Type J3 5.00 unit Rp 1,826,173.85 Rp 9,130,869.27 7.10
D.4 Jendela aluminium Type J4 15.00 unit Rp 1,792,573.81 Rp 26,888,607.21 20.91
D.5 Jendela aluminium Type J5 3.00 unit Rp 1,624,573.61 Rp 4,873,720.84 3.79
D.6 Jendela aluminium Type J6 19.00 unit Rp 1,658,173.65 Rp 31,505,299.43 24.50
D.7 Jendela aluminium Type J7 2.00 unit Rp 1,422,973.37 Rp 2,845,946.75 2.21
D.8 Jendela aluminium Type J8 6.00 unit Rp 1,624,573.61 Rp 9,747,441.68 7.58
E PEKERJAAN PERAPIHAN Rp 2,324,548.87 1.81
E.1 Pembersihan lapangan dan perataan 1,298.00 m2 Rp 1,790.87 Rp 2,324,548.87 1.81
JUMLAH HARGA Rp 128,617,195.36 100.00
PPN 10.00 % Rp 12,861,719.54
TOTAL HARGA Rp 141,478,914.90
REKAPITULASI ANGGARAN BIAYA

NAMA PROYEK PENGGANTIAN JENDELA


LOKASI KOTA BANDUNG
TAHUN 2021

NO URAIAN PEKERJAAN HARGA %


A PEKERJAAN PERSIAPAN Rp 18,224,561.84 14.17
B KESELAMATAN DAN KESEHATAN KERJA (K3) Rp 2,850,000.00 2.22
C PEKERJAAN BONGLARAN Rp 8,995,592.68 6.99
D PEKERJAAN JENDELA Rp 96,222,491.98 74.81
E PEKERJAAN PERAPIHAN Rp 2,324,548.87 1.81
JUMLAH HARGA Rp 128,617,195.36 100.00
PPN 10.00 % Rp 12,861,719.54
TOTAL HARGA Rp 141,478,914.90
DIBULATKAN Rp 141,479,000.00

TERBILANG: Seratus Empat Puluh Satu Juta Empat Ratus Tujuh Puluh Sembilan Ribu Rupiah
REKAPITULASI BAHAN

NAMA PROYEK PENGGANTIAN JENDELA


LOKASI KOTA BANDUNG
TAHUN 2021

NO. URAIAN BAHAN VOLUME SATUAN MERK SPESIFIKASI SUMBER JUMLAH HARGA %
5 Kaca tebal 5 mm 217.1700 m2 Standar Bening Survey Rp 27,146,250.00 27.65
3 Frame daun jendela 215.2000 m1 Alexindo Warna silver Survey Rp 25,393,643.04 25.87
4 Handle jendela alumunium 114.0000 set Weldom Rambuncis Handle Jendela AlumunSurvey Rp 17,214,000.00 17.54
2 Cathment 12 " 114.0000 set Xolani / Lainnya Window Casement 12 Inch HD FrictSurvey Rp 11,970,022.80 12.19
8 Sealent 215.2000 m1 Standar Standar Survey Rp 10,760,000.00 10.96
10 Test SWAB Anti Gen 2x1 Bulan 10.0000 bh Standar Standar Survey Rp 5,250,000.00 5.35
6 Kayu papan kelas III 0.0700 m3 Kamper Standar IKK BPS 2021 Rp 175,353.28 0.18
1 Cat Kayu 1.5000 kg EMCO Standar IKK BPS 2021 Rp 130,245.08 0.13
9 Seng plat BJLS 30 lebar 45 3.6000 m1 Standar Standar Estimator.id Rp 103,544.82 0.11
7 Paku biasa 0.6000 kg Standar 1 3/4 "- (reng kayu) IKK BPS 2021 Rp 18,885.53 0.02
JUMLAH HARGA Rp 98,161,944.55 100.00
REKAPITULASI UPAH

NAMA PROYEK PENGGANTIAN JENDELA


LOKASI KOTA BANDUNG
TAHUN 2021

NO. URAIAN UPAH VOLUME SATUAN MERK SPESIFIKASI SUMBER JUMLAH HARGA %
2 Mandor 49.4300 OH Standar Standar IKK BPS 2021 Rp 6,974,514.67 38.01
3 Pekerja 60.8100 OH Standar Standar IKK BPS 2021 Rp 6,600,169.02 35.97
1 Kepala Tukang Alumunium 19.2500 OH Standar Standar Estimator.id Rp 2,507,217.60 13.66
4 Tukang Alumunium 16.9000 OH Standar Standar Estimator.id Rp 2,017,713.14 11.00
5 Tukang cat 1.0000 OH Standar Standar IKK BPS 2021 Rp 124,818.19 0.68
6 Tukang Kayu 1.0000 OH Standar Kasar IKK BPS 2021 Rp 124,818.19 0.68
JUMLAH HARGA Rp 18,349,250.81 100.00
REKAPITULASI ALAT

NAMA PROYEK PENGGANTIAN JENDELA


LOKASI KOTA BANDUNG
TAHUN 2021

NO. URAIAN ALAT VOLUME SATUAN MERK SPESIFIKASI SUMBER JUMLAH HARGA %
10 Sewa Scafolding 1.0000 set Standar Standar Survey Rp 3,500,000.00 28.91
1 Desinfektan 4.0000 ls Standar Standar Survey Rp 2,800,000.00 23.13
5 Kotak P3k obat Luka, Perban DLL 2.0000 ls Standar Standar Survey Rp 1,400,000.00 11.56
6 Masker Medis 10.0000 psg Standar Standar Survey Rp 1,000,000.00 8.26
11 Thermogun 4.0000 buah Standar Standar Survey Rp 916,000.00 7.57
3 Hand Sanitizer 6.0000 liter Standar Standar Survey Rp 540,000.00 4.46
2 Face Shield 10.0000 bh Standar Standar Survey Rp 500,000.00 4.13
9 Sepatu Keselamatan 10.0000 psg Standar Standar Survey Rp 500,000.00 4.13
7 Rompi Keselamatan 10.0000 psg Standar Standar Survey Rp 400,000.00 3.30
4 Helm Pelindung 10.0000 bh Standar Standar Survey Rp 350,000.00 2.89
8 Sarung Tangan 10.0000 psg Standar Standar Survey Rp 200,000.00 1.65
JUMLAH HARGA Rp 12,106,000.00 100.00
JADWAL WAKTU PELAKSANAAN (TIME SCHEDULE)
PEKERJAAN PENGGANTIAN JENDELA

Nama Ins UPTD Pelatihan Kesehatan


:
: Dinas Kesehatan Provinsi Jawa Barat
Paket Pe : Rehabilitasi Gedunga dan Bangunan UPTD Pelatihan Kesehatan Dinas Kesehatan Provinsi Jawa Barat
: Penggantian Jendela
Lokasi : UPTD Pelatihan Kesehatan
: Jl. Pasteur No. 31, Pasir Kaliki, Kec. Cicendo, Kota Bandung Jawabarat 40171
Tahun A : 2021

NO URAIAN PEKERJAAN BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Ket.


A PEKERJAAN PERSIAPAN 14.17
A.1 Papan Nama Proyek 80 x 120 cm, t = 250 cm 0.810 0.405 0.405
A.2 Pembersihan Lokasi 1.810 0.453 0.453 0.453 0.453
A.3 Mob De Mob Atat Bandu, Pekerja Dan Material 3.000 0.600 0.600 0.600 0.600 0.600
A.4 Pencenggahan Covid - 19 8.560 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428 0.428
B KESELAMATAN DAN KESEHATAN KERJA (K3) 2.220
B.1 Keselamatan dan Kesehatan Kerja 2.220 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111 0.111
C PEKERJAAN BONGLARAN 6.990
C.1 Pekerjaan bongkar jendela alumunium 4.280 0.713 0.713 0.713 0.713 0.713 0.713
C.2 Pekerjaan bongkar kaca 2.720 0.453 0.453 0.453 0.453 0.453 0.453
D PEKERJAAN JENDELA 74.810
D.1 Jendela aluminium Type J1 7.430 1.858 1.858 1.858 1.858
D.2 Jendela aluminium Type J2 1.300 0.650 0.650
D.3 Jendela aluminium Type J3 7.100 0.888 0.888 0.888 0.888 0.888 0.888 0.888 0.888
D.4 Jendela aluminium Type J4 20.910 2.091 2.091 2.091 2.091 2.091 2.091 2.091 2.091 2.091 2.091
D.5 Jendela aluminium Type J5 3.790 0.948 0.948 0.948 0.948
D.6 Jendela aluminium Type J6 24.500 2.450 2.450 2.450 2.450 2.450 2.450 2.450 2.450 2.450 2.450
D.7 Jendela aluminium Type J7 2.210 1.105 1.105
D.8 Jendela aluminium Type J8 7.580 1.516 1.516 1.516 1.516 1.516
E PEKERJAAN PERAPIHAN 1.810
E.1 Pembersihan lapangan dan perataan 1.810 0.453 0.453 0.453 0.453
JUMLAH HARGA 100.000
1.444 0.944 1.544 2.306 4.163 4.813 6.606 6.542 7.134 5.968 5.968 5.968 5.968 6.873 6.028 7.544 7.544 5.453 3.160 4.065
1.444 2.388 3.932 6.238 10.401 15.214 21.820 28.361 35.496 41.463 47.431 53.398 59.366 66.238 72.266 79.809 87.353 92.805 95.965 100.030