NO URAIAN PEKERJAAN JUMLAH HARGA


A B C
I PEKERJAAN PERSIAPAN SMK 1 KASIMBAR
1.1 PEKERJAAN PERSIAPAN Rp 10,186,534.99

II LABORATORIUM KIMIA & KOMPUTER


2.1 PEKERJAAN STRUKTUR Rp 320,552,990.27
2.2 PEKERJAAN ARSITEKTUR Rp 403,776,777.10

III UKS DAN OSIS


3.1 PEKERJAAN STRUKTUR Rp 131,098,956.87
3.2 PEKERJAAN ARSITEKTUR Rp 217,422,266.44

IV RUANG KELAS
4.1 PEKERJAAN STRUKTUR Rp 226,870,439.73
4.2 PEKERJAAN ARSITEKTUR Rp 258,187,264.80

V PEKERJAAN AKHIR
5.1 PEMBERSIHAN & PELAPORAN Rp 6,500,000.00

VI BIAYA PENGELOLAAN ADMINISTRASI Rp 15,905,000.00

A. Real Cost (I+II+III+IV+V) Rp 1,574,595,230.20


D. Dibulatkan Rp 1,574,595,000.00

SATU MILIAR LIMA RATUS TUJUH PULUH EMPAT JUTA LIMA RATUS SEMBILAN
Terbilang :
PULUH LIMA RIBU RUPIAH

MENYETUJUI : Dibuat Oleh :


KEPALA SEKOLAH FASILITATOR

RUSTAM ABDI , S.Pd. M.P ABDUL RIFAL (YOYO)


197010052007011042
RENCANA PENGGUNAAN DANA (RPD)
DANA ALOKASI KHUSUS (DAK) FISIK PENUGASAN SMK
APD TAHUN 2022
ENGINEERING ESTIMATE (EE)
NAMA SEKOLAH : SMKN 1 KASIMBAR
KAB/KOTA : Kab. Parigi Moutong
PROVINSI : SULAWESI TENGAH

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT.
(Rp) (Rp)
A B C D E F

I PEKERJAAN PERSIAPAN SMK 1 KASIMBAR


1.1 PEKERJAAN PERSIAPAN Rp 10,186,534.99
A. Pekerjaan Persiapan & Lainnya Rp 10,186,534.99
1 Papan Nama Proyek 1.00 Ls Rp 150,000.00 Rp 150,000.00
2 Pembersihan lapangan & peralatan 469.21 M2 Rp -
3 Kesehatan dan Keselamatan Kerja (K3)
d. Alat Pelindung Kerja & Alat Pelindung Diri
1). APK Antara Lain
- Spanduk/Banner 1.00 Bh Rp 152,000.00 Rp 152,000.00
- Poster 1.00 Set Rp 15,000.00 Rp 15,000.00
- Papan Informasi K3 1.00 Bh Rp 105,000.00 Rp 105,000.00
2). APD Antara Lain
- Helm/Safety Helmet 10.00 Bh Rp 45,000.00 Rp 450,000.00
- Sepatu/Safety Shoes) 10.00 Bh Rp 120,000.00 Rp 1,200,000.00
- Sarung Tangan/Safety Gloves 10.00 Bh Rp 10,000.00 Rp 100,000.00
- Rompi Keselamatan/Safety Vest 10.00 Psg Rp 35,000.00 Rp 350,000.00
3). Fasilitas, Sarana & Prasarana K3
- Peralatan P3K 3.00 Ls Rp 235,000.00 Rp 705,000.00
4 Pengukuran dan Pas Bouwplank Lab. Kimia komputer 89.38 M1 Rp 32,386.50 Rp 2,894,705.37
5 Pengukuran dan Pas Bouwplank uks & osis 55.30 M1 Rp 32,386.50 Rp 1,790,973.45
6 Pengukuran dan Pas Bouwplank Ruang kelas 70.21 M1 Rp 32,386.50 Rp 2,273,856.17

II LABORATORIUM KIMIA & KOMPUTER

2.1 PEKERJAAN STRUKTUR Rp 320,552,990.27


A. Pekerjaan Tanah dan Pasir Rp 28,365,145.88
1 Pek. Galiaan Tanah Pondasi Foot Plat 8.82 M3 Rp 81,000.00 Rp 714,420.00
2 Pek. Galiaan Tanah Pondasi Batu Kali 70.74 M3 Rp 67,500.00 Rp 4,775,274.00
3 Pek. Urugan Pasir Bawah Pondasi Foot Plat t=5cm 0.22 M3 Rp 171,000.00 Rp 37,705.50
4 Pek. Urugan Pasir Bawah Pondasi Batu Kali t=5cm 5.05 M3 Rp 171,000.00 Rp 864,097.20
5 Pek. Urugan Pasir Bawah Lantai t=5cm 25.12 M3 Rp 171,000.00 Rp 4,295,528.55
6 Pek. Urugan Kembali Tanah Bekas Galian Pondasi Foot Plat 2.94 M3 Rp 45,000.00 Rp 132,300.00
7 Pek. Urugan Kembali Tanah Bekas Galian Pondasi Batu Kali 17.69 M3 Rp 45,000.00 Rp 795,879.00
8 Pek. Urugan Tanah dalam pondasi ( Sirtu Padat) 100.60 M3 Rp 166,500.00 Rp 16,749,941.63

B. Pekerjaan Rabat Beton & Pondasi Rp 83,718,091.96


1 Pek. Coor Lantai Kerja t=5cm Pondasi Foot Plat 0.392 M3 Rp 886,268.13 Rp 347,417.11
2 Pek. Rabat Beton Bawah Lantai t=5cm 12.56 M3 Rp 907,548.13 Rp 11,398,827.14
3 Pek. Pondasi Foot Plat P.K1
- Pile Cap Beton K175 0.588 M3 Rp 1,039,171.88 Rp 611,033.06
- Pedestal 15x20 Beton K175 0.588 M3 Rp 1,039,171.88 Rp 611,033.06
- Pembesian Pile Cap 61.75 Kg Rp 15,283.72 Rp 943,831.05
- Pembesian Pedestal 128.72 Kg Rp 15,283.72 Rp 1,967,330.21
- Bekisting Pile Cap 1.68 M2 Rp 170,612.50 Rp 286,629.00
- Bekisting Pedestal 6.86 M2 Rp 327,112.50 Rp 2,243,991.75
4 Pek. Pondasi Foot Plat P.K2
- Pile Cap Beton K175 0.59 M3 Rp 1,039,171.88 Rp 611,033.06
- Pedestal 20x30 Beton K175 1.18 M3 Rp 1,039,171.88 Rp 1,222,066.13
- Pembesian Pile Cap 61.75 Kg Rp 15,283.72 Rp 943,831.05
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT.
(Rp) (Rp)
A B C D E F
- Pembesian Pedestal 144.82 Kg Rp 15,283.72 Rp 2,213,368.30
- Bekisting Pile Cap 1.68 M2 Rp 170,612.50 Rp 286,629.00
- Bekisting Pedestal 9.80 M2 Rp 327,112.50 Rp 3,205,702.50
5 Pek. Pasangan Batu Kosong 15.16 M3 Rp 490,080.00 Rp 7,429,416.77
6 Pek. Pasangan Batu Kali 59.17 M3 Rp 834,780.00 Rp 49,395,952.77

C . Pekerjaan Sloof,Kolom, & Balok Rp 110,088,187.40


1 Pekerjaan Sloof 15x20
- Beton K.175 3.92 M3 Rp 1,039,171.88 Rp 4,073,034.16
- Pembesian 726.76 Kg Rp 15,283.72 Rp 11,107,543.30
- Bekisting Sloof ( 2 x Pakai ) 35.93 M2 Rp 180,175.00 Rp 6,473,462.53
2 Pekerjaan Kolom KP 11x11
- Beton K.175 1.51 M3 Rp 1,039,171.88 Rp 1,571,118.76
- Pembesian 434.86 Kg Rp 15,283.72 Rp 6,646,352.63
- Bekisting Kolom KP ( 2 x Pakai ) 13.74 M2 Rp 327,112.50 Rp 4,495,997.76
3 Pekerjaan Kolom K1 15x20
- Beton K.175 1.36 M3 Rp 1,039,171.88 Rp 1,415,352.09
- Pembesian 263.36 Kg Rp 15,283.72 Rp 4,025,134.89
- Bekisting Kolom K1 ( 2 x Pakai ) 15.89 M2 Rp 327,112.50 Rp 5,197,817.63
4 Pekerjaan Kolom K2 20x30
- Beton K.175 2.49 M3 Rp 1,039,171.88 Rp 2,587,537.97
- Pembesian 362.77 Kg Rp 15,283.72 Rp 5,544,408.03
- Bekisting Kolom K2 ( 2 x Pakai ) 20.75 M2 Rp 327,112.50 Rp 6,787,584.38
5 Pekerjaan Balok Latei 11x11 Ev +3.15
- Beton K.175 0.80 M3 Rp 1,039,171.88 Rp 831,768.76
- Pembesian 346.36 Kg Rp 15,283.72 Rp 5,293,618.03
- Bekisting Balok Latei ( 2 x Pakai ) 7.28 M2 Rp 337,237.50 Rp 2,453,908.67
6 Pekerjaan Balok 11x20 Ev +4.50
- Beton K.175 2.99 M3 Rp 1,039,171.88 Rp 3,108,059.16
- Pembesian 491.52 Kg Rp 15,283.72 Rp 7,512,207.20
- Bekisting Balok ( 2 x Pakai ) 34.67 M2 Rp 337,237.50 Rp 11,691,096.72
7 Pekerjaan Balok 11x20 Ev +5.25
- Beton K.175 0.13 M3 Rp 1,039,171.88 Rp 130,312.15
- Pembesian 33.25 Kg Rp 15,283.72 Rp 508,237.50
- Bekisting Balok ( 2 x Pakai ) 1.45 M2 Rp 337,237.50 Rp 490,174.71
8 Pekerjaan Balok 11x20 Ev +5.20
- Beton K.175 0.13 M3 Rp 1,039,171.88 Rp 132,598.33
- Pembesian 33.40 Kg Rp 15,283.72 Rp 510,488.83
- Bekisting Balok ( 2 x Pakai ) 1.48 M2 Rp 337,237.50 Rp 498,774.26
9 Pekerjaan Balok 11x11 Ev +5.55
- Beton K.175 0.07 M3 Rp 1,039,171.88 Rp 69,156.89
- Pembesian 33.91 Kg Rp 15,283.72 Rp 518,207.67
- Bekisting Balok ( 2 x Pakai ) 0.61 M2 Rp 337,237.50 Rp 204,028.69
10 Pekerjaan Ring Balok 11x20 Ev +6.00
- Beton K.175 1.05 M3 Rp 1,039,171.88 Rp 1,087,205.72
- Pembesian 347.40 Kg Rp 15,283.72 Rp 5,309,601.50
- Bekisting Balok ( 2 x Pakai ) 12.13 M2 Rp 337,237.50 Rp 4,089,570.57
11 Pekerjaan talang beton
- Beton kedap air 0.89 M3 Rp 943,225.90 Rp 834,754.92
- Pembesian 167.57 Kg Rp 15,283.72 Rp 2,561,122.52
- Bekisting talang beton ( 2 x Pakai ) 6.90 M2 Rp 337,237.50 Rp 2,327,950.46

D. Pekerjaan Atap Rp 98,381,565.04


1 Pek. Rangka Atap Baja Ringan 278.84 M2 Rp 169,500.27 Rp 47,264,150.92
2 Pek. Penutup Atap Spandek 278.84 M2 Rp 162,112.50 Rp 45,204,114.97
3 Pek. Nok dan Jurai Atap Spandek 94.91 M1 Rp 32,862.50 Rp 3,118,914.15
4 Pek. Pemasangan lisplank 25.85 M1 Rp 108,100.00 Rp 2,794,385.00

2.2 PEKERJAAN ARSITEKTUR Rp 403,776,777.10

A. Pekerjaan Dinding Rp 142,595,357.45


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT.
(Rp) (Rp)
A B C D E F
1 Pek. Pemasangan Dinding 1/2 Bata Merah 1:5 383.26 M2 Rp 132,735.00 Rp 50,871,920.53
2 Pek. Plesteran Dinding,Kolom,Balok & Sloof 905.47 M2 Rp 59,868.00 Rp 54,208,882.71
3 Pek. Plesteran Kaki Pondasi Batu Kali 1:3 33.40 M2 Rp 63,882.00 Rp 2,133,904.70
4 Pek. Acian 943.88 M2 Rp 37,484.38 Rp 35,380,649.52

B. Pekerjaan Penutup Lantai & Dinding Rp 67,996,510.50


1 Pek. Pemasangan Granit 60x60cm 236.70 M2 Rp 287,264.79 Rp 67,996,510.50

C. Pekerjaan Kusen Pintu/Jendela + Assesories Rp 69,194,635.31


1 2 Unit Kusen Pintu Type PJ
- Pek. Pemasangan Kusen aluminium type PJ 47.20 M1 Rp 79,902.50 Rp 3,771,398.00
- Pek. Pemasangan daun pintu multiplaks Type PJ 4.05 M2 Rp 827,306.61 Rp 3,350,591.78
- Pek. Pemasangan Kaca 5 mm 10.20 M2 Rp 215,146.88 Rp 2,193,637.54
- Pek. Pemasangan handel pintu tanam 60 cm Ex dekson 2.00 Set Rp 205,000.00 Rp 410,000.00
- Pek. Pemasangan kunci Pintu 2 Slaag Ex dekson 2.00 Bh Rp 352,150.00 Rp 704,300.00
- Pek. Pemasangan engsel Pintu 6.00 Bh Rp 67,350.00 Rp 404,100.00

2 1 Unit Kusen Pintu Type PJ1


- Pek. Pemasangan Kusen aluminium Type PJ1 16.650 M1 Rp 79,902.50 Rp 1,330,376.63
- Pek. Pemasangan daun pintu multiplaks Type PJ1 1.84 M2 Rp 827,306.61 Rp 1,520,175.90
- Pek. Pemasangan Kaca 5 mm 3.12 M2 Rp 215,146.88 Rp 672,098.94
- Pek. Pemasangan handel pintu tanam 60 cm Ex dekson 1.00 Set Rp 205,000.00 Rp 205,000.00
- Pek. Pemasangan Kunci Pintu 2 Slaag Ex dekson 1.00 Bh Rp 352,150.00 Rp 352,150.00
- Pek. Pemasangan engsel Pintu 3.00 Bh Rp 67,350.00 Rp 202,050.00

3 2 Unit Kusen Pintu Type P1


- Pek. Pemasangan Kusen aluminium Type P1 19.600 M1 Rp 79,902.50 Rp 1,566,089.00
- Pek. Pemasangan daun pintu multiplaks Type P1 4.17 M2 Rp 827,306.61 Rp 3,445,732.04
- Pek. Pemasangan Kaca 5 mm 2.16 M2 Rp 215,146.88 Rp 464,071.81
- Pek. Pemasangan handel pintu tanam 60 cm Ex dekson 4.00 Set Rp 205,000.00 Rp 820,000.00
- Pek. Pemasangan Kunci Pintu 2 Slaag Ex dekson 2.00 Bh Rp 352,150.00 Rp 704,300.00
- Pek. Pemasangan engsel Pintu 6.00 Bh Rp 67,350.00 Rp 404,100.00

4 2 Unit Kusen Pintu Type P2


- Pek. Pemasangan Kusen aluminium Type P2 15.600 M1 Rp 79,902.50 Rp 1,246,479.00
- Pek. Pemasangan daun pintu multiplaks Type P2 4.41 M2 Rp 827,306.61 Rp 3,648,422.16
- Pek. Pemasangan Kaca 5 mm 1.15 M2 Rp 215,146.88 Rp 246,558.32
- Pek. Pemasangan handel pintu tanam 60 cm Ex dekson 2.00 Set Rp 205,000.00 Rp 410,000.00
- Pek. Pemasangan Kunci Pintu 2 Slaag Ex dekson 2.00 Bh Rp 352,150.00 Rp 704,300.00
- Pek. Pemasangan engsel Pintu 6.00 Bh Rp 67,350.00 Rp 404,100.00

5 10 Unit Kusen Jendela Type J


- Pek. Pemasangan Kusen aluminium Type J 138.000 M1 Rp 79,902.50 Rp 11,026,545.00
- Pek. Pemasangan Slimar daun Jendela Type J 139.40 M1 Rp 48,140.00 Rp 6,710,716.00
- Pek. Pemasangan Kaca 5 mm 24.20 M2 Rp 215,146.88 Rp 5,206,554.38
- Pek. Pemasangan handel Jendela Type J 20.00 Set Rp 53,125.00 Rp 1,062,500.00
- Pek. Pemasangan Grendel Jendela 20.00 Bh Rp 39,225.00 Rp 784,500.00
- Pek. Pemasangan engsel Jendela 40.00 Bh Rp 48,650.00 Rp 1,946,000.00
- Pek. Pemasangan Hak angin Lipat 40.00 Bh Rp 56,100.00 Rp 2,244,000.00

6 2 Unit Kusen Jendela Type J1


- Pek. Pemasangan Kusen aluminium Type J1 17.600 M1 Rp 79,902.50 Rp 1,406,284.00
- Pek. Pemasangan Slimar daun Jendela Type J1 14.54 M1 Rp 48,140.00 Rp 699,955.60
- Pek. Pemasangan Kaca 5 mm 2.94 M2 Rp 215,146.88 Rp 632,531.81
- Pek. Pemasangan handel Jendela Type J1 2.00 Bh Rp 53,125.00 Rp 106,250.00
- Pek. Pemasangan Grendel Jendela 2.00 Bh Rp 39,225.00 Rp 78,450.00
- Pek. Pemasangan engsel Jendela 4.00 Bh Rp 48,650.00 Rp 194,600.00
- Pek. Pemasangan Hak angin Lipat 4.00 Bh Rp 56,100.00 Rp 224,400.00

7 2 Unit Kusen Jendela Type J2


- Pek. Pemasangan Kusen aluminium Type J2 51.300 M1 Rp 79,902.50 Rp 4,098,998.25
- Pek. Pemasangan Kaca 5 mm 14.42 M2 Rp 215,146.88 Rp 3,102,417.94
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT.
(Rp) (Rp)
A B C D E F

8 2 Unit Kusen Ventilasi Type V1


- Pek. Pemasangan Kusen aluminium Type V1 4.600 M1 Rp 79,902.50 Rp 367,551.50
- Pek. Pemasangan Kaca 5 mm 0.57 M2 Rp 215,146.88 Rp 122,349.72

D. Pekerjaan Plafond Rp 54,205,817.12


1 Pek. Rangka Plafond Hollow 40x40mm 276.60 M2 Rp 143,500.00 Rp 39,691,970.85
2 Pek. Plafond Gypsum Board 9mm 276.60 M2 Rp 52,472.50 Rp 14,513,846.27

E. Pekerjaan Finishing & Pengecetan Rp 48,506,814.31


1 Pek. Pengecatan Dinding 943.88 M2 Rp 40,072.50 Rp 37,823,521.87
2 Pek. Pengecatan Plafond Gypsum 266.60 M2 Rp 40,072.50 Rp 10,683,292.43

F. Pekerjaan Instalasi Air Bersih & Kotor + Sanitary Rp 6,632,835.63


1 Pipa Air Bersih
- Pek. PVC dia 1/2 inc (AW) Include Accessories 31.16 M1 Rp 23,941.88 Rp 745,971.36
2 Pipa Air Kotor
- Pek. PVC dia 2 inc (AW) Include Accessories 7.95 M1 Rp 48,214.69 Rp 383,070.51
3 Pek. Pemasangan Kran air Bersih 2.00 Bh Rp 133,821.88 Rp 267,643.75
4 Pek. Pemasangan wastafel 2.00 Bh Rp 2,618,075.00 Rp 5,236,150.00

G. Pekerjaan Elektrikal Rp 12,008,043.75


1 Pek. Pemasangan Box MCB 4 Grup Include 3 Bh MCB 1.00 Unit Rp 1,201,500.00 Rp 1,201,500.00
2 Pek. Instalasi 1 Titik Lampu 13.00 Titik Rp 337,743.75 Rp 4,390,668.75
3 Pek.Pemasangan 1 bh Lampu Downlight 18 Watt 13.00 Bh Rp 133,875.00 Rp 1,740,375.00
4 Pek. Pemasangan 1 Bh Lampu Spot 12 watt 8.00 Bh Rp 151,875.00
5 Pek. Pemasangan Lampu LED strip 34.80 M1 Rp 22,500.00 Rp 783,000.00
6 Pek. Instalasi Stop Kontak 10.00 Bh Rp 33,750.00 Rp 337,500.00
7 Pek. Instalasi Stop Kontak Lantai 12.00 Bh Rp 225,000.00 Rp 2,700,000.00
8 Pek. Instalasi Stop kontak AC 6.00 Bh Rp 84,375.00 Rp 506,250.00
9 Pek. Instalasi Saklar Tunggal 8.00 Bh Rp 33,750.00 Rp 270,000.00
10 Pek. Instalasi Saklar Ganda 2.00 Bh Rp 39,375.00 Rp 78,750.00

H. Pekerjaan Lain-Lain Rp 2,636,763.01


1 Pek. Rabat Beton Keliling Bangunan & Saluran Keliling Setempat
- Pek. Galian Saluran Keliling 19.01 M3 Rp 67,500.00
- Pek. Urugan Pasir Bawah Saluran Keliling 1.56 M3 Rp 171,000.00
- Pek. Pasangan Batu Kali Alas Saluran Keliling 1.56 M3 Rp 834,780.00
- Pek. Rolag Bata Pasangan Dinding Saluran Keliling 70.072 M2 Rp 132,735.00
- Pek. Plesteran dinding saluran Keliling 70.072 M2 Rp 63,882.00
- Pek. Acian dinding saluran keliling 70.072 M2 Rp 37,484.38
- Pek. Urugan Pasir Bawah Rabat Keliling 3.18 M3 Rp 133,821.88
- Pek. Rabat Beton Keliling 7.03 M3 Rp 907,548.13
2 Pek. Pasangan Tangga Luar
- Pek. Galian Tanah Tangga Luar 0.21 M3 Rp 67,500.00 Rp 14,215.50
- Pek. Pasangan Rolag 1/2 Bata dinding tangga 6.40 M2 Rp 140,049.38 Rp 896,633.91
- Pek. Urugan Tanah Bawah Lantai Pijakan Tangga 0.69 M3 Rp 166,500.00 Rp 114,720.66
- Pek. Urugan Pasir Bawah Lantai Pijakan Tangga 0.26 M3 Rp 171,000.00 Rp 45,015.75
- Pek. Rabat Beton Pijakan Tangga 0.31 M3 Rp 907,548.13 Rp 277,748.52
- Pek. Plesteran Tangga 12.71 M2 Rp 63,882.00 Rp 811,979.32
- Pek. Acian Tangga 12.71 M2 Rp 37,484.38 Rp 476,449.35
RENCANA PENGGUNAAN DANA (RPD)
DANA ALOKASI KHUSUS (DAK) FISIK PENUGASAN SMK
APD TAHUN 2022
ENGINEERING ESTIMATE (EE)
PEKERJAAN : SMKN 1 KASIMBAR
LOKASI : Kab. Parigi Moutong
TH. ANGGARAN : SULAWESI TENGAH

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT.
(Rp) (Rp)
A B C D E F

III UKS DAN OSIS

3.1 PEKERJAAN STRUKTUR Rp 131,098,956.87


A. Pekerjaan Tanah dan Pasir Rp 8,705,793.66
1 Pek. Galiaan Tanah Pondasi Foot Plat 6.86 M3 Rp 81,000.00 Rp 555,660.00
2 Pek. Galiaan Tanah Pondasi Batu Kali 37.24 M3 Rp 67,500.00 Rp 2,513,560.14
3 Pek. Urugan Pasir Bawah Pondasi Foot Plat t=5cm 0.17 M3 Rp 171,000.00 Rp 29,326.50
4 Pek. Urugan Pasir Bawah Pondasi Batu Kali t=5cm 2.66 M3 Rp 171,000.00 Rp 454,834.69
5 Pek. Urugan Pasir Bawah Lantai t=5cm 8.11 M3 Rp 171,000.00 Rp 1,386,155.84
6 Pek. Urugan Kembali Tanah Bekas Galian Pondasi Foot Plat 2.29 M3 Rp 45,000.00 Rp 102,900.00
7 Pek. Urugan Kembali Tanah Bekas Galian Pondasi Batu Kali 9.31 M3 Rp 45,000.00 Rp 418,926.69
8 Pek. Urugan Tanah dalam pondasi ( Sirtu Padat) 19.49 M3 Rp 166,500.00 Rp 3,244,429.80

B. Pekerjaan Rabat Beton & Pondasi Rp 40,190,059.62


1 Pek. Coor Lantai Kerja t=5cm Pondasi Foot Plat 0.196 M3 Rp 886,268.13 Rp 173,708.55
2 Pek. Rabat Beton Bawah Lantai t=5cm 4.32 M3 Rp 907,548.13 Rp 3,917,283.78
3 Pek. Pondasi Foot Plat P.K1
- Pile Cap Beton K175 0.44 M3 Rp 1,039,171.88 Rp 458,274.80
- Pedestal 15x20 Beton K175 0.44 M3 Rp 1,039,171.88 Rp 458,274.80
- Pembesian Pile Cap 46.32 Kg Rp 15,283.72 Rp 707,873.29
- Pembesian Pedestal 96.54 Kg Rp 15,283.72 Rp 1,475,497.66
- Bekisting Pile Cap 1.26 M2 Rp 170,612.50 Rp 214,971.75
- Bekisting Pedestal 5.15 M2 Rp 170,612.50 Rp 877,801.31
4 Pek. Pondasi Foot Plat P.K2
- Pile Cap Beton K175 0.15 M3 Rp 1,039,171.88 Rp 152,758.27
- Pedestal 20x30 Beton K175 0.29 M3 Rp 1,039,171.88 Rp 305,516.53
- Pembesian Pile Cap 15.44 Kg Rp 15,283.72 Rp 235,957.76
- Pembesian Pedestal 36.20 Kg Rp 15,283.72 Rp 553,342.07
- Bekisting Pile Cap 0.42 M2 Rp 170,612.50 Rp 71,657.25
- Bekisting Pedestal 2.45 M2 Rp 170,612.50 Rp 418,000.63
5 Pek. Pasangan Batu Kosong 7.98 M3 Rp 490,080.00 Rp 3,910,620.80
6 Pek. Pasangan Batu Kali 31.46 M3 Rp 834,780.00 Rp 26,258,520.38

C . Pekerjaan Sloof,Kolom, & Balok Rp 51,446,474.85


1 Pekerjaan Sloof 15x20
- Beton K.175 1.99 M3 Rp 1,039,171.88 Rp 2,067,199.67
- Pembesian 368.29 Kg Rp 15,283.72 Rp 5,628,850.71
- Bekisting Sloof ( 2 x Pakai ) 18.24 M2 Rp 180,175.00 Rp 3,285,496.53
2 Pekerjaan Kolom KP 11x11
- Beton K.175 0.71 M3 Rp 1,039,171.88 Rp 735,829.29
- Pembesian 205.46 Kg Rp 15,283.72 Rp 3,140,127.44
- Bekisting Kolom KP ( 2 x Pakai ) 6.44 M2 Rp 327,112.50 Rp 2,105,688.59
3 Pekerjaan Kolom K1 15x20
- Beton K.175 0.96 M3 Rp 1,039,171.88 Rp 993,552.23
- Pembesian 186.11 Kg Rp 15,283.72 Rp 2,844,445.54
- Bekisting Kolom K1 ( 2 x Pakai ) 11.15 M2 Rp 327,112.50 Rp 3,648,776.38
4 Pekerjaan Kolom K2 20x30
- Beton K.175 0.68 M3 Rp 1,039,171.88 Rp 702,064.52
- Pembesian 97.48 Kg Rp 15,283.72 Rp 1,489,893.30
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT.
(Rp) (Rp)
A B C D E F
- Bekisting Kolom K2 ( 2 x Pakai ) 5.63 M2 Rp 327,112.50 Rp 1,841,643.38
5 Pekerjaan Balok Latei 11x11 Ev +3.15
- Beton K.175 0.36 M3 Rp 1,039,171.88 Rp 369,790.68
- Pembesian 144.51 Kg Rp 15,283.72 Rp 2,208,707.41
- Bekisting Balok Latei ( 2 x Pakai ) 3.24 M2 Rp 337,237.50 Rp 1,090,967.36
6 Pekerjaan Balok 11x20 Ev +450
- Beton K.175 1.33 M3 Rp 1,039,171.88 Rp 1,383,348.09
- Pembesian 328.17 Kg Rp 15,283.72 Rp 5,015,593.18
- Bekisting Balok ( 2 x Pakai ) 15.43 M2 Rp 337,237.50 Rp 5,203,522.69
7 Pekerjaan Balok 11x20 Ev +485
- Beton K.175 0.13 M3 Rp 1,039,171.88 Rp 130,312.15
- Pembesian 33.25 Kg Rp 15,283.72 Rp 508,237.50
- Bekisting Balok ( 2 x Pakai ) 1.45 M2 Rp 337,237.50 Rp 490,174.71
8 Pekerjaan Balok 11x20 Ev +500
- Beton K.175 0.13 M3 Rp 1,039,171.88 Rp 132,598.33
- Pembesian 33.40 Kg Rp 15,283.72 Rp 510,488.83
- Bekisting Balok ( 2 x Pakai ) 1.48 M2 Rp 337,237.50 Rp 498,774.26
9 Pekerjaan Ring Balok 11x20 Ev +563
- Beton K.175 0.62 M3 Rp 1,039,171.88 Rp 648,131.50
- Pembesian 152.73 Kg Rp 15,283.72 Rp 2,334,286.37
- Bekisting Balok ( 2 x Pakai ) 7.23 M2 Rp 337,237.50 Rp 2,437,974.20

D. Pekerjaan Atap Rp 30,756,628.74


1 Pek. Rangka Atap Baja Ringan 85.44 M2 Rp 169,500.27 Rp 14,482,807.29
2 Pek. Penutup Atap Spandek 85.44 M2 Rp 162,112.50 Rp 13,851,565.58
3 Pek. Nok dan Jurai Atap Spandek 29.63 M1 Rp 32,862.50 Rp 973,715.88
4 Pek. Pemasangan lisplank 13.40 M1 Rp 108,100.00 Rp 1,448,540.00

3.2 PEKERJAAN ARSITEKTUR Rp 217,422,266.44

A. Pekerjaan Dinding Rp 86,319,809.11


1 Pek. Pemasangan Dinding 1/2 Bata Merah 1:5 233.43 M2 Rp 132,735.00 Rp 30,984,938.71
2 Pek. Pemasangan Dinding trasram 1/2 Bata Merah 1:3 8.10 M2 Rp 63,882.00 Rp 517,444.20
3 Pek. Plesteran Dinding,Kolom,Balok & Sloof 525.35 M2 Rp 59,868.00 Rp 31,451,627.46
4 Pek. Plesteran Dinding Trasram 1:3 16.20 M2 Rp 63,882.00 Rp 1,034,888.40
5 Pek. Plesteran Kaki Pondasi Batu Kali 1:3 20.04 M2 Rp 63,882.00 Rp 1,280,120.54
6 Pek. Acian 561.59 M2 Rp 37,484.38 Rp 21,050,789.81

B. Pekerjaan Penutup Lantai & Dinding Rp 27,767,962.09


1 Pek. Pemasangan Granit 60x60cm 87.36 M2 Rp 287,264.79 Rp 25,096,815.53
2 Pek.keramik dinding Km 20x40 8.06 M2 Rp 331,305.00 Rp 2,671,146.56

C. Pekerjaan Kusen Pintu/Jendela + Assesories Rp 33,932,918.81


1 2 Unit Kusen Pintu Type P1
- Pek. Pemasangan Kusen aluminium Type P1 19.600 M1 Rp 79,902.50 Rp 1,566,089.00
- Pek. Pemasangan daun pintu multiplaks Type P1 4.17 M2 Rp 827,306.61 Rp 3,445,732.04
- Pek. Pemasangan Kaca 5 mm 2.16 M2 Rp 215,146.88 Rp 464,071.81
- Pek. Pemasangan handel pintu tanam 60 cm Ex dekson 4.00 Set Rp 205,000.00 Rp 820,000.00
- Pek. Pemasangan Kunci Pintu 2 Slaag Ex dekson 2.00 Bh Rp 352,150.00 Rp 704,300.00
- Pek. Pemasangan engsel Pintu 6.00 Bh Rp 67,350.00 Rp 404,100.00

2 3 Unit Kusen Pintu Type P2


- Pek. Pemasangan Kusen aluminium Type P2 23.400 M1 Rp 79,902.50 Rp 1,869,718.50
- Pek. Pemasangan daun pintu multiplaks Type P2 6.62 M2 Rp 827,306.61 Rp 5,472,633.24
- Pek. Pemasangan Kaca 5 mm 1.72 M2 Rp 215,146.88 Rp 369,837.48
- Pek. Pemasangan handel pintu tanam 60 cm Ex dekson 3.00 Set Rp 205,000.00 Rp 615,000.00
- Pek. Pemasangan Kunci Pintu 2 Slaag Ex dekson 3.00 Bh Rp 352,150.00 Rp 1,056,450.00
- Pek. Pemasangan engsel Pintu 9.00 Bh Rp 67,350.00 Rp 606,150.00

3 1 Unit Kusen Pintu Type P3


- Pek. Pemasangan Kusen aluminium Type P3 5.700 M1 Rp 79,902.50 Rp 455,444.25
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT.
(Rp) (Rp)
A B C D E F
- Pek. Pemasangan Slimar daun pintu aluminium Type P3 5.98 M1 Rp 48,140.00 Rp 287,877.20
- Pek. Pemasangan Strip Slimar daun Pintu aluminium Type P3 6.48 M1 Rp 48,140.00 Rp 311,947.20
- Pek. Pemasangan sirip aluminium 4.86 M1 Rp 48,140.00 Rp 233,960.40
- Pek. Pemasangan handel bulat Ex. Dekson 1.00 Set Rp 205,000.00 Rp 205,000.00
- Pek. Pemasangan Kunci Pintu 2 Slaag Ex dekson 1.00 Bh Rp 352,150.00 Rp 352,150.00
- Pek. Pemasangan engsel Pintu 3.00 Bh Rp 67,350.00 Rp 202,050.00

4 5 Unit Kusen Jendela Type J


- Pek. Pemasangan Kusen aluminium Type J 69.000 M1 Rp 79,902.50 Rp 5,513,272.50
- Pek. Pemasangan Slimar daun Jendela Type J 69.70 M1 Rp 48,140.00 Rp 3,355,358.00
- Pek. Pemasangan Kaca 5 mm 12.10 M2 Rp 215,146.88 Rp 2,603,277.19
- Pek. Pemasangan handel Jendela Type J 10.00 Set Rp 53,125.00 Rp 531,250.00
- Pek. Pemasangan Grendel Jendela 10.00 Bh Rp 39,225.00 Rp 392,250.00
- Pek. Pemasangan engsel Jendela 20.00 Bh Rp 48,650.00 Rp 973,000.00
- Pek. Pemasangan Hak angin Lipat 20.00 Bh Rp 56,100.00 Rp 1,122,000.00

D. Pekerjaan Plafond Rp 15,835,899.83


1 Pek. Rangka Plafond Hollow 40x40mm 80.81 M2 Rp 143,500.00 Rp 11,595,767.91
2 Pek. Plafond Gypsum Board 9mm 80.81 M2 Rp 52,472.50 Rp 4,240,131.93

E. Pekerjaan Finishing & Pengecetan Rp 25,742,379.05


1 Pek. Pengecatan Dinding 561.59 M2 Rp 40,072.50 Rp 22,504,250.76
2 Pek. Pengecatan Plafond Gypsum 80.81 M2 Rp 40,072.50 Rp 3,238,128.29

F. Pekerjaan Instalasi Air Bersih & Kotor + Sanitary Rp 6,541,428.74


1 Pipa Air Bersih
- Pek. PVC dia 1/2 inc (AW) Include Accessories 11.19 M1 Rp 23,941.88 Rp 267,900.00
2 Pipa Air Kotor
- Pek. PVC dia 2 inc (AW) Include Accessories 8.63 M1 Rp 48,214.69 Rp 416,150.61
- Pek. PVC dia 4 inc (AW) Include Accessories 10.00 M1 Rp 175,407.19 Rp 1,754,071.88
3 Pek. Pemasangan Kran air Bersih 2.00 Bh Rp 133,821.88 Rp 267,643.75
4 Pek. Pemasangan Floor drain 1.00 Bh Rp 49,775.00 Rp 49,775.00
4 Pek. Pemasangan wastafel 1.00 Bh Rp 2,618,075.00 Rp 2,618,075.00
5 Pek. Pemasangan Kloset duduk 1.00 Set Rp 1,167,812.50 Rp 1,167,812.50

G. Pekerjaan Elektrikal Rp 5,283,825.00


1 Pek. Pemasangan Box MCB 3 Grup Include 2 Bh MCB 1.00 Unit Rp 1,201,500.00 Rp 1,201,500.00
2 Pek. Instalasi 1 Titik Lampu 8.00 Titik Rp 337,743.75 Rp 2,701,950.00
3 Pek. Pemasangan 1 bh Lampu Downligt 18 Watt 8.00 Bh Rp 133,875.00 Rp 1,071,000.00
4 Pek. Pemasangan 1 Bh Lampu Spot 12 watt 2.00 Bh Rp 151,875.00
5 Pek. Instalasi Stop Kontak 3.00 Bh Rp 33,750.00 Rp 101,250.00
6 Pek. Instalasi Saklar Tunggal 5.00 Bh Rp 33,750.00 Rp 168,750.00
7 Pek. Instalasi Saklar Ganda 1.00 Bh Rp 39,375.00 Rp 39,375.00

H. Pekerjaan Lain-Lain Rp 15,998,043.80


1 Pek. Rabat Beton Keliling Bangunan & Saluran Keliling Setempat
- Pek. Galian Saluran Keliling 12.15 M3 Rp 67,500.00
- Pek. Urugan Pasir Bawah Saluran Keliling 0.997 M3 Rp 171,000.00
- Pek. Pasangan Batu Kali Alas Saluran Keliling 0.997 M3 Rp 834,780.00
- Pek. Rolag Bata Pasangan Dinding Saluran Keliling 44.336 M2 Rp 132,735.00
- Pek. Plesteran dinding saluran Keliling 44.336 M2 Rp 63,882.00
- Pek. Acian dinding saluran keliling 44.336 M2 Rp 37,484.38
- Pek. Urugan Pasir Bawah Rabat Keliling 1.56 M3 Rp 133,821.88
- Pek. Rabat Beton Keliling 3.39 M3 Rp 907,548.13
2 Pek. Pasangan Tangga Luar
- Pek. Galian Tanah Tangga Luar 0.54 M3 Rp 67,500.00 Rp 36,738.36
- Pek. Pasangan Rolag 1/2 Bata dinding tangga 27.63 M2 Rp 140,049.38 Rp 3,869,537.34
- Pek. Urugan Tanah Bawah Lantai Pijakan Tangga 2.07 M3 Rp 166,500.00 Rp 345,040.01
- Pek. Urugan Pasir Bawah Lantai Pijakan Tangga 0.65 M3 Rp 171,000.00 Rp 111,177.36
- Pek. Rabat Beton Pijakan Tangga 0.77 M3 Rp 907,548.13 Rp 702,442.25
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT.
(Rp) (Rp)
A B C D E F
- Pek. Plesteran Tangga 24.81 M2 Rp 63,882.00 Rp 1,584,705.44
- Pek. Acian Tangga 24.81 M2 Rp 37,484.38 Rp 929,865.89
3 Pek. 1 Unit septitank & resapan
- Pek.Galian Septitank & Resapan 8.48 M3 Rp 81,000.00 Rp 687,197.93
- Pek. Urugan Pasir Bawah septitank 0.31 M3 Rp 171,000.00 Rp 52,326.00
- Pek.Pengecoran lantai septitank 0.38 M3 Rp 886,268.13 Rp 338,997.56
- Pek.Sloof 11x11 septitank
Beton K175 0.15 M3 Rp 1,039,171.88 Rp 151,013.50
Pembesian 46.55 Kg Rp 15,283.72 Rp 711,507.38
Bekisting 0.66 M2 Rp 180,175.00 Rp 119,014.60
- Pek.Kolom 11x11 septitank
Beton K175 0.12 M3 Rp 1,039,171.88 Rp 120,710.21
Pembesian 38.20 Kg Rp 15,283.72 Rp 583,858.03
Bekisting 1.06 M2 Rp 327,112.50 Rp 345,430.80
- Pek.Balok 11x11 septitank
Beton K175 0.15 M3 Rp 1,039,171.88 Rp 151,013.50
Pembesian 46.55 Kg Rp 15,283.72 Rp 711,507.38
Bekisting 1.98 M2 Rp 337,237.50 Rp 668,286.69
- Pek.Plat Penutup Septitank
Beton K175 0.43 M3 Rp 1,039,171.88 Rp 444,245.98
Pembesian 30.64 Kg Rp 15,283.72 Rp 468,316.62
Bekisting 2.57 M2 Rp 337,237.50 Rp 867,543.47
- Pek.Penutup Mainhole septitank 50x50
Beton K175 0.02 M3 Rp 1,039,171.88 Rp 20,783.44
Pembesian 3.77 Kg Rp 15,283.72 Rp 57,694.50
Bekisting 0.21 M2 Rp 337,237.50 Rp 69,133.69
- Pek.dinding trasram septitank 5.06 M2 Rp 140,049.38 Rp 708,817.90
- Pek. Plesteran dinding septitank 5.06 M2 Rp 63,882.00 Rp 323,319.58
- Pek.Acian septitank 5.06 M2 Rp 37,484.38 Rp 189,715.92
- Pek. Urugan tanah atas septitank 0.84 M3 Rp 45,000.00 Rp 37,867.50
- Pek.Pasangan Batu karang resapan 1.70 M3 Rp 274,800.00 Rp 467,160.00
- Pek. Urugan lapisan ijuk resapan 0.10 M3 Rp 114,750.00 Rp 11,475.00
- Pek.Urugan Sirtu resapan 0.40 M3 Rp 166,500.00 Rp 66,600.00
- Pek.Urugan kembali Tanah top resapan 1.00 M3 Rp 45,000.00 Rp 45,000.00
RENCANA PENGGUNAAN DANA (RPD)
DANA ALOKASI KHUSUS (DAK) FISIK PENUGASAN SMK
APD TAHUN 2022
ENGINEERING ESTIMATE (EE)
PEKERJAAN : SMKN 1 KASIMBAR
LOKASI : Kab. Parigi Moutong
TH. ANGGARAN : SULAWESI TENGAH

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT.
(Rp) (Rp)
A B C D E F
IV RUANG KELAS

4.1 PEKERJAAN STRUKTUR Rp 226,870,439.73


A. Pekerjaan Tanah dan Pasir Rp 15,552,022.68
1 Pek. Galiaan Tanah Pondasi Foot Plat 7.84 M3 Rp 81,000.00 Rp 635,040.00
2 Pek. Galiaan Tanah Pondasi Batu Kali 43.13 M3 Rp 67,500.00 Rp 2,911,327.89
3 Pek. Urugan Pasir Bawah Pondasi Foot Plat t=5cm 0.20 M3 Rp 171,000.00 Rp 33,516.00
4 Pek. Urugan Pasir Bawah Pondasi Batu Kali t=5cm 3.08 M3 Rp 171,000.00 Rp 526,291.23
5 Pek. Urugan Pasir Bawah Lantai t=5cm 8.23 M3 Rp 171,000.00 Rp 1,406,923.88
6 Pek. Urugan Kembali Tanah Bekas Galian Pondasi Foot Plat 2.61 M3 Rp 45,000.00 Rp 117,600.00
7 Pek. Urugan Kembali Tanah Bekas Galian Pondasi Batu Kali 10.78 M3 Rp 45,000.00 Rp 485,221.31
8 Pek. Urugan Tanah dalam pondasi ( Sirtu Padat) 56.67 M3 Rp 166,500.00 Rp 9,436,102.37

B. Pekerjaan Rabat Beton & Pondasi Rp 54,043,091.40


1 Pek. Coor Lantai Kerja t=5cm Pondasi Foot Plat 0.3185 M3 Rp 886,268.13 Rp 282,276.40
2 Pek. Rabat Beton Bawah Lantai t=5cm 9.11 M3 Rp 907,548.13 Rp 8,271,223.45
3 Pek. Pondasi Foot Plat P.K1
- Pile Cap Beton K175 0.515 M3 Rp 1,039,171.88 Rp 534,653.93
- Pedestal 15x20 Beton K175 0.515 M3 Rp 1,039,171.88 Rp 534,653.93
- Pembesian Pile Cap 54.03 Kg Rp 15,283.72 Rp 825,852.17
- Pembesian Pedestal 112.63 Kg Rp 15,283.72 Rp 1,721,413.93
- Bekisting Pile Cap 1.47 M2 Rp 170,612.50 Rp 250,800.38
- Bekisting Pedestal 6.00 M2 Rp 170,612.50 Rp 1,024,101.53
4 Pek. Pondasi Foot Plat P.K2
- Pile Cap Beton K175 0.44 M3 Rp 1,039,171.88 Rp 458,274.80
- Pedestal 20x30 Beton K175 0.88 M3 Rp 1,039,171.88 Rp 916,549.59
- Pembesian Pile Cap 46.32 Kg Rp 15,283.72 Rp 707,873.29
- Pembesian Pedestal 144.82 Kg Rp 15,283.72 Rp 2,213,368.30
- Bekisting Pile Cap 1.26 M2 Rp 170,612.50 Rp 214,971.75
- Bekisting Pedestal 7.35 M2 Rp 170,612.50 Rp 1,254,001.88
5 Pek. Pasangan Batu Kosong 9.24 M3 Rp 490,080.00 Rp 4,529,471.65
6 Pek. Pasangan Batu Kali 36.30 M3 Rp 834,780.00 Rp 30,303,604.43

C . Pekerjaan Sloof,Kolom, & Balok Rp 82,010,573.81


1 Pekerjaan Sloof 15x20
- Beton K.175 2.62 M3 Rp 1,039,171.88 Rp 2,723,149.90
- Pembesian 485.53 Kg Rp 15,283.72 Rp 7,420,722.84
- Bekisting Sloof ( 2 x Pakai ) 24.02 M2 Rp 180,175.00 Rp 4,328,028.72
2 Pekerjaan Kolom KP 11x11
- Beton K.175 0.57 M3 Rp 1,039,171.88 Rp 591,731.48
- Pembesian 163.69 Kg Rp 15,283.72 Rp 2,501,812.38
- Bekisting Kolom KP ( 2 x Pakai ) 5.18 M2 Rp 327,112.50 Rp 1,693,330.57
3 Pekerjaan Kolom K1 15x20
- Beton K.175 1.61 M3 Rp 1,039,171.88 Rp 1,673,482.39
- Pembesian 313.13 Kg Rp 15,283.72 Rp 4,785,810.69
- Bekisting Kolom K1 ( 2 x Pakai ) 18.79 M2 Rp 327,112.50 Rp 6,145,789.65
4 Pekerjaan Kolom K2 20x30
- Beton K.175 1.91 M3 Rp 1,039,171.88 Rp 1,982,739.94
- Pembesian 277.45 Kg Rp 15,283.72 Rp 4,240,466.46
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT.
(Rp) (Rp)
A B C D E F
- Bekisting Kolom K2 ( 2RUANG
x Pakai ) KELAS 15.90 M2 Rp 327,112.50 Rp 5,201,088.75
5 Pekerjaan Balok Latei 11x11 Ev +3.15
- Beton K.175 0.41 M3 Rp 1,039,171.88 Rp 430,030.11
- Pembesian 309.39 Kg Rp 15,283.72 Rp 4,728,634.98
- Bekisting Balok Latei ( 2 x Pakai ) 3.76 M2 Rp 337,237.50 Rp 1,268,687.48
6 Pekerjaan Balok 11x20 Ev +4.50
- Beton K.175 1.92 M3 Rp 1,039,171.88 Rp 1,991,261.15
- Pembesian 411.87 Kg Rp 15,283.72 Rp 6,294,841.29
- Bekisting Balok ( 2 x Pakai ) 22.21 M2 Rp 337,237.50 Rp 7,490,213.49
7 Pekerjaan Balok 11x20 Ev +5.08
- Beton K.175 0.13 M3 Rp 1,039,171.88 Rp 130,312.15
- Pembesian 33.25 Kg Rp 15,283.72 Rp 508,237.50
- Bekisting Balok ( 2 x Pakai ) 1.45 M2 Rp 337,237.50 Rp 490,174.71
8 Pekerjaan Balok 11x20 Ev +5.23
- Beton K.175 0.13 M3 Rp 1,039,171.88 Rp 132,598.33
- Pembesian 33.40 Kg Rp 15,283.72 Rp 510,488.83
- Bekisting Balok ( 2 x Pakai ) 1.48 M2 Rp 337,237.50 Rp 498,774.26
9 Pekerjaan Balok 11x11 Ev +5.55
- Beton K.175 0.07 M3 Rp 1,039,171.88 Rp 69,156.89
- Pembesian 33.91 Kg Rp 15,283.72 Rp 518,207.67
- Bekisting Balok ( 2 x Pakai ) 0.61 M2 Rp 337,237.50 Rp 204,028.69
10 Pekerjaan Ring Balok 11x20 Ev +5.85
- Beton K.175 0.88 M3 Rp 1,039,171.88 Rp 914,471.25
- Pembesian 334.87 Kg Rp 15,283.72 Rp 5,118,004.32
- Bekisting Balok ( 2 x Pakai ) 10.20 M2 Rp 337,237.50 Rp 3,439,822.50
11 Pekerjaan talang beton
- Beton kedap air 0.62 M3 Rp 943,225.90 Rp 580,083.93
- Pembesian 116.90 Kg Rp 15,283.72 Rp 1,786,662.23
- Bekisting talang beton ( 2 x Pakai ) 4.80 M2 Rp 337,237.50 Rp 1,617,728.29

D. Pekerjaan Atap Rp 75,264,751.85


1 Pek. Rangka Atap Baja Ringan 214.56 M2 Rp 169,500.27 Rp 36,368,801.57
2 Pek. Penutup Atap Spandek 214.56 M2 Rp 162,112.50 Rp 34,783,645.87
3 Pek. Nok dan Jurai Atap Spandek 60.66 M1 Rp 32,862.50 Rp 1,993,544.41
4 Pek. Pemasangan lisplank 19.60 M1 Rp 108,100.00 Rp 2,118,760.00

4.2 PEKERJAAN ARSITEKTUR Rp 258,187,264.80

A. Pekerjaan Dinding Rp 90,853,835.92


1 Pek. Pemasangan Dinding 1/2 Bata Merah 1:5 226.53 M2 Rp 132,735.00 Rp 30,067,960.47
2 Pek. Plesteran Dinding,Kolom,Balok & Sloof 605.45 M2 Rp 59,868.00 Rp 36,247,121.31
3 Pek. Plesteran Kaki Pondasi Batu Kali 1:3 18.19 M2 Rp 63,882.00 Rp 1,161,988.03
4 Pek. Acian 623.64 M2 Rp 37,484.38 Rp 23,376,766.12

B. Pekerjaan Penutup Lantai & Dinding Rp 48,200,806.24


1 Pek. Pemasangan Granit 60x60cm 167.79 M2 Rp 287,264.79 Rp 48,200,806.24

C. Pekerjaan Kusen Pintu/Jendela + Assesories Rp 36,385,108.23


1 2 Unit Kusen Pintu Type P1
- Pek. Pemasangan Kusen aluminium Type P1 19.600 M1 Rp 79,902.50 Rp 1,566,089.00
- Pek. Pemasangan daun pintu multiplaks Type P1 4.17 M2 Rp 827,306.61 Rp 3,445,732.04
- Pek. Pemasangan Kaca 5 mm 2.16 M2 Rp 215,146.88 Rp 464,071.81
- Pek. Pemasangan handel pintu tanam 60 cm Ex dekson 4.00 Set Rp 205,000.00 Rp 820,000.00
- Pek. Pemasangan Kunci Pintu 2 Slaag Ex dekson 2.00 Bh Rp 352,150.00 Rp 704,300.00
- Pek. Pemasangan engsel Pintu 6.00 Bh Rp 67,350.00 Rp 404,100.00

2 10 Unit Kusen Jendela Type J


- Pek. Pemasangan Kusen aluminium Type J 138.000 M1 Rp 79,902.50 Rp 11,026,545.00
- Pek. Pemasangan Slimar daun Jendela Type J 139.40 M1 Rp 48,140.00 Rp 6,710,716.00
- Pek. Pemasangan Kaca 5 mm 24.20 M2 Rp 215,146.88 Rp 5,206,554.38
- Pek. Pemasangan handel Jendela Type J 20.00 Set Rp 53,125.00 Rp 1,062,500.00
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT.
(Rp) (Rp)
A B C D E F
RUANG
- Pek. Pemasangan Grendel KELAS
Jendela 20.00 Bh Rp 39,225.00 Rp 784,500.00
- Pek. Pemasangan engsel Jendela 40.00 Bh Rp 48,650.00 Rp 1,946,000.00
- Pek. Pemasangan Hak angin Lipat 40.00 Bh Rp 56,100.00 Rp 2,244,000.00

D. Pekerjaan Plafond Rp 35,866,641.98


1 Pek. Rangka Plafond Hollow 40x40mm 183.02 M2 Rp 143,500.00 Rp 26,263,190.63
2 Pek. Plafond Gypsum Board 9mm 183.02 M2 Rp 52,472.50 Rp 9,603,451.36

E. Pekerjaan Finishing & Pengecetan Rp 31,924,118.98


1 Pek. Pengecatan Dinding 613.64 M2 Rp 40,072.50 Rp 24,590,100.12
2 Pek. Pengecatan Plafond Gypsum 183.02 M2 Rp 40,072.50 Rp 7,334,018.86

F. Pekerjaan Instalasi Air Bersih & Kotor + Sanitary Rp 7,094,051.32


1 Pipa Air Bersih
- Pek. PVC dia 1/2 inc (AW) Include Accessories 30.49 M1 Rp 23,941.88 Rp 730,097.90
2 Pipa Air Kotor
- Pek. PVC dia 2 inc (AW) Include Accessories 17.84 M1 Rp 48,214.69 Rp 860,159.67
3 Pek. Pemasangan Kran air Bersih 2.00 Bh Rp 133,821.88 Rp 267,643.75
4 Pek. Pemasangan wastafel 2.00 Bh Rp 2,618,075.00 Rp 5,236,150.00

G. Pekerjaan Elektrikal Rp 5,783,568.75


1 Pek. Pemasangan Box MCB 4 Grup Include 2 Bh MCB 1.00 Unit Rp 1,201,500.00 Rp 1,201,500.00
2 Pek. Instalasi 1 Titik Lampu 9.00 Titik Rp 337,743.75 Rp 3,039,693.75
4 Pek. Pemasangan 1 bh Lampu Downligt 18 Watt 9.00 Bh Rp 133,875.00 Rp 1,204,875.00
3 Pek. Pemasangan 1 Bh Lampu Spot 12 watt Bh Rp 151,875.00 Rp -
5 Pek. Instalasi Stop Kontak 6.00 Bh Rp 33,750.00 Rp 202,500.00
6 Pek. Instalasi Saklar Tunggal 4.00 Bh Rp 33,750.00 Rp 135,000.00
7 Pek. Instalasi Saklar Ganda Bh Rp 39,375.00 Rp -

H. Pekerjaan Lain-Lain Rp 2,079,133.37


1 Pek. Rabat Beton Keliling Bangunan & Saluran Keliling Setempat
- Pek. Galian Saluran Keliling 15.29 M3 Rp 67,500.00
- Pek. Urugan Pasir Bawah Saluran Keliling 1.25 M3 Rp 171,000.00
- Pek. Pasangan Batu Kali Alas Saluran Keliling 1.25 M3 Rp 834,780.00
- Pek. Rolag Bata Pasangan Dinding Saluran Keliling 59.048 M2 Rp 132,735.00
- Pek. Plesteran dinding saluran Keliling 59.048 M2 Rp 63,882.00
- Pek. Acian dinding saluran keliling 59.048 M2 Rp 37,484.38
- Pek. Urugan Pasir Bawah Rabat Keliling 2.07 M3 Rp 171,000.00
- Pek. Rabat Beton Keliling 4.50 M3 Rp 907,548.13
2 Pek. Pasangan Tangga Luar
- Pek. Galian Tanah Tangga Luar 0.12 M3 Rp 67,500.00 Rp 7,880.13
- Pek. Pasangan Rolag 1/2 Bata dinding tangga 4.06 M2 Rp 140,049.38 Rp 568,309.57
- Pek. Urugan Tanah Bawah Lantai Pijakan Tangga 0.41 M3 Rp 166,500.00 Rp 68,766.17
- Pek. Urugan Pasir Bawah Lantai Pijakan Tangga 0.36 M3 Rp 171,000.00 Rp 62,021.70
- Pek. Rabat Beton Pijakan Tangga 0.18 M3 Rp 907,548.13 Rp 159,274.70
- Pek. Plesteran Tangga 11.97 M2 Rp 63,882.00 Rp 764,368.57
- Pek. Acian Tangga 11.97 M2 Rp 37,484.38 Rp 448,512.54

V PEKERJAAN AKHIR

5.1 PEMBERSIHAN & PELAPORAN Rp 6,500,000.00

A. Pek. Pembersihan Akhir 1.00 Ls Rp 2,500,000.00 Rp 2,500,000.00


B. As Build Drawing 1.00 Ls Rp 4,000,000.00 Rp 4,000,000.00
HARGA SATUAN UPAH, BAHAN & PERALATAN
PEKERJAAN : SMKN 1 KASIMBAR
LOKASI : Kab. Parigi Moutong
TH. ANGGARAN : SULAWESI TENGAH

NO URAIAN SATUAN HARGA KETERANGAN

A. UPAH 1 Hari Kerja = 7 Jam


1 Pekerja Org/Hari Rp 90,000.00 12,857.14 / Jam
2 Tukang Batu / Kayu / Besi / Cat Org/Hari Rp 125,000.00 17,857.14 / Jam
3 Kepala Tukang Org/Hari Rp 150,000.00 21,428.57 / Jam
4 Mandor Org/Hari - / Jam

B. BAHAN & MATERIAL


I TANAH DAN PASIR
1 Pasir urug M3 Rp 120,000.00 Rp 85.71 / Kg
2 Pasir Pasang M3 Rp 120,000.00 Rp 85.71 / Kg
3 Pasir beton/Cor M3 Rp 120,000.00 Rp 80.00 / Kg
4 Sirtu M3 Rp 120,000.00
5 Pasir Plester M3 Rp 175,000.00
6 Tanah urug (biasa) M3 Rp 120,000.00

II KERIKIL
1 Kerikil split M3 Rp 421,875.00 Rp 234.38
2 Kerikil sungai/Koral M3 Rp 200,000.00 Rp 111.11

III BATUBATUAN
1 Batu kali M3 Rp 250,000.00
2 Batu karang M3 Rp 125,000.00

IV BATU CETAK
1 Batu bata Bh Rp 1,000.00
2 Roster Beton 20x20 Bh Rp 30,000.00
3 Batu GRC Krawang tempel M2 Rp 225,000.00
4 Batu GRC Krawang bolong M2 Rp 225,000.00

V SEMEN
1 Semen Tonasa 50Kg Zak Rp 84,375.00 Rp 1,687.50 / Kg
2 Semen Putih Kg Rp 50,625.00
3 Semen warna Kg Rp 39,375.00
4 Water Proofing No Drop 1 Kaleng/5Kg Klg Rp -
5 Strorox 100 Kg Rp 25,000.00

VI BAHAN ATAP
1 Seng plat/Seng Talang L.45 Cm M1 Rp 28,125.00
2 Atap metal spandek 0.25 mm Ex Kencana L.80 Cm M2 Rp 65,250.00
3 Genteng metal 0.80x0.77 T.0.25mm Sakura roof Lbr Rp 56,250.00
4 Bumbungan genteng metal p.100cm Bh Rp 30,375.00
5 Bumbungan metal spandek P.3M/Lbr Lbr Rp 84,375.00
6 Lisplank Calsiboard L.20cm P.4 m Lbr Rp 78,750.00
7 Main Truss (C 75, 0.75) Ex kencana 1 btg. 6 m Btg Rp 151,875.00 Rp 10,910.56 / Kg
8 Reng R30,45 Ex kencana 1 btg. 6 m Btg Rp 67,500.00 Rp 11,250.00 / M
NO URAIAN SATUAN HARGA KETERANGAN

9 Screw Truss Dos Rp 225,000.00 Rp 225.00 / Bh


10 Screw Reng Dos Rp 253,125.00 Rp 253.13 / Bh
11 Screw roofing Dos Rp 241,875.00 Rp 241.88 / Bh
12 Dynabolt Bh Rp 16,875.00

VII BAHAN KAYU


1 Kayu Papan Kelas I Ex kala kala M3 Rp 4,500,000.00
2 Kayu Balok Kelas I Ex kala kala M3 Rp 4,500,000.00
3 Kayu Papan Kelas II Ex Palapi M3 Rp 3,375,000.00
4 Kayu Balok Kelas II Ex Palapi M3 Rp 3,375,000.00
5 Kayu Papan Kelas III Ex durian M3 Rp 2,475,000.00
6 Kayu Balok Kelas III Ex durian M3 Rp 2,475,000.00
7 Kayu terentang Kelas IV Peruntukan maal M3 Rp 1,912,500.00
8 Dolken ( tiang perancah) Btg Rp 13,500.00
9 Minyak bekisting Ltr Rp 24,750.00

VIII BAHAN LANTAI / TEGEL KERAMIK


1 Tegel Keramik 20x20 cm (1 dos. 25 Bh = 1 m2) Dos Rp 78,750.00
2 Tegel Keramik 20x20 cm anti slip (1 dos. 25 Bh=1 m2) Dos Rp 90,000.00
3 Tegel Keramik 20x25 cm (1 dos. 20 Bh=1 m2) Dos Rp 78,750.00
4 Tegel Keramik 25x25 cm (1 dos. 16 Bh=1 m2) Dos Rp 78,750.00
5 Tegel Keramik 25x25 cm anti slip (1 dos. 16 Bh=1 m2) Dos Rp 90,000.00
6 Tegel Keramik 20x40 cm (1 dos = 1 m2) Dos Rp 67,500.00
7 Tegel Keramik 30x60 cm (1 dos= 1 m2) Dos Rp 112,500.00
8 Plint Granit 10x60 Bh Rp 33,750.00
9 Granit 60x60 cm (1 dos = 3 Bh) Dos Rp 157,500.00 Rp 52,500.00 / Bh
10 Granit 60x60 cm (1 dos = 4 Bh) Dos Rp 213,750.00 Rp 71,250.00
11 Granit 40x40 cm Dos Rp 135,000.00 Rp 22,500.00
12 Granit 20x40 cm (1 dos = 12 Bh) Dos Rp 112,500.00 Rp 9,375.00

IX BAHAN BESI & ALUMINIUM


1 Besi Polos Ø 6 mm SNI Btg Rp 42,750.00
2 Besi Polos Ø 8 mm SNI Btg Rp 63,000.00
3 Besi Polos Ø 10 mm SNI Btg Rp 106,875.00
4 Besi Polos Ø 12 mm SNI Btg Rp 135,000.00 Rp 12,640.45 / Kg
5 Besi Ulir D 11 mm SNI Btg Rp 126,000.00
6 Besi Ulir D 13 mm SNI Btg Rp 191,250.00
7 Kawat ikat beton/bendrat Kg Rp 33,750.00
8 Hollow besi Uk. 40.80.1.4 mm P.6 m Btg Rp -
9 Alluminium Profil Ex Alexindo. L=4". Coklat Btg Rp 365,625.00 Rp 60,937.50
10 Alluminium Profil Ex Alexindo. L=4". Silver Btg Rp 365,625.00 Rp 60,937.50
11 Alluminium Profil Ex Alexindo. L=4". Putih Btg Rp 365,625.00 Rp 60,937.50
12 Slimar Alluminium 3/8" Ex Alexindo Coklat Btg Rp 192,375.00 Rp 32,062.50
13 Slimar Alluminium 3/8" Ex Alexindo Silver Btg Rp 192,375.00 Rp 32,062.50
14 Slimar Alluminium 3/8" Ex Alexindo Putih Btg Rp 192,375.00 Rp 32,062.50
15 Alluminium srtip Btg Rp 151,875.00 Rp 25,312.50
16 Kawat Ram Alluminium L.80 cm M Rp -
17 Kawat Ram Alluminium L.80 cm M2 Rp -
18 Baut Screw diver Bh Rp -
19 Hollow Galvalum Uk. 20x40x0.25 P. 4 m Btg Rp 36,000.00 Rp 6,000.00
20 Hollow Galvalum Uk. 40x40x0.3 P. 4 m Btg Rp 47,250.00 Rp 7,875.00
21 Kusen & Pintu Alluminium (Terpasang) Set Rp 1,350,000.00
NO URAIAN SATUAN HARGA KETERANGAN

X BAHAN LANGIT-LANGIT
1 Multipleks Uk. 120x240x 4 mm Lbr Rp 73,125.00 Rp 24,564.97 / M2
2 Multipleks Uk. 120x240x 6 mm Lbr Rp 106,875.00 Rp 35,902.65 / M2
3 Multipleks Uk. 120x240x 9 mm Lbr Rp 146,250.00 Rp 49,129.94 / M2
4 Gypsum Board Uk. 120x240x 9 mm Ex. Knauf Lbr Rp 90,000.00 Rp 30,233.81 / M2
5 Gypsum Board Uk. 120x240x 4 mm Ex. Knauf Lbr Rp 84,375.00 Rp 28,344.20 / M2
6 List Plafond Profil Gypsumboard 10/10 Btg Rp 33,750.00
7 Acrilick Ukuran 120x240x 10 mm Lbr Rp -
8 Acrilick Ukuran 120x240x 5 mm Lbr Rp -

XI BAHAN FINISHING
1 Cat kayu/Besi Kg Rp 90,000.00
2 Cat kayu dasar Kg Rp -
3 Dempul besi Ex Isamu 2 Kg Klg Rp 90,000.00
4 Dempul kayu Ex Sampolac Kg Rp -
5 Politur Kg Rp 95,625.00
6 Tiner Ex Impala Ltr Rp 50,625.00
7 Kuas 4" Bh Rp 28,125.00
8 Kuas 2" Bh Rp 16,875.00
9 Kertas pasir Lbr Rp 16,875.00
10 Lem kayu Klg Rp 28,125.00
11 Lem perekat HPL Kg Rp 40,500.00
12 Sealent / Silicon 1 Tabung = 380 ml Bh Rp 42,187.50
13 Cat tembok finished Ex Jotun, Dulux 1 Pail=25 Kg Pail Rp 1,912,500.00 Rp 76,500.00
14 Plamur tembok Kg Rp 19,125.00
15 Cat Meni kayu 1 klg= 4 Kg Klg Rp 135,000.00
16 Cat Meni besi 1 klg= 4 Kg Klg Rp 135,000.00
17 Textile Tape 1 pak = 4 roll Pak Rp 135,000.00
18 Counpound gypsum Zak Rp 90,000.00
19 High Pressure Laminates (HPL) Lbr Rp 281,250.00 Rp 94,480.65 / M2

XII BAHAN PENGGANTUNG


1 Kunci Pintu 2 Slaag (silinder+Locase+handle) Ex dekson Set Rp 281,250.00
2 Engsel (untuk pintu) Ex dekson Psg Rp 45,000.00
3 Engsel (untuk jendela) Ex dekson Psg Rp 33,750.00
4 Grendel pintu tanam 60 cm Ex dekson Bh Rp 50,625.00
5 Grendel pintu tanam 15 cm Ex dekson Bh Rp 33,750.00
6 Grendel (kunci) pintu Ex dekson Bh Rp 28,125.00
7 Grendel (kunci) jendela Ex dekson Bh Rp 16,875.00
8 Kait angin Ex dekson Psg Rp 33,750.00
9 Tarikan pintu stainlees 30 cm/45 cm/60 cm Psg Rp 168,750.00
10 Tarikan jendela Bh Rp 16,875.00

XIII PAKU-PAKUAN
1 Paku beton Dos Rp 50,625.00
2 Paku biasa 1" - 2" Kg Rp 28,125.00
3 Paku biasa 3" Kg Rp 28,125.00
4 Paku biasa 4" Kg Rp 28,125.00
5 Paku biasa 5" - 12" Kg Rp 28,125.00
6 Paku sekrup Kg Rp 33,750.00
7 Sekrup Fixer Bh Rp 562.50
NO URAIAN SATUAN HARGA KETERANGAN

8 Paku Tripleks Kg Rp 33,750.00

XIV BAHAN KACA


1 Kaca 5 mm (120 x 152) M2 Rp 168,750.00
2 Kaca tempered 12 mm 1 lbr= 80 cm x 250 cm x 12 mm Lbr Rp -
3 Floor Hinge + Fixed Ex dekson atau setara Set Rp -

XV BAHAN LISTRIK
1 MCB Box 8 Group Unit Rp 140,625.00
2 MCB 6 A Bh Rp 66,937.50
3 Stop Kontak Biasa Ex. Broco Bh Rp 34,312.50
4 Stop Kontak AC (Engkel ON/ OF) Bh Rp 84,375.00
5 T Dos Biasa Bh Rp 9,000.00
6 L Bow Bh Rp 3,937.50
7 Inbow Dos Rp 56,250.00 Rp 4,687.50
8 Inbow untuk lantai Bh Rp 5,625.00
9 Last Dop Bks Rp 56,250.00 Rp 56.25
10 Lampu LED 18 Watt Bh Rp 133,875.00
11 Lampu LED 20 Watt Bh Rp 168,750.00
12 Lampu Inderect LED STRIP M' Rp 22,500.00
13 Lampu Spot 12 watt Bh Rp 151,875.00
14 Klem Kabel Dos Rp 13,500.00 Rp 270.00
15 Armature Down Light 4" Bh Rp 70,875.00
16 Kabel NYM 3 x 2.5 mm (Ex Eterna 1 roll=100 m) Roll Rp 1,541,250.00 Rp 30,825.00
17 Kabel NYM 2 x 1.5 mm (Ex Eterna 1 roll = 100 m) Roll Rp 832,500.00 Rp 16,650.00
18 Pipa listrik Ø 5/8 P = 4 m Btg Rp 11,250.00
19 Saklar singel tanam Ex. Panasonic Bh Rp 33,750.00
20 Saklar doubel tanam Ex. Panasonic Bh Rp 39,375.00
21 Saklar triple tanam Ex. Panasonic Bh Rp 39,375.00
22 Stop kontak Ex. Panasonic Bh Rp 33,750.00
23 Stop kontak Lantai + Data Lan komputer Bh Rp 219,375.00

XVI SANITASI
1 Kloset Jongkok Porselen Bh Rp -
2 Kloset Duduk Keramik Monoblock Bh Rp 3,853,125.00
3 Kloset Duduk Keramik ( Biasa ) Bh Rp 928,125.00
4 Floor Drain (Sreen + Avoer) Bh Rp 34,875.00
5 Floor Drain PVC Bh Rp -
6 Keran Air Stainleest Steell Bh Rp -
7 Kran Wastafel Bh Rp 76,500.00
8 Kran Air Biasa Bh Rp -
9 Wastafel Standar Ex. Toto Set Rp 1,912,500.00
10 Urinoir Rp -
11 Jet Spray Rp -
12 Septictank dan Peresapan Rp -
13 Instalasi Titik Air ( Lengkap Material Pipa ) Rp -
14 Closed Duduk Rp -
15 Pipa Hawa T Rp -
16 Seal Tape Rp 16,875.00
17 Air Kerja Rp -
18 Pipa PVC ø 20 mm ( ½ " ) Btg Rp 30,375.00 Rp 7,593.75
19 Pipa PVC ø 63 mm ( 2 " ) Btg Rp 75,937.50 Rp 18,984.38
NO URAIAN SATUAN HARGA KETERANGAN

20 Pipa PVC ø 90 mm ( 3 " ) Btg Rp 126,000.00 Rp 31,500.00


21 Pipa PVC ø 110 mm ( 4 " ) Btg Rp 368,437.50 Rp 92,109.38
22 Ijuk Untuk resapan septik Kg Rp 16,875.00
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN

1.1.2.11 m2 Pembersihan lapangan dan peralatan Rp 9,000


HARGA JUMLAH
NO KODE ITEM SAT KOEF. SATUAN HARGA
(Rp.) (Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.1 Rp 90,000 Rp 9,000
2 L.4.1 Mandor OH 0.05 Rp -
Jumlah Upah Rp 9,000
B. Bahan

Jumlah Bahan Rp -
C. Peralatan

Jumlah Peralatan Rp -
D. (Jumlah A+B+C) Jumlah Harga Rp 9,000
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 9,000

1.1.5.51 m Pengukuran dan pemasangan bouwplank #REF!


HARGA JUMLAH
NO KODE ITEM SAT KOEF. SATUAN HARGA
(Rp.) (Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.100 Rp 90,000 Rp 9,000
2 L.2.6 Tukang Kayu OH 0.100 Rp 125,000 Rp 12,500
3 L.3.1 Kepala Tukang OH 0.010 Rp 150,000 Rp 1,500
4 L.4.1 Mandor OH 0.005 Rp -
Jumlah Upah Rp 23,000
B. Bahan
1 M.10.11.6 Kayu Balok 5/7 m3 0.012 Rp 13,500 Rp 162
2 M.4.16.15 Paku Biasa 2" - 5" kg 0.020 Rp 28,125 Rp 563
3 M.10.16.4 Papan Kayu 3/20 Kelas I m3 0.007 Rp 4,500,000 Rp 31,500
Jumlah Bahan Rp 32,225
C. Peralatan

Jumlah Peralatan Rp -
D. (Jumlah A+B+C) Jumlah Harga Rp 32,387
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 32,387

1.2.1.11
1 m3 Penggalian tanah biasa secara manual kedalaman ≤ 1 m 67,500
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.750 90,000 67,500
2 L.4.1 Mandor OH 0.025 -
Jumlah Upah 67,500
B. Bahan
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 67,500
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 67,500

1.2.1.12
1 m3 Penggalian tanah biasa secara manual kedalaman > 1 m s.d. 2 m 81,000
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.900 90,000 81,000
2 L.4.1 Mandor OH 0.045 -
Jumlah Upah 81,000
B. Bahan

Jumlah Bahan -
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 81,000
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 81,000

1.2.2.51 m3 Pengurugan pasir secara manual 171,000


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.300 90,000 27,000
2 L.4.1 Mandor OH 0.010 -
Jumlah Upah 27,000
B. Bahan
1 M.3.16.9 Pasir urug m3 1.200 120,000 144,000
Jumlah Bahan 144,000
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 171,000
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 171,000

1.2.2.31 m3 Pengurugan kembali galian tanah secara manual 45,000


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.500 90,000 45,000
2 L.4.1 Mandor OH 0.050 -
Jumlah Upah 45,000
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
B. Bahan

Jumlah Bahan -
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 45,000
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 45,000

1.2.2.71 m3 Pengurugan sirtu secara manual 166,500


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.250 90,000 22,500
2 L.4.1 Mandor OH 0.025 -
Jumlah Upah 22,500
B. Bahan
1 M.3.16.2 Pasir Batu (Sirtu) m3 1.200 120,000 144,000
Jumlah Bahan 144,000
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 166,500
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 166,500

2.2.1.30
1 m3 Pembuatan beton mutu f'c = 7,4 Mpa (K 100) 907,548
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 1.650 90,000 148,500
2 L.2.2 Tukang Batu OH 0.275 125,000 34,375
3 L.3.1 Kepala Tukang OH 0.028 150,000 4,200
4 L.4.1 Mandor OH 0.083 - -
Jumlah Upah 187,075
B. Bahan
1 M.3.19.3 Semen @ 40 Kg kg 247.0 1,688 416,813
2 M.3.16.3 Pasir Beton kg 869.0 80 69,520
3 M.3.2.16 Batu Kerikil (Maks 30 mm) kg 999.0 234 234,141
4 M.4.1.1 Air ltr 215.0 - -
Jumlah Bahan 720,473
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 907,548
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 907,548

2.2.1.43
1 m3 Pembuatan lantai kerja beton f'c = 7,4 Mpa slump (3-6) cm, w/c = 0,87 886,268
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 1.200 90,000 108,000
2 L.2.2 Tukang Batu OH 0.200 125,000 25,000
3 L.3.1 Kepala Tukang OH 0.020 150,000 3,000
4 L.4.1 Mandor OH 0.060 -
Jumlah Upah 136,000
B. Bahan
1 M.3.19.3 Semen @ 40 Kg kg 230.0 1,688 388,125
2 M.3.16.3 Pasir Beton kg 893.0 80 71,440
3 M.3.2.16 Batu Kerikil (Maks 30 mm) kg 1027.0 234 240,703
4 M.4.19.17 Strorox - 100 kg 2.000 25,000 50,000
Jumlah Bahan 750,268
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 886,268
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 886,268

2.2.1.22
1 m3 Pembuatan beton mutu f'c = 14,5 Mpa (K 175) 1,039,172
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 1.650 90,000 148,500
2 L.2.2 Tukang Batu OH 0.275 125,000 34,375
3 L.3.1 Kepala Tukang OH 0.028 150,000 4,200
4 L.4.1 Mandor OH 0.083 -
Jumlah Upah 187,075
B. Bahan
1 M.3.19.3 Semen @ 40 Kg kg 326.0 1,688 550,125
2 M.3.16.3 Pasir Beton kg 760.0 80 60,800
3 M.3.2.16 Batu Kerikil (Maks 30 mm) kg 1029.0 234 241,172
4 M.4.1.1 Air ltr 215.0 - -
Jumlah Bahan 852,097
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 1,039,172
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 1,039,172

2.2.1.20
1 m3 Pembuatan beton kedap air dengan strorox - 100 943,226
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 2.100 90,000 189,000
2 L.2.2 Tukang Batu OH 0.350 125,000 43,750
3 L.3.1 Kepala Tukang OH 0.035 150,000 5,250
4 L.4.1 Mandor OH 0.105 -
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Upah 238,000
B. Bahan
1 M.3.19.3 Semen @ 40 Kg kg 400.0 1,688 675,000
2 M.3.16.3 Pasir Beton kg 0.480 80 38
3 M.3.2.16 Batu Kerikil (Maks 30 mm) kg 0.800 234 188
4 M.4.19.17 Strorox - 100 kg 1.200 25,000 30,000
Jumlah Bahan 705,226
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 943,226
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 943,226

2.2.1.15
1 kg Pembesian besi polos/ulir 15,284
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.007 90,000 630
2 L.2.1 Tukang OH 0.007 125,000 875
3 L.4.1 Mandor OH 0.001 -
Jumlah Upah 1,505
B. Bahan
1 M.5.2.9 Besi Beton (Polos/ulir) kg 1.050 12,640 13,272
2 M.4.11.11 Kawat Beton kg 0.015 33,750 506
Jumlah Bahan 13,779
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 15,284
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 15,284

1.5.1.11 m3 Pasangan batu kosong (aanstamping) 490,080


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.780 90,000 70,200
2 L.2.3 Tukang Besi OH 0.390 125,000 48,750
3 L.3.1 Kepala Tukang OH 0.039 150,000 5,850
4 L.4.1 Mandor OH 0.039 -
Jumlah Upah 124,800
B. Bahan
1 M.3.2.13 Batu Kali / Batu Belah (Sungai / Gunung) m3 1.200 250,000 300,000
2 M.3.16.7 Pasir Pasang (1400 kg/m3) m3 0.544 120,000 65,280
Jumlah Bahan 365,280
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 490,080
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 490,080
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN

2.1.1.21 m3 Pasangan batu belah campuran (1 PC : 5 PS) 834,780


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 1.500 90,000 135,000
2 L.2.3 Tukang Besi OH 0.750 125,000 93,750
3 L.3.1 Kepala Tukang OH 0.075 150,000 11,250
4 L.4.1 Mandor OH 0.075 -
Jumlah Upah 240,000
B. Bahan
1 M.3.2.13 Batu Kali / Batu Belah (Sungai / Gunung) m3 1.200 250,000 300,000
2 M.3.19.9 Semen Portland kg 136 1,688 229,500
3 M.3.16.7 Pasir Pasang (1400 kg/m3) m3 0.544 120,000 65,280
Jumlah Bahan 594,780
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 834,780
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 834,780

2.2.1.81 m2 Pemasangan bekisting untuk pondasi 170,613


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.520 90,000 46,800
2 L.2.6 Tukang Kayu OH 0.260 125,000 32,500
3 L.3.1 Kepala Tukang OH 0.026 150,000 3,900
4 L.4.1 Mandor OH 0.026 -
Jumlah Upah 83,200
B. Bahan
1 M.10.11.19 Kayu Kelas III (Borneo/dll) m3 0.040 1,912,500 76,500
2 M.4.16.16 Paku Biasa 5 cm - 10 cm kg 0.300 28,125 8,438
3 M.4.13.1 Minyak Bekesting ltr 0.100 24,750 2,475
Jumlah Bahan 87,413
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 170,613
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 170,613

2.2.1.91 m2 Pemasangan bekisting untuk sloof 180,175


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.520 90,000 46,800
2 L.2.6 Tukang Kayu OH 0.260 125,000 32,500
3 L.3.1 Kepala Tukang OH 0.026 150,000 3,900
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
4 L.4.1 Mandor OH 0.026 -
Jumlah Upah 83,200
B. Bahan
1 M.10.11.19 Kayu Kelas III (Borneo/dll) m3 0.045 1,912,500 86,063
2 M.4.16.16 Paku Biasa 5 cm - 10 cm kg 0.300 28,125 8,438
3 M.4.13.1 Minyak Bekesting ltr 0.100 24,750 2,475
Jumlah Bahan 96,975
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 180,175
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 180,175

2.2.1.61 m2 Pemasangan bekisting untuk kolom 327,113


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.660 90,000 59,400
2 L.2.6 Tukang Kayu OH 0.330 125,000 41,250
3 L.3.1 Kepala Tukang OH 0.033 150,000 4,950
4 L.4.1 Mandor OH 0.033 -
Jumlah Upah 105,600
B. Bahan
1 M.10.11.19 Kayu Kelas III (Borneo/dll) m3 0.040 1,912,500 76,500
2 M.4.16.17 Paku Biasa 5 cm - 12 cm kg 0.400 28,125 11,250
3 M.4.13.1 Minyak Bekesting ltr 0.200 24,750 4,950
4 M.10.2.2 Balok Kayu Kelas II m3 0.015 3,375,000 50,625
5 M.10.13.11 Multiplek 9 MM lbr 0.350 146,250 51,188
6 M.10.11.11 Kayu Dolken Ø 8-10/400 cm btg 2.000 13,500 27,000
Jumlah Bahan 221,513
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 327,113
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 327,113

2.2.1.41 m2 Pemasangan bekisting untuk balok 337,238


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.660 90,000 59,400
2 L.2.6 Tukang Kayu OH 0.330 125,000 41,250
3 L.3.1 Kepala Tukang OH 0.033 150,000 4,950
4 L.4.1 Mandor OH 0.033 -
Jumlah Upah 105,600
B. Bahan
1 M.10.11.19 Kayu Kelas III (Borneo/dll) m3 0.040 1,912,500 76,500
2 M.4.16.17 Paku Biasa 5 cm - 12 cm kg 0.400 28,125 11,250
3 M.4.13.1 Minyak Bekesting ltr 0.200 24,750 4,950
4 M.10.2.2 Balok Kayu Kelas II m3 0.018 3,375,000 60,750
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
5 M.10.13.11 Multiplek 9 MM lbr 0.350 146,250 51,188
6 M.10.11.11 Kayu Dolken Ø 8-10/400 cm btg 2.000 13,500 27,000
Jumlah Bahan 231,638
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 337,238
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 337,238

2.2.3.14
1 m2 Pemasangan rangka atap baja ringan 169,500
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.200 90,000 18,000
2 L.2.1 Tukang OH 0.200 125,000 25,000
3 L.3.1 Kepala Tukang OH 0.200 150,000 30,000
4 L.4.1 Mandor OH 0.020 -
Jumlah Upah 73,000
B. Bahan
1 M.11.18.2 Rangka Baja Ringan C75 kg 1.730 10,911 18,875
2 M.4.2.10 Baut screw driver bh 30.00 225 6,750
3 M.4.4.2 Dinabolt ø12mm (10 s.d 15 cm) bh 2.000 16,875 33,750
4 M.11.18.6 Reng allumunium m 3.300 11,250 37,125
Jumlah Bahan 96,500
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 169,500
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 169,500

A.4.5.2.42
1 m2 Pemasangan atap aluminium gelombang 95 cm x 180 cm 162,113
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.150 90,000 13,500
2 L.2.6 Tukang Kayu OH 0.750 125,000 93,750
3 L.3.1 Kepala Tukang OH 0.080 150,000 12,000
4 L.4.1 Mandor OH 0.006 -
Jumlah Upah 119,250
B. Bahan
1 aluminium gelombang 95 cm x 180 cm Lbr 0.750 56,250 42,188
2 Paku atap Kg 0.020 33,750 675
Jumlah Bahan 42,863
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 162,113
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 162,113
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN

2.3.5.49
1 m Pemasangan lisplang ukuran (3x20) cm, kayu kelas I atau kelas II 108,100
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.100 90,000 9,000
2 L.2.6 Tukang Kayu OH 0.200 125,000 25,000
3 L.3.1 Kepala Tukang OH 0.020 150,000 3,000
4 L.4.1 Mandor OH 0.005 -
Jumlah Upah 37,000
B. Bahan
1 M.10.16.3 Papan kayu m3 0.011 4,500,000 48,600
2 M.4.16.18 Paku Biasa 5 cm - 7 cm kg 0.100 225,000 22,500
Jumlah Bahan 71,100
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 108,100
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 108,100

2.3.5.41
1 m Pemasangan bubungan atap seng 32,863
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.150 90,000 13,500
2 L.2.6 Tukang Kayu OH 0.070 125,000 8,750
3 L.3.1 Kepala Tukang OH 0.007 150,000 1,050
4 L.4.1 Mandor OH 0.006 -
Jumlah Upah 23,300
B. Bahan
1 M.11.19.9 Seng pelat 3" x 6" bjls 28 Lbr 0.300 28,125 8,438
2 M.4.16.14 Paku Biasa 1/2" - 1" kg 0.040 28,125 1,125
Jumlah Bahan 9,563
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 32,863
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 32,863

2.3.1.14
1 m2 Pemasangan dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 5PP 132,735
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.300 90,000 27,000
2 L.2.2 Tukang Batu OH 0.100 125,000 12,500
3 L.3.1 Kepala Tukang OH 0.010 150,000 1,500
4 L.4.1 Mandor OH 0.015 -
Jumlah Upah 41,000
B. Bahan
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
1 M.3.2.10 Batu Bata Merah bh 70.000 1,000 70,000
2 M.3.19.3 Semen @ 40 Kg kg 9.680 1,688 16,335
3 M.3.16.7 Pasir Pasang (1400 kg/m3) m3 0.045 120,000 5,400
Jumlah Bahan 91,735
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 132,735
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 132,735

2.3.1.12
1 m2 Pemasangan dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3PP 140,049
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.300 90,000 27,000
2 L.2.2 Tukang Batu OH 0.100 125,000 12,500
3 L.3.1 Kepala Tukang OH 0.010 150,000 1,500
4 L.4.1 Mandor OH 0.015 -
Jumlah Upah 41,000
B. Bahan
1 M.3.2.10 Batu Bata Merah bh 70.000 1,000 70,000
2 M.3.19.3 Semen @ 40 Kg kg 14.370 1,688 24,249
3 M.3.16.7 Pasir Pasang (1400 kg/m3) m3 0.040 120,000 4,800
Jumlah Bahan 99,049
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 140,049
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 140,049

2.3.2.19
1 m2 Pemasangan plesteran 1SP : 5PP tebal 15 mm 59,868
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.300 90,000 27,000
2 L.2.2 Tukang Batu OH 0.150 125,000 18,750
3 L.3.1 Kepala Tukang OH 0.015 150,000 2,250
4 L.4.1 Mandor OH 0.015 -
Jumlah Upah 48,000
B. Bahan
1 M.3.19.3 Semen @ 40 Kg kg 5.184 1,688 8,748
2 M.3.16.7 Pasir Pasang (1400 kg/m3) m3 0.026 120,000 3,120
Jumlah Bahan 11,868
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 59,868
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 59,868
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN

2.3.2.15
1 m2 Pemasangan plesteran 1SP : 3PP tebal 15 mm 63,882
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.300 90,000 27,000
2 L.2.2 Tukang Batu OH 0.150 125,000 18,750
3 L.3.1 Kepala Tukang OH 0.015 150,000 2,250
4 L.4.1 Mandor OH 0.015 -
Jumlah Upah 48,000
B. Bahan
1 M.3.19.3 Semen @ 40 Kg kg 7.776 1,688 13,122
2 M.3.16.7 Pasir Pasang (1400 kg/m3) m3 0.023 120,000 2,760
Jumlah Bahan 15,882
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 63,882
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 63,882

2.3.2.11 m2 Pemasangan acian 37,484


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.200 90,000 18,000
2 L.2.2 Tukang Batu OH 0.100 125,000 12,500
3 L.3.1 Kepala Tukang OH 0.010 150,000 1,500
4 L.4.1 Mandor OH 0.010 -
Jumlah Upah 32,000
B. Bahan
1 M.3.19.3 Semen @ 40 Kg kg 3.250 1,688 5,484
Jumlah Bahan 5,484
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 37,484
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 37,484

2.3.3.35
1 m2 Pemasangan lantai ubin granit ukuran 60 cm x 60 cm polished 287,265
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.700 90,000 63,000
2 L.2.2 Tukang Batu OH 0.350 125,000 43,750
3 L.3.1 Kepala Tukang OH 0.035 150,000 5,250
4 L.4.1 Mandor OH 0.035 -
Jumlah Upah 112,000
B. Bahan
1 M.12.8.2 Homogenius tile 600 x 600 polished bh 3.00 52,500 157,500
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
2 M.3.19.9 Semen Portland kg 10.40 1,688 17,550
3 M.3.16.7 Pasir Pasang (1400 kg/m3) Kg 1.620 86 139
4 M.3.19.14 Semen Warna @ 50 Kg kg 0.045 1,688 76
Jumlah Bahan 175,265
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 287,265
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 287,265

2.3.3.33
1 m2 Pemasangan lantai ubin granit ukuran 40 cm x 40 cm 262,375
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.250 90,000 22,500
2 L.2.2 Tukang Batu OH 0.125 125,000 15,625
3 L.3.1 Kepala Tukang OH 0.013 150,000 1,950
4 L.4.1 Mandor OH 0.013 - -
Jumlah Upah 40,075
B. Bahan
1 M.12.21.2 Ubin Granit bh 6.630 22,500 149,175
2 M.3.19.3 Semen @ 40 Kg kg 9.800 1,688 16,538
3 M.3.19.14 Semen Warna @ 50 Kg kg 1.300 39,375 51,188
4 M.3.16.7 Pasir Pasang (1400 kg/m3) m3 0.045 120,000 5,400
Jumlah Bahan 222,300
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 262,375
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 262,375

2.3.3.81 m2 Pemasangan dinding keramik ukuran 25 cm x 40 cm 331,305


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.900 90,000 81,000
2 L.2.2 Tukang Batu OH 0.450 125,000 56,250
3 L.3.1 Kepala Tukang OH 0.045 150,000 6,750
4 L.4.1 Mandor OH 0.045 -
Jumlah Upah 144,000
B. Bahan
1 M.12.11.4 Keramik 25 x 40 dos 1.200 112,500 135,000
2 M.3.19.9 Semen Portland kg 8.360 1,688 14,108
3 M.3.16.7 Pasir Pasang (1400 kg/m3) m3 0.023 120,000 2,760
4 M.3.19.14 Semen Warna @ 50 Kg kg 0.900 39,375 35,438
Jumlah Bahan 187,305
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 331,305
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 331,305

2.3.6.48
1 m Pemasangan kusen pintu aluminium 79,903
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.043 90,000 3,870
2 L.2.13 Tukang Allumunium OH 0.043 125,000 5,375
3 L.3.1 Kepala Tukang OH 0.004 150,000 645
4 L.4.1 Mandor OH 0.002 -
Jumlah Upah 9,890
B. Bahan
1 M.5.16.7 Profil allumunium m 1.100 60,938 67,031
2 M.4.19.12 Skrup Fixer bh 2.000 225 450
3 M.4.19.4 Sealent tube 0.060 42,188 2,531
Jumlah Bahan 70,013
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 79,903
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 79,903

1 m Pemasangan Slimar aluminium 48,140


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.043 90,000 3,870
2 L.2.13 Tukang Allumunium OH 0.043 125,000 5,375
3 L.3.1 Kepala Tukang OH 0.004 150,000 645
4 L.4.1 Mandor OH 0.002 -
Jumlah Upah 9,890
B. Bahan
1 Profil Slimar allumunium m 1.100 32,063 35,269
2 Skrup Fixer Bh 2.000 225 450
3 Sealent Tube 0.060 42,188 2,531
Jumlah Bahan 38,250
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 48,140
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 48,140

Pembuatan 1 M2 Pek dan Pas. Daun Pintu Multipleks Rangkap Lapis HPL, Rangka Kayu Kelas II 827,307
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.850 90,000 76,500
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
2 L.2.6 Tukang Kayu OH 2.550 125,000 318,750
3 L.3.1 Kepala Tukang OH 0.255 150,000 38,250
4 L.4.1 Mandor OH 0.043 -
Jumlah Upah 433,500
B. Bahan
1 M.10.16.3 Papan kayu m3 0.026 3,375,000 86,400
2 M.10.13.13 Multiplek tebal 4MM ukuran (90 x 220) cm M2 2.200 24,565 54,043
3 M.7.8.2 HPL Motif "Wood Grain" M2 2.200 94,481 207,857
4 M.4.12.6 Lem Kuning kg 0.700 40,500 28,350
5 M.4.12.5 Lem Kayu kg 0.300 28,125 8,438
6 M.4.16.30 Paku skrup 1 cm - 2,5 cm Dos 0.310 28,125 8,719
Jumlah Bahan 393,807
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 827,307
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 827,307

2.3.6.32
1 m2 Pemasangan kaca tebal 5 mm 215,147
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.015 90,000 1,350
2 L.2.6 Tukang Kayu OH 0.150 125,000 18,750
3 L.3.1 Kepala Tukang OH 0.015 150,000 2,250
4 L.4.1 Mandor OH 0.001 -
Jumlah Upah 22,350
B. Bahan
1 M.7.11.17 Kaca tebal 5MM m2 1.100 168,750 185,625
2 M.4.19.4 Sealent tube 0.170 42,188 7,172
Jumlah Bahan 192,797
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 215,147
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 215,147

2.3.6.21
1 bh Pemasangan handle pintu 205,000
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.125 90,000 11,250
2 L.2.1 Tukang OH 0.125 125,000 15,625
3 L.3.1 Kepala Tukang OH 0.063 150,000 9,375
4 L.4.1 Mandor OH 0.025 -
Jumlah Upah 36,250
B. Bahan
1 M.2.8.3 Handle bh 1.000 168,750 168,750
Jumlah Bahan 168,750
C. Peralatan
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 205,000
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 205,000

1 bh Pemasangan handle Jendela 53,125


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.125 90,000 11,250
2 L.2.1 Tukang OH 0.125 125,000 15,625
3 L.3.1 Kepala Tukang OH 0.063 150,000 9,375
4 L.4.1 Mandor OH 0.025 -
Jumlah Upah 36,250
B. Bahan
1 M.2.8.3 Handle bh 1.000 16,875 16,875
Jumlah Bahan 16,875
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 53,125
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 53,125

2.3.6.45
1 bh Pemasangan kunci tanam biasa 352,150
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.010 90,000 900
2 L.2.6 Tukang Kayu OH 0.500 125,000 62,500
3 L.3.1 Kepala Tukang OH 0.050 150,000 7,500
4 L.4.1 Mandor OH 0.005 -
Jumlah Upah 70,900
B. Bahan
1 M.2.11.9 Kunci tanam biasa bh 1.000 281,250 281,250
Jumlah Bahan 281,250
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 352,150
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 352,150

2.3.6.39
1 bh Pemasangan kunci kamar mandi 351,700
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.005 90,000 450
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
2 L.2.6 Tukang Kayu OH 0.500 125,000 62,500
3 L.3.1 Kepala Tukang OH 0.050 150,000 7,500
4 L.4.1 Mandor OH 0.003 -
Jumlah Upah 70,450
B. Bahan
1 M.2.11.10 Kunci tanam KM bh 1.000 281,250 281,250
Jumlah Bahan 281,250
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 351,700
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 351,700

2.3.6.10
1 bh Pemasangan engsel pintu 67,350
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.015 90,000 1,350
2 L.2.6 Tukang Kayu OH 0.150 125,000 18,750
3 L.3.4 Kepala Tukang Kayu OH 0.015 150,000 2,250
4 L.4.1 Mandor OH 0.001 -
Jumlah Upah 22,350
B. Bahan
1 M.2.5.8 Engsel Pintu bh 1.000 45,000 45,000
Jumlah Bahan 45,000
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 67,350
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 67,350

2.3.6.91 bh Pemasangan engsel jendela kupu-kupu 48,650


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.010 90,000 900
2 L.2.6 Tukang Kayu OH 0.100 125,000 12,500
3 L.3.4 Kepala Tukang Kayu OH 0.010 150,000 1,500
4 L.4.1 Mandor OH 0.001 -
Jumlah Upah 14,900
B. Bahan
1 M.2.5.7 Engsel kupu-kupu bh 1.000 33,750 33,750
Jumlah Bahan 33,750
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 48,650
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 48,650
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN

2.3.6.17
1 bh Pemasangan grendel tanam 39,225
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.015 90,000 1,350
2 L.2.6 Tukang Kayu OH 0.150 125,000 18,750
3 L.3.4 Kepala Tukang Kayu OH 0.015 150,000 2,250
4 L.4.1 Mandor OH 0.001 -
Jumlah Upah 22,350
B. Bahan
1 M.2.7.5 Grendel tanam bh 1.000 16,875 16,875
Jumlah Bahan 16,875
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 39,225
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 39,225

2.3.6.19
1 bh Pemasangan hak angin siku 56,100
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.015 90,000 1,350
2 L.2.6 Tukang Kayu OH 0.150 125,000 18,750
3 L.3.4 Kepala Tukang Kayu OH 0.015 150,000 2,250
4 L.4.1 Mandor OH 0.001 -
Jumlah Upah 22,350
B. Bahan
1 M.2.8.2 Hak angin siku bh 1.000 33,750 33,750
Jumlah Bahan 33,750
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 56,100
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 56,100

2.3.4.12
1 m2 Pemasangan rangka plafon (60x60) cm besi hollow galvanis 1 x 40.40.2 mm 143,500
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.350 90,000 31,500
2 L.2.6 Tukang Kayu OH 0.350 125,000 43,750
3 L.3.1 Kepala Tukang OH 0.035 150,000 5,250
4 L.4.1 Mandor OH 0.018 -
Jumlah Upah 80,500
B. Bahan
1 M.5.8.7 Hollow galvanis 40 x 40 cm m 4.000 7,875 31,500
2 M.4.1.7 Assesoris (Perkuatan, las dll) ls 4.000 7,875 31,500
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan 63,000
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 143,500
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 143,500

2.3.4.71 m2 Pemasangan plafon gypsum board ukuran (120x240x9)mm, tebal 9 mm 52,473


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.100 90,000 9,000
2 L.2.6 Tukang Kayu OH 0.050 125,000 6,250
3 L.3.1 Kepala Tukang OH 0.005 150,000 750
4 L.4.1 Mandor OH 0.005 -
Jumlah Upah 16,000
B. Bahan
1 M.10.7.1 Gypsum board lbr 0.364 90,000 32,760
2 M.4.16.31 Paku skrup 10 cm kg 0.110 33,750 3,713
Jumlah Bahan 36,473
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 52,473
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 52,473

2.4.1.17
1 m2 Pengecatan permukaan dinding (1 lapis plamir, 1 lapis cat dasar dan 2 lapis cat penutup) 40,073
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.020 90,000 1,800
2 L.2.4 Tukang Cat / Pelitur OH 0.063 125,000 7,875
3 L.3.1 Kepala Tukang OH 0.006 150,000 945
4 L.4.1 Mandor OH 0.003 -
Jumlah Upah 10,620
B. Bahan
1 M.7.16.1 Plamur kg 0.100 19,125 1,913
2 M.7.3.4 Cat Dasar kg 0.100 76,500 7,650
3 M.7.3.19 Cat Penutup kg 0.260 76,500 19,890
Jumlah Bahan 29,453
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 40,073
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 40,073

A.5.1.1.5
Pemasangan 1 Bh wastafel 2,618,075
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 1.200 90,000 108,000
2 L.2.8 Tukang pipa OH 1.450 125,000 181,250
3 L.3.1 Kepala Tukang OH 0.150 150,000 22,500
4 L.4.1 Mandor OH 0.060 -
Jumlah Upah 311,750
B. Bahan
1 M.15.23.1 wastafel bh 1.200 1,912,500 2,295,000
2 M.3.19.9 Semen portland kg 6.000 1,688 10,125
3 M.3.16.6 pasir pasang m3 0.010 120,000 1,200
Jumlah Bahan 2,306,325
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 2,618,075
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 2,618,075

A.5.1.1.25
Pemasangan 1 M' Pipa PVC tipe AW diameter 1/2" 23,942
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.036 90,000 3,240
2 L.2.8 Tukang pipa OH 0.060 125,000 7,500
3 L.3.1 Kepala Tukang OH 0.006 150,000 900
4 L.4.1 Mandor OH 0.002 -
Jumlah Upah 11,640
B. Bahan
1 pipa PVC 1/2" m' 1.200 7,594 9,113
2 perlengkapan 35% Ls 0.420 7,594 3,189
Jumlah Bahan 12,302
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 23,942
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 23,942

A.5.1.1.29
Pemasangan 1 M' Pipa PVC tipe AW diameter 2" 48,215
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.054 90,000 4,860
2 L.2.8 Tukang pipa OH 0.090 125,000 11,250
3 L.3.1 Kepala Tukang OH 0.009 150,000 1,350
4 L.4.1 Mandor OH 0.003 -
Jumlah Upah 17,460
B. Bahan
1 pipa PVC 2" m' 1.200 18,984 22,781
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
2 perlengkapan 35% Ls 0.420 18,984 7,973
Jumlah Bahan 30,755
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 48,215
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 48,215

A.5.1.1.32
Pemasangan 1 M' Pipa PVC tipe AW diameter 4" 175,407
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.081 90,000 7,290
2 L.2.8 Tukang pipa OH 0.135 125,000 16,875
3 L.3.1 Kepala Tukang OH 0.014 150,000 2,025
4 L.4.1 Mandor OH 0.004 -
Jumlah Upah 26,190
B. Bahan
1 pipa PVC 4" m' 1.200 92,109 110,531
2 perlengkapan 35% Ls 0.420 92,109 38,686
Jumlah Bahan 149,217
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 175,407
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 175,407

A.5.1.1.35
Pemasangan 1 Bh Kran diameter 1/2"atau 3/4" 133,822
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.010 90,000 900
2 L.2.8 Tukang pipa OH 0.400 125,000 50,000
3 L.3.1 Kepala Tukang OH 0.040 150,000 6,000
4 L.4.1 Mandor OH 0.005 -
Jumlah Upah 56,900
B. Bahan
1 Kran air Bh 1.000 76,500 76,500
2 Sealtape Bh 0.025 16,875 422
Jumlah Bahan 76,922
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 133,822
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 133,822

A.5.1.1.36
Pemasangan 1 Bh Floor drain 49,775
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.010 90,000 900
2 L.2.8 Tukang pipa OH 0.100 125,000 12,500
3 L.3.1 Kepala Tukang OH 0.010 150,000 1,500
4 L.4.1 Mandor OH 0.005 -
Jumlah Upah 14,900
B. Bahan
1 floor drain Bh 1.000 34,875 34,875
Jumlah Bahan 34,875
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 49,775
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 49,775

A.5.1.1.1
Pemasangan 1 Bh Closet duduk 1,167,813
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.500 90,000 45,000
2 L.2.8 Tukang pipa OH 1.100 125,000 137,500
3 L.3.1 Kepala Tukang OH 0.010 150,000 1,500
4 L.4.1 Mandor OH 0.160 -
Jumlah Upah 184,000
B. Bahan
1 Closet duduk Bh 1.000 928,125 928,125
2 Perlengkapan Ls 0.060 928,125 55,688
Jumlah Bahan 983,813
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 1,167,813
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 1,167,813

A.6.1.1.1
Pemasangan 1 Bh MCCB 1,201,500
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 Upah % 100 90,000 90,000
Jumlah Upah 90,000
B. Bahan
1 pipa listrik 5/8 Btg 3.000 11,250 33,750
2 kabel M' 15.000 30,825 462,375
3 T dus Bh 1.000 9,000 9,000
4 L bow Bh 2.000 3,938 7,875
5 Klem biasa Bh 24.000 13,500 324,000
6 MCCB (Boks MCB) Bh 1.000 140,625 140,625
ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
7 MCB Bh 2.000 66,938 133,875
Jumlah Bahan 1,111,500
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 1,201,500
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 1,201,500

Pemasangan 1 Bh titik lampu 337,744


JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 Upah % 100 90,000 90,000
Jumlah Upah 90,000
B. Bahan
1 pipa listrik 5/8 Btg 1.200 11,250 13,500
2 kabel M' 4.000 30,825 123,300
3 T dus Bh 2.000 9,000 18,000
4 L bow Bh 3.000 3,938 11,813
5 Lastdop Bh 3.000 56 169
6 Klem biasa Bh 20.000 270 5,400
7 Mangkok Bh 1.000 4,688 4,688
9 Fitting Bh 1.000 70,875 70,875
Jumlah Bahan 247,744
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 337,744
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 337,744

A.1.5.1.13
Pemasangan 1 M2 Lapisan Ijuk tebal 10 cm untuk bidang resapan tangki septik 114,750
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.150 90,000 13,500
4 L.4.1 Mandor OH 0.015 -
Jumlah Upah 13,500
B. Bahan
1 ijuk Kg 6.000 16,875 101,250
Jumlah Bahan 101,250
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 114,750
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 114,750

Praktis1 m3 Pasangan Batu karang 274,800


ENGINEERING ESTIMATE
ANALISA HARGA SATUAN PEKERJAAN
JUMLAH
HARGA SATUAN
NO KODE ITEM SAT KOEF. HARGA
(Rp.)
(Rp.)
A. Upah
1 L.1.1 Pekerja OH 0.780 90,000 70,200
2 L.2.3 Tukang Besi OH 0.390 125,000 48,750
3 L.3.1 Kepala Tukang OH 0.039 150,000 5,850
4 L.4.1 Mandor OH 0.039 -
Jumlah Upah 124,800
B. Bahan
1 Batu Karang M3 1.200 125,000 150,000
Jumlah Bahan 150,000
C. Peralatan

Jumlah Peralatan -
D. (Jumlah A+B+C) Jumlah Harga Rp 274,800
E. Biaya Umum dan Keuntungan (Maksimum 15%) 0% Rp -
F. Harga Satuan Pekerjaan (D+E) Rp 274,800