REKAPITULASI BACKUP VOLUME

NAMA KEGIATAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
NAMA PEKERJAAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
LOKASI : EDU WISATA PEMPROV

PERHITUNGAN VOLUME

A. LAPIS PONDASI AGREGAT KELAS C (SIRTU)


Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu)
V.T = S1 + S2 + S3 + S4 + S5 + S6
= 1.64 + 2.84 + 7.59 + 2.43 + 5.21 + 6.11
= 25.82 M2

Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu) Total


VT = 25.82 m3
B. Pasir
Volume Pekerjaan Timbunan Pasir
V.T = S1 + S2 + S3 + S4 + S5 + S6
= 0.44 + 0.38 + 0.68 + 0.22 + 1.56 + 0.55
= 3.84 m3

Volume Pekerjaan Pasir


VT = 3.84 m3
C. PAVING BLOCK
Luas Pasangan Paving Block
V.T = S1 + S2 + S3 + S4 + S5 + S6
= 8.76 + 17.01 + 43.38 + 13.86 + 30.2 + 34.9
= 148.13 m2

Luas Pekerjaan Pasangan Paving Block Total


VT = 148.13 m2

D. PAS. KANSTEEN BETON


Volume Kansteen Beton Manual uk. 15x20 cm
V.T = S1 + S2 + S3 + S4 + S5 + S6
= 0.44 + 0.38 + 1.45 + 0.46 + 0.91 + 1.16
= 4.79 m3

Volume Kansteen Beton Manual uk. 15x20 cm


VT = 4.79 m3

Bekisting = S1 + S2 + S3 + S4 + S5 + S6
= 5.84 + 5.04 + 19.28 + 6.16 12.1 15.5
= 63.92 m2
Luas Bekisting untuk Kansteen
VT = 63.92
BACKUP VOLUME

NAMA KEGIATAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
NAMA PEKERJAAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
LOKASI : EDU WISATA PEMPROV

URAIAN/SKETSA GAMBAR

Paving Bloc k, t=8 cm


Urugan Pas ir, t=5 cm
Pas.Kasten Manual 15 x 20
Urugan Sirtu, t=15 cm

15

20
200
230

PERHITUNGAN VOLUME SKETSA

S5 P = 15.10 m
A. LAPIS PONDASI AGREGAT KELAS C (SIRTU)
Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu)
P = 15.1 m
L = 2.3 m
T = 0.15 m Paving Block, t=8 cm
Urugan Pasir, t=5 cm
Urugan Sir tu, t=15 cm

V1 = 15 x 2.3 x 0.15
= 5.21 m3

Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu) Total


VT = 5.21 m3
B. Pasir
Volume Pekerjaan Pasir
P = 5.2 m
L = 2.0 m
T = 0.15 m Paving Block, t=8 cm
Urugan Pasir, t=5 cm
Urugan Sir tu, t=15 cm

V1 = 5 x 2.0 x 0.15
= 1.56 m3

Volume Pekerjaan Pasir


VT = 1.56 m3
C. PAVING BLOCK
Luas Pasangan Paving Block
P = 15.1 m
15.1
2.3

S5

L = 2.00 m

V1 = 30.20 m2

Luas Pekerjaan Pasangan Paving Block Total


VT = 30.20 m2

D. PAS. KANSTEEN BETON


Volume Kansteen Beton Manual uk. 15x20 cm
P = 15.1 m
L = 0.15 m
T = 0.20 m
V1 = P x L x T x 2 Sisi Pas.Kasten Manual 15 x 20
= 15 x 0.15 x 0.20 x 2.00
= 0.906 m3

Volume Kansteen Beton Manual uk. 15x20 cm


VT = 0.91 m3

Bekisting = 0.4 x 15 x 2 Sisi


= 12.08 m2

Luas Bekisting untuk Kansteen


VT = 12.08 m2
BACKUP VOLUME

NAMA KEGIATAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
NAMA PEKERJAAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
LOKASI : EDU WISATA PEMPROV

URAIAN/SKETSA GAMBAR

Paving Block, t=8 cm


Urugan Pasir, t=5 cm
Pas.Kasten Manual 15 x 20
Urugan Sirtu, t=10 cm

15

20
180
210

PERHITUNGAN VOLUME SKETSA

S4 P = 7.70 m
A. LAPIS PONDASI AGREGAT KELAS C (SIRTU)
Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu)
P = 7.7 m
L = 2.1 m
T = 0.15 m Paving Block, t=8 cm
Urugan Pasir, t=5 cm
Urugan Sirtu, t=15 cm

V1 = 8 x 2.1 x 0.15
= 2.43 m3

Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu) Total


VT = 2.43 m3
B. Pasir
Volume Pekerjaan Pasir
P = 2.4 m
L = 1.8 m
T = 0.05 m Paving Block, t=8 cm
Urugan Pasir, t=5 cm
Urugan Sirtu, t=15 cm

V1 = 2 x 1.8 x 0.05
= 0.22 m3

Volume Pekerjaan Pasir


VT = 0.22 m3
C. PAVING BLOCK
Luas Pasangan Paving Block
P = 7.7 m
L = 1.80 m
S4
.7
7

V1 = 13.86 m2

Luas Pekerjaan Pasangan Paving Block Total


VT = 13.86 m2

D. PAS. KANSTEEN BETON


Volume Kansteen Beton Manual uk. 15x20 cm
P = 7.7 m
L = 0.15 m
T = 0.20 m
V1 = P x L x T x 2 Sisi Pas.Kasten Manual 15 x 20

= 8 x 0.15 x 0.20 x 2.00


= 0.462 m3

Volume Kansteen Beton Manual uk. 15x20 cm


VT = 0.46 m3

Bekisting = 0.4 x 8 x 2 Sisi


= 6.16 m2

Luas Bekisting untuk Kansteen


VT = 6.16 m2
BACKUP VOLUME

NAMA KEGIATAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
NAMA PEKERJAAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
LOKASI : EDU WISATA PEMPROV

URAIAN/SKETSA GAMBAR

Paving Block, t=8 cm


Urugan Pasir, t=5 cm
Pas.Kasten Manual 15 x 20
Urugan Sirtu, t=10 cm

15

20
180
210

PERHITUNGAN VOLUME SKETSA

S3 P = 24.10 m
A. LAPIS PONDASI AGREGAT KELAS C (SIRTU)
Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu)
P = 24 m
L = 2.1 m
T = 0.15 m
Paving Block, t=8 cm
Urugan Pasir, t=5 cm
Urugan Sirtu, t=15 cm

V1 = 24 x 2.1 x 0.15
= 7.59 m3

Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu) Total


VT = 7.59 m3
B. Pasir
Volume Pekerjaan Pasir
P = 8 m
L = 1.8 m
T = 0.05 m
Paving Block, t=8 cm
Urugan Pasir, t=5 cm
Urugan Sirtu, t=15 cm

V1 = 8 x 1.8 x 0.05
= 0.68 m3

Volume Pekerjaan Pasir


VT = 0.68 m3
C. PAVING BLOCK
Luas Pasangan Paving Block
P = 24.1 m
L = 1.80 m

V1 = 43.38 m2 S3

Luas Pekerjaan Pasangan Paving Block Total


VT = 43.38 m2

D. PAS. KANSTEEN BETON


Volume Kansteen Beton Manual uk. 15x20 cm
P = 24.1 m
L = 0.15 m
T = 0.20 m
V1 = P x L x T x 2 Sisi
Pas.Kasten Manual 15 x 20
= 24 x 0.15 x 0.20 x 2.00
= 1.446 m3

Volume Kansteen Beton Manual uk. 15x20 cm


VT = 1.45 m3

Bekisting = 0.4 x 24 x 2 Sisi


= 19.28 m2

Luas Bekisting untuk Kansteen


VT = 19.28 m2
BACKUP VOLUME

NAMA KEGIATAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
NAMA PEKERJAAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
LOKASI : EDU WISATA PEMPROV

URAIAN/SKETSA GAMBAR

Paving Block, t=8 cm


Urugan Pasir, t=5 cm
Pas.Kasten Manual 15 x 20
Urugan Sirtu, t=15 cm

15

20
270
300

PERHITUNGAN VOLUME SKETSA

S2 P = 6.30 m
A. LAPIS PONDASI AGREGAT KELAS C (SIRTU)
Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu)
P = 6.30 m
L = 3.0 m
T = 0.15 m
Paving Block, t=8 cm
Urugan Pasir, t=5 cm
Urugan Sirtu, t=15 cm

V1 = 6 x 3.0 x 0.15
= 2.84 m3

Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu) Total


VT = 2.84 m3
B. Pasir
Volume Pekerjaan Pasir
P = 2.84 m
L = 2.7 m
T = 0.05 m
Paving Block, t=8 cm
Urugan Pasir, t=5 cm
Urugan Sirtu, t=15 cm

V1 = 3 x 2.7 x 0.05
= 0.38 m3

Volume Pekerjaan Pasir


VT = 0.38 m3
C. PAVING BLOCK
Luas Pasangan Paving Block
P = 6.3 m 8.1

L = 2.70 m
1.5

S2
4.4

V1 = 17.01 m2 2.1

Luas Pekerjaan Pasangan Paving Block Total


VT = 17.01 m2

D. PAS. KANSTEEN BETON


Volume Kansteen Beton Manual uk. 15x20 cm
P = 6.3 m
L = 0.15 m
T = 0.20 m Pas.Kasten Manual 15 x 20

V1 = P x L x T x 2 Sisi
= 6 x 0.15 x 0.20 x 2.00
= 0.378 m3

Volume Kansteen Beton Manual uk. 15x20 cm


VT = 0.38 m3

Bekisting = 0.4 x 6 x 2 Sisi


= 5.04 m2

Luas Bekisting untuk Kansteen


VT = 5.04 m2
BACKUP VOLUME

NAMA KEGIATAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
NAMA PEKERJAAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
LOKASI : EDU WISATA PEMPROV

URAIAN/SKETSA GAMBAR

Pav ing Block , t=8 cm


Urugan Pasi r, t=5 cm
Pas.K as ten Manual 15 x 20
Urugan Si rtu, t=15 cm

15

20
120
150

PERHITUNGAN VOLUME SKETSA

S1 P = 7.30 m
A. LAPIS PONDASI AGREGAT KELAS C (SIRTU)
Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu)
P = 7.30 m
L = 1.5 m
T = 0.15 m

V1 = 7 x 1.5 x 0.15
Paving Block, t=8 cm
Urugan Pasir, t=5 cm
Urugan Sirtu, t=15 cm

= 1.64 m3

Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu) Total


VT = 1.64 m3

B. Pasir
Volume Pekerjaan Pasir
P = 7.30 m
L = 1.2 m
T = 0.05 m

Paving Block, t=8 cm

V1 = 7 x 1.2 x 0.05
Urugan Pasir, t=5 cm
Urugan Sirtu, t=15 cm

= 0.44 m3

Volume Pekerjaan Pasir


VT = 0.44 m3

C. PAVING BLOCK
Luas Pasangan Paving Block
P = 7.3 m
L = 1.20 m
1.5

S1

V1 = 8.76 m2

Luas Pekerjaan Pasangan Paving Block Total


VT = 8.76 m2

D. PAS. KANSTEEN BETON


Volume Kansteen Beton Manual uk. 15x20 cm
P = 7 m
L = 0.15 m
T = 0.20 m
V1 = P x L x T x 2 Sisi Pas.Kasten Manual 15 x 20

= 7 x 0.15 x 0.20 x 2.00


= 0.438 m3

Volume Kansteen Beton Manual uk. 15x20 cm


VT = 0.44 m3

Bekisting = 0.4 x 7 x 2 Sisi


= 5.84 m2

Luas Bekisting untuk Kansteen


VT = 5.84 m2
BACKUP VOLUME

NAMA KEGIATAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
NAMA PEKERJAAN : PEMBANGUNAN RUMAH KAYU DAN RUMAH SEHAT DI DAERAH GOR SUDIANG
LOKASI : EDU WISATA PEMPROV

URAIAN/SKETSA GAMBAR

Paving Block, t=8 cm


Urugan Pasir, t=5 cm
Pas.Kasten Manual 15 x 20
Urugan Sirtu, t=10 cm

15

20
180
210

PERHITUNGAN VOLUME SKETSA

S6 P = 19.40 m
A. LAPIS PONDASI AGREGAT KELAS C (SIRTU)
Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu)
P = 19.4 m
L = 2.1 m
T = 0.15 m
Paving Block, t=8 cm
Urugan Pasir, t=5 cm
Urugan Sirtu, t=15 cm

V1 = 19 x 2.1 x 0.15
= 6.11 m3

Volume Pekerjaan Lapis Pondasi Agregat Kelas C (Sirtu) Total


VT = 6.11 m3
B. Pasir
Volume Pekerjaan Pasir
P = 6.1 m
L = 1.8 m
T = 0.05 m
Paving Block, t=8 cm
Urugan Pasir, t=5 cm
Urugan Sirtu, t=15 cm

V1 = 6 x 1.8 x 0.05
= 0.55 m3

Volume Pekerjaan Pasir


VT = 0.55 m3
C. PAVING BLOCK
Luas Pasangan Paving Block
P = 19.4 m
L = 1.80 m S6
4
9
1
.

V1 = 34.92 m2 2.1

Luas Pekerjaan Pasangan Paving Block Total


VT = 34.92 m2

D. PAS. KANSTEEN BETON


Volume Kansteen Beton Manual uk. 15x20 cm
P = 19.4 m
L = 0.15 m
T = 0.20 m
V1 = P x L x T x 2 Sisi
= 19 x 0.15 x 0.20 x 2.00
Pas.Kasten Manual 15 x 20
= 1.164 m3

Volume Kansteen Beton Manual uk. 15x20 cm


VT = 1.16 m3

Bekisting = 0.4 x 19 x 2 Sisi


= 15.52 m2

Luas Bekisting untuk Kansteen


VT = 15.52 m2

Anda mungkin juga menyukai