a) Kriteria perencanaan :
Tebal cake = 60 cm
( Sumber : Waste Water Engineering Treatment Disposal Reuse, Metcalf & Eddy hal 840, tahun 1985 )
b) Direncanakan :
Td = 1 hari
c) Perhitungan :
1. Volume lumpur yang masuk
= 90,87 m3/hari
Volume cake sludge ( Vi )
Vol. Lumpur * ( 1 P )
V1 =
1 Pi
= 64,9 m3/hr
2. Volume bed ( Vb ) = Vi . t
3. Dimensi Bed.
Direncanakan :
- Perbandingan p : l = 3:1
Perhitungan :
2) A =P*l P=2l
54 m2 = 2l * l
67,61 m2 = 2 * l2
l2 = 27 m
l = √27
l = 5,2 m P = 2 * l = 10,4 m
4. Dimensi Underdrain.
Direncanakan : td = 1 hari.
90,87 m 3 64,9 m 3
= x 1 hari = 2,59 m3
10
b. Kedalaman Underdrain
Volume
air
h =
A
2,59
= = 0,04 m + 0,2 m ( freeboard ) = 0,6 m
54
5. Pipa outlet.
Perhitungan :
Q 0,035 m 3 /dt
A= = 0,11 m2
v 0,3 m/dt
2) Diameter pipa ( D )
4*A 4 * 0,14
D= = = 0,37 m
π 3,14
6. Sketsa
10,4 m
5,2 m
Direncanakan :
- v = 0,5 m/det
Perhitungan :
Vol 90,87 m 3
1) Debit (Q) = = 0,001 m3/dtk
td 86400 det
Q 0,001 m 3 / dt
2) A= = 0,002 m2
v 0,5m / dt
1 1
4 .* A 2 4 * 0,002 m 2 2
D= = = 0,05 m
3,14
Pipa Inlet
60 cm
30 cm
60 cm
60 cm
Pipa Outlet
28,5 m
Ruang rembesan
Kerikil
Pasir
Cake