Data Sungai :
+ 5.2 + 5.4
A B = 50 m
MAB : + 4.5 B
+ 0
C
b = 15.00 m
K = b + 2h 1 + m2
= 15 + 2 . 4.5 1 + 3.889 2
= 51.1386 m
Jadi A 146.25
R = = = 2.85987 m
K 51.1386
1 1
V= . R 0.67 i. 0.5 = . 2.85987 0.67 . 0.0008 0.5
n 0.025
= 2.28748 m/dt
Sehingga debit banjir (Q) :
Q = A . V = 146.25 . 2.28748
= 334.544 m3/dt
Q
d = 0.473 . 0.333
f
335
= 0.473 . 0.333
1.25
= 3.0425 m
jembatan mempunyai tiga bentang , sehingga ada pilar dengan dua tumpuan pada ujung-ujungnya,
sehingga kedalaman penggerusan max dm adalah :
dm = 2 . d
= 2 x 3.0425 = 6.08503 m
M.A.B
d
dmax
20 m
1.9
Balok pratekan
20 m 20 m
M.A.N
Tiang sandaran
Lantai trotoar
Lantai kendaraan
Gelagar
Diafragma
p p
I = . D4 - d4 = . 6.05 4 - 5.59 4 = 17.84059 cm4
64 64
p p
W = . D3 - d3 = . 6.05 3 - 5.59 3 = 4.59331 cm4
32 32
Perhitungan pembebanan :
- Berat sendiri = 3.302517 kg/m
- Beban luar (beban orang) = 100 kg/m
qv = 103.3025 kg/m
= 143.7756 kg/m
Kontrol lendutan :
M 636265.5975
fytd = = = 138.5201 N/mm2
W 4593.309875
250 250
fizin = = = 217.3913 N/mm2
gm 1.15 fytd < fizin Aman !!!
2. Tiang sandaran
Direncanakan :
- Dimensi tiang sandaran = 15 x 15 cm
- Jarak antar tiang = 1.90 m
- Mutu beton ( f'c ) = 45 Mpa
- Mutu baja = U - 32
fy = 400 Mpa
- q beton = 2.5 t/m3 = 2500 kg/m
- q pavement = 2.2 t/m3 = 2200 kg/m
H = 100 kg/m H = 100 kg/m
30 cm Pot. I - I
I I
30 cm
h = 15 cm
30 cm
b = 15 cm
12 cm 50 cm
a. Beban horisontal
Tiang-tiang sandaran pada tepi jembatan harus diperhitungkan untuk dapat menahan
beban sebesar 100 kg/m yang bekerja pada setinggi 90 cm diatas lantai kendaraan.
P = 100 kg
M = 100 x 0.9 = 90 kgm = 882630 Nmm
fy2 Mu
AS2 - fy . d. AS. + = 0
1,7 . fc' .b f
4000 2 882630
AS2 - 4000 . 150 . AS. + = 0
1.7 450 150 0.8
1.4 1.4
ρmin
= = = 0.0035
fy 400
As. 2.26
ρada
= = = 0.010053 Ok !!!
b. d 15 . 15
= 0.036577 Ok !!!
k . Lu
< 22 SK. SNI T - 15 - 1991 - 03. 33 11 4)
r
dimana :
k = faktor tekuk = 1
lu = panjang kolom = 0.9
I 1/ 12 . 15 . 15 3
r = radius girasi = = = 4.330127
A 15 . 15
atau r = 0,3 . h. = 0.3 . 15 = 4.5
Jadi :
k . Lu 1. 0.9
= = 20 < 22
r 0.045
Cm
d = > 1
Pu
1 -
f . Pc
Dimana : Cm = 1 (konservatif)
Pu = 0.076065105 ton
p2 . EI
Pc =
(k . Lu)2
Ec . Ig
EI =
2,5 . (1 + bd)
Ec = 4700 f'c = 4700 45 = 31528.558 Mpa = 3152855.8 t/m2
Ig = 1/12 . b. h3
1
Ig = . 0.15 . 0.15 3 = 4.21875E-05 m4
12
1,2 . qdl 1.2 . 0.076065
Bd = = = 0.363255
1,2 . qdl + 1,6 . qll 1.2 . 0.076065 + 1.6 . 0.1
diperoleh :
3152855.8 . 4.21875E-05
EI = = 39.0274955597
2.5 . ( 1+ 0.363255 )
p2 . 39.02749556
Pc = = 475.0562
1. 0.9 2
1
d = = 1.000 > 1 Ok ! ! !
0.0760651046
1 -
0.65 . 475.0562
Mu = 0.0900 tm
Mc = d . Mu
= 1.000246 . 0.09 = 0.090022176
Hitung :
Pu 0.076065105
Pn perlu = = = 0.117023 ton
f 0.65
Mc 0.0900
Mn perlu = = = 0.138496 tm
f 0.65
Eksentrisitas :
Mn perlu 0.1384956549
e = = = 1.183488 = 1183.488
Pn perlu 0.1170232378
Hitung nilai r
~ Sumbu vertikal
Pu 760.6510457143
= = 0.00136
f . Ag . 0,85 . fc' 0.65 . 150 . 150 . 0.85 . 45
~ Sumbu horizontal
Pu e 1183.488
. = 0.00136 . = 0.010728
f . Ag . 0,85 . Fc' h 150
Eksentrisitas (e) :
M 882630
e = = = 11603.61252 mm
N 76.06510457
Syarat : h e 11603.61252
e < - d2 atau > 1 = 77.36 > 1
2 ht 150
Momen dan gaya aksial (M & N) dapat digantikan oleh suatu momen tambahan, dimana :
h
Ma = M + N . - d2 = 0,156 . fcu . b . d2 + 087 . fy . As . (d - d')
2
0,87 . fy . As = 0,156 . fcu . b . d2 + 087 . fy . As . (d - d')
150
= 882630 + 76.0651 + - 30
2
= 886052.9297 N/mm2
Sehingga :
886052.9297 = 23692500 + 41760 As
As = -546.131 mm 2
(tarik) Digunakan tulangan : 2 15 = 353.6 mm2
Kontrol tegangan :
P 0
sytd = < sizin < 0,58 st , dimana s= 1400 kg/cm2
As 1.0
0 < 812 kg/cm2 OK
V. 2. LANTAI DAN BALOK
1. Lantai trotoar
Direncanakan :
tebal lantai trotoar = 20 cm
tebal pelat = 20 cm
P= 100 kg/m'
15 x 15 qLL = 500 kg/m2
90 I
20
20
I
150 15
20
0.65 m 110 1.60 m
Mu = 263.089 kgm
d = 20 - 3 = 17 cm
Mn = Mu = 263.0887 = 328.8608594 kgm
0.8 = 3225138.448 Nmm
Rn = Mu = 2580110.7583125 = 0.111596
b d2 0.8 x 1000 x 170 2
ρ = 1 1 - 1 - 2 m Rn
m fy
= 1 1 - 1 - 2 10.45752 . 0.111596
10.45752 400
= 0.000279399
Mu = 263.089 kgm
Modulus elastis baja ( Es ) = 2 x 10 5 Mpa
Modulus elastis beton ( Ec ) = 4700 f'c = 4700 45 = 31528.56
Modulus rasio ( n ) = Es = 6
Ec
Total luas = b x h
= 1000 x 200 = 200000 mm2
Perhitungan momen statis untuk menentukan letak garis netral :
M = 1000 x 200 x 100 = 20000000.00 mm3
y = M = 20000000.00 = 100.00 mm
A 200000
y1 = d - y
= 170 - 100.00 = 70.00 mm
2. Lantai Kendaraan :
Pembebanan pada lantai :
* Beban merata :
- Akibat berat sendiri = 0.2 . 2.50 = 0.5 t/m2
- Akibat lantai trotoar = 0.2 . 2.50 = 0.5 t/m2
- Akibat berat air hujan = 0.05 t/m2
qDL = 1.05 t/m2
Momen akibat beban mati :
1
Mxm = . 1.05 . 1.60 2 = 0.269 tm
10
1
Mxm = . 0.269 = 0.090 tm
3
* Beban akibat muatan - T :
- Beban roda : T = 10 ton
Kelas I = 100% x 10 = 10 ton
- Ukuran ban : 50 x 20 cm
50 20
lapisan aspal
10 10
45 0
10 10
a b
a = 50 + 2 ( tan 45 . 20 ) b = 20 + 2 ( tan 45 . 20 )
= 90 cm = 60 cm
10
Muatan T disebarkan : T = = 18.519 t/m2
0.9 x 0.6
tx = a tx 90
= = 0.6 fxm = 0.1312
y (∞) a lx = 160 Ix 160
b ty = b ty 60
= = 0.4 fym = 0.0735
lx = 160 Ix 160
* Dicari momen pada saat 2 (dua) roda berdekatan dengan jarak antara as ke as
minimum = 1,00 m
50 50
100
60
10
10
10
90 10 90 75 75
160
Luas bidang kontak diatas dapat diuraikan menjadi 2 bagian (I & II) sebagai berikut :
(I) (II)
= -
Bagian - II : tx = 10 tx 10
= = 0.1 fxm = 0.2216
Ix = 160 Ix 160
ty = 60 ty 60
= = 0.4 fym = 0.0938
Ix = 160 Ix 160
Jadi :
Mxm = (I) - (II) = 1.5947 - 0.2462 = 1.3484 tm
Mym = (I) - (II) = 0.9333 - 0.1042 = 0.8291 tm
Dengan membandingkan momen Mxm dan Mym untuk beban 1 (satu) roda terhadap beban
2 (dua) roda diperoleh momen yang menentukan adalah sebagai berikut :
arah - x Mxm = 1.6172 tm
arah - y M ym = 0.9187 tm
Akibat beban sementara :
Disini beban sementara adalah beban angin yang bekerja pada kendaraan.
2 x 5
x 1 x 100
Reaksi pada roda =
1.75
2
= 571.4286 kg ≈ 600 kg
≈ 0.6 ton
1.75
Ditinjau akibat beban 1 (satu) roda (yang menentukan) pada tengah-tengah pelat :
Mxm = 0.1312 x 19.630 x 0.90 x 0.60 = 1.3907 tm
Mym = 0.0735 x 19.630 x 0.90 x 0.60 = 0.7791 tm
Perencanaan Penulangan
Penulangan arah x :
Mu = 1659.5200 kgm
d = 170 mm
Mn = Mu = 1659.5200 = 2074.4 kgm
0.8 = 20343640.8 Nmm
Rn = Mu = 16274912.64 = 0.703932
b d2 0.8 x 1000 x 170 2
ρ = 1 1 - 1 - 2 m Rn
m fy
= 1 1 - 1 - 2 10.45752 . 0.703932
10.45752 400
= 0.001776329
Penulangan arah y :
Mu = 918.7111 kgm
d = 170 mm
Mn = Mu = 918.7111 = 1148.388889 kgm
0.8 = 11262249.83 Nmm
ρ = 1 1 - 1 - 2 m Rn
m fy
= 1 1 - 1 - 2 10.45752 . 0.389697
10.45752 400
= 0.000979257
Mu = 1659.520 kgm
Modulus elastis baja ( Es ) = 2 x 10 5 Mpa
Modulus elastis beton ( Ec ) = 4700 f'c = 4700 45 = 31528.56
Modulus rasio ( n ) = Es = 6
Ec
Total luas = b x h
= 1000 x 200 = 200000 mm2
Perhitungan momen statis untuk menentukan letak garis netral :
M = 1000 x 200 x 100 = 20000000.00 mm3
y = M = 20000000.00 = 100.00 mm
A 200000
y1 = d - y
= 170 - 100.00 = 70.00 mm
C. Balok melintang :
Dimensi balok melintang 20 / 110
Balok melintang hanya memikul akibat berat sendiri.
* Pembebanan :
- Akibat berat sendiri balok = 0.2 x 1.1 x 2500 x 1
= 550 kg/m'
Penulangan :
Mu = 107.800 kgm
d = 110 - 5 = 105 cm
Mn = Mu = 134.75 kgm
= 1321493.25 Nmm
PERHITUNGANABALOK MEMANJANG
A
BENTANG L1 DAN L3 ( PRETENSION )
Panjang bentang = 20 m
Beban - beban yang bekerja :
- Beban garis P = 12 t
20
Koefisien kejut = 1 + = 1.29
50 + 20.0
Lebar jalur minimum 2.75 m harus digunakan untuk menentukan muatan per jalur ,
sehingga muatan per meter lebar jembatan menjadi :
2.2
p = x 1.3 = 1.0286 t/m
2.75
12
P = x 1.3 = 5.6104 t/m
2.75
Langkah 1
Rencana penampang balok adalah sbb :
50
20
I
I
15 II II
15 15
20
75 150
III
25 25 Potongan melintang
20 IV IV
V
20
70
20 50
20 I
BAGIAN LUAS (cm2) Yi MOMEN STATIS I
15 II II
I 1000 140 140000
II 225 125 28125 82.308 15 15
III 2200 75 165000 20
IV 500 26.667 13333.333333333 75 150
V 1400 10 14000 III
TOTAL 5325 360458.33333333 25 25
67.692 20 IV IV
Statis momen 360458.333
Yb = = = 67.692 cm V
Luas 5325 20
Ix 13516839.544
Zt = = = 164222.083 cm3
Yt 82.308
Ix 13516839.544
Zb = = = 199682.36 cm3
Yb 67.692
Balok dan lantai dianggap bekerja sama sehingga terbentuk konstruksi komposit antara
balok pratekan dan lantai beton beton bertulang
f 'c = 45 MPa
t = 20 cm Bm Ec = 136 kg/cm2
f 'c = 45 MPa
Ec = 135.76 kg/cm2
Dengan mengambil lebar manfat lantai = 0,8 x = 1.7 m, maka dapat dianggap bahwa kekakuan
beton pratekan dan lantai adalah sama.
Tabel 1
Balok pratekan sendiri
Tabel 2
A Y A.Y A.Y2 Io
Penampang
(Cm2 ) (Cm) (Cm )
3
(Cm )
4
(Cm4 )
Lantai 1700 10 17000 170000 113333.333
Balok 5325 102.308 544791.667 55736706.1 13516839.5
Jumlah 7025 112.3083 561791.667 55906706.1 13630172.9
I Composit 24610206.1
Zct = = = 307741.657 Cm3
Yct 79.970
I Composit 24610206.1
Zcb = = = 273356.661 Cm3
Ycb 90.030
Langkah 2
Perhitungan tegangan
Balok pratekan memikul beban :
- Beban mati (DL)
Balok pratekan = 1278 Kg/m'
Lantai kendaraan = 800 Kg/m'
Lapisan Aspal = 352 Kg/m'
Berat air hujan = 0.08 Kg/m'
Beban melintang
(balok diagfragma) = 550 kg/m'
qdl = 2980.080 kg/m'
- Beban hidup (LL)
Beban merata p = 1028.571 kg/m
Beban garis P = 5610.390 kg/m
Beban hidup trotoar = 366.000 kg/m
qLl = 7004.961 kg/m
Beban akibat berat sendiri balok, plat lantai atap dipikul oleh balok pratekan
* Momen akibat balok pratekan (MG)
MG = 1/8 1278 x 20 2 = 63900 Kg.m
MG 6390000
fGt = = = 38.91072 Kg/cm2
Zt 164222.1
MG 6390000
fGb = = = -32.00082 Kg/cm2
Zb 199682.4
Langkah 3
Menentukan tegangan akibat beban luar
Beban akibat beban aspal, air hujan & beban hidup dipikul oleh penampang komposit
(balok + lantai)
* Momen akibat beban luar (air hujan dan aspal) (Mws)
Mws = 1/8 352.08 x 20 2 = 17604 Kg.m
Mws 1760400
fwsts = = = 5.720383 Kg/cm2
Zct 307741.7
Mws 1760400
fwsb = = = -6.439938 Kg/cm2
Zcb 273356.7
Ytc - t
fwst = x fwsts
Ytc
79.970 - 20
= x 5.7204 = 4.289757 Kg/cm2
79.970
Tabel 3
Hasil-hasil yang diperoleh dari langkah 2 & 3
ft fb f ts
Momen (kg.cm)
(kg/cm2 ) (kg/cm2 ) (Cm3 )
MG = 6390000 38.910723 -32.0008238 -
Mss = 4000000 24.3572601 -20.0318146 -
Mdd = 2750000 16.7456163 -13.7718725 -
Mws = 1760400 4.28975657 -6.43993819 5.72038254
ML = 5142857.14285714 12.5321548 -18.8137254 16.7116054
MPS = 1402597.4025974 3.41786039 -5.13101601 4.55771057
ML = 1830000 4.4593584 -6.6945506 5.94654627
Total 104.71273 -102.883741
f ts
ft
ytc +
ybc
-
fb
bo
F F.e1 F.e2
fc sisa = + +
A Zcb Zcb
F F x 53 F x 31
88.0345 = + +
5325 273356.661 273356.661
F = 178631 Kg
82.31 cm
150 cm
CGC
67.69 cm CGS
e = 52.692 cm
15 cm
Digunakan kawat diameter 5 mm ; jenis IS - 1343
Luas satu kawat = 19.625 mm2 = 0.19625 cm2
dengan tegangan karakteristik = σ izin 19000 kg/cm2
P= 100 kg/m'
15 x 15 qLL = 500 kg/m2
90
20
20
77 15 cm
0.65 m 0.80 m
Mu = 263.089 kgm
d = 20 - 3 = 17 cm
Mn = Mu = 263.089 = 328.860859 kgm
0.8 = 3225138.45 Nmm
Rn = Mu = 2580110.7583125 = 0.1116
b d2 0.8 x 1000 x 170 2
ρ = 1 1 - 1 - 2 m Rn
m fy
= 1 1 - 1 - 2 #REF! . 0.1116
#REF! #REF!
= #REF!
Gelagar memanjang direncanakan sebagai balok komposit ; faktor kekakuan melintang tidak
diperhitungkan.
80 cm d = 30.3 inch = 77 cm
Pembebanan :
* Akibat beban murni :
akibat pelat = 0.2 x 0.8 x 2500 = 400 kg/m
akibat girder = 140% x 198 = 277.2 kg/m
~ Abutment II
Elevasi Sondir = + 121.75 m
Elevasi Kaki poer = + 116.25 m
Elevasi tanah keras = + 121.75 - 15 = 106.75 m
Direncanakan panjang tiang pancang = 15 - 5.5 = 9.5 10 m
Data sondir : qc = 150 kg/cm2
STf = 800 kg/cm
~ Abutment I
qc . A STf . K A = 1/4 p d2
Q = +
3 5 = 1/4 . 3,14 . 40 2
= 1256 cm2
= 83.524 ton
~ Abutment II
qc . A STf . K A = 1/4 p d2
Q = +
3 5 = 1/4 . 3,14 . 40 2
= 1256 cm2
= 82.896 ton
0.50
1.25
1.25
0.50
1.00 1.50 1.50 1.50 1.50 1.50 1.50 1.00
S ³ 3
Sn = 150 cm dan Sm = 125 cm
P1
P2 P0
P3
X3 X4 P4
P5
X2 X5 P6
X1 X6
Analogi :
P2 : P1 = X1 : X2 P4 = P1.(X4/X1)
P2 = P1.(X2/X1) P5 = P1.(X5/X1)
P3 = P1.(X3/X1) P6 = P1.(X6/X1)
M. X1
P1 =
(2X12 + X22 + 2X32 + 2 X42 + X52 + 2 X62)
DIMANA :
M = 282.03968 - 240.23076 = 41.80892
X1 = 4.5 m X4 = 1.5 m
X2 = 3.0 m X5 = 3.0 m
X3 = 1.5 m X6 = 4.5 m
41.80892 x 4.50
PM =
( 2. 4.5 ^2 + 3.0 ^2 + 2. 1.5 ^2 + 2. 1.5 ^2 + 3.0 ^2 + 2. 4.5 ^2)
188.14016
PM = = 1.742 Ton
108.00
V
PMAKS = + PM
n
699.3256
PMAKS = + 1.742
11
A B B A
A A
C D C
D E C
C A
A B B A
A B
1. Metode Feld
3 8
Effisiensi Tiang A = 1 - =
11 11
4 7
Effisiensi Tiang B = 1 - =
11 11
4 7
Effisiensi Tiang C = 1 - =
11 11
4 7
Effisiensi Tiang D = 1 - =
11 11
8 32
4 Buah Tiang A = 4 x Eff A = 4 =
11 11
7 28
4 Buah Tiang B = 4 x Eff B = 4 =
11 11
7 14
2 Buah Tiang C = 2 x Eff C = 2 =
11 11
7 7
1 Buah Tiang D = 1 x Eff D = 1 =
11 11
81
Total Eff. = = 7.3636
11
7.3636
Effisiensi Satu Tiang = = 0.6694
Effisiensi Satu Tiang = = 0.6694
11
q (n - 1) m + (m - 1) n
SFf . N = 1 - .
90 m .n
Dimana : 40
q = Arc Tan = 17.7447 0
125
m =
3
n =
7
17.74 7- 1 3+ 3- 1 7
SFf . N = 1 - .
90 3. 7
= 0.69956
= 77.2977 ton
= 76.8584 ton
1256 . 156767
Kv = 2.2925 . = 180557 kg/cm
2500
E = 156767 kg/cm
p
I = . D4 = 125664 cm4
I = . D4 = 125664 cm4
64
4 k.D
b = = 0.0071956072 cm-1
4EI
k = ko . y-1/2 = 5.2812204 kg/cm2
ko = 0,2 . Eo . D-3/4 = 5.28122
Eo = 28 N = 420 kg/cm2
Untuk kemiringan tiang pancang dianggap qi = 0, hal ini adalah kondisi kritis pada
stabilitas abutment.
dx = 0.48097962 cm
dy = 0.35210576 cm
a = 0.00354976 rad
Pni = Kv . dyi
PHi = K1 dx - K2 a
PH1 = 6879.12264 kg
PH2= 6879.12264 kg
PH3 = 6879.12264 kg
Mt1 = 25179.7002 kg m
Mt2= 25179.7002 kg m
Mt3 = 25179.7002 kg m
Kontrol !!!
SHi = n . PHi = 89428.5943
SVi = 5 . PN1 + 3 PN2 + 5 PN3 =
Mti = S (Mti + Vi . Xi)
= n . Mti + 5 V1 . 125 + 5 V3 (-125)
=
a. diangkat
a L - 2a a
M1 M3
M2
4a2 + 4a L - L2 =0 L = 10 m
4a2 + 4a 10 - 10 2= 0
4 a2 + 40 a - 100 = 0
Dengan rumus ABC diperoleh :
a1 = 2.07107
a2 = -12.071 (tidak memenuhi)
b. diangkat
2a2 - 4a 10 - 10 2= 0
L-a 2 a2 + 20 a - 100 = 0
Dengan rumus ABC diperoleh :
a1 = 3.66025
a2 = -13.66 (tidak memenuhi)
Jadi keadaan yang paling menentukan adalah keadaan b. (Mmaks = 2020.29 kgm)
Penulangan diambil = 12 19
PERENCANAAN JEMBATAN
BAB III
PERHITUNGAN KONSTRUKSI BANGUNAN BAWAH
2
I
0.7 II
0.7
III IV
4 Pa1
Pp1
0.3 VI VII
Pp2
0.6 VIII
Pp3
2 1 2
Arif
PERENCANAAN JEMBATAN
S F.X 25.9245
X = = = 2.46 m
SF 10.53
S F.Y 27.991
Y = = = 2.66 m
SF 10.53
Arif
PERENCANAAN JEMBATAN
Beban mati
* Berat aspal = 770 kg/m
* Berat lantai kendaraan = 3024 kg/m
* Berat gelagar induk = 7837.87 kg/m
* Berat trotoar = 993.6 kg/m
* Berat pipa sandaran = 96.48 kg/m
* Berat beton pengisi = 552 kg/m
q = 13274 kg/m
Beban hidup
20
* Koefisien kejut (K) = 1 + = 1.22
50 + 40.0
12 1
* Beban terpusat (P) = . 5.5 + . 1.5 . 1.22 = 33333 kg
2.75 2
2.2 1
* Beban jalur (q) = . 5.5 + . 1.5 . 1.5 = 7500 kg
2.75 2
Reaksi total
* Beban mati = 1/2 . 13274 . 40.0 + 1/2 . 6231.36 = 268595 kg
Beban terpusat = = 33333 kg
Beban merata = 1/2 . 7500 = 3750 kg
Beban hidup trotoar = 1/2 . 1000 . 40.0 = 20000 kg
S Rtot = 325678 kg
Arif
PERENCANAAN JEMBATAN
~ Gaya normal
N = SG + SB + R
= 25848.5 + 25272 + 325678
= 376799 kg
MT = N . X
SH = Pa + HR + K - Pp
Nf = N . Tan j
Arif
PERENCANAAN JEMBATAN
~ Kontrol kestabilan
- Stabilitas terhadap guling
Syarat : MT > 2
MG
- Stabilitas terhadap gaya vertikal, titik tangkap harus berada didaerah pusat.
Penulangan Abutment
0.3
I I
Pa
II II
Pp
2 1 2
III IV
Potongan I - I
Pa = 1/2 . gt . h2 . Ka = 1/2 . 1.7 . 2 2 . 0.35 = 1.17971 kg/m
M = Pa'
Arif
PERENCANAAN JEMBATAN
Mu = 0 kg.cm
fy2 Mu
AS2 - fy . d. AS. + = 0
1,7 . fc' .b f
0 2 0
AS2 - 0 . 0 . AS. + = 0
1.7 0 0 0.8
f 16 - 20 = 10.05 cm2
Kontrol
1.4 0
rmin = = = ###
fy 0
As. 10.05
rada = = = ### #DIV/0!
b. d 0 . 0
= ### ###
Sehingga :
.
st = + = ### + ###
Arif
PERENCANAAN JEMBATAN
st min = 0 - 0 = 0
Arif
BAB VI
PERHITUNGAN KONSTRUKSI BANGUNAN BAWAH
7.0 m
12
P = = 4.364 t/m
2.75
~ Beban jalur
1.1
q = 2.2 - .( L - 30 )
60
1.1
= 2.2 - .( 45 - 30 )
60
= 1.925 t/m2
PNH = (q . 5,5) . 100% + (q . 1,5) . 50% . 0,5 . L + (P . 5,5) . 100% + (P . 1,5) . 50%
0.65 m
I
0.65 m
I
II 0.9 m
III 0.4 m
IV V 0.4 m
0.7 m
5.5 m
VI
2.35 m
0.3 m
VII VIII
IX 0.5 m
1.45 0.6 1.45
My 280.306
Yca = = = 1.9011 m
G 147.444
b. Sayap
2.7 m 0.2 0.6
0.65 m I
0.9 m
II
II
0.4 m
0.4 m III
IV
1.05 m V
VI
1.30 VII
Torsi Mx = 43.2934 tm
57.8061
y = = 3.15 m
18.3528
c. Berat tanah
0.2 0.2 0.6
0.65 m I
1.3 m II
0.4 m II
IV
I 0.7 m
2.35 m V
0.3 m VI
0.5 m
1.45 0.6 1.45
Torsi Mx = 120.107 tm
292.73
y = = 2.764 m
105.908
Pa1
Pa2
1.7 m
Pa2 = 1/2 gt . H2 . Ka . L
= 1/2 . 1.8 . 5.5 2 . 0.35 . 11
= 104 ton
Pa total = 127 t
= 0.8436781518
0.9901 . 2.07045
= 0.41156
- Pasif
KEP= cos2 (f - fo) 0.8436781518
=
sin f . sin (f - fo) 0.19168
cos2 fo 1 - 2 0.9901 . 1 - 2
cos fo 0.99504
= 0.8436781518
0.9901 . 0.31483
= 2.70661
- Pasif
PEp = 1/2 gt . H2 . KEp . L
= 1/2 . 1.8 . 1.70 2 . 2.71 . 11
= 77.44 ton
5. Beban Angin
1. Beban angin tegak lurus
(50% . (30% + 50%) . (L - 5) - H . 150 + 100% . L . 2 . 150)
Ar =
2
Dimana : L = 45 m
H = 3.55 m
Ar = -7008.25 t
Menurut ketentuan gaya angin yang dipilih adalah arah memanjang Al = 2,1 t setinggi
H = 5,5 m
MAl = 2,1 . 5,5 = 11.55 tm
0,3 Mp + Ma
Tg = 2p . h3
3 EI . g
Dimana : Mp = 147.444
Ma = 242.213
E = 6400 sb = 6400 225 = 960000 t/m2
I = 1/12 . 3.5 . 11 3 = 388.208 m4
g = 9.8 m/det2
h = 5.5 m
2. KOMBINASI II
Muatan V (ton) H (ton) MV ton.m MH (ton.m)
M 550.3377 240.23076
Ta -44.122711 -206.12123
Gg -36.331875 -143.51091
A -2.1 -11.55
125% 550.3377 -82.554586 240.23076 -361.18214
100% 440.27016 -66.043669 192.184608 -288.94571
3. KOMBINASI III
Muatan V (ton) H (ton) MV ton.m MH (ton.m)
M 699.325626 -44.122711 240.23076 -206.12123
Rm -7.4493963 -48.793546
Gg -36.331875 -143.51091
A -2.1 -11.55
140% 699.325626 -90.003982 240.23076 -409.97568
100% 499.518304 -64.288559 171.5934 -292.83977
4. KOMBINASI IV
Muatan V (ton) H (ton) MV ton.m MH (ton.m)
M 550.3377 240.23076
Gh -40.80093 -167.02813
Tag -72.704593 -256.0314
150% 550.3377 -113.50552 240.23076 -423.05953
100% 366.8918 -75.670349 -282.03968
Dari tabel diatas diperoleh kombinasi maksimum
Vertikal = 699.326 t
Horisontal = 75.6703 t
Mv = 240.231 tm
Mh = 282.04 tm
0.65 m
1.3 m
0.4 m
2.35 m
I III II I
0.3 m VI
0.5 m
1.45 0.6 1.45
III II
I. Potongan I - I
q = 1.08 tm/m2
II
III
IV V
4.70 m
Pa1
VI
Pa2
I I
Diketahui :
Ls = 11 m
Pa total = 95.25 t
SM = M1 + M2 = 164.407 tm
SM 164.407
y= = = 1.726 m
SP 95.2537
Bangunan bawah
a. Berat abutment
I 2.45 4.375 3.432 - - 8.4084
II 2.55 3.6 9.504 - - 24.2352
III 1.75 2.95 21.12 - - 36.96
IV 2.28333 2.61667 3.696 - - 8.4392
V 1.21667 2.61667 3.696 - - 4.4968
VI 1.75 1.375 48.312 - - 84.546
b. Tekanan tanah
Pa1 - 2.35 19.3736 45.528
Pa2 - 1.56667 75.8801 118.879
517.38 181.936 515.470 213.901
fy2 Mu
AS2 - fy . d. AS. + = 0
1,7 . fc' .b f
3000 2 3015691940.6
AS2 - 3000 . 960 . AS. + = 0
1.7 223.5 1000 0.8
Kontrol
1.4 1.4
rmin = = = 0.00467
fy 300
As. 1767.15
rada = = = 0.00184
revisi tulangan
b. d 1000 . 960
= 0.02691 Ok !!!
II. Potongan II - II
II I
1.7
0.3 1 II
Pp
0.5 2
1.45 0.6 1.45
II
fy2 Mu
AS2 - fy . d. AS. + = 0
1,7 . fc' .b f
3000 2 93297233.443
AS2 - 3000 . 500 . AS. + = 0
1.7 223.5 1000 0.8
Kontrol
1.4 1.4
rmin = = = 0.00467
rmin = = = 0.00467
fy 300
As. 2454.37
rada = = = 0.00491 Ok !!!
b. d 1000 . 500
= 0.02691 Ok !!!
0.65 m I
0.9 m
II
0.4 m
0.4 m III
IV
1.05 m V
VI
1.30 VII
0.3 m 1.75
VIII IX
0.5 m X
1.45 0.6 1.45
fy2 Mu
AS2 - fy . d. AS. + = 0
1,7 . fc' .b f
3000 2 4098465614.3
AS2 - 3000 . 500 . AS. + = 0
1.7 223.5 1000 0.8
Kontrol
1.4 1.4
rmin = = = 0.00467
fy 300
As. 3926.99
rada = = = 0.00785 Ok !!!
b. d 1000 . 500
= 0.02691 Ok !!!
VI. 2. PERHITUNGAN PIER JEMBATAN
1
#REF!
I
1
II
0.5 III IV
0.5 8.75
19 ### m
###
6
0.5
VI VII
1
VIII 1
1.5 1 1.5
Tekanan air pada pier (P) = K . V2 Dimana : K = Koef. Bentuk = 0,075 (balok persegi)
V= 2.287 m/det
P = 0.075 . 2.287 2 = 0.392 t/m2
Penulangan Pier
#REF!
I
1
II
0.5 III IV
0.5 8.75
19 #REF! m
###
6
0.5
VI VII
1
VIII 1
1.5 1 1.5
Bangunan bawah
a. Berat abutment
I 0.5 #REF! #REF! - - #REF!
II 0 #REF! 4.8 - - 0
III 0.66667 20.8333 0.3 - - 0.2
IV 0.66667 20.8333 0.3 - - 0.2
V 0 11 48 - - 0
VI 1 1.16667 0.9 - - 0.9
VII 1 1.16667 0.9 - - 0.9
VIII 0 0.5 9.6 - - 0
b. Tekanan Air
Pa - #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
Penulangan Pier
#REF!
I
1
II
I I
0.5 III IV
0.5 8.75
V
19 #REF! m
###
II III II
6
0.5
VI VII
1
VIII 1
1.5 1 1.5
III
I. Potongan I - I
sa 1740
fo = = = Err:509
s
n. b ### . ###
M #REF!
eo1 = = = #REF! m
N #REF!
1 1
eo2 = . ht = . 1 = 0.033 m
30 30
lk 1
e1 = C 2 ht = 7.58 1 = 0.0758 m
100 . ht 100 . 1
e2 = 0,15 . ht = 0.15 m
e = eo + e1 + e2 = #REF! m
h = ht - 5 = 95 cm
95
Ca = = Err:509
### . #REF!
1 . 1740.0
ea #REF!
= = ### Dari tabel diperoleh i = 3.97
h 0.95
sa 1740
fo = = = Err:509
n . sb ### . ###
M #REF!
eo1 = = = #REF! m
N #REF!
1 1
eo2 = . ht = . 1 = 0.033 m
30 30
eo #REF!
= = ### Dari tabel diperoleh C = 7.7
ht 1
lk 1
e1 = C 2 ht = 7.7 1 = 0.077 m
100 . ht 100 . 1
e2 = 0,15 . ht = 0.15 m
e = eo + e1 + e2 = #REF! m
95
Ca = = Err:509
### . #REF!
1 . 1740.0
ea #REF!
= = ### Dari tabel diperoleh i = 1.47
h 0.95
Err:509
A = A' = = ### cm2 (tulangan simetris)
1.47
V M #REF! #REF!
smax = + = + = #REF! t/m
A w 5.250 3.33333
V M #REF! #REF!
smin = - = - = #REF! t/m
A w 5.250 3.33333
#REF!
sa 1740
fo = = = Err:509
n . sb ### . ###
M #REF!
eo1 = = = #REF! m
N #REF!
1 1
eo2 = . ht = . 1 = 0.033 m
30 30
eo #REF!
= = ### Dari tabel diperoleh C = 7.69
ht 1
lk 1
e1 = C 2 ht = 7.69 1 = 0.0769 m
100 . ht 100 . 1
e2 = 0,15 . ht = 0.15 m
e = eo + e1 + e2 = #REF! m
h = ht - 5 = 95 cm
95
Ca = = Err:509
### . #REF!
1 . 1740.0
ea #REF!
= = ### Dari tabel diperoleh i = 2
h 0.95
Err:509
A = = ### cm2
2
qc . A STf . K A = 1/4 p d2
Q = +
3 5 = 1/4 . 3,14 . 40 2
= 1256 cm2
= 51.0773 ton
Jumlah tiang pancang
V #REF!
n =
Q
=
51.0773
= ### » 11 buah
0.50
1.25
1.25
0.50
S ³ 3
Sn = 150 cm dan Sm = 125 cm
P1
P2 P0
P3
X3 X4 P4
P5
X2 X5 P6
X1 X6
Analogi :
P2 : P1 = X1 : X2 P4 = P1.(X4/X1)
P2 = P1.(X2/X1) P5 = P1.(X5/X1)
P3 = P1.(X3/X1) P6 = P1.(X6/X1)
M. X1
P1 =
(2X12 + X22 + 2X32 + 2 X42 + X52 + 2 X62)
DIMANA :
M = #REF! - #REF! = #REF!
X1 = 4.5 m X4 = 1.5 m
X2 = 3.0 m X5 = 3.0 m
X3 = 1.5 m X6 = 4.5 m
#REF! x 4.50
PM =
( 2. 4.5 ^2 + 3.0 ^2 + 2. 1.5 ^2 + 2. 1.5 ^2 + 3.0 ^2 + 2. 4.5 ^2)
#REF!
PM = = #REF!
108.00
V
PMAKS = + PM
n
0.0000
PMAKS = + #REF!
11
A B B A
A A
C D C
D E C
C A
A B A
B
A B
1. Metode Feld
3 8
Effisiensi Tiang A = 1 - =
Effisiensi Tiang A = 1 - =
11 11
4 7
Effisiensi Tiang B = 1 - =
11 11
4 7
Effisiensi Tiang C = 1 - =
11 11
4 7
Effisiensi Tiang D = 1 - =
11 11
8 32
4 Buah Tiang A = 4 x Eff A = 4 =
11 11
7 28
4 Buah Tiang B = 4 x Eff B = 4 =
11 11
7 14
2 Buah Tiang C = 2 x Eff C = 2 =
11 11
7 7
1 Buah Tiang D = 1 x Eff D = 1 =
11 11
81
Total Eff. = = 7.3636
11
7.3636
Effisiensi Satu Tiang = = 0.6694
11
q (n - 1) m + (m - 1) n
SFf . N = 1 - .
90 m .n
Dimana : 40
q = Arc Tan = 17.7447 0
125
m =
3
n =
7
17.74 7- 1 3+ 3- 1 7
SFf . N = 1 - .
90 3. 7
= 0.69956
= 47.6812 ton
1256 . 156767
Kv = 2.2925 . = 180557 kg/cm
2500
E = 156767 kg/cm
p
I = . D4 = 125664 cm4
64
4 k.D
b = = 0.0071956072 cm-1
4EI
k = ko . y-1/2 = 5.2812204 kg/cm2
ko = 0,2 . Eo . D-3/4 = 5.28122
Eo = 28 N = 420 kg/cm2
Untuk kemiringan tiang pancang dianggap qi = 0, hal ini adalah kondisi kritis pada
stabilitas abutment.
dx = #REF! cm
dy = #REF! cm
a = #REF! rad
Pni = Kv . dyi
PHi = K1 dx - K2 a
PH1 = #REF! kg
PH2= #REF! kg
PH3 = #REF! kg
Mt1 = #REF! kg m
Mt2= #REF! kg m
Mt3 = #REF! kg m
a. diangkat
a L - 2a a
M1 M3
M2
4a2 + 4a L - L2 =0 L = 10 m
4a2 + 4a 10 - 10 2= 0
4 a2 + 40 a - 100 = 0
Dengan rumus ABC diperoleh :
a1 = 2.07107
a2 = -12.071 (tidak memenuhi)
b. diangkat
2a2 - 4a 10 - 10 2= 0
L-a 2 a2 + 20 a - 100 = 0
Dengan rumus ABC diperoleh :
a1 = 3.66025
a2 = -13.66 (tidak memenuhi)
Jadi keadaan yang paling menentukan adalah keadaan b. (Mmaks = 2020.29 kgm)
Penulangan diambil = 6 f 19