PERENCANAAN JEMBATAN

BAB I
KEDALAMAN PENGGERUSAN

Data Sungai :

+ 10.4 + 10.4
A B = 25 m
MAB : + 7.38 B

+ 3.32
C
b = 20 m

- Lebar rata-rata dasar Sungai (b) = 20 m


- Lebar rata-rata muka air banjir (B) = 25 m
- Kemiringan rata-rata talud Sungai (m) = 0.6158
- Kemiringan muka air aliran (i) = 0.0057

Menentukan debit banjir (Q) :

Q=A.V Dimana : Q = Debit banjir (m3/dt)


A = Luas penampang basah (m2)
V = Kecepatan aliran (m/dt)

Rumus manning untuk kecepatan aliran :


1
V= . R 0.67 i. 0.5
n

Dimana : n = Koefisien kekasaran Manning diambil 0.025 (tanah)


R = Jari - jari hidrolis (m)
i. = Kemiringan muka air aliran

A A = b + m . h . h , h = tinggi muka air banjir


R =
K = 20 + 0.62 . 4.06 . 4.06
= 91.35 m2

K = b + 2 h 1 + m2
2
= 20 + 2 . 4.06 1 + 0.62
= 29.536 m

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Jadi A 91.35
R = = = 3.0928 m
K 29.536

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

1 0.67 0.5 1 0.67 0.5


V= . R i. = . 3.0928 . 0.0057
n 0.025

= 6.4348 m/dt

Sehingga debit banjir (Q) :

Q=A.V = 91.35 . 6.4348


= 587.82 m3/dt

Menentukan kedalaman penggerusan (d) :


Q 0.333
d = 0.473 .
f

588 0.333
= 0.473 .
1.25

= 3.6707 m

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


Perencanaan Bangunan Atas IV -

4. 1. Perhitungan Pipa Sandaran

Pipa sandaran direncanakan :


- Pipa bulat f (D)= 76.2 mm Diameter lubang (d) = 76.2 - 2 . 2.3 = 7.16 cm
- Tebal pipa (t) = 2.3 mm
- Jarak antar tiang = 2 m

Sifat-sifat penampang pipa :


(A) = LD - Ld = 1/4 . p . D2 - 1/4 . p . d2 = 1/4 . p 7.62 2
- 7.16 2
= 5.3419 cm2

p p 4 4
I = . D4 - d4 = . 7.62 - 7.16 = 36.502 cm4
64 64

p p 3 3
W = . D3 - d3 = . 7.62 - 7.16 = 7.4043 cm4
32 32

Untuk 1 meter panjang pipa :


Berat isi baja tuang = 7.85 t/m3 = 7850 kg/m3
Berat pipa sandaran = A x 1 x Berat isi baja tuang
= 0.0005342 . 1 . 7850 = 4.1934 kg/m

Perhitungan pembebanan :
- Berat sendiri = 4.1934 kg/m
- Beban luar (beban orang) = 100 kg/m
qv = 104.19 kg/m

- Beban horisontal qh = 100 kg/m

2 2 2 2
qtot = qv + qh = 104.19 + 100

= 144.42 kg/m

Momen maksimum terjadi dimana tiang sandaran menjadi perletakan :


1 1 2
Mmax = . qtot . L2 = . 144.42 . 2 = 72.208 kgm
8 8
= 708148.68 Nmm

Kontrol lendutan :
M 708148.68
fytd = = = 95.64 N/mm2
W 7404.2799

250 250
fizin = = = 217.39 N/mm2
gm 1.15 fytd < fizin Aman !!!

4.2 Perhitungan Tiang Sandaran

H = 100 kg/m H = 100 kg/m

45 cm Pot. I - I
I I

h = 16 cm
cm
65

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -
65

b= 10 cm

16 cm 100 cm

Direncanakan :
- Ukuran tiang sandaran = 10 . 16 cm2
- Jarak antar tiang = 2 m
- gbeton = 2.5 t/m3

Beban-beban yang bekerja pada tiang sandaran :

a. Beban vertikal
- Berat sendiri pipa sandaran = 2 . 4.1934 . 2.00 = 16.774 kg
- Berat sendiri tiang sandaran = 0.1 . 0.16 . 1 . 2500 = 40 kg
N = 56.774 kg

a. Beban horisontal
Tiang-tiang sandaran pada tepi jembatan harus diperhitungkan untuk dapat menahan
beban sebesar 100 kg/m yang bekerja pada setinggi 90 cm diatas lantai kendaraan.
(PPPJJR, SKBI - 1.3.28 - 1987)
P = 100 . 2 = 200 kg
M = 200 . 1.1 . = 220 kgm = 2157540 Nmm

- Mutu baja (fy) = 240 N/mm2


- Mutu beton (f'c) = 25 N/mm2

fy2 Mu
AS2 - fy . d. AS. + = 0
1,7 . fc' .b f

2
2400 2157540
AS2 - 2400 . 160 . AS. + = 0
1.7 250 100 0.8

135.52941 AS2 - 384000 AS. + 2696925 = 0

Dengan rumus ABC diperoleh : AS. = 7.041 cm2


2 f 19 = 5.7 cm2

Kontrol

1.4 1.4
rmin = = = 0.0058
fy 240

As. 5.67
rada = = = 0.0354 Ok !!!
b. d 10 . 16

0.85 . f'c 600 0.85 . f'c25 600


rmaks = 0.75 . b 1 . = 0.75 0.85
fy 600 + fy 240 600 + 240

= 0.0403 Ok !!!

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

4
1. Lantai trotoar

P= 100 kg/m'
2
10 qLL = 500 kg/m
90 16 I

20
20
I

75

25
56 20 45 1.75 m
16 50

Ditinjau jalur selebar 1 m :


MI-I = Momen pada irisan pertama
2 2
0.56 0.40
= P . 1.1 + 0.20 + 2500 . 1 + 0.20 . 2200 + 500 .
2 2

+ 0.10 . 0.16 . 1.10 . 2500 . 0.48

= 110 + 78.4 + 75.2 + 21.1 = 284.72 kgm

DI-I = 0.20 . 2500 . 0.56 + 0.20 . 2200 + 500 . 0.40 +


0.10 . 0.16 . 1.10 . 2500
= 700 kg

Penulangan : Akibat momen pada pembebanan tetap.

Cara Elastis : Beton K-325 sb = 110 kg/cm2


n = 19
Baja U-30 sa = 1740 kg/cm2

h = 20 - 3 = 17 cm

sa 1740
fo = = = 0.8325
n . sb 19 . 110

17
Ca = = 9.6413
19 . 284.72
1740 . 1.0

Ca = 9.6413 ) nw = 0.0115 z = 0.95


d = 0.2 ) f = 6.143 (OK)

0.0115
A = . 100 . 17 = 1.03 cm2
19

Amin = 0.25% b. h = 0.25% . 100 . 17 = 4.25 cm2

Amin > Aperlu

A = 4.25 cm2

dipilih tulangan : f 12 - 20 = 5.65 cm2

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

A' = A = 0.2 . 5.65 = 1.13 cm2


dipilih tulangan : f 8 - 30 = 1.68 cm2

Kontrol tebal plat dan tegangan-tegangan yang terjadi


Mu 284.72 kgm
1 1
zb = = = 0.5457
sa 1740
1 + 1 +
n . sb 19 . 110

Kb = 1/2 . zb (1 - 1/3 . zb) . sb


= 1/2 . 0.5457 ( 1 - 1/3 . 0.5457 ) . 110
= 24.554

28472
h' = = 3.4053 cm
100 24.554

Tebal plat yang diperoleh = h' + a = 3.4053 + 3 = 6.41 cm < 20 cm Ok !!!

Tegangan yang terjadi :

Mu 28472
sb ytd = = = 2.6739
A.h.f.n.z 5.65 . 17 . 6.14 . 19 . 0.95

sa ytd = n . f . sbytd = 19 . 6.14 . 2.6739 = 312.09 kg/cm2 < 1740 kg/cm2

Akibat gaya lintang :


8 D 8 700
tb = . = . = 0.47 kg/cm2
7 b . h 7 100 . 17

t'b = 0.47 kg/cm2 < t'b = 6.5 kg/cm2

Praktis tidak perlu tulangan geser

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

4.4. Perhitungan Lantai Kendaraan


Pembebanan pada lantai :
* Beban merata :
- Akibat berat sendiri = 0.2 1.0 2.50 = 0.5 t/m1
- Akibat berat aspal = 0.05 1.0 2.00 = 0.1 t/m1
- Akibat berat air hujan 0.05 1.0 1.00 = 0.05 t/m1
qDL = 0.65 t/m1
Jarak gelagar = 1.75 m
1 2
Mxm = . 0.65 . 1.75 = 0.199 tm
10

1
Mxm = . 0.199 = 0.066 tm
3

* Beban hidup- T :
- Beban roda :
T = 10 ton (Kelas I = 100 % . 10 = 10 ton
- Bidang kontak 40 . 70 cm2
:
10
- Muatan T disebarkan : T = = 35.714 t/m2
0.4 . 0.7
50 20

5 5
10 10
450 10 10
b = 0.7 a = 0.4

0
a = 20 +2 0.5 20 tg 45 = 40 cm = 0.4 m
0
b = 50 +2 0.5 20 tg 45 = 70 cm = 0.7 m

T 10
WL = =
a b 0.4 0.7

= 35.714 t / m2 x pias 1 meter


= 35.714 t / m'

Dipakai tabel Bittner (dari Dr. Ing Ernst Bittner)


dengan : Ix = 1.75 m
Iy = ~ (lantai tidak mampu menumpu pada diafragma)

* Dicari momen pada saat 1 (satu) roda pada tengah-tengah pelat :


X
tx = 70 tx 70
= = 0.45 fxm = 0.1499
y( ) 70 lx = 175 Ix 175
40 ty = 40 ty 40
= = 0.22857 fym = 0.1274
lx = 175 Ix 175

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

Dari tabel bittner (Mxm) :


0.5 - 0.45
0.1407 + 0.1444 - 0.1407 = 0.1426
0.5 - 0.4
0.5 - 0.45
0.1546 + 0.1597 - 0.1546 = 0.1572
0.5 - 0.4
0.5 - 0.45
0.1426 + 0.1572 - 0.1426 = 0.1499
0.5 - 0.4

Dari tabel bittner (Mym) :


0.3 - 0.2286
0.1053 + 0.1280 - 0.1053 = 0.122
0.3 - 0.2
0.3 - 0.2286
0.1111 + 0.1372 - 0.1111 = 0.12974
0.3 - 0.2
0.3 - 0.2286
0.122 + 0.12974 - 0.1215 = 0.1274
0.3 - 0.2

Mxm = 0.1499 . 35.714 . 0.40 . 0.70 = 1.4985 tm/m


Mym = 0.1274 . 35.714 . 0.40 . 0.70 = 1.2739 tm/m

Momen total :
Arah - x : Mxm = 0.199 + 1.4985 = 1.6976 tm/m'
Arah - y : Mym = 0.066 + 1.274 = 1.3403 tm/m'

* Dicari momen pada saat 2 (dua) roda berdekatan dengan jarak antara as ke as
minimum = 1,00 m
50 50
100

0.4
10

10
70 30 70 72.5 10
72.5

175

Luas bidang kontak diatas dapat dihitung atas 2 keadaan (I & II) sebagai berikut :

(I) (II)

= -

Keadaan - I : tx = 175 tx 175


= = 1 fxm = 0.2714
Ix = 175 Ix 175
ty = 40 ty 40
= = 0.22857 fym = 0.2129
Ix = 175 Ix 175

Dari tabel bittner (Mxm) :

= 0.2714

Dari tabel bittner (Mym) :


0.3 - 0.2286
0.1887 + . 0.1926 - 0.1887 = 0.1915
0.3 - 0.2

0.3 - 0.2286
0.2160 + . 0.2237 - 0.2160 = 0.2215
0.3 - 0.2

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

0.3 - 0.2286
0.1915 + . 0.2215 - 0.1915 = 0.2129
0.3 - 0.2

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

Mxm = 0.2714 . 35.714 . 0.400 . 1.75 = 6.7850 tm/m


Mym = 0.2129 . 35.714 . 0.400 . 1.75 = 5.3231 tm/m

Bagian - II : tx = 30 tx 30
= = 0.17143 fxm = 0.22971
Ix = 175 Ix 175
ty = 40 ty 40
= = 0.22857 fym = 0.12445
Ix = 175 Ix 175

Dari tabel bittner (Mxm) :


0.2 - 0.1714
0.2160 + 0.2237 - 0.2160 = 0.2182
0.2 - 0.1
0.2 - 0.1714
0.2533 + 0.2714 - 0.2533 = 0.2585
0.2 - 0.1
0.2 - 0.1714
0.21820 + 0.2585 - 0.21820 = 0.22971
0.2 - 0.1

Dari tabel bittner (Mym) :


0.3 - 0.2286
0.1053 + 0.1280 - 0.1053 = 0.12151
0.3 - 0.2
0.3 - 0.2286
0.1111 + 0.1372 - 0.1111 = 0.12974
0.3 - 0.2
0.3 - 0.2286
0.12151 + 0.12974 - 0.1215 = 0.12445
0.3 - 0.1

Mxm = 0.2297 . 35.714 . 0.400 . 0.30 = 0.9845 tm/m


Mym = 0.12445 . 35.714 . 0.400 . 0.30 = 0.5334 tm/m

Jadi :
Mxm = (I) - (II) = 6.7850 - 0.9845 = 5.8005 tm/m
Mym = (I) - (II) = 5.3231 - 0.5334 = 4.7897 tm/m

Momen total :
Mxm = 0.199 + 5.8005 = 5.9996 tm/m
Mym = 0.066 + 4.7897 = 4.8561 tm/m

Dengan membandingkan momen Mxm dan Mym untuk beban 1 (satu) roda terhadap beban
2 (dua) roda diperoleh momen yang menentukan adalah sebagai berikut :
arah - x : Mxm = 5.9996 tm/m
arah - y : Mym = 4.8561 tm/m

0.3 - 0.2286
0.1053 + 0.128 - 0.1053 = 0.122
0.3 - 0.2
0.3 - 0.2286
0.1111 + 0.1372 - 0.1111 = 0.1297
0.3 - 0.2
0.3 - 0.2286
0.12151 + 0.1297 - 0.12151 = 0.12738
0.3 - 0.2

Penulangan :
arah - x : Mxm = 6000 kgm

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

h = 20 - 4 = 16 cm

16
Ca = = 1.9768
19 . 6000
1740 . 1.0

Ca = 1.9768 ) nw = 0.0682
d = 0.2 ) f = 2.333 > fo (OK)

0.0682
A = . 100 . 16 = 5.74 cm2
19

Mmin = 0.25% b. h = 0.25% . 16 . 100 = 4 cm2

Mperlu > Mmin A = 5.74 cm2


dipilih tulangan : f 12 - 15 = 7.54 cm2

A' = 0,2 A = 1.15 cm2


dipilih tulangan : f 8 - 30 = 1.68 cm2
arah - y : Mym = 4856 kgm
h = 20 - 3 = 17 cm

17
Ca = = 2.3345
19 . 4856
1740 . 1.0
Ca = 2.3345 ) nw = 0.0434
d = 0.2 ) f = 3 > fo (OK)

0.0434
A = . 100 . 17 = 3.88 cm2
19
dipilih tulangan : f 12 - 15 = 7.54 cm2

A' = 0,2 A = 0.78 cm2


dipilih tulangan : f 8 - 30 = 1.68 cm2

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

Akibat beban sementara :


Disini beban sementara adalah beban angin yang bekerja pada kendaraan.

2 . 5 . 1 . 150
Gaya pada roda =
1.75
2
= 857.14
= 0.857 Ton
ket : - tinggi kendaraan (2m)
1.75 - Lebar kendaraan (5 m)

Sehingga beban roda : T = 10


0.857 = +10.9 ton
10.9
Muatan T disebarkan : WL = = 38.776 ton / m2 x pias 1 meter
0.40 . 0.70
= 38.776 ton/m2

Ditinjau akibat beban 1 (satu) roda (yang menentukan) pada tengah-tengah pelat :
Mxm = 0.1499 . 38.776 . 0.40 . 0.70 = 1.6269 tm/m
Mym = 0.1274 . 38.776 . 0.40 . 0.70 = 1.3831 tm/m

Momen total :
Mxm = 0.199 + 1.6269 = 1.8260 tm/m
Mym = 0.066 + 1.3831 = 1.4495 tm/m

Penulangan plat lantai kendaraan

- Tebal plat (h) = 20 cm = 200 mm


- Penutup beton (p) = 40 mm
- Diameter tulangan utama yang diperkirakan
Arah x =  12 mm
Arah y =  12 mm
- Tinggi efektif (d) dalam arah y dan x
dx = h - p - 0.5  x
= 200 - 40 - 0.5 12
= 154 mm
- Tulanganlapangan arah x :

Mu = 1.2 MD + 1.6 ML 7) hal 75


= 1.2 0.199 + 1.6 1.8260
= 3.160 tm
= 31.605 KNm

mu 31.605
= = 1332.638 KN/m
b d2
2
1.0 0.154

Dari tabel untuk f'c = 25 M dan fy = 240 Mpa

mu 8) hal 46
= 1300 ρ = 0.0071
b d2
mu
= 1400 ρ = 0.0076
b d2

Dengan cara interpolasi diperoleh harga ρ untuk :

mu
= 1332.638
b d2
1332.64 - 1300
ρ = 0.0071 + 0.0076 - 0.0071
100

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

= 0.00726

ρ min = 0.0025 (tabel 7) *….)hal 51

ρ max = 0.0404 ( tabel 8) *….) hal 52

ρ > ρ min sehinga:

As = ρ b d
= 0.00726 x 1000 x 154
= 1118.5 mm2

Digunakan tulangan  12 - 100 = 1131 mm2 > 1118.5 mm2

- Tulanganlapangan arah y :

Mu = 1.2 MD + 1.6 ML 7) hal 75


= 1.2 0.066 + 1.6 1.4495
= 2.399 tm
= 23.988 KNm

mu 23.988
= = 1011.456 KN/m
b d2
2
1.0 0.154

Dari tabel untuk f'c = 25 M dan fy = 240 Mpa

mu 8) hal 46
= 1000 ρ = 0.0054
b d2
mu
= 1100 ρ = 0.0059
b d2

Dengan cara interpolasi diperoleh harga ρ untuk :

mu
= 1011.456
b d2

1011.46 - 1000
ρ = 0.0054 + 0.0059 - 0.0054
100

= 0.00546

ρ min = 0.0025 (tabel 7) *….)hal 51

ρ max = 0.0404 ( tabel 8) *….) hal 52

ρ > ρ min sehinga:

As = ρ b d
= 0.00546 x 1000 x 154
= 840.42 mm2

Digunakan tulangan  12 - 125 = 905 mm2 > 840.42 mm2


4.5 Perhitungan Balok Diagfragma

- Ditaksir ukuran balok diafragma 30 x 50


- Bentang balok diafragma L = 1.75 m

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

Beban-beban yang bekerja :

- Beban akibat berat sendiri balok diafragma :

Wd = 0.3 x 0.5 x 2500


= 375 Kg/m'

Momen yang terjadi :

M tumpuan = 1 12 . WD . L2

= 1 12 . 375 . 1.75 2

= 96 kgm = 0.957 KNm

M lapangan = 1 24 . WD . L2

= 1 24 . 375 . 1.75 2

= 47.9 kgm = 0.479 KNm


Perhitungan tulangan
1 Tulangan lapangan

- Tinggi balok (h) = 500 mm


- Selimut beton (p) = 40 mm
- Diameter tulangan utama (ØD) = 16 mm
- Diameter tulangan sengkang (ØS) = 8 mm

- Tinggi efektif (d) = h - p - ØS - 0.5 ØD

= 500 - 40 - 8 - 0.5 16

= 444 mm

MD = 0.479 KNm

Mu = 1.2 x MD = 1.2 x 0.479

= 0.574 KNm
mu 0.574
= = 9.709 KN/m
b d2
2
0.30 0.444
Diambil ρ = ρ min = 0.0058

As = ρ min b d

= 0.0058 x 300 x 444

= 772.56 mm2

Digunakan tulangan 4 Ø 16 = 804 mm2 > 772.56

2 Tulangan tumpuan

MD = 0.957 KNm

Mu = 1.2 x MD = 1.2 x 0.957

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

= 1.148 KNm

mu 1.148
= = 19.419 KN/m
b d2
2
0.30 0.444

Diambil ρ = ρ min = 0.0058

As = ρ min b d

= 0.0058 x 300 x 444

= 772.56 mm2
Digunakan tulangan 4 Ø 16 = 804 mm2 > 772.56
Kontrol lebar balok

Lebar minimum yang dibutuhkan :

4 x  16 (diameter tulangan utama) = 64 mm

2 x  8 (diameter tulangan sengkang) = 16 mm

3 x 25 (jarak minimum antar tulangan) = 75 mm

2 x 40 (selimut beton) = 80 mm
total = 235 mm

Jadi lebar balok 30 mm memadai, cukup disusun 1 baris


50

50

30 30

Tulangan Lapangan Tulangan Tumpuan

Gambar 4.6. Penulangan balok diafragma

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

0
= = ####
0 . 0
0 . 1.0
= #### ) nw = 0.0711
= 0.2 ) f = 2.279 > fo (OK)

0.0711 cm2
= . 100 . 0 = ###
0
dipilih tulangan : f - 15 = 7.54
#
### cm2
dipilih tulangan : f - 30 = 1.68 cm2
8
1449 tm/m
h = ### - 3 = ### cm cm2

#REF!
= = #REF!
0 . 1449
0 . 1.0
= #REF! ) nw = 0.0393
= 0.2 ) f = 3.167 > fo (OK)
0.0393 cm2
= . 100 . 0 = ###
0
dipilih tulangan : f # - 15 = 7.54

### cm2
dipilih tulangan : f 8 - 30 = 1.68 cm2

Ca
25 / 45 cm2

Ca
d Pembebanan :
- Akibat berat sendiri balok = 0.25 . 0.45 . 2500 . 1
A = 281.25 kg/m'

Balok melintang merupakan balok dalam beberapa tumpuan


1 1 2 kgm
Diambil Mtumpuan = ql2 = . 281.25 . 1.75 = 86.133
A' = 0,2 A = 10 10

arah - y : M
Mym
= = 86.133 kgm h= 45 - 5 = 40 cm

40
Ca = = 41.245
Ca 19 . 86.13
1740 . 1.0

Ca 12 b .h 12 . 25 . 40
= = 4.32 cm2
d s*au #

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

A 4 f 12 =

4.32 cm2
4.52 cm2
A' = 0,2 A =
*

H1

H2
Jadi A = Amin =
Berat sendiri

16 15 100 cm

Berat lapisan aspal


4.3 Perhitungan Lantai Lantai
Gambar Penampang TrotoarTrotoar

Berat pipa dan tiang sandaran


45

Beban
W1 hidup
= 0.2 x 1.15 x 2500 x 1.00 = 575 Kg
45

Gaya
W2horisontal
= 0.2pada
x tiang
1.00sandaran
x 2200 x 1.00 = 440 kg
20

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

20
W3 = 0.05 x 1.00 x 2000 x 1.00 = 100 kg

20
Gaya horisontal pada kerb:

W4 = 16.8 + 40 = 56.8 kg

MD W5 = 500 x 1.00 = 500 kg

Beban-beban yang bekerja pada lantai trotoar per meter:


H1 = 100 x 1.00 = 100 kg
-

- H2 = 500 x 1.00 = 500 kg


ML

-
1.15 1.00 1.00 0.16
= W1 + W2 + W3 + W4 + 1.00 + H1 1.10
2 2 2 2
- Mu

+ H2 0.20

-
= 871.94 Kgm

- 1.00
= W5
2

= 250 Kgm
-
= 1.2 MD + 1.6 ML

Momen yang
= terjadi
1.2 871.94
pada potongan
+ 1.6
I - I 250

= 1446.3 Kgm = 14174.02 Nm = 14.174 KNm

200 mm
= 40 mm
 = 12 mm
l 115
= = = 8.85 cm < h = # cm (ok)
13 13

d = h - p - 0.5 

= 200 - 40 - 0.5 12

= 154 mm

Direncanakan
Mu tebal14.174
plat h = KN/m2
2 = 2 = 597.656
Tebal penutup
b . D2
d beton
1.0 0.15
perkiraan diameter tulangan utama :

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

Kontrol hmin
= 25 Mpa ; fy = 240 Mpa
Perhitungan tulangan : *….) hal 46
Mu
= 500 ρ = 0.0026
d2 :
Tinggi befektif
. D2

Mu
= 600 ρ = 0.0032
d2
b . D2

Mu
= 597.656 KN/m2
d2
b . D2

597.656 - 500 0
ρ = 0.0026 + - 0.0026
100
Dari tabel 5.1.c
= 0.0032
f'c
ρ min = 0.0025 (tabel 7)

ρ max = 0.0404 ( tabel 8)


*….)hal 51
ρ > ρ min sehinga:
*….) hal 52
As = ρ b d
Dengan cara interpolasi
= 0.0032makax diperoleh
1000 xharga
154ρ untuk :
= 490.63 mm2

Digunakan tulangan  12 - 225 = # mm2 > 490.63 mm2

0.25 b h
As =
Beban-beban yang100
bekerja pada lantai kendaraan :

a. 0.25 1000 200

4.3 Perhitungan Lantai Trotoar

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

H1 = 100 kg

#
45
45
20
20 H2 = 500 kg

16 15 100

Gambar 4.5. Penampang Lantai Trotoar

Beban-beban yang bekerja pada lantai trotoar per meter panjang jembatan:

- Berat sendiri lantai trotoar ( W1 )

W1 = 0.2 x 1.15 x 2500 1.0 = 575 kg

- Berat beton pengisi ( W2 )

W2 = 0.2 x 1.0 x 2200 1.0 = 440 kg

- Berat lapisan aspal ( W3 )

W3 = 0.05 x 1.0 x 2000 1.0 = 100 kg

- Beban hidup (W4)

W4 = 500 x 1.0 = 500 kg

- Berat pipa dan tiang sandaran (W5)

W5 = 2 4.193 1.0 + 0.1 0.16 1.2 2500

= 56.387 kg

- Gaya horizontal pada tiang sandaran (H1)

H1 = 100 x 1.0 = 100 kg

- Gaya horizontal pada kerb (H2)

H2 = 500 x 1.0 = 500 Kg

Momen yang terjadi pada potongan I - I

1.15 1.15 1.00 0.16


MD = W1 + W2 + W3 + W5 + 1.15 + H1 1.2
2 2 2 2

+ H2 0.2

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -
+ H2 0.2

.
= 922.98 kgm

1.0 1.0
ML = W4 = 500 = 250 kgm
2 2

Mu = 1.2 MD + 1.6 ML

= 1.2 922.98 + 1.6 250

= 1507.58 kgm = 15.076 KNm

Penulangan lantai trotoar

- Direncanakan tebal plat = 20 cm = 200 mm

L 115
Kontrol hmin = = = 8.846 < 20 cm
13 13

- Penutup beton (p) = 40 mm `

- Rencana diameter tulangan utama Ø D = 12 mm

d = h - p - 0.5 ØD

= 200 - 40 - 0.5 12

= 154 mm

mu 15.076
= = 635.679 KN/m
b d2
2
1.0 0.154

Dari tabel untuk f'c = 25 M dan fy = 240 Mpa


mu 8) hal 46
= 600 ρ = 0.0032
b d2
mu
= 700 ρ = 0.0037
b d2

Dengan cara interpolasi diperoleh harga ρ untuk :

mu
= 635.679 KN/m
b d2

635.68 - 600
ρ = 0.0032 + 0.0037 - 0.0032
100

= 0.00338

ρ min = 0.0025 (tabel 7) *….)hal 51

ρ max = 0.0404 ( tabel 8) *….) hal 52

ρ > ρ min sehinga:

As = ρ b d
= 0.00338 x 1000 x 154

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -

= 520.27 mm2

Digunakan tulangan  12 - 200 = 565 mm2 > 520.27 mm2

Luas tulangan pembagi

0.25 x b x h
As =
100
0.25 x 1000 x 200
=
100
= 500 mm2

Digunakan tulangan  12 - 200 = 565 mm2 > 500 mm2

Jurusan Teknik Sipil - UKIP


PERHITUNGAN BALOK INDUK BENTANG L1 (POST-TENTIONING) = 25 m
Beban - beban yang bekerja :
* Pembebanan :
* Akibat beban mati
- Akibat pelat = 0.20 . 2500 . 1.75 = 875 kg/m'
- Akibat pavement = 0.10 . 2000 . 1.75 = 350 kg/m'
- Akibat air = 0.05 . 1000 . 1.75 = 87.5 kg/m'
qDL = 1312.5 kg/m'
= 1.3125 t/m'

* Akibat beban hidup


- Beban terbagi rata
1.1 Untuk L > 30 (PPPJJR 1987)
q = . L - 30
60

1.1
q = . 25 - 30 = -0.0917 t/m
60

q' = Untuk satu gelagar

-0.0917 . 1.75
q = = -0.0583 t/m
2.75

- Beban garis P = 12 t

20
- Koefisien kejut = 1 + = 1.27
50 + 25.0

P ' = Untuk satu gelagar

12 . 2.00
P' = . 1.2667 = 11.055 t/m
2.75

- Beban hidup trotoar


Untuk sebuah gelagar q = 1440 . 0.5 . 60%
= 432 kg/m

Langkah 1
Rencana penampang balok adalah sbb :

50

20 I
I
15 II II

15 15
20
15
55 135
III
25 25 Potongan A - A

25 IV IV

V
20
70

JURUSAN TEK. SIPIL UKI


50

20 I
BAGIAN LUAS (cm2) Yi MOMEN STATIS I
15 II II
I 1000 125 125000
II 225 110 24750 74.862 15 15
III 1900 67.5 128250 20
IV 625 28.333 17708.33333 60 135
V 1400 10 14000 III
TOTAL 5150 309708.3333 25 25

60.138 25 IV IV
Statis momen 309708.3333
Yb = = = 60.138 cm V
Luas 5150 20

Yt = 135 - Yb = 135 - 60.138 = 74.862 cm 70 mm

BAGIAN Ai (cm2) (Y - yi) (cm) Ai.(Y - yi)2 (cm4) Io (cm4) Ix (cm4)


I 1000 64.862 4207138.658 33333.333 4240471.992
II 225 44.862 452844.0622 1406.25 454250.3122
III 1900 7.362 102991.0401 1666666.667 1769657.707
IV 625 23.471 344301.1977 10850.694 355151.8921
V 1400 50.138 3519282.148 46666.667 3565948.814
TOTAL 5150 10385480.717

Ix 10385480.72
Zt = = = 138727.4848 cm3
Yt 74.862

Ix 10385480.72
Zb = = = 172695.4684 cm3
Yb 60.138

Untuk balok pratekan, digunakan mutu beton K-325


fc' = 0,33 f'ck = 0.33 x 325 = 107.3 kg/cm2
0,5
fc = 0,48 f'ck = 0.48 x 325 0.5
= 8.6533 kg/cm2
tb = 0,43 f'ck0,5 = 0.43 x 325 0.5 = 7.7519 kg/cm2
Ec pratekan = 6400 325 0.5 Ec lantai = 6400 325 0.5
= 115.37764 kg/cm2 = 115 kg/cm2
Balok dan lantai dianggap bekerja sama sehingga terbentuk konstruksi komposit antara balok pratekan
dan lantai beton beton bertulang
f 'c = 25 MPa
2
t = 20 cm Bm Ec = 115 kg/cm

f 'c = 25 MPa
Balok pracetak
prategang
Ec = 115.38 kg/cm2

1.75 m 1.75 m 1.75 m 1.75 m

Sistem struktur komposit

JURUSAN TEK. SIPIL UKI


Lebar efektif lantai beton (Bm) diberikan sbb :
1 Bm < L = 1.75 m
2 Bm < L/3 = 0.5833 m
3 Bm < 16 t = 3.2 m ( paling memenuhi)
4 Bm < 4 h = 5.4 m
5 Bm < 8 bo = 5.6 m

Dengan mengambil lebar manfaat lantai = 0,8 x 3.2 = 2.56 m, maka dapat dianggap bahwa kekakuan
beton pratekan dan lantai adalah sama.

Tabel 1
Balok pratekan sendiri

A = 5150 cm2 I balok = 10385481 cm2


Yt = 74.862 cm Zt = 138727.48 cm3
Yb = 60.138 cm Zb = 172695.47 cm3
Wb = 1236 kg/m'

Tabel 2

A Y A.Y A.Y2 Io
Penampang 2 3 4
(Cm ) (Cm) (Cm ) (Cm ) (Cm4 )
Lantai 2560 10 25600 256000 170666.667
Balok 5150 94.862 488541.6667 46344264.09 10385480.7
Jumlah 7710 104.86246 514141.6667 46600264.09 10556147.38

Yct = S AY / S A = 514142 / 7710 = 66.685 Cm


b
Yc = 155.000 - 66.685 = 88.315 Cm

I composit = ( Io + AY2 ) - Ac ( Yct )2


= ( 10556147 + 46600264.09 ) - [ 7710 ( 66.685 ) 2 ]
= ( 57156411.48 - 34285558.16 )
= 22870853.32 cm4

I Composit 22870853.32
Zct = = = 342968.2722 Cm3
Yct 66.685
I Composit 22870853.32
Zcb = = = 258969.1893 Cm3
Ycb 88.315

JURUSAN TEK. SIPIL UKI


Langkah 2
Perhitungan tegangan
Balok pratekan memikul beban
- Beban mati (DL)
Balok pratekan = 1236 Kg/m'
Lantai kendaraan = 875 Kg/m'
Lapisan Aspal = 350 Kg/m'
Berat air hujan = 87.5 Kg/m'

- Beban hidup (LL)

-0.0917 . 1.75
q = = -0.0583 t/m
2.75

- Beban hidup trotoar


Untuk sebuah gelagar q = 1440 . 0.5 . 60%
= 432 kg/m

- Beban titik
12 . 2.00
P' = . 1.2667 = 11.055 t/m
2.75

- Beban melintang (balok diagfragma)


= 281.3 kg/m'

(ditinjau 1 arah saja = 1/2 P )


Beban hidup = 0.5 x 400 x 5 = 1000 Kg/m'
Beban akibat berat sendiri balok, plat lantai atap dipikul oleh balok pratekan
* Momen akibat balok pratekan (MG)
2
MG = 1/8 1236 x 25 = 96562.5 Kg.m
MG 9656250
f Gt = = = 69.60589 Kg/cm2
Zt 138727.48
MG 9656250
f Gb = = = -55.914901 Kg/cm2
Zb 172695.47

* Momen akibat lantai kendaraan (Mss)


2
Mss = 1/8 875 x 25 = 68359.375 Kg.m
Mss 6835937.5
fSt = = = 49.276014 Kg/cm2
Zt 138727.48
b Mss 6835937.5
fS = = = -39.583769 Kg/cm2
Zb 172695.47

* Momen akibat balok diagfragma (Mdd)


2
Mdd = 1/8 281.25 x 25 = 21972.656 Kg.m
t Mdd 2197265.6
fd = = = 15.838719 Kg/cm2
Zt 138727.48
b Mdd 2197265.6
fd = = = -12.723354 Kg/cm2
Zb 172695.47

JURUSAN TEK. SIPIL UKI


Langkah 3
Menentukan tegangan akibat beban luar
Beban akibat beban aspal, air hujan & beban hidup dipikul oleh penampang komposit
(balok + lantai)
* Momen akibat beban luar (air hujan dan aspal) (Mws)
Mws = 1/8 437.5 x 25 2 = 34179.688 Kg.m
Mws 3417968.8
fwsts = = = 9.9658453 Kg/cm2
Zct 342968.27
Mws 3417968.8
fwsb = b = = -13.198361 Kg/cm2
Zc 258969.19
t
Y c - t
fwst = x fwsts
Ytc
66.685 - 20
= x 9.9658 = 6.9769155 Kg/cm2
66.685

* Momen akibat beban hidup (MLS)


2
MLs = 1/8 -58.333 x 25 = -4557.2917 Kg.m
MLs -455729.2
fLsts = t = = -1.3287794 Kg/cm2
Zc 342968.27
b MLs -455729.2
fLs = = = 1.7597814 Kg/cm2
Zcb 258969.19
Ytc - t
fLst = x fwsts
Ytc
66.685 - 20
= x -1.3288 = -0.9302554 Kg/cm2
66.685

* Momen akibat beban titik (Mps)


Mps = 1/4 11055 x 25 = 34545.455 Kg.m
Mps 3454545.5
fpsts = = = 10.072493 Kg/cm2
Zct 342968.27
Mps 3454545.5
fpsb = b = = -13.3396 Kg/cm2
Zc 258969.19
t
Yc - t
fpst = x fpsts
Ytc
66.685 - 20
= x 10.072 = 7.0515776 Kg/cm2
66.685

* Momen akibat beban hidup trotoar (MT)


2
ML = 1/8 432 x 25 = 33750 Kg.m

JURUSAN TEK. SIPIL UKI


MT 3375000
fTs = = = 9.8405604 Kg/cm2
Zct 342968.27
MT 3375000
fTb = = = -13.032438 Kg/cm2
Zcb 258969.19
Ytc
- t
fTt = xt fLts
Yc
66.685 - 20
= x 9.8406 = 6.8892057 Kg/cm2
66.685

Tabel 3
Hasil-hasil yang diperoleh dari langkah 2 & 3

ft fb f ts
Momen (kg.cm)
(kg/cm2 ) (kg/cm2 ) (Cm3 )
MG = 9656250 69.60588967 -55.91490089 -
Mss = 6835937.5 49.27601413 -39.58376883 -
Mdd = 2197265.625 15.83871883 -12.72335427 -
Mws = 3417968.75 6.976915521 -13.19836062 9.965845319
ML = -455729.1667 -0.930255403 1.759781416 -1.328779376
MPS = 3454545.455 7.051577578 -13.33960022 10.07249281
ML = 3375000 6.889205726 -13.03243837 9.840560407
Total 154.708066 -146.0326418

Tegangan-tegangan yang diizinkan bekerja pada kawat pratekan


f 'c (tekan) = 0.33 fck = 0.33 x 325 = 107.25 Kg/cm2
1 1
f c (tarik) = 0.48 fck = 0.48 x 325 = 8.6533231 Kg/cm2
b
fc sisa = f total - fc (tarik)
= 146.03264 - 8.6533231 = 137.37932 Kg/cm2
fc sisa inilah yang harus ditahan oleh kawat pratekan
Check apakah dibutuhkan "deflected-tendons" ditinjau untuk tegangan tekan pada serat bawah
137.37932 Kg/cm2 > fc'
2
137.37932 Kg/cm > 107.3 Kg/cm2 Ok

f ts
t
f

ytc +

ybc
-

fb
bo

Gambar tegangan penampang komposite

JURUSAN TEK. SIPIL UKI


Langkah 4
Perencanaan kawat pratekan
Tinggi balok pratekan = 135 cm
Taksir letak titik berat kawat pratekan = 15% x tinggi balok dari dasar
= 15% x 135 ~ 20 cm
e = 60.138 - 20
= 40.138 cm

F F.e
fc sisa = +
A Zb
F F . 40.1
137.37932 = +
5150 172695.4684
F = 322038.54 Kg

74.86 cm
135 cm
CGC

60.14 cm CGS

e = 40.138 cm
20 cm

Digunakan kawat pratekan tipe 270K f 1/2" dengan final force = 17615 lbs = 824498 kg
322038.54
Jumlah kawat yang diperlukan = = 0.39
824497.5
Digunakan sebanyak 1 buah kawat

JURUSAN TEK. SIPIL UKI


JURUSAN TEK. SIPIL UKI
JURUSAN TEK. SIPIL UKI
JURUSAN TEK. SIPIL UKI
Tabel 8

Jarak dari Precast-Section Composite-Section


tumpuan
(X) MG fGt fGb MS fst fsb Mws fwst fwsb ML

0m 0 0 0 0 0 0 0 0 0 0

5.625 m 4224609.4 m 30.5 m -24.463 2990722.7 m 21.6 m -17.318 1495361.3 m 4.36 m -5.7743 1476562.5 m

11.25 m 7242187.5 m 52.2 m -41.936 5126953.1 m 37 m -29.688 2563476.6 m 7.47 m -9.8988 2531250 m

15 m 8583333.3 m 61.9 m -49.702 6076388.9 m 43.8 m -35.186 3038194.4 m 8.86 m -11.732 3000000 m

22.5 m 9656250 69.606 -55.915 6835937.5 49.276 -39.584 3417968.75 9.9658 -13.198 3375000

Catatan : Momen dalam ( Kg.Cm ) dan tegangan dalam ( Kg/cm2 )


Composite-Section S
ML fLt fLb ftG+S+WS+L fbG+S+WS+L

0 0 0 0 0

1476562.5 m 4.31 m -5.7017 60.676135 -53.25664

2531250 m 7.38 m -9.7743 104.01623 -91.2971

3000000 m 8.75 m -11.584 123.2785 -108.204

3375000 9.8406 -13.032 138.68831 -121.7295


PERENCANAAN JEMBATAN

f = 5.2 m

2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m 2,5 m

L = 40 m

Data - data jembatan


~ Panjang jembatan
~ Jarak antar portal
~ Tabel panjang tiap portal
Diperoleh dengan rumus :
4 . f . x . (L - x) Dimana : f = Tinggi portal di tengah bentang = 5.2 m
y =
L2 x = Jarak total portal selain yang ditinjau (m)
L = Panjang total jembatan (m)
d = Jarak antar portal = 2.5 m

Portal xn yn Portal xn yn Portal xn yn Portal xn yn


1 37.5 1.22 5 27.5 4.47 9 17.5 5.12 13 10 3.9
2 35 2.28 6 25 4.88 10 15 4.88 14 7.5 3.17
3 32.5 3.17 7 22.5 5.12 11 12.5 4.47 15 5 2.28
4 30 3.9 8 20 5.2 12 10 3.9 16 2.5 1.22

Perencanaan konstruksi balok pelengkung


Dimensi balok = 20 x 20 cm

~ Menentukan momen maximum


Kedua ujung struktur dianggap jepit sempurna, sehingga untuk menyelesaikannya
digunakan metode Slope Deflection

Beban-beban yang bekerja pada struktur :


- Beban hidup (pekerja & peralatannya) P = 100 kg Pu = 160 kg
- Beban balok (beban merata) q = 0.2 x 0.2 x 2400 = 96 kg/m
qu = 115 kg/m

Pu = 160 kg
qu = 115 kg/m

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

A 2.5 m

Menentukan momen primer


1 PL
MFAB = (-) . q . L 2
+ (-)
12 8

1 2 160 . 2.5
= (-) . 115 . 2.5 + (-)
12 8

= -110 kgm

MFAB = 110 kgm

Persamaan Slope Deflection :

2 EI EI = konstan
MAB = MFAB + 2 qA + qB
L

= -110 + 0.8 2 qA + qB = -110 + 1.6 qA + 0.8 qB

2 EI
MBA= MFBA + qA + 2qB
L

= 110 + 0.8 qA + 2qB = 110 + 0.8 qA + 1.6 qB

Karena kedua ujungnya jepit, maka putaran sudut (q) =0


Pu = 160 kg
qu = 115 kg/m
S MB = 0
MBA VA . 2.5 - Pu . 1.25 - Q . 1.25 - MAB + MBA = 0
C VB VA . 2.5 - 200 - 360 = 0
2.5 m 560
VA = = 224 m
MAB 2.5
VA
S MA = 0 SV=0 VA + VB = Pu + Qu
VB = VA = 224 m 448 = 448 Ok

Gaya dalam
Bentang AC ( 0 < x < 1.25 )

Mx = VA.x - MAB - 1/2 qx2 = 224 x - 110 - 57.6 x2

Untuk x =0 MA = -110 kgm Untuk x = 1.25 MC = 80 kgm

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Untuk mendesain tulangan digunakan momen maksimum = 110 kg.m

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

- Mutu baja (fy) = 300 N/mm2


- Mutu beton (f'c) = 22.4 N/mm2

fy2 Mu
AS2 - fy . d. AS. + = 0
1,7 . fc' .b f

2
3000 1100000
AS2 - 3000 . 160 . AS. + = 0
1.7 224 200 0.8

118.43664 AS2 - 480000 AS. + 1375000 = 0

2
Dengan rumus ABC diperoleh : AS. = 2.867 cm
2 f 15 = 3.53 cm2
Tulangan tekan AS' = 0,25 . AS = 0.72 cm2
2 f 10 = 1.57 cm2

Kontrol

1.4 1.4
rmin = = = 0.0047
fy 300

As. 3.53
rada = = = 0.011 Ok !!!
b. d 20 . 16

0.85 . f'c 600 0.85 . f'c22.4 600


rmaks = 0.75 . b1 . = 0.75 0.85
fy 600 + fy 300 600 + 300

= 0.0269 Ok !!!

Perencanaan konstruksi kolom


Dalam hal ini diambil contoh kolom yang paling tinggi yang mewakili semua kolom

Pu = 448 kg

Mu = 210 kgm

20 x 20 cm
Lu = 5.2 m

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Penulangan Kolom
~ Mengecek pengaruh kelangsingan kolom
Untuk komponen struktur tekan yang tidak ditahan terhadap goyangan ke samping, pengaruh
kelangsingan dapat diabaikan jika memenuhi :

k . Lu
< 22 SK. SNI T - 15 - 1991 - 03. 33 11 4)
r
dimana :
k = faktor tekuk = 1
lu = panjang kolom = 5.2
3
I 1 / 12 . 20 . 20
r = radius girasi = = = 5.7735
A 20 . 20
atau r = 0,3 . h. = 0.3 . 20 = 6

Jadi :
k . Lu 1 . 5.2
= = 86.667 > 22
r 0.06

Berarti faktor kelangsingan tak dapat diabaikan

~ Faktor pembesar momen ( d )

Cm
d = > 1
Pu
1 -
f . Pc

Dimana : Cm = 1 (konservatif)
Pu = 0.448 ton
2
p . EI
Pc =
(k . Lu)2
Ec . Ig
EI =
2,5 . (1 + bd)
Ec = 4700 . fc' = 4700 22.4 = 22219.620 Mpa = 2221962.0 t/m2
Ig = 1/12 . b. h3 =
1
Ig = . 0.2 . 0.2 3 = 0.0001333 m4
12
1,2 . qdl 1.2 . 96
Bd = = = 0.4186
1,2 . qdl + 1,6 . qll 1.2 . 96 + 1.6 . 100
diperoleh :
2221962.0 . 0.0001333
EI = = 83.53605661
2.5 . ( 1 + 0.4186 )

p2 . 83.536057
Pc = = 30.46

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Pc = 2
= 30.46
1 . 5.2

1
d = = 1.023 > 1 Ok !!!
0.448
1 -
0.65 . 30.46
Mu = 0.21 tm
Mc = d . Mu
= 1.0232 . 0.21 = 0.2149 tm

Hitung :
Pu 0.448
Pn perlu = = = 0.6892 ton
f 0.65

Mc 0.2149
Mn perlu = = = 0.3306 tm
f 0.65

Eksentrisitas :
Mn perlu 0.330556619
e = = = 0.4796 = 479.6
Pn perlu 0.689230769

emin = 15 + 0,03 . h. = 15 + 0.03 . 200 = 21

Syarat : emin < e Ok !!!

Hitung nilai r
~ Sumbu vertikal
Pu 4480
= = 0.0091
f . Ag . 0,85 . fc' 0.65 . 200 . 200 . 0.85 . 22.4

~ Sumbu horizontal
Pu e 479.6
. = 0.0091 . = 0.0218
f . Ag . 0,85 . Fc' h 200

Dari diagram interaksi kolom, diperoleh :


b = 0.85
r = 0.01

Maka, r = b . r = 0.85 . 0.01 = 0.0085


Hitung luas tulangan :
Ast = r . Ag
= 0.0085 . 200 . 200.0
2
= 340 mm

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

As = As' = 1/2 . Ast = 0.5 . 340 = 170 mm2

Digunakan Tulangan : 2 f 12 = 226.286 mm2

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Perencanaan Balok Memanjang untuk bentang L = 40 m


Balok memanjang tengah direncanakan sebagai balok - T.
* Pembebanan :
* Akibat beban mati
- Akibat pelat = 0.20 . 2500 . 1.75 = 875 kg/m'
- Akibat balok = 0.20 . 0.75 . 2500 = 375 kg/m'
- Akibat pavement = 0.10 . 2000 . 1.75 = 350 kg/m'
- Akibat air = 0.05 . 1000 . 1.75 = 87.5 kg/m'
qDL = 1688 kg/m'
= 1.69 t/m'

* Diafragma = 0.25 . 0.45 . 2500 . 1.75 - 0.20 = 0.4359 t


* Akibat beban portal (pelengkung) = 0.45 t

* Akibat beban hidup


20
Koefisien kejut = 1 + = 1.22
50 + 40.0

1.75
Beban garis : P = 12 . . 1.22 = 9.33 ton
2.75
1.75
Beban merata : P = 2.2 . . 1.22 = 1.71 ton
2.75

0.8839 t 0.8839 t
3.3986 a b c d

A a b c
1m 1m 1m 17 m

RA = DA = 3.3986 . 20 + 7.07 = 73.822 t

2
Md = 73.822 . 20 - 0.8839 . 30 - 0.5 . 3.3986 . 20

= 770.2 tm

Dd = 73.822 - 3.3986 . 20 - 1.7679 = 4.0821 t

2
Mc = 73.822 . 3 - 0.8839 . 3.5 - 0.5 . 3.3986 . 3

= 203.08 tm

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Dc = 73.822 - 3.3986 . 3 - 1.7679 = 61.859 t

2
Mb = 73.822 . 2 - 0.8839 . 2 - 0.5 . 3.3986 . 2

= 139.08 tm

Db = 73.822 - 3.3986 . 2 - 0.8839 = 66.141 t

Ma = 73.822 - 0.8839 . 0.5 . 3.3986 = 71.239 tm

Da = 73.822 - 3.3986 . 0.8839 = = 69.54 t


b

bk b0

bm b0 + I0/5 20 + 1000 bm 220 cm


5
bm b0 + I0/10 + bk/2 20 + 1000 + 175 bm 208 cm
10 2
bm b bm 175 cm

Sehingga, bm = 175 cm bm 175


= = 8.75 < 5 balok T sempit
b0 20

t 20
= = 0.22
h 90

Penulangan :
Md = 77020 kgm

h = 95 - 5 = 90 cm

90
Ca = = 4.1054
19 . 77020
1740 . 1.7500
Ca = 4.1054 )
nw = 0.0773
d = 0.2 ) f = 2.175 > fo (OK)

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

0.0773
A = . 175 . 90 = 64.1 cm2
19
2
15 f 22 = 57.02 cm

A' = 0,2 A = 12.8 cm2 3 f 1"

8 D 8 4082.125
td = . = . = 2.59 < tb = 6.5 kg/cm2
7 bh 7 20 . 90

Mc = 20308 kbm

Taksir x = 0.34 l = 0.93 b = l . bm = 1.581 m


h = 95 - 5 = 90 cm

90
Ca = = 7.5993
19 . 20308
1740 . 1.581

Ca = 7.5993 ) dari tabel diperoleh x = 0.358 (OK)


nw = 0.1091
d = 0.2 ) f = 1.789 > fo (OK)

0.1091
A = . 175 . 90 = 90.4 cm2 12 f 1"
19

A' = 0,2 A = 18.1 cm2 3 f 1"

8 D 8 61858.51389
tc = . = . = 39.3 <t= 5.5 kg/cm2
7 bh 7 20 . 90

Mb = 139079 kgm

Taksir x = 0.28 l = 0.97 b = l . bm = 1.649 m


h = 95 - 5 = 90 cm

90
Ca = = 2.9656
19 . 139079
1740 . 1.649

Ca = 2.9656 ) dari tabel diperoleh x = 0.283 (OK)


nw = 0.0589
d = 0.2 ) f = 2.532 > fo (OK)

0.0589
A = . 175 . 90 = 48.8 cm2 7 f 1"

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

A = . 175 . 90 = 48.8 cm2 7 f 1"


19

A' = 0,2 A = 9.77 cm2 2 f 1"

8 D 8 66141.0625
tb = . = . = 42 <t= 5.5 kg/cm2
7 bh 7 20 . 90

Ma = 71239 kgm

Taksir x = 0.22 l = 0.99 b = l . bm = 1.683 m


h = 95 - 5 = 90 cm

90
Ca = = 4.1862
19 . 71239
1740 . 1.683

Ca = 4.1862 ) dari tabel diperoleh x = 0.217 (OK)


nw = 0.0309
d = 0.2 ) f = 3.615 > fo (OK)

0.0309
A = . 175 . 90 = 25.6 cm2 4 f 1"
19

A' = 0,2 A = 5.12 cm2 2 f 1"

8 D 8 69539.67361
ta = . = . = 44.2 >t= 5.5 kg/cm2
7 bh 7 20 . 90

tsisa = 44.2 - 5.5 = 38.7 kg/cm2


Pakai tulangan beugel f 3/8" - 20 As = 1.43 cm2

As . sa 1.43 . 1400
tyang terjadi = = = 5.01 kg/cm2 > tsisa (OK)
b .d 20 . 20

E. Balok Memanjang tepi :


Agar lebih ekonomis, balok memanjang tepi harus dihitung tersendiri dengan memperhitungkan
beban-beban jalur sebesar setengah beban jalur BM-tengah serta beban tambahan yaitu
beban trotoir.
Selanjutnya perhitungan BM-tepi dapat diselesaikan analog dengan cara perhitungan untuk
BM-tengah.

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Perencanaan Tiang Pancang


Data - data perencanaan
~ Abutment I
Elevasi Sondir = + 87.5 m
Elevasi Kaki poer = + 80.5 m
Elevasi tanah keras = + 87.5 - 20 = 67.5 m
Direncanakan panjang tiang pancang = 20 - 7 = 13 15 m
2
Data sondir : qc = 150 kg/cm
STf = 825 kg/cm

~ Abutment II
Elevasi Sondir = + 85.2 m
Elevasi Kaki poer = + 78.2 m
Elevasi tanah keras = + 85.2 - 15 = 70.2 m
Direncanakan panjang tiang pancang = 15 - 7 = 8 10 m
Data sondir : qc = 150 kg/cm2
STf = 800 kg/cm

~ Abutment I

qc . A STf . K A = 1/4 p d2
Q = + 2
3 5 = 1/4 . 3,14 . 40
= 1256 cm2

150 . 1256 825 . ( p . 40)


Q = + = 83524 kg
3 5

= 83.524 ton

~ Abutment II

qc . A STf . K A = 1/4 p d2
Q = + 2
3 5 = 1/4 . 3,14 . 40
2
= 1256 cm

150 . 1256 800 . ( p . 40)


Q = + = 82896 kg
3 5

= 82.896 ton

Jumlah tiang pancang


V 793.85
n = = = 9.58  11 buah
Q 82.896

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D1198060


PERENCANAAN JEMBATAN

0.50

1.25

1.25

0.50

1.00 1.50 1.50 1.50 1.50 1.50 1.50 1.00

Syarat S < 2,5 D


S  3,0 D (min 0,60 m dan maks 2,00 m)

S  3
Sn = 150 cm dan Sm = 125 cm

Menentukan Beban Akibat Momen Yang Dipikul Tiang Tengah

P1
P2 P0
P3

X3 X4 P4
P5
X2 X5 P6

X1 X6

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D1198060


PERENCANAAN JEMBATAN

M = 2 P1.X1 + P2.X2 + 2 P3.X3 + 3 P0. 0 + 2 P4.X4 + P5.X5 + 2 P6.X6

Analogi :
P2 : P1 = X1 : X2 P4 = P1. (X4/X1)

P2 = P1. (X2/X1) P5 = P1. (X5/X1)

P3 = P1. (X3/X1) P6 = P1. (X6/X1)

M = 2 P1.X1 + P1.(X22/X1) + 2 P1.(X32/X1) + 0 + 2 P1.(X42/X1) + P1.(X52/X1)


+ 2 P1.(X62/X1)

M = (P1/X1) (2X12 + X22 + 2X32 + 2 X42 + X52 + 2 X62)

M. X1
P1 =
(2X1 + X2 + 2X3 + 2 X42 + X52 + 2 X62)
2 2 2

DIMANA :
M = 521.78769 - 289.58496 = 232.20273

X1 = 4.5 m X4 = 1.5 m
X2 = 3.0 m X5 = 3.0 m
X3 = 1.5 m X6 = 4.5 m

232.20273 x 4.50
PM =
( 2. 4.5 ^2 + 3.0 ^2 + 2. 1.5 ^2 + 2. 1.5 ^2 + 3.0 ^2 + 2. 4.5 ^2)

1044.91229
PM = = 9.675 Ton
108.00

V
PMAKS = + PM
n

793.8549
PMAKS = + 9.675
11

PMAKS = 81.844 < QTanah ( 82.896 ) Oke ….!

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D1198060


PERENCANAAN JEMBATAN

Effisiensi Kelompok Tiang Pancang

A B B A

C D C

A B A
B

1. Metode Feld

3 8
Effisiensi Tiang A = 1 - =
11 11
4 7
Effisiensi Tiang B = 1 - =
11 11
4 7
Effisiensi Tiang C = 1 - =
11 11
4 7
Effisiensi Tiang D = 1 - =
11 11

8 32
4 Buah Tiang A = 4 x Eff A = 4 =
11 11
7 28
4 Buah Tiang B = 4 x Eff B = 4 =
11 11
7 14
2 Buah Tiang C = 2 x Eff C = 2 =
11 11
7 7
1 Buah Tiang D = 1 x Eff D = 1 =
11 11
81
Total Eff. = = 7.3636
11
7.3636
Effisiensi Satu Tiang = = 0.6694
11

2. Metode Converse Labone Formulae

q (n - 1) m + (m - 1) n
SFf . N = 1 - .
90 m .n

Dimana : 40 0
q = Arc Tan = 17.745
125
m = 3
n = 7
17.7 7 - 1 3 + 3 - 1 7
SFf . N = 1 - .
90 3 . 7

= 0.6996

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D1198060


PERENCANAAN JEMBATAN

Karena tiang juga mengandalkan friction, maka :

150 . 1256 825 . ( p . 40)


Q = + 0.6996 = 77298 kg
3 5

= 77.298 ton

150 . 1256 800 . ( p . 40)


Q = + 0.6996 = 76858 kg
3 5

= 76.858 ton

Q > Q ( 81.844 ton ) Tidak Oke Cess…!

Kontrol dengan cara perpindahan :


1. Menentukan konstanta pegas
~ Konstanta pegas arah axial
Ap . Ep
Kv = a .
l
dimana :
l
a = 0.041 - 0.27 = 2.2925
D
Ap = 1256 cm2
Ep = 6400 . fck = 156767 kg/cm2
l = 25 m = 2500 cm

1256 . 156767
Kv = 2.2925 . = 180557 kg/cm
2500

~ Konstanta pegas arah ortogonal


K1 = 4EI b3 = 29358.02518 kg/cm
K2=K3 = 2EI b2 = 2039996.384 kg/rad
K4 = 2EI b = 283505802.8 kgcm/rad

E = 156767 kg/cm
p
I = . D4 = 125664 cm4
64
4 k.D
b = = 0.007195607 cm-1
4EI
k = ko . y-1/2 = 5.2812204 kg/cm2
ko = 0,2 . Eo . D-3/4 = 5.2812
Eo = 28 N = 420 kg/cm2

Untuk kemiringan tiang pancang dianggap qi = 0, hal ini adalah kondisi kritis pada
stabilitas abutment.

1. Menentukan koefisien matriks perpindahan

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D1198060


PERENCANAAN JEMBATAN

Axx = S (K1 cos2qi + Kv sin qi) = n . K1 = 322938.28


Axy = Ayx = S (Kv . K1) sin qi . cos qi = 0
Axa = Aax = S (Kv - K1) xi sin qi . cos qi - K2 cos qi = -n . K2 = -22439960

Ayy = S (K1 cos2qi + Kv sin qi) = n . Kv = 1986123.8


2 2
Aya = Aay = S (Kv cos qi + K1 sin qi) xi +K2 sin qi) = 0
Aaa = S (Kv cos2qi + K1 sin2 qi) xi2 +(K2 + K3) xi . sin qi K4)
= SKv . x2 + SK4 = 3123032609

Formula Matriks perpindahan tiang pancang

Axx Axy Axa dx Ho


Ayx Ayy Aya dy = Vo
Aaa Aay Aaa d Mo

322938.28 0 -22439960.2 dx 135078


0 1986123.8 0 dy = 793855
-22439960 0 3123032609 a 518442

dx = 0.8583974 cm
dy = 0.3997006 cm
a = 0.0063339 rad

dxi' = dx cos qi - (dy + axi) sin qi = dx cos qi = dxi


dx1 = dx = 0.858397419 cm
dx2 = dx = 0.858397419 cm
dx = dx = 0.858397419 cm

dyi' = dx cos qi - (dy + axi) cos qi = (dy + axi)


dy1 = 0.864731278 cm
dy2 = 0.399700608 cm
dy3 = 0.345633618 cm

Pni = Kv . dyi

PN1 = 180556.71 . 0.864731278 = kg


PN2= 180556.71 . 0.399700608 = kg
PN3 = 180556.71 . 0.345633618 = kg

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D1198060


PERENCANAAN JEMBATAN

PHi = K1 dx - K2 a

PH1 = 12279.805 kg
PH2= 12279.805 kg
PH3 = 12279.805 kg

Mti = -K3 dxi + K4 a

Mt1 = 44557.953 kg m
Mt2= 44557.953 kg m
Mt3 = 44557.953 kg m

Kontrol !!!
SHi = n . PHi = 159637.47
SVi = 5 . PN1 + 3 PN2 + 5 PN3 =
Mti = S (Mti + Vi . Xi)
= n . Mti + 5 V1 . 125 + 5 V3 (-125)
=

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D1198060


PERENCANAAN JEMBATAN

Penulangan Tiang Pancang


Penulangan tiang pancang dihitung berdasarkan kebutuhan pada waktu pengangkatan

a. diangkat

a L - 2a a

M1 M3

M2

M1 = 1/2 . g . a2 g = Berat tiang pancang (kg/m) = 302 kg/m

M2 = 1/8 . g . (L - 2a)2 - 1/2 g . a2

M1 = M2 1/2 .g. a2 = 1/8 . g . (L - 2a)2 - 1/2 g . a2

4a2 + 4a L - L2 =0 L = 15 m

4a2 + 4a 15 - 15 2
= 0

4 a2 + 60 a - 225 = 0
Dengan rumus ABC diperoleh :
a1 = 3.1066
a2 = -18.107 (tidak memenuhi)

M1 = M2 =1/2 g. a2 = 1/2 . 302 . 3.11 2


= 1455.3 kgm

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D1198060


PERENCANAAN JEMBATAN

b. diangkat

Dari penurunan rumus diperoleh


a persamaan :
2 a2 - 4 a L + L2 = 0

2a2 - 4a 15 - 15 2
= 0

L-a 2 a2 + 30 a - 225 = 0
Dengan rumus ABC diperoleh :
a1 = 5.4904
a2 = -20.49 (tidak memenuhi)

M1 = M2 =1/2 g. a2 = 1/2 . 302 . 5.49 2


= 4545.7 kgm

Jadi keadaan yang paling menentukan adalah keadaan b. (Mmaks = 4545.7 kgm)
Penulangan diambil = 12 f 19

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D1198060


PERENCANAAN JEMBATAN

BAB III
PERHITUNGAN KONSTRUKSI BANGUNAN BAWAH

III. 1. PERHITUNGAN ABUTMENT


0.3

1
I

0.7
II

0.7 III IV

4.1 Pa1

Pp1

0.2 VI VII
Pp2
0.4 VIII
Pp3
2 1 2

Data - data tanah :


Dari grafik sondir, diperoleh :
- Kedalaman tanah keras = 20 m
- g tanah = 1.7
- j = 29 0
- Nilai konus C
Ka = tan2 (45 - f/2) = 0.35
2
Kp = tan (45 + f/2) = 2.88
3
- g beton = 2400 kg/m

Menentukan lokasi titik berat abutment

Arif
PERENCANAAN JEMBATAN

Luas (F)
Bagian X Y F.X F.Y
m2
I 0.3 1.85 6.6 0.555 1.98
II 1.12 2.5 5.75 2.8 6.44
III 0.105 1.8 5.166667 0.189 0.5425
IV 0.105 3.1 5.166667 0.3255 0.5425
V 5 2.5 2.65 12.5 13.25
VI 0.2 1.333333 0.466667 0.266666667 0.093333
VII 0.2 3.666667 0.466667 0.733333333 0.093333
VIII 2 2.5 0.2 5 0.4
9.03 22.3695 23.34167

S F.X 22.3695
X = = = 2.477 m
SF 9.03

S F.Y 23.34167
Y = = = 2.585 m
SF 9.03

~ Perhitungan berat sendiri abutment (B)

B = Luas total x berat beton


= 9.03 . 2400
= 21672 kg/m

~ Perhitungan tekanan tanah aktif (Pa)

Pa = 1/2 . gt . h2 . Ka = 1/2 . 1700 . 7.1 2


. 0.35 = 14867.32 kg/m

~ Perhitungan berat tanah pengisi (G)

G1 = 2.4 . 2 . 1700 = 8160 kgm


G2 = 0.7 . 0.3 . 0.5 . 1700 = 178.5 kgm
G3 = 4.1 . 2 . 1700 = 13940 kgm
G4 = 0.2 . 2 . 0.5 . 1700 = 340 kgm
= 22618.5 kgm

~ Perhitungan tekanan tanah pasif

Pp3 = 1/2 . gt . h2 . Kp = 1/2 . 1700 . 0.4 2


. 2.88 = 391.9602 kg/m

~ Beban - beban yang bekerja pada abutment


Beban mati
* Berat aspal = 770 kg/m
* Berat lantai kendaraan = 3024 kg/m

Arif
PERENCANAAN JEMBATAN

* Berat gelagar induk = 7837.872 kg/m


* Berat trotoar = 993.6 kg/m
* Berat pipa sandaran = 96.48 kg/m
* Berat beton pengisi = 552 kg/m
q = 13273.952 kg/m

Beban balok diafrgma = 5376 kg


Tiang sandaran = 855.36 kg
P = 6231.36 kg

Beban hidup

20
* Koefisien kejut (K) = 1 + = 1.222
50 + 40.0

12 1
* Beban terpusat (P) = . 5.5 + . 1.5 . 1.222 = 33333.33 kg
2.75 2

2.2 1
* Beban jalur (q) = . 5.5 + . 1.5 . 1.5 = 7500 kg
2.75 2

* Beban hidup trotoar = 1000 kg/m

Reaksi total
* Beban mati = 1/2 . 13273.952 . 40.0 + 1/2 . 6231.36 = 268594.7
Beban terpusat = = 33333.33
Beban merata = 1/2 . 7500 = 3750
Beban hidup trotoar = 1/2 . 1000 . 40.0 = 20000
S Rtot = 325678.1

~ Gaya akibat rem dan traksi (HR)


Diambil 5 % dari muatan D dengan titik tangkap 1,2 m diatas jembatan

HR = 5% ( n . Pb + n . 50% Pb + n . L . P' + n . L . 50% . P')

Dimana : n = jumlah jalur = 2


L = bentang jembatan = 40.0 m
Pb = Berat kendaraan = 12 ton
p' = 2.2 ton

HR = 5% ( 2 . 12 + 2. 50% . 12 + 2 . 40.0 . 2.2 +


+ 2 . 40.0 . 2.2 . 50% )
= 15 ton = 15000 kg

Arif
PERENCANAAN JEMBATAN

~ Gaya akibat gempa bumi


K = E . (SB + R) = 0.14 . ( 21672 + 325678.1 )
= 48629.01 kg

~ Momen pada tengah alas abutment


Mo = 325678.1

~ Gaya normal
N = SG + SB + R
= 22618.5 + 21672 + 325678.0533
= 369968.6 kg

~ Letak titik tangkap gaya normal (N) terhadap titik A

~ Momen guling ditinjau terhadap titik A

~ Momen tahanan (MT)

MT = N . X 916501.8

~ Gaya geser (SH)

SH = Pa + HR + K - Pp

~ Gaya tahanan (Nf)

Nf = N . Tan j

~ Kontrol kestabilan
- Stabilitas terhadap guling
Syarat : MT > 2 916502
MG

Arif
PERENCANAAN JEMBATAN

- Stabilitas terhadap gaya vertikal, titik tangkap harus berada didaerah pusat.

- Stabilitas terhadap gaya geser

Penulangan Abutment

0.3

I I

Pa

II II

Pp
2 1 2

III IV

Potongan I - I
Pa = 1/2 . gt . h2 . Ka = 1/2 . 1.7 . 1 2
. 0.35 = 0.294928 kg/m
M = Pa'
=

Mu = 0 kg.cm

fy2 Mu
AS2 - fy . d. AS. + = 0

Arif
PERENCANAAN JEMBATAN

AS2 - fy . d. AS. + = 0
1,7 . fc' .b f

2
0 0
AS2 - 0 . 0 . AS. + = 0
1.7 0 0 0.8

#DIV/0! AS2 - 0 AS. + 0 = 0

Dengan rumus ABC diperoleh : AS. = #DIV/0! cm2

f 16 - 20 = 10.05 cm2

Kontrol

1.4 0
rmin = = = #DIV/0!
fy 0

As. 10.05
rada = = = #DIV/0! #DIV/0!
b. d 0 . 0

0.85 . f'c 600 0.85 . f'c 0 600


rmaks = 0.75 . b1 . = 0.75 0.85
fy 600 + fy 0 600

= #DIV/0! #DIV/0!

Potongan III - III = Potongan IV - IV


Untuk mendesain tulangan pada pot. Tersebut didasarkan pada momen guling, tahanan
dan gaya vertikal
N N.E
st = +
F W

Dimana : F = Luas abutment


W = 1/6 . b2 . h

Sehingga :
.
st = + = #DIV/0! + #DIV/0!

st max = #DIV/0! + #DIV/0! = #DIV/0!

st min = 0 - 0 = 0

Berat beban bagian


- Kiri : Berat tanah

Arif
PERENCANAAN JEMBATAN

Berat plat

Arif
PERENCANAAN JEMBATAN

Pp3

Arif
PERENCANAAN JEMBATAN

Arif
PERENCANAAN JEMBATAN

kg
kg
kg
kg
kg

Arif
PERENCANAAN JEMBATAN

Arif
PERENCANAAN JEMBATAN

Arif
PERENCANAAN JEMBATAN

600
+ 0

Arif
PERHITUNGAN ABUTMENT

III. 1. PERHITUNGAN ABUTMENT


I. Analisa Pembebanan
1. Elemen bangunan atas/Beban mati super struktur (DL)
~ Berat gelagar induk = 5 . ( 0.515 . 45 . 2500 ) = 289687.5 kg
~ Berat trotoar = 2 . ( 0.2 . 1. 45 . 2400 ) = 43200 kg
~ Berat lantai kendaraan = 0.2 . 7. 45 . 2400 = 151200 kg
~ Berat lapisan aspal = 0.05 . 7. 45 . 2200 = 34650 kg
~ Berat air hujan = 0.05 . 7. 45 . 1000 = 15750 kg
Total = 534487.5 kg
Untuk satu abutment = 267243.75 kg
Jadi PND = 267.24375 ton

2. Beban hidup (LL)


~ Beban garis P = 12 ton/jalur
5.5 m
100%P
50%P

7.0 m

12
P = = 4.364 t/m
2.75

~ Beban jalur

1.1
q = 2.2 - .( L - 30 )
60

1.1
= 2.2 - .( 45 - 30 )
60

= 1.925 t/m2

PNH = (q . 5,5) . 100% + (q . 1,5) . 50% . 0,5 . L + (P . 5,5) . 100% + (P . 1,5) . 50%

= 297.9759 ton Untuk satu abutment = 148.9879 ton


3. Perhitungan Berat Konstruksi
a. Abutmen
0.2 0.2 1.6 m

0.65 m
I

II 0.9 m

III 0.4 m

IV V 0.4 m
0.7 m

7 m

VI
3.85 m

VII VIII 0.3 m

IX 0.5 m
1.45 0.6 1.45

Menentukan lokasi titik berat abutment


Luas (F) Jarak xa Jarak ya
Bagian 2 Berat (t) Mx My
m (m) (m)
I 0.13 3.432 2.45 6.675 8.4084 22.9086
II 0.36 9.504 2.55 5.9 24.2352 56.0736
III 0.8 21.12 1.75 5.25 36.96 110.88
IV 0.14 3.696 2.283333 4.916667 8.4392 18.172
V 0.14 3.696 1.216667 4.916667 4.4968 18.172
VI 2.73 72.072 1.75 2.775 126.126 199.9998
VII 0.2175 5.742 2.533333 0.6 14.5464 3.4452
VIII 0.2175 5.742 0.966667 0.6 5.5506 3.4452
IX 1.75 46.2 1.75 0.25 80.85 11.55
171.204 309.6126 444.6464

Mx 309.6126 Torsi M = G . Xo = 171.204 . 0.058443


Xca = = = 1.808443 m
G 171.204 = 10.0056 tm

My 444.6464
Yca = = = 2.597173 m
G 171.204
b. Sayap
2.7 m 0.2 0.6

0.65 m I

0.9 m
0.9 m
II
0.4 m

0.4 m III
IV

1.05 m V

VI
2.80 VII

0.3 m 1.75 VIII


0.5 m
1.45 0.6 1.45

Luas (F) Jarak Xo Jarak Yo


Bagian 2 Berat (t) Mx My
m (m) (m)
I 1.755 2.5272 2.15 6.675 5.43348 16.86906
II 3.25 4.68 2.25 5.7 10.53 26.676
III 1 1.44 2.25 4.85 3.24 6.984
IV 0.14 0.2016 0.766667 4.783333 0.15456 0.96432
V 3.36 4.8384 3.5 4.125 16.9344 19.9584
VI 2.45 3.528 2.333333 2.666667 8.232 9.408
VII 4.06 5.8464 1.025 2.2 5.99256 12.86208
VIII 0.2175 0.3132 1.266667 0.7 0.39672 0.21924
23.3748 50.91372 93.9411

Torsi Mx = 50.91372 tm

93.9411
y = = 4.019 m
23.3748
c. Berat tanah
0.2 0.2 0.6

0.65 m I

1.3 m II

0.4 m III
IV
0.7 m

3.85 m V

0.3 m VI
0.5 m
1.45 0.6 1.45

Menentukan lokasi titik berat abutment


Luas (F) Jarak Xo Jarak Yo
Bagian 2 Berat (t) Mx My
m (m) (m)
I 0.6175 11.5596 1.275 6.675 14.73849 77.16033
II 0.975 18.252 1.375 5.7 25.0965 104.0364
III 0.3 5.616 1.375 4.85 7.722 27.2376
IV 0.14 2.6208 0.766667 4.783333 2.00928 12.53616
V 5.5825 104.5044 1.025 2.725 107.117 284.7745
VI 0.2175 4.0716 1.266667 0.7 5.15736 2.85012
146.6244 161.8406 508.5951

Torsi Mx = 161.8406 tm

508.5951
y = = 3.469 m
146.6244
4. Tekanan Tanah Normal
- Berat jenis tanah = 1.8 ton/m3
0
- Sudut geser dalam tanah j = 29
- Koefisien tekanan tanah
Ka = tan2 (45 - f/2) = 0.35
2
Kp = tan (45 + f/2) = 2.88
- Beban merata dibelakang abutment diperhitungkan senilai dengan muatan tanah setinggi
60 cm (PPPJJR, hal 13)
q = gt . h = 1,8 . 0,6 = 1.08 tm/m2

Diagram tekanan tanah


q = 1.08 tm/m2

3.8 m

Pa1

Pa2

1.7 m

~ Tekanan tanah aktif


Pa1 = q . H . Ka . L
= 1.08 . 7 . 0.35 . 11
= 28.85 ton

Pa2 = 1/2 gt . H2 . Ka . L
2
= 1/2 . 1.8 . 7 . 0.35 . 11
= 168.3 ton

Pa total = 197.2 ton

SMPa = Pa1 (1/2 H) + Pa2 (1/3 H)


= 28.85 . 3.5 + 168.3 . 2.333
= 493.7 tm
~ Tekanan tanah Pasif
Pp = 1/2 gt . H2 . Kp . L
2
= 1/2 . 1.8 . 1.70 . 2.88 . 11
= 82.46 ton

SMPp = Pp (1/3) H = 46.73

~ Tekanan tanah pada saat gempa bumi


Koef. Tekanan tanah
0
Data tanah : f = 29
Eh Dimana Eh = 0,1, Ev = 0
fo = Arc tan
L - Ev
0
fo = 5.7106
- Aktif
KEA = cos2 (f - fo) = 0.843678152
2 sin f . sin (f - fo) 2 0.191682 2
cos fo 1 + 0.990099 . 1 +
cos fo 0.995037

= 0.843678152
0.990099 . 2.070449

= 0.411561

- Pasif
KEP= cos2 (f - fo) = 0.843678152
sin f . sin (f - fo) 0.191682
cos2 fo 1 - 2
0.990099 . 1 - 2
cos fo 0.995037

= 0.843678152
0.990099 . 0.314827

= 2.706612

Koef. Tekanan tanah akibat gempa


- Aktif
PEA1 = q . H . KEA . L = 1.08 . 7 . 0.412 . 11 = 34.23 t

2
PEA2 = 1/2 gt . H . KEA . L = 1/2 . 1.8 . 7 . 0.412 . 11 = 199.6 t

PEA tot = 233.8734 t


SMPEA = PEA1 (1/2 H) + PEA2 (1/3 H)
= 34.23 . 3.5 + 199.6 . 2.333
= 585.6 tm

- Pasif
PEp = 1/2 gt . H2 . KEp . L
2
= 1/2 . 1.8 . 1.70 . 2.71 . 11
= 77.44 ton

SMPa = Pp (1/3) H = 43.88 tm

5. Beban Angin
1. Beban angin tegak lurus
(50% . (30% + 50%) . (L - 5) - H . 150 + 100% . L . 2 . 150)
Ar =
2

Dimana : L = 45 m
H = 3.55 m
Ar = -7008.25 t

2. Beban angin arah memanjang


Al = 2 ( 6 + 2 . 0,5) . 150
= 2.1 ton

Menurut ketentuan gaya angin yang dipilih adalah arah memanjang Al = 2,1 t setinggi
H = 5,5 m
MAl = 2,1 . 5,5 = 11.55 tm

6. Gaya Gesek Tumpuan (Gg) bekerja pada ketinggian H = 5.45 m

Gg = 0,15 . Beban mati


= 0.15 . 267.24375 = 40.08656 t

MGg = 40.08656 . 5.45 = 218.4718 tm

7. Gaya gempa horisontal eqivalent akibat gempa (Gh)


Koef. Gempa horisontal (Kh)
Kh = Kr . f . p . b

0,3 Mp + Ma
Tg = 2p . h3
3 EI . g

Dimana : Mp = 171.204
Ma = 267.2438
E = 6400 sb = 6400 225 = 960000 t/m2
3
I = 1/12 . 3.5 . 11 = 388.2083 m4
g = 9.8 m/det2
h = 7 m

0.3 . 171.204 + 267.2438 3


Tg = 2p . 7
3 . 960000 . 388.2083 . 9.8

= 0.367315 Zone IV diperoleh Kr = 0.05


Beban mati struktur yang ditinjau
1. Beban mati diatas struktur (M = 267.2438 tm)
Gh1 = 0.1 . 267.2438 = 26.72438 t
MGh1 = 26.72438 . 7 = 187.0706 t

2. Akibat beban mati abutment (M = 171.204 tm)


Hg1 = 2.597173 m
Gh2 = 0.1 . 171.204 = 17.1204 t
MGh2 = 17.1204 . 2.597 = 44.46464 t

3. Akibat beban mati sayap (M = 23.3748 tm)


Hg3 = 4.018905 m
Gh3 = 0.1 . 23.3748 = 2.33748 t
MGh3 = 2.33748 . 4.019 = 9.39411 t

Sehingga SGh = 46.18226


SMGh = 240.9294

8. Beban rem (Rm) bekerja setinggi H = 5.35 + 1.2 = 6.55 m

Rm = 5% dari beban mati total


= 5% . 148.9879
= 7.449396 t

MRm = 7.449396 . 6.55


= 48.79355 tm

9. Beban merata permukaan


Q = 1,08 . 27,5 = 29,7 tm Plat injak (5,6/2 . 2,4) = 6,72 t
M = 29,7 . 2,25 = 66,825 tm
Rekapitulasi Gaya pada Abutment
Vertikal Horisontal
No. Gaya pada abutment Simbol Mx My
V (ton) H (ton)
I.
a. Beban mati 267.2438
b. Beban hidup 148.9879
c. Gaya rem Rm -7.44939631 -48.7935458
d. Gaya gesek Gg -40.0865625 -218.471766
e. Beban angin A -2.1 -11.55
f. Beban gempa Gh -46.182255 -240.929375
g. Beban merata q 29.7
h. Plat injak 6.72 66.825

II. Bangunan bawah


a. Berat abutment 171.204 10.0056
b. Berat sayap 23.3748 50.91372
c. Berat tanah 146.6244 161.84064

III. Tekanan tanah T


a. Keadaan normal Ta -114.712842 -447.003616
1. Aktif Taa -197.171463 -493.730168
2. Pasif Tap 82.45862057 46.72655166
b. Keadaan gempa Tg -156.434528 -541.752162
1. Aktif Tga -233.873392 -585.634186
2. Pasif Tgp 77.43886488 43.88202343

Mmv = 289.585 t
Mv = 644.867

KOMBINASI PEMBEBANAN
1. KOMBINASI I
Muatan V (ton) H (ton) MV ton.m MH (ton.m)
M 644.86695 289.58496
H 148.9879261
Ta -114.712842 -447.003616
Tu
100% 793.8548761 -114.712842 289.58496 -447.003616
100% 793.8548761 -114.712842 289.58496 -447.003616

2. KOMBINASI II
Muatan V (ton) H (ton) MV ton.m MH (ton.m)
M 644.86695 289.58496
Ta -114.712842 -447.003616
Gg -40.0865625 -218.471766
A -2.1 -11.55
125% 644.86695 -156.899405 289.58496 -677.025382
100% 515.89356 -125.519524 231.667968 -541.620305

3. KOMBINASI III
Muatan V (ton) H (ton) MV ton.m MH (ton.m)
M 793.8548761 -114.712842 289.58496 -447.003616
Rm -7.44939631 -48.7935458
Gg -40.0865625 -218.471766
A -2.1 -11.55
140% 793.8548761 -164.348801 289.58496 -725.818927
100% 567.0391972 -117.392001 206.8464 -518.442091

4. KOMBINASI IV
Muatan V (ton) H (ton) MV ton.m MH (ton.m)
M 644.86695 289.58496
Gh -46.182255 -240.929375
Tag -156.434528 -541.752162
150% 644.86695 -202.616783 289.58496 -782.681537
100% 429.9113 -135.077855 -521.787692

Dari tabel diatas diperoleh kombinasi maksimum


Vertikal = 793.8549 t
Horisontal = 135.0779 t
Mv = 289.585 tm
Mh = 521.7877 tm
II. Penulangan Abutment

0.2 0.2 0.6

0.65 m

1.3 m

0.4 m

3.85 m

I III II I

0.3 m VI
0.5 m
1.45 0.6 1.45

III II
I. Potongan I - I

q = 1.08 tm/m2

II

III
IV V

6.20 m
Pa1
VI

Pa2

I I

Diketahui :
Ls = 11 m

Pa1 = q . H . Ka . L Pa2 = 1/2 gt . H2 . Ka . L


2
= 1.08 . 6.20 . 0.35 . 11 = 1/2 . 1.8 . 6.20 . 0.35 . 11
= 25.56 ton = 132 ton

Pa total = 157.6 t

Lengan tekanan tanah (y) dan momen (M)


y1 = 3.1 m M1 = Pa1 . Y1 = 25.56 . 3.1 = 79.22583 tm
y2 = 2.067 m M2 = Pa2 . Y2 = 132 . 2.067 = 272.889 tm

SM = M1 + M2 = 352.1148 tm

SM 352.1148
y= = = 2.234 m
SP 157.5998
Tabel perhitungan gaya geser dan momen
Jarak Jarak V H Mx = H . y. My = V . x.
Beban
x (m) y (m) (ton) (ton) tm tm
Bangunan atas
a. Beban mati 0 0 267.2438 0 0
b. Beban hidup 0 0 148.9879 0 0
c. Gaya rem Rm - 5.55 7.449396 41.3441495 -
d. Gaya gesek Gg - 5.55 40.08656 222.4804219 -
e. Beban angin A - 5.55 2.1 11.655 -
f. Beban gempa Gh - 5.55 46.18226 256.3115153 -
g. Beban merata q 1.35 - 29.7 40.095
h. Plat injak 1 - 6.72 6.72

Bangunan bawah
a. Berat abutment
I 2.45 5.875 3.432 - - 8.4084
II 2.55 5.1 9.504 - - 24.2352
III 1.75 4.45 21.12 - - 36.96
IV 2.283333 4.116667 3.696 - - 8.4392
V 1.216667 4.116667 3.696 - - 4.4968
VI 1.75 2.125 72.072 - - 126.126
b. Tekanan tanah
Pa1 - 3.1 25.55672 79.226
Pa2 - 2.066667 132.043 272.889
566.1717 253.418 883.906 255.481

Dari perhitungan diatas diperoleh :


Gaya geser = 566.1717 ton
Momen = 628.425 ton m
Normal = 253.418 ton

- Mutu baja (fy) = 300 N/mm2


- Mutu beton (f'c) = 22.35 N/mm2

fy2 Mu
AS2 - fy . d. AS. + = 0
1,7 . fc' .b f

2
3000 6284252852
AS2 - 3000 . 960 . AS. + = 0
1.7 223.5 1000 0.8

23.68732728 AS2 - 2880000 AS. + 7855316066 = 0


Dengan rumus ABC diperoleh : AS. = 2791.64 mm2 /meter
Dipilih tulangan= f 25 - 10 = 4908.7 mm2
2
Tulangan tekan AS' = 0,25 . AS = 697.9 cm
Dipilih tulangan= f 12 - 20 = 565.5 mm2

Kontrol

1.4 1.4
rmin = = = 0.004667
fy 300

As. 4908.74
rada = = = 0.005113 Ok !!!
b. d 1000 . 960

0.85 . f'c 600 0.85 . f'c22.35 600


rmaks = 0.75 . b1 . = 0.75 0.85
fy 600 + fy 300 600 + 300

= 0.026913 Ok !!!
II. Potongan II - II

II I
1.7
0.3 1 II
Pp
0.5 2
1.45 0.6 1.45

II

Tabel perhitungan gaya geser dan momen


Beban Berat G (ton) Jarak x (m) Jarak y (m) Mx = G . y. My = G . x.
Berat tanah
I 25.839 1.025 - - 26.485
II 4.3065 1.2667 - - 5.455
Berat abutment -
1 5.742 0.7833 - - 4.498
2 19.14 1.025 - - 19.619
Pp 82.45862057 - 0.56667 46.727 -
46.727 56.056

Dari perhitungan diatas diperoleh :


Momen = 9.330 ton m

fy2 Mu
AS2 - fy . d. AS. + = 0
1,7 . fc' .b f

2
3000 93297233.44
AS2 - 3000 . 500 . AS. + = 0
1.7 223.5 1000 0.8

23.68732728 AS2 - 1500000 AS. + 116621541.8 = 0

Dengan rumus ABC diperoleh : AS. = 77.84 mm2 /meter


Dipilih tulangan= f 25 - 20 = 2454.4 mm2
2
Tulangan tekan AS' = 0,25 . AS = 19.46 cm
Dipilih tulangan= f 12 - 20 = 565.5 mm2
Kontrol

1.4 1.4
rmin = = = 0.004667
fy 300

As. 2454.37
rada = = = 0.004909 Ok !!!
b. d 1000 . 500

0.85 . f'c 600 0.85 . f'c22.35 600


rmaks = 0.75 . b1 . = 0.75 0.85
fy 600 + fy 300 600 + 300

= 0.026913 Ok !!!

III. Potongan III - III


2.7 m 0.2 0.6

0.65 m I

0.9 m
II
0.4 m

0.4 m III
IV

1.05 m V

VI
2.80 VII

0.3 m 1.75 VIII IX


0.5 m X
1.45 0.6 1.45
Tabel perhitungan gaya geser dan momen
Beban Berat G (ton) Jarak x (m) Jarak y (m) Mx = G . y. My = G . x.
Beban merata
Berat sayap
I 2.5272 2.1500 - - 5.433
II 4.68 2.2500 - - 10.530
III 1.44 2.2500 - - 3.240
IV 0.2016 0.7667 - - 0.155
V 4.8384 3.5000 - - 16.934
VI 3.528 2.3333 - - 8.232
VII 5.8464 1.0250 - - 5.993
VIII 0.3132 1.2667 - - 0.397
Berat Tanah
I 34.749 2.1500 74.710
II 64.35 2.2500 144.788
III 19.8 2.2500 44.550
IV 2.772 0.7667 2.125
V 66.528 3.5000 232.848
VI 48.51 2.3333 113.190
VII 80.388 1.0250 82.398
VIII 4.3065 1.2667 5.455
Berat Abutment
IX 5.742 0.7833 4.498
X 19.14 1.0250 19.619
Pa1 28.85436045 - 3.5000 100.990
Pa2 168.3171026 - 2.3333 392.740
493.730 775.094

Dari perhitungan diatas diperoleh :


Momen = 281.364 ton m

fy2 Mu
AS2 - fy . d. AS. + = 0
1,7 . fc' .b f

2
3000 2813636023
AS2 - 3000 . 500 . AS. + = 0
1.7 223.5 1000 0.8

23.68732728 AS2 - 1500000 AS. + 3517045029 = 0

Dengan rumus ABC diperoleh : AS. = 2438.61 mm2 /meter


Dipilih tulangan= f 25 - 12.5 = 3927.0 mm2
2
Tulangan tekan AS' = 0,25 . AS = 609.7 cm
Dipilih tulangan= f 16 - 20 = 1005.3 mm2
Kontrol

1.4 1.4
rmin = = = 0.004667
fy 300

As. 3926.99
rada = = = 0.007854 Ok !!!
b. d 1000 . 500

0.85 . f'c 600 0.85 . f'c22.35 600


rmaks = 0.75 . b1 . = 0.75 0.85
fy 600 + fy 300 600 + 300

= 0.026913 Ok !!!
Perencanaan Bangunan Atas IV -1

BAB IV
PERENCANAAN BANGUNAN ATAS
(SUPER STRUKTUR)

10

45
100 100

45
2% 2%
20
20
Blk. Girder

175 175 175 175

700

Gambar 4.1. Penampang melintang superstruktur

Data-data perencanaan :

Lokasi jembatan : Ruas Makassar - Bone Kabupaten Maros

Panjang bentang : 24 m

Kelas muatan : Kelas I

Lebar trotoar : 2x 1.0 m

Lebar lantai kendaraan : 7.0 m

Beban muatan sesuai Peraturan Muatan untuk Jembatan Jalan Raya No. SK 131. 28-1987
(khusus untuk lantai kendaraan menggunakan tabel Bitner)

Rencana penggunaan bahan :

- Tian sandaran : Mutu beton (f'c) = 24 Mpa, fy = 240 Mpa


- Lantai kendaraab dan lantai trotoar : Mutu beton (f'c) = 25 Mpa, fy = 240 Mpa
- Balok diafragma : Mutu beton (f'c) = 25 Mpa, fy = 240 Mpa
- Gelagar utama : Balok beton prategang type "I" dengan sistem
Post-Tensioning dan mutu beton (f'c) = 50 Mpa
serta tendon VSL.

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV -2

Rencana denah jembatan :

- Jarak antar gelagar : 1.75 m

- Jarak antar balok diafragma : 5.0 m

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 3

4.6. Perhitungan Gelagar Utama

Dimensi gelagar utama

Ditaksir tinggi balok prategang (h) L = 25 m

1 1
h = L L
17 25

= 1.471 - 1

Penampang yang ditinjau :

penampangh : AASTHO I - Beams Type III (panjang bentang maximum = 25 m)


Catatan : Type ini dimodifikasi
B1

I D2

II II D4

B4
B3
D1

III
B6

D5
IV IV

V D6

B2

Gambar 4.6 Dimensi Balok Prategang ( type III)

Dimensi (mm)
D1 D2 D4 D5 D6 B1 B2 B3 B4 B6

1150 150 150 200 200 500 600 200 150 200

Luas penampang = 417500 mm2


##
= 4175 cm2

Beban-beban yang bekerja pada gelagar utama :

a. Akibat beban mati yang dipikul oleh balok beton prategang

- Berat plat lantai (gp) = 0.20 x 1.75 x 2500 = 875 kg/m'

- Berat balok prategang (gG) = 0.4175 x 2500 = 1043.75 kg/m'

- Berat balok diafragma (gd) = 0.3 x 0.5 x 2500 = 375 kg/m'

b. Akibat beban hidup dan beban mati tambahan yang dipikul oleh balok komposit

- Berat lapisan aspal (gas) = 0.05 x 1.75 x 2200 = 192.5 kg/m'

- Berat air hujan (gw) = 0.05 x 1.75 x 1000 = 87.5 kg/m'

- Beban hidup trotoar diperhitungkan pengaruhnya terhadap balok gelagar utama sebesar

60 % dari beban hidup yang bekerja pada trotoar = 0.6 x 500 x 1.00

= 300 kg/m'
- Beban hidup/lalulintas terdiri dari

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 4

1 Muatan garis p = 12 Ton

Muatan garis = 12 ton yang bekerja = 100 % (kelas I)

= 12 x 1.0

= 12 ton

Beban garis yang dipikul oleh satu gelagar :

p
p' = a s
2.75

Dimana :

a = faktor distribusi sesuai PPPJJR SKBI 1.3 28 1987

1.0 bila kekuatan gelagar melintang tidak diperhitungkan


s = jarak gelagar

12
p' = 1.0 1.75
2.75

= 7.636 t

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 5

2 Muatan terbagi rata (g)

Untuk bentang L < 30 m maka : 1) hal 7

q = 2.2 t/m

Untuk jembatan kelas I bekerja 100 % beban terbagi rata (g) yaitu :

2.2 x 100 % = 2.2 t/m

beban merata yang dipikul oleh satu gelagar :

q 2.2
q' = a s = 1.0 1.8
2.75 2.75

= 1.4 t/m'

Koefisien kejut (K)

K = 1 + 20 50 + L

= 1 + 20 50 + 25

= 1.267

Momen-momen yang terjadi akibat beba yang bekerja :

- Yang dipikul oleh balok prategang :

1 Momen akibat berat sendiri balok prategang

1
MG = WG L2
8

1 2
= 1044 25
8

= 81542.9688 kgm

2 Momen akibat berat plat lantai

1
Mp = qp L2
8

1 2
= 875 25
8

= 68359.375 kgm

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 6

3 Momen akibat berat balok diagfragma

d d d d d

5.0 5.0 5.0 5.0 5.0

RA RB
5 d
RA = RB =
2

5 375
=
2

= 937.5 kg

Md = (RA ) 10.0 - d 10.0 - d 6

= 937.5 10.0 - 0 10.0 - 0 6

= 9375 kgm

- Yang dipikul oleh balok komposit

1 Momen akibat berat berat lapisan aspal

1 1 2
Mas = qas L2 = 192.5 25 = 15039.06 kgm
8 8

2 Momen akibat berat berat air hujan

1 1 2
Mw = qw L2 = 87.5 25 = 6835.938 kgm
8 8

3 Momen akibat beban hidup trotoar

1 1 2
Mtr = qtr L2 = 300 25 = 23437.5 kgm
8 8

4 Momen akibat beban hidup lalu lintas

ML1 1 1
= p' L K = 7.636 25 1.27 = 60.455 tm
4 4

= 60454.545 kgm

1 1 2
ML2 = q' L2 = 1.4 25 = 109.4 tm
8 8

= 109375 kgm

MD = MG + Mp + Md + Mas + Mw + Mtr

= 81542.9688 + 68359 + 9375 + 15039 + 6836 + 23438

= 204589.844 kgm

ML = ML1 + ML2

= 60454.545 + 109375

= 169829.545 kgm

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 7

MT = MD + ML

= 204589.844 + 169829.545 = 374419.389 kgm

= 37441938.9 kgcm
Hitung luas penampang beton dengan rumus :

F *5) hal 167


Ac =
0.5 fc

MT
F =
0.65 h

37441938.9
=
0.65 x 115

= 500895.504 kg

500895.504
Ac =
0.5 x 225

= 4452.404 cm2 < A taksiran = 4175 cm2

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 8

50

15
I

62.146 cm
15
II II

15
20
115

III
20

52.854 cm
20
IV IV

20
V

60

TAHAP I

a Perhitungan sifat-sifat penampang prategang

- Perhitungan letak garis netral penampang prategang.

Luas penampang Jarak terhadap serat Statis Momen


Penampang (A) Atas (y) (S=A.Y)
cm 2 cm cm 3

A1 = 50 x 15 = 750 7.5 5625

A2 = 2( 1/2 x 15 x 15)= 225 20 4500

A3 = 80 x 20 = 1600 55 88000

A4 = 2( 1/2 x 20 x 20)= 400 88.333 35333.333

A5 = 60 x 20 = 1200 105 126000

A = 4175 s = 259458.33

S 259458.33
Yt = = = 62.146 cm
A 4175

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 9

Yb = h - Yt = 115 - 62.146

= 52.854 cm

- Perhitungan momen inersia penampang prategang.

3
I1 = 1/12 50 15 + 750 54.64571 2 = 2253677.600 cm4

3
I2 = 2 1/36 15 15 + 225 42.14571 2 = 802129.8384 cm4

3 2
I3 = 1/12 20 80 + 1600 7.146 = 935031.175 cm4

3
I4 = 2 1/36 20 20 + 400 26.18762 2 = 557522.241 cm4

3 2
I5 = 1/12 60 20 + 1200 42.854 = 2243788.351 cm4

I = 6792149.206 cm4
- Perhitungan modulus penampang prategang.

I 6792149.206
Zt = = = 109293.938 cm3
Yt 62.146

I 6792149.206
Zb = = = 128507.053 cm3
Yb 52.854

- Perhitungan letak titik gali (kern) penampang prategang.

I 6792149.206
i2 = = = 1626.862 cm2
A 4175

i2 1626.862
kt = = = 30.780 cm
Yb 52.854

kb i2 1626.862
= = = 26.178 cm
Yt 62.146

- Hasil perhitungan sifat-sifat penampang balok prategang

A = 4175 cm2 I = 6792149.206 cm4

Yt = 62.146 cm Zt = 109293.938 cm3

Yb = 52.854 cm Zb = 128507.053 cm3

h = 115 cm Kt = 30.780 cm

i = 1626.862 cm Kb = 26.178 cm

b Perhitungan sifat-sifat penampang komposit

- Lebar efektif plat lantai.

Untuk gelagar dalam dengan plat dikedua sisi gelagar :

be < L/4 = 25 4 = 6.25 m

be < l = 2 m

Be<bw + 12 t = 20 + 12 20 = 260 cm = 2.6 m

Diambil be yang terkecil = 2 m

- Akibat perbedaan mutu beton antara plat lantai dan balok prategang maka perlu

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 10

disamakan kekuatan plat lantai dan balok prategang dengan mengalikan lebar efektif

(be) dengan modulus elastis beton (n).

E plat 4700 f'c 4700 25 *3) hal.9


n = = = = 0.707
E balok 4700 f'c 4700 50

Dengan demikian kekuatan plat dan balok dianggap sama untuk semua lebar plat dan

ditulis :

Le = n be

Jadi lebar efektif :

Le = 0.707 x 2 = 1.414 m = 141.4 cm

Le = 141.4 cm

20
Yct

Garis netral komposit

Ycb

Gambar 4.8 Penampang komposit

- Perhitungan letak garis netral penampang komposit

Luas penampang Jarak ke serat atas Statis momen


No
Acomp (cm 2 ) Y (cm) Sc = Acomp . Y (cm 3 )

1 Plat lantai Y1 = 1/2 t 28284.2712


A1 = 141.4 x 20 = 10
= 2828.427

t
2 Balok Prategang Y2 = Y + t 342958.333
A2 = 4175 = 62.146 + 20
= 82.146

Acomp = 7003.427 Sc = 371242.605

Sc 371242.605
Yct = = = 53.009 cm
Acomp 7003.427

Ycb = h + t - Yct

= 115 + 20 - 53.009

= 81.991 cm

- Perhitungan momen inersia penampang komposit

I comp = I prategang + I plat

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 11

= Ib + (Ab . Y2) + (Ip + (Ap . Y2)


2
3 2
= 6792149.206 + 4175 29.137 + 1/12 141.4 20 + 2828.427 43.00871

= 10336577.914 + 5326160.392

= 15662738.306 cm4

- Perhitungan Modulus penampang komposit

I comp 15662738.306
Zct = = = 295474.832 cm3
Yct 53.009

I comp 15662738.306
Zcb = = = 191029.284 cm3
Ycb 81.991

- Perhitungan letak titik gali (kern)

I comp 15662738.306
i2 = = = 2236.439 cm2
A comp 7003.427

i2 2236.439
kct = = = 27.27654
Ycb 81.991

i2 2236.439
kcb = = = 42.19003
Yct 53.009

- Hasil perhitungan sifat-sifat penampang komposit :

A comp = 7003.427 cm2 I comp = 15662738.306 cm4

Yct = 53.009 cm Zct = 295474.832 cm3

Ycb = 81.991 cm Zcb = 191029.284 cm3

kct = 27.277 cm kcb = 42.190 cm

TAHAP II

Perhitngan tegangan-tegangan yang diakibatkan oleh beban mati yang harus dipikul oleh

balok prategang.

Tegangan-tegangan yang terjadi :

1. Akibat berat lantai kendaraan Mp = 6835937.5 kgcm

Mp 6835937.5
fpt = = = 62.546 kg/cm2
Zt 109293.938

Mp 6835937.5
fpb = = = 53.195 kg/cm2
Zb 128507.053

2. Akibat berat sendiri balok prategang MG = 8154296.88 kgcm

MG 8154296.875
fGt = = = 74.609 kg/cm2
Zt 109293.938

MG 8154296.875
fGb = = = 63.454 kg/cm2
Zb 128507.053

3. Akibat berat balok diagfragma Md = 937500 kgcm

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 12

Md 937500
fdt = = = 8.578 kg/cm2
Zt 109293.938

Md 937500
fdb = = = 7.295 kg/cm2
Zb 128507.053

Tabel perhitungan momen dan tegangan.

No Momen (kg cm) f t (kg/cm2) f b (kg/cm2)

1 Mp = 6835937.5 62.546 53.195

2 MG = 8154296.875 74.609 63.454

3 Md = 937500 8.578 7.295

 Mt 1 = 15927734.38 145.733 123.944

TAHAP III

Perhitungan tegangan - tegangan akibat beban mati dan beban hidup yang dipikul oleh

penampang komposit.

Tegangan-tegangan yang terjadi :

1. Akibat lapisan aspal Mas = 1503906.25 kg cm

ts M as 1503906.25
fas = = = 5.090 kg/cm2
Zct 295474.832

Yct - t 53.009 - 20
fas t = fas ts
= 5.090 = 3.169 kg/cm2
Yct 53.009

M as 1503906.25
fas b = = = 7.873 kg/cm2
Zcb 191029.284

2. Akibat air hujan Mw = 683593.75 kg cm

ts Mw 683593.75
fw = = = 2.314 kg/cm2
Zct 295474.832

Yct - t 53.009 - 20
fw t = fw ts
= 2.314 = 1.441 kg/cm2
Yct 53.009

Mw 683593.75
fw b = = = 3.578 kg/cm2
Zcb 191029.284

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 13

3. Akibat beban hidup terotoar Mtr = 2343750 kg cm

ts Mtr 2343750
ftr = = = 7.932 kg/cm2
Zct 295474.832

Yct - t 53.009 - 20
ftr t = ftr ts
= 7.932 = 4.939 kg/cm2
Yct 53.009

Mw 2343750
ftr b = = = 12.269 kg/cm2
Zcb 191029.284

4. Akibat beban hidup/lalu lintas ML = 16982954.545 kg cm

ts Mw 16982954.545
fL = = = 57.477 kg/cm2
Zct 295474.832

Yct - t 53.009 - 20
fL t = fL ts
= 57.477 = 35.791 kg/cm2
Yct 53.009

Mw 16982954.55
fL b = = = 88.902 kg/cm2
Zcb 191029.284

Tabel perhitungan momen dan tegangan

No Momen (kg cm) f t (kg/cm2) f b (kg/cm2) f ts (kg/cm2)

1 Mas = 1503906.25 3.169 7.873 5.090

2 Mw = 683593.75 1.441 3.578 2.314

3 Mtr = 2343750 4.939 12.269 7.932

4 ML = 16982954.545 35.791 88.902 57.477

 Mt 2 = 21514204.55 45.340 112.623 72.812

Momen total adalah :

M = Mt1 + Mt2 = 15927734.38 + 21514204.545

= 37441938.920 kg cm

Tegangan total adalah :

ft = f1t + f2t = 145.733 + 45.340 = 191.073 kg/cm2 (tekan)

fb = f1b + f2b = 123.944 + 112.623 = 236.567 kg/cm2 (tarik)

f ts = 72.812 kg/cm2 (tekan)

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 14

TAHAP IV

Perencanaan tendon prategang dan besarnya gaya prategang.

Dalam perencanaan tegangan tarik pada serat bawah beton prategang difungsikan, sehingga

yang ditahan oleh post-tensioning adalah :

f b post b
= f total - fts

= 236.567 - 35.35

= 201.217 kg/cm2

Perkiraan letak kawat prategang diambil 15 % dari tinggi (h) balok dari bagian dasar

x = 15 % . H = 0.15 . 115

= 17.25 cm

b
f = Y - x = 52.854 - 17.25

= 35.604 cm

Besarnya gaya prategang (F)

F Fe
f bpost = +
A Zb

F F 35.604
201.217 = +
4175 128507.053

= 389516.0973 kg

Dari tabel VSL digunakan tendon VSL unit type 19 dengan nomor starnds 14

(untaian 14 kawat) yang mempunyai kapasitas 1930 KN atau 1930 x 101.97

= 196802.1 kg pada beban putus 75 %

Jumlah tendon yang dibutuhkan (n) adalah :

389516.0973
n = = 2.0 2 tendon
196802.10

F untuk 2 tendon = 2 x 196802.10 = 393604.20 > F = 389516.0973 kg

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 15

TAHAP V

Menentukan letak tendon dalam balok prategang kontrol harga e dan x

F F. e
f b post = +
A Zb

393604.20 393604.20 x e
201.217 = +
4175 128507.053

e = 34.91 cm

X = Yb - e = 52.85 - 34.91

= 17.94 cm

X diambil = 18 cm

e = 52.85 - 18 = 34.91 cm

2X = 1 . 10 + 1 . 15

25
X = = 12.5 cm
2
50 cm
Y = 52.85cm Y = 62.146 cm
115 cm

e = 34.91 cm
15
x = 17.94 cm
b

20
60 cm

Ganbar 4.9 Letak posisi tendon ditengah bentang

Tegangan yang terjadi akibat gaya prategang.

F F. e
f Ft = +
A Zt

393604 393604 . 34.915


= - = -31.463 kg/cm2 (tarik)
4175 109293.938

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 16

F F. e
f Fb = -
A Zb

393604 393604 . 34.915


= + = 201.217 kg/cm2 (tekan)
4175 128507.053

Pada daerah tumpuan tendon direncanakan diletakkan pada daerah dimana terletak

titik berat balok prategang sehingga e pada c.g.s =0, karena jumlah tendon yang digunakan

ada dua buah maka tendon diletakkan masing-masing dibawah dan diatas titik berat penampang

balok prategang dimana jarak antara tendon adalah 32,5 cm diukur dari as ke as dari tendon.

Yt

32.5

Yb

Gambar 4.10 Letak tendon pada daerah tumpuan

TAHAP VI

Kontrol tegangan-tegangan yang terjadi pada serat atas dan serat bawah

A. Pada saat pengecoran (dipikul oleh balok prategang)

a. Pada saat pengecoran (dipikul oleh balok prategang)

ft = fFt + fgt + fpt + fdt

= -31.463 + 74.609 + 62.546 + 8.578

= 114.270 kg/cm2 < fci = 300 kg/cm2


fb = fFb + fgb + fpb + fdb

= 201.217 - 63.454 - 53.195 - 7.295

= 77.273 kg/cm2 < fci = 300 kg/cm2

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 17

114.270

77.273
Gambar 4.11 Tegangan pada tengah bentang

b. Tegangan diperletakan (ujung balok)

Dari brosur VSL diperoleh untuk tipe tendon VSL 19 sc 19 tebal plat angker

= 265 mm, jadi tebal balok diperletakan diperbesar, bw = 265 + 2 . 100 = 465 mm

Diambil tebal badan (bw) = 48 cm

48 cm

Gambar 4.12 Dimesi penampang yang diperbesar pada perletakan


50 cm
15

I
1

II II
1 cm 48 cm

6 cm III

IV IV
6
20

60 cm

Gambar 4.12 Dimesi penampang yang diperbesar pada perletakan

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 18

- Perhitungan sifat-sifat penampang diperletakan titik berat penampang prategang

Luas penampang Jarak terhadap serat Statis Momen


Penampang (A) Atas (y) (S=A.Y)
cm 2 cm cm 3

A1 = 50 x 15 = 750 7.5 5625

A2 = 2( 1/2 x 1.0 x 1)= 1.0 15.333 15.333

A3 = 48 x 80 = 3840 55 211200

A4 = 2( 1/2 x 6 x 6)= 36 93.0 3348.000

A5 = 60 x 20 = 1200 105 126000

A = 5827 s = 346188.33

S 346188.33
Yt = = = 59.411 cm
A 5827

Yb = h - Yt = 115 - 59.411

= 55.589 cm

- Perhitungan momen inersia penampang prategang.

3
I1 = 1/12 50 15 + 750 51.91107 2 = 2035132.271 cm4

3
I2 = 2 1/36 1.0 1.0 + 1.0 44.07774 2 = 3885.750155 cm4

3 2
I3 = 1/12 48 80 + 3840 4.411 = 2122717.113 cm4

3
I4 = 2 1/36 6 6 + 36 33.58893 2 = 81303.544 cm4

3 2
I5 = 1/12 60 20 + 1200 45.589 = 2534020.112 cm4

I = 6777058.791 cm4
- Perhitungan modulus penampang prategang.

I 6777058.791
Zt = = = 114070.631 cm3
Yt 59.411

I 6777058.791
Zb = = = 121913.830 cm3
Yb 55.589

- Perhitungan letak titik gali (kern) penampang prategang.

I 6777058.791
i2 = = = 1163.044 cm2
A 5827

2
kt = i = 1163.044 = 20.922 cm
Yb 55.589

2
kb = i = 1163.044 = 19.576 cm
Yt 59.411

- Statis momen terhadap garis netral

S = 750 . 51.91107 + 1.0 . 44.07774 + 3840 . 4.411 +

36 . 33.58893 + 1200 . 45.589

3
= 111831.823 cm

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 19

Titik berat penampang komposit

Luas penampang Jarak ke serat atas Statis momen


No
Acomp (cm2) Y (cm) Sc = Acomp . Y (cm3)

1 Plat lantai Y1 = 1/2 t 28284.2712


A1 = 141.4 x 20 = 10
= 2828.427

t
2 Balok Prategang Y2 = Y + t 462728.333
A2 = 5827 = 59.411 + 20
= 79.411

 Acomp = 8655.427 Sc = 491012.605

Sc 491012.605
Yct = = = 56.729 cm
Acomp 8655.427

Ycb = h + t - Yct

= 115 + 20 - 56.729

= 78.271 cm

- Perhitungan momen inersia penampang komposit

I comp = I prategang + I plat

= Ib + (Ab . Y2) + (Ip + (Ap . Y2)


2
3 2
= 6777058.791 + 5827 22.682 + 1/12 141.4 20 + 2828.427 46.729

= 9774947.707 + 6270398.564

= 16045346.271 cm4

- Perhitungan letak titik gali (kern) penampang komposit

I comp 16045346.271
i2 = = = 1853.790 cm2
A comp 8655.427

i2 1853.790
kct = = = 23.68421
Ycb 78.271

kcb i2 1853.790
= = = 32.67807
Yct 56.729

- Statis momen terhadap titik berat penampang composit.

S comp = 2828.427 . 46.729 + 750 . 29.22887 + 1.0 . 21.39554 +

3840 . 18.27113 + 36 . 56.27113 + 1200 . 68.27113

= 308224.507 cm3

Jadi luas penampang balok diperletakan (ujung balok) A = 5827 cm2

Untuk menghindari tegangan yang berlebihan pada bagian akibat gaya prategang maka

tendon dibengkokkan keatas hingga titik berat tendon berimpit dengan titik berat penam-

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 20

pang prategang. Jadi tegangan yang terjadi pada ujung balok (prategang) adalah tega-

ngan merata akibat gaya prategang.

F 393604.20
ft = = = 67.548 kg/cm2 < f ci = 300 kg/cm2
A 5827

F 393604.20
fb = = = 67.548 kg/cm2 < f ci = 300 kg/cm2
A 5827

67.548

67.548
Gambar 4.13 Tegangan pada perletakan
B. Pada saat beban hidup bekerja (dipikul oleh penampang komposit)

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 21

a. Ditengah bentang

fcts = fasts + fwts + fLts

= 5.090 + 2.314 + 57.477

= 64.880 kg/cm2

fct = fFt + fpt + fdt + fgt + fast + fwt + ftrt + fLt

= -31.463 + 62.546 + 8.578 + 74.609 + 3.169 + 1.441

+ 4.939 + 35.791

= 159.610 kg/cm2 < fcs = 225 kg/cm2

fcb = fFb + fpb + fdb + fgb + fasb + fwb + ftrb + fLb

= 201.217 - 53.195 - 7.295 - 63.454 - 7.873 - 3.578

- 12.269 - 88.902

= -19.605 kg/cm2 < fts = -35.35 kg/cm2

64.880
159.610

-19.605

Gambar 4. 14 Tegangan pada tengah bentang setelah beban hidup bekerja

b. Pada perletakan

F 393604.20
fct = = = 67.548 kg/cm2 < f cs = 225 kg/cm2
A 5827

F 393604.20
fcb = = = 67.548 kg/cm2 < f cs = 225 kg/cm2
A 5827

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 22

67.548

67.548
Gambar 4.15 Tegangan pada perletakan

TAHAP VII

Perhitungan kehilangan-kehilangan gaya prategang

1. Akibat relaksasi baja

D fs1 = 7 % f nominal baja

Dimana :
2.
1930 x 1.0197 . 10
f nominal =
-2.
1417 . 10

= 13888.645 kg/cm2

D fs1 = 7% 13888.645

= 972.2052 kg/cm2

2. Akibat perpendekan elastin beton

F
D fs2 = n
A

Es = Modulus elastis baja VSL = 1.98 . 10 6


kg/cm2

Ec = Modulus elastis beton = 4700 f 'c

= 4700 50

= 33234.019 Mpa

= 332340.187 kg/cm2

F = Gaya prategang = 393604.20 kg

A = Luas penampang beton = 4175 cm2

6
n = Es = 1.98 . 10 = 5.958
Ec 332340.187

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 23

Afs2 F
= n
A

393604.20
= 5.958
4175

= 561.68 kg/cm2

3. Akibat penyusutan beton

D fs3 =  Cs . Es

Dimana :

6
200 . 10
 Cs =
Log 10 (28 + 2)

t = umur beton pada saat transfer diambil 28 hari

6
Es = 1.98 . 10

6
200 . 10
D fe3 = 1.98 . 10 6
(28 + 2)
Log 10

= 132 kg/cm2

4. Akibat rangkak beton (creep)

D fe4 = n . Ø . f 'c

Dimana :

n = perbandingan modulus elastis baja dan beton = 5.96

Ø = Koofisien rangkak = 1.5

f 'c = tegangan isin beton = 500 kg/cm2

D fe4 = 5.96 . 1.5 . 500

= 4470 kg/cm2

5. Akibat gesekan dan woobble effect dari tendon

D fe4 = f pj - f ps

Dimana :

f ps = f pj . e- (µ

e = 2.7183

µ = koofisien rangkak = 0.2

k = koofisien wobble = 0.0016

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 24

52.85 34.91

17.94
1/2 L = 13 M

Gambar 4.16 Lengkungan tendon dari ujung jacking

4 . fx 4fx 4fx2
Y = (L-x) = -
L2 L L2

dy 4f 8fx
= -
dx L L2

dy
Untuk : x = 1/2 . L (ditengah bentang) = 0
dx

dy 4f
x = 0 (ujung bentang) =
dx L

Jadi sudut kemiringan pada perletakan adalah

4f
a = (radian)
L

4 . 0.3491
= = 0.055864
25

(μa + kx) = 0.2 x 0.055864 + 0.0016 x 13 = 0.031173

f ps = f pj . e- 0.0312

fpu
f pj = 0.85
As

Dari tabel brosur VSL diperoleh untuk VSL unit type 19 dengan nomor strands 14

As = 14.17 cm2

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 25

fpu = Kekuatan baja pada beban (100%)

= 2500 x 1.0197 x 10 2 = 254925 kg

254925
f pj = 0.85 = 15291.90 kg/cm2
14.17

f ps = f pj . e- 0.0312

0.0312
= 15291.90 x 2.7183

= 14822.56 kg/cm2

D fe4 = f pj - f ps

= 15291.90 - 14822.56

= 469.34 kg/cm2

6. Akibat slip penjangkaran

Da . Es
D fe4 =
l

Dimana :

Da = besarnya slip penjangkaran = 0.6

Es = 1980000

l = panjang lengkungan tendon

l = L + 8 . f2
3 L

dimana :

L = Panjang bentang
f = Tinggi maximum lengkung
69.104
36.604

35

20

Gambar 4.17 Letak tendon pada tumpuan dan lapangan

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 26

f1 = 36.604 - 20 = 16.60

f2 = 69.104 - 35 = 34.10

Diambil f = f2 = 34.10 cm = 0.34 m

Panjang lengkung tendon ( l )

2
8 0.341
l = 25 + . = 25.0124 m = 2501.24 cm
3 25

0.6 x 1980000
D fs4 =
2501.24

= 474.9643 kg/cm2

Total kehilangan gaya prategang

Δ fs total = Δfs1 + Δfs2 + Δfs3 + Δfs4 + Δfs5 + Δfs6

= 972.2052 + 561.68 + 132 + 4470.00 + 469.34 + 474.9643

= 7080.19 kg/cm2

Persentase kehilangan gaya prategang

Δ fs total
% fs total = x 100 %
f pj

7080.19
= x 100 % = 46.30 %
15291.90

Besarnya gaya prategang awal yang harus diberikan

Fo = 100 % + 30.16 % = 130.16 %

= 130.16 % x 393604.20

= 512315.23 kg

512315.23
Untuk 1 buah tendon =
2

= 256157.613 kg

Tegangan putus tendon VSL 19 Sc 14 = 263082.6

Fo untuk 1 tendon = 256157.613 kg < 263082.6 kg (aman)

Tegangan-tegangan akibat prategang awal

1. Pada tengah bentang (sebelum komposit)

Jurusan Teknik Sipil - UKIP


Perencanaan Bangunan Atas IV - 27

fFOt = 130.16 % x fFt

= 130.16 % x -31.463 = -40.9529 kg/cm2

fFOb= 130.16 % x fFb

= 130.16 % x 201.217 = 261.904 kg/cm2

2. Pada perletakan (sebelum komposit)

fFOt = 130.16 % x fFt

= 130.16 % x 67.548 = 87.92092 kg/cm2

fFOb= 130.16 % x fFb

= 130.16 % x 67.548 = 87.92092 kg/cm2

Kontrol tegangan setelah gaya prategang dipindahkan kebeton

1. Pada tengah bentang

f t = fFOt + f gt

2 2
= -40.9529 + 74.609 = 33.656 kg/cm < f ci = 300 kg/cm

f b = fFOb + f gb

2 2
= 261.904 - 63.454 = 198.450 kg/cm < f ci = 300 kg/cm

2. Pada perletakan

f t = fFOt = 87.92092 kg/cm


2
< f ci = 300 kg/cm
2

f b = fFOb = 87.92092 kg/cm


2
< f ci = 300 kg/cm
2

Tegangan-tegangan yang terjadi pada tingkat beban kerja setelah komposit

1. Pada tengah bentang

f t = fFOt + f gt + f pt + f dt + f ast + f wt + f trt + f Lt

= -40.9529 + 74.609 + 62.546 + 8.578 + 3.169 + 1.441 + 4.939 +

35.791

2
= 150.121 kg/cm2 < f ci = 300 kg/cm

f b = fFOb + fgb + fpt + fdt + fast + fwt + ftrt + fLt

= 261.904 + 63.454 + 53.195 + 7.295 + 7.873 + 3.578 + 12.269 +

88.902

2
= 498.471 kg/cm2 < f ci = 300 kg/cm

2. Pada perletakan

f t = fFOt = 87.92092 kg/cm


2
< f ci = 300 kg/cm
2

f b = fFOb = 87.92092 kg/cm


2
< f ci = 300 kg/cm
2

Jurusan Teknik Sipil - UKIP


PERENCANAAN JEMBATAN

III. 2. PERHITUNGAN PIER JEMBATAN


1

0.6
I
1
II

0.5 III IV
0.5 8.75

19 22.6 m

6.85

6
0.5
VI VII
1 VIII 1

1.5 1 1.5

A. BEBAN - BEBAN YANG BEKERJA PADA PIER


I. Berat jembatan
V = 267.24 ton

II. Berat sendiri pier

Bagian Luas Berat (ton)


I 0.6 1.44
II 2 4.8
III 0.125 0.3
IV 0.125 0.3
V 20 48
VI 0.375 0.9
VII 0.375 0.9
VIII 4 9.6
27.6 66.24

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

III. Beban akibat aliran air dan benda-benda hanyut

Tekanan air pada pier (P) = K . V2 Dimana : K = Koef. Bentuk = 0,075 (balok persegi)
V= 6.435 m/det
2
P = 0.075 . 6.43 = 3.106 t/m2

Gp = P . F = 3.106 . ( 1 . 6.85 ) = 21.273 ton

Penulangan Pier

0.6
I
1
II

0.5 III IV
0.5 8.75

19 22.6 m

6.85

6
0.5
VI VII
1 VIII 1

1.5 1 1.5

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Tabel perhitungan gaya geser dan momen


Jarak Jarak V H Mx = H . y. My = V . x.
Beban
x (m) y (m) (ton) (ton) tm tm
Bangunan atas
a. Beban mati 0 0 267.24 0 0
b. Beban hidup 0 0 148.99 0 0
c. Gaya rem Rm - 5.55 7.4494 41.3441495 -
d. Gaya gesek Gg - 5.55 40.087 222.4804219 -
e. Beban angin A - 5.55 2.1 11.655 -
f. Beban gempa Gh - 5.55 46.182 256.3115153 -
g. Beban merata q 1.35 - 29.7 40.095
h. Plat injak 1 - 6.72 6.72

Bangunan bawah
a. Berat abutment
I 0.5 22.3 1.44 - - 0.72
II 0 21.5 4.8 - - 0
III 0.6667 20.833 0.3 - - 0.2
IV 0.6667 20.833 0.3 - - 0.2
V 0 11 48 - - 0
VI 1 1.1667 0.9 - - 0.9
VII 1 1.1667 0.9 - - 0.9
VIII 0 0.5 9.6 - - 0
b. Tekanan Air
Pa - 9.2833 21.273 197.483
518.89 117.09 729.274 49.735

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Penulangan Pier

0.6
I
1
II

I III IV I
0.5
0.5 8.75

19 22.6 m

6.85

II III II

6
0.5
VI VII
1 VIII 1

1.5 1 1.5

III

I. Potongan I - I

Tabel perhitungan gaya geser dan momen


Beban Berat G (ton) Jarak y (m) Mx = G . y.
Bangunan atas
Vertikal 452.6516761 0 0.000
Horisontal 95.81821381 2.1000 201.218
Berat abutment
I 1.44 1.8000 2.592
II 4.8 1 4.800
III 0.3 0.333333333 0.100
IV 0.3 0.333333333 0.100
V 48 0.25 12.000
507.4916761 220.8102490

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Dik : K 325 s'b = 110 kg/cm2


n = 19
U32 sa = 1740 kg/cm2

sa 1740
fo = = = 0.8325
n . sb 19 . 110

M 220810
eo1 = = = 0.4351 m
N 507492

1 1
eo2 = . ht = . 1 = 0.03 m
30 30

eo = eo1 + eo2 = 0.4684 m

eo 0.4684
= = 0.47 Dari tabel diperoleh C = 7.58
ht 1

lk 2 1
e1 = C ht = 7.58 1 = 0.0758 m
100 . ht 100 . 1

e2 = 0,15 . ht = 0.15 m

e = eo + e1 + e2 = 0.6942 m

ea = e + 1/2 ht - 0,05 = 1.1442 m

N ea = 507491.68 . 1.1442 = 580690 kgm

h = ht - 5 = 95 cm

95
Ca = = 1.193
19 . 580690
1 . 1740.0

Ca = 1.193 ) nw = 0.7439 z = 0.87


d = 0.6 ) f = 0.852 (OK)

ea 1.1442
= = 1.2 Dari tabel diperoleh i = 3.97
h 0.95

iA = w.b.h = 0.0392 . 100 . 95

371.95
A = A' = = 93.7 cm2 (tulangan simetris)
3.97

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Dipilih tulangan= f 19 - 25 = 113 cm2

II. Potongan II - II

Tabel perhitungan gaya geser dan momen


Beban Berat G (ton) Jarak y (m) Mx = G . y.
Bangunan atas
Vertikal 452.6516761 0 0.000
Horisontal 95.81821381 21.1000 2021.764
Berat abutment
I 1.44 20.8000 29.952
II 4.8 20 96.000
III 0.3 19.33333333 5.800
IV 0.3 19.33333333 5.800
V 45.6 9.5 433.200
Tekanan air
21.27285637 8.283333333 176.210
526.3645325 2768.726

Dik : K 325 s'b = 110 kg/cm2


n = 19
U32 sa = 1740 kg/cm2

sa 1740
fo = = = 0.8325
n . sb 19 . 110

M 2768726.472
eo1 = = = 5.2601 m
N 526364.5325

1 1
eo2 = . ht = . 1 = 0.03 m
30 30

eo = eo1 + eo2 = 5.2934 m

eo 5.2934
= = 5.29 Dari tabel diperoleh C = 7.7
ht 1

lk 2 1
e1 = C ht = 7.7 1 = 0.077 m
100 . ht 100 . 1

e2 = 0,15 . ht = 0.15 m

e = eo + e1 + e2 = 5.5204 m

ea = e + 1/2 ht - 0,05 = 5.9704 m

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

N ea = 526364.53 . 5.9704 = 3E+06 kgm

h = ht - 5 = 95 cm

95
Ca = = 0.5128
19 . 3E+06
1 . 1740.0

Ca = 0.5128 ) nw = 3.511 z = 0.89


d = 1 ) f = 0.887 (OK)

ea 5.9704
= = 6.28 Dari tabel diperoleh i = 1.47
h 0.95

iA = w.b.h = 0.1848 . 100 . 95

1755.5
A = A' = = 1194 cm2 (tulangan simetris)
1.47

Dipilih tulangan= 3f 25 - 12 = 1227 cm2

III. Potongan III - III


Berdasarkan pada momen guling, tahanan, gaya vertikal.
SMx 729.274
x = = = 1.4054 m
SVx 518.892

M = V . e + My = 518.892 . ( 2.5 - 1.41 ) + 49.735 = 617.69 tm

wx = 1/6 . b2 . h = 1/6 . 4 2
. 1.25 = 3.3333333 m3

V M 518.892 617.69
smax = + = + = 284.14 t/m
A w 5.250 3.3333

V M 518.892 617.69
smin = - = - = -86.471 t/m
A w 5.250 3.3333

Beban - beban yang bekerja pada kaki abutment


q = 158.98 + 20.55 + 32.4
= 211.93 t/m2

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Menentukan momen maksimum

211.93

211.93
Mmaks = 1/8 . q . l2 = 105.96 tm
N = 119.19
Dik : K 325 s'b = 110 kg/cm2
n = 19
U32 sa = 1740 kg/cm2

sa 1740
fo = = = 0.8325
n . sb 19 . 110

M 105963
eo1 = = = 0.889 m
N 119190

1 1
eo2 = . ht = . 1 = 0.03 m
30 30

eo = eo1 + eo2 = 0.9224 m

eo 0.9224
= = 0.92 Dari tabel diperoleh C = 7.69
ht 1

lk 2 1
e1 = C ht = 7.69 1 = 0.0769 m
100 . ht 100 . 1

e2 = 0,15 . ht = 0.15 m

e = eo + e1 + e2 = 1.1493 m

ea = e + 1/2 ht - 0,05 = 1.5993 m

N ea = 119190 . 1.5993 = 190616 kgm

h = ht - 5 = 95 cm

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

95
Ca = = 2.0823
19 . 190616
1 . 1740.0

Ca = 2.0823 ) nw = 0.2685 z = 0.85


d = 0.2 ) f = 1.062 (OK)

ea 1.5993
= = 1.68 Dari tabel diperoleh i = 2
h 0.95

iA = w.b.h = 0.0141 . 100 . 95

134.25
A = = 67.1 cm2
2

Dipilih tulangan= f 25 - 20 = 245 cm2

A' = d . i . A = 26.9 cm2

Dipilih tulangan= f 12 - 20 = 57 cm2

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Perencanaan Tiang Pancang

Data - data perencanaan


Elevasi Sondir = + 71.25 m
Elevasi Kaki pier = + 71.25 m
Elevasi tanah keras = + 71.25 - 11 = 60.25 m
Direncanakan panjang tiang pancang = 11 - 1 = 10 10 m
2
Data sondir : qc = 95 kg/cm
STf = 450 kg/cm

qc . A STf . K A = 1/4 p d2
Q = + 2
3 5 = 1/4 . 3,14 . 40
= 1256 cm2

95 . 1256 450 . ( p . 40)


Q = + = 51077 kg
3 5

= 51.077 ton

Jumlah tiang pancang


V 518.89
n = = = 10.2  11 buah
Q 51.077

0.50

1.25

1.25

0.50

1.00 1.50 1.50 1.50 1.50 1.50 1.50 1.00

Syarat S < 2,5 D


S  3,0 D (min 0,60 m dan maks 2,00 m)

S  3
Sn = 150 cm dan Sm = 125 cm

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

Menentukan Beban Akibat Momen Yang Dipikul Tiang Tengah

P1
P2 P0
P3

X3 X4 P4
P5
X2 X5 P6

X1 X6

M = 2 P1.X1 + P2.X2 + 2 P3.X3 + 3 P0. 0 + 2 P4.X4 + P5.X5 + 2 P6.X6

Analogi :
P2 : P1 = X1 : X2 P4 = P1. (X4/X1)

P2 = P1. (X2/X1) P5 = P1. (X5/X1)

P3 = P1. (X3/X1) P6 = P1. (X6/X1)

M = 2 P1.X1 + P1.(X22/X1) + 2 P1.(X32/X1) + 0 + 2 P1.(X42/X1) + P1.(X52/X1)


+ 2 P1.(X62/X1)

M = (P1/X1) (2X12 + X22 + 2X32 + 2 X42 + X52 + 2 X62)

M. X1
P1 =
(2X1 + X2 + 2X3 + 2 X42 + X52 + 2 X62)
2 2 2

DIMANA :
M = 729.27410 - 49.73500 = 679.53910

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

X1 = 4.5 m X4 = 1.5 m
X2 = 3.0 m X5 = 3.0 m
X3 = 1.5 m X6 = 4.5 m

679.53910 x 4.50
PM =
( 2. 4.5 ^2 + 3.0 ^2 + 2. 1.5 ^2 + 2. 1.5 ^2 + 3.0 ^2 + 2. 4.5 ^2)

3057.92596
PM = = 28.314 Ton
108.00

V
PMAKS = + PM
n

#REF!
PMAKS = + 28.314
11

PMAKS = #REF! < QTanah ( 51.077 ) #REF!

Effisiensi Kelompok Tiang Pancang

A B B A

C D C

A B A
B

1. Metode Feld

3 8
Effisiensi Tiang A = 1 - =
11 11
4 7
Effisiensi Tiang B = 1 - =
11 11
4 7
Effisiensi Tiang C = 1 - =
11 11
4 7
Effisiensi Tiang D = 1 - =
11 11

8 32
4 Buah Tiang A = 4 x Eff A = 4 =
11 11
7 28
4 Buah Tiang B = 4 x Eff B = 4 =
11 11
7 14
2 Buah Tiang C = 2 x Eff C = 2 =
11 11

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

7 7
1 Buah Tiang D = 1 x Eff D = 1 =
11 11
81
Total Eff. = = 7.3636
11
7.3636
Effisiensi Satu Tiang = = 0.6694
11

2. Metode Converse Labone Formulae

q (n - 1) m + (m - 1) n
SFf . N = 1 - .
90 m .n

Dimana : 40 0
q = Arc Tan = 17.745
125
m = 3
n = 7
17.7 7 - 1 3 + 3 - 1 7
SFf . N = 1 - .
90 3 . 7

= 0.6996

Karena tiang juga mengandalkan friction, maka :

95 . 1256 450 . ( p . 40)


Q = + 0.6996 = 47681 kg
3 5

= 47.681 ton

Q > Q ( #REF! ton ) #

Kontrol dengan cara perpindahan :


1. Menentukan konstanta pegas
~ Konstanta pegas arah axial
Ap . Ep
Kv = a .
l
dimana :
l
a = 0.041 - 0.27 = 2.2925
D
Ap = 1256 cm2
Ep = 6400 . fck = 156767 kg/cm2
l = 25 m = 2500 cm

1256 . 156767
Kv = 2.2925 . = 180557 kg/cm
2500

~ Konstanta pegas arah ortogonal

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

K1 = 4EI b3 = 29358.02518 kg/cm


2
K2=K3 = 2EI b = 2039996.384 kg/rad
K4 = 2EI b = 283505802.8 kgcm/rad

E = 156767 kg/cm
p
I = . D4 = 125664 cm4
64
4 k.D
b = = 0.007195607 cm-1
4EI
k = ko . y-1/2 = 5.2812204 kg/cm2
ko = 0,2 . Eo . D-3/4 = 5.2812
Eo = 28 N = 420 kg/cm2

Untuk kemiringan tiang pancang dianggap qi = 0, hal ini adalah kondisi kritis pada
stabilitas abutment.

1. Menentukan koefisien matriks perpindahan


Axx = S (K1 cos2qi + Kv sin qi) = n . K1 = 322938.28
Axy = Ayx = S (Kv . K1) sin qi . cos qi = 0
Axa = Aax = S (Kv - K1) xi sin qi . cos qi - K2 cos qi = -n . K2 = -22439960

Ayy = S (K1 cos2qi + Kv sin qi) = n . Kv = 1986123.8


2 2
Aya = Aay = S (Kv cos qi + K1 sin qi) xi +K2 sin qi) = 0
Aaa = S (Kv cos2qi + K1 sin2 qi) xi2 +(K2 + K3) xi . sin qi K4)
= SKv . x2 + SK4 = 3123032609

Formula Matriks perpindahan tiang pancang

Axx Axy Axa dx Ho


Ayx Ayy Aya dy = Vo
Aaa Aay Aaa d Mo

322938.28 0 -22439960.2 dx 117091


0 1986123.8 0 dy = 518892
-22439960 0 3123032609 a 729.274

dx = 0.7241569 cm
dy = 0.2612585 cm
a = 0.0052035 rad

dxi' = dx cos qi - (dy + axi) sin qi = dx cos qi = dxi


dx1 = dx = 0.724156928 cm
dx2 = dx = 0.724156928 cm
dx = dx = 0.724156928 cm

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

dyi' = dx cos qi - (dy + axi) cos qi = (dy + axi)


dy1 = 0.729360455 cm
dy2 = 0.26125848 cm
dy3 = 0.190551604 cm

Pni = Kv . dyi

PN1 = 180556.71 . 0.729360455 = kg


PN2= 180556.71 . 0.26125848 = kg
PN3 = 180556.71 . 0.190551604 = kg

PHi = K1 dx - K2 a

PH1 = 10644.643 kg
PH2= 10644.643 kg
PH3 = 10644.643 kg

Mti = -K3 dxi + K4 a

Mt1 = -2047.648 kg m
Mt2= -2047.648 kg m
Mt3 = -2047.648 kg m

Penulangan Tiang Pancang


Penulangan tiang pancang dihitung berdasarkan kebutuhan pada waktu pengangkatan

a. diangkat

a L - 2a a

M1 M3

M2

M1 = 1/2 . g . a2 g = Berat tiang pancang (kg/m) = 302 kg/m

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060


PERENCANAAN JEMBATAN

M2 = 1/8 . g . (L - 2a)2 - 1/2 g . a2

M1 = M2 1/2 .g. a2 = 1/8 . g . (L - 2a)2 - 1/2 g . a2

4a2 + 4a L - L2 =0 L = 10 m

4a2 + 4a 10 - 10 2
= 0

4 a2 + 40 a - 100 = 0
Dengan rumus ABC diperoleh :
a1 = 2.0711
a2 = -12.071 (tidak memenuhi)

M1 = M2 =1/2 g. a2 = 1/2 . 302 . 2.07 2


= 646.81 kgm

b. diangkat

Dari penurunan rumus diperoleh


a persamaan :
2 a2 - 4 a L + L2 = 0

2a2 - 4a 10 - 10 2
= 0

L-a 2 a2 + 20 a - 100 = 0
Dengan rumus ABC diperoleh :
a1 = 3.6603
a2 = -13.66 (tidak memenuhi)

M1 = M2 =1/2 g. a2 = 1/2 . 302 . 3.66 2


= 2020.3 kgm

Jadi keadaan yang paling menentukan adalah keadaan b. (Mmaks = 2020.3 kgm)
Penulangan diambil = 6 f 19

Andi Burhanuddin/D11198107 Arif Hasan Akuba/D11198060