RENCANA ANGGARAN BIAYA

BACK UP SISTEM TATA UDARA LAB MIKROBIOLOGI BSL II


LABORATORIUM MIKROBIOLOGI RSUP PERSAHABATAN
TA.2021

NO. ITEM PEKERJAAN VOL SAT HARGA SAT HARGA

I
A PEKERJAAN MEKANIKAL, ELEKTRIKAL KALSIFIKASI KHUSUS
PENGADAAN DAN PEMASANGAN

Peralatan Utama
1 a. Sistem Pendingin Ruangan 1,00 unit 266.271.000 266.271.000
AHU (Air Handling Unit) merk MQ- Quay
Special Custom for BSL
Casing Indoor double skin, 50mm PolyUrethan + 1.2mm alluminum plat
Nominal Capacity, : 140.000 Btu/h
Nominal Capacity, W : 29310 Watt
Nominal Total Input Power, W : 10,072 KW / 22,6 Ampere
Refrigerant Freon Type : R407
Refrigerant Control : Indoor TXV
Control : Wired Control
Sound Pressure Level, dBA : 57 dbA
Airflow, cfm : 4200 Cfm

Out Door AHU 16 PK : 2,00 Unit 35.209.000 70.418.000


Product MQ- Quay
Special Custom for clean room/ BSL fungsi khusus
Casing galfanis : 15,9 A
Static Pressure minimum : 4.0 (onsite setup)
Air Flow Capacity 4500 cfm
Support Ambalan Beton Site Mix untuk peletakan unit Out Door

b. Suppport Unit AHU dengan UNP 150x75x65 196,00 Kg 18.500 3.626.000


c. Biaya Erection Support Unit AHU 196,00 Kg 4.500 882.000
d. Pembuatan Atap Spandek rangka Hollo dan tiang 40x60 Hollo termasuk umpakan kolom 24,00 m2 165.000 3.960.000
e. Alat Bantu Angkat AHU sewa Forklip 1,00 Ls 3.000.000 3.000.000

2 Pekerjaan Instalasi Pipa Refrigrant, Pipa Drain Sistem Pendingin


- Pipa tembaga ATSM B280 Dia 1 1/8" + Isolasi Class A 10,00 m' 345000 3.450.000
- Pipa tembaga ATSM B280 Dia 3/8 " + Isolasi Class A 10,00 m' 125000 1.250.000
- Filter Dryer Sesuai Kapasitas AHU 16 PK 2,00 Bh 675.000 1.350.000
- Sight Glass Sesuai Kapasitas AHU 16 PK 2,00 Bh 350.000 700.000
- Pipa Drain PVC 1 Inch ex Wavin AW 10,00 m' 84.000 840.000
- Penambahan Freon R407 1,00 Ls 3.250.000 3.250.000
- Pemasangan Cable Tray 150x50 non Cover termasuk Support 10,00 m' 225.000 2.250.000

5 Pekerjaan Ducting
a. Ducting A Suplay Air 12,60 m2 795.000 10.017.000
Material BJLS 80um
Isolasi-luar, Material
termasuk Hanger Support per 1 meter
b. Ducting B Return Air 16,00 m2 795.000 12.720.000
Material BJLS 80um
Isolasi-luar, Material
termasuk Hanger Support per 1 meter
termasuk Hanger Support per 1 meter
d. Box Plennum Return 1500x1000x800 + isolasi Thermobreak 12mm, lot 1,00 Unit 2.250.000 2.250.000
Material BJLS 80
e. NRD Non Return Damper Motoriized sesuai ukuran ducting/ Bibo 4,00 Bh 2.600.000 10.400.000

6 Motor fan exhaust Kapasitas 6550 cfm termasuk Asesories Chasing + Support Pemasangan 1,00 unit 58.500.000 58.500.000
Ex Nicotra
Voltage: 380V/ 50 Hz
Daya : Sesuai Keluaran Product (Watt)
Kecepatan fan dapat diatur dengan variable Speed
termasuk pondasi beton

7 Pekerjaan Instalasi Pengkabelan Sistem HVAC


a. Main Kabel Power untuk AHU 15,00 m' 72.000 1.080.000
NYY 4 x 6mm , setara Supreme/ 4 Besar
b. Main Kabel Power untuk AHU ke Heater 15,00 m' 72.000 1.080.000
NYY 4 x 6mm , setara Supreme/ 4 Besar
c. Main Kabel untuk Exhaust Fan 15,00 m' 72.000 1.080.000
NYY 4 x 6mm , setara Supreme/ 4 Besar
d. Main Panel AC ke Outdoor Unit 30,00 m' 72.000 2.160.000
NYY 4 x 6mm , setara Supreme/ 4 Besar
e Kabel Kontrol dari Panel HVAC ke Panel Bcakup spliter AHU 336,00 m' 15.200 5.107.200
NYYHY 3 x 0.75mm

8 Balancing, Documentation, and Test Commissioning 1,00 lot 2.500.000 2.500.000


RENCANA ANGGARAN BIAYA
BACK UP SISTEM TATA UDARA LAB MIKROBIOLOGI BSL II
LABORATORIUM MIKROBIOLOGI RSUP PERSAHABATAN
TA.2021

NO. ITEM PEKERJAAN VOL SAT HARGA SAT HARGA

9 Panel Kontrol Sistem Negatif Presure (Sistem Backup)


- Box panel Uk.600x800x300 (Out door) 1,00 Bh 2.500.000 2.500.000
Bus Bar + Bus Plate 1,00 Ls 650.000 650.000
Contactor 25A/3P 20,00 Bh 517.000 10.340.000
Timer 24 Hours 1,00 Bh 575.000 575.000
Timer Delay 8,00 Bh 650.000 5.200.000
Lamp Pilot 20,00 Bh 35.000 700.000
Selector M.O.A 2,00 Bh 165.000 330.000
Relay Omron 220 10,00 Bh 225.000 2.250.000
Biaya Wiring 1,00 Ls 2.350.000 2.350.000
- Sistem kontrol backup bergantian 12 jam on/off
Manual - Automatis Kontrol

SUB TOTAL PEK. KHUSUS PERALATAN UTAMA BACKUP SISTEM BSL II : 493.036.200
PPN 10 % : 49.303.620
JUMLAH TOTAL : 542.339.820
PEMBULATAN : 542.339.000

Jakarta 09 Oktober 2020


Ka. Instalasi Pemeliharaan Sarana
RSUP Persahabatan

Fredi Frima Sati. A.Md