TUMONO,S PdI
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN 3 RUANG KELAS MI NURUL ISLAM CANDIPURO
NO URAIAN PEKERJAAN VOLUME SAT HARGA JUMLAH HARGA SUB JUMLAH JUMLAH HARGA
A LANTAI 02
I PEKERJAAN STUKTUR
1 Beton Kolom K-250 10.824 m3 7,976,000.00 86,328,874.08
2 Beton Ring Balok K-250 6.830 m3 5,976,000.00 40,816,080.00
Jumlah B.I 127,144,954.08
II PEKERJAAN PASANGAN
1 Pek. Pasangan Batu Bata 1/2 Batu 533.511 m2 63,750.50 34,011,561.13
2 Pek. Plesteran 1067.021 m2 34,875.40 37,212,784.18
3 cor dak 2067.021 m2 54,875.40 113,428,604.18
4 Pek. Acian 1067.021 m2 24,355.00 25,987,296.46
5 Pek. Sponengan 718.360 m' 6,707.45 4,818,363.78
Jumlah B.II 215,458,609.73
III PEKERJAAN KUSEN DAN KACA
1 Pek. Pembuatan Kusen Aluminium 2.244 m3 217,813.00 488,667.82
2 Pek. Daun Jendela Kaca 5 mm Rangka Aluminium 50.074 m2 223,925.00 11,212,730.88
3 Pek. Pembuatan Daun Pintu Panil Jati 12.600 m2 242,830.00 3,059,658.00
4 Pek. Pasang Selot Pintu 8.000 bh 150,550.00 1,204,400.00
5 Pek. Pasang Engsel Pintu 8.000 psg 35,000.00 280,000.00
6 Pek. Pasang engsel Jendela 132.000 psg 35,000.00 4,620,000.00
7 Pek. Pasang Hak Angin 132.000 psg 30,000.00 3,960,000.00
8 Pek. Pasang Grendel Tanam Jendela 132.000 bh 20,000.00 2,640,000.00
Jumlah B.III 27,465,456.70
IV PEKERJAAN LANTAI DAN PLAFOND
1 Pek. Pasangan Keramik Lantai 402.900 m2 115,817.00 46,662,669.30
2 Pek. Pasangan Keramik Dinding 118.100 m2 95,000.00 11,219,500.00
3 Pek. Pasangan Langit-langit Gypsum rangka hollow 0.4m 438.900 m2 85,000.00 37,306,500.00
4 Pek. Pasang List Plafond t:12 cm gypsum 305.200 m' 24,750.00 7,553,700.00
Jumlah B.IV 102,742,369.30
V PEKERJAAN ATAP
1 Pek. Rangka Atap Baja Ringan t:0.75 lapis alumunium foil 651.200 m2 230,000.00 149,776,000.00
2 Pek. Pasangan Genteng Vlampress Sokka 651.200 m2 82,504.00 53,726,604.80
3 Pek. Pasangan Bubungan Genteng Sejenis 43.000 m' 48,014.00 2,064,602.00
4 Pek. Pasangan Talang BJLS 0.2 12.600 m2 35,514.60 447,483.96
Jumlah B.V 206,014,690.76
VI PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi Titik Lampu 51.000 ttk 130,000.00 6,630,000.00
2 Pek. Pasang Lampu Neon 1x20 W inbox 43.000 bh 125,000.00 5,375,000.00
3 Pek. Pasang Saklar Single 4.000 bh 25,000.00 100,000.00
4 Pek. Pasang Saklar Double 15.000 bh 25,000.00 375,000.00
5 Pek. Stop Kontak 8.000 bh 25,000.00 200,000.00
Jumlah B.VI 12,680,000.00
VII PEKERJAAN PENGECATAN
1 Pek. Cat Dinding dan plafond 1067.021 m2 43,778.00 46,712,045.34
2 Pek. Pelitur Kayu 335.000 m2 38,293.00 12,828,155.00
Jumlah B.VII 59,540,200.34
JUMLAH LANTAI 02 751,046,280.91
JUMLAH TOTAL 751,046,280.91
DIBULATKAN 750,000,000.00