RENCANA ANGGARAN BIAYA

Proyek :

RENOVASI MASJID AL - KAUTSAR

TAHUN
2020

PERENCANA
REKAPITULASI RENCANA ANGGARAN BIAYA
RENOVASI MASJID AL-KAUTSAR

I. PEKERJAAN STRUKTUR .................................................................... Rp. 325.289.459,11


I.1 PEKERJAAN TANAH ….....................................Rp. 5.696.900,97
I.2 PEKERJAAN STRUKTUR MASJID ….....................................Rp. 254.919.465,44
I.3 PEKERJAAN STRUKTUR MENARA ….....................................Rp. 64.673.092,70

II. PEKERJAAN ARSITEKTUR .................................................................... Rp. 859.794.417,90


II.1 PEKERJAAN ARSITEKTUR MASJID ….....................................Rp. 775.047.378,31
II.2 PEKERJAAN MENARA ….....................................Rp. 84.747.039,59

III. PEKERJAAN MEP .................................................................... Rp. 191.683.670,67


III.1 PEKERJAAN PLUMBING ….....................................Rp. 46.421.819,29
III.2 PEKERJAAN EXHAUST FAN ….....................................Rp. 6.404.704,13
III.3 PEKERJAAN ELEKTRIKAL ….....................................Rp. 129.017.147,25
III.4 PEKERJAAN PENANGKAL PETIR ….....................................Rp. 9.840.000,00

JUMLAH BIAYA KONSTRUKSI . ………………… Rp. 1.376.767.547,68


DIBULATKAN . ………………… Rp. 1.376.800.000,00
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME
Rp. Rp.
1 2 3 4 5 6 (5X6)

II PEKERJAAN STRUKTUR
II.1 PEKERJAAN TANAH
1 Pek. Pembersihan lahan m2 7,58 108.000,00 818.640,00
2 Pek. Pemasangan bouwplank m1 11,90 77.500,00 922.250,00
3 Pek. Galian tanah untuk pondasi dan sloof m3 16,66 79.000,00 1.316.140,00
4 Pek. Urugan kembali bekas galian m3 13,25 58.000,00 768.500,00
5 Pek. Buangan tanah bekas galian m3 3,40 34.600,00 117.640,00
6 Pek. Pas. Urugan pasir di bawah pondasi & sloof m3 2,96 176.200,00 521.552,00
7 Pek. Pas. Lantai kerja di bawah pondasi & sloof m3 1,48 832.553,36 1.232.178,97

JUMLAH PEKERJAAN TANAH Rp. 5.696.900,97


II.2 PEKERJAAN STRUKTUR MASJID
II.2.2 PEKERJAAN STRUKTUR S/D ELV. - 1.700

1 Pek. Pas. Strauss PIle Ø300 pada P1


- Cor beton Beton Ready mix K-300 m3 0,25 1.116.535,62 279.133,90
- Besi tulangan 6 D13 Mutu baja BJTD 40 (ulir) kg 28,82 12.052,00 347.338,64
- Besi tulangan Ø8-150 Mutu baja BJTP 24 (polos) kg 11,33 11.527,00 130.600,91

2 Pek. Pas. Pondasi P1 800X800X350


- Cor beton Beton Ready mix K-300 m3 0,45 1.116.535,62 502.441,03
- Besi D13-150 Mutu baja BJTD 40 (ulir) kg 57,14 12.052,00 688.651,28
- Bekisting Bekisting batako m2 2,24 94.569,60 211.835,90

3 Pek. Pas. Kolom pedestal 150x300 pada P1


- Cor beton Beton Ready mix K-300 m3 0,07 1.116.535,62 78.157,49
- Besi tulangan 6 D12 Mutu baja BJTD 40 (ulir) kg 17,83 12.052,00 214.887,16
- Besi tulangan Ø8-100&150 Mutu baja BJTP 24 (polos) kg 6,09 11.527,00 70.199,43
- Bekisting Bekisting batako m2 1,44 94.569,60 136.180,22

4 Pek. Pas. Sloof SL1 300X400


- Cor beton Beton Ready mix K-300 m3 4,72 1.116.535,62 5.270.048,12
- Besi tulangan 10 D16 Mutu baja BJTD 40 (ulir) kg 496,43 12.052,00 5.982.974,36
- Besi tulangan 6 D16 Mutu baja BJTD 40 (ulir) kg 297,86 12.052,00 3.589.808,72
- Besi Tulangan Ø10 - 100&150 Mutu baja BJTP 24 (polos) kg 296,00 11.527,00 3.411.992,00
- Bekisting Bekisting batako m2 43,26 94.569,60 4.091.080,90

JUMLAH PEKERJAAN STRUKTUR S/D ELV.-1.700 Rp. 25.005.330,07


II.2.3 PEKERJAAN STRUKTUR S/D ELV. -2.25

1 Pek. Pas. Kolom K1 150X300


- Cor beton Beton Ready mix K-300 m3 0,18 1.116.535,62 200.976,41
- Besi tulangan 6 D12 Mutu baja BJTD 40 (ulir) kg 26,74 12.052,00 322.270,48
- Besi tulangan Ø8-100&150 Mutu baja BJTP 24 (polos) kg 7,50 11.527,00 86.452,50
- Bekisting Bekisting papan Kayu m2 3,56 224.448,00 799.034,88

2 Pek. Pas. Balok B1 200x300


- Cor beton Beton Ready mix K-300 m3 0,76 1.116.535,62 848.567,07
- Besi tulangan 6 D16 Mutu baja BJTD 40 (ulir) kg 110,94 12.052,00 1.337.048,88
- Besi tulangan 4 D16 Mutu baja BJTD 40 (ulir) kg 110,94 12.052,00 1.337.048,88
- Besi Tulangan Ø8 - 100&150 Mutu baja BJTP 24 (polos) kg 44,69 11.527,00 515.141,63
- Bekisting Bekisting papan Kayu m2 10,12 224.448,00 2.271.413,76

3 Pek. Pas. Balok B2 150x250


- Cor beton Beton Ready mix K-300 m3 0,09 1.116.535,62 100.488,21
- Besi tulangan 5 Ø12 Mutu baja BJTP 24 (polos) kg 17,57 11.527,00 202.529,39
- Besi Tulangan Ø8 - 100&150 Mutu baja BJTP 24 (polos) kg 7,45 11.527,00 85.876,15
- Bekisting Bekisting papan Kayu m2 1,64 224.448,00 368.094,72

4 Pek. Pas. Struktur Tangga


Pek. Pas. Tangga s/d bordes elv +0.034
a - Cor beton Beton Ready mix K-300 m3 2,54 1.116.535,62 2.836.000,47
- Besi Tulangan D13 - 150 Mutu baja BJTD 40 (ulir) kg 56,59 12.052,00 682.022,68
- Besi Tulangan Ø10 - 150 Mutu baja BJTP 24 (polos) kg 36,14 11.527,00 416.585,78
- Bekisting Bekisting papan Kayu m2 2,64 224.448,00 592.542,72

b Pek. Pas. Balok bordes elv +0,34 150x200


- Cor beton Beton Ready mix K-300 m3 0,10 1.116.535,62 111.653,56
- Besi Tulangan 4 D16 Mutu baja BJTD 40 (ulir) kg 38,76 12.052,00 467.135,52
- Besi Tulangan Ø8-150 Mutu baja BJTP 24 (polos) kg 6,57 11.527,00 75.732,39
- Bekisting Bekisting papan Kayu m2 1,78 224.448,00 399.517,44

c Pek. Pas. Plat bordes elv +0,34 T.150mm


- Cor beton Beton Ready mix K-300 m3 0,36 1.116.535,62 401.952,82
- Besi Tulangan Ø10-150&200 Mutu baja BJTP 24 (polos) kg 47,57 11.527,00 548.339,39
- Bekisting Bekisting papan Kayu m2 2,43 224.448,00 545.408,64

d Pek. Pas. Tangga s/d bordes elv +1.53


- Cor beton Beton Ready mix K-300 m3 7,58 1.116.535,62 8.463.340,00
- Besi Tulangan D13 - 150 Mutu baja BJTD 40 (ulir) kg 98,96 12.052,00 1.192.665,92
- Besi Tulangan Ø10 - 150 Mutu baja BJTP 24 (polos) kg 61,22 11.527,00 705.682,94
- Bekisting Bekisting papan Kayu m2 7,60 224.448,00 1.705.804,80

e Pek. Pas. Balok bordes elv +1.53 150x200


- Cor beton Beton Ready mix K-300 m3 0,10 1.116.535,62 111.653,56
- Besi Tulangan 4 D16 Mutu baja BJTD 40 (ulir) kg 38,76 12.052,00 467.135,52
- Besi Tulangan Ø8-150 Mutu baja BJTP 24 (polos) kg 6,57 11.527,00 75.732,39
- Bekisting Bekisting papan Kayu m2 1,78 224.448,00 399.517,44

f Pek. Pas. Plat bordes elv +1.53 T.150mm


- Cor beton Beton Ready mix K-300 m3 0,36 1.116.535,62 401.952,82
- Besi Tulangan Ø10-150&200 Mutu baja BJTP 24 (polos) kg 47,57 11.527,00 548.339,39
- Bekisting Bekisting papan Kayu m2 2,43 224.448,00 545.408,64
5 Pek. Pas. Plat lantai S1 T.120mm
- Cor beton Beton Ready mix K-300 m3 1,08 1.116.535,62 1.205.858,47
- Besi Ø8-150 Mutu baja BJTP 24 (polos) kg 108,99 11.527,00 1.256.327,73
- Bekisting Bekisting papan Kayu m2 9,02 224.448,00 2.024.520,96

JUMLAH PEKERJAAN STRUKTUR S/D ELV. -2.250 Rp. 34.655.774,96


II.2.4 PEKERJAAN STRUKTUR S/D ELV. +3.515
1 Pek. Pas. Kolom K1 150X300
- Cor beton Beton Ready mix K-300 m3 0,32 1.116.535,62 357.291,40
- Besi tulangan 6 D12 Mutu baja BJTD 40 (ulir) kg 43,48 12.052,00 524.020,96
- Besi tulangan Ø8-100&150 Mutu baja BJTP 24 (polos) kg 12,24 11.527,00 141.090,48
- Bekisting Bekisting papan Kayu m2 6,34 224.448,00 1.423.000,32

2 Pek. Pas. Kolom K2 400X400


- Cor beton Beton Ready mix K-300 m3 2,25 1.116.535,62 2.512.205,14
- Besi tulangan 12 D16 Mutu baja BJTD 40 (ulir) kg 321,40 12.052,00 3.873.512,80
- Besi tulangan Ø10-100&150 Mutu baja BJTP 24 (polos) kg 65,55 11.527,00 755.594,85
- Bekisting Bekisting papan Kayu m2 22,53 224.448,00 5.056.813,44

3 Pek. Pas. Balok B1 200x300


- Cor beton Beton Ready mix K-300 m3 0,55 1.116.535,62 614.094,59
- Besi tulangan 6 D16 Mutu baja BJTD 40 (ulir) kg 77,32 12.052,00 931.860,64
- Besi tulangan 4 D16 Mutu baja BJTD 40 (ulir) kg 51,54 12.052,00 621.160,08
- Besi Tulangan Ø8 - 100&150 Mutu baja BJTP 24 (polos) kg 31,81 11.527,00 366.673,87
- Bekisting Bekisting papan Kayu m2 7,31 224.448,00 1.640.714,88

4 Pek. Pas. Balok BA1 150x300


- Cor beton Beton Ready mix K-300 m3 1,20 1.116.535,62 1.339.842,74
- Besi tulangan 5 Ø12 Mutu baja BJTP 24 (polos) kg 66,39 11.527,00 765.277,53
- Besi Tulangan Ø8 - 150 Mutu baja BJTP 24 (polos) kg 60,92 11.527,00 702.224,84
- Bekisting Bekisting papan Kayu m2 19,95 224.448,00 4.477.737,60

5 Pek. Pas. Plat lantai S1 T.120mm


- Cor beton Beton Ready mix K-300 m3 1,09 1.116.535,62 1.217.023,83
- Besi Ø8-150 Mutu baja BJTP 24 (polos) kg 56,55 11.527,00 651.851,85
- Bekisting Bekisting papan Kayu m2 9,09 224.448,00 2.040.232,32

JUMLAH PEKERJAAN STRUKTUR S/D ELV. -3.515 Rp. 30.012.224,16


II.2.5 PEKERJAAN STRUKTUR S/D ELV. +4.945

1 Pek. Pas. Balok B1 200x300


- Cor beton Beton Ready mix K-300 m3 1,94 1.116.535,62 2.166.079,10
- Besi tulangan 6 D16 Mutu baja BJTD 40 (ulir) kg 239,54 12.052,00 2.886.936,08
- Besi tulangan 4 D16 Mutu baja BJTD 40 (ulir) kg 159,69 12.052,00 1.924.583,88
- Besi Tulangan Ø8 - 100&150 Mutu baja BJTP 24 (polos) kg 109,07 11.527,00 1.257.249,89
- Bekisting Bekisting papan Kayu m2 25,93 224.448,00 5.819.936,64

2 Pek. Pas. Balok B3 200x400


- Cor beton Beton Ready mix K-300 m3 1,30 1.116.535,62 1.451.496,31
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) kg 151,30 12.052,00 1.823.467,60
- Besi Tulangan Ø8 - 100&150 Mutu baja BJTP 24 (polos) kg 64,76 11.527,00 746.488,52
- Bekisting Bekisting papan Kayu m2 7,70 224.448,00 1.728.249,60

3 Pek. Pas. Balok 250x125


- Baja IWF 250.125.5.8 kg 766,27 30.045,00 23.022.582,15
- Stiffener T.10mm kg 69,55 30.045,00 2.089.629,75
- Voute baja WF 250x125 kg 51,47 30.045,00 1.546.416,15
- Plat penghubung T.10mm kg 46,36 30.045,00 1.392.886,20
- Baut HTB 8 M19mm bh 48,00 20.000,00 960.000,00
- Pengecatan besi duco m2 25,89 159.020,00 4.117.027,80

4 Pek. Pas. Struktur Tangga


a Pek. Tanah
- Galian Tanah m2 0,80 79.000,00 63.200,00
- Urugan Tanah m3 0,56 58.000,00 32.480,00
- Buangan Tanah Bekas Galian m3 0,24 34.600,00 8.304,00
- Urugan Pasir m3 0,08 176.200,00 14.096,00
- Lantai Kerja m3 0,04 832.553,36 33.302,13

b Pek. Pas. Pondasi 1000x600x200


- Cor beton Beton Ready mix K-300 m3 0,12 1.116.535,62 133.984,27
- Besi D13-150 Mutu baja BJTD 40 (ulir) kg 26,93 12.052,00 324.560,36
- Bekisting Bekisting Batako m2 0,64 94.569,60 60.524,54

c Pek. Pas. Tangga s/d bordes elv +1.65


- Cor beton Beton Ready mix K-300 m3 8,36 1.116.535,62 9.334.237,78
- Besi Tulangan D13 - 150 Mutu baja BJTD 40 (ulir) kg 202,46 12.052,00 2.440.047,92
- Bekisting Bekisting papan Kayu m2 8,33 224.448,00 1.869.651,84

d Pek. Pas. Balok bordes elv +1.65 200x150


- Cor beton Beton Ready mix K-300 m3 0,11 1.116.535,62 122.818,92
- Besi Tulangan 4 D16 Mutu baja BJTD 40 (ulir) kg 41,66 12.052,00 502.086,32
- Besi Tulangan Ø8-150 Mutu baja BJTP 24 (polos) kg 7,58 11.527,00 87.374,66
- Bekisting Bekisting papan Kayu m2 1,85 224.448,00 415.228,80

e Pek. Pas. Plat bordes elv +1.65 T.150mm


- Cor beton Beton Ready mix K-300 m3 0,11 1.116.535,62 122.818,92
- Besi Tulangan Ø10-150&200 Mutu baja BJTP 24 (polos) kg 18,26 11.527,00 210.483,02
- Bekisting Bekisting papan Kayu m2 0,75 224.448,00 168.336,00

5 Pek. Pas. Plat lantai S1 T.120mm


- Cor beton Beton Ready mix K-300 m3 3,44 1.116.535,62 3.840.882,53
- Besi Ø8-150 Mutu baja BJTP 24 (polos) kg 171,96 11.527,00 1.982.182,92
- Bekisting Bekisting papan Kayu m2 15,92 224.448,00 3.573.212,16

JUMLAH PEKERJAAN STRUKTUR S/D ELV. -4.945 Rp. 78.272.842,76


II.2.6 PEKERJAAN STRUKTUR ATAP

1 Pek. Pas. Balok RB 150x300


- Cor beton Beton Ready mix K-300 m3 1,81 1.116.535,62 2.020.929,47
- Besi tulangan 2 D13 Mutu baja BJTD 40 (ulir) kg 86,13 12.052,00 1.038.038,76
- Besi Tulangan Ø8 - 100&150 Mutu baja BJTP 24 (polos) kg 136,15 11.527,00 1.569.401,05
- Bekisting Bekisting papan Kayu m2 33,22 224.448,00 7.456.162,56

2 Pek. Rangka atap


- Besi Hollow galvanish 40/60 m1 498,30 42.504,00 21.179.743,20
- Pengecatan Cat Duco m2 149,49 159.020,00 23.771.899,80

3 Pek. Pas. Dinding Beton Atap Miring


- Cor beton Beton Ready mix K-300 m3 18,23 1.116.535,62 20.354.444,34
- Besi Ø8 - 150 Mutu baja BJTP 24 (polos) kg 239,78 11.527,00 2.763.944,06
- Bekisting Bekisting papan Kayu m2 30,38 224.448,00 6.818.730,24

JUMLAH PEKERJAAN STRUKTUR ATAP Rp. 86.973.293,48


JUMLAH PEKERJAAN STRUKTUR MASJID Rp. 254.919.465,44
II.3 PEKERJAAN STRUKTUR MENARA

1 Pek. Pas. Strauss PIle Ø300


- Cor beton Beton Ready mix K-300 m3 0,85 1.116.535,62 949.055,28
- Besi tulangan 6 D13 Mutu baja BJTD 40 (ulir) kg 89,79 12.052,00 1.082.149,08
- Besi tulangan Ø8-150 Mutu baja BJTP 24 (polos) kg 36,62 11.527,00 422.118,74

2 Pek. Pas. Pondasi Menara 1800X1800X300


- Cor beton Beton Ready mix K-300 m3 0,97 1.116.535,62 1.083.039,55
- Besi Ø13-150 Mutu baja BJTP 24 (polos) kg 114,40 11.527,00 1.318.688,80
- Bekisting Bekisting Batako m2 2,16 94.569,60 204.270,34

3 Pek. Pas. Kolom KL 150X1000


- Cor beton Beton Ready mix K-300 m3 7,17 1.116.535,62 8.005.560,39
- Besi tulangan 12 D16 Mutu baja BJTD 40 (ulir) kg 960,33 12.052,00 11.573.897,16
- Besi tulangan Ø10 - 100&150 Mutu baja BJTP 24 (polos) kg 305,56 11.527,00 3.522.190,12
- Bekisting Bekisting papan Kayu m2 109,94 224.448,00 24.675.813,12

4 Pek. Pas. Balok B 150x250


- Cor beton Beton Ready mix K-300 m3 0,81 1.116.535,62 904.393,85
- Besi tulangan 2 Ø12 Mutu baja BJTP 24 (polos) kg 256,89 12.052,00 3.096.038,28
- Besi Tulangan Ø8 - 150 Mutu baja BJTP 24 (polos) kg 46,51 11.527,00 536.120,77
- Bekisting Bekisting papan Kayu m2 14,04 224.448,00 3.151.249,92

5 Pek. Pas. Plat lantai S1 T.120mm


- Cor beton Beton Ready mix K-300 m3 1,16 1.116.535,62 1.295.181,32
- Besi Ø8-150 Mutu baja BJTP 24 (polos) kg 59,05 11.527,00 680.669,35
- Bekisting Bekisting papan Kayu m2 9,68 224.448,00 2.172.656,64

JUMLAH PEKERJAAN STRUKTUR MENARA Rp. 64.673.092,70


JUMLAH PEKERJAAN STRUKTUR Rp. 325.289.459,11
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME
Rp. Rp.
1 2 3 4 5 6 (5X6)

III PEKERJAAN ARSITEKTUR


III.1 PEKERJAAN ARSITEKTUR MASJID
III.1.1 PEKERJAAN ARSITEKTUR LANTAI BASEMESNT
III.1.1.1 PEK. BONGKARAN
1 Pek. Bongkaran Pelapis Lantai m2 20,12 25.600,00 515.072,00
2 Pek. Bongkaran Dinding m3 0,20 719.980,00 143.996,00
3 Pek. Bongkaran Pelapisan Dinding Keramik m2 69,12 25.600,00 1.769.472,00

4 Pek. Bongkaran Pintu Unit 2,00 101.000,00 202.000,00


5 Pek. Bongkaran Tangga m3 0,75 1.439.860,00 1.079.895,00

III.1.1.2 PEK. PAS. DINDING DAN PELAPISAN DINDING


1 Pek. Pas. Dinding bata Bata ringan Bata ringan T.10cm setara Hebel, agregate instan setara Drymix, MU m2 20,58 162.800,00 3.350.424,00

2 Pek. Pas. Kolom praktis 150/150


- Cor Beton Cor beton site mix K - 175 m3 0,09 1.008.191,46 90.737,23
- Besi 4 Ø 10 Mutu baja BJTP 24 ( polos ) kg 14,06 11.527,00 162.069,62
- Besi Ø 8 - 150 Mutu baja BJTP 24 ( polos ) kg 6,37 11.527,00 73.426,99
- Bekisting Bekisting papan m2 1,20 224.448,00 269.337,60

3 Pek. Pas. Balok praktis 150/200 ( di atas kusen )


- Cor Beton Cor beton site mix K - 175 m3 0,59 1.008.191,46 594.832,96
- Besi 4 Ø 10 Mutu baja BJTP 24 ( polos ) kg 7,41 11.527,00 85.415,07
- Besi Ø 8 - 150 Mutu baja BJTP 24 ( polos ) kg 21,15 11.527,00 243.796,05
- Bekisting Bekisting papan m2 3,57 224.448,00 801.279,36

4 Pek. Pas. Plesteran dan acian agregate instan, setara Drymix MU m2 28,91 121.656,25 3.517.082,19
5 Pek. Pas. Tali air m1 36,07 15.000,00 541.050,00
6 Pek. Pas. Pelapisan dinding keramik uk. 200x400, setara Roman m2 56,43 289.600,00 16.342.128,00
7 Pek. Pas. Waterproofing dinding KM/ toilet m2 18,03 150.000,00 2.704.500,00

III.1.1.3 PEK. PAS. KUSEN, DAUN PINTU DAN JENDELA


1 Pek. Pas. Pintu P2 Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 3,00 3.310.850,00 9.932.550,00
Daun Pintu WPC
(Accesories lihat analisa dan gambar kerja)

2 Pek. Pas. Pintu P3 Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 1,00 3.249.933,67 3.249.933,67
Daun Ointu Multipleks 6mm Lapis Megateak
(Accesories lihat analisa dan gambar kerja)

III.1.1.4 PEK. PAS. PLAFOND


1 Pek. Pas. Plafond Beton Ekspose agregate instan, setara Drymix MU m2 28,38 45.156,25 1.281.534,38

III.1.1.5 PEK. PAS. PELAPISAN LANTAI


1 Pek. Pas. Urugan pasir m3 0,70 176.200,00 123.340,00
2 Pek. Pas. Lantai kerja m3 0,35 832.553,36 291.393,68
3 Pek. Pas. Keramik Tile 400x400 uk. 400x400, setara Roman m2 21,39 288.237,50 6.165.400,13
4 Pek. Pas. Keramik Tile 200x200 Non Slip uk. 200x200 Non Slip , setara Roman m2 13,55 259.887,50 3.521.475,63

III.1.1.6 PEK. PAS. FINISHING DAN PENGECATAN


1 Pek. Pengecatan dinding Interior Cat dasar, Merk : Attaboy OS super primer color m2 11,27 64.675,33 728.891,01
Cat tembok interior, Merk : Attaboy O.S. Stainblocking Masonry paint Color
2 Pek. Pengecatan dinding Eksterior Cat dasar, Merk : Attaboy OS Super Primer White m2 11,50 78.453,00 902.209,50
Cat tembok eksterior, Merk : Attaboy Weatherguard
3 pek. Pengecatan Plafond Cat dasar, Merk : Attaboy OS super primer color m2 28,38 55.276,67 1.568.751,80
Cat tembok interior, Merk : Attaboy O.S. Stainblocking Masonry paint Color

III.1.1.7 PEK. PAS. PLUMBING FIXTURES


1 Pek. Pas. Closet Jongkok Setara Toto unit 1,00 921.522,40 921.522,40
2 Pek. Pas. Kran Air Setara Toto unit 5,00 141.325,00 706.625,00
3 Pek. Pas. Floor drain Setara Toto bh 2,00 292.950,00 585.900,00

JUMLAH PEKERJAAN ARSITEKTUR BASEMENT Rp. 62.466.041,24

III.1.2 PEKERJAAN ARSITEKTUR LANTAI DASAR


III.1.2.1 PEK. BONGKARAN
1 Pek. Bongkaran Pelapis Lantai m2 159,80 25.600,00 4.090.880,00
2 Pek. Bongkaran Dinding m3 10,90 719.980,00 7.847.782,00
3 Pek. Bongkaran Pintu dan Jendela unit 7,00 101.000,00 707.000,00

III.1.2.2 PEK. PAS. DINDING DAN PELAPISAN DINDING


1 Pek. Pas. Dinding bata Bata ringan Bata ringan T.10cm setara Hebel, agregate instan setara Drymix, MU m2 104,81 162.800,00 17.063.068,00
2 Pek. Pas.Panel GRC Fasad Deco Panel GRC Board T.11 m2 17,65 874.526,50 15.435.392,73

3 Pek. Pas. Kolom praktis 150/150


- Cor Beton Cor beton site mix K - 175 m3 1,56 1.008.191,46 1.572.778,67
- Besi 4 Ø 10 Mutu baja BJTP 24 ( polos ) kg 221,77 11.527,00 2.556.342,79
- Besi Ø 8 - 150 Mutu baja BJTP 24 ( polos ) kg 102,50 11.527,00 1.181.517,50
- Bekisting Bekisting papan m2 20,79 224.448,00 4.666.273,92

4 Pek. Pas. Balok praktis 150/200 ( di atas kusen )


- Cor Beton Cor beton site mix K - 175 m3 4,50 1.008.191,46 4.536.861,55
- Besi 4 Ø 10 Mutu baja BJTP 24 ( polos ) kg 54,46 11.527,00 627.760,42
- Besi Ø 8 - 150 Mutu baja BJTP 24 ( polos ) kg 145,24 11.527,00 1.674.181,48
- Bekisting Bekisting papan m2 28,39 224.448,00 6.372.078,72

5 Pek. Pas. Plesteran dan acian agregate instan, setara Drymix MU m2 188,62 121.656,25 22.946.801,88
6 Pek. Pas. Tali air m1 14,00 15.000,00 210.000,00
7 Pek. Pas. Pelapisan dinding keramik uk. 200x400, setara Roman m2 21,00 289.600,00 6.081.600,00
Pek. Pas. Waterproofing dinding KM/ toilet m2 7,00 150.000,00 1.050.000,00
III.1.2.3 PEK. PAS. KUSEN, DAUN PINTU DAN JENDELA
1 Pek. Pas. Pintu P1 Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 2,00 4.013.820,47 8.027.640,94
Daun Pintu Multipleks 6mm Lapis Megateak
(Accesories lihat analisa dan gambar kerja)

2 Pek. Pas. Pintu PS Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 2,00 7.490.916,00 14.981.832,00
Rangka Pintu Aluminium, Merk : Powder Coating Fin. Alexindo
Kaca polos T.6mm, Merk : Asahimas
(Accesories lihat analisa dan gambar kerja)

3 Pek. Pas. Pintu Jendela PJ1 Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 1,00 5.152.895,47 5.152.895,47
Daun Pintu Multipleks 6mm Lapis Megateak
Kaca polos T.6mm, Merk : Asahimas
(Accesories lihat analisa dan gambar kerja)

4 Pek. Pas. Jendela J1 Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 5,00 6.070.206,00 30.351.030,00
Rangka Pintu Aluminium, Merk : Powder Coating Fin. Alexindo
Kaca polos T.6mm, Merk : Asahimas
(Accesories lihat analisa dan gambar kerja)

5 Pek. Pas. Jendela J3 Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 1,00 1.362.462,50 1.362.462,50
Kaca polos T.6mm, Merk : Asahimas
(Accesories lihat analisa dan gambar kerja)

6 Pek. Pas. Jendela J3' Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 1,00 1.986.280,00 1.986.280,00
Kaca polos T.6mm, Merk : Asahimas
(Accesories lihat analisa dan gambar kerja)

7 Pek. Pas. Bouven Light BV1 Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 1,00 894.240,00 894.240,00
Kaca polos T.6mm, Merk : Asahimas
(Accesories lihat analisa dan gambar kerja)

8 Pek. Pas. Glass Block GB1 m2 1,60 350.088,75 560.142,00


9 Pek. Pas. Glass Block GB2 m2 0,64 350.088,75 224.056,80
10 Pek. Pas. Rooster R1 m2 0,96 255.972,75 245.733,84

III.1.2.4 PEK. PAS. PLAFOND


1 Pek. Pas. Gymsumboard 9mm Gypsumboard T.9mm, Merk : Jayaboard m2 120,90 44.460,00 5.375.214,00
2 Pek. Pas. Beton Ekspose agregate instan, setara Drymix MU m2 29,78 45.156,25 1.344.753,13

III.1.2.5 PEK. PAS. PELAPISAN LANTAI


1 Pek. Pas. Keramik Tile 200x200 Non Slip uk. 200x200 Non Slip , setara Roman m2 6,60 259.887,50 1.715.257,50
2 Pek. Pas. Granite Tile 600x600 Granite Tile , uk. 600x600, Merk : Indogress m2 160,00 493.945,50 79.031.280,00
3 Pek. Pas. Batu Coral Sikat m2 39,70 191.300,00 7.594.610,00

III.1.2.6 PEK. PAS. FINISHING DAN PENGECATAN


1 Pek. Pengecatan dinding Interior Cat dasar, Merk : Attaboy OS super primer color m2 181,07 64.675,33 11.710.762,61
Cat tembok interior, Merk : Attaboy O.S. Stainblocking Masonry paint Color
2 Pek. Pengecatan dinding Eksterior Cat dasar, Merk : Attaboy OS Super Primer White m2 234,97 78.453,00 18.434.101,41
Cat tembok eksterior, Merk : Attaboy Weatherguard
3 Pek. Pelapisan Marmer pada Kolom Marmer Tile Carrara 400x400 m2 1,78 1.424.245,50 2.535.156,99
4 Pek. Pengecatan Plafond m2 150,68 55.276,67 8.329.088,13

III.1.2.7 PEK. PAS. PLUMBING FIXTURES


1 Pek. Pas. Closet Jongkok Setara Toto unit 1,00 921.522,40 921.522,40
2 Pek. Pas. Kran Air Setara Toto unit 9,00 141.325,00 1.271.925,00
3 Pek. Pas. Floor drain Setara Toto bh 3,00 292.950,00 878.850,00

JUMLAH PEKERJAAN ARSITEKTUR LANTAI DASAR Rp. 301.549.154,36


III.1.3 PEKERJAAN ARSITEKTUR LANTAI ATAS
III.1.3.1 PEK. BONGKARAN
1 Pek. Bongkaran Dinding m3 0,94 719.980,00 676.781,20
2 Pek. Bongkaran Pelapis Dinding Fasad m2 5,93 25.600,00 151.808,00
3 Pek. Bongkaran Lantai Cor Beton m3 13,25 1.439.860,00 19.078.145,00
4 Pek. Bongkaran Pelapis Lantai m2 142,36 25.600,00 3.644.416,00

5 Pek. Bongkaran Railling Void m1 6,21 50.000,00 310.500,00


6 Pek. Bongkaran Pintu dan Jendela unit 12,00 101.000,00 1.212.000,00
7 Pek. Bongkaran Tangga m3 0,80 1.439.860,00 1.151.888,00

III.1.3.2 PEK. PAS. DINDING DAN PELAPISAN DINDING


1 Pek. Pas. Dinding bata Bata ringan Bata ringan T.10cm setara Hebel, agregate instan setara Drymix, MU m2 22,88 162.800,00 3.724.864,00
2 Pek. Pas.Panel GRC Fasad Deco Panel GRC Board T.11 m2 74,88 874.526,50 65.484.544,32

3 Pek. Pas. Kolom praktis 150/150


- Cor Beton Cor beton site mix K - 175 m3 0,17 1.008.191,46 171.392,55
- Besi 4 Ø 10 Mutu baja BJTP 24 ( polos ) kg 28,37 11.527,00 327.020,99
- Besi Ø 8 - 150 Mutu baja BJTP 24 ( polos ) kg 11,67 11.527,00 134.520,09
- Bekisting Bekisting papan m2 2,25 224.448,00 505.008,00

4 Pek. Pas. Balok praktis 150/200 ( di atas kusen )


- Cor Beton Cor beton site mix K - 175 m3 5,92 1.008.191,46 5.968.493,42
- Besi 4 Ø 10 Mutu baja BJTP 24 ( polos ) kg 49,08 11.527,00 565.745,16
- Besi Ø 8 - 150 Mutu baja BJTP 24 ( polos ) kg 188,05 11.527,00 2.167.652,35
- Bekisting Bekisting papan m2 35,49 224.448,00 7.965.659,52

5 Pek. Pas. Plesteran dan acian agregate instan, setara Drymix MU m2 37,29 121.656,25 4.536.561,56
6 Pek. Pas. Tali air m1 5,65 15.000,00 84.750,00
7 Pek. Pas. Pelapisan dinding keramik uk. 200x400, setara Roman m2 8,48 289.600,00 2.455.808,00
8 Pek. Pas. Waterproofing dinding KM/ toilet m2 2,83 150.000,00 424.500,00

III.1.3.3 PEK. PAS. KUSEN, DAUN PINTU DAN JENDELA


1 Pek. Pas. Pintu PS Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 1,00 7.490.916,00 7.490.916,00
Rangka Pintu Aluminium, Merk : Powder Coating Fin. Alexindo
Kaca polos T.6mm, Merk : Asahimas
(Accesories lihat analisa dan gambar kerja)
2 Pek. Pas. Pintu Jendela PJ1 Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 1,00 5.152.895,47 5.152.895,47
Daun Pintu Multipleks 6mm Lapis Megateak
Kaca polos T.6mm, Merk : Asahimas
(Accesories lihat analisa dan gambar kerja)

3 Pek. Pas. Jendela J1 Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 2,00 6.070.206,00 12.140.412,00
Rangka Pintu Aluminium, Merk : Powder Coating Fin. Alexindo
Kaca polos T.6mm, Merk : Asahimas
(Accesories lihat analisa dan gambar kerja)

4 Pek. Pas. Jendela J2 Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 3,00 3.133.893,75 9.401.681,25
Rangka Pintu Aluminium, Merk : Powder Coating Fin. Alexindo
Kaca polos T.6mm, Merk : Asahimas
(Accesories lihat analisa dan gambar kerja)

5 Pek. Pas. Bouven Light BV1 Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo unit 1,00 894.240,00 894.240,00
Kaca polos T.6mm, Merk : Asahimas
(Accesories lihat analisa dan gambar kerja)

III.1.3.4 PEK. PAS. PLAFOND


1 Pek. Pas. Gymsumboard 9mm Gypsumboard T.9mm, Merk : Jayaboard m2 122,52 44.460,00 5.447.239,20
2 Pek. Pas. Beton Ekspose agregate instan, setara Drymix MU m2 19,64 45.156,25 886.868,75

III.1.3.5 PEK. PAS. PELAPISAN LANTAI


1 Pek. Pas. Keramik Tile 200x200 Non slip uk. 200x200 Non Slip , setara Roman m2 2,06 259.887,50 535.368,25
2 Pek. Pas. Granite Tile 600x600 Granite Tile , uk. 600x600, Merk : Indogress m2 138,00 493.945,50 68.164.479,00

III.1.3.6 PEK. PAS. FINISHING DAN PENGECATAN


1 Pek. Pengecatan dinding Interior Cat dasar, Merk : Attaboy OS super primer color m2 188,44 64.675,33 12.187.419,81
Cat tembok interior, Merk : Attaboy O.S. Stainblocking Masonry paint Color
2 Pek. Pengecatan dinding Eksterior Cat dasar, Merk : Attaboy OS Super Primer White m2 235,77 78.453,00 18.496.863,81
Cat tembok eksterior, Merk : Attaboy Weatherguard
3 Pek. Pengecatan Plafond Cat dasar, Merk : Attaboy OS super primer color m2 142,16 55.276,67 7.858.130,93
Cat tembok interior, Merk : Attaboy O.S. Stainblocking Masonry paint Color

III.1.3.7 PEK. PAS. PLUMBING FIXTURES


1 Pek. Pas. Kran Air Setara Toto unit 3,00 141.325,00 423.975,00
2 Pek. Pas. Floor drain Setara Toto bh 1,00 292.950,00 292.950,00

III.1.3.8 LAIN-LAIN
1 Pek. Pas. Huruf MASJID T. 35 unit 1,00 3.150.000,00 3.150.000,00
2 Pek. Pas. Huruf AL-KAUTSAR T. 45 unit 1,00 6.750.000,00 6.750.000,00
3 Pek. Pas. Railling m1 11,74 387.691,73 4.551.500,91

JUMLAH PEKERJAAN ARSITEKTUR LANTAI ATAS Rp. 284.566.998,54


III.1.4 PEKERJAAN ATAP
III.1.4.1 PEK. BONGKARAN
1 Pek. Bongkaran Atap
- Penutup Atap m2 210,80 25.600,00 5.396.480,00
- Kubah Masjid unit 1,00 500.000,00 500.000,00

III.1.4.2 PEK. PAS. DINDING DAN PELAPISAN DINDING


1 Pek. Pas. Dinding bata Bata ringan Bata ringan T.10cm setara Hebel, agregate instan setara Drymix, MU m2 74,15 433.101,90 32.114.505,89
2 Pek. Pas. Plesteran dan acian agregate instan, setara Drymix MU m2 148,30 127.524,38 18.911.864,81

III.1.4.3 PEK. PAS. PENGECATAN DAN PENUTUP ATAP


1 Pek. Pengecatan dinding Eksterior Cat dasar, Merk : Attaboy OS Super Primer White m2 188,44 55.276,67 10.416.335,07
Cat tembok eksterior, Merk : Attaboy Weatherguard
2 Pek. Pas. Penutup Atap UPVC Atap Alderon T.12mm m2 221,44 252.350,00 55.880.384,00
3 Pek. Pas. Listplank m1 55,16 58.840,00 3.245.614,40

JUMLAH PEKERJAAN ATAP Rp. 126.465.184,16


JUMLAH PEKERJAAN ARSITEKTUR MASJID Rp. 775.047.378,31
III.2 PEKERJAAN MENARA
1 Pek. Pas. Dinding bata Bata ringan Bata ringan T.10cm setara Hebel, agregate instan setara Drymix, MU m2 5,76 433.101,90 2.494.666,94
2 Pek. Pas. Panel GRC Deco Panel GRC Board T.11 m2 31,99 874.526,50 27.976.102,74
3 Pek. Pas. Plesteran dan acian agregate instan, setara Drymix MU m2 11,52 127.524,38 1.469.080,80
4 Pek. Pengecatan dinding Eksterior Cat dasar, Merk : Attaboy OS Super Primer White m2 395,87 78.453,00 31.057.189,11
Cat tembok eksterior, Merk : Attaboy Weatherguard
5 Pek. Pas. Kubah Unit 1,00 21.750.000,00 21.750.000,00

JUMLAH PEKERJAAN MINIRET Rp. 84.747.039,59


JUMLAH PEKERJAAN ARSITEKTUR Rp. 859.794.417,90
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME
Rp. Rp.
1 2 3 4 5 6 (5X6)

III. PEKERJAAN MEP


III.1 PEKERJAAN PLUMBING
III.1.1 Pekerjaan Instalasi Air Bersih
1 Peralatan Utama
1 Ground Reservoir & Ruang Pompa kap. 9 M3 unit Bak GR - By Struktur
- Floating valve dia. 25 Standard SNI, Merk : Onda bh 2,00 309.400,00 618.800,00

2 Pompa Transfer Air bersih (PA.1 & PA.2)+lengkap accessories kapasitas : 50 lpm, head 40 m unit 2,00 2.327.800,00 4.655.600,00
- Panel control dan pengkabelan Standard SNI set 1,00 850.000,00 850.000,00
- Instalasi daya listrik Pompa Standard SNI ttk 1,00 150.000,00 150.000,00

3 Instalasi pemipaan di ruang pompa ke bangunan


- Pipa PVC dia. 25 mm (dari pompa sampai GWT) Standard SNI, merk : Rucika, Wavin m' 40,00 22.693,53 907.741,07

2 Instalasi pemipaan
Pemipaan air bersih menggunakan PVC kelas AW
lengkap fitting dan alat bantunya.

1 Lantai Basemen
a. Pemipaan ruang wudhu & toilet
- dia. 15 mm Standard SNI, merk : Rucika, Wavin m' 22,60 16.131,03 364.561,21
- dia. 20 mm m' 6,50 18.887,28 122.767,30
dia. 25 mm m' 5,30 22.693,53 120.275,69
b. Valve-valve
- Ball valve dia. 15 mm Standard SNI, Kelas 10 K, merk : Onda bh 4,00 90.142,86 360.571,43
- Ball valve dia. 20 mm bh 1,00 105.142,86 105.142,86
- Ball valve dia. 25 mm bh 1,00 122.142,86 122.142,86

2 Lantai 2
a. Pemipaan toilet
- dia. 15 mm Standard SNI, merk : Rucika, Wavin m' 3,70 16.131,03 59.684,80
- dia. 20 mm m' 19,80 18.887,28 373.968,08
- dia. 25 mm m' 33,00 22.693,53 748.886,38
- dia. 32 mm m' 0,50 0,00

b. Valve-valve
- Ball valve dia. 15 mm Standard SNI, Kelas 10 K, merk : Onda bh 1,00 90.142,86 90.142,86
- Ball valve dia. 20 mm bh 3,00 105.142,86 315.428,57
- Ball valve dia. 25 mm bh 2,00 122.142,86 244.285,71
Ball valve dia. 32 mm bh 1,00 145.142,86 145.142,86

3 Lantai 3
a. Pemipaan toilet
- dia. 15 mm Standard SNI, merk : Rucika, Wavin m' 0,60 16.131,03 9.678,62
- dia. 20 mm m' 6,50 18.887,28 122.767,30
dia. 40 mm m' 1,70 0,00
b. Valve-valve
- Ball valve dia. 20 mm bh 1,00 90.142,86 90.142,86
- Ball valve dia. 40 mm bh 1,00 105.142,86 105.142,86

c. Tangki Air
- Rooftank kap. 1000 liter bh 2,00 2.062.337,50 4.124.675,00
Accessories
Sensor radar unit 1,00 150.000,00 150.000,00
Floating valve dia. 25 mm bh 1,00 183.400,00 183.400,00
Ball valve dia. 32 mm bh 2,00 145.142,86 290.285,71
Header pipa dia. 65 mm m' 2,00 54.062,28 108.124,55

4 Pipa pengisian rooftank lantai atap


- pipa dia. 25 mm Standard SNI, merk : Rucika, Wavin m' 43,00 22.693,53 975.821,65
- Ball Valve dia. 25 mm termasuk fitting & alat bantunya m' 1,00 122.142,86 122.142,86

5 Pipa Riser suply air bersih


- Pipa dia. 25 mm Standard SNI, merk : Rucika, Wavin m' 3,00 22.693,53 68.080,58
- Pipa dia. 40 mm termasuk fitting & alat bantunya m' 1,50 32.898,21 49.347,32

III.1.2 Pekerjaan Air Kotor


1 Instalasi Pemipaan Standard SNI, merk : Rucika, Wavin
Pipa Air Kotor PVC kelas 10 kG/cm2 termasuk fitting & alat bantunya
1. Pemipaan lantai basemen
Pipa air kotor & air bekas
- PVC dia. 100 mm m' 71,00 114.831,03 8.153.003
- PVC dia. 65 mm m' 8,00 54.062,28 432.498
- PVC dia. 50 mm m' 19,00 39.723,21 754.741
- Clean Out ( CO ) dia. 100 mm bh 1,00 55.285,71 55.286
- Clean Out ( CO ) dia. 65 mm bh 1,00 42.285,71 42.286
- Clean Out ( CO ) dia. 50 mm bh 3,00 39.285,71 117.857

Pipa Vent
- PVC dia 32 mm m' 16,00 29.748,21 475.971

2. Pemipaan lantai dasar


Pipa air kotor & air bekas Standard SNI, merk : Rucika, Wavin
- PVC dia. 100 mm termasuk fitting & alat bantunya m' 6,00 114.831,03 688.986
- PVC dia. 65 mm m' 12,90 54.062,28 697.403
- PVC dia. 50 mm m' 13,20 39.723,21 524.346
- Clean Out ( CO ) dia. 100 mm bh 1,00 55.285,71 55.285,71
- Clean Out ( CO ) dia. 65 mm bh 1,00 42.285,71 42.285,71

Pipa Vent
- PVC dia 32 mm m' 5,00 29.748,21 148.741

3. Pemipaan lantai 3
- PVC dia. 65 mm m' 2,50 54.062,28 135.156

2 Pekerjaan Talang air hujan Standard SNI, merk : Rucika, Wavin


a. Pipa PVC dia. 80 mm termasuk fitting & alat bantunya m' 137,80 72.666,96 10.013.507,68
b. Roof drain bh 13,00 102.285,71 1.329.714,29
c. Sumur resapan bh 5,00 1.200.000,00 6.000.000,00

PEKERJAAN PLUMBING Rp. 46.421.819,29


III.2 PEKERJAAN EXHAUST FAN
a. Unit Fan
Extract fan kapasitas 75 cfm Unit 5,00 698.780,00 3.493.900,00

b. Saluran udara
- pipa dia. 100 mm m' 7,50 114.831,03 861.232,70
- grille ukuran 6"x6" bh 5,00 163.914,29 819.571,43

3. Instalasi Listrik
Titik instalasi daya listrik Exhaust Fan titik 5,00 246.000,00 1.230.000,00

PEKERJAAN EXHAUST FAN Rp. 6.404.704,13

III.3 PEKERJAAN ELEKTRIKAL


III.3.1 BIAYA PENYAMBUNGAN LISTRIK
1. Biaya Penyambungan listrik Daya tersambung, 10600 VA ls 1,00 5.800.000,00 5.800.000,00
2. Biaya SLO ls 1,00 350.000,00 350.000,00

III.3.2 PEKERJAAN PANEL DISTRIBUSI


Pengadaan dan Pemasangan Panel Distribusi Tegangan Rendah Panel Maker ( Sier Panel )
1. Panel Listrik Lantai 1 Kompnen ( Ex, Schneider, ABB )
- Panel PP/LP Masjid unit 1,00 12.000.000,00 12.000.000,00

III.3.3 PEKERJAAN KABEL FEEDER termasuk skoen, klem dan aksesories lainnya
Pengadaan dan Pemasangan Kabel Feeder ( Ex. Suppreme, Kabelmetal, Kabelindo )

1 Kabel Feeder di lantai 1


- Kabel dari meter listrik ke PP/LP Masjid , NYY 4 x 10 mm2 + BCC 50 mm Pada pada kabel tray m' 20,00 150.088,50 3.001.770,00

III.3.4 PEKERJAAN RAK KABEL termasuk Tee, Cros, Elbow, Reducer) dan aksesories lainnya
Pengadaan dan Pemasangan Rak Kabel lengkap Sambungan dan dudukan ( Ex. Tri Abadi, Tresstar )

1. Rak kabel di lantai 1


- Kabel Tray ( 15 cm ) 150 x 100 m' 23,00 289.382,75 6.655.803,25

III.3.5 PEKERJAAN PENERANGAN DAN STOP KONTAK DAYA


Pengadaan dan pemasangan Armature lampu, saklar, stop kontak termasuk dudukan dan material bantu lainnya.
1. Penerangan Lantai Basemen ( Ex. Artolite, setara )
- Fixtures lampu
- TL LED 2 x 16 W Type TKI/Inbow Terpasang Inbow bh 2,00 773.830,00 1.547.660,00
- Downlight LED 12 w type Reccesed di Plafond bh 18,00 297.205,00 5.349.690,00
- Downlight LED 15 w type Reccesed di Plafond bh 21,00 314.015,00 6.594.315,00
- Baret LED 17w Terpasang Outbow (Out) di Plafond bh 4,00 243.905,00 975.620,00
- Saklar ( Ex. Clipsal/ Schneider )
- Saklar tunggal Terpasang Inbow lengkap alat bantunya bh 9,00 26.564,00 239.076,00
- Saklar Ganda bh 4,00 30.254,00 121.016,00
- Stop kontak ( Ex. Clipsal/ Schneider )
- Stop kontak 10 A / 1 Phase Terpasang Inbow lengkap di dinding bh 15,00 27.114,00 406.710,00

- Titik instalasi
- Instalasi penerangan, NYM 3 x 2,5 mm2 dalam konduit PVC Dalam konduit PVC Hight Impact titik 45,00 229.775,00 10.339.875,00
- Instalasi stop kontak daya, NYM 3 x 2,5 mm2 dalam konduit PVC Kabel Power ( Ex. Suppreme ) titik 15,00 324.650,00 4.869.750,00

2. Penerangan Lantai 2 ( Ex. Artolite, setara )


- Fixtures lampu
- TL LED 2 x 16 W Type TKI/Inbow Terpasang Inbow bh 7,00 773.830,00 5.416.810,00
- Downlight LED 12 w type Reccesed di Plafond bh 15,00 297.205,00 4.458.075,00
- Downlight LED 15 w type Reccesed di Plafond bh 37,00 314.015,00 11.618.555,00
- Downlight LED 32 w type Reccesed di Plafond bh 1,00 435.580,00 435.580,00
- Baret LED 17w Terpasang Outbow (Out) di Plafond bh 2,00 243.905,00 487.810,00
- Saklar ( Ex. Clipsal/ Schneider )
- Saklar tunggal Terpasang Inbow lengkap alat bantunya bh 10,00 26.564,00 265.640,00
- Saklar Ganda bh 6,00 30.254,00 181.524,00
- Stop kontak ( Ex. Clipsal/ Schneider )
- Stop kontak 10 A / 1 Phase Terpasang Inbow lengkap di dinding bh 23,00 27.114,00 623.622,00

- Titik instalasi
- Instalasi penerangan, NYM 3 x 2,5 mm2 da;am konduit PVC Dalam konduit PVC Hight Impact titik 62,00 229.775,00 14.246.050,00
- Instalasi stop kontak daya, NYM 3 x 2,5 mm2 dalam konduit PVC Kabel Power ( Ex. Suppreme ) titik 23,00 324.650,00 7.466.950,00

2. Penerangan Lantai 3 ( Ex. Artolite, setara )


- Fixtures lampu
- TL LED 2 x 16 W Type TKI/Inbow Terpasang Inbow bh 3,00 773.830,00 2.321.490,00
- Downlight LED 12 w type Reccesed di Plafond bh 11,00 297.205,00 3.269.255,00
- Downlight LED 15 w type Reccesed di Plafond bh 17,00 314.015,00 5.338.255,00
- Baret LED 17w Terpasang Outbow (Out) di Plafond bh 1,00 243.905,00 243.905,00
- Lampu hias gantung 150 W bh 1,00 3.500.000,00 3.500.000,00

- Saklar ( Ex. Clipsal/ Schneider )


- Saklar tunggal Terpasang Inbow lengkap alat bantunya bh 2,00 26.564,00 53.128,00
Saklar Ganda bh 3,00 30.254,00 90.762,00
- Stop kontak ( Ex. Clipsal/ Schneider )
Stop kontak 10 A / 1 Phase Terpasang Inbow lengkap di dinding bh 9,00 27.114,00 244.026,00

- Titik instalasi
- Instalasi penerangan, NYM 3 x 2,5 mm2 da;am konduit PVC Dalam konduit PVC Hight Impact titik 33,00 229.775,00 7.582.575,00
- Instalasi stop kontak daya, NYM 3 x 2,5 mm2 dalam konduit PVC Kabel Power ( Ex. Suppreme ) titik 9,00 324.650,00 2.921.850,00

PEKERJAAN ELEKTRIKAL Rp. 129.017.147,25

III.4 PEKERJAAN PENANGKAL PETIR


1. Batang Penangkal Petir ( Splitzent ) Konvensional Bh 8,00 150.000,00 1.200.000,00
2. Kabel BC 50 mm lengkap dudukan Kawat hantaran m' 55,00 48.000,00 2.640.000,00
3. Bak kontrol & Elektroda pentanahan ttk 4,00 1.500.000,00 6.000.000,00

PEKERJAAN PENANGKAL PETIR Rp. 9.840.000,00


ANALISA HARGA SATUAN PEKERJAAN STRUKTUR DAN ARSITEKTUR

A.2.2.1.13. Pembongkaran 1 m3 Beton Bertulang


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 13,3330 100.000,00 1.333.300,00
Mandor L.04 OH 0,6660 160.000,00 106.560,00
JUMLAH TENAGA KERJA 1.439.860,00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 1.439.860,00


E. Overhead & Profit 15% -
F. Harga Satuan Pekerjaan (D+E) 1.439.860,00

Pek. Bongkaran 1 m3 dinding Sumber : Lampiran Permen PU Tahun 2016


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6,6670 100.000,00 666.700,00
Mandor L.04 OH 0,3330 160.000,00 53.280,00
JUMLAH TENAGA KERJA 719.980,00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 719.980,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 719.980,00

Pek. Bongkaran Pelapisan Lantai Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,1600 100.000,00 16.000,00
Mandor L.04 OH 0,0600 160.000,00 9.600,00
JUMLAH TENAGA KERJA 25.600,00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 25.600,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 25.600,00
Pek. Bongkaran Pelapisan Dinding Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,1600 100.000,00 16.000,00
Mandor L.04 OH 0,0600 160.000,00 9.600,00
JUMLAH TENAGA KERJA 25.600,00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 25.600,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 25.600,00

Pek. Bongkaran Penutup Atap Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,1600 100.000,00 16.000,00
Mandor L.04 OH 0,0600 160.000,00 9.600,00
JUMLAH TENAGA KERJA 25.600,00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 25.600,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 25.600,00

Pek. Bongkaran kusen,pintu dan jendela Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,4500 100.000,00 45.000,00
Mandor L.04 OH 0,3500 160.000,00 56.000,00
JUMLAH TENAGA KERJA 101.000,00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 101.000,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 101.000,00
Pek. Bongkaran Plafond Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,1500 100.000,00 15.000,00
Mandor L.04 OH 0,0500 160.000,00 8.000,00
JUMLAH TENAGA KERJA 23.000,00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 23.000,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 23.000,00

A.2.2.1.9. Pembersihan 1 m2 Lapangan dan Perataan Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1,0000 100.000,00 100.000,00
Mandor L.04 OH 0,0500 160.000,00 8.000,00
JUMLAH TENAGA KERJA 108.000,00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 108.000,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 108.000,00

A.2.2.1.4. Pengukuran dan pemasangan 1 m1 Bouwplank Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,1000 100.000,00 10.000,00
Tukang Kayu L.02 OH 0,1000 120.000,00 12.000,00
Kepala Tukang L.03 OH 0,0100 140.000,00 1.400,00
Mandor L.04 OH 0,0050 160.000,00 800,00
JUMLAH TENAGA KERJA 24.200,00
B. BAHAN
Balok Kayu Kelas III m3 0,0120 3.000.000,00 36.000,00
Paku Biasa 2" - 3" kg 0,0200 25.000,00 500,00
Kayu Kelas III m3 0,0070 2.400.000,00 16.800,00
JUMLAH HARGA BAHAN 53.300,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 77.500,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 77.500,00
A.2.3.1.1. Penggalian 1 m3 Tanah Biasa Sedalam 1m Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,7500 100.000,00 75.000,00
Mandor L.04 OH 0,0250 160.000,00 4.000,00
JUMLAH TENAGA KERJA 79.000,00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 79.000,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 79.000,00

A.2.3.1.8. Pembuangan 1 m3 Tanah Sejauh 30 meter Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,3300 100.000,00 33.000,00
Mandor L.04 OH 0,0100 160.000,00 1.600,00
JUMLAH TENAGA KERJA 34.600,00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 34.600,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 34.600,00

A.2.3.1.9. Pengurugan Kembali 1 m3 Galian Tanah Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,5000 100.000,00 50.000,00
Mandor L.04 OH 0,0500 160.000,00 8.000,00
JUMLAH TENAGA KERJA 58.000,00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 58.000,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 58.000,00
1 m3 Pek. Urugan tanah kembali dan pemadatan Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,500 100.000,00 50.000,00
Mandor L.04 OH 0,025 160.000,00 4.000,00
JUMLAH TENAGA KERJA 54.000,00
B. BAHAN
Bahan Timbunan m3 1,143 60.000,00 68.598,00
JUMLAH HARGA BAHAN 68.598,00
C. PERALATAN
Alat Bantu Ls 0,125 54.000,00 6.750,00
JUMLAH HARGA PERALATAN 6.750,00

D. Jumlah (A+B+C) 129.348,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 129.348,00

A.2.3.1.11. Pengurugan 1 m3 Dengan Pasir Urug Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,3000 100.000,00 30.000,00
Mandor L.04 OH 0,0100 160.000,00 1.600,00
JUMLAH TENAGA KERJA 31.600,00
B. BAHAN
Pasir Urug L.04 m3 1,2000 120.500,00 144.600,00
JUMLAH HARGA BAHAN 144.600,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 176.200,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 176.200,00

A.4.1.1.4. Membuat 1 m3 Lantai Kerja Beton Mutu f'c = 7,4 Mpa Slump (3-6)cm, w/c = 0,87 Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1,2000 100.000,00 120.000,00
Tukang Batu L.02 OH 0,2000 120.000,00 24.000,00
Kepala Tukang L.03 OH 0,0200 140.000,00 2.800,00
Mandor L.04 OH 0,0600 160.000,00 9.600,00
JUMLAH TENAGA KERJA 156.400,00
B. BAHAN
Semen Portland kg 230,0000 1.400,00 322.000,00
Pasir Beton kg 893,0000 151,72 135.489,66
Kerikil (Maks 30mm) kg 1.027,0000 183,70 188.663,70
Air ltr 200,0000 150,00 30.000,00
JUMLAH HARGA BAHAN 676.153,36
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 832.553,36


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 832.553,36
A.4.1.1.5. Membuat 1 m3 Beton Mutu f'c = 14,5 Mpa (K-175) Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1,6500 100.000,00 165.000,00
Tukang Batu L.02 OH 0,2750 120.000,00 33.000,00
Kepala Tukang L.03 OH 0,0280 140.000,00 3.920,00
Mandor L.04 OH 0,0830 160.000,00 13.280,00
JUMLAH TENAGA KERJA 215.200,00
B. BAHAN
Semen Portland kg 326,0000 1.400,00 456.400,00
Pasir Beton kg 760,0000 151,72 115.310,34
Kerikil (Maks 30mm) kg 1.029,0000 183,70 189.031,11
Air ltr 215,0000 150,00 32.250,00
JUMLAH HARGA BAHAN 792.991,46
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 1.008.191,46


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 1.008.191,46

A.4.1.1.10. Membuat 1 m3 Beton Mutu f'c = 26,40 Mpa (K-300) Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1,6500 100.000,00 165.000,00
Tukang Batu L.02 OH 0,2750 120.000,00 33.000,00
Kepala Tukang L.03 OH 0,0280 140.000,00 3.920,00
Mandor L.04 OH 0,0830 160.000,00 13.280,00
JUMLAH TENAGA KERJA 215.200,00
B. BAHAN
Semen Portland kg 413,0000 1.400,00 578.200,00
Pasir Beton kg 681,0000 151,72 103.324,14
Kerikil (Maks 30mm) kg 1.021,0000 183,70 187.561,48
Air ltr 215,0000 150,00 32.250,00
JUMLAH HARGA BAHAN 901.335,62
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 1.116.535,62


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 1.116.535,62
A.4.1.1.17. Pembesian 1 kg dengan Besi Polos Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,0070 100.000,00 700,00
Tukang besi L.02 OH 0,0070 120.000,00 840,00
Kepala Tukang L.03 OH 0,0007 140.000,00 98,00
Mandor L.04 OH 0,0004 160.000,00 64,00
JUMLAH TENAGA KERJA 1.702,00
B. BAHAN
Besi Beton Polos kg 1,0500 9.000,00 9.450,00
Kawat Beton kg 0,0150 25.000,00 375,00
JUMLAH HARGA BAHAN 9.825,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 11.527,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 11.527,00

A.4.1.1.17. Pembesian 1 kg dengan Besi Ulir Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,0070 100.000,00 700,00
Tukang besi L.02 OH 0,0070 120.000,00 840,00
Kepala Tukang L.03 OH 0,0007 140.000,00 98,00
Mandor L.04 OH 0,0004 160.000,00 64,00
JUMLAH TENAGA KERJA 1.702,00
B. BAHAN
Besi Beton Ulir kg 1,0500 9.500,00 9.975,00
Kawat Beton kg 0,0150 25.000,00 375,00
JUMLAH HARGA BAHAN 10.350,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 12.052,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 12.052,00

A.4.1.1.19. Pemasangan 1 kg Jaring Kawat Baja (Wiremesh) Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,0025 100.000,00 250,00
Tukang besi L.02 OH 0,0025 120.000,00 300,00
Kepala Tukang L.03 OH 0,0025 140.000,00 350,00
Mandor L.04 OH 0,0001 160.000,00 16,00
JUMLAH TENAGA KERJA 916,00
B. BAHAN
Jaring Kawat Baja Dilas kg 1,0200 9.500,00 9.690,00
Kawat Beton kg 0,0050 25.000,00 125,00
JUMLAH HARGA BAHAN 9.815,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 10.731,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 10.731,00
A.4.1.1.23. Pemasangan 1 m2 Bekisting Papan kayu
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,66 100.000,00 66.000,00
Tukang kayu L.02 OH 0,33 120.000,00 39.600,00
Kepala Tukang L.03 OH 0,03 140.000,00 4.620,00
Mandor L.04 OH 0,03 160.000,00 5.280,00
JUMLAH TENAGA KERJA 115.500,00
B. BAHAN
Kayu Papan Albasiah m3 0,04 1.251.200,00 50.048,00
Paku 5-10cm kg 0,40 16.000,00 6.400,00
Minyak Bekisting ltr 0,20 12.000,00 2.400,00
Balok Kayu Albasiah m3 0,01 900.000,00 8.100,00
Plywood tebal 9mm lbr 0,35 120.000,00 42.000,00
JUMLAH HARGA BAHAN 108.948,00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 224.448,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 224.448,00

Pemasangan 1 m2 Bekisting Batako


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,32 100.000,00 32.180,00
Tukang kayu L.02 OH 0,18 120.000,00 21.660,00
Kepala Tukang L.03 OH 0,02 140.000,00 2.212,00
Mandor L.04 OH 0,01 160.000,00 1.328,00
JUMLAH TENAGA KERJA 57.380,00
B. BAHAN
Batako bh 13,00 2.450,00 31.850,00
Semen PC 50kg zak 0,04 70.000,00 2.903,60
Pasir pasang m3 0,01 210.000,00 2.436,00
JUMLAH HARGA BAHAN 37.189,60
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 94.569,60


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 94.569,60
Pemasangan 1 m2 1 Dinding Bata Ringan Tebal 10cm, Merk : Hebel, Liebel Dengan Mortar Siap Pakai Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,3350 100.000,00 33.500,00
Tukang Batu L.02 OH 0,2600 120.000,00 31.200,00
Kepala Tukang L.03 OH 0,0260 140.000,00 3.640,00
Mandor L.04 OH 0,0030 160.000,00 480,00
JUMLAH TENAGA KERJA 68.820,00
B. BAHAN
Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m3 0,1100 750.000,00 82.500,00
Drymix Thinbed M-101 (40kg) zak 0,1000 96.800,00 9.680,00
Angkur dia. 8mm kg 0,20 9.000,00 1.800,00
JUMLAH HARGA BAHAN 93.980,00

C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 162.800,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 162.800,00

Pemasangan 1 m2 Partisi GRC T.12mm+Rangka Besi Hollow Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,1500 100.000,00 15.000,00
Tukang Batu L.02 OH 0,2000 120.000,00 24.000,00
Kepala Tukang L.03 OH 0,0400 140.000,00 5.600,00
Mandor L.04 OH 0,0100 160.000,00 1.600,00
JUMLAH TENAGA KERJA 46.200,00
B. BAHAN
Besi Hollow Galvanis 40x80 m1 1,0500 42.160,00 44.268,00
Cat Duco m2 1,0500 159.020,00 166.971,00
Deco Panel GRC Board T.11 m2 1,0500 475.000,00 498.750,00
Cat Tembok m2 1,3889 78.453,00 108.962,50
Sekrup kg 0,3750 25.000,00 9.375,00
JUMLAH HARGA BAHAN 828.326,50

C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 874.526,50


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 874.526,50
A.4.4.2.5. Pemasangan 1 m2 plesteran tebal 15mm 1SP:5PP Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,3000 100.000,00 30.000,00
Tukang Batu L.02 OH 0,1500 120.000,00 18.000,00
Kepala Tukang L.03 OH 0,0150 140.000,00 2.100,00
Mandor L.04 OH 0,0150 160.000,00 2.400,00
JUMLAH TENAGA KERJA 52.500,00
B. BAHAN
Drymix Plester 16 (50kg) kg 10,0000 2.400,00 24.000,00
JUMLAH HARGA BAHAN 24.000,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 76.500,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 76.500,00

A.4.4.2.27. Pemasangan 1 m2 acian Sumber : Lampiran Permen PU Tahun 2016


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,2000 100.000,00 20.000,00
Tukang Batu L.02 OH 0,1000 120.000,00 12.000,00
Kepala Tukang L.03 OH 0,0100 140.000,00 1.400,00
Mandor L.04 OH 0,0100 160.000,00 1.600,00
JUMLAH TENAGA KERJA 35.000,00
B. BAHAN
Drymix Acian (40kg) kg 3,2500 3.125,00 10.156,25
JUMLAH HARGA BAHAN 10.156,25
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 45.156,25


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 45.156,25

Pemasangan 1 m2 Langit - langit Kalsium silikat mm, tebal 9mm Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,1000 100.000,00 10.000,00
Tukang Kayu L.02 OH 0,0500 120.000,00 6.000,00
Kepala Tukang L.03 OH 0,0050 140.000,00 700,00
Mandor L.04 OH 0,0050 160.000,00 800,00
JUMLAH TENAGA KERJA 17.500,00
B. BAHAN
Kalsium silikat plafond tipe kalsi ling 6 setara Kalsiboard lbr 0,3640 90.108,00 32.799,31
Sekrup kg 0,1100 25.000,00 2.750,00
Compound kg 0,5500 1.000,00 550,00
JUMLAH HARGA BAHAN 36.099,31
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 53.599,31


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 53.599,31
A.4.5.1.7. Pemasangan 1 m2 Langit - langit gypsum board ukuran (120x240x9) mm, tebal 9mm Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,1000 100.000,00 10.000,00
Tukang Kayu L.02 OH 0,0500 120.000,00 6.000,00
Kepala Tukang L.03 OH 0,0050 140.000,00 700,00
Mandor L.04 OH 0,0050 160.000,00 800,00
JUMLAH TENAGA KERJA 17.500,00
B. BAHAN
Gypsumboard T.9mm, Merk : Jayaboard lbr 0,3640 65.000,00 23.660,00
Sekrup kg 0,1100 25.000,00 2.750,00
Compound kg 0,5500 1.000,00 550,00
JUMLAH HARGA BAHAN 26.960,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 44.460,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 44.460,00

Pemasangan 1 m2 Dinding keramik ukuran 20cm x 40cm Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,9000 100.000,00 90.000,00
Tukang Batu L.02 OH 0,4500 120.000,00 54.000,00
Kepala Tukang L.03 OH 0,0450 140.000,00 6.300,00
Mandor L.04 OH 0,0450 160.000,00 7.200,00
JUMLAH TENAGA KERJA 157.500,00
B. BAHAN
Keramik, uk. 200x400, Merk : Roman m2 1,0500 102.000,00 107.100,00
Drymix TA water repellent (40kg) zak 0,1250 170.000,00 21.250,00
Semen Warna kg 0,5000 7.500,00 3.750,00
JUMLAH HARGA BAHAN 132.100,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 289.600,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 289.600,00

Pemasangan 1 m2 Keramik uk. 200x200, setara Roman Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,7000 100.000,00 70.000,00
Tukang Batu L.02 OH 0,3500 120.000,00 42.000,00
Kepala Tukang L.03 OH 0,0350 140.000,00 4.900,00
Mandor L.04 OH 0,0350 160.000,00 5.600,00
JUMLAH TENAGA KERJA 122.500,00
B. BAHAN
Keramik, uk. 200x200, Merk : Roman m2 1,0500 98.000,00 102.900,00
Drymix TA water repellent (40kg) zak 0,2000 170.000,00 34.000,00
Semen Warna kg 0,0650 7.500,00 487,50
JUMLAH HARGA BAHAN 137.387,50
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 259.887,50


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 259.887,50
Pemasangan 1 m2 Keramik uk. 400x400, setara Roman Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,7000 100.000,00 70.000,00
Tukang Batu L.02 OH 0,3500 120.000,00 42.000,00
Kepala Tukang L.03 OH 0,0350 140.000,00 4.900,00
Mandor L.04 OH 0,0350 160.000,00 5.600,00
JUMLAH TENAGA KERJA 122.500,00
B. BAHAN
Keramik, uk. 400x400, Merk : Roman m2 1,0500 125.000,00 131.250,00
Drymix TA water repellent (40kg) zak 0,2000 170.000,00 34.000,00
Semen Warna kg 0,0650 7.500,00 487,50
JUMLAH HARGA BAHAN 165.737,50
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 288.237,50


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 288.237,50

Pemasangan 1 m2 Keramik uk. 600x600, setara Indogress Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,1875 100.000,00 18.750,00
Tukang Batu L.02 OH 0,3750 120.000,00 45.000,00
Kepala Tukang L.03 OH 0,0750 140.000,00 10.500,00
Mandor L.04 OH 0,0188 160.000,00 3.008,00
JUMLAH TENAGA KERJA 77.258,00
B. BAHAN
Granite Tile , uk. 600x600, Merk : Indogress m2 1,0500 364.000,00 382.200,00
Drymix TA water repellent (40kg) zak 0,2000 170.000,00 34.000,00
Semen Warna kg 0,0650 7.500,00 487,50
JUMLAH HARGA BAHAN 416.687,50
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 493.945,50


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 493.945,50
Pemasangan 1 m2 Marmer 400x400, setara Carrara Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,1875 100.000,00 18.750,00
Tukang Batu L.02 OH 0,3750 120.000,00 45.000,00
Kepala Tukang L.03 OH 0,0750 140.000,00 10.500,00
Mandor L.04 OH 0,0188 160.000,00 3.008,00
JUMLAH TENAGA KERJA 77.258,00
B. BAHAN
Marmer Carrara 400x400 m2 1,0500 1.250.000,00 1.312.500,00
Drymix TA water repellent (40kg) zak 0,2000 170.000,00 34.000,00
Semen Warna kg 0,0650 7.500,00 487,50
JUMLAH HARGA BAHAN 1.346.987,50
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 1.424.245,50


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 1.424.245,50

Pemasangan 1 m2 Coral sikat Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,7000 100.000,00 70.000,00
Tukang Batu L.02 OH 0,3500 120.000,00 42.000,00
Kepala Tukang L.03 OH 0,0350 140.000,00 4.900,00
Mandor L.04 OH 0,0350 160.000,00 5.600,00
JUMLAH TENAGA KERJA 122.500,00
B. BAHAN
Koral tabur Kg 15,0000 3.000,00 45.000,00
Semen Portland kg 11,7500 1.400,00 16.450,00
Pasir Pasang m3 0,0350 210.000,00 7.350,00
JUMLAH HARGA BAHAN 68.800,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 191.300,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 191.300,00
A.4.7.1.10. Pengecatan 1 m2 tembok baru (1 lapis cat dasar, 2 lapis cat penutup) interior
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
pekerja L.01 OH 0,0200 100.000,00 2.000,00
tukang cat L.02 OH 0,0630 120.000,00 7.560,00
kepala tukang L.03 OH 0,0063 140.000,00 882,00
Mandor L.04 OH 0,0030 160.000,00 480,00
JUMLAH TENAGA KERJA 10.922,00
B. BAHAN
Thinner OS 2000 ltr 0,1000 30.000,00 3.000,00
Cat dasar, Merk : Attaboy OS super primer color pail 0,0083 830.000,00 6.916,67
Cat tembok interior, Merk : Attaboy O.S. Stainblocking Masonry paint Color pail 0,0125 1.300.000,00 16.250,00
Rol cat bh 0,0100 21.000,00 210,00
Steger werk lot 1,0000 26.376,67 26.376,67
Ampelas tembok lbr 0,2500 4.000,00 1.000,00
JUMLAH HARGA BAHAN 53.753,33
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 64.675,33


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 64.675,33

A.4.7.1.5. Pengecatan 1 m2 bidang plafond baru ( 3 lapis cat penutup) Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
pekerja L.01 OH 0,1000 100.000,00 10.000,00
tukang cat L.02 OH 0,1500 120.000,00 18.000,00
kepala tukang L.03 OH 0,0150 140.000,00 2.100,00
Mandor L.04 OH 0,0050 160.000,00 800,00
JUMLAH TENAGA KERJA 30.900,00
B. BAHAN
Cat dasar, Merk : Attaboy OS super primer color pail 0,0083 830.000,00 6.916,67
Cat tembok interior, Merk : Attaboy O.S. Stainblocking Masonry paint Color pail 0,0125 1.300.000,00 16.250,00
Rol cat bh 0,0100 21.000,00 210,00
Ampelas tembok lbr 0,2500 4.000,00 1.000,00
JUMLAH HARGA BAHAN 24.376,67
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 55.276,67


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 55.276,67
A.4.7.1.10. Pengecatan 1 m2 tembok baru (1 lapis cat dasar, 2 lapis cat penutup) eksterior
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
pekerja L.01 OH 0,0280 100.000,00 2.800,00
tukang cat L.02 OH 0,0420 120.000,00 5.040,00
kepala tukang L.03 OH 0,0042 140.000,00 588,00
Mandor L.04 OH 0,0030 160.000,00 480,00
JUMLAH TENAGA KERJA 8.908,00
B. BAHAN
Thinner OS 2000 ltr 0,1000 30.000,00 3.000,00
Cat dasar, Merk : Attaboy OS Super Primer White pail 0,0083 840.000,00 7.000,00
Cat tembok eksterior, Merk : Attaboy Weatherguard pail 0,0125 1.925.000,00 24.062,50
Rol cat bh 0,0100 21.000,00 210,00
Steger werk lot 1,0000 34.272,50 34.272,50
Ampelas tembok lbr 0,2500 4.000,00 1.000,00
JUMLAH HARGA BAHAN 69.545,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 78.453,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 78.453,00

1 m2 Pengecatan Besi cat Duco Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,1300 100.000,00 13.000,00
Tukang cat L.02 OH 0,2000 120.000,00 24.000,00
Kepala Tukang L.03 OH 0,0200 140.000,00 2.800,00
Mandor L.04 OH 0,0100 160.000,00 1.600,00
JUMLAH TENAGA KERJA 41.400,00
B. BAHAN
Cat duco polyurethane clear matt MV-3, Merk : Petalac 2K ltr 0,1670 310.000,00 51.770,00
Cat epoxy undercoat, Merk : Petalac ltr 0,2000 196.500,00 39.300,00
Cat polyster putty, Merk : Petalac ltr 0,1000 175.000,00 17.500,00
Thinner P.U. ltr 0,1000 31.000,00 3.100,00
Thinner slow dry ltr 0,1000 38.500,00 3.850,00
Ampelas besi lbr 0,4000 4.000,00 1.600,00
Kwas 3" bh 0,0500 10.000,00 500,00
JUMLAH HARGA BAHAN 117.620,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 159.020,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 159.020,00
1 kg Pekerjaan baja Profil Sumber : Lampiran Permen PU Tahun 2016
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,060 100.000,00 6.000,00
Tukang besi profil L.02 OH 0,060 120.000,00 7.200,00
Kepala Tukang L.03 OH 0,006 140.000,00 840,00
Mandor L.04 OH 0,003 160.000,00 480,00
JUMLAH TENAGA KERJA 14.520,00
B. BAHAN
Baja Profil, Merk : DN kg 1,150 13.500,00 15.525,00
JUMLAH HARGA BAHAN 15.525,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 30.045,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 30.045,00

1 m2 Pengecatan kayu Polyurethane acrylic Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,2600 100.000,00 26.000,00
Tukang cat L.02 OH 0,4000 120.000,00 48.000,00
Kepala Tukang L.03 OH 0,0400 140.000,00 5.600,00
Mandor L.04 OH 0,0200 160.000,00 3.200,00
JUMLAH TENAGA KERJA 82.800,00
B. BAHAN
(Untuk kayu solid dengan memakai dempul dan anti getah)
Wood filler + wood stain kg 0,2000 44.000,00 8.800,00
Meiji gum sealer kg 0,1000 42.000,00 4.200,00
Cat Petalac-2K Super Sanding sealer ltr 0,2500 70.400,00 17.600,00
Thinner Super Sanding Sealer ltr 0,1000 30.800,00 3.080,00
Cat Petalac-2K Clear Matt MV-3 ltr 0,2500 115.500,00 28.875,00
Thinner Slow Dry ltr 0,1000 38.500,00 3.850,00
Ampelas kayu lbr 0,1000 4.000,00 400,00
JUMLAH HARGA BAHAN 66.805,00
C. PERALATAN
Alat Bantu ls 0,0500 149.605,00 7.480,25
JUMLAH HARGA PERALATAN 7.480,25

D. Jumlah (A+B+C) 157.085,25


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 157.085,25
1 m2 Waterproofing Formdex Uniflex Cementitious Membrance Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Upah pasang ls 1,0000 55.000,00 55.000,00
JUMLAH TENAGA KERJA 55.000,00
B. BAHAN
Waterproofing Formdex Uniflex Cementitious Membrance, m2 1,0000 95.000,00 95.000,00
Merk : Hitchins, Penetron, Sika
- Coating membrance (3x)
JUMLAH HARGA BAHAN 95.000,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 150.000,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 150.000,00

1 unit ClosetJongkok Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3,3000 100.000,00 330.000,00
Tukang L.02 OH 1,1000 120.000,00 132.000,00
Kepala Tukang L.03 OH 0,0100 140.000,00 1.400,00
Mandor L.04 OH 0,1600 160.000,00 25.600,00
JUMLAH TENAGA KERJA 489.000,00
B. BAHAN
Closet Jongkok, Merk : Toto unit 1,0100 404.000,00 408.040,00
JUMLAH HARGA BAHAN 408.040,00
C. PERALATAN
Material & alat Bantu ls 0,0600 408.040,00 24.482,40
JUMLAH HARGA PERALATAN 24.482,40

D. Jumlah (A+B+C) 921.522,40


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 921.522,40

1 unit Floor Drain Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,0100 100.000,00 1.000,00
Tukang L.02 OH 0,1000 120.000,00 12.000,00
Kepala Tukang L.03 OH 0,0100 140.000,00 1.400,00
Mandor L.04 OH 0,0050 160.000,00 800,00
JUMLAH TENAGA KERJA 15.200,00
B. BAHAN
Floordrain, Merk : Toto unit 1,0100 275.000,00 277.750,00
JUMLAH HARGA BAHAN 277.750,00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 292.950,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 292.950,00
1 unit Kran Dinding Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,0100 100.000,00 1.000,00
Tukang L.02 OH 0,4000 120.000,00 48.000,00
Kepala Tukang L.03 OH 0,0400 140.000,00 5.600,00
Mandor L.04 OH 0,0050 160.000,00 800,00
JUMLAH TENAGA KERJA 55.400,00
B. BAHAN
Kran dinding, Merk : Toto unit 1,0100 85.000,00 85.850,00
Seal Tape bh 0,0250 3.000,00 75,00
JUMLAH HARGA BAHAN 85.925,00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 141.325,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 141.325,00

1 m1 Pek. Pas. Railling Tangga Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 1,0000 59.644,88 59.644,88
JUMLAH TENAGA KERJA 59.644,88
B. BAHAN
Plat Besi 11mm kg 3,8858 22.392,00 87.009,71
Pipa Besi Medium Galvanis 3" m1 1,2000 104.200,00 125.040,00
Dynabolt bh 8,0000 10.000,00 80.000,00
Fin. Cat Duco Polyurethane m2 0,0250 159.020,00 3.975,50
Fin. Cat Polyurethane Acrylic m2 0,0140 157.085,25 2.199,19

JUMLAH HARGA BAHAN 298.224,41


C. PERALATAN
Material & alat Bantu ls 1,0000 29.822,44 29.822,44
JUMLAH HARGA PERALATAN 29.822,44

D. Jumlah (A+B+C) 387.691,73


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 387.691,73

1 m1 Nok atap Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0,2000 116.800,00 23.360,00
JUMLAH TENAGA KERJA 23.360,00
B. BAHAN
Nok Atap m1 1,2000 90.000,00 108.000,00
Safe Top Nail bh 8,0000 1.100,00 8.800,00
JUMLAH HARGA BAHAN 116.800,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 140.160,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 140.160,00
1 m1 Listplank Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0,5000 39.226,67 19.613,33
JUMLAH TENAGA KERJA 19.613,33
B. BAHAN
Kalsiplank 8mm, uk. 0,2x3m lbr 0,3333 56.000,00 18.666,67
Metal square hollow 30/60, T. 1,20mm m1 1,0000 20.000,00 20.000,00
Sekrup bh 8,0000 70,00 560,00
JUMLAH HARGA BAHAN 39.226,67
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 58.840,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 58.840,00

1 m1 Flashing atap Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Upah pasang ls 1,0000 12.600,00 12.600,00
JUMLAH TENAGA KERJA 12.600,00
B. BAHAN
Flashing atap pcs 1,0500 120.000,00 126.000,00
JUMLAH HARGA BAHAN 126.000,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 138.600,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 138.600,00

1 m2 Atap UPVC Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja OH 0,200 100.000,00 20.000,00
Tukang kayu OH 0,100 120.000,00 12.000,00
Kepala tukang OH 0,010 140.000,00 1.400,00
Mandor OH 0,010 160.000,00 1.600,00
JUMLAH TENAGA KERJA 35.000,00
B. BAHAN
Atap UPVC ex. Alderon m2 1,0500 180.000,00 189.000,00
Aksesoris Ls 1,0000 28.350,00 28.350,00
JUMLAH HARGA BAHAN 217.350,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 252.350,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 252.350,00
1 m1 Pek. Pas. Hollow 40x60
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,00 5.544,00 5.544,00
JUMLAH TENAGA KERJA 5.544,00
B. BAHAN
Metal square hollow 40/60, tebal 2,3mm m1 1,05 32.000,00 33.600,00
JUMLAH HARGA BAHAN 33.600,00
C. PERALATAN
Material & alat Bantu ls 1,00 3.360,00 3.360,00
JUMLAH HARGA PERALATAN 3.360,00

D. Jumlah (A+B+C) 42.504,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 42.504,00

1 m2 Glassblock
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,00 45.663,75 45.663,75
JUMLAH TENAGA KERJA 45.663,75
B. BAHAN
Glassblock dus 2,05 135.000,00 276.750,00
JUMLAH HARGA BAHAN 276.750,00
C. PERALATAN
Material & alat Bantu ls 1,00 27.675,00 27.675,00
JUMLAH HARGA PERALATAN 27.675,00

D. Jumlah (A+B+C) 350.088,75


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 350.088,75

1 m2 Rooster
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,00 33.387,75 33.387,75
JUMLAH TENAGA KERJA 33.387,75
B. BAHAN
Roster Bh 13,49 15.000,00 202.350,00
JUMLAH HARGA BAHAN 202.350,00
C. PERALATAN
Material & alat Bantu ls 1,00 20.235,00 20.235,00
JUMLAH HARGA PERALATAN 20.235,00

D. Jumlah (A+B+C) 255.972,75


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 255.972,75
ANALISA HARGA SATUAN PEKERJAAN KUSEN

1 m2 Daun Pintu Double Multipleks 6mm Lapis Megateak 4mm Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,7000 100.000,00 70.000,00
Tukang kayu L.02 OH 2,1000 120.000,00 252.000,00
Kepala tukang L.03 OH 0,2100 140.000,00 29.400,00
Mandor L.04 OH 0,0350 160.000,00 5.600,00
JUMLAH TENAGA KERJA 357.000,00
B. BAHAN
kayu solid kamper samarinda oven m3 0,0150 11.600.000,00 174.000,00
Multiplek T.6mm lbr 0,6944 74.000,00 51.388,89
Megateak 4mm lbr 1,0000 112.000,00 112.000,00
Lem putih (Fox) kg 1,0000 19.000,00 19.000,00
Paku triplek kg 0,0300 25.000,00 750,00
Pengecatan polyurethane acrylic m1 2,0000 157.085,25 314.170,50
JUMLAH HARGA BAHAN 671.309,39
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 1.028.309,39


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 1.028.309,39

1 unit Pintu tipe P1 Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 523.541,80 523.541,80
JUMLAH TENAGA KERJA 523.541,80
B. BAHAN

Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo m1 5,3000 135.000,00 715.500,00
Daun Pintu Multipleks 6mm Lapis Megateak m2 1,9350 1.028.309,39 1.989.778,67
Engsel pintu, Merk : Dekkson ESS DL psg 1,5000 70.000,00 105.000,00
Lever Handle, Merk : Dekkson, Solid set 1,0000 330.000,00 330.000,00
Lockcase swing, Merk : Dekkson, Solid set 1,0000 200.000,00 200.000,00
Double Cylinder, Merk : Dekkson, Solid bh 1,0000 150.000,00 150.000,00

JUMLAH HARGA BAHAN 3.490.278,67


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 4.013.820,47


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 4.013.820,47
1 unit Pintu tipe P2 Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 431.850,00 431.850,00
JUMLAH TENAGA KERJA 431.850,00
B. BAHAN

Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo m1 4,4000 135.000,00 594.000,00
Daun Pintu WPC unit 1,0000 1.500.000,00 1.500.000,00
Engsel pintu, Merk : Dekkson ESS DL psg 1,5000 70.000,00 105.000,00
Lever Handle, Merk : Dekkson, Solid set 1,0000 330.000,00 330.000,00
Lockcase swing, Merk : Dekkson, Solid set 1,0000 200.000,00 200.000,00
Double Cylinder, Merk : Dekkson, Solid bh 1,0000 150.000,00 150.000,00

JUMLAH HARGA BAHAN 2.879.000,00


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 3.310.850,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 3.310.850,00

1 unit Pintu tipe P3 Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 423.904,39 423.904,39
JUMLAH TENAGA KERJA 423.904,39
B. BAHAN

Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo m1 4,5500 135.000,00 614.250,00
Daun Pintu Multipleks 6mm Lapis Megateak m2 1,3875 1.028.309,39 1.426.779,28
Engsel pintu, Merk : Dekkson ESS DL psg 1,5000 70.000,00 105.000,00
Lever Handle, Merk : Dekkson, Solid set 1,0000 330.000,00 330.000,00
Lockcase swing, Merk : Dekkson, Solid set 1,0000 200.000,00 200.000,00
Double Cylinder, Merk : Dekkson, Solid bh 1,0000 150.000,00 150.000,00

JUMLAH HARGA BAHAN 2.826.029,28


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 3.249.933,67


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 3.249.933,67
1 unit Pintu tipe P4 Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 444.000,00 444.000,00
JUMLAH TENAGA KERJA 444.000,00
B. BAHAN

Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo m1 5,0000 135.000,00 675.000,00
Daun Pintu WPC unit 1,0000 1.500.000,00 1.500.000,00
Engsel pintu, Merk : Dekkson ESS DL psg 1,5000 70.000,00 105.000,00
Lever Handle, Merk : Dekkson, Solid set 1,0000 330.000,00 330.000,00
Lockcase swing, Merk : Dekkson, Solid set 1,0000 200.000,00 200.000,00
Double Cylinder, Merk : Dekkson, Solid bh 1,0000 150.000,00 150.000,00

JUMLAH HARGA BAHAN 2.960.000,00


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 3.404.000,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 3.404.000,00

1 unit Pintu tipe PS Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 977.076,00 977.076,00
JUMLAH TENAGA KERJA 977.076,00
B. BAHAN
Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo m1 6,3000 135.000,00 850.500,00
Rangka Pintu Aluminium, Merk : Powder Coating Fin. Alexindo m1 23,9000 160.000,00 3.824.000,00
Kaca polos T.6mm, Merk : Asahimas m2 2,6934 100.000,00 269.340,00
Engsel pintu, Merk : Dekkson ESS DL psg 3,0000 70.000,00 210.000,00
Lever Handle, Merk : Dekkson, Solid set 2,0000 330.000,00 660.000,00
Lockcase swing, Merk : Dekkson, Solid set 2,0000 200.000,00 400.000,00
Double Cylinder, Merk : Dekkson, Solid bh 2,0000 150.000,00 300.000,00
JUMLAH HARGA BAHAN 6.513.840,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 7.490.916,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 7.490.916,00
1 unit Pintu tipe PJ1 Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 672.116,80 672.116,80
JUMLAH TENAGA KERJA 672.116,80
B. BAHAN

Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo m1 11,6000 135.000,00 1.566.000,00
Daun Pintu Multipleks 6mm Lapis Megateak m2 1,9350 1.028.309,39 1.989.778,67
Kaca polos T.6mm, Merk : Asahimas m2 1,4000 100.000,00 140.000,00
Engsel pintu, Merk : Dekkson ESS DL psg 1,5000 70.000,00 105.000,00
Lever Handle, Merk : Dekkson, Solid set 1,0000 330.000,00 330.000,00
Lockcase swing, Merk : Dekkson, Solid set 1,0000 200.000,00 200.000,00
Double Cylinder, Merk : Dekkson, Solid bh 1,0000 150.000,00 150.000,00

JUMLAH HARGA BAHAN 4.480.778,67


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 5.152.895,47


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 5.152.895,47

1 unit Pintu tipe J1 Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 791.766,00 791.766,00
JUMLAH TENAGA KERJA 791.766,00
B. BAHAN

Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo m1 14,8000 135.000,00 1.998.000,00
Rangka Pintu Aluminium, Merk : Powder Coating Fin. Alexindo m1 5,9640 160.000,00 954.240,00
Kaca polos T.6mm, Merk : Asahimas m2 18,9120 100.000,00 1.891.200,00
Casement Stay : setara Fino, Kend, Cisa psg 3,0000 75.000,00 225.000,00
Rambuncis : setara Fino, Kend, Cisa bh 3,0000 70.000,00 210.000,00

JUMLAH HARGA BAHAN 5.278.440,00


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 6.070.206,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 6.070.206,00
1 unit Pintu tipe J2 Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 408.768,75 408.768,75
JUMLAH TENAGA KERJA 408.768,75
B. BAHAN

Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo m1 11,2500 135.000,00 1.518.750,00
Rangka Pintu Aluminium, Merk : Powder Coating Fin. Alexindo m1 6,4650 160.000,00 1.034.400,00
Kaca polos T.6mm, Merk : Asahimas m2 1,7198 100.000,00 171.975,00
Casement Stay : setara Fino, Kend, Cisa psg 3,0000 75.000,00 225.000,00
Rambuncis : setara Fino, Kend, Cisa bh 3,0000 70.000,00 210.000,00

JUMLAH HARGA BAHAN 2.725.125,00


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 3.133.893,75


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 3.133.893,75

1 unit Pintu tipe J3 Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 177.712,50 177.712,50
JUMLAH TENAGA KERJA 177.712,50
B. BAHAN

Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo m1 6,8500 135.000,00 924.750,00
Kaca polos T.6mm, Merk : Asahimas m2 2,6000 100.000,00 260.000,00

JUMLAH HARGA BAHAN 1.184.750,00


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 1.362.462,50


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 1.362.462,50

1 unit Pintu tipe J3' Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 259.080,00 259.080,00
JUMLAH TENAGA KERJA 259.080,00
B. BAHAN

Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo m1 9,6000 135.000,00 1.296.000,00
Kaca polos T.6mm, Merk : Asahimas m2 4,3120 100.000,00 431.200,00

JUMLAH HARGA BAHAN 1.727.200,00


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 1.986.280,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 1.986.280,00
1 unit Pintu tipe BV1 Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 116.640,00 116.640,00
JUMLAH TENAGA KERJA 116.640,00
B. BAHAN

Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo m1 5,3000 135.000,00 715.500,00
Kaca polos T.6mm, Merk : Asahimas m2 0,6210 100.000,00 62.100,00

JUMLAH HARGA BAHAN 777.600,00


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 894.240,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 894.240,00

1 unit Pintu tipe GB1 Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 32.400,00 32.400,00
JUMLAH TENAGA KERJA 32.400,00
B. BAHAN

Glassblock m2 1,6000 135.000,00 216.000,00

JUMLAH HARGA BAHAN 216.000,00


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 248.400,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 248.400,00
1 unit Pintu tipe GB2 Sumber : Analisa Survey Pasar
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 12.960,00 12.960,00
JUMLAH TENAGA KERJA 12.960,00
B. BAHAN

Glassblock m2 0,6400 135.000,00 86.400,00

JUMLAH HARGA BAHAN 86.400,00


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 99.360,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 99.360,00

1 m2 Rooster Sumber : Analisa Survey Pasar


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1,0000 45.000,00 45.000,00
JUMLAH TENAGA KERJA 45.000,00
B. BAHAN

Roster bh 20,0000 15.000,00 300.000,00

JUMLAH HARGA BAHAN 300.000,00


C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 345.000,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 345.000,00
ANALISA HARGA SATUAN PEKERJAAN MEP

Memasang 1 bh Floting Valve 10K 1" (25 mm) lengkap


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,250 100.000,00 25.000,00
Tukang L.02 OH 0,200 120.000,00 24.000,00
Kepala tukang L.03 OH 0,040 140.000,00 5.600,00
Mandor L.04 OH 0,030 160.000,00 4.800,00
JUMLAH TENAGA KERJA 59.400,00
B. BAHAN
Floating valve dia. 25 mm bh 1,000 250.000,00 250.000,00
JUMLAH HARGA BAHAN 250.000,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 309.400,00


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 309.400,00

Memasang 1 set Radar level control


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,500 100.000,00 50.000,00
Tukang L.02 OH 0,400 120.000,00 48.000,00
Kepala tukang L.03 OH 0,040 140.000,00 5.600,00
Mandor L.04 OH 0,030 160.000,00 4.800,00
JUMLAH TENAGA KERJA 108.400,00
B. BAHAN
Water Level Control ( WLC ) #N/A 1,000 75.000,00 75.000,00
JUMLAH HARGA BAHAN 75.000,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 183.400,00


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 183.400,00

Memasang 1 Unit Pompa Transfer Air Bersih


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,500 100.000,00 50.000,00
Tukang L.02 OH 0,500 120.000,00 60.000,00
Kepala tukang L.03 OH 0,070 140.000,00 9.800,00
Mandor L.04 OH 0,050 160.000,00 8.000,00
JUMLAH TENAGA KERJA 127.800,00
B. BAHAN
Pompa Transfer, kapasitas : 50 Lpm/ head 40 meter (lengkap accessories) unit 1,000 2.000.000,00 2.000.000,00
JUMLAH HARGA BAHAN 2.000.000,00
C. PERALATAN
Alat bantu ls 1,000 200.000,00 200.000,00
JUMLAH HARGA PERALATAN 200.000,00

D. Jumlah (A+B+C) 2.327.800,00


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 2.327.800,00
Memasang 1 m' pipa PVC tipe AW ø1/2" (15 mm)
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100.000,00 3.571,43
Tukang L.02 OH 0,036 120.000,00 4.285,71
Kepala tukang L.03 OH 0,003 140.000,00 400,00
Mandor L.04 OH 0,001 160.000,00 228,57
JUMLAH TENAGA KERJA 8.485,71
B. BAHAN
PVC Dia. 15mm m1 1,000 5.825,00 5.825,00
Fitting & sambungan m' 1,000 1.456,25 1.456,25
JUMLAH HARGA BAHAN 7.281,25
C. PERALATAN
Fitting, sambungan, klem dll bh 1,000 364,06 364,06
JUMLAH HARGA PERALATAN 364,06

D. Jumlah (A+B+C) 16.131,03


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 16.131,03

Memasang 1 m' pipa PVC tipe AW ø3/4" (20 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100.000,00 3.571,43
Tukang L.02 OH 0,036 120.000,00 4.285,71
Kepala tukang L.03 OH 0,003 140.000,00 400,00
Mandor L.04 OH 0,001 160.000,00 228,57
JUMLAH TENAGA KERJA 8.485,71
B. BAHAN
PVC Dia. 20mm m1 1,000 7.925,00 7.925,00
Fitting & sambungan m' 1,000 1.981,25 1.981,25
JUMLAH HARGA BAHAN 9.906,25
C. PERALATAN
Fitting, sambungan, klem dll bh 1,000 495,31 495,31
JUMLAH HARGA PERALATAN 495,31

D. Jumlah (A+B+C) 18.887,28


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 18.887,28

Memasang 1 m' pipa PVC tipe AW ø1" (25 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100.000,00 3.571,43
Tukang L.02 OH 0,036 120.000,00 4.285,71
Kepala tukang L.03 OH 0,003 140.000,00 400,00
Mandor L.04 OH 0,001 160.000,00 228,57
JUMLAH TENAGA KERJA 8.485,71
B. BAHAN
PVC Dia. 25mm m1 1,000 10.825,00 10.825,00
Fitting & sambungan m' 1,000 2.706,25 2.706,25
JUMLAH HARGA BAHAN 13.531,25
C. PERALATAN
Fitting, sambungan, klem dll bh 1,000 676,56 676,56
JUMLAH HARGA PERALATAN 676,56

D. Jumlah (A+B+C) 22.693,53


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 22.693,53
Memasang 1 m' pipa PVC tipe AW ø1 1/4" (32 mm)
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100.000,00 3.571,43
Tukang L.02 OH 0,036 120.000,00 4.285,71
Kepala tukang L.03 OH 0,003 140.000,00 400,00
Mandor L.04 OH 0,001 160.000,00 228,57
JUMLAH TENAGA KERJA 8.485,71
B. BAHAN
PVC Dia. 32mm m1 1,000 16.200,00 16.200,00
Fitting & sambungan m' 1,000 4.050,00 4.050,00
JUMLAH HARGA BAHAN 20.250,00
C. PERALATAN
Fitting, sambungan, klem dll bh 1,000 1.012,50 1.012,50
JUMLAH HARGA PERALATAN 1.012,50

D. Jumlah (A+B+C) 29.748,21


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 29.748,21

Memasang 1 m' pipa PVC tipe AW ø1 1/2" (40 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100.000,00 3.571,43
Tukang L.02 OH 0,036 120.000,00 4.285,71
Kepala tukang L.03 OH 0,003 140.000,00 400,00
Mandor L.04 OH 0,001 160.000,00 228,57
JUMLAH TENAGA KERJA 8.485,71
B. BAHAN
PVC Dia. 40mm m1 1,000 18.600,00 18.600,00
Fitting & sambungan m' 1,000 4.650,00 4.650,00
JUMLAH HARGA BAHAN 23.250,00
C. PERALATAN
Fitting, sambungan, klem dll bh 1,000 1.162,50 1.162,50
JUMLAH HARGA PERALATAN 1.162,50

D. Jumlah (A+B+C) 32.898,21


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 32.898,21

Memasang 1 m' pipa PVC tipe AW ø2" (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100.000,00 3.571,43
Tukang L.02 OH 0,036 120.000,00 4.285,71
Kepala tukang L.03 OH 0,003 140.000,00 400,00
Mandor L.04 OH 0,001 160.000,00 228,57
JUMLAH TENAGA KERJA 8.485,71
B. BAHAN
PVC Dia. 50mm m' 1,000 23.800,00 23.800,00
Fitting & sambungan m' 1,000 5.950,00 5.950,00
JUMLAH HARGA BAHAN 29.750,00
C. PERALATAN
Fitting, sambungan, klem dll bh 1,000 1.487,50 1.487,50
JUMLAH HARGA PERALATAN 1.487,50

D. Jumlah (A+B+C) 39.723,21


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 39.723,21

Memasang 1 m' pipa PVC tipe AW ø2 1/2" (65 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100.000,00 3.571,43
Tukang L.02 OH 0,036 120.000,00 4.285,71
Kepala tukang L.03 OH 0,003 140.000,00 400,00
Mandor L.04 OH 0,001 160.000,00 228,57
JUMLAH TENAGA KERJA 8.485,71
B. BAHAN
PVC Dia. 65mm m' 1,000 34.725,00 34.725,00
Fitting & sambungan m' 1,000 8.681,25 8.681,25
JUMLAH HARGA BAHAN 43.406,25
C. PERALATAN
Fitting, sambungan, klem dll bh 1,000 2.170,31 2.170,31
JUMLAH HARGA PERALATAN 2.170,31

D. Jumlah (A+B+C) 54.062,28


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 54.062,28

Memasang 1 m' pipa PVC tipe AW ø3" (80 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100.000,00 3.571,43
Tukang L.02 OH 0,036 120.000,00 4.285,71
Kepala tukang L.03 OH 0,003 140.000,00 400,00
Mandor L.04 OH 0,001 160.000,00 228,57
JUMLAH TENAGA KERJA 8.485,71
B. BAHAN
PVC Dia. 80mm m' 1,000 48.900,00 48.900,00
Fitting & sambungan m' 1,000 12.225,00 12.225,00
JUMLAH HARGA BAHAN 61.125,00
C. PERALATAN
Fitting, sambungan, klem dll bh 1,000 3.056,25 3.056,25
JUMLAH HARGA PERALATAN 3.056,25

D. Jumlah (A+B+C) 72.666,96


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 72.666,96

Memasang 1 m' pipa PVC tipe AW ø4" (100 mm)


HARGA JUMLAH
URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100.000,00 3.571,43
Tukang L.02 OH 0,036 120.000,00 4.285,71
Kepala tukang L.03 OH 0,003 140.000,00 400,00
Mandor L.04 OH 0,001 160.000,00 228,57
JUMLAH TENAGA KERJA 8.485,71
B. BAHAN
PVC Dia. 100mm m' 1,000 81.025,00 81.025,00
Fitting & sambungan m' 1,000 20.256,25 20.256,25
JUMLAH HARGA BAHAN 101.281,25
C. PERALATAN
Fitting, sambungan, klem dll bh 1,000 5.064,06 5.064,06
JUMLAH HARGA PERALATAN 5.064,06

D. Jumlah (A+B+C) 114.831,03


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 114.831,03

Memasang 1 m' pipa PVC tipe AW ø6" (150 mm)


HARGA JUMLAH
URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100.000,00 3.571,43
Tukang L.02 OH 0,036 120.000,00 4.285,71
Kepala tukang L.03 OH 0,003 140.000,00 400,00
Mandor L.04 OH 0,001 160.000,00 228,57
JUMLAH TENAGA KERJA 8.485,71
B. BAHAN
PVC Dia. 150mm m' 1,000 180.050,00 180.050,00
Fitting & sambungan m' 1,000 45.012,50 45.012,50
JUMLAH HARGA BAHAN 225.062,50
C. PERALATAN
Fitting, sambungan, klem dll bh 1,000 11.253,13 11.253,13
JUMLAH HARGA PERALATAN 11.253,13

D. Jumlah (A+B+C) 244.801,34


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 244.801,34

Memasang 1 m' pipa PVC tipe AW ø8" (200 mm)


HARGA JUMLAH
URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,036 100.000,00 3.571,43
Tukang L.02 OH 0,036 120.000,00 4.285,71
Kepala tukang L.03 OH 0,003 140.000,00 400,00
Mandor L.04 OH 0,001 160.000,00 228,57
JUMLAH TENAGA KERJA 8.485,71
B. BAHAN
PVC Dia. 200mm m' 1,000 302.150,00 302.150,00
Fitting & sambungan m' 1,000 75.537,50 75.537,50
JUMLAH HARGA BAHAN 377.687,50
C. PERALATAN
Fitting, sambungan, klem dll bh 1,000 18.884,38 18.884,38
JUMLAH HARGA PERALATAN 18.884,38

D. Jumlah (A+B+C) 405.057,59


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 405.057,59

Memasang 1 bh Ball Valve 10K 1/2" (15 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,125 100.000,00 12.500,00
Tukang L.02 OH 0,125 120.000,00 15.000,00
Kepala tukang L.03 OH 0,011 140.000,00 1.500,00
Mandor L.04 OH 0,007 160.000,00 1.142,86
JUMLAH TENAGA KERJA 30.142,86
B. BAHAN
Gate valve 10 K dia. 15 mm bh 1,000 60.000,00 60.000,00
JUMLAH HARGA BAHAN 60.000,00
C. PERALATAN
Pelatana bantu Ls 1,000 1.200,00 1.200,00
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 90.142,86


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 90.142,86
Memasang 1 bh Ball Valve 10K 3/4" (20 mm)
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,125 100.000,00 12.500,00
Tukang L.02 OH 0,125 120.000,00 15.000,00
Kepala tukang L.03 OH 0,011 140.000,00 1.500,00
Mandor L.04 OH 0,007 160.000,00 1.142,86
JUMLAH TENAGA KERJA 30.142,86
B. BAHAN
Gate valve 10 K dia. 20 mm bh 1,000 75.000,00 75.000,00
JUMLAH HARGA BAHAN 75.000,00
C. PERALATAN
Pelatana bantu Ls 1,000 1.500,00 1.500,00
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 105.142,86


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 105.142,86

Memasang 1 bh Ball Valve 10K 1" (25 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,125 100.000,00 12.500,00
Tukang L.02 OH 0,125 120.000,00 15.000,00
Kepala tukang L.03 OH 0,011 140.000,00 1.500,00
Mandor L.04 OH 0,007 160.000,00 1.142,86
JUMLAH TENAGA KERJA 30.142,86
B. BAHAN
Gate valve 10 K dia. 25 mm bh 1,000 92.000,00 92.000,00
JUMLAH HARGA BAHAN 92.000,00
C. PERALATAN
Pelatana bantu Ls 1,000 1.840,00 1.840,00
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 122.142,86


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 122.142,86

Memasang 1 bh Ball Valve 10K 1 1/4" (32 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,125 100.000,00 12.500,00
Tukang L.02 OH 0,125 120.000,00 15.000,00
Kepala tukang L.03 OH 0,011 140.000,00 1.500,00
Mandor L.04 OH 0,007 160.000,00 1.142,86
JUMLAH TENAGA KERJA 30.142,86
B. BAHAN
Gate valve 10 K dia. 32 mm bh 1,000 115.000,00 115.000,00
JUMLAH HARGA BAHAN 115.000,00
C. PERALATAN
Pelatana bantu Ls 1,000 2.300,00 2.300,00
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 145.142,86


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 145.142,86
Memasang 1 bh Ball Valve 10K 1 1/2" (40 mm)
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,125 100.000,00 12.500,00
Tukang L.02 OH 0,125 120.000,00 15.000,00
Kepala tukang L.03 OH 0,011 140.000,00 1.500,00
Mandor L.04 OH 0,007 160.000,00 1.142,86
JUMLAH TENAGA KERJA 30.142,86
B. BAHAN
Gate valve 10 K dia. 40 mm bh 1,000 125.000,00 125.000,00
JUMLAH HARGA BAHAN 125.000,00
C. PERALATAN
Pelatana bantu Ls 1,000 2.500,00 2.500,00
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 155.142,86


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 155.142,86

Memasang 1 unit Rooftank kapasitas 1 m3


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,500 100.000,00 50.000,00
Tukang L.02 OH 0,500 120.000,00 60.000,00
Kepala tukang L.03 OH 0,030 140.000,00 4.200,00
Mandor L.04 OH 0,020 160.000,00 3.200,00
JUMLAH TENAGA KERJA 117.400,00
B. BAHAN
Roof Tank ( PRF ), kapasitas 6000 L unit 1,000 1.650.000,00 1.650.000,00
Dudukan tanki Ls 1,000 247.500,00 247.500,00
JUMLAH HARGA BAHAN 1.897.500,00
C. PERALATAN
Perlengkapan ( alat bantu pemasangan ) ls 1,000 47.437,50 47.437,50
JUMLAH HARGA PERALATAN 47.437,50

D. Jumlah (A+B+C) 2.062.337,50


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 2.062.337,50

Memasang 1 bh Clean out 2" (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,143 100.000,00 14.285,71
Tukang L.02 OH 0,107 120.000,00 12.857,14
Kepala tukang L.03 OH 0,014 140.000,00 2.000,00
Mandor L.04 OH 0,007 160.000,00 1.142,86
JUMLAH TENAGA KERJA 30.285,71
B. BAHAN
CO diameter 50 mm bh 1,000 9.000,00 9.000,00
JUMLAH HARGA BAHAN 9.000,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 39.285,71


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 39.285,71
Memasang 1 bh Clean out 2 1/2" (65 mm)
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,143 100.000,00 14.285,71
Tukang L.02 OH 0,107 120.000,00 12.857,14
Kepala tukang L.03 OH 0,014 140.000,00 2.000,00
Mandor L.04 OH 0,007 160.000,00 1.142,86
JUMLAH TENAGA KERJA 30.285,71
B. BAHAN
CO diameter 65 mm bh 1,000 12.000,00 12.000,00
JUMLAH HARGA BAHAN 12.000,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 42.285,71


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 42.285,71

Memasang 1 bh Clean out 3" (80 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,143 100.000,00 14.285,71
Tukang L.02 OH 0,107 120.000,00 12.857,14
Kepala tukang L.03 OH 0,014 140.000,00 2.000,00
Mandor L.04 OH 0,007 160.000,00 1.142,86
JUMLAH TENAGA KERJA 30.285,71
B. BAHAN
CO diameter 80 mm bh 1,000 15.000,00 15.000,00
JUMLAH HARGA BAHAN 15.000,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 45.285,71


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 45.285,71

Memasang 1 bh Clean out 4" (100 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,143 100.000,00 14.285,71
Tukang L.02 OH 0,107 120.000,00 12.857,14
Kepala tukang L.03 OH 0,014 140.000,00 2.000,00
Mandor L.04 OH 0,007 160.000,00 1.142,86
JUMLAH TENAGA KERJA 30.285,71
B. BAHAN
CO diameter 100 mm bh 1,000 25.000,00 25.000,00
JUMLAH HARGA BAHAN 25.000,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 55.285,71


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 55.285,71
Memasang 1 bh Roof Drian 3" (80 mm)
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,143 100.000,00 14.285,71
Tukang L.02 OH 0,107 120.000,00 12.857,14
Kepala tukang L.03 OH 0,014 140.000,00 2.000,00
Mandor L.04 OH 0,007 160.000,00 1.142,86
JUMLAH TENAGA KERJA 30.285,71
B. BAHAN
RD diameter 80 mm bh 1,000 72.000,00 72.000,00
JUMLAH HARGA BAHAN 72.000,00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 102.285,71


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 102.285,71

1 M Kabel Tray 15 cm ( 150 x 100 )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,043 100.000,00 4.250,00
Tukang L.02 OH 0,043 120.000,00 5.100,00
Kepala tukang L.03 OH 0,017 140.000,00 2.324,00
Mandor L.04 OH 0,014 160.000,00 2.240,00
JUMLAH TENAGA KERJA 13.914,00
B. BAHAN
Kabel Tray 15 cm ( 150 x 100 ) m1 1,000 215.000,00 215.000,00
Tee, Cros, Elbow, Reducer, & dudukan/penggantung ls 1,000 53.750,00 53.750,00
JUMLAH HARGA BAHAN 268.750,00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1,000 6.718,75 6.718,75
JUMLAH HARGA PERALATAN 6.718,75

D. Jumlah (A+B+C) 289.382,75


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 289.382,75

1 bh Lampu TL LED 2 x 16 Watt TKI/Inbow


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,100 100.000,00 10.000,00
Tukang L.02 OH 0,100 120.000,00 12.000,00
Kepala tukang L.03 OH 0,013 140.000,00 1.820,00
Mandor L.04 OH 0,011 160.000,00 1.760,00
JUMLAH TENAGA KERJA 25.580,00
B. BAHAN
TL LED 2 x 16 Watt TKI/Inbow bh 1,000 730.000,00 730.000,00
JUMLAH HARGA BAHAN 730.000,00
C. PERALATAN
Perlengkapan Instalasi ls 1,000 18.250,00 18.250,00
JUMLAH HARGA PERALATAN 18.250,00

D. Jumlah (A+B+C) 773.830,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 773.830,00
1 bh Lampu Downlight LED 12 Watt
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,100 100.000,00 10.000,00
Tukang L.02 OH 0,100 120.000,00 12.000,00
Kepala tukang L.03 OH 0,013 140.000,00 1.820,00
Mandor L.04 OH 0,011 160.000,00 1.760,00
JUMLAH TENAGA KERJA 25.580,00
B. BAHAN
Downlight 12 Watt bh 1,000 265.000,00 265.000,00
JUMLAH HARGA BAHAN 265.000,00
C. PERALATAN
Perlengkapan Instalasi ls 1,000 6.625,00 6.625,00
JUMLAH HARGA PERALATAN 6.625,00

D. Jumlah (A+B+C) 297.205,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 297.205,00

1 bh Lampu Downlight LED 15 Watt


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,100 100.000,00 10.000,00
Tukang L.02 OH 0,100 120.000,00 12.000,00
Kepala tukang L.03 OH 0,013 140.000,00 1.820,00
Mandor L.04 OH 0,011 160.000,00 1.760,00
JUMLAH TENAGA KERJA 25.580,00
B. BAHAN
Downlight 15 Watt bh 1,000 281.400,00 281.400,00
JUMLAH HARGA BAHAN 281.400,00
C. PERALATAN
Perlengkapan Instalasi ls 1,000 7.035,00 7.035,00
JUMLAH HARGA PERALATAN 7.035,00

D. Jumlah (A+B+C) 314.015,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 314.015,00

1 bh Lampu Downlight LED 32 Watt


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,100 100.000,00 10.000,00
Tukang L.02 OH 0,100 120.000,00 12.000,00
Kepala tukang L.03 OH 0,013 140.000,00 1.820,00
Mandor L.04 OH 0,011 160.000,00 1.760,00
JUMLAH TENAGA KERJA 25.580,00
B. BAHAN
Downlight 15 Watt bh 1,000 400.000,00 400.000,00
JUMLAH HARGA BAHAN 400.000,00
C. PERALATAN
Perlengkapan Instalasi ls 1,000 10.000,00 10.000,00
JUMLAH HARGA PERALATAN 10.000,00

D. Jumlah (A+B+C) 435.580,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 435.580,00
1 bh Lampu Baret LED 17 Watt
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,100 100.000,00 10.000,00
Tukang L.02 OH 0,100 120.000,00 12.000,00
Kepala tukang L.03 OH 0,013 140.000,00 1.820,00
Mandor L.04 OH 0,011 160.000,00 1.760,00
JUMLAH TENAGA KERJA 25.580,00
B. BAHAN
Baret 17 Watt bh 1,000 213.000,00 213.000,00
JUMLAH HARGA BAHAN 213.000,00
C. PERALATAN
Perlengkapan Instalasi ls 1,000 5.325,00 5.325,00
JUMLAH HARGA PERALATAN 5.325,00

D. Jumlah (A+B+C) 243.905,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 243.905,00

1 bh Saklar tunggal
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,025 100.000,00 2.500,00
Tukang L.02 OH 0,025 120.000,00 3.000,00
Kepala tukang L.03 OH 0,017 140.000,00 2.324,00
Mandor L.04 OH 0,014 160.000,00 2.240,00
JUMLAH TENAGA KERJA 10.064,00
B. BAHAN
Saklar Tunggal bh 1,000 16.500,00 16.500,00
JUMLAH HARGA BAHAN 16.500,00
C. PERALATAN

JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 26.564,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 26.564,00

1 bh Saklar Ganda
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,025 100.000,00 2.500,00
Tukang L.02 OH 0,025 120.000,00 3.000,00
Kepala tukang L.03 OH 0,017 140.000,00 2.324,00
Mandor L.04 OH 0,014 160.000,00 2.240,00
JUMLAH TENAGA KERJA 10.064,00
B. BAHAN
Saklar Ganda bh 1,000 20.190,00 20.190,00
JUMLAH HARGA BAHAN 20.190,00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 30.254,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 30.254,00
1 bh Stop Kontak daya 1 Ph
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,025 100.000,00 2.500,00
Tukang L.02 OH 0,025 120.000,00 3.000,00
Kepala tukang L.03 OH 0,017 140.000,00 2.324,00
Mandor L.04 OH 0,014 160.000,00 2.240,00
JUMLAH TENAGA KERJA 10.064,00
B. BAHAN
Stop Kontak 10 A/16A/1Phase #N/A 1,000 17.050,00 17.050,00
JUMLAH HARGA BAHAN 17.050,00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 27.114,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 27.114,00

1 Titik Instalasi Lampu


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,150 100.000,00 15.000,00
Tukang L.02 OH 0,150 120.000,00 18.000,00
Kepala tukang L.03 OH 0,100 140.000,00 14.000,00
Mandor L.04 OH 0,075 160.000,00 12.000,00
JUMLAH TENAGA KERJA 59.000,00
B. BAHAN
NYM 3 x 2,5 MM2 #N/A 9,000 13.000,00 117.000,00
Pipa Conduit m1 9,000 3.500,00 31.500,00
JUMLAH HARGA BAHAN 148.500,00
C. PERALATAN
Perlengkapan Instalasi ( tee doos, klamp, soket, fhiser, lasdop, dll ) ls 1,000 22.275,00 22.275,00
JUMLAH HARGA PERALATAN 22.275,00

D. Jumlah (A+B+C) 229.775,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 229.775,00

1 Titik Instalasi Stop kontak


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,150 100.000,00 15.000,00
Tukang L.02 OH 0,150 120.000,00 18.000,00
Kepala tukang L.03 OH 0,100 140.000,00 14.000,00
Mandor L.04 OH 0,075 160.000,00 12.000,00
JUMLAH TENAGA KERJA 59.000,00
B. BAHAN
NYM 3 x 2,5 MM2 #N/A 14,000 13.000,00 182.000,00
Pipa Conduit m1 14,000 3.500,00 49.000,00
JUMLAH HARGA BAHAN 231.000,00
C. PERALATAN
Perlengkapan Instalasi ( tee doos, klamp, soket, fhiser, lasdop, dll ) ls 1,000 34.650,00 34.650,00
JUMLAH HARGA PERALATAN 34.650,00

D. Jumlah (A+B+C) 324.650,00


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 324.650,00

Memasang 1 bh Exhaust Fan 75 Cfm ESP. 0,3 inwg - Extract Fan


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,200 100.000,00 20.000,00
Tukang L.02 OH 0,200 120.000,00 24.000,00
Kepala tukang L.03 OH 0,350 140.000,00 49.000,00
Mandor L.04 OH 0,350 160.000,00 56.000,00
JUMLAH TENAGA KERJA 149.000,00
B. BAHAN
Exhaust Fan, kap. 75 Cfm - Extract fan unit 1,000 539.000,00 539.000,00
JUMLAH HARGA BAHAN 539.000,00
C. PERALATAN
Perlengkapan ( dudukan ) bh 1,000 10.780,00 10.780,00
JUMLAH HARGA PERALATAN 10.780,00

D. Jumlah (A+B+C) 698.780,00


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 698.780,00

Memasang Exhaust Air Grille uk. 6" x 6"


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,143 100.000,00 14.285,71
Tukang L.02 OH 0,143 120.000,00 17.142,86
Kepala tukang L.03 OH 0,036 140.000,00 5.000,00
Mandor L.04 OH 0,014 160.000,00 2.285,71
JUMLAH TENAGA KERJA 38.714,29
B. BAHAN
Exhaust Air Grille uk. 6" x 6 " bh 1,000 125.200,00 125.200,00
JUMLAH HARGA BAHAN 125.200,00
C. PERALATAN
Perlengkapan ( dudukan ) bh 1,000 3.756,00 3.756,00
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 163.914,29


E. Overhead & Profit 10% -
F. Harga Satuan Pembantu Tukangan (D+E) 163.914,29

Memasang 1 M Kabel Power NYY 4 x 95 mm + BCC 50 mm Data Hasil Survey


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,166 100.000,00 16.600,00
Tukang L.02 OH 0,166 120.000,00 19.920,00
Kepala tukang L.03 OH 0,033 140.000,00 4.620,00
Mandor L.04 OH 0,017 160.000,00 2.656,00
JUMLAH TENAGA KERJA 43.796,00
B. BAHAN
Kabel NYY 4 X 10 mm2 m1 1,000 67.000,00 67.000,00
BCC 50 mm m1 1,000 36.700,00 36.700,00
Skun kabel set 1,000 2.592,50 2.592,50
JUMLAH HARGA BAHAN 106.292,50
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 150.088,50


E. Overhead & Profit 10% -
F. Harga Satuan Pekerjaan (D+E) 150.088,50
HARGA SATUAN
NO URAIAN SAT
( Rp )

I. HARGA BAHAN ARSITEKTUR DAN STRUKTUR


1 Air ltr 150,00
2 Ampelas besi lbr 4.000,00
3 Ampelas kayu lbr 4.000,00
4 Ampelas tembok lbr 4.000,00
5 Angkur dia. 8mm kg 9.000,00
6 Atap UPVC ex. Alderon m2 180.000,00
7 Baja Profil, Merk : DN kg 13.500,00
8 Balok Kayu Albasiah m3 900.000,00
9 Balok Kayu Kelas Iii m3 3.200.000,00
10 Balok Kayu Kelas Iii m3 1.200.000,00
11 Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m3 750.000,00
12 Batako bh 2.450,00
13 Batu pecah mesin 1-2 kg 183,70
14 Besi Beton Polos kg 9.000,00
15 Besi Beton Ulir kg 9.500,00
16 Cat dasar Attaboy OS super primer color pail 830.000,00
17 Cat dasar, Merk : Attaboy OS super primer color pail 830.000,00
18 Cat dasar, Merk : Attaboy OS Super Primer White pail 840.000,00
19 Cat duco polyurethane clear matt MV-3, Merk : Petalac 2K ltr 310.000,00
20 Cat epoxy undercoat, Merk : Petalac ltr 196.500,00
21 Cat Petalac-2K Clear Matt MV-3 ltr 115.500,00
22 Cat Petalac-2K Super Sanding sealer ltr 70.400,00
23 Cat polyster putty, Merk : Petalac ltr 175.000,00
24 Cat tembok eksterior, Merk : Attaboy Weatherguard pail 1.925.000,00
25 Cat tembok interior, Merk : Attaboy O.S. Stainblocking Masonry paint Color pail 1.300.000,00
26 Cat tembok interior, setara Attaboy O.S. Stainblocking Masonry paint Color pail 1.300.000,00
27 Compound kg 1.000,00
28 Deco Panel GRC Board T.11 m2 475.000,00
29 Drymix Acian (40kg) kg 3.125,00
30 Drymix Plester 16 (50kg) kg 2.400,00
31 Drymix TA water repellent (40kg) zak 170.000,00
32 Drymix Thinbed M-101 (40kg) zak 96.800,00
33 Dynabolt bh 10.000,00
34 Flashing atap pcs 120.000,00
35 Glassblock dus 135.000,00
36 Granite Tile , uk. 600x600, Merk : Indogress m2 364.000,00
37 Gypsumboard T.9mm, Merk : Jayaboard lbr 65.000,00
38 Besi Hollow Galvanis 40x80 m1 42.160,00
39 Homogeneous Tile 800x800 Estillo Ines, Merk : Niro granit m2 271.500,00
40 HPL lbr 240.000,00
41 Jaring Kawat Baja Dilas kg 9.500,00
42 Kaca polos T.6mm, Merk : Asahimas m2 100.000,00
43 Kaca Tempered T.12mm, Merk : Asahimas, Mulia m2 850.000,00
44 Kaca Tempered T.8mm, Merk : Asashimas m2 600.000,00
45 Kaca tinted Stopsol 5 mm, merek asahimas m2 436.000,00
46 Kalsiplank 8mm, uk. 0,2x3m lbr 56.000,00
47 Kalsium silikat plafond tipe kalsi ling 6 setara Kalsiboard lbr 90.108,00
48 Kawat Beton kg 25.000,00
49 Kayu Albasiah 5/7 m3 900.000,00
50 Kayu balok borneo super m3 4.784.000,00
51 Kayu Kelas III m3 3.200.000,00
52 Kayu papan albasiah m3 1.251.200,00
53 Kayu Papan Kelas IV m3 1.200.000,00
54 kayu solid kamper samarinda oven m3 11.600.000,00
55 Keramik, uk. 200x200, Merk : Roman m2 98.000,00
56 Keramik, uk. 200x400, Merk : Roman m2 102.000,00
57 Keramik, uk. 400x400, Merk : Roman m2 125.000,00
58 Koral tabur Kg 3.000,00
59 Kwas 3" bh 10.000,00
60 Lem putih (Fox) kg 19.000,00
61 Marmer Carrara 400x400 m2 1.250.000,00
62 Megateak 4mm lbr 112.000,00
63 Meiji gum sealer kg 42.000,00
64 Metal furing acoustic Tee m1 10.000,00
65 Metal furing acoustic wall angle m1 10.000,00
66 Metal square hollow 30/60, T. 1,20mm m1 20.000,00
67 Metal square hollow 40/40, T. 1,10mm m1 12.000,00
68 Metal square hollow 40/60, tebal 2,3mm m1 32.000,00
69 Minyak Bekisting ltr 12.000,00
70 MU Plester (50kg) kg 2.400,00
71 MU Plester 16 (50kg) kg 2.400,00
72 Multiplek T.6mm lbr 74.000,00
73 Nok Atap m1 90.000,00
74 Paku 5-10cm kg 16.000,00
75 Paku Biasa 2" - 3" kg 25.000,00
76 Paku triplek kg 25.000,00
77 Pasir Beton kg 151,72
78 Pasir Pasang m3 210.000,00
79 Pasir Urug m3 120.500,00
80 Pipa Besi Medium Galvanis 3" m1 104.200,00
81 Plat Besi 11mm kg 22.392,00
82 Plint Granit 10x80 m1 25.000,00
83 Plywood tebal 9mm lbr 120.000,00
84 Rol cat bh 21.000,00
85 Roster Bh 15.000,00
86 Rumset bh 3.500,00
87 Safe Top Nail bh 1.100,00
88 Sekrup kg 25.000,00
89 Semen PC 50kg zak 70.000,00
90 Semen Portland kg 1.400,00
91 Semen Warna kg 7.500,00
92 Thinner OS 2000 ltr 30.000,00
93 Thinner P.U. ltr 31.000,00
94 Thinner Slow Dry ltr 38.500,00
95 Thinner Super Sanding Sealer ltr 30.800,00
96 Triplek lbr 45.000,00
97 Wood filler + wood stain kg 44.000,00
98 Waterproofing Formdex Uniflex Cementitious Membrance, m2 95.000,00
Merk : Sika, Fosroc

99 Plumbing Fixtures :
Closet Duduk, Merk : Toto unit 3.400.000,00
Closet Jongkok, Merk : Toto unit 404.000,00
Washtafel, Merk : Toto unit 640.000,00
Kran washtafel, Merk : Toto unit 900.000,00
Floordrain, Merk : Toto unit 275.000,00
Handrail tipe, Merk : Toto unit 702.000,00
Shower Spray, Merk : Toto unit 408.000,00
Shower, Merk : Toto unit 2.760.000,00
Mixed Shower, Merk : Toto unit 1.220.000,00
Jet Washer, Merk : Toto unit 515.000,00
Folding Shower unit 724.000,00
Kran dinding, Merk : Toto unit 85.000,00

100 Perlengkapan Kusen :

Kusen Aluminium 4", T.1,3mm, fin. Anodize, Merk : Alexindo m1 135.000,00


Engsel pintu, Merk : Dekkson ESS DL psg 70.000,00
Pull Handle, Merk : Dekkson, Solid set 800.000,00
Lockcase swing, Merk : Dekkson, Solid set 200.000,00
Double Cylinder, Merk : Dekkson, Solid bh 150.000,00
Stainless Steel 1mm cm2 10.000,00
Rangka Pintu Aluminium, Merk : Powder Coating Fin. Alexindo m1 160.000,00
Rangka Jendela Aluminium, Merk : Powder Coating Fin. Alexindo m1 160.000,00
Lever Handle, Merk : Dekkson, Solid set 330.000,00
Casement Stay : setara Fino, Kend, Cisa psg 75.000,00
Rambuncis : setara Fino, Kend, Cisa bh 70.000,00

II. HARGA BAHAN MEP


1 Floating valve dia. 25 mm bh 250.000,00
2 Pompa Transfer Air Bersih kapasitas 50 lpm head 40 meter (lengkap accessories) unit 2.000.000,00
3 PVC dia. 15mm m1 5.825,00
4 PVC dia. 20mm m1 7.925,00
5 PVC Dia. 25mm m1 10.825,00
6 PVC Dia. 32mm m1 16.200,00
7 PVC Dia. 40mm m1 18.600,00
8 PVC Dia. 50mm m1 23.800,00
9 PVC Dia. 65mm m1 34.725,00
10 PVC Dia. 80mm m1 48.900,00
11 PVC Dia. 100mm m1 81.025,00
12 PVC Dia. 150mm m1 180.050,00
13 PVC Dia. 200mm m1 302.150,00
14 Ball Valve dia. 15mm bh 60.000,00
15 Ball Valve dia. 20mm bh 75.000,00
16 Ball Valve dia. 25mm bh 92.000,00
17 Ball Valve dia. 32mm bh 115.000,00
18 Ball Valve dia. 40mm bh 125.000,00
19 Clean Out dia. 50mm bh 9.000,00
20 Clean Out dia. 65mm bh 12.000,00
21 Clean Out dia. 80mm bh 15.000,00
22 Clean Out dia. 100mm bh 25.000,00
23 Roof drain dia. 80 mm bh 72.000,00
24 Rooftank kapasitas 1000 liter bh 1.650.000,00
25 Extract fan kapasitas 75 cfm unit 539.000,00
26 Exhaust Air Grille uk. 8" x8" bh 125.200,00
27 TL LED 2 x 16 Watt TKI/Inbow bh 730.000,00
28 Downlight LED 12 Watt bh 265.000,00
29 Downlight LED 15 Watt bh 281.400,00
30 Downlight LED 32 Watt bh 400.000,00
31 Baret LED 17 Watt bh 213.000,00
32 Saklar tunggal bh 16.500,00
33 Saklar ganda bh 20.190,00
34 Stop kontak bh 17.050,00
35 Kabel Tray 15 cm ( 150 x 100 ) m1 215.000,00
36 Pipa Conduit m1 3.500,00
37 BCC 50 mm m1 36.700,00
38 Kabel NYY 4 X 10 mm2 m1 67.000,00

III. HARGA UPAH PEKERJA


1 Pekerja OH 100.000,00
2 Tukang OH 120.000,00
3 Tukang Batu OH 120.000,00
4 Tukang Besi Profil OH 120.000,00
5 Tukang Cat OH 120.000,00
6 Tukang besi OH 120.000,00
7 Tukang Kayu OH 120.000,00
8 Kepala Tukang OH 140.000,00
9 Mandor OH 160.000,00
10 Tukang Gali OH 120.000,00
11 Tukang Tanam OH 120.000,00
12 Tukang Penyiraman OH 120.000,00