TIME LINE :

PEMASANGAN SENSOR FURNICE EXIT GAS TEMPERATURE (FEGT) PLTU REMBANG UNIT 20

Date : 15 Mei 2022


Perolehan Progres : 19% of 100%
Hari Kerja : 4 of 11
BULAN MEI 2022
BOBOT
NO NAMA KEGIATAN HARI KE 1 2 3 4 5 6 7 8 9 10 11 TOTAL
PEK. %
TANGGAL 12 13 14 15 16 17 18 19 20 27 28 PROGRES
HARI THU FRI SAT SUN MON TUE WED THU FRI FRI SAT

I. Persiapan : 99% 100%


1 Open Permit 1.0% 1 Hari 1%
89%
2 Safety Induction 2.0% 1 Hari 2%
83%
3 Preparation, Lansir Tools & Consumable ke Unit 5.0% 1 Hari 5%

II. Pelaksanaan Pekerjaaan :


58%
1 Fabrikasi pipa instrument & Fabrikasi support Sensor 25% 3 Hari 5% 6%
2 Pulling kabel & Isolasi kabel tray 25% 2 Hari 45%
3 Install Support Sensor & Instalation Sensor FEGT 25% 1 Hari
5 Tes Kebocoran Instrument Air (NDT Tes) & I/O Test 5% 2 Hari 33%
25%
III. Finishing 19%
16%
13%
1 Commissioning Test 10% 1 Hari 8%
2 Pembuangan Limbah Kerja 1% 1 Hari 1%
3 Penutupan Work Permit 1% 1 Hari ACTUAL TIMELINE
1 2 3 4 5 6 7 8 9 10 11

TOTAL 100% 19%


JUMLAH PROGRES 1% 7% 5% 6% 0% 0% 0% 0% 0% 0% 0%
TOTAL ACUMULATIF PROGRES 1% 8% 13% 19%
TARGET PROGRESH 1% 8% 16% 25% 33% 45% 58% 83% 89% 99% 100%

Diketahui : Direview Oleh : Dibuat :


PT PJB PT Prima Layanan Suku Cadang PT. Meia Sinergi Utama
PLTU REMBANG UNIT 20 PLN SC

Djoko Sriyono Gunawan M. Rizki Setiawan


Pengawas Pekerjaan PIC Penanggung Jawab Pekerjaan
DAILY REPORT
PEMASANGAN SENSOR FURNICE EXIT GAS
TEMPERATURE (FEGT) PLTU REMBANG UNIT 20
PLTU REMBANG UNIT 20 BULAN APRIL/MEI - TH.2022

PO NO. : EMS08/DO/UJRBG/2022 HARI / TGL : 15 Mei 2022


TANGGAL : 21 Maret 2022 HARI KE : 4 of 11
LOKASI : PLTU REMBANG UNIT 20

1 JAM KERJA
Masuk Pkl 08.00 - Pulang 17.00

2 SAFETY ACTIVITY
Tidak ada Insiden (kondisii hujan)
3 MANPOWER
1). Project Leader 1
2). Safety Man 1
3). Electrikal 1 TOTAL MANPOWER : 3
PROGRESS
4 KEGIATAN HARI INI 5 RENCANA KEGIATAN BESOK

1 Fablikasi support sensor fablikasi line instrument air sama pulling kabel

NO URAIAN BOBOT RENCANA REALISASI SELISIH


1 Open Work Permit
Scofe Of Work : Pengurusan Dokumen Open Work Permit, Indaction Safety
K3, Lansir Tools & Consumable to site. 8.0% 8.0% 8.0% 0.0%

2 Pabrikasi Support
Scofe Of Work : Pabrikasi flange sensor, parikasi support pipa instrument
air dan support pipa conduit kabel. 25.0% 25.0% 11.0% 14.0%

3 Wairing Kabel Komunikasi


Scofe Of Work : Penarikan Kabel Komunikasi Dari Lokasi Pemasangan
Sensor FEGT Menuju Ruangan Control Room, Posisi Pemasangan 25.0%
Mengikuti Kabel Tray Eksisting, Pemasangan Pipa dan plexsible Counduit
4 Instalation Sensor FEGT
Scofe Of Work : Pemasangan Boddy Sensor FEGT di Dinding Boiler, Proses
Pengelasan, Proses Cover Insulation dengan Semen Api. 25.0%

5 Instalasi Electrikal Control


Scofe Of Work : Proses Singkron Instalasi kabel Komunikasi Menuju
Control Room (Dilakukan Oleh Team PT MSU).
6 Commisoning Test 10.0%
7 Tes kebocoran instrument air & NDT Penetrant Test. 5.0%
8 Penutupan Work Permit 2.0%
TOTAL 100.0% 19.0%

6 CATATAN : Safety Induction dilakukan Selasa 14 Desember 2021 Pukul 10:00 di gedung akademi PJB

Mengetahui Direview Oleh: Dilaporkan Oleh


PT PJB PT PRIMA LAYANAN SUKU PT MEIA SINERGI UTAMA
PLTU REMBANG UNIT 20 CADANG (PLN SC)

Djoko Sriyono Gunawan M. Rizki Setiawan


Pengawas Pekerjaan PIC Penanggung Jawab Pekerjaan
DAILY REPORT
PEMASANGAN SENSOR FURNICE EXIT GAS
TEMPERATURE (FEGT) PLTU REMBANG UNIT 20
PLTU REMBANG UNIT 20 BULAN MEI - TH.2022

PO NO. : EMS08/DO/UJRBG/2022 HARI / TGL : 15 Mei 2022


TANGGAL : 21 Maret 2022 HARI KE : 4 of 11
LOKASI : PLTU REMBANG UNIT 20

Mengetahui Direview Oleh : Dilaporkan Oleh


PT PJB PT PRIMA LAYANAN SUKU PT MEIA SINERGI UTAMA
PLTU REMBANG UNIT 20 CADANG (PLN SC)

Djoko Sriyono Gunawan M. Rizki Setiawan


Pengawas Pekerjaan PIC Penanggung Jawab Pekerjaan