A ITEM PEKERJAAN
1 perizinan,security,dll by owner by owner
2 air/sumur sebagai sarana kerja by owner by owner
3 listrik/pln sebagai sarana kerja by ow ner by ow ner
4 bongkar atap m2 70 hanya jasa 25,000 1,750,000
5 bongkar plafon m2 70 hanya jasa 20,000 1,400,000
6 pasang rangka atap m2 107 baja ringan 0,75 non tasso 195,000 20,865,000
7 pasang penutup atap m2 107 spandex polos 0,3 130,000 13,910,000
8 pasang listplank m1 36 lisplank GRC 20cm 65,000 2,340,000
9 pasang karpus/nok m1 10 nok spandex 85,000 850,000
10 pasang plafon over stek m2 18 hollow 4x2,gypsum aplus 165,000 2,970,000
11 cat plafon over stek m2 18 cat vinilex 35,000 630,000
12 cat listplank m1 36 cat minyak avian/sejenis 45,000 1,620,000
13 pasang plafon m2 70 rangka hollow 4x2,gypsum aplus 165,000 11,550,000
14 cat plafon m2 70 cat vinilex 35,000 2,450,000
15 pembersihan area pasca kerja ls 1 mobil pick up 1,500,000 1,500,000
total 61,835,000