TOTAL Rp -
PPN 11 % Rp -
TOTAL = (JUMLAH + PPN 11%) Rp -
DIBULATKAN Rp -
TERBILANG :
#VALUE!
REKAPITULASI TOTAL
RINCIAN RENCANA ANGGARAN BIAYA
PEMBANGUNAN GEDUNG SUBSTATION DAN INFRASTRUKTUR
PEKERJAAN UTILITAS ELEKTRIKAL
UNIVERSITAS ISLAM NEGERI SULTAN MAULANA HASANUDDIN BANTEN
(PROYEK SBSN 6 IN 1)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bowplank m' 165.60 - -
JUMLAH I.PEKERJAAN PERSIAPAN -
B. LANTAI DAK
1 Balok Type B1 (250x600)
- Besi D 16 Kg 1,289.74 - -
- Besi D 10 Kg 84.57 - -
- Besi D 10 (sengkang) Kg 627.44 - -
- Begisting Multiplex m2 95.70 - -
- Cor Beton K-300 m3 9.90 - -
2 Balok Type B2 (250x600)
- Besi D 16 Kg 644.87 - -
- Besi D 10 Kg 42.28 - -
- Besi D 10 (sengkang) Kg 313.72 - -
- Begisting Multiplex m2 47.85 - -
- Cor Beton K-300 m3 4.95 - -
3 Plat Lantai SB (t=130mm)
- Besi P8 Dobel Layer Kg 1,869.60 - -
- Begisting Multiplex m2 90.00 - -
- Cor Beton K-300 m3 11.70 - -
JUMLAH B. LANTAI DAK -
DASAR PERHITUNGAN
PPN 3,600,000,000.00
PATOKAN 0.90909090909 x 3,600,000,000.00 3,272,727,272.73 (NILAI PROYEK DIKALIKAN PPN 11%)
327,272,727.27
PROSENTASE
NILAI PROYEK JKK + JKM NILAI PROYEK NILAI BPJS (JKK+JKM)
100 JUTA 0.24% x 100,000,000.00 240,000.00
400 JUTA 0.19% x 400,000,000.00 760,000.00
500 JUTA - 1 MILYAR 0.15% x 500,000,000.00 750,000.00
1 MILYAR - 5 MILYAR 0.12% x 4,000,000,000.00 4,800,000.00
> 5 MILYAR 0.10% x - 1,727,272,727.27 (1,727,272.73) +
4,822,727.27
71,826,508,000.00
RINCIAN RENCANA ANGGARAN BIAYA
PEMBANGUNAN GEDUNG SUBSTATION DAN INFRASTRUKTUR
(PROYEK SBSN 6 IN 1)
PROJECT :
LOCATION :
P PANEL
I SUB STATION
1 LVMDP-D CAKRA RAYA TEK.
a Material/Components :
- Cubicle complete with components CRT 1.000 unit 0.00 0.00
- Base/Foundation 1.00 ls - 0.00
0.00
b Transportation
- From Jakarta 1.152 m3 0.00 0.00
0.00
c Insurance - % 0.00
0.00
d Fixing Cost :
- Foreman 0.120 man/day 0.00 0.00
- Chief Electrician 0.400 man/day 0.00 0.00
- Electrician 4.000 man/day 0.00 0.00
- Labour 8.000 man/day 0.00 0.00
0.00
c Insurance - % 0.00
0.00
d Fixing Cost :
- Foreman 0.120 man/day 0.00 0.00
- Chief Electrician 0.400 man/day 0.00 0.00
- Electrician 4.000 man/day 0.00 0.00
- Labour 8.000 man/day 0.00 0.00
0.00
c Insurance - % 0.00
0.00
d Fixing Cost :
lv-paneln(ELEC) Page : 11 of 40
UNIT PRICE TOTAL PRICE
NO / CODE DESCRIPTION REFERENCE QUANTITY UNIT
(RP) (RP)
- Foreman 0.060 man/day 0.00 0.00
- Chief Electrician 0.200 man/day 0.00 0.00
- Electrician 2.000 man/day 0.00 0.00
- Labour 4.000 man/day 0.00 0.00
0.00
4 PP/LP-PH.B
a Material/Components :
- Cubicle complete with components CRT 1.000 set 0.00 0.00
- Base/Foundation 1.000 ls - 0.00
0.00
b Transportation
- From Jakarta 0.110 m3 0.00 0.00
0.00
c Insurance - % 0.00
0.00
d Fixing Cost :
- Foreman 0.060 man/day 0.00 0.00
- Chief Electrician 0.200 man/day 0.00 0.00
- Electrician 2.000 man/day 0.00 0.00
- Labour 4.000 man/day 0.00 0.00
0.00
5 PP/LP-PH.D
a Material/Components :
- Cubicle complete with components CRT 1.000 set 0.00 0.00
- Base/Foundation 1.000 ls - 0.00
0.00
b Transportation
- From Jakarta 0.110 m3 0.00 0.00
0.00
c Insurance - % 0.00
0.00
d Fixing Cost :
- Foreman 0.060 man/day 0.00 0.00
- Chief Electrician 0.200 man/day 0.00 0.00
- Electrician 2.000 man/day 0.00 0.00
- Labour 4.000 man/day 0.00 0.00
0.00
6 PP/LP-PH.K
a Material/Components :
- Cubicle complete with components CRT 1.000 set 0.00 0.00
- Base/Foundation 1.000 ls - 0.00
0.00
b Transportation
- From Jakarta 0.110 m3 0.00 0.00
0.00
c Insurance - % 0.00
0.00
d Fixing Cost :
- Foreman 0.060 man/day 0.00 0.00
- Chief Electrician 0.200 man/day 0.00 0.00
lv-paneln(ELEC) Page : 12 of 40
UNIT PRICE TOTAL PRICE
NO / CODE DESCRIPTION REFERENCE QUANTITY UNIT
(RP) (RP)
- Electrician 2.000 man/day 0.00 0.00
- Labour 4.000 man/day 0.00 0.00
0.00
lv-paneln(ELEC) Page : 13 of 40
BREAKDOWN COST
PROJECT :
LOCATION :
MV MV CUBICLE
I SUB STATION
MVMDP - K
1 Panel MVMDP-K ABB
a Material/Components :
- Panel MVMDP-K 1.000 set 0.00 0.00
- Base/Foundation 1.00 ls 0.00 0.00
0.00
b Transportation
- From Jakarta 1.152 m3 0.00 0.00
0.00
c Insurance - % 0.00
0.00
d Fixing Cost :
- Foreman 1.200 man/day 0.00 0.00
- Chief Electrician 4.000 man/day 0.00 0.00
- Electrician 2.000 man/day 0.00 0.00
- Labour 8.000 man/day 0.00 0.00
0.00
2 MVMDP - B ABB
Panel MVMDP-B
a Material/Components :
- MVMDP - B 1.000 set 0.00 0.00
- Base/Foundation 1.000 ls 0.00 0.00
0.00
b Transportation
- From Jakarta 0.110 m3 0.00 0.00
0.00
c Insurance - % 0.00
0.00
d Fixing Cost :
- Foreman 1.200 man/day 0.00 0.00
- Chief Electrician 4.000 man/day 0.00 0.00
- Electrician 2.000 man/day 0.00 0.00
- Labour 8.000 man/day 0.00 0.00
0.00
3 MVMDP - D ABB
Panel MVMDP-D
a Material/Components :
- MVMDP - D 1.000 set 0.00 0.00
- Base/Foundation 1.000 ls 0.00 0.00
c Insurance - % 0.00
0.00
d Fixing Cost :
- Foreman 1.200 man/day 0.00 0.00
- Chief Electrician 4.000 man/day 0.00 0.00
- Electrician 2.000 man/day 0.00 0.00
- Labour 8.000 man/day 0.00 0.00
0.00
c Insurance - % 0.00
0.00
d Fixing Cost :
- Foreman 1.200 man/day 0.00 0.00
- Chief Electrician 4.000 man/day 0.00 0.00
- Electrician 2.000 man/day 0.00 0.00
- Labour 8.000 man/day 0.00 0.00
0.00
1 Transformator Dry Type Cast Resin Transformer CU Cu, 250 kVA, 20 kV - 380 Volt lengkap dengan houseng, Install, peralatan bantu, dan accessories.
a Material/Components :
- Transformator Dry Type Cast Resin Transformer CU 1.000 set - 0.00
- Base/Foundation 1.000 ls 0.00 0.00
0.00
b Transportation
- From Jakarta 0.048 m3 0.00 0.00
0.00
c Insurance - % 0.00
0.00
d Fixing Cost :
- Foreman 0.050 man/day 0.00 0.00
- Chief Electrician 0.500 man/day 0.00 0.00
- Electrician 1.000 man/day 0.00 0.00
- Labour 2.000 man/day 0.00 0.00
0.00
SUB DIVISION :
Unit Price
No./Code Description Reference Quantity Unit
(Rp.)
R Raceway
R.I Ladder Type SLW
R.I.3 Lader 600x100 mm & Fittings DS TRAY
R.I.3.1 Straight Ladder
a Material :
- Straight Ladder 1.00 meter 0.00
b Transportation
From Jakarta 8.95 kg
c Insurance - %
d Fixing Cost :
- Foreman 0.02 man/day 0.00
- Chief Electrician 0.02 man/day 0.00
- Electrician 0.19 man/day 0.00
- Worker 0.38 man/day 0.00
Sub Total
e Profit & Overhead 10.00 %
Total
Rounded
TOTAL PRICE
(Rp.)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
BREAKDOWN COST
PROJECT :
LOCATION :
SUB DIVISIO :
A. DAFTAR UPAH
1 Pekerja Rp - hari
2 Tukang pipa Rp - hari
3 Tukang listrik Rp - hari
4 Tukang AC Rp - hari
5 Kepala tukang AC Rp - hari
6 Kepala tukang listrik Rp - hari
7 Kepala tukang pipa Rp - hari
8 Mandor Rp - hari
PEKERJAAN ELEKTRIKAL
B. PEKERJAAN KABEL
1 Kabel N2XSEbY 3 x 150 mm2 Rp - m¹
2 Kabel N2XSY 1 x 70 mm2 Rp - m¹
3 Kabel NYA 1 x 5 mm2 Rp - m'
4 Kabel NYA 1 x 25 mm2 Rp - m'
5 Kabel NYA 1 x 120 mm2 Rp - m'
6 Kabel NYM 3 x 2,5 mm2 Rp - m'
7 Kabel NYM 3 x 4 mm2 Rp - m'
8 Kabel NYY 1 x 185 mm2 Rp - m'
9 Kabel NYY 1 x 240 mm2 Rp - m'
10 Kabel NYY 1 x 150 mm2 Rp - m'
11 Kabel NYY 2 x 1,5 mm2 Rp - m'
12 Kabel NYY 4 x 6 mm2 Rp - m'
13 Kabel NYY 4 x 50 mm2 Rp - m'
18 Galian, Urugan & Pelindung kabel/Sparing Rp - m'
NO. URAIAN SAT INDEK HARGA SATUAN JUMLAH HARGA TOTAL HARGA
1 UNIT PP OT 1 Phase, 10 KVA, with fault locator (88 MCB), Type Test Standar Rp -
1 INCLUDE : unit 1.0000 Rp - Rp - EFEKTIF BEKE
Panel Box (Sistem Prisma M) ###
- Dimensi : 2100 x 600 x 600mm ###
- Family : Prisma M (Free Standing) RUMUS :
Power Incomer and TN Earting Zone
Analisa Harga Satuan Elektrikal - page 23 of 40
NO. URAIAN SAT INDEK HARGA SATUAN JUMLAH HARGA TOTAL HARGA
- LBS 3P 63A Pekerja
- Quick Device Feeder, Multiclip Busbar, 80A Tukang
- MCB Multi 9, iC60L, C-Curve, 2P, 16A, isc 16kA Kepala tukan
- MCB Multi 9, iC60L, C-Curve, 2P, 2A, isc 16kA Mandor
- Residual Current Disconnector, iC60, 2P, 25A
- Universal Power Supply 150W, 24 VDC
- Terminal Block 24 mm
- Terminal Block 10 mm
- Pilot Lamp 230/250 V
- STI
- Tabung Sektring
Isolated earting system
- Current Transformer for 10 KVA
- MCB MULTI 9, IC60N, 2 Poles, 16A, C Curve
- Isolation Transformer with temperatur set Point
- Insulation Monitoring IMD Vigilohm IM20-H w/ Modbus RS485 Port
- Vigilohm Display HRP
- Fault ocator Vigilohm System with Separate Sensor
- Sensor Vigilohm
Other
- CU Busbar
- Wiring Aksesoris
2 Alat Bantu Penunjang lot 1.0000 Rp - Rp -
3 Tenaga Kerja :
Pekerja hari orang 0.0432 Rp - Rp -
Tukang Listrik hari orang 0.0864 Rp - Rp -
Kepala Tukang listrik hari orang 0.0086 Rp - Rp -
Mandor hari orang 0.0043 Rp - Rp -
Jumlah Rp -
Keuntungan 10% Rp -
Total = Jumlah+(Keuntungan 10%) Rp -
1 UNIT PP OT 1 Phase, 10 KVA, with fault locator (80 MCB), Type Test Standar Rp -
1 INCLUDE : unit 1.0000 Rp - Rp - EFEKTIF BEKE
Panel Box (Sistem Prisma M) ###
- Dimensi : 2100 x 600 x 600mm ###
- Family : Prisma M (Free Standing) RUMUS :
Power Incomer and TN Earting Zone
- LBS 3P 63A Pekerja
- Quick Device Feeder, Multiclip Busbar, 80A Tukang
- MCB Multi 9, iC60L, C-Curve, 2P, 16A, isc 16kA Kepala tukan
- MCB Multi 9, iC60L, C-Curve, 2P, 2A, isc 16kA Mandor
- Residual Current Disconnector, iC60, 2P, 25A
- Universal Power Supply 150W, 24 VDC
- Terminal Block 24 mm
- Terminal Block 10 mm
- Pilot Lamp 230/250 V
- STI
- Tabung Sektring
Isolated earting system
- Current Transformer for 10 KVA
- MCB MULTI 9, IC60N, 2 Poles, 16A, C Curve
- Isolation Transformer with temperatur set Point
- Insulation Monitoring IMD Vigilohm IM20-H w/ Modbus RS485 Port
- Vigilohm Display HRP
- Fault ocator Vigilohm System with Separate Sensor
- Sensor Vigilohm
Other
- CU Busbar
- Wiring Aksesoris
2 Alat Bantu Penunjang lot 1.0000 Rp - Rp -
3 Tenaga Kerja :
Pekerja hari orang 0.0432 Rp - Rp -
Tukang Listrik hari orang 0.0864 Rp - Rp -
Kepala Tukang listrik hari orang 0.0086 Rp - Rp -
Mandor hari orang 0.0043 Rp - Rp -
Jumlah Rp -
Keuntungan 10% Rp -
Total = Jumlah+(Keuntungan 10%) Rp -
1 UNIT PP OT 1 Phase, 10 KVA, with fault locator (72 MCB), Type Test Standar Rp -
1 INCLUDE : unit 1.0000 Rp - Rp - EFEKTIF BEKE
Panel Box (Sistem Prisma M) ###
- Dimensi : 2200 x 1200 x 600mm ###
- Family : Prisma M (Free Standing) RUMUS :
Power Incomer and TN Earting Zone
- LBS 4P 63A Pekerja
- Quick Device Feeder, Multiclip Busbar, 80A Tukang
- MCB Multi 9, iC60L, C-Curve, 2P, 16A, isc 16kA Kepala tukan
- MCB Multi 9, iC60L, C-Curve, 2P, 2A, isc 16kA Mandor
- Residual Current Disconnector, iC60, 2P, 25A
- Universal Power Supply 150W, 24 VDC
- Terminal Block 24 mm
- Terminal Block 10 mm
- Pilot Lamp 230/250 V
- STI
- Tabung Sektring
Isolated earting system
- Current Transformer for 10 KVA
- MCB MULTI 9, IC60N, 2 Poles, 16A, C Curve
- Isolation Transformer with temperatur set Point
- Insulation Monitoring IMD Vigilohm IM20-H w/ Modbus RS485 Port
- Vigilohm Display HRP
- Fault ocator Vigilohm System with Separate Sensor
- Sensor Vigilohm
Other
- CU Busbar
- Wiring Aksesoris
2 Alat Bantu Penunjang lot 1.0000 Rp - Rp -
3 Tenaga Kerja :
Pekerja hari orang 0.0432 Rp - Rp -
Tukang Listrik hari orang 0.0864 Rp - Rp -
Kepala Tukang listrik hari orang 0.0086 Rp - Rp -
Mandor hari orang 0.0043 Rp - Rp -
Jumlah Rp -
Keuntungan 10% Rp -
Total = Jumlah+(Keuntungan 10%) Rp -
1 UNIT PP OT 1 Phase, 10 KVA, with fault locator (56 MCB), Type Test Standar Rp -
Analisa Harga Satuan Elektrikal - page 24 of 40
NO. URAIAN SAT INDEK HARGA SATUAN JUMLAH HARGA TOTAL HARGA
1 INCLUDE : unit 1.0000 Rp - Rp - EFEKTIF BEKE
Panel Box (Sistem Prisma M) ###
- Dimensi : 2200 x 1200 x 600mm ###
- Family : Prisma M (Free Standing) RUMUS :
Power Incomer and TN Earting Zone
- LBS 4P 63A Pekerja
- Quick Device Feeder, Multiclip Busbar, 80A Tukang
- MCB Multi 9, iC60L, C-Curve, 2P, 16A, isc 16kA Kepala tukan
- MCB Multi 9, iC60L, C-Curve, 2P, 2A, isc 16kA Mandor
- Residual Current Disconnector, iC60, 2P, 25A
- Universal Power Supply 150W, 24 VDC
- Terminal Block 24 mm
- Terminal Block 10 mm
- Pilot Lamp 230/250 V
- STI
- Tabung Sektring
Isolated earting system
- Current Transformer for 10 KVA
- MCB MULTI 9, IC60N, 2 Poles, 16A, C Curve
- Isolation Transformer with temperatur set Point
- Insulation Monitoring IMD Vigilohm IM20-H w/ Modbus RS485 Port
- Vigilohm Display HRP
- Fault ocator Vigilohm System with Separate Sensor
- Sensor Vigilohm
Other
- CU Busbar
- Wiring Aksesoris
2 Alat Bantu Penunjang lot 1.0000 Rp - Rp -
3 Tenaga Kerja :
Pekerja hari orang 0.0432 Rp - Rp -
Tukang Listrik hari orang 0.0864 Rp - Rp -
Kepala Tukang listrik hari orang 0.0086 Rp - Rp -
Mandor hari orang 0.0043 Rp - Rp -
Jumlah Rp -
Keuntungan 10% Rp -
Total = Jumlah+(Keuntungan 10%) Rp -
1 UNIT PP OT 1 Phase, 10 KVA, with fault locator (40 MCB), Type Test Standar Rp -
1 INCLUDE : unit 1.0000 Rp - Rp - EFEKTIF BEKE
Panel Box (Sistem Prisma M) ###
- Dimensi : 2200 x 1200 x 600mm ###
- Family : Prisma M (Free Standing) RUMUS :
Power Incomer and TN Earting Zone
- LBS 4P 63A Pekerja
- Quick Device Feeder, Multiclip Busbar, 80A Tukang
- MCB Multi 9, iC60L, C-Curve, 2P, 16A, isc 16kA Kepala tukan
- MCB Multi 9, iC60L, C-Curve, 2P, 2A, isc 16kA Mandor
- Residual Current Disconnector, iC60, 2P, 25A
- Universal Power Supply 150W, 24 VDC
- Terminal Block 24 mm
- Terminal Block 10 mm
- Pilot Lamp 230/250 V
- STI
- Tabung Sektring
Isolated earting system
- Current Transformer for 10 KVA
- MCB MULTI 9, IC60N, 2 Poles, 16A, C Curve
- Isolation Transformer with temperatur set Point
- Insulation Monitoring IMD Vigilohm IM20-H w/ Modbus RS485 Port
- Vigilohm Display HRP
- Fault ocator Vigilohm System with Separate Sensor
- Sensor Vigilohm
Other
- CU Busbar
- Wiring Aksesoris
2 Alat Bantu Penunjang lot 1.0000 Rp - Rp -
3 Tenaga Kerja :
Pekerja hari orang 0.0432 Rp - Rp -
Tukang Listrik hari orang 0.0864 Rp - Rp -
Kepala Tukang listrik hari orang 0.0086 Rp - Rp -
Mandor hari orang 0.0043 Rp - Rp -
Jumlah Rp -
Keuntungan 10% Rp -
Total = Jumlah+(Keuntungan 10%) Rp -
1 UNIT PP OT 1 Phase, 10 KVA, with fault locator (18 MCB), Type Test Standar Rp -
1 INCLUDE : unit 1.0000 Rp - Rp - EFEKTIF BEKE
Panel Box (Sistem Prisma M) ###
- Dimensi : 2200 x 1200 x 600mm ###
- Family : Prisma M (Free Standing) RUMUS :
Power Incomer and TN Earting Zone
- LBS 4P 63A Pekerja
- Quick Device Feeder, Multiclip Busbar, 80A Tukang
- MCB Multi 9, iC60L, C-Curve, 2P, 16A, isc 16kA Kepala tukan
- MCB Multi 9, iC60L, C-Curve, 2P, 2A, isc 16kA Mandor
- Residual Current Disconnector, iC60, 2P, 25A
- Universal Power Supply 150W, 24 VDC
- Terminal Block 24 mm
- Terminal Block 10 mm
- Pilot Lamp 230/250 V
- STI
- Tabung Sektring
Isolated earting system
- Current Transformer for 10 KVA
- MCB MULTI 9, IC60N, 2 Poles, 16A, C Curve
- Isolation Transformer with temperatur set Point
- Insulation Monitoring IMD Vigilohm IM20-H w/ Modbus RS485 Port
- Vigilohm Display HRP
- Fault ocator Vigilohm System with Separate Sensor
- Sensor Vigilohm
Other
- CU Busbar
- Wiring Aksesoris
2 Alat Bantu Penunjang lot 1.0000 Rp - Rp -
3 Tenaga Kerja :
Pekerja hari orang 0.0432 Rp - Rp -
Tukang Listrik hari orang 0.0864 Rp - Rp -
Kepala Tukang listrik hari orang 0.0086 Rp - Rp -
Mandor hari orang 0.0043 Rp - Rp -
Analisa Harga Satuan Elektrikal - page 25 of 40
NO. URAIAN SAT INDEK HARGA SATUAN JUMLAH HARGA TOTAL HARGA
Jumlah Rp -
Keuntungan 10% Rp -
Total = Jumlah+(Keuntungan 10%) Rp -
C. BAHAN KAYU
1 Kayu papan begisting kelas IV Rp - m³
2 Kayu 5/7 kelas IV Rp - m³
3 Kayu Kelas III Rp - m³
4 Multiplek 12 mm Rp - lbr
D. LAIN - LAIN
1 Air Rp - ltr
2 Paku Rp - kg
3 Minyak bekisiting Rp - ltr
4 Kawat beton Rp - kg
5 Paku biasa Rp - kg
6 Concrate Pump Rp - Hari
7 Perancah Scafolding Rp - m2
HARGA SATUAN
NO. URAIAN PEKERJAAN
TERPASANG
PEKERJAAN PERSIAPAN
1 1 m¹ Pengukuran dan pemasangan bowplank Rp -
2 1 ls Mobilisasi dan Demobilisasi Peralatan Bored Rp -
3 1 titik Axial test Reaction Pile/angkur (Kap. 330 ton) Rp -
4 1 titik Lateral test (Kap. 36 ton) Rp -
5 1 titik PDA Test Rp -
PEKERJAAN STRUKTUR
1 1 m³ Galian Tanah biasa sedalam 1 meter Rp -
2 1 m³ Galian tanah biasa sedalam 2 meter Rp -
3 1 m³ Galian tanah biasa sedalam 3 meter Rp -
4 1 m³ Urugan Pasir Urug Rp -
5 1 m³ Memasang Lantai Kerja Rp -
6 1 kg Memasang Besi Beton BJTP 24 Rp -
7 1 kg Memasang Besi Beton BJTD 42 Rp -
8 1 m² Memasang bekisting untuk kolom (3x Pakai) Rp -
9 1 m² Memasang bekisting untuk balok (3x Pakai) Rp -
10 1 m² Memasang bekisting untuk dinding (3x Pakai) Rp -
11 1 m² Memasang bekisting untuk plat lantai (3x Pakai) Rp -
12 1 m² Memasang bekisting untuk tangga Rp -
13 1 m² Memasang Begisting Batako Rp -
14 1 m³ Beton Ready mix f'c=25 Mpa Rp -
15 1 m³ Memasang Beton Site Mix K-175. slump 12±2 cm, w/c=0.66 Rp -
16 1 m³ Memasang Beton Site Mix K-250. slump 12±2 cm, w/c=0.56 Rp -
17 1 titik Pekerjaan Bobokan Kepala Bore Pile Ø800 Rp -
18 1 titik Pekerjaan Bobokan Kepala Strauss Pile Ø300 Rp -
19 1 m³ Mengurug kembali galian Rp -
20 1 m³ Memadatkan tanah 1 m2 tanah per 20 cm Rp -
21 1 m³ Mengurug pasir urug Rp -
22 1 m² Membuat Screed Beton + kawat ayam Rp -
23 1 m³ Memasang Pondasi Batu Kosong (Aanstamping) Rp -
C. BAHAN KAYU
1 Kayu Kelas III Rp - m³
D. BAHAN FINISHING
1 Plamur (1 Galon = 5 kg) Rp - kg
2 Cat weathershield (1 pail = @ 20 liter) Rp - kg
3 Cat dustrproof (1 pail = @ 20 liter) Rp - kg
4 Cat dasar interior (@1pail = 20 liter) Rp - kg
5 Cat dasar eksterior (@1pail = 20 liter) Rp - kg
6 Cat dasar solvent based / sealer (1 pail = @ 20 liter) Rp - kg
7 Cat acrylic enamel (1 pail = @ 20 liter) Rp - kg
E. LAIN - LAIN
1 Air Rp - ltr
2 Paku Rp - kg
3 Minyak bekisiting Rp - ltr
4 Kawat beton Rp - kg
5 Dump truck 3-4 ton Rp - jam
6 Excavator 80-140 HP Kap. 0,9 m3 Rp - jam
7 Water Tank Truck 3000-4000 l Rp - jam
8 Motor Grader > 100 HP Rp - jam
9 Vibrator Roller kap. 5-8 Ton Rp - jam
Tenaga Kerja :
1 Pekerja L.01 oh 0.0100 Rp - Rp -
2 Tukang batu L.02 oh 0.0200 Rp - Rp -
3 Kepala tukang L.03 oh 0.0010 Rp - Rp -
4 Mandor L.04 oh 0.0010 Rp - Rp -
Jumlah harga persatuan pekerjaan Rp -
Keuntungan+Over head 10% Rp -
Total = Jumlah+(Keuntungan+Over head 10%) Rp -
9 1 m' Pemasangan Opening Pintu dan Jendela Semen Biasa Rp -
Bahan:
1 Membuat plesteran semen biasa m' 0.1650 Rp - Rp -
2 Membuat acian semen biasa m' 0.1650 Rp - Rp -
Jumlah harga persatuan pekerjaan Rp -
10 1 m' Pemasangan Ban-Banan 10 cm Rp -
Bahan:
1 Membuat plesteran semen biasa m' 0.5500 Rp - Rp -
2 Membuat acian semen biasa m' 0.5500 Rp - Rp -
Jumlah harga persatuan pekerjaan Rp -
11 1 m' Pemasangan Kolom Praktis 11/11 cm Rp -
1 Kayu kelas III m³ 0.0020 Rp - Rp -
2 Paku 5 cm - 12 cm kg 0.0100 Rp - Rp -
3 Minyak bekisting ltr besi 8
4 Besi beton polos kg 4.8671 Rp - Rp -
5 Kawat beton kg 0.4500 Rp - Rp -
6 Semen portland kg 4.0000 Rp - Rp -
7 Pasir beton m³ 0.0060 Rp - Rp -
8 kerikil m³ 0.0090 Rp - Rp -
Tenaga Kerja:
1 Pekerja L.01 oh 0.1800 Rp - Rp -
2 Tukang batu L.02 oh 0.0200 Rp - Rp -
3 Tukang kayu L.02 oh 0.0200 Rp - Rp -
4 Tukang besi L.02 oh 0.0200 Rp - Rp -
5 Kepala tukang L.03 oh 0.0060 Rp - Rp -
6 Mandor L.04 oh 0.0090 Rp - Rp -
Jumlah harga persatuan pekerjaan Rp -
Keuntungan+Over head 10% Rp -
Total = Jumlah+(Keuntungan+Over head 10%) Rp -
12 1 m' Pemasangan Balok Praktis 11/15 cm Rp -
1 Kayu kelas III m³ 0.0030 Rp - Rp -
2 Paku 5 cm - 12 cm kg 0.0200 Rp - Rp -
3 Minyak bekisting ltr ###
4 Besi beton polos kg 3.5182 Rp - Rp -
5 Kawat beton kg 0.0500 Rp - Rp -
6 Semen portland kg 5.5000 Rp - Rp -
7 Pasir beton m³ 0.0090 Rp - Rp -
8 kerikil m³ 0.0150 Rp - Rp -
Tenaga Kerja:
1 Pekerja L.01 oh 0.2970 Rp - Rp -
2 Tukang batu L.02 oh 0.0330 Rp - Rp -
3 Tukang kayu L.02 oh 0.0330 Rp - Rp -
4 Tukang besi L.02 oh 0.0330 Rp - Rp -
5 Kepala tukang L.03 oh 0.0100 Rp - Rp -
6 Mandor L.04 oh 0.0150 Rp - Rp -
Jumlah harga persatuan pekerjaan Rp -
Keuntungan+Over head 10% Rp -
Total = Jumlah+(Keuntungan+Over head 10%) Rp -
13 1 m³ Membuat Beton Site Mix K-175. slump 12±2 cm, w/c=0.66 Rp -
Bahan: ###
1 Semen kg 326.0000 Rp - Rp -
2 Pasir Beton m³ 0.5630 Rp - Rp -
3 Batu Split 1/2 m³ 0.7097 Rp - Rp -
Tenaga Kerja: