6,176,062,654

1 Pekerjaan Dinding Area Parkir Harga sat Bobot


- Dinding pasangan batako 7/20/40 cm 36.00 M2 111,442.10 4,011,915.60 0.065
- Plesteran dinding 72.00 M2 73,392.22 5,284,239.84 0.086
- Batu Alam 30.24 M2 300,008.50 9,072,257.04 0.147
- Cat Tembok Interior 41.76 M2 46,946.35 1,960,479.58 0.032
Total 20,328,892.06 0.329

Plint keramik 92.49 M2 86,434.70 7,994,172.53 0.13

RUMAH GENSET
A PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 13.5 M2 19,800.00 267,300.00 0.00
2 Pengukuran dan pemasangan bowplank 15 M 110,578.60 1,658,679.00 0.03
B PEKERJAAN PONDASI
1 Galian tanah pondasi 6.776 M3 90,750.00 614,922.00 0.01
2 Pasir alas pondasi T=5 cm 0.33 M3 192,060.00 63,379.80 0.00
3 Lantai kerja beton K.100 T=5 cm 0.33 M3 963,070.89 317,813.40 0.01
4 Cerucuk D.10 cm panjang 4 meter 44 Btg 12,000.00 528,000.00 0.01
5 Pemancangan cerucuk 88 M 1,800.00 158,400.00 0.00
6 Urugan kembali tanah galian 4.4044 M3 66,000.00 290,690.40 0.00
7 Pasangan batu spesi 13 2.75275 M3 1,092,305.50 3,006,843.97 0.05
8 Plesteran pasangan batu T.1,5 cm spesi 13 0.55 M2 73,392.22 40,365.72 0.00
C PEKERJAAN STRUKTUR BETON BERTULANG
1 Balok Sloof uk. 15/25 cm
- Beton K.300 0.165 M3 1,174,256.57 193,752.33 0.00
- Tulangan utama 4 D.8 mm U24 17.38 Kg 16,188.15 281,350.05 0.00
- Beugel D.8 U24 20.1845 Kg 16,188.15 326,749.71 0.01
- Bekisting sloof 2.145 M2 234,828.00 503,706.06 0.01
- Plesteran T.1,5 cm spesi 1:3 (Keliling bangunan) 1.65 M2 73,392.22 121,097.16 0.00
7 Kolom praktis uk.10/10 cm
- Beton K.300 0.11 M3 1,174,256.57 129,168.22 0.00
- Tulangan utama 4 D.8 mm U32 17.38 Kg 16,188.15 281,350.05 0.00
- Beugel D.8 U24 17.064 Kg 16,188.15 276,234.59 0.00
- Bekisting kolom 2.86 M2 274,654.05 785,510.58 0.01
8 Ring Balok uk. 10/15 cm - 0.00
- Beton K.300 0.165 M3 1,174,256.57 193,752.33 0.00
- Tulangan utama 4 D.8 mm U32 17.38 Kg 16,188.15 281,350.05 0.00
- Beugel D.8 U24 15.879 Kg 16,188.15 257,051.63 0.00
- Bekisting balok 2.2 M2 282,499.80 621,499.56 0.01
9 Plat dak beton T.10 cm - 0.00
- Bekisting plat dak 33.152 M2 301,054.05 9,980,543.87 0.16
- Pembesian wiremesh M7 (1 lapis) 197.4912 Kg 15,760.25 3,112,510.68 0.05
- Plastik cor beton 47.36 Kg 1,700.00 80,512.00 0.00
- Beton K.300 T.10 cm 4.736 M3 1,174,256.57 5,561,279.11 0.09
- Plesteran T.1,5 cm spesi 13 94.72 M2 73,392.22 6,951,711.08 0.11
- Pekerjaan acian dinding 94.72 M2 44,385.00 4,204,147.20 0.07
10 Water proofing 47.36 M2 62,513.00 2,960,615.68 0.05
D PEKERJAAN LANTAI
1 Pasir urug bawah lantai 0.968 M3 192,060.00 185,914.08 0.00
2 Pembesian wiremesh M7 (1 lapis) 18.348 Kg 15,760.25 289,169.07 0.00
3 Plastik cor beton 4.4 M2 3,400.00 14,960.00 0.00
4 Lantai Beton K.300 T.8 cm 0.5776 M3 1,250,011.74 722,006.78 0.01
5 Pondasi dudukan Mesin Genset
- Cerucuk D.10 cm panjang 4 meter 12 Btg 12,000.00 144,000.00 0.00
- Pemancangan cerucuk 48 M 1,800.00 86,400.00 0.00
- Pembesian wiremesh M7 (2 lapis) 16.68 Kg 15,760.25 262,880.97 0.00
- Pasir urug bawah lantai 0.2 M3 192,060.00 38,412.00 0.00
- Lantai kerja T.5 cm 0.1 M3 963,070.89 96,307.09 0.00
- Beton K.300 1.4 M3 1,250,011.74 1,750,016.44 0.03
- Bekisting 2.94 M2 234,828.00 690,394.32 0.01
6 Ramp naik dan turun rumah mesin genset
- Cerucuk D.10 cm panjang 4 meter 9 Btg 12,000.00 108,000.00 0.00
- Pemancangan cerucuk 27 M 1,800.00 48,600.00 0.00
- Pembesian wiremesh M7 (2 lapis) 12.7602 Kg 15,760.25 201,103.94 0.00
- Pasir urug bawah lantai 0.15 M3 192,060.00 28,809.00 0.00
- Lantai kerja T.5 cm 0.075 M3 963,070.89 72,230.32 0.00
- Beton K.300 0.225 M3 1,250,011.74 281,252.64 0.00
- Bekisting 0.21 M2 234,828.00 49,313.88 0.00
- Plesteran lantai T.1,5 cm 1.53 M2 73,392.22 112,290.10 0.00
E PEKERJAAN DINDING
1 Dinding pasangan batako 7/20/40 cm 3 M2 111,442.10 334,326.30 0.01
2 Plesteran dinding T.1,5 cm spesi 13 6 M2 73,392.22 440,353.32 0.01
4 Besi teralis hollow 5.4 M2 131,175.00 708,345.00 0.01
F PEKERJAAN PINTU DAN VENTILASI
3 Pintu teralis hollow 2 Bh 1,250,000.00 2,500,000.00 0.04
G PEKERJAAN PENGECATAN
1 Cat tembok eksterior (Weather shield) 27.4 M2 52,666.35 1,443,057.99 0.02
2 Cat tembok interior 10 M2 46,946.35 469,463.50 0.01
Total 55,127,892.97 0.89

Total 28,323,064.59 0.46

PERIJINAN