I Volume Galian dan Timbunan

Volume
No. STA. Luas Galian (m2) Luas Timbunan (m2)
Galian (m3) Timbunan (m3)
1 STA. 0+000 1249.995 0 28993 0
2 STA. 0+100 304.45875 8.505 2178.35 340.2
3 STA. 0+200 0 106.7 0 4268
4 STA. 0+300 229.95 0 9198 0
5 STA. 0+400 463.39975 0 96877.86 0
6 STA. 0+500 267.11 72.5 175323.2 2900
7 STA. 0+600 0 855.302 0 9124.696
8 STA. 0+700 0 1439.688 0 6450.56
9 STA. 0+800 0 300 0 6000
Total 2514.9135 2782.695 312570 29083.456
kondisi Ls 390713.0125 36354.32
kondisi BM 325594.177083 30295.27
II Produktifitas alat
1 BACKHOE KOMATSU PC300-1
Bucket ƒactor untuk tanah lempung keras = 0,80
Kapasitas bucket PC 220-1 = 1,20 m3 peres
    JM = 0,75 (baik/baik) 25 detik =
kondisi sedang → t1 = 13 detik
swing 90o → t2 = 7 detik

ditumpuk terlebih dahulu → t3 = 8 detik


T =TI +2T2 +T3
T= 35
= 0.58 menit
Produktifitas = 60 X BC X JM X BF
T
= 74.48275862069 m3/hari
Site out per hari = 521.38 hari
koef. Alat = 1/Q = 1.34259259259259
Waktu kerja yang dibutuhkan = volume galian 749.383 hari
produksi per hari
jumlah alat yang dibutuhkan = waktu yg dibutuhkan 24.98 25 unit
waktu pelaksanaan

2 Bulldozer (komatsu D65WX-18)


L: 3.58 m
H: 1.425 m
Faktor Blade (a) = 0.9
Efisiensi Kerja(E) = 0.75
Jarak Gusur (D) = 50 m
kec. Maju (F) = 5.533 km/jam = 92.2167 m/menit
kec. Mundur R= 6.633 km/jam = 110.55 m/menit
Waktu ganti perseneling
0.10 menit
(Z) =
Produksi per siklus q =L x H^2 x a = 6.54 m3
Cm = D D (+)Z
x
F R
0.542 x 0.452 0.10
0.345 menit
q x 60 x E x faktor
Produktifitas Bulldozer Q=
konversi tanah = 1066.03 m3/jam
CT
koef. Alat= 1/Q = 0.0938057562878253
site out per hari = 7462.23 m3/hari
waktu kerja yang
dibutuhkan volume galian = 52.359 hari
site out put per
hari
jumlah alat yg waktu kerja yg
dibutuhkan = dibutuhkan = 0.58 1 unit
waktu
pelaksanaan

3 Wheel Loader (996D CAT)


kap. Bucket = 3.1 m3
metode pemuatan silang : (cross loading)
jarak angkut : 20 m
tipe material butiran : (12 - 20) mm
berat : 1300 kg/m3
stockpile : 6m
Factor bucket : 0.9
CT :
basic ct : 0.5 menit
stockpile : 0 menit
material 12-20mm -0.03 menit
operasi tetap : -0.05 menit
truck sewa : 0.05 menit
0.47 menit
jumlah siklus/jam 127.66 siklus/jam
kap. Bucket = 3.1 m3 x 0.85 2.635 m3
x q x Factor Bucket x
produksi per jam ( Q) = 60 E = 295.62 m3/jam
CT
koef. Alat= 1/Q = 0.338270645305235
static tipping load : 12900 kg
kap. Angkat : 50% x 12900kg = 6450 kg
2.635m3 x
berat material :
1300kg/m3 3425.50 kg
berat material < kapasitas angkat => loader aman (tidak terguling)

hari kerja x
site out per hari = produksi per jam 2069.35 m3/hari

Waktu kerja yang Volume galian =


dibutuhkan = 188.81 hari
site out per hari

jumlah alat yang waktu kerja yg


dibutuhkan = dibutuhkan = 2.10 unit (dibulatkan jadi 2 unit)
waktu
pelaksanaan

4 Dump Truck
berat kosong : 20 ton
kapasitas : 9.8 m3
tahanan gelinding 60 kg/ton
bekerja dengan loader 3.1 m3
berkapasitas :
waktu siklus : 0.47 menit
berat tanah : 325594.17708333 kg/m3 (BM)
swell : 20 %
fill factor : 0.90
jarak angkut : 6000 m
effisiensi : 0.83

Berat material
kapasitas truck /
jumlah siklus loader / kap. Bucket x fill 2.845 3
truck (n) = factor =
muatan truck = 3 x 3.1 x 0.90 8.37 m3 ( tanah lepas)
Berat material = 8.37/1.2 x 481250 2271019.38515625 kg
2271.01938515625 ton
berat kosong = 20 ton
rimpul yg digunakan 20 ton x 60kg/ton 1200 kg
kecepatan truck = 33.3 km/jam (gigi 4)

berat total = 2291.0193851563 ton


rimpul yg digunakan 3376.72 x 60 = 137461.163109375 kg
kecepatan truck 5.1 km/jam (gigi 1)

Waktu Siklus :
waktu muat = n x Cm loader = 1.41 menit
waktu angkut = 6000 = 18.56 menit
323.3
waktu kembali= 6000 = 10.811 menit
555

waktu bongkar dan waktu tunggu = 1.15 menit


waktu mengambil posisi dimuati = 0.3 menit
waktu siklus = 32.23 menit

jumlah Dump Truck yang dibutuhkan (M)


M= 22.86 23 (dibulatkan)
jika M = 23
Produksi per jam
Q= q x 60 x E 297.46 m3/jam
xM =
Cm truck
koef. Alat = 1/Q
0.336178489877059
waktu hilang
M = 23 waktu muat = 1.41 menit x 23 = 32.43 menit
0.3 menit x 23 = 6.9 menit
waktu hilang waktu muat - waktu
loader = siklus 0.20 menit

5 Motor Grader
panjang blade : 3.1 m
lebar pembentukan 20 m
jalan :
panjang jalan : 6000 m
luas area perataan : 120000 m2
v, kecepatan maju : 5 km/jam 83.33 m/menit
sudut oprasi : 60 derajat
banyak haluan (n) : 10 kali
Efisiensi : 0.83
rencana lo awal: 0.20 m
lebar Jalan = lintasan
jumlah lintasan: 6.252 6 (dibulatkan)
(p. blade - lo)
panjang blade total = 7 x 3.1 = 18.6 meter
21.7 - 20 = -1.4 meter
lo = 1.7 / 7 = -0.233 meter
Menghitung Produktivitas
Le = sin (60) x 3.1 m = 2.68 m
Q' = (60 x V x (Le-Lo))= 87.40 m2/jam
n
Q= 73.11 x 0.83 72.54 m2/jam
koef. Alat = 1/Q 0.1378511758705
Menghitung Durasi
Durasi = vol. pekerjaan = 1654.21 jam
produktivitas x
jml. Alat 236.32 hari

6 Tandem Roller
lebar efektif (b) : 1.5 m
Faktor efisiensi : 0.83
v (kec. Rata-rata): 5 km/jam
n (jumlah lintasan) 10 lintasan
t (tebal hamparan) 0.8 m
volume pekerjaan 30295.27 m3

produktivitas Q : ((v x 1000) x b x t x


Fa) 498 m3/jam
n
koefisien alat/m3: 1:Q 0.2008 jam

Q x Jam kerja
volume dalam sehari = efektif 3486 m3/hari

volume yg
Lama waktu pekerjaan = direncanakan = 8.69 hari/alat
volume dalam
sehari

7 Vibrator Roller (sakai SV900D)


lebar drum : 2.15 m
diameter drum : 1.65 m
Efisiensi kerja (E): 0.75
v (kec. Operasi) : 1500 m/jam
lebar efektif pemadatan 0.2 m
(W) :
jumlah lintasan (n) : 5 lintasan
tebal lapisan (H) : 0.30 m

W x H x V x 1000 x
Produktivitas Q =
E= 18000 m3/jam
n
site out per hari = Q x jam kerja
efektif = 126000 m3/hari
KOEF= 0.0799826666667
jumlah vibrator roller volume yang unit
0.24 1
yang dibutuhkan = direncanakan = (dibulatkan)
site out per hari

8 Pemakaian Alat Water Tank


Wc (kebutuhan air/m3 0.07 m3
material padat) =
Factor efisiensi : 0.83
v (tangki air) : 4.00 m3
pa (kap. Pompa air) 200.00 liter/menit

produktivitas Q : pa x Fa x 60 = 142.286 m3/jam


(1000 x Wc)

koefisien alat/m3 = 1:Q 0.703 jam

volume dalam sehari = Q x Jam kerja


efektif = 996.00 m3/hari

Lama waktu pengerjaan Volume pekerjaan


= = 30.417 hari/alat
Volume dalam
sehari
Jumlah alat yang waktu pengerjaan
dibutuhkan = 1.01389781347613 1 unit
waktu pelaksanaan=

III Tenaga Kerja


1 Excavator
Tenaga = 4 Orang
Mandor = 1 orang
Koefisien tenaga
4 orang x 7 jam 0.376 JAM
Prod. AB
Koefisien mandor
1 orang x 7 jam 0.094 JAM
Prod. AB
Galian dan Timbunan
Tenaga = 6 Orang
Mandor = 1 orang
Koefisien tenaga
6 orang x 7 jam 0.564 JAM
Prod. AB
Koefisien mandor
1 orang x 7 jam 0.094 JAM
Prod. AB

2 Bulldozer
Tenaga = 4 Orang
Mandor = 1 orang
Koefisien tenaga
4 orang x 7 jam 0.026 JAM
Prod. AB
Koefisien mandor
1 orang x 7 jam 0.007 JAM
Prod. AB
Galian dan Timbunan
Tenaga = 6 Orang
Mandor = 1 orang
Koefisien tenaga
6 orang x 7 jam 0.894 JAM
Prod. AB
Koefisien mandor
1 orang x 7 jam 0.007 JAM
Prod. AB

3 Wheel Loader
Tenaga = 2 Orang
Mandor = 1 orang
Koefisien tenaga
2 orang x 7 jam 0.047 JAM
Prod. AB
Koefisien mandor
1 orang x 7 jam 0.024 JAM
Prod. AB
Galian dan Timbunan
Tenaga = 6 Orang
Mandor = 1 orang
Koefisien tenaga
6 orang x 7 jam 0.113 JAM
Prod. AB
Koefisien mandor
1 orang x 7 jam 0.024 JAM
Prod. AB

5 Motor Greder
Tenaga = 2 Orang
Mandor = 1 orang
Koefisien tenaga
4 orang x 7 jam 0.386 JAM
Prod. AB
Koefisien mandor
1 orang x 7 jam 0.096 JAM
Prod. AB

6 Vibrator Roller (sakai SV900D)


Tenaga = 2 Orang
Mandor = 1 orang
Koefisien tenaga
4 orang x 7 jam 0.002 JAM
Prod. AB
Koefisien mandor
1 orang x 7 jam 0.000 JAM
Prod. AB

7 Water Tank
Tenaga = 2 Orang
Mandor = 1 orang
Koefisien tenaga
2 orang x 7 jam 0.098 JAM
Prod. AB
Koefisien mandor
1 orang x 7 jam 0.049 JAM
Prod. AB

8 Tandem Roller
Tenaga = 2 Orang
Mandor = 1 orang
Koefisien tenaga
4 orang x 7 jam 0.056 JAM
Prod. AB
Koefisien mandor
1 orang x 7 jam 0.014 JAM
III. SEWA ALAT BERAT
1 Bulldozer
biaya kepemilikan
1. Nilai sisa dihitung
𝐴=𝑃⌊(𝑖(1+𝑖))/ 〖 (1+𝑖) 〗 ^(𝑛−1) ⌋

A= Rp 98,379,630.00 /tahun
Rp 70,271.16 /jam

Biaya Operasional
a) BBM = 0,04 x (150) x 0,6 x(3,78) 13.63 liter
b) Pelumas = (0,6 x (150) x 0,006)/7,4 + (14/85) 0.238 gallon x
c) Maintance
15% nilai depresiasi alat
D =(P - t )/n 850000000 - 122000000
15% 145600000 15600000 jt/thn

a) BBM 13.63 x 8000


b) Pelumas 0.90 x 25000
c) Maintance 7222 /jam
Harga sewa Bulldozer Rp 644,600.00 /jam
Total harga sewa Bulldozer Rp 853,591.75 /jam

2 Wheel Loader
BIAYA KEPEMILIKAN
𝐴=𝑃⌊(𝑖(1+𝑖))/ 〖 (1+𝑖) 〗 ^(𝑛−1) ⌋

A= Rp 47,795,138.90 /TAHUN
A= Rp 34,139.38 /HARI

Biaya Operasional
a) BBM = 0,04 x (100) x 0,6 x(3,78) 9.08 liter
b) Pelumas = (0,6 x (100) x 0,006)/7,4 + (14/85) 0.213 gallon x
c) Maintance
15% nilai depresiasi alat
D =(P - t )/n 412950000 - 82590000
15% 66072000 9910800 jt/thn

a) BBM 9.08 x 8000


b) Pelumas 0.81 x 25000
c) Maintance 4588 /jam
Harga sewa wheel loader Rp. Rp 301,934.00 /jam
Total harga sewa wheel loader Rp. Rp 433,522.39 /jam

3 Dump Truk
BIAYA KEPEMILIKAN
𝐴=𝑃⌊(𝑖(1+𝑖))/ 〖 (1+𝑖) 〗 ^(𝑛−1) ⌋
A= Rp 34,722,222.20 /TAHUN
A= Rp 24,801.59 /HARI

Biaya Operasional
a) BBM = 0,04 x (6,664) x 0,6 x(3,78) 0.61 liter
b) Pelumas = (0,6 x (6,664) x 0,006)/7,4 + (14/85) 0.168 gallon x
c) Maintance
15% nilai depresiasi alat
D =(P - t )/n - Rp 60,000,000.00
15% Rp 300,000,000.00 Rp 7,200,000.00 jt/thn
Rp 48,000,000.00

a) BBM 0.61 x 8000


b) Pelumas 0.64 x 25000
c) Maintance Rp 3,333.33
Harga sewa dump truk Rp 3,333.33 Rp 345,000.00 /jam
Total harga sewa dump truk Rp. Rp 21,207,678.97 /jam
Rp.
4 Motor Greder
𝐴=𝑃⌊(𝑖(1+𝑖))/ 〖 (1+𝑖) 〗 ^(𝑛−1) ⌋

A= Rp 104,166,666.70 /TAHUN
A= Rp 74,404.76 /HARI

Biaya Operasional
a) BBM = 0,04 x (100) x 0,6 x(3,78) 9.08 liter
b) Pelumas = (0,6 x (100) x 0,006)/7,4 + (14/85) 0.213 gallon x
c) Maintance
15% nilai depresiasi alat
D =(P - t )/n - Rp 180,000,000.00
15% Rp 900,000,000.00 Rp 21,600,000.00 jt/thn
Rp 144,000,000.00

a) BBM x Rp 8,000.00
b) Pelumas 9.08 x Rp 25,000.00
c) Maintance 0.81 /jam
Harga sewa wheel loader Rp 10,000.00 Rp 395,000.00 /jam
Total harga sewa wheel loader Rp 572,265.43 /jam

5 Tandem Rollerr
Biaya Operasional
a) BBM = 0,04 x (110) x 0,6 x(3,78) 9.99 liter
b) Pelumas = (0,6 x (110) x 0,006)/7,4 + (14/85) 0.218 gallon x
c) Maintance
15% nilai depresiasi alat
D =(P - t )/n - 140000000
15% 700000000 16800000 jt/thn
112000000

a) BBM x 8000
b) Pelumas 9.99 x 25000
c) Maintance 0.83 /jam
Harga sewa tandem roller 7778 395000 /jam
Total harga sewa tandem roller Rp. 503366 /jam
Rp.
6 Vibrator Roller
𝐴=𝑃⌊(𝑖(1+𝑖))/ 〖 (1+𝑖) 〗 ^(𝑛−1) ⌋

A= Rp 92,592,592.59 /TAHUN
A= Rp 66,137.57

Biaya Operasional
a) BBM = 0,04 x (100) x 0,6 x(3,78) 9.99 liter
b) Pelumas = (0,6 x (100) x 0,006)/7,4 + (14/85) 0.218 gallon x
c) Maintance
15% nilai depresiasi alat
D =(P - t )/n - Rp 160,000,000.00
15% Rp 800,000,000.00 Rp 19,200,000.00 jt/thn
Rp 128,000,000.00

a) BBM 9.99 x Rp 8,000.00


b) Pelumas 0.83 x Rp 25,000.00
c) Maintance Rp 8,888.89 /jam
Harga sewa tandem roller Rp 8,888.89 /jam
Total harga sewa tandem roller Rp 175,614.67 /jam

7 Water Tanker
𝐴=𝑃⌊(𝑖(1+𝑖))/ 〖 (1+𝑖) 〗 ^(𝑛−1) ⌋

A= Rp 5,555,555.56 /TAHUN
Rp 3,968.25 /HARI

Biaya Operasional
a) BBM = 0,04 x (100) x 0,6 x(3,78) 9.99 liter
b) Pelumas = (0,6 x (100) x 0,006)/7,4 + (14/85) 0.218 gallon x
c) Maintance
15% nilai depresiasi alat
D =(P - t )/n - Rp 60,000,000.00
15% Rp 300,000,000.00 Rp 7,200,000.00 jt/thn
Rp 48,000,000.00

a) BBM 9.99 x 8000


b) Pelumas 0.83 x 25000
c) Maintance Rp 3,333.33 /jam
Harga sewa tandem roller Rp 3,333.33 /jam
Total harga sewa tandem roller Rp. Rp 107,889.80 /jam
Rp.
8 EXCAVATOR
𝐴=𝑃⌊(𝑖(1+𝑖))/ 〖 (1+𝑖) 〗 ^(𝑛−1) ⌋
A= Rp 98,379,629.63 /TAHUN
A= Rp 70,271.16 /HARI

Biaya Operasional
a) BBM = 0,04 x (150) x 0,6 x(3,78) 13.63 liter
b) Pelumas = (0,6 x (150) x 0,006)/7,4 + (14/85) 0.238 gallon x
c) Maintance
15% nilai depresiasi alat
D =(P - t )/n - Rp 122,000,000.00
15% Rp 850,000,000.00 Rp 15,600,000.00 jt/thn
Rp 145,600,000.00

a) BBM x 8000
b) Pelumas 13.63 x 25000
c) Maintance 0.90 /jam
Harga sewa Bulldozer Rp 7,222.22 Rp 644,600.00 /jam
Total harga sewa Bulldozer Rp 853,591.75 /jam
3.785 = 0.90 liter

/5 = Rp 145,600,000.00 jt/thn
/2160 jam = Rp 7,222.22 /jam

= 109008 /jam
= 22490 /jam

x 2 bulldozer = Rp 1,707,183.50 /jam

412950000
47795138.9
34139.3849

3.785 = 0.81 liter

/5 = 66072000 jt/thn
/2160 jam = 4588 /jam

= 72672 /jam
= 20189 /jam
34722222.2
3.785 = 0.64 liter 24801.5873

/5 = Rp 48,000,000.00 jt/thn
/2160 jam = Rp 3,333.33 /jam

= Rp 1,210.72 /jam
= Rp 20,833,333.33 /jam

x 4 Dump Truk = Rp 84,830,715.88 /jam

3.785 = 0.81 liter

/5 = Rp 144,000,000.00 jt/thn
/2160 jam = Rp 10,000.00 /jam

= Rp 72,672.00 /jam
= 20189 /jam

x 2 Motor greder = Rp 1,144,530.87 /jam

3.785 = 0.83 liter

/5 = 112000000 jt/thn
/2160 jam = 7778 /jam

= 79939 /jam
= 20649 /jam

= 1006732 /jam

3.785 = 0.83 liter

/5 = Rp 128,000,000.00 jt/thn
/2160 jam = Rp 8,888.89 /jam

= Rp 79,939.20 /jam
= Rp 20,649.01 /jam

= Rp 351,229.33 /jam

3.785 = 0.83 liter

/5 = Rp 48,000,000.00 jt/thn
/2160 jam = Rp 3,333.33 /jam

= Rp 79,939.20 /jam
= Rp 20,649.01 /jam

= Rp 215,779.60 /jam
3.785 = 0.90 liter

/5 = Rp 145,600,000.00 jt/thn
/2160 jam = Rp 7,222.22 /jam

= Rp 109,008.00 /jam
= Rp 22,490.36 /jam

x 2 bulldozer = Rp 1,707,183.50 /jam


0.24
2.0736
850000000
98379630
70271.164
jumlah
NO Komponen Satuan Koefisien Harga Satuan alat Jumlah
I. PEMBERSIHAN LAHAN M3
a. Tenaga
1. Pekerja M3 0.073 Rp 80,000.00 Rp 5,840.00
2. Mandor M3 0.31 Rp 120,000.00 Rp 37,200.00
b. Alat
1. Bulldozer M3 0.094 Rp 853,591.75 2 Rp 80,237.62
2. wheel loader M3 0.338 Rp 433,522.39 1 Rp 146,530.57
3. Dump truck jam 0.336 Rp 21,207,678.97 4 Rp 7,125,780.13
c. bahan
1. pencetakan papan nama kegiatan m' 3 Rp 23,000.00 Rp 23,000.00
2. bahan bakar minyak Liter Rp 10,000.00 Rp 10,000.00
3. gemuk Liter Rp 4,000.00 Rp 4,000.00
jumlah harga tenaga dan bahan Rp 7,432,588.33
overhead 15%
jumlah total Rp 7,432,588.48

II.PEKERJAAN GALIAN TANAH


a. Tenaga
1. pekerja M3 0.52 Rp 80,000.00 Rp 41,600.00
2. Mandor M3 0.041 Rp 120,000.00 Rp 4,920.00
b. Alat
1. Bulldozer M3 0.094 Rp 853,591.75 2 Rp 80,237.62
2. wheel loader M3 0.338 Rp 433,522.39 1 Rp 146,530.57
3. Dump truck M3 0.336 Rp 21,207,678.97 4 Rp 7,125,780.13
4. Excavator M3 1.34 Rp 853,591.75 3 Rp 1,143,812.95
c. bahan
1. pencetakan papan nama kegiatan m' 3 Rp 23,000.00 Rp 23,000.00
2. bahan bakar minyak Liter Rp 10,000.00 Rp 10,000.00
3. gemuk Liter Rp 4,000.00 Rp 4,000.00
jumlah harga tenaga dan bahan Rp 8,579,881.27
overhead 15%
JUMLAH TOTAL Rp 8,579,881.42

III. Pekerjaan Timbunan Tanah


a. Tenaga
1. pekerja M3 0.52 Rp 80,000.00 Rp 41,600.00
2. Mandor M3 0.041 Rp 120,000.00 Rp 4,920.00
b. Alat
1. Bulldozer M3 0.094 Rp 853,591.75 2 Rp 80,237.62
2. wheel loader M3 0.338 Rp 433,522.39 1 Rp 146,530.57
3. Dump truck M3 0.336 Rp 21,207,678.97 4 Rp 7,125,780.13
4. Excavator M3 1.34 Rp 853,591.75 3 Rp 1,143,812.95
5. Motor Greder M3 0.138 Rp 573,265.43 2 Rp 79,110.63
6. Vibrator Roller M3 0.0799 Rp 175,164.67 1 Rp 13,995.66
7. WATER TANK M3 0.703 Rp 107,889.89 1 Rp 75,846.59
c. bahan
1. pencetakan papan nama kegiatan m' 3 Rp 23,000.00 Rp 23,000.00
2. bahan bakar minyak Liter Rp 10,000.00 Rp 10,000.00
3. gemuk Liter Rp 4,000.00 Rp 4,000.00
4. air Liter Rp 3,500.00 Rp 3,500.00
jumlah harga tenaga dan bahan Rp 8,752,334.15
overhead 15%
JUMLAH TOTAL Rp 8,752,334.30

IV.Pekerjaan Penyiapan Badan Jalan


a. Tenaga
1. pekerja M3 0.52 Rp 80,000.00 Rp 41,600.00
2. Mandor M3 0.041 Rp 120,000.00 Rp 4,920.00
b. Alat
1. Bulldozer M3 0.094 Rp 853,591.75 Rp 80,237.62
2. wheel loader M3 0.338 Rp 433,522.39 Rp 146,530.57
3. Dump truck M3 0.336 Rp 21,207,678.97 Rp 7,125,780.13
4. Water tank M3 0.703 Rp 107,889.89 Rp 75,846.59
5. Motor Greder M3 0.138 Rp 573,265.43 Rp 79,110.63
6. Vibrator Roller M3 0.0799 Rp 175,164.67 Rp 13,995.66
c. bahan
1. pencetakan papan nama kegiatan m' 3 Rp 23,000.00 Rp 23,000.00
2. bahan bakar minyak Liter Rp 10,000.00 Rp 10,000.00
3. gemuk Liter Rp 4,000.00 Rp 4,000.00
4. air Liter Rp 3,500.00 Rp 3,500.00
jumlah harga tenaga dan bahan Rp 7,515,414.92
overhead 15%
JUMLAH Rp 7,515,415.07
TOTAL KESELURUHAN Rp 32,280,219.27
SCHEDULLE ALAT BERAT
Jumlah Waktu (Minggu)
No Uraian Kegiatan Alat Berat
(unit) 1 2 3 4 5 6 7 8 9 10 11 12
Bulldozer 2
Wheel
Pembersihan 1
1 Loader
lahan
Dump
4
Truk
Bulldozer 2
Wheel
1
Loader
Pekerjaan Galian
2 Dump
Tanah 4
Truk

Excavator 3

Bulldozer 2
Wheel
1
Loader
Dump
4
Truk
Motor
2
Greder
Pekerjaan
3
Timbunan Tanah Tandem 1
Roller
Vibrator
1
Roller

Excavator 3

Water
1
Tank
Bulldozer 2

Pekerjaan
2 Penyiapan
Badan Jalan
Wheel
1
Pekerjaan Loader
2 Penyiapan Dump
Badan Jalan 4
Truk
Water
Tank 1

SITUASI
A. Galian > Timbunan
B
RENCANA ANGGARAN BIAYA

NO URAIAN SATUAN VOLUME HARGA SATUAN HARGA TOTAL (Rp)


(Rp)
I. PEMBERSIHAN LAHAN M3
a. Tenaga
1. Pekerja M3 16000 Rp 5,840.00 Rp 93,440,000.00
2. Mandor M3 16000 Rp 37,200.00 Rp 595,200,000.00
b. Alat
1. Bulldozer M3 16000 Rp 853,591.75 Rp 13,657,468,000.00
2. wheel loader M3 16000 Rp 146,530.57 Rp 2,344,489,120.00
3. Dump truck M3 16000 Rp 7,125,780.23 Rp 114,012,483,680.00
c. bahan
1. pencetakan papan nama kegiatan m' 3 Rp 23,000.00 Rp 69,000.00
2. bahan bakar minyak Liter 464.52 Rp 10,000.00 Rp 4,645,200.00
3. gemuk Liter 51.24 Rp 4,000.00 Rp 204,960.00
jumlah total Rp 130,707,999,960.00

II. PEKERJAAN GALIAN TANAH


a. Tenaga
1. Pekerja M3 312570 Rp 5,840.00 Rp 1,825,408,800.00
2. Mandor M3 312570 Rp 37,200.00 Rp 11,627,604,000.00
b. Alat
1. Bulldozer M3 312570 Rp 853,591.75 Rp 266,807,173,297.50
2. wheel loader M3 312570 Rp 146,530.57 Rp 45,801,060,264.90
3. Dump truck M3 312570 Rp 7,125,780.23 Rp 2,227,305,126,491.10
4. Excavator M3 312570 Rp 1,143,812.95 Rp 357,521,613,781.50
c. bahan
1. bahan bakar minyak Liter 464.52 Rp 10,000.00 Rp 4,645,200.00
2. gemuk Liter 51.24 Rp 4,000.00 Rp 204,960.00
jumlah total Rp 2,553,371,223,013.50

II. PEKERJAAN TIMBUNAN TANAH


a. Tenaga
1. Pekerja M3 29083.46 Rp 5,840.00 Rp 169,847,383.04
2. Mandor M3 29083.46 Rp 37,200.00 Rp 37,200.00
b. Alat
1. Bulldozer M3 29083.46 Rp 853,591.75 Rp 24,825,398,103.09
2. wheel loader M3 29083.46 Rp 146,530.57 Rp 4,261,615,385.25
3. Dump truck M3 29083.46 Rp 7,125,780.23 Rp 207,242,315,784.88
4. Excavator M3 29083.46 Rp 1,143,812.95 Rp 33,266,033,603.56
5. Motor Greder M3 29083.46 Rp 573,265.43 Rp 16,672,539,909.73
6. Vibrator Roller M3 29083.46 Rp 175,164.67 Rp 5,094,393,972.70
7. WATER TANK M3 29083.46 Rp 107,889.89 Rp 3,137,810,868.66
c. bahan
1. bahan bakar minyak Liter 464.52 Rp 10,000.00 Rp 4,645,200.00
2. gemuk Liter 51.24 Rp 4,000.00 Rp 204,960.00
3. Air Liter 51.24 Rp 3,500.00 Rp 179,340.00
jumlah total Rp 294,675,021,710.89

II. Pekerjaan Penyiapan Badan Jalan


a. Tenaga
1. Pekerja M3 16000 Rp 5,840.00 Rp 93,440,000.00
2. Mandor M3 16000 Rp 37,200.00 Rp 37,200.00
b. Alat
1. Bulldozer M3 16000 Rp 853,591.75 Rp 13,657,468,000.00
2. wheel loader M3 16000 Rp 146,530.57 Rp 2,344,489,120.00
3. Dump truck M3 16000 Rp 7,125,780.23 Rp 114,012,483,680.00
5. Motor Grader M3 16000 Rp 573,265.43 Rp 9,172,246,880.00
6. Vibrator Roller M3 16000 Rp 175,164.67 Rp 2,802,634,720.00
7. WATER TANK M3 16000 Rp 107,889.89 Rp 1,726,238,240.00
c. bahan
1. bahan bakar minyak Liter 464.52 Rp 10,000.00 Rp 4,645,200.00
2. gemuk Liter 51.24 Rp 4,000.00 Rp 204,960.00
3. Air Liter 51.24 Rp 3,500.00 Rp 179,340.00
jumlah total Rp 143,814,067,340.00
jumlah total keseluruhan Rp 3,122,568,312,024.39
Dibulatkan Rp 3,200,000,000,000.00