PEKERJAAN GALIAN TANAH PADA JALAN UNTUK PENYIAPAN REPLACEMENT/IMPROVEMENT

SUBGRADE
PROYEK PEMBANGUNAN JALAN TOLL
SERANG PANIMBANG TAHAP 3
STA. 58+650 ~ STA 59+075
KABUPATEN PANDEGLANG PROVINSI BANTEN

LAPORAN AKTIFITAS HARIAN


LAPORAN NO.:006/LAH/TIS-APTK/XII/2022 TANGGAL : 5 JANUARY 2023

Total Total
INDIRECT MANPOWER QTY DIRECT MANPOWER QTY
Jam Kerja Jam Kerja

1 Project Manager 1 9 1 Site Manager 1 9

2 Admin Project 1 9 2 Supervisor 1 9

3 Checker 1 9 3 Safety Officer 1 9


4 Checker -
5 Surveyor 3 9
6 Driver 15 9
7 Operator for Equipments 6 9
8 Purchasinng -

Sub Total Indirect Manpower : 3 27 Sub Total Direct Manpower : 27 54

Total Total Jam


Peralatan QTY Kondisi Cuaca Keterangan
Jam Kerja Jam Menit
1 . Excavator 5 9 1. 07.00 ~ 10.00 C / B / H / Hd C = Cerah
2 .Vibro Roller 1 9 2. 10.00 ~ 13.00 C / B / H / Hd B = Berawan
3 . Dozer - - 3. 13.00 ~ 16.00 C / B / H / Hd H = Hujan Gerimis

4. Dump Truck ;24 m3 15 9 4. 16.00 ~ 19.00 C / B / H / Hd Hd = Hujan Deras

5. 19.00 ~ 22.00 C / B / H / Hd
*Jam Kerja Hilang
Sub Total Peralatan 21 27 Total 0 0

Aktifitas Hari ini : Permasalahan / Area of Concern : Rencana aktivitas besok


1. Penggalian badan jalan di STA 58+650 - 58+675 selebar 50
1. Jalan akses masih belum maksimal, jadi harus 1. Pemadatan akses jalan ke area disposal dengan 1 unit exca dan penambahan batu
m kedalam kurang lebih 2 m
ditambah batu agar dapat dijadikan akses
dan penambahan batu untuk lapisan atas akses untuk lapisan atas akses
dumptruck
2. Membuang air dan lumpur menggunakan pompa di area 2. melanjutkan penggalian diarea STA 58+650 dengan 4 unit exca
STA 58+675 3. Loading tanah dari galian ke area disposal
3. Loading tanah dari galian ke area disposal

Surveyor
Mengontrol kedalaman yang akan digali

Disiapkan oleh Di review oleh Di setujui oleh

ALYA SHENXUDONG