WAKTU PELAKSANAAN

NO URAIAN PEKERJAAN BOBOT TOTAL


M1 M2 M3 M4

1 Survei Bangunan Baruga 11% 11%


6% 6%
2 Survei Masjid 11% 11%
6% 6%
3 Survei Pelataran 11% 11%
6% 6%
4 Survei Tempat Pelantikan 11% 11%
6% 6%
5 Survei Pada Area Taman 11% 11%
6% 6%
Survei Tiang Bendera Dan Area
6 11% 11%
Sekitar Tiang Bendera 6% 6%
7 Survei Area Jangkar 11% 11%
6% 6%
8 Survei Area Publik 11% 11%
6% 6%
Survei harga pekerja, bahan dan
9 11% 11%
material 6% 6%

TOTAL 100%

RENCANA PROGRES MINGGUAN 17% 33% 33% 17%


100%
KOMULATIF PROGRES MINGGUAN 17% 50% 83% 100%
WAKTU PELAKSANAAN
NO URAIAN PEKERJAAN
M1 M2 M3 M4

1 Survei Bangunan Baruga

2 Survei Masjid

3 Survei Pelataran

4 Survei Tempat Pelantikan

5 Survei Pada Area Taman

Survei Tiang Bendera Dan Area


6
Sekitar Tiang Bendera
7 Survei Area Jangkar

8 Survei Area Publik

Survei harga pekerja, bahan dan


9
material