Anda di halaman 1dari 79

PERHITUNGAN VOL

LANTAI I
I PEKERJAAN PERSIAPAN
panjang
1 Pembersihan lokasi = 7.00 x
2 Pengukuran dan pasang bouplank = 2.00 x

II PEKERJAAN GALIAN & URUGAN panjang


1 Galian tanah pondasi batu kali
tengah = 41.00 x
Tepi = 42.00 x
=

2 Galian tanah pondasi Sepatu Panjang

Type A = 1.00 x
Type B =
Tangga =

3 Urugan tanah kembali


V.Galian -
- pondasi batu kali (tengah) = 22.96 -
- pondasi batu kali (tepi) = 23.52 -
= - -
- pondasi Plat Sepatu (Type A) = 7.00 -
- pondasi Plat Sepatu (Type B) = - -
- pondasi Plat Sepatu (Tangga) = - -

4 Urugan tanah bawah lantai luas x


Elv. ±0,00 = - x
Elv. +0,20 =
Elv. - 0,05 =
Elv. - 0,20 =

5 Urugan pasir pondasi Batu kali panjang


- Urugan pasir pondasi (tengah) = 41.00 x
- Urugan pasir pondasi (tepi) = 42.00 x
= - x

6 Urugan pasir pondasi Plat Sepatu panjang


- Urugan pasir Plat Type A = 1.00 x
Plat Type B = - x
Plat Tangga = - x

7 Urugan pasir bawah lantai luas x


induk = 98.00 x
carport = - x

III PEKERJAAN PONDASI


1 Cor lantai kerja pondasi plat banyak
Type A = 7.00 x
Type B = - x
Tangga = - x

2 Pondasi batu kali panjang


pondasi tengah = 41.00 x

pondasi tepi = 42.00 x

= - x

3 Pondasi batu kosong (anstampeng) panjang


Tengah = 41.00 x
Tepi = 42.00 x
= - x

4 Pondasi beton plat sepatu banyak


Cor pondasi plat type A = 7.00 x
Cor pondasi plat type B = - x
Cor pondasi plat Tangga = - x
5 Kolom struktur Pondasi banyak
Pondasi A (K1 15/30) = 7.00 x
Pondasi B (K1 15/30) = - x
Pondasi Tangga (Dinding Plat 30/100) = - x

6 Pondasi bata merah (Rollag) panjang


Depan & Belakang = 6.50 x
= 3.50 x
= 3.50 x

IV PEKERJAAN PEMBETONAN panjang


1 Beton Sloof SL1 (20/35) = 50.00 x
SL2 (15/20) = 83.00 x
SL Tangga (30/55) = 1.00 x

2 Kolom struktur banyak


Kolom 1 (15/20) = 7.00 x
Kolom 3 (30/40) = - x

3 Kolom Praktis banyak


K 2 (15/15) Depan = 14.00 x
Km/Wc Tengah = - x
Mushola = - x
Km/Wc Belakang = - x
Pagar Depan = - x
Pagar Belakang = - x
Gewel Depan = - x
Gewel Kanan = - x
= - x

Balok panjang
4 Balok 1 (15/20) = 56.00 x
5 Balok 2 (15/30) = - x
6 Balok 3 (8/45) = - x
7 Balok Tangga (15/25) = - x
8 Balok Tangga (15/35) = - x

9 Balok Plat Atap panjang


Balok 1 (15/20) = x

10 Balok Plat Kanopi panjang


Balok 1 (15/20) = - x
Balok 1 (15/30) = x

11 Ring Balk panjang


Balok 1 (15/20) = 84.00 x
Gewel = 17.84 x

12 Pelat Lantai t 12 cm luas


Lantai 2 = - x

13 Pelat kanopi t 10 cm panjang


Teras Belakang = x
= x
KM/WC Belakang = x
Dapur = - x
Mushola = x
Garasi = x
Kamar Depan = - x
Teras Depan = - x
= 1.50 x

14 Pelat Meja Dapur t 10 cm panjang


Plat Atas = - x
Dinding = - x

15 Pelat tangga t 12 cm luas


Step 1 = - x
= - x
bordes = - x
Step 2 = - x
= - x
16 Menbongkar cetakan beton =

17 Rabat Beton luas


induk = - x

V PEKERJAAN PASANGAN & PLESTERAN


1 Pasangan dinding trasraam panjang
dinding samping = x
KM/WC Tengah = x
KM/WC Belakang = x
Bak Air = x

2 Pasangan dinding bata merah panjang


dinding depan beratap = 83.00 x
= x
dinding samping luar mushola = x
dinding samping = x
dinding dalam = x
= x
dinding KM/WC Belakang = x
dinding KM/WC Tengah = x
dinding Teras = x
dinding bawah tangga (segitiga) = x
dinding gewel kiri/tengah (segitiga) = 11.00 x
dinding gewel kanan (segitiga) = 9.00 x
dinding pagar depan = x
dekat gewel kiri (trapesium) =
dekat gewel kanan (trapesium) =
dinding pagar belakang = 7.00 x
dinding Tempat Tanaman = x
dinding penebalan kolom = x

dikurangi lubang kusen : banyak


P1 = 4.00 x
= 1.00 x
P2 = x
P3 (KM/WC) = 2.00 x
P4 (Garasi) = - x
J1 = 1.00 x
J2 = 1.00 x
J4 = 1.00 x
BV = 2.00 x
Kisi-kisi 1 = 4.00 x
Kisi-kisi 2 = 1.00 x

3 Pasangan batu alam templek panjang


Dinding depan = 2.85 x
= 0.34 x
= 3.35 x
= 5.42 x
Dinding belakang = 2.85 x
= 2.50 x
= 0.14 x
= 0.24 x

4 Pasangan batu alam Palimanan Putih 20/40 panjang


Kolom Teras = 2.20 x

sisi
5 Plesteran + Acian Trasraam = 2.00 x
= 1.00 x

sisi
6 Plesteran + Acian dinding = 2.00 x

VI PEKERJAAN KUSEN PINTU & JENDELA


1 Kusen Aluminium banyak
P1 = 4.00 x
= 1.00 x
P2 = - x
P4 = - x
J1 = 1.00 x
J2 = 1.00 x
J4 = 1.00 x
BV = 2.00 x
2 Kusen Kayu 10/10 banyak
Kisi-kisi 1 = 4.00 x
Kisi-kisi 2 = 1.00 x

3 Daun pintu panil kayu banyak


P1 = 8.00 x
P2 = - x

4 Daun pintu jalusi banyak


P4 = - x

5 Daun Jendela kaca Aluminium banyak


P1 = 4.00 x
dikurangi kaca = 4.00 x

J1 = 1.00 x
dikurangi kaca = 1.00 x

J2 = 1.00 x
= 1.00 x

J4 = 1.00 x
= 1.00 x

6 Pasang kaca bening 5 mm banyak


P1 = 4.00 x
P4 = - x
J1 = 1.00 x
J2 = 1.00 x
J4 = 1.00 x

7 Pasang kaca Es 5 mm banyak


BV = 4.00 x

8 Pasang Pintu PVC


P3 =
VII PEKERJAAN PENUTUP PLAFOND
1 Pasang Plafond calsiboard + rangka Hollow 4x4 = Luas Lantai - Void
2 Pasang plafond =
3 List Gypsum profil sisi
R. Makan + Dapur = 1.00 x
Teras belakang = 1.00 x
KM/WC = 1.00 x
R.Tidur belakang = 1.00 x
Mushola = 1.00 x
Garasi = 1.00 x
KM/WC tengah = 1.00 x
Ruang tamu = 1.00 x
R.Tidur depan = 1.00 x
Teras depan = 1.00 x
Dinding luar depan = 1.00 x
Dinding luar Garasi belakang = 1.00 x

VIII PEKERJAAN SANITAIR


1 Instalasi air bersih pipa PVC AW 3/4" = 20.00 m'
2 Instalasi air kotor pipa PVC AW 3" = 20.00 m'
3 Instalasi air kotoran pipa PVC AW 4" = 20.00 m'
4 Klosed jongkok = 2.00 unit
5 Kran air = 4.00 bh
6 Floor drain = 2.00 bh
7 Mesin Pompa = 1.00 bh
8 Resapan + Septictank = 1.00 unit

IX PEKERJAAN INSTALASI LISTRIK


1 Meteran PLN = 1.00 bh
2 Box sekering = 1.00 bh
3 MCB = 1.00 bh
4 Lampu downlight = 15.00 bh
5 Saklar ganda = 4.00 bh
6 Saklar tunggal = 7.00 bh
7 Stop kontak 220 V = 8.00 bh
8 Kabel NYA = 50.00 m'

X PEKERJAAN PENUTUP LANTAI & DINDING


1 Keramik lantai motif 40/40 luas
= 74.10
tangga =
=
=

2 Keramik lantai motif anti slip 20/20 panjang


KM/WC = 1.50 x
Meja Dapur = - x
= - x

3 Keramik dinding warna 20/30 panjang


KM/WC belakang = 5.50 x
KM/WC depan = 5.50 x
Bak air = - x

13 Pasangan Paving Stone luas


carport = - x

XI PEKERJAAN RANGKA & PENUTUP ATAP


1 Pasang Rangka Galvalum panjang
I = 6.00 x
II = 4.50 x
= - x
= - x

2 Pasang Genteng Beton Flat panjang


I = 6.00 x
II = 4.50 x
= - x
= - x

3 Pasang Genteng Bubungan panjang


I = 3.50 x
= x
0 = x
4 Pasang lisplank panjang
I = 7.00 x
= x
0 = x

XII PEKERJAAN PENGECATAN sisi


1 Cat dinding interior dan ekterior dinding trasram = 1.00 x
2 Cat dinding interior dan ekterior dinding = 1.00 x
3 Cat interior plafon = Luas plafon

4 Cat eksterior kanopi Luas


= - x

5 Cat lisplank kayu T. Panjang


= - x

XIII PEKERJAAN PASANG PENGUNCI


1 Kunci Pintu banyak
P1 = 4.00 x
P2 = - x
P4 = - x

2 Engsel Pintu banyak


P1 = 4.00 x
P2 = - x
P4 = - x

3 Grendel Pintu banyak


P1 = 4.00 x
P2 = - x
P3 = - x

4 Grendel jendela banyak


P1 = 4.00 x
J1 = 1.00 x
J2 = 1.00 x
J4 = 1.00 x

5 Engsel Jendela banyak


P1 = 4.00 x
J1 = 1.00 x
J2 = 1.00 x
J4 = 1.00 x

6 Kait angin banyak


P1 = 4.00 x
J1 = 1.00 x
J2 = 1.00 x
J4 = 1.00 x

LANTAI 2

I PEKERJAAN PEMBETONAN
1 Kolom struktur banyak
Kolom 1 (15/20) = 23.00 x

2 Kolom Praktis banyak


Kolom 3 (15/15) = 5.00 x

3 Balok 15/20 panjang


Balok Plat KM/WC = x
Balok Plat kanopi = x
Ring Balk = 104.00 x
Balok Gewel = 6.80 x
= 5.65 x
= 2.76 x

4 Pelat atap KM/WC t 10 cm panjang


atap = x

5 Pelat kanopi t 10 cm panjang


Belakang = - x

6 Menbongkar cetakan beton

II PEKERJAAN PASANGAN & PLESTERAN


1 Pasangan dinding trasraam panjang
KM/WC = 7.00 x
Bak air = 1.50 x
2 Pasangan dinding bata merah panjang
induk 1 = 104.00 x
KM/WC = 4.50 x
Gewel = 4.10 x
trapesium = 4.13 x
= 8.15 x
= 3.00 x

dikurangi lubang kusen : banyak


P2 = 2.00 x
P3 (KM/WC) = 1.00 x
J1 = 1.00 x
J2 = 1.00 x
J3 = 1.00 x
BV = 1.00 x

sisi
4 Plesteran + Acian Trasraam = 1.00 x

5 Plesteran + Acian dinding = 2.00 x

3 Pasangan batu alam palimanan panjang


Dinding belakang = 1.30 x
= 2.04 x
= 1.87 x

III PEKERJAAN KUSEN PINTU & JENDELA


1 Kusen Kayu 6/15 banyak
P2 = 4.00 x
J1 = 2.00 x
J2 = 2.00 x
J3 = 1.00 x
BV = 1.00 x

2 Daun Pintu panil kayu banyak


P2 = 4.00 x
3 Daun Jendela kaca kayu banyak
J1 = 4.00 x
dikurangi kaca = 4.00 x

J2 = 2.00 x
= 2.00 x

J3 = 3.00 x
= 3.00 x

4 Pasang kaca bening 5 mm banyak


J1 = 4.00 x
J2 = 2.00 x
J4 = 3.00 x

5 Pasang kaca Es 5 mm banyak


BV = 2.00 x

6 Pasang Pintu PVC


P3 =

IV PEKERJAAN PENUTUP PLAFOND


1 Pasang Plafond calsiboard + rangka hollow = Luas Lantai
2 Pasang plafond =
3 List Gypsum profil sisi
R. Santai + Void = 1.00 x
KM/WC = 1.00 x
R.Tidur belakang = 1.00 x
R.Tidur depan = 1.00 x

V PEKERJAAN SANITAIR
1 Instalasi air bersih pipa PVC AW 3/4" = 2.00 m'
2 Instalasi air kotor pipa PVC AW 3" = 3.00 m'
3 Instalasi air kotoran pipa PVC AW 4" = 2.00 m'
4 Klosed jongkok = 1.00 unit
5 Kran air = 1.00 bh
6 Floor drain = 1.00 bh

VI PEKERJAAN INSTALASI LISTRIK


1 Lampu downlight = 8.00 bh
2 Saklar ganda = 2.00 bh
3 Saklar tunggal = 4.00 bh
4 Stop kontak 220 V = 3.00 bh
5 Kabel NYA = 25.00 m'

VII PEKERJAAN PENUTUP LANTAI & DINDING


1 Keramik lantai motif 40/40 luas
induk = 34.00

2 Keramik lantai motif anti slip 20/20 panjang


KM/WC = 2.00 x

3 Keramik dinding warna 20/30 panjang


KM/WC = 7.00 x
bak air = 1.50 x

VIII PEKERJAAN RANGKA & PENUTUP ATAP


1 Pasang Rangka Galvalum panjang
Tengah = 5.65 x
Samping Kiri = 4.50 x
Samping kanan = 2.76 x

2 Pasang Genteng panjang


Tengah = 5.65 x
Samping Kiri = 4.50 x
Samping kanan = 2.76 x

3 Pasang Genteng Bubungan


Tengah =
Samping Kiri =
Samping kanan =
4 Pasang Lisplank panjang
Tengah = 4.28 x
Samping Kiri = 3.00 x
Samping kanan = 3.28 x

IX PEKERJAAN PENGECATAN sisi


1 Cat dinding interior dan ekterior dinding trasram = 1.00 x
2 Cat dinding interior dan ekterior dinding = dinding induk + Gewel
3 Cat interior plafon = Luas Plafond

4 Cat eksterior kanopi panjang


Teras + WC = 4.00 x
R. tidur = 1.50 x
R. tidur = 2.50 x

5 Cat lisplank kayu T. Panjang


= 24.12 x

X PEKERJAAN PASANG PENGUNCI


1 Kunci Pintu banyak
P2 = 4.00 x

2 Engsel Pintu banyak


P2 = 4.00 x

3 Grendel Pintu banyak


P2 = 4.00 x

4 Grendel jendela banyak


J1 = 2.00 x
J2 = 2.00 x
J3 = 1.00 x

5 Engsel Jendela banyak


J1 = 2.00 x
J2 = 2.00 x
J3 = 1.00 x
6 Kait angin banyak
J1 = 2.00 x
J2 = 2.00 x
J3 = 1.00 x
ITUNGAN VOLUME

lebar
14.00 = 98.00 m2
( 7.00 + 14.00 ) = 42.00 m'

lebar kedalaman Banyak


(Trapesium)
0.70 x 0.80 = 22.96 m3
0.70 x 0.80 = 23.52 m3
= - m3
Jumlah = 46.48 m3

lebar kedalaman Banyak

1.00 x 1.00 x 7.00 = 7.00 m3


= - m3
= - m3
Jumlah = 7.00 m3

V.pondasi - V.pasir - V.anstampeng/LK


15.58 - 3.69 - 7.38 = m3
15.96 - 3.36 - 6.72 = m3
- - - - - = m3
1.25 - 0.70 - 0.35 = m3
- - - - - = m3
- - - - - = m3
Jumlah = 2.10 m3

kedalaman
0.15 = - m3
= m3
= m3
= m3
Jumlah = - m3

lebar tebal
0.95 x 0.10 = 3.90 m3
0.85 x 0.10 = 3.57 m3
0.65 x 0.10 = - m3
Jumlah = m3

lebar tebal Banyak


1.05 x 0.10 x 7.00 = 0.74 m3
1.05 x 0.10 x - = - m3
0.96 x 0.10 x - = - m3
Jumlah = m3

Tebal
0.05 = 4.90 m3
- = - m3
Jumlah = 4.90 m3

panjang lebar tebal


0.80 x 0.80 x 0.05 = 0.22 m3
1.03 x 1.03 x 0.05 = - m3
1.00 x 0.96 x 0.05 = - m3
Jumlah = 0.22 m3

lbr atas lbr bawah tinggi


( 0.30 + 0.70 ) x 0.80 = 16.40 m3
2
( 0.30 + 0.70 ) x 0.80 = 16.80 m3
2
( 0.30 + 0.50 ) x 0.80 = - m3
2
Jumlah = 33.20 m3

lebar tebal
0.90 x 0.20 = 7.38 m3
0.80 x 0.20 = 6.72 m3
0.60 x 0.20 = - m3
Jumlah = 14.10 m3

pajang lebar tinggi


0.80 x 0.80 x 0.25 = 1.12 m3
0.18 x 0.80 x = - m3
0.13 x 1.00 x = - m3
Jumlah = 1.12 m3

tinggi lebar panjang


1.00 x 0.15 x 0.25 = 0.26 m3
1.80 x 0.15 x 0.25 = - m3
0.95 x 0.30 x 1.00 = - m3
Jumlah = 0.26 m3

Tinggi Banyak
0.40 x 2.00 = 5.20 m2
0.30 x 2.00 = 2.10 m2
0.20 x 2.00 = 1.40 m2
Jumlah = 8.70 m2

lebar tinggi
0.20 x 0.35 = m3
0.15 x 0.20 = 2.49 m3
0.30 x 0.55 = m3
Jumlah = 2.49 m3

tinggi lebar panjang


4.00 x 0.15 x 0.20 = 0.84 m3
3.25 x 0.30 x 0.40 = - m3
Jumlah = 0.84 m3

tinggi lebar panjang


4.47 x 0.15 x 0.15 = 1.41 m3
2.60 x 0.15 x 0.15 = - m3
3.75 x 0.15 x 0.15 = - m3
3.95 x 0.15 x 0.15 = - m3
1.95 x 0.15 x 0.15 = - m3
2.95 x 0.15 x 0.15 = - m3
1.26 x 0.15 x 0.15 = - m3
1.75 x 0.15 x 0.15 = - m3
0.30 x 0.15 x 0.15 = - m3
Jumlah = 1.41 m3

lebar tinggi
0.15 x 0.20 = 1.68 m3
0.15 x 0.30 = - m3
0.08 x 0.45 = - m3
0.15 x 0.25 = - m3
0.15 x 0.35 = - m3
Jumlah = 1.68 m3

lebar tinggi
0.15 x 0.20 = - m3

lebar tinggi
0.15 x 0.20 = - m3
0.15 x 0.30 = - m3
Jumlah = - m3

lebar tinggi
0.15 x 0.20 = m3
0.15 x 0.20 = 0.54 m3
Jumlah = 0.54 m3
tebal
0.12 = - m3

lebar tebal banyak


0.60 x 0.10 = - m3
0.60 x 0.10 x 2.00 = - m3
0.60 x 0.10 = - m3
0.60 x 0.10 = - m3
0.60 x 0.10 = - m3
0.60 x 0.10 = - m3
0.60 x 0.10 = - m3
0.60 x 0.10 = - m3
0.60 x 0.10 x = - m3
Jumlah = - m3

lebar tebal banyak


0.50 x 0.10 = - m3
0.50 x 0.10 x 5.00 = - m3
Jumlah = - m3

tebal banyak
0.12 = - m3
1.00 x 9.00 = - m3
0.12 = - m3
0.12 = - m3
1.00 x 6.00 = - m3
Jumlah = - m3

= 7.22 m3

tebal banyak
0.05 = - m3

tinggi
0.50 = - m2
1.75 = - m2
4.00 = - m2
0.90 = - m2
Jumlah = - m2

tinggi banyak Pembagi


4.00 = 332.00 m2
4.10 = - m2
2.70 = - m2
3.10 = - m2
3.60 = - m2
0.45 = - m2
1.75 = - m2
0.45 = - m2
1.26 x 2.00 = - m2
1.85 x 2.00 : 2.00 = - m2
2.10 x 2.00 : 2.00 = 23.10 m2
1.72 : 2.00 = 7.74 m2
1.05 = - m2
= - m2
= - m2
2.05 = 14.35 m2
0.40 = - m2
2.96 x 4.00 = - m2
Jumlah = 377.19 m2
lebar tinggi
0.80 x 2.10 = 6.72 m2
1.20 x 2.10 = 2.52 m2
0.82 x 2.26 = - m2
0.82 x 2.26 = 3.71 m2
3.10 x 2.56 = - m2
1.38 x 2.12 = 2.93 m2
0.72 x 2.12 = 1.53 m2
1.38 x 1.22 = 1.68 m2
0.72 x 0.57 = 0.82 m2
0.54 x 0.69 = 1.49 m2
2.65 x 0.69 = 1.83 m2
Jumlah = 23.22 m2

Jumlah Ps. Bata = 353.97 m2

tinggi banyak
0.40 = 1.14 m2
2.91 = 0.99 m2
0.80 = 2.68 m2
0.35 x 2.00 = 3.79 m2
4.10 = 11.69 m2
0.83 = 2.08 m2
2.91 = 0.41 m2
0.35 = 0.08 m2
Jumlah = m2

tinggi banyak
2.96 x 4.00 = m2

luas
- = - m2
- = - m2
Jumlah = - m2
luas
353.97 = 707.94 m2

Lebar Tinggi panjang


- x - x 5.00 = 20.00 m1
- x - x 5.96 = 5.96 m1
- x - x 5.34 = - m1
- x - x 8.22 = - m1
- x - x 9.12 = 9.12 m1
- x - x 5.68 = 5.68 m1
- x - x 6.42 = 6.42 m1
- x - x 2.58 = 5.16 m1
Jumlah = 52.34 m1
Lebar Tinggi panjang
0.10 x 0.10 x 1.38 = 0.06 m3
0.10 x 0.10 x 1.38 = 0.01 m3
Jumlah = 0.07 m3

Lebar Tinggi
0.72 x 2.26 = 13.02 m2
0.72 x 2.21 = - m2
Jumlah = 13.02 m2

Lebar Tinggi
0.50 x 2.51 = - m2

Lebar Tinggi
0.62 x 2.02 = 5.01 m2
0.44 x 1.84 = 3.24 m2
= 1.77 m2
0.62 x 2.02 = 1.25 m2
0.44 x 1.84 = 0.81 m2
= 0.44 m2
0.62 x 2.02 = 1.25 m2
0.44 x 1.84 = 0.81 m2
= 0.44 m2
0.62 x 1.12 = 0.69 m2
0.44 x 0.94 = 0.41 m2
= 0.28 m2
Jumlah = 2.94 m2

Lebar Tinggi
0.45 x 1.85 = 3.33 m2
0.30 x 0.12 = - m2
0.45 x 1.85 = 0.83 m2
0.45 x 1.85 = 0.83 m2
0.45 x 0.95 = 0.43 m2
Jumlah = 5.42 m2

Lebar Tinggi
0.62 x 0.25 = 0.62 m2

= 2.00 unit
Lantai - Void = 78.00 m2
= 78.00 m2
T. Panjang
21.40 = - m'
9.40 = - m'
6.40 = - m'
11.40 = - m'
9.40 = - m'
16.40 = - m'
6.40 = - m'
13.40 = - m'
12.40 = - m'
9.40 = - m'
13.85 = - m'
3.50 = - m'
Jumlah = - m'

unit

unit

panjang lebar banyak


= 74.10 m2
0.50 x 1.00 x 10.00 = m2
1.50 x 2.00 x 1.00 = m2
0.50 x 1.00 x 7.00 = m2
Jumlah = 74.10 m2

lebar banyak
1.50 x 2.00 = 4.50 m2
0.50 x 1.00 = - m2
0.50 x 1.00 = - m2
Jumlah = 4.50 m2

tinggi banyak
1.80 x 1.00 = 9.90 m2
1.80 x 1.00 = 9.90 m2
0.90 x 2.00 = - m2
Jumlah = 19.80 m2

= - m2

lebar sisi
3.50 x 2.00 = 42.00 m2
3.50 x 2.00 = 31.50 m2
0.75 x 2.00 = - m2
3.50 x 2.00 = - m2
Jumlah = 73.50 m2

lebar sisi
3.50 x 2.00 = 42.00 m2
3.50 x 2.00 = 31.50 m2
0.75 x 2.00 = - m2
3.50 x 2.00 = - m2
Jumlah = 73.50 m2

sisi
2.00 = 7.00 m'
1.00 = - m'
1.00 = - m'
Jumlah = 7.00 m'
sisi
2.00 = 14.00 m'
1.00 = - m'
2.00 = - m'
Jumlah = 14.00 m'

luas
- = - m2
707.94 = 707.94 m2
= 78.00 m2

sisi
2.00 = - m2

T. sisi
0.22 = - m2

jumlah
1.00 unit = 4.00 unit
1.00 unit = - unit
1.00 unit = - unit
Jumlah = 4.00 unit
jumlah
3.00 = 12.00 bh
3.00 = - bh
- = - bh
Jumlah = 12.00 bh
jumlah
2.00 = 8.00 bh
1.00 = - bh
- = - bh
Jumlah = 8.00 bh
jumlah
2.00 = 8.00 bh
2.00 = 2.00 bh
1.00 = 1.00 bh
2.00 = 2.00 bh
Jumlah = 13.00 bh
jumlah
4.00 = 16.00 bh
4.00 = 4.00 bh
2.00 = 2.00 bh
4.00 = 4.00 bh
Jumlah = 26.00 bh

jumlah
4.00 = 16.00 bh
4.00 = 4.00 bh
2.00 = 2.00 bh
4.00 = 4.00 bh
Jumlah = 26.00 bh

tinggi lebar panjang


3.70 x 0.15 x 0.20 = 2.55 m3

tinggi lebar panjang


3.50 x 0.15 x 0.15 = 0.39 m3

lebar tinggi
0.15 x 0.20 = - m3
0.15 x 0.20 = - m3
0.15 x 0.20 = 3.12 m3
0.15 x 0.20 = 0.20 m3
0.15 x 0.20 x 2.00 = 0.34 m3
0.15 x 0.20 x 2.00 = 0.17 m3
Jumlah = 3.83 m3

lebar tebal
2.43 x 0.10 = - m3

lebar tebal
0.68 x 0.10 = - m3

= 6.78 m3

tinggi
1.75 = 12.25 m2
1.10 = 1.65 m2
Jumlah = 13.90 m2

tinggi
3.50 = 364.00 m2
1.15 = 5.18 m2
2.35 : 2.00 = 4.82 m2
1.00 : 2.00 = 2.07 m2
2.35 : 2.00 = 9.58 m2
0.91 : 2.00 = 1.37 m2
Jumlah = 387.00 m2

lebar tinggi
0.82 x 2.26 = 3.71 m2
0.82 x 2.26 = 1.85 m2
1.38 x 2.12 = 2.93 m2
0.72 x 2.12 = 1.53 m2
2.04 x 2.12 = 4.32 m2
0.72 x 0.57 = 0.41 m2
Jumlah = 14.75 m2
Jumlah = 372.25 m2
luas
12.25 = 12.25 m2

372.25 = 744.50 m2

tinggi
2.84 = 3.69 m2
0.47 = 0.96 m2
2.84 = 5.31 m2
Jumlah = m2

Lebar Tinggi panjang


0.06 x 0.15 x 5.34 = 0.19 m3
0.06 x 0.15 x 9.12 = 0.16 m3
0.06 x 0.15 x 5.68 = 0.10 m3
0.06 x 0.15 x 12.56 = 0.11 m3
0.06 x 0.15 x 2.58 = 0.21 m3
Jumlah = 0.78 m3

Lebar Tinggi
0.72 x 2.21 = 6.36 m2
Lebar Tinggi
0.62 x 2.02 = 5.01 m2
0.44 x 1.84 = 3.24 m2
= 1.77 m2
0.62 x 2.02 = 2.50 m2
0.44 x 1.84 = 1.62 m2
= 0.89 m2
0.62 x 2.02 = 3.76 m2
0.44 x 1.84 = 2.43 m2
= 1.33 m2
Jumlah = 3.99 m3

Tinggi lebar Sisi


0.45 x 1.85 = 3.33 m2
0.45 x 1.85 = 1.67 m2
0.45 x 1.85 = 2.50 m2
Jumlah = 7.49 m2

Lebar Tinggi
0.62 x 0.25 = 0.31 m2

= 1.00 unit

= 56.50 m2
= 56.50 m2
T. Panjang
28.40 = 28.40 m'
6.40 = 6.40 m'
12.40 = 12.40 m'
11.40 = 11.40 m'
Jumlah = 58.60 m'
unit

= 34.00 m2

lebar
1.50 = 3.00 m2

tinggi banyak
1.75 x 2.00 = 24.50 m2
1.10 x 2.00 = 3.30 m2
Jumlah = 27.80 m2

lebar sisi
4.28 x 2.00 = 48.36 m2
3.00 x 2.00 = 27.00 m2
3.28 x 2.00 = 18.11 m2
Jumlah = 93.47 m2

lebar sisi
4.28 x 2.00 = 48.36 m2
3.00 x 2.00 = 27.00 m2
3.28 x 2.00 = 18.11 m2
Jumlah = 93.47 m2

= 4.28 m'
= 3.00 m'
= 3.28 m'
Jumlah = 10.56 m'
sisi
2.00 = 8.56 m'
2.00 = 7.50 m'
2.00 = 8.06 m'
Jumlah = 24.12 m'

luas
12.25 = 12.25 m2
ing induk + Gewel = 744.50 m2
= 56.50 m2

lebar sisi
0.60 x 2.00 = 4.80 m2
0.60 x 2.00 = 1.80 m2
0.60 x 2.00 = 3.00 m2
Jumlah = 9.60 m2
T. sisi
0.22 = 5.31 m2

jumlah
1.00 unit = 4.00 unit
Jumlah = 4.00 unit
jumlah
3.00 = 12.00 bh
Jumlah = 12.00 bh
jumlah
1.00 = 4.00 bh
Jumlah = 4.00 bh
jumlah
2.00 = 4.00 bh
1.00 = 2.00 bh
3.00 = 3.00 bh
Jumlah = 9.00 bh

jumlah
4.00 = 8.00 bh
2.00 = 4.00 bh
6.00 = 6.00 bh
Jumlah = 18.00 bh
jumlah
4.00 = 8.00 bh
2.00 = 4.00 bh
6.00 = 6.00 bh
Jumlah = 18.00 bh
DAFTAR STANDARISASI HARGA SATUAN BAHAN & UPAH KERJA
NO. NAMA BAHAN SAT KET
HPS 2021 EE 2022

I. BAHAN PASIR

1 Pasir Pasang ( Lokal ) M³ 257,142.00 285,714


2 Pasir Pasang ( Jawa ) M³ 285,741.00
3 Pasir Urug ( Lokal ) M³ 71,428.00 78,570.80
4 Sirtu ( Jawa ) M³ 253,000.00
5 Pasir Cor ( Jawa ) M³ 285,714.00
6 Tanah Urug ( Lokal ) M³ 82,500.00
7 Pudel Putih ( Lokal ) M³ 57,142.00
8 Pudel Kuning / Pasir Katel ( Lokal ) M³ 115,000.00
9 Abu Batu M³ 310,500.00

II. BAHAN BATU

1 Batu Gunung Belah 15/20 ( Lokal ) M³ 192,500.00


2 Batu Gunung Belah 10/15 ( Lokal ) M³ 225,100.00
3 Batu Gunung Pecah 5/7 ( Lokal ) M³ 238,300.00
4 Batu Gunung Pecah 4/6 ( Lokal ) M³ 284,200.00
5 Batu Gunung Pecah 3/5 ( Lokal ) M³ 283,000.00
6 Batu Gunung Pecah 2/3 ( Lokal ) M³ 833,500.00
7 Batu Gunung Split 0,5 ( Jawa ) M³ 301,050.00 331,155.00
8 Batu Pecah Tempel/Hiasan ( Jawa ) M³ 172,500.00
9 Batu Setrikan ( Batu Rain ) Lokal Dia. 18-20 Cm M² 1,600.00
10 Batu Setrikan ( Batu Rain ) Jawa Dia. 13-15 Cm M² 2,300.00

III. BAHAN KORAL/KERIKIL

1 Batu Pecah Mesin 1/2 ( Jawa ) M³ 427,750.00


2 Batu Pecah Mesin 2/3 ( Jawa ) M³ 399,000.00

IV. BAHAN BATU BATA

1 Batu Bata Merah ( Jawa ) Bh 1,200.00


2 Batu Putih ( Lokal ) Bh 1,000.00
3 Batu Bata Merah ( Lokal ) Bh 1,000.00
4 Bataco Bh 5,200.00
5 Paving Stone 6 Cm ( Lokal ) M² 54,000.00
6 Paving Stone 6 Cm K-350 ( Jawa ) M² 65,500.00
7 Paving Stone 8 Cm K-350 ( Jawa ) M² 98,900.00
8 Paving Stone 8 Cm K-300 ( Jawa ) Warna/Motif M²
9 Kanstein 15 x 30 x 50 Cm Bh 40,200.00
10 Curbing 8 Cm ( Jawa ) Bh 5,100.00
11 Koral Sikat M² 253,000.00
12 Glass Block M² 28,700.00

V. PORTLAND CEMENT ( PC )

1 Semen Gresik 40 Kg Zak 62,000.00


2 Semen Tiga Roda 40 Kg Zak 58,000.00
3 Semen Putih ( Azona / Tiga Roda ) 50 Kg Zak 120,700.00
4 Semen Putih ( Gresik ) 40 Kg Zak 97,700.00

VI. BAHAN KAPUR

1 Kapur Bubuk / Kapur Pasang M³ 632,500.00


2 Kapur Gamping Kg 6,900.00

VII. BAHAN BESI

1 Besi Beton Polos Kg 15,500.00


2 Besi Beton Ulir Kg 15,500.00
3 Pipa air Galvanis Medium 1/2" x 6,00 m' Ljr 402,500.00
4 Pipa air Galvanis Medium 3/4" x 6,00 m' Ljr 460,000.00
5 Pipa Air Galvanis Medium 1" Ljr 747,500.00
6 Pipa Air Galvanis Medium 2" x 6,00 m' Ljr 1,403,000.00
7 Pipa Air Galvanis medium 2,5" x 6,00 m' Ljr 1,610,000.00
8 Kawat Beton / Kawat Bendrat Kg 18,400.00
9 Pipa Hitam Kg 27,600.00
10 Kawat Brojong Kg 22,400.00
11 Baut Baja + Mur Baja Kg 25,100.00
12 Baja Konstruksi / Profil Kg 18,400.00
13 Besi Siku 5.5 x 50 x 6,00 m" Kg
NO. NAMA BAHAN SAT KET
HPS 2021 EE 2022
VIII. BAHAN LANTAI

1 Tegel abu-abu 20 x 20 cm M² 0.00 0.00


2 Tegel Wafel / Berwarna 20 x 20 cm M² 0.00 0.00
3 Tegel plint abu-abu 20 x 20 cm M' 0.00 0.00
4 Tegel plint Wafel / Berwarna 20 x 20 cm M' 0.00 0.00
5 Tegel Trasso 20 x 20 cm M² 0.00 0.00
6 Tegel Trasso 30 x 30 cm M² 0.00 0.00
7 Tegel Plint Trasso 10 x 20 cm M' 0.00 0.00
8 Tegel Plint Trasso 10 x 30 cm M' 0.00 0.00
9 Marmer Klas I ( Lampung ) M² 892,000.00 981,200.00
10 Marmer Klas I ( Tulung Agung ) M² 557,500.00 613,250.00

IX. BAHAN KERAMIK

1 Porselein 11 x 11 cm Kw I M² 110,000.00
2 Porselein 15 x 15 cm Kw I M² 62,000.00
3 Keramik 10 x 20 cm Kw I M² 70,600.00
4 Keramik 20 x 20 cm Kw I M² 83,200.00
5 Keramik 20 x 25 cm Kw I M² 89,000.00
6 Keramik 30 x 30 cm Kw I M² 90,100.00
7 Keramik 40 x 40 cm Kw I M² 116,000.00

X. BAHAN BUIS BETON

1 Buis Beton 1/2 Bulat 15 cm x 1,00 m' Bh 29,250.00 32,175.00


2 Buis Beton 1/2 Bulat 20 cm x 1,00 m' Bh 39,000.00 42,900.00
3 Buis Beton 1/2 Bulat 30 cm x 1,00 m' Bh 42,350.00 46,585.00
4 Buis Beton Bulat 20 cm x 1,00 m' Bh 61,300.00 67,430.00
5 Buis Beton Bulat 30 cm x 1,00 m' Bh 72,450.00 79,695.00
6 Buis Beton Bulat 40 cm x 1,00 m' Bh 78,050.00 85,855.00
7 Buis Beton Bulat 50 cm x 0,50 m' Bh 80,800.00 88,880.00
8 Buis Beton Bulat 60 cm x 0,50 m' Bh 100,350.00 110,385.00
9 Buis Beton Bulat 80 cm x 0,50 m' Bh 122,650.00 134,915.00
10 Buis Beton Bulat 100 cm x 0,50 m' Bh 167,250.00 183,975.00

XI. BAHAN KAYU

1 Kayu Kamper Balok 8/12, 6/12, 8/15 Klas I M³ 12,650,000.00


2 Kayu Kamper Papan 3/20, 3/30 x 4,00 m' M³ 13,225,000.00
3 Kayu Bangkirai Balok 8/12, 6/12, 8/15 Klas I M³ 10,925,000.00
4 Kayu Bangkirai Papan 2/20, 3/20 x 4,00 m' M³ 11,500,000.00
5 Kayu Meranti Balok 3/15, 8/12, 6/12 Klas I M³ 6,325,000.00
6 Kayu Meranti Papan 2/20, 3/20 x 4,00 m' M³ 6,612,500.00
7 Kayu Papan Begesting 2/20 x 4,00 m' M³ 4,025,000.00
8 Kayu Jati Lokal Klas I M³ 20,125,000.00
9 Kayu Kelapa Btg 1,725,000.00
10 Kayu Untuk Perancah M³ 2,012,500.00
11 Kayu Bakar M³ 115,000.00
12 Bambu Bongkotan Btg 28,700.00
13 Gedek Halus M² 14,900.00
14 Gedek Kulitan M² 18,400.00
15 Kayu Dolken Btg 39,100.00
16 Kayu Jati Balok Ex. Bojonegoro M³ 73,600,000.00
17 Kayu Jati Balok Ex. Kangean M³ 51,750,000.00
18 Kayu Kempas Balok M³ 6,900,000.00
19 Kayu Kempas Papan M³ 7,475,000.00
20 Kayu Blangiran Balok M³ 6,900,000.00
21 Kayu List Profil M' 8,400.00 9,240.00

XII. BAHAN PENUTUP ATAP

1 Genteng Vlam Pres Lokal Bh 1,100.00


2 Genteng Bubungan Vlam Lokal Bh 3,100.00
3 Genteng Kodok Model Ex. Karang Penang Bh 1,800.00
4 Genteng Bubungan Ex. Karang Penang Bh 3,450.00
5 Genteng Kodok Ex. Bambe Bh 4,250.00
6 Genteng Bubungan Ex. Bambe Bh 10,900.00
7 Genteng Beton Bh 5,750.00
8 Bubungan Genteng Beton Bh 17,250.00
9 Genteng Glossur Ruby Maron Bh 15,700.00
10 Bubungan Genteng Glossur Ruby Maron Bh 31,600.00
11 Bubungan Jurai Keramik Glossur Bh 103,500.00
12 Bubungan Cabang 3 arah Keramik Glossur Bh 132,250.00
NO. NAMA BAHAN SAT KET
HPS 2021 EE 2022
XIII. BAHAN ASBES DATAR/GELOMBANG

1 Asbes Gelombang Kecil 2,10 x 1,05 x 0,4 mm Lbr 57,500.00


2 Nok / Karpus Asbes Gelombang Kecil M' 51,700.00
3 Asbes Gelombang Besar 1,050 x 2,442 x 0,6 mm Lbr 103,500.00
4 Nok / Karpus Asbes Gelombang Besar M' 69,000.00
5 Asbes Datar 1,00 x 1,00 m ex Gresik Lbr 20,700.00
6 Asbes Datar 1,00 x 1,00 m ex Atrisco Lbr 18,400.00
7 Asbes Datar 1,00 x 1,00 m ex Kerang Lbr 15,500.00
8 Asbes Datar 0,50 x 2,00 m Lbr 18,400.00
9 Asbes Datar 0,60 x 2,00 m Lbr 20,100.00
10 Calsiboard 1,22 x 2,44 m Tebal 4 mm Lbr 69,000.00
11 List Gypsum 15 cm M' 23,000.00

XIV. BAHAN SENG DATAR/GELOMBANG

1 Seng Gelombang BJLS 20 ( Uk 0,90 x 1,80 m ) Lbr 69,100.00 76,010.00


2 Seng Gelombang BJLS 26 ( Uk 0,90 x 1,80 m ) Lbr 78,050.00 85,855.00
3 Seng Gelombang BJLS 28 ( Uk 0,90 x 1,80 m ) Lbr 90,850.00 99,935.00
4 Seng Gelombang BJLS 30 ( Uk 0,90 x 1,80 m ) Lbr 98,100.00 107,910.00
5 Seng Gelombang BWG 26 ( Uk 0,90 x 1,80 m ) Lbr 107,000.00 117,700.00
6 Seng Gelombang BWG 28 ( Uk 0,90 x 1,80 m ) Lbr 112,600.00 123,860.00
7 Seng Gelombang BWG 30 ( Uk 0,90 x 1,80 m ) Lbr 128,200.00 141,020.00
8 Seng Plat / Datar BJLS 26 ( 0,60 x 1,00 m ) M' 39,550.00 43,505.00
9 Seng Plat / Datar BJLS 28 ( 0,60 x 1,00 m ) M' 41,800.00 45,980.00
10 Seng Plat / Datar BJLS 30 ( 0,60 x 1,00 m ) M' 44,600.00 49,060.00
11 Seng Plat / Datar BWG 38 ( 0,60 x 1,00 m ) M' 0.00 0.00
12 Seng Plat / Datar BWG 30 ( 0,60 x 1,00 m ) M' 0.00 0.00

XV. BAHAN PIPA PARALON/PVC SANITASI

1 Pipa PVC 1/2" x 4,00 M' (AW) Ljr 27,900.00 30,690.00


2 Pipa PVC 3/4" x 4,00 M' (AW) Ljr 53,500.00 58,850.00
3 Pipa PVC 1" x 4,00 M' (AW) Ljr 57,400.00 63,140.00
4 Pipa PVC 1,5" x 4,00 M' (D) Ljr 39,000.00 42,900.00
5 Pipa PVC 2" x 4,00 M' (AW) Ljr 78,050.00 85,855.00
6 Pipa PVC 2" x 4,00 M' (D) Ljr 50,200.00 55,220.00
7 Pipa PVC 2,5" x 4,00 M' (AW) Ljr 133,800.00 147,180.00
8 Pipa PVC 2,5" x 4,00 M' (D) Ljr 72,450.00 79,695.00
9 Pipa PVC 3" x 4,00 M' (AW) Ljr 144,950.00 159,445.00
10 Pipa PVC 3" x 4,00 M' (D) Ljr 3,600.00 3,960.00
11 Pipa PVC 4" x 4,00 M' (AW) Ljr 189,550.00 208,505.00
12 Pipa PVC 4" x 4,00 M' (D) Ljr 105,900.00 116,490.00
13 Pipa PVC 6" x 4,00 M' (AW) Ljr 278,250.00 306,075.00
14 Pipa PVC 6" x 4,00 M' (D) Ljr 156,100.00 171,710.00
15 Pipa PVC 1,5" x 4,00 M' (AW) Ljr 56,800.00 62,480.00

XVI. BAHAN CAT

1 Plamur Tembok Kg 19,500.00 21,450.00


2 Plamur Kayu Ex Pedang Kg 22,300.00 24,530.00
3 Cat Kayu/ Besi ex EMCO Kg 58,000.00 63,800.00
4 Cat Tembok Decolith ( 5 Kg ) Gln 78,050.00 85,855.00
5 Cat Tembok Paragon ( 5 Kg ) Gln 75,250.00 82,775.00
6 Cat Tembok Eks. Altex ( 20 Kg ) Gln 356,800.00 392,480.00
7 Cat Dinding Standart Eksterior 2.5 Ltr 267,600.00 294,360.00
8 Cat Dinding Standart Interior 2.5 Ltr 178,400.00 196,240.00
9 Cat Dinding Khusus Eksterior 2.5 Ltr 295,500.00 325,050.00
10 Cat Dinding Khusus Interior 2.5 Ltr 223,000.00 245,300.00
11 Dempul Kayu / Besi Kg 37,900.00 41,690.00
12 Minyak Cat /Tinner A Ltr 22,300.00 24,530.00
13 Minyak Cat /Tinner B Ltr 16,750.00 18,425.00
14 Cat Meni ( Kayu ) Kg 27,850.00 30,635.00
15 Cat Meni ( Besi ) Kg 25,100.00 27,610.00
16 Cat Dasar (Kayu) Kg 50,150.00 55,165.00
17 Cat Dasar ( Dinding ) Kg 16,700.00 18,370.00
18 Plitur Biasa Ltr 44,600.00 49,060.00
19 Plitur Warna Ltr 55,750.00 61,325.00
20 Plitur Ex. Ultran Lazur ( 2 Ltr ) Ltr 72,450.00 79,695.00
21 Spritus Ltr 22,300.00 24,530.00
22 Cat Brown Kg 61,300.00 67,430.00
23 Lem Kg 13,350.00 14,685.00
24 Amplas Lbr 7,800.00 8,580.00
25 Zincromate Kg 33,450.00 36,795.00
26 Residu Ltr 22,300.00 24,530.00
27 Lem Pipa Tube 8,350.00 9,185.00
NO. NAMA BAHAN SAT KET
HPS 2021 EE 2022
XVII. BAHAN KACA POLOS/RAYBEN

1 Kaca Buram 5 mm M² 117,000.00 128,700.00


2 Kaca Polos 5 mm M² 105,900.00 116,490.00
3 Kaca Rayben 5 mm M² 117,000.00 128,700.00
4 Kaca Nako + Kerangka merk Nicky Daun 33,450.00 36,795.00
5 Krepyak Kaca Nako Daun 13,350.00 14,685.00
6 Kaca Es 3 mm Daun 95,000.00 104,500.00

XVIII. BAHAN TRIPLEK/KAYU LAPIS

1 Triplek 1,22 x 2,44 x 4 mm Lbr 55,750.00 61,325.00


2 Multiplek 1,22 x 2,44 x 6 mm Lbr 72,450.00 79,695.00
3 Multiplek 1,22 x 2,44 x 9 mm Lbr 122,650.00 134,915.00
4 Teakwood 1,22 x 2,44 x 4 mm Lbr 83,600.00 91,960.00

XIX. BAHAN ALAT PENGGANTUNG/PENGUNCI

1 Kunci 2x Putar Ex. Kuda Terbang Kecil Bh 61,300.00 67,430.00


2 Kunci 2x Putar Setara Ex. Merk Union Besar Bh 0.00 0.00
3 Kunci 2x Putar Setara Ex. Merk Union Kecil Bh 0.00 0.00
4 Kunci 2x Putar Setara Ex. Merk Bagus Bh 195,100.00 214,610.00
5 Kunci 2x Putar Setara Ex. Merk Anchor Besar Bh 150,500.00 165,550.00
6 Kunci 2x Putar Setara Ex. Merk Anchor Kecil Bh 122,650.00 134,915.00
7 Engsel Nylon Setara Ex. Arch Besar ( Pintu ) Stel 22,300.00 24,530.00
8 Engsel Nylon Setara Ex. Arch Kecil ( Jendela ) Stel 18,950.00 20,845.00
9 Grendel Besar ( Pintu ) Bh 27,850.00 30,635.00
10 Grendel Kecil ( Jendela ) Bh 11,150.00 12,265.00
11 Hak Angin Besar Bh 16,700.00 18,370.00
12 Hak Angin Kecil Bh 8,350.00 9,185.00

XX. BAHAN SANITASI

1 Closed Jongkok Porselin ( Ex. INA, KIA ) Bh 167,250.00 183,975.00


2 Closed Duduk Porselin ( Ex . Toto ) Bh 836,200.00 919,820.00
3 Closed Monoblok ( Ex. Toto ) Set 3,902,500.00 4,292,750.00
4 Closed Monoblok ( Ex. KIA ) Set 1,672,500.00 1,839,750.00
5 Closed Monoblok ( Ex. INA ) Set 156,100.00 171,710.00
6 Bak Mandi Fiberglass Bh 669,000.00 735,900.00
7 Bak Cuci Tangan /Wastafel Besar ( Ex. INA ) Bh 446,000.00 490,600.00
8 Bak Cuci Tangan /Wastafel Kecil ( Ex. INA ) Bh 278,750.00 306,625.00
9 Bak Cuci Piring Aluminium Bh 390,250.00 429,275.00
10 Kran Air 3/4 Bh 133,800.00 147,180.00
11 Kran Air 1/2 Stainlessteel Bh 100,350.00 110,385.00
12 Kran Air 1/2 Plastik Bh 16,700.00 18,370.00
13 Floor Drain Bh 22,300.00 24,530.00
14 Avour Bak Mandi Bh 27,900.00 30,690.00
15 Tempat Sabun ( Besar ) Bh 33,450.00 36,795.00
16 Tempat Sabun ( Kecil ) Bh 27,900.00 30,690.00

XXI. BAHAN PAKU

1 Paku Reng Kg 16,700.00 18,370.00


2 Paku Usuk Kg 14,500.00 15,950.00
3 Paku Triplek Kg 19,000.00 20,900.00
4 Paku Seng Kg 22,300.00 24,530.00
5 Paku Jembatan / Sumbat Kg 27,900.00 30,690.00
6 Paku Sekrup Kg 27,900.00 30,690.00
7 Paku Baja / Kait Kg 33,450.00 36,795.00
8 Paku Kayu / Dudor Kg 0.00 0.00

XXII. BAHAN LAMPU

1 Lampu TL Komplit 20 watt Ex. Chiyoda Bh 66,900.00 73,590.00


2 Lampu TL Komplit 40 watt Ex. Chiyoda Bh 89,200.00 98,120.00
3 Lampu TL Komplit 20 watt Ex. Phillips Bh 83,700.00 92,070.00
4 Lampu TL Komplit 40 watt Ex. Phillips Bh 111,500.00 122,650.00
5 Lampu SL 8 watt Ex. Philips Bh 33,450.00 36,795.00
6 Lampu SL 14 watt Ex. Philips Bh 39,000.00 42,900.00
7 Lampu Pijar 10 - 60 watt Ex. Chiyoda Bh 16,750.00 18,425.00
8 Lampu Pijar 10 - 60 watt Ex. Phillip Bh 22,300.00 24,530.00
9 Titik Lampu + Instalasi Set 144,950.00 159,445.00
10 Stop Kontak + Instalasi Ex. Merk Broco Bh 161,700.00 177,870.00
11 Stop Kontak Tunggal Ex. Merk Broco Bh 22,300.00 24,530.00
12 Stop Kontak Ganda Ex. Merk Broco Bh 33,450.00 36,795.00
13 Saklar Tunggal Ex. Merk Broco Bh 16,750.00 18,425.00
14 Saklar Ganda Ex. Merk Broco Bh 22,300.00 24,530.00
15 MCB + Box 1 Group Lokal Bh 89,200.00 98,120.00
16 MCB + Box 2 Group Lokal Bh 144,950.00 159,445.00
17 MCB + Box 3 Group Lokal Bh 200,700.00 220,770.00
18 MCB + Box 4 Group Lokal Bh 256,450.00 282,095.00
NO. NAMA BAHAN SAT KET
HPS 2021 EE 2022
XXIII. BAHAN KABEL LISTRIK/SUPREME

1 Kabel NYA / NGA 1000 1,50 mm ex. Supreme M' 206,300.00 226,930.00
2 Kabel NYA / NGA 1000 2,50 mm M' 30,700.00 33,770.00
3 Kabel NYA / NGA 1000 4,00 mm M' 0.00 0.00
4 Kabel NYM Uk 2 x 2.5 mm M' 947,750.00 1,042,525.00
5 Kabel NYM Uk 4 x 6 mm M' 0.00 0.00
6 Kabel BC 4 mm M' 7,800.00 8,580.00
7 Kabel BC 6 mm M' 10,100.00 11,110.00
8 Kabel BC 10 mm M' 16,750.00 18,425.00
9 Kabel BC ( Penangkal Petir ) 16 mm M' 27,900.00 30,690.00
10 Kabel BC ( Penangkal Petir ) 25 mm M' 33,450.00 36,795.00

XXIV. BAHAN ASPAL/LAIN-LAIN

1 Aspal 60/70 - 150 kg ( Pertamina ) Kg 10,050.00 11,055.00


2 Aspal Curah Kg 9,800.00 10,780.00
3 Tear Kg 7,800.00 8,580.00
4 Plinkoat Air Kg 39,000.00 42,900.00
5 Plinkoat Minyak Kg 41,800.00 45,980.00
6 Minyak Diesel / solar Ltr 10,650.00 11,715.00
7 Minyak Bakar Ltr 600.00 660.00
8 Minyak Tanah Ltr 11,000.00 12,100.00
9 Minyak Begisting Ltr 3,000.00 3,300.00
10 Bensin / Premium Ltr 10,000.00 11,000.00
11 Minyak Pelumas / Oli Ltr 35,000.00 38,500.00
12 Stempet / Gemuk Kg 33,000.00 36,300.00
13 Ijuk Ikat 21,750.00 23,925.00
14 Kawat Duri M² 16,700.00 18,370.00
15 Kawat Nyamuk / Kasa Plastik M² 22,300.00 24,530.00
16 Kawat Nyamuk / Kasa Logam M² 27,900.00 30,690.00
17 Kawat Harmonika M² 39,000.00 42,900.00
18 Beton Rooster / Kerawang Bakar 25/25 Bh 27,900.00 30,690.00
19 Beton Rooster / Kerawang Bakar 10/25 Bh 22,300.00 24,530.00
20 Beton Rooster / Kerawang Bakar 30/30 Bh 33,450.00 36,795.00
21 Elektrode Las Kg 16,900.00 18,590.00
22 Sewa Welding Set Jam 77,300.00 85,030.00
23 Filler Kg 675.00 742.50
24 Alat - alat Bantu Unit 175,000.00 192,500.00

X BAHAN ALUMINIUM
1 Skrup/Ripet bh 275.00
2 Aluminium Putih Uk. 3 x 8, Profil 3" m1 69,300.00
3 Karet Kusen Aluminium m 33,000.00
4 Aluminium Putih Uk. 4 x 10, Profil 4" m1 82,500.00
5 Baja Plat kg 15,840.00
6 Sunscreen ( sirip aluminium ) m 19,272.00
7 Cat Besi sunshading (ex.Nippe) m2
8 Sealant tube 23,760.00
9 Pintu alumunium m2 528,000.00
NO. NAMA BAHAN SAT KET
HPS 2021 EE 2022

XXV. UPAH KERJA

1 Mandor Hari 150,000.00


2 Kepala Tukang Gali Tanah Hari 140,000.00
3 Kepala Tukang Batu Hari 140,000.00
4 Kepala Tukang Kayu Hari 140,000.00
5 Kepala Tukang Besi Hari 140,000.00
6 Kepala Tukang Cat Hari 140,000.00
7 Kepala Tukang Listrik Hari 125,000.00
8 Tukang Gali Tanah Hari 125,000.00
9 Tukang Batu Hari 125,000.00
10 Tukang Kayu Hari 125,000.00
11 Tukang Besi Hari 125,000.00
12 Tukang Cat Hari 125,000.00
13 Tukang Listrik Hari 125,000.00
14 Tukang Pipa Hari 125,000.00
15 Pembantu Tukang/Pekerja Terampil Hari 100,000.00
16 Mekanik Hari
17 Mekanik Pembantu Hari
18 Buruh Terampil Hari
19 Buruh Tak Terampil Hari
20 Operator Terlatih Hari
21 Operator Kurang Terlatih Hari
22 Pembantu Operator Hari
23 Supir Material/Truck Hari
24 Supir Personil Hari
25 Pembantu Supir/Kenek Hari
26 Pekerja Harian Tetap Hari
27 Penjaga Harian Hari
28 Montir Hari
29 Masinis Hari
30 Penjaga Malam ( Waker ) Hari
DAFTAR ANALISA BIAYA
DINAS PU BINA MARGA DAN PENGAIRAN
KABUPATEN BANGKALAN
TAHUN 2013

SNI. 03-2835-2002 PEKERJAAN PERSIAPAN


1 1,00 M' Pengukuran dan Pemasangan Bowplank
Bahan :
0.012 M3 Usuk Meranti @ Rp. 6,325,000.00 75,900.00
0.007 M3 Papan Meranti @ Rp. 6,612,500.00 46,287.50
0.020 Kg Paku @ Rp. 15,950.00 319.00
Upah :
0.100 Oh Pekerja @ Rp. 100,000.00 10,000.00
0.100 Oh Tukang Kayu @ Rp. 125,000.00 12,500.00
0.010 Oh Kep. Tukang @ Rp. - -
0.005 Oh Mandor @ Rp. 150,000.00 750.00
122,506.50 23,250.00
Jumlah 145,756.50

2 1,00 M2 Pekerjaan Pembersihan Lapangan dan Perataan


Upah :
0.100 Oh Pekerja @ Rp. 100,000.00 10,000.00
0.050 Oh Mandor @ Rp. 150,000.00 7,500.00
Jumlah 17,500.00

3 1,00 M3 Pekerjaan Pembongkaran Beton Bertulang


Upah :
6.667 Oh Pekerja @ Rp. 100,000.00 666,700.00
0.333 Oh Mandor @ Rp. 150,000.00 49,950.00
Jumlah 716,650.00

4 1,00 M3 Pekerjaan Pembongkaran Dinding Tembok Bata Merah


Upah :
6.667 Oh Pekerja @ Rp. 100,000.00 666,700.00
0.033 Oh Mandor @ Rp. 150,000.00 4,950.00
Jumlah 671,650.00

5 1,00 M2 Pekerjaan Pembongkaran Lantai


Upah :
0.800 Oh Pekerja @ Rp. 100,000.00 80,000.00
0.008 Oh Mandor @ Rp. 150,000.00 1,200.00
Jumlah 81,200.00

6 1,00 M2 Pekerjaan Pembongkaran Usuk / Reng ( Atap )


Upah :
0.040 Oh Pekerja @ Rp. 100,000.00 4,000.00
0.004 Oh Mandor @ Rp. 150,000.00 600.00
4,600.00

SNI. 2835-2008 PEKERJAAN TANAH


7 1,00 M3 Pekerjaan Galian Tanah Biasa Sedalam 1 Meter
Upah :
0.750 Oh Pekerja @ Rp. 100,000.00 75,000.00
0.025 Oh Mandor @ Rp. 150,000.00 3,750.00
Jumlah 78,750.00

8 1,00 M3 Pekerjaan Galian Tanah Biasa Sedalam 2 Meter


Upah :
0.900 Oh Pekerja @ Rp. 100,000.00 90,000.00
0.045 Oh Mandor @ Rp. 150,000.00 6,750.00
Jumlah 96,750.00

9 1,00 M3 Pekerjaan Galian Tanah Keras Sedalam 1 Meter


Upah :
1.000 Oh Pekerja @ Rp. 100,000.00 100,000.00
0.032 Oh Mandor @ Rp. 150,000.00 4,800.00
Jumlah 104,800.00

10 1,00 M3 Pekerjaan Galian Tanah Berbatu Sedalam 1 Meter


Upah :
1.250 Oh Pekerja @ Rp. 100,000.00 125,000.00
0.125 Oh Mandor @ Rp. 150,000.00 18,750.00
Jumlah 143,750.00

11 1,00 M3 Pekerjaan Galian Tanah Lumpur Sedalam 1 Meter


Upah :
0.823 Oh Pekerja @ Rp. 100,000.00 82,300.00
0.083 Oh Mandor @ Rp. 150,000.00 12,450.00
Jumlah 94,750.00

12 1,00 M3 Urugan Tanah Kembali


Upah :
0.192 Oh Pekerja @ Rp. 100,000.00 19,200.00
0.019 Oh Mandor @ Rp. 150,000.00 2,850.00
Jumlah 22,050.00

13 1,00 M3 Pemadatan Tanah


Upah :
0.500 Oh Pekerja @ Rp. 100,000.00 50,000.00
0.050 Oh Mandor @ Rp. 150,000.00 7,500.00
Jumlah 57,500.00

14 1,00 M3 Urugan Peddel


Bahan :
1.200 M3 Peddel Putih @ Rp. 57,142.00 68,570.40
Sewa alat + Pemadatan 3,000.00
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.010 Oh Mandor @ Rp. 150,000.00 1,500.00
71,570.40 31,500.00
Jumlah 103,070.40

15 1,00 M3 Urugan Pasir


Bahan :
1.200 M3 Pasir Pasang (Lokal) @ Rp. 257,142.00 308,570.40
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.010 Oh Mandor @ Rp. 150,000.00 1,500.00
308,570.40 31,500.00
Jumlah 340,070.40

16 1,00 M3 Urugan Tanah Lokal


Bahan :
1.200 M3 Tanah Urug (Lokal) @ Rp. 82,500.00 99,000.00
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.010 Oh Mandor @ Rp. 150,000.00 1,500.00
99,000.00 31,500.00
Jumlah 130,500.00

17 1,00 M2 Pekerjaan Stripping Setinggi 1 Meter


Upah :
0.050 Oh Pekerja @ Rp. 100,000.00 5,000.00
0.005 Oh Mandor @ Rp. 150,000.00 750.00
5,750.00
Jumlah 5,750.00

18 1,00 M3 Pekerjaan Pembuangan Tanah Sejauh 15 Meter


Upah :
0.330 Oh Pekerja @ Rp. 100,000.00 33,000.00
0.010 Oh Mandor @ Rp. 150,000.00 1,500.00
34,500.00
Jumlah 34,500.00

19 1,00 M' Pekerjaan Pengeboran Strausz O 30 Cm


Bahan :
0.250 Hr Sewa Bor Strouss @ Rp. 28,750.00 7,187.50
Upah :
0.125 Oh Pekerja @ Rp. 100,000.00 12,500.00
0.250 Oh Mandor @ Rp. 150,000.00 37,500.00
7,187.50 50,000.00
Jumlah 57,187.50
SNI. 2836-2008 PEKERJAAN PONDASI
20 1,00 M3 Pasangan Batu Kosong ( Anstamping )
Bahan :
1.200 M3 Batu Belah 15 / 20 ( Lokal ) @ Rp. 192,500.00 231,000.00
0.432 M3 Pasir Urug (Lokal) @ Rp. 257,142.00 111,085.34
Upah :
0.780 Oh Pekerja @ Rp. 100,000.00 78,000.00
0.390 Oh Tukang Batu @ Rp. 125,000.00 48,750.00
0.039 Oh Kepala Tukang Batu @ Rp. - -
0.039 Oh Mandor @ Rp. 150,000.00 5,850.00
342,085.34 132,600.00
Jumlah 474,685.34

21 1,00 M3 Pasangan Batu Gunung Campuran 1 Pc : 3 Ps


Bahan :
1.200 M3 Batu Belah 15 / 20 ( Lokal ) @ Rp. 192,500.00 231,000.00
202.000 Kg Semen ( Pc ) @ Rp. 1,550.00 313,100.00
0.485 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 138,584.39
Upah
1.500 Oh Pekerja @ Rp. 100,000.00 150,000.00
0.750 Oh Tukang Batu @ Rp. 125,000.00 93,750.00
0.075 Oh Kepala Tukang Batu @ Rp. - -
0.075 Oh Mandor @ Rp. 150,000.00 11,250.00
682,684.39 255,000.00
Jumlah 937,684.39

22 1,00 M3 Pasangan Batu Gunung Campuran 1 Pc : 4 Ps


Bahan :
1.200 M3 Batu Belah 15 / 20 ( Lokal ) @ Rp. 192,500.00 231,000.00
163.000 Kg Semen ( Pc ) @ Rp. 1,550.00 252,650.00
0.520 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 148,585.32
Upah
1.500 Oh Pekerja @ Rp. 100,000.00 150,000.00
0.750 Oh Tukang Batu @ Rp. 125,000.00 93,750.00
0.075 Oh Kepala Tukang Batu @ Rp. - -
0.075 Oh Mandor @ Rp. 150,000.00 11,250.00
632,235.32 255,000.00
Jumlah 887,235.32

23 1,00 M3 Pasangan Batu Gunung Campuran 1 Pc : 5 Ps


Bahan :
1.200 M3 Batu Belah 15 / 20 ( Lokal ) @ Rp. 192,500.00 231,000.00
136.000 Kg Semen ( Pc ) @ Rp. 1,550.00 210,800.00
0.544 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 155,443.10
Upah
1.500 Oh Pekerja @ Rp. 100,000.00 150,000.00
0.750 Oh Tukang Batu @ Rp. 125,000.00 93,750.00
0.075 Oh Kepala Tukang Batu @ Rp. - -
0.075 Oh Mandor @ Rp. 150,000.00 11,250.00
597,243.10 255,000.00
Jumlah 852,243.10

24 1,00 M3 Pasangan Batu Gunung Campuran 1 Pc : 6 Ps


Bahan :
1.200 M3 Batu Belah 15 / 20 ( Lokal ) @ Rp. 192,500.00 231,000.00
117.000 Kg Semen ( Pc ) @ Rp. 1,550.00 181,350.00
0.561 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 160,300.70
Upah :
1.500 Oh Pekerja @ Rp. 100,000.00 150,000.00
0.750 Oh Tukang Batu @ Rp. 125,000.00 93,750.00
0.075 Oh Kepala Tukang Batu @ Rp. - -
0.075 Oh Mandor @ Rp. 150,000.00 11,250.00
572,650.70 255,000.00
Jumlah 827,650.70

SNI. 6897-2008 PEKERJAAN DINDING (PASANGAN)


25 1,00 M2 Pasangan Bata Merah (Tembok) Tebal 1/2 Bata Camp. 1 Pc : 2 Ps
Bahan :
70.000 Bh Bata Merah ( Lokal ) @ Rp. 1,000.00 70,000.00
18.950 Kg Semen ( Pc ) @ Rp. 1,550.00 29,372.50
0.038 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 10,858.16
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
110,230.66 44,750.00
Jumlah 154,980.66

26 1,00 M2 Pasangan Bata Merah (Tembok) Tebal 1/2 Bata Camp. 1 Pc : 3 Ps


Bahan :
70.000 Bh Bata Merah ( Lokal ) @ Rp. 1,000.00 70,000.00
14.370 Kg Semen ( Pc ) @ Rp. 1,550.00 22,273.50
0.040 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 11,429.64
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
103,703.14 44,750.00
Jumlah 148,453.14

27 1,00 M2 Pasangan Bata Merah (Tembok) Tebal 1/2 Bata Camp. 1 Pc : 4 Ps


Bahan :
70.000 Bh Bata Merah ( Lokal ) @ Rp. 1,000.00 70,000.00
11.500 Kg Semen ( Pc ) @ Rp. 1,550.00 17,825.00
0.043 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 12,286.86
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
100,111.86 44,750.00
Jumlah 144,861.86

28 1,00 M2 Pasangan Bata (Tembok) Tebal 1/2 Bata Camp. 1 Pc : 4 Ps


Bahan :
55.000 Bh Bata Putih ( Lokal ) @ Rp. 1,000.00 55,000.00
11.500 Kg Semen ( Pc ) @ Rp. 1,550.00 17,825.00
0.043 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 12,286.86
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
85,111.86 44,750.00
Jumlah 129,861.86

29 1,00 M2 Pasangan Bata Merah (Tembok) Tebal 1/2 Bata Camp. 1 Pc : 5 Ps


Bahan :
70.000 Bh Bata Merah ( Lokal ) @ Rp. 1,000.00 70,000.00
9.680 Kg Semen ( Pc ) @ Rp. 1,550.00 15,004.00
0.045 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 12,858.35
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
97,862.35 44,750.00
Jumlah 142,612.35

30 1,00 M2 Pasangan Bata Merah (Tembok) Tebal 1/2 Bata Camp. 1 Pc : 6 Ps


Bahan :
70.000 Bh Bata Merah ( Lokal ) @ Rp. 1,000.00 70,000.00
8.320 Kg Semen ( Pc ) @ Rp. 1,550.00 12,896.00
0.049 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 14,001.31
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
96,897.31 44,750.00
Jumlah 141,647.31

31 1,00 M2 Pasangan Bata (Tembok) Tebal 1/2 Bata Camp. 1 Pc : 6 Ps


Bahan :
55.000 Bh Bata Putih ( Lokal ) @ Rp. 1,000.00 55,000.00
8.320 Kg Semen ( Pc ) @ Rp. 1,550.00 12,896.00
0.049 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 14,001.31
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
81,897.31 44,750.00
Jumlah 126,647.31

32 1,00 M2 Pasangan Bata Merah (Tembok) Tebal 1 Bata Camp. 1 Pc : 2 Ps


Bahan :
140.000 Bh Bata Merah ( Lokal ) @ Rp. 1,000.00 140,000.00
43.500 Kg Semen ( Pc ) @ Rp. 1,550.00 67,425.00
0.080 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 22,859.28
Upah :
0.600 Oh Pekerja @ Rp. 100,000.00 60,000.00
0.200 Oh Tukang Batu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Batu @ Rp. - -
0.030 Oh Mandor @ Rp. 150,000.00 4,500.00
230,284.28 89,500.00
Jumlah 319,784.28

33 1,00 M2 Pasangan Bata Merah (Tembok) Tebal 1 Bata Camp. 1 Pc : 3 Ps


Bahan :
140.000 Bh Bata Merah ( Lokal ) @ Rp. 1,000.00 140,000.00
32.950 Kg Semen ( Pc ) @ Rp. 1,550.00 51,072.50
0.091 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 26,002.43
Upah :
0.600 Oh Pekerja @ Rp. 100,000.00 60,000.00
0.200 Oh Tukang Batu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Batu @ Rp. - -
0.030 Oh Mandor @ Rp. 150,000.00 4,500.00
217,074.93 89,500.00
Jumlah 306,574.93

34 1,00 M2 Pasangan Bata Merah (Tembok) Tebal 1 Bata Camp. 1 Pc : 4 Ps


Bahan :
140.000 Bh Bata Merah ( Lokal ) @ Rp. 1,000.00 140,000.00
26.550 Kg Semen ( Pc ) @ Rp. 1,550.00 41,152.50
0.093 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 26,573.91
Upah :
0.600 Oh Pekerja @ Rp. 100,000.00 60,000.00
0.200 Oh Tukang Batu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Batu @ Rp. - -
0.030 Oh Mandor @ Rp. 150,000.00 4,500.00
207,726.41 89,500.00
Jumlah 297,226.41

35 1,00 M2 Pasangan Bata Merah (Tembok) Tebal 1 Bata Camp. 1 Pc : 6 Ps


Bahan :
140.000 Bh Bata Merah ( Lokal ) @ Rp. 1,000.00 140,000.00
18.500 Kg Semen ( Pc ) @ Rp. 1,550.00 28,675.00
0.122 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 34,860.40
Upah :
0.600 Oh Pekerja @ Rp. 100,000.00 60,000.00
0.200 Oh Tukang Batu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Batu @ Rp. - -
0.030 Oh Mandor @ Rp. 150,000.00 4,500.00
203,535.40 89,500.00
Jumlah 293,035.40

36 1,00 M2 Pasangan Roolag


Bahan :
140.000 Bh Bata Merah ( Lokal ) @ Rp. 1,000.00 140,000.00
26.550 Kg Semen ( Pc ) @ Rp. 1,550.00 41,152.50
0.093 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 26,573.91
Upah :
0.600 Oh Pekerja @ Rp. 100,000.00 60,000.00
0.200 Oh Tukang Batu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Batu @ Rp. - -
0.030 Oh Mandor @ Rp. 150,000.00 4,500.00
207,726.41 89,500.00
Jumlah 297,226.41

37 1,00 M2 Pasang Rooster 10/25 Camp. 1 Pc : 3 Ps


Bahan :
30.000 Bh Rooster/Kerawang 10 x 25 @ Rp. 24,530.00 735,900.00
14.000 Kg Semen ( Pc ) @ Rp. 1,550.00 21,700.00
0.032 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 9,143.71
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
766,743.71 44,750.00
Jumlah 811,493.71

SNI. 2837-2008 PEKERJAAN PLESTERAN


38 1,00 M2 Plesteran Tembok Camp. 1 Pc : 2 Ps Tebal 15 Mm
Bahan :
10.224 Kg Semen ( Pc ) @ Rp. 1,550.00 15,847.20
0.020 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 5,714.82
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.150 Oh Tukang Batu @ Rp. 125,000.00 18,750.00
0.015 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
21,562.02 51,000.00
Jumlah 72,562.02

39 1,00 M2 Plesteran Tembok Camp. 1 Pc : 3 Ps Tebal 15 Mm


Bahan :
7.776 Kg Semen ( Pc ) @ Rp. 1,550.00 12,052.80
0.023 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 6,572.04
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.150 Oh Tukang Batu @ Rp. 125,000.00 18,750.00
0.015 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
18,624.84 51,000.00
Jumlah 69,624.84

40 1,00 M2 Plesteran Tembok Camp. 1 Pc : 4 Ps Tebal 15 Mm


Bahan :
6.240 Kg Semen ( Pc ) @ Rp. 1,550.00 9,672.00
0.024 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 6,857.78
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.150 Oh Tukang Batu @ Rp. 125,000.00 18,750.00
0.015 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
16,529.78 51,000.00
Jumlah 67,529.78

41 1,00 M2 Plesteran Tembok Camp. 1 Pc : 5 Ps Tebal 15 Mm


Bahan :
5.184 Kg Semen ( Pc ) @ Rp. 1,550.00 8,035.20
0.026 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 7,429.27
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.150 Oh Tukang Batu @ Rp. 125,000.00 18,750.00
0.015 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
15,464.47 51,000.00
Jumlah 66,464.47

42 1,00 M2 Plesteran Tembok Camp. 1 Pc : 6 Ps Tebal 15 Mm


Bahan :
4.416 Kg Semen ( Pc ) @ Rp. 1,550.00 6,844.80
0.027 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 7,715.01
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.150 Oh Tukang Batu @ Rp. 125,000.00 18,750.00
0.015 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
14,559.81 51,000.00
Jumlah 65,559.81

43 1,00 M' Plesteran Skoning / Benangan 1 Pc : 2 Ps


Bahan :
0.500 Kg Semen ( Pc ) @ Rp. 1,550.00 775.00
0.013 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 3,714.63
Upah :
0.080 Oh Pekerja @ Rp. 100,000.00 8,000.00
0.400 Oh Tukang Batu @ Rp. 125,000.00 50,000.00
0.040 Oh Kepala Tukang Batu @ Rp. - -
0.004 Oh Mandor @ Rp. 150,000.00 600.00
4,489.63 58,600.00
Jumlah 63,089.63

44 1,00 M2 Plesteran Berapen Pondasi 1 Pc : 5 Ps Tebal 15 mm


Bahan :
5.184 Kg Semen ( Pc ) @ Rp. 1,550.00 8,035.20
0.026 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 7,429.27
Upah :
0.150 Oh Pekerja @ Rp. 100,000.00 15,000.00
0.075 Oh Tukang Batu @ Rp. 125,000.00 9,375.00
0.008 Oh Kepala Tukang Batu @ Rp. - -
0.008 Oh Mandor @ Rp. 150,000.00 1,200.00
15,464.47 25,575.00
Jumlah 41,039.47

45 1,00 M2 Plesteran Beton 1 Pc : 2 Ps Tebal 15 Mm


Bahan :
9.300 Kg Semen ( Pc ) @ Rp. 1,550.00 14,415.00
0.018 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 5,143.34
Upah :
0.260 Oh Pekerja @ Rp. 100,000.00 26,000.00
0.200 Oh Tukang Batu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Batu @ Rp. - -
0.013 Oh Mandor @ Rp. 150,000.00 1,950.00
19,558.34 52,950.00
Jumlah 72,508.34
46 1,00 M2 Plesteran Ciprat ( Camfrut )1 Pc : 2 Ps
Bahan :
4.320 Kg Semen ( Pc ) @ Rp. 1,550.00 6,696.00
0.006 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 1,714.45
Upah :
0.300 Oh Pekerja @ Rp. 100,000.00 30,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
8,410.45 44,750.00
Jumlah 53,160.45

47 1,00 M2 Acian
Bahan :
3.250 Kg Semen ( Pc ) @ Rp. 1,550.00 5,037.50
Upah :
0.200 Oh Pekerja @ Rp. 100,000.00 20,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.010 Oh Mandor @ Rp. 150,000.00 1,500.00
5,037.50 34,000.00
Jumlah 39,037.50

SNI. 3434-2008 PEKERJAAN KAYU


48 1,00 M2 Pasang Usuk dan Reng Bangkirai ( Genteng Kodok )
Bahan :
0.009 M3 Kayu Usuk 5/7 @ Rp. 10,925,000.00 98,325.00
0.0040 M3 Kayu Reng 2/3 @ Rp. 10,925,000.00 43,700.00
0.250 Kg Paku @ Rp. 15,950.00 3,987.50
Upah :
0.100 Oh Pekerja @ Rp. 100,000.00 10,000.00
0.100 Oh Tukang Kayu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Kayu @ Rp. - -
0.005 Oh Mandor @ Rp. 150,000.00 750.00
146,012.50 23,250.00
Jumlah 169,262.50

49 1,00 M2 Pasang Usuk dan Reng Bangkirai ( Genteng Keramik )


Bahan :
0.014 M3 Kayu Usuk 5/7 @ Rp. 10,925,000.00 152,950.00
0.0036 M3 Kayu Reng 3/5 @ Rp. 10,925,000.00 39,330.00
0.250 Kg Paku @ Rp. 15,950.00 3,987.50
Upah :
0.100 Oh Pekerja @ Rp. 100,000.00 10,000.00
0.100 Oh Tukang Kayu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Kayu @ Rp. - -
0.005 Oh Mandor @ Rp. 150,000.00 750.00
196,267.50 23,250.00
Jumlah 219,517.50

50 1,00 M2 Pasang Usuk dan Reng Bangkirai ( Genteng Beton )


Bahan :
0.014 M3 Kayu Usuk 5/7 @ Rp. 10,925,000.00 152,950.00
0.0072 M3 Kayu Reng 3/5 @ Rp. 10,925,000.00 78,660.00
0.250 Kg Paku @ Rp. 15,950.00 3,987.50
Upah :
0.100 Oh Pekerja @ Rp. 100,000.00 10,000.00
0.100 Oh Tukang Kayu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Kayu @ Rp. - -
0.005 Oh Mandor @ Rp. 150,000.00 750.00
235,597.50 23,250.00
Jumlah 258,847.50

51 1,00 M' Pasang Lisplank Bangkirai ( Ukuran 3 x 30 Cm )


Bahan :
0.011 M3 Kayu Bangkirai Papan @ Rp. 11,500,000.00 126,500.00
0.050 Kg Paku @ Rp. 15,950.00 797.50
Upah :
0.100 Oh Pekerja @ Rp. 100,000.00 10,000.00
0.200 Oh Tukang Kayu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Kayu @ Rp. - -
0.005 Oh Mandor @ Rp. 150,000.00 750.00
127,297.50 35,750.00
Jumlah 163,047.50

52 1,00 M' Pasang Lisplank Bangkirai ( Ukuran 3 x 20 Cm )


Bahan :
0.0108 M3 Kayu Bangkirai Papan @ Rp. 11,500,000.00 124,200.00
0.100 Kg Paku @ Rp. 15,950.00 1,595.00
Upah :
0.100 Oh Pekerja @ Rp. 100,000.00 10,000.00
0.200 Oh Tukang Kayu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Kayu @ Rp. - -
0.005 Oh Mandor @ Rp. 150,000.00 750.00
125,795.00 35,750.00
Jumlah 161,545.00

53 1,00 M3 Pasang Kuda - Kuda Kayu Bangkirai ( Konvensional )


Bahan :
1.100 M3 Kayu Bangkirai ( Klas I ) @ Rp. 10,925,000.00 12,017,500.00
15.000 Kg Besi Strip dan Mur Baut @ Rp. 25,100.00 376,500.00
5.600 Kg Paku @ Rp. 15,950.00 89,320.00
Upah :
4.000 Oh Pekerja @ Rp. 100,000.00 400,000.00
12.000 Oh Tukang Kayu @ Rp. 125,000.00 1,500,000.00
1.200 Oh Kepala Tukang Kayu @ Rp. - -
0.200 Oh Mandor @ Rp. 150,000.00 30,000.00
12,483,320.00 1,930,000.00
Jumlah 14,413,320.00

54 1,00 M3 Pasang Kuda - Kuda Kayu Bangkirai ( Ekspose )


Bahan :
1.100 M3 Kayu Bangkirai ( Klas I ) @ Rp. 10,925,000.00 12,017,500.00
15.000 Kg Besi Strip dan Mur Baut @ Rp. 25,100.00 376,500.00
5.600 Kg Paku @ Rp. 15,950.00 89,320.00
Upah :
6.000 Oh Pekerja @ Rp. 100,000.00 600,000.00
20.100 Oh Tukang Kayu @ Rp. 125,000.00 2,512,500.00
2.010 Oh Kepala Tukang Kayu @ Rp. - -
0.335 Oh Mandor @ Rp. 150,000.00 50,250.00
12,483,320.00 3,162,750.00
Jumlah 15,646,070.00

55 1,00 M3 Pasang Gording dan Nok


Bahan :
1.100 M3 Kayu Bangkirai ( Klas I ) @ Rp. 10,925,000.00 12,017,500.00
15.000 Kg Besi strip @ Rp. 25,100.00 376,500.00
3.000 Kg Paku @ Rp. 15,950.00 47,850.00
Upah :
2.400 Oh Pekerja @ Rp. 100,000.00 240,000.00
7.200 Oh Tukang Kayu @ Rp. 125,000.00 900,000.00
0.720 Oh Kepala Tukang Kayu @ Rp. - -
0.120 Oh Mandor @ Rp. 150,000.00 18,000.00
12,441,850.00 1,158,000.00
Jumlah 13,599,850.00

56 1,00 M3 Pasang Ikatan Angin


Bahan :
1.100 M3 Kayu Bangkirai ( Klas I ) @ Rp. 10,925,000.00 12,017,500.00
0.800 Kg Paku @ Rp. 15,950.00 12,760.00
Upah :
2.400 Oh Pekerja @ Rp. 100,000.00 240000
7.200 Oh Tukang Kayu @ Rp. 125,000.00 900,000.00
0.720 Oh Kepala Tukang Kayu @ Rp. - -
0.120 Oh Mandor @ Rp. 150,000.00 18,000.00
12030260 1,158,000.00
Jumlah 13,188,260.00

57 1,00 M' Pasang Papan Reuter 2/20


Bahan :
0.004 M3 Kayu Papan Meranti @ Rp. 6,325,000.00 25,300.00
0.020 Kg Paku @ Rp. 15,950.00 319.00
Upah :
0.100 Oh Pekerja @ Rp. 100,000.00 10,000.00
0.050 Oh Tukang Kayu @ Rp. 125,000.00 6,250.00
0.020 Oh Kepala Tukang Kayu @ Rp. - -
0.010 Oh Mandor @ Rp. 150,000.00 1,500.00
25,619.00 17,750.00
Jumlah 43,369.00

58 1,00 M' Pasang Papan Kompres 2/15


Bahan :
0.003 M3 Kayu Papan Bangkirai @ Rp. 11,500,000.00 34,500.00
0.020 Kg Paku @ Rp. 15,950.00 319.00
Upah :
0.150 Oh Pekerja @ Rp. 100,000.00 15,000.00
0.180 Oh Tukang Kayu @ Rp. 125,000.00 22,500.00
0.023 Oh Kepala Tukang Kayu @ Rp. - -
0.015 Oh Mandor @ Rp. 150,000.00 2,250.00
34,819.00 39,750.00
Jumlah 74,569.00

59 1,00 M3 Pek. Kusen Pintu / Jendela Kayu Bangkirai


Bahan :
1.100 M3 Kayu Bangkirai ( Klas I ) @ Rp. 10,925,000.00 12,017,500.00
1.250 Kg Paku @ Rp. 15,950.00 19,937.50
1.000 Kg Lem Kayu @ Rp. 14,685.00 14,685.00
Upah :
7.000 Oh Pekerja @ Rp. 100,000.00 700,000.00
21.000 Oh Tukang Kayu @ Rp. 125,000.00 2,625,000.00
2.100 Oh Kepala Tukang Kayu @ Rp. - -
0.350 Oh Mandor @ Rp. 150,000.00 52,500.00
12,052,122.50 3,377,500.00
Jumlah 15,429,622.50

SNI. DT 91-0014-2007 (6.11)


1,00 m' Pemasangan Kusen Alumunium Profil 4"
Bahan :
1.100 m1 Aluminium Putih Uk. 4 x 10, Profil 4" @ Rp. 82,500.00 90,750.00
2.000 Bh Skrup/Ripet @ Rp. 275.00 550.00
0.060 tube Sealent @ Rp. 23,760.00 1,425.60
Upah :
0.002 Oh Mandor @ Rp. 150,000.00 331.50
0.004 Oh Kepala Tukang Kayu @ Rp. 0.00 -
0.043 Oh Tukang Kayu @ Rp. 125,000.00 5,375.00
0.043 Oh Pekerja Terampil @ Rp. 100,000.00 4,300.00
92,725.60 10,006.50
Jumlah 102,732.10

1,00 m2 Pemasangan Pintu Alumunium


Bahan :
1.100 m2 Pintu alumunium @ Rp. 528,000.00 580,800.00

Upah :
0.005 Oh Mandor @ Rp. 150,000.00 780.00
0.105 Oh Kepala Tukang besi @ Rp. 0.00 -
1.050 Oh Tukang besi @ Rp. 125,000.00 131,250.00
1.050 Oh Pekerja Terampil @ Rp. 100,000.00 105,000.00
580,800.00 237,030.00
Jumlah 817,830.00

1,00 m' Pemasangan slimar Alumunium Profil 3"


Bahan :
1.100 m1 Aluminium Putih Uk. 3 x 8, Profil 3" @ Rp. 69,300.00 76,230.00
2.000 Bh Skrup/Ripet @ Rp. 275.00 550.00
0.060 tube Sealent @ Rp. 23,760.00 1,425.60
Upah :
0.002 Oh Mandor @ Rp. 150,000.00 331.50
0.004 Oh Kepala Tukang Kayu @ Rp. 0.00 -
0.043 Oh Tukang Kayu @ Rp. 125,000.00 5,375.00
0.043 Oh Pekerja Terampil @ Rp. 100,000.00 4,300.00
78,205.60 10,006.50
Jumlah 88,212.10

60 1,00 M2 Pek. Daun Pintu dan Jendela Panil Kayu Bangkirai


Bahan :
0.040 M3 Kayu Papan Bangkirai @ Rp. 11,500,000.00 460,000.00
0.500 Kg Lem Kayu @ Rp. 14,685.00 7,342.50
Upah :
1.000 Oh Pekerja @ Rp. 100,000.00 100,000.00
3.000 Oh Tukang Kayu @ Rp. 125,000.00 375,000.00
0.300 Oh Kepala Tukang Kayu @ Rp. - -
0.050 Oh Mandor @ Rp. 150,000.00 7,500.00
467,342.50 482,500.00
Jumlah 949,842.50

61 1,00 M2 Pekerjaan Pintu/Jendela Jalusi Kayu Bangkirai


Bahan :
0.064 M3 Kayu Papan Bangkirai @ Rp. 11,500,000.00 736,000.00
0.500 Kg Lem Kayu @ Rp. 14,685.00 7,342.50
Upah :
1.000 Oh Pekerja @ Rp. 100,000.00 100,000.00
3.000 Oh Tukang Kayu @ Rp. 125,000.00 375,000.00
0.300 Oh Kepala Tukang Kayu @ Rp. - -
0.050 Oh Mandor @ Rp. 150,000.00 7,500.00
743,342.50 482,500.00
Jumlah 1,225,842.50

62 1,00 M2 Pek. Daun Pintu Kaca Kayu Bangkirai


Bahan :
0.024 M3 Kayu Papan Bangkirai @ Rp. 11,500,000.00 276,000.00
0.300 Kg Lem Kayu @ Rp. 14,685.00 4,405.50
Upah :
0.800 Oh Pekerja @ Rp. 100,000.00 80,000.00
2.400 Oh Tukang Kayu @ Rp. 125,000.00 300,000.00
0.240 Oh Kepala Tukang Kayu @ Rp. - -
0.040 Oh Mandor @ Rp. 150,000.00 6,000.00
280,405.50 386,000.00
Jumlah 666,405.50

63 1,00 M2 Pek. Daun Jendela Kaca Kayu Bangkirai


Bahan :
0.024 M3 Kayu Papan Bangkirai @ Rp. 11,500,000.00 276,000.00
0.300 Kg Lem Kayu @ Rp. 14,685.00 4,405.50
Upah :
0.800 Oh Pekerja @ Rp. 100,000.00 80,000.00
2.400 Oh Tukang Kayu @ Rp. 125,000.00 300,000.00
0.240 Oh Kepala Tukang Kayu @ Rp. - -
0.040 Oh Mandor @ Rp. 150,000.00 6,000.00
280,405.50 386,000.00
Jumlah 666,405.50

64 1,00 M2 Pek. Pintu Teakwood Rangkap, Rangka Kayu Bangkirai


Bahan :
0.025 M3 Kayu Papan Bangkirai @ Rp. 11,500,000.00 287,500.00
0.030 Kg Paku Reng @ Rp. 18,370.00 551.10
0.300 Kg Lem Kayu @ Rp. 14,685.00 4,405.50
1.000 Lbr Teakwood 1,22 x 2,44 x 4 mm @ Rp. 91,960.00 91,960.00
Upah :
0.800 Oh Pekerja @ Rp. 100,000.00 80,000.00
2.400 Oh Tukang Kayu @ Rp. 125,000.00 300,000.00
0.240 Oh Kepala Tukang Kayu @ Rp. - -
0.040 Oh Mandor @ Rp. 150,000.00 6,000.00
384,416.60 386,000.00
Jumlah 770,416.60

65 1,00 M2 Pekerjaan Jalusi Kayu Bangkirai


Bahan :
0.060 M3 Kayu Papan Bangkirai @ Rp. 11,500,000.00 690,000.00
0.150 Kg Paku Reng @ Rp. 18,370.00 2,755.50
Upah :
0.670 Oh Pekerja @ Rp. 100,000.00 67,000.00
2.000 Oh Tukang Kayu @ Rp. 125,000.00 250,000.00
0.200 Oh Kepala Tukang Kayu @ Rp. - -
0.335 Oh Mandor @ Rp. 150,000.00 50,250.00
692,755.50 367,250.00
Jumlah 1,060,005.50

66 1,00 M2 Rangka Dinding Pemisah Teakwood Rangkap


Bahan :
0.028 M3 Kayu Balok Bangkirai 6/12 @ Rp. 10,925,000.00 305,900.00
0.150 Kg Paku @ Rp. 15,950.00 2,392.50
0.860 Lbr Teakwood 1,22 x 2,44 x 4 mm @ Rp. 91,960.00 79,085.60
0.560 Kg Lem Kayu @ Rp. 14,685.00 8,223.60
Upah :
0.150 Oh Pekerja @ Rp. 100,000.00 15,000.00
0.450 Oh Tukang Kayu @ Rp. 125,000.00 56,250.00
0.045 Oh Kepala Tukang Kayu @ Rp. - -
0.008 Oh Mandor @ Rp. 150,000.00 1,200.00
395,601.70 72,450.00
Jumlah 468,051.70

1,00 m1 Pasang list profil cornees gypsum lebar 5 - 10 cm


Bahan :
1.100 m1 List profil cornees gypsum @ Rp. 23,000.00 25,300.00
0.875 kg Tepung gypsum @ Rp. 4,284.00 3,748.50
0.004 kg Alkasit @ Rp. 367,200.00 1,615.68
Upah :
0.038 org Tukang kayu @ Rp. 100,000.00 3,750.00
0.004 org Kepala tukang kayu @ Rp. 125,000.00 462.50
0.113 org Pekerja @ Rp. - -
0.007 org Mandor @ Rp. 150,000.00 975.00
5,364.18 5,187.50
Jumlah 10,551.68

67 1,00 M' Pasang List Kayu Profil


Bahan :
1.050 M' Kayu Profil @ Rp. 9,240.00 9,702.00
0.010 Kg Paku Reng @ Rp. 18,370.00 183.70
Upah :
0.050 Oh Pekerja @ Rp. 100,000.00 5,000.00
0.050 Oh Tukang Kayu @ Rp. 125,000.00 6,250.00
0.005 Oh Kepala Tukang Kayu @ Rp. - -
0.003 Oh Mandor @ Rp. 150,000.00 450.00
9,885.70 11,700.00
Jumlah 21,585.70

SNI.DT 91-0008-2007 PEKERJAAN BETON


68 1,00 M3 Pekerjaan Beton Rabat Camp. 1Pc : 3Psr : 5Krl
Bahan :
218.000 Kg Semen ( Pc ) @ Rp. 1,550.00 337,900.00
0.520 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 148,571.28
0.870 M3 Batu Pecah 2/3 ( Lokal ) @ Rp. 833,500.00 725,145.00
Upah :
1.650 Oh Pekerja @ Rp. 100,000.00 165,000.00
0.250 Oh Tukang Batu @ Rp. 125,000.00 31,250.00
0.025 Oh Kepala Tukang Batu @ Rp. - -
0.080 Oh Mandor @ Rp. 150,000.00 12,000.00
1,211,616.28 208,250.00
Jumlah 1,419,866.28

SNI. 00-0000-2002 PEKERJAAN BETON


69 1,00 M3 Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K 100), slump (3-6) cm
Bahan :
230.000 Kg Semen ( Pc ) @ Rp. 1,550.00 356,500.00
0.638 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 182,285.53
0.761 M3 Batu Pecah 2/3 ( Lokal ) @ Rp. 833,500.00 634,293.50
Upah :
1.200 Oh Pekerja @ Rp. 100,000.00 120,000.00
0.200 Oh Tukang Batu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Batu @ Rp. - -
0.060 Oh Mandor @ Rp. 150,000.00 9,000.00
1,173,079.03 154,000.00
Jumlah 1,327,079.03

70 1 M3 Beton Mutu K 225 (f'c = 19,3 Mpa)


Bahan :
371.000 Kg Semen ( Pc ) @ Rp. 1,550.00 575,050.00
0.499 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 142,571.29
0.776 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 309,624.00
Upah :
1.650 Oh Pekerja @ Rp. 100,000.00 165,000.00
0.275 Oh Tukang Batu @ Rp. 125,000.00 34,375.00
0.028 Oh Kepala Tukang Batu @ Rp. - -
0.083 Oh Mandor @ Rp. 150,000.00 12,450.00
1,027,245.29 211,825.00
Jumlah 1,239,070.29

71 1 M3 Beton Mutu K 250 (f'c = 21,7 Mpa)


Bahan :
384.000 Kg Semen ( Pc ) @ Rp. 1,550.00 595,200.00
0.494 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 141,142.72
0.770 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 307,230.00
Upah :
1.650 Oh Pekerja @ Rp. 100,000.00 165,000.00
0.275 Oh Tukang Batu @ Rp. 125,000.00 34,375.00
0.028 Oh Kepala Tukang Batu @ Rp. - -
0.083 Oh Mandor @ Rp. 150,000.00 12,450.00
1,043,572.72 211,825.00
Jumlah 1,255,397.72

72 1 M3 Beton Mutu K 275 (f'c = 24 Mpa)


Bahan :
406.000 Kg Semen (Pc) @ Rp. 1,550.00 629,300.00
0.489 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 139,714.15
0.760 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 303,240.00
Upah :
1.650 Oh Pekerja @ Rp. 100,000.00 165,000.00
0.275 Oh Tukang Batu @ Rp. 125,000.00 34,375.00
0.028 Oh Kepala Tukang Batu @ Rp. - -
0.083 Oh Mandor @ Rp. 150,000.00 12,450.00
1,072,254.15 211,825.00
Jumlah 1,284,079.15

73 1 M3 Beton Mutu K 300 (f'c = 26,4 Mpa)


Bahan :
413.000 Kg Semen (Pc) @ Rp. 1,550.00 640,150.00
0.486 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 138,857.00
0.756 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 301,644.00
Upah :
1.650 Oh Pekerja @ Rp. 100,000.00 165,000.00
0.275 Oh Tukang Batu @ Rp. 125,000.00 34,375.00
0.028 Oh Kepala Tukang Batu @ Rp. - -
0.083 Oh Mandor @ Rp. 150,000.00 12,450.00
1,080,651.00 211,825.00
Jumlah 1,292,476.00

74 1,00 Kg Pekerjaan Pembesian ( Polos / Ulir )


Bahan :
1.050 Kg Besi Beton Polos @ Rp. 15,500.00 16,275.00
0.015 Kg Kawat Beton @ Rp. 18,400.00 276.00
Upah :
0.007 Oh Pekerja @ Rp. 100,000.00 700.00
0.007 Oh Tukang Besi @ Rp. 125,000.00 875.00
0.0007 Oh Kepala Tukang Besi @ Rp. - -
0.0004 Oh Mandor @ Rp. 150,000.00 60.00
16,551.00 1,635.00
Jumlah 18,186.00
75 1,00 Kg Pekerjaan Jaring Kawat Beton / Wire Mesh
Bahan :
1.020 Kg Wire Mesh dilas @ Rp. - -
0.050 Kg Kawat Beton @ Rp. 18,400.00 920.00
Upah :
0.025 Oh Pekerja @ Rp. 100,000.00 2,500.00
0.025 Oh Tukang Besi @ Rp. 125,000.00 3,125.00
0.0020 Oh Kepala Tukang Besi @ Rp. - -
0.0010 Oh Mandor @ Rp. 150,000.00 150.00
920.00 5,775.00
Jumlah 6,695.00
76 1,00 M2 Pekerjaan Begisting Pondasi
Bahan :
0.040 M3 Kayu Begisting @ Rp. 4,025,000.00 161,000.00
0.300 Kg Paku @ Rp. 15,950.00 4,785.00
0.100 Ltr Minyak Begisting @ Rp. 3,300.00 330.00
Upah :
0.520 Oh Pekerja @ Rp. 100,000.00 52,000.00
0.260 Oh Tukang Kayu @ Rp. 125,000.00 32,500.00
0.026 Oh Kepala Tukang Kayu @ Rp. - -
0.026 Oh Mandor @ Rp. 150,000.00 3,900.00
166,115.00 88,400.00
Jumlah 254,515.00
77 1,00 M2 Pekerjaan Begisting Sloof
Bahan :
0.045 M3 Kayu Begisting @ Rp. 4,025,000.00 181,125.00
0.300 Kg Paku @ Rp. 15,950.00 4,785.00
0.100 Ltr Minyak Begisting @ Rp. 3,300.00 330.00
Upah :
0.520 Oh Pekerja @ Rp. 100,000.00 52,000.00
0.260 Oh Tukang Kayu @ Rp. 125,000.00 32,500.00
0.026 Oh Kepala Tukang Kayu @ Rp. - -
0.026 Oh Mandor @ Rp. 150,000.00 3,900.00
186,240.00 88,400.00
Jumlah 274,640.00
78 1,00 M2 Pekerjaan Begisting Kolom
Bahan :
0.008 M3 Kayu Balok Klas II @ Rp. 6,325,000.00 47,437.50
0.020 M3 Kayu Papan Begisting @ Rp. 4,025,000.00 80,500.00
0.400 Kg Paku @ Rp. 15,950.00 6,380.00
1.000 Btg Dolken ( Dia 8-10 Cm ) x 4 M @ Rp. 39,100.00 39,100.00
0.200 Ltr Minyak Begisting @ Rp. 3,300.00 660.00
0.175 Lbr Multiplek 1,22 x 2,44 x 6 mm @ Rp. 79,695.00 13,946.63
Upah :
0.660 Oh Pekerja @ Rp. 100,000.00 66,000.00
0.330 Oh Tukang Kayu @ Rp. 125,000.00 41,250.00
0.033 Oh Kepala Tukang Kayu @ Rp. - -
0.033 Oh Mandor @ Rp. 150,000.00 4,950.00
188,024.13 112,200.00
Jumlah 300,224.13
79 1,00 M2 Pekerjaan Begisting Balok
Bahan :
0.015 M3 Kayu Balok Klas II @ Rp. 6,325,000.00 94,875.00
0.040 M3 Kayu Papan Begisting @ Rp. 4,025,000.00 161,000.00
0.400 Kg Paku @ Rp. 15,950.00 6,380.00
2.000 Btg Dolken ( Dia 8-10 Cm ) x 4 M @ Rp. 39,100.00 78,200.00
0.200 Ltr Minyak Begisting @ Rp. 3,300.00 660.00
Upah :
0.660 Oh Pekerja @ Rp. 100,000.00 66,000.00
0.330 Oh Tukang Kayu @ Rp. 125,000.00 41,250.00
0.033 Oh Kepala Tukang Kayu @ Rp. - -
0.033 Oh Mandor @ Rp. 150,000.00 4,950.00
341,115.00 112,200.00
Jumlah 453,315.00
80 1,00 M2 Pekerjaan Begisting Plat Lantai
Bahan :
0.015 M3 Kayu Balok Klas II @ Rp. 6,325,000.00 94,875.00
0.400 Kg Paku @ Rp. 15,950.00 6,380.00
0.040 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 161,000.00
0.350 Lbr Multiplek 1,22 x 2,44 x 6 mm @ Rp. 79,695.00 27,893.25
6.000 Btg Dolken ( Dia 8-10 Cm ) x 4 M @ Rp. 39,100.00 234,600.00
0.200 Ltr Minyak Begisting @ Rp. 3,300.00 660.00
Upah :
0.660 Oh Pekerja @ Rp. 100,000.00 66,000.00
0.330 Oh Tukang Kayu @ Rp. 125,000.00 41,250.00
0.033 Oh Kepala Tukang Kayu @ Rp. - -
0.033 Oh Mandor @ Rp. 150,000.00 4,950.00
525,408.25 112,200.00
Jumlah 637,608.25

81 1,00 M2 Pekerjaan Begisting Tangga


Bahan :
0.015 M3 Kayu Balok Klas II @ Rp. 6,325,000.00 94,875.00
0.400 Kg Paku @ Rp. 15,950.00 6,380.00
0.030 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 120,750.00
0.350 Lbr Multiplek tebal 6 Mm @ Rp. 79,695.00 27,893.25
2.000 Btg Dolken ( Dia 8-10 Cm ) x 4 M @ Rp. 39,100.00 78,200.00
0.150 Ltr Minyak Begisting @ Rp. 3,300.00 495.00
Upah :
0.660 Oh Pekerja @ Rp. 100,000.00 66,000.00
0.330 Oh Tukang Kayu @ Rp. 125,000.00 41,250.00
0.033 Oh Kepala Tukang Kayu @ Rp. - -
0.033 Oh Mandor @ Rp. 150,000.00 4,950.00
328,593.25 112,200.00
Jumlah 440,793.25

82 1,00 M3 Pekerjaan Pondasi Beton Bertulang (150 Kg Besi + Begesting)


Bahan :
0.200 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 805,000.00
1.500 Kg Paku @ Rp. 15,950.00 23,925.00
0.400 Ltr Minyak Begisting @ Rp. 3,300.00 1,320.00
157.500 Kg Besi Beton Polos @ Rp. 15,500.00 2,441,250.00
2.250 Kg Kawat Beton/Bendrat @ Rp. 18,400.00 41,400.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
Upah :
5.300 Oh Pekerja @ Rp. 100,000.00 530,000.00
0.275 Oh Tukang Batu @ Rp. 125,000.00 34,375.00
1.300 Oh Tukang Kayu @ Rp. 125,000.00 162,500.00
1.050 Oh Tukang Besi @ Rp. 125,000.00 131,250.00
0.262 Oh Kepala Tukang @ Rp. - -
0.265 Oh Mandor @ Rp. 150,000.00 39,750.00
4,311,170.56 897,875.00
Jumlah 5,209,045.56
83 1,00 M3 Pekerjaan Sloof Beton Bertulang (200 Kg Besi + Begesting)
Bahan :
0.270 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 1,086,750.00
2.000 Kg Paku @ Rp. 15,950.00 31,900.00
0.600 Ltr Minyak Begisting @ Rp. 3,300.00 1,980.00
210.000 Kg Besi Beton Polos @ Rp. 15,500.00 3,255,000.00
3.000 Kg Kawat Beton/Bendrat @ Rp. 18,400.00 55,200.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
Upah :
5.650 Oh Pekerja @ Rp. 100,000.00 565,000.00
0.275 Oh Tukang Batu @ Rp. 125,000.00 34,375.00
1.560 Oh Tukang Kayu @ Rp. 125,000.00 195,000.00
1.400 Oh Tukang Besi @ Rp. 125,000.00 175,000.00
0.323 Oh Kepala Tukang @ Rp. - -
0.283 Oh Mandor @ Rp. 150,000.00 42,450.00
5,429,105.56 1,011,825.00
Jumlah 6,440,930.56
84 1,00 M3 Pekerjaan Sloof Beton Bertulang (130 Kg Besi + Begesting)
Bahan :
0.176 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 706,387.50
1.300 Kg Paku @ Rp. 15,950.00 20,735.00
0.390 Ltr Minyak Begisting @ Rp. 3,300.00 1,287.00
136.500 Kg Besi Beton Polos @ Rp. 15,500.00 2,115,750.00
1.950 Btg Kawat Beton/Bendrat @ Rp. 18,400.00 35,880.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
Upah :
3.673 Oh Pekerja @ Rp. 100,000.00 367,250.00
0.179 Oh Tukang Batu @ Rp. 125,000.00 22,343.75
1.014 Oh Tukang Kayu @ Rp. 125,000.00 126,750.00
0.910 Oh Tukang Besi @ Rp. 125,000.00 113,750.00
0.210 Oh Kepala Tukang @ Rp. - -
0.184 Oh Mandor @ Rp. 150,000.00 27,592.50
3,878,315.06 657,686.25
Jumlah 4,536,001.31

85 1,00 M3 Pekerjaan Sloof Beton Bertulang (110 Kg Besi + Begesting)


Bahan :
0.149 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 597,712.50
1.100 Kg Paku @ Rp. 15,950.00 17,545.00
0.330 Ltr Minyak Begisting @ Rp. 3,300.00 1,089.00
115.500 Kg Besi Beton Polos @ Rp. 15,500.00 1,790,250.00
1.650 Kg Kawat Beton/Bendrat @ Rp. 18,400.00 30,360.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
Upah :
3.108 Oh Pekerja @ Rp. 100,000.00 310,750.00
0.151 Oh Tukang Batu @ Rp. 125,000.00 18,906.25
0.858 Oh Tukang Kayu @ Rp. 125,000.00 107,250.00
0.770 Oh Tukang Besi @ Rp. 125,000.00 96,250.00
0.178 Oh Kepala Tukang @ Rp. - -
0.156 Oh Mandor @ Rp. 150,000.00 23,347.50
3,435,232.06 556,503.75
Jumlah 3,991,735.81

86 1,00 M3 Pekerjaan Kolom Beton Bertulang (250 Kg Besi + Begesting)


Bahan :
0.333 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 1,341,666.67
3.333 Kg Paku @ Rp. 15,950.00 53,166.67
1.667 Ltr Minyak Begisting @ Rp. 3,300.00 5,500.00
262.500 Kg Besi Beton Polos @ Rp. 15,500.00 4,068,750.00
3.750 Kg Kawat Beton/Bendrat @ Rp. 18,400.00 69,000.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.150 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 948,750.00
3.500 Lbr Multipleks 6 mm @ Rp. 79,695.00 278,932.50
20.000 Btg Kayu Dolken, panjang 4 m @ Rp. 39,100.00 782,000.00
Upah : -
5.875 Oh Pekerja @ Rp. 100,000.00 587,500.00
0.229 Oh Tukang Batu @ Rp. 125,000.00 28,645.83
1.375 Oh Tukang Kayu @ Rp. 125,000.00 171,875.00
1.750 Oh Tukang Besi @ Rp. 125,000.00 218,750.00
0.336 Oh Kepala Tukang @ Rp. - -
0.294 Oh Mandor @ Rp. 150,000.00 44,125.00
8,546,041.39 1,050,895.83
Jumlah 9,596,937.23

87 1,00 M3 Pekerjaan Kolom Beton Bertulang (300 Kg Besi + Begesting)


Bahan :
0.400 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 1,610,000.00
4.000 Kg Paku @ Rp. 15,950.00 63,800.00
2.000 Ltr Minyak Begisting @ Rp. 3,300.00 6,600.00
315.000 Kg Besi Beton Polos @ Rp. 15,500.00 4,882,500.00
4.500 Btg Kawat Beton/Bendrat @ Rp. 18,400.00 82,800.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.150 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 948,750.00
3.500 Lbr Multipleks 6 mm @ Rp. 79,695.00 278,932.50
20.000 Btg Kayu Dolken, panjang 4 m @ Rp. 39,100.00 782,000.00
Upah :
7.050 Oh Pekerja @ Rp. 100,000.00 705,000.00
0.275 Oh Tukang Batu @ Rp. 125,000.00 34,375.00
1.650 Oh Tukang Kayu @ Rp. 125,000.00 206,250.00
2.100 Oh Tukang Besi @ Rp. 125,000.00 262,500.00
0.403 Oh Kepala Tukang @ Rp. - -
0.353 Oh Mandor @ Rp. 150,000.00 52,950.00
9,653,658.06 1,261,075.00
Jumlah 10,914,733.06

88 1,00 M3 Pekerjaan Balok Beton Bertulang (200 Kg Besi + Begesting)


Bahan :
0.320 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 1,288,000.00
3.200 Kg Paku @ Rp. 15,950.00 51,040.00
1.600 Ltr Minyak Begisting @ Rp. 3,300.00 5,280.00
210.000 Kg Besi Beton Polos @ Rp. 15,500.00 3,255,000.00
3.000 kg Kawat Beton/Bendrat @ Rp. 18,400.00 55,200.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.140 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 885,500.00
2.800 Lbr Multipleks 6 mm @ Rp. 79,695.00 223,146.00
16.000 Btg Kayu Dolken, panjang 4 m @ Rp. 39,100.00 625,600.00
Upah :
6.350 Oh Pekerja @ Rp. 100,000.00 635,000.00
0.275 Oh Tukang Batu @ Rp. 125,000.00 34,375.00
1.650 Oh Tukang Kayu @ Rp. 125,000.00 206,250.00
1.400 Oh Tukang Besi @ Rp. 125,000.00 175,000.00
0.333 Oh Kepala Tukang @ Rp. - -
0.318 Oh Mandor @ Rp. 150,000.00 47,700.00
7,387,041.56 1,098,325.00
Jumlah 8,485,366.56

89 1,00 M3 Pekerjaan Balok Beton Bertulang (160 Kg Besi + Begesting)


Bahan :
0.256 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 1,030,400.00
2.560 Kg Paku @ Rp. 15,950.00 40,832.00
1.280 Ltr Minyak Begisting @ Rp. 3,300.00 4,224.00
168.000 Kg Besi Beton Polos @ Rp. 15,500.00 2,604,000.00
2.400 kg Kawat Beton/Bendrat @ Rp. 18,400.00 44,160.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.140 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 885,500.00
2.800 Lbr Multipleks 6 mm @ Rp. 79,695.00 223,146.00
16.000 Btg Kayu Dolken, panjang 4 m @ Rp. 39,100.00 625,600.00
Upah : -
5.080 Oh Pekerja @ Rp. 100,000.00 508,000.00
0.220 Oh Tukang Batu @ Rp. 125,000.00 27,500.00
1.320 Oh Tukang Kayu @ Rp. 125,000.00 165,000.00
1.120 Oh Tukang Besi @ Rp. 125,000.00 140,000.00
0.266 Oh Kepala Tukang @ Rp. - -
0.254 Oh Mandor @ Rp. 150,000.00 38,160.00
6,456,137.56 878,660.00
Jumlah 7,334,797.56

90 1,00 M3 Pekerjaan Balok Beton Bertulang (130 Kg Besi + Begesting)


Bahan :
0.208 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 837,200.00
2.080 Kg Paku @ Rp. 15,950.00 33,176.00
1.040 Ltr Minyak Begisting @ Rp. 3,300.00 3,432.00
136.500 Kg Besi Beton Polos @ Rp. 15,500.00 2,115,750.00
1.950 Btg Kawat Beton/Bendrat @ Rp. 18,400.00 35,880.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.140 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 885,500.00
2.800 Lbr Multipleks 6 mm @ Rp. 79,695.00 223,146.00
16.000 Btg Kayu Dolken, panjang 4 m @ Rp. 39,100.00 625,600.00
Upah : -
4.128 Oh Pekerja @ Rp. 100,000.00 412,750.00
0.179 Oh Tukang Batu @ Rp. 125,000.00 22,343.75
1.073 Oh Tukang Kayu @ Rp. 125,000.00 134,062.50
0.910 Oh Tukang Besi @ Rp. 125,000.00 113,750.00
0.216 Oh Kepala Tukang @ Rp. - -
0.207 Oh Mandor @ Rp. 150,000.00 31,005.00
5,757,959.56 713,911.25
Jumlah 6,471,870.81

91 1,00 M3 Pekerjaan Balok Beton Bertulang (180 Kg Besi + Begesting)


Bahan :
0.288 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 1,159,200.00
2.880 Kg Paku @ Rp. 15,950.00 45,936.00
1.440 Ltr Minyak Begisting @ Rp. 3,300.00 4,752.00
189.000 Kg Besi Beton Polos @ Rp. 15,500.00 2,929,500.00
2.700 Btg Kawat Beton/Bendrat @ Rp. 18,400.00 49,680.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.140 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 885,500.00
2.800 Lbr Multipleks 6 mm @ Rp. 79,695.00 223,146.00
16.000 Btg Kayu Dolken, panjang 4 m @ Rp. 39,100.00 625,600.00
Upah : -
5.715 Oh Pekerja @ Rp. 100,000.00 571,500.00
0.248 Oh Tukang Batu @ Rp. 125,000.00 30,937.50
1.485 Oh Tukang Kayu @ Rp. 125,000.00 185,625.00
1.260 Oh Tukang Besi @ Rp. 125,000.00 157,500.00
0.300 Oh Kepala Tukang @ Rp. - -
0.286 Oh Mandor @ Rp. 150,000.00 42,930.00
6,921,589.56 988,492.50
Jumlah 7,910,082.06

92 1,00 M3 Pekerjaan Plat Beton Bertulang (110 Kg Besi + Begesting)


Bahan :
0.235 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 944,533.33
2.347 Kg Paku @ Rp. 15,950.00 37,429.33
1.173 Ltr Minyak Begisting @ Rp. 3,300.00 3,872.00
115.500 Kg Besi Beton Polos @ Rp. 15,500.00 1,790,250.00
1.650 Btg Kawat Beton/Bendrat @ Rp. 18,400.00 30,360.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.120 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 759,000.00
2.800 Lbr Multipleks 6 mm @ Rp. 79,695.00 223,146.00
Upah :
3.887 Oh Pekerja @ Rp. 100,000.00 388,666.67
0.202 Oh Tukang Batu @ Rp. 125,000.00 25,208.33
0.953 Oh Tukang Kayu @ Rp. 125,000.00 119,166.67
0.770 Oh Tukang Besi @ Rp. 125,000.00 96,250.00
0.194 Oh Kepala Tukang @ Rp. - -
0.194 Oh Mandor @ Rp. 150,000.00 29,150.00
4,786,866.23 658,441.67
Jumlah 5,445,307.89

92 1,00 M3 Pekerjaan Plat Beton Bertulang (110 Kg Besi + Begesting)


Bahan :
0.235 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 944,533.33
2.347 Kg Paku @ Rp. 15,950.00 37,429.33
1.173 Ltr Minyak Begisting @ Rp. 3,300.00 3,872.00
115.500 Kg Besi Beton Polos @ Rp. 15,500.00 1,790,250.00
1.650 Btg Kawat Beton/Bendrat @ Rp. 18,400.00 30,360.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.120 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 759,000.00
2.800 Lbr Multipleks 9 mm @ Rp. 134,915.00 377,762.00
Upah :
3.887 Oh Pekerja @ Rp. 100,000.00 388,666.67
0.202 Oh Tukang Batu @ Rp. 125,000.00 25,208.33
0.953 Oh Tukang Kayu @ Rp. 125,000.00 119,166.67
0.770 Oh Tukang Besi @ Rp. 125,000.00 96,250.00
0.194 Oh Kepala Tukang @ Rp. - -
0.194 Oh Mandor @ Rp. 150,000.00 29,150.00
4,941,482.23 658,441.67
Jumlah 5,599,923.89

93 1,00 M3 Pekerjaan Plat Beton Bertulang (110 Kg Besi + Begesting + Perancah)


Bahan :
0.235 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 944,533.33
2.347 Kg Paku @ Rp. 15,950.00 37,429.33
1.173 Ltr Minyak Begisting @ Rp. 3,300.00 3,872.00
115.500 Kg Besi Beton Polos @ Rp. 15,500.00 1,790,250.00
1.650 Btg Kawat Beton/Bendrat @ Rp. 18,400.00 30,360.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.120 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 759,000.00
2.800 Lbr Multipleks 6 mm @ Rp. 79,695.00 223,146.00
32.000 Btg Kayu Dolken, panjang 4 m @ Rp. 39,100.00 1,251,200.00
Upah : -
3.887 Oh Pekerja @ Rp. 100,000.00 388,666.67
0.202 Oh Tukang Batu @ Rp. 125,000.00 25,208.33
0.953 Oh Tukang Kayu @ Rp. 125,000.00 119,166.67
0.770 Oh Tukang Besi @ Rp. 125,000.00 96,250.00
0.194 Oh Kepala Tukang @ Rp. - -
0.194 Oh Mandor @ Rp. 150,000.00 29,150.00
6,038,066.23 658,441.67
Jumlah 6,696,507.89

94 1,00 M3 Pekerjaan Plat Beton Bertulang (130 Kg Besi + Begesting)


Bahan :
0.277 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 1,116,266.67
2.773 Kg Paku @ Rp. 15,950.00 44,234.67
1.387 Ltr Minyak Begisting @ Rp. 3,300.00 4,576.00
136.500 Kg Besi Beton Polos @ Rp. 15,500.00 2,115,750.00
1.950 Btg Kawat Beton/Bendrat @ Rp. 18,400.00 35,880.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.120 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 759,000.00
2.800 Lbr Multipleks 9 mm @ Rp. 79,695.00 223,146.00
Upah :
4.593 Oh Pekerja @ Rp. 100,000.00 459,333.33
0.238 Oh Tukang Batu @ Rp. 125,000.00 29,791.67
1.127 Oh Tukang Kayu @ Rp. 125,000.00 140,833.33
0.910 Oh Tukang Besi @ Rp. 125,000.00 113,750.00
0.230 Oh Kepala Tukang @ Rp. - -
0.230 Oh Mandor @ Rp. 150,000.00 34,450.00
5,297,128.89 778,158.33
Jumlah 6,075,287.23

95 1,00 M3 Pekerjaan Plat Beton Bertulang (130 Kg Besi + Begesting + Perancah)


Bahan :
0.277 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 1,116,266.67
2.773 Kg Paku @ Rp. 15,950.00 44,234.67
1.387 Ltr Minyak Begisting @ Rp. 3,300.00 4,576.00
136.500 Kg Besi Beton Polos @ Rp. 15,500.00 2,115,750.00
1.950 Kg Kawat Beton/Bendrat @ Rp. 18,400.00 35,880.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.120 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 759,000.00
2.800 Lbr Multipleks 9 mm @ Rp. 79,695.00 223,146.00
Btg Kayu Dolken, panjang 4 m @ Rp. 39,100.00 -
Upah :
4.593 Oh Pekerja @ Rp. 100,000.00 459,333.33
0.238 Oh Tukang Batu @ Rp. 125,000.00 29,791.67
1.127 Oh Tukang Kayu @ Rp. 125,000.00 140,833.33
0.910 Oh Tukang Besi @ Rp. 125,000.00 113,750.00
0.230 Oh Kepala Tukang @ Rp. - -
0.230 Oh Mandor @ Rp. 150,000.00 34,450.00
5,297,128.89 778,158.33
Jumlah 6,075,287.23
96 1,00 M3 Pekerjaan Plat Beton Bertulang (150 Kg Besi + Begesting)
Bahan :
0.320 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 1,288,000.00
3.200 Kg Paku @ Rp. 15,950.00 51,040.00
1.600 Ltr Minyak Begisting @ Rp. 3,300.00 5,280.00
157.500 Kg Besi Beton Polos @ Rp. 15,500.00 2,441,250.00
2.250 Btg Kawat Beton/Bendrat @ Rp. 18,400.00 41,400.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.120 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 759,000.00
2.800 Lbr Multipleks 9 mm @ Rp. 79,695.00 223,146.00
32.000 Btg Kayu Dolken, panjang 4 m @ Rp. 39,100.00 1,251,200.00
Upah :
5.300 Oh Pekerja @ Rp. 100,000.00 530,000.00
0.275 Oh Tukang Batu @ Rp. 125,000.00 34,375.00
1.300 Oh Tukang Kayu @ Rp. 125,000.00 162,500.00
1.050 Oh Tukang Besi @ Rp. 125,000.00 131,250.00
0.265 Oh Kepala Tukang @ Rp. - -
0.265 Oh Mandor @ Rp. 150,000.00 39,750.00
7,058,591.56 897,875.00
Jumlah 7,956,466.56

97 1,00 M3 Pekerjaan Plat Beton Bertulang (160 Kg Besi + Begesting)


Bahan :
0.341 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 1,373,866.67
3.413 Kg Paku @ Rp. 15,950.00 54,442.67
1.707 Ltr Minyak Begisting @ Rp. 3,300.00 5,632.00
168.000 Kg Besi Beton Polos @ Rp. 15,500.00 2,604,000.00
2.400 Btg Kawat Beton/Bendrat @ Rp. 18,400.00 44,160.00
336.000 Kg Semen (PC) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Jawa ) @ Rp. 399,000.00 323,190.00
0.120 M3 Kayu Balok Meranti @ Rp. 6,325,000.00 759,000.00
2.800 Lbr Multipleks 9 mm @ Rp. 79,695.00 223,146.00
32.000 Btg Kayu Dolken, panjang 4 m @ Rp. 39,100.00 1,251,200.00
Upah :
5.653 Oh Pekerja @ Rp. 100,000.00 565,333.33
0.293 Oh Tukang Batu @ Rp. 125,000.00 36,666.67
1.387 Oh Tukang Kayu @ Rp. 125,000.00 173,333.33
1.120 Oh Tukang Besi @ Rp. 125,000.00 140,000.00
0.283 Oh Kepala Tukang @ Rp. - -
0.283 Oh Mandor @ Rp. 150,000.00 42,400.00
7,313,722.89 957,733.33
Jumlah 8,271,456.23

98 1,00 M3 Pekerjaan Beton Bertulang Camp. 1Pc : 2Ps : 3 Krl ( Strausz Dia. 30 cm )
Bahan :
336.000 Kg Semen ( Pc ) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah 2/3 ( Lokal ) @ Rp. 833,500.00 675,135.00
Upah :
1.650 Oh Pekerja @ Rp. 100,000.00 165,000.00
0.275 Oh Tukang Batu @ Rp. 125,000.00 34,375.00
0.028 Oh Kepala Tukang Batu @ Rp. - -
0.083 Oh Mandor @ Rp. 150,000.00 12,450.00
1,350,220.56 211,825.00
Jumlah 1,562,045.56
Pekerjaan Pembesian :
Bahan :
110.000 Kg Besi Beton Polos @ Rp. 15,500.00 1,705,000.00
1.500 Kg Kawat Beton @ Rp. 18,400.00 27,600.00
Jumlah 1,732,600.00
Upah :
0.770 Oh Pekerja @ Rp. 100,000.00 77,000.00
0.770 Oh Tukang Besi @ Rp. 125,000.00 96,250.00
0.077 Oh Kepala Tukang Besi @ Rp. - -
0.044 Oh Mandor @ Rp. 150,000.00 6,600.00
Jumlah 179,850.00
Pek. Pembesian = 1,732,600.00 + 179,850.00 1,912,450.00

Jadi untuk 1,00 M3 Pekerjaan Strouss Dia 30 cm : Rp. 1,562,045.56


Rp. 1,912,450.00
Rp. 3,474,495.56

99 1,00 M3 Pekerjaan Beton Bertulang Camp. 1Pc : 2Ps : 3 Krl ( Sloof 15/20 )
Bahan :
336.000 Kg Semen ( Pc ) @ Rp. 1,550.00 520,800.00
0.540 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 154,285.56
0.810 M3 Batu Pecah Mesin 2/3 (Jawa) @ Rp. 399,000.00 323,190.00
Upah :
1.650 Oh Pekerja @ Rp. 100,000.00 165,000.00
0.275 Oh Tukang Batu @ Rp. 125,000.00 34,375.00
0.028 Oh Kepala Tukang Batu @ Rp. - -
0.083 Oh Mandor @ Rp. 150,000.00 12,450.00
998,275.56 211,825.00
Jumlah 1,210,100.56
Pekerjaan Pembesian :
Bahan :
120.000 Kg Besi Beton Polos @ Rp. 15,500.00 1,860,000.00
1.700 Kg Kawat Beton @ Rp. 18,400.00 31,280.00
Jumlah 1,891,280.00
Upah :
0.791 Oh Pekerja @ Rp. 100,000.00 79,100.00
0.791 Oh Tukang Besi @ Rp. 125,000.00 98,875.00
0.079 Oh Kepala Tukang Besi @ Rp. - -
0.045 Oh Mandor @ Rp. 150,000.00 6,780.00
Jumlah 184,755.00
Pek. Pembesian = 1,891,280.00 + 184,755.00 2,076,035.00
Pekerjaan Begesting ( 1 kali Pakai ) :
Bahan :
3.900 Kg Paku @ Rp. 15,950.00 62,205.00
0.585 M3 Kayu Begisting @ Rp. 4,025,000.00 2,354,625.00
1.300 Ltr Minyak Begesting @ Rp. 3,300.00 4,290.00
Upah :
6.760 Oh Pekerja @ Rp. 100,000.00 676,000.00
3.380 Oh Tukang Kayu @ Rp. 125,000.00 422,500.00
0.338 Oh Kepala Tukang Kayu @ Rp. - -
0.338 Oh Mandor @ Rp. 150,000.00 50,700.00
2,421,120.00 1,149,200.00
Jumlah 3,570,320.00
Jadi untuk 1,00 M3 Pekerjaan Beton Bertulang : Rp. 1,210,100.56
Rp. 2,076,035.00
Rp. 3,570,320.00
Rp. 6,856,455.56

Pekerjaan Begesting ( 2 kali Pakai ) :


Bahan :
1.950 Kg Paku @ Rp. 15,950.00 31,102.50
0.293 M3 Kayu Begisting @ Rp. 4,025,000.00 1,177,312.50
0.650 Ltr Minyak Begesting @ Rp. 3,300.00 2,145.00
Upah :
6.760 Oh Pekerja @ Rp. 100,000.00 676,000.00
3.380 Oh Tukang Kayu @ Rp. 125,000.00 422,500.00
0.338 Oh Kepala Tukang Kayu @ Rp. - -
0.338 Oh Mandor @ Rp. 150,000.00 50,700.00
1,210,560.00 1,149,200.00
Jumlah 2,359,760.00
Jadi untuk 1,00 M3 Pekerjaan Beton Bertulang : Rp. 1,210,100.56
Rp. 2,076,035.00
Rp. 2,359,760.00
Rp. 5,645,895.56

100 1,00 M3 Pekerjaan Beton Bertulang Camp. 1Pc : 2Ps : 3 Krl ( Kolom Praktis 11 x 11 CM)
Bahan :
330.000 Kg Semen ( Pc ) @ Rp. 1,550.00 511,500.00
0.495 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 141,428.43
0.743 M3 Batu Pecah Mesin 2/3 (Jawa) @ Rp. 399,000.00 296,257.50
0.825 Kg Paku @ Rp. 15,950.00 13,158.75
0.165 M3 Kayu Begisting @ Rp. 4,025,000.00 664,125.00
247.000 Kg Besi Beton Polos @ Rp. 15,500.00 3,828,500.00
3.713 Kg Kawat Beton @ Rp. 18,400.00 68,310.00
Upah :
14.850 Oh Pekerja @ Rp. 100,000.00 1,485,000.00
1.650 Oh Tukang Batu @ Rp. 125,000.00 206,250.00
1.650 Oh Tukang Kayu @ Rp. 125,000.00 206,250.00
1.650 Oh Tukang Besi @ Rp. 125,000.00 206,250.00
0.495 Oh Kepala Tukang @ Rp. - -
0.743 Oh Mandor @ Rp. 150,000.00 111,375.00
5,523,279.68 2,215,125.00
Jumlah 7,738,404.68
101 1,00 M3 Pekerjaan Beton Bertulang Camp. 1Pc : 2Ps : 3 Krl ( Rink Balok 11 x 15 CM)
Bahan :
333.000 Kg Semen ( Pc ) @ Rp. 1,550.00 516,150.00
0.545 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 155,828.42
0.909 M3 Batu Pecah Mesin 2/3 (Jawa) @ Rp. 399,000.00 362,691.00
1.212 Kg Paku @ Rp. 15,950.00 19,331.40
0.182 M3 Kayu Begisting @ Rp. 4,025,000.00 731,745.00
218.000 Kg Besi Beton Polos @ Rp. 15,500.00 3,379,000.00
3.030 Kg Kawat Beton @ Rp. 18,400.00 55,752.00
Upah :
18.00 Oh Pekerja @ Rp. 100,000.00 1,799,820.00
2.000 Oh Tukang Batu @ Rp. 125,000.00 249,975.00
2.000 Oh Tukang Kayu @ Rp. 125,000.00 249,975.00
2.000 Oh Tukang Besi @ Rp. 125,000.00 249,975.00
0.606 Oh Kepala Tukang @ Rp. - -
0.909 Oh Mandor @ Rp. 150,000.00 136,350.00
5,220,497.82 2,686,095.00
Jumlah 7,906,592.82
102 1,00 M3 Pekerjaan Beton Bertulang Camp. 1Pc : 2Ps : 3 Kr ( Plat 12 cm, K 250/ 19,3 MPa )
Bahan :
371.000 Kg Semen ( Pc ) @ Rp. 1,550.00 575,050.00
0.499 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 142,448.84
0.776 M3 Batu Pecah Mesin 2/3 (Jawa) @ Rp. 399,000.00 309,446.67
Upah :
1.650 Oh Pekerja @ Rp. 100,000.00 165,000.00
0.275 Oh Tukang Batu @ Rp. 125,000.00 34,375.00
0.028 Oh Kepala Tukang Batu @ Rp. - -
0.083 Oh Mandor @ Rp. 150,000.00 12,450.00
1,026,945.50 211,825.00
Jumlah 1,238,770.50
Pekerjaan Pembesian :
Bahan :
160.000 Kg Besi Beton Polos @ Rp. 15,500.00 2,480,000.00
2.400 Kg Kawat Beton @ Rp. 18,400.00 44,160.00
Jumlah 2,524,160.00
Upah :
1.071 Oh Pekerja @ Rp. 100,000.00 107,100.00
1.071 Oh Tukang Besi @ Rp. 125,000.00 133,875.00
0.107 Oh Kepala Tukang Besi @ Rp. - -
0.061 Oh Mandor @ Rp. 150,000.00 9,180.00
Jumlah 250,155.00
Pek. Pembesian = 1,697,400.00 + 250,155.00 1,947,555.00
Pekerjaan Begesting ( 1 kali Pakai ) :
Bahan :
0.125 M3 Kayu Balok Klas II @ Rp. 6,325,000.00 790,308.75
3.332 Kg Paku @ Rp. 15,950.00 53,145.40
0.333 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 1,341,130.00
2.916 Lbr Multiplek 1,22 x 2,44 x 9 mm @ Rp. 79,695.00 232,350.77
49.980 Btg Dolken ( Dia 8-10 Cm ) x 4 M @ Rp. 39,100.00 1,954,218.00
1.666 Ltr Minyak Begisting @ Rp. 3,300.00 5,497.80
Upah :
5.498 Oh Pekerja @ Rp. 100,000.00 549,780.00
2.749 Oh Tukang Kayu @ Rp. 125,000.00 343,612.50
0.275 Oh Kepala Tukang Kayu @ Rp. - -
0.275 Oh Mandor @ Rp. 150,000.00 41,233.50
4,376,650.72 934,626.00
Jumlah 5,311,276.72

Jadi untuk 1,00 M3 Pek. Beton Bertulang ( Plat ) : Rp. 1,238,770.50


Rp. 1,947,555.00
Rp. 5,311,276.72
Rp. 8,497,602.23
Pekerjaan Begesting ( 2 kali Pakai ) :
Bahan :
0.062 M3 Kayu Balok Klas II @ Rp. 6,325,000.00 395,154.38
1.666 Kg Paku @ Rp. 15,950.00 26,572.70
0.167 M3 Kayu Papan Begesting @ Rp. 4,025,000.00 670,565.00
1.458 Lbr Multiplek 1,22 x 2,44 x 9 mm @ Rp. 79,695.00 116,175.39
24.990 Btg Dolken ( Dia 8-10 Cm ) x 4 M @ Rp. 39,100.00 977,109.00
0.833 Ltr Minyak Begisting @ Rp. 3,300.00 2,748.90
Upah :
5.498 Oh Pekerja @ Rp. 100,000.00 549,780.00
2.749 Oh Tukang Kayu @ Rp. 125,000.00 343,612.50
0.275 Oh Kepala Tukang Kayu @ Rp. - -
0.275 Oh Mandor @ Rp. 150,000.00 41,233.50
2,188,325.36 934,626.00
Jumlah 3,122,951.36
Jadi untuk 1,00 M3 Pek. Beton Bertulang ( Plat ) : Rp. 1,238,770.50
Rp. 1,947,555.00
Rp. 3,122,951.36
Rp. 6,309,276.87

1.0000 m3 Membongkar cetakan


4.0000 org Pekerja @ Rp. 100,000.00 = 400,000.00
Jumlah = 400,000.00

SNI. 03-3436-2002 PEKERJAAN PENUTUP ATAP


103 1,00 M2 Pasang Genteng Kodok Ex. Karang Penang
Bahan :
25.000 Bh Genteng Kodok ex. Kr. Penang @ Rp. 1,800.00 45,000.00
Upah :
0.150 Oh Pekerja @ Rp. 100,000.00 15,000.00
0.075 Oh Tukang Batu @ Rp. 125,000.00 9,375.00
0.008 Oh Kepala Tukang Batu @ Rp. - -
0.008 Oh Mandor @ Rp. 150,000.00 1,200.00
45,000.00 25,575.00
Jumlah 70,575.00
104 1,00 M' Pasang Genteng Wuwung Ex. Karang Penang
Bahan :
5.000 Bh Genteng Wuwung Kr. Penang @ Rp. 3,450.00 17,250.00
8.000 Kg Semen ( Pc ) @ Rp. 1,550.00 12,400.00
0.032 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 9,143.71
Upah :
0.400 Oh Pekerja @ Rp. 100,000.00 40,000.00
0.200 Oh Tukang Batu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Batu @ Rp. - -
0.002 Oh Mandor @ Rp. 150,000.00 300.00
38,793.71 65,300.00
Jumlah 104,093.71
105 1,00 M2 Pasang Genteng Glazuur
Bahan :
25.000 Bh Genteng Glazuur @ Rp. 15,700.00 392,500.00
Upah :
0.150 Oh Pekerja @ Rp. 100,000.00 15,000.00
0.075 Oh Tukang Batu @ Rp. 125,000.00 9,375.00
0.008 Oh Kepala Tukang Batu @ Rp. - -
0.008 Oh Mandor @ Rp. 150,000.00 1,200.00
392,500.00 25,575.00
Jumlah 418,075.00
106 1,00 M' Pasang Genteng Wuwung Glazuur
Bahan :
5.000 Bh Genteng Wuwung Glazuur @ Rp. 31,600.00 158,000.00
8.000 Kg Semen ( Pc ) @ Rp. 1,550.00 12,400.00
0.032 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 9,143.71
Upah :
0.400 Oh Pekerja @ Rp. 100,000.00 40,000.00
0.200 Oh Tukang Batu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Batu @ Rp. - -
0.002 Oh Mandor @ Rp. 150,000.00 300.00
179,543.71 65,300.00
Jumlah 244,843.71
107 1,00 M2 Pasang Genteng Beton
Bahan :
11.000 Bh Genteng Beton @ Rp. 5,750.00 63,250.00
0.030 Kg Paku @ Rp. 15,950.00 478.50
Upah :
0.150 Oh Pekerja @ Rp. 100,000.00 15,000.00
0.075 Oh Tukang Batu @ Rp. 125,000.00 9,375.00
0.008 Oh Kepala Tukang Batu @ Rp. - -
0.008 Oh Mandor @ Rp. 150,000.00 1,200.00
63,728.50 25,575.00
Jumlah 89,303.50

108 1,00 M2 Pasang Asbes Gelombang (1,05 x 2,442 m) x 6mm


Bahan :
0.430 Lbr Asbes Gelombang Besar @ Rp. 103,500.00 44,505.00
0.120 Kg Paku ASG @ Rp. 36,795.00 4,415.40
Upah :
0.140 Oh Pekerja @ Rp. 100,000.00 14,000.00
0.070 Oh Tukang Kayu @ Rp. 125,000.00 8,750.00
0.007 Oh Kepala Tukang Kayu @ Rp. - -
0.007 Oh Mandor @ Rp. 150,000.00 1,050.00
48,920.40 23,800.00
Jumlah 72,720.40

109 1,00 M' Pasang Nok Stel Gelombang 1,05 M


Bahan :
2.100 Lbr Nok Asbes Gelombang Besar @ Rp. 69,000.00 144,900.00
6.000 Bh Paku ASG / Sekrup 3,5" @ Rp. 30,690.00 184,140.00
Upah :
0.084 Oh Pekerja @ Rp. 100,000.00 8,400.00
0.125 Oh Tukang Kayu @ Rp. 125,000.00 15,625.00
0.013 Oh Kepala Tukang Kayu @ Rp. - -
0.004 Oh Mandor @ Rp. 150,000.00 600.00
329,040.00 24,625.00
Jumlah 353,665.00

110 1,00 M2 Pasang Atap Seng Galvalume


Bahan :
1.370 M2 Seng Galvalume @ Rp. - -
4.000 Bh Paku Rifet ( Scrup ) @ Rp. 30,690.00 122,760.00
1.000 Ls Biaya Mekanik / Peralatan @ Rp. 2,500.00 2,500.00
Upah :
0.150 Oh Pekerja @ Rp. 100,000.00 15,000.00
0.750 Oh Tukang Besi @ Rp. 125,000.00 93,750.00
0.008 Oh Kepala Tukang Besi @ Rp. - -
0.006 Oh Mandor @ Rp. 150,000.00 900.00
122,760.00 109,650.00
Jumlah 232,410.00

110 1,00 M2 Pasang Aluminium Foil/Sisalation


Bahan :
1.050 M2 Aluminium Foil/Sisalation @ Rp. 10,000.00 10,500.00
Upah :
0.150 Oh Pekerja @ Rp. 100,000.00 15,000.00
0.050 Oh Tukang Besi @ Rp. 125,000.00 6,250.00
0.005 Oh Kepala Tukang Kayu @ Rp. - -
0.008 Oh Mandor @ Rp. 150,000.00 1,200.00
10,500.00 22,450.00
Jumlah 32,950.00

SNI. 2839-2008 PEKERJAAN LANGIT-LANGIT


111 1,00 M2 Langit-Langit Asbes 1 x 1 m Rangka Kayu Meranti
Bahan : `
1.100 M2 Asbes Datar 1,00x1,00 m Ex. Atrisco @ Rp. 18,400.00 20,240.00
0.0154 M3 Kayu Meranti Klas I @ Rp. 6,325,000.00 97,405.00
0.200 Kg Paku @ Rp. 15,950.00 3,190.00
0.010 Kg Paku Triplek @ Rp. 20,900.00 209.00
Upah :
0.180 Oh Pekerja @ Rp. 100,000.00 18,000.00
0.370 Oh Tukang Kayu @ Rp. 125,000.00 46,250.00
0.037 Oh Kepala Tukang Kayu @ Rp. - -
0.079 Oh Mandor @ Rp. 150,000.00 11,850.00
121,044.00 76,100.00
Jumlah 197,144.00

112 1,00 M2 Langit-Langit Calsiboard Rangka Kayu Meranti


Bahan : `
0.364 Lbr Calsiboard 1,22 x 2,44 x 4 mm @ Rp. 69,000.00 25,116.00
0.016 M3 Kayu Meranti Klas I @ Rp. 6,325,000.00 103,097.50
0.200 Kg Paku @ Rp. 15,950.00 3,190.00
0.110 Kg Paku Triplek @ Rp. 20,900.00 2,299.00
Upah :
0.250 Oh Pekerja @ Rp. 100,000.00 25,000.00
0.350 Oh Tukang Kayu @ Rp. 125,000.00 43,750.00
0.035 Oh Kepala Tukang Kayu @ Rp. - -
0.080 Oh Mandor @ Rp. 150,000.00 12,000.00
133,702.50 80,750.00
Jumlah 214,452.50

88 1,00 M2 Pasang Plafond Calsiboard Rangka Metal Hollow


Bahan : `
1.100 M2 Polywood Ceiling @ Rp. - -
0.012 M3 Kayu Meranti Klas I @ Rp. 6,325,000.00 75,900.00
0.060 Kg Paku @ Rp. 20,900.00 1,254.00
Upah :
0.270 Oh Pekerja @ Rp. 100,000.00 27,000.00
0.400 Oh Tukang Kayu @ Rp. 125,000.00 50,000.00
0.040 Oh Kepala Tukang Kayu @ Rp. - -
0.014 Oh Mandor @ Rp. 150,000.00 2,100.00
77,154.00 79,100.00
Jumlah 156,254.00

88 1,00 M2 Pasang Plafond Calsiboard Rangka Metal Hollow


Bahan : `
4.500 m1 Rangka hollow 4x4 cm @ Rp. 11400 51,300.00
0.360 lbr Kalsiboard 3.5 mm @ Rp. 69,000.00 24,840.00
0.050 roll Kasa gypsum @ Rp. 12,240.00 612.00
0.450 kg Tepung gypsum @ Rp. 4,284.00 1,927.80
0.003 kg Alkasit @ Rp. 367,200.00 1,101.60
0.150 kg Paku skrup @ Rp. 12,240.00 1,836.00
5.000 m1 Kawat penggantung @ Rp. 612.00 3,060.00
Upah :
0.180 Oh Pekerja @ Rp. 100,000.00 18,000.00
0.320 Oh Tukang Kayu @ Rp. 125,000.00 40,000.00
0.032 Oh Kepala Tukang Kayu @ Rp. - -
0.076 Oh Mandor @ Rp. 150,000.00 11,400.00
84,677.40 69,400.00
Jumlah 154,077.40

SNI. 00-0000-2002 PEKERJAAN SANITASI


115 1,00 Buah Pasang Closed Duduk Monoblock
Bahan :
1.000 Bh Closet Duduk Monoblok ex. Toto @ Rp. 4,292,750.00 4,292,750.00
1.000 Ls Perlengkapan (6% Harga Kloset) @ Rp. 257,565.00 257,565.00
Upah :
3.300 Oh Pekerja @ Rp. 100,000.00 330,000.00
1.100 Oh Tukang Batu @ Rp. 125,000.00 137,500.00
0.001 Oh Kepala Tukang Batu @ Rp. - -
0.160 Oh Mandor @ Rp. 150,000.00 24,000.00
4,550,315.00 491,500.00
Jumlah 5,041,815.00
116 1,00 Buah Pasang Closed Jongkok Porselen
Bahan :
1.000 Bh Closed Jongkok ex. INA, KIA @ Rp. 183,975.00 183,975.00
6.000 Kg Semen (Pc) @ Rp. 1,550.00 9,300.00
0.010 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 2,857.41
Upah :
1.000 Oh Pekerja @ Rp. 100,000.00 100,000.00
1.500 Oh Tukang Batu @ Rp. 125,000.00 187,500.00
1.500 Oh Kepala Tukang Batu @ Rp. - -
0.160 Oh Mandor @ Rp. 150,000.00 24,000.00
196,132.41 311,500.00
Jumlah 507,632.41
117 1,00 Buah Pasang Urinoir
Bahan :
1.000 Bh Urinoir Keramik @ Rp. 1,055,000.00 1,055,000.00
1.000 Ls Perlengkapan (30% Harga Urinoir) @ Rp. 316,500.00 316,500.00
6.000 Kg Semen (Pc) @ Rp. 1,550.00 9,300.00
0.010 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 2,857.41
Upah :
1.000 Oh Pekerja @ Rp. 100,000.00 100,000.00
1.000 Oh Tukang Batu @ Rp. 125,000.00 125,000.00
0.100 Oh Kepala Tukang Batu @ Rp. - -
0.100 Oh Mandor @ Rp. 150,000.00 15,000.00
1,383,657.41 240,000.00
Jumlah 1,623,657.41
118 1,00 Buah Pasang Wastafel
Bahan :
1.000 Bh Wastafel ex. INA @ Rp. 490,600.00 490,600.00
1.000 Ls Perlengkapan (12% Harga Wastafel) @ Rp. 58,872.00 58,872.00
6.000 Kg Semen (Pc) @ Rp. 1,550.00 9,300.00
0.010 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 2,857.41
Upah :
1.200 Oh Pekerja @ Rp. 100,000.00 120,000.00
1.450 Oh Tukang Batu @ Rp. 125,000.00 181,250.00
0.150 Oh Kepala Tukang Batu @ Rp. - -
0.100 Oh Mandor @ Rp. 150,000.00 15,000.00
561,629.41 316,250.00
Jumlah 877,879.41
119 1,00 Buah Pasang Bak Mandi Fiberglass ( 0,3 M3 )
Bahan :
1.000 Bh Bak Fiberglass @ Rp. 735,900.00 735,900.00
1.000 Ls Perlengkapan (18% Harga Bak) @ Rp. 132,462.00 132,462.00
Upah :
1.800 Oh Pekerja @ Rp. 100,000.00 180,000.00
2.700 Oh Tukang Batu @ Rp. 125,000.00 337,500.00
0.540 Oh Kepala Tukang Batu @ Rp. - -
0.110 Oh Mandor @ Rp. 150,000.00 16,500.00
868,362.00 534,000.00
Jumlah 1,402,362.00
120 1,00 Buah Pasang Kran Air ( Steinlessteel )
Bahan :
1.000 Bh Kran Air ( Steinlessteel ) @ Rp. 110,385.00 110,385.00
0.025 Bh Seal Tape @ Rp. 5,000.00 125.00
Upah :
0.010 Oh Pekerja @ Rp. 100,000.00 1,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.005 Oh Mandor @ Rp. 150,000.00 750.00
110,510.00 14,250.00
Jumlah 124,760.00
121 1,00 Buah Pasang Floor Drain
Bahan :
1.000 Bh Floor Drain @ Rp. 24,530.00 24,530.00
Upah :
0.010 Oh Pekerja @ Rp. 100,000.00 1,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.005 Oh Mandor @ Rp. 150,000.00 750.00
24,530.00 14,250.00
Jumlah 38,780.00
122 1,00 Buah Pasang Avour Bak Mandi
Bahan :
1.000 Bh Avour Bak Mandi @ Rp. 30,690.00 30,690.00
Upah :
0.010 Oh Pekerja @ Rp. 100,000.00 1,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Batu @ Rp. - -
0.005 Oh Mandor @ Rp. 150,000.00 750.00
30,690.00 14,250.00
Jumlah 44,940.00

123 1,00 M' Pasang Pipa Pvc Ø 1/2" AW


Bahan :
1.200 M' Pipa Pvc Ø 1/2" AW @ Rp. 30,690.00 36,828.00
1.000 ls Perlengkapan (35% Harga Pipa) @ Rp. 10,741.50 10,741.50
Upah :
0.036 Oh Pekerja @ Rp. 100,000.00 3,600.00
0.060 Oh Tukang Batu @ Rp. 125,000.00 7,500.00
0.006 Oh Kepala Tukang Batu @ Rp. - -
0.0018 Oh Mandor @ Rp. 150,000.00 270.00
47,569.50 11,370.00
Jumlah 58,939.50

124 1,00 M' Pasang Pipa Pvc Ø 3/4" AW


Bahan :
1.200 M' Pipa Pvc Ø 3/4" AW @ Rp. 14,712.50 17,655.00
1.000 ls Perlengkapan (35% Harga Pipa) @ Rp. 5,149.38 5,149.38
Upah :
0.036 Oh Pekerja @ Rp. 100,000.00 3,600.00
0.060 Oh Tukang Pipa @ Rp. 125,000.00 7,500.00
0.006 Oh Kepala Tukang Batu @ Rp. - -
0.0018 Oh Mandor @ Rp. 150,000.00 270.00
22,804.38 11,370.00
Jumlah 34,174.38

125 1,00 M' Pasang Pipa Pvc Ø 3" AW


Bahan :
1.200 M' Pipa Pvc Ø 3" AW @ Rp. 39,861.25 47,833.50
1.000 ls Perlengkapan (35% Harga Pipa) @ Rp. 13,951.44 13,951.44
Upah :
0.081 Oh Pekerja @ Rp. 100,000.00 8,100.00
0.135 Oh Tukang Pipa @ Rp. 125,000.00 16,875.00
0.0135 Oh Kepala Tukang Batu @ Rp. - -
0.0041 Oh Mandor @ Rp. 150,000.00 615.00
61,784.94 25,590.00
Jumlah 87,374.94

126 1,00 M' Pasang Pipa Pvc Ø 4" AW


Bahan :
1.200 M' Pipa Pvc Ø 4" AW @ Rp. 52,126.25 62,551.50
1.000 ls Perlengkapan (35% Harga Pipa) @ Rp. 18,244.19 18,244.19
Upah :
0.081 Oh Pekerja @ Rp. 100,000.00 8,100.00
0.135 Oh Tukang Pipa @ Rp. 125,000.00 16,875.00
0.0135 Oh Kepala Tukang Batu @ Rp. - -
0.0041 Oh Mandor @ Rp. 150,000.00 615.00
80,795.69 25,590.00
Jumlah 106,385.69

127 1,00 Buah Bak Kontrol (30 x 30) t = 35 cm


Bahan :
119.000 Bh Bata Merah ( Lokal ) @ Rp. 1,200.00 142,800.00
44.000 Kg Semen ( Pc ) @ Rp. 1,550.00 68,200.00
0.070 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 20,001.87
0.070 M3 Batu Pecah Mesin 2/3 (Jawa) @ Rp. 399,000.00 27,930.00
1.600 Kg Besi Beton Polos @ Rp. 15,500.00 24,800.00
0.060 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 17,142.84
Upah :
3.200 Oh Pekerja @ Rp. 100,000.00 320,000.00
1.015 Oh Tukang Batu @ Rp. 125,000.00 126,875.00
0.0015 Oh Kepala Tukang Batu @ Rp. - -
0.016 Oh Mandor @ Rp. 150,000.00 2,400.00
300,874.71 449,275.00
Jumlah 750,149.71

128 1,00 Buah Bak Kontrol (60 x 60) t = 65 cm


Bahan :
306.00 Bh Bata Merah ( Lokal ) @ Rp. 1,200.00 367,200.00
114.00 Kg Semen ( Pc ) @ Rp. 1,550.00 176,700.00
0.184 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 52,576.34
0.033 M3 Batu Pecah Mesin 2/3 (Jawa) @ Rp. 399,000.00 13,167.00
4.850 Kg Besi Beton Polos @ Rp. 15,500.00 75,175.00
0.120 M3 Pasir Beton ( Jawa ) @ Rp. 285,714.00 34,285.68
Upah :
2.160 Oh Pekerja @ Rp. 100,000.00 216,000.00
0.720 Oh Tukang Batu @ Rp. 125,000.00 90,000.00
0.072 Oh Kepala Tukang Batu @ Rp. - -
0.100 Oh Tukang Gali @ Rp. 125,000.00 12,500.00
0.108 Oh Mandor @ Rp. 150,000.00 16,200.00
719,104.02 334,700.00
Jumlah 1,053,804.02

104 Septictank + Resapan 3 Kompartemen Ukuran Besar ( 3,50 x 1,80 x 1,50 )


A. Septictank
Bahan :
9.450 M3 Galian Tanah @ Rp. 78,750.00 744,187.50
2.060 M3 Urugan Peddel @ Rp. 103,070.40 212,325.02
13.880 M2 Pasangan 1 Bata 1 : 3 @ Rp. 306,574.93 4,255,260.04
1.600 M2 Pasangan 1/2 Bata 1 : 3 @ Rp. 148,453.14 237,525.02
25.680 M2 Plesteran 1 : 3 @ Rp. 69,624.84 1,787,965.97
0.054 M3 Balok Beton 15/20 @ Rp. #REF! #REF!
0.480 M3 Plat Beton @ Rp. #REF! #REF!
Jumlah #REF!
B. Resapan
Bahan :
2.200 M3 Galian Tanah @ Rp. 78,750.00 173,250.00
1.560 M3 Anstampeng @ Rp. 474,685.34 740,509.14
1.560 M2 Pasangan 1 Bata 1 : 3 @ Rp. 306,574.93 478,256.89
0.100 M3 Plat Beton @ Rp. #REF! #REF!
2.000 M' Pipa PVC O 2" @ Rp. #VALUE! #VALUE!
1.000 M3 Kerikil @ Rp. 833,500.00 833,500.00
1.000 Ls Ijuk #REF! #REF!
Jumlah #REF!
Jadi Untuk Pekerjaan Septictank dan Resapan = #REF!
#REF!
#REF!
105 Septictank + Resapan 3 Kompartemen Ukuran Sedang ( 2,60 x 1,10 x 1,20 )
A. Septictank
Bahan :
3.580 M3 Galian Tanah @ Rp. 78,750.00 281,925.00
0.860 M3 Urugan Peddel @ Rp. 103,070.40 88,640.54
11.240 M2 Pasangan 1/2 Bata 1 : 3 @ Rp. 306,574.93 3,445,902.22
20.320 M2 Plesteran 1 : 3 @ Rp. 69,624.84 1,414,776.81
0.033 M3 Balok Beton 15/20 @ Rp. #REF! #REF!
0.260 M3 Plat Beton @ Rp. #REF! #REF!
Jumlah #REF!
B. Resapan
Bahan :
2.940 M3 Galian Tanah @ Rp. 78,750.00 231,525.00
1.800 M3 Anstampeng @ Rp. 474,685.34 854,433.62
0.100 M3 Plat Beton @ Rp. #REF! #REF!
2.000 M' Pipa PVC O 2" @ Rp. #VALUE! #VALUE!
1.000 M3 Kerikil @ Rp. 833,500.00 833,500.00
1.000 Ls Ijuk #REF! #REF!
Jumlah #REF!
Jadi Untuk Pekerjaan Septictank dan Resapan = #REF!
#REF!
#REF!
106 Septictank + Resapan 2 Kompartemen Ukuran Kecil ( 1,65 x 1,10 x 1,25 )
A. Septictank
Bahan :
3.010 M3 Galian Tanah @ Rp. 78,750.00 237,037.50
0.940 M3 Urugan Peddel @ Rp. 103,070.40 96,886.18
8.510 M2 Pasangan 1/2 Bata 1 : 3 @ Rp. 306,574.93 2,608,952.66
20.610 M2 Plesteran 1 : 3 @ Rp. 69,624.84 1,434,968.01
0.240 M3 Plat Beton @ Rp. 5,599,923.89 1,343,981.73
Jumlah 5,721,826.09
B. Resapan
Bahan :
2.940 M3 Galian Tanah @ Rp. 78,750.00 231,525.00
1.800 M3 Anstampeng @ Rp. 474,685.34 854,433.62
0.100 M3 Plat Beton @ Rp. 5,599,923.89 559,992.39
2.000 M' Pipa PVC O 2" @ Rp. 21,463.75 42,927.50
1.000 M3 Kerikil @ Rp. 833,500.00 833,500.00
1.000 Ls Ijuk 23,925.00 23,925.00
Jumlah 2,546,303.51
Jadi Untuk Pekerjaan Septictank dan Resapan = 5,721,826.09
2,546,303.51
8,268,129.60
SNI. 00-0000-2002 PEKERJAAN BESI
129 1,00 M' Pasang Talang Datar / Jurai Seng BJLS 28 Lebar 90 Cm
Bahan :
1.050 M' Seng Plat BJLS 28 @ Rp. 99,935.00 104,931.75
0.015 Kg Paku @ Rp. 24,530.00 367.95
0.0190 M3 Kayu Meranti Papan @ Rp. 6,612,500.00 125,637.50
Upah :
0.200 Oh Pekerja @ Rp. 100,000.00 20,000.00
0.400 Oh Tukang Kayu @ Rp. 125,000.00 50,000.00
0.025 Oh Kepala Tukang Kayu @ Rp. - -
0.01000 Oh Mandor @ Rp. 150,000.00 1,500.00
230,937.20 71,500.00
Jumlah 302,437.20

130 1,00 Kg Pasang Besi Profil


Bahan :
1.150 Kg Besi Profil @ Rp. 18,400.00 21,160.00
Upah :
0.060 Oh Pekerja @ Rp. 100,000.00 6,000.00
0.060 Oh Tukang Besi @ Rp. 125,000.00 7,500.00
0.006 Oh Kepala Tukang Besi @ Rp. - -
0.0030 Oh Mandor @ Rp. 150,000.00 450.00
21,160.00 13,950.00
Jumlah 35,110.00

131 10,00 Cm Pengelasan dengan Las Listrik


Bahan :
0.400 Kg Elektrode Las @ Rp. 18,590.00 7,436.00
0.170 Jam Sewa Welding Set @ Rp. 85,030.00 14,455.10
0.300 Ltr Solar @ Rp. 11,715.00 3,514.50
0.040 Ltr Minyak Pelumas @ Rp. 38,500.00 1,540.00
Upah :
0.040 Oh Pekerja @ Rp. 100,000.00 4,000.00
0.020 Oh Tukang Besi @ Rp. 125,000.00 2,500.00
0.0002 Oh Kepala Tukang Besi @ Rp. - -
0.0002 Oh Mandor @ Rp. 150,000.00 30.00
26,945.60 6,530.00
Jumlah 33,475.60

132 1,00 Kg Pasang Rangka Kuda-kuda Baja WF


Bahan :
1.150 Kg Besi Baja WF @ Rp. 18,400.00 21,160.00
Upah :
0.060 Oh Pekerja @ Rp. 100,000.00 6,000.00
0.060 Oh Tukang Las Konstruksi @ Rp. 125,000.00 7,500.00
0.006 Oh Kepala Tukang Besi @ Rp. - -
0.0030 Oh Mandor @ Rp. 150,000.00 450.00
21,160.00 13,950.00
Jumlah 35,110.00

133 1,00 Kg Pekerjaan Perakitan


Bahan :
0.008 Jam Sewa Welding Set @ Rp. 85,030.00 680.24
0.010 Ltr Solar @ Rp. 11,715.00 117.15
0.001 Ltr Minyak Pelumas @ Rp. 38,500.00 38.50
Upah :
0.001 Oh Pekerja @ Rp. 100,000.00 100.00
0.001 Oh Tukang Besi Konstruksi @ Rp. 125,000.00 125.00
0.00001 Oh Kepala Tukang @ Rp. - -
0.005 Oh Mandor @ Rp. 150,000.00 750.00
835.89 975.00
Jumlah 1,810.89

134 1 M2 Pengecatan Permukaan Baja dengan Meni Besi


Bahan :
0.100 Kg Meni Besi @ Rp. 27,610.00 2,761.00
0.010 Bh Kuas @ Rp. - -
Upah :
0.020 Oh Pekerja @ Rp. 100,000.00 2,000.00
0.200 Oh Tukang Cat @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang @ Rp. - -
0.010 Oh Mandor @ Rp. 150,000.00 1,500.00
2,761.00 28,500.00
Jumlah 31,261.00

SNI. 00-0000-2002 PEKERJAAN KUNCI DAN KACA


135 1,00 Buah Pasang Kunci Biasa 2 x Putar
Bahan :
1.000 Bh Kunci Biasa ex. Merk Anchor Kecil @ Rp. 134,915.00 134,915.00
Upah :
0.010 Oh Pekerja @ Rp. 100,000.00 1,000.00
0.500 Oh Tukang Kayu @ Rp. 125,000.00 62,500.00
0.010 Oh Kepala Tukang Kayu @ Rp. - -
0.005 Oh Mandor @ Rp. 150,000.00 750.00
134,915.00 64,250.00
Jumlah 199,165.00

136 1,00 Buah Pasang Kunci Silinder


Bahan :
1.000 Bh Kunci Silinder @ Rp. - -
Upah :
0.005 Oh Pekerja @ Rp. 100,000.00 500.00
0.500 Oh Tukang Kayu @ Rp. 125,000.00 62,500.00
0.005 Oh Kepala Tukang Kayu @ Rp. - -
0.00025 Oh Mandor @ Rp. 150,000.00 37.50
- 63,037.50
Jumlah 63,037.50

137 1,00 Buah Pasang Engsel Pintu


Bahan :
1.000 Bh Engsel Pintu @ Rp. 24,530.00 24,530.00
Upah :
0.015 Oh Pekerja @ Rp. 100,000.00 1,500.00
0.150 Oh Tukang Kayu @ Rp. 125,000.00 18,750.00
0.015 Oh Kepala Tukang Kayu @ Rp. - -
0.00075 Oh Mandor @ Rp. 150,000.00 112.50
24,530.00 20,362.50
Jumlah 44,892.50

138 1,00 Buah Pasang Engsel Jendela


Bahan :
1.000 Bh Engsel Jendela @ Rp. 20,845.00 20,845.00
Upah :
0.010 Oh Pekerja @ Rp. 100,000.00 1,000.00
0.100 Oh Tukang Kayu @ Rp. 125,000.00 12,500.00
0.010 Oh Kepala Tukang Kayu @ Rp. - -
0.00050 Oh Mandor @ Rp. 150,000.00 75.00
20,845.00 13,575.00
Jumlah 34,420.00

139 1,00 Buah Pasang Grendel Jendela


Bahan :
1.000 Bh Grendel Jendela @ Rp. 12,265.00 12,265.00
Upah :
0.020 Oh Pekerja @ Rp. 100,000.00 2,000.00
0.200 Oh Tukang Kayu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Kayu @ Rp. - -
0.0010 Oh Mandor @ Rp. 150,000.00 150.00
12,265.00 27,150.00
Jumlah 39,415.00

1,00 Buah Pasang Grendel pintu


Bahan :
1.000 Bh Grendel Pintu @ Rp. 30,635.00 30,635.00
Upah :
0.020 Oh Pekerja @ Rp. 100,000.00 2,000.00
0.200 Oh Tukang Kayu @ Rp. 125,000.00 25,000.00
0.020 Oh Kepala Tukang Kayu @ Rp. - -
0.0010 Oh Mandor @ Rp. 150,000.00 150.00
30,635.00 27,150.00
Jumlah 57,785.00

140 1,00 Buah Pasang Hag/Kait Angin


Bahan :
1.000 Bh Hag Angin @ Rp. 18,370.00 18,370.00
Upah :
0.015 Oh Pekerja @ Rp. 100,000.00 1,500.00
0.150 Oh Tukang Kayu @ Rp. 125,000.00 18,750.00
0.015 Oh Kepala Tukang Kayu @ Rp. - -
0.00075 Oh Mandor @ Rp. 150,000.00 112.50
18,370.00 20,362.50
Jumlah 38,732.50

141 1,00 Buah Pasang Door Closer


Bahan :
1.000 Bh Door Closer @ Rp. - -
Upah :
0.050 Oh Pekerja @ Rp. 100,000.00 5,000.00
0.500 Oh Tukang Kayu @ Rp. 125,000.00 62,500.00
0.050 Oh Kepala Tukang Kayu @ Rp. - -
0.0025 Oh Mandor @ Rp. 150,000.00 375.00
- 67,875.00
Jumlah 67,875.00

142 1,00 Buah Pasang Door Holder


Bahan :
1.000 Bh Door Holder @ Rp. - -
Upah :
0.050 Oh Pekerja @ Rp. 100,000.00 5,000.00
0.500 Oh Tukang Kayu @ Rp. 125,000.00 62,500.00
0.050 Oh Kepala Tukang Kayu @ Rp. - -
0.0025 Oh Mandor @ Rp. 150,000.00 375.00
- 67,875.00
Jumlah 67,875.00

143 1,00 M2 Pasang Kaca bening t = 5 mm


Bahan :
1.000 M2 Kaca Polos 5 mm @ Rp. 116,490.00 116,490.00
Upah :
0.015 Oh Pekerja @ Rp. 100,000.00 1,500.00
0.150 Oh Tukang Kayu @ Rp. 125,000.00 18,750.00
0.015 Oh Kepala Tukang Kayu @ Rp. - -
0.00075 Oh Mandor @ Rp. 150,000.00 112.50
116,490.00 20,362.50
Jumlah 136,852.50

1,00 M2 Pasang Kaca es t = 3 mm


Bahan :
1.000 M2 Kaca Es 3 mm @ Rp. 104,500.00 104,500.00
Upah :
0.015 Oh Pekerja @ Rp. 100,000.00 1,500.00
0.150 Oh Tukang Kayu @ Rp. 125,000.00 18,750.00
0.015 Oh Kepala Tukang Kayu @ Rp. - -
0.00075 Oh Mandor @ Rp. 150,000.00 112.50
104,500.00 20,362.50
Jumlah 124,862.50

SNI. 00-0000-2002 PEKERJAAN PENUTUP LANTAI DAN DINDING


144 1,00 M2 Lantai Keramik 30 x 30 cm
Bahan :
1.060 M2 Keramik Polos @ Rp. 90,100.00 95,506.00
10.00 Kg Semen ( Pc ) @ Rp. 1,550.00 15,500.00
0.045 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 12,858.35
1.500 Kg Semen Warna @ Rp. 3,000.00 4,500.00
Upah :
0.700 Oh Pekerja @ Rp. 100,000.00 70,000.00
0.350 Oh Tukang Batu @ Rp. 125,000.00 43,750.00
0.035 Oh Kepala Tukang Batu @ Rp. - -
0.030 Oh Mandor @ Rp. 150,000.00 4,500.00
128,364.35 118,250.00
Jumlah 246,614.35
1,00 M2 Lantai Keramik Motif 40 x 40 cm
1.0000 m2 Keramik motip 40/40 @ Rp. 116,000.00 116000
4.6800 kg PC @ Rp. 1,550.00 7254
0.0090 m3 Pasir pasang @ Rp. 285,741.00 2571.669
1.0000 kg Semen putih @ Rp. 97,700.00 97700
0.5000 org Tukang batu @ Rp. 125,000.00 62,500.00
0.0500 org Kep. Tk. Batu @ Rp. - -
0.2500 org Pekerja @ Rp. 100,000.00 25,000.00
0.0125 org Mandor @ Rp. 150,000.00 1,875.00
223525.669 89,375.00
Jumlah 312,900.67

145 1,00 M2 Lantai Keramik 20 x 20 cm


Bahan :
1.060 M2 Keramik @ Rp. 83,200.00 88,192.00
10.40 Kg Semen ( Pc ) @ Rp. 1,550.00 16,120.00
0.045 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 12,858.35
1.620 Kg Semen Warna @ Rp. 3,000.00 4,860.00
Upah :
0.700 Oh Pekerja @ Rp. 100,000.00 70,000.00
0.350 Oh Tukang Batu @ Rp. 125,000.00 43,750.00
0.035 Oh Kepala Tukang Batu @ Rp. - -
0.035 Oh Mandor @ Rp. 150,000.00 5,250.00
122,030.35 119,000.00
Jumlah 241,030.35

146 1,00 M2 Dinding Keramik 20 x 20 cm


Bahan :
1.060 M2 Keramik @ Rp. 83,200.00 88,192.00
9.30 Kg Semen ( Pc ) @ Rp. 1,550.00 14,415.00
0.018 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 5,143.34
1.940 Kg Semen Warna @ Rp. 3,000.00 5,820.00
Upah :
0.600 Oh Pekerja @ Rp. 100,000.00 60,000.00
0.450 Oh Tukang Batu @ Rp. 125,000.00 56,250.00
0.045 Oh Kepala Tukang Batu @ Rp. - -
0.045 Oh Mandor @ Rp. 150,000.00 6,750.00
113,570.34 123,000.00
Jumlah 236,570.34

147 1,00 M2 Dinding Keramik 20 x 25 cm


Bahan :
1.060 M2 Keramik @ Rp. 89,000.00 94,340.00
9.30 Kg Semen ( Pc ) @ Rp. 1,550.00 14,415.00
0.018 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 5,143.34
1.940 Kg Semen Warna @ Rp. 3,000.00 5,820.00
Upah :
0.600 Oh Pekerja @ Rp. 100,000.00 60,000.00
0.450 Oh Tukang Batu @ Rp. 125,000.00 56,250.00
0.045 Oh Kepala Tukang Batu @ Rp. - -
0.045 Oh Mandor @ Rp. 150,000.00 6,750.00
119,718.34 123,000.00
Jumlah 242,718.34

148 1,00 M' Plint Keramik 10 x 20 cm


Bahan :
1.060 M2 Plint Keramik @ Rp. 70,600.00 74,836.00
1.14 Kg Semen ( Pc ) @ Rp. 1,550.00 1,767.00
0.003 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 857.22
0.025 Kg Semen Warna @ Rp. 3,000.00 75.00
Upah :
0.090 Oh Pekerja @ Rp. 100,000.00 9,000.00
0.090 Oh Tukang Batu @ Rp. 125,000.00 11,250.00
0.009 Oh Kepala Tukang Batu @ Rp. - -
0.005 Oh Mandor @ Rp. 150,000.00 750.00
77,535.22 21,000.00
Jumlah 98,535.22

149 1,00 M2 Lantai Marmer


Bahan :
1.060 M2 Marmer @ Rp. 613,250.00 650,045.00
8.190 Kg Semen ( Pc ) @ Rp. 1,550.00 12,694.50
0.045 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 12,858.35
0.650 Kg Semen Warna @ Rp. 3,000.00 1,950.00
Upah :
0.700 Oh Pekerja @ Rp. 100,000.00 70,000.00
0.350 Oh Tukang Batu @ Rp. 125,000.00 43,750.00
0.035 Oh Kepala Tukang Batu @ Rp. - -
0.035 Oh Mandor @ Rp. 150,000.00 5,250.00
677,547.85 119,000.00
Jumlah 796,547.85

150 1,00 M2 Dinding Batu Tempel


Bahan :
1.100 M2 Batu Tempel Hitam @ Rp. 172,500.00 189,750.00
11.75 Kg Semen ( Pc ) @ Rp. 1,550.00 18,212.50
0.035 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 10,000.94
Upah :
0.700 Oh Pekerja @ Rp. 100,000.00 70,000.00
0.350 Oh Tukang Batu @ Rp. 125,000.00 43,750.00
0.035 Oh Kepala Tukang Batu @ Rp. - -
0.035 Oh Mandor @ Rp. 150,000.00 5,250.00
217,963.44 119,000.00
Jumlah 336,963.44

151 1,00 M2 Pasang Paving Stone t = 8 Cm


Bahan :
1.000 M2 Paving Stone t = 8 Cm @ Rp. 98,900.00 98,900.00
0.005 M3 Pasir Hitam Jawa ( Sawur ) @ Rp. 285,741.00 1,428.71
0.100 M3 Urugan Pasir ( Lokal ) @ Rp. 257,142.00 25,714.20
Upah :
0.010 Oh Pekerja @ Rp. 100,000.00 1,000.00
0.160 Oh Tukang Batu @ Rp. 125,000.00 20,000.00
0.050 Oh Kepala Tukang Batu @ Rp. - -
0.025 Oh Mandor @ Rp. 150,000.00 3,750.00
126,042.91 24,750.00
Jumlah 150,792.91

152 1,00 M2 Pasang Paving Stone t = 6 Cm


Bahan :
1.000 M2 Paving Stone t = 6 Cm @ Rp. 54,000.00 54,000.00
0.005 M3 Pasir Hitam Jawa ( Sawur ) @ Rp. 285,741.00 1,428.71
0.100 M3 Urugan Pasir ( Lokal ) @ Rp. 257,142.00 25,714.20
Upah : -
0.010 Oh Pekerja @ Rp. 100,000.00 1,000.00
0.160 Oh Tukang Batu @ Rp. 125,000.00 20,000.00
0.050 Oh Kepala Tukang Batu @ Rp. - -
0.025 Oh Mandor @ Rp. 150,000.00 3,750.00
81,142.91 24,750.00
Jumlah 105,892.91

153 1,00 M' Pasang Kanstein


Bahan :
2.000 Bh Kanstein @ Rp. 40,200.00 80,400.00
0.150 Kg Semen ( Pc ) @ Rp. 1,550.00 232.50
0.001 M3 Pasir Pasang ( Jawa ) @ Rp. 285,741.00 285.74
Upah :
0.050 Oh Pekerja @ Rp. 100,000.00 5,000.00
0.100 Oh Tukang Batu @ Rp. 125,000.00 12,500.00
0.050 Oh Kepala Tukang Batu @ Rp. - -
0.025 Oh Mandor @ Rp. 150,000.00 3,750.00
80,918.24 21,250.00
Jumlah 102,168.24
SNI. 00-0000-2002 PEKERJAAN PENGECATAN
154 1,00 M2 Pekerjaan Plituran
Bahan :
0.150 Ltr Plitur @ Rp. 61,325.00 9,198.75
2.000 Bh Kertas Gosok @ Rp. 8,580.00 17,160.00
0.372 Ltr Plitur Jadi @ Rp. 79,695.00 29,646.54
Upah :
0.250 Oh Pekerja @ Rp. 100,000.00 25,000.00
0.125 Oh Tukang Plitur @ Rp. 125,000.00 15,625.00
0.013 Oh Kepala Tukang Cat @ Rp. - -
56,005.29 40,625.00
Jumlah 96,630.29
155 1,00 M2 Pekerjaan Cat Kayu ( Ulang )
Bahan :
0.075 Kg Plamir (Kayu) @ Rp. 24,530.00 1,839.75
0.170 Kg Cat Kilap Emco @ Rp. 63,800.00 10,846.00
0.170 Kg Cat Dasar @ Rp. 55,165.00 9,378.05
Upah :
0.070 Oh Pekerja @ Rp. 100,000.00 7,000.00
0.075 Oh Tukang Cat @ Rp. 125,000.00 9,375.00
0.0075 Oh Kepala Tukang Cat @ Rp. - -
0.0025 Oh Mandor @ Rp. 150,000.00 375.00
22,063.80 16,750.00
Jumlah 38,813.80
156 1,00 M2 Pekerjaan Cat Kayu 2 Lapis Cat Penutup ( Baru )
Bahan :
0.170 Kg Cat Dasar @ Rp. 55,165.00 9,378.05
0.260 Kg Cat Kilap Emco @ Rp. 63,800.00 16,588.00
0.150 Kg Plamir (Kayu) @ Rp. 24,530.00 3,679.50
0.200 Kg Cat meni @ Rp. 30,635.00 6,127.00
Upah :
0.070 Oh Pekerja @ Rp. 100,000.00 7,000.00
0.009 Oh Tukang Cat @ Rp. 125,000.00 1,125.00
0.006 Oh Kepala Tukang Cat @ Rp. - -
0.0025 Oh Mandor @ Rp. 150,000.00 375.00
35,772.55 8,500.00
Jumlah 44,272.55
157 1,00 M2 Pekerjaan Cat Dinding dan Plafond 2 Lapis Penutup ( Baru )
Bahan :
0.100 Kg Plamur @ Rp. 21,450.00 2,145.00
0.260 Kg Cat Decolith @ Rp. 17,171.00 4,464.46
0.100 Kg Cat Dasar @ Rp. 18,370.00 1,837.00
0.500 Lbr Kertas Gosok @ Rp. 8,580.00 4,290.00
Upah :
0.020 Oh Pekerja @ Rp. 100,000.00 2,000.00
0.063 Oh Tukang Cat @ Rp. 125,000.00 7,875.00
0.006 Oh Kepala Tukang Cat @ Rp. - -
0.0025 Oh Mandor @ Rp. 150,000.00 375.00
12,736.46 10,250.00
Jumlah 22,986.46
158 1,00 M2 Pekerjaan Cat Dinding dan Plafond ( Lama )
Bahan :
0.180 Kg Cat Decolith @ Rp. 17,171.00 3,090.78
0.120 Kg Cat Dasar @ Rp. 18,370.00 2,204.40
Upah :
0.028 Oh Pekerja @ Rp. 100,000.00 2,800.00
0.042 Oh Tukang Cat @ Rp. 125,000.00 5,250.00
0.0042 Oh Kepala Tukang Cat @ Rp. - -
0.0025 Oh Mandor @ Rp. 150,000.00 375.00
5,295.18 8,425.00
Jumlah 13,720.18
W-1
159 1,00 M3 Urugan Pudel Dibawah Alas Jalan
Bahan :
1.200 M3 Pasir Pedel Putih @ Rp. 57,142.00 68,570.40
Upah :
0.375 Oh Pekerja @ Rp. 100,000.00 37,500.00
0.0199 Oh Mandor @ Rp. 150,000.00 2,985.00
68,570.40 40,485.00
Jumlah 109,055.40
W-2
160 1,00 M2 Lapis Dasar / Telford
Bahan :
0.160 M3 Batu Pecah 10/15 @ Rp. 225,100.00 36,016.00
0.040 M3 Batu Pecah 5/7 @ Rp. 238,300.00 9,532.00
0.050 M3 Pudel Kuning @ Rp. 115,000.00 5,750.00
Upah :
0.375 Oh Pekerja @ Rp. 100,000.00 37,500.00
0.0190 Oh Mandor @ Rp. 150,000.00 2,850.00
Alat :
0.000133 Bln Biaya Mesin Gilas @ Rp. 27,291,500.00 3,629.77
51,298.00 43,979.77
Jumlah 95,277.77

W-3
161 1,00 M2 Lapis Macadam
Bahan :
6.000 M3 Batu Pecah 5/7 @ Rp. 238,300.00 1,429,800.00
2.000 M3 Batu Pecah 2/3 @ Rp. 833,500.00 1,667,000.00
2.000 M3 Pasir Urug (Lokal) @ Rp. 78,570.80 157,141.60
Upah :
7.500 Oh Pekerja @ Rp. 100,000.00 750,000.00
0.3750 Oh Mandor @ Rp. 150,000.00 56,250.00
Alat :
0.026667 Bln Biaya Mesin Gilas @ Rp. 27,291,500.00 727,782.43
3,253,941.60 1,534,032.43
Untuk 100 M2 Pekerjaan Macadam 4,787,974.03
Untuk 1 M2 Pekerjaan Macadam 1/100 x 4,787,974.03 47,879.74
Jumlah 47,879.74

W-4
162 Biaya Gilas 1 Bulan
Bahan :
1,000.000 Ltr Solar @ Rp. 11,715.00 11,715,000.00
20.000 Ltr Olie @ Rp. 38,500.00 770,000.00
5.000 Kg Gemuk / Stempet @ Rp. 36,300.00 181,500.00
Upah :
24.000 Oh Masinis @ Rp. - -
24.000 Oh Kenek @ Rp. - -
24.000 Oh Penjaga / Waker @ Rp. - -
120.000 Oh Pekerja @ Rp. 100,000.00 12,000,000.00
Alat :
Biaya Pemeliharaan Mesin Gilas @ Rp. 2,625,000.00
12,666,500.00 14,625,000.00
Jumlah 27,291,500.00

W-5
163 1,00 M2 Latasir ( Sand Sheed)
Bahan :
250.000 Kg Aspal @ Rp. 11,055.00 2,763,750.00
1.200 M3 Kerikil Halus + Pasir @ Rp. 310,500.00 372,600.00
0.900 M3 Kayu Bakar @ Rp. 115,000.00 103,500.00
1.840 Set Alat Bantu @ Rp. 192,500.00 354,200.00
Upah :
0.500 Oh Tukang aspal @ Rp. 125,000.00 62,500.00
10.000 Oh Pekerja @ Rp. 100,000.00 1,000,000.00
0.500 Oh Mandor @ Rp. 150,000.00 75,000.00
Alat :
0.000133 Bln Biaya Mesin Gilas @ Rp. 27,291,500.00 3,629.77
3,594,050.00 1,141,129.77
Untuk 100 M2 Pekerjaan Latasir (Sand Sheed) 4,735,179.77
Untuk 1 M2 Pekerjaan Latasir (Sand Sheed) 1/100 x 4,735,179.77 47,351.80
Jumlah 47,351.80

DPUTL
164 1,00 M2 Lapis Penetrasi Tebal 5 cm
Bahan :
450.000 Kg Aspal @ Rp. 11,055.00 4,974,750.00
2.100 M3 Batu Pecah 2/3 @ Rp. 833,500.00 1,750,350.00
5.250 M3 Batu Pecah 3/5 @ Rp. 283,000.00 1,485,750.00
1.200 M3 Abu Batu @ Rp. 310,500.00 372,600.00
0.600 M3 Kayu Bakar @ Rp. 115,000.00 69,000.00
Upah :
2.500 Oh Tukang aspal @ Rp. 125,000.00 312,500.00
6.000 Oh Pekerja @ Rp. 100,000.00 600,000.00
0.300 Oh Mandor @ Rp. 150,000.00 45,000.00
Alat :
0.026667 Bln Biaya Mesin Gilas @ Rp. 27,291,500.00 727,782.43
8,652,450.00 1,685,282.43
Untuk 100 M2 Pekerjaan Lapis Penetrasi 10,337,732.43
Untuk 1 M2 Pekerjaan Lapis Penetrasi 1/100 x 10,337,732.43 103,377.32
Jumlah 103,377.32

DPUTL
165 1,00 M2 Mengaspal Buras
Bahan :
100.000 Kg Aspal @ Rp. 11,055.00 1,105,500.00
1.000 M3 Abu Batu @ Rp. 310,500.00 310,500.00
0.170 M3 Kayu Bakar @ Rp. 115,000.00 19,550.00
Upah :
0.200 Oh Tukang aspal @ Rp. 125,000.00 25,000.00
6.000 Oh Pekerja @ Rp. 100,000.00 600,000.00
0.300 Oh Mandor @ Rp. 150,000.00 45,000.00
Alat :
0.026667 Bln Biaya Mesin Gilas @ Rp. 27,291,500.00 727,782.43
1,435,550.00 1,397,782.43
Untuk 100 M2 Pekerjaan Buras 2,833,332.43
Untuk 1 M2 Pekerjaan Buras 1/100 x 2,833,332.43 28,333.32
Jumlah 28,333.32

DPUTL
166 1,00 M2 Mengaspal Burda
Bahan :
400.000 Kg Aspal @ Rp. 11,055.00 4,422,000.00
4.000 M3 Batu Pecah 2/3 @ Rp. 833,500.00 3,334,000.00
0.900 M3 Abu Batu @ Rp. 310,500.00 279,450.00
0.600 M3 Kayu Bakar @ Rp. 115,000.00 69,000.00
Upah :
2.000 Oh Tukang aspal @ Rp. 125,000.00 250,000.00
5.000 Oh Pekerja @ Rp. 100,000.00 500,000.00
0.200 Oh Mandor @ Rp. 150,000.00 30,000.00
Alat :
0.026667 Bln Biaya Mesin Gilas @ Rp. 27,291,500.00 727,782.43
8,104,450.00 1,507,782.43
Untuk 100 M2 Pekerjaan Burda 9,612,232.43
Untuk 1 M2 Pekerjaan Burda 1/100 x 9,612,232.43 96,122.32
Jumlah 96,122.32

A1 + G2
167 1,00 M' Pasangan Batu Tepi
Bahan :
0.036 M3 Batu Pecah 10/15 @ Rp. 225,100.00 8,103.60
Upah :
2.250 Oh Pekerja @ Rp. 100,000.00 225,000.00
0.100 Oh Mandor @ Rp. 150,000.00 15,000.00
8,103.60 240,000.00
248,103.60
1/30 dari upah 1/30 x 240,000.00 8,000.00
Untuk memasang 1 m' Batu Tepi 8,103.60 + 8,000.00 16,103.60

A
168 1,00 M2 Pembersihan semak / Damija
Upah :
0.050 Oh Pekerja @ Rp. 100,000.00 5,000.00
0.002 Oh Mandor @ Rp. 150,000.00 300.00
5,300.00

GK = Uk. 0,40 x 0,60


169 1,00 M' Gorong-Gorong Kotak Pasangan Batu (Uk. 0,40 x 0,60 m)
Pek. 1,00 m' Gorong-Gorong Kotak Pasangan Batu (Uk. 0,40 x 0,60 m)
1.190 M3 Pek. Galian Tanah (Per m') @ Rp. 78,750.00 93,712.50
0.220 M3 Pek. Urugan Tanah Lokal (Per m') @ Rp. 130,500.00 28,710.00
0.595 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Per m') @ Rp. 887,235.32 527,905.02
0.135 M3 Pek. Plat Beton Bertulang 1Pc : 2Ps : 3Kr (110 Kg) (Per m') @ Rp. 5,599,923.89 755,989.73
0.045 M3 Pek. Bantalan Beton Bertulang 1Pc : 2Ps : 3Kr (110 Kg) (Per m') @ Rp. 3,991,735.81 179,628.11
1.400 M2 Pek. Plesteran 1Pc : 3Ps (Per m') @ Rp. 69,624.84 97,474.78
1,683,420.13
Pek. Book Gorong-Gorong Kotak (Uk. 0,90 x 0,50 x 0,3m)
0.770 M2 Pek. Plesteran 1Pc : 3Ps (GK Samping) @ Rp. 69,624.84 53,611.13
0.270 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Book) @ Rp. 887,235.32 239,553.54
2.940 M2 Pek. Plesteran 1Pc : 3Ps (Book) @ Rp. 69,624.84 204,697.04
497,861.70
Untuk Pekerjaan 1,00 m' Gorong-Gorong Kotak Pasangan Batu (Uk. 0,40 x 0,60 m) 1,683,420.13
Untuk Pekerjaan Book Gorong-Gorong Kotak (Uk. 0,90 x 0,50 x 0,3m) 497,861.70

GK = Uk. 0,60 x 0,80


170 1,00 M' Gorong-Gorong Kotak Pasangan Batu (Uk. 0,60 x 0,80 m)
Pek. 1,00 m' Gorong-Gorong Kotak Pasangan Batu (Uk. 0,60 x 0,80 m)
1.900 M3 Pek. Galian Tanah (Per m') @ Rp. 78,750.00 149,625.00
0.300 M3 Pek. Urugan Tanah Lokal (Per m') @ Rp. 130,500.00 39,150.00
0.955 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Per m') @ Rp. 887,235.32 847,309.73
0.165 M3 Pek. Plat Beton Bertulang 1Pc : 2Ps : 3Kr (110 Kg) (Per m') @ Rp. 5,599,923.89 923,987.44
0.045 M3 Pek. Bantalan Beton Bertulang 1Pc : 2Ps : 3Kr (110 Kg) (Per m') @ Rp. 3,991,735.81 179,628.11
2.000 M2 Pek. Plesteran 1Pc : 3Ps (Per m') @ Rp. 69,624.84 139,249.69
2,278,949.97
Pek. Book Gorong-Gorong Kotak (Uk. 1,10 x 0,50 x 0,3m)
1.200 M2 Pek. Plesteran 1Pc : 3Ps (GK Samping) @ Rp. 69,624.84 83,549.81
0.330 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Book) @ Rp. 887,235.32 292,787.66
3.460 M2 Pek. Plesteran 1Pc : 3Ps (Book) @ Rp. 69,624.84 240,901.96
617,239.42
Untuk Pekerjaan 1,00 m' Gorong-Gorong Kotak Pasangan Batu (Uk. 0,60 x 0,80 m) 2,278,949.97
Untuk Pekerjaan Book Gorong-Gorong Kotak (Uk. 1,10 x 0,50 x 0,3m) 617,239.42

GK 127 = Uk. 0,80 x 1,00


171 1,00 M' Gorong-Gorong Kotak K. 127 (Uk. 0,80 x 1,00 m)
Pek. 1,00 m' Gorong-Gorong Kotak K.127 (Uk. 0,80 x 1,00 m)
2.530 M3 Pek. Galian Tanah (Per m') @ Rp. 78,750.00 199,237.50
0.400 M3 Pek. Urugan Tanah Lokal (Per m') @ Rp. 130,500.00 52,200.00
0.755 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Per m') @ Rp. 887,235.32 669,862.67
0.260 M3 Pek. Plat Beton Bertulang 1Pc : 2Ps : 3Kr (130 Kg) (Per m') @ Rp. 6,075,287.23 1,579,574.68
0.045 M3 Pek. Bantalan Beton Bertulang 1Pc : 2Ps : 3Kr (110 Kg) (Per m') @ Rp. 3,991,735.81 179,628.11
0.330 M3 Pek. Beton Rabat 1Pc : 3Ps : 5Kr (Per m') @ Rp. 1,419,866.28 468,555.87
2.600 M2 Pek. Plesteran 1Pc : 3Ps (Per m') @ Rp. 69,624.84 181,024.59
3,330,083.42
Pek. Book Gorong-Gorong Kotak (Uk. 1,30 x 0,60 x 0,3m)
1.600 M2 Pek. Plesteran 1Pc : 3Ps (GK Samping) @ Rp. 69,624.84 111,399.75
0.468 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Book) @ Rp. 887,235.32 415,226.13
4.100 M2 Pek. Plesteran 1Pc : 3Ps (Book) @ Rp. 69,624.84 285,461.86
812,087.73
Untuk Pekerjaan 1,00 m' Gorong-Gorong Kotak K.127 (Uk. 0,80 x 1,00 m) 3,330,083.42
Untuk Pekerjaan Book Gorong-Gorong Kotak (Uk. 1,30 x 0,60 x 0,3m) 812,087.73

GK 128 = Uk. 1,20 x 1,50


172 1,00 M' Gorong-Gorong Kotak K. 128 (Uk. 1,20 x 1,50 m)
Pek. 1,00 m' Gorong-Gorong Kotak K.128 (Uk. 1,20 x 1,50 m)
5.115 M3 Pek. Galian Tanah (Per m') @ Rp. 78,750.00 402,806.25
0.700 M3 Pek. Urugan Tanah Lokal (Per m') @ Rp. 130,500.00 91,350.00
1.760 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Per m') @ Rp. 887,235.32 1,561,534.16
0.380 M3 Pek. Beton Bertulang 1Pc : 2Ps : 3Kr (130 Kg) (Per m') @ Rp. 6,075,287.23 2,308,609.15
0.060 M3 Pek. Bantalan Beton Bertulang 1Pc : 2Ps : 3Kr (110 Kg) (Per m') @ Rp. 3,991,735.81 239,504.15
0.495 M3 Pek. Beton Rabat 1Pc : 3Ps : 5Kr (Per m') @ Rp. 1,419,866.28 702,833.81
3.900 M2 Pek. Plesteran 1Pc : 3Ps (Per m') @ Rp. 69,624.84 271,536.89
5,578,174.40
Pek. Book Gorong-Gorong Kotak (Uk. 1,90 x 0,60 x 0,3m)
3.640 M2 Pek. Plesteran 1Pc : 3Ps (GK Samping) @ Rp. 69,624.84 253,434.43
0.684 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Book) @ Rp. 887,235.32 606,868.96
5.660 M2 Pek. Plesteran 1Pc : 3Ps (Book) @ Rp. 69,624.84 394,076.61
1,254,380.00
Untuk Pekerjaan 1,00 m' Gorong-Gorong Kotak K.128 (Uk. 1,20 x 1,50 m) 5,578,174.40
Untuk Pekerjaan Book Gorong-Gorong Kotak (Uk. 1,90 x 0,60 x 0,3m) 1,254,380.00

GK 128-A = Uk. 2,50 x 1,50


173 1,00 M' Gorong-Gorong Kotak K. 128-A (Uk. 2,50 x 1,50 m)
Pek. 1,00 m' Gorong-Gorong Kotak K. 128-A (Uk. 2,50 x 1,50 m)
8.040 M3 Pek. Galian Tanah (Per m') @ Rp. 78,750.00 633,150.00
0.473 M3 Pek. Urugan Tanah Lokal (Per m') @ Rp. 130,500.00 61,661.25
3.098 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Per m') @ Rp. 887,235.32 2,748,211.40
0.360 M3 Pek. Beton Bertulang 1Pc : 2Ps : 3Kr (130 Kg) (Per m') @ Rp. 6,075,287.23 2,187,103.40
0.060 M3 Pek. Bantalan Beton Bertulang 1Pc : 2Ps : 3Kr (110 Kg) (Per m') @ Rp. 3,991,735.81 239,504.15
8.000 M2 Pek. Plesteran 1Pc : 3Ps (Per m') @ Rp. 69,624.84 556,998.74
6,426,628.95
Pek. Book Gorong-Gorong Kotak (Uk. 2,10 x 0,60 x 0,3m)
5.355 M2 Pek. Plesteran 1Pc : 3Ps (GK Samping) @ Rp. 69,624.84 372,841.03
0.756 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Book) @ Rp. 887,235.32 670,749.90
6.180 M2 Pek. Plesteran 1Pc : 3Ps (Book) @ Rp. 69,624.84 430,281.53
1,473,872.47
Untuk Pekerjaan 1,00 m' Gorong-Gorong Kotak K. 128-A (Uk. 2,50 x 1,50 m) 6,426,628.95
Untuk Pekerjaan Book Gorong-Gorong Kotak (Uk. 2,10 x 0,60 x 0,3m) 1,473,872.47

Buis Ø 50 cm
174 1,00 M' Buis Ø 50 cm
Pekerjaan 1,00 M' Buis Ø 50 cm
1.100 M3 Pek. Galian Tanah (Per m') @ Rp. 78,750.00 86,625.00
0.630 M3 Pek. Pasir Urug (Per m') @ Rp. 340,070.40 214,244.35
1.000 Bh Pengad. Buis Beton Ø 50 cm (Per m') @ Rp. 88,880.00 88,880.00
0.200 M3 Pek. Urugan Pudel Putih (Per m') @ Rp. 103,070.40 20,614.08
410,363.43
Pek. Pondasi Gorong-Gorong Buis Beton
0.542 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Pondasi) @ Rp. 887,235.32 481,103.35
0.211 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Cincin) @ Rp. 887,235.32 187,317.56
668,420.91

Pek. Book Gorong-Gorong Kotak (Uk. 1,00 x 0,60 x 0,3m)


1.408 M2 Pek. Plesteran 1Pc : 3Ps (GK Samping) @ Rp. 69,624.84 97,996.97
0.360 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Book) @ Rp. 887,235.32 319,404.72
3.720 M2 Pek. Plesteran 1Pc : 3Ps (Book) @ Rp. 69,624.84 259,004.42
676,406.10
Untuk Pekerjaan 1,00 m' Buis Ø 50 cm 410,363.43
Pek. Pasangan Batu Belah 1Pc : 4Ps (Pondasi) 481,103.35
Pek. Cincin Gorong-Gorong Buis Beton (per cincin) 187,317.56
Pek. Book Gorong-Gorong Kotak (Uk. 1,00 x 0,60 x 0,3m) 676,406.10

Buis Ø 40 cm
175 1,00 M' Buis Ø 40 cm
Pekerjaan 1,00 M' Buis Ø 40 cm
1.000 M3 Pek. Galian Tanah (Per m') @ Rp. 78,750.00 78,750.00
0.560 M3 Pek. Pasir Urug (Per m') @ Rp. 340,070.40 190,439.42
1.000 Bh Pengad. Buis Beton Ø 40 cm (Per m') @ Rp. 85,855.00 85,855.00
0.200 M3 Pek. Urugan Pudel Putih (Per m') @ Rp. 103,070.40 20,614.08
375,658.50
Pek. Pondasi Gorong-Gorong Buis Beton
0.525 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Pondasi) @ Rp. 887,235.32 465,479.14
0.202 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Cincin) @ Rp. 887,235.32 179,505.45
644,984.59
Pek. Book Gorong-Gorong Kotak (Uk. 1,00 x 0,60 x 0,3m)
1.349 M2 Pek. Plesteran 1Pc : 3Ps (GK Samping) @ Rp. 69,624.84 93,909.99
0.360 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Book) @ Rp. 887,235.32 319,404.72
3.720 M2 Pek. Plesteran 1Pc : 3Ps (Book) @ Rp. 69,624.84 259,004.42
672,319.12
Untuk Pekerjaan 1,00 m' Buis Ø 40 cm 375,658.50
Pek. Pasangan Batu Belah 1Pc : 4Ps (Pondasi) 465,479.14
Pek. Cincin Gorong-Gorong Buis Beton (per cincin) 179,505.45
Pek. Book Gorong-Gorong Kotak (Uk. 1,00 x 0,60 x 0,3m) 672,319.12

Buis Ø 30 cm
176 1,00 M' Buis Ø 30 cm
Pekerjaan 1,00 M' Buis Ø 30 cm
0.900 M3 Pek. Galian Tanah (Per m') @ Rp. 78,750.00 70,875.00
0.490 M3 Pek. Pasir Urug (Per m') @ Rp. 340,070.40 166,634.50
1.000 Bh Pengad. Buis Beton Ø 30 cm (Per m') @ Rp. 79,695.00 79,695.00
0.200 M3 Pek. Urugan Pudel Putih (Per m') @ Rp. 103,070.40 20,614.08
337,818.58
Pek. Pondasi Gorong-Gorong Buis Beton
0.498 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Pondasi) @ Rp. 887,235.32 441,497.17
0.189 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Cincin) @ Rp. 887,235.32 167,514.46
609,011.63

Pek. Book Gorong-Gorong Kotak (Uk. 1,00 x 0,60 x 0,3m)


1.259 M2 Pek. Plesteran 1Pc : 3Ps (GK Samping) @ Rp. 69,624.84 87,636.79
0.360 M3 Pek. Pasangan Batu Belah 1Pc : 4Ps (Book) @ Rp. 887,235.32 319,404.72
3.720 M2 Pek. Plesteran 1Pc : 3Ps (Book) @ Rp. 69,624.84 259,004.42
666,045.92
Untuk Pekerjaan 1,00 m' Buis Ø 30 cm 337,818.58
Pek. Pasangan Batu Belah 1Pc : 4Ps (Pondasi) 441,497.17
Pek. Cincin Gorong-Gorong Buis Beton (per cincin) 167,514.46
Pek.Book Gorong-Gorong Kotak (Uk. 1,00 x 0,60 x 0,3m) 666,045.92

PEK. SALURAN BIASA (LIGHT DUTY)


177 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 300/300 - 600 + Pasang
Bahan :
1.000 M' Material U-Ditch 300/300-600 @ Rp. 386,100.00 386,100.00
Upah :
1.000 M' Pemasangan Material U-Ditch 300/300-600 @ Rp. 154,440.00 154,440.00
386,100.00 154,440.00
Jumlah 540,540.00

178 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 400/400 - 1000 + Pasang
Bahan :
1.000 M' Material U-Ditch 400/400-1000 @ Rp. 583,700.00 583,700.00
Upah :
1.000 M' Pemasangan Material U-Ditch 400/400-1000 @ Rp. 233,480.00 233,480.00
583,700.00 233,480.00
Jumlah 817,180.00

179 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 400/500 - 1000 + Pasang
Bahan :
1.000 M' Material U-Ditch 400/500-1000 @ Rp. 657,800.00 657,800.00
Upah :
1.000 M' Pemasangan Material U-Ditch 400/500-1000 @ Rp. 263,120.00 263,120.00
657,800.00 263,120.00
Jumlah 920,920.00

180 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 500/500 - 2400 + Pasang
Bahan :
1.000 M' Material U-Ditch 500/500-2400 @ Rp. 1,085,500.00 1,085,500.00
Upah :
1.000 M' Pemasangan Material U-Ditch 500/500-2400 @ Rp. 434,200.00 434,200.00
1,085,500.00 434,200.00
Jumlah 1,519,700.00

181 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 600/500 - 1000 + Pasang
Bahan :
1.000 M' Material U-Ditch 600/500-1000 @ Rp. 815,100.00 815,100.00
Upah :
1.000 M' Pemasangan Material U-Ditch 600/500-1000 @ Rp. 326,040.00 326,040.00
815,100.00 326,040.00
Jumlah 1,141,140.00

182 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 600/600 - 2400 + Pasang
Bahan :
1.000 M' Material U-Ditch 600/600-2400 @ Rp. 1,357,200.00 1,357,200.00
Upah :
1.000 M' Pemasangan Material U-Ditch 600/600-2400 @ Rp. 542,880.00 542,880.00
1,357,200.00 542,880.00
Jumlah 1,900,080.00

183 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 800/600 - 1000 + Pasang
Bahan :
1.000 M' Material U-Ditch 800/600-1000 @ Rp. 1,107,600.00 1,107,600.00
Upah :
1.000 M' Pemasangan Material U-Ditch 800/600-1000 @ Rp. 443,040.00 443,040.00
1,107,600.00 443,040.00
Jumlah 1,550,640.00

184 1,00 M' Pekerjaan Cover = 400 x 600 x 60 + Pasang


Bahan :
1.000 M' Material Cover 400 x 600 x 60 @ Rp. 171,600.00 171,600.00
Upah :
1.000 M' Pemasangan Material Cover 400 x 600 x 60 @ Rp. 68,640.00 68,640.00
171,600.00 68,640.00
Jumlah 240,240.00

185 1,00 M' Pekerjaan Cover = 500 x 1000 x 100 + Pasang


Bahan :
1.000 M' Material Cover 500 x 1000 x 100 @ Rp. 357,500.00 357,500.00
Upah :
1.000 M' Pemasangan Material Cover 500 x 1000 x 100 @ Rp. 143,000.00 143,000.00
357,500.00 143,000.00
Jumlah 500,500.00

186 1,00 M' Pekerjaan Cover = 680 x 2400 x 150 + Pasang


Bahan :
1.000 M' Material Cover 680 x 2400 x 150 @ Rp. 746,200.00 746,200.00
Upah :
1.000 M' Pemasangan Material Cover 680 x 2400 x 150 @ Rp. 298,480.00 298,480.00
746,200.00 298,480.00
Jumlah 1,044,680.00

187 1,00 M' Pekerjaan Cover = 750 x 1000 x 100 + Pasang


Bahan :
1.000 M' Material Cover 750 x 1000 x 100 @ Rp. 549,900.00 549,900.00
Upah :
1.000 M' Pemasangan Material Cover 750 x 1000 x 100 @ Rp. 219,960.00 219,960.00
549,900.00 219,960.00
Jumlah 769,860.00

188 1,00 M' Pekerjaan Cover = 800 x 2400 x 150 + Pasang


Bahan :
1.000 M' Material Cover 800 x 2400 x 150 @ Rp. 877,500.00 877,500.00
Upah :
1.000 M' Pemasangan Material Cover 800 x 2400 x 150 @ Rp. 351,000.00 351,000.00
877,500.00 351,000.00
Jumlah 1,228,500.00

189 1,00 M' Pekerjaan Cover = 950 x 1000 x 100 + Pasang


Bahan :
1.000 M' Material Cover 950 x 1000 x 100 @ Rp. 692,900.00 692,900.00
Upah :
1.000 M' Pemasangan Material Cover 950 x 1000 x 100 @ Rp. 277,160.00 277,160.00
692,900.00 277,160.00
Jumlah 970,060.00

PEK. SALURAN CROSS JALAN (HEAVY DUTY)


190 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 560/500 - 1000 + Pasang
Bahan :
1.000 M' Material U-Ditch 560/500-1000 @ Rp. 1,701,700.00 1,701,700.00
Upah :
1.000 M' Pemasangan Material U-Ditch 560/500-1000 @ Rp. 680,680.00 680,680.00
1,701,700.00 680,680.00
Jumlah 2,382,380.00

191 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 600/600 - 1000 + Pasang
Bahan :
1.000 M' Material U-Ditch 600/600-1000 @ Rp. 2,171,000.00 2,171,000.00
Upah :
1.000 M' Pemasangan Material U-Ditch 600/600-1000 @ Rp. 868,400.00 868,400.00
2,171,000.00 868,400.00
Jumlah 3,039,400.00

192 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 800/800 - 2400 + Pasang
Bahan :
1.000 M' Material U-Ditch 800/800-2400 @ Rp. 2,610,400.00 2,610,400.00
Upah :
1.000 M' Pemasangan Material U-Ditch 800/800-2400 @ Rp. 1,044,160.00 1,044,160.00
2,610,400.00 1,044,160.00
Jumlah 3,654,560.00

193 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 1000/1000 - 1200 + Pasang
Bahan :
1.000 M' Material U-Ditch 1000/1000-1200 @ Rp. 3,123,900.00 3,123,900.00
Upah :
1.000 M' Pemasangan Material U-Ditch 1000/1000-1200 @ Rp. 1,249,560.00 1,249,560.00
3,123,900.00 1,249,560.00
Jumlah 4,373,460.00

194 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 1500/1000 - 1200 + Pasang
Bahan :
1.000 M' Material U-Ditch 1500/1000-1200 @ Rp. 5,695,300.00 5,695,300.00
Upah :
1.000 M' Pemasangan Material U-Ditch 1500/1000-1200 @ Rp. 2,278,120.00 2,278,120.00
5,695,300.00 2,278,120.00
Jumlah 7,973,420.00

195 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 1500/1200 - 1200 + Pasang
Bahan :
1.000 M' Material U-Ditch 1500/1200-1200 @ Rp. 6,202,300.00 6,202,300.00
Upah :
1.000 M' Pemasangan Material U-Ditch 1500/1200-1200 @ Rp. 2,480,920.00 2,480,920.00
6,202,300.00 2,480,920.00
Jumlah 8,683,220.00

196 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 1500/1500 - 1200 + Pasang
Bahan :
1.000 M' Material U-Ditch 1500/1500-1200 @ Rp. 6,935,500.00 6,935,500.00
Upah :
1.000 M' Pemasangan Material U-Ditch 1500/1500-1200 @ Rp. 2,774,200.00 2,774,200.00
6,935,500.00 2,774,200.00
Jumlah 9,709,700.00

197 1,00 M' Pekerjaan Cover = 810 x 1000 x 150 + Pasang


Bahan :
1.000 M' Material Cover 810 x 1000 x 150 @ Rp. 886,600.00 886,600.00
Upah :
1.000 M' Pemasangan Material Cover 810 x 1000 x 150 @ Rp. 354,640.00 354,640.00
886,600.00 354,640.00
Jumlah 1,241,240.00

198 1,00 M' Pekerjaan Cover = 900 x 1000 x 150 + Pasang


Bahan :
1.000 M' Material Cover 900 x 1000 x 150 @ Rp. 986,700.00 986,700.00
Upah :
1.000 M' Pemasangan Material Cover 900 x 1000 x 150 @ Rp. 394,680.00 394,680.00
986,700.00 394,680.00
Jumlah 1,381,380.00

199 1,00 M' Pekerjaan Cover = 1080 x 2400 x 150 + Pasang


Bahan :
1.000 M' Material Cover 1080 x 2400 x 150 @ Rp. 1,183,000.00 1,183,000.00
Upah :
1.000 M' Pemasangan Material Cover 1080 x 2400 x 150 @ Rp. 473,200.00 473,200.00
1,183,000.00 473,200.00
Jumlah 1,656,200.00

200 1,00 M' Pekerjaan Cover = 1280 x 1200 x 150 + Pasang


Bahan :
1.000 M' Material Cover 1280 x 1200 x 150 @ Rp. 1,752,400.00 1,752,400.00
Upah :
1.000 M' Pemasangan Material Cover 1280 x 1200 x 150 @ Rp. 700,960.00 700,960.00
1,752,400.00 700,960.00
Jumlah 2,453,360.00

201 1,00 M' Pekerjaan Cover = 1900 x 1200 x 200 + Pasang


Bahan :
1.000 M' Material Cover 1900 x 1200 x 200 @ Rp. 2,772,900.00 2,772,900.00
Upah :
1.000 M' Pemasangan Material Cover 1900 x 1200 x 200 @ Rp. 1,109,160.00 1,109,160.00
2,772,900.00 1,109,160.00
Jumlah 3,882,060.00

193 1,00 M' Pekerjaan Saluran U-DITCH / U-GUTTER = 1000/800 - 1200 + Pasang menggunakan Alat
Bahan :
1.000 M' Material U-Ditch 1000/800-1200 @ Rp. 2,645,000.00 2,645,000.00
1.000 M' Material Cover 1280 x 1200 x 150 @ Rp. 1,380,000.00 1,380,000.00
Upah :
1.000 M' Pemasangan Material U-Ditch 1000/1000-1200 dan @ Rp. 2,635,417.00 2,635,417.00
Material Cover 1280 x 1200 x 150 4,025,000.00 2,635,417.00
Jumlah 6,660,417.00
REKAPITULASI DAFTAR ANALISA HARGA SATUAN TAHUN ANGGARAN 2013

NO KODE ANALISA JENIS PEKERJAAN HARGA SATUAN


1 2 3 4
1 SNI. 03-2835-2002 PEKERJAAN PERSIAPAN 1,00 M2 Pekerjaan Pembersihan Lapangan dan Perataan 17,500.00
2 SNI. 03-2835-2002 PEKERJAAN PERSIAPAN 1,00 M' Pengukuran dan Pemasangan Bowplank 145,756.50
3 SNI. 2835-2008 PEKERJAAN TANAH 1,00 M3 Pekerjaan Galian Tanah Biasa Sedalam 1 Meter 78,750.00
4 SNI. 2835-2008 PEKERJAAN TANAH 1,00 M3 Urugan Tanah Kembali 22,050.00
5 SNI. 2835-2008 PEKERJAAN TANAH 1,00 M3 Urugan Tanah Lokal 130,500.00
6 SNI. 2835-2008 PEKERJAAN TANAH 1,00 M3 Urugan Pasir 340,070.40
7 SNI. 2836-2008 PEKERJAAN PONDASI 1,00 M3 Pasangan Batu Gunung Campuran 1 Pc : 5 Ps 852,243.10
8 SNI. 2836-2008 PEKERJAAN PONDASI 1,00 M3 Pasangan Batu Kosong ( Anstamping ) 474,685.34
9 SNI. 00-0000-2002 PEKERJAAN BETON 1,00 M3 Pekerjaan Sloof Beton Bertulang (200 Kg Besi + Begesting) 6,440,930.56
10 SNI. 00-0000-2002 PEKERJAAN BETON 1,00 M3 Pekerjaan Pondasi Beton Bertulang (150 Kg Besi + Begesting) 5,209,045.56
11 SNI. 00-0000-2002 PEKERJAAN BETON 1,00 M3 Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K 100), slump (3-6) cm 1,327,079.03
12 SNI. 00-0000-2002 PEKERJAAN BETON 1,00 M3 Pekerjaan Beton Bertulang Camp. 1Pc : 2Ps : 3 Krl ( Kolom Praktis 11 x 11 CM) 7,738,404.68
13 SNI. 00-0000-2002 PEKERJAAN BETON 1,00 M3 Pekerjaan Kolom Beton Bertulang (250 Kg Besi + Begesting) 9,596,937.23
14 SNI. 00-0000-2002 PEKERJAAN BETON 1,00 M3 Pekerjaan Balok Beton Bertulang (200 Kg Besi + Begesting) 8,485,366.56
15 SNI. 00-0000-2002 PEKERJAAN BETON 1,00 M3 Pekerjaan Balok Beton Bertulang (160 Kg Besi + Begesting) 7,334,797.56
16 SNI. 00-0000-2002 PEKERJAAN BETON 1,00 M3 Pekerjaan Beton Bertulang Camp. 1Pc : 2Ps : 3 Krl ( Rink Balok 11 x 15 CM) 7,906,592.82
17 SNI. 00-0000-2002 PEKERJAAN BETON 1,00 M3 Pekerjaan Plat Beton Bertulang (130 Kg Besi + Begesting + Perancah) 6,075,287.23
18 SNI.DT 91-0008-2007 PEKERJAAN BETON 1,00 M3 Pekerjaan Beton Rabat Camp. 1Pc : 3Psr : 5Krl 1,419,866.28
19 SNI.DT 91-0008-2007 PEKERJAAN BETON 1,00 M3 Membongkar cetakan 400,000.00
20 SNI. 6897-2008 PEKERJAAN DINDING (PASANGAN) 1,00 M2 Pasangan Bata Merah (Tembok) Tebal 1/2 Bata Camp. 1 Pc : 2 Ps 154,980.66
21 SNI. 6897-2008 PEKERJAAN DINDING (PASANGAN) 1,00 M2 Pasangan Bata Merah (Tembok) Tebal 1/2 Bata Camp. 1 Pc : 5 Ps 142,612.35
22 SNI. 6897-2008 PEKERJAAN DINDING (PASANGAN) 1,00 M2 Pasangan Roolag 297,226.41
23 SNI. 00-0000-2002 PEKERJAAN PENUTUP LANTAI DAN DINDING 1,00 M2 Dinding Batu Tempel 336,963.44
24 SNI. 00-0000-2002 PEKERJAAN PENUTUP LANTAI DAN DINDING 1,00 M2 Pasang Paving Stone t = 8 Cm 150,792.91
25 SNI. 2837-2008 PEKERJAAN PLESTERAN 1,00 M2 Plesteran Tembok Camp. 1 Pc : 2 Ps Tebal 15 Mm 72,562.02
26 SNI. 2837-2008 PEKERJAAN PLESTERAN 1,00 M2 Plesteran Tembok Camp. 1 Pc : 4 Ps Tebal 15 Mm 67,529.78
27 SNI. 2837-2008 PEKERJAAN PLESTERAN 1,00 M2 Acian 39,037.50
28 SNI. 3434-2008 PEKERJAAN KAYU 1,00 M3 Pek. Kusen Pintu / Jendela Kayu Bangkirai 15,429,622.50
29 SNI. 3434-2008 PEKERJAAN KAYU 1,00 M2 Pek. Daun Pintu dan Jendela Panil Kayu Bangkirai 949,842.50
30 SNI. 3434-2008 PEKERJAAN KAYU 1,00 M2 Pekerjaan Pintu/Jendela Jalusi Kayu Bangkirai 1,225,842.50
31 SNI. 3434-2008 PEKERJAAN KAYU 1,00 M2 Pek. Daun Jendela Kaca Kayu Bangkirai 666,405.50
32 SNI. 00-0000-2002 PEKERJAAN KUNCI DAN KACA 1,00 M2 Pasang Kaca bening t = 5 mm 136,852.50
33 SNI. 00-0000-2002 PEKERJAAN KUNCI DAN KACA 1,00 M2 Pasang Kaca es t = 3 mm 124,862.50
34 SNI. 2839-2008 PEKERJAAN LANGIT-LANGIT 1,00 M2 Langit-Langit Calsiboard Rangka Kayu Meranti 214,452.50
35 SNI. 2839-2008 PEKERJAAN LANGIT-LANGIT 1,00 M2 Pasang Plafond Calsiboard Rangka Metal Hollow 154,077.40
36 SNI. 2839-2008 PEKERJAAN LANGIT-LANGIT 1,00 m1 Pasang list profil cornees gypsum lebar 5 - 10 cm 10,551.68
37 SNI. 00-0000-2002 PEKERJAAN SANITASI 1,00 Buah Pasang Closed Jongkok Porselen 507,632.41
38 SNI. 00-0000-2002 PEKERJAAN SANITASI 1,00 M' Pasang Pipa Pvc Ø 3/4" AW 34,174.38
39 SNI. 00-0000-2002 PEKERJAAN SANITASI 1,00 M' Pasang Pipa Pvc Ø 3" AW 87,374.94
40 SNI. 00-0000-2002 PEKERJAAN SANITASI 1,00 M' Pasang Pipa Pvc Ø 4" AW 106,385.69
41 SNI. 00-0000-2002 PEKERJAAN SANITASI 1,00 Buah Pasang Kran Air ( Steinlessteel ) 124,760.00
42 SNI. 00-0000-2002 PEKERJAAN SANITASI 1,00 Buah Pasang Floor Drain 38,780.00
43 SNI. 00-0000-2002 PEKERJAAN SANITASI Septictank + Resapan 2 Kompartemen Ukuran Kecil ( 1,65 x 1,10 x 1,25 ) 8,268,129.60
44 SNI. 00-0000-2002 PEKERJAAN PENUTUP LANTAI DAN DINDING 1,00 M2 Lantai Keramik Motif 40 x 40 cm 312,900.67
45 SNI. 00-0000-2002 PEKERJAAN PENUTUP LANTAI DAN DINDING 1,00 M2 Lantai Keramik 30 x 30 cm 246,614.35
46 SNI. 00-0000-2002 PEKERJAAN PENUTUP LANTAI DAN DINDING 1,00 M2 Lantai Keramik 20 x 20 cm 241,030.35
47 SNI. 00-0000-2002 PEKERJAAN PENUTUP LANTAI DAN DINDING 1,00 M2 Dinding Keramik 20 x 25 cm 242,718.34
48 SNI. 00-0000-2002 PEKERJAAN PENGECATAN 1,00 M2 Pekerjaan Cat Dinding dan Plafond 2 Lapis Penutup ( Baru ) 22,986.46
49 SNI. 00-0000-2002 PEKERJAAN PENGECATAN 1,00 M2 Pekerjaan Cat Kayu 2 Lapis Cat Penutup ( Baru ) 44,272.55
50 SNI. 00-0000-2002 PEKERJAAN KUNCI DAN KACA 1,00 Buah Pasang Kunci Biasa 2 x Putar 199,165.00
51 SNI. 00-0000-2002 PEKERJAAN KUNCI DAN KACA 1,00 Buah Pasang Engsel Pintu 44,892.50
52 SNI. 00-0000-2002 PEKERJAAN KUNCI DAN KACA 1,00 Buah Pasang Grendel Jendela 39,415.00
53 SNI. 00-0000-2002 PEKERJAAN KUNCI DAN KACA 1,00 Buah Pasang Grendel pintu 57,785.00
54 SNI. 00-0000-2002 PEKERJAAN KUNCI DAN KACA 1,00 Buah Pasang Engsel Jendela 34,420.00
55 SNI. 00-0000-2002 PEKERJAAN KUNCI DAN KACA 1,00 Buah Pasang Hag/Kait Angin 38,732.50
56 SNI. 03-3436-2002 PEKERJAAN PENUTUP ATAP 1,00 M2 Pasang Genteng Kodok Ex. Karang Penang 70,575.00
57 SNI. 03-3436-2002 PEKERJAAN PENUTUP ATAP 1,00 M' Pasang Genteng Wuwung Ex. Karang Penang 104,093.71
58 SNI. 3434-2008 PEKERJAAN KAYU 1,00 M' Pasang Lisplank Bangkirai ( Ukuran 3 x 20 Cm ) 161,545.00
59 SNI. DT 91-0014-2007 (6.11) 1,00 m' Pemasangan Kusen Alumunium Profil 4" 102,732.10
60 1,00 m2 Pemasangan Pintu Alumunium 817,830.00
61 1,00 m' Pemasangan slimar Alumunium Profil 3" 88,212.10
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
ANALISA HARGA SATUAN TAHUN ANGGARAN 2013

KETERANGAN
5
RENCANA ANGGARAN BIAYA ( RAB )

KEGIATAN : PEMBANGUNAN RUMAH TINGGAL


LOKASI : JAWA TIMUR
TAHUN : 2022

NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH


1 2 3 4 5 6

A LANTAI I
I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 98.00 m2 17,500.00 1,715,000.00
2 Pengukuran dan pasang bouplank 14.00 m' 145,756.50 2,040,591.00
Sub Jumlah I 3,755,591.00
II PEKERJAAN GALIAN & URUGAN
1 Galian tanah pondasi batu kali 46.48 m3 78,750.00 3,660,300.00
2 Galian tanah pondasi Sepatu 7.00 m3 78,750.00 551,250.00
3 Urugan tanah kembali 2.10 m3 22,050.00 46,305.00
4 Urugan tanah bawah lantai - m3 130,500.00 -
5 Urugan pasir pondasi Batu kali - m3 340,070.40 -
6 Urugan pasir pondasi Plat Sepatu - m3 340,070.40 -
7 Urugan pasir bawah lantai 4.90 m3 340,070.40 1,666,344.96
Sub Jumlah II 5,924,199.96
III PEKERJAAN PONDASI
1 Cor lantai kerja pondasi plat 0.22 m3 1,327,079.03 297,265.70
2 Pondasi batu kali 33.20 m3 852,243.10 28,294,471.05
3 Pondasi batu kosong (anstampeng) 14.10 m3 474,685.34 6,693,063.35
4 Pondasi beton plat sepatu 1.12 m3 5,209,045.56 5,834,131.03
5 Kolom struktur Pondasi 0.26 m3 8,485,366.56 2,227,408.72
6 Pondasi bata merah (Rollag) 8.70 m2 297,226.41 2,585,869.79
Sub Jumlah III 45,932,209.65
IV PEKERJAAN PEMBETONAN
1 Beton Sloof 2.49 m3 6,440,930.56 16,037,917.09
2 Kolom struktur 0.84 m3 9,596,937.23 8,061,427.27
3 Kolom Praktis 1.41 m3 7,738,404.68 10,896,060.71
4 Balok 1 (15/20) 1.68 m3 8,485,366.56 14,255,415.82
5 Balok 2 (15/30) - m3 8,485,366.56 -
6 Balok 3 (8/45) - m3 6,075,287.23 -
7 Balok Tangga (15/25) - m3 7,334,797.56 -
8 Balok Tangga (15/35) - m3 7,334,797.56 -
9 Balok Plat Atap - m3 7,334,797.56 -
10 Balok Plat Kanopi - m3 7,334,797.56 -
11 Ring Balk 0.54 m3 7,906,592.82 4,231,608.47
12 Pelat Lantai t 12 cm - m3 6,075,287.23 -
13 Pelat kanopi t 10 cm - m3 6,075,287.23 -
14 Pelat Meja Dapur t 10 cm - m3 7,334,797.56 -
15 Pelat tangga t 12 cm - m3 6,075,287.23 -
16 Rabat Beton - m3 1,419,866.28 -
17 Menbongkar cetakan beton - m3 400,000.00 -
Sub Jumlah IV 53,482,429.37
V PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding trasraam - m2 154,980.66 -
2 Pasangan dinding bata merah 353.97 m2 142,612.35 50,480,249.32
3 Pasangan batu alam templek - m2 336,963.44 -
4 Pasangan batu alam Palimanan Putih 20/40 - m2 336,963.44 -
5 Plesteran + Acian Trasraam - m2 111,599.52 -
6 Plesteran + Acian dinding 707.94 m2 106,567.28 75,442,880.71
Sub Jumlah V 125,923,130.02
VI PEKERJAAN KUSEN PINTU & JENDELA
1 Kusen Aluminium Profil 4" 52.34 m1 102,732.10 5,376,998.11
2 Daun Pintu Aluminium 13.02 m2 817,830.00 10,646,183.81
3 Daun Jendela kaca Aluminium 2.94 m2 666,405.50 1,957,632.80
4 Pasang Pintu PVC 2.00 unit 240,000.00 480,000.00
Sub Jumlah VI 18,460,814.72
VII PEKERJAAN PENUTUP PLAFOND
1 Pasang Plafond calsiboard + rangka Hollow 4x4 78.00 m2 154,077.40 12,018,037.20
2 List Gypsum profil - m' 10,551.68 -
Sub Jumlah VII 12,018,037.20
VIII PEKERJAAN SANITAIR
1 Instalasi air bersih pipa PVC AW 3/4" 20.00 m' 34,174.38 683,487.50
2 Instalasi air kotor pipa PVC AW 3" 20.00 m' 87,374.94 1,747,498.75
3 Instalasi air kotoran pipa PVC AW 4" 20.00 m' 106,385.69 2,127,713.75
4 Klosed jongkok 2.00 unit 507,632.41 1,015,264.82
5 Kran air 4.00 bh 124,760.00 499,040.00
6 Floor drain 2.00 bh 38,780.00 77,560.00
7 Mesin Pompa 1.00 bh 750,000.00 750,000.00
8 Resapan + Septictank 1.00 unit 4,500,000.00 4,500,000.00
Sub Jumlah VIII 11,400,564.82
IX PEKERJAAN INSTALASI LISTRIK
1 Meteran PLN 1.00 bh -
2 Box sekering 1.00 bh 36,720.00 36,720.00
3 MCB 1.00 bh 159,445.00 159,445.00
4 Lampu downlight 10.00 bh 42,900.00 429,000.00
5 Saklar ganda 5.00 bh 24,530.00 122,650.00
6 Saklar tunggal 5.00 bh 18,425.00 92,125.00
7 Stop kontak 220 V 5.00 bh 177,870.00 889,350.00
8 Kabel NYA 75.00 m' 33,770.00 2,532,750.00
Sub Jumlah IX 4,262,040.00
X PEKERJAAN PENUTUP LANTAI & DINDING
1 Keramik lantai motif 40/40 74.10 m2 312,900.67 23,185,939.57
2 Keramik lantai motif anti slip 20/20 4.50 m2 241,030.35 1,084,636.55
3 Keramik dinding warna 20/30 19.80 m2 242,718.34 4,805,823.09
4 Pasangan Paving Stone - m2 150,792.91 -
Sub Jumlah X 29,076,399.22
XI PEKERJAAN RANGKA & PENUTUP ATAP
1 Pasang Rangka Galvalum 73.50 m2 158,400.00 11,642,400.00
2 Pasang Genteng Beton Flat 73.50 m2 70,575.00 5,187,262.50
3 Pasang Genteng Bubungan 7.00 m' 104,093.71 728,655.98
4 Pasang lisplank 14.00 m' 161,545.00 2,261,630.00
Sub Jumlah X 19,819,948.48
XII PEKERJAAN PENGECATAN
1 Cat dinding interior dan ekterior dinding trasram - m2 22,986.46 -
2 Cat dinding interior dan ekterior dinding 707.94 m2 22,986.46 16,272,956.34
3 Cat interior plafon 78.00 m2 22,986.46 1,792,943.88
4 Cat eksterior kanopi - m2 22,986.46 -
5 Cat lisplank kayu - m2 44,272.55 -
Sub Jumlah XI 18,065,900.22
XII PEKERJAAN PASANG PENGUNCI
1 Kunci Pintu 4.00 unit 199,165.00 796,660.00
2 Engsel Pintu 12.00 bh 44,892.50 538,710.00
3 Grendel Pintu 8.00 bh 57,785.00 462,280.00
4 Grendel jendela 13.00 bh 39,415.00 512,395.00
5 Engsel Jendela 26.00 bh 34,420.00 894,920.00
6 Kait angin 26.00 bh 38,732.50 1,007,045.00
Sub Jumlah XII 4,212,010.00
REKAPITULASI ANGGARAN BIAYA ( RAB )

KEGIATAN : PEMBANGUNAN RUMAH TINGGAL


LOKASI : JAWA TIMUR
TAHUN : 2022

NO URAIAN PEKERJAAN JUMLAH


1 2 3

A LANTAI I
I PEKERJAAN PERSIAPAN 3,755,591.00
II PEKERJAAN GALIAN & URUGAN 5,924,199.96
III PEKERJAAN PONDASI 45,932,209.65
IV PEKERJAAN PEMBETONAN 53,482,429.37
V PEKERJAAN PASANGAN & PLESTERAN 125,923,130.02
VI PEKERJAAN KUSEN PINTU & JENDELA 18,460,814.72
VII PEKERJAAN PENUTUP PLAFOND 12,018,037.20
VIII PEKERJAAN SANITAIR 11,400,564.82
IX PEKERJAAN INSTALASI LISTRIK 4,262,040.00
X PEKERJAAN PENUTUP LANTAI & DINDING 29,076,399.22
XI PEKERJAAN RANGKA & PENUTUP ATAP 19,819,948.48
XII PEKERJAAN PENGECATAN 18,065,900.22
XII PEKERJAAN PASANG PENGUNCI 4,212,010.00
Jumlah Lantai 1 352,333,274.66

1 Total 352,333,274.66
2 Dibulatkan 352,333,000.00
Terbilang :
RENCANA ANGGARAN BIAYA ( RAB )

KEGIATAN : PEMBANGUNAN RUMAH TINGKAT 2 LANTAI


LOKASI : BANGKALAN - JAWA TIMUR
TAHUN : 2019

NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH


1 2 3 4 5 6

A LANTAI 2
I PEKERJAAN PEMBETONAN
1 Kolom struktur 2.55 m3 9,596,937.23 24,500,980.74
2 Kolom Praktis 0.39 m3 7,738,404.68 3,046,996.84
3 Balok 15/20 3.83 m3 7,906,592.82 30,271,181.25
4 Pelat atap KM/WC t 10 cm - m3 6,075,287.23 -
5 Pelat kanopi t 10 cm - m3 6,075,287.23 -
6 Menbongkar cetakan beton 6.78 m3 400,000.00 2,710,140.00
Sub Jumlah I 60,529,298.84
II PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan dinding trasraam 13.90 m2 154,980.66 2,154,231.15
2 Pasangan dinding bata merah 372.25 m2 142,612.35 53,087,723.52
3 Pasangan batu alam palimanan - m2 336,963.44 -
4 Plesteran + Acian Trasraam 12.25 m2 111,599.52 1,367,094.12
5 Plesteran + Acian dinding 744.50 m2 106,567.28 79,339,758.55
Sub Jumlah II 135,948,807.34
III PEKERJAAN KUSEN PINTU & JENDELA
1 Kusen Kayu 6/15 0.78 m' 102,732.10 80,303.63
2 Daun Pintu panil kayu 6.36 m' 817,830.00 5,205,324.38
3 Daun Jendela kaca kayu 3.99 m' 666,405.50 2,655,759.20
4 Pasang kaca bening 5 mm 7.49 m2 #REF! #REF!
5 Pasang kaca Es 5 mm 0.31 m2 #REF! #REF!
Pasang Pintu PVC 1.00 unit 240,000
Sub Jumlah III #REF!
IV PEKERJAAN PENUTUP PLAFOND
1 Pasang Plafond calsiboard + rangka hollow 56.50 m2 154,077.40 8,705,373.10
2 List Gypsum profil 58.60 m' 10,551.68 618,328.45
Sub Jumlah IV 9,323,701.55
V PEKERJAAN SANITAIR
1 Instalasi air bersih pipa PVC AW 3/4" 2.00 m' 34,174.38 68,348.75
2 Instalasi air kotor pipa PVC AW 3" 3.00 m' 87,374.94 262,124.81
3 Instalasi air kotoran pipa PVC AW 4" 2.00 m' 106,385.69 212,771.38
4 Klosed jongkok 1.00 unit 507,632.41 507,632.41
5 Kran air 1.00 bh 124,760.00 124,760.00
6 Floor drain 1.00 bh 38,780.00 38,780.00
Sub Jumlah V 1,214,417.35
VI PEKERJAAN INSTALASI LISTRIK
1 Lampu downlight 8.00 bh 42,900.00 343,200.00
2 Saklar ganda 2.00 bh 24,530.00 49,060.00
3 Saklar tunggal 4.00 bh 18,425.00 73,700.00
4 Stop kontak 220 V 3.00 bh 177,870.00 533,610.00
5 Kabel NYA 25.00 m' 33,770.00 844,250.00
Sub Jumlah VI 1,843,820.00
VII PEKERJAAN PENUTUP LANTAI & DINDING
1 Keramik lantai motif 40/40 34.00 m2 312,900.67 10,638,622.75
2 Keramik lantai motif anti slip 20/20 3.00 m2 241,030.35 723,091.04
3 Keramik dinding warna 20/30 27.80 m2 242,718.34 6,747,569.80
Sub Jumlah VII 18,109,283.58
VIII PEKERJAAN RANGKA & PENUTUP ATAP
1 Pasang Rangka Galvalum 93.47 m2 158,400.00 14,805,584.64
2 Pasang Genteng 93.47 m2 70,575.00 6,596,617.02
3 Pasang Genteng Bubungan 10.56 m' 104,093.71 1,099,229.60
4 Pasang Lisplank 24.12 m' 161,545.00 3,896,465.40
Sub Jumlah VIII 26,397,896.66
IX PEKERJAAN PENGECATAN
1 Cat dinding interior dan ekterior dinding trasram 12.25 m2 22,986.46 281,584.14
2 Cat dinding interior dan ekterior dinding 744.50 m2 22,986.46 17,113,509.12
3 Cat interior plafon 56.50 m2 22,986.46 1,298,734.99
4 Cat eksterior kanopi 9.60 m2 22,986.46 220,670.02
5 Cat lisplank kayu 5.31 m2 44,272.55 234,927.86
Sub Jumlah IX 19,149,426.12
X PEKERJAAN PASANG PENGUNCI
1 Kunci Pintu 4.00 unit 199,165.00 796,660.00
2 Engsel Pintu 12.00 bh 44,892.50 538,710.00
3 Grendel Pintu 4.00 bh 57,785.00 231,140.00
4 Grendel jendela 9.00 bh 39,415.00 354,735.00
5 Engsel Jendela 18.00 bh 34,420.00 619,560.00
6 Kait angin 18.00 bh 38,732.50 697,185.00
- Sub Jumlah X 3,237,990.00