Anda di halaman 1dari 7

PT.

JAYA TEKNIK INDONESIA


Doc. No : JTI/WIND/ MVAC//MS./1001

WINDSOR APARTMENT PROJECT Date : 9 July 2012 Revision : 0

1. SKOPE PEKERJAAN
Skope pekerjaan instalasi ducting isolasi supply 1. SCOPE OF WORK :
dan return ini meliputi hampir seluruh area di Scope work of this installationof supply and return
Windsor Apartment Yang meliputi : insulate air duct all area in area in the Windsor
1. Seluruh lantai Apartment. To include the following specific area :
1. Seluruh lantai

2. PERSIAPAN PEKERJAAN : 2. WORKS PREPARATION


Maksud dan tujuan dari persiapan pekerjaan The work preparation is intended with the
adalah untuk mengkondisikan agar pekerjaan purpose of ensuring that works implemented
tersebut berjalan dengan aman, baik dan dapat according to technical specification, site
termonitor sesuai dengan gambar kerja yang telah coordination to achieve a smooth work
disetujui, sesuai dengan spesifikasi teknis dan implementation and to achieve this purpose
koordinasi lapangan. Untuk mencapai maksud dan several pre-requisite has to be done :
tujuan tersebut, dilakukan :
1. Survey lokasi ketersediaan lahan kerja. 1. Check actual work area condition
2. Menyiapkan gambar kerja yang telah 2. Prepare approved shop drawing.
disetujui. 3. Prepare material based on approved
3. Menyiapkan material yang akan digunakan specifications.
dan telah disetujui. 4. Prepare experience workers and supervision.
4. Menyiapkan tenaga kerja dan pembagian 5. Prepare operational working tools and
tugasnya. equipment.
5. Menyiapkan peralatan kerja. 6. Requested issue work permit to main
6. Mengajukan ijin pelaksanaan pekerjaan contractor.
kepada kontraktor utama.

REFERENSI : REFFERENCE
1. Persetujuan gambar kerja 1. Shop drawing approval
2. Persetujuan material. 2. Material approval
3. Pedoman SMACNA edisi 1985 3. SMACNA Standart edition 1985
4. Petunjuk spesifikasi teknik kontrak 4. Technical specification contract
PT. JAYA TEKNIK INDONESIA
Doc. No : JTI/WIND/ MVAC//MS./1001

WINDSOR APARTMENT PROJECT Date : 9 July 2012 Revision : 0

3. MATERIAL YANG DIGUNAKAN :


1. Baja lapis seng
2. Support (besi siku) 3. MATERIALS NEED EQUIPMENT :
3. Baut dan Mur 1. Galvanized steel sheet
4. Dynabolt 2. Support ( angle steel)
5. Karet Paking 3. Nut and Bolt
6. Flint Coat 4. Dynabolt
7. Glass Wool – Density 24 kg/m3(Isolasi Luar) 5. Rubber gasket
– Density 48 kg/m3(Plenum) 6. Flint coat
8. Lem 7. Glass wool – Density 24 kg/m3(with Isolation)
9. Kawat ayam – Density 48 kg/m3(Plenum)
10. Paku leuress 8. Sealant
11. Kain pelapis 9. Wire mash
10. Spidle rim
4. PERALATAN KERJA : 11. Glass coat
1. Obeng minus
2. Obeng plus 4. WORKING TOOLS :
3. Mesin bor 1. Screwdrivers
4. Meteran 2. Screwdrivers
5. Gunting Seng 3. Drilling machine
6. Tang rivet 4. Meter
7. Kunci pas 10 mm – 22 mm 5. GI sheet cutter
8. Kabel power 6. Rivets
9. Sifat air 7. Close wrench 10 mm – 12 mm
10. Palu 8. Cable power
11. Gergaji besi 9. Carpenter level
12. Benang ( untuk lot instalasi pipa) 10. Hammer
13. Tambang 11. Hacksaw
14. Lampu sorot 500 Watt 12. Yarn ( for leveling)
15. Gelas ukur 13. Mine
14. Spot lamp 500 Watt
5. ALAT BANTU : 15. Measuring tube
1. Scaffolding komplit standart sagety 5. MISCELEANUS TOOLS:
2. Tangga 1. Scaffolding according to safety
2. ladder
6. ANALISA RESIKO BAHAYA PEKERJAAN :
1. Terjatuh 6. HAZARD ANALYSIST :
2. Mata terkena debu pengeboran 1. Fall
3. Terkena bor 2. Eyes hit by drilling dust
4. Tersengat aliran listri 3. Hit by drill
5. Kebakaran yang diakibatkan dari pengelasan 4. Electricution
6. Mata gerinda pecah 5. Fire cause by welding works
7. Terkena percikan las. (Lebih detail lihat JSA / Risk 6. Broken grinding wheel
Assessment terlampir). 7. Hit by welding slugs. (More detail see JSA /
Risk Assessment attachment)
PT. JAYA TEKNIK INDONESIA
Doc. No : JTI/WIND/ MVAC//MS./1001

WINDSOR APARTMENT PROJECT Date : 9 July 2012 Revision : 0

7. LANGKAH KERJA DUCTING DENGAN ISOLASI : 7. INSULATION DUCT STEP OF WORK :


Dalam pekerjaan instalasi pemasangan ducting In the duct non isolation supply and return
dengan isolasi, kerja yang akan dilakukan untuk installation several steps shall be done to include :
membuat instalasi supply dan return duct yang 1. Ducting fabrication in accordance with the
akan dilakukan di antaranya : drawing in the workshop
1. Fabrarikasi ducting sesuai dengan gambar 2. Fabrication duct are deliverd to the side
yang sudah disetujui di work shop. 3. Duct assembling according to duct Size.
2. Hasil fabrikasi ducting tersebut dikirim ke site 4. Install rubber gasket for each duct joint and
proyek sealant
3. Perakitan ducting sesuai dengan ukuran. 5. Ducting painted with plink coat thoroughly
4. Ducting yang di rakit, disambung, antara coat the mater surface.
sambungan dipasang karet gasket dan sealant 6. Ducting in wraping with wool glass and bound
5. Ducting di cat flint coat secara menyeluruh with string of rapiah boisterous till then wrap
pada permukaan luar ducting. foil aluminum later; then for boisterous.
6. Ducting di balut dengan glass wool dan diikat gummed by tape duct.
dengan tali plastik hingga kencang lalu balut 7. For wide ducting more than 800 in tide of
alumunium foil kemudian untuk spindle pin apart 500 horizontal mm &
pengencangan direkatkan menggunakan duct vertical.
tape 8. Installation of scaffolding. Marking the
7. Untuk ducting lebar lebih dari 800 di pasang position of ducting and hanger support
spindle pin berjarak 500 mm horizontal & 9. Drill slab concrete for both sides of the
vertikal ducting install the dynabolt/ dynaset. Install
8. Pasang scaffolding, marking posisi ducting dan the support and foundation. Ducting installed
gantungan support in accordance with the drawing.
9. Melubangi slab dak di dua sisi ducting yang 10. Leak test shall be electric lamp 500 Watt,
akan dipasang dynaset. Pasang support dan which the tighey use mine in to Ducting
landasan , Ducting dipasang sesuai dengan 11. Or use fogging method which is duct line will
gambar. be pressed by fogging and see fogg come out
10. Tes kebocoran dengan lampu listrik 500 watt from the leak area to identify the leakage.
yang di ikat tambang di masukkan ke dalam 12. If there is leaking hence dabbing sealant on
ducting. the surface of ducting.
11. Atau dapat menggunakan metode
pengasapan yang ditekankan ke dalam ducting
dan akan terlihat ada asap keluar dari celah
kebocoran untuk identifikasi kebocoran
tersebut.
12. Jika ada bocor maka oleskan sealant di
permukaan ducting yang bocor tersebut.
PT. JAYA TEKNIK INDONESIA
Doc. No : JTI/WIND/ MVAC//MS./1001

WINDSOR APARTMENT PROJECT Date : 9 July 2012 Revision : 0

8. LANGKAH KERJA UNTUK DUCTING ISOLASI


8. INTERNAL INSULATION DUCT STEP OF
DALAM :
Dalam pekerjaan instalasi pemasangan ducting WORK :
dengan isolasi dalam, kerja yang akan dilakukan In the duct non isolation supply and return
untuk membuat instalasi supply dan return duct installation several step shall be done to include :
yang akan dilakukan di antaranya : 1. Ducting fabrication in accordance with the
1. Fabrarikasi ducting sesuai dengan gambar drawing in the workshop
yang sudah disetujui di work shop. 2. Fabrication duct are deliverd to the side
2. Hasil fabrikasi ducting tersebut dikirim ke 3. BJLS before made by ducting have to in
site / proyek insulation tide in beforehand
3. BJLS sebelum dirakit harus di pasang isolasi 4. Surface of sheet interior of BJLSM in tide stick
dalam terlebih dahulu. on and Spindle with distance which have been
4. Permukaan bagian dalam lembaran BJLS determined
diberi perekat dan Spindle dengan jarak yang 5. Surface which there no Spindle dabbed by
sudah ditentukan. glue of Aica and in tide of glass wool flatten
5. Permukaan yang tidak ada Spindle dioleskan 6. Surface of wool glass in tide of glass coat and
perekat yang kuat dan di pasang glass wool followed by installation of mesh wire, in pin
merata. key of ( Pin Spindle).
6. Permukaan glass wool di pasang glass coat 7. Part of periphery of attached by BJLS is cloth
dan diikuti pemasangan wire mesh, di kunci and insulation of glass coat in primping and
dengan menggunakan spindle pin. dabbed by glue of Aica
7. Bagian pinggir dari BJLS yang dipasang isolasi 8. Duct assembling according to duct Size.
dan kain glass coat di rapihkan dan dioleskan 9. Install rubber gasket for each duct joint and
perekat. seal.
8. Perakitan ducting sesuai dengan ukuran. 10. Install scaffolding, Marking the position of
9. Ducting yang dirakit, disambung, antara ducting and hanger support
sambungan dipasang karet gasket dan sealant 11. Drill slab concrete for both sides of the
10. Pasang scaffolding, marking posisi ducting dan ducting install the dynabolt/ dynaset. Install
gantungan support the support and foundation. Ducting installed
11. Melubangi slab dak di dua sisi ducting yang in accordance with the drawing.
akan dipasang dynaset. Pasang support dan 12. Leak test shall be electric lamp 500 Watt,
landasan , Ducting dipasang sesuai dengan which the tighey use mine in to Ducting
gambar. 13. Or use fogging method which is duct line will
12. Tes kebocoran dengan lampu listrik 500 watt be pressed by fogging and see fogg come out
yang di ikat tambang di masukkan ke dalam from the leak area to identify the leakage.
ducting. 14. If there is leaking hence dabbing sealant on
13. Atau dapat menggunakan metode the surface of ducting.
pengasapan yang ditekankan ke dalam ducting
dan akan terlihat ada asap keluar dari celah
kebocoran untuk identifikasi kebocoran
tersebut.
14. Jika ada bocor maka oleskan sealant di
permukaan ducting.
PT. JAYA TEKNIK INDONESIA
Doc. No : JTI/WIND/ MVAC//MS./1001

WINDSOR APARTMENT PROJECT Date : 9 July 2012 Revision : 0

KRITERIA YANG BISA DITERIMA PEKERJAAN DUCTING:


ACCEPTABLE CRITERION OF DUCTING WORKS:
1. Ducting terpasang sesuai dengan BOD persetujuan
1. Ducting attached as according to BOD
gambar kerja
approval/permission of job/activity picture
2. Ducting terpasang harus lurus dan level
2. Ducting attached have to be diametrical and level
3. Sambungan ducting tidak ada yang bocor
3. Extension of Ducting nothing that leak
PT. JAYA TEKNIK INDONESIA
Doc. No : JTI/WIND/ MVAC//MS./1001

WINDSOR APARTMENT PROJECT Date : 9 July 2012 Revision : 0


PT. JAYA TEKNIK INDONESIA
Doc. No : JTI/WIND/ MVAC//MS./1001

WINDSOR APARTMENT PROJECT Date : 9 July 2012 Revision : 0

Anda mungkin juga menyukai