No. Uraian Satuan Jumlah Harga Satuan (Rp) Jumlah (Rp) Keterangan
I. BIAYA PERSONIL
1. Ketua Tim (Teknik Sipil) OB 7 22,416,000 156,912,000
2. Ahli Teknik Sipil (SDA - Pemetaan) OB 7 18,469,850 129,288,950
3. Ahli Teknik Sipil (SDA - Geoteknik) OB 7 18,469,850 129,288,950
4. Ahli Teknik Sipil (SDA - Hidrologi Struktur) OB 7 18,469,850 129,288,950
5. Ahli Sosial Ekonomi OB 7 18,469,850 129,288,950
6. Asisten Ahli Teknik OB 7 12,609,000 88,263,000
7. Drafter - 1 OB 4 10,507,500 42,030,000
8. Drafter - 2 OB 4 10,507,500 42,030,000
9. Chief Surveyor OB 6 9,947,100 59,682,600
10. Tenaga Adminitrasi OB 6 9,573,500 57,441,000
11. Office Boy OB 6 4,016,200 24,097,200
12. Supir 1 OB 5 4,670,000 23,350,000
13. Supir 2 OB 5 4,670,000 23,350,000
14. Surveyor lokal Ls 1 10,000,000 10,000,000