45000 28,999,378.57
28 29 30 1 2 3 4 5 6 7 8 9 10
NO PILCAPE
DiAM BESI PJG TULANGAN JMLH TULANGAN
1 D.12 6.82 10
PEDESTAL
1 D.16 2.2 12
2 D.8 1.1 5
TIE BEAM
1 D.16/MEMANJANG 42.07 10
2 D.16/MEMANJANG 44.97 10
3 D.16/MEMANJANG 9.9 10
4 D.16/MEMANJANG 6.1 10
5 D.16/MELINTANG 46.4 10
6 D.16/MELINTANG 12.4 10
7 D.16/MELINTANG 17.4 10
8 D.8/MEMANJANG 1.9 200
9 D.8/MEMANJANG 1.9 215
10 D.8/MEMANJANG 1.9 35
11 D.8/MEMANJANG 1.9 26
12 D.8/MELINTANG 1.9 215
13 D.8/MELINTANG 1.9 57
1.9 79
REKAP
D.16 610.604
D.12 421
D.8 546.91666
KEBUTUHAN URUGAN/PEDEL
Kebutuhan Pedel urugan utk jalan 341.87 4
Sirtu 341.87 4
DATA HITUNGAN VOLUME BEKISTING DAN BETON PILCAPE DAN PEDESTAL ASRAMA PUTRI
NO TIPE PILCAPE PJG TINGGI/LEBAR
1 PC 1 ; 1/1.5x1.5 6 0.25
2 PC 1 ; 2 7.2 0.3
3 PC 1 ; 1 1.5 1.5
4 PC 1 ; 2 1.8 1.8
5 Bekisting pedestal 1.2 0.55
6 Beton pedestal 0.3 0.3
HITUNGAN BESI PILECAPE : PC 1 / PC 2/PEDESTAL
NO TYPE PILCAPE PANJANG M1 PANJANG M1
TULANGAN ATAS TULANGAN BAWAH
1 PC.1/D.12/1.5x1.5 1.6
PC.1/D.12/1.5x1.5 1.85
2 PC.2/D.12/80x1.50 1.4
PC.2/D.12/80x1.50 1.65
1 PEDESTAL : D.16 3
2 PEDESTAL : D.8 1
DATA HITUNGAN VOLUME BETON PLAT LT.1 /AS : 1-6 / A - F/GEDUNG SEKOLAH
NO ITEM PEKERJAAN PANJANG LEBAR
1 Luas As 1-2 /A-F 7.7 6.9
2 Luas As 2 -3 /A-F 7.7 2.2
3 Luas As 3-4 / A - F 7.7 5.7
4 Luas As 4-5 / A - F 7.7 2.2
5 Luas As 5-6 / A - F 7.7 6.9
DATA HITUNGAN VOL WIEREMES DAN PERATAAN GALIAN PLAT TIEBEM GEDUNG SEKOLAH
NO ITEM PEKERJAAN PANJANG LEBAR
1 As 1-6 /A - F 40.3 25.3
2 As B - E /3 -4/ Pengurangan volume 23.7 5.7
DATA HITUNGAN PEMBESIAN KOLOM 30 X 30 / GEDUNG SEKOLAH.A
TINGGI PANJANG
NO ITEM PEKERJAAN KOLOM TULANGAN
1 TULANGAN /D.16 3.8 3.8
2 SENGKANG/ D. 8 3.8 1.1
3 TIIS/SEPIHAK/D.8 0.74
4 BEKISTING KOLOM 3.2 1.2
5 BETON KOLOM 3.2 0.3
TOTAL PANJANG
TULANGAN/PILCAPE/BLK
JMLH PILCAPE/BALOK JMLH PJG JMLH/12 M JMLH KG
68.2 74 5046.8 420.566666666667 4500.06333333333
BESI
11558.73372
4504.7
2592.3849684
EM ASRAMA BUDIMULYA
TERKIRIM KURANG
24 0
0 48
0 56
10 0
0 10
85 7
170 14
170 14
0 10 kolom
TUHAN URUGAN/PEDEL
0.3 410.244
0.1 136.748
JUMLAH JUMLAH
SIKU TAIROT SIKU
30 30
70 70
120 120
220 220
673 0.5
SRAMA PUTRI
JUMLAH TINGGI JUMLAH M2 JUMLAH M3
67 100.5
5 10.8
67 0.275 41.45625
5 0.375 6.075
72.00 47.52
0.55 72 3.564
158.82 51.09525
45000
C 1 / PC 2/PEDESTAL
JUMLAH /BATANG JMLH M1 JMLH UNIT JMLH PJG M1 PANJANG /12M
TULANGAN PJG TULANGAN PILCAPE TULANGAN
18 28.8 67 1929.6 160.8
18 33.3 67 2231.1 185.925
16 22.4 5 112 9.33333333333333
16 26.4 5 132 11
12 36 72 2592 216
10 10 72 720 60
643.058333333333
VOL M2
692.865 BERAT BESI
113.68 D.8 /polos 4.74
70.18 D.12/polos 10.7
692.865 D.16/ulir 18.93
1569.59
1233.09
JUMLAH HARGA
7,146,900.00
9,130,884.40
3,065,700.00
42,399,000.00
16,083,168.64
8,479,800.00
9,906,600.00
7,847,950.00
7,701,766.60
13,137,300.00
1,313,280.00
2,486,250.00
5,047,500.00
18,503,850.00
152,249,949.64
27 0.275 16.71
4.00 0.325 6.50
4 0.325 5.2
33 0.55 1.63
7 3.6 4.032
130.2 34.07
45000 60,000.00
5,859,000.00 2,044,305.00
83.181 554.54
DUNG SEKOLAH
JUMLAH JUMLAH M 2
1 1019.59
1 135.09
884.5
JUMLAH HARGA
5,859,000.00
5,884,244.30
2,044,200.00
24,954,300.00
9,759,918.30
4,990,860.00
5,677,056.00
4,422,500.00
4,053,561.60
6,912,000.00
691,200.00
1,631,250.00
1,631,250.00
-
78,511,340.20
1100 19,739,046.53
60000 8,479,800.00
45000 42,399,000.00
336.5
BERAT BESI
67 150.75 D.8 /polos 4.74
5 15 D.12/polos 10.7
165.75 D.16/ulir 18.93
2,299,286.25
JUMLAH
KG
1720.56
1989.3975
99.8666666666667
117.7
4088.88
284.4
8300.80416666667
1000 8,300,804.17
JUMLAH JUMLAH
PJG /12 M1 Kg
170.96 3236.2728
60.9866666666667 1154.4776
13.4666666666667 254.924
8.6 162.798
130.826666666667 2476.5488
8.18666666666667 154.9736
98.3466666666667 1861.7024
124.106666666667 588.2656
734.54 3481.7196
5.33333333333333 100.96
8 151.44 15,289.38
8 151.44
5.33333333333333 100.96
1.66666666666667 31.55
2.5 47.325
1.66666666666667 31.55
1.5 28.395
3.33333333333333 63.1
0.66666666666667 12.62
4 75.72
4 75.72
4 75.72
4 75.72
4 75.72
4 75.72
0.66666666666667 12.62
3.33333333333333 63.1
14621.0624
#VALUE!
JMLH GALIAN M2
60.75
20
28
108.75
7,903,305.00
JUMLAH
KG
693.36
801.6975
123.585
137.2275
204.013333333333
202.158666666667
54.9266666666667
34.454
927.57
1874.07
99.54
130.35
66.36
5349.31266666667
1100 5,884,243.93
JUMLAH JUMLAH
PANJANG TIEBEM Kg
241.8 3252.174
8.3 107.901
8.3 107.901
102.8 1380.628
20 258.71
20 258.71
6 78.875
49.69125
75.72
6.78325
75.72
75.72
75.72
88.0245
58.683
9.7805
6.31
134.403
2037.356833
733.841666666667
407.2 8872.65299966667
1100
9,759,918.30
JUMLAH JUMLAH BERAT BESI
PANJANG TIEBEM Kg D.8 /polos 4.74
241.8 3252.174 D.12/polos 10.7
8.3 107.901 D.16/ulir 18.93
8.3 107.901
102.8 1380.628
20 258.71
PROGRAM KERJA HARIAN PONDOK CEPU
HARI / NO ITEM PEKERJAAN TGL HARI KERJA
(1)1 Streping cuting dan perataan area Asrama 22/10/22 9 sd 16
2 Bongkar tonggak 22/10/22 10.30 sd 11.30
3 Cuting ,perataan area Asrama dan jalan 23/10/22 8 sd 16
4 Streping dan cuting area Asrama 23/10/22 8 sd 12
5 Cuting perataan asrama dan Sekolah 24/10/22 8 sd 16
6 striping danCuting elv 17 Sekolah 24/10/22 8 sd 16
7 Fabrikasi kolom pedestal 24/10/22 8 sd 16
8 Seting out dan bowplang Asrama 24/10/22 8 sd 16
( 2 )1 Cuting sekolah dan nimbun 25/10/22 8 sd 16
2 Cuting elv 17 Sekolah dan galian pilcape 25/10/22 8 sd 12 /15-16
3 Monitor gali sekolah dan bowplang Asrama 25/10/22 8 sd 16
4 Langsir pricas pilcape,begel 60 ,30 dan besi pedestal 25/10/22 8 sd 16
5 Vabrikasi kolom pedestal 25/10/22 8 sd 16
6 Langsir bekisting pilcape 25/10/22 8 sd 16
(3) 1 Cuting Elv 17 sekolah dan nimbun 26/10/22 8 sd 16
2 Galian pilcape 26/10/22 8 sd 16
3 Perapihan galian pilcape dan pasang plastik 26/10/22 8 sd 18
4 Pembesian pilcape dan colom pedestal 26/10/22
5 Bekisting pilcape 26/10/22
6 Langsir pricast pilcape 26/10/22
7 Vabrikasi begel 70 posisi tiebem keliling Gedung 26/10/22 8 sd 22
8 Pasang atap singkalum tempat berteduh 26/10/22 8 sd 16
9 Monitor galian pilcape dan galian sekolah 26/10/22
(4) 1 Galian pilcape 27/10/22 8 sd 12
2 Cuting Elv 17 sekolah dan nimbun 27/10/22 8 sd 16
3 Perapihan galian pilcape dan pasang bek pilcape 27/10/22 8 sd 22
4 Pembesian pilcape dan colom pedestal 27/10/22 8sd 22
5 Vabrikasi begel 70 posisi tiebem keliling 27/10/22 8 sd 22
6 Penerangan lampu dan terpal utk Lembur lapangan 27/10/22 8 sd 22
7 Monitor galian pilcape dan galian sekolah 27/10/22 8 sd 22
(5)1 Cuting Elv 17 sekolah dan buat axes jln Mixer 28/10/22 8 sd 16
2 Galian pilcape dan buat axes jln mixer 28/10/22 8 sd 20.30
3 Pemadatan axes temporari 28/10/22 8 sd 22
4 Pembesian pilcape dan colom pedestal 28/10/22 8 sd 22
5 Vabrikasi begel 70 posisi tiebem keliling Gedung 28/10/22 8 sd 22
6 Pasang deking paving 10 pilcape 28/10/22 8 sd 22
7 Seting persiapan Cor 28/10/22 8 sd 22
8 Cor pilcape dan colom Pedestal /Vibrator jam 13 28/ 10/22 8 sd 22
( 6 )1 Cuting elv 17 Sekolah dan galian pilcape 29/10/22 8 sd 16 00
Buat axes jalan design dalam 60 cm dari top jalan 29/10/22 8 sd 16 00
2 Galian pilcape 14 unit 29/10/22 8 sd 18.30
Timbunan pilcape dan galian tie bem 29/10/22 8 sd 18.30
Bantu cor bila terjadi kendala 29/10/22 8 sd 18.30
3 Perapian galian pilcape 29/10/22 8 sd 22
4 Bongkar pasang bekisting pilcape dan tie beam 29/10/22 8 sd 22
5 Pembesian pilcape dan colom pedestal 29/10/22 8 sd 22
6 Cor pilcape dan colom Pedestal 10 unit 29/10/22 8 sd 22
7 Vabriakasi begel 70 dan 60 29/10/22 8 sd 22
8 Vabrikasi Bekisting pilcape deletasi 29/10/22 8 sd 22
9 Produksi beton dacking ukuran 4 inci X 5cm 29/10/22 8 sd 22
10 Monitor galian pilcape.cek as dan galian sekolah 29/10/22 8 sd 22
(7)1 Cuting elv 16 00 Sekolah dan perataan 30/10/22 8 sd 10.30
Galian jalan design 30 /10/22
2 galian pilcape,timbunan pilcape 30/10/22 8 sd 16
Bantu cor bila terjadi kendala 30 /10/ 22
bantu gali jln design 30 /10/ 22
3 Bongkar pasang 10 pilcape 30 /10/ 22 8 sd 22
5 Pembesian stek kolm 30/10/ 22 8 sd 22
6 Galian tiebem 30 /10/ 22 8 sd 22
7 Streping perapiha galian pilcape 30/10/ 22 8 sd 22
8 vabrikasi begel kolom dan begel 70 30/10/ 22 8 sd 22
9 Fabrikasi Bekisting PC 2 30/10/ 22 8 sd 22
10 Cor pilcape 30 /10 22 8 sd 22
(8)1 Timbunan pilcape dan galian tie bem 31/10/2022 8 sd 17
Galian pilcape dan buat axes jln mixer 31/10/2022 8 sd 22
2 Bekisting pilcapedan pembesian Kolom pedestal 31/10/2022 8 sd 22
3 Vabrikasi precast pilcape dan begel 70 31/10/2022 8 sd 22
4 Langsir besi 16 dan begel 70 dari Plan 31/10/2022 8 sd 22
5 Streping perapihan galian pilcap 31/10/2022 8 sd 22
6 Galian perapihan tieabem 31/10/2022 8 sd 22
7 Cor pilcape as 4 31/10/2022 8 sd 22
8 Cek as kolom as 4 yg mau di cor 31/10/2022 8 sd 22
9 Monitor galian pilcap 31/10/2022 8 sd 22
( 9 )1 Galian pilcape 1/11/2022 8 sd18
Timbunan pilcape dan galian tie bem 1/11/2022 8 sd 18
2 Bekisting pilcape dan pembesian 1/11/2022 8 sd 18
3 Cor pilcape 1/11/2022 8 sd 18
4 Perapian galian pilcape dan tiebeam 1/11/2022 8 sd 18
5 Pembesian balok tiebeam 1/11/2022 8 sd 18
6 Langsir besi 16 dan begel 70 1/11/2022 8 sd 18
7 Precas pilcape dan begel 70 1/11/2022 8 sd 18
8 Perataan Elv 16 1/11/2022 8 sd 18
9 Monitor galian dan as 1/11/2022 8 sd 18
( 10 ) 1 Perataan Elv 16 dan axes rencana jalan 2/11/2022 8 sd 17
2 Galian pilcap 2/11/2022 8 sd 21
Timbunan pilcape dan galian tie bem 2/11/2022 8 sd 21
Bantu axes rencana jalan 2/11/2022 8 sd 21
3 Bekisting pilcape 2/11/2022 8 sd 22
4 Pembesian kolom pedestal Asrama lanjutan 2/11/2022 8 sd 22
5 Pembesian tieabem 2/11/2022 8 sd 22
6 Vabrikasi precast pilcape 2 x 2m dan 150 2/11/2022 8 sd 22
7 Langsir besi 16 dan begel 70 dari Plan 2/11/2022 8 sd 22
8 Bongkar material tiebeam dari truk 2/11/2022 8 sd 22
9 Cor pilcape 2/11/2022 8 sd 22
10 Monitorgalian pilcape dan As 2/11/2022 8 sd 22
11 Monitor galian Elv 16 dan Axes rencana jalan 2/11/2022 8 sd 22
(11)1 Cuting elvasi 16 dan axes rencana jalan 3/11/2022 8 sd 17
2 Galian dan timbunan pilcape Asrama 3/11/2022 8 sd 17
Buat axes cor 3/11/2022 8 sd 17
3 Pembesian tieabem 1,2,3,4 / A - I 3/11/2022 8 sd 22
4 Bekisting tieabem 3/11/2022 8 sd 22
5 Langsir bekisting tiebem dan siku dari area Makam 3/11/2022 8 sd 22
6 Fabrikasi begel 70 dan pilcape 2x2m jumlah ; 12 unit 3/11/2022 8 sd 22
7 Bekisting pilcape dan pembesian 3/11/2022 8 sd 22
8 Cor pilcape 3/11/2022 8 sd 22
9 Monitor galianpilcap dan cating elv 16 3/11/2022 8 sd 22
10 Exet as gedung sekolah 3/11/2022 8 sd 22
11 Exet rencana jalan samping makam 3/11/2022 8 sd 22
(12)1 Cuting elvasi 16 dan axes rencana jalan 8 sd 17
2 Galian dan timbunan pilcape Asrama 4/11/2022 8 sd 17
3 Buat axes cor 4/11/2022 8 sd 17
4 Pembesian tieabem 1,2,3,4 / A - I 4/11/2022 8 sd 18
5 Bekisting tieabem 4/11/2022 8 sd 18
6 Cor pilcape 4/11/2022 8 sd 18
7 Bekisting pilcape dan pembesian 4/11/2022 8 sd 18
8 Monito galian dan as Asrama 4/11/2022 8 sd 18
9 Exet rencana jalan 4/11/2022 8 sd 18
(13)1 Cuting axes rencana jalan samping makam 5/11/2022 8
`2 Timbunan Asrama Putri 5/11/2022 8
3 Galian dan timbunan pilcape 5/11/2022 8
Bantu axes rencana jalan 5/11/2022 8
Bongkar tonggak area makam 5/11/2022 8
4 Bongkar pasang bekisting pilcape 5/11/2022 8
5 Bekisting tiebem 5/11/2022 8
6 Pembesian tiebem asrama as 6,7,8/B-I 5/11/2022 8
7 Galian perapihan tieabem 5/11/2022 8
8 Cor pilcape Gedung sekolah/Pedestal kolom 40x40 5/11/2022 8
9 Cor Pilcape Asrama 5/11/2022 8
10 Fabrikasi begel 70 dan pilcape 2x2m jumlah ; 12 unit 5/11/2022 8
Pak Edy
Tim Survey
Dozer 1
Exavator 1 Cor pilcape
Vibro 1
Mdr Aris 12 2400000
Mdr Aris
Mdr Aris
Mdr Aris /tim Survey
Mdr Aris/Pak Edy 9/ 7 m3
Dozer 1 3200000
Kebutuhan material pendukung
Exavator PC 200 1 1) Triplek 2 .lbr
2) paku 5 ;10 kg
3) Selang air kerja 2 Rol
Mdr Aris 16 4) drum : 2 buah
Mdr Aris 5) semen utk beton dacking
Mdr Aris 6)Adibon : 1 drum
Mdr Aris 10/7.5 m3 7) lampu penerangan
Mdr Aris Penanggung jawab
Mdr Aris Bos Edy Cs
Mdr Aris
Tim Survey
Dozer Rusak
Exavator PC 200
2 unit/pilcap deletasi
5/ 4m3
Exavator PC 200 1
Material pendukung
Mdr Aris 27 5400000
Mdr Aris Streform ukuran
Armada Bos EDY 2 cm x 50 cm x1 mtr
Mdr Aris sebanyak 5 lembar utk deletasi
Mdr Aris BOS EDY
Mdr Aris 4/ 3 m3
Tim survey
Tim survey
Exavator PC 200
Hujan mulai jam 17,30
Mdr Aris 27 5400000
11 /7.5 m3
Dozer of/rusak
Tim survey
DOZER D.65 1
Exavator PC 200 1
Mdr Aris 27 5400000
Mdr Aris
Mdr Aris
Mdr Aris
Armada Bos EDY 3 rit
Mdr Aris
Mdr Aris 8 + pc 2 :2/ 8 m3
Tim survey
Tim survey
DOZER D.65 1
Exavator PC 200 1
Exavator PC 200 1
Mdr Aris 29 5800000
Mdr Aris/Darwanto
Armada Bos EDY Langsir besi of dulu
Mdr Aris
Mdr Aris/Darwanto
Mdr Aris 4/4m3
Tim survey
Tim survey
Tim survey
DOZER D.65 1
Exavator PC 200 1
Exavator PC 20 lansir besi 1 x
Mdr Aris 31 3720000
Mdr Aris
Mdr Aris 5/ 4 m3
Mdr Aris
Tim survey
Tim survey
DOZER D.65 1
Exavator PC.200 1
Exavator PC.201
Exavator PC.202
Exavator PC.203
Mdr Aris
Mdr Aris 31
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris 5/4 m3
Mdr Aris
DOZER D.65 1
DOZER D.66
Exavator PC.200 1.00
Exavator PC.201
Exavator PC.202
Exavator PC.203
Mdr Aris 22 150000
Mdr Aris
Mdr Aris
Mdr Aris/Bos Edi kompresor/jetkliner/Bos Edy
Bos Edi
Tim survey 2
DOZER D.65 1
DOZER D.66 1
Exavator PC.200 1
Exavator PC.201 1
Exavator PC.202 1
Exavator PC.203 1
Dozer D.65 1
EXAVATOR PC 200 1
EXAVATOR PC 200 1
TIM SURVEY 3
Mdr Aris 33
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris 49.5
Mdr Aris
Dozer D.65 1
EXAVATOR PC 200 1
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
Pak Edy ok
Mdr Aris 63
Travo las pak Edy
Darwanto
DOZER D.65 1
DOZER D.65 1
EXAVATOR PC .200 1
EXAVATOR PC .200 1
EXAVATOR PC .200 1
Mdr Aris 2
Mdr Aris 7
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris kontinyu
Tim survey ok
Tim survey ok
2 2 rit
DOZER D 65 1
DOZER D 65 1
EXAVATOR PC .200 1
EXAVATOR PC .200 1
EXAVATOR PC .200 1
EXAVATOR PC .200 1 pak Edy 4 rit
Mdr.Aris 36
Mdr.Aris
Mdr.Aris 10
Mdr.Aris 2
Mdr.Aris
Mdr.Aris 6
Tim survey kontinyu
DOZER D 65
EXAVATOR PC .200
Mdr.Aris
Mdr.Aris
Mdr.Aris
Mdr.Aris
Mdr.Aris
Mdr.Aris
Mdr.Aris
pak Edy
Tim survey
DOZER D.65
EXAVATOR PC 200
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
DOZER D.65
EXAVATOR PC 200
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris 9 m3
Mdr Aris
Pak Edy 0
EXAVATOR PC 200
EXAVATOR PC 200
EXAVATOR PC 200 pak Edy 5 rit
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
Mdr Aris
EXAVATOR PC 200
EXAVATOR PC 200 pak Edy 5 rit/ok pak Edy
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Mdr Aris/Darwanto
EXAVATOR PC 200
Mdr Aris/Darwanto
Mdr Aris/Darwanto 36
Mdr Aris/Darwanto 3 m3
Mdr Aris/Darwanto 6 m3
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Pak Edy 5 rit
EXAVATOR PC 200 1
EXAVATOR PC 201 1
EXAVATOR PC 202 1
Mdr Aris/Darwanto
Mdr Aris/Darwanto 3 Mixer /13.5 m3
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Mdr Aris/Darwanto
EXAVATOR PC 200 1
EXAVATOR PC 201 1
EXAVATOR PC 202 1
Mdr Aris/Darwanto
Mdr Aris/Darwanto 22 m3
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Mdr Aris/Darwanto
EXAVATOR PC 200
EXAVATOR PC 201
EXAVATOR PC 202
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Mdr Aris/Darwanto
Mdr Aris/Darwanto
EXAVATOR PC 200 Pak Edy
Mdr Aris/Darwanto
Pak Edy
1,600,000.00
2,400,000.00
2,400,000.00
2,400,000.00
2,400,000.00
Besi : 11
Galian+cor : 5
Bekiting :
3,200,000.00
cor pilcape Beton
9 7
10 7.5
5 4
4 4
3,200,000.00 11 7.5
10 8
4 4
5 4
58 46
5,400,000.00
5,400,000.00
5,400,000.00
5,800,000.00
5,800,000.00
11 4
15 4
8 4
4
5 15
6 60000
900000
49
3,300,000.00
4,650,000.00
6,000,000.00
4,650,000.00
4,650,000.00
6,200,000.00
4,650,000.00
6,200,000.00
4,200,000.00
3,000,000.00
6,600,000.00
58,300,000.00
PENGELUARAN CEPU
NO ITEM Tgl NOMINAL
1 Riyadi 22/10/22 200,000.00
2 Dispenser 23/10/22 125,000.00
3 Aqua galon 23/10/22 55,000.00
4 Kopi mes 24/10/22 50,000.00
5 Kopi pekerja 25/10/22 30,000.00
6 Lembur pekerja 27/10/22 30,000.00
7 kopi tim lapangan 29/10/22 50,000.00
8 Minum kru survey 31/9/2022 50,000.00
9 Kopi survey dan exa 1/11/2022 50,000.00
10 Kopi survey /p supri Cs 2/11/2022 50,000.00
11 Minum kru survey 3/11/2022 30,000.00
12 Aqua galon 3/11/2022 22,000.00
13 Kopi lapangan 6/11/2022 50,000.00
14 Minum kru survey 11/11/2022 50,000.00
15 Minum kru survey 13/11/2022 50,000.00
892,000.00
PANJANG JMLH PJG /12m BERAT/
1 D.8 1.78 1900 281.8333333333 1335.89
2 D.12/PC 1/ bawah 1.85 18 185.925 1989.3975
3 D.12/PC 1/Atas 1.6 18 160.8 1720.56
4 D.12/PC 2/Bawah 1.65 16 22 235.4
5 D.12/p2 /Atas 1.4 16 18.66666666667 199.7333333333
6 D.12/peminggang 46 492.2
7 D.8/ begelpedestal 1 10 63.33333333333 300.2
8 D,16/Stek kolom 3 12 228 4316.04
9 D.16/tiebem 251 4751.43
JUMLAH kg 15340.85083333
850
Rp 13,039,723.21
VOL TIEBEM
BLK MEMANJANG JMLH TIEBEM JMLH TIEBEM TINGGI JMLH LUAS
1 1B - 1. I
40.05 4 2 0.7 224.28
BLK MELINTANG
6.2 8 2 0.7 69.44
3.7 8 2 0.7 41.44
6.2 8 2 0.7 69.44
404.6
40,000.00
Rp 16,184,000.00
110,000,000.00 31,393.85
31
67
10
begel klmPc 2 76
Stek klm 76
1 32
2 32
3 32
4 43
tiebem 139
pjg blk
160.2
49.6
29.6
49.6
total pjg 289 10,000.00
Gran total
rupiah
31,588,000.00
11,200,000.00
`
5,600,000.00
48,388,000.00
pjg lbr
40.1 46.3
3 12.3
11.7 27.17
11.7 6.12
PJG/UNIT
1,670.89 10,025.36 17500 670.3
17,142.86 45,714.29 40500 76
200000
14 86800000
BERAT BESI
D.8 /polos 4.74
D.12/polos 10.7
D.16/ulir 18.93
B
14
112
1000000
1856.63 2 3713.26
36.9 108.5
317.889
71.604 3821.76 3503.871 m2
426.393 x 70,000.00
Rp 245,270,970.00
11,730,250.00
3,078,000.00
114,675,694.00
55,000,000.00
59,675,694.00