SCHEDULE PERSIAPAN/MOBILISASI PROYEK ADARO

BULAN I BULAN II BULAN III


No URAIAN
1-7 8 - 15 16 - 23 24 - 31 1-7 8 - 15 16 - 23 24 - 31 1-7 8 - 15 16 - 23

1 MOBILISASI PERSONIL (BALIKPAPAN - SITE ADARO)


>> Crew Tahap 1
>> Crew Tahap 2

2 MIBILISASI AMP, EQUIPMENT (BALIKPAPAN - SITE ADARO)


>> Transport AMP, Equipment ke Handil
>> Loading AMP, Equipment ke ponton (Handil), Lasing
>> Pengiriman AMP, Equip. Dari handil ke Jetty Adaro
>> Bongkar AMP, Equipment di Jetty Adaro dan Transport AMP,
Equipment ke (Site) Adaro

3 FASILITAS KONTRAKTOR (Direksi Keet, Workshop, Gudang)

4 PEMBUATAN PONDASI AMP SHIN SHAENG


>> Shop Drawing & Bill of quantity
>> Pengadaan Material Angkur Bold
>> Penyiapan Lahan Untuk AMP dan Fasilitas Kontraktor
>> Pembuatan Pondasi AMP (Galian + Penimbunan)

5 ERECTION AMP + ELEKTRIKAL

6 LABORATORIUM
>> Formula Campuran Rancangan (FCR)
>> Kalibrasi Timbangan & Pintu Cold Bin
>> Percobaan Produksi Hotmix & Pemeriksaan Hotbin + Trial Lapangan
>> Pemeriksaan & Evaluasi Hasil Trial Hotmix Lapangan (Sudah sesuai spec.)
(disetujui FCK = Formula Campuran Kerja) atau JMF

7 PELAKSANAAN HOTMIX & PRIME COAT (Mixing, Racing, Compaction)