KURVA - S

PEKERJAAN DAN PERENCANAAN REVITALISASI TPA REGIONAL SARBAGITA SUWUNG


No. KONTRAK : 08/KONTRAK-JK/KSP/III/2016

BOBOT Jan-18 Feb-17 Mar-17 Apr-17 May-17


NO URAIAN KETERANGAN
(%) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

I PEKERJAAN PERSIAPAN

1 Pengukuran topografi dan situasi TPA 4.28% 2.14% 2.14%

2 Penyelidikan tanah dan test laboratorium (Soil Test) TPA 5.74% 1.44% 1.44% 1.44% 1.44%

II LINGKUP KEGIATAN

1 Desain galian, Pemindahan dan pemadatan sampah 3.18% 1.06% 1.06% 1.06%

2 Desain pipa flaring, sulingan dan saluran lindi 3.34% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56%

3 Desain Buffer zone dan landscapping 4.30% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54%

4 Desain Jalan pedestrian Terasering 1.87% 0.47% 0.47% 0.47% 0.47%

5 Desain Tangga Pedestrian 1.87% 0.47% 0.47% 0.47% 0.47%

6 Desain Saluran drainase untuk jalan operasional 2.42% 0.61% 0.61% 0.61% 0.61%

7 Desain bronjong 2.31% 0.58% 0.58% 0.58% 0.58%

8 Desain coversoil 3.34% 0.56% 0.56% 0.56% 0.56% 0.56% 0.56%

III PEKERJAAN SANITARY LANDFILL TPA (Luas 5 Ha)

1 Desain galian dan pemindahan sampah 2.31% 0.58% 0.58% 0.58% 0.58%

2 Desain zona landfill 1.87% 0.47% 0.47% 0.47% 0.47%

3 Desain IPL (paket) kapasitas 350 m3/hari 1.87% 0.47% 0.47% 0.47% 0.47%

4 Desain saluran drainase (U-ditch 500x500x1200 mm) 1.87% 0.47% 0.47% 0.47% 0.47%

5 Desain jalan operasional 2.17% 0.54% 0.54% 0.54% 0.54%

6 Desain buffer zone 3.67% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%

IV PEKERJAAN PEMATANGAN LAHAN LOKASI PLTSA (luas 5 Ha)

1 Desain galian dan pemindahan sampah 2.31% 0.58% 0.58% 0.58% 0.58%

V OPTIMALISASI INSTALASI PENGOLAHAN LINDI (IPL) EKSISTING

1 Desain kolam Anaerob 3.67% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%

2 Desain kolam fakultatif 3.67% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%

3 Desain kolam Aerobik (gabungan dari kolam maturasi dan wetland) 3.67% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%

4 Desain kolam Biofilter 3.67% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%

5 Desain bak Penampung 3.67% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%

VI INFRASTRUKTUR PENDUKUNG

1 Desain pos Jaga 3.29% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41%

2 Desain jembatan Timbang 3.29% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41%

3 Desain kantor Pengelola 3.29% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41%

4 Desain garasi dan Bengkel Mobil 3.29% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41%

5 Desain garasi Alat Berat 3.29% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41%

6 Desain tempat Cuci Kendaraan 3.29% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41%

7 Desain rumah Genset + Unit genset 3.29% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41%

8 Desain lampu penerangan 3.29% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41%

9 Desain jalan operasional 3.29% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41%

10 Desain sumur pantau 3.29% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41%

TOTAL 100.00% 3.57% 4.63% 5.34% 5.34% 5.72% 5.72% 4.53% 4.53% 4.43% 4.43% 3.89% 3.89% 6.87% 6.87% 6.87% 6.87% 4.12% 4.12% 4.12% 4.12%

3.57% 8.21% 13.55% 18.89% 24.61% 30.33% 34.87% 39.40% 43.84% 48.27% 52.16% 56.06% 62.92% 69.79% 76.66% 83.53% 87.64% 91.76% 95.88% 100.00%