PERTEMUAN IV
AGREGAT
• PASIR
• KERIKIL
• AGREGAT PECAH
AGREGAT
• TERAK DAPUR TINGGI
• ABU
DARI PELAPUKAN BATUAN,
TUMBUHAN DAN BINATANG
AGREGAT/BATUAN
KEMUDIAN MENGALAMI
ENDAPAN
PROSES PELEKATAN DAN
PENEKANAN OLEH ALAM
CONTOH:
BATUAN KAPUR, BATUAN SILIKA/KUARSA, BATU PASIR
AGRGAT/BATUAN BEUK DARI PROSES PENDINGINAN
(VULCANIC ROCK) DAN PEMBEKUAN MAGMA.
1. SYARAT GRADASI
% LOLOS
UKURAN
No. LPA LPB
SARINGAN
MAKA
DIBUTUHKAN PENGGABUNGAN DUA ATAU LEBIH
CAMPURAN MATERIAL UNTUK MASUK SPESIFIKASI
LAPIS PONDASI AGREGAT
(MIX DESIGN LAPIS PONDASI AGREGAT)
JENIS MATERIAL A
LPA/LPB
PEMERIKSAAN
PENGAMBILAN KEPADATAN LAB.
MATERIAL DAN CBR
PEMERIKSAAN SIFAT-SIFAT Y
MATERIAL: GRADASI, ATTER- SPEK?
BERG, ABRASI,
BJ,PENYERAPAN, MATERIAL LAPIS
KADAR LUMPUR DLL N PONDASI AGREGAT:
LPA, LPB
KOMBINASI MATERIAL
SPEK? PEMERIKSAAN
N
KEPADATAN LAB.
DAN CBR
Y
Y
A N
SPEK?
PENGGABUNGAN AGREGAT
PENGGABUNGAN AGREGAT (BLENDING AGGREGATE)
DILAKUKAN DENGAN TUJUAN UNTUK MENDAPATKAN GRADASI
AGREGAT YANG SESUAI DENGAN GRADASI YANG DITENTUKAN
DALAM SPESIFIKASI
CARA ANALITIS
DIMANA:
a+b=1 MAKA a=1–b
P A P-B
b juga, a
B A A-B
CONTOH: TABEL GRADASI AGREGAT A DAN B SERTA SPEC.
GRADASI
AGREGAT A AKAN
DICAMPUR DENGAN
AGREGAT B UNTUK
MEMENUHI
SPESIFIKASI YANG
DITENTUKAN. HASIL
ANALISA SARINGAN
AGREGAT A DAN
AGREGAT B DAN SPEC
GRADASI YANG
DIBERIKAN DISAJIKAN
PADA TABEL DI
SAMPING
PENYELESAIAN:
P A P-B
BERDASARKAN SARINGAN NO. 8 b juga, a
B A A-B
MAKA:
b= ( 42,5 – 3,2 ) / ( 82 – 3,2 ) = 0,50 = 50%
SEHINGGA: a = 1 – 0,50 = 0,50 = 50%
CONTOH:
TENTUKANLAH
PROPORSI AGREGAT
A DAN B DENGAN
CARA GRAFIS BILA
DIRENCANAKAN
KEDUA AGREGAT
AKAN DIGABUNGKAN
DENGAN SPESIFIKASI
YG DIBERIKAN
DARI GRAFIK DI SAMPING DIDAPATKAN:
• PROPORSI AGR. A:
a= (43 +54)/2 = 48,5%= 48%
• PROPORSI AGR. B:
b= 100% - 48%= 52%
PENGGABUNGAN AGREGAT DENGAN CARA MATRIK
A a1 b1 c1 100-P#8
B
a 2 b2 c 2 P#8-P#200
C
a3 b3 c3
P#200
CONTOH 1
TABEL GRADASI AGREGAT A , B DAN C SERTA SPEC. GRADASI
A a1 b1 c1 1.026 -0.028 0.002
B = a2 b2 c2 S-1 = -0.062 1.205 -0.143
C a3 b3 c3 0.022 -0.423 1.402
A 97.6 5 0 A 57.5
B = 2.3 86.2 26 B = 35.5
C 0.1 8.8 74 C 7
%A A
%B = S-1 B
97.6 2.3 0.1 %C C
1/10
S = 0 5 86.2 8.8
0 26 74 A 58.02
0.976 0.023 0.001 B = 38.22
S = 0.05 0.862 0.088 C -3.97
0 0.26 0.74
Ag.Kasar 58.02 58 57 56
Ag.Halus 38.22 38 39 40
Filler -3.97 4 4 4
Ukuran Persen lolos
Saringan Ag.Kasar Ag.Halus Filler Spec Tengah Ag.Gabungan
3/4 in 100 100 100 100 100 100 100 100
1/2 in 85 100 100 80 - 100 90 91.3 91.5 91.6
3/8 in 58 100 100 70 - 90 80 75.6 76.1 76.5
No.4 29 100 100 50 -70 60 58.8 59.5 60.2
No.8 2.4 95 100 35-50 42.5 41.5 42.4 43.3
No.30 0.5 47 100 18 - 29 33.5 22.2 22.6 23.1
No.100 0.3 23 95 8 - 16 12 12.7 12.9 13.2
No.200 0.1 8.8 74 4 - 10 7 6.4 6.4 6.5
CONTOH 2
Ukuran Gradasi agregat Batas Nilai
Saringan A B C Spec Tengah
19.1 100 100 100 100 100
12.7 93.7 100 100 90 -100 95
9.52 50.1 96.8 90.3 75 -80 77.5
6.35 20.5 95.3 87.6
4.76 13.2 93.4 84.5
2.38 4.1 90.7 64.1 50 -72 56
1.18 3.4 86.9 42.6
0.6 2.4 65.1 29.5 35 - 60 47.5
0.074 2 6.5 11.5 6 - 12 9
100
90
80
60 Agregat A
Agregat B (pasir)
50
Agregat C (Abu batu)
40
30
20
10
0
5 .7 51 76 38 19 595 25 149 074
.0 12 9. 4. 2. 1. 0.
19 0. 0. 0.
A 29
B = 35
C 36
A= 0.29 0.35 0.35 0.35
B= 0.35 0.35 0.30 0.36
HRS-WC C= 0.36 0.30 0.35 0.29
Bukaan A B C Batas Spec I II II IV
19.1 100 100 100 100 100.00 100.00 100.00 100.00
12.7 93.7 100 100 90 -100 98.17 97.80 97.80 97.80
9.52 50.1 96.8 90.3 75 -80 80.92 78.51 78.18 78.57
6.35 20.5 95.3 87.6 70.84 66.81 66.43 66.89
4.76 13.2 93.4 84.5 66.94 62.66 62.22 62.75
2.38 4.1 90.7 64.1 50 -72 56.00 52.41 51.08 52.68
1.18 3.4 86.9 42.6 46.71 44.39 42.17 44.83
0.6 2.4 65.1 29.5 35 - 60 34.08 32.48 30.70 32.83
0.074 2 6.5 11.5 6 - 12 7.00 6.43 6.68 10.90
0.6 35 60 32.83
20
0.074 6 12 10.90
0
19.1 12.7 9.52 2.38 0.6 0.074