Rincian BK-PU antara Laporan LEP dengan SAP Proyek Pengadaan SP Seksi 3

Proyek Pengadaan SP Seksi 3


Annual sd Juni 2023

No Rincian LEP SAP Selisih Keterangan


1 2 3 4 5=3-4 6
A. BK
1 Bahan 46.448.925.734 46.448.925.734 -
2 Upah 251.587.929 251.587.929 -
3 Subkon 9.608.223.130 9.608.223.130 -
4 Peralatan 2.429.768.323 2.429.768.323 -
5 Persiapan & Penyelesaian 655.536.788 655.536.788 -
6 Administrasi Proyek 2.721.050.693 2.721.050.693 -
7 Pemasaran -
8 Bank 166.444.482 166.444.482 -
Total 62.281.537.079 62.281.537.079 -

B. PU
1 PU 65.167.280.800 65.167.280.800 -
95,57% 95,57%

Manager Proyek Adkon Keu


Rincian BK-PU antara Laporan LEP dengan SAP Proyek Pengadaan Seksi 3B
Proyek Pengadaan Seksi 3B
Annual sd Juni 2023

No Rincian LEP SAP Selisih Keterangan


1 2 3 4 5=3-4 6
A. BK
1 Bahan 22.455.538.524 22.455.538.524 -
2 Upah 2.175.273.317 2.175.273.317 -
3 Subkon 4.929.482.505 4.929.482.505 -
4 Peralatan 562.264.511 562.264.511 -
5 Persiapan & Penyelesaian 89.116.125 89.116.125 -
6 Administrasi Proyek 393.244.054 393.244.054 -
7 Pemasaran -
8 Bank 695.800 695.800 -
Total 30.605.614.836 30.605.614.836 -

B. PU
1 PU 31.916.640.000 31.916.640.000 -
95,89% 95,89%

Manager Proyek Adkon Keu


Rincian BK-PU antara Laporan LEP dengan SAP Proyek SOP Seksi 3B
Proyek SOP Seksi 3B
Annual sd Juni 2023

No Rincian LEP SAP Selisih Keterangan


1 2 3 4 5=3-4 6
A. BK
1 Bahan 9.496.844.574 9.496.844.574 -
2 Upah 4.596.217.215 4.596.217.215 -
3 Subkon 5.441.226.550 5.441.226.550 -
4 Peralatan 4.207.877.853 4.207.877.853 -
5 Persiapan & Penyelesaian 1.989.670.722 1.989.670.722 -
6 Administrasi Proyek 2.367.087.084 2.367.087.084 -
7 Pemasaran -
8 Bank 510.800 510.800 -
Total 28.099.434.798 28.099.434.798 -

B. PU
1 PU 29.455.353.564 29.455.353.564 -
95,40% 95,40%

Manager Proyek Adkon Keu


Rincian BK-PU antara Laporan LEP dengan SAP Proyek SOP Seksi 3
Proyek SOP Seksi 3
Annual sd Juni 2023

No Rincian LEP SAP Selisih Keterangan


1 2 3 4 5=3-4 6
A. BK
1 Bahan 14.863.187.319 14.863.187.319 -
2 Upah 5.195.138.843 5.195.138.843 -
3 Subkon 9.925.903.810 9.925.903.810 -
4 Peralatan 5.864.395.638 5.864.395.638 -
5 Persiapan & Penyelesaian 743.122.270 743.122.270 -
6 Administrasi Proyek 3.812.457.878 3.812.457.878 -
7 Pemasaran -
8 Bank 635.600 635.600 -
Total 40.404.841.359 40.404.841.359 -

B. PU
1 PU 42.889.875.279 42.889.875.279 -
94,21% 94,21%

Manager Proyek Adkon Keu


Rincian BK-PU antara Laporan LEP dengan SAP Proyek Pengadaan FS SEKSI 3 DAN 3B
Proyek Pengadaan FS SEKSI 3 DAN 3B
Annual sd Juni 2023

No Rincian LEP SAP Selisih Keterangan


1 2 3 4 5=3-4 6
A. BK
1 Bahan 105.549.544.653 105.549.544.653 -
2 Upah 951.022.401 951.022.401 -
3 Subkon 38.357.212.886 38.357.212.886 -
4 Peralatan 6.554.290.201 6.554.290.201 -
5 Persiapan & Penyelesaian 111.111.111 111.111.111 -
6 Administrasi Proyek 2.722.804.907 2.722.804.907 -
7 Pemasaran -
8 Bank 610.812 610.812 -
Total 154.246.596.971 154.246.596.971 -

B. PU
1 PU 164.458.572.470 164.458.572.470 -
93,79% 93,79%

Manager Proyek Adkon Keu


Rincian BK-PU antara Laporan LEP dengan SAP Proyek Pengadaan FS dan SP Seksi 2
Proyek Pengadaan FS dan SP Seksi 2
Annual sd Juni 2023

No Rincian LEP SAP Selisih Keterangan


1 2 3 4 5=3-4 6
A. BK
1 Bahan 12.646.220.112 12.646.220.112 -
2 Upah 192.728.722 192.728.722 -
3 Subkon 3.933.554.614 3.933.554.614 -
4 Peralatan 60.000.000 60.000.000 -
5 Persiapan & Penyelesaian - - -
6 Administrasi Proyek - - -
7 Pemasaran - - -
8 Bank - - -
Total 16.832.503.448 16.832.503.448 -

B. PU
1 PU 19.023.818.800 19.023.818.800 -
88,48% 88,48%

Manager Proyek Adkon Keu


Rincian BK-PU antara Laporan LEP dengan SAP Proyek SOP Seksi 2
Proyek Pengadaan SOP Seksi 2 Proyek
Annual sd Juni 2023

No Rincian LEP SAP Selisih Keterangan


1 2 3 4 5=3-4 6
A. BK
1 Bahan - - -
2 Upah 116.000.000 116.000.000 -
3 Subkon 3.103.721.689 3.103.721.689 -
4 Peralatan - - -
5 Persiapan & Penyelesaian - - -
6 Administrasi Proyek 883.953.124 883.953.124 -
7 Pemasaran - - -
8 Bank - - -
Total 4.103.674.813 4.103.674.813 -

B. PU
1 PU 4.744.400.800 4.744.400.800 -
86,50% 86,50%

Manager Proyek Adkon Keu