DINAS PERTANIAN
Jl. T. Bachtiar Panglima Polem, S.H., Telp. (0651) 92626
KOTA JANTHO
Konsultan Perencana
KOTA JANTHO
ENGINEERING ESTIMATE
Konsultan Perencana
KOTA JANTHO
Konsultan Perencana
KOTA JANTHO
Konsultan Perencana
KOTA JANTHO
BACK UP DATA
Konsultan Perencana
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.00 Ls Lampiran 1.2 14,725,000.00 14,725,000.00
SUB TOTAL (I) 14,725,000.00
JUMLAH HARGA
NO. URAIAN
( Rp. )
Mengetahui/Menyetujui:
PENGGUNA ANGGARAN
DINAS PERTANIAN DAN PERKEBUNAN ACEH
PERTANIAN/PERKEBUNAN
I. BAHAN
1 Pasir Batu ( Sirtu ) - Material Jalan 562.85 M³ 125,000.00 70,356,000.00
2 Alat Bantu 2.85 Set 5,000.00 14,263.53
3 Batu Kali / Batu Belah (Sungai / Gunung ) 4.96 M³ 198,000.00 982,080.00
4 Pasir Pasang 1.26 M³ 185,000.00 232,434.00
5 Semen @ 40 Kg 32.26 Zak 61,400.00 1,980,690.98
6 Pasir Urug 0.20 M³ 75,000.00 15,120.00
7 Pasir Beton / Kerikil 0.71 M³ 185,000.00 130,680.00
8 Batu Pecah 2-3 cm 1.06 M³ 240,000.00 254,296.22
9 Paku Kayu 1.12 Kg 24,000.00 26,880.00
10 Kayu Klas III 0.12 M³ 4,250,000.00 489,090.00
11 Besi Beton Polos 234.04 Kg 14,500.00 3,393,625.36
12 Kawat Beton 2.34 Kg 22,000.00 51,489.49
Sub Total (Bahan) 77,926,649.58
(A) JUMLAH 77,926,649.58
(B) PPN = 10 % x (A) 7,792,664.96
(C) TOTAL = (A) + (B) 85,719,314.53
II. PERALATAN
8 Dump Truck 3-4 M3 112.73 Jam 295,737.31 33,337,006.71
10 Excavator 80 - 140 Hp 19.82 Jam 353,397.17 7,003,867.28
1 Motor Grader > 100 Hp 23.57 Jam 521,283.75 12,286,657.99
2 Tandem Roller 6 - 10 T 12.79 Jam 221,588.46 2,834,559.61
5 Concrete Vibrator 1.18 Jam 22,517.06 26,509.27
3 Truck Tangki Air 115 Hp 12.79 Jam 267,554.43 3,422,556.20
4 Pump Water / Concrete Pump 1.46 Jam 26,909.12 39,365.87
Sub Total (Peralatan) 58,988,350.16
(D) JUMLAH 58,988,350.16
(E) PPN = 10 % x (D) 5,898,835.02
(F) TOTAL = (D) + (E) 64,887,185.17
III. UPAH PEKERJA
1 Buruh lapangan tak terlatih 39.77 OH 89,000.00 3,539,471.30
3 Buruh lapangan terlatih 2.09 OH 89,500.00 187,480.24
2 Kepala tukang 1.60 OH 130,000.00 207,669.73
3 Mandor lapangan 7.17 OH 112,800.00 808,975.87
4 Operator terampil 8.98 OH 165,900.00 1,489,450.20
5 Pembantu operator 8.98 OH 89,000.00 799,042.00
6 Supir 4.26 OH 118,700.00 506,136.80
7 Tukang 2.52 OH 101,000.00 254,907.07
Sub Total (Upah Pekerja) 7,793,133.21
(G) JUMLAH 7,793,133.21
(H) PPN = 0 % x (G) 779,313.32
(I) TOTAL = (G) + (H) 8,572,446.53
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME
(Rp.) (Rp.)
Mengetahui/Menyetujui:
PENGGUNA ANGGARAN
DINAS PERTANIAN DAN PERKEBUNAN ACEH
RUAS I
1 0 + 000 4.00
50 200.00
2 0 + 050 4.00
50 200.00
3 0 + 100 4.00
50 200.00
4 0 + 150 4.00
50 200.00
5 0 + 200 4.00
50 200.00
6 0 + 250 4.00
20 80.00
7 0 + 270 4.00
TEBAL LUAS
PANJANG LEBAR VOLUME
NO. STA KET
M1 M1 M2 M1 M3
1 2 3 4 5 6 7 8
RUAS I
1 0 + 000 0.32 3.00
50 16.00 48.00
2 0 + 050 0.32 3.00
50 16.00 48.00
3 0 + 100 0.32 3.00
50 16.00 48.00
4 0 + 150 0.32 3.00
50 16.00 48.00
5 0 + 200 0.32 3.00
50 16.00 48.00
6 0 + 250 0.32 3.00
50 16.00 48.00
7 0 + 300 0.32 3.00
50 16.00 48.00
8 0 + 350 0.32 3.00
50 16.00 48.00
9 0 + 400 0.32 3.00
50 16.00 48.00
10 0 + 450 0.32 3.00
50 16.00 48.00
11 0 + 500 0.32 3.00
33 10.56 31.68
12 0 + 533 0.32 3.00
NO PEKERJAAN PERHITUNGAN
REKAPITULASI PERHITUNGAN
1 Galian Tanah Biasa (MP) 2.24 M³
2 Pasir Urug 0.17 M³
3 Pasangan Batu Gunung/Kali 1 : 4 4.96 M³
4 Plesteran 1 : 4 Tebal 1,0 cm 6.00 M2
5 Beton Cor (Lantai Saluran) 0.25 M³
6 Beton Cor Plat Lantai t = 20 cm 1.20 M³
7 Bekisting Plat Beton 5.60 M2
8 Pembesian Plat Lantai 212.77 Kg
SKET GAMBAR
TABEL PERHITUNGAN VOLUME PEKERJAAN
NO PERHITUNGAN
REKAPITULASI PERHITUNGAN
- BERAT TOTAL TULANGAN 212.766 KG
DAFTAR HARGA
UPAH DAN TENAGA KERJA
UPAH
1 Buruh lapangan tak terlatih Orang/ Hari L-101 89,000.00
2 Buruh lapangan kurang terlatih Orang/ Hari L-103 89,250.00
3 Buruh lapangan terlatih Orang/ Hari L-106 89,500.00
4 Kepala tukang Orang/ Hari L-073 130,000.00
5 Mandor lapangan Orang/ Hari L-061 112,800.00
6 Mekanik Orang/ Hari L-071 167,000.00
7 Operator terampil Orang/ Hari L-081 165,900.00
8 Operator kurang terampil Orang/ Hari L-082 141,000.00
9 Pekerja Orang/ Hari - 90,000.00
10 Pembantu mekanik Orang/ Hari - 89,000.00
11 Pembantu operator Orang/ Hari L-083 89,000.00
12 Pembantu supir Orang/ Hari L-099 89,000.00
13 Supir Orang/ Hari L-091 118,700.00
14 Supir personil Orang/ Hari L-092 118,700.00
15 Tukang Orang/ Hari L-079 101,000.00
DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA
BIAYA SEWA ALAT
HARGA ALAT
NO PERALATAN KODE KET.
Rp. 000 ( Rp. )
1 ASPHALT MIXING PLANT E - 155 2,600,000.00 1,808,248.80
2 ASPHALT FINISHER E - 157 550,000.00 271,473.04
3 ASPHALT SPRAYER E - 154 145,000.00 71,745.21
4 BULLDOZER 100-150 HP E - 001 1,350,000.00 538,709.62
5 COMPRESSOR AIR 210 m3/h E - 301 98,000.00 200,432.80
6 CONCRETE MIXER 0.3 -0.6 M3 E - 252 45,000.00 78,410.71
7 SCREENING PLANT E - 040 150,000.00 115,802.90
8 DUMP TRUCK 3-4 M3 E - 211 325,000.00 295,737.31
9 DUMP TRUCK E - 212 535,000.00 398,229.78
10 EXCAVATOR 80 - 140 HP E - 100 790,000.00 353,397.17
11 FLAT BED TRUCK 3 - 4 M3 E - 221 175,000.00 262,465.69
12 GENERATOR SET 125 KVA - 150,000.00 493,408.69
13 MOTOR GRADER > 100 HP E - 010 1,400,000.00 521,283.75
14 TRACK LOADER 75 - 100 HP E - 053 700,000.00 385,687.55
15 WHEEL LOADER 1.0 - 1,6 M3 E - 052 950,000.00 445,551.50
16 THREE WHEEL ROLLER 6 - 8 T E - 080 350,000.00 199,841.68
17 TANDEM ROLLER 6 - 10 T E - 081 500,000.00 221,588.46
18 TIRE ROLLER 8 - 10 T E - 084 396,100.00 235,687.55
19 VIBRATORY ROLLER 5 - 8 T E - 082 650,000.00 322,994.10
20 CONCRETE VIBRATOR E - 089 21,120.00 22,517.06
21 STONE CRUSHER E - 031 700,000.00 652,475.20
22 WATER PUMP E - 341 24,000.00 26,909.12
23 TRUCK TANGKI AIR 115 HP E - 182 200,000.00 267,554.43
24 PEDESTRIAN ROLLER 1 T E - 087 77,000.00 49,956.87
25 TAMPER VIB PLATE E - 088 29,150.00 27,346.90
26 PUMP WATER / CONCRETE PUMP E - 341 176,000.00 26,909.12
27 TRAILER, TRONTON E - 019 276,000.00 153,049.45
28 CONCRETE MIXER 125 Ltr E - 251 25,000.00 32,130.57
29 CONCRETE MIXER 250 Ltr E - 253 40,000.00 78,410.71
DAFTAR HARGA BAHAN / MATERIAL
UNTUK JALAN USAHA TANI DAN JARINGAN IRIGASI
DINAS PERTANIAN DAN PERKEBUNAN ACEH
1 Asphalt Kg 15,550
2 Atap Seng Metal M2 85,836
3 Alat Bantu Set M-170 5,000
4 Baja Profil Kg 36,000
5 Bak Cuci Piring Stainless Buah 373,200
6 Bak Cuci Tangan / Wastafel Keramik Buah 600,000
7 Bak Mandi Acrylic Buah 2,400,000
8 Bak Mandi Fibre Buah 400,000
9 Bambu Batang 7,500
10 Bataco Buah 6,000
11 Batang Kelapa Btg 300,000
12 Batu ( < 250 ) Kg - Material Breakwater M3 275,000
13 0 0 -
14 0 0 -
15 Batu Bata Buah 850
16 Batu Kali / Batu Belah (Sungai / Gunung ) M3 M-010 198,000
17 Batu Pakhlag ( Batu 5-7 cm ) M3 205,000
18 Batu Pecah 2-3 cm M3 M-024 240,000
19 Batu Tempel M3 275,000
20 Baut Kap Ø 1/2 - 8 Buah 5,500
21 Bed Matress (Terrafix) M3 130,620
22 Besi Beton Polos Kg M-167 14,500
23 Besi Beton Ulir Kg 20,000
24 Besi Bout ( Kuda-Kuda ) 5/8 - 10 " Buah 9,952
25 Beton Rooster / Kerawang Buah 12,000
26 Bitumen Geomembran Type ES. I (3,5MM) M² 348,320
27 Bubungan Genteng M' 47,000
28 Bubungan Seng M' 12,500
29 Cat Kayu Dasar Kg 47,500
30 Cat Kayu Mengkilat Kg 67,000
31 Cat Marka Jalan ( Non Thermoplast ) Kg 66,500
32 Cat Menie Besi Kg 47,000
33 Cat Tembok Kg 80,000
34 Dempul Kayu Kg 21,000
35 Engsel Jendela Pasang 28,000
36 Engsel Pintu Pasang 35,000
37 Espagnolet Buah 20,000
38 Filler Kg 17,000
39 Floor Drain Buah 35,000
40 Gebalan Rumput M² 32,344
41 Genteng Beton Keping 31,100
42 Genteng Keramik Keping 26,000
43 Geosand Bag (2.4 m x 1.45 m) bag 701,616
44 Geotekstil Non Woven M² 58,500
45 Geotekstil Non Woven Type - A M² 46,100
46 Geotekstil Non Woven Type - B M² 52,200
47 Geotube (P + 20 m, T + 1.5 m, L + 1.8 m) tube 100,764,000
48 Gipsum ( 120 x 240 cm ) Tebal 1,2 cm Lbr 99,520
49 Granite 60 x 60 M² 248,800
NO JENIS PEKERJA/KEAHLIAN SATUAN KODE HARGA (Rp)
156 Pipa HDPE SDR 17 (PN 10) Dia. 100 mm 4 Inchi M' 177,908
157 Pipa HDPE SDR 17 (PN 10) Dia. 150 mm 6 Inchi M' 371,412
158 Pipa HDPE SDR 17 (PN 10) Dia. 200 mm 8 Inchi M' 580,048
159 Pipa HDPE SDR 17 (PN 10) Dia. 250 mm 10 Inchi M' 901,717
160 Pipa HDPE SDR 17 (PN 10) Dia. 300 mm 12 Inchi M' 1,434,311
161 Pipa HDPE SDR 17 (PN 10) Dia. 350 mm 14 Inchi M' 1,944,201
162 Pipa HDPE SDR 17 (PN 10) Dia. 400 mm 16 Inchi M' 2,462,360
163 Pipa HDPE SDR 17 (PN 10) Dia. 450 mm 18 Inchi M' 3,121,868
164 Pipa HDPE SDR 17 (PN 10) Dia. 500 mm 20 Inchi M' 3,998,468
165 Pipa HDPE SDR 17 (PN 10) Dia. 600 mm 24 Inchi M' 6,304,922
166 Pipa Leiding Ø 1/2 " Galvanis Tebal 3,2 mm Batang 153,000
167 Pipa Leiding Ø 11/2 " Galvanis Tebal 3,2 mm Batang 311,000
168 Pipa Leiding Ø 2 " Galvanis Tebal 3,2 mm Batang 398,080
169 Pipa Leiding Ø 3" Galvanis Tebal 3,2 mm Batang 204,000
170 Pipa Leiding Ø 4 " Galvanis Tebal 3,2 mm Batang 283,000
171 Pipa Leiding Ø 6" Galvanis Tebal 3,2 mm Batang 1,020,080
172 Pipa Leiding Ø 1 " Galvanis Tebal 3,2 mm Batang 248,800
173 Pipa PVC Ø 1 " Batang 65,000
174 Pipa PVC Ø 1/2 " Kualitas AWE (United) Batang 38,000
175 Pipa PVC Ø 11/2 " Batang 90,000
176 Pipa PVC Ø 2 " Batang 130,000
177 Pipa PVC Ø 3/4 " Batang 48,000
178 Pipa PVC Ø 3 " Batang 190,000
179 Pipa PVC Ø 4 " Batang 285,000
180 Pipa PVC RRJ, S-10 Dia. 50 mm M' 45,738
181 Pipa PVC RRJ, S-10 Dia. 75 mm M' 94,501
182 Pipa PVC RRJ, S-10 Dia. 100 mm M' 141,671
183 Pipa PVC RRJ, S-10 Dia. 150 mm M' 300,015
184 Pipa PVC RRJ, S-10 Dia. 200 mm M' 489,888
185 Pipa PVC RRJ, S-10 Dia. 250 mm M' 791,884
186 Pipa PVC RRJ, S-10 Dia. 300 mm M' 1,201,958
187 Pipa PVC RRJ, S-10 Dia. 350 mm M' 1,797,860
188 Pipa PVC RRJ, S-10 Dia. 400 mm M' 2,314,026
189 Pipa PVC RRJ, S-12,5 Dia. 50 mm M' 36,000
190 Pipa PVC RRJ, S-12,5 Dia. 75 mm M' 71,000
191 Pipa PVC RRJ, S-12,5 Dia. 100 mm M' 105,000
192 Pipa PVC RRJ, S-12,5 Dia. 150 mm M' 216,000
193 Pipa PVC RRJ, S-12,5 Dia. 200 mm M' 400,000
194 Pipa PVC RRJ, S-12,5 Dia. 250 mm M' 650,000
195 Pipa PVC RRJ, S-12,5 Dia. 300 mm M' 1,100,000
196 Pipa PVC RRJ, S-12,5 Dia. 350 mm M' 1,462,743
197 Pipa PVC RRJ, S-12,5 Dia. 400 mm M' 1,875,675
198 Plint Keramik 15 x 30 Buah 19,750
199 Bensin / Pertalite Liter 8,556
200 Residu Kg 21,500
201 Semen @ 40 Kg Zak M-080 61,400
202 Semen @ 50 Kg Zak 75,000
203 Semen Putih @ 50 Kg Zak 230,000
204 Seng BJLS 0,20 Lbr 72,000
205 Seng BJLS 0,20 Cat Pabrik Lbr 87,000
206 Seng Gelombang BJLS 30 M2 97,000
207 Seng Gelombang BJLS 30 Cat Pabrik M2 110,000
208 Seng Plat BJLS 20 M2 66,000
NO JENIS PEKERJA/KEAHLIAN SATUAN KODE HARGA (Rp)
A. Sewa Tanah M2 - - -
B. PERALATAN
Periksa lembar 1.2-2 Ls - 7,650,000.00
E. MOBILISASI LAINNYA
E.1 PEKERJAAN DARURAT
1 Perkuatan Jembatan Lama Ls
2 Pemeliharaan Jalan Kerja / Samping Ls
3 -
E.II. LAIN-LAIN
1 Pengukuran/Pemasangan Profil Pkt 1.00 1,380,000.00 1,380,000.00
2 Papan Nama Proyek Buah 1.00 400,000.00 400,000.00
3 Cetak Batu Prasasti Unit 1.00 500,000.00 500,000.00
4 Administrasi dan Dokumentasi Paket 1.00 2,500,000.00 2,500,000.00
Catatan : Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasuk over-head dan laba
serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.
ANALISA HARGA LUMP SUM UNTUK MOBILISASI
B. PERALATAN
URAIAN : ANGGAPAN/ASUMSI :
1 Penggadaan bahan oleh leveransir 1. Kelompok tukang kayu memasang 20 m2 dalam 1 hari kerja
2 Tukang kayu memotong dan membuat acuan / 2. 1/2 material dapat dipakai kembali
perancah 3. Penggadaan bahan oleh leveransir
3 Tukang kayu membongkar acuan/perancah setelah 4. Untuk 1 m3 beton digunakan 20 lbr playwood uk.: 120cm x 240cm x 1,75cm
disetujui oleh direksi 5. Tukang kayu membongkar perancah
MATERIAL 1,845,550
HARI JAM HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KODE
KERJA KERJA (Rp/Jam) (Rp.) (Rp.)
P
E
R
A
L
A
T
A
N
PERALATAN
JUMLAH (Rp.) 2,712,550
URAIAN : ANGGAPAN/ASUMSI :
1 Pemotongan dan pembengkokan dan perakitan 1. 200 kg tulangan jadi disiapkan dalam 1 hari
tulangan dilakukan ditempat pekerjaan bersama-sama 2. Besi untuk tulangan dikirim ke tempat pekerjaan oleh leveransir
persiapan pekerjaan beton 3. Batang-batang tulangan dibengkok ditempat pekerjaan
4. Penyusutan tulangan dihitung 10% dan pemakaian kawat baja dihitung 1%
MATERIAL 3,239,000
HARI JAM HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KODE
KERJA KERJA (Rp/Jam) (Rp.) (Rp.)
P
E
R
A
L
A
T
A
N
PERALATAN
JUMLAH (Rp.) 3,720,300
URAIAN : ANGGAPAN/ASUMSI :
1 Pemasok mengirim material 1. Bahan-bahan dasar dikirim kelokasi pekerjaan oleh pemasok
2 Acuan dan tulangan besi beton dipasang 2. Dipakai agregat pecah dan tersaring yang termurah
3 Beton diaduk dilokasi pekerjaan 3. Dicor 6,17 m3/hari dengan 54 adukan/6 jam/hari
4 Beton dicor dan digetar sampai padat 4. Adukan 1 Pc:2Ps:3Kr (Yaitu 1:5):semen:350 Kg/m3:air:160Kg/m3:2487Kg
5. Anggap tiap adukan membutuhkan 1 zak (27,8 liter lepas) semen portland
55,6 liter pasir:83,3 liter kerikil dan 18,3 liter air
6. Tidak termasuk acuan dan tulangan besi beton yang sudah dipasang
7. Beton bertulang dipakai untuk pilar, gorong-gorong, dinding penahan dll
8. Sesuai Peraturan beton bertulang Indonesia (PBI 1971 NI.2)
1
1. Depresiasi : 0,9 x Harga Alat x (CRF) x Jam/Thn
1
1. Depresiasi : 0,9 x Harga Alat x (CRF) x Jam/Thn
1
1. Depresiasi : 0,9 x Harga Alat x (CRF) x Jam/Thn
1
1. Depresiasi : 0,9 x Harga Alat x (CRF) x Jam/Thn
1
1. Depresiasi : 0,9 x Harga Alat x (CRF) x Jam/Thn
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Berat volume tanah (lepas) D 1.60 ton/m3 1.40 - 1.80
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.50 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.83
Faktor konversi , kedalaman < 40 % Fv 0.90 Faktor konversi
Waktu siklus Ts1 menit dihapus, masuk
- Menggali , memuat T1 0.320 menit dalam waktu siklus
- Lain lain T2 0.100 menit disesuaikam
Waktu siklus = T1 x Fv Ts1 0.42 menit
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 49.40 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 345.83 M3
Kebutuhan tenaga :
- Pekerja P 0.00 orang
- Mandor M 0.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0000 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0000 Jam
Rp. 0.00 / M3