Anda di halaman 1dari 5

PROGRESS

PEKERJAAN CUT AND FILL, PEMBENTUKAN BADAN JALAN DAN PARIT LAHAN TAHAP 4 WAREHOUSE
Jl. Pancing Psr. V Barat - Medan Estate

Kontrak : 23 Juli 2022 s/d 23 September 2022 Minggu Ke : 7

PROGRESS
Bobot
Periode Lalu Periode Ini Akumulasi
No. URAIAN PEKERJAAN Vol Sat Total
Prestasi Bobot Prestasi Bobot Prestasi Bobot
(%) (%) (%) (%) (%) (%) (%)
A CUT AND FILL
1 Mobilisasi / Demobilisasi Dozer 1.00 ls 0.251 50% 0.126 0% - 50% 0.126
2 Mobilisasi / Demobilisasi Excavator 1.00 ls 0.251 50% 0.126 0% - 50% 0.126
3 Mobilisasi / Demobilisasi Bomak 1.00 ls 0.251 0% - 0% - 0% -
Sub total A 0.754 0.251 - 0.251
B CUT AND FILL DIPADATKAN
1 Cut and fill dipadatkan 4,966.69 m3 22.259 47% 10.462 3% 0.668 50% 11.130
Sub total B 22.259 10.462 0.668 11.130
C PERKERASAN JALAN
1 Timbunan sirtu 2 layer 4,082.01 m3 75.230 0% - 0% - 0% -
Sub total C 75.230 - - -
D GALIAN PARIT SEMENTARA
1 Galian parit sementara 466.00 m1 1.757 0% - 0% - 0% -
Sub total D 1.757 - - -
100.00 10.71 0.67 11.38
Rencana 77.78
Deviasi - 66.40

Medan, 03 September 2022


Dibuat oleh,

Mhd. Faisal
FOTO DOKUMENTASI

TAMPAK DEPAN ROW 30 MTR

TAMPAK DEPAN ARAH BLOK J

TAMPAK DEPAN ARAH BLOK H & K


FOTO DOKUMENTASI

TAMPAK DEPAN ROW 24 MTR

TAMPAK DEPAN ARAH BLOK L

TAMPAK DEPAN ARAH BLOK M

Anda mungkin juga menyukai