138712271 40

350000000

350000000 85267541 24.3621545714286


91143559 26.0410168571429
Waktu
Harga Satuan Metode
No Paket Pengadaan Uraian Volume Satuan
(Rp)
Jumlah Biaya (Rp)
Pengadaan Pelaksaan
Pengadaan

1 2 3 4 5 6 7 8 9

1 Informasi dan Publikasi Poster 30 Lbr 10,000 300,000 Langsung 3 Hari


Baliho 2 Lbr 250,000 500,000 Langsung 3 Hari
Spanduk 2 Lbr 250,000 500,000 Langsung 3 Hari

2 Pekerjaan Bangunan Tower Semen Portland 232.6 Zak 65,000 15,119,000 Langsung 3 Hari
Besi polos dia. 16 mm SNI 15.80 Btg 150,000 2,370,250 Langsung 3 Hari
Besi polos dia. 12 mm SNI 98.06 Btg 80,000 7,844,480 Langsung 4 Hari
Besi polos dia. 8 mm SNI 91.16 Btg 40,000 3,646,292 Langsung 5 Hari
Kawat Ikat 71.77 Kg 20,000 1,435,400 Langsung 3 Hari
Paku 2-3 Inchi 52.30 Kg 15,000 784,440 Langsung 1 Hari
Minyak Bekisting 30.78 Liter 10,000 307,794 Langsung 1 Hari
Plywood tebal 9 mm 12.64 Lbr 135,000 1,706,872 Langsung 1 Hari
Bata Merah 2223.48 Bh 900 2,001,132 Langsung 1 Hari
Lamir 13.26 Kg 50,000 663,000 Langsung 1 Hari
Cat Dasar 13.26 Kg 75,000 994,500 Langsung 1 Hari
Cat Penutup Setara Vinelek 34.47 Kg 45,000 1,551,150 Langsung 1 Hari
Pipa GI Ø 3" Medium A 1.00 m 175,000 175,000 Langsung 1 Hari
Pipa GI Ø 1 1/2" Medium A 3.00 m 135,000 405,000 Langsung 1 Hari
Baut Flange 12.00 bh 10,000 120,000 Langsung 1 Hari
Box Kontrol 60x60 1.00 unit 150,000 150,000 Langsung 1 Hari
Double Niple GI Ø 1 1/2" 2.00 bh 20,000 40,000 Langsung 1 Hari
Flange Las Ø 3" 1.00 bh 50,000 50,000 Langsung 1 Hari
Flange Spigot Ø 3" 1.00 bh 90,000 90,000 Langsung 1 Hari
Gate Valve GI Ø 3" 1.00 bh 300,000 300,000 Langsung 1 Hari
Knee GI Ø 1 1/2" 7.00 bh 18,000 126,000 Langsung 1 Hari
Knee GI Ø 3" 3 bh 25,000 75,000 Langsung 1 Hari
Manhole 60 x 60 Cm 1.00 bh 50,000 50,000 Langsung 1 Hari
Packing Karet Ø 3" 2 bh 15,000 30,000 Langsung 1 Hari
Stop Kran GI Ø 1 1/2" 1.00 bh 185,000 185,000 Langsung 1 Hari
Tee GI Ø 1 1/2 1 bh 24,000 24,000 Langsung 1 Hari
Watermoor GI Ø 1 1/2 2.00 bh 30,000 60,000 Langsung 1 Hari
Plat Penutup Main Hole 80x80 CM t=8MM 1 set 300,000 300,000 Langsung 1 Hari
Klep Pelampung p=75 CM 1.00 set 100,000 100,000 Langsung 1 Hari
Lampu Philipsh sl 25 watt 2 set 30,000 60,000 Langsung 1 Hari
Tangga Besi 657x50 CM 1.00 bh 750,000 750,000 Langsung 1 Hari
Gembok + Engsel 2 set 30,000 60,000 Langsung 1 Hari
Engsel Pintu 4" 1.0 psg 50,000 50,000 Langsung 1 Hari
Engsel Jendela 3" 2.0 psg 30,000 60,000 Langsung 1 Hari
Daun Pintu 80X210CM 1.0 set 500,000 500,000 Langsung 1 Hari
Daun Jendela Kaca 50X152CM 2.0 set 350,000 700,000 Langsung 1 Hari
Grendel jendela 2.0 set 20,000 40,000 Langsung 1 Hari
Handle Jendela 2.0 set 20,000 40,000 Langsung 1 Hari
Hak Angin 2.0 psg 10,000 20,000 Langsung 1 Hari
Kunci Pintu 1.0 set 75,000 75,000 Langsung 1 Hari
Kusen Pintu 92X210CM 1.0 bh 200,000 200,000 Langsung 1 Hari
Kusen Jendela 56X158CM 2.0 set 300,000 600,000 Langsung 1 Hari
stop Kontak dan cok 1.0 set 20,000 20,000 Langsung 1 Hari
Kabel Serabut 20.0 m 10,000 200,000 Langsung 1 Hari
Helm 10.0 bh 75,000 750,000 Langsung 1 Hari
Rompi 10.0 bh 25,000 250,000 Langsung 1 Hari
Sarung tangan 10.0 bh 145,000 1,450,000 Langsung 1 Hari
Sepatu 13.0 bh 5,000 65,000 Langsung 1 Hari
Peralatan P3k 1.0 bh 50,000 50,000 Langsung 1 Hari

2 Pekerjaan Sumur Bor Pekerjaan Geo Listrik 1 Kali 5,000,000 5,000,000 Langsung 3 Hari
Mobilisasi/demobilisasi Drilling dan Peralatan
Pengeboran 1 LS 2,660,000 2,660,000 Langsung 1 hari
Pengadaan Kotak Contoh 1 unit 388,991 388,991 Langsung 1 Hari
Pengeboran cesing conduktor 14" dari 0 m'
s/d 18m' 12 m 1,852,800 22,233,600 Langsung 7 Hari
m Langsung
Pengeboran Pilot Hole Ø 6" Dari Kedalaman 0
M s/d 50 M 50 m 254,786 12,739,286 Langsung 7 Hari
Pengeboran Pilot Hole Ø 6" Dari Kedalaman 50
M s/d 80 M 30 m 286,200 8,586,000 Langsung 7 Hari

Pembesaran Lubang Bor/Reaming Ø 9" dari 0


m' s/d 80 m' Dari Kedalaman 0 M s/d 50 M 32 m 230,500 7,376,000 Langsung 7 Hari
Pembesaran Lubang Bor/Reaming Ø 9" dari 0
m' s/d 80 m' Dari Kedalaman 50 M s/d 80 M 30 m 223,350 6,700,500 Langsung 7 Hari
Pipa Jombang PCV Ø 6 " Wavin AW 30 M 320,763 9,622,890 Langsung 10 Hari
Pipa Jombang PCV Ø 4" Wavin AW 38 M 174,096 6,615,648 Langsung 10 Hari
Pipa Screen PCV Ø 4" 12 M 545,863 6,550,356 Langsung 10 Hari
Pipa PVC AW Ø 1" 50 M 47,350 2,367,500 Langsung 10 Hari
Elbow + aksesoris PVC Ø 1" 10 BH 33,450 334,500 Langsung 1 Hari
Lem pipa PVC 1 kg 55,000 55,000 Langsung 1 Hari
Bottom Cup 1 BH 125,000 125,000 Langsung 1 Hari
Kerikil Pembalut 4 M3 705,000 2,820,000 Langsung 1 Hari
Lempung Pembalut 4 zak 194,000 776,000 Langsung 1 Hari
Beton Lantai Sumur 1 M3 325,000 325,000 Langsung 1 Hari
Penutup Sumur (Flange) 1 Psg 100,000 100,000 Langsung 1 Hari
Grouting Cement/mortar 2 M3 2,100,000 4,200,000 Langsung 1 Hari
Water Jetting 1 Unit 1,391,000 1,391,000 Langsung 1 Hari
Air Lift 1 Unit 1,680,000 1,680,000 Langsung 1 Hari
Pemompaan Uji, termaksud steep draw test
long periode test, recovery 24 Jam 190,000 4,560,000 Langsung 1 Hari
Pompa Submersible deep weel 1 unit 19,000,000 19,000,000 Langsung 10 Hari
Panel Kontrol (Double WLC, Contactor+OLR,
Electroda) 1 unit 5,000,000 5,000,000 Langsung 3 Hari
Stabilizer Kapasitas3000 Watt 1 unit 2,000,000 2,000,000 Langsung 3 Hari
Kabel NYYHY 3 x 1,5 20 m' 12,000 240,000 Langsung 3 Hari
Penyambungan Daya PLN 2200 Va 1 unit 4,000,000 4,000,000 Langsung 3 Hari
Helmet 5 Bh 75,000 375,000 Langsung 1 Hari
Rompi 6 Bh 25,000 150,000 Langsung 1 Hari
Sepatu 5 Bh 145,000 725,000 Langsung 1 Hari
Papan Informasi 4 Bh 5,000 20,000 Langsung 1 Hari
Peralatan P3K 1 Bh 50,000 50,000 Langsung 1 Hari

Jasa Pemasangan Pipa dan


3 Asesoris (Distribusi) Pembersihan Lapangan 27.94185 m2 10,000 279,419 Langsung 3 Hari
Galian tanah 126.9 m3 75,000 9,517,500 Langsung 2 Hari
Urugan Kembali Tanah Galian 122.3163 m3 50,000 6,115,815 Langsung 1 hari
Angkut Pipa PVC Ø 3" SNI S12,5 390 M 16,000 6,240,000 Langsung 1 Hari
Angkut Pipa PVC Ø 1" SNI S12,5 666 M 7,000 4,662,000 Langsung 1 Hari
Angkut Pipa PVC Ø 1/2" SNI S12,5 60 M 3,000 180,000 Langsung 1 Hari

Pipa dan Asesoris (untuk


4 distribusi) Pipa PVC Ø 3" SNI S12,5 390 m' 43,000 16,770,000 Langsung 10 Hari
Pipa PVC Ø 1" SNI S12,5 666 m' 25,000 16650000 Langsung 10 Hari
Pipa PVC Ø 1/2" SNI S12,5 60 m' 12,500 750000 Langsung 10 Hari
Gate Valve dia. 1" 4 Bh 40,000 160,000 Langsung 1 Hari
Flange Socket dia. 1" 8 Bh 125,000 1,000,000 Langsung 1 Hari
Bend All Socket dia. 1" x 90° 6 Bh 55,000 330,000 Langsung 1 Hari
Bend All Socket dia. 3" x 90° 6 Bh 135,000 810,000 Langsung 1 Hari
Tee All Socket dia. 1" x 1" 4 Bh 60,000 240,000 Langsung 1 Hari
Tee All Socket dia. 3" x 1" 4 Bh 270,000 1,080,000 Langsung 1 Hari
Tee All Socket dia. 3" x 3" 2 Bh 425,000 850,000 Langsung 1 Hari
Dop PVC dia. 1" 8 Bh 70,000 560,000 Langsung 1 Hari
Dop PVC dia. 3" 3 Bh 210,000 630,000 Langsung 1 Hari
Pipa Selubung Street Box 4 Bh 150,000 600,000 Langsung 1 Hari
Street Box 4 Bh 500,000 2,000,000 Langsung 1 Hari
Baut 16 Bh 5,000 80,000 Langsung 1 Hari
Paking 0 m2 250,000 21,025 Langsung 1 Hari
Sock Drat dia. 1/2" 50 Bh 7,000 350,000 Langsung 1 Hari
Hand Kran dia.1/2" 50 Bh 25,000 1,250,000 Langsung 1 Hari
Lem Pipa (400 gr) 1 Bh 50,000 50,000 Langsung 1 Hari
Helmet 10 Bh 75,000 750,000 Langsung 1 Hari
Rompi 10 Bh 25,000 250,000 Langsung 1 Hari
Sepatu 10 Bh 145,000 1,450,000 Langsung 1 Hari
Sarung Tangan 10 Bh 5,000 50,000 Langsung 1 Hari
Papan Informasi 1 Bh 100,000 100,000 Langsung 1 Hari
Peralatan P3K 1 Pkt 50,000 50,000 Langsung 1 Hari