Anda di halaman 1dari 1

ANALISA HARGA SATUAN PEKERJAAN

A. PEKERJAAN PERSIAPAN, K3, DAN ALAT BERAT

KEGIAT AN : KANTOR PERTANAHAN KOTA BATU PROPINSI JAWA TIMUR


PEKERJAAN : PERENCANAAN PEMBANGUNAN GEDUNG ARSIP
LOKASI : JL. MAWAR No 12 KOTA BATU
TAHUN ANGGARAN : 2023

A ANALISA BIAYA KONSTRUKSI PEKERJAAN PERSIAPAN, K3, DAN ALAT BERAT


A.1 PEKERJAAN PERSIAPAN

A.1.1 1M² MEMBERSIHKAN SITE AWAL DAN AKHIR PEKERJAAN


0,05000 OH Pekerja @ Rp, 122.000,00 = Rp, 6.100,00 100,00% Rp, 6.100,00
0,02500 OH Mandor @ Rp, 150.000,00 = Rp, 3.750,00 100,00% Rp, 3.750,00
Jumlah 1 = Rp, 9.850,00 Rp, 9.850,00
12,5% Keuntungan & Overhead = Rp, 1.231,25 Rp, 1.231,25
Total = Rp, 11.081,25 100,00 Rp, 11.081,25

A.1.3 1M¹ PEKERJAAN PENGUKURAN DAN PEMASANGAN BOWPLANK


a. Bahan
0,01300 m3 Kayu Balok Kelas III @ Rp, 2.800.000,00 = Rp, 36.400,00 100,00% Rp, 36.400,00
0,02000 kg Paku 2"- 5" @ Rp, 25.000,00 = Rp, 500,00 31,65% Rp, 158,25
0,00700 m3 Kayu Papan Kelas III @ Rp, 2.800.000,00 = Rp, 19.600,00 100,00% Rp, 19.600,00
Jumlah 1 = Rp, 56.500,00 Rp, 56.158,25
Rp,
b. Tenaga Rp,
0,12000 OH Pekerja @ Rp, 122.000,00 = Rp, 14.640,00 100,00% Rp, 14.640,00
0,00600 OH Tukang Kayu @ Rp, 135.000,00 = Rp, 810,00 100,00% Rp, 810,00
0,00060 OH Kepala Tukang @ Rp, 140.000,00 = Rp, 84,00 100,00% Rp, 84,00
0,00120 OH Mandor @ Rp, 150.000,00 = Rp, 180,00 100,00% Rp, 180,00
Jumlah 2 = Rp, 15.714,00 Rp, 15.714,00
Jumlah1+ 2 = Rp, 72.214,00 Rp, 71.872,25
12,5% Keuntungan & Overhead = Rp, 9.026,75 Rp, 8.984,03
Total = Rp, 81.240,75 99,53 Rp, 80.856,28

A.1.4 1M³ PEMBUANGAN BEKAS BONGKARAN KE LUAR LOKASI PEKERJAAN (TERMASUK LANGSIR 100M DARI LOKASI)
0,60000 OH Pekerja @ Rp, 122.000,00 = Rp, 73.200,00 100,00% Rp, 73.200,00
0,03000 OH Mandor @ Rp, 150.000,00 = Rp, 4.500,00 100,00% Rp, 4.500,00
Ongkos Angkut/M3 = Rp, 35.000,00 100,00% Rp, 35.000,00
Jumlah 1 = Rp, 112.700,00 112.700,00
12,5% Keuntungan & Overhead = Rp, 14.087,50 14.087,50
Total = Rp, 126.787,50 100,00 126.787,50

A.1.5 1M³ MENGANGKUT (LANGSIR) MATERIAL KE LOKASI PEKERJAAN + 100 M


0,60000 OH Pekerja @ Rp, 122.000,00 = Rp, 73.200,00 100,00% Rp, 73.200,00
0,03000 OH Mandor @ Rp, 150.000,00 = Rp, 4.500,00 100,00% Rp, 4.500,00
Jumlah 1 = Rp, 77.700,00 Rp, 77.700,00
12,5% Keuntungan & Overhead = Rp, 9.712,50 Rp, 9.712,50
Total = Rp, 87.412,50 100,00 Rp, 87.412,50