Anda di halaman 1dari 1

REKAPITULASI OE

PEKERJAAN : RENOVASI ATAP DAN RUANG LABORATORIUM LT. 4 GEDUNG B DEPARTEMEN TEKNIK ELEKTRO FT-EIC ITS

LOKASI : KAMPUS INSTITUT TEKNOLOGI SEPULUH NOPEMBER


Jl. Arief Rachman Hakim, Sukolilo, Surabaya
WAKTU PENGERJAAN : 5 BULAN

JUMLAH HARGA Jumlah Harga KDN Jumlah Harga KLN Persentase TKDN
NO URAIAN PEKERJAAN
( Rp ) ( Rp ) ( Rp ) (%)
A PEKERJAAN PERSIAPAN :
I PEKERJAAN PERSIAPAN : Rp 31,243,785 Rp 31,243,785 Rp - 100%
JUMLAH Rp 31,243,785 Rp 31,243,785 Rp -
B PEKERJAAN BETON
I PEKERJAN PELAT Rp 172,180,347 Rp 148,427,004 Rp 23,753,343 86%
II PEKERJAN BALOK LATEI Rp 18,904,283 Rp 16,498,635 Rp 2,405,647 87%
JUMLAH Rp 191,084,629 Rp 164,925,639 Rp 26,158,990
C PEKERJAAN BESI DAN BAJA
I PEKERJAAN BESI DAN BAJA ATAP Rp 691,234,471 Rp 489,538,055 Rp 201,696,416 71%
II PEKERJAAN ATAP DAN LANGIT-LANGIT Rp 199,543,405 Rp 151,109,236 Rp 48,434,169 76%
III PEKERJAAN DINDING GEWEL Rp 12,584,483 Rp 12,318,159 Rp 266,324 98%
IV PEKERJAAN AREA SCREEDING DAN WATERPROOFING Rp 20,545,908 Rp 18,580,681 Rp 1,965,227 90%
JUMLAH Rp 923,908,266 Rp 671,546,131 Rp 252,362,135
D PEKERJAAN ARSITEKTUR
I PEKERJAAN PERSIAPAN Rp 73,548,424 Rp 61,716,443 Rp 11,831,981 84%
II PEKERJAAN DINDING Rp 123,427,658 Rp 91,841,186 Rp 31,586,472 74%
III PEKERJAAN PENUTUP LANTAI DAN DINDING Rp 246,291,034 Rp 226,664,690 Rp 19,626,344 92%
IV PEKERJAAN PLAFOND Rp 152,918,690 Rp 103,542,449 Rp 49,376,241 68%
V PEKERJAAN KUSEN PINTU DAN JENDELA Rp 283,098,130 Rp 95,354,905 Rp 187,743,225 34%
VI PEKERJAAN PENGECATAN Rp 85,120,438 Rp 62,696,016 Rp 22,424,422 74%
VII PEKERJAAN MEBELER Rp 150,269,385 Rp 104,863,890 Rp 45,405,495 70%
VIII PENGADAAN BARANG Rp 326,180,000 Rp 326,180,000 - 100%
JUMLAH Rp 1,440,853,759 Rp 1,072,859,580 Rp 367,994,180
E PEKERJAAN MEKANIKAL ELEKTRIKAL
I PEKERJAAN PANEL Rp 94,586,126 Rp 62,538,237 Rp 32,047,889 66%
II PEKERJAAN KABEL FEEDER Rp 80,821,355 Rp 78,453,951 Rp 2,367,404 97%
III PEKERJAAN TRAY Rp 114,988,507 Rp 69,948,312 Rp 45,040,195 61%
IV PEKERJAAN LAMPU PENERANGAN, SAKLAR & STOP KONTAK Rp 149,329,301 Rp 126,358,627 Rp 22,970,673 85%
V PEKERJAAN AIR HUJAN Rp 169,338,260 Rp 105,964,701 Rp 63,373,559 63%
VI PEKERJAAN TATA UDARA Rp 216,124,745 Rp 88,309,491 Rp 127,815,253 41%
VII PEKERJAAN ELEKTRONIK Rp 218,930,416 Rp 166,195,792 Rp 52,734,623 76%
VIII PERAPIAN KABEL TRAY DALAM SHAFT Rp 24,316,094 Rp 20,420,102 Rp 3,895,992 84%
IX PEKERJAAN PENYALUR PETIR Rp 46,081,591 Rp 37,280,285 Rp 8,801,306 81%
X PEKERJAAN SITEM GROUNDING PETIR Rp 5,544,037 Rp 4,464,968 Rp 1,079,069 81%
JUMLAH Rp 1,120,060,430 Rp 759,934,467 Rp 360,125,963
SUB TOTAL Rp 3,707,150,869 Rp 2,700,509,601 Rp 1,006,641,268 73%
PPN 11% Rp 407,786,596
JUMLAH Rp 4,114,937,464
PEMBULATAN Rp 4,114,937,000
Terbilang :
Empat Milyar Seratus Empat Belas Juta Sembilan Ratus Tiga Puluh Tujuh Ribu Rupiah

Surabaya, 25 Desember 2023


Dibuat Oleh,
Pejabat Pembuat Komitmen

Harun Al Rasyid, S.T., M.T., PhD


NIP. 19830808 200812 1 005

Anda mungkin juga menyukai