PPK : DINAS PEKERJAAN UMUM, PENATAAN RUANG, PERUMAHAN DAN KAWASAN PERMUKIMAN PROVINSI GORONTALO
DIVISI 1. UMUM
1.2 Mobilisasi
1.2 Mobilisasi LS 66,885,000.00 1.00 0.00
3b APD
Skh-1.1.22.(3b1) Topi pelindung (Safety Helmet) Bh 60,000.00 10.00 600,000.00
Skh-1.1.22.(3b7) Sarung tangan (Safety Gloves) Psg 20,000.00 10.00 200,000.00
Skh-1.1.22.(3b8) Sepatu keselamatan (Safety Shoes, rubber safety shoesand toe cap) Psg 350,000.00 10.00 3,500,000.00
Skh-1.1.22.(3b11) Rompi keselamatan (Safety Vest) Bh 150,000.00 10.00 1,500,000.00
7 Rambu dan Perlengkapan lalu lintas yang diperlukan atau manajemen lalu lintas:
Skh-1.1.22.(7a) Rambu petunjuk Bh 100,000.00 1.00 100,000.00
Skh-1.1.22.(7c) Rambu peringatan Bh 100,000.00 1.00 100,000.00
Skh-1.1.22.(7e) Rambu informasi Bh 100,000.00 2.00 200,000.00
Skh-1.1.22.(7h) Kerucut lalu lintas (traffic cone) Bh 100,000.00 2.00 200,000.00
Skh-1.1.22.(7i) Tongkat pengatur lalu lintas (Warning Lights Stick) Bh 45,000.00 2.00 90,000.00
Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 47,653,700.00
DIVISI 2. DRAINASE
3
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M 90,772.10 31.25 2,836,628.19
Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 2,836,628.19
Jumlah Harga Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 787,785.13
Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 94,592,914.56
DIVISI 7. STRUKTUR
3
7.1 (6a) Beton struktur, fc’25 Mpa M 3,741,189.56 251.00 939,038,579.08
3
7.1 (10) Beton, fc’10 Mpa M 3,408,856.83 7.50 25,566,426.21
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 34,738.00 27,580.63 958,095,908.25
Jumlah Harga Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 2,047,313,642.00
Jumlah Harga Pekerjaan DIVISI 9 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 22,229,740.22