Anda di halaman 1dari 3

PT.

Lyduma Intermas Consultant


Proyek : 2000 MT/ DAY REFINERY AND FRACTIONATION PLANS, STORAGE TANKS FARM,
POWER PLANT CAPACITY 1,5 MW ANCILLARIES, INFRASTRUCTURE, AND
OTHERS PT. PASIFIC BIO INDUSTRY AT KIJING PORT-MEMPAWAH-INDONESIA
SCOPE OF WORK : PACKAGE 1 - EARTH WORK AND FENCING
Pekerjaan : MANAJEMEN KONSTRUKSI
Office : Jl. Abdullah Lubis No.37/25 Medan 20154, North Sumater -Indonesia
Phone : (061) – 4148585 (Huting) Fax. : .(061) –4560940, email : lic@indo.net.id

MEMO LAPANGAN
No. 01/ML/EWF/XII/2024

Project : 2000 MT/Day Refinery And Fractionation Plans Storage Tanks Farm Power Plant
Capacity 1.5 MW Ancillaries, Infrastructure, And Others, Package 1 Earth Work And
Fencing at Kijing Port - Sei Kunyit,West Kalimantan, Indonesia
Owner : PT. Pacific Bio Industry
Contractor : PT. Mitra Jasa Mineral
Consultant : PT. Lyduma Intermas Consultant

Dengan Hormat,
Berdasarkan laporan progress yang kami buat meyesuaikan dengan kondisi actual dilapangan, pada
minggu ke-7 deviasi progress antara rencana kontraktor dan pelaksanaan dilapangan sudah mencapai
lebih dari -43%. Untuk itu kami mengingatkan kepada pihak kontraktor untuk segera :
1. Memaksimalkan jam kerja harian. Kontraktor harus menambah jam kerjanya pada malam hari.
2. Mengamankan/melindungi semaksimal mungkin tanah yang sudah terhampar yang belum
dipadatkan dari air hujan.
3. Kontraktor harus segera melengkapi berkas-berkas administrasi proyek secara officialy seperti
rencana kerja, metoda kerja, target-target pekerjaan yang lebih detail, laporan harian, laporan
progress mingguan, approval material, berita acara pemeriksaan pekerjaan khususnya pekerjaan
pemadatan dan test CBR dan Sandcone. Untuk progress real lapangan sampai saat ini belum ada
kesepakatan yang jelas antara kontraktor dan konsultan pengawas. Hal ini sudah di tekankan
berulang kali oleh team kami yang ada dilokasi. Kami meminta kepada kontraktor untuk
menyediakan tenaga administrasi teknis dilapangan untuk menyelesaikan berkas-berkas diatas
sekaligus mendampingi site manager kontraktor untuk keperluan pemberkasan kedepannya.
4. Kontraktor harus menyediakan alat dan personil pengukuran yang standby dilokasi untuk
mengontrol elevasi pekerjaan penimbunan dilokasi. Khususnya pada finishing top level elevasi.
PT. Lyduma Intermas Consultant
Proyek : 2000 MT/ DAY REFINERY AND FRACTIONATION PLANS, STORAGE TANKS FARM,
POWER PLANT CAPACITY 1,5 MW ANCILLARIES, INFRASTRUCTURE, AND
OTHERS PT. PASIFIC BIO INDUSTRY AT KIJING PORT-MEMPAWAH-INDONESIA
SCOPE OF WORK : PACKAGE 1 - EARTH WORK AND FENCING
Pekerjaan : MANAJEMEN KONSTRUKSI
Office : Jl. Abdullah Lubis No.37/25 Medan 20154, North Sumater -Indonesia
Phone : (061) – 4148585 (Huting) Fax. : .(061) –4560940, email : lic@indo.net.id

5. Melampirkan hasil pengukuran opname pekerjaan timbunan tanah yang diadakan setiap
minggunya untuk acuan progress real pekerjaan dilapangan.
6. Segera memulai pekerjaan pagar untuk menambah progress pekerjaan.

Demikian memo ini kami buat dengan tujuan sebagai pengingat untuk pihak kontraktor. Memo ini tidak
perlu dibalas. Diharapkan poin-poin diatas dapat segera dilaksanakan oleh pihak kontraktor.

Mempawah, 03 Januari 2024

Hormat kami,
PT. LYDUMA INTERMAS CONSULTANT

Yuda Rifani
Supervision Engineer/Admin
Tembusan :
1. PT. Pasific Bio Industry
2. PT. Lyduma Intermas Consultant
SCHEDULE OF WORK

PROJECT : 2000 MT/ DAY REFINERY AND FRACTIONATION PLANS, STORAGE TANKS
FARM, POWER PLANT CAPACITY 1,5 MW ANCILLARIES,
INFRASTRUCTURE, AND OTHERS
SCOPE OF WORK : PACKAGE 1 - EARTH WORK AND FENCING
LOCATION : AT KIJING PORT - WEST KALIMANTAN, INDONESIA
OWNER : PT. PACIFIC BIO INDUSTRY PT. PACIFIC BIO PT. MITRA JASA MINERAL
INDUSTRY PT. LYDUMA INTERMAS
CONSULTANT : PT. LYDUMA INTERMAS CONSULTANT - INDONESIA CONSULTANT

CONTRACTOR : PT. MITRA JASA MINERAL


6 7 7 7 7 7 7 7 7 7 7 7 7 83
NOVEMBER - 2023 DECEMBER - 2023 JANUARY - 2024 February - 2024
WEIGHT VALUE 30-Oct 6-Nov 14-Nov 20-Nov 27-Nov 4-Dec 11-Dec 18-Dec 25-Dec 1-Jan 8-Jan 15-Jan 22-Jan 29-Jan 5-Feb
NO. ITEM OF WORKS to to to to to to to to to to to to to to Information
(%) (%)
5-Nov 13-Nov 19-Nov 26-Nov 3-Dec 10-Dec 17-Dec 24-Dec 31-Dec 7-Jan 14-Jan 21-Jan 28-Jan 4-Feb 11-Feb
-1 0 1 2 3 4 5 6 7 8 9 10 11 12 13
100%
I PRELIMINERIES 6,816 Plan 6,816
5,904 86,62% Actual 1,174 1,373 2,817 0,335 0,045 0,059 0,027 0,027 0,045
II EARTH WORKS AND COMPACTION (PHASE 1)
1 Land Stripping 100 mm thick depth of Natural Ground Level 1,263 Plan 1,263
1,136 90,00% Actual 0,126 0,126 0,265 0,316 0,303
2 Compaction for Base, with CBR 6 or sand cone test 90% of dry density 10,101 Plan 0,101 2,000 2,000 2,000 2,000 2,000
1,925 19,06% Actual 0,485 0,485 0,955
3 Supply, Spread and Compact Soil above NGL (Natural Ground Level) land (variable) 53,030 Plan 3,030 10,000 10,000 10,000 10,000 10,000
up to DGL (Design Ground Level) + 3,600m and compacted every 300 mm thick 24,056 45,36% Actual 0,224 0,349 1,101 3,650 3,883 5,091 3,169 3,049 3,540
back filling layers. (Compaction Coefficient 25 % and The land lies in loose condition) 50%

III FENCE WORKS


1 EARTH WORKS 1,458 Plan 0,729 0,729
- Actual
2 CONCRETE WORKS 16,046 Plan 4,011 4,011 4,011 4,011
- Actual
3 BRICK WALL WORKS 1,625 Plan 0,812 0,812
- Actual
4 FENCE BRC WORKS 9,138 Plan 3,046 3,046 3,046
- Actual
5 PAINTING WORKS 0,524 Plan 0,524
- Actual 0%

Plan Progress ( % ) 100,000 11,109 10,101 12,000 12,000 12,000 12,729 6,740 4,011 4,824 7,870 3,046 3,046 0,524
Cumulative Plan Progress ( % ) 0,00 0,00 11,109 21,210 33,210 45,210 57,210 69,939 76,679 80,690 85,514 93,384 96,430 99,476 100,000
Actual Progress ( % ) 1,399 1,848 4,044 4,250 4,244 5,938 3,681 3,076 4,541
Cumulative Actual Progress ( % ) 0,00 1,399 3,247 7,291 11,541 15,785 21,724 25,405 28,480 33,022
Deviation This Week ( % ) -7,065 -5,851 -7,756 -6,062 -8,319 -9,653 -2,199
Cumulative Deviation This Week ( % ) -3,818 -9,669 -17,424 -23,486 -31,805 -41,458 -43,657

Kijing Port, December 31, 2023

Made By,
PT. LYDUMA INTERMAS CONSULTANT

Yuda Rifani
Supervision Engineer/Admin