MONTH FEBRUARY
TANGGAL 5 6 7 8 9 10 11 12 13 14 15 16 17
DAY COUNT 1 2 3 4 5 6 7 8 9 10 11 12 13
1 Pre assembling Frame 100 Pc
2 Instal Frame Complete
3 Pre assembling floor 184 pc
Done
4 Pre assembling curtain 184 pc
5 Install egg conveyor
6 Install complete nest
7 Material Roxell dikirim
8 Finishing , egg return dan egg colettor table PE
9 Pre assembling slate support GROUP 1
10 Lasser Marking & Mapping Kaki slate
11 Install slate
12 Pre assembling pan feeder GROUP 2
13 pre assembling nipple
14 instal suspension system feeder& niple MATERIAL BANTU
15 Install line nipple & feeder
16 Instal in-out nipple (WATER Panel) MATERIAL
17 instal ccpe & Hopper
18 Pekerjaan sentinel Complete
19 Pekerjaan Electrical nest MATER
20 Hato lighting
21 Test & Commisioning
22 Hand over
MATERIAL BANTU : * Untuk Suspensi winching, Motor, hopper (feeder & Nipple
* Pipa Air Dan Acsesories nya untuk input dan output Nipple
* Pipa conduit Untuk kabel autonest
* Pipa Conduit, junction box, electrical Cable untuk instalasi Lampu H
BRUARY MARET
`18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
GROUP 1 DAN 2
M ALL TEAM
24 25 26 27 28 29 30
80 81 82 83 84 85 86