Anda di halaman 1dari 8

Work Method

Statement
(System to Work Safely)
Company/Department : PT. Lancang Kuning Sukses WMS No:
Address :
Work Location / Area : MAX POWER BATAMINDO

DESCRIPTION & SCOPE OF WORK

PENJELASAN SINGKAT DAN LINGKUP PEKERJAAN

PEKERJAAN JACK PILE


NAME OF CONTRACTOR SUPERVISOR AND SUPERVISOR JOB DESCRIPTION

NAMA PENGAWAS, ENGINEER & HSE KONTRAKTOR PELAKSANA DAN APA SAJA TUGAS TUGASNYA

METHOD STATEMENT JACK PILE WORK WITH HYDRAULIC STATIC PILE

DRIVER

1. Pendahuluan

Jack Pile adalah salah satu bagian dari pemancangan pondasi. Dalam metode pemancangan ini akan
menggunakan mesin Hydraulic Static Pile Driver. Pile terbesar yang dapat dipakai pada ZYC180B-B
adalah spun pile Ø400 dan RC pile 400 x 400 dengan panjang maksimal ≥2.5 m , ≤ 12 m (middle pile)
dan ≥2.5 m,≤9 m (side pile).

1.1. Persiapan dokumen WMS dan JSA ke MPI dan BATAMINDO


1.2. Safety briefing and TBM sebelum melaksanakan pekerjaan
1.3. PIC akan mengkonfirmasi bahwa pekerjaan boleh untuk dilaksanakan
1.4. Identifikasi peralatan khusus untuk pekerjaan
1.5. Barikade area kerja
1.6. Semua peralatan kerja dicek sebelum bekerja
ZYC180B-B

2. Pengambilan Posisi

Pengambilan posisi pemancangan akan disediakan oleh surveyor. Ukuran mesin saat bekerja sebesar
panjang, lebar, tinggi = 10m x 5.9m x 19m.

Jarak maksimal terhadap tembok untuk center pile dan side pile
3. Support and Clawing

Pile harus sejajar dengan posisi lubang yg letak penjepitnya. Penjepit kemudian menjepit pile sehingga
pile akan secara erat diam pada posisi yang ditentukan untuk membantu
4. Pemotongan dan Penyambungan Pile

Pile yang masih utuh dan belum terpotong akan digunakan kembali. Ketika diperlukan pemotongan
maka akan dilakukan ketika telah mencapai kedalaman yang memadai. Penyambungan pile dengan
welding yang menggunakan tipe weld ESAB 6013 dan Kobelco RB26 4 mm oleh welder.

5. Pile Jacking

Proses memasukkan pile harus dilakukan dengan sekaligus sampai perlu di-joint atau dolly untuk
menghindari gesekan berlebihan pada tanah. Kedalaman pile yang masuk kedalam tanah harus mencapai
factor keselamatan sebesar 2 kali dari working load.

6. Piling Record

Supervisor akan mencatat record pile yang terpancang setiap hari. Record yang tercatat akan sesuai
format yang sudah disiapkan yang dimana terisi:
1. Nama dan posisi pile
2. Ukuran dan jumlah pile yang dipakai
3. Jumlah dan panjang pile yang digunakan
4. Kedalaman pile yang terpancang
5. Jumlah dolly dan joint jika ada
6. Kondisi cuaca
7. Informasi oil pressure dan lain-lain

Pressure Gauge

7. Peralatan

Untuk mencapai hasil yang memadai, kita menggunakan crane yang dapat mengangkat beban sampai 8
ton. Crane pengangkat pile digunakan untuk membantu pengangkatan pile ke posisi yang ditentukan.

8. Kejadian yang tidak diterduga

Pemberi kerja akan diinfokan secepatnya jika terjadi kejadian pada tanah yang tidak terduga seperti
terkena tanah keras yang tidak sesuai ekspetasi.
9. Jacking dengan Dolly

Ketika memancang pondasi yang dibawah level tanah akan digunakan pile lain yang tidak di las untuk
memasukkannya

Oil Pressure & the Pile Driving Force


Oil Pile Driving Force Pile Driving Force Pile Driving Force
Pressure (Fast Position) (Slower Position) (slowest position)
with two main cylinders with two main with main and auxiliary
(Mpa) working (KN) cylinders working (KN) cylinders working (KN)

1 33.4 52 98.3
2 51.8 91 186.6
3 70.2 130 274.9
4 88.6 169 363.2
5 107 208 451.5
6 125.4 247 539.8
7 143.8 286 628.1
8 162.2 325 716.4
9 180.6 364 804.7
10 199 403 893
11 217.4 442 981.3
12 235.8 481 1069.6
13 254.2 520 1157.9
14 272.6 559 1246.2
15 291 598 1334.5
16 309.4 637 1422.8
17 327.8 676 1511.1
18 346.2 715 1599.4
19 364.6 754 1687.7
20 383 793 1776
21 401.4 832 1864.3
22 419.8 871 1952.6
23 438.2 910 2040.9
24 456.6 949 2129.2
Note: 1, fast position refers to the two main cylinders are differentially connected and its
operation is relative to speed up the fast handle operations, piles pressure calculation formula
for power: F1 = 18.4P +15 (KN)
2, slow position refers to the two main cylinders pressing piles, pile pressure calculation
formula for power: F2 = (39P +13) (KN)
3, slowest position refers to the four cylinders pressing piles, piling pressure calculation
formula for power: F3 = 88.3P +10 (KN)

IMPLEMENTATION PLAN (Start Date and End) And the Hour Start and Finish Every Day
RENCANA WAKTU PELAKSANAAN (Tanggal Mulai dan Selesai) Dan Jam Mulai dan Selesai Setiap Hari

Employee/Worker List
(list all employees/workers involved in work process)

No Name Position Department Competence/License/ Remarks


Certificate

1 SUHERNO SITE MANAGER Project

2 ERMIYANTO SUPERENTENDENT Project

3 SUDOMO HSE MANAGER Project

4 ERFAQ SPV CIVIL Project

4 WIGIK FEBRIYANTO HSE OFFICER Project

5 MULYA ENGINEER Project

6 MARMUN OPERATOR Project YES

Tools & Equipment


(List all)

Result direct checks


Kind of equipment & Tools Brand
Condition & Function Safe - Unsafe

EXCAVATOR TBA Good Safe

Bulldozer TBA Good Safe

Vibro Roller (Compactor) TBA Good Safe

Stamper TBA Good Safe

Cangkul TBA Good Safe


Banding besi TBA Good Safe
Ngaung TBA Good Safe
Gegep TBA Good Safe
Scope TBA Good Safe
Martil/bodem TBA Good Safe
Cetok semen TBA Good Safe
Personal Protective Equipment (PPE ) Required
(List all)

Mandatory:

1. Safety Vest
2. Safety Helmet
3. Safety Glass
4. Safety Shoes
5. Hand cotton Gloves
6. Safety glove
7. Ear Plug.

Additional:
Emergency Response at Site Project

No. Department / Person Tel

1 Fire Department (0778)-371 560 dan


Kantor Duriangkang ( sebelah Stadion Tumenggung Abdul Jamal (0778)-371 561
No Rumah Sakit No Telephone
2 Police Department:
1. i.
RS. Harapan Polsek
Bunda Batamindo +62 778
(0778) 456444
393435
ii. Poltabes Barelang (0778) 455 300
2. ELIZABETH +62 778 457357
3 Ambulance (Paramedic):
i. Rumah Sakit Embung Fatimah (0778) 364446
3. RS. Awal
ii. Bross
RS Budi Kemuliaan +62 778
(0778) 454431777
044
Prepared by, Checked by, Approved by,
Project In charge QHSE Site Department (Project Leader)

Name : Mulya Name : Wigik F Name : ERMIYANTO


Tittle : Engineering Tittle : HSE LKS Tittle : Superentendent
Date : 17 January 2022 Date : 17 January 2022 Date : 17 January 2022

Anda mungkin juga menyukai